Академический Документы
Профессиональный Документы
Культура Документы
--
1
Page
POSSIBUILD BUILDING TECHNOLOGIES
Plot No.135, Mythri Nagar – Phase -1, Madinaguda,
Miyapur, Hyderabad – 500045
-------------------------------------------------------------------------------------------------------------
TABLE OF CONTENTS
a. Assembly of mould
b. Mould cleaning and preparation
c. Fixing of Rebars/Cast-in-items
d. Final Inspection before casting
e. Concreting
f. Curing
g. Demoulding
h. Final Inspection and transfer to storage yard
2. Logistics
3. Handling
4. Storage
5. Installation
a. Setting out
b. Lifting and Installation
c. Grouting work
d. Joint casting and sealing
2
Page
POSSIBUILD BUILDING TECHNOLOGIES
Plot No.135, Mythri Nagar – Phase -1, Madinaguda,
Miyapur, Hyderabad – 500045
-------------------------------------------------------------------------------------------------------------
• To check the level and flatness of the base mould before assembling the mould for panel
casting.
• Dimensions of the mould needs to be checked as per the drawings. Tolerances shall be
allowed within as specified by the code.
• Mould needs to be ensured as leak proof as this allows the chances of formation of honey
combs in the wall panels.
• Squareness of the mould forms to be checked.
• Mould should be made clean and free from debris and old mortars using remover or scaling
bars.
• Form oil or mould release agent should be applied evenly over the mould surfaces
• Check that the joints and edges of the mould, bolts, stoppers, tie rods, side props, Magnets
and rubber seal are intact and properly secured.
• Incase if any openings are present, the shutters or forms shall be ensured for proper angles
as per the drawing using proper bracing mechanism. 4
Page
POSSIBUILD BUILDING TECHNOLOGIES
Plot No.135, Mythri Nagar – Phase -1, Madinaguda,
Miyapur, Hyderabad – 500045
-------------------------------------------------------------------------------------------------------------
`
Fig 4. Side braces of props.
• Check that the rebar size, spacing and lap length and location of precast inserts like corrugated
sleeve pipes, recess, lifting inserts as per the approved structural drawings.
• Ensure proper location of electrical and plumbing inserts if any present as per the production
5
Page
drawing.
POSSIBUILD BUILDING TECHNOLOGIES
Plot No.135, Mythri Nagar – Phase -1, Madinaguda,
Miyapur, Hyderabad – 500045
-------------------------------------------------------------------------------------------------------------
• Use of fabrication rig can help to ensure the accuracy of rebars fixing and spacing.
• Where needed, tack welding may be carried out to secure inserts.
• Sufficient number of spaces with the correct sizes should be properly placed and secured to
achieve the required concrete cover during casting
7
Page
POSSIBUILD BUILDING TECHNOLOGIES
Plot No.135, Mythri Nagar – Phase -1, Madinaguda,
Miyapur, Hyderabad – 500045
-------------------------------------------------------------------------------------------------------------
1e. Concreting:
• Check the specifications of the concrete like grade, slump etc., as per the fabrication drawings
before the concrete mix is placed in the mould.
• Ensure that the drop height of concrete shall not be more than 1m.
• Proper vibration and compaction should be carried out in particular, in more congested areas.
• Form vibrator can be used for slender and thin elements.
• Spreading and levelling of concrete surface level after initial set.
• Maintain the thickness required by use of screeder.
• Use of power trowel/ float is recommended for smoother finishes.
• Appropriate number of cubes may be collected for strength checking during the time of
8
Fig 9. Picture showing the fixation of mould vibrator the wall palette
1f. Curing:
• Observe adequate curing time and desired environment. Curing compounds may also be
applied with reference to the details as approved by engineer – in – charge.
• Concrete cubes should be subjected to the same curing conditions as the precast concrete
elements.
1g. Demoulding:
• Depending on the anchor length of inserts and type of precast elements, minimum concrete
strength required may be higher to overcome the suction and frictional forces during
demoulding.
• Cube tests should be conducted to verify the concrete strength of elements before
demoulding.
• As a general guide, ensure that the concrete strengths attained for reinforced precast
9
• Check the condition of the finished product. It shall be free from major defects likes honey
combs, cracks and breaking of edges etc.,
• Verification of critical dimensions to be made.
• Elements needs to be identified with markings and should be marked with the location,
member type, size, weight and orientation as per shop drawings.
• Check the elements have achieved 75% of their design concrete strength before delivery to
site for erection.
10
Page
POSSIBUILD BUILDING TECHNOLOGIES
Plot No.135, Mythri Nagar – Phase -1, Madinaguda,
Miyapur, Hyderabad – 500045
-------------------------------------------------------------------------------------------------------------
2. Logistics
Delivery of precast element should be planned according to the general erection sequence to minimise
unnecessary site storage and handling. Where possible, it is desirable to transport the precast
elements in to a manner which they can be lifted directly for erection or storage without much change
in orientation and sequence.
Precast elements should be loaded and delivered with proper supports, frames, cushioning and tie
downs to prevent in-transit damage. Adequate packing or protection to the edges of precast elements
should also be provided to minimise risk of damages during transit.
It mainly involves the removal of precast elements from the mould, transportation to the storage yard,
loading and unloading operation and erection of these elements at the job site.
Different sets of lifting points and cast-in-devices will have to be used for various handling stages.
Typically, precast concrete elements are demoulded and lifted from their casting position to storage
yard and delivery to site once they reach the expected concrete strength required. As these elements
have not gained their full designed strength, they are generally more susceptible to damage during
handling. It is therefore important to ensure that they are handled in a way that is consistent with
their shapes and sizes, to avoid excessive stresses or damages.
For elements with large openings, temporary bracing, ties or strongbacks should be provided for safe
handlings.
Fig 11. Bracing of elements for wall panels with larger openings
POSSIBUILD BUILDING TECHNOLOGIES
Plot No.135, Mythri Nagar – Phase -1, Madinaguda,
Miyapur, Hyderabad – 500045
-------------------------------------------------------------------------------------------------------------
4. Storage
The storage area provided in the yard and job site should be adequate to permit easy access and
handling of the precast elements. The area should be relatively level, firm and well drained to avoid
any differential ground settlements which may damage the stored elements.
Appropriate stacking method be used to store the precast elements to prevent any undue stressed
and damages.
Precast wall and façade panels are usually stored in vertical position supporting their own weight using
racks with staibilising wall. Storage condition can be an important factor in achieving and maintaining
panel bowing and warping tolerances. More lateral support should be given to slender panels which
are more likely to bow or warp. To minimise handling, the elements should be stored based on the
erection sequence.
13
Page
POSSIBUILD BUILDING TECHNOLOGIES
Plot No.135, Mythri Nagar – Phase -1, Madinaguda,
Miyapur, Hyderabad – 500045
-------------------------------------------------------------------------------------------------------------
Fig 12. Stacking of wall panels in storage yard in self stabilised storage rack.
The storage area at the job site should preferably be close to the location where the precast elements
are to be installed to minimise the risk of damage by handling.
5. Installation
Proper planning and preparatory works are required before the actual erection of precast concrete
elements to ensure efficient and quality installation.
• Set reference line and offset line to determine the position of the precast elements to be
14
5c. Grouting
• Prepare and apply non-shrink mortar to sear the gaps along the bottom edged of the inner
side of the panel.
• Check the joint width between panels are within design allowances before grouting.
• Non-shrink grout used at the interface with the precast elements should preferably be free
flowing and self compacting in nature so as to ensure good compaction at the joint and to
minimise the risk of cracking.
• Check that all the horizontal joints are properly sealed.
• For corrugated pipe sleeve or splice sleeve connection, prepare and pour non-shrink grout or
proprietary grout in to the pipe inlets provided.
• Non-shrink grout should be prepared in accordance with the specification.
• Keep the installed panels undisturbed for atleast 24 hours.
16
Page
POSSIBUILD BUILDING TECHNOLOGIES
Plot No.135, Mythri Nagar – Phase -1, Madinaguda,
Miyapur, Hyderabad – 500045
-------------------------------------------------------------------------------------------------------------
• For panels with cast-in-situ joints, install the joint rebars as required. Joint rebars should be
correctly placed in accordance with the design specifications.
• Set up forms for the casting of vertical joint. It should be secured properly against plumb outs
and blug outs.
• Carry out concreting casting
• Remove forms after sufficient concrete strength has been achieved.
• For joints between façade walls or between external columns with beams or walls elements,
approved sealant and grout will be installed at later stage.
• The joint gaps should be consistent to allow for proper installation of sealant or grout for
better watertightness.
• For panel with welded connection, place the connecting plate between the panels and carry
out welding as per design requirement.
17
Page
POSSIBUILD BUILDING TECHNOLOGIES
Plot No.135, Mythri Nagar – Phase -1, Madinaguda,
Miyapur, Hyderabad – 500045
-------------------------------------------------------------------------------------------------------------
Prepared by
Pavan Patchigolla, MTech, AMIE,
18