Вы находитесь на странице: 1из 45

ACCAspace

Provided by
ACCA Research Institute

ACCA P4
Advanced Financial Management (AFM)
高级财务管理
ACCA Lecturer: Lily Wang

ACCAspace 中国ACCA特许公认会计师教育平台 Copyright © ACCAspace.com


P4 Chapter 4 Content

1 Introduction

2 The risk adjusted WACC

3 The adjusted present value(APV) technique

4 Analysis of Comprehensive Example

ACCAspace 中国ACCA特许公认会计师教育平台 Copyright © ACCAspace.com 2


Chapter Summary

Beta revisited
• Asset beta-relfects pure systematic business risk
• Equity beta-reflects business and gearing risk
• Betas can be geard and ungeard:
Ve
 asset   equity 
Ve  Vd (1  T )

Investment Appraisal

Problems with the risk-adjusted WACC Adjusted present value model


• Can't cope if gearing ratio changed by Two-part approach:
project • Find base NPV
• Over-values tax shield where debt • PV of project flows using asset
not pernament beta in the CAPM
• Ignore costs of raising finance • Find PV of financing
• PV of issue costs on equity
• PV of issue costs on debt
ACCAspace 中国ACCA特许公认会计师教育平台 Copyright © ACCAspace.com 3
• PV of tax relief
1.Introduction

 Alternatives to the use of existing WACC as a discount rate in


project appraisal
 We have now established that the existing WACC should only be
used as a discount rate for a new investment project if the
business risk and the capital structure (financial risk) are likely to
stay constant. Alternatively,

 If the business riskof the new project differs from the entity's
existing business risk
 A risk adjusted WACC can be calculated, by recalculating the cost
of equity to reflect the business risk of the new project. (Degearing
and regearing beta factors)

ACCAspace 中国ACCA特许公认会计师教育平台 Copyright © ACCAspace.com 4


1.Introduction

 If the capital structure (financial risk) is expected to change when the new
project is undertaken

 The simplest way of incorporating a change in capital structure is to


recalculate the WACC using the new capital structure weightings.

 This is appropriate when the chanage in capital structure is not significant,


or if the new investment project can be effectively treated as a new
business, with its own long term gearing level.

 If the capital structure is expected to change significantly ,the APV method


of project appraisal should be used. This method separates the investment
element of the decision from the financing element and appraises them
independently. APV is generally recommended when there are complex
funding arrangements.

ACCAspace 中国ACCA特许公认会计师教育平台 Copyright © ACCAspace.com 5


2.The risk adjusted WACC

 Basic principle
 If the business risk of the new project is different from the business risk of a
company's existing operations, the company's shareholders will expect a
different return to compensate them for this new level risk. Thus, the
discount rate for project's cf is not existIng WACC, but a risk adjusted
WACC which incorporates this new required return to the shareholders

 Calculating a risk-adjusted WACC


 Find the appropriate equity beta from a suitable quoted company.
 Adjust the available equity beta to convert it to an asset beta-degearit.
 Readjust the asset beta to reflect the project gearing levels-regear the beta
 Use this beta in the CAPM equation to find Ke
 Use this Ke to find the WACC
 Evaluate the project

ACCAspace 中国ACCA特许公认会计师教育平台 Copyright © ACCAspace.com 6


2.The risk adjusted WACC

 Example
B plc is a hot air balloon manufacturer whose equity:debt ratio is 5:2

The company is considering a waterbed-manufacturing project.B plc will finance


the project to maintain its exisitng capital structure.

S plc is a waterbed-manufacturing company. I t has an equity beta of 1.59 and


a Ve:Vd ratio of 2:1

The yield on Bplc's debt, which is assumed to be risk frr, is 11%. B plc's equity
beta is 1.10. The average return on the stock market is 16% Thecorporation tax
rate is 30%

Required:

Calculate a suitable cost of capital to apply to the project.

ACCAspace 中国ACCA特许公认会计师教育平台 Copyright © ACCAspace.com 7


2.The risk adjusted WACC

 Answer
Degear the equity beta of the company in the nwe industry and find the busines
s risk asset beta of the new project/industry.
Ve
 asset   equity 
Ve  Vd (1  T )
=1.59x(2/(2+1(1-0.3)))
=1.18
Calculate the equity beta of the nwe project, by regearing:
incorporate the financial risk of our company using our gearing ratio(5:2)
Ve
 asset   equity 
Ve  Vd (1  T )
1.18=  e X [5/(5+2(1-0.3))]
1.18=0.78  e
=1.51
Ke=22%+1.51(16%-11%)=18.55% Kd=11%(1-0.3)=7.7%
WACC=18.55%X5/7+7.70X2/7=15.45%

ACCAspace 中国ACCA特许公认会计师教育平台 Copyright © ACCAspace.com 8


2.The risk adjusted WACC

 Using the risk-adjusted WACC

TWO other issues also need to be considered:

 The method used to gear and degear betas is based on the assum
ption that debt is perpetual. This overvalues the tax shield where d
ebt is finite.

 Issue costs on equity are ignored

ACCAspace 中国ACCA特许公认会计师教育平台 Copyright © ACCAspace.com 9


3.The adjusted present value(APV) technique

 Basic principle
 The APV method evalueates the project and the impact of financin
g separately. Hence, it can be used if a new project has a different
financial risk (debt-equity ratio) from the company

 APV consists of two different elements:

 APV = Base case NPV + Financing impact

(3) Value (1)Value of an all (2)Present value of

of a geared equity financed financing side effects

project project

ACCAspace 中国ACCA特许公认会计师教育平台 Copyright © ACCAspace.com 10


3.The adjusted present value(APV) technique

 The investment element (Base case NPV)


 The projct is evaluated as though it were being undertaken by an
all equity company with all financing side effects ignored. The fina
ncial risk is quantified later in the second part of the APV analysis.
Therefore:

• ignore the financial risk in the investment decision process

• use a beta that reflects ust the business risk, i.e.β

Find the project β

Calculate the base case discount rate=Keu


by putting the βasset in the CAPM formula

Calculate the base case NPV


ACCAspace 中国ACCA特许公认会计师教育平台 Copyright © ACCAspace.com 11
3.The adjusted present value(APV) technique

 The financing impact

 Financing cashflows consist of :


 issue cost

 tax reliefs

 As all financing cash flows are low risk they are discounted
at either:
 the Kd or

 the risk free rate

ACCAspace 中国ACCA特许公认会计师教育平台 Copyright © ACCAspace.com 12


3.The adjusted present value(APV) technique

 APV exam tricks

 Grossing up
A firm will know how much finance is required for the investment.
Issue costs of finance will usually be quoted on top. It will therefore
be necessary to gross up the funds to be raised.

• e.g. the finance required for a planned investment is 2m (net of


issue costs), Issue costs are 3%. And the finance raised will
also have to cover the issue costs. What are the issue costs
and what sum will need to be raised altogther?

• 2m is 97% of the amount to be raised:

• therefore,2m/0.97=2,061,856 will be needed.

• Issue costs are 3% 3%x2061856=61,856


ACCAspace 中国ACCA特许公认会计师教育平台 Copyright © ACCAspace.com 13
3.The adjusted present value(APV) technique

 APV exam tricks


 PV of debt issue costs

Equity issue costs Equity issue costs

Not tax deductible Are tax deductible-


RTQ for timing of tax flows
 Method:
issue costs at T0 (X)
tax relief at the CT rate(issue costs x CT rate) X
PV of the tax relief(RTQ for timing of tax flows) X
PV of the issue costs X
(issue costs-PV of tax relief)

ACCAspace 中国ACCA特许公认会计师教育平台 Copyright © ACCAspace.com 14


3.The adjusted present value(APV) technique

 APV exam tricks


 PV of the tax relief on interest payment
The PV of the tax relief on interest payments is also known as the
PV of the tax shield .
The method adopted depends on the information given:
Simple scenario: Debentures- interest paid at a fixed amount
each year
Annual tax relief= total loan x interest rate x tax rate (X)
Annuity factor for n years X
Year one discount factor(if tax is delayed one year) X
PV of the tax shield X

ACCAspace 中国ACCA特许公认会计师教育平台 Copyright © ACCAspace.com 15


3.The adjusted present value(APV) technique

 APV exam tricks

 Calculation of APV( in detail)


The base case NPV is used as a starting point. The costs and benefits
of the financing are then added to find a final adjusted present value.

Base case NPV x

PV of the issue costs

Equity (x)

Debt (x)

PV of the tax shield x

Adjusted Present Value x

ACCAspace 中国ACCA特许公认会计师教育平台 Copyright © ACCAspace.com 16


3.The adjusted present value(APV) technique

 Example
Rounding plc is a company currently engaged in the manufacture of
baby equipment. It wishes to diversify into the manufacture of snowboards
The investment details
The company's equity beta is 1.27 and is current debt to equity ratio is
25:75,, however the company's gearing ratio will change as a result of the
new project.
Firms involved in snowboard manufacture have an average equity
beta of 1.19 and an average debt to equity ratio of 30:70
Assume that the debt is risk frr, that the risk free rate is 10% and that
the expected return from the market porfolio is 16%
The new projct will invove the purchase of new machinery for a cost of
800,000(net of issue cost), which will produce annual cash inflows of
450,000 for 3years. At the end of this time it will have no scrap value.
ACCAspace 中国ACCA特许公认会计师教育平台 Copyright © ACCAspace.com 17
3.The adjusted present value(APV) technique

 Example
Corporation tax is payable in the same year at rate of 33%. The
machine will attract writing down allowances of 25% pa on a reducing
balance basis, with a balancing allowance ata the end of the project life
when the machine is scrapped.

The financing details:

The new investment will be financed as follows:

Debentues(redeemble in three years time ) 40%

Rights issue of equity 60%

The issue costs are 4% on the gross equity issued and 2% on the
gross debt issud , Assume that the debt issue costs are tax deductible.

Calculate the APV


ACCAspace 中国ACCA特许公认会计师教育平台 Copyright © ACCAspace.com 18
3.The adjusted present value(APV) technique

 Answer
The investment element

Firstly,COMPUTE the asset beta of the project. This is achieved by de


gearing the equity beta from the snow board indutry average.
Ve
 asset   equity 
Ve  Vd (1  T )
βa=1.19 x (70/(70+30(1-0.33)))

βa=0.92

The next task is to determine base case discount rate for the project.

E(Rf)=Rf + (E(Rm)-Rf) βa

=10%+(16%-10%)0.92

=15.52%(round to 16%)

ACCAspace 中国ACCA特许公认会计师教育平台 Copyright © ACCAspace.com 19


3.The adjusted present value(APV) technique

 Answer
(1) Base case NPV calculation($000)

Time 0 1 2 3
Receipts 450 450 450
Corporation tax (149) (149) (149)
@33%
Tax relief on capital allowance(W1) 66 50 149
Initial outlay ( 800)
Net cash flow (800) 367 351 450
Discount rate@16% 1 0.862 0.743 0.641
Present value (800) 316 261 288
Base case NPV 65

ACCAspace 中国ACCA特许公认会计师教育平台 Copyright © ACCAspace.com 20


3.The adjusted present value(APV) technique

 Answer
(W1)Capital allowances computation W1

W.D.A Tax relief@33% Timing

Investment 800

Y1 WDA (200) 66 T1

600

Y1 WDA (150) 50 T2

450

Y1 WDA 0

Balancing allowance 450 149 T3

ACCAspace 中国ACCA特许公认会计师教育平台 Copyright © ACCAspace.com 21


3.The adjusted present value(APV) technique

 Answer

(2) The financing impact

lay out the financing package.

Equity- 60%x 800,000 480,000 issue cost 4%

Debt - 40% x 800,000 320,000 issue cost 2%

A. PV of issue cost on equity

Equity issue cost 480,000x4/96=(20,000)

B. PV of issue cost on debt

Debt issue cost: 320,000x 2/98=(6,531)

Tax relief@33% 2,155

PV of the issue cost on debt 4,376


ACCAspace 中国ACCA特许公认会计师教育平台 Copyright © ACCAspace.com 22
3.The adjusted present value(APV) technique

 Answer

(2) The financing impact

C. PV of Tax shield

Total amount raised by loan- don't forget to add the issue


costs=320,000+6,531=326,531

Annual tax relief=326,531 x 0.10 x 0.33=10,776

AFfor 3 yrs 2.487

PV of the tax shield 26,800

(3) The APV calculation

ACCAspace 中国ACCA特许公认会计师教育平台 Copyright © ACCAspace.com 23


3.The adjusted present value(APV) technique

 Answer

(3) The APV calculation


Base case NPV 65,000

PV of the issue costs

Equity (20,000)

Debt (4,376)

PV of the tax shield: 26,800

APV 67,424

Financially viable.

ACCAspace 中国ACCA特许公认会计师教育平台 Copyright © ACCAspace.com 24


3.The adjusted present value(APV) technique

 Additional Factors regarding the APV method

 Additional factors-subsidised/cheap loans


If the loan is cheap ,the interest cost is lower. However, the benefit is
reduced since the tax shield will also be lower:

PV of the cheap loan (opportunity benefit):

PV of the interest saved x

Less: PV of the tax relief lost (x)

PV of the cheap loan x

ACCAspace 中国ACCA特许公认会计师教育平台 Copyright © ACCAspace.com 25


3.The adjusted present value(APV) technique

 Additional Factors regarding the APV method

 Additional factors-subsidised/cheap loans


Example: A plc requires 1million in debt finance for 5years

It has borrowed 700,000 in the form of 10% debentures redeemablein


5years and the remainder under a government subsidised loan scheme
at6%. The tax rate is 30%. Assume that tax is delayed one year.

Calculate the PV of the tax shields and the PV of the cheap loan.

(a) PV of the tax shields

Although the cheap loan has a cost of 6% it has the same risk as a
normal loan ,therefore the appropriate discount rate is 10%pa

ACCAspace 中国ACCA特许公认会计师教育平台 Copyright © ACCAspace.com 26


3.The adjusted present value(APV) technique

 Additional Factors regarding the APV method


 Additional factors-subsidised/cheap loans
Answers: (a) PV of the tax shields
Although the cheap loan has a cost of 6% it has the same risk as a
normal loan ,therefore the appropriate discount rate is 10%pa
Normal loan Cheap loan
Annual tax relief=total loan x
interest rate x tax rate
700,000 x 0.1x 0.3 21,000
300,000 x 0.6x 0.3 54,000
Annual factor for 5 yrs@10% 3.791 3.791
Discount factor for 1 yr@10% 0.909 0.909
PV of the tax shield 72,366 18,609
ACCAspace 中国ACCA特许公认会计师教育平台 Copyright © ACCAspace.com 27
3.The adjusted present value(APV) technique

 Additional Factors regarding the APV method


 Additional factors-subsidised/cheap loans
Answers: (b) PV of the cheap loan

0 1 2 3 4 5 6
Annuity PV of the interest saved x x x x x
Deferred PV of the tax relief lost . . (x)(x)(x)(x)(x)
annuity
Interest saved tax relief lost
Annual amount
300,000 x (0.1-0.06) = 12,000
12,000 x 0.3= 3,600
Annual factor for 5 yrs@10% 3.791 3.791
Discount factor for 1 yr@10% 0.909
PV of the tax shield 45,492 (12,406)
ACCAspace 中国ACCA特许公认会计师教育平台 Copyright © ACCAspace.com 28
3.The adjusted present value(APV) technique

 Additional Factors regarding the APV method


 Additional factors-subsidised/cheap loans
The APV calculation is therefore amended as follows:
Base case NPV X/(X)
PV of the issue costs
Equity (X)
Debt (X)
PV of the tax shield:
Normal loan X
Cheap loan X
PV of the cheap loan:
Interest saved X
tax relief lost (X)
APV X/(X)
ACCAspace 中国ACCA特许公认会计师教育平台 Copyright © ACCAspace.com 29
3.The adjusted present value(APV) technique

 Advantages and disadvantages of APV


Advantages Disadvantages
• Step-by-step approach gives Based on M&M with-tax theory.
clear understanding of the Ignores:
element of the decision * bankruptcy risk
* tax exhaustion
* agency costs
• Can evaluate any type of Based on M&M with-taxt theory
financing package Assumes:
* debt is risk free and irredeema
ble
• More straightforward than
adjusting the WACC which can
中国ACCA特许公认会计师教育平台
be complex
ACCAspace Copyright © ACCAspace.com 30
Analysis of Example

Burung Co (6/14)
You have recently commenced working for Burung Co and are reviewing a
four-year project which the company is considering for investment. The
project is in a business activity which is very different from Burung Co's
current line of business.
The following net present value estimate has been made for the project:

ACCAspace 中国ACCA特许公认会计师教育平台 Copyright © ACCAspace.com 31


Analysis of Example

Net present value is negative $1.65 million, and therefore the


recommendation is that the project should not be accepted.

In calculating the net present value of the project, the following notes were
made:

(i) Since the real cost of capital is used to discount cash flows, neither the
sales revenue nor the direct project costs have been inflated. It is estimated
that the inflation rate applicable to sales revenue is 8% per year and to the
direct project costs is 4% per year.

(ii) The project will require an initial investment of $38 million. Of this, $16
million relates to plant and machinery, which is expected to be sold for $4
million when the project ceases, after taking any taxation and inflation
impact into account.

ACCAspace 中国ACCA特许公认会计师教育平台 Copyright © ACCAspace.com 32


Analysis of Example

(iii) Tax allowable depreciation is available on the plant and machinery at


50% in the first year, followed by 25% per year thereafter on a reducing
balance basis. A balancing adjustment is available in the year the plant and
machinery is sold. Burung Co pays 20% tax on its annual taxable profits. No
tax allowable depreciation is available on the remaining investment assets
and they will have a nil value at the end of the project.

(iv) Burung Co uses either a nominal cost of capital of 11% or a real cost of
capital of 7% to discount all projects, given that the rate of inflation has been
stable at 4% for a number of years.

(v) Interest is based on Burung Co's normal borrowing rate of 150 basis
points over the 10-year government yield rate.

ACCAspace 中国ACCA特许公认会计师教育平台 Copyright © ACCAspace.com 33


Analysis of Example

(vi) At the beginning of each year, Burung Co will need to provide working capital
of 20% of the anticipated sales revenue for the year. Any remaining working
capital will be released at the end of the project.

(vii) Working capital and depreciation have not been taken into account in the
net present value calculation above, since depreciation is not a cash flow and all
the working capital is returned at the end of the project.

It is anticipated that the project will be financed entirely by debt, 60% of which
will be obtained from a subsidised loan scheme run by the Government, which
lends money at a rate of 100 basis points below the 10-year government debt
yield rate of 2.5%. Issue costs related to raising the finance are 2% of the gross
finance required. The remaining 40% will be funded from Burung Co's normal
borrowing sources. It can be assumed that the debt capacity available to Burung
Co is equal to the actual amount of debt finance raised for the project.

ACCAspace 中国ACCA特许公认会计师教育平台 Copyright © ACCAspace.com 34


Analysis of Example

Burung Co has identified a company, Lintu Co, which operates in the same
line of business as that of the project it is considering. Lintu Co is financed
by 40 million shares trading at $3.20 each and $34 million debt trading at
$94 per $100. Lintu Co's equity beta is estimated at 1.5. The current yield on
government treasury bills is 2% and it is estimated that the market risk
premium is 8%. Lintu Co pays tax at an annual rate of 20%.

Both Burung Co and Lintu Co pay tax in the same year as when profits are
earned.

ACCAspace 中国ACCA特许公认会计师教育平台 Copyright © ACCAspace.com 35


Analysis of Example

Required

(a) Calculate the adjusted present value (APV) for the project, correcting
any errors made in the net present value estimate above, and conclude
whether the project should be accepted or not. Show all relevant
calculations. (15 marks)

(b) Comment on the corrections made to the original net present value
estimate and explain the APV approach taken in part (a), including any
assumptions made. (10 marks)

(Total = 25 marks)

ACCAspace 中国ACCA特许公认会计师教育平台 Copyright © ACCAspace.com 36


Solution of Example

Answers:

ACCAspace 中国ACCA特许公认会计师教育平台 Copyright © ACCAspace.com 37


Solution of Example

ACCAspace 中国ACCA特许公认会计师教育平台 Copyright © ACCAspace.com 38


Solution of Example

ACCAspace 中国ACCA特许公认会计师教育平台 Copyright © ACCAspace.com 39


Solution of Example

(b) Corrections made to the original net present value

(1) Cash flows are inflated and the nominal rate based on Lintu Co's
all-equity financed rate is used (see below). Where different cash flows
are subject to different rates of inflation, applying a real rate to non-
inflated amounts would not give an accurate answer because the effect of
inflation on profit margins is being ignored.

(2) Interest is not normally included in the net present value


calculations. Instead, it is normally imputed within the cost of capital or
discount rate. In this case, it is included in the financing side effects.

ACCAspace 中国ACCA特许公认会计师教育平台 Copyright © ACCAspace.com 40


Solution of Example

(b) Corrections made to the original net present value

(3) The approach taken to exclude depreciation from the net present
value computation is correct, but capital allowances need to be taken away
from profit estimates before tax is calculated, reducing the profits on which
tax is payable.

(4) The impact of the working capital requirement is included in the


estimate as, although all the working capital is recovered at the end of the
project, the flows of working capital are subject to different discount rates
when their present values are calculated

ACCAspace 中国ACCA特许公认会计师教育平台 Copyright © ACCAspace.com 41


Solution of Example

(b) Approach taken (relates to errors 5 & 6)

The value of the project is initially assessed considering only the


business risk involved in undertaking the project. The discount rate used is
based on Lintu Co's asset beta which measures only the business risk of
that company. Since Lintu Co is in the same line of business as the project,
it is deemed appropriate to use its discount rate, instead of 11% that
Burung Co uses normally.

The impact of debt financing and the subsidy benefit are then
considered. In this way, Burung Co can assess the value created from its
investment activity and then the additional value created from the manner
in which the project is financed.

ACCAspace 中国ACCA特许公认会计师教育平台 Copyright © ACCAspace.com 42


Solution of Example

(b) Assumptions made

It is assumed that all figures used are accurate and any estimates
made are reasonable. Burung Co may want to consider undertaking a
sensitivity analysis to assess this.

It is assumed that the initial working capital required will form part of the
funds borrowed but that the subsequent working capital requirements will
be available from the funds generated by the project. The validity of this
assumption needs to be assessed since the working capital requirements
at the start of years 2 and 3 are substantial.

ACCAspace 中国ACCA特许公认会计师教育平台 Copyright © ACCAspace.com 43


Solution of Example

(b) Assumptions made

It is assumed that Lintu Co's asset beta and all-equity financed


discount rate represent the business risk of the project. The validity of this
assumption also needs to be assessed. For example, Lintu Co's entire
business may not be similar to the project, and it may undertake other lines
of business. In this case, the asset beta would need to be adjusted so that
just the project's business risk is considered.

It is also assumed that there are no adverse side-effects of taking on


the extra debt eg a worsening credit rating which could impact Burung's
trading position.

ACCAspace 中国ACCA特许公认会计师教育平台 Copyright © ACCAspace.com 44


ACCAspace

Provided by
ACCA Research Institute

Вам также может понравиться