Вы находитесь на странице: 1из 2

TASK ACTICITY CONTROL MEASURE

1.Empty wagons a) On information from station Master 1. Ensure full inspection of


from station to CDS ,whom instructs to Loco LOCO before use.
operator to bring empty wagons from 2.Ensure proper coupling –
LKE. Decoupling of wagons /
b) Usually Loco # 11, bring full empty loco by pointsmen
rake from LKE station at a time, 3. Use of Wheel choke to
containing 58/59 wagons. prevent roll off.
c) Loco #9, separate out first 38 boxes 4. Hooter should be used
from rest and get coupled with last 20 while crossing barrier
Wagons. both inside and outside
d) First 38 Boxes are called inside plant, the plant.
to distribute in 2 parts , first 20 5. Proper communication
Boxes in store Line and Second through mobile or Walky
18/19 boxes in Coal Line 2.It Talkie.
enables us to continuous Loading
and wagon ceiling can be done
easily.

2. Placement of 1. Loco #9 , after loco # 11 made 1. Crossing gate should be


unloading wagons placement, place 20 wagons to locked before movement
loading site, where before loading of loco (specially Crusher
with claim shell sealing of wagons Gate).
done. 2. Proper guidelines was
given to loco operator by
In charge Material
handling
2.Sealing of wagons 1.Sealing of wagons done by trained and 1. Use of standard tools
side door experience labours, using rods they and tackles.
manual open the door and get check 2. Steel ladder should be
gaps in floor of wagons and seal the used for entry in wagons.
gaps with waste plastic bags if need. 3. Yard supervisor will be
Otherwise, seal the gaps in door with associated and coordinate
waste plastic bags. with labours while moving
2.Once sealing of wagons done , of loco, only.
permission was given by labours for
loading process
3.Loading of wagons 1. Wagons are placed within range of 1. Nobody should allow to
from claim shell & claim shell boom and pay loader with stand in the range of boom
pay loader its lift bucket fills clinker. of claim shell or pay loader
2. Operation of claim shell and pay path.
loader should follow separate SOP to 2. Claim shell operator and
be referred. Pay loader operator should
3. Carrying capacity of wagons of type of follow SOP applied to the
wagons and filling clinker based on operation of their machine.
route ( refer to Annexure 1) 3. standard PPE should be
4. Based on past experience, clinker is used by this operators
loaded on no. of bucket of claim shell 4. By horn sound , operator
/pay loader in operation. informs completion of
5. Yard Supervisor with Third party clinker filling.
supervisor coordinate with Pointsmen 5. While moving forward
while moving forward after filling wagons, hooter sound ON
wagons, ask loco operator to pull by the Points men standing
wagon forward one of three wagons at there.
time. 6. While pulling another lot
6. Usually in three Lot clinker is filled , after completion of previous
20 wagons, each , last lot containing ! lot. Pointsment should
8/20 wagons apply wheel choke in 1st
box to avoid wagon roll off.

4. Tarpaulin cover in 1. During the period of Monsoon, 1. Since Wagon cap


Monsoon period Tarpaulin covering done over the covering is done
clinker rake to protect clinker from manually, all the safety
rain. aspects should be looked
2. After the loading done, Loco #11 will after by the contractor
carry loaded wagon in Railway Yard under how trained
where, at a time, 20 boxes are subject persons are used to cover
to tarpaulin cover manually done by the wagon cap.
business partners. 2. Used of standard ladder
3. Preparation of nylon ropes and steel and necessary PPE
wire were lifted from plant to site. should be weared by the
4. Specified dimension wagon caps persons deployed for this
were subject to cover the wagon tie, job to prevent slip or fall ,
tightly by nylon rope, the sides of the fall from height etc by
cap were tied with steel wire. applying all standard
norms of FPE.
5. Shifting of Loaded 1.Loco # 11 ,usually deployed to carry 1. While moving along the
wagons to LKE loaded wagon with or without tracks LOCO operators
tarpaulin to LKE in 3 lots and should aware about the
assemble their in full loaded rake. persons involve in
2.The loaded period was given 7 hrs, covering wagon cap,
from the period where indent was Hooter should
placed to last boxes shunted. continuously bowled and
3. Weightment of rake done at SWM Rly motion of loco in reduced
way station on RLY WB and its weight speed.
is considered as Final weight and 2. Once confirmed by Rate
considered as INVOICE WEIGHT. contract contractor of
covering done and
manpower separate out,
then only LOCO shunting
is allowed.,
3. However in NON
Monsoon period , LOCO
just shunt inside the
plant and carry to LKE.,

Вам также может понравиться