Академический Документы
Профессиональный Документы
Культура Документы
The role of Planning Engineer in Construction Projects at site varies depending upon
which type of company you are working, Means the roles will be different when you
work with
1. Collect all the FEED documents, Estimation files, of course all planning
related documents (for reference read only) get hand over from HO or
Regional office planner to site or to have all planning related files in
separate share folder between HO and site planning team.
2. Prepare, submit and get approval of Level-4 Construction schedule from
PMC: or desired levels below depending upon the client requirement at site
in Primavera or any software mentioned in the contract. Normally
construction planner have no freedom and have to use Construction WBS
from Level-1 EPC schedule. The resource loading will be done to the
schedule after completing the below two steps.
Example of Level-4
Level -3 - Expansion of each Discipline Eg. Civil - Building, Pipe rack, Equipment
foundation, Control room etc.
Level-5/6/7 - Adding more activities example. FDT- Base, laying vapor barrier, Base
Rebar works, shuttering base, RCC for base, De-shuttering base, pedestal Rebar
works, fixing anchor bolts, Shuttering pedestal, RCC for pedestal, deshuttering,
Bitumen coating, Backfilling, FDT - layers, Handing over to Mechanical for equipment
erection.
2. Re-estimate and revise the Scope: There may be scope changes normally addition
to that of Initial scope. At site for working contingency we can add some% more to
the estimated quantities from Engineering to avoid over reporting. Normally these
quantities are verified by the Quantity surveyors at site.
3. Manpower and resource estimation. Normally in a project standard man hours for
each work will be given to estimate the man hours for the project. From that
Manpower requirement shall be calculated. Other resources viz. Lifting equipment,
Scaffolding material, welding machines etc. also to be estimated Discipline wise.
5. PMS :Establish Progress measurement system for construction once the schedule
and weight ages are approved by client. Invoice PMS also made according to cost
and weightages against the activities.
5. Generate Template for Daily, weekly and Monthly reporting purpose according to
agreed format in the Contract with the PMC.
6. Once all the above are approved by Client/PMC, Progress Reporting, Progress
monitoring etc. shall begin.
7. Get the construction schedules from the sub-contractors, review and approve
procedures etc.