Академический Документы
Профессиональный Документы
Культура Документы
Bored piles:
In this process, a void is formed by
boring or excavation before pile is
introduced into the ground. Piles can SHEET PILES
be produced by casting concrete in the Sheet piles are used to restrain
void. Boring piles are considered as soft soil above the bedrock in
non-displacement piles. excavation
Sheet piling is a form of driven
Pile Installation Methods piling using thin interlocking
In pile foundations, Installation process sheets of steel to obtain a
and methods of installation are equally continuous barrier in the
important as the design process. ground.
During the design of piles, The main application of sheet
the installation method and equipment piles is in retaining
should be carefully selected in order to walls and cofferdams erected to
avoid the damages to the pile. enable permanent works to
Pile driving methods (displacement proceed.
piles) Normally, vibrating hammer, t-
crane and crawl drilling are
Dropping weight: used to establish sheet piles
A hammer with approximately the
weight of the pile is raised to a suitable
height and is released to strike the pile
head.
Vibration:
The amplitude of vibration used here
should be sufficient to break the skin
friction on sides of pile. This is bested
suited for sandy or gravelly soils. Can be used to construct of piers, oil
terminals, waste storage facilities,
Under reaming: bridges, houses, buildings, dry
This is a special type of auger bored docks other construction sites and for
piles which is used to exploit the the strengthening of pond banks,
bearing capacity of respective strata preventing slumping into a pit and
by providing an enlarged base. flooding.
Steel is the most common form
of sheet piles as it has good resistance
to high driving stresses, excellent
water-tightness, and can be increased
in length either by welding or bolting.
They are connected by interlocking.
Application:
Used in foundation pits, coastline
strengthening, bridge construction,
piers, tide control, flood protection,
agriculture irrigation, water reservoir
and other work requiring extremely
strong support in a narrow geometry.
Steel sheet piling is the most common They are used for the following
because of several advantages over purposes:
other materials: • To construct retaining walls in
1. Provides high resistance to driving docks and other marine works.
stresses. • To protect erosion of river
2. Light weight banks.
3. Can be reused on several projects. • To retain the sides of the
4. Long service life above or below foundation trenches.
water with modest protection. • To confine the soil to increase
5. Easy to adapt the pile length by its bearing capacity.
either welding or bolting • To protect the foundation of
6. Joints are less apt to deform during structures from the erosion
driving. caused by river or sea.
• To isolate foundation from
Lengths can reach 34 meters. adjacent soil
Each segment is flipped 180° versus
the preceding segment. Timber sheet piles are generally used
The segments lock together using a for short spans in
variety of interconnections. temporary structures, and to resist light
The fully assembled structure is lateral loads.
formed in a linear, circular, or other They are typically connected together
shape. by tongue and groove joints.
To reduce the filtering space, mixed The disadvantage of timber piles is
sealant is injected. Additionally, it may that they require preservative
be combined with the use of dowels, treatment and are not generally
metal beams and pipes. suitable for soils consisting of stones.
Metal dowels are hot-rolled and cold-
rolled. Reinforced concrete sheet piles are
formed using precast
concrete members, usually connected • Secant pile walls are formed by
together by tongue and groove joints. constructing intersecting
They are commonly used in reinforced concrete piles.
permanent river embankments, canals • The secant piles are reinforced
and other marine structures. with either steel rebar or with
The toes of the piles are usually cut steel beams and are
with an oblique face to facilitate easy constructed by either drilling
driving and interlocking, while the under mud or auguring.
heads are finished off by casting a • Primary piles are installed first
capping beam. with secondary piles
constructed in between primary
Sheet pile walls are constructed by: piles once the latter gain
sufficient strength.
1. Laying out a sequence of sheet pile • Pile overlap is typically in the
sections, and ensuring that sheet piles order of 3 inches (8 cm).
will interlock.
2. Driving (or vibrating) the individual In a tangent pile wall, there is no pile
sheet piles to the desired depth. overlap as the piles are constructed
3. Driving the second sheet pile with flush to each other.
the interlocks between the first sheet ADVANTAGES:
pile and second "locked" 1. Increased construction alignment
4. Repeating steps 2 & 3 until the wall flexibility.
perimeter is completed 2. Increased wall stiffness compared to
5. Use connector elements when more sheet piles.
complex shapes are used. 3. Can be installed in difficult ground
(cobbles/boulders).
Sheet pile wall disadvantages are: 4. Less noisy construction.
1. Sections can rarely be used as part The main disadvantages of secant
of the permanent structure. pile walls are:
2. Installation of sheet piles is difficult 1. Verticality tolerances may be hard to
in soils with boulders or cobbles. In achieve for deep piles.
such cases, the desired wall depths 2. Total waterproofing is very difficult
may not be reached. to obtain in joints.
3. Excavation shapes are dictated by 3. Increased cost compared to sheet
the sheet pile section and interlocking pile walls.
elements. Secant pile wall design when steel
4. Sheet pile driving may cause beams are used involves the use of
neighborhood disturbances weaker than normal concrete.
5. Settlements in adjacent properties
may take place due to installation
vibrations