Date of Submission
Substation Data:
Client: Sector: Plot:
HV Switchgear Make: No of 11kV
(if by contractor) Panels
Distribution Transformer Make:
TR Rating
(if by contractor)
LV Switchgear Make:
Ready? * Remarks
1 SUB-STATION / ELEC. ROOM ACCESSIBILITY
2 SUB-STATION / ELEC. ROOM DIMENSION
3 SUB-STATION / ELEC. ROOM CLEANLINESS
4 SUB-STATION / ELEC. ROOM PAINTING
5 DUCTS CEILING
6 TRENCHES & COVERS
7 CABLE LAYING & TERMINATION FOR 1C 630 LV CABLE
8 LIGHTING AND SOCKET OUTLET AVAILABILTY
9 TESTING OF S/S EQUIPMENT
10 CIRCUIT BREAKER OPERATIONAL
11 EARTHING SYSTEM
12 DOOR LOCKING SYSTEM
13 FIRE EXTINGUISHER
14 INSTALLATION OF EXHAUST FANS FOR DRY TYPE TR
15 INSTALLATION OF A/C FOR HV ROOM
16 INSTALLATION OF APPROVED SUB-STATION NAME PLATES
17 INSTALLATION OF BATTERY BANK
18 INSTALLATION OF BATTERY CHARGER
19 MATERIALS APPROVAL LETTER BY ASSET DIR. [BULK] **
20 TRANSFORMER INSTALLATION [BULK] **
21 TRM / QRM / SWITCHGEAR & PACKAGE UNIT INSTALLATION [BULK] **
22 CABLE LAYING [BULK] **
23 CABLE TERMINATION FOR 3C HV CABLE [BULK] **
24 EQUIPMENT TESTING [BULK] **
25 GIS APPROVAL [BULK] **
26 HV METER CLEARANCE (FOR HV METERING) [BULK] **
27 UNDERTAKING LETTER FOR O&M [PRIVATE] **
* All points must be cleared and ready for inspection before submission of CTA
** Points required only if work is carried by client/contractor
COMMENTS: