Вы находитесь на странице: 1из 2

UiPath Quiz Level 2 - Orchestrator 2018.

3 Training
Study online at quizlet.com/_6delsc

1. Assets can be: - Global 14. A Robot is executing a workflow that No, only the log
- Per Robot uses the "Log Message" activity with messages of type
the 'Info' level. If the log level of the 'Error' and 'Critical'
2. Can a Machine Template Yes, only if there are Edit
robot is set to 'Error', does the Info are displayed on the
name be changed? rights on Machines.
log appear on the Orchestrator Orchestrator Robots
3. Can the parameters from yes Robots > Logs page? > Logs page
the Orchestrator overwrite
15. The Schedule 'stop after' option The amount of time
the ones existing in the Main
refers to: until the scheduled
file of the process?
process will be
4. Can the parameters of the Yes canceled/terminated
main workflow be inserted
16. Select only the specifications that - The package name
from the Orchestrator?
are mandatory when deploying a The package version
5. Can we set up a reviewer yes process: - The package
for the Failed Transactions? version
6. How are Robot Keys Orchestrator generates - The environment
generated? unique Robot Keys during the 17. Select the charts included in the - Robots
robot provisioning process Orchestrator Dashboard: - Job results
7. How can a job be initialized - Manually, from the Jobs - Transactions
using Orchestrator? page 18. There are 3 robots in the "ABC" NOT THIS ONE - By
- At specific times, using environment. How can the execution adding all 3 robots
Schedules of a package be assigned to all 3 of and the package in
8. How can a process be - By creating a job and them? the same
allocated to three different selecting all three robots environment
robots? - By scheduling the process 19. What are the statuses that can be NOT THIS ONE - It's
and adjusting the settings in set manually for the transactions not possible to set
the Execution Target tab that failed due to an application the status of any
accordingly exception? failed transaction
9. How can a process that has By going to Processes, manually
more package versions be selecting the targeted 20. What filter types are available for - State
updated? process, clicking View Jobs? - Source
Versions and selecting the
21. What happens if an active package Active packages
desired option
version in Orchestrator is deleted? cannot be deleted
10. How can the processes in a - Processes can run on all the
22. What happens if the status of a Its status is changed
schedule be assigned to the robots in an environment
Transaction that is "In Progress" is to Abandoned
robots in a specific - Processes can run on
not updated within 24 hours?
environment? specific robots in an
environment, depending on 23. What is the easiest way to manage By using the Review
the user's choice the Items that were assigned to you Requests Menu
for Review?
11. How can you see only the By selecting "Agent" from the
jobs that ran on attended Source Filter in the Jobs 24. What is the mandatory field required Template Name
robots? menu. to complete when creating a new
Machine Template?
12. Is using the 'Publish' button No. Packages can also be
in Studio the only way to published via the Packages 25. What is the purpose of the Queues To store data that is
upload a package to page in Orchestrator section in Orchestrator? processed by
Orchestrator? multiple robots
13. Machine Templates only ... 26. When should the Add Log Fields When the standard
work for: activity be used? log message has to
be customized by
adding new fields to
it
27. Where can the parameters be modified from in the Orchestrator? - Processes -> Parameters
- Jobs -> Start Job -> Parameters
28. Where can you check whether a job was scheduled or manually Go to the Jobs page and check the Source column
started?
29. Which command instructs a robot to gracefully terminate the running NOT THIS ONE - Stop
process?
30. Which of the following data types can be stored as Assets? - Integer
- String
- Credential
- Boolean
31. Which of the following Properties can be used as Filters for the - Priority
Review Requests Menu? - Queue
- Revision
- Status
32. Which of the steps below are required in order to establish a - Provisioning the Robot in Orchestrator
connection between a robot and Orchestrator? - Configuring the Robot on the local machine using the
Orchestrator URL and the Robot key
33. Which options and actions can be triggered on the Packages page? - View all published packages
- Delete package versions
34. Which options can be used to end the execution of a running - Stop
process? - Kill
35. Which parameters need to be defined when creating a new Name
environment?