MATERIAL REQUISITION FOR FLOW Rev.: 0
METER ANDTRANSMITTERS
1. SCOPE
This document covers the technical and commercial requirements for the flow
metering, registering and transmitting instruments to be installed in the fuel
supply system within the scope of Reconstruction Of The International Airport
Astana.
2. DEFINITIONS
Supplier: The Bidder becomes the Supplier when his Bid is accepted and a
Purchase Order or a Supply Agreement is made between the Bidder and the
Contractor.
Contract: The main Contract between the Employer and the Contractor.
3. TECHNICAL REQUIREMENTS
4. COMMERCIAL REQUIREMENTS
Page 1 / 8
Doc. No. Reconstruction Of The International Airport Astana Prep.By:
MATERIAL REQUISITION FOR FLOW Rev.: 0
METER ANDTRANSMITTERS
APPENDIX – I
General requirements related with the manufacture and supply of the flow
meter-transmitters shall include:
Operating and design temperature range for the instruments shall be:
Low: -40°C
High: +50°C
1.4. Material:
Page 2 / 8
Doc. No. Reconstruction Of The International Airport Astana Prep.By:
MATERIAL REQUISITION FOR FLOW Rev.: 0
METER ANDTRANSMITTERS
2. CONSTRUCTION
The rotor shaft shall protrude from the chamber cover and connect,
through a calibration mechanism to a pulse emitter, which in turn provides the
flow information for the electronic meter. Couplings shall be magnetic driven.
2.2. Materials:
Vanes : Teflon
Gaskets : CAF
2.3. Installation:
Page 3 / 8
Doc. No. Reconstruction Of The International Airport Astana Prep.By:
MATERIAL REQUISITION FOR FLOW Rev.: 0
METER ANDTRANSMITTERS
24 VDC ± 10%
3.1 General:
Page 4 / 8
Doc. No. Reconstruction Of The International Airport Astana Prep.By:
MATERIAL REQUISITION FOR FLOW Rev.: 0
METER ANDTRANSMITTERS
The Bidder shall calculate the required size for the flow rates mentioned in
Appendix II hereto. The sizes given are for reference only.
The connecting flanges shall be sized and drilled as per ANSI B16.5.
5. ACCURACY:
Page 5 / 8
Doc. No. Reconstruction Of The International Airport Astana Prep.By:
MATERIAL REQUISITION FOR FLOW Rev.: 0
METER ANDTRANSMITTERS
Index
Description of equipment and accessories
Maintenance instructions
Safety instructions
List of enclosures (diagram, drawings, pamphlets)
List of all parts of each meter-transmitter together with catalogue
number for eventual orders
Purchasing specification
Identification number
Instructions for repairs and replacement with details of mounting
clearances
8. MARKING:
1. Supplier
2. Connection size
3. Max. Flow Capacity (m3/h)
4. Maximum Pressure (Barg)
5. Pressure Design Standard
6. Tag number
Page 6 / 8
Doc. No. Reconstruction Of The International Airport Astana Prep.By:
MATERIAL REQUISITION FOR FLOW Rev.: 0
METER ANDTRANSMITTERS
Furthermore, the meter head shall be provided with a nameplate including the
following information as a minimum:
1. Supplier
2. Power rating (V, A, Hz)
3. Serial data connection type
4. Protection class
5. Explosion protection class
Supplier shall insure that the flange finishes are protected from damage
during shipping and storage. The ends of socket, threaded and weld ends
fittings and flanges shall be protected by securely fastened tight fitting plastic
caps.
The meter heads shall be shipped separately from the flow meters and shall
be packed securely against impacts.
Installation and maintenance manuals for the flow meters shall be provided
by the Supplier in digital format and three fold hard-copies.
11.1 Provision
11.2 Availability
The Bidder shall confirm in writing that spare parts for the suggested
equipment will be available for a minimum of twelve years following sale.
Where special tools are required to operate and maintain any part of the
supplied equipment, the Supplier shall provide two sets of such tools with
casing. List of special tools shall be prepared by the Supplier and shall be
subject to the approval of the Engineer.
Page 7 / 8
Doc. No. Reconstruction Of The International Airport Astana Prep.By:
MATERIAL REQUISITION FOR FLOW Rev.: 0
METER ANDTRANSMITTERS
APPENDIX-II
COMMERCIAL DOCUMENTS
1. BID BASIS
The Bidder will propose their best prices, best possible delivery, transport and
payment.
3. COMPLIANCE STATEMENT
The Bidder shall certify submittals forwarded to SMLA with the following
certifying statement: "I hereby certify that the (equipment) (material) (article)
shown and marked in this bid is that proposed to be incorporated with Astana
Airport Reconstruction Project, is in compliance with the attached specification
and is submitted for the SMLA approval”.
Bidder must sign and stamp all the pages of specification and its attachments
and provide with the compliance statement.
Page 8 / 8