EXCAVATION WORKS
Size of footing = (0.8x 0.8 x 1.25) (9) +(0.8 x1.6 x1.25)(4) = 13.6m3
Size of tie beam = 53.1 x 0.2 x 0.8 = 8.496m3
CONCRETE
a.) Single Footing
total Volume = 1.44m3
using Class A mixture (40kg Portland Cement)
Cement: 1.44m3 x 9.0 = 12.96 say 13 bags
Sand: 1.44m3 x 0.5 = 0.72m3
Gravel: 1.44m3 x 1.0 = 1.44m3
b.) combined footing
total Volume = 1.28m3
using Class A mixture (40kg Portland Cement)
Cement: 1.28m3 x 9.0 = 11.52 say 12 bags
Sand: 1.28m3 x 0.5 = 0.64m3
Gravel: 1.28m3 x 1.0 = 1.28m3
c.) Concrete column
total Volume = 1.08m3
using Class A mixture (40kg Portland Cement)
Cement: 1.08m3 x 9.0 = 9.72 say 10 bags
Sand: 1.08m3 x 0.5 = 0.54m3
Gravel: 1.08m3 x 1.0 = 1.08m3
d.) tie beam
total Volume = 3.186m3
using Class A mixture (40kg Portland Cement)
Cement: 3.186m3 x 9.0 = 28.67 say 29 bags
Sand: 3.186m3 x 0.5 = 1.593m3
Gravel: 3.186m3 x 1.0 = 3.186m3
e.) CHB
(from tie beam to floor line)
Using area method: AT = 37m2
Number of CHB = 37m2 (12.5/m2) = 462.5 say 466pcs. of 4” CHB
For CR:
Total area = 28.47m2
Number of CHB = 28.47m2 (12.5/m2) = 355.88 say356pcs. of 4” CHB
WOODEN COLUMNS
First Floor
Total height = 8.53ft/ column
17 columns ( 5” x 5” x8.53’)
Number of board feet = =302.1 say 303 bdft 5” x 5” x 12” yakal
12
Second Floor
Total height = 8.56ft/ column
17 columns ( 4” x 4” x 8.56’)
Number of board feet = =194.03 say 195 bdft 4” x 4” x 12” yakal
12
FLOOR BEAM
Perimeter length = 60m = 196.8ft
Number of pieces = 196.8ft/ 12’ =16.4 say 15 pcs.
15( 6” x 9” x 12 ’)
Number of board feet = = 810 bdft 6” x 9” x 12” yakal
12
ROOF BEAM
Perimeter length = 68m =223.04ft
Number of pieces = 223.04ft/ 12’ =18.59 say 19 pcs.
19 ( 4” x 8” x 12 ’)
Number of board feet = = 608bdft 4” x 8” x 12” yakal
12
WALLS
Total area =177.5 (2) =355m2
Total pcs. of fiber cement board= 355m2 / 2.97m2 per piece= 119.53 say 120pcs. hardiflex
For nails = 355m2(0.033) = 11.72 say 12kg of finishing nails
WALL STUDS
Using area method: using 2”x3” spaced at 0.6m O.C.
Total area =122.64m2
Total board feet = 122.64m2 (6.898bdft /m2) = 845.97bdft mahogany
For nails = 122.64m2(0.05) = 6.132 say 7kg of finishing nails
FLOOR JOISTS
Total board feet = 632 bdft 3” x 5” x 12” lauan
For bridging = 150 bdft 3” x 5” x 12” lauan
Nails = (782/1000) (15) = 12kg of 3” CW nails
SECOND FLOORING
Total board feet = 786.66 say 787bdft 1” x 20” x 10’ mahogany board
Nails = (787/1000) (15) = 12kg of 2.5” CW nails
STAIRS
a.) Thread =12pcs (1”x 10” x 6’)/12 = 60bdft yakal
b.) Stringers = 4pcs (2” x 15” x 10’) /12 = 100bdft yakal
Nails = (160/1000) (15) = 3kg of 3” CW nails
TILE WORKS
a.) tiles (ground floor)
total area = 58.5m2
number of tiles using 60cm x 60 cm floor tiles:
= 58.5m2 x 3/sq.m = 176 pcs. 60cm x 60 cm floor tiles
tiles (bathroom)
total area = 22m2
number of tiles using 30cm x30 cm floor tiles:
=22m2 x 12/sq.m = 264 pcs. 30cm x30 cm floor tiles
b.) cement mortar and joint filler
cement: 80.5m 2x 0.3 = 25 bags
tile adhesive: 80.5m 2 x 0.11 = 8.86bags
cement mortar: 80.5m 2x 0.086 = 6.92 bags