Вы находитесь на странице: 1из 564

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 100(1) Clearing & Grubbing (with Stripping)


Unit of Measurement : sq.m.
Output per hour : 500.00

Designation No. of Person No. of Hours Hourly Rate

A. Labor

a. Construction Foreman 1 1 109.19


b. Laborer 2 1 61.44

Sub - Total for A


Name and Capacity No of Units No. of Hours Hourly Rate

B. Equipment

a. Dump Truck (10 cu.m.) 2 1 1,352.00


b. Payloader (1.50 cu.m.) 1 1 1,733.00
c. Bulldozer (155 Hp), D65A-8 1 1 2,299.00

(Hauling Distance - within three (3) km.)

Assumed 150mm cut

Sub - Total for B


C. Total (A + B)
D. Output per hour = 500.00 sq.m.
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost

F. Materials

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G
I. Contractor's Profit (CP) 8% of G
J. Value Added Tax (VAT) 12% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
Item No./Description : 100(2)a Individual Removal of Trees (small a, 150-300mm Ø)
Unit of Measurement : ea.
Output per hour : 3.00

Designation No. of Person No. of Hours Hourly Rate

A. Labor

a. Construction Foreman 1 1 109.19


b. Skilled Laborer 1 1 79.70
c. Laborer 2 1 61.44

Sub - Total for A


Name and Capacity No of Units No. of Hours Hourly Rate

B. Equipment

a. Backhoe (0.80 cu.m.) 1 0.50 1,537.00


b. Dump Truck (10 cu.m.) 1 0.50 1,352.00
c. Chain Saw 1 0.50 121.50
Minor Tools (5% of labor)

* Boom Truck - if necessary for trimming in Urban


Areas

Sub - Total for B


C. Total (A + B)
D. Output per hour = 3.00 ea.
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost

F. Materials

a. Rope, 1" dia. m. 20.00 3.50

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G
I. Contractor's Profit (CP) 8% of G
J. Value Added Tax (VAT) 12% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
Item No./Description : 100(2)b Individual Removal of Trees (small b, 301-500mm Ø)
Unit of Measurement : ea.
Output per hour : 1.00

Designation No. of Person No. of Hours Hourly Rate

A. Labor

a. Construction Foreman 1 1 109.19


b. Skilled Laborer 1 1 79.70
c. Laborer 2 1 61.44

Sub - Total for A


Name and Capacity No of Units No. of Hours Hourly Rate

B. Equipment

a. Backhoe (0.80 cu.m.) 1 0.50 1,537.00


b. Dump Truck (10 cu.m.) 1 0.50 1,352.00
c. Chain Saw 1 0.50 121.50
Minor Tools (5% of labor)

* Boom Truck - if necessary for trimming in Urban


Areas

Sub - Total for B


C. Total (A + B)
D. Output per hour = 1.00 ea.
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost

F. Materials

a. Rope, 1" dia. m. 20.00 3.50

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G
I. Contractor's Profit (CP) 8% of G
J. Value Added Tax (VAT) 12% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 100(3)a Individual Removal of Trees (large a, 501-750mm Ø)


Unit of Measurement : ea.
Output per hour : 0.25

Designation No. of Person No. of Hours Hourly Rate

A. Labor

a. Construction Foreman 1 1 109.19


b. Skilled Laborer 1 1 79.70
c. Laborer 2 1 61.44

Sub - Total for A


Name and Capacity No of Units No. of Hours Hourly Rate
B. Equipment

a. Backhoe (0.80 cu.m.) 1 1 1,537.00


b. Dump Truck (10 cu.m.) 1 1 1,352.00
c. Chain Saw 1 1 121.50
Minor Tools (5% of labor)

* Boom Truck - if necessary for trimming in Urban


Areas

Sub - Total for B


C. Total (A + B)
D. Output per hour = 0.25 ea.
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost

F. Materials

a. Rope, 1" dia. m. 20.00 3.50

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G
I. Contractor's Profit (CP) 8% of G
J. Value Added Tax (VAT) 12% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
Item No./Description : 100(3)b Individual Removal of Trees (large b, 751-900mm Ø)
Unit of Measurement : ea.
Output per hour : 0.125

Designation No. of Person No. of Hours Hourly Rate

A. Labor

a. Construction Foreman 1 1 109.19


b. Skilled Laborer 1 1 79.70
c. Laborer 2 1 61.44

Sub - Total for A


Name and Capacity No of Units No. of Hours Hourly Rate
B. Equipment

a. Backhoe (0.80 cu.m.) 1 1 1,537.00


b. Dump Truck (10 cu.m.) 1 1 1,352.00
c. Chain Saw 1 1 121.50
Minor Tools (5% of labor)

* Boom Truck - if necessary for trimming in Urban


Areas

Sub - Total for B


C. Total (A + B)
D. Output per hour = 0.125 ea.
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost

F. Materials

a. Rope, 1" dia. m. 20.00 3.50

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G
I. Contractor's Profit (CP) 8% of G
J. Value Added Tax (VAT) 12% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
Item No./Description : 101(1) Removal of Structures and Obstruction (other than concrete)
Unit of Measurement : cu.m.
Output per hour : 10.00

Designation No. of Person No. of Hours Hourly Rate

A. Labor

a. Construction Foreman 1 1 109.19


b. Skilled Laborer 1 1 79.70
c. Laborer 2 1 61.44

Sub - Total for A


Name and Capacity No of Units No. of Hours Hourly Rate

B. Equipment

a. Backhoe (0.80 cu.m.) 1 1 1,537.00


b. Dump Truck (10 cu.m.) 1 1 1,352.00
Minor Tools (10% of Labor)

Sub - Total for B


C. Total (A + B)
D. Output per hour = 10.00 cu.m.
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost

F. Materials

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G
I. Contractor's Profit (CP) 8% of G
J. Value Added Tax (VAT) 12% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 101(2) Removal of Concrete Bridge Structures


Unit of Measurement : cu.m.
Output per hour : 1.00

Designation No. of Person No. of Hours Hourly Rate

A. Labor

a. Construction Foreman 1 1 109.19


b. Skilled Laborer 2 1 79.70
c. Laborer 4 1 61.44

Sub - Total for A


Name and Capacity No of Units No. of Hours Hourly Rate

B. Equipment

a. Backhoe w/ Breaker (0.80 cu.m.) 1 0.50 2,074.95


b. Jackhammer 2 1 514.31
c. Air Compressor (103 Hp) 1 1 675.00
d. Dump Truck (10 cu.m.) 1 0.125 1,352.00
e. Payloader (1.50 cu.m.) 1 0.125 1,733.00
f. Truck Mounted Crane (35 T) 1 0.25 1,553.00
g. Cutting Outfit 1 1 45.00

* Disposal area (within three (3) km.)

Sub - Total for B


C. Total (A + B)
D. Output per hour = 1.00 cu.m.
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost

F. Materials

a. Oxy/Acytelene set 0.10 2,500.00

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G
I. Contractor's Profit (CP) 8% of G
J. Value Added Tax (VAT) 12% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 101(2) Removal of Steel Bridge Structures


Unit of Measurement : kg.
Output per hour : 1,000.00

Designation No. of Person No. of Hours Hourly Rate

A. Labor

a. Construction Foreman 1 1 109.19


b. Skilled Laborer 2 1 79.70
c. Laborer 4 1 61.44

Sub - Total for A


Name and Capacity No of Units No. of Hours Hourly Rate

B. Equipment

a. Service Truck/Cargo Truck 1 1 712.00


b. Welding Machine 1 1 391.00
c. Truck Mounted Crane (35 T) 1 1 1,553.00
d. Cutting Outfit 1 1 45.00
Minor Tools (10% of Labor)

Sub - Total for B


C. Total (A + B)
D. Output per hour = 1000.00 kg.
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost

F. Materials

a. Oxy/Acytelene set 0.00025 2,500.00


b. Welding Rod kg. 0.002 90.00
c. Rope 1" dia. m. 0.05 3.50

* Include shoring materials if needed based on


actual field condition

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G
I. Contractor's Profit (CP) 8% of G
J. Value Added Tax (VAT) 12% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 101(2) Removal of Stone Masonry Lined Drainage Structures


Unit of Measurement : cu.m.
Output per hour : 5.00

Designation No. of Person No. of Hours Hourly Rate

A. Labor

a. Construction Foreman 1 1 109.19


b. Skilled Laborer 2 1 79.70
c. Laborer 4 1 61.44

Sub - Total for A


Name and Capacity No of Units No. of Hours Hourly Rate

B. Equipment

a. Backhoe w/ Breaker (0.80 cu.m.) 1 0.50 2,074.95


b. Backhoe (0.80 cu.m.) 1 0.50 1,537.00
c. Dump Truck (10 cu.m.) 1 0.25 1,352.00

* Disposal area (within three (3) km.)

Sub - Total for B


C. Total (A + B)
D. Output per hour = 5.00 cu.m.
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost

F. Materials

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G
I. Contractor's Profit (CP) 8% of G
J. Value Added Tax (VAT) 12% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 101(2) Removal of Concrete Drainage Structures


Unit of Measurement : cu.m.
Output per hour : 2.00

Designation No. of Person No. of Hours Hourly Rate

A. Labor

a. Construction Foreman 1 1 109.19


b. Skilled Laborer 2 1 79.70
c. Laborer 4 1 61.44

Sub - Total for A


Name and Capacity No of Units No. of Hours Hourly Rate

B. Equipment

a. Backhoe w/ Breaker (0.80 cu.m.) 1 0.50 2,074.95


b. Backhoe (0.80 cu.m.) 1 0.50 1,537.00
d. Dump Truck (10 cu.m.) 1 0.125 1,352.00
e. Cutting Outfit 1 1 45.00

* Disposal area (within three (3) km.)

Sub - Total for B


C. Total (A + B)
D. Output per hour = 2.00 cu.m.
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost

F. Materials

a. Oxy/Acetylene set 0.10 2,500.00

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G
I. Contractor's Profit (CP) 8% of G
J. Value Added Tax (VAT) 12% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 101(2)a Removal of RCPC (24" dia.) - 610mm


Unit of Measurement : l.m.
Output per hour : 6.00

Designation No. of Person No. of Hours Hourly Rate

A. Labor

a. Construction Foreman 1 1 109.19


b. Laborer 2 1 61.44

Sub - Total for A


Name and Capacity No of Units No. of Hours Hourly Rate

B. Equipment

a. Backhoe (0.80 cu.m.) 1 1 1,537.00


b. Boom Truck 1 0.50 961.20
Minor Tools (10 % of Labor)

Note: Exclude Excavation Works

* Disposal area (within three (3) km.)

Sub - Total for B


C. Total (A + B)
D. Output per hour = 6.00 l.m.
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost

F. Materials

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G
I. Contractor's Profit (CP) 8% of G
J. Value Added Tax (VAT) 12% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 101(2)b Removal of RCPC (30" dia.) - 760mm


Unit of Measurement : l.m.
Output per hour : 5.00

Designation No. of Person No. of Hours Hourly Rate

A. Labor

a. Construction Foreman 1 1 109.19


b. Laborer 2 1 61.44

Sub - Total for A


Name and Capacity No of Units No. of Hours Hourly Rate
B. Equipment

a. Backhoe (0.80 cu.m.) 1 1 1,537.00


b. Boom Truck 1 0.50 961.20
Minor Tools (10 % of Labor)

Note: Exclude Excavation Works

* Disposal area (within three (3) km.)

Sub - Total for B


C. Total (A + B)
D. Output per hour = 5.00 l.m.
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost

F. Materials

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G
I. Contractor's Profit (CP) 8% of G
J. Value Added Tax (VAT) 12% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 101(2)c Removal of RCPC (36" dia.) - 910mm


Unit of Measurement : l.m.
Output per hour : 4.00

Designation No. of Person No. of Hours Hourly Rate

A. Labor

a. Construction Foreman 1 1 109.19


b. Laborer 2 1 61.44

Sub - Total for A


Name and Capacity No of Units No. of Hours Hourly Rate
B. Equipment

a. Backhoe (0.80 cu.m.) 1 1 1,537.00


b. Boom Truck 1 0.50 961.20
Minor Tools (10 % of Labor)

Note: Exclude Excavation Works

* Disposal area (within three (3) km.)

Sub - Total for B


C. Total (A + B)
D. Output per hour = 4.00 l.m.
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost

F. Materials

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G
I. Contractor's Profit (CP) 8% of G
J. Value Added Tax (VAT) 12% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 101(2)d Removal of RCPC (42" dia.) - 1070mm


Unit of Measurement : l.m.
Output per hour : 4.00

Designation No. of Person No. of Hours Hourly Rate

A. Labor

a. Construction Foreman 1 1 109.19


b. Laborer 2 1 61.44

Sub - Total for A

Name and Capacity No of Units No. of Hours Hourly Rate

B. Equipment

a. Backhoe (0.80 cu.m.) 1 1 1,537.00


b. Boom Truck 1 0.50 961.20
Minor Tools (10 % of Labor)

Note: Exclude Excavation Works

* Disposal area (within three (3) km.)

Sub - Total for B


C. Total (A + B)
D. Output per hour = 4.00 l.m.
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost

F. Materials

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G
I. Contractor's Profit (CP) 8% of G
J. Value Added Tax (VAT) 12% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 101(2)e Removal of RCPC (48" dia.) - 1220mm


Unit of Measurement : l.m.
Output per hour : 3.00

Designation No. of Person No. of Hours Hourly Rate

A. Labor

a. Construction Foreman 1 1 109.19


b. Laborer 2 1 61.44

Sub - Total for A

Name and Capacity No of Units No. of Hours Hourly Rate

B. Equipment

a. Backhoe (0.80 cu.m.) 1 1 1,537.00


b. Boom Truck 1 0.50 961.20
Minor Tools (10 % of Labor)

Note: Exclude Excavation Works

* Disposal area (within three (3) km.)

Sub - Total for B


C. Total (A + B)
D. Output per hour = 3.00 l.m.
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost

F. Materials

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G
I. Contractor's Profit (CP) 8% of G
J. Value Added Tax (VAT) 12% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 101(2)f Removal of RCPC (60" dia.) - 1520mm


Unit of Measurement : l.m.
Output per hour : 2.00

Designation No. of Person No. of Hours Hourly Rate

A. Labor

a. Construction Foreman 1 1 109.19


b. Laborer 2 1 61.44

Sub - Total for A


Name and Capacity No of Units No. of Hours Hourly Rate

B. Equipment

a. Backhoe (0.80 cu.m.) 1 1 1,537.00


b. Boom Truck 1 0.50 961.20
Minor Tools (10 % of Labor)

Note: Exclude Excavation Works

* Disposal area (within three (3) km.)

Sub - Total for B


C. Total (A + B)
D. Output per hour = 2.00 l.m.
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost

F. Materials

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G
I. Contractor's Profit (CP) 8% of G
J. Value Added Tax (VAT) 12% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
Item No./Description : 101(2)g Removal of Pipes other than Pipe Culverts (PVC/GI/Asbestos, up to 200m
Unit of Measurement : ea.
Output per hour : 2.00

Designation No. of Person No. of Hours Hourly Rate

A. Labor

a. Construction Foreman 1 1 109.19


b. Skilled Laborer 1 1 79.70
c. Laborer 2 1 61.44

Sub - Total for A


Name and Capacity No of Units No. of Hours Hourly Rate

B. Equipment

a. Cargo Truck (10 T) 1 0.25 1,102.00


Minor Tools (10% of Labor)

Note: Exclude Excavation Works

* Disposal area (within three (3) km.)

Sub - Total for B


C. Total (A + B)
D. Output per hour = 2.00 ea.
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost

F. Materials

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G
I. Contractor's Profit (CP) 8% of G
J. Value Added Tax (VAT) 12% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
Item No./Description : 101(3)a.1 Removal of Existing Concrete Pavement (0.23m thk.)
Unit of Measurement : sq.m.
Output per hour : 40.00

Designation No. of Person No. of Hours Hourly Rate

A. Labor

a. Construction Foreman 1 1 109.19


b. Laborer 2 1 61.44

Sub - Total for A


Name and Capacity No of Units No. of Hours Hourly Rate

B. Equipment

a. Backhoe w/ Pavement Breaker (0.80 cu.m.) 1 1 2,074.95


b. Payloader (1.50 cu.m.), LX80-2C 1 1 1,733.00
c. Dump Truck (10 cu.m.) 1 0.50 1,352.00
Minor Tools (10% of Labor)

* Disposal area (within three (3) km.)

Sub - Total for B


C. Total (A + B)
D. Output per hour = 40.00 sq.m.
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost

F. Materials

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G
I. Contractor's Profit (CP) 8% of G
J. Value Added Tax (VAT) 12% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 101(3)a.2 Removal of Existing PCC Pavement, 0.23m thk. (for Reblocking at intermitt
Unit of Measurement : sq.m.
Output per hour : 30.00

Designation No. of Person No. of Hours Hourly Rate

A. Labor

a. Construction Foreman 1 1 109.19


b. Laborer 2 1 61.44

Sub - Total for A


Name and Capacity No of Units No. of Hours Hourly Rate

B. Equipment

a. Backhoe w/ Pavement Breaker (0.80 cu.m.) 1 1 2,074.95


b. Payloader (1.50 cu.m.), LX80-2C 1 1 1,733.00
c. Dump Truck (10 cu.m.) 1 0.50 1,352.00
d. Concrete Saw, Blade Ø 14" (7.5 Hp) 1 0.50 167.38
Minor Tools (10% of Labor)

* Disposal area (within three (3) km.)

Sub - Total for B


C. Total (A + B)
D. Output per hour = 30.00 sq.m.
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost

F. Materials

a. Concrete Saw (diamond blade 14") pc. 0.00015 8,000.00

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G
I. Contractor's Profit (CP) 8% of G
J. Value Added Tax (VAT) 12% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
Item No./Description : 101(3)b Removal of Existing Asphalt Pavement (100mm thk.)
Unit of Measurement : sq.m.
Output per hour : 60.00

Designation No. of Person No. of Hours Hourly Rate

A. Labor

a. Construction Foreman 1 1 109.19


b. Laborer 2 1 61.44

Sub - Total for A


Name and Capacity No of Units No. of Hours Hourly Rate

B. Equipment

a. Motorized Road Grader w/ Scarifier, G710A 1 1 2,173.00


b. Payloader (1.50 cu.m.), LX80-2C 1 1 1,733.00
c. Dump Truck (10 cu.m.) 1 0.50 1,352.00
Minor Tools (10% of Labor)

* Disposal area (within three (3) km.)

Sub - Total for B


C. Total (A + B)
D. Output per hour = 60.00 sq.m.
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost

F. Materials

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G
I. Contractor's Profit (CP) 8% of G
J. Value Added Tax (VAT) 12% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
Item No./Description : 101(3)c Removal of Sidewalk
Unit of Measurement : sq.m.
Output per hour : 60.00

Designation No. of Person No. of Hours Hourly Rate

A. Labor

a. Construction Foreman 1 1 109.19


b. Laborer 2 1 61.44

Sub - Total for A


Name and Capacity No of Units No. of Hours Hourly Rate

B. Equipment

a. Backhoe w/ Pavement Breaker (0.80 cu.m.) 1 0.50 2,074.95


b. Backhoe (0.80 cu.m.) 1 0.50 1,537.00
c. Dump Truck (10 cu.m.) 1 0.50 1,352.00

* Disposal area (within three (3) km.)

Sub - Total for B


C. Total (A + B)
D. Output per hour = 60.00 sq.m.
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost

F. Materials

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G
I. Contractor's Profit (CP) 8% of G
J. Value Added Tax (VAT) 12% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
Item No./Description : 101(4)a Removal of Curb
Unit of Measurement : l.m.
Output per hour : 50.00

Designation No. of Person No. of Hours Hourly Rate

A. Labor

a. Construction Foreman 1 1 109.19


b. Laborer 2 1 61.44

Sub - Total for A


Name and Capacity No of Units No. of Hours Hourly Rate

B. Equipment

a. Backhoe w/ Breaker (0.80 cu.m.) 1 0.50 2,074.95


b. Backhoe (0.80 cu.m.) 1 0.50 1,537.00
c. Dump Truck (10 cu.m.) 1 0.50 1,352.00

* Disposal area (within three (3) km.)

Sub - Total for B


C. Total (A + B)
D. Output per hour = 50.00 l.m.
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost

F. Materials

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G
I. Contractor's Profit (CP) 8% of G
J. Value Added Tax (VAT) 12% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
Item No./Description : 101(4)b Removal of Curb & Gutter
Unit of Measurement : l.m.
Output per hour : 30.00

Designation No. of Person No. of Hours Hourly Rate

A. Labor

a. Construction Foreman 1 1 109.19


b. Laborer 2 1 61.44

Sub - Total for A


Name and Capacity No of Units No. of Hours Hourly Rate

B. Equipment

a. Backhoe w/ Breaker (0.80 cu.m.) 1 0.50 2,074.95


b. Backhoe (0.80 cu.m.) 1 0.50 1,537.00
c. Dump Truck (10 cu.m.) 1 0.50 1,352.00

* Disposal area (within three (3) km.)

Sub - Total for B


C. Total (A + B)
D. Output per hour = 30.00 l.m.
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost

F. Materials

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G
I. Contractor's Profit (CP) 8% of G
J. Value Added Tax (VAT) 12% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
Item No./Description : 102(1) Roadway Excavation (Unsuitable)
Unit of Measurement : cu.m.
Output per hour : 20.00

Designation No. of Person No. of Hours Hourly Rate

A. Labor

a. Construction Foreman 1 1 109.19


b. Laborer 3 1 61.44

Sub - Total for A


Name and Capacity No of Units No. of Hours Hourly Rate

B. Equipment

a. Dump Truck (10 cu.m.) 2 1 1,352.00


b. Backhoe (0.80 cu.m.) 1 1 1,537.00
c. Payloader (1.50 cu.m.) at disposal site 1 0.10 1,733.00
Minor Tools (10% of Labor)

* Disposal area (within three (3) km.)

Sub - Total for B


C. Total (A + B)
D. Output per hour = 20.00 cu.m.
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost

F. Materials

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G
I. Contractor's Profit (CP) 8% of G
J. Value Added Tax (VAT) 12% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 102(2)a Roadway Excavation (Surplus


Unit of Measurement : Common) cu.m.
Output per hour : 60.00

Designation No. of Person No. of Hours Hourly Rate

A. Labor

a. Construction Foreman 1 1 109.19


b. Laborer 2 1 61.44

Sub - Total for A


Name and Capacity No of Units No. of Hours Hourly Rate

B. Equipment

a. Bulldozer (155 Hp), D65A-8 1 1 2,299.00


b. Payloader (1.50 cu.m.) 1 1 1,733.00
c. Payloader (1.50 cu.m.) - at disposal area 1 0.25 1,733.00
d. Dump Truck (10 cu.m.) 2 1 1,352.00

(Hauling Distance - within three (3) km.)

Sub - Total for B


C. Total (A + B)
D. Output per hour = 60.00 cu.m.
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost

F. Materials

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G
I. Contractor's Profit (CP) 8% of G
J. Value Added Tax (VAT) 12% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
Amount

109.19
122.88

232.07
Amount

2,704.00
1,733.00
2,299.00

6,736.00
6,968.07

13.94
Amount

0.00
13.94
1.25
1.11
1.96
18.26
Amount

109.19
79.70
122.88

311.77
Amount

768.50
676.00
60.75
15.59

1,520.84
1,832.61

610.87
Amount

70.00

70.00
680.87
61.28
54.47
95.59
892.21
Amount

109.19
79.70
122.88

311.77
Amount

768.50
676.00
60.75
15.59

1,520.84
1,832.61

1,832.61
Amount

70.00

70.00
1,902.61
171.23
152.21
267.13
2,493.18
Amount

109.19
79.70
122.88

311.77
Amount

1,537.00
1,352.00
121.50
15.59

3,026.09
3,337.86

13,351.43
Amount

70.00

70.00
13,421.43
1,207.93
1,073.71
1,884.37
17,587.45
Amount

109.19
79.70
122.88

311.77
Amount

1,537.00
1,352.00
121.50
15.59

3,026.09
3,337.86

26,702.87
Amount

70.00

70.00
26,772.87
2,409.56
2,141.83
3,758.91
35,083.17
Amount

109.19
79.7
122.88

311.77
Amount

1,537.00
1,352.00
31.18

2,920.18
3,231.95

323.19
Amount

0.00
323.19
29.09
25.86
45.38
423.51
Amount

109.19
159.40
245.76

514.35
Amount

1,037.48
1,028.62
675.00
169.00
216.63
388.25
45.00

3,559.97
4,074.32

4,074.32
Amount

250.00

250.00
4,324.32
389.19
345.95
607.13
5,666.59
Amount

109.19
159.40
245.76

514.35
Amount

712.00
391.00
1,553.00
45.00
51.44

2,752.44
3,266.79

3.27
Amount

0.63
0.18
0.18

0.98
4.25
0.38
0.34
0.60
5.56

Amount

109.19
159.40
245.76

514.35

Amount

1,037.48
768.50
338.00

2,143.98
2,658.33

531.67
Amount

0.00
531.67
47.85
42.53
74.65
696.69
Amount

109.19
159.40
245.76

514.35

Amount

1,037.48
768.50
169.00
45.00

2,019.98
2,534.33

1,267.16
Amount

250.00

250.00
1,517.16
136.54
121.37
213.01
1,988.09
Amount

109.19
122.88

232.07
Amount

1,537.00
480.60
23.21

2,040.81
2,272.88

378.81
Amount

0.00
378.81
34.09
30.31
53.19
496.40
Amount

109.19
122.88

232.07

Amount

1,537.00
480.60
23.21

2,040.81
2,272.88

454.58
Amount

0.00
454.58
40.91
36.37
63.82
595.68
Amount

109.19
122.88

232.07

Amount

1,537.00
480.60
23.21

2,040.81
2,272.88

568.22
Amount

0.00
568.22
51.14
45.46
79.78
744.59
Amount

109.19
122.88

232.07

Amount

1,537.00
480.60
23.21

2,040.81
2,272.88

568.22
Amount

0.00
568.22
51.14
45.46
79.78
744.59
Amount

109.19
122.88

232.07

Amount

1,537.00
480.60
23.21

2,040.81
2,272.88

757.63
Amount

0.00
757.63
68.19
60.61
106.37
992.79
Amount

109.19
122.88

232.07
Amount

1,537.00
480.60
23.21

2,040.81
2,272.88

1,136.44
Amount

0.00
1,136.44
102.28
90.92
159.56
1,489.19
m Ø), L=10 ft.

Amount

109.19
79.70
122.88

311.77
Amount

275.50
31.18

306.68
618.45

309.22
Amount

0.00
309.22
27.83
24.74
43.41
405.21
Amount

109.19
122.88

232.07
Amount

2,074.95
1,733.00
676.00
23.21

4,507.16
4,739.23

118.48
Amount

0.00
118.48
10.66
9.48
16.63
155.26
ent section)

Amount

109.19
122.88

232.07
Amount

2,074.95
1,733.00
676.00
83.69
23.21

4,590.85
4,822.92

160.76
Amount

1.20

1.20
161.96
14.58
12.96
22.74
212.24
Amount

109.19
122.88

232.07
Amount

2,173.00
1,733.00
676.00
23.21

4,605.21
4,837.28

80.62
Amount

0.00
80.62
7.26
6.45
11.32
105.65
Amount

109.19
122.88

232.07
Amount

1,037.48
768.50
676.00

2,481.98
2,714.05

45.23
Amount

0.00
45.23
4.07
3.62
6.35
59.27
Amount

109.19
122.88

232.07
Amount

1,037.48
768.50
676.00

2,481.98
2,714.05

54.28
Amount

0.00
54.28
4.89
4.34
7.62
71.13
Amount

109.19
122.88

232.07
Amount

1,037.48
768.50
676.00

2,481.98
2,714.05

90.47
Amount

0.00
90.47
8.14
7.24
12.70
118.55
Amount

109.19
184.32

293.51
Amount

2,704.00
1,537.00
173.30
29.35

4,443.65
4,737.16

236.86
Amount

0.00
236.86
21.32
18.95
33.25
310.38
Amount

109.19
122.88

232.07
Amount

2,299.00
1,733.00
433.25
2,704.00

7,169.25
7,401.32

123.36
Amount

0.00
123.36
11.10
9.87
17.32
161.64
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 102(2)b Roadway Excavation (Surplus Common)


Unit of Measurement : cu.m.
Output per hour : 80.00

Designation No. of Person No. of Hours Hourly Rate

A. Labor

a. Construction Foreman 1 1 109.19


b. Laborer 2 1 61.44

Sub - Total for A


Name and Capacity No of Units No. of Hours Hourly Rate

B. Equipment

a. Bulldozer (155 Hp), D65A-8 1 1 2,299.00


b. Payloader (1.50 cu.m.) 1 1 1,733.00
c. Payloader (1.50 cu.m.) - at disposal area 1 0.30 1,733.00
d. Dump Truck (10 cu.m.) 3 1 1,352.00
e. Backhoe (0.80 cu.m.) 1 1 1,537.00

(Hauling Distance - within three (3) km.)

Sub - Total for B


C. Total (A + B)
D. Output per hour = 80.00 cu.m.
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost

F. Materials

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G
I. Contractor's Profit (CP) 8% of G
J. Value Added Tax (VAT) 12% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
DETAILED UNIT PRICE ANALYSIS
(DUPA)
Item No./Description : 102(3)a Roadway Excavation (Surplus Soft Rock)
Unit of Measurement : cu.m.
Output per hour : 56.00

Designation No. of Person No. of Hours Hourly Rate

A. Labor

a. Construction Foreman 1 1 109.19


b. Laborer 2 1 61.44

Sub - Total for A


Name and Capacity No of Units No. of Hours Hourly Rate

B. Equipment

a. Bulldozer w/ Ripper (155 Hp), D65A-8 1 1 2,758.80


b. Payloader (1.50 cu.m.) 1 1 1,733.00
c. Payloader (1.50 cu.m.) at disposal area 1 0.25 1,733.00
d. Dump Truck (10 cu.m.) 2 1 1,352.00
e. Backhoe (0.80 cu.m.) w/ attachment 1 1 2,074.95

(Hauling Distance - within three (3) km.)

Sub - Total for B


C. Total (A + B)
D. Output per hour = 56.00 cu.m.
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost

F. Materials

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G
I. Contractor's Profit (CP) 8% of G
J. Value Added Tax (VAT) 12% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
Item No./Description : 102(3)b Roadway Excavation (Surplus Soft Rock)
Unit of Measurement : cu.m.
Output per hour : 42.00

Designation No. of Person No. of Hours Hourly Rate

A. Labor

a. Construction Foreman 1 1 109.19


b. Laborer 2 1 61.44

Sub - Total for A


Name and Capacity No of Units No. of Hours Hourly Rate

B. Equipment

a. Bulldozer w/ Ripper (155 Hp), D65A-8 1 1 2,758.80


b. Payloader (1.50 cu.m.) 1 1 1,733.00
c. Payloader (1.50 cu.m.) at disposal area 1 0.20 1,733.00
d. Dump Truck (10 cu.m.) 2 1 1,352.00

(Hauling Distance - within three (3) km.)

Sub - Total for B


C. Total (A + B)
D. Output per hour = 42.00 cu.m.
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost

F. Materials

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G
I. Contractor's Profit (CP) 8% of G
J. Value Added Tax (VAT) 12% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
Item No./Description : 102(3)c Roadway Excavation (Surplus Hard Rock) - Blasting
Unit of Measurement : cu.m.
Output per hour : 10.00

Designation No. of Person No. of Hours Hourly Rate

A. Labor
a. Construction Foreman (Drilling) 1 1 109.19
b. Skilled Laborer 2 1 79.70
c. Laborer 4 1 61.44
a. Construction Foreman (Blasting) 1 1 109.19
b. Skilled Laborer 1 1 79.70
c. Laborer 2 1 61.44
a. Construction Foreman (Disposal) 1 1 109.19
b Laborer 2 1 61.44
Sub - Total for A
Name and Capacity No of Units No. of Hours Hourly Rate

B. Equipment

a. Backhoe (0.80 cu.m.) 1 0.25 1,537.00


b. Payloader (1.50 cu.m.) 1 0.25 1,733.00
c. Payloader (1.50 cu.m.) - at disposal area 1 0.05 1,733.00
d. Dump Truck (10 cu.m.) 1 0.50 1,352.00
e. Pneumatic Drilling Machine 2 1 514.31
f. Compressor 1 1 358.00
(Hauling Distance - within three (3) km.)

Sub - Total for B


C. Total (A + B)
D. Output per hour = 10.00 cu.m.
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost

F. Materials

a. Dynamite kg. 0.40 280.00


b. Detonation Cord m. 2.00 80.00
c. Detonator pc. 0.15 260.00
d. Ammonium Sulfate kg. 0.20 75.00
e. Blasting Cap pc. 0.30 45.00
f. Safety Fuse m. 0.10 40.00

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G
I. Contractor's Profit (CP) 8% of G
J. Value Added Tax (VAT) 12% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 102(3)d Roadway Excavation (Surplus Hard Rock) - Blasting (Tunnel
Unit of Measurement Excavation)
: cu.m.
Output per hour : 6.50

Designation No. of Person No. of Hours Hourly Rate

A. Labor
a. Construction Foreman (Drilling) 1 4 109.19
b. Skilled Laborer 1 4 79.70
c. Laborer 2 4 61.44
a. Construction Foreman (Blasting) 1 1.50 109.19
b. Skilled Laborer 1 1.50 79.70
c. Laborer 2 1.50 61.44
a. Construction Foreman (Disposal) 1 1 109.19
b Laborer 1 1 61.44
Sub - Total for A
Name and Capacity No of Units No. of Hours Hourly Rate

B. Equipment

a. Backhoe (0.80 cu.m.) 1 0.50 1,537.00


b. Dump Truck (10 cu.m.) 1 0.30 1,352.00
c. Pneumatic Drilling Machine 2 4 514.31
d. Compressor 1 4 358.00
e. Payloader (1.50 cu.m.) 1 0.15 1,733.00
f. Payloader (1.50 cu.m.) - at disposal area 1 0.03 1,733.00

(Hauling Distance - within three (3) km.)

Sub - Total for B


C. Total (A + B)
D. Output per hour = 6.50 cu.m.
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost

F. Materials

a. Dynamite kg. 3.10 280.00


b. Detonation Cord m. 2.30 80.00
c. Detonator pc. 3.10 260.00
d. Ammonium Sulfate kg. 1.50 75.00
e. Blasting Cap pc. 0.50 45.00
f. Safety Fuse m. 0.15 40.00

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G
I. Contractor's Profit (CP) 8% of G
J. Value Added Tax (VAT) 12% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 102(4) Roadway Excavation


Unit of Measurement : (Unclassified) cu.m.
Output per hour : 50.00

Designation No. of Person No. of Hours Hourly Rate

A. Labor

a. Construction Foreman 1 1 109.19


b. Laborer 2 1 61.44

Sub - Total for A


Name and Capacity No of Units No. of Hours Hourly Rate
B. Equipment

a. Bulldozer (155 Hp), D65A-8 1 1 2,299.00


b. Payloader (1.50 cu.m.) 1 1 1,733.00
c. Payloader (1.50 cu.m.) - at disposal area 1 0.20 1,733.00
d. Dump Truck (10 cu.m.) 2 1 1,352.00

(Hauling Distance - within three (3) km.)

Sub - Total for B


C. Total (A + B)
D. Output per hour = 50.00 cu.m.
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost

F. Materials

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G
I. Contractor's Profit (CP) 8% of G
J. Value Added Tax (VAT) 12% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 103(1)a Structure Excavation (Common Soil)


Unit of Measurement : cu.m.
Output per hour : 20.00

Designation No. of Person No. of Hours Hourly Rate

A. Labor

a. Construction Foreman 1 1 109.19


b. Laborer 3 1 61.44

Sub - Total for A


Name and Capacity No of Units No. of Hours Hourly Rate
B. Equipment

a. Dump Truck (10 cu.m.) 2 1 1,352.00


b. Backhoe (0.80 cu.m.) 1 1 1,537.00
Minor Tools (10% of Labor)

Sub - Total for B


C. Total (A + B)
D. Output per hour = 20.00 cu.m.
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost

F. Materials

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G
I. Contractor's Profit (CP) 8% of G
J. Value Added Tax (VAT) 12% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 103(1)b Structure Excavation (Soft Rock)


Unit of Measurement : cu.m.
Output per hour : 14.00

Designation No. of Person No. of Hours Hourly Rate

A. Labor

a. Construction Foreman 1 1 109.19


b. Laborer 3 1 61.44

Sub - Total for A


Name and Capacity No of Units No. of Hours Hourly Rate
B. Equipment

a. Dump Truck (10 cu.m.) 2 1 1,352.00


b. Backhoe (0.80 cu.m.) 1 0.50 1,537.00
c. Backhoe w/ Breaker (0.80 cu.m.) 1 0.50 2,074.95
Minor Tools (10% of Labor)

Sub - Total for B


C. Total (A + B)
D. Output per hour = 14.00 cu.m.
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost

F. Materials

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G
I. Contractor's Profit (CP) 8% of G
J. Value Added Tax (VAT) 12% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 103(1)c Structure Excavation (Solid Rock)


Unit of Measurement : cu.m.
Output per hour : 4.00

Designation No. of Person No. of Hours Hourly Rate

A. Labor

a. Construction Foreman 1 1 109.19


b. Laborer 3 1 61.44

Sub - Total for A


Name and Capacity No of Units No. of Hours Hourly Rate

B. Equipment

a. Dump Truck (10 cu.m.) 1 1 1,352.00


b. Backhoe (0.80 cu.m.) 1 0.50 1,537.00
c. Backhoe w/ Breaker (0.80 cu.m.) 1 0.50 2,074.95
Minor Tools (10% of Labor)

Sub - Total for B


C. Total (A + B)
D. Output per hour = 4.00 cu.m.
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost

F. Materials

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G
I. Contractor's Profit (CP) 8% of G
J. Value Added Tax (VAT) 12% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 103(2)a Bridge Excavation (Common Soil)


Unit of Measurement : cu.m.
Output per hour : 20.00

Designation No. of Person No. of Hours Hourly Rate

A. Labor

a. Construction Foreman 1 1 109.19


b. Skilled Laborer 1 1 79.70
c. Laborer 2 1 61.44

Sub - Total for A


Name and Capacity No of Units No. of Hours Hourly Rate

B. Equipment

b. Backhoe (0.80 cu.m.) 1 1 1,537.00


b. Dump Truck (10 cu.m.) 2 1 1,352.00
Minor Tools (10% of Labor)

Sub - Total for B


C. Total (A + B)
D. Output per hour = 20.00 cu.m.
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost

F. Materials

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G
I. Contractor's Profit (CP) 8% of G
J. Value Added Tax (VAT) 12% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 103(2)b Bridge Excavation (Soft Rock)


Unit of Measurement : cu.m.
Output per hour : 14.00

Designation No. of Person No. of Hours Hourly Rate

A. Labor

a. Construction Foreman 1 1 109.19


b. Skilled Laborer 1 1 79.70
c. Laborer 2 1 61.44

Sub - Total for A


Name and Capacity No of Units No. of Hours Hourly Rate

B. Equipment

a. Backhoe (0.80 cu.m.) 1 0.50 1,537.00


b. Backhoe w/ Breaker (0.80 cu.m.) 1 0.50 2,074.95
c. Dump Truck (10 cu.m.) 2 1 1,352.00
Minor Tools (10% of Labor)

Sub - Total for B


C. Total (A + B)
D. Output per hour = 14.00 cu.m.
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost

F. Materials

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G
I. Contractor's Profit (CP) 8% of G
J. Value Added Tax (VAT) 12% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 103(2)c Bridge Excavation (Solid Rock)


Unit of Measurement : cu.m.
Output per hour : 4.00

Designation No. of Person No. of Hours Hourly Rate

A. Labor

a. Construction Foreman 1 1 109.19


b. Skilled Laborer 1 1 79.70
c. Laborer 2 1 61.44

Sub - Total for A


Name and Capacity No of Units No. of Hours Hourly Rate

B. Equipment

a. Backhoe (0.80 cu.m.) 1 0.50 1,537.00


b. Backhoe w/ Breaker (0.80 cu.m.) 1 0.50 2,074.95
c. Dump Truck (10 cu.m.) 1 1 1,352.00
Minor Tools (10% of Labor)

Sub - Total for B


C. Total (A + B)
D. Output per hour = 4.00 cu.m.
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost

F. Materials

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G
I. Contractor's Profit (CP) 8% of G
J. Value Added Tax (VAT) 12% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 103(3) Foundation Fill


Unit of Measurement : cu.m.
Output per hour : 1.25

Designation No. of Person No. of Hours Hourly Rate

A. Labor

a. Construction Foreman 1 1 109.19


b. Laborer 4 1 61.44

Sub - Total for A


Name and Capacity No of Units No. of Hours Hourly Rate
B. Equipment

a. Plate Compactor (5 Hp) 1 1 123.00


b. Water Truck (1000 gal.) 1 0.01 1,065.00
Minor Tools (10% of Labor)

Sub - Total for B


C. Total (A + B)
D. Output per hour = 1.25 cu.m.
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost

F. Materials

a. Filling Materials cu.m. 1.15 465.00

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G
I. Contractor's Profit (CP) 8% of G
J. Value Added Tax (VAT) 12% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 103(4) Excavation ordered below Plan Elevation


Unit of Measurement : cu.m.
Output per hour : 20.00

Designation No. of Person No. of Hours Hourly Rate

A. Labor

a. Construction Foreman 1 1 109.19


b. Laborer 3 1 61.44

Sub - Total for A

Name and Capacity No of Units No. of Hours Hourly Rate

B. Equipment

a. Dump Truck (10 cu.m.) 2 1 1,352.00


b. Backhoe (0.80 cu.m.) 1 1 1,537.00
Minor Tools (10% of Labor)

Sub - Total for B


C. Total (A + B)
D. Output per hour = 20.00 cu.m.
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost

F. Materials

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G
I. Contractor's Profit (CP) 8% of G
J. Value Added Tax (VAT) 12% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 103(5)a Shoring


Unit of Measurement : l.s.
Output : 1.00

Designation No. of Person No. of Hours Hourly Rate

A. Labor

Note:
*) The component quantity of items of work involved such as item 404/405/509 shall be based on the
actual design of the shoring.
**) Costing of this item shall be based on the standard Detailed Unit Price Analysis (DUPA) of item
404/405
as processed component pay item.

Sub - Total for A

Name and Capacity No of Units No. of Hours Hourly Rate

B. Equipment

Sub - Total for B


C. Total (A + B)
D. Output = 1.00 l.s.
E. Direct Unit Cost (C ÷ D)
Direct Unit
Name and Specification Unit Quantity
Cost
F. Materials/Processed Component Pay Item

a. 404 - Reinforcing Steel Bar kg. *


b. 405 - Structural Concrete cu.m. *
c. 509 - Steel Sheet Pile l.m. *

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G
I. Contractor's Profit (CP) 8% of G
J. Value Added Tax (VAT) 12% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 103(5)b Cribbing/Cofferdamming


Unit of Measurement : l.s.
Output : 1.00

Designation No. of Person No. of Hours Hourly Rate


A. Labor

a. Construction Foreman 1 135 109.19


b. Skilled Laborer 2 135 79.70
c. Laborer 4 135 61.44

Sub - Total for A


Name and Capacity
No of Units No. of Hours Hourly Rate
B. Equipment

a. Crawler Crane (36 - 40 T) 1 135 1,729.00


b. Vibro Hammer (Hydraulic Operated) 1 135 1,800.00
c. Welding Machine 1 33.75 391.00
d. Cutting Outfit 1 33.75 45.45
e. Water Pump, 100mm suction diameter 1 135 266.25

Sub - Total for B Total (A + B)


C.
Output = 1.00 l.s.
Direct Unit Cost (C ÷ D)
Name and Specification
Materials Unit Quantity Unit Cost

Steel Sheet Pile kg. 51,840.00 48.00


Walling, Bracing, Diagonal, etc. Miscellaneous (1% of Materials) kg. 7,323.77 48.00

Note:
a.) The assume dimesion of area to be provided with cofferdam is 12m x 12m square with Steel Sheet Piles depth of 9m at 48 kg./m.
b.) The quantity of component materials requirement may vary depending on the actual design of Cribbing/Cofferdamming.

Sub - Total for F


Direct Unit Cost (E + F)
Overhead, Contingencies & Miscellaneous (OCM) 9% of G
Contractor's Profit (CP) 8% of G
Value Added Tax (VAT) 12% of (G + H + I) (G + H + I + J)
Total Unit Cost
Item No./Description : 103(6) Pipe Culvert and Drain Excavation
Unit of Measurement : cu.m.
Output per hour : 20.00

Designation No. of Person No. of Hours Hourly Rate

A. Labor

a. Construction Foreman 1 1 109.19


b. Laborer 3 1 61.44

Sub - Total for A


Name and Capacity No of Units No. of Hours Hourly Rate

B. Equipment

a. Dump Truck (10 cu.m.) 2 1 1,352.00


b. Backhoe (0.80 cu.m.) 1 1 1,537.00
Minor Tools (10% of Labor)

Sub - Total for B


C. Total (A + B)
D. Output per hour = 20.00 cu.m.
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost

F. Materials

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G
I. Contractor's Profit (CP) 8% of G
J. Value Added Tax (VAT) 12% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 104(1)a Embankment (from Borrow)


Unit of Measurement : cu.m.
Output per hour : 50.00

Designation No. of Person No. of Hours Hourly Rate

A. Labor

a. Construction Foreman 1 1 109.19


b. Laborer 2 1 61.44

Sub - Total for A


Name and Capacity No of Units No. of Hours Hourly Rate

B. Equipment

a. Motorized Road Grader, G710A 1 1 2,173.00


b. Vibratory Roller (10 m.t.), SP56 1 1 1,507.00
c. Water Truck (1000 gal.) 1 0.25 1,065.00

Sub - Total for B


C. Total (A + B)
D. Output per hour = 50.00 cu.m.
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost

F. Materials

a. Common Borrow (w/ 25% Shrinkage Factor) cu.m. 1.25 400.00

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G
I. Contractor's Profit (CP) 8% of G
J. Value Added Tax (VAT) 12% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
Item No./Description : 104(1)b Embankment from Roadway Excavation
Unit of Measurement : cu.m.
Output per hour : 50.00

Designation No. of Person No. of Hours Hourly Rate

A. Labor
For Excavation Work:
a. Construction Foreman 1 0.83 109.19
b. Laborer 2 0.83 61.44

Spreading and Compaction:


a. Construction Foreman 1 1 109.19
b. Laborer 2 1 61.44

Sub - Total for A


Name and Capacity No of Units No. of Hours Hourly Rate

B. Equipment
For Excavation Work:
a. Bulldozer (155 Hp), D65A-8 1 0.83 2,299.00
b. Payloader (1.50 cu.m.) 1 0.83 1,733.00
c. Dump Truck (10 cu.m.) 2 0.83 1,352.00

Spreading and Compaction:


a. Motorized Road Grader, G710A 1 1 2,173.00
b. Vibratory Roller (10 m.t.), SP56 1 1 1,507.00
c. Water Truck (1000 gal.) 1 0.25 1,065.00

Sub - Total for B


C. Total (A + B)
D. Output per hour = 50.00 cu.m.
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost

F. Materials

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G
I. Contractor's Profit (CP) 8% of G
J. Value Added Tax (VAT) 12% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 104(2) Selected Borrow for topping , case


Unit of Measurement : 1 cu.m.
Output per hour : 50.00

Designation No. of Person No. of Hours Hourly Rate

A. Labor

a. Construction Foreman 1 1 109.19


b. Laborer 2 1 61.44

Sub - Total for A


Name and Capacity No of Units No. of Hours Hourly Rate

B. Equipment

a. Motorized Road Grader, G710A 1 1 2,173.00


b. Vibratory Roller (10 m.t.) 1 1 1,507.00
c. Water Truck (1000 gal.) 1 0.25 1,065.00

Sub - Total for B


C. Total (A + B)
D. Output per hour = 50.00 cu.m.
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost

F. Materials

a. Selected Borrow (w/ 25% Shrinkage Factor) cu.m. 1.25 420.00

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G
I. Contractor's Profit (CP) 8% of G
J. Value Added Tax (VAT) 12% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 104(3) Selected Borrow for topping , case


Unit of Measurement : 2 cu.m.
Output per hour : 50.00

Designation No. of Person No. of Hours Hourly Rate

A. Labor

a. Construction Foreman 1 1 109.19


b. Laborer 2 1 61.44

Sub - Total for A


Name and Capacity No of Units No. of Hours Hourly Rate

B. Equipment

a. Motorized Road Grader, G710A 1 1 2,173.00


b. Vibratory Roller (10 m.t.) 1 1 1,507.00
c. Water Truck (1000 gal.) 1 0.25 1,065.00

Sub - Total for B


C. Total (A + B)
D. Output per hour = 50.00 cu.m.
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost

F. Materials

a. Selected Borrow (w/ 25% Shrinkage Factor) cu.m. 1.25 420.00

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G
I. Contractor's Profit (CP) 8% of G
J. Value Added Tax (VAT) 12% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 104(4) Earth Berm


Unit of Measurement : cu.m.
Output per hour : 1.25

Designation No. of Person No. of Hours Hourly Rate

A. Labor

a. Construction Foreman 1 1 109.19


b. Laborer 4 1 61.44

Sub - Total for A


Name and Capacity No of Units No. of Hours Hourly Rate

B. Equipment

a. Plate Compactor (5 Hp) 1 1 123.00


b. Water Truck (1000 gal.) 1 0.01 1,065.00
Minor Tools (10% of Labor)

Sub - Total for B


C. Total (A + B)
D. Output per hour = 1.25 cu.m.
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost

F. Materials

a. Filling Materials cu.m. 1.25 420.00

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G
I. Contractor's Profit (CP) 8% of G
J. Value Added Tax (VAT) 12% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 105(1) Subgrade Preparation (Common Material)


Unit of Measurement : sq.m.
Output per hour : 300.00

Designation No. of Person No. of Hours Hourly Rate

A. Labor

a. Construction Foreman 1 1 109.19


b. Laborer 2 1 61.44

Sub - Total for A


Name and Capacity No of Units No. of Hours Hourly Rate

B. Equipment

a. Motorized Road Grader, G710A 1 1 2,173.00


b. Vibratory Roller (10 m.t.), SP56 1 1 1,507.00
c. Water Truck (1000 gal.) 1 0.25 1,065.00

Sub - Total for B


C. Total (A + B)
D. Output per hour = 300.00 sq.m.
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost

F. Materials

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G
I. Contractor's Profit (CP) 8% of G
J. Value Added Tax (VAT) 12% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 105(2) Subgrade Preparation (Existing


Unit of Measurement : Pavement) sq.m.
Output per hour : 300.00

Designation No. of Person No. of Hours Hourly Rate

A. Labor

a. Construction Foreman 1 1 109.19


b. Laborer 2 1 61.44

Sub - Total for A


Name and Capacity No of Units No. of Hours Hourly Rate

B. Equipment

a. Motorized Road Grader, G710A 1 1 2,173.00


b. Vibratory Roller (10 m.t.), SP56 1 1 1,507.00
c. Water Truck (1000 gal.) 1 0.25 1,065.00

Sub - Total for B


C. Total (A + B)
D. Output per hour = 300.00 sq.m.
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost

F. Materials

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G
I. Contractor's Profit (CP) 8% of G
J. Value Added Tax (VAT) 12% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 105(3) Subgrade Preparation (Unsuitable Material)


Unit of Measurement : sq.m.
Output per hour : 300.00

Designation No. of Person No. of Hours Hourly Rate

A. Labor

a. Construction Foreman 1 1 109.19


b. Laborer 2 1 61.44

Sub - Total for A


Name and Capacity No of Units No. of Hours Hourly Rate

B. Equipment

a. Motorized Road Grader, G710A 1 1 2,173.00


b. Vibratory Roller (10 m.t.), SP56 1 1 1,507.00
c. Water Truck (1000 gal.) 1 0.25 1,065.00

Sub - Total for B


C. Total (A + B)
D. Output per hour = 300.00 sq.m.
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost

F. Materials

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G
I. Contractor's Profit (CP) 8% of G
J. Value Added Tax (VAT) 12% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
Amount

109.19
122.88

232.07
Amount

2,299.00
1,733.00
519.90
4,056.00
1,537.00

10,144.90
10,376.97

129.71
Amount

0.00
129.71
11.67
10.38
18.21
169.97
Amount

109.19
122.88

232.07
Amount

2,758.80
1,733.00
433.25
2,704.00
2,074.95

9,704.00
9,936.07

177.43
Amount

0.00
177.43
15.97
14.19
24.91
232.50
Amount

109.19
122.88

232.07
Amount

2,758.80
1,733.00
346.60
2,704.00

7,542.40
7,774.47

185.11
Amount

0.00
185.11
16.66
14.81
25.99
242.56
Amount

109.19
159.4
245.76
109.19
79.7
122.88
109.19
122.88
1,058.19

Amount

384.25
433.25
86.65
676.00
1,028.62
358.00

2,966.77
4,024.96

402.50
Amount

112.00
160.00
39.00
15.00
13.50
4.00

343.50
746.00
67.14
59.68
104.74
977.55
Amount

436.76
318.8
491.52
163.785
119.55
184.32
109.19
61.44
1,885.37

Amount

768.50
405.60
4,114.48
1,432.00
259.95
51.99

7,032.52
8,917.89

1,371.98
Amount

868.00
184.00
806.00
112.50
22.50
6.00

1,999.00
3,370.98
303.39
269.68
473.29
4,417.34
Amount

109.19
122.88

232.07
Amount

2,299.00
1,733.00
346.60
2,704.00

7,082.60
7,314.67

146.29
Amount

0.00
146.29
13.17
11.70
20.54
191.70
Amount

109.19
184.32

293.51
Amount

2,704.00
1,537.00
29.35

4,270.35
4,563.86

228.19
Amount

0.00
228.19
20.54
18.26
32.04
299.02
Amount

109.19
184.32

293.51
Amount

2,704.00
768.50
1,037.48
29.35

4,539.33
4,832.84

345.20
Amount

0.00
345.20
31.07
27.62
48.47
452.35

Amount

109.19
184.32

293.51

Amount

1,352.00
768.50
1,037.48
29.35

3,187.33
3,480.84

870.21
Amount

0.00
870.21
78.32
69.62
122.18
1,140.32
Amount

109.19
79.70
122.88

311.77

Amount

1,537.00
2,704.00
31.18

4,272.18
4,583.95

229.20
Amount

0.00
229.20
20.63
18.34
32.18
300.34
Amount

109.19
79.70
122.88

311.77
Amount

768.50
1,037.48
2,704.00
31.18

4,541.15
4,852.92

346.64
Amount

0.00
346.64
31.20
27.73
48.67
454.23
Amount

109.19
79.70
122.88

311.77

Amount

768.50
1,037.48
1,352.00
31.18

3,189.15
3,500.92

875.23
Amount

0.00
875.23
78.77
70.02
122.88
1,146.90
Amount

109.19
245.76

354.95

Amount

123.00
10.65
35.50

169.15
524.10

419.28
Amount

534.75

534.75
954.03
85.86
76.32
133.95
1,250.16
Amount

109.19
184.32

293.51

Amount

2,704.00
1,537.00
29.35

4,270.35
4,563.86

228.19
Amount

0.00
228.19
20.54
18.26
32.04
299.02
Amount

/509

Amount

Direct Cost
Amount

14,740.65
21,519.00
33,177.60

69,437.25
Amount

233,415.00
243,000.00
13,196.25
1,533.94
35,943.75

527,088.94
596,526.19

596,526.19
Amount

2,488,320.00
351,540.96
28,398.61

2,868,259.57
3,464,785.76
311,830.72
277,182.86
486,455.92
4,540,255.26
Amount

109.19
184.32

293.51
Amount

2,704.00
1,537.00
29.35

4,270.35
4,563.86

228.19
Amount

0.00
228.19
20.54
18.26
32.04
299.02
Amount

109.19
122.88

232.07
Amount

2,173.00
1,507.00
266.25

3,946.25
4,178.32

83.57
Amount

500.00

500.00
583.57
52.52
46.69
81.93
764.71
Amount

90.63
101.99

109.19
122.88

424.69
Amount

1,908.17
1,438.39
2,244.32

2,173.00
1,507.00
266.25

9,537.13
9,961.82

199.24
Amount

0.00
199.24
17.93
15.94
27.97
261.08
Amount

109.19
122.88

232.07
Amount

2,173.00
1,507.00
266.25

3,946.25
4,178.32

83.57
Amount

525.00

525.00
608.57
54.77
48.69
85.44
797.47
Amount

109.19
122.88

232.07
Amount

2,173.00
1,507.00
266.25

3,946.25
4,178.32

83.57
Amount

525.00

525.00
608.57
54.77
48.69
85.44
797.47
Amount

109.19
245.76

354.95
Amount

123.00
10.65
35.50

169.15
524.10

419.28
Amount

525.00

525.00
944.28
84.98
75.54
132.58
1,237.38
Amount

109.19
122.88

232.07
Amount

2,173.00
1,507.00
266.25

3,946.25
4,178.32

13.93
Amount

0.00
13.93
1.25
1.11
1.96
18.25
Amount

109.19
122.88

232.07
Amount

2,173.00
1,507.00
266.25

3,946.25
4,178.32

13.93
Amount

0.00
13.93
1.25
1.11
1.96
18.25
Amount

109.19
122.88

232.07
Amount

2,173.00
1,507.00
266.25

3,946.25
4,178.32

13.93
Amount

0.00
13.93
1.25
1.11
1.96
18.25
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 200 Aggregate Subbase Course


Unit of Measurement : cu.m
Output per hour : 50.00

Designation No. of Person No. of Hours Hourly Rate

A. Labor

a. Construction Foreman 1 1 109.19


b. Laborers 2 1 61.44

Sub - Total for A


Name and Capacity No of Units No. of Hours Hourly Rate

B. Equipment

a. Motorized Road Grader, G710A 1 1 2,173.00


b. Vibratory Roller (10 m.t.), SP56 1 1 1,507.00
c. Water Truck (1000 gal.) 1 0.25 1,065.00

Sub - Total for B


C. Total (A + B)
D. Output per hour = 50.00 cu.m.
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost

F. Materials

a. Aggregate Subbase Course cu.m. 1.15 580.00


(w/ 15% Shrinkage Factor)

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G
I. Contractor's Profit (CP) 8% of G
J. Value Added Tax (VAT) 12% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
Item No./Description : 200(1) Aggregate Subbase Course (for Intermittent Reblocking)
Unit of Measurement : cu.m
Output per hour : 40.00

Designation No. of Person No. of Hours Hourly Rate

A. Labor

a. Construction Foreman 1 1 109.19


b. Laborers 2 1 61.44

Sub - Total for A


Name and Capacity No of Units No. of Hours Hourly Rate

B. Equipment

a. Motorized Road Grader, G710A 1 1 2,173.00


b. Vibratory Roller (10 m.t.), SP56 1 1 1,507.00
c. Plate Compactor (5 Hp) 1 0.25 123.00
d. Water Truck (1000 gal.) 1 0.25 1,065.00

Sub - Total for B


C. Total (A + B)
D. Output per hour = 40.00 cu.m.
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost

F. Materials

a. Aggregate Subbase Course cu.m. 1.15 580.00


(w/ 15% Shrinkage Factor)

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G
I. Contractor's Profit (CP) 8% of G
J. Value Added Tax (VAT) 12% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 201 Aggregate Base Course


Unit of Measurement : cu.m
Output per hour : 50.00

Designation No. of Person No. of Hours Hourly Rate

A. Labor

a. Construction Foreman 1 1 109.19


b. Laborers 2 1 61.44

Sub - Total for A


Name and Capacity No of Units No. of Hours Hourly Rate
B. Equipment

a. Motorized Road Grader, G710A 1 1 2,173.00


b. Vibratory Roller (10 m.t.), SP56 1 1 1,507.00
c. Water Truck (1000 gal.) 1 0.25 1,065.00

Sub - Total for B


C. Total (A + B)
D. Output per hour = 50.00 cu.m.
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost

F. Materials

a. Aggregate Base Course cu.m. 1.15 650.00


(w/ 15% Shrinkage Factor)

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G
I. Contractor's Profit (CP) 8% of G
J. Value Added Tax (VAT) 12% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 201(1) Aggregate Base Course (for Reblocking)


Unit of Measurement : cu.m
Output per hour : 40.00

Designation No. of Person No. of Hours Hourly Rate

A. Labor

a. Construction Foreman 1 1 109.19


b. Laborers 2 1 61.44

Sub - Total for A


Name and Capacity No of Units No. of Hours Hourly Rate
B. Equipment

a. Motorized Road Grader, G710A 1 1 2,173.00


b. Vibratory Roller (10 m.t.), SP56 1 1 1,507.00
c. Plate Compactor (5 Hp) 1 0.25 123.00
d. Water Truck (1000 gal.) 1 0.25 1,065.00

Sub - Total for B


C. Total (A + B)
D. Output per hour = 40.00 cu.m.
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost

F. Materials

a. Aggregate Base Course cu.m. 1.15 650.00


(w/ 15% Shrinkage Factor)

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G
I. Contractor's Profit (CP) 8% of G
J. Value Added Tax (VAT) 12% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 202 Crushed Aggregate Base Course


Unit of Measurement : cu.m
Output per hour : 50.00

Designation No. of Person No. of Hours Hourly Rate

A. Labor

a. Construction Foreman 1 1 109.19


b. Laborers 2 1 61.44

Sub - Total for A


Name and Capacity No of Units No. of Hours Hourly Rate

B. Equipment

a. Motorized Road Grader, G710A 1 1 2,173.00


b. Vibratory Roller (10 m.t.), SP56 1 1 1,507.00
c. Water Truck (1000 gal.) 1 0.25 1,065.00

Sub - Total for B


C. Total (A + B)
D. Output per hour = 50.00 cu.m.
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost

F. Materials

a. Crushed Aggregate Base Course cu.m. 1.15 700.00


(w/ 15% Shrinkage Factor)

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G
I. Contractor's Profit (CP) 8% of G
J. Value Added Tax (VAT) 12% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
Amount

109.19
122.88

232.07
Amount

2,173.00
1,507.00
266.25

3,946.25
4,178.32

83.57
Amount

667.00

667.00
750.57
67.55
60.05
105.38
983.54
Amount

109.19
122.88

232.07
Amount

2,173.00
1,507.00
30.75
266.25

3,977.00
4,209.07

105.23
Amount

667.00

667.00
772.23
69.50
61.78
108.42
1,011.93
Amount

109.19
122.88

232.07
Amount

2,173.00
1,507.00
266.25

3,946.25
4,178.32

83.57
Amount

747.50

747.50
831.07
74.80
66.49
116.68
1,089.03
Amount

109.19
122.88

232.07
Amount

2,173.00
1,507.00
30.75
266.25

3,977.00
4,209.07

105.23
Amount

747.50

747.50
852.73
76.75
68.22
119.72
1,117.41
Amount

109.19
122.88

232.07

Amount

2,173.00
1,507.00
266.25

3,946.25
4,178.32

83.57
Amount

805.00

805.00
888.57
79.97
71.09
124.75
1,164.38
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 203 Lime Stabilized Road Mix Base


Unit of Measurement : Course cu.m.
Output per hour : 15.00

Designation No. of Person No. of Hours Hourly Rate

A. Labor

a. Construction Foreman 1 1 109.19


b. Laborer 10 1 61.44

Sub - Total for A


Name and Capacity No of Units No. of Hours Hourly Rate

B. Equipment

a. Motorized Road Grader (140 Hp) 1 1 2,173.00


b. Vibratory Roller (10 m.t.), SP56 1 1 1,507.00
c. Water Truck (1000 gal.) 1 0.25 1,065.00

Sub - Total for B


C. Total (A + B)
D. Output per hour = 15.00 cu.m.
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost

F. Materials

a. Hydrated Lime, Type N (Normal) bag 2.80 180.00


b. Aggregate Base Course cu.m. 1.15 650.00

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G
I. Contractor's Profit (CP) 8% of G
J. Value Added Tax (VAT) 12% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 204 Portland Cement Stabilized Road Mix Base


Unit of Measurement : Course cu.m.
Output per hour : 15.00

Designation No. of Person No. of Hours Hourly Rate

A. Labor

a. Construction Foreman 1 1 109.19


b. Laborer 10 1 61.44

Sub - Total for A


Name and Capacity No of Units No. of Hours Hourly Rate

B. Equipment

a. Motorized Road Grader (140 Hp) 1 1 2,173.00


b. Vibratory Roller (10 m.t.), SP56 1 1 1,507.00
c. Water Truck (1000 gal.) 1 0.25 1,065.00

Sub - Total for B


C. Total (A + B)
D. Output per hour = 15.00 cu.m.
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost

F. Materials

a. Cement bag 3 220.00


b. Aggregate Base Course cu.m. 1.15 650.00

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G
I. Contractor's Profit (CP) 8% of G
J. Value Added Tax (VAT) 12% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 205 Asphalt Stabilized Road Mix Base Course


Unit of Measurement : cu.m.
Output per hour : 15.00

Designation No. of Person No. of Hours Hourly Rate

A. Labor

a. Construction Foreman 1 1 109.19


b. Laborer 10 1 61.44

Sub - Total for A


Name and Capacity No of Units No. of Hours Hourly Rate
B. Equipment

a. Motorized Road Grader (140 Hp) 1 1 2,173.00


b. Vibratory Roller (10 m.t.), SP56 1 1 1,507.00
c. Water Truck (1000 gal.) 1 0.25 1,065.00
d. Asphalt Distributor, 10 ft. wide (5 tons) 1 1 936.00

Sub - Total for B


C. Total (A + B)
D. Output per hour = 15.00 cu.m.
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost

F. Materials

a. Emulsified Asphalt SS-1 m.t. 0.07 44,000.00


b. Aggregate Base Course cu.m. 1.15 650.00

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G
I. Contractor's Profit (CP) 8% of G
J. Value Added Tax (VAT) 12% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 206 Portland Cement Treated Plant Mix Base Course
Unit of Measurement : cu.m.
Output per hour : 15.00

Designation No. of Person No. of Hours Hourly Rate

A. Labor

a. Construction Foreman 1 1 109.19


b. Skilled Laborer 2 1 79.70
c. Laborer 4 1 61.44

Sub - Total for A


Name and Capacity No of Units No. of Hours Hourly Rate

B. Equipment

a. Batching Plant (30 cu.m.) 1 0.50 1,208.03


b. Dump Truck (10 cu.m.) 3 0.50 1,352.00
c. Motorized Road Grader, G710A 1 0.50 2,173.00
d. Vibratory Roller (10 m.t.), SP56 1 0.50 1,507.00
e. Payloader (1.50 cu.m.), LX80-2C 1 0.50 1,733.00
f. Water Truck (1000 gal.) 1 0.25 1,065.00
g. Asphalt Distributor, 10 ft. wide (5 tons) 1 0.10 936.00

Sub - Total for B


C. Total (A + B)
D. Output per hour = 15.00 cu.m.
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost

F. Materials

a. Cement bag 3 220.00


b. Aggregate Base Course cu.m. 1.15 650.00
c. MC 70 Cut-back Asphalt m.t. 0.0075 40,300.00

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G
I. Contractor's Profit (CP) 8% of G
J. Value Added Tax (VAT) 12% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
Amount

109.19
614.40

723.59
Amount

2,173.00
1,507.00
266.25

3,946.25
4,669.84

311.32
Amount

504.00
747.50

1,251.50
1,562.82
140.65
125.03
219.42
2,047.92
Amount

109.19
614.40

723.59
Amount

2,173.00
1,507.00
266.25

3,946.25
4,669.84

311.32
Amount

660.00
747.50

1,407.50
1,718.82
154.69
137.51
241.32
2,252.35
Amount

109.19
614.40

723.59
Amount

2,173.00
1,507.00
266.25
936.00

4,882.25
5,605.84

373.72
Amount

3,080.00
747.50

3,827.50
4,201.22
378.11
336.10
589.85
5,505.28
Amount

109.19
159.40
245.76

514.35
Amount

604.02
2,028.00
1,086.50
753.50
866.50
266.25
93.60

5,698.37
6,212.72

414.18
Amount

660.00
747.50
302.25

1,709.75
2,123.93
191.15
169.91
298.20
2,783.20
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 300(1) Gravel Surface Course (Uncrushed)


Unit of Measurement : cu.m
Output per hour : 50.00

Designation No. of Person No. of Hours Hourly Rate

A. Labor

a. Construction Foreman 1 1 109.19


b. Laborer 2 1 61.44

Sub - Total for A


Name and Capacity No of Units No. of Hours Hourly Rate
B. Equipment

a. Motorized Road Grader, G710A 1 1 2,173.00


b. Vibratory Roller (10 m.t.), SP56 1 1 1,507.00
c. Water Truck (1000 gal.), All Make 1 0.25 1,065.00

Sub - Total for B


C. Total (A + B)
D. Output per hour = 50.00 cu.m.
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost

F. Materials

a. Uncrushed Aggregate Surface Course cu.m. 1.15 700.00


(w/ 15% Shrinkage Factor)

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G
I. Contractor's Profit (CP) 8% of G
J. Value Added Tax (VAT) 12% of (G + H + I)

1762
K. Total Unit Cost (G + H + I + J)

5485
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 300(2) Crushed Aggregate Surface Course


Unit of Measurement : cu.m
Output per hour : 50.00

Designation No. of Person No. of Hours Hourly Rate

A. Labor

a. Construction Foreman 1 1 109.19


b. Laborer 2 1 61.44

Sub - Total for A


Name and Capacity No of Units No. of Hours Hourly Rate
B. Equipment

a. Motorized Road Grader, G710A 1 1 2,173.00


b. Vibratory Roller (10 m.t.), SP56 1 1 1,507.00
c. Water Truck (1000 gal.), All Make 1 0.25 1,065.00

Sub - Total for B


C. Total (A + B)
D. Output per hour = 50.00 cu.m.
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost

F. Materials

a. Crushed Aggregate Surface Course cu.m. 1.15 750.00


(w/ 15% Shrinkage Factor)

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G
I. Contractor's Profit (CP) 8% of G
J. Value Added Tax (VAT) 12% of (G + H + I)

1782
K. Total Unit Cost (G + H + I + J)

5485
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 301(1) Bituminous Prime Coat (MC Cut-back Asphalt)


Unit of Measurement : m.t.
Output per hour : 0.30

Designation No. of Person No. of Hours Hourly Rate

A. Labor

a. Construction Foreman 1 1 109.19


b. Laborer 3 1 61.44

Sub - Total for A


Name and Capacity No of Units No. of Hours Hourly Rate
B. Equipment

a. Asphalt Distributor, 10 ft. wide (5 tons) 1 1 936.00


b. Power Broom (20 m. wide) 1 1 130.54

Sub - Total for B


C. Total (A + B)
D. Output per hour = 0.30 m.t.
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost

F. Materials

a. MC 70 Cut-back Asphalt m.t. 1.05 40,300.00


(w/ 5% wastage)

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G
I. Contractor's Profit (CP) 8% of G
J. Value Added Tax (VAT) 12% of (G + H + I)

1802
K. Total Unit Cost (G + H + I + J)

5485
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 301(2) Bituminous Prime Coat (RC Cut-back Asphalt)


Unit of Measurement : m.t.
Output per hour : 0.30

Designation No. of Person No. of Hours Hourly Rate

A. Labor

a. Construction Foreman 1 1 109.19


b. Laborer 3 1 61.44

Sub - Total for A


Name and Capacity No of Units No. of Hours Hourly Rate
B. Equipment

a. Asphalt Distributor, 10 ft. wide (5 tons) 1 1 936.00


b. Power Broom (20 m. wide) 1 1 130.54

Sub - Total for B


C. Total (A + B)
D. Output per hour = 0.30 m.t.
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost

F. Materials

a. RC 70 Cut-back Asphalt m.t. 1.05 41,575.00


(w/ 5% wastage)

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G
I. Contractor's Profit (CP) 8% of G
J. Value Added Tax (VAT) 12% of (G + H + I)

1822
K. Total Unit Cost (G + H + I + J)

5485
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 302(1) Bituminous Tack Coat (RC Cut-back Asphalt)


Unit of Measurement : m.t.
Output per hour : 0.30

Designation No. of Person No. of Hours Hourly Rate

A. Labor

a. Construction Foreman 1 1 109.19


b. Laborer 3 1 61.44

Sub - Total for A


Name and Capacity No of Units No. of Hours Hourly Rate
B. Equipment

a. Asphalt Distributor, 10 ft. wide (5 tons) 1 1 936.00


b. Power Broom (20 m. wide) 1 1 130.54

Sub - Total for B


C. Total (A + B)
D. Output per hour = 0.30 m.t.
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost

F. Materials

a. RC 70 Cut-back Asphalt m.t. 1.05 41,575.00


(w/ 5% wastage)

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G
I. Contractor's Profit (CP) 8% of G
J. Value Added Tax (VAT) 12% of (G + H + I)

1842
K. Total Unit Cost (G + H + I + J)

5485
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 302(2) Bituminous Tack Coat (Emulsified


Unit of Measurement : Asphalt) m.t.
Output per hour : 0.30

Designation No. of Person No. of Hours Hourly Rate

A. Labor

a. Construction Foreman 1 1 109.19


b. Laborer 3 1 61.44

Sub - Total for A


Name and Capacity No of Units No. of Hours Hourly Rate
B. Equipment

a. Asphalt Distributor, 10 ft. wide (5 tons) 1 1 936.00


b. Power Broom (20 m. wide) 1 1 130.54

Sub - Total for B


C. Total (A + B)
D. Output per hour = 0.30 m.t.
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost

F. Materials

a. Emulsified Asphalt SS-1 m.t. 1.05 44,000.00


(w/ 5% wastage)

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G
I. Contractor's Profit (CP) 8% of G
J. Value Added Tax (VAT) 12% of (G + H + I)
K. Total Unit Cost (G + H + I + J)

1862
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 303(1) Bituminous Seal Coat (Cover


Unit of Measurement : Aggregate) m.t.
Output per hour : 16.00

Designation No. of Person No. of Hours Hourly Rate

A. Labor

a. Construction Foreman 1 1 109.19


b. Laborer 20 1 61.44

Sub - Total for A


Name and Capacity No of Units No. of Hours Hourly Rate
B. Equipment

a. Tandem Steel Roller (10.1 m.t.), CC421 1 1 1,652.00


b. Water Truck (1000 gal.) 1 0.25 1,065.00

Sub - Total for B


C. Total (A + B)
D. Output per hour = 16.00 m.t.
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost

F. Materials

a. Cover Aggregate m.t. 1.15 406.25


(w/ 15% Shrinkage Factor)

Note: 1.60 m.t./cu.m.


using unit wt. of 1,600 kg./m³

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G
I. Contractor's Profit (CP) 8% of G
J. Value Added Tax (VAT) 12% of (G + H + I)
K. Total Unit Cost (G + H + I + J)

5485
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 303(2) Bituminous Seal Coat (MC Cut-back


Unit of Measurement : Asphalt) m.t.
Output per hour : 0.30

Designation No. of Person No. of Hours Hourly Rate

A. Labor

a. Construction Foreman 1 1 109.19


b. Laborer 3 1 61.44

Sub - Total for A


Name and Capacity No of Units No. of Hours Hourly Rate
B. Equipment

a. Asphalt Distributor, 10 ft. wide (5 tons) 1 1 936.00


b. Power Broom (20 m. wide) 1 1 130.54

Sub - Total for B


C. Total (A + B)
D. Output per hour = 0.30 m.t.
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost
F. Materials

a. MC Cut-back Asphalt m.t. 1.05 40,300.00


(w/ 5% Wastage)

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G
I. Contractor's Profit (CP) 8% of G
J. Value Added Tax (VAT) 12% of (G + H + I)
K. Total Unit Cost (G + H + I + J)

1882
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 303(3) Bituminous Seal Coat (RC Cut-back


Unit of Measurement : Asphalt) m.t.
Output per hour : 0.30

Designation No. of Person No. of Hours Hourly Rate

A. Labor

a. Construction Foreman 1 1 109.19


b. Laborer 3 1 61.44

Sub - Total for A


Name and Capacity No of Units No. of Hours Hourly Rate
B. Equipment

a. Asphalt Distributor, 10 ft. wide (5 tons) 1 1 936.00


b. Power Broom (20 m. wide) 1 1 130.54

Sub - Total for B


C. Total (A + B)
D. Output per hour = 0.30 m.t.
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost
F. Materials

a. RC 70 Cut-back Asphalt m.t. 1.05 41,575.00


(w/ 5% Wastage)

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G
I. Contractor's Profit (CP) 8% of G
J. Value Added Tax (VAT) 12% of (G + H + I)
K. Total Unit Cost (G + H + I + J)

5485
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 303(4) Bituminous Seal Coat (Asphalt Cement Penetration Grade 120-
Unit of Measurement : 150) m.t.
Output per hour : 0.30

Designation No. of Person No. of Hours Hourly Rate

A. Labor

a. Construction Foreman 1 1 109.19


b. Laborer 3 1 61.44

Sub - Total for A


Name and Capacity No of Units No. of Hours Hourly Rate
B. Equipment

a. Asphalt Distributor, 10 ft. wide (5 tons) 1 1 936.00


b. Power Broom (20 m. wide) 1 1 130.54

Sub - Total for B


C. Total (A + B)
D. Output per hour = 0.30 m.t.
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost
F. Materials

a. Asphalt Cement Penetration Grade 120-150 m.t. 1.05 50,775.00


(w/ 5% Wastage)

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G
I. Contractor's Profit (CP) 8% of G
J. Value Added Tax (VAT) 12% of (G + H + I)
K. Total Unit Cost (G + H + I + J)

1902
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 304(1) Bituminous Surface Treatment (Aggregate


Unit of Measurement : Grading) m.t.
Output per hour : 16.00

Designation No. of Person No. of Hours Hourly Rate

A. Labor

a. Construction Foreman 1 1 109.19


b. Laborer 20 1 61.44

Sub - Total for A


Name and Capacity No of Units No. of Hours Hourly Rate
B. Equipment

a. Vibratory Roller (10 m.t.), SP56 1 1 1,507.00


b. Water Truck (1000 gal.) 1 0.25 1,065.00

Sub - Total for B


C. Total (A + B)
D. Output per hour = 16.00 m.t.
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost
F. Materials

a. Aggregates m.t. 1.15 406.25


(w/ 15% Shrinkage Factor)

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G
I. Contractor's Profit (CP) 8% of G
J. Value Added Tax (VAT) 12% of (G + H + I)
K. Total Unit Cost (G + H + I + J)

5485
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 304(2) Bituminous Surface Treatment (Asphalt Cement Penetration Grade 120-
Unit of Measurement : 15 m.t.
Output per hour : 0.30

Designation No. of Person No. of Hours Hourly Rate

A. Labor

a. Construction Foreman 1 1 109.19


b. Laborer 3 1 61.44

Sub - Total for A


Name and Capacity No of Units No. of Hours Hourly Rate
B. Equipment

a. Asphalt Distributor, 10 ft. wide (5 tons) 1 1 936.00


b. Power Broom (20 m. wide) 1 1 130.54

Sub - Total for B


C. Total (A + B)
D. Output per hour = 0.30 m.t.
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost
F. Materials

a. Asphalt Cement Penetration Grade 120-150 m.t. 1.05 50,775.00


(w/ 5% Wastage)

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G
I. Contractor's Profit (CP) 8% of G
J. Value Added Tax (VAT) 12% of (G + H + I)
K. Total Unit Cost (G + H + I + J)

1922
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 304(3) Bituminous Surface Treatment (MC Cut-back


Unit of Measurement : Asphalt) m.t.
Output per hour : 0.30

Designation No. of Person No. of Hours Hourly Rate

A. Labor

a. Construction Foreman 1 1 109.19


b. Laborer 3 1 61.44

Sub - Total for A


Name and Capacity No of Units No. of Hours Hourly Rate
B. Equipment

a. Asphalt Distributor, 10 ft. wide (5 tons) 1 1 936.00


b. Power Broom (20 m. wide) 1 1 130.54

Sub - Total for B


C. Total (A + B)
D. Output per hour = 0.30 m.t.
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost
F. Materials

a. MC Cut-back Asphalt m.t. 1.05 40,300.00


(w/ 5% Wastage)

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G
I. Contractor's Profit (CP) 8% of G
J. Value Added Tax (VAT) 12% of (G + H + I)
K. Total Unit Cost (G + H + I + J)

5485
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 304(4) Bituminous Surface Treatment (RC Cut-back


Unit of Measurement : Asphalt) m.t.
Output per hour : 0.30

Designation No. of Person No. of Hours Hourly Rate

A. Labor

a. Construction Foreman 1 1 109.19


b. Laborer 3 1 61.44

Sub - Total for A


Name and Capacity No of Units No. of Hours Hourly Rate
B. Equipment

a. Asphalt Distributor, 10 ft. wide (5 tons) 1 1 936.00


b. Power Broom (20 m. wide) 1 1 130.54

Sub - Total for B


C. Total (A + B)
D. Output per hour = 0.30 m.t.
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost
F. Materials

a. RC 70 Cut-back Asphalt m.t. 1.05 41,575.00


(w/ 5% Wastage)

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G
I. Contractor's Profit (CP) 8% of G
J. Value Added Tax (VAT) 12% of (G + H + I)
K. Total Unit Cost (G + H + I + J)

1942
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 304(5) Bituminous Surface Treatment (Emulsified


Unit of Measurement : Asphalt) m.t.
Output per hour : 0.30

Designation No. of Person No. of Hours Hourly Rate

A. Labor

a. Construction Foreman 1 1 109.19


b. Laborer 3 1 61.44

Sub - Total for A


Name and Capacity No of Units No. of Hours Hourly Rate
B. Equipment

a. Asphalt Distributor, 10 ft. wide (5 tons) 1 1 936.00


b. Power Broom (20 m. wide) 1 1 130.54

Sub - Total for B


C. Total (A + B)
D. Output per hour = 0.30 m.t.
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost
F. Materials

a. Emulsified Asphalt SS-1 m.t. 1.05 44,000.00


(w/ 5% wastage)

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G
I. Contractor's Profit (CP) 8% of G
J. Value Added Tax (VAT) 12% of (G + H + I)
K. Total Unit Cost (G + H + I + J)

5485
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 305(1) Bituminous Penetration Macadam Pavement


Unit of Measurement : (Aggregates) m.t.
Output per hour : 16.00

Designation No. of Person No. of Hours Hourly Rate

A. Labor

a. Construction Foreman 1 1 109.19


b. Laborer 20 1 61.44

Sub - Total for A


Name and Capacity No of Units No. of Hours Hourly Rate
B. Equipment

a. Vibratory Roller (10 m.t.), SP56 1 1 1,507.00


b. Water Truck (1000 gal.) 1 0.25 1,065.00

Sub - Total for B


C. Total (A + B)
D. Output per hour = 16.00 m.t.
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost
F. Materials

a. Aggregates m.t. 1.15 406.25


(w/ 15% Shrinkage Factor)

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G
I. Contractor's Profit (CP) 8% of G
J. Value Added Tax (VAT) 12% of (G + H + I)
K. Total Unit Cost (G + H + I + J)

1962
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 305(2) Bituminous Penetration Macadam Pavement (Asphalt


Unit of Measurement : Cement) m.t.
Output per hour : 0.30

Designation No. of Person No. of Hours Hourly Rate

A. Labor

a. Construction Foreman 1 1 109.19


b. Laborer 3 1 61.44

Sub - Total for A


Name and Capacity No of Units No. of Hours Hourly Rate
B. Equipment

a. Asphalt Distributor, 10 ft. wide (5 tons) 1 1 936.00


b. Power Broom (20 m. wide) 1 1 130.54

Sub - Total for B


C. Total (A + B)
D. Output per hour = 0.30 m.t.
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost
F. Materials

a. Asphalt Cement (w/ 5% Wastage) m.t. 1.05 50,775.00

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G
I. Contractor's Profit (CP) 8% of G
J. Value Added Tax (VAT) 12% of (G + H + I)
K. Total Unit Cost (G + H + I + J)

5485
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 305(3) Bituminous Penetration Macadam Pavement (RC Cut-back


Unit of Measurement : Asphalt) m.t.
Output per hour : 0.30

Designation No. of Person No. of Hours Hourly Rate

A. Labor

a. Construction Foreman 1 1 109.19


b. Laborer 3 1 61.44

Sub - Total for A


Name and Capacity No of Units No. of Hours Hourly Rate
B. Equipment

a. Asphalt Distributor, 10 ft. wide (5 tons) 1 1 936.00


b. Power Broom (20 m. wide) 1 1 130.54

Sub - Total for B


C. Total (A + B)
D. Output per hour = 0.30 m.t.
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost
F. Materials

a. RC 70 Cut-back Asphalt m.t. 1.05 41,575.00


(w/ 5% Wastage)

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G
I. Contractor's Profit (CP) 8% of G
J. Value Added Tax (VAT) 12% of (G + H + I)
K. Total Unit Cost (G + H + I + J)

1982
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 305(4) Bituminous Penetration Macadam Pavement (Emulsified Asphalt)


Unit of Measurement : m.t.
Output per hour : 0.30

Designation No. of Person No. of Hours Hourly Rate

A. Labor

a. Construction Foreman 1 1 109.19


b. Laborer 3 1 61.44

Sub - Total for A


Name and Capacity No of Units No. of Hours Hourly Rate

B. Equipment

a. Asphalt Distributor, 10 ft. wide (5 tons) 1 1 936.00


b. Power Broom (20 m. wide) 1 1 130.54

Sub - Total for B


C. Total (A + B)
D. Output per hour = 0.30 m.t.
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost

F. Materials

a. Emulsified Asphalt SS-1 m.t. 1.05 44,000.00


(w/ 5% wastage)

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G
I. Contractor's Profit (CP) 8% of G
J. Value Added Tax (VAT) 12% of (G + H + I)
K. Total Unit Cost (G + H + I + J)

5485
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 306(a) Bituminous Road Mix Surface Course


Unit of Measurement : m.t.
Output per hour : 12.00

Designation No. of Person No. of Hours Hourly Rate

A. Labor

a. Construction Foreman 1 1 109.19


b. Skilled Laborer 1 1 79.70
c. Laborer 3 1 61.44

Sub - Total for A


Name and Capacity No of Units No. of Hours Hourly Rate

B. Equipment

a. Road Grader w/ Scarifier, G710A 1 1 2,933.55


b. Tandem Steel Roller (10.1 m.t.), CC421 1 1 1,652.00
c. Pneumatic Tire Roller (10 m.t.) 1 1 553.00
d. Asphalt Distributor, 10 ft. wide (5 tons) 1 1 936.00
e. Water Truck (1000 gal.) 1 0.25 1,065.00
Minor Tools (10% of Labor)

Sub - Total for B


C. Total (A + B)
D. Output per hour = 12.00 m.t.
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost

F. Materials

a. Crushed Gravel m.t. 1.15 406.25


b. MC Cut-back Asphalt (7%) m.t. 0.07 40,300.00
c. Hydrated Lime (0.75%) bag 0.30 180.00

0.0575(2.335)(1.05) = 0.141
0.0075(35.29) = 0.26, say 0.30

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G
I. Contractor's Profit (CP) 8% of G
J. Value Added Tax (VAT) 12% of (G + H + I)
K. Total Unit Cost (G + H + I + J)

2002
Item No./Description : 306(b) Bituminous Road Mix Surface Course
Unit of Measurement : m.t.
Output per hour : 12.00

Designation No. of Person No. of Hours Hourly Rate

A. Labor

a. Construction Foreman 1 1 109.19


b. Skilled Laborer 1 1 79.70
c. Laborer 3 1 61.44

Sub - Total for A


Name and Capacity No of Units No. of Hours Hourly Rate

B. Equipment

a. Road Grader w/ Scarifier, G710A 1 1 2,933.55


b. Tandem Steel Roller (10.1 m.t.), CC421 1 1 1,652.00
c. Pneumatic Tire Roller (10 m.t.) 1 1 553.00
d. Asphalt Distributor, 10 ft. wide (5 tons) 1 1 936.00
e. Water Truck (1000 gal.) 1 0.25 1,065.00
Minor Tools (10% of Labor)

Sub - Total for B


C. Total (A + B)
D. Output per hour = 12.00 m.t.
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost

F. Materials

a. Crushed Gravel m.t. 1.15 406.25


b. Emulsified Asphalt (10%) m.t. 0.10 44,000.00
c. Hydrated Lime (0.75%) bag 0.30 180.00

0.08(2.335)(1.05) = 0.196
0.0075(35.29) = 0.26, say 0.30

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G
I. Contractor's Profit (CP) 8% of G
J. Value Added Tax (VAT) 12% of (G + H + I)
K. Total Unit Cost (G + H + I + J)

5485
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 306(1) Aggregates for Bituminous Road Mix Surface


Unit of Measurement : Course m.t.
Output per hour : 12.00

Designation No. of Person No. of Hours Hourly Rate

A. Labor

a. Construction Foreman 1 1 109.19


b. Skilled Laborer 1 1 79.70
c. Laborer 3 1 61.44

Sub - Total for A


Name and Capacity No of Units No. of Hours Hourly Rate
B. Equipment

a. Road Grader w/ Scarifier, G710A 1 1 2,933.55


b. Tandem Steel Roller (10.1 m.t.), CC421 1 1 1,652.00
c. Pneumatic Tire Roller (10 m.t.) 1 1 553.00
d. Water Truck (1000 gal.) 1 0.25 1,065.00
Minor Tools (10% of Labor)

Sub - Total for B


C. Total (A + B)
D. Output per hour = 12.00 m.t.
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost
F. Materials

a. Crushed Gravel m.t. 1.15 406.25

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G
I. Contractor's Profit (CP) 8% of G
J. Value Added Tax (VAT) 12% of (G + H + I)
K. Total Unit Cost (G + H + I + J)

2022
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 306(2) Bituminous Material for Bituminous Road Mix Surface
Unit of Measurement : m.t.
Output per hour : 1.00

Amount Designation No. of Person No. of Hours

A. Labor

109.19 a. Construction Foreman 1 1


122.88 b. Skilled Laborer 1 1
c. Laborer 3 1

232.07 Sub - Total for A


Amount Name and Capacity No of Units No. of Hours
B. Equipment

2,173.00 a. Asphalt Distributor, 10 ft. wide (5 tons) 1 1.00


1,507.00
266.25

3,946.25 Sub - Total for B


4,178.32 C. Total (A + B)
D. Output per hour = 1.00 m.t.
83.57 E. Direct Unit Cost (C ÷ D)
Amount Name and Specification Unit Quantity

F. Materials

805.00 a. MC Cut-back Asphalt m.t. 1.05

805.00 Sub - Total for F


888.57 G. Direct Unit Cost (E + F)
79.97 H. Overhead, Contingencies & Miscellaneous (OCM) 9%
71.09 I. Contractor's Profit (CP) 8%
124.75 J. Value Added Tax (VAT) 12%

5485
1,164.38 K. Total Unit Cost

2042
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 307 Bituminous Plant Mix Surface Course-General (50mm t


Unit of Measurement : sq.m.
Output per hour : 171.30

Amount Designation No. of Person No. of Hours

A. Labor

109.19 a. Construction Foreman 1 1


122.88 b. Skilled Laborer 6 1
c. Laborer 12 1

232.07 Sub - Total for A


Amount Name and Capacity No of Units No. of Hours
B. Equipment

2,173.00 a. Asphalt Paver (80 Hp), NF220BIIVDM 1 1


1,507.00 b. Pneumatic Tire Roller (10 m.t.) 1 1
266.25 c. Tandem Steel Roller (10.1 m.t.), CC421 1 1
d. Dump Truck (10 cu.m.) 2 1
e. Asphalt Batch Plant ( 60-80 TPH) 1 1
f. Water Truck (1000 gal.) 1 1
g. Payloader (1.50 cu.m.), LX80-2C 1 1
Minor Tools (10% of Labor)

3,946.25 Sub - Total for B


4,178.32 C. Total (A + B)
D. Output per hour = 171.30 sq.m.
83.57 E. Direct Unit Cost (C ÷ D)
Amount Name and Specification Unit Quantity

F. Materials

862.50 a. Bituminous Material (8%) m.t 0.00981


b. Aggregates (93%) cu.m. 0.0488
c. Mineral Filler (7%) bag 0.13
(w/ 5% wastage)

862.50 Sub - Total for F


946.07 G. Direct Unit Cost (E + F)
85.15 H. Overhead, Contingencies & Miscellaneous (OCM) 9%
75.69 I. Contractor's Profit (CP) 8%
132.83 J. Value Added Tax (VAT) 12%

5485
1,239.73 K. Total Unit Cost

2062
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 308(a) Cold Asphalt Plant Mix (50mm thk.)


Unit of Measurement : sq.m.
Output per hour : 171.30

Amount Designation No. of Person No. of Hours

A. Labor

109.19 a. Construction Foreman 1 1


184.32 b. Skilled Laborer 6 1
c. Laborer 12 1

293.51 Sub - Total for A


Amount Name and Capacity No of Units No. of Hours
B. Equipment

936.00 a. Asphalt Paver (80 Hp), NF220BIIVDM 1 1


130.54 b. Pneumatic Tire Roller (10 m.t.) 1 1
c. Tandem Steel Roller (10.1 m.t.), CC421 1 1
d. Dump Truck (10 cu.m.) 2 1
e. Asphalt Batch Plant ( 60-80 TPH) 1 1
f. Water Truck (1000 gal.) 1 1
g. Payloader (1.50 cu.m.), LX80-2C 1 1
Minor Tools (10% of Labor)

1,066.54 Sub - Total for B


1,360.05 C. Total (A + B)
D. Output per hour = 171.30 sq.m.
4,533.50 E. Direct Unit Cost (C ÷ D)
Amount Name and Specification Unit Quantity

F. Materials

42,315.00 a. Emulsified Asphalt (10%) m.t 0.01226


b. Aggregates (93%) cu.m. 0.0488
c. Mineral Filler (7%) bag 0.13
(w/ 5% wastage)

42,315.00 Sub - Total for F


46,848.50 G. Direct Unit Cost (E + F)
4,216.37 H. Overhead, Contingencies & Miscellaneous (OCM) 9%
3,747.88 I. Contractor's Profit (CP) 8%
6,577.53 J. Value Added Tax (VAT) 12%

5485
61,390.27 K. Total Unit Cost

2082
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 308(b) Cold Asphalt Plant Mix (50mm thk.)


Unit of Measurement : sq.m.
Output per hour : 171.30

Amount Designation No. of Person No. of Hours

A. Labor

109.19 a. Construction Foreman 1 1


184.32 b. Skilled Laborer 6 1
c. Laborer 12 1

293.51 Sub - Total for A


Amount Name and Capacity No of Units No. of Hours
B. Equipment

936.00 a. Asphalt Paver (80 Hp), NF220BIIVDM 1 1


130.54 b. Pneumatic Tire Roller (10 m.t.) 1 1
c. Tandem Steel Roller (10.1 m.t.), CC421 1 1
d. Dump Truck (10 cu.m.) 2 1
e. Asphalt Batch Plant ( 60-80 TPH) 1 1
f. Water Truck (1000 gal.) 1 1
g. Payloader (1.50 cu.m.), LX80-2C 1 1
Minor Tools (10% of Labor)

1,066.54 Sub - Total for B


1,360.05 C. Total (A + B)
D. Output per hour = 171.30 sq.m.
4,533.50 E. Direct Unit Cost (C ÷ D)
Amount Name and Specification Unit Quantity

F. Materials

43,653.75 a. MC - 70 Cut-back Asphalt (7%) m.t 0.00858


b. Aggregates (93%) cu.m. 0.0488
c. Mineral Filler (7%) bag 0.13
(w/ 5% wastage)

43,653.75 Sub - Total for F


48,187.25 G. Direct Unit Cost (E + F)
4,336.85 H. Overhead, Contingencies & Miscellaneous (OCM) 9%
3,854.98 I. Contractor's Profit (CP) 8%
6,765.49 J. Value Added Tax (VAT) 12%

5485
63,144.57 K. Total Unit Cost

2102
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 309 Bituminous Plant Mix (Stockpile Maintenance Mixture)


Unit of Measurement : sq.m.
Output per hour : 171.30

Amount Designation No. of Person No. of Hours

A. Labor

109.19 a. Construction Foreman 1 1


184.32 b. Skilled Laborer 6 1
c. Laborer 12 1

293.51 Sub - Total for A


Amount Name and Capacity No of Units No. of Hours
B. Equipment

936.00 a. Dump Truck (10 cu.m.) 2 1


130.54 b. Asphalt Batch Plant ( 60-80 TPH) 1 1
c. Water Truck (1000 gal.) 1 1
d. Payloader (1.50 cu.m.), LX80-2C 1 1
Minor Tools (10% of Labor)

1,066.54 Sub - Total for B


1,360.05 C. Total (A + B)
D. Output per hour = 171.30 sq.m.
4,533.50 E. Direct Unit Cost (C ÷ D)
Amount Name and Specification Unit Quantity

F. Materials

43,653.75 a. MC - 70 Cut-back Asphalt (10%) m.t 0.00981


b. Aggregates (93%) cu.m. 0.0488
c. Mineral Filler (7%) bag 0.13
(w/ 5% wastage)

43,653.75 Sub - Total for F


48,187.25 G. Direct Unit Cost (E + F)
4,336.85 H. Overhead, Contingencies & Miscellaneous (OCM) 9%
3,854.98 I. Contractor's Profit (CP) 8%
6,765.49 J. Value Added Tax (VAT) 12%

5485
63,144.57 K. Total Unit Cost

2122
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 310(a.1) Bituminous Concrete Surface Course (30mm


Unit of Measurement : thk.) sq.m.
Output per hour : 285.51

Amount Designation No. of Person No. of Hours

A. Labor

109.19 a. Construction Foreman 1 1


184.32 b. Skilled Laborer 4 1
c. Laborer 8 1

293.51 Sub - Total for A


Amount Name and Capacity No of Units No. of Hours
B. Equipment

936.00 a. Asphalt Paver (80 Hp) 1 1


130.54 b. Pneumatic Tire Roller (10 m.t.) 1 1
c. Tandem Steel Roller (10.1 m.t.), CC421 1 1
d. Water Truck (1000 gal.) 1 1
Minor Tools (10% of Labor)

1,066.54 Sub - Total for B


1,360.05 C. Total (A + B)
D. Output per hour = 285.51 sq.m.
4,533.50 E. Direct Unit Cost (C ÷ D)
Amount Name and Specification Unit Quantity

F. Materials

46,200.00 a. Bituminous Concrete Surface Course m.t. 0.074


thickness = 30mm (w/ 5% wastage)

46,200.00 Sub - Total for F


50,733.50 G. Direct Unit Cost (E + F)
4,566.02 H. Overhead, Contingencies & Miscellaneous (OCM) 9%
4,058.68 I. Contractor's Profit (CP) 8%
7,122.98 J. Value Added Tax (VAT) 12%
66,481.18 K. Total Unit Cost

5485
Amount Designation No. of Person No. of Hours

A. Labor

109.19 a. Construction Foreman 1 1


1,228.80 b. Skilled Laborer 4 1
c. Laborer 8 1

1,337.99 Sub - Total for A


Amount Name and Capacity No of Units No. of Hours
B. Equipment

1,652.00 a. Asphalt Paver (80 Hp) 1 1


266.25 b. Pneumatic Tire Roller (10 m.t.) 1 1
c. Tandem Steel Roller (10.1 m.t.), CC421 1 1
d. Water Truck (1000 gal.) 1 1
Minor Tools (10% of Labor)

1,918.25 Sub - Total for B


3,256.24 C. Total (A + B)
D. Output per hour = 214.13 sq.m.
203.52 E. Direct Unit Cost (C ÷ D)
Amount Name and Specification Unit Quantity

F. Materials

467.19 a. Bituminous Concrete Surface Course m.t. 0.098


thickness = 40mm (w/ 5% wastage)

467.19 Sub - Total for F


670.70 G. Direct Unit Cost (E + F)
60.36 H. Overhead, Contingencies & Miscellaneous (OCM) 9%
53.66 I. Contractor's Profit (CP) 8%
94.17 J. Value Added Tax (VAT) 12%
878.89 K. Total Unit Cost

2142
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 310(a.3) Bituminous Concrete Surface Course (50mm thk.)


Unit of Measurement : sq.m.
Output per hour : 171.30

Amount Designation No. of Person No. of Hours

A. Labor

109.19 a. Construction Foreman 1 1


184.32 b. Skilled Laborer 4 1
c. Laborer 8 1

293.51 Sub - Total for A


Amount Name and Capacity No of Units No. of Hours

B. Equipment

936.00 a. Asphalt Paver (80 Hp) 1 1


130.54 b. Pneumatic Tire Roller (10 m.t.) 1 1
c. Tandem Steel Roller (10.1 m.t.), CC421 1 1
d. Water Truck (1000 gal.) 1 1
Minor Tools (10% of Labor)

1,066.54 Sub - Total for B


1,360.05 C. Total (A + B)
D. Output per hour = 171.30 sq.m.
4,533.50 E. Direct Unit Cost (C ÷ D)
Amount Name and Specification Unit Quantity

F. Materials

42,315.00 a. Bituminous Concrete Surface Course m.t. 0.123


thickness = 50mm (w/ 5% wastage)

42,315.00 Sub - Total for F


46,848.50 G. Direct Unit Cost (E + F)
4,216.37 H. Overhead, Contingencies & Miscellaneous (OCM) 9%
3,747.88 I. Contractor's Profit (CP) 8%
6,577.53 J. Value Added Tax (VAT) 12%
61,390.27 K. Total Unit Cost

5485
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 310(b.1) Bituminous Concrete Surface Course (30mm


Unit of Measurement : thk.) sq.m.
Output per hour : 285.51

Amount Designation No. of Person No. of Hours

A. Labor

109.19 a. Construction Foreman 1 1


184.32 b. Skilled Laborer 6 1
c. Laborer 12 1

293.51 Sub - Total for A


Amount Name and Capacity No of Units No. of Hours
B. Equipment

936.00 a. Asphalt Paver (80 Hp), NF220BIIVDM 1 1


130.54 b. Pneumatic Tire Roller (10 m.t.) 1 1
c. Tandem Steel Roller (10.1 m.t.), CC421 1 1
d. Dump Truck (10 cu.m.) 2 1
e. Asphalt Batch Plant ( 60-80 TPH) 1 1
f. Water Truck (1000 gal.) 1 1
g. Payloader (1.50 cu.m.), LX80-2C 1 1
Minor Tools (10% of Labor)

1,066.54 Sub - Total for B


1,360.05 C. Total (A + B)
D. Output per hour = 285.51 sq.m.
4,533.50 E. Direct Unit Cost (C ÷ D)
Amount Name and Specification Unit Quantity
F. Materials

43,653.75 a. Asphalt Cement (8%) m.t 0.00588


b. Aggregates (93%) cu.m. 0.0293
c. Mineral Filler (7%) bag 0.078
(w/ 5% wastage)

43,653.75 Sub - Total for F


48,187.25 G. Direct Unit Cost (E + F)
4,336.85 H. Overhead, Contingencies & Miscellaneous (OCM) 9%
3,854.98 I. Contractor's Profit (CP) 8%
6,765.49 J. Value Added Tax (VAT) 12%
63,144.57 K. Total Unit Cost

2162
Amount Designation No. of Person No. of Hours

A. Labor

109.19 a. Construction Foreman 1 1


184.32 b. Skilled Laborer 6 1
c. Laborer 12 1

293.51 Sub - Total for A


Amount Name and Capacity No of Units No. of Hours
B. Equipment

936.00 a. Asphalt Paver (80 Hp), NF220BIIVDM 1 1


130.54 b. Pneumatic Tire Roller (10 m.t.) 1 1
c. Tandem Steel Roller (10.1 m.t.), CC421 1 1
d. Dump Truck (10 cu.m.) 2 1
e. Asphalt Batch Plant ( 60-80 TPH) 1 1
f. Water Truck (1000 gal.) 1 1
g. Payloader (1.50 cu.m.), LX80-2C 1 1
Minor Tools (10% of Labor)

1,066.54 Sub - Total for B


1,360.05 C. Total (A + B)
D. Output per hour = 214.13 sq.m.
4,533.50 E. Direct Unit Cost (C ÷ D)
Amount Name and Specification Unit Quantity
F. Materials

53,313.75 a. Asphalt Cement (8%) m.t 0.00785


b. Aggregates (93%) cu.m. 0.0391
c. Mineral Filler (7%) bag 0.104
(w/ 5% wastage)

53,313.75 Sub - Total for F


57,847.25 G. Direct Unit Cost (E + F)
5,206.25 H. Overhead, Contingencies & Miscellaneous (OCM) 9%
4,627.78 I. Contractor's Profit (CP) 8%
8,121.75 J. Value Added Tax (VAT) 12%
75,803.04 K. Total Unit Cost

5485
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 310(b.3) Bituminous Concrete Surface Course (50mm thk.)


Unit of Measurement : sq.m.
Output per hour : 171.30

Amount Designation No. of Person No. of Hours

A. Labor

109.19 a. Construction Foreman 1 1


1,228.80 b. Skilled Laborer 6 1
c. Laborer 12 1

1,337.99 Sub - Total for A


Amount Name and Capacity No of Units No. of Hours

B. Equipment

1,507.00 a. Asphalt Paver (80 Hp), NF220BIIVDM 1 1


266.25 b. Pneumatic Tire Roller (10 m.t.) 1 1
c. Tandem Steel Roller (10.1 m.t.), CC421 1 1
d. Dump Truck (10 cu.m.) 2 1
e. Asphalt Batch Plant ( 60-80 TPH) 1 1
f. Water Truck (1000 gal.) 1 1
g. Payloader (1.50 cu.m.), LX80-2C 1 1
Minor Tools (10% of Labor)

1,773.25 Sub - Total for B


3,111.24 C. Total (A + B)
D. Output per hour = 171.30 sq.m.
194.45 E. Direct Unit Cost (C ÷ D)
Amount Name and Specification Unit Quantity

F. Materials

467.19 a. Asphalt Cement (8%) m.t 0.00981


b. Aggregates (93%) cu.m. 0.0488
c. Mineral Filler (7%) bag 0.13
(w/ 5% wastage)

467.19 Sub - Total for F


661.64 G. Direct Unit Cost (E + F)
59.55 H. Overhead, Contingencies & Miscellaneous (OCM) 9%
52.93 I. Contractor's Profit (CP) 8%
92.89 J. Value Added Tax (VAT) 12%
867.01 K. Total Unit Cost

2182
0) Item No./Description : 311(1)a.1 PCC Pavement (Plain) - Conventional Method, 150mm
Unit of Measurement : sq.m.
Output per hour : 107.33

Amount Designation No. of Person No. of Hours

A. Labor

109.19 a. Construction Foreman 1 1


184.32 b. Skilled Laborer 4 1
c. Laborer 12 1

293.51 Sub - Total for A


Amount Name and Capacity No of Units No. of Hours

B. Equipment

936.00 a. Transit Mixer (5 cu.m.) 4 1


130.54 b. Concrete Vibrator 2 1
c. Batching Plant (30 cu.m.) 1 1
d. Payloader (1.50 cu.m.), LX80-2C 1 1
e. Concrete Screeder (5.5 Hp) 1 1
f. Water Truck (1000 gal.) 1 1
g. Concrete Saw, Blade Ø 14" (7.5 Hp) 1 1
h. Bar Cutter, Single Phase 1 0.10
Minor Tools (5% of Labor)

1,066.54 Sub - Total for B


1,360.05 C. Total (A + B)
D. Output per hour = 107.33 sq.m.
4,533.50 E. Direct Unit Cost (C ÷ D)
Amount Name and Specification Unit Quantity

F. Materials

53,313.75 a. Reinforcing Steel Bar kg. 0.33


b. Curing Compound lit. 0.29
c. Asphalt Sealant lit. 0.12
d. Steel Forms (Rental) l.m. 0.46
e. Sand cu.m. 0.0825
f. Gravel cu.m. 0.15
g. Cement bag 1.43
h. Concrete Saw (diamond blade 14") pc. 0.00015
i. Pipe Sleeve, 1" dia. l.m. 0.0078
j. Grease/Tar lit. 0.0015

53,313.75 Sub - Total for F


57,847.25 G. Direct Unit Cost (E + F)
5,206.25 H. Overhead, Contingencies & Miscellaneous (OCM) 9%
4,627.78 I. Contractor's Profit (CP) 8%
8,121.75 J. Value Added Tax (VAT) 12%
75,803.04 K. Total Unit Cost

5485
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 311(1)a.2 PCC Pavement (Plain) - Conventional Method,


Unit of Measurement : 200mm sq.m.
Output per hour : 80.50

Amount Designation No. of Person No. of Hours

A. Labor

109.19 a. Construction Foreman 1 1


184.32 b. Skilled Laborer 4 1
c. Laborer 12 1

293.51 Sub - Total for A


Amount Name and Capacity No of Units No. of Hours
B. Equipment

936.00 a. Transit Mixer (5 cu.m.) 4 1


130.54 b. Concrete Vibrator 2 1
c. Batching Plant (30 cu.m.) 1 1
d. Payloader (1.50 cu.m.), LX80-2C 1 1
e. Concrete Screeder (5.5 Hp) 1 1
f. Water Truck (1000 gal.) 1 1
g. Concrete Saw, Blade Ø 14" (7.5 Hp) 1 1
h. Bar Cutter, Single Phase 1 0.10
Minor Tools (5% of Labor)

1,066.54 Sub - Total for B


1,360.05 C. Total (A + B)
D. Output per hour = 80.50 sq.m.
4,533.50 E. Direct Unit Cost (C ÷ D)
Amount Name and Specification Unit Quantity
F. Materials

42,315.00 a. Reinforcing Steel Bar kg. 0.39


b. Curing Compound lit. 0.29
c. Asphalt Sealant lit. 0.12
d. Steel Forms (Rental) l.m. 0.46
e. Sand cu.m. 0.11
f. Gravel cu.m. 0.20
g. Cement bag 1.90
h. Concrete Saw (diamond blade 14") pc. 0.00015
i. Pipe Sleeve, 1 1/2" dia. l.m. 0.0086
j. Grease/Tar lit. 0.0056

42,315.00 Sub - Total for F


46,848.50 G. Direct Unit Cost (E + F)
4,216.37 H. Overhead, Contingencies & Miscellaneous (OCM) 9%
3,747.88 I. Contractor's Profit (CP) 8%
6,577.53 J. Value Added Tax (VAT) 12%
61,390.27 K. Total Unit Cost

2202
Amount Designation No. of Person No. of Hours

A. Labor

109.19 a. Construction Foreman 1 1


184.32 b. Skilled Laborer 4 1
c. Laborer 12 1

293.51 Sub - Total for A


Amount Name and Capacity No of Units No. of Hours
B. Equipment

936.00 a. Transit Mixer (5 cu.m.) 4 1


130.54 b. Concrete Vibrator 2 1
c. Batching Plant (30 cu.m.) 1 1
d. Payloader (1.50 cu.m.), LX80-2C 1 1
e. Concrete Screeder (5.5 Hp) 1 1
f. Water Truck (1000 gal.) 1 1
g. Concrete Saw, Blade Ø 14" (7.5 Hp) 1 1
h. Bar Cutter, Single Phase 1 0.10
Minor Tools (5% of Labor)

1,066.54 Sub - Total for B


1,360.05 C. Total (A + B)
D. Output per hour = 70.00 sq.m.
4,533.50 E. Direct Unit Cost (C ÷ D)
Amount Name and Specification Unit Quantity
F. Materials

43,653.75 a. Reinforcing Steel Bar kg. 0.43


b. Curing Compound lit. 0.29
c. Asphalt Sealant lit. 0.12
d. Steel Forms (Rental) l.m. 0.46
e. Sand cu.m. 0.1265
f. Gravel cu.m. 0.23
g. Cement bag 2.19
h. Concrete Saw (diamond blade 14") pc. 0.00015
i. Pipe Sleeve, 2" dia. l.m. 0.0071
j. Grease/Tar lit. 0.0087

43,653.75 Sub - Total for F


48,187.25 G. Direct Unit Cost (E + F)
4,336.85 H. Overhead, Contingencies & Miscellaneous (OCM) 9%
3,854.98 I. Contractor's Profit (CP) 8%
6,765.49 J. Value Added Tax (VAT) 12%
63,144.57 K. Total Unit Cost

5485
Amount Designation No. of Person No. of Hours

A. Labor

109.19 a. Construction Foreman 1 1


184.32 b. Skilled Laborer 4 1
c. Laborer 12 1

293.51 Sub - Total for A


Amount Name and Capacity No of Units No. of Hours
B. Equipment

936.00 a. Transit Mixer (5 cu.m.) 4 1


130.54 b. Concrete Vibrator 2 1
c. Batching Plant (30 cu.m.) 1 1
d. Payloader (1.50 cu.m.), LX80-2C 1 1
e. Concrete Screeder (5.5 Hp) 1 1
f. Water Truck (1000 gal.) 1 1
g. Concrete Saw, Blade Ø 14" (7.5 Hp) 1 1
h. Bar Cutter, Single Phase 1 0.10
Minor Tools (5% of Labor)

1,066.54 Sub - Total for B


1,360.05 C. Total (A + B)
D. Output per hour = 64.40 sq.m.
4,533.50 E. Direct Unit Cost (C ÷ D)
Amount Name and Specification Unit Quantity
F. Materials

46,200.00 a. Reinforcing Steel Bar kg. 0.45


b. Curing Compound lit. 0.29
c. Asphalt Sealant lit. 0.15
d. Steel Forms (Rental) l.m. 0.46
e. Sand cu.m. 0.1375
f. Gravel cu.m. 0.25
g. Cement bag 2.38
h. Concrete Saw (diamond blade 14") pc. 0.00015
i. Pipe Sleeve, 2" dia. l.m. 0.0078
j. Grease/Tar lit. 0.0095

46,200.00 Sub - Total for F


50,733.50 G. Direct Unit Cost (E + F)
4,566.02 H. Overhead, Contingencies & Miscellaneous (OCM) 9%
4,058.68 I. Contractor's Profit (CP) 8%
7,122.98 J. Value Added Tax (VAT) 12%
66,481.18 K. Total Unit Cost

2222
Amount Designation No. of Person No. of Hours

A. Labor

109.19 a. Construction Foreman 1 1


1,228.80 b. Skilled Laborer 4 1
c. Laborer 12 1

1,337.99 Sub - Total for A


Amount Name and Capacity No of Units No. of Hours
B. Equipment

1,507.00 a. Transit Mixer (5 cu.m.) 4 1


266.25 b. Concrete Vibrator 2 1
c. Batching Plant (30 cu.m.) 1 1
d. Payloader (1.50 cu.m.), LX80-2C 1 1
e. Concrete Screeder (5.5 Hp) 1 1
f. Water Truck (1000 gal.) 1 1
g. Concrete Saw, Blade Ø 14" (7.5 Hp) 1 1
h. Bar Cutter, Single Phase 1 0.10
Minor Tools (5% of Labor)

1,773.25 Sub - Total for B


3,111.24 C. Total (A + B)
D. Output per hour = 57.50 sq.m.
194.45 E. Direct Unit Cost (C ÷ D)
Amount Name and Specification Unit Quantity
F. Materials

467.19 a. Reinforcing Steel Bar kg. 0.50


b. Curing Compound lit. 0.29
c. Asphalt Sealant lit. 0.17
d. Steel Forms (Rental) l.m. 0.46
e. Sand cu.m. 0.154
f. Gravel cu.m. 0.28
g. Cement bag 2.66
h. Concrete Saw (diamond blade 14") pc. 0.00015
i. Pipe Sleeve, 2" dia. l.m. 0.0078
j. Grease/Tar lit. 0.0078

467.19 Sub - Total for F


661.64 G. Direct Unit Cost (E + F)
59.55 H. Overhead, Contingencies & Miscellaneous (OCM) 9%
52.93 I. Contractor's Profit (CP) 8%
92.89 J. Value Added Tax (VAT) 12%
867.01 K. Total Unit Cost

5485
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 311(1)a.6 PCC Pavement (Plain) - Conventional Method, 300mm


Unit of Measurement : sq.m.
Output per hour : 53.67

Amount Designation No. of Person No. of Hours

A. Labor

109.19 a. Construction Foreman 1 1


184.32 b. Skilled Laborer 4 1
c. Laborer 12 1

293.51 Sub - Total for A


Amount Name and Capacity No of Units No. of Hours

B. Equipment

936.00 a. Transit Mixer (5 cu.m.) 4 1


130.54 b. Concrete Vibrator 2 1
c. Batching Plant (30 cu.m.) 1 1
d. Payloader (1.50 cu.m.), LX80-2C 1 1
e. Concrete Screeder (5.5 Hp) 1 1
f. Water Truck (1000 gal.) 1 1
g. Concrete Saw, Blade Ø 14" (7.5 Hp) 1 1
h. Bar Cutter, Single Phase 1 0.10
Minor Tools (5% of Labor)

1,066.54 Sub - Total for B


1,360.05 C. Total (A + B)
D. Output per hour = 53.67 sq.m.
4,533.50 E. Direct Unit Cost (C ÷ D)
Amount Name and Specification Unit Quantity

F. Materials

53,313.75 a. Reinforcing Steel Bar kg. 0.55


b. Curing Compound lit. 0.29
c. Asphalt Sealant lit. 0.18
d. Steel Forms (Rental) l.m. 0.46
e. Sand cu.m. 0.165
f. Gravel cu.m. 0.30
g. Cement bag 2.85
h. Concrete Saw (diamond blade 14") pc. 0.00015
i. Pipe Sleeve, 2" dia. l.m. 0.0094
j. Grease/Tar lit. 0.0094

53,313.75 Sub - Total for F


57,847.25 G. Direct Unit Cost (E + F)
5,206.25 H. Overhead, Contingencies & Miscellaneous (OCM) 9%
4,627.78 I. Contractor's Profit (CP) 8%
8,121.75 J. Value Added Tax (VAT) 12%
75,803.04 K. Total Unit Cost

2242
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 311(1)b.1 PCC Pavement (Plain) - Using Concrete Paver,


Unit of Measurement : 230mm sq.m.
Output per hour : 90.00

Amount Designation No. of Person No. of Hours

A. Labor

109.19 a. Construction Foreman 1 1


184.32 b. Skilled Laborer 4 1
c. Laborer 10 1

293.51 Sub - Total for A


Amount Name and Capacity No of Units No. of Hours
B. Equipment

936.00 a. Batching Plant (30 cu.m.) 1 1


130.54 b. Concrete Paver, GP-2000 Slipform 1 1
c. Transit Mixer (5 cu.m.) 4 1
d. Payloader (1.50 cu.m.), LX80-2C 1 1
e. Water Truck (1000 gal.) 1 1
f. Concrete Saw, Blade Ø 14" (7.5 Hp) 1 1
g. Concrete Vibrator 1 0.10
h. Bar Cutter, Single Phase 1 0.10

1,066.54 Sub - Total for B


1,360.05 C. Total (A + B)
D. Output per hour = 90.00 sq.m.
4,533.50 E. Direct Unit Cost (C ÷ D)
Amount Name and Specification Unit Quantity
F. Materials

43,653.75 a. Reinforcing Steel Bar kg. 0.43


b. Curing Compound lit. 0.29
c. Asphalt Sealant lit. 0.12
d. Sand cu.m. 0.1265
e. Gravel cu.m. 0.23
f. Cement bag 2.19
g. Concrete Saw (diamond blade 14") pc. 0.00015
h. Pipe Sleeve, 2" dia. l.m. 0.0071
i. Grease/Tar lit. 0.0087

43,653.75 Sub - Total for F


48,187.25 G. Direct Unit Cost (E + F)
4,336.85 H. Overhead, Contingencies & Miscellaneous (OCM) 9%
3,854.98 I. Contractor's Profit (CP) 8%
6,765.49 J. Value Added Tax (VAT) 12%
63,144.57 K. Total Unit Cost

5485
Amount Designation No. of Person No. of Hours

A. Labor

109.19 a. Construction Foreman 1 1


184.32 b. Skilled Laborer 4 1
c. Laborer 10 1

293.51 Sub - Total for A


Amount Name and Capacity No of Units No. of Hours
B. Equipment

936.00 a. Batching Plant (30 cu.m.) 1 1


130.54 b. Concrete Paver, GP-2000 Slipform 1 1
c. Transit Mixer (5 cu.m.) 4 1
d. Payloader (1.50 cu.m.), LX80-2C 1 1
e. Water Truck (1000 gal.) 1 1
f. Concrete Saw, Blade Ø 14" (7.5 Hp) 1 1
g. Concrete Vibrator 1 0.10
h. Bar Cutter, Single Phase 1 0.10

1,066.54 Sub - Total for B


1,360.05 C. Total (A + B)
D. Output per hour = 82.80 sq.m.
4,533.50 E. Direct Unit Cost (C ÷ D)
Amount Name and Specification Unit Quantity
F. Materials

46,200.00 a. Reinforcing Steel Bar kg. 0.45


b. Curing Compound lit. 0.29
c. Asphalt Sealant lit. 0.15
d. Sand cu.m. 0.1375
e. Gravel cu.m. 0.25
f. Cement bag 2.38
g. Concrete Saw (diamond blade 14") pc. 0.00015
h. Pipe Sleeve, 2" dia. l.m. 0.0078
i. Grease/Tar lit. 0.0095

46,200.00 Sub - Total for F


50,733.50 G. Direct Unit Cost (E + F)
4,566.02 H. Overhead, Contingencies & Miscellaneous (OCM) 9%
4,058.68 I. Contractor's Profit (CP) 8%
7,122.98 J. Value Added Tax (VAT) 12%
66,481.18 K. Total Unit Cost

2262
Amount Designation No. of Person No. of Hours

A. Labor

109.19 a. Construction Foreman 1 1


79.70 b. Skilled Laborer 4 1
184.32 c. Laborer 10 1

373.21 Sub - Total for A


Amount Name and Capacity No of Units No. of Hours
B. Equipment

2,933.55 a. Batching Plant (30 cu.m.) 1 1


1,652.00 b. Concrete Paver, GP-2000 Slipform 1 1
553.00 c. Transit Mixer (5 cu.m.) 4 1
936.00 d. Payloader (1.50 cu.m.), LX80-2C 1 1
266.25 e. Water Truck (1000 gal.) 1 1
37.32 f. Concrete Saw, Blade Ø 14" (7.5 Hp) 1 1
g. Concrete Vibrator 1 0.10
h. Bar Cutter, Single Phase 1 0.10

6,378.12 Sub - Total for B


6,751.33 C. Total (A + B)
D. Output per hour = 73.93 sq.m.
562.61 E. Direct Unit Cost (C ÷ D)
Amount Name and Specification Unit Quantity
F. Materials

467.19 a. Reinforcing Steel Bar kg. 0.50


2,821.00 b. Curing Compound lit. 0.29
54.00 c. Asphalt Sealant lit. 0.17
d. Sand cu.m. 0.154
e. Gravel cu.m. 0.28
f. Cement bag 2.66
g. Concrete Saw (diamond blade 14") pc. 0.00015
h. Pipe Sleeve, 2" dia. l.m. 0.0078
i. Grease/Tar lit. 0.0078

3,342.19 Sub - Total for F


3,904.80 G. Direct Unit Cost (E + F)
351.43 H. Overhead, Contingencies & Miscellaneous (OCM) 9%
312.38 I. Contractor's Profit (CP) 8%
548.23 J. Value Added Tax (VAT) 12%
5,116.85 K. Total Unit Cost

5485
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 311(1)b.4 PCC Pavement (Plain) - Using Concrete Paver, 300mm
Unit of Measurement : sq.m.
Output per hour : 69.00

Amount Designation No. of Person No. of Hours

A. Labor

109.19 a. Construction Foreman 1 1


79.70 b. Skilled Laborer 4 1
184.32 c. Laborer 10 1

373.21 Sub - Total for A


Amount Name and Capacity No of Units No. of Hours

B. Equipment

2,933.55 a. Batching Plant (30 cu.m.) 1 1


1,652.00 b. Concrete Paver, GP-2000 Slipform 1 1
553.00 c. Transit Mixer (5 cu.m.) 4 1
936.00 d. Payloader (1.50 cu.m.), LX80-2C 1 1
266.25 e. Water Truck (1000 gal.) 1 1
37.32 f. Concrete Saw, Blade Ø 14" (7.5 Hp) 1 1
g. Concrete Vibrator 1 0.10
h. Bar Cutter, Single Phase 1 0.10

6,378.12 Sub - Total for B


6,751.33 C. Total (A + B)
D. Output per hour = 69.00 sq.m.
562.61 E. Direct Unit Cost (C ÷ D)
Amount Name and Specification Unit Quantity

F. Materials

467.19 a. Reinforcing Steel Bar kg. 0.55


4,400.00 b. Curing Compound lit. 0.29
54.00 c. Asphalt Sealant lit. 0.18
d. Sand cu.m. 0.165
e. Gravel cu.m. 0.30
f. Cement bag 2.85
g. Concrete Saw (diamond blade 14") pc. 0.00015
h. Pipe Sleeve, 2" dia. l.m. 0.0094
i. Grease/Tar lit. 0.0094

4,921.19 Sub - Total for F


5,483.80 G. Direct Unit Cost (E + F)
493.54 H. Overhead, Contingencies & Miscellaneous (OCM) 9%
438.70 I. Contractor's Profit (CP) 8%
769.93 J. Value Added Tax (VAT) 12%
7,185.97 K. Total Unit Cost

2282
Item No./Description : 311(1)c PCC Pavement (Plain) - Conventional Method, 150mm
Unit of Measurement : sq.m.
Output per hour : 12.00

Amount Designation No. of Person No. of Hours

A. Labor

109.19 a. Construction Foreman 1 1


79.70 b. Skilled Laborer 8 1
184.32 c. Laborer 16 1

373.21 Sub - Total for A


Amount Name and Capacity No of Units No. of Hours

B. Equipment

2,933.55 a. One Bagger Mixer 1 1


1,652.00 b. Water Truck (1000 gal.) 1 0.05
553.00 c. Concrete Vibrator 2 1
266.25 d. Bar Cutter, Single Phase 1 0.05
37.32 e. Concrete Saw, Blade Ø 14" (7.5 Hp) 1 0.10
Minor Tools (5% of Labor)

5,442.12 Sub - Total for B


5,815.33 C. Total (A + B)
D. Output per hour = 12.00 sq.m.
484.61 E. Direct Unit Cost (C ÷ D)
Amount Name and Specification Unit Quantity

F. Materials

467.19 a. Reinforcing Steel Bar kg. 0.33


b. Curing Compound lit. 0.29
c. Asphalt Sealant lit. 0.12
d. Steel Forms (Rental) l.m. 0.46
e. Sand cu.m. 0.0825
f. Gravel cu.m. 0.15
g. Cement bag 1.43
h. Concrete Saw (diamond blade 14") pc. 0.00015
i. Pipe Sleeve, 1" dia. l.m. 0.0078
j. Grease/Tar lit. 0.0015

467.19 Sub - Total for F


951.80 G. Direct Unit Cost (E + F)
85.66 H. Overhead, Contingencies & Miscellaneous (OCM) 9%
76.14 I. Contractor's Profit (CP) 8%
133.63 J. Value Added Tax (VAT) 12%
1,247.24 K. Total Unit Cost

5485
DETAILED UNIT PRICE A

Course
Item No./Description : 311(2) PCC Pavement (Reinforced), 230m
Unit of Measurement : sq.m.
Output per hour : 6.00

Hourly Rate Amount Designation No. of Person

A. Labor

109.19 109.19 a. Construction Foreman 1


79.70 79.70 b. Skilled Laborer 4
61.44 184.32 c. Laborer 12

373.21 Sub - Total for A


Hourly Rate Amount Name and Capacity No of Units

B. Equipment

936.00 936.00 a. Batching Plant (30 cu.m.) 1


b. Concrete Screeder (5.5 Hp) 1
c. Transit Mixer (5 cu.m.) 3
d. Payloader (1.50 cu.m.), LX80-2C 1
e. Water Truck (1000 gal.) 1
f. Concrete Vibrator 2
g. Bar Cutter, Single Phase 1
h. Bar Bender 1
Minor Tools (5% of Labor)

936.00 Sub - Total for B


1,309.21 C. Total (A + B)
D. Output per hour = 6.00 sq.m.
1,309.21 E. Direct Unit Cost (C ÷ D)
Unit Cost Amount Name and Specification Unit

F. Materials

40,300.00 42,315.00 a. Reinforcing Steel Bar kg.


b. Curing Compound lit.
c. Asphalt Sealant lit.
d. Steel Forms (Rental) l.m.
e. Sand cu.m.
f. Gravel cu.m.
g. Cement bag
h. # 16 GI Tie Wire (2% of RSB) kg.

42,315.00 Sub - Total for F


43,624.21 G. Direct Unit Cost (E + F)
of G 3,926.18 H. Overhead, Contingencies & Miscellaneous (OCM)
of G 3,489.94 I. Contractor's Profit (CP)
of (G + H + I) 6,124.84 J. Value Added Tax (VAT)

2302
(G + H + I + J) 57,165.16 K. Total Unit Cost

5485
hk.)

Hourly Rate Amount

109.19 109.19
79.70 478.20
61.44 737.28

1,324.67

Hourly Rate Amount

1,833.00 1,833.00
553.00 553.00
1,652.00 1,652.00
1,352.00 2,704.00
1,214.73 1,214.73
1,065.00 1,065.00
1,733.00 1,733.00
132.47

10,887.20
12,211.87

71.29
Unit Cost Amount

44,000.00 431.64
650.00 31.72
240.56 31.27

494.63
565.92
of G 50.93
of G 45.27
of (G + H + I) 79.46

2322
(G + H + I + J) 741.58

5485
Hourly Rate Amount

109.19 109.19
79.70 478.20
61.44 737.28

1,324.67

Hourly Rate Amount

1,833.00 1,833.00
553.00 553.00
1,652.00 1,652.00
1,352.00 2,704.00
1,214.73 1,214.73
1,065.00 1,065.00
1,733.00 1,733.00
132.47

10,887.20
12,211.87

71.29
Unit Cost Amount

44,000.00 539.44
650.00 31.72
240.56 31.27

602.43
673.72
of G 60.63
of G 53.90
of (G + H + I) 94.59

2342
(G + H + I + J) 882.85

5485
Hourly Rate Amount

109.19 109.19
79.70 478.20
61.44 737.28

1,324.67

Hourly Rate Amount

1,833.00 1,833.00
553.00 553.00
1,652.00 1,652.00
1,352.00 2,704.00
1,214.73 1,214.73
1,065.00 1,065.00
1,733.00 1,733.00
132.47

10,887.20
12,211.87

71.29
Unit Cost Amount

40,300.00 345.77
650.00 31.72
240.56 31.27

408.77
480.06
of G 43.21
of G 38.40
of (G + H + I) 67.40

2362
(G + H + I + J) 629.07

5485
Hourly Rate Amount

109.19 109.19
79.70 478.20
61.44 737.28

1,324.67

Hourly Rate Amount

1,352.00 2,704.00
1,214.73 1,214.73
1,065.00 1,065.00
1,733.00 1,733.00
132.47

6,849.20
8,173.87

47.72
Unit Cost Amount

40,300.00 395.34
650.00 31.72
240.56 31.27

458.34
506.05
of G 45.54
of G 40.48
of (G + H + I) 71.05

2382
(G + H + I + J) 663.13

5485
Hourly Rate Amount

109.19 109.19
79.70 318.80
61.44 491.52

919.51

Hourly Rate Amount

1,833.00 1,833.00
553.00 553.00
1,652.00 1,652.00
1,065.00 1,065.00
91.95

5,194.95
6,114.46

21.42
Unit Cost Amount

4,500.00 333.00

333.00
354.42
of G 31.90
of G 28.35
of (G + H + I) 49.76
(G + H + I + J) 464.43

2402
Hourly Rate Amount

109.19 109.19
79.70 318.80
61.44 491.52

919.51

Hourly Rate Amount

1,833.00 1,833.00
553.00 553.00
1,652.00 1,652.00
1,065.00 1,065.00
91.95

5,194.95
6,114.46

28.55
Unit Cost Amount

4,500.00 441.00

441.00
469.55
of G 42.26
of G 37.56
of (G + H + I) 65.93
(G + H + I + J) 615.30

5485
Hourly Rate Amount

109.19 109.19
79.70 318.80
61.44 491.52

919.51

Hourly Rate Amount

1,833.00 1,833.00
553.00 553.00
1,652.00 1,652.00
1,065.00 1,065.00
91.95

5,194.95
6,114.46

35.69
Unit Cost Amount

4,500.00 553.50

553.50
589.19
of G 53.03
of G 47.14
of (G + H + I) 82.72
(G + H + I + J) 772.08

2422
Hourly Rate Amount

109.19 109.19
79.70 478.20
61.44 737.28

1,324.67

Hourly Rate Amount

1,833.00 1,833.00
553.00 553.00
1,652.00 1,652.00
1,352.00 2,704.00
1,214.73 1,214.73
1,065.00 1,065.00
1,733.00 1,733.00
132.47

10,887.20
12,211.87

42.77
Unit Cost Amount

50,775.00 298.56
650.00 19.05
240.56 18.76

336.37
379.14
of G 34.12
of G 30.33
of (G + H + I) 53.23
(G + H + I + J) 496.82

5485
Hourly Rate Amount

109.19 109.19
79.70 478.20
61.44 737.28

1,324.67

Hourly Rate Amount

1,833.00 1,833.00
553.00 553.00
1,652.00 1,652.00
1,352.00 2,704.00
1,214.73 1,214.73
1,065.00 1,065.00
1,733.00 1,733.00
132.47

10,887.20
12,211.87

57.03
Unit Cost Amount

50,775.00 398.58
650.00 25.42
240.56 25.02

449.02
506.05
of G 45.54
of G 40.48
of (G + H + I) 71.05
(G + H + I + J) 663.12

2442
Hourly Rate Amount

109.19 109.19
79.70 478.20
61.44 737.28

1,324.67

Hourly Rate Amount

1,833.00 1,833.00
553.00 553.00
1,652.00 1,652.00
1,352.00 2,704.00
1,214.73 1,214.73
1,065.00 1,065.00
1,733.00 1,733.00
132.47

10,887.20
12,211.87

71.29
Unit Cost Amount

50,775.00 498.10
650.00 31.72
240.56 31.27

561.10
632.38
of G 56.91
of G 50.59
of (G + H + I) 88.79
(G + H + I + J) 828.68

5485
thk.

Hourly Rate Amount

109.19 109.19
79.70 318.80
61.44 737.28

1,165.27

Hourly Rate Amount

1,279.00 5,116.00
148.88 297.76
1,208.03 1,208.03
1,733.00 1,733.00
545.00 545.00
1,065.00 1,065.00
167.38 167.38
219.75 21.98
58.26

10,212.41
11,377.68

106.01
Unit Cost Amount

40.00 13.20
28.00 8.12
44.00 5.28
50.00 23.00
850.00 70.13
650.00 97.50
220.00 314.60
8,000.00 1.20
34.33 0.27
300.00 0.45

533.74
639.75
of G 57.58
of G 51.18
of (G + H + I) 89.82
(G + H + I + J) 838.33

2462
Hourly Rate Amount

109.19 109.19
79.70 318.80
61.44 737.28

1,165.27

Hourly Rate Amount

1,279.00 5,116.00
148.88 297.76
1,208.03 1,208.03
1,733.00 1,733.00
545.00 545.00
1,065.00 1,065.00
167.38 167.38
219.75 21.98
58.26

10,212.41
11,377.68

141.34
Unit Cost Amount

40.00 15.60
28.00 8.12
44.00 5.28
50.00 23.00
850.00 93.50
650.00 130.00
220.00 418.00
8,000.00 1.20
67.67 0.58
300.00 1.68

696.96
838.30
of G 75.45
of G 67.06
of (G + H + I) 117.70
(G + H + I + J) 1,098.51

5485
Hourly Rate Amount

109.19 109.19
79.70 318.80
61.44 737.28

1,165.27

Hourly Rate Amount

1,279.00 5,116.00
148.88 297.76
1,208.03 1,208.03
1,733.00 1,733.00
545.00 545.00
1,065.00 1,065.00
167.38 167.38
219.75 21.98
58.26

10,212.41
11,377.68

162.54
Unit Cost Amount

40.00 17.20
28.00 8.12
44.00 5.28
50.00 23.00
850.00 107.53
650.00 149.50
220.00 481.80
8,000.00 1.20
97.00 0.69
300.00 2.61

796.92
959.46
of G 86.35
of G 76.76
of (G + H + I) 134.71
(G + H + I + J) 1,257.28

2482
Hourly Rate Amount

109.19 109.19
79.70 318.80
61.44 737.28

1,165.27

Hourly Rate Amount

1,279.00 5,116.00
148.88 297.76
1,208.03 1,208.03
1,733.00 1,733.00
545.00 545.00
1,065.00 1,065.00
167.38 167.38
219.75 21.98
58.26

10,212.41
11,377.68

176.67
Unit Cost Amount

40.00 18.00
28.00 8.12
44.00 6.60
50.00 23.00
850.00 116.88
650.00 162.50
220.00 523.60
8,000.00 1.20
97.00 0.76
300.00 2.85

863.50
1,040.17
of G 93.62
of G 83.21
of (G + H + I) 146.04
(G + H + I + J) 1,363.04

5485
Hourly Rate Amount

109.19 109.19
79.70 318.80
61.44 737.28

1,165.27

Hourly Rate Amount

1,279.00 5,116.00
148.88 297.76
1,208.03 1,208.03
1,733.00 1,733.00
545.00 545.00
1,065.00 1,065.00
167.38 167.38
219.75 21.98
58.26

10,212.41
11,377.68

197.87
Unit Cost Amount

40.00 20.00
28.00 8.12
44.00 7.48
50.00 23.00
850.00 130.90
650.00 182.00
220.00 585.20
8,000.00 1.20
97.00 0.76
300.00 2.34

961.00
1,158.87
of G 104.30
of G 92.71
of (G + H + I) 162.71
(G + H + I + J) 1,518.58

2502
Hourly Rate Amount

109.19 109.19
79.70 318.80
61.44 737.28

1,165.27

Hourly Rate Amount

1,279.00 5,116.00
148.88 297.76
1,208.03 1,208.03
1,733.00 1,733.00
545.00 545.00
1,065.00 1,065.00
167.38 167.38
219.75 21.98
58.26

10,212.41
11,377.68

211.99
Unit Cost Amount

40.00 22.00
28.00 8.12
44.00 7.92
50.00 23.00
850.00 140.25
650.00 195.00
220.00 627.00
8,000.00 1.20
97.00 0.91
300.00 2.82

1,028.22
1,240.22
of G 111.62
of G 99.22
of (G + H + I) 174.13
(G + H + I + J) 1,625.18

5485
Hourly Rate Amount

109.19 109.19
79.70 318.80
61.44 614.40

1,042.39

Hourly Rate Amount

1,208.03 1,208.03
6,765.00 6,765.00
1,279.00 5,116.00
1,733.00 1,733.00
1,065.00 1,065.00
167.38 167.38
148.88 14.89
219.75 21.98

16,091.27
17,133.66

190.37
Unit Cost Amount

40.00 17.20
28.00 8.12
44.00 5.28
850.00 107.53
650.00 149.50
220.00 481.80
8,000.00 1.20
97.00 0.69
300.00 2.61

773.92
964.30
of G 86.79
of G 77.14
of (G + H + I) 135.39
(G + H + I + J) 1,263.62

2522
Hourly Rate Amount

109.19 109.19
79.70 318.80
61.44 614.40

1,042.39

Hourly Rate Amount

1,208.03 1,208.03
6,765.00 6,765.00
1,279.00 5,116.00
1,733.00 1,733.00
1,065.00 1,065.00
167.38 167.38
148.88 14.89
219.75 21.98

16,091.27
17,133.66

206.93
Unit Cost Amount

40.00 18.00
28.00 8.12
44.00 6.60
850.00 116.88
650.00 162.50
220.00 523.60
8,000.00 1.20
97.00 0.76
300.00 2.85

840.50
1,047.43
of G 94.27
of G 83.79
of (G + H + I) 147.06
(G + H + I + J) 1,372.55

5485
Hourly Rate Amount

109.19 109.19
79.70 318.80
61.44 614.40

1,042.39

Hourly Rate Amount

1,208.03 1,208.03
6,765.00 6,765.00
1,279.00 5,116.00
1,733.00 1,733.00
1,065.00 1,065.00
167.38 167.38
148.88 14.89
219.75 21.98

16,091.27
17,133.66

231.76
Unit Cost Amount

40.00 20.00
28.00 8.12
44.00 7.48
850.00 130.90
650.00 182.00
220.00 585.20
8,000.00 1.20
97.00 0.76
300.00 2.34

938.00
1,169.75
of G 105.28
of G 93.58
of (G + H + I) 164.23
(G + H + I + J) 1,532.84

2542
Hourly Rate Amount

109.19 109.19
79.70 318.80
61.44 614.40

1,042.39

Hourly Rate Amount

1,208.03 1,208.03
6,765.00 6,765.00
1,279.00 5,116.00
1,733.00 1,733.00
1,065.00 1,065.00
167.38 167.38
148.88 14.89
219.75 21.98

16,091.27
17,133.66

248.31
Unit Cost Amount

40.00 22.00
28.00 8.12
44.00 7.92
850.00 140.25
650.00 195.00
220.00 627.00
8,000.00 1.20
97.00 0.91
300.00 2.82

1,005.22
1,253.54
of G 112.82
of G 100.28
of (G + H + I) 176.00
(G + H + I + J) 1,642.63

5485
Hourly Rate Amount

109.19 109.19
79.70 637.60
61.44 983.04

1,729.83

Hourly Rate Amount

172.00 172.00
1,065.00 53.25
148.88 297.76
219.75 10.99
167.38 16.74
86.49

637.23
2,367.06

197.25
Unit Cost Amount

40.00 13.20
28.00 8.12
44.00 5.28
50.00 23.00
850.00 70.13
650.00 97.50
220.00 314.60
8,000.00 1.20
34.33 0.27
300.00 0.45

533.74
731.00
of G 65.79
of G 58.48
of (G + H + I) 102.63
(G + H + I + J) 957.90

2562
NALYSIS (DUPA)

m thk.

No. of Hours Hourly Rate Amount

1 109.19 109.19
1 79.70 318.80
1 61.44 737.28

1,165.27

No. of Hours Hourly Rate Amount

0.10 1,208.03 120.80


0.10 545.00 54.50
0.10 1,279.00 383.70
0.10 1,733.00 173.30
0.10 1,065.00 106.50
0.10 148.88 29.78
0.25 219.75 54.94
0.25 351.50 87.88
58.26

1,069.66
2,234.93

372.49
Quantity Unit Cost Amount

40.86 40.00 1,634.40


0.29 28.00 8.12
0.12 44.00 5.28
0.46 50.00 23.00
0.1265 850.00 107.53
0.23 650.00 149.50
2.19 220.00 481.80
0.817 47.00 38.40

2,448.02
2,820.51
9% of G 253.85
8% of G 225.64
12% of (G + H + I) 396.00

5485
(G + H + I + J) 3,696.00

2582
5485
2602
5485
2622
5485
2642
5485
2662
5485
2682
5485
2702
5485
2722
5485
2742
5485
2762
5485
2782
5485
2802
5485
2822
5485
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 404 Reinforcing Steel Bar, Grade 40 (Minor Structures)


Unit of Measurement : kg.
Output per hour : 180.00

Designation No. of Person No. of Hours Hourly Rate

A. Labor

a. Construction Foreman 1 1 109.19


b. Skilled Laborer 2 1 79.70
c. Laborer 8 1 61.44

Sub - Total for A


Name and Capacity No of Units No. of Hours Hourly Rate

B. Equipment

a. Bar Cutter 1 0.50 219.75


b. Bar Bender 1 0.50 351.50
c. Cargo Truck (10 T, 270 Hp) 1 0.15 1,102.00

Sub - Total for B


C. Total (A + B)
D. Output per hour = 180.00 kg.
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost

F. Materials

a. Tie Wire (2% of RSB) kg. 0.021 47.00


b. Reinforcing Steel Bar, Grade 40 kg. 1.05 40.00
(w/ 5% Wastage)

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G
I. Contractor's Profit (CP) 8% of G
J. Value Added Tax (VAT) 12% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
Item No./Description : 405 Structural Concrete Class A (Minor Structures)
Unit of Measurement : cu.m.
Output per hour : 1.40

Designation No. of Person No. of Hours Hourly Rate

A. Labor

a. Construction Foreman 1 1 109.19


b. Skilled Laborer 4 1 79.70
c. Laborer 8 1 61.44

Installation/Removal of Formworks
a. Skilled Laborer 4 1 79.70
b. Laborer 8 1 61.44
Sub - Total for A
Name and Capacity No of Units No. of Hours Hourly Rate

B. Equipment

a. One Bagger Mixer 1 1 172.00


b. Concrete Vibrator 1 1 148.88
c. Water Truck (1000 gal.) 1 0.10 1,065.00
Minor Tools (5% of Labor)

Sub - Total for B


C. Total (A + B)
D. Output per hour = 1.40 cu.m.
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost

F. Materials

a. Lumber, Good - 4 uses bd.ft. * 70.00 40.00


b. Marine Plywood (1/2" x 4' x 8') - 4 uses pc. * 1.60 700.00
c. Assorted CWN (1kg./100 bd.ft. of Lumber) kg. * 0.70 68.00
d. Cement bag 9.50 220.00
e. Sand cu.m. 0.50 850.00
f. Gravel cu.m. 1 650.00

Note:
*Quantities for lumber, plywood and CWN are
dependent on the type of minor structure.
The above-computed quantities are based on box
culvert.

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G
I. Contractor's Profit (CP) 8% of G
J. Value Added Tax (VAT) 12% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
Amount

109.19
159.40
491.52

760.11
Amount

109.88
175.75
165.30

450.93
1,211.04

6.73
Amount

0.99
42.00

42.99
49.71
4.47
3.98
6.98
65.15
Amount

109.19
318.80
491.52

318.80
491.52
1,729.83
Amount

172.00
148.88
106.50
86.49

513.87
2,243.70

1,602.64
Amount

700.00
280.00
47.60
2,090.00
425.00
650.00

4,192.60
5,795.24
521.57
463.62
813.65
7,594.09
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 500(1)a Pipe Culverts, 610mm dia. (24" Ø)


Unit of Measurement : l.m.
Output per hour : 2.25

Designation No. of Person No. of Hours Hourly Rate

A. Labor

a. Construction Foreman 1 1 109.19


b. Skilled Laborer 2 1 79.70
c. Laborer 4 1 61.44

Sub - Total for A


Name and Capacity No of Units No. of Hours Hourly Rate

B. Equipment

a. Backhoe (0.80 cu.m.) 1 0.50 1,537.00


b. Plate Compactor (5 Hp) 1 0.50 123.00
Minor Tools (10 % of Labor)

Sub - Total for B


C. Total (A + B)
D. Output per hour = 2.25 l.m.
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost

F. Materials

a. Portland Cement bag 0.774 220.00


b. Sand cu.m. 0.044 850.00
c. R.C. Pipes (610mm dia.) pc. 1 950.00
d. Sand Bedding/Selected Sandy Soil cu.m. 0.088 850.00

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G
I. Contractor's Profit (CP) 8% of G
J. Value Added Tax (VAT) 12% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
Item No./Description : 500(1)b Pipe Culverts, 760mm dia. (30" Ø)
Unit of Measurement : l.m.
Output per hour : 2.00

Designation No. of Person No. of Hours Hourly Rate

A. Labor

a. Construction Foreman 1 1 109.19


b. Skilled Laborer 2 1 79.70
c. Laborer 4 1 61.44

Sub - Total for A


Name and Capacity No of Units No. of Hours Hourly Rate

B. Equipment

a. Backhoe (0.80 cu.m.) 1 0.50 1,537.00


b. Plate Compactor (5 Hp) 1 0.50 123.00
Minor Tools (10 % of Labor)

Sub - Total for B


C. Total (A + B)
D. Output per hour = 2.00 l.m.
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost

F. Materials

a. Portland Cement bag 0.918 220.00


b. Sand cu.m. 0.052 850.00
c. R.C. Pipes (760mm dia.) pc. 1 1,750.00
d. Sand Bedding/Selected Sandy Soil cu.m. 0.108 850.00

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G
I. Contractor's Profit (CP) 8% of G
J. Value Added Tax (VAT) 12% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 500(1)c Pipe Culverts, 910mm dia. (36" Ø)


Unit of Measurement : l.m.
Output per hour : 1.75

Designation No. of Person No. of Hours Hourly Rate

A. Labor

a. Construction Foreman 1 1 109.19


b. Skilled Laborer 2 1 79.70
c. Laborer 4 1 61.44

Sub - Total for A


Name and Capacity No of Units No. of Hours Hourly Rate

B. Equipment

a. Backhoe (0.80 cu.m.) 1 0.50 1,537.00


b. Plate Compactor (5 Hp) 1 0.50 123.00
Minor Tools (10 % of Labor)

Sub - Total for B


C. Total (A + B)
D. Output per hour = 1.75 l.m.
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost

F. Materials

a. Portland Cement bag 1.080 220.00


b. Sand cu.m. 0.061 850.00
c. R.C. Pipes (910mm dia.) pc. 1 2,170.00
d. Sand Bedding/Selected Sandy Soil cu.m. 0.128 850.00

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G
I. Contractor's Profit (CP) 8% of G
J. Value Added Tax (VAT) 12% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 500(1)d Pipe Culverts, 1070mm dia. (42" Ø)


Unit of Measurement : l.m.
Output per hour : 1.50

Designation No. of Person No. of Hours Hourly Rate

A. Labor

a. Construction Foreman 1 1 109.19


b. Skilled Laborer 2 1 79.70
c. Laborer 4 1 61.44

Sub - Total for A


Name and Capacity No of Units No. of Hours Hourly Rate

B. Equipment

a. Backhoe (0.80 cu.m.) 1 0.50 1,537.00


b. Plate Compactor (5 Hp) 1 0.50 123.00
Minor Tools (10 % of Labor)

Sub - Total for B


C. Total (A + B)
D. Output per hour = 1.50 l.m.
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost

F. Materials

a. Portland Cement bag 1.242 220.00


b. Sand cu.m. 0.070 850.00
c. R.C. Pipes (1070mm dia.) pc. 1 2,900.00
d. Sand Bedding/Selected Sandy Soil cu.m. 0.149 850.00

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G
I. Contractor's Profit (CP) 8% of G
J. Value Added Tax (VAT) 12% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 500(1)e Pipe Culverts, 1220mm dia. (48" Ø)


Unit of Measurement : l.m.
Output per hour : 1.25

Designation No. of Person No. of Hours Hourly Rate

A. Labor

a. Construction Foreman 1 1 109.19


b. Skilled Laborer 2 1 79.70
c. Laborer 4 1 61.44

Sub - Total for A


Name and Capacity No of Units No. of Hours Hourly Rate

B. Equipment

a. Backhoe (0.80 cu.m.) 1 0.50 1,537.00


b. Plate Compactor (5 Hp) 1 0.50 123.00
Minor Tools (10 % of Labor)

Sub - Total for B


C. Total (A + B)
D. Output per hour = 1.25 l.m.
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost

F. Materials

a. Portland Cement bag 1.404 220.00


b. Sand cu.m. 0.080 850.00
c. R.C. Pipes (1220mm dia.) pc. 1 3,800.00
d. Sand Bedding/Selected Sandy Soil cu.m. 0.170 850.00

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G
I. Contractor's Profit (CP) 8% of G
J. Value Added Tax (VAT) 12% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 500(1)f Pipe Culverts, 1520mm dia. (60" Ø)


Unit of Measurement : l.m.
Output per hour : 1.00

Designation No. of Person No. of Hours Hourly Rate

A. Labor

a. Construction Foreman 1 1 109.19


b. Skilled Laborer 2 1 79.70
c. Laborer 4 1 61.44

Sub - Total for A


Name and Capacity No of Units No. of Hours Hourly Rate

B. Equipment

a. Backhoe (0.80 cu.m.) 1 0.50 1,537.00


b. Plate Compactor (5 Hp) 1 0.50 123.00
Minor Tools (10 % of Labor)

Sub - Total for B


C. Total (A + B)
D. Output per hour = 1.00 l.m.
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost

F. Materials

a. Portland Cement bag 1.710 220.00


b. Sand cu.m. 0.097 850.00
c. R.C. Pipes (1520mm dia.) pc. 1 6,175.00
d. Sand Bedding/Selected Sandy Soil cu.m. 0.210 850.00

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G
I. Contractor's Profit (CP) 8% of G
J. Value Added Tax (VAT) 12% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 501(1) Underdrain


Unit of Measurement : l.m.
Output per hour : 1.25

Designation No. of Person No. of Hours Hourly Rate

A. Labor

a. Construction Foreman 1 1 109.19


b. Laborer 4 1 61.44

Sub - Total for A


Name and Capacity No of Units No. of Hours Hourly Rate
B. Equipment

a. Plate Compactor (5 Hp) 1 0.50 123.00


Minor Tools (10% of Labor)

Sub - Total for B


C. Total (A + B)
D. Output per hour = 1.25 l.m.
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost

F. Materials

a. Coarse Aggregates cu.m. 0.20 900.00


b. Fine Aggregates cu.m. 0.39 850.00
c. Filter Cloth sq.m. 2 275.00
d. 150 mm. dia. Concrete Perforated Pipe pc. 1.05 230.00

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G
I. Contractor's Profit (CP) 8% of G
J. Value Added Tax (VAT) 12% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 501(2) Blind Drain


Unit of Measurement : l.m.
Output per hour : 1.25

Designation No. of Person No. of Hours Hourly Rate

A. Labor

a. Construction Foreman 1 1 109.19


b. Laborer 4 1 61.44

Sub - Total for A


Name and Capacity No of Units No. of Hours Hourly Rate

B. Equipment

Minor Tools (10% of Labor)

Sub - Total for B


C. Total (A + B)
D. Output per hour = 1.25 l.m.
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost

F. Materials

a. Coarse Aggregates cu.m. 0.22 900.00


b. Fine Aggregates cu.m. 0.39 850.00
c. Filter Cloth sq.m. 2 275.00

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G
I. Contractor's Profit (CP) 8% of G
J. Value Added Tax (VAT) 12% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 501(3) Granular Backfill filter material for Underdrains


Unit of Measurement : cu.m.
Output per hour : 1.25

Designation No. of Person No. of Hours Hourly Rate

A. Labor

a. Construction Foreman 1 1 109.19


b. Laborer 4 1 61.44

Sub - Total for A


Name and Capacity No of Units No. of Hours Hourly Rate
B. Equipment

a. Plate Compactor (5 Hp) 1 1 123.00


Minor Tools (10% of Labor)

Sub - Total for B


C. Total (A + B)
D. Output per hour = 1.25 cu.m.
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost

F. Materials

a. Coarse Aggregates (Granular Backfill Materials) cu.m. 1.15 900.00


(w/ 15% Shrinkage Factor)

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G
I. Contractor's Profit (CP) 8% of G
J. Value Added Tax (VAT) 12% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 502 Manhole/Catch Basin/Inlet


Unit of Measurement : ea.
Output : 1.00

Designation No. of Person No. of Hours Hourly Rate

A. Labor

Sub - Total for A


Name and Capacity No of Units No. of Hours Hourly Rate

B. Equipment

Sub - Total for B


C. Total (A + B)
D. Output = 1.00 ea.
E. Direct Unit Cost (C ÷ D)
Direct Unit
Name and Specification Unit Quantity
Cost
F. Materials/Processed Component Pay Item

a. 103(3) - Foundation Fill cu.m.


b. 404 - Reinforcing Steel Bar kg.
c. 405 - Structural Concrete cu.m.

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G
I. Contractor's Profit (CP) 8% of G
J. Value Added Tax (VAT) 12% of (G + H + I)
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 502(4) Concrete Covers


Unit of Measurement : ea.
Output : 5.00

Designation No. of Person No. of Hours Hourly Rate

A. Labor

a. Construction Foreman 1 1 109.19


b. Skilled Laborer 2 1 79.70
c. Laborer 4 1 61.44

Sub - Total for A


Name and Capacity No of Units No. of Hours Hourly Rate

B. Equipment

a. One Bagger Mixer 1 0.50 172.00


b. Bar Cutter 1 0.50 219.75
c. Concrete Vibrator 1 0.50 148.88
d. Welding Machine (GasType) 1 0.25 391.00
e. Water Truck 1 0.05 1,065.00
Minor Tools (10% of Labor)

Sub - Total for B


C. Total (A + B)
D. Output = 5.00 ea.
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost

F. Materials

Dimension: 1.31m x 0.573m x 0.20m


a. Portland Cement bag 1.31 220.00
b. Sand cu.m. 0.06 850.00
c. Gravel cu.m. 0.12 650.00
d. Reinforcing Steel Bar kg. 48.25 40.00
e. #16 GI Tie Wire (2% of RSB) kg. 0.97 47.00
f. 6mm thk. Steel Plate kg. 36.79 48.00
g. 16mm thk. Steel Plate kg. 2.83 48.00
h. 1/2" Ordinary Plywood - 2 uses pc. 0.30 620.00
i. 16mm dia. U-bolt & Knot set 2.00 250.00
j. Welding Rod (1 kg./2000 kg. of Steel) kg. 0.02 90.00

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G
I. Contractor's Profit (CP) 8% of G
J. Value Added Tax (VAT) 12% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
Item No./Description : 502(5) Metal Frames and Gratings
Unit of Measurement : pair
Output : 1.00

Designation No. of Person No. of Hours Hourly Rate

A. Labor

a. Construction Foreman 1 0.50 109.19


b. Skilled Laborer 1 0.50 79.70
c. Laborer 1 0.50 61.44

Sub - Total for A


Name and Capacity No of Units No. of Hours Hourly Rate

B. Equipment

Minor Tools (10% of Labor)

Sub - Total for B


C. Total (A + B)
D. Output = 1.00 pair
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost

F. Materials

a. 410mmx660mmx60mm, C.I. Cover with Frame set 1.00 4,700.00

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G
I. Contractor's Profit (CP) 8% of G
J. Value Added Tax (VAT) 12% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 502(6) Metal Frames and Covers (Circular)


Unit of Measurement : pair
Output : 1.00

Designation No. of Person No. of Hours Hourly Rate

A. Labor

a. Construction Foreman 1 0.50 109.19


b. Skilled Laborer 1 0.50 79.70
c. Laborer 1 0.50 61.44

Sub - Total for A


Name and Capacity No of Units No. of Hours Hourly Rate

B. Equipment

Minor Tools (10% of Labor)

Sub - Total for B


C. Total (A + B)
D. Output = 1.00 pair
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost

F. Materials

a. 580mm dia. C.I. Manhole Cover with Frame set 1.00 5,700.00

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G
I. Contractor's Profit (CP) 8% of G
J. Value Added Tax (VAT) 12% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 503(a) Drainage Steel Grating with Frame (675mm x 975mm Sump Grating)
Unit of Measurement : set
Output per hour : 0.25

Designation No. of Person No. of Hours Hourly Rate

A. Labor

a. Construction Foreman 1 1 109.19


b. Skilled Laborer 1 1 79.70
c. Laborer 1 1 61.44

Sub - Total for A


Name and Capacity No of Units No. of Hours Hourly Rate

B. Equipment

a. Bar Cutter 1 0.50 219.75


b. Welding Machine 1 1 391.00

Sub - Total for B


C. Total (A + B)
D. Output per hour = 0.25 set
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost

F. Materials

a. 65mm x 5mm Flat Bar kg. 62.557 48.00


b. 6mm dia. x 975mm Twisted Cross Rod kg. 1.244 48.00
c. 75mm x 75mm x 9mm Angle Bar kg. 38.36 48.00
d. Welding Rod (1 kg./2000 kg. of Steel) kg. 0.051 90.00

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G
I. Contractor's Profit (CP) 8% of G
J. Value Added Tax (VAT) 12% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
Item No./Description : 503(b) Drainage Steel Grating with Frame (715mm x 2000mm Trench Grating)
Unit of Measurement : set
Output per hour : 0.125

Designation No. of Person No. of Hours Hourly Rate

A. Labor

a. Construction Foreman 1 1 109.19


b. Skilled Laborer 1 1 79.70
c. Laborer 1 1 61.44

Sub - Total for A


Name and Capacity No of Units No. of Hours Hourly Rate

B. Equipment

a. Bar Cutter 1 0.50 219.75


b. Welding Machine 1 1 391.00

Sub - Total for B


C. Total (A + B)
D. Output per hour = 0.125 set
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost

F. Materials

a. 65mm x 5mm Flat Bar kg. 127.066 48.00


b. 6mm dia. x 975mm Twisted Cross Rod kg. 3.174 48.00
c. 75mm x 75mm x 9mm Angle Bar kg. 41.64 48.00
d. Welding Rod (1 kg./2000 kg. of Steel) kg. 0.086 90.00

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G
I. Contractor's Profit (CP) 8% of G
J. Value Added Tax (VAT) 12% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
Item No./Description : 504(1)a Removing, Cleaning, Stockpiling Salvaged Culvert Pipe (24" dia) - 610mm
Unit of Measurement : l.m.
Output per hour : 3.00

Designation No. of Person No. of Hours Hourly Rate

A. Labor

a. Construction Foreman 1 1 109.19


b. Skilled Laborer 2 1 79.70
c. Laborer 4 1 61.44

Sub - Total for A


Name and Capacity No of Units No. of Hours Hourly Rate

B. Equipment

a. Backhoe (0.80 cu.m.) 1 0.50 1,537.00


b. Boom Truck 1 0.50 961.20
c. Water Truck (1000 gal.) 1 0.25 1,065.00
Minor Tools (10% of Labor)

Sub - Total for B


C. Total (A + B)
D. Output per hour = 3.00 l.m.
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost

F. Materials

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G
I. Contractor's Profit (CP) 8% of G
J. Value Added Tax (VAT) 12% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
Item No./Description : 504(1)b Removing, Cleaning, Stockpiling Salvaged Culvert Pipe (30" dia.) - 760mm
Unit of Measurement : l.m.
Output per hour : 2.50

Designation No. of Person No. of Hours Hourly Rate

A. Labor

a. Construction Foreman 1 1 109.19


b. Skilled Laborer 2 1 79.70
c. Laborer 4 1 61.44

Sub - Total for A


Name and Capacity No of Units No. of Hours Hourly Rate

B. Equipment

a. Backhoe (0.80 cu.m.) 1 0.50 1,537.00


b. Boom Truck 1 0.50 961.20
c. Water Truck (1000 gal.) 1 0.25 1,065.00
Minor Tools (10% of Labor)

Sub - Total for B


C. Total (A + B)
D. Output per hour = 2.50 l.m.
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost

F. Materials

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G
I. Contractor's Profit (CP) 8% of G
J. Value Added Tax (VAT) 12% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
Item No./Description : 504(1)c Removing, Cleaning, Stockpiling Salvaged Culvert Pipe (36" dia.) - 910mm
Unit of Measurement : l.m.
Output per hour : 2.00

Designation No. of Person No. of Hours Hourly Rate

A. Labor

a. Construction Foreman 1 1 109.19


b. Skilled Laborer 2 1 79.70
c. Laborer 4 1 61.44

Sub - Total for A


Name and Capacity No of Units No. of Hours Hourly Rate

B. Equipment

a. Backhoe (0.80 cu.m.) 1 0.50 1,537.00


b. Boom Truck 1 0.50 961.20
c. Water Truck (1000 gal.) 1 0.25 1,065.00
Minor Tools (10% of Labor)

Sub - Total for B


C. Total (A + B)
D. Output per hour = 2.00 l.m.
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost

F. Materials

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G
I. Contractor's Profit (CP) 8% of G
J. Value Added Tax (VAT) 12% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 504(1)d Removing, Cleaning, Stockpiling Salvaged Culvert Pipe (42" dia.) - 1070m
Unit of Measurement : l.m.
Output per hour : 2.00

Designation No. of Person No. of Hours Hourly Rate

A. Labor

a. Construction Foreman 1 1 109.19


b. Skilled Laborer 2 1 79.70
c. Laborer 4 1 61.44

Sub - Total for A


Name and Capacity No of Units No. of Hours Hourly Rate

B. Equipment

a. Backhoe (0.80 cu.m.) 1 0.50 1,537.00


b. Boom Truck 1 0.50 961.20
c. Water Truck (1000 gal.) 1 0.25 1,065.00
Minor Tools (10% of Labor)

Sub - Total for B


C. Total (A + B)
D. Output per hour = 2.00 l.m.
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost

F. Materials

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G
I. Contractor's Profit (CP) 8% of G
J. Value Added Tax (VAT) 12% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
Item No./Description : 504(1)e Removing, Cleaning, Stockpiling Salvaged Culvert Pipe (48" dia.) - 1220m
Unit of Measurement : l.m.
Output per hour : 1.50

Designation No. of Person No. of Hours Hourly Rate

A. Labor

a. Construction Foreman 1 1 109.19


b. Skilled Laborer 2 1 79.70
c. Laborer 4 1 61.44

Sub - Total for A


Name and Capacity No of Units No. of Hours Hourly Rate

B. Equipment

a. Backhoe (0.80 cu.m.) 1 0.50 1,537.00


b. Boom Truck 1 0.50 961.20
c. Water Truck (1000 gal.) 1 0.25 1,065.00
Minor Tools (10% of Labor)

Sub - Total for B


C. Total (A + B)
D. Output per hour = 1.50 l.m.
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost

F. Materials

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G
I. Contractor's Profit (CP) 8% of G
J. Value Added Tax (VAT) 12% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 504(2)a Removing, Cleaning and Re-laying Salvaged Culvert Pipe (24" dia.) - 610m
Unit of Measurement : l.m.
Output per hour : 1.50

Designation No. of Person No. of Hours Hourly Rate

A. Labor

a. Construction Foreman 1 1 109.19


b. Skilled Laborer 2 1 79.70
c. Laborer 4 1 61.44

Sub - Total for A


Name and Capacity No of Units No. of Hours Hourly Rate

B. Equipment

a. Backhoe (0.80 cu.m.) 1 0.60 1,537.00


b. Plate Compactor (5 Hp) 1 0.50 123.00
c. Water Truck (1000 gal.) 1 0.15 1,065.00
Minor Tools (10 % of Labor)

Sub - Total for B


C. Total (A + B)
D. Output per hour = 1.50 l.m.
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost

F. Materials

a. Portland Cement bag 0.774 220.00


b. Sand cu.m. 0.044 850.00
c. Sand Bedding cu.m. 0.088 850.00

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G
I. Contractor's Profit (CP) 8% of G
J. Value Added Tax (VAT) 12% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
Item No./Description : 504(2)b Removing, Cleaning and Re-laying Salvaged Culvert Pipe (30" dia.) - 760m
Unit of Measurement : l.m.
Output per hour : 1.25

Designation No. of Person No. of Hours Hourly Rate

A. Labor

a. Construction Foreman 1 1 109.19


b. Skilled Laborer 2 1 79.70
c. Laborer 4 1 61.44

Sub - Total for A


Name and Capacity No of Units No. of Hours Hourly Rate

B. Equipment

a. Backhoe (0.80 cu.m.) 1 0.60 1,537.00


b. Plate Compactor (5 Hp) 1 0.50 123.00
c. Water Truck (1000 gal.) 1 0.15 1,065.00
Minor Tools (10 % of Labor)

Sub - Total for B


C. Total (A + B)
D. Output per hour = 1.25 l.m.
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost

F. Materials

a. Portland Cement bag 0.918 220.00


b. Sand cu.m. 0.052 850.00
c. Sand Bedding cu.m. 0.108 850.00

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G
I. Contractor's Profit (CP) 8% of G
J. Value Added Tax (VAT) 12% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
Item No./Description : 504(2)c Removing, Cleaning and Re-laying Salvaged Culvert Pipe (36" dia.) - 910m
Unit of Measurement : l.m.
Output per hour : 1.00

Designation No. of Person No. of Hours Hourly Rate

A. Labor

a. Construction Foreman 1 1 109.19


b. Skilled Laborer 2 1 79.70
c. Laborer 4 1 61.44

Sub - Total for A


Name and Capacity No of Units No. of Hours Hourly Rate

B. Equipment

a. Backhoe (0.80 cu.m.) 1 0.60 1,537.00


b. Plate Compactor (5 Hp) 1 0.50 123.00
c. Water Truck (1000 gal.) 1 0.15 1,065.00
Minor Tools (10 % of Labor)

Sub - Total for B


C. Total (A + B)
D. Output per hour = 1.00 l.m.
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost

F. Materials

a. Portland Cement bag 1.080 220.00


b. Sand cu.m. 0.061 850.00
c. Sand Bedding cu.m. 0.128 850.00

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G
I. Contractor's Profit (CP) 8% of G
J. Value Added Tax (VAT) 12% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 504(2)d Removing, Cleaning and Re-laying Salvaged Culvert Pipe (42" dia.) - 1070
Unit of Measurement : l.m.
Output per hour : 1.00

Designation No. of Person No. of Hours Hourly Rate

A. Labor

a. Construction Foreman 1 1 109.19


b. Skilled Laborer 2 1 79.70
c. Laborer 4 1 61.44

Sub - Total for A


Name and Capacity No of Units No. of Hours Hourly Rate

B. Equipment

a. Backhoe (0.80 cu.m.) 1 0.60 1,537.00


b. Plate Compactor (5 Hp) 1 0.50 123.00
c. Water Truck (1000 gal.) 1 0.15 1,065.00
Minor Tools (10 % of Labor)

Sub - Total for B


C. Total (A + B)
D. Output per hour = 1.00 l.m.
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost

F. Materials

a. Portland Cement bag 1.242 220.00


b. Sand cu.m. 0.070 850.00
c. Sand Bedding cu.m. 0.149 850.00

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G
I. Contractor's Profit (CP) 8% of G
J. Value Added Tax (VAT) 12% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
Item No./Description : 504(2)e Removing, Cleaning and Re-laying Salvaged Culvert Pipe (48" dia.) - 1220
Unit of Measurement : l.m.
Output per hour : 0.75

Designation No. of Person No. of Hours Hourly Rate

A. Labor

a. Construction Foreman 1 1 109.19


b. Skilled Laborer 2 1 79.70
c. Laborer 4 1 61.44

Sub - Total for A


Name and Capacity No of Units No. of Hours Hourly Rate

B. Equipment

a. Backhoe (0.80 cu.m.) 1 0.60 1,537.00


b. Plate Compactor (5 Hp) 1 0.50 123.00
c. Water Truck (1000 gal.) 1 0.15 1,065.00
Minor Tools (10 % of Labor)

Sub - Total for B


C. Total (A + B)
D. Output per hour = 0.75 l.m.
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost

F. Materials

a. Portland Cement bag 1.404 220.00


b. Sand cu.m. 0.080 850.00
c. Sand Bedding cu.m. 0.170 850.00

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G
I. Contractor's Profit (CP) 8% of G
J. Value Added Tax (VAT) 12% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 504(3)a Cleaning Culvert Pipe in place (610mm dia.) - Half Silted
Unit of Measurement : l.m.
Output per hour : 8.00

Designation No. of Person No. of Hours Hourly Rate

A. Labor

a. Construction Foreman 1 1 109.19


b. Skilled Laborer 2 1 79.70
c. Laborer 4 1 61.44

Sub - Total for A


Name and Capacity No of Units No. of Hours Hourly Rate

B. Equipment

a. Cargo Truck (10 T) 1 1 1,102.00


b. Steel Wheel with Nylon Rope l.s. 300.00
c. Improvised Bamboo with Bucket l.s. 200.00
Minor Tools (10% of Labor)

Sub - Total for B


C. Total (A + B)
D. Output per hour = 8.00 l.m.
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost

F. Materials

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G
I. Contractor's Profit (CP) 8% of G
J. Value Added Tax (VAT) 12% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
Item No./Description : 504(3)b Cleaning Culvert Pipe in place (760mm dia.) - Half Silted
Unit of Measurement : l.m.
Output per hour : 5.25

Designation No. of Person No. of Hours Hourly Rate

A. Labor

a. Construction Foreman 1 1 109.19


b. Skilled Laborer 2 1 79.70
c. Laborer 4 1 61.44

Sub - Total for A


Name and Capacity No of Units No. of Hours Hourly Rate

B. Equipment

a. Cargo Truck (10 T) 1 1 1,102.00


b. Steel Wheel with Nylon Rope l.s. 300.00
c. Improvised Bamboo with Bucket l.s. 200.00
Minor Tools (10% of Labor)

Sub - Total for B


C. Total (A + B)
D. Output per hour = 5.25 l.m.
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost

F. Materials

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G
I. Contractor's Profit (CP) 8% of G
J. Value Added Tax (VAT) 12% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
Amount

109.19
159.40
245.76

514.35
Amount

768.50
61.50
51.44

881.44
1,395.79

620.35
Amount

170.28
37.40
950.00
74.80

1,232.48
1,852.83
166.75
148.23
260.14
2,427.95
Amount

109.19
159.40
245.76

514.35
Amount

768.50
61.50
51.44

881.44
1,395.79

697.89
Amount

201.96
44.20
1,750.00
91.80

2,087.96
2,785.85
250.73
222.87
391.13
3,650.58
Amount

109.19
159.40
245.76

514.35
Amount

768.50
61.50
51.44

881.44
1,395.79

797.59
Amount

237.60
51.85
2,170.00
108.80

2,568.25
3,365.84
302.93
269.27
472.56
4,410.60
Amount

109.19
159.40
245.76

514.35
Amount

768.50
61.50
51.44

881.44
1,395.79

930.52
Amount

273.24
59.50
2,900.00
126.65

3,359.39
4,289.91
386.09
343.19
602.30
5,621.50
Amount

109.19
159.40
245.76

514.35
Amount

768.50
61.50
51.44

881.44
1,395.79

1,116.63
Amount

308.88
68.00
3,800.00
144.50

4,321.38
5,438.01
489.42
435.04
763.50
7,125.97
Amount

109.19
159.40
245.76

514.35
Amount

768.50
61.50
51.44

881.44
1,395.79

1,395.79
Amount

376.20
82.45
6,175.00
178.50

6,812.15
8,207.94
738.71
656.63
1,152.39
10,755.68
Amount

109.19
245.76

354.95
Amount

61.50
35.50

97.00
451.95

361.56
Amount

180.00
331.50
550.00
241.50

1,303.00
1,664.56
149.81
133.16
233.70
2,181.23
Amount

109.19
245.76

354.95
Amount

35.50

35.50
390.45

312.36
Amount

198.00
331.50
550.00

1,079.50
1,391.86
125.27
111.35
195.42
1,823.89
Amount

109.19
245.76

354.95
Amount

123.00
35.50

158.50
513.45

410.76
Amount

1,035.00

1,035.00
1,445.76
130.12
115.66
202.98
1,894.52

Amount

Amount

Direct Cost
Amount

109.19
159.40
245.76

514.35
Amount

86.00
109.88
74.44
97.75
53.25
51.44

472.75
987.10

197.42
Amount

288.20
51.00
78.00
1,930.00
45.59
1,765.92
67.92
93.00
250.00
0.90

4,570.53
4,767.95
429.12
381.44
669.42
6,247.92
Amount

54.60
39.85
30.72

125.17
Amount

12.52

12.52
137.68

137.68
Amount

4,700.00

4,700.00
4,837.68
435.39
387.01
679.21
6,339.30
Amount

54.60
39.85
30.72

125.17
Amount

12.52

12.52
137.68

137.68
Amount

5,700.00

5,700.00
5,837.68
525.39
467.01
819.61
7,649.70
Amount

109.19
79.70
61.44

250.33
Amount

109.88
391.00

500.88
751.21

3,004.82
Amount

3,002.74
59.71
1,841.28
4.59

4,908.32
7,913.14
712.18
633.05
1,111.00
10,369.38
Amount

109.19
79.70
61.44

250.33
Amount

109.88
391.00

500.88
751.21

6,009.64
Amount

6,099.17
152.35
1,998.72
7.74

8,257.98
14,267.62
1,284.09
1,141.41
2,003.17
18,696.29
Amount

109.19
159.40
245.76

514.35
Amount

768.50
480.60
266.25
51.44

1,566.79
2,081.14

693.71
Amount

0.00
693.71
62.43
55.50
97.40
909.04
Amount

109.19
159.40
245.76

514.35
Amount

768.50
480.60
266.25
51.44

1,566.79
2,081.14

832.45
Amount

0.00
832.45
74.92
66.60
116.88
1,090.85
Amount

109.19
159.40
245.76

514.35
Amount

768.50
480.60
266.25
51.44

1,566.79
2,081.14

1,040.57
Amount

0.00
1,040.57
93.65
83.25
146.10
1,363.56
m

Amount

109.19
159.40
245.76

514.35

Amount

768.50
480.60
266.25
51.44

1,566.79
2,081.14

1,040.57
Amount

0.00
1,040.57
93.65
83.25
146.10
1,363.56
Amount

109.19
159.40
245.76

514.35
Amount

768.50
480.60
266.25
51.44

1,566.79
2,081.14

1,387.42
Amount

0.00
1,387.42
124.87
110.99
194.79
1,818.08
Amount

109.19
159.40
245.76

514.35
Amount

922.20
61.50
159.75
51.44

1,194.89
1,709.24

1,139.49
Amount

170.28
37.40
74.80

282.48
1,421.97
127.98
113.76
199.64
1,863.35
Amount

109.19
159.40
245.76

514.35
Amount

922.20
61.50
159.75
51.44

1,194.89
1,709.24

1,367.39
Amount

201.96
44.20
91.80

337.96
1,705.35
153.48
136.43
239.43
2,234.69
Amount

109.19
159.40
245.76

514.35
Amount

922.20
61.50
159.75
51.44

1,194.89
1,709.24

1,709.24
Amount

237.60
51.85
108.80

398.25
2,107.49
189.67
168.60
295.89
2,761.65
mm

Amount

109.19
159.40
245.76

514.35

Amount

922.20
61.50
159.75
51.44

1,194.89
1,709.24

1,709.24
Amount

273.24
59.50
126.65

459.39
2,168.63
195.18
173.49
304.47
2,841.77
Amount

109.19
159.40
245.76

514.35
Amount

922.20
61.50
159.75
51.44

1,194.89
1,709.24

2,278.98
Amount

308.88
68.00
144.50

521.38
2,800.36
252.03
224.03
393.17
3,669.59
Amount

109.19
159.40
245.76

514.35
Amount

1,102.00
300.00
200.00
51.44

1,653.44
2,167.79

270.97
Amount

0.00
270.97
24.39
21.68
38.04
355.08
Amount

109.19
159.40
245.76

514.35
Amount

1,102.00
300.00
200.00
51.44

1,653.44
2,167.79

412.91
Amount

0.00
412.91
37.16
33.03
57.97
541.08
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 504(3)c Cleaning Culvert Pipe in place (910mm dia.) - Half
Unit of Measurement : Silted l.m.
Output per hour : 3.75

Designation No. of Person No. of Hours Hourly Rate

A. Labor

a. Construction Foreman 1 1 109.19


b. Skilled Laborer 2 1 79.70
c. Laborer 4 1 61.44

Sub - Total for A


Name and Capacity No of Units No. of Hours Hourly Rate

B. Equipment

a. Cargo Truck (10 T) 1 1 1,102.00


Minor Tools (10% of Labor)

Sub - Total for B


C. Total (A + B)
D. Output per hour = 3.75 l.m.
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost

F. Materials

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G
I. Contractor's Profit (CP) 8% of G
J. Value Added Tax (VAT) 12% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 504(3)d Cleaning Culvert Pipe in place (1070mm dia.) - Half
Unit of Measurement : Silted l.m.
Output per hour : 2.75

Designation No. of Person No. of Hours Hourly Rate

A. Labor

a. Construction Foreman 1 1 109.19


b. Skilled Laborer 2 1 79.70
c. Laborer 4 1 61.44

Sub - Total for A


Name and Capacity No of Units No. of Hours Hourly Rate

B. Equipment

a. Cargo Truck (10 T) 1 1 1,102.00


Minor Tools (10% of Labor)

Sub - Total for B


C. Total (A + B)
D. Output per hour = 2.75 l.m.
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost

F. Materials

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G
I. Contractor's Profit (CP) 8% of G
J. Value Added Tax (VAT) 12% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 504(3)e Cleaning Culvert Pipe in place (1220mm dia.) - Half Silted
Unit of Measurement : l.m.
Output per hour : 2.00

Designation No. of Person No. of Hours Hourly Rate

A. Labor

a. Construction Foreman 1 1 109.19


b. Skilled Laborer 2 1 79.70
c. Laborer 4 1 61.44

Sub - Total for A


Name and Capacity No of Units No. of Hours Hourly Rate

B. Equipment

a. Cargo Truck (10 T) 1 1 1,102.00


Minor Tools (10% of Labor)

Sub - Total for B


C. Total (A + B)
D. Output per hour = 2.00 l.m.
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost

F. Materials

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G
I. Contractor's Profit (CP) 8% of G
J. Value Added Tax (VAT) 12% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 504(3)f Cleaning Culvert Pipe in place (1520mm dia.) - Half Silted
Unit of Measurement : l.m.
Output per hour : 1.50

Designation No. of Person No. of Hours Hourly Rate

A. Labor

a. Construction Foreman 1 1 109.19


b. Skilled Laborer 2 1 79.70
c. Laborer 4 1 61.44

Sub - Total for A


Name and Capacity No of Units No. of Hours Hourly Rate

B. Equipment

a. Cargo Truck (10 T) 1 1 1,102.00


Minor Tools (10% of Labor)

Sub - Total for B


C. Total (A + B)
D. Output per hour = 1.50 l.m.
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost

F. Materials

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G
I. Contractor's Profit (CP) 8% of G
J. Value Added Tax (VAT) 12% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 504(4) Reconditioning Drainage Structures


Unit of Measurement : ea.
Output : 1.00

Designation No. of Person No. of Hours Hourly Rate

A. Labor

a. Construction Foreman 1 0.50 109.19


b. Skilled Laborer 1 0.50 79.70
c. Laborer 2 0.50 61.44

Sub - Total for A


Name and Capacity No of Units No. of Hours Hourly Rate

B. Equipment

a. Cargo Truck (10 T) 1 0.25 1,102.00


b. Bamboo with Bucket - 4 uses 1 1 200.00
Minor Tools (10% of Labor)

Sub - Total for B


C. Total (A + B)
D. Output = 1.00 ea.
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost

F. Materials

* If some repair is needed, component materials


required and corresponding man-hour will be
added to DUPA

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G
I. Contractor's Profit (CP) 8% of G
J. Value Added Tax (VAT) 12% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 505(1) Riprap (Class A)


Unit of Measurement : cu.m.
Output per hour : 1.50

Designation No. of Person No. of Hours Hourly Rate


A. Labor

a. Construction Foreman 1 1 109.19


b. Skilled Laborer 2 1 79.70
c. Laborer 8 1 61.44

Sub - Total for A


Name and Capacity
No of Units No. of Hours Hourly Rate
B. Equipment

Minor Tools (5% of Labor)

Sub - Total for B Total (A + B)


C.
Output per hour = 1.50 cu.m.
Direct Unit Cost (C ÷ D)
Name and Specification
Materials Unit Quantity Unit Cost

a. Boulders (15 - 25 kg.) Miscellaneous (1% of Materials) cu.m. 1.05 920.00

Sub - Total for F


Direct Unit Cost (E + F)
Overhead, Contingencies & Miscellaneous (OCM) 9% of G
Contractor's Profit (CP) 8% of G
Value Added Tax (VAT) 12% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 505(2) Riprap (Class B)


Unit of Measurement : cu.m.
Output per hour : 1.25

Designation No. of Person No. of Hours Hourly Rate


A. Labor

a. Construction Foreman 1 1 109.19


b. Skilled Laborer 2 1 79.70
c. Laborer 4 1 61.44

Sub - Total for A


Name and Capacity
No of Units No. of Hours Hourly Rate
B. Equipment

a. Backhoe (Wheel Type 0.28 cu.m.) Minor Tools (5% of Labor) 1 0.50 840.00

Sub - Total for B Total (A + B)


C.
Output per hour = 1.25 cu.m.
Direct Unit Cost (C ÷ D)
Name and Specification
Materials Unit Quantity Unit Cost

a. Boulders (30 - 70 kg.) Miscellaneous (1% of Materials) cu.m. 1.05 810.00

Sub - Total for F


Direct Unit Cost (E + F)
Overhead, Contingencies & Miscellaneous (OCM) 9% of G
Contractor's Profit (CP) 8% of G
Value Added Tax (VAT) 12% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 505(3) Riprap (Class C)


Unit of Measurement : cu.m.
Output per hour : 1.00

Designation No. of Person No. of Hours Hourly Rate


A. Labor

a. Construction Foreman 1 1 109.19


b. Skilled Laborer 2 1 79.70
c. Laborer 4 1 61.44

Sub - Total for A


Name and Capacity
No of Units No. of Hours Hourly Rate
B. Equipment

c. Backhoe (Wheel Type 0.28 cu.m.) Minor Tools (5% of Labor) 1 0.75 840.00

Sub - Total for B Total (A + B)


C.
Output per hour = 1.00 cu.m.
Direct Unit Cost (C ÷ D)
Name and Specification
Materials Unit Quantity Unit Cost

a. Boulders (50 - 100 kg.) Miscellaneous (1% of Materials) cu.m. 1.05 740.00

Sub - Total for F


Direct Unit Cost (E + F)
Overhead, Contingencies & Miscellaneous (OCM) 9% of G
Contractor's Profit (CP) 8% of G
Value Added Tax (VAT) 12% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 505(4) Riprap (Class D)


Unit of Measurement : cu.m.
Output per hour : 0.75

Designation No. of Person No. of Hours Hourly Rate


A. Labor

a. Construction Foreman 1 1 109.19


b. Skilled Laborers 2 1 79.70
c. Laborers 4 1 61.44

Sub - Total for A


Name and Capacity
No of Units No. of Hours Hourly Rate
B. Equipment

a. Backhoe (Wheel Type 0.28 cu.m.) Minor Tools (5% of Labor) 1 1.00 840.00

Sub - Total for B Total (A + B)


C.
Output per hour = 0.75 cu.m.
Direct Unit Cost (C ÷ D)
Name and Specification
Materials Unit Quantity Unit Cost

a. Boulders (100 - 200 kg.) Miscellaneous (1% of Materials) cu.m. 1.05 650.00

Sub - Total for F


Direct Unit Cost (E + F)
Overhead, Contingencies & Miscellaneous (OCM) 9% of G
Contractor's Profit (CP) 8% of G
Value Added Tax (VAT) 12% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 505(5) Grouted Riprap (Class A)


Unit of Measurement : cu.m.
Output per hour : 1.25

Designation No. of Person No. of Hours Hourly Rate


A. Labor

a. Construction Foreman 1 1 109.19


b. Skilled Laborer 2 1 79.70
c. Laborer 8 1 61.44

Sub - Total for A


Name and Capacity
No of Units No. of Hours Hourly Rate

B. Equipment

a. One Bagger Mixer 1 1 172.00


b. Water Truck (1000 gal.) 1 0.05 1,065.00
Minor Tools (5% of Labor)

Sub - Total for B Total (A + B)


C.
D. Output per hour = 1.25 cu.m.
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost
F. Materials

a. Cement bag 3.00 220.00


b. Sand cu.m. 0.25 850.00
c. Gravel Fill cu.m. 0.015 650.00
d. Weep Holes (PVC) l.m. 0.30 144.67
e. Filter Cloth sq.m. 0.015 275.00
f. Boulders (15 - 25 kg.) cu.m. 1.05 920.00
Miscellaneous (1% of Materials)

Sub - Total for F


Direct Unit Cost (E + F)
Overhead, Contingencies & Miscellaneous (OCM) 9% of G
Contractor's Profit (CP) 8% of G
Value Added Tax (VAT) 12% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 505(6) Grouted Riprap (Class B)


Unit of Measurement : cu.m.
Output per hour : 1.00

Designation No. of Person No. of Hours Hourly Rate


A. Labor

a. Construction Foreman 1 1 109.19


b. Skilled Laborer 2 1 79.70
c. Laborer 4 1 61.44

Sub - Total for A


Name and Capacity
No of Units No. of Hours Hourly Rate
B. Equipment

a. One Bagger Mixer 1 1 172.00


b. Water Truck (1000 gal.) 1 0.05 1,065.00
c. Backhoe (Wheel Type 0.28 cu.m.) 1 0.50 840.00
Minor Tools (5% of Labor)

Sub - Total for B Total (A + B)


C.
D. Output per hour = 1.00 cu.m.
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost
F. Materials

a. Cement bag 2.50 220.00


b. Sand cu.m. 0.21 850.00
c. Gravel Fill cu.m. 0.015 650.00
d. Weep Holes (PVC) l.m. 0.30 144.67
e. Filter Cloth sq.m. 0.015 275.00
f. Boulders (30 - 70 kg.) cu.m. 1.05 810.00
Miscellaneous (1% of Materials)

Sub - Total for F


Direct Unit Cost (E + F)
Overhead, Contingencies & Miscellaneous (OCM) 9% of G
Contractor's Profit (CP) 8% of G
Value Added Tax (VAT) 12% of (G + H + I) (G + H + I + J)
Total Unit Cost
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 505(7) Grouted Riprap (Class C)


Unit of Measurement : cu.m.
Output per hour : 0.75

Designation No. of Person No. of Hours Hourly Rate


A. Labor

a. Construction Foreman 1 1 109.19


b. Skilled Laborer 2 1 79.70
c. Laborer 4 1 61.44

Sub - Total for A


Name and Capacity
No of Units No. of Hours Hourly Rate
B. Equipment

a. One Bagger Mixer 1 1 172.00


b. Water Truck (1000 gal.) 1 0.05 1,065.00
c. Backhoe (Wheel Type 0.28 cu.m.) 1 0.75 840.00
Minor Tools (5% of Labor)

Sub - Total for B Total (A + B)


C.
D. Output per hour = 0.75 cu.m.
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost
F. Materials

a. Cement bag 2.20 220.00


b. Sand cu.m. 0.18 850.00
c. Gravel Fill cu.m. 0.015 650.00
d. Weep Holes (PVC) l.m. 0.30 144.67
e. Filter Cloth sq.m. 0.015 275.00
f. Boulders (60 - 100 kg.) cu.m. 1.05 730.00
Miscellaneous (1% of Materials)

Sub - Total for F


Direct Unit Cost (E + F)
Overhead, Contingencies & Miscellaneous (OCM) 9% of G
Contractor's Profit (CP) 8% of G
Value Added Tax (VAT) 12% of (G + H + I) (G + H + I + J)
Total Unit Cost
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 505(8) Grouted Riprap (Class D)


Unit of Measurement : cu.m.
Output per hour : 0.50

Designation No. of Person No. of Hours Hourly Rate


A. Labor

a. Construction Foreman 1 1 109.19


b. Skilled Laborer 2 1 79.70
c. Laborer 4 1 61.44

Sub - Total for A


Name and Capacity
No of Units No. of Hours Hourly Rate
B. Equipment

a. One Bagger Mixer 1 1 172.00


b. Water Truck (1000 gal.) 1 0.05 1,065.00
c. Backhoe (Wheel Type 0.28 cu.m.) 1 1 840.00
Minor Tools (5% of Labor)

Sub - Total for B Total (A + B)


C.
D. Output per hour = 0.50 cu.m.
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost
F. Materials

a. Cement bag 1.80 220.00


b. Sand cu.m. 0.15 850.00
c. Gravel Fill cu.m. 0.015 650.00
d. Weep Holes (PVC) l.m. 0.30 144.67
e. Filter Cloth sq.m. 0.015 275.00
f. Boulders (100 - 200 kg.) cu.m. 1.05 650.00
Miscellaneous (1% of Materials)

Sub - Total for F


Direct Unit Cost (E + F)
Overhead, Contingencies & Miscellaneous (OCM) 9% of G
Contractor's Profit (CP) 8% of G
Value Added Tax (VAT) 12% of (G + H + I) (G + H + I + J)
Total Unit Cost
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 505(9) Filter Layer of Granular


Unit of Measurement : Material cu.m.
Output per hour : 1.00

Designation No. of Person No. of Hours Hourly Rate

A. Labor

a. Construction Foreman 1 1 109.19


b. Skilled Laborer 1 1 79.70
c. Laborer 2 1 61.44

Sub - Total for A


Name and Capacity No of Units No. of Hours Hourly Rate

B. Equipment

Minor Tools (10% of Labor)

Sub - Total for B


C. Total (A + B)
D. Output per hour = 1.00 cu.m.
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost

F. Materials

a. Granular Materials cu.m. 1.05 900.00

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G
I. Contractor's Profit (CP) 8% of G
J. Value Added Tax (VAT) 12% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 506 Stone Masonry


Unit of Measurement : cu.m.
Output per hour : 1.5625

Designation No. of Person No. of Hours Hourly Rate


A. Labor

a. Construction Foreman 1 1 109.19


b. Skilled Laborer 2 1 79.70
c. Laborer 8 1 61.44

Sub - Total for A


Name and Capacity
No of Units No. of Hours Hourly Rate
B. Equipment

a. One Bagger Mixer 1 1 172.00


b. Water Truck (1000 gal.) 1 0.05 1,065.00
c. Backhoe (Wheel Type 0.28 cu.m.) 1 0.10 840.00
Minor Tools (10% Labor)

Sub - Total for B Total (A + B)


C.
D. Output per hour =1.5625 cu.m.
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost
F. Materials

a. Cement bag 5.50 220.00


b. Sand cu.m. 0.30 850.00
c. Gravel Fill cu.m. 0.02 650.00
d. Weep Holes (PVC) l.m. 0.30 144.67
e. Filter Cloth sq.m. 0.015 275.00
f. Boulders cu.m. 1.05 920.00
Miscellaneous (1% of Materials)

Sub - Total for F


Direct Unit Cost (E + F)
Overhead, Contingencies & Miscellaneous (OCM) 9% of G
Contractor's Profit (CP) 8% of G
Value Added Tax (VAT) 12% of (G + H + I) (G + H + I + J)
Total Unit Cost
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 507 Rubble Concrete


Unit of Measurement : cu.m.
Output per hour : 1.40

Designation No. of Person No. of Hours Hourly Rate


A. Labor

a. Construction Foreman 1 1 109.19


b. Skilled Laborer 2 1 79.70
c. Laborer 8 1 61.44

Sub - Total for A


Name and Capacity
No of Units No. of Hours Hourly Rate
B. Equipment

a. One Bagger Mixer 1 1 172.00


b. Water Truck (1000 gal.) 1 0.05 1,065.00
c. Backhoe (Wheel Type 0.28 cu.m.) 1 0.10 840.00
Minor Tools (10% Labor)

Sub - Total for B Total (A + B)


C.
D. Output per hour = 1.40 cu.m.
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost
F. Materials

a. Cement bag 4.20 220.00


b. Sand cu.m. 0.2625 850.00
c. Gravel Fill cu.m. 0.02 650.00
d. Weep Holes (PVC) l.m. 0.30 144.67
e. Filter Cloth sq.m. 0.015 275.00
f. Boulders cu.m. 0.63 810.00
g. Gravel cu.m. 0.525 650.00
Miscellaneous (2% of Materials)
Note:
60% Boulder
50% Class "B" Concrete (w/ side forms only)

Sub - Total for F


Direct Unit Cost (E + F)
Overhead, Contingencies & Miscellaneous (OCM) 9% of G
Contractor's Profit (CP) 8% of G
Value Added Tax (VAT) 12% of (G + H + I) (G + H + I + J)
Total Unit Cost
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 508 Hand Laid Rock Embankment


Unit of Measurement : cu.m.
Output per hour : 3.125

Designation No. of Person No. of Hours Hourly Rate

A. Labor

a. Construction Foreman 1 1 109.19


b. Skilled Laborer 2 1 79.70
c. Laborer 8 1 61.44

Sub - Total for A


Name and Capacity No of Units No. of Hours Hourly Rate

B. Equipment

Minor Tools (10% of Labor)

Sub - Total for B


C. Total (A + B)
D. Output per hour = 3.125 cu.m.
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost

F. Materials

a. Boulders cu.m. 1.05 920.00

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G
I. Contractor's Profit (CP) 8% of G
J. Value Added Tax (VAT) 12% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 509(a) Timber Sheet Pile


Unit of Measurement : l.m.
Output per hour : 4.00

Designation No. of Person No. of Hours Hourly Rate

A. Labor

a. Construction Foreman 1 1 109.19


b. Skilled Laborer 1 1 79.70
c. Laborer 2 1 61.44

Sub - Total for A


Name and Capacity No of Units No. of Hours Hourly Rate

B. Equipment

a. Crawler Crane (45 T) 1 1 1,772.00


b. Drop Hammer (15 T) 1 1 200.00
Minor Tools (10% of Labor)

Sub - Total for B


C. Total (A + B)
D. Output per hour = 4.00 l.m.
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost

F. Materials

a. Timber Sheet Piles, ave. dia. 395mm bd.ft. 52.25 40.00


b. Coco Log - 2 uses m. 1.00 350.00
c. Lumber (Falsework) - 4 uses bd.ft. 16.00 40.00
d. Nail/Spike (1 kg./100 bd.ft. of Lumber) kg. 0.16 68.00

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G
I. Contractor's Profit (CP) 8% of G
J. Value Added Tax (VAT) 12% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
Item No./Description : 509(b.1) Steel Sheet Pile (Slope Protection)
Unit of Measurement : l.m.
Output per hour : 10.00

Designation No. of Person No. of Hours Hourly Rate


A. Labor

a. Construction Foreman 1 1 109.19


b. Skilled Laborer 2 1 79.70
c. Laborer 4 1 61.44

Sub - Total for A


Name and Capacity
No of Units No. of Hours Hourly Rate
B. Equipment

a. Crawler Crane (36 - 40 T) 1 1 1,729.00


b. Vibro Hammer (Hydraulic Operated) 1 1 1,800.00
c. Welding Machine (Gas Operated) 1 0.25 371.00
d. Cutting Outfit 1 0.25 45.45

Sub - Total for B Total (A + B)


C.
D. Output per hour = 10.00 l.m.
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost
F. Materials

a. Steel Sheet Piles (48 kg./l.m.) kg. 48.00 48.00


Miscellaneous (3% of Materials)

Sub - Total for F


Direct Unit Cost (E + F)
Overhead, Contingencies & Miscellaneous (OCM) 9% of G
Contractor's Profit (CP) 8% of G
Value Added Tax (VAT) 12% of (G + H + I) (G + H + I + J)
Total Unit Cost
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 509(b.2) Steel Sheet Pile (for Cofferdaming)


Unit of Measurement : l.m.
Output per hour : 10.00

Designation No. of Person No. of Hours Hourly Rate

A. Labor

a. Construction Foreman 1 1 109.19


b. Skilled Laborer 2 1 79.70
c. Laborer 4 1 61.44

Sub - Total for A


Name and Capacity No of Units No. of Hours Hourly Rate

B. Equipment

a. Crawler Crane (36 - 40 T) 1 1 1,729.00


b. Vibro Hammer (Hydraulic Operated) 1 1 1,800.00
c. Welding Machine 1 0.25 391.00
d. Cutting Outfit 1 0.25 45.45
e. Water Pump, 100mm suction diameter 1 1 266.25

Sub - Total for B


C. Total (A + B)
D. Output per hour = 10.00 l.m.
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost

F. Materials

a. Steel Sheet Piles (48 kg./l.m.) kg. 48.00 48.00


b. Structural Steel (Walling, Bracing, kg. 4.80 48.00
Diagonal etc.)
c. (Miscellaneous 1% of Materials)

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G
I. Contractor's Profit (CP) 8% of G
J. Value Added Tax (VAT) 12% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
Item No./Description : 509(c) Concrete Sheet Pile, furnished and driven
Unit of Measurement : l.m.
Output per hour : 1.20

Designation No. of Person No. of Hours Hourly Rate

A. Labor

a. Construction Foreman 1 1 109.19


b. Skilled Laborer 4 1 79.70
c. Laborer 6 1 61.44
Formworks
b. Skilled Laborer 2 1 79.70
c. Laborer 4 1 61.44

Sub - Total for A


Name and Capacity No of Units No. of Hours Hourly Rate

B. Equipment

a. Crawler Crane (45 T) 1 0.10 1,772.00


b. One Bagger Mixer 1 0.40 172.00
c. Concrete Vibrator 1 0.15 148.88
d. Water Truck (1000 gal.) 1 0.03 1,065.00
e. Bar Cutter 1 0.03 219.75
f. Bar Bender 1 0.03 351.50
g. Drop Hammer 1 0.10 200.00
h. Jack Hammer 1 0.10 514.31
i. Air Compressor (103 Hp) 1 0.10 675.00
j. Plate Compactor (5 Hp) 1 0.03 123.00
Minor Tools (5% of Labor)

Sub - Total for B


C. Total (A + B)
D. Output per hour = 1.20 l.m.
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost

F. Materials

a. Reinforcing Steel Bar kg. 28.11 40.00


b. Cement bag 1.44 220.00
c. Sand cu.m. 0.08 850.00
d. Gravel cu.m. 0.15 650.00
e. Marine Plywood, 1/2" x 4' x 8' pc. 0.15 700.00
f. Lumber, 2' x 2' bd.ft. 5.90 40.00
g. # 16 GI Tie Wire (2% of RSB) kg. 0.562 47.00
h. Assorted CWN (1 kg./100 bd.ft. of Lumber) kg. 0.059 68.00
Casting Bed
a. Ready Mix Concrete cu.m 0.030 2,840.00
b. Coco Lumber - 4 uses bd.ft. 1.500 20.00
c. Base Course cu.m 0.030 530.00

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G
I. Contractor's Profit (CP) 8% of G
J. Value Added Tax (VAT) 12% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
Item No./Description : 510(1) Bed Course Granular Material
Unit of Measurement : cu.m. in-place
Output per hour : 1.25

Designation No. of Person No. of Hours Hourly Rate

A. Labor

a. Construction Foreman 1 1 109.19


b. Laborer 4 1 61.44

Sub - Total for A


Name and Capacity No of Units No. of Hours Hourly Rate

B. Equipment

a. Plate Compactor 1 1 123.00


Minor Tools (10% of Labor)

Sub - Total for B


C. Total (A + B)
D. Output per hour = 1.25 cu.m. in-place
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost

F. Materials

a. Aggregate Subbase Course cu.m. 1.15 580.00


(w/ 15% Shrinkage Factor)

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G
I. Contractor's Profit (CP) 8% of G
J. Value Added Tax (VAT) 12% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 510(2) Concrete Slope Protection


Unit of Measurement : cu.m. in-place
Output per hour : 1.00

Designation No. of Person No. of Hours Hourly Rate

A. Labor

a. Construction Foreman 1 1 109.19


b. Skilled Laborer 4 1 79.70
c. Laborer 8 1 61.44
Installation of Formworks & Rebars
a. Skilled Laborer 2 1 79.70
b. Laborer 4 1 61.44

Sub - Total for A


Name and Capacity No of Units No. of Hours Hourly Rate

B. Equipment

a. One Bagger Mixer 1 1 172.00


b. Water Truck (1000 gal.) 1 0.05 1,065.00
c. Backhoe (Wheel Type 0.28 cu.m.) 1 0.10 840.00
d. Concrete Vibrator 1 0.05 148.88
e. Bar Cutter 1 0.05 219.75
f. Bar Bender 1 0.05 351.50
Minor Tools (10% Labor)

Sub - Total for B


C. Total (A + B)
D. Output per hour = 1.00 cu.m. in-place
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost

F. Materials

a. Cement bag 8.40 220.00


b. Sand cu.m. 0.50 850.00
c. Weep Holes (PVC) l.m. 0.21 144.67
d. Filter Cloth sq.m. 0.015 275.00
e. Gravel cu.m. 1 650.00
f. Granular Filter cu.m. 0.016 650.00
f. Reinforcing Steel Bar kg. * 26.03 40.00
g. Marine Plywood 1/2" x 4' x 8' - 4 uses pc. 0.48 700.00
h. Lumber - 4 uses bd.ft. 18.76 40.00
i. #16 GI Tie Wire (2% of RSB) kg. 0.521 47.00
j. Assorted CWN (1 kg./100 bd.ft. of Lumber) kg. 0.188 68.00

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G
I. Contractor's Profit (CP) 8% of G
J. Value Added Tax (VAT) 12% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
* Note: RSB quantity is variable based on approved plan.
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 511(1) Gabions


Unit of Measurement : cu.m.
Output per hour : 2.50

Designation No. of Person No. of Hours Hourly Rate

A. Labor

a. Construction Foreman 1 1 109.19


b. Skilled Laborer 2 1 79.70
c. Laborer 8 1 61.44

Sub - Total for A


Name and Capacity No of Units No. of Hours Hourly Rate

B. Equipment

Note: Exclude Excavation Works


Backhoe excluded, excavation should be separate as the
quantity is variable.

Sub - Total for B


C. Total (A + B)
D. Output per hour = 2.50 cu.m.
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost

F. Materials

a. Gabion Wire Mesh (1 x 1 x 2) pc. 0.50 2,900.00


(w/ complete accessories)
b. Boulders cu.m. 1.05 920.00

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G
I. Contractor's Profit (CP) 8% of G
J. Value Added Tax (VAT) 12% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 511(2) Mattresses


Unit of Measurement : cu.m.
Output per hour : 3.125

Designation No. of Person No. of Hours Hourly Rate

A. Labor

a. Construction Foreman 1 1 109.19


b. Skilled Laborer 2 1 79.70
c. Laborer 8 1 61.44

Sub - Total for A


Name and Capacity No of Units No. of Hours Hourly Rate

B. Equipment

Note: Exclude Excavation Works


Backhoe excluded, excavation should be separate as the
quantity is variable.

Sub - Total for B


C. Total (A + B)
D. Output per hour = 3.125 cu.m.
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost

F. Materials

a. Mattresses (6 x 2 x 0.3 ) pc. 0.28 5,000.00


(w/ complete accessories)
b. Boulders cu.m. 1.05 920.00

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G
I. Contractor's Profit (CP) 8% of G
J. Value Added Tax (VAT) 12% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 511(3) Filter Cloth


Unit of Measurement : sq.m.
Output per hour : 100.00

Designation No. of Person No. of Hours Hourly Rate


A. Labor

a. Construction Foreman 1 1 109.19


b. Skilled Laborer 2 1 79.70
c. Laborer 8 1 61.44

Sub - Total for A


Name and Capacity
No of Units No. of Hours Hourly Rate
B. Equipment

a. Cargo Truck (10 T)10.251,102.00

Sub - Total for B Total (A + B)


C.
Output per hour = 100.00 sq.m.
Direct Unit Cost (C ÷ D)
Name and Specification
Materials Unit Quantity Unit Cost

a. Filter Cloth sq.m. 1.05 275.00


Miscellaneous (5% of Materials)

Sub - Total for F


Direct Unit Cost (E + F)
Overhead, Contingencies & Miscellaneous (OCM) 9% of G
Contractor's Profit (CP) 8% of G
Value Added Tax (VAT) 12% of (G + H + I) (G + H + I + J)
Total Unit Cost
Amount

109.19
159.40
245.76

514.35
Amount

1,102.00
51.44

1,153.44
1,667.79

444.74
Amount

0.00
444.74
40.03
35.58
62.44
582.79
Amount

109.19
159.40
245.76

514.35
Amount

1,102.00
51.44

1,153.44
1,667.79

606.47
Amount

0.00
606.47
54.58
48.52
85.15
794.71
Amount

109.19
159.40
245.76

514.35
Amount

1,102.00
51.44

1,153.44
1,667.79

833.89
Amount

0.00
833.89
75.05
66.71
117.08
1,092.73
Amount

109.19
159.40
245.76

514.35
Amount

1,102.00
51.44

1,153.44
1,667.79

1,111.86
Amount

0.00
1,111.86
100.07
88.95
156.10
1,456.98
Amount

54.60
39.85
61.44

155.89
Amount

275.50
50.00
15.59

341.09
496.97

496.97
Amount

0.00
496.97
44.73
39.76
69.78
651.23
Amount

109.19
159.40
491.52

760.11
Amount

38.01

38.01
798.12

532.08
Amount

966.00
9.66

975.66
1,507.74
135.70
120.62
211.69
1,975.74
Amount

109.19
159.40
245.76

514.35
Amount

420.00
25.72

445.72
960.07

768.05
Amount

850.50
8.51

859.01
1,627.06
146.44
130.16
228.44
2,132.10
Amount

109.19
159.40
245.76

514.35
Amount

630.00
25.72

655.72
1,170.07

1,170.07
Amount

777.00
7.77

784.77
1,954.84
175.94
156.39
274.46
2,561.62
Amount

109.19
159.40
245.76

514.35
Amount

840.00
25.72

865.72
1,380.07

1,840.09
Amount

682.50
6.83

689.33
2,529.42
227.65
202.35
355.13
3,314.55

Amount

109.19
159.40
491.52

760.11

Amount

172.00
53.25
38.01

263.26
1,023.37

818.69
Amount

660.00
212.50
9.75
43.40
4.13
966.00
18.96

1,914.73
2,733.43
246.01
218.67
383.77
3,581.88
Amount

109.19
159.40
245.76

514.35
Amount

172.00
53.25
420.00
25.72

670.97
1,185.32

1,185.32
Amount

550.00
178.50
9.75
43.40
4.13
850.50
16.36

1,652.64
2,837.96
255.42
227.04
398.45
3,718.86
Amount

109.19
159.40
245.76

514.35
Amount

172.00
53.25
630.00
25.72

880.97
1,395.32

1,860.42
Amount

484.00
153.00
9.75
43.40
4.13
766.50
14.61

1,475.38
3,335.81
300.22
266.86
468.35
4,371.24
Amount

109.19
159.40
245.76

514.35
Amount

172.00
53.25
840.00
25.72

1,090.97
1,605.32

3,210.64
Amount

396.00
127.50
9.75
43.40
4.13
682.50
12.63

1,275.91
4,486.54
403.79
358.92
629.91
5,879.17
Amount

109.19
79.70
122.88

311.77
Amount

31.18

31.18
342.95

342.95
Amount

945.00

945.00
1,287.95
115.92
103.04
180.83
1,687.73
Amount

109.19
159.40
491.52

760.11
Amount

172.00
53.25
84.00
76.01

385.26
1,145.37

733.04
Amount

1,210.00
255.00
13.00
43.40
4.13
966.00
24.92

2,516.44
3,249.48
292.45
259.96
456.23
4,258.12
Amount

109.19
159.40
491.52

760.11
Amount

172.00
53.25
84.00
76.01

385.26
1,145.37

818.12
Amount

924.00
223.13
13.00
43.40
4.13
510.30
341.25
36.72

2,095.92
2,914.04
262.26
233.12
409.13
3,818.56
Amount

109.19
159.40
491.52

760.11
Amount

76.01

76.01
836.12

267.56
Amount

966.00

966.00
1,233.56
111.02
98.68
173.19
1,616.46
Amount

109.19
79.70
122.88

311.77
Amount

1,772.00
200.00
31.18

2,003.18
2,314.95

578.74
Amount

2,090.00
175.00
160.00
10.88

2,435.88
3,014.62
271.32
241.17
423.25
3,950.35
Amount

109.19
159.40
245.76

514.35
Amount

1,729.00
1,800.00
92.75
11.36

3,633.11
4,147.46

414.75
Amount

2,304.00
69.12

2,373.12
2,787.87
250.91
223.03
391.42
3,653.22
Amount

109.19
159.40
245.76

514.35
Amount

1,729.00
1,800.00
97.75
11.36
266.25

3,904.36
4,418.71

441.87
Amount

2,304.00
230.40

25.34

2,559.74
3,001.62
270.15
240.13
421.43
3,933.32
Amount

109.19
318.80
368.64

159.40
245.76

1,201.79
Amount

177.20
68.80
22.33
31.95
6.59
10.55
20.00
51.43
67.50
3.69
60.09

520.13
1,721.92

1,434.93
Amount

1,124.40
316.80
68.00
97.50
105.00
236.00
26.41
4.01

85.20
7.50
15.90

2,086.73
3,521.66
316.95
281.73
494.44
4,614.78
Amount

109.19
245.76

354.95
Amount

123.00
35.50

158.50
513.45

410.76
Amount

667.00

667.00
1,077.76
97.00
86.22
151.32
1,412.29
Amount

109.19
318.80
491.52

159.40
245.76

1,324.67
Amount

172.00
53.25
84.00
7.44
10.99
17.58
132.47

477.72
1,802.39

1,802.39
Amount

1,848.00
425.00
30.38
4.13
650.00
10.40
1,041.20
84.00
187.60
24.49
12.78

4,317.98
6,120.37
550.83
489.63
859.30
8,020.13
Amount

109.19
159.40
491.52

760.11
Amount

0.00
760.11

304.04
Amount

1,450.00

966.00

2,416.00
2,720.04
244.80
217.60
381.89
3,564.35
Amount

109.19
159.40
491.52

760.11
Amount

0.00
760.11

243.24
Amount

1,400.00

966.00

2,366.00
2,609.24
234.83
208.74
366.34
3,419.14
Amount

109.19
159.40
491.52

760.11
Amount

275.50

275.50
1,035.61

10.36
Amount

288.75
14.44

303.19
313.54
28.22
25.08
44.02
410.87
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 600(1) Concrete Curb (Cast in place) - 0.45m x


Unit of Measurement : 0.15/0.20m l.m.
Output per hour : 17.50

Designation No. of Person No. of Hours Hourly Rate

A. Labor

a. Construction Foreman 1 1 109.19


b. Skilled Laborer 4 1 79.70
c. Laborer 8 1 61.44

Sub - Total for A


Name and Capacity No of Units No. of Hours Hourly Rate

B. Equipment

a. Concrete Vibrator 1 1 148.88


b. One Bagger Mixer 1 1 172.00
c. Water Truck (1000 gal.) 1 0.05 1,065.00
Minor Tools (10% of Labor)

Sub - Total for B


C. Total (A + B)
D. Output per hour = 17.50 l.m.
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost

F. Materials

a. Cement bag 0.72 220.00


b. Sand cu.m. 0.04 850.00
c. Gravel cu.m. 0.08 650.00
d. Plywood Marine, 1/2" thk. x 4' x 8 - 4 uses pc. 0.28 700.00
e. Form Lumber - 4 uses bd.ft. 12.16 40.00
f. Assorted CWN (1 kg./100 bd.ft. of Lumber) kg. 0.12 68.00

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G
I. Contractor's Profit (CP) 8% of G
J. Value Added Tax (VAT) 12% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 600(2) Concrete Gutter (Cast in place) - 0.50m x


Unit of Measurement : 0.15m l.m.
Output per hour : 17.50

Designation No. of Person No. of Hours Hourly Rate

A. Labor

a. Construction Foreman 1 1 109.19


b. Skilled Laborer 4 1 79.70
c. Laborer 8 1 61.44

Sub - Total for A


Name and Capacity No of Units No. of Hours Hourly Rate

B. Equipment

a. Concrete Vibrator 1 1 148.88


b. One Bagger Mixer 1 1 172.00
c. Water Truck (1000 gal.) 1 0.05 1,065.00
Minor Tools (10% of Labor)

Sub - Total for B


C. Total (A + B)
D. Output per hour = 17.50 l.m.
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost

F. Materials

a. Cement bag 0.72 220.00


b. Sand cu.m. 0.04 850.00
c. Gravel cu.m. 0.08 650.00
d. Good Lumber - 4 uses bd.ft. 6.56 40.00
e. Assorted CWN (1 kg./100 bd.ft. of Lumber) kg. 0.07 68.00

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G
I. Contractor's Profit (CP) 8% of G
J. Value Added Tax (VAT) 12% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 600(3) Concrete Curb and Gutter, Type A (Cast in place) - National
Unit of Measurement : Road l.m.
Output per hour : 10.30

Designation No. of Person No. of Hours Hourly Rate


A. Labor

a. Construction Foreman 1 1 109.19


b. Skilled Laborer 4 1 79.70
c. Laborer 8 1 61.44

Sub - Total for A


Name and Capacity
No of Units No. of Hours Hourly Rate
B. Equipment

a. Concrete Vibrator 1 1 148.88


b. One Bagger Mixer 1 1 172.00
c. Water Truck (1000 gal.) 1 0.05 1,065.00
Minor Tools (10% of Labor)

Sub - Total for B Total (A + B)


C.
D. Output per hour = 10.30 l.m.
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost
F. Materials

a. Cement bag 1.29 220.00


b. Sand cu.m. 0.07 850.00
c. Gravel cu.m. 0.14 650.00
d. Plywood Marine, 1/2" thk. x 4' x 8 - 4 uses pc. 0.24 700.00
e. Form Lumber - 4 uses bd.ft. 11.47 40.00
f. Assorted CWN (1 kg./100 bd.ft. of Lumber) kg. 0.11 68.00
Miscellaneous (2% of Materials)

Sub - Total for F


Direct Unit Cost (E + F)
Overhead, Contingencies & Miscellaneous (OCM) 9% of G
Contractor's Profit (CP) 8% of G
Value Added Tax (VAT) 12% of (G + H + I) (G + H + I + J)
Total Unit Cost
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 600(4) Concrete Curb (Precast)


Unit of Measurement : pc.
Output per hour : 4.00

Designation No. of Person No. of Hours Hourly Rate


A. Labor

a. Construction Foreman 1 1 109.19


b. Skilled Laborer 1 1 79.70
c. Laborer 1 1 61.44

Sub - Total for A


Name and Capacity
No of Units No. of Hours Hourly Rate
B. Equipment

a. Boom Truck 1 0.50 961.20


Minor Tools (10% of Labor)

Sub - Total for B Total (A + B)


C.
Output per hour = 4.00 pc.
Direct Unit Cost (C ÷ D)
Name and Specification
Materials Unit Quantity Unit Cost

a. Fabricated Concrete Curb Miscellaneous (5% of materials) l.m. 1.00 690.00

Sub - Total for F


Direct Unit Cost (E + F)
Overhead, Contingencies & Miscellaneous (OCM) 9% of G
Contractor's Profit (CP) 8% of G
Value Added Tax (VAT) 12% of (G + H + I) (G + H + I + J)
Total Unit Cost
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 600(5) Concrete Gutter (Precast)


Unit of Measurement : pc.
Output per hour : 4.00

Designation No. of Person No. of Hours Hourly Rate


A. Labor

a. Construction Foreman 1 1 109.19


b. Skilled Laborer 1 1 79.70
c. Laborer 1 1 61.44

Sub - Total for A


Name and Capacity
No of Units No. of Hours Hourly Rate
B. Equipment

a. Boom Truck 1 0.50 961.20


Minor Tools (10% of Labor)

Sub - Total for B Total (A + B)


C.
Output per hour = 4.00 pc.
Direct Unit Cost (C ÷ D)
Name and Specification
Materials Unit Quantity Unit Cost

a. Fabricated Concrete Gutter Miscellaneous (5% of materials) l.m. 1.00 680.00

Sub - Total for F


Direct Unit Cost (E + F)
Overhead, Contingencies & Miscellaneous (OCM) 9% of G
Contractor's Profit (CP) 8% of G
Value Added Tax (VAT) 12% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 600(6) Concrete Curb and Gutter (Precast)


Unit of Measurement : pc.
Output per hour : 3.00

Designation No. of Person No. of Hours Hourly Rate


A. Labor

a. Construction Foreman 1 1 109.19


b. Skilled Laborer 1 1 79.70
c. Laborer 1 1 61.44

Sub - Total for A


Name and Capacity
No of Units No. of Hours Hourly Rate
B. Equipment

a. Boom Truck 1 0.50 961.20


Minor Tools (10% of Labor)

Sub - Total for B Total (A + B)


C.
Output per hour = 3.00 pc.
Direct Unit Cost (C ÷ D)
Name and Specification
Materials Unit Quantity Unit Cost

a. Fabricated Concrete Curb and Gutter Miscellaneous (5% of materials) l.m. 1.00 1,750.00

Sub - Total for F


Direct Unit Cost (E + F)
Overhead, Contingencies & Miscellaneous (OCM) 9% of G
Contractor's Profit (CP) 8% of G
Value Added Tax (VAT) 12% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 601(a) Sidewalk (100mm thk.)


Unit of Measurement : sq.m.
Output per hour : 161.00

Designation No. of Person No. of Hours Hourly Rate

A. Labor

a. Construction Foreman 1 1 109.19


b. Skilled Laborer 4 1 79.70
c. Laborer 12 1 61.44

Sub - Total for A


Name and Capacity No of Units No. of Hours Hourly Rate

B. Equipment

a. Transit Mixer (5 cu.m.) 4 1 1,279.00


b. Concrete Vibrator 2 1 148.88
c. Batching Plant (30 cu.m.) 1 1 1,208.03
d. Payloader (1.50 cu.m.), LX80-2C 1 1 1,733.00
e. Concrete Screeder (5.5 Hp) 1 1 545.00
f. Water Truck (1000 gal.) 1 1 1,065.00
g. Concrete Saw, Blade Ø 14" (7.5 Hp) 1 1 167.38
Minor Tools (5% of Labor)

Sub - Total for B


C. Total (A + B)
D. Output per hour = 161.00 sq.m.
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost

F. Materials

a. Curing Compound lit. 0.29 28.00


b. Asphalt Sealant lit. 0.12 44.00
c. Forms l.m. 0.46 250.00
d. Sand cu.m. 0.055 850.00
e. Gravel cu.m. 0.10 650.00
f. Cement bag 0.95 220.00

Note : Bed Course excluded

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G
I. Contractor's Profit (CP) 8% of G
J. Value Added Tax (VAT) 12% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 601(b) Sidewalk (100mm thk.)


Unit of Measurement : sq.m.
Output per hour : 20.00

Designation No. of Person No. of Hours Hourly Rate

A. Labor

a. Construction Foreman 1 1 109.19


b. Skilled Laborer 4 1 79.70
c. Laborer 12 1 61.44

Sub - Total for A


Name and Capacity No of Units No. of Hours Hourly Rate

B. Equipment

a. One Bagger Mixer 1 1 172.00


b. Concrete Vibrator 2 1 148.88
c. Water Truck (1000 gal.) 1 0.125 1,065.00
d. Concrete Saw, Blade Ø 14" (7.5 Hp) 1 1 167.38
Minor Tools (5% of Labor)

Sub - Total for B


C. Total (A + B)
D. Output per hour = 20.00 sq.m.
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost

F. Materials

a. Curing Compound lit. 0.29 28.00


b. Asphalt Sealant lit. 0.12 44.00
c. Forms l.m. 0.46 250.00
d. Sand cu.m. 0.055 850.00
e. Gravel cu.m. 0.10 650.00
f. Cement bag 0.95 220.00

Note : Bed Course excluded

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G
I. Contractor's Profit (CP) 8% of G
J. Value Added Tax (VAT) 12% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 602(1)a Right-of-Way Monument


Unit of Measurement : ea.
Output per hour : 2.00

Designation No. of Person No. of Hours Hourly Rate

A. Labor

a. Construction Foreman 1 1 109.19


b. Skilled Laborer 1 1 79.70
c. Laborer 2 1 61.44

Sub - Total for A


Name and Capacity No of Units No. of Hours Hourly Rate

B. Equipment

a. Concrete Vibrator 1 0.20 148.88


b. Cargo Truck (10 T) 1 0.05 1,102.00
Minor Tools (10% of Labor)

Sub - Total for B


C. Total (A + B)
D. Output per hour = 2.00 ea.
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost

F. Materials

a. Concrete Class "A" cu.m. 0.03 3,538.78


b. Reinforcing Steel Bar, Grade 40 kg. 7.15 40.00
c. Plywood, 1/2" x 4' x 8' - 4 uses pc. 0.22 700.00
d. Form Lumber, Good - 4 uses bd.ft. 13.53 40.00
e. Reflectorized Paint, Marker lit. 0.10 475.00
f. # 16 Tie Wire (2% of RSB) kg. 0.14 47.00
g. Assorted CWN (1 kg./100 bd.ft. of Lumber) kg. 0.14 68.00

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G
I. Contractor's Profit (CP) 8% of G
J. Value Added Tax (VAT) 12% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 602(1)b Right-of-Way Monument (Precast)


Unit of Measurement : ea.
Output per hour : 4.00

Designation No. of Person No. of Hours Hourly Rate

A. Labor

a. Construction Foreman 1 1 109.19


b. Skilled Laborer 1 1 79.70
c. Laborer 2 1 61.44

Sub - Total for A


Name and Capacity No of Units No. of Hours Hourly Rate

B. Equipment

a. Cargo Truck (10 T) 1 0.05 1,102.00


Minor Tools (10% of Labor)

Sub - Total for B


C. Total (A + B)
D. Output per hour = 4.00 ea.
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost

F. Materials

a. Fabricated Right-of-Way Monument ea. 1 3,320.00


(delivered at site)

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G
I. Contractor's Profit (CP) 8% of G
J. Value Added Tax (VAT) 12% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 602(2)a Maintenance Marker Post


Unit of Measurement : ea.
Output per hour : 2.00

Designation No. of Person No. of Hours Hourly Rate

A. Labor

a. Construction Foreman 1 1 109.19


b. Skilled Laborer 1 1 79.70
c. Laborer 2 1 61.44

Sub - Total for A


Name and Capacity No of Units No. of Hours Hourly Rate

B. Equipment

a. Concrete Vibrator 1 0.20 148.88


b. Cargo Truck (10 T) 1 0.05 1,102.00
Minor Tools (10% of Labor)

Sub - Total for B


C. Total (A + B)
D. Output per hour = 2.00 ea.
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost

F. Materials

a. Concrete Class "A" cu.m. 0.03 3,400.00


b. Reinforcing Steel Bar, Grade 40 kg. 7.00 40.00
c. Plywood, 1/2" x 4' x 8' - 4 uses pc. 0.22 700.00
d. Form Lumber, Good - 4 uses bd.ft. 13.53 40.00
e. Reflectorized Paint, Marker lit. 0.10 475.00
f. # 16 Tie Wire (2% of RSB) kg. 0.14 47.00
g. Assorted CWN (1 kg./100 bd.ft. of Lumber) kg. 0.14 68.00

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G
I. Contractor's Profit (CP) 8% of G
J. Value Added Tax (VAT) 12% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 602(2)b Maintenance Marker Post (Precast)


Unit of Measurement : ea.
Output per hour : 4.00

Designation No. of Person No. of Hours Hourly Rate

A. Labor

a. Construction Foreman 1 1 109.19


b. Skilled Laborer 1 1 79.70
c. Laborer 2 1 61.44

Sub - Total for A


Name and Capacity No of Units No. of Hours Hourly Rate

B. Equipment

a. Cargo Truck (10 T) 1 0.05 1,102.00


Minor Tools (10% of Labor)

Sub - Total for B


C. Total (A + B)
D. Output per hour = 4.00 ea.
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost

F. Materials

a. Fabricated Maintenance Marker Post ea. 1 1,650.00


(delivered at site)

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G
I. Contractor's Profit (CP) 8% of G
J. Value Added Tax (VAT) 12% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 602(3)a Kilometer Post


Unit of Measurement : ea.
Output : 1.00

Designation No. of Person No. of Hours Hourly Rate

A. Labor

a. Construction Foreman 1 1.50 109.19


b. Skilled Laborer 1 1.50 79.70
c. Laborer 2 1.50 61.44

Sub - Total for A


Name and Capacity No of Units No. of Hours Hourly Rate

B. Equipment

a. Cargo Truck (10 T) 1 0.50 1,102.00


b. Concrete Vibrator 1 0.10 148.88
Minor Tools (10% of Labor)

Sub - Total for B


C. Total (A + B)
D. Output = 1.00 ea.
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost

F. Materials

a. Concrete Class "A" cu.m. 0.184 3,400.00


b. Reinforcing Steel Bar kg. 7.59 40.00
c. Plywood 1/2" x 4' x 8' - 2 uses pc. 0.604 700.00
d. Lumber - 2 uses bd.ft. 7.15 20.00
e. Portland Cement bag 0.775 220.00
f. Pebble cu.m. 0.044 900.00
g. Reflectorized Paint, Marker lit. 0.20 475.00
h. # 16 Tie Wire (2% of RSB) kg. 0.14 47.00
i. Assorted CWN (1 kg./100 bd.ft. of Lumber) kg. 0.07 68.00

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G
I. Contractor's Profit (CP) 8% of G
J. Value Added Tax (VAT) 12% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 602(3)b Kilometer Post (Precast)


Unit of Measurement : ea.
Output : 2.00

Designation No. of Person No. of Hours Hourly Rate

A. Labor

a. Construction Foreman 1 1.50 109.19


b. Skilled Laborer 1 1.50 79.70
c. Laborer 2 1.50 61.44

Sub - Total for A


Name and Capacity No of Units No. of Hours Hourly Rate

B. Equipment

a. Cargo Truck (10 T) 1 0.50 1,102.00


b. Concrete Vibrator 1 0.05 148.88
Minor Tools (10% of Labor)

Sub - Total for B


C. Total (A + B)
D. Output = 2.00 ea.
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost

F. Materials

a. Fabricated Kilometer Post ea. 1 4,150.00


b. Concrete Class "A" cu.m. 0.095 3,400.00
c. Reflectorized Paint, Marker lit. 0.20 475.00

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G
I. Contractor's Profit (CP) 8% of G
J. Value Added Tax (VAT) 12% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 602(4) Guide Post


Unit of Measurement : ea.
Output per hour : 50.00

Designation No. of Person No. of Hours Hourly Rate

Labor
Construction Foreman11109.19
Laborer2161.44

Sub - Total for A


Name and Capacity
No of Units No. of Hours Hourly Rate
B. Equipment

Minor Tools (10% of Labor)

Sub - Total for B Total (A + B)


C.
D. Output per hour = 50.00 ea.
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost
F. Materials

a. Guide Post (Portable) ea. 1 1,240.00


b. Post Reflector ea. 1 85.00
Miscellaneous (5% of Materials)

Sub - Total for F


Direct Unit Cost (E + F)
Overhead, Contingencies & Miscellaneous (OCM) 9% of G
Contractor's Profit (CP) 8% of G
Value Added Tax (VAT) 12% of (G + H + I) (G + H + I + J)
Total Unit Cost
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 603(1) Cable Wire Guardrail


Unit of Measurement : l.m.
Output per hour : 1.15

Designation No. of Person No. of Hours Hourly Rate

A. Labor

a. Construction Foreman 1 1 109.19


b. Skilled Laborer 2 1 79.70
c. Laborer 8 1 61.44

Sub - Total for A


Name and Capacity No of Units No. of Hours Hourly Rate

B. Equipment

a. One Bagger Mixer 1 1 172.00


b. Concrete Vibrator 1 1 148.88
c. Water Truck (1000 gal.) 1 0.10 1,065.00
d. Cargo Truck (5 T) 1 0.25 712.00
Minor Tools (10% of Labor)

Sub - Total for B


C. Total (A + B)
D. Output per hour = 1.15 l.m.
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost

F. Materials

a. Cement bag 4.18 220.00


b. Sand cu.m. 0.22 850.00
c. Gravel cu.m. 0.43 650.00
d. Guardrail Post set 0.27 *1,800.00
e. Galvanized Wire Rope (1.21 kg./m) kg. 4.92 186.44
f. Check Rope set 0.22 *750.00
g. Hook Bolt ea. 0.33 *350.00
h. Anchor Bracket unit 0.11 *1,200.00
i. Wire Mesh sq.m. 0.11 *295.00
j. Tension Fittings set 0.65 *1,000.00
Miscellaneous (5% of Materials)

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G
I. Contractor's Profit (CP) 8% of G
J. Value Added Tax (VAT) 12% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
* Tentative Canvass Price
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 603(3)a Metal Guardrails (Metal Beam) including Concrete Post
Unit of Measurement : l.m.
Output per hour : 4.20

Designation No. of Person No. of Hours Hourly Rate

A. Labor

a. Construction Foreman 1 1 109.19


b. Skilled Laborer 2 1 79.70
c. Laborer 4 1 61.44

Sub - Total for A


Name and Capacity No of Units No. of Hours Hourly Rate

B. Equipment

a. One Bagger Mixer 1 0.50 172.00


b. Concrete Vibrator 1 0.50 148.88
c. Water Truck (1000 gal.) 1 0.05 1,065.00
d. Cargo Truck (10 T) 1 0.25 1,102.00
Minor Tools (5 % of Labor)

Sub - Total for B


C. Total (A + B)
D. Output per hour = 4.20 l.m.
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost

F. Materials

a. Cement bag 0.33 220.00


b. Sand cu.m. 0.018 850.00
c. Gravel cu.m. 0.036 650.00
d. Metal Beam Guardrail l.m. 1 1,950.00
e. Plywood Marine, 1/2" thk. x 4' x 8' - 4 uses pc. 0.25 700.00
f. Lumber - 4 uses bd.ft. 8 40.00
g. Reinforcing Steel Bars, Grade 40 kg. 4 40.00
h. Tie Wire (2% of RSB) kg. 0.08 47.00
i. Assorted CWN (1 kg./100 bd.ft. of Lumber) kg. 0.08 68.00
j. Bolt, Nut & Washer 5/8" dia. x 9" pc. 0.50 28.00
k. Bolt, Nut & Washer 5/8" dia. x 1" pc. 2 21.00

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G
I. Contractor's Profit (CP) 8% of G
J. Value Added Tax (VAT) 12% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
Item No./Description : 603(3)b Metal Beam End Piece
Unit of Measurement : ea.
Output per hour : 6.00

Designation No. of Person No. of Hours Hourly Rate

A. Labor

a. Construction Foreman 1 1 109.19


b. Skilled Laborer 1 1 79.70
c. Laborer 2 1 61.44

Sub - Total for A


Name and Capacity No of Units No. of Hours Hourly Rate
B. Equipment

a. Cargo Truck (10 T) 1 1 1,102.00


Minor Tools (5% of Labor)

Sub - Total for B


C. Total (A + B)
D. Output per hour = 6.00 ea.
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost

F. Materials

a. Metal Guardrail End Piece ea. 1.00 1,350.00

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G
I. Contractor's Profit (CP) 8% of G
J. Value Added Tax (VAT) 12% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
Item No./Description : 603(4) Guardrail (Timber)
Unit of Measurement : l.m.
Output per hour : 5.00

Designation No. of Person No. of Hours Hourly Rate


A. Labor

a. Construction Foreman 1 1 109.19


b. Skilled Laborer 2 1 79.70
c. Laborer 4 1 61.44

Sub - Total for A


Name and Capacity
No of Units No. of Hours Hourly Rate
B. Equipment

a. Cargo Truck (10 T) Minor Tools (10% of Labor) 1 0.50 1,102.00

Sub - Total for B Total (A + B)


C.
D. Output per hour = 5.00 l.m.
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost
F. Materials

a. Lumber, 8" x 8" x 5.5' Treated Post (Tanguile) bd.ft. 14.67 90.00
b. Lumber, 3" x 8" Plank (Tanguile) - Untreated bd.ft. 6.67 55.00
c. Carriage Bolt, 1/2"Ø x 12" pc. 1.60 350.00
Miscellaneous (5% of Materials)

Note: Exclude Excavation Works

Sub - Total for F


Direct Unit Cost (E + F)
Overhead, Contingencies & Miscellaneous (OCM) 9% of G
Contractor's Profit (CP) 8% of G
Value Added Tax (VAT) 12% of (G + H + I) (G + H + I + J)
Total Unit Cost
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 604(1) Fencing (Barbed Wire)


Unit of Measurement : l.m.
Output per hour : 18.00

Designation No. of Person No. of Hours Hourly Rate


A. Labor

a. Construction Foreman 1 1 109.19


b. Skilled Laborer 1 1 79.70
c. Laborer 2 1 61.44

Sub - Total for A


Name and Capacity
No of Units No. of Hours Hourly Rate
B. Equipment

a. Welding Machine 1 0.10 391.00


Minor Tools (10% of Labor)

Sub - Total for B Total (A + B)


C.
Output per hour = 18.00 l.m.
Direct Unit Cost (C ÷ D)
Name and Specification
Materials Unit Quantity Unit Cost

3-Strand Galvanized Barbed Wire, Ga 12.5 l.m. kg. 1 15.00


50mmx50mmx6m Angle Bar pc. 0.52 48.00
Ga. 9 Twisted Wire Fastener 0.67 81.15
Miscellaneous (2% of Materials, Welding Rod & etc.)

Sub - Total for F


Direct Unit Cost (E + F)
Overhead, Contingencies & Miscellaneous (OCM) 9% of G
Contractor's Profit (CP) 8% of G
Value Added Tax (VAT) 12% of (G + H + I) (G + H + I + J)
Total Unit Cost
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 604(2) Fencing (Chain Link Fence Fabric)


Unit of Measurement : l.m.
Output per hour : 5.00

Designation No. of Person No. of Hours Hourly Rate


A. Labor

a. Construction Foreman 1 1 109.19


b. Skilled Laborer 2 1 79.70
c. Laborer 8 1 61.44

Sub - Total for A


Name and Capacity
No of Units No. of Hours Hourly Rate
B. Equipment

a. One Bagger Mixer 1 1 172.00


b. Concrete Vibrator 1 0.50 148.88
c. Water Truck (1000 gal.) 1 0.10 1,065.00
d. Welding Machine 1 0.50 391.00
Minor Tools (10% of Labor)

Sub - Total for B Total (A + B)


C.
D. Output per hour = 5.00 l.m.
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost
F. Materials

a. Cement bag 1.623 220.00


b. Sand cu.m. 0.085 850.00
c. Gravel, G1 cu.m. 0.171 650.00
d. Chainlink Fence, 4' l.m. 1 661.67
e. G.I. Pipe 2" dia. (corner or pull posts) pc. 0.03 1,500.00
f. G.I. Pipe 1 1/4" dia. (line post) pc. 0.12 1,140.00
g. G.I. Pipe 1 1/4" dia. (brace) pc. 0.50 1,140.00
h. Flat Bar, 3/16" x 3/4" (stretch bar) kg. 0.14 48.00
i. Plain Bar, 3/8" dia. (truss rod) kg. 0.30 40.00
j. Tension Wire, 0.177" dia. l.m. 2 134.44
Miscellaneous (5% of Materials)

Sub - Total for F


Direct Unit Cost (E + F)
Overhead, Contingencies & Miscellaneous (OCM) 9% of G
Contractor's Profit (CP) 8% of G
Value Added Tax (VAT) 12% of (G + H + I) (G + H + I + J)
Total Unit Cost
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 604(3) Fencing (Post)


Unit of Measurement : ea.
Output : 1.00

Designation No. of Person No. of Hours Hourly Rate

A. Labor

a. Construction Foreman 1 1.50 109.19


b. Skilled Laborer 2 1.50 79.70
c. Laborer 2 1.50 61.44

Sub - Total for A


Name and Capacity No of Units No. of Hours Hourly Rate

B. Equipment

a. One Bagger Mixer 1 0.75 172.00


b. Bar Cutter 1 0.50 219.75
c. Bar Bender 1 0.50 351.50
d. Water Truck (1000 gal.) 1 0.05 1,065.00
Minor Tools (10% of Labor)

Sub - Total for B


C. Total (A + B)
D. Output = 1.00 ea.
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost

F. Materials

a. Cement bag 2.105 220.00


b. Sand cu.m. 0.095 850.00
c. Gravel cu.m. 0.185 650.00
d. Reinforcing Steel Bar kg. 20.615 40.00
e. # 16 Tie Wire (2% of RSB) kg. 0.412 47.00
f. Plywood 1/4' x 4' x 8' - 2 uses pc. 0.760 350.00
g. Lumber - 2 uses bd.ft. 22.695 20.00
h. Assorted CWN (1 kg./100 bd.ft. of Lumber) kg. 0.227 68.00

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G
I. Contractor's Profit (CP) 8% of G
J. Value Added Tax (VAT) 12% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 604(4) Fencing (Gates) - (Height 3m. & Length 4.24m.)
Unit of Measurement : ea.
Output : 1.00

Designation No. of Person No. of Hours Hourly Rate

A. Labor

a. Construction Foreman 1 3 109.19


b. Skilled Laborer 1 3 79.70
c. Laborer 2 3 61.44

Sub - Total for A


Name and Capacity No of Units No. of Hours Hourly Rate

B. Equipment

a. Welding Machine 1 2 391.00


Minor Tools (10% of Labor)

Sub - Total for B


C. Total (A + B)
D. Output = 1.00 ea.
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost

F. Materials

a. 50 mm. Ø G.I. Pipe, Schedule 40 pc. 5 1,550.00


b. Cyclone Wire Galvanized 10' Gauge 10 l.m. 4.24 3,300.00
c. Aluminum Paint gal. 1.06 565.00
d. 6mm dia. Plain Bar kg. 1.607 40.00
e. Gate Lock/Hinge (12mm thk. Plate) kg. 9.743 48.00
b. Welding Rod (1 kg./2000 kg. of Steel) kg. 0.006 90.00

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G
I. Contractor's Profit (CP) 8% of G
J. Value Added Tax (VAT) 12% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 605(1)a Danger/Warning Signs (60cm Triangle)


Unit of Measurement : ea.
Output per hour : 1.00

Designation No. of Person No. of Hours Hourly Rate

A. Labor

a. Construction Foreman 1 1 109.19


b. Skilled Laborer 1 1 79.70
c. Laborer 2 1 61.44

Sub - Total for A


Name and Capacity No of Units No. of Hours Hourly Rate
B. Equipment

a. Cargo Truck (5 T) 1 0.25 712.00


Minor Tools (10 % of Labor)

Sub - Total for B


C. Total (A + B)
D. Output per hour = 1.00 ea.
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost

F. Materials

a. Portland Cement bag 0.48 220.00


b. Sand cu.m. 0.025 850.00
c. Gravel cu.m. 0.050 650.00
d. Form Lumber, Good - 4 uses bd.ft. 8 40.00
e. 3"Ø G.I. Pipe m. 3.10 530.00
f. Plate kg. 2 48.00
g. Bolts, 5mm Ø pc. 12 10.00
h. Sign Face, 3mm thk. Aluminum Sheet pc. 1 2,800.00
i. Assorted CWN (1 kg./100 bd.ft. of Lumber) kg. 0.08 68.00

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G
I. Contractor's Profit (CP) 8% of G
J. Value Added Tax (VAT) 12% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
Item No./Description : 605(1)b Danger/Warning Signs (90cm Triangle)
Unit of Measurement : ea.
Output per hour : 1.00

Designation No. of Person No. of Hours Hourly Rate

A. Labor

a. Construction Foreman 1 1 109.19


b. Skilled Laborer 1 1 79.70
c. Laborer 2 1 61.44

Sub - Total for A


Name and Capacity No of Units No. of Hours Hourly Rate
B. Equipment

a. Cargo Truck (5 T) 1 0.25 712.00


Minor Tools (10 % of Labor)

Sub - Total for B


C. Total (A + B)
D. Output per hour = 1.00 ea.
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost

F. Materials

a. Portland Cement bag 0.48 220.00


b. Sand cu.m. 0.025 850.00
c. Gravel cu.m. 0.050 650.00
d. Form Lumber, Good - 4 uses bd.ft. 8 40.00
e. 3"Ø G.I. Pipe m. 3.10 530.00
f. Plate kg. 2 48.00
g. Bolts, 5mm Ø pc. 12 10.00
h. Sign Face, 3mm thk. Aluminum Sheet pc. 1 4,200.00
i. Assorted CWN (1 kg./100 bd.ft. of Lumber) kg. 0.08 68.00

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G
I. Contractor's Profit (CP) 8% of G
J. Value Added Tax (VAT) 12% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 605(2)a Regulatory Signs (60cm Triangle)


Unit of Measurement : ea.
Output per hour : 1.00

Designation No. of Person No. of Hours Hourly Rate

A. Labor

a. Construction Foreman 1 1 109.19


b. Skilled Laborer 1 1 79.70
c. Laborer 2 1 61.44

Sub - Total for A


Name and Capacity No of Units No. of Hours Hourly Rate
B. Equipment

a. Cargo Truck (5 T) 1 0.25 712.00


Minor Tools (10 % of Labor)

Sub - Total for B


C. Total (A + B)
D. Output per hour = 1.00 ea.
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost

F. Materials

a. Portland Cement bag 0.48 220.00


b. Sand cu.m. 0.025 850.00
c. Gravel cu.m. 0.050 650.00
d. Form Lumber, Good - 4 uses bd.ft. 8 40.00
e. 3"Ø G.I. Pipe m. 3.10 530.00
f. Plate kg. 2 48.00
g. Bolts, 5mm Ø pc. 12 10.00
h. Sign Face, 3mm thk. Aluminum Sheet pc. 1 2,800.00
i. Assorted CWN (1 kg./100 bd.ft. of Lumber) kg. 0.08 68.00

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G
I. Contractor's Profit (CP) 8% of G
J. Value Added Tax (VAT) 12% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
Item No./Description : 605(2)b Regulatory Signs (90cm Triangle)
Unit of Measurement : ea.
Output per hour : 1.00

Designation No. of Person No. of Hours Hourly Rate

A. Labor

a. Construction Foreman 1 1 109.19


b. Skilled Laborer 1 1 79.70
c. Laborer 2 1 61.44

Sub - Total for A


Name and Capacity No of Units No. of Hours Hourly Rate
B. Equipment

a. Cargo Truck (5 T) 1 0.25 712.00


Minor Tools (10 % of Labor)

Sub - Total for B


C. Total (A + B)
D. Output per hour = 1.00 ea.
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost

F. Materials

a. Portland Cement bag 0.48 220.00


b. Sand cu.m. 0.025 850.00
c. Gravel cu.m. 0.050 650.00
d. Form Lumber, Good - 4 uses bd.ft. 8 40.00
e. 3"Ø G.I. Pipe m. 3.10 530.00
f. Plate kg. 2 48.00
g. Bolts, 5mm Ø pc. 12 10.00
h. Sign Face, 3mm thk. Aluminum Sheet pc. 1 4,200.00
i. Assorted CWN (1 kg./100 bd.ft. of Lumber) kg. 0.08 68.00

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G
I. Contractor's Profit (CP) 8% of G
J. Value Added Tax (VAT) 12% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 605(2)c Regulatory Signs (60cm


Unit of Measurement : Octagon) ea.
Output per hour : 1.00

Amount Designation No. of Person No. of Hours

A. Labor

109.19 a. Construction Foreman 1 1


318.80 b. Skilled Laborer 1 1
491.52 c. Laborer 2 1

919.51 Sub - Total for A


Amount Name and Capacity No of Units No. of Hours

B. Equipment

148.88 a. Cargo Truck (5 T) 1 0.25


172.00 Minor Tools (10 % of Labor)
53.25
91.95

466.08 Sub - Total for B


1,385.59 C. Total (A + B)
D. Output per hour = 1.00 ea.
79.18 E. Direct Unit Cost (C ÷ D)
Amount Name and Specification Unit Quantity

F. Materials

158.40 a. Portland Cement bag 0.48


34.00 b. Sand cu.m. 0.025
52.00 c. Gravel cu.m. 0.050
49.00 d. Form Lumber, Good - 4 uses bd.ft. 8
121.60 e. 3"Ø G.I. Pipe m. 3.10
8.16 f. Plate kg. 2
g. Bolts, 5mm Ø pc. 12
h. Sign Face, 3mm thk. Aluminum Sheet pc. 1
i. Assorted CWN (1 kg./100 bd.ft. of Lumber) kg. 0.08

423.16 Sub - Total for F


502.34 G. Direct Unit Cost (E + F)
45.21 H. Overhead, Contingencies & Miscellaneous (OCM) 9%
40.19 I. Contractor's Profit (CP) 8%
70.53 J. Value Added Tax (VAT) 12%
658.26 K. Total Unit Cost
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 605(2)d Regulatory Signs (90cm Octagon)


Unit of Measurement : ea.
Output per hour : 1.00

Amount Designation No. of Person No. of Hours

A. Labor

109.19 a. Construction Foreman 1 1


318.80 b. Skilled Laborer 1 1
491.52 c. Laborer 2 1

919.51 Sub - Total for A


Amount Name and Capacity No of Units No. of Hours

B. Equipment

148.88 a. Cargo Truck (5 T) 1 0.25


172.00 Minor Tools (10 % of Labor)
53.25
91.95

466.08 Sub - Total for B


1,385.59 C. Total (A + B)
D. Output per hour = 1.00 ea.
79.18 E. Direct Unit Cost (C ÷ D)
Amount Name and Specification Unit Quantity

F. Materials

158.40 a. Portland Cement bag 0.48


34.00 b. Sand cu.m. 0.025
52.00 c. Gravel cu.m. 0.050
65.60 d. Form Lumber, Good - 4 uses bd.ft. 8
4.76 e. 3"Ø G.I. Pipe m. 3.10
f. Plate kg. 2
g. Bolts, 5mm Ø pc. 12
h. Sign Face, 3mm thk. Aluminum Sheet pc. 1
i. Assorted CWN (1 kg./100 bd.ft. of Lumber) kg. 0.08

314.76 Sub - Total for F


393.94 G. Direct Unit Cost (E + F)
35.45 H. Overhead, Contingencies & Miscellaneous (OCM) 9%
31.51 I. Contractor's Profit (CP) 8%
55.31 J. Value Added Tax (VAT) 12%
516.21 K. Total Unit Cost
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 605(3)a Informative Signs (12"x24")


Unit of Measurement : ea.
Output per hour : 1.00

Amount Designation No. of Person No. of Hours

A. Labor

109.19 a. Construction Foreman 1 1


318.80 b. Skilled Laborer 1 1
491.52 c. Laborer 2 1

919.51 Sub - Total for A


Amount Name and Capacity No of Units No. of Hours

B. Equipment

148.88 a. Cargo Truck (5 T) 1 0.25


172.00 Minor Tools (10 % of Labor)
53.25
91.95

466.08 Sub - Total for B


1,385.59 C. Total (A + B)
D. Output per hour = 1.00 ea.
134.52 E. Direct Unit Cost (C ÷ D)
Amount Name and Specification Unit Quantity

F. Materials

283.80 a. Portland Cement bag 1.320


59.50 b. Sand cu.m. 0.073
91.00 c. Gravel cu.m. 0.145
42.00 d. Form Lumber, Good - 4 uses bd.ft. 8
114.70 e. 3"Ø G.I. Pipe m. 3.10
7.48 f. Plate kg. 2
11.97 g. Bolts, 5mm Ø pc. 12
h. Sign Face, 3mm thk. Aluminum Sheet pc. 1
i. Assorted CWN (1 kg./100 bd.ft. of Lumber) kg. 0.08

610.45 Sub - Total for F


744.97 G. Direct Unit Cost (E + F)
67.05 H. Overhead, Contingencies & Miscellaneous (OCM) 9%
59.60 I. Contractor's Profit (CP) 8%
104.59 J. Value Added Tax (VAT) 12%
976.21 K. Total Unit Cost
Item No./Description : 605(3)b Informative Signs (12"x48")
Unit of Measurement : ea.
Output per hour : 1.00

Amount Designation No. of Person No. of Hours

A. Labor

109.19 a. Construction Foreman 1 1


79.70 b. Skilled Laborer 1 1
61.44 c. Laborer 2 1

250.33 Sub - Total for A


Amount Name and Capacity No of Units No. of Hours

B. Equipment

480.60 a. Cargo Truck (5 T) 1 0.25


25.03 Minor Tools (10 % of Labor)

505.63 Sub - Total for B


755.96 C. Total (A + B)
D. Output per hour = 1.00 ea.
188.99 E. Direct Unit Cost (C ÷ D)
Amount Name and Specification Unit Quantity

F. Materials

690.00 a. Portland Cement bag 1.320


34.50 b. Sand cu.m. 0.073
c. Gravel cu.m. 0.145
d. Form Lumber, Good - 4 uses bd.ft. 8
e. 3"Ø G.I. Pipe m. 3.10
f. Plate kg. 2
g. Bolts, 5mm Ø pc. 12
h. Sign Face, 3mm thk. Aluminum Sheet pc. 1
i. Assorted CWN (1 kg./100 bd.ft. of Lumber) kg. 0.08

724.50 Sub - Total for F


913.49 G. Direct Unit Cost (E + F)
82.21 H. Overhead, Contingencies & Miscellaneous (OCM) 9%
73.08 I. Contractor's Profit (CP) 8%
128.25 J. Value Added Tax (VAT) 12%
1,197.04 K. Total Unit Cost
Item No./Description : 605(3)c Informative Signs (18"x24")
Unit of Measurement : ea.
Output per hour : 1.00

Amount Designation No. of Person No. of Hours

A. Labor

109.19 a. Construction Foreman 1 1


79.70 b. Skilled Laborer 1 1
61.44 c. Laborer 2 1

250.33 Sub - Total for A


Amount Name and Capacity No of Units No. of Hours

B. Equipment

480.60 a. Cargo Truck (5 T) 1 0.25


25.03 Minor Tools (10 % of Labor)

505.63 Sub - Total for B


755.96 C. Total (A + B)
D. Output per hour = 1.00 ea.
188.99 E. Direct Unit Cost (C ÷ D)
Amount Name and Specification Unit Quantity

F. Materials

680.00 a. Portland Cement bag 1.320


34.00 b. Sand cu.m. 0.073
c. Gravel cu.m. 0.145
d. Form Lumber, Good - 4 uses bd.ft. 8
e. 3"Ø G.I. Pipe m. 3.10
f. Plate kg. 2
g. Bolts, 5mm Ø pc. 12
h. Sign Face, 3mm thk. Aluminum Sheet pc. 1
i. Assorted CWN (1 kg./100 bd.ft. of Lumber) kg. 0.08

714.00 Sub - Total for F


902.99 G. Direct Unit Cost (E + F)
81.27 H. Overhead, Contingencies & Miscellaneous (OCM) 9%
72.24 I. Contractor's Profit (CP) 8%
126.78 J. Value Added Tax (VAT) 12%
1,183.28 K. Total Unit Cost
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 605(3)d Informative Signs (18"x48")


Unit of Measurement : ea.
Output per hour : 1.00

Amount Designation No. of Person No. of Hours

A. Labor

109.19 a. Construction Foreman 1 1


79.70 b. Skilled Laborer 1 1
61.44 c. Laborer 2 1

250.33 Sub - Total for A


Amount Name and Capacity No of Units No. of Hours
B. Equipment

480.60 a. Cargo Truck (5 T) 1 0.25


25.03 Minor Tools (10 % of Labor)

505.63 Sub - Total for B


755.96 C. Total (A + B)
D. Output per hour = 1.00 ea.
251.99 E. Direct Unit Cost (C ÷ D)
Amount Name and Specification Unit Quantity

F. Materials

1,750.00 a. Portland Cement bag 1.320


87.50 b. Sand cu.m. 0.073
c. Gravel cu.m. 0.145
d. Form Lumber, Good - 4 uses bd.ft. 8
e. 3"Ø G.I. Pipe m. 3.10
f. Plate kg. 2
g. Bolts, 5mm Ø pc. 12
h. Sign Face, 3mm thk. Aluminum Sheet pc. 1
i. Assorted CWN (1 kg./100 bd.ft. of Lumber) kg. 0.08

1,837.50 Sub - Total for F


2,089.49 G. Direct Unit Cost (E + F)
188.05 H. Overhead, Contingencies & Miscellaneous (OCM) 9%
167.16 I. Contractor's Profit (CP) 8%
293.36 J. Value Added Tax (VAT) 12%
2,738.06 K. Total Unit Cost
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 606(1) Pavement Marking (Premix Reflectorized)


Unit of Measurement : sq.m.
Output per hour : 10.00

Amount Designation No. of Person No. of Hours

A. Labor

109.19 a. Construction Foreman 1 1


318.80 b. Skilled Laborer 1 1
737.28 c. Laborer 2 1

1,165.27 Sub - Total for A


Amount Name and Capacity No of Units No. of Hours
B. Equipment

5,116.00 a. Cargo Truck (5 T) 1 0.05


297.76 Minor Tools (5% of Labor)
1,208.03
1,733.00
545.00
1,065.00
167.38
58.26

10,190.43 Sub - Total for B


11,355.70 C. Total (A + B)
D. Output per hour = 10.00 sq.m.
70.53 E. Direct Unit Cost (C ÷ D)
Amount Name and Specification Unit Quantity

F. Materials

8.12 a. Pavement Markings (White) lit. 1.00


5.28 Miscellaneous (5% of above)
115.00
46.75
65.00
209.00

449.15 Sub - Total for F


519.68 G. Direct Unit Cost (E + F)
46.77 H. Overhead, Contingencies & Miscellaneous (OCM) 9%
41.57 I. Contractor's Profit (CP) 8%
72.96 J. Value Added Tax (VAT) 12%
680.99 K. Total Unit Cost
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 606(2)a Pavement Markings (Reflectorized Thermoplastic)


Unit of Measurement : sq.m.
Output per hour : 10.00

Amount Designation No. of Person No. of Hours

A. Labor

109.19 a. Construction Foreman 1 1


318.80 b. Skilled Laborer 1 1
737.28 c. Laborer 2 1

1,165.27 Sub - Total for A


Amount Name and Capacity No of Units No. of Hours
B. Equipment

172.00 a. Cargo Truck (5 T) 1 0.05


297.76 Minor Tools (10% of Labor)
133.13
167.38
58.26

828.53 Sub - Total for B


1,993.80 C. Total (A + B)
D. Output per hour = 10.00 sq.m.
99.69 E. Direct Unit Cost (C ÷ D)
Amount Name and Specification Unit Quantity

F. Materials

8.12 a. Reflectorized Traffic Paint (White) lit. 1.00


5.28 Miscellaneous (5% of above)
115.00
46.75
65.00
209.00

449.15 Sub - Total for F


548.84 G. Direct Unit Cost (E + F)
49.40 H. Overhead, Contingencies & Miscellaneous (OCM) 9%
43.91 I. Contractor's Profit (CP) 8%
77.06 J. Value Added Tax (VAT) 12%
719.20 K. Total Unit Cost
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 606(2)b Pavement Markings (Reflectorized Thermoplastic)


Unit of Measurement : sq.m.
Output per hour : 10.00

Amount Designation No. of Person No. of Hours

A. Labor

109.19 a. Construction Foreman 1 1


79.70 b. Skilled Laborer 1 1
122.88 c. Laborer 2 1

311.77 Sub - Total for A


Amount Name and Capacity No of Units No. of Hours
B. Equipment

29.78 a. Cargo Truck (5 T) 1 0.05


55.10 Minor Tools (10% of Labor)
31.18

116.05 Sub - Total for B


427.82 C. Total (A + B)
D. Output per hour = 10.00 sq.m.
213.91 E. Direct Unit Cost (C ÷ D)
Amount Name and Specification Unit Quantity

F. Materials

106.16 a. Reflectorized Traffic Paint (Yellow) lit. 1.00


286.00 Miscellaneous (5% of above)
38.50
135.30
47.50
6.58
9.52

629.56 Sub - Total for F


843.47 G. Direct Unit Cost (E + F)
75.91 H. Overhead, Contingencies & Miscellaneous (OCM) 9%
67.48 I. Contractor's Profit (CP) 8%
118.42 J. Value Added Tax (VAT) 12%
1,105.29 K. Total Unit Cost
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 607 Reflective Pavement Studs (4" RPM)


Unit of Measurement : ea.
Output per hour : 10.00

Amount Designation No. of Person No. of Hours

A. Labor

109.19 a. Construction Foreman 1 1


79.70 b. Laborer 3 1
122.88

311.77 Sub - Total for A


Amount Name and Capacity No of Units No. of Hours

B. Equipment

55.10 a. Drill, CP-8 with attachment 1 1


31.18 b. Cargo Truck (5 T) 1 0.25
c. Compressor (20 Hp) 1 1
Minor Tools (5% of Labor)

86.28 Sub - Total for B


398.05 C. Total (A + B)
D. Output per hour = 10.00 ea.
99.51 E. Direct Unit Cost (C ÷ D)
Amount Name and Specification Unit Quantity

F. Materials

3,320.00 a. Reflective Stud Catcheye Raised Surface pc. 1


100mm x 100mm (type depends on the req.)
b. Concrete Epoxy A & B lit. 0.012

3,320.00 Sub - Total for F


3,419.51 G. Direct Unit Cost (E + F)
307.76 H. Overhead, Contingencies & Miscellaneous (OCM) 9%
273.56 I. Contractor's Profit (CP) 8%
480.10 J. Value Added Tax (VAT) 12%
4,480.93 K. Total Unit Cost
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 608(1) Furnishing and Placing Topsoil


Unit of Measurement : cu.m.
Output per hour : 1.25

Amount Designation No. of Person No. of Hours

A. Labor

109.19 a. Construction Foreman 1 1


79.70 b. Skilled Laborer 2 1
122.88 c. Laborer 2 1

311.77 Sub - Total for A


Amount Name and Capacity No of Units No. of Hours

B. Equipment

29.78 a. Plate Compactor 1 1


55.10 Minor Tools (10% of Labor)
31.18

116.05 Sub - Total for B


427.82 C. Total (A + B)
D. Output per hour = 1.25 cu.m.
213.91 E. Direct Unit Cost (C ÷ D)
Amount Name and Specification Unit Quantity

F. Materials

102.00 a. Topsoil cu.m. 1.05


280.00
38.50
135.30
47.50
6.58
9.52

619.40 Sub - Total for F


833.31 G. Direct Unit Cost (E + F)
75.00 H. Overhead, Contingencies & Miscellaneous (OCM) 9%
66.66 I. Contractor's Profit (CP) 8%
117.00 J. Value Added Tax (VAT) 12%
1,091.97 K. Total Unit Cost
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 608(2) Placing Topsoil


Unit of Measurement : cu.m.
Output per hour : 1.25

Amount Designation No. of Person No. of Hours

A. Labor

109.19 a. Construction Foreman 1 1


79.70 b. Skilled Laborer 2 1
122.88 c. Laborer 2 1

311.77 Sub - Total for A


Amount Name and Capacity No of Units No. of Hours

B. Equipment

55.10 a. Plate Compactor 1 1


31.18 Minor Tools (10% of Labor)

86.28 Sub - Total for B


398.05 C. Total (A + B)
D. Output per hour = 1.25 cu.m.
99.51 E. Direct Unit Cost (C ÷ D)
Amount Name and Specification Unit Quantity

F. Materials

1,650.00

1,650.00 Sub - Total for F


1,749.51 G. Direct Unit Cost (E + F)
157.46 H. Overhead, Contingencies & Miscellaneous (OCM) 9%
139.96 I. Contractor's Profit (CP) 8%
245.63 J. Value Added Tax (VAT) 12%
2,292.56 K. Total Unit Cost
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 609 Sprigging


Unit of Measurement : sq.m.
Output per hour : 35.00

Amount Designation No. of Person No. of Hours

A. Labor

163.79 a. Construction Foreman 1 1


119.55 b. Skilled Laborer 2 1
184.32 c. Laborer 2 1

467.66 Sub - Total for A


Amount Name and Capacity No of Units No. of Hours

B. Equipment

551.00 a. Water Truck (1000 gal.) 1 0.25


14.89 Minor Tools (10% of Labor)
46.77

612.65 Sub - Total for B


1,080.31 C. Total (A + B)
D. Output per hour = 35.00 sq.m.
1,080.31 E. Direct Unit Cost (C ÷ D)
Amount Name and Specification Unit Quantity

F. Materials

625.60 a. Sprigs sq.m. 1.05


303.60 b. Fertilizer kg. 0.10
211.40
71.50
170.50
39.60
95.00
6.58
4.76

1,528.54 Sub - Total for F


2,608.85 G. Direct Unit Cost (E + F)
234.80 H. Overhead, Contingencies & Miscellaneous (OCM) 9%
208.71 I. Contractor's Profit (CP) 8%
366.28 J. Value Added Tax (VAT) 12%
3,418.64 K. Total Unit Cost
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 610 Sodding


Unit of Measurement : sq.m.
Output per hour : 25.00

Amount Designation No. of Person No. of Hours

A. Labor

163.79 a. Construction Foreman 1 1


119.55 b. Laborer 8 1
184.32

467.66 Sub - Total for A


Amount Name and Capacity No of Units No. of Hours

B. Equipment

551.00 a. Water Truck (1000 gal.) 1 0.50


7.44 Minor Tools (10% of Labor)
46.77

605.21 Sub - Total for B


1,072.86 C. Total (A + B)
D. Output per hour = 25.00 sq.m.
536.43 E. Direct Unit Cost (C ÷ D)
Amount Name and Specification Unit Quantity

F. Materials

4,150.00 a. Sods sq.m. 1.05


323.00
95.00

4,568.00 Sub - Total for F


5,104.43 G. Direct Unit Cost (E + F)
459.40 H. Overhead, Contingencies & Miscellaneous (OCM) 9%
408.35 I. Contractor's Profit (CP) 8%
716.66 J. Value Added Tax (VAT) 12%
6,688.85 K. Total Unit Cost
Item No./Description : 611(1) Trees (Furnishing and Transplanting), 150mm dia. or le
Unit of Measurement : ea.
Output per hour : 1.00

Amount Designation No. of Person No. of Hours

A. Labor

109.19 a. Construction Foreman 1 1


122.88 b. Skilled Laborer 1 1
c. Laborer 2 1

232.07 Sub - Total for A


Amount Name and Capacity No of Units No. of Hours

B. Equipment

23.21 a. Cargo Truck (10 T) 1 1


b. Backhoe (0.80 cu.m.) 1 1
c. Water Truck (1000 gal.) 1 0.50
Minor Tools (10% of Labor)

Note: Includes watering for three (3) months

23.21 Sub - Total for B


255.28 C. Total (A + B)
D. Output per hour = 1.00 ea.
5.11 E. Direct Unit Cost (C ÷ D)
Amount Name and Specification Unit Quantity

F. Materials

1,240.00 a. Trees (Delivered at Site) pc. 1


85.00 b. Fertilizers kg. 3
66.25 c. Bamboo Pole pc. 3
d. Polyethylene Sheets sq.m. 3
e. Tie Wire kg. 0.25

1,391.25 Sub - Total for F


1,396.36 G. Direct Unit Cost (E + F)
125.67 H. Overhead, Contingencies & Miscellaneous (OCM) 9%
111.71 I. Contractor's Profit (CP) 8%
196.05 J. Value Added Tax (VAT) 12%
1,829.78 K. Total Unit Cost
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 611(2) Trees (Transplanting), 150mm dia. or


Unit of Measurement : less ea.
Output per hour : 1.00

Amount Designation No. of Person No. of Hours

A. Labor

109.19 a. Construction Foreman 1 1


159.40 b. Skilled Laborer 1 1
491.52 c. Laborer 2 1

760.11 Sub - Total for A


Amount Name and Capacity No of Units No. of Hours

B. Equipment

172.00 a. Cargo Truck (10 T) 1 1


148.88 b. Backhoe (0.80 cu.m.) 1 1
106.50 c. Water Truck (1000 gal.) 1 0.50
178.00 Minor Tools (10% of Labor)
76.01

681.39 Sub - Total for B


1,441.50 C. Total (A + B)
D. Output per hour = 1.00 ea.
1,253.48 E. Direct Unit Cost (C ÷ D)
Amount Name and Specification Unit Quantity

F. Materials

919.60 a. Fertilizers kg. 3


187.00 b. Bamboo Pole pc. 3
279.50 c. Polyethylene Sheets sq.m. 3
486.00 d. Tie Wire kg. 0.25
917.28
165.00
115.50
132.00
32.45
650.00
194.22

4,078.55
5,332.03 Sub - Total for F
479.88 G. Direct Unit Cost (E + F)
426.56 H. Overhead, Contingencies & Miscellaneous (OCM) 9%
748.62 I. Contractor's Profit (CP) 8%
6,987.09 J. Value Added Tax (VAT) 12%
K. Total Unit Cost
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 612(1) Reflectorized Thermoplastic Pavement Markings


Unit of Measurement : (Whit sq.m.
Output per hour : 25.00

Amount Designation No. of Person No. of Hours

A. Labor

109.19 a. Construction Foreman 1 1


159.40 b. Skilled Laborer 2 1
245.76 c. Laborer 6 1

514.35 Sub - Total for A


Amount Name and Capacity No of Units No. of Hours

B. Equipment

86.00 a. Cargo Truck/Delivery Truck (5 T) 1 1


74.44 b. Applicator Machine 1 1
53.25 c. Kneading Machine 1 1
275.50 Minor Tools (10 % of Labor)
25.72

514.91 Sub - Total for B


1,029.26 C. Total (A + B)
D. Output per hour = 25.00 sq.m.
245.06 E. Direct Unit Cost (C ÷ D)
Amount Name and Specification Unit Quantity

F. Materials

72.60 a. Thermoplastic Paint (White) bag 0.325


15.30 b. Glass Beads bag 0.033
23.40 c. Primer liter 0.120
1,950.00 d. LPG (50 kg.) cyl. 0.004
43.75 e. LPG (12 kg.) cyl. 0.002
80.00 f. Calsumine kg. 0.125
160.00 Miscellaneous (5% of Materials)
3.76
5.44
14.00
42.00

2,410.25 Sub - Total for F


2,655.31 G. Direct Unit Cost (E + F)
238.98 H. Overhead, Contingencies & Miscellaneous (OCM) 9%
212.42 I. Contractor's Profit (CP) 8%
372.81 J. Value Added Tax (VAT) 12%
3,479.52 K. Total Unit Cost
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 612(2) Reflectorized Thermoplastic Pavement Markings


Unit of Measurement : (Yello sq.m.
Output per hour : 25.00

Amount Designation No. of Person No. of Hours

A. Labor

109.19 a. Construction Foreman 1 1


79.70 b. Skilled Laborer 2 1
122.88 c. Laborer 6 1

311.77 Sub - Total for A


Amount Name and Capacity No of Units No. of Hours

B. Equipment

1,102.00 a. Cargo Truck/Delivery Truck (5 T) 1 1


15.59 b. Applicator Machine 1 1
c. Kneading Machine 1 1
Minor Tools (10 % of Labor)

1,117.59 Sub - Total for B


1,429.36 C. Total (A + B)
D. Output per hour = 25.00 sq.m.
238.23 E. Direct Unit Cost (C ÷ D)
Amount Name and Specification Unit Quantity

F. Materials

1,350.00 a. Thermoplastic Paint (Yellow)) bag 0.325


b. Glass Beads bag 0.033
c. Primer liter 0.120
d. LPG (50 kg.) cyl. 0.004
e. LPG (12 kg.) cyl. 0.002
f. Calsumine kg. 0.125
Miscellaneous (5% of Materials)

1,350.00 Sub - Total for F


1,588.23 G. Direct Unit Cost (E + F)
142.94 H. Overhead, Contingencies & Miscellaneous (OCM) 9%
127.06 I. Contractor's Profit (CP) 8%
222.99 J. Value Added Tax (VAT) 12%
2,081.21 K. Total Unit Cost
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 613 Concrete Joint Sealant (Hot Poured Elastic and Cold-A
Unit of Measurement : kg.
Output per hour : 20.00
.
Amount Designation No. of Person No. of Hours

A. Labor

109.19 a. Construction Foreman 1 1


159.40 b. Laborer 6 1
245.76

514.35 Sub - Total for A


Amount Name and Capacity No of Units No. of Hours

B. Equipment

551.00 a. Asphalt Kettle/Drum 1 1


51.44 Minor Tools (5% of Labor)

602.44 Sub - Total for B


1,116.79 C. Total (A + B)
D. Output per hour = 20.00 kg.
223.36 E. Direct Unit Cost (C ÷ D)
Amount Name and Specification Unit Quantity

F. Materials

1,320.30 a. Blown Asphalt kg. 1.05


366.85 Miscellaneous (5% of Materials)
560.00
112.36

2,359.51 Sub - Total for F


2,582.86 G. Direct Unit Cost (E + F)
232.46 H. Overhead, Contingencies & Miscellaneous (OCM) 9%
206.63 I. Contractor's Profit (CP) 8%
362.63 J. Value Added Tax (VAT) 12%
3,384.59 K. Total Unit Cost
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 620(a) Chevron Signs (450mmx600mm)


Unit of Measurement : ea.
Output per hour : 1.00

Amount Designation No. of Person No. of Hours

A. Labor

109.19 a. Construction Foreman 1 1


79.70 b. Skilled Laborer 1 1
122.88 c. Laborer 2 1

311.77 Sub - Total for A


Amount Name and Capacity No of Units No. of Hours

B. Equipment

39.10 a. Cargo Truck (5 T) 1 0.25


31.18 Minor Tools (10 % of Labor)

70.28 Sub - Total for B


382.05 C. Total (A + B)
D. Output per hour = 1.00 ea.
21.22 E. Direct Unit Cost (C ÷ D)
Amount Name and Specification Unit Quantity

F. Materials

15.00 a. Portland Cement bag 0.48


24.96 b. Sand cu.m. 0.025
54.37 c. Gravel cu.m. 0.050
1.89 d. Form Lumber, Good - 4 uses bd.ft. 8
e. 75mm Ø G.I. Pipe m. 3.25
f. G.I. Flat Bar, 1 1/2"x1/8" kg. 5
g. G.I. Bolts w/ Nuts & Washer, 5mm Ø pc. 3
h. G.I. Bolts w/ Nuts & Washer, 2mm Ø pc. 12
i. Sign Face, 3mm thk. Aluminum Sheet pc. 2
j. Assorted CWN (1 kg./100 bd.ft. of Lumber) kg. 0.08
Miscellaneous (0.3% of Materials)

96.22 Sub - Total for F


117.44 G. Direct Unit Cost (E + F)
10.57 H. Overhead, Contingencies & Miscellaneous (OCM) 9%
9.40 I. Contractor's Profit (CP) 8%
16.49 J. Value Added Tax (VAT) 12%
153.90 K. Total Unit Cost
Item No./Description : 620(b) Chevron Signs (600mmx800mm)
Unit of Measurement : ea.
Output per hour : 1.00

Amount Designation No. of Person No. of Hours

A. Labor

109.19 a. Construction Foreman 1 1


159.40 b. Skilled Laborer 1 1
491.52 c. Laborer 2 1

760.11 Sub - Total for A


Amount Name and Capacity No of Units No. of Hours

B. Equipment

172.00 a. Cargo Truck (5 T) 1 0.25


74.44 Minor Tools (10 % of Labor)
106.50
195.50
76.01

624.45 Sub - Total for B


1,384.56 C. Total (A + B)
D. Output per hour = 1.00 ea.
276.91 E. Direct Unit Cost (C ÷ D)
Amount Name and Specification Unit Quantity

F. Materials

357.06 a. Portland Cement bag 0.48


72.25 b. Sand cu.m. 0.025
111.15 c. Gravel cu.m. 0.050
661.67 d. Form Lumber, Good - 4 uses bd.ft. 8
45.00 e. 75mm Ø G.I. Pipe m. 3.45
136.80 f. G.I. Flat Bar, 1 1/2"x1/8" kg. 5
570.00 g. G.I. Bolts w/ Nuts & Washer, 5mm Ø pc. 3
6.72 h. G.I. Bolts w/ Nuts & Washer, 2mm Ø pc. 12
12.00 i. Sign Face, 3mm thk. Aluminum Sheet pc. 2
268.89 j. Assorted CWN (1 kg./100 bd.ft. of Lumber) kg. 0.08
112.08 Miscellaneous (0.2% of Materials)

2,353.61 Sub - Total for F


2,630.53 G. Direct Unit Cost (E + F)
236.75 H. Overhead, Contingencies & Miscellaneous (OCM) 9%
210.44 I. Contractor's Profit (CP) 8%
369.33 J. Value Added Tax (VAT) 12%
3,447.04 K. Total Unit Cost
Item No./Description : 622(1)a Bio-Engineering Solutions (Coco-net)
Unit of Measurement : sq.m.
Output per hour : 50.00

Amount Designation No. of Person No. of Hours

A. Labor

163.79 a. Construction Foreman 1 1


239.10 b. Laborer 8 1
184.32

587.21 Sub - Total for A


Amount Name and Capacity No of Units No. of Hours

B. Equipment

129.00 a. Water Truck (1000 gal.) 1 0.25


109.88 Minor Tools (10% of Labor)
175.75
53.25
58.72

526.60 Sub - Total for B


1,113.80 C. Total (A + B)
D. Output per hour = 50.00 sq.m.
1,113.80 E. Direct Unit Cost (C ÷ D)
Amount Name and Specification Unit Quantity

F. Materials

463.10 a. Erosion Control Net CGN 400 w/ 5 % wastage sq.m. 1.05


80.75 (Price includes bamboo pegs)
120.25
824.60
19.36
133.00
226.95
15.44

1,883.45 Sub - Total for F


2,997.25 G. Direct Unit Cost (E + F)
269.75 H. Overhead, Contingencies & Miscellaneous (OCM) 9%
239.78 I. Contractor's Profit (CP) 8%
420.81 J. Value Added Tax (VAT) 12%
3,927.60 K. Total Unit Cost
Item No./Description : 622(1)b Bio-Engineering Solutions (Coco-net)
Unit of Measurement : sq.m.
Output per hour : 50.00

Amount Designation No. of Person No. of Hours

A. Labor

327.57 a. Construction Foreman 1 1


239.10 b. Laborer 8 1
368.64

935.31 Sub - Total for A


Amount Name and Capacity No of Units No. of Hours

B. Equipment

782.00 a. Water Truck (1000 gal.) 1 0.25


93.53 Minor Tools (10% of Labor)

875.53 Sub - Total for B


1,810.84 C. Total (A + B)
D. Output per hour = 50.00 sq.m.
1,810.84 E. Direct Unit Cost (C ÷ D)
Amount Name and Specification Unit Quantity

F. Materials

7,750.00 a. Erosion Control Net CGN 700 w/ 5 % wastage sq.m. 1.05


13,992.00 (Price includes bamboo pegs)
598.90
64.28
467.66
0.54

22,873.38 Sub - Total for F


24,684.23 G. Direct Unit Cost (E + F)
2,221.58 H. Overhead, Contingencies & Miscellaneous (OCM) 9%
1,974.74 I. Contractor's Profit (CP) 8%
3,465.67 J. Value Added Tax (VAT) 12%
32,346.21 K. Total Unit Cost
Item No./Description : 622(2)a Bio-Engineering Solutions (Coco-logs/Fascine)
Unit of Measurement : l.m.
Output per hour : 15.00

Amount Designation No. of Person No. of Hours

A. Labor

109.19 a. Construction Foreman 1 1


79.70 b. Laborer 8 1
122.88

311.77 Sub - Total for A


Amount Name and Capacity No of Units No. of Hours

B. Equipment

178.00 Minor Tools (10% of Labor)


31.18

209.18 Sub - Total for B


520.95 C. Total (A + B)
D. Output per hour = 15.00 l.m.
520.95 E. Direct Unit Cost (C ÷ D)
Amount Name and Specification Unit Quantity

F. Materials

105.60 a. Coco Fiber Roll (CGR 200) l.m. 1.05


21.25 (Price includes nylon ropes and live stakes)
32.50
80.00
1,643.00
96.00
120.00 `
2,800.00
5.44

4,903.79 Sub - Total for F


5,424.74 G. Direct Unit Cost (E + F)
488.23 H. Overhead, Contingencies & Miscellaneous (OCM) 9%
433.98 I. Contractor's Profit (CP) 8%
761.63 J. Value Added Tax (VAT) 12%
7,108.58 K. Total Unit Cost
Item No./Description : 622(2)b Bio-Engineering Solutions (Coco-logs/Fascine)
Unit of Measurement : l.m.
Output per hour : 15.00

Amount Designation No. of Person No. of Hours

A. Labor

109.19 a. Construction Foreman 1 1


79.70 b. Laborer 8 1
122.88

311.77 Sub - Total for A


Amount Name and Capacity No of Units No. of Hours

B. Equipment

178.00 Minor Tools (10% of Labor)


31.18

209.18 Sub - Total for B


520.95 C. Total (A + B)
D. Output per hour = 15.00 l.m.
520.95 E. Direct Unit Cost (C ÷ D)
Amount Name and Specification Unit Quantity

F. Materials

105.60 a. Coco Fiber Roll (CGR 300) l.m. 1.05


21.25 (Price includes nylon ropes and live stakes)
32.50
80.00
1,643.00
96.00
120.00
4,200.00
5.44

6,303.79 Sub - Total for F


6,824.74 G. Direct Unit Cost (E + F)
614.23 H. Overhead, Contingencies & Miscellaneous (OCM) 9%
545.98 I. Contractor's Profit (CP) 8%
958.19 J. Value Added Tax (VAT) 12%
8,943.14 K. Total Unit Cost
Item No./Description : 622(3)a Bio-Engineering Solutions (Vegetation)
Unit of Measurement : sq.m.
Output per hour : 62.50

Amount Designation No. of Person No. of Hours

A. Labor

109.19 a. Construction Foreman 1 1


79.70 b. Laborer 2 1
122.88

311.77 Sub - Total for A


Amount Name and Capacity No of Units No. of Hours

B. Equipment

178.00 a. Hydroseeding Machine 1 1


31.18 b. Water Truck (1000 gal.) 1 1
(including maintenance time)

209.18 Sub - Total for B


520.95 C. Total (A + B)
D. Output per hour = 62.50 sq.m.
520.95 E. Direct Unit Cost (C ÷ D)
Amount Name and Specification Unit Quantity

F. Materials

105.60 a. Grass Cover sq.m. 1.05


21.25 (Price includes grass seeds, mulch, cocopeat
32.50 & binding agent for hydroseeding)
80.00
1,643.00
96.00
120.00
2,800.00
5.44

4,903.79 Sub - Total for F


5,424.74 G. Direct Unit Cost (E + F)
488.23 H. Overhead, Contingencies & Miscellaneous (OCM) 9%
433.98 I. Contractor's Profit (CP) 8%
761.63 J. Value Added Tax (VAT) 12%
7,108.58 K. Total Unit Cost
Item No./Description : 622(3)b Bio-Engineering Solutions (Vegetation)
Unit of Measurement : sq.m.
Output per hour : 35.00

Amount Designation No. of Person No. of Hours

A. Labor

109.19 a. Construction Foreman 1 1


79.70 b. Laborer 8 1
122.88

311.77 Sub - Total for A


Amount Name and Capacity No of Units No. of Hours

B. Equipment

178.00 a. Water Truck (1000 gal.) 1 0.50


31.18 Minor Tools (10% of Labor)

209.18 Sub - Total for B


520.95 C. Total (A + B)
D. Output per hour = 35.00 sq.m.
520.95 E. Direct Unit Cost (C ÷ D)
Amount Name and Specification Unit Quantity

F. Materials

105.60 a. Vetiver Grass System sq.m. 1.05


21.25 (Price includes cocopeat fertilizer)
32.50
80.00
1,643.00
96.00
120.00
4,200.00
5.44

6,303.79 Sub - Total for F


6,824.74 G. Direct Unit Cost (E + F)
614.23 H. Overhead, Contingencies & Miscellaneous (OCM) 9%
545.98 I. Contractor's Profit (CP) 8%
958.19 J. Value Added Tax (VAT) 12%
8,943.14 K. Total Unit Cost
Hourly Rate Amount

109.19 109.19
79.70 79.70
61.44 122.88

311.77

Hourly Rate Amount

712.00 178.00
31.18

209.18
520.95

520.95
Unit Cost Amount

220.00 105.60
850.00 21.25
650.00 32.50
40.00 80.00
530.00 1,643.00
70.78 141.56
10.00 120.00
4,500.00 4,500.00
68.00 5.44

6,649.35
7,170.30
of G 645.33
of G 573.62
of (G + H + I) 1,006.71
(G + H + I + J) 9,395.96
Hourly Rate Amount

109.19 109.19
79.70 79.70
61.44 122.88

311.77

Hourly Rate Amount

712.00 178.00
31.18

209.18
520.95

520.95
Unit Cost Amount

220.00 105.60
850.00 21.25
650.00 32.50
40.00 80.00
530.00 1,643.00
48.00 96.00
10.00 120.00
7,500.00 7,500.00
68.00 5.44

9,603.79
10,124.74
of G 911.23
of G 809.98
of (G + H + I) 1,421.51
(G + H + I + J) 13,267.46
Hourly Rate Amount

109.19 109.19
79.70 79.70
61.44 122.88

311.77

Hourly Rate Amount

712.00 178.00
31.18

209.18
520.95

520.95
Unit Cost Amount

220.00 290.40
850.00 62.05
650.00 94.25
40.00 80.00
530.00 1,643.00
48.00 96.00
10.00 120.00
2,750.00 2,750.00
68.00 5.44

5,141.14
5,662.09
of G 509.59
of G 452.97
of (G + H + I) 794.96
(G + H + I + J) 7,419.60
Hourly Rate Amount

109.19 109.19
79.70 79.70
61.44 122.88

311.77

Hourly Rate Amount

712.00 178.00
31.18

209.18
520.95

520.95
Unit Cost Amount

220.00 290.40
850.00 62.05
650.00 94.25
40.00 80.00
530.00 1,643.00
48.00 96.00
10.00 120.00
5,450.00 5,450.00
68.00 5.44

7,841.14
8,362.09
of G 752.59
of G 668.97
of (G + H + I) 1,174.04
(G + H + I + J) 10,957.68
Hourly Rate Amount

109.19 109.19
79.70 79.70
61.44 122.88

311.77

Hourly Rate Amount

712.00 178.00
31.18

209.18
520.95

520.95
Unit Cost Amount

220.00 290.40
850.00 62.05
650.00 94.25
40.00 80.00
530.00 1,643.00
48.00 96.00
10.00 120.00
3,750.00 3,750.00
68.00 5.44

6,141.14
6,662.09
of G 599.59
of G 532.97
of (G + H + I) 935.36
(G + H + I + J) 8,730.00
Hourly Rate Amount

109.19 109.19
79.70 79.70
61.44 122.88

311.77

Hourly Rate Amount

712.00 178.00
31.18

209.18
520.95

520.95
Unit Cost Amount

220.00 290.40
850.00 62.05
650.00 94.25
40.00 80.00
530.00 1,643.00
48.00 96.00
10.00 120.00
8,200.00 8,200.00
68.00 5.44

10,591.14
11,112.09
of G 1,000.09
of G 888.97
of (G + H + I) 1,560.14
(G + H + I + J) 14,561.28
Hourly Rate Amount

109.19 109.19
79.70 79.70
61.44 122.88

311.77

Hourly Rate Amount

712.00 35.60
15.59

51.19
362.96

36.30
Unit Cost Amount

450.00 450.00
22.50

472.50
508.80
of G 45.79
of G 40.70
of (G + H + I) 71.43
(G + H + I + J) 666.73
Hourly Rate Amount

109.19 109.19
79.70 79.70
61.44 122.88

311.77

Hourly Rate Amount

712.00 35.60
31.18

66.78
378.55

37.85
Unit Cost Amount

450.00 450.00
22.50

472.50
510.35
of G 45.93
of G 40.83
of (G + H + I) 71.65
(G + H + I + J) 668.77
Hourly Rate Amount

109.19 109.19
79.70 79.70
61.44 122.88

311.77

Hourly Rate Amount

712.00 35.60
31.18

66.78
378.55

37.85
Unit Cost Amount

475.00 475.00
23.75

498.75
536.60
of G 48.29
of G 42.93
of (G + H + I) 75.34
(G + H + I + J) 703.17
Hourly Rate Amount

109.19 109.19
61.44 184.32

293.51

Hourly Rate Amount

201.25 201.25
712.00 178.00
189.00 189.00
14.68

582.93
876.44

87.64
Unit Cost Amount

3,465.00 3,465.00

1,200.00 14.40

3,479.40
3,567.04
of G 321.03
of G 285.36
of (G + H + I) 500.81
(G + H + I + J) 4,674.25
Hourly Rate Amount

109.19 109.19
79.70 159.40
61.44 122.88

391.47

Hourly Rate Amount

123.00 123.00
39.15

162.15
553.62

442.89
Unit Cost Amount

490.00 514.50

514.50
957.39
of G 86.17
of G 76.59
of (G + H + I) 134.42
(G + H + I + J) 1,254.57
Hourly Rate Amount

109.19 109.19
79.70 159.40
61.44 122.88

391.47

Hourly Rate Amount

123.00 123.00
39.15

162.15
553.62

442.89
Unit Cost Amount

0.00
442.89
of G 39.86
of G 35.43
of (G + H + I) 62.18
(G + H + I + J) 580.37
Hourly Rate Amount

109.19 109.19
79.70 159.40
61.44 122.88

391.47

Hourly Rate Amount

1,065.00 266.25
39.15

305.40
696.87

19.91
Unit Cost Amount

89.00 93.45
26.00 2.60

96.05
115.96
of G 10.44
of G 9.28
of (G + H + I) 16.28
(G + H + I + J) 151.95
Hourly Rate Amount

109.19 109.19
61.44 491.52

600.71

Hourly Rate Amount

1,065.00 532.50
60.07

592.57
1,193.28

47.73
Unit Cost Amount

89.00 93.45

93.45
141.18
of G 12.71
of G 11.29
of (G + H + I) 19.82
(G + H + I + J) 185.00
ss

Hourly Rate Amount

109.19 109.19
79.70 79.70
61.44 122.88

311.77

Hourly Rate Amount

1,102.00 1,102.00
1,537.00 1,537.00
1,065.00 532.50
31.18

3,202.68
3,514.45

3,514.45
Unit Cost Amount

400.00 400.00
26.00 78.00
50.00 150.00
10.00 30.00
46.67 11.67

669.67
4,184.11
of G 376.57
of G 334.73
of (G + H + I) 587.45
(G + H + I + J) 5,482.86
Hourly Rate Amount

109.19 109.19
79.70 79.70
61.44 122.88

311.77

Hourly Rate Amount

1,102.00 1,102.00
1,537.00 1,537.00
1,065.00 532.50
31.18

3,202.68
3,514.45

3,514.45
Unit Cost Amount

26.00 78.00
50.00 150.00
10.00 30.00
46.67 11.67

269.67
3,784.11
of G 340.57
of G 302.73
of (G + H + I) 531.29
(G + H + I + J) 4,958.70
e)

Hourly Rate Amount

109.19 109.19
79.70 159.40
61.44 368.64

637.23

Hourly Rate Amount

712.00 712.00
93.75 93.75
187.50 187.50
63.72

1,056.97
1,694.20

67.77
Unit Cost Amount

1,565.00 508.63
650.00 21.45
160.00 19.20
3,800.00 15.20
735.00 1.47
3.00 0.38
28.32

594.64
662.40
of G 59.62
of G 52.99
of (G + H + I) 93.00
(G + H + I + J) 868.01
w)

Hourly Rate Amount

109.19 109.19
79.70 159.40
61.44 368.64

637.23

Hourly Rate Amount

712.00 712.00
93.75 93.75
187.50 187.50
63.72

1,056.97
1,694.20

67.77
Unit Cost Amount

1,780.00 578.50
650.00 21.45
175.00 21.00
3,800.00 15.20
735.00 1.47
3.00 0.38
31.90

669.89
737.66
of G 66.39
of G 59.01
of (G + H + I) 103.57
(G + H + I + J) 966.63
pplied Types)

Hourly Rate Amount

109.19 109.19
61.44 368.64

477.83

Hourly Rate Amount

10.00 10.00
23.89

33.89
511.72

25.59
Unit Cost Amount

250.00 262.50
13.13

275.63
301.21
of G 27.11
of G 24.10
of (G + H + I) 42.29
(G + H + I + J) 394.71
Hourly Rate Amount

109.19 109.19
79.70 79.70
61.44 122.88

311.77

Hourly Rate Amount

712.00 178.00
31.18

209.18
520.95

520.95
Unit Cost Amount

220.00 105.60
850.00 21.25
650.00 32.50
40.00 80.00
530.00 1,722.50
48.00 240.00
10.00 30.00
10.00 120.00
3,750.00 7,500.00
68.00 5.44
29.57

9,886.86
10,407.81
of G 936.70
of G 832.62
of (G + H + I) 1,461.26
(G + H + I + J) 13,638.39
Hourly Rate Amount

109.19 109.19
79.70 79.70
61.44 122.88

311.77

Hourly Rate Amount

712.00 178.00
31.18

209.18
520.95

520.95
Unit Cost Amount

220.00 105.60
850.00 21.25
650.00 32.50
40.00 80.00
530.00 1,828.50
48.00 240.00
10.00 30.00
10.00 120.00
7,500.00 15,000.00
68.00 5.44
34.93

17,498.22
18,019.16
of G 1,621.72
of G 1,441.53
of (G + H + I) 2,529.89
(G + H + I + J) 23,612.31
Hourly Rate Amount

109.19 109.19
61.44 491.52

600.71

Hourly Rate Amount

1,065.00 266.25
60.07

326.32
927.03

18.54
Unit Cost Amount

110.00 115.50

115.50
134.04
of G 12.06
of G 10.72
of (G + H + I) 18.82
(G + H + I + J) 175.65
Hourly Rate Amount

109.19 109.19
61.44 491.52

600.71

Hourly Rate Amount

1,065.00 266.25
60.07

326.32
927.03

18.54
Unit Cost Amount

156.00 163.80

163.80
182.34
of G 16.41
of G 14.59
of (G + H + I) 25.60
(G + H + I + J) 238.94
Hourly Rate Amount

109.19 109.19
61.44 491.52

600.71

Hourly Rate Amount

60.07

60.07
660.78

44.05
Unit Cost Amount

388.00 407.40

407.40
451.45
of G 40.63
of G 36.12
of (G + H + I) 63.38
(G + H + I + J) 591.58
Hourly Rate Amount

109.19 109.19
61.44 491.52

600.71

Hourly Rate Amount

60.07

60.07
660.78

44.05
Unit Cost Amount

509.00 534.45

534.45
578.50
of G 52.07
of G 46.28
of (G + H + I) 81.22
(G + H + I + J) 758.07
Hourly Rate Amount

109.19 109.19
61.44 122.88

232.07

Hourly Rate Amount

952.00 952.00
1,065.00 1,065.00

2,017.00
2,249.07

35.99
Unit Cost Amount

45.00 47.25

47.25
83.24
of G 7.49
of G 6.66
of (G + H + I) 11.69
(G + H + I + J) 109.07
Hourly Rate Amount

109.19 109.19
61.44 491.52

600.71

Hourly Rate Amount

1,065.00 532.50
60.07

592.57
1,193.28

34.09
Unit Cost Amount

70.00 73.50

73.50
107.59
of G 9.68
of G 8.61
of (G + H + I) 15.11
(G + H + I + J) 140.99
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : SPL 2(a) Crack and Seat


Unit of Measurement : sq.m.
Output per hour : 35.00

Designation No. of Person No. of Hours Hourly Rate

A. Labor

a. Construction Foreman 1 1 109.19


b. Skilled Laborer 1 1 79.70
c. Laborer 2 1 61.44

Sub - Total for A


Name and Capacity No of Units No. of Hours Rental Rate

B. Equipment

a. Backhoe w/ Breaker (0.80 cu.m.) 1 1.00 2,074.95


b. Vibratory Roller (10 m.t.), SP56 1 0.75 1,507.00
c. Water Truck (1000 gal.) 1 0.10 1,065.00

Sub - Total for B


C. Total (A + B)
D. Output per hour = 35.00 sq.m.
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost

F. Materials

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G
I. Contractor's Profit (CP) 8% of G
J. Value Added Tax (VAT) 12% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : SPL 2(b) Crack and Seat


Unit of Measurement : sq.m.
Output per hour : 30.00

Designation No. of Person No. of Hours Hourly Rate

A. Labor

a. Construction Foreman 1 1 109.19


b. Skilled Laborer 1 1 79.70
c. Laborer 2 1 61.44

Sub - Total for A


Name and Capacity No of Units No. of Hours Rental Rate
B. Equipment

a. Arrow Master D 500 1 1.00 1,485.84


(Additional 35% for Oil and Lubricants)
b. Vibratory Roller (10 m.t.), SP56 1 0.75 1,507.00
c. Water Truck (1000 gal.) 1 0.10 1,065.00

Sub - Total for B


C. Total (A + B)
D. Output per hour = 30.00 sq.m.
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost

F. Materials

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G
I. Contractor's Profit (CP) 8% of G
J. Value Added Tax (VAT) 12% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : SPL 3(a) Tree Planting


Unit of Measurement : pc.
Output per hour : 60.00

Amount Designation No. of Person No. of Hours

A. Labor

109.19 a. Construction Foreman 1 1


79.70 b. Laborer 10 1
122.88

311.77 Sub - Total for A


Amount Name and Capacity No of Units No. of Hours
B. Equipment

2,074.95 a. Cargo Truck (5 T) 1 0.25


1,130.25 b. Water Truck (1000 gal.) 1 0.25
106.50 Minor Tools (10% of Labor)

3,311.70 Sub - Total for B


3,623.47 C. Total (A + B)
D. Output per hour = 60.00 pc.
103.53 E. Direct Unit Cost (C ÷ D)
Amount Name and Specification Unit Quantity

F. Materials

a. Saplings pc. 1
b. Coco Lumber bd.ft. 8
c. Assorted CWN (1 kg./100 bd.ft.) kg. 0.08
d. Fertilizers kg. 0.10

0.00 Sub - Total for F


103.53 G. Direct Unit Cost (E + F)
9.32 H. Overhead, Contingencies & Miscellaneous (OCM) 9%
8.28 I. Contractor's Profit (CP) 8%
14.54 J. Value Added Tax (VAT) 12%
135.66 K. Total Unit Cost
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : SPL 3(b) Tree Planting


Unit of Measurement : pc.
Output per hour : 60.00

Amount Designation No. of Person No. of Hours

A. Labor

109.19 a. Construction Foreman 1 1


79.70 b. Laborer 10 1
122.88

311.77 Sub - Total for A


Amount Name and Capacity No of Units No. of Hours

B. Equipment

1,485.84 a. Cargo Truck (5 T) 1 0.25


b. Water Truck (1000 gal.) 1 0.25
1,130.25 Minor Tools (10% of Labor)
106.50

2,722.59 Sub - Total for B


3,034.36 C. Total (A + B)
D. Output per hour = 60.00 pc.
101.15 E. Direct Unit Cost (C ÷ D)
Amount Name and Specification Unit Quantity

F. Materials

a. Saplings pc. 1
b. Fertilizers kg. 0.10

0.00 Sub - Total for F


101.15 G. Direct Unit Cost (E + F)
9.10 H. Overhead, Contingencies & Miscellaneous (OCM) 9%
8.09 I. Contractor's Profit (CP) 8%
14.20 J. Value Added Tax (VAT) 12%
132.54 K. Total Unit Cost
Hourly Rate Amount

109.19 109.19
61.44 614.40

723.59

Hourly Rate Amount

712.00 178.00
1,065.00 266.25
72.36

516.61
1,240.20

20.67
Unit Cost Amount

50.00 50.00
20.00 160.00
68.00 5.44
50.00 5.00

220.44
241.11
of G 21.70
of G 19.29
of (G + H + I) 33.85
(G + H + I + J) 315.95

Hourly Rate Amount

109.19 109.19
61.44 614.40

723.59

Hourly Rate Amount

712.00 178.00
1,065.00 266.25
72.36

516.61
1,240.20

20.67
Unit Cost Amount

50.00 50.00
26.00 2.60

52.60
73.27
of G 6.59
of G 5.86
of (G + H + I) 10.29
(G + H + I + J) 96.01
ITEM NO. DESCRIPTION
PART C EARTHWORKS
100(1) Clearing and Grubbing (with Stripping)
100(2)a Individual Removal of Trees (small a,150-300mm Ø)
100(2)b Individual Removal of Trees (small b, 301-500mm Ø)
100(3)a Individual Removal of Trees (large a, 501-750mm Ø)
100(3)b Individual Removal of Trees (large b, 751-900mm Ø)
101(1) Removal of Structures and Obstruction (other than concrete)
101(2) Removal of Concrete Bridge Structures
101(2) Removal of Steel Bridge Structures
101(2) Removal of Stone Masonry Lined Drainage Structures
101(2) Removal of Concrete Drainage Structures
101(2)a Removal of RCPC (24" dia.) - 610mm
101(2)b Removal of RCPC (30" dia.) - 760mm
101(2)c Removal of RCPC (36" dia.) - 910mm
101(2)d Removal of RCPC (42" dia.) - 1070mm
101(2)e Removal of RCPC (48" dia.) - 1220mm
101(2)f Removal of RCPC (60" dia.) - 1520mm
101(2)g Removal of Pipes other than Pipe Culverts (PVC/GI/Asbestos, up to 200mm Ø), L = 10
ft.
101(3)a.1 Removal of Existing Concrete Pavement (0.23m thk.)
101(3)a.2 Removal of Existing PCC Pavement, 0.23m thk. (for Reblocking at intermittent section))
101(3)b Removal of Existing Asphalt Pavement (100mm thk.)
101(3)c Removal of Sidewalk
101(4)a Removal of Curb
101(4)b Removal of Existing Curbs & Gutter
102(1) Roadway Excavation (Unsuitable)
102(2)a Roadway Excavation (Surplus Common)
102(2)b Roadway Excavation (Surplus Common) - w/ Backhoe
102(3)a Roadway Excavation (Surplus Soft Rock) - w/ Backhoe
102(3)b Roadway Excavation (Surplus Soft Rock)
102(3)c Roadway Excavation (Surplus Hard Rock) - Blasting
102(3)d Roadway Excavation (Surplus Hard Rock) - Blasting (Tunnel Excavation)
102(4) Roadway Excavation (Unclassified)
103(1)a Structure Excavation (Common Soil)
103(1)b Structure Excavation (Soft Rock)
103(1)c Structure Excavation (Solid Rock)
103(2)a Bridge Excavation (Common Soil)
103(2)b Bridge Excavation (Soft Rock)
103(2)c Bridge Excavation (Solid Rock)
103(3) Foundation Fill
103(4) Excavation ordered below Plan Elevation
103(5)a Shoring
103(5)b Cribbing/Cofferdamming
103(6) Pipe Culvert and Drain Excavation
104(1)a Embankment from Borrow
104(1)b Embankment from Roadway Excavation
ITEM NO. DESCRIPTION
104(2) Selected Borrow for topping, case 1
104(3) Selected Borrow for topping, case 2
104(4) Earth Berm
105(1) Subgrade Preparation (Common Material)
105(2) Subgrade Preparation (Existing Pavement)
105(3) Subgrade Preparation (Unsuitable Material)
PART D SUBBASE AND BASE COURSE
200 Aggregate Subbase Course
200(1) Aggregate Subbase Course (for intermittent Reblocking)
201 Aggregate Base Course
201(1) Aggregate Base Course (for Reblocking)
202 Crushed Aggregate Base Course
203 Lime Stabilized Road Mix Base Course
204 Portland Cement Stabilized Road Mix Base Course
205 Asphalt Stabilized Road Mix Base Course
206 Portland Cement Treated Plant Mix Base Course
PART E SURFACE COURSE
300(1) Gravel Surface Course (Uncrushed)
300(2) Crushed Aggregate Surface Course
301(1) Bituminous Prime Coat (MC Cut-back Asphalt)
301(2) Bituminous Prime Coat (RC Cut-back Asphalt)
302(1) Bituminous Tack Coat (RC Cut-back Asphalt)
302(2) Bituminous Tack Coat (Emulsified Asphalt)
303(1) Bituminous Seal Coat (Cover Aggregate)
303(2) Bituminous Seal Coat (MC Cut-back Asphalt)
303(3) Bituminous Seal Coat (RC Cut-back Asphalt)
303(4) Bituminous Seal Coat (Asphalt Cement Penetration Grade 120-150)
304(1) Bituminous Surface Treatment (Aggregate Grading)
304(2) Bituminous Surface Treatment (Asphalt Cement Penetration Grade 120-150)
304(3) Bituminous Surface Treatment (MC Cut-back Asphalt)
304(4) Bituminous Surface Treatment (RC Cut-back Asphalt)
304(5) Bituminous Surface Treatment (Emulsified Asphalt)
305(1) Bituminous Penetration Macadam Pavement (Aggregates)
305(2) Bituminous Penetration Macadam Pavement (Asphalt Cement)
305(3) Bituminous Penetration Macadam Pavement (RC Cut-back Asphalt)
305(4) Bituminous Penetration Macadam Pavement (Emulsified Asphalt)
306(a) Bituminous Road Mix Surface Course (MC Cut-back Asphalt)
306(b) Bituminous Road Mix Surface Course (Emulsified Asphalt)
306(1) Aggregate for Bituminous Road Mix Surface Course
306(2) Bituminous Material for Bituminous Road Mix Surface Course
307 Bituminous Plant Mix Surface Course-General - 50mm thk.
308(a) Cold Asphalt Plant Mix (Emulsified Asphalt) - 50mm thk.
308(b) Cold Asphalt Plant Mix (Cut-back Asphalt) - 50mm thk.
309 Bituminous Plant Mix (Stockpile Maintenance Mixture)
310(a.1) Bituminous Concrete Surface Course, Hot Laid - 30mm thk. (Delivered)
ITEM NO. DESCRIPTION
310(a.2) Bituminous Concrete Surface Course, Hot Laid - 40mm thk. (Delivered)
310(a.3) Bituminous Concrete Surface Course, Hot Laid - 50mm thk. (Delivered)
310(b.1) Bituminous Concrete Surface Course, Hot Laid - 30mm thk. (Batching Plant)
310(b.2) Bituminous Concrete Surface Course, Hot Laid - 40mm thk. (Batching Plant)
310(b.3) Bituminous Concrete Surface Course, Hot Laid - 50mm thk. (Batching Plant)
311(1)a.1 PCC Pavement (Plain) - Conventional Method, 150mm thk.
311(1)a.2 PCC Pavement (Plain) - Conventional Method, 200mm thk.
311(1)a.3 PCC Pavement (Plain) - Conventional Method, 230mm thk.
311(1)a.4 PCC Pavement (Plain) - Conventional Method, 250mm thk.
311(1)a.5 PCC Pavement (Plain) - Conventional Method, 280mm thk.
311(1)a.6 PCC Pavement (Plain) - Conventional Method, 300mm thk.
311(1)b.1 PCC Pavement (Plain) - Using Concrete Paver, 230mm thk.
311(1)b.2 PCC Pavement (Plain) - Using Concrete Paver, 250mm thk.
311(1)b.3 PCC Pavement (Plain) - Using Concrete Paver, 280mm thk.
311(1)b.4 PCC Pavement (Plain) - Using Concrete Paver, 300mm thk.
311(1)c PCC Pavement (Plain) - Conventional Method, 150mm thk. (Using One Bagger Mixer)
311(2) PCC Pavement (Reinforced), 230mm thk.
PART G DRAINAGE AND SLOPE PROTECTION STRUCTURES
404 Reinforcing Steel Bar, Grade 40 (Minor Structures)
405 Structural Concrete Class A (Minor Structures)
500(1)a Pipe Culverts, 610mm dia. (24" Ø)
500(1)b Pipe Culverts, 760mm dia. (30" Ø)
500(1)c Pipe Culverts, 910mm dia. (36" Ø)
500(1)d Pipe Culverts, 1070mm dia. (42" Ø)
500(1)e Pipe Culverts, 1220mm dia. (48" Ø)
500(1)f Pipe Culverts, 1520mm dia. (60" Ø)
501(1) Underdrain
501(2) Blind drain
501(3) Granular Backfill filter material for Underdrains
502 Manhole/Catch Basin/Inlet
502(4) Concrete Covers
502(5) Metal Frames and Gratings
502(6) Metal Frames and Covers (Circular)
503(a) Drainage Steel Grating w/ Frame (675mm x 975mm Sump Grating)
503(b) Drainage Steel Grating w/ Frame (715mm x 2000mm Trench Grating)
504(1)a Removing, Cleaning, Stockpiling Salvaged Culvert Pipe (24" dia.) - 610mm
504(1)b Removing, Cleaning, Stockpiling Salvaged Culvert Pipe (30" dia.) - 760mm
504(1)c Removing, Cleaning, Stockpiling Salvaged Culvert Pipe (36" dia.) - 910mm
504(1)d Removing, Cleaning, Stockpiling Salvaged Culvert Pipe (42" dia.) - 1070mm
504(1)e Removing, Cleaning, Stockpiling Salvaged Culvert Pipe (48" dia.) - 1220mm
504(2)a Removing, Cleaning, and Re-laying Salvaged Culvert Pipe (24" dia.) - 610mm
504(2)b Removing, Cleaning, and Re-laying Salvaged Culvert Pipe (30" dia.) - 760mm
504(2)c Removing, Cleaning, and Re-laying Salvaged Culvert Pipe (36" dia.) - 910mm
504(2)d Removing, Cleaning, and Re-laying Salvaged Culvert Pipe (42" dia.) - 1070mm
504(2)e Removing, Cleaning, and Re-laying Salvaged Culvert Pipe (48" dia.) - 1220mm
504(3)a Cleaning Culvert Pipe in place (610mm dia.) - Half Silted
ITEM NO. DESCRIPTION
504(3)b Cleaning Culvert Pipe in place (760mm dia.) - Half Silted
504(3)c Cleaning Culvert Pipe in place (910mm dia.) - Half Silted
504(3)d Cleaning Culvert Pipe in place (1070mm dia.) - Half Silted
504(3)e Cleaning Culvert Pipe in place (1220mm dia.) - Half Silted
504(3)f Cleaning Culvert Pipe in place (1520mm dia.) - Half Silted
504(4) Reconditioning Drainage Structures
505(1) Riprap, Class A
505(2) Riprap, Class B
505(3) Riprap, Class C
505(4) Riprap, Class D
505(5) Grouted Riprap, Class A
505(6) Grouted Riprap, Class B
505(7) Grouted Riprap, Class C
505(8) Grouted Riprap, Class D
505(9) Filter Layer of Granular Material
506 Stone Masonry
507 Rubble Concrete
508 Hand-Laid Rock Embankment
509(a) Sheet Piles (Timber)
509(b.1) Sheet Piles (Steel) - Slope Protection
509(b.2) Sheet Piles (Steel) - Cofferdamming
509(c) Sheet Piles (Concrete), furnished and driven
510(1) Bed Course Granular Material
510(2) Concrete Slope Protection
511(1) Gabions
511(2) Mattresses
511(3) Filter Cloth
PART H MISCELLANEOUS STRUCTURES
600(1) Concrete Curb (Cast in place)
600(2) Concrete Gutter (Cast in place)
600(3) Concrete Curb and Gutter, Type A (Cast in place) - National Road
600(4) Concrete Curb (Precast)
600(5) Concrete Gutter (Precast)
600(6) Concrete Curb & Gutter (Precast)
601(a) Sidewalk (100mm thk.)
601(b) Sidewalk - Using One Bagger Mixer, (100mm thk.)
602(1)a Right-of-Way Monuments (Cast in place)
602(1)b Right-of-Way Monuments (Precast)
602(2)a Maintenance Marker Posts (Cast in place)
602(2)b Maintenance Marker Posts (Precast)
602(3)a Kilometer Post (Cast in Place)
602(3)b Kilometer Post (Precast)
602(4) Guide Post
603(1) Cable Wire Guardrail
603(3)a Metal Guardrail (Metal Beam) including Concrete Post
ITEM NO. DESCRIPTION
603(3)b Metal Beam End Piece
603(4) Guardrail (Timber)
604(1) Fencing (Barbed Wire)
604(2) Fencing (Chain Link Fence Fabric)
604(3) Fencing (Posts)
604(4) Fencing (Gates) - (Height = 3m & length = 4.24m)
605(1)a Danger/Warning Signs (60cm Triangle)
605(1)b Danger/Warning Signs (90cm Triangle)
605(2)a Regulatory Signs (60cm Triangle)
605(2)b Regulatory Signs (90cm Triangle)
605(2)c Regulatory Signs (60cm Octagon)
605(2)d Regulatory Signs (90cm Octagon)
605(3)a Informative Signs (12" x 24")
605(3)b Informative Signs (12" x 48")
605(3)c Informative Signs (18" x 24")
605(3)d Informative Signs (18" x 48")
606(1) Pavement Markings (Premix Reflectorized)
606(2)a Pavement Markings (Reflectorized Thermoplastic), White
606(2)b Pavement Markings (Reflectorized Thermoplastic), Yellow
607(1) Reflectorized Pavement Studs (Flush Type)
607(2) Reflectorized Pavement Studs (Raised Profile Type)
608(1) Furnishing and Placing Topsoil
608(2) Placing Topsoil
609 Sprigging
610 Sodding
611(1) Trees (Furnishing and Transplanting), 150mm dia. or less
611(2) Trees (Transplanting), 150mm dia. or less
612(1) Reflectorized Thermoplastic Pavement Markings (White)
612(2) Reflectorized Thermoplastic Pavement Markings (Yellow)
613 Concrete Joint Sealant (Hot Poured Elastic and Cold-Applied Types)
620(a) Chevron Signs (450mmx600mm)
620(b) Chevron Signs (600mmx800mm)
622(1)a Bio-Engineering Solutions (Coco-net), CGN 400
622(1)b Bio-Engineering Solutions (Coco-net), CGN 700
622(2)a Bio-Engineering Solutions (Coco-logs/Fascine), CGR 200
622(2)b Bio-Engineering Solutions (Coco-logs/Fascine), CGR 300
622(3)a Bio-Engineering Solutions (Vegetation), Hydroseeding
622(3)b Bio-Engineering Solutions (Vegetation), Vetiver Grass System
PART J SPECIAL ITEMS
SPL 2(a) Crack and Seat - Using Backhoe
SPL 2(b) Crack and Seat - Using Arrow Master
SPL 3(a) Tree Planting - With Tree Guard
SPL 3(b) Tree Planting
ITEM NO. DESCRIPTION

Вам также может понравиться