Академический Документы
Профессиональный Документы
Культура Документы
EIA can ensure that the subjectivity and duplication of effort are maintained and
the short term and long term consequences of inappropriate decisions are avoided. In
order to be effective, EIA should be implemented in the early stages of projects
planning and design. Instead of utilizing it after the design stage is completed, it should
be an integral component in project design. The EIA procedure should be applied to all
actions likely to have a significant environment effect. It should have following
objectives:
1
Quantities of Waste Discharges from the Plant
But the regulatory requirements and the cost of complying with them that make it
difficult for industry to give waste minimization the priority and resources it deserves if
it is to have broad implementation. In practice, waste minimization is sometimes
subordinated to pollution control, even though reducing waste can be most effective
way to prevent environmental risk. Pollution control has dominated over waste
reduction for a long period of time and is only being reserved. There are several
approaches to pollution prevention and waste minimization:
2
Summary of Waste from Plant
The waste water from the bottom of quench tower must be decanted and sent for
further processing before discharge.
It is seldom possible to convert 100% of the raw materials into sale able products,
so there is almost always some waste or residual. It is follows the second
thermodynamics law, which state that, more entropy is generate when the work is
increased. Direct discharge of waste produced from plant to environment may cause of
3
pollution and destroy the balancing of the ecosystem. Therefore, there were need some
proper planning of waste management include it waste treatment unit, ways to dispose
and also the cost of waste operating.
Most of chemical plant will discharge waste water from their manufacturing plant.
When water is fed into a process or the produces water, waste water is usually one of
the process effluents. This waste water may contain lot of chemical or waste that can
give bad impact to the environment. So that, before discharge it into river, it must be
treated well and comply the parameters with Environmental Quality Act 1974, in order
to follow the standard of waste water discharge from Department of Environment
(DOE). For this chapter, the waste treatment strategy for Butadiene plant has been
planned carefully in order to meet the regulation of Environmental Quality Act 1974
(amended 1996) Malaysia. Before the wastes are discharged to the environment, some
consideration must be done:
Consider the economic aspect, whether the waste can be recover and sell as a
product or not.
Consider the waste properties, whether it can be discharged directly to the
environment or we need to treat it first.
Consider from the safety reason, whether it is dangerous to the environment or
not.
Waste minimization and treatment plant must fulfill the objectives below:
4
Butene
Air Steam
Oxidative Dehydrogenation
1243.11 ton/hrs
Waste
Quench Tower Water
Water
Treatmen
31.52 ton/hrs
Flue gas
Absorption Tower Flue treatment
Gas company
Butadiene
5
6.1.2 Treatment of Waste
For our plant, we have proposed several methods to dispose our waste based on
the type of wastes in our plant. In the production of Butadiene, it considers two types of
wastes which are gaseous and liquid.
Waste Water
The method use for dispose the liquid waste is the waste water treatment. This is
because the liquid waste product is the water. So, the best method to treat the waste
water to is through the waste water treatment. In waste water treatment, it consist two
stages of treatment which are primary treatment and secondary treatment. In primary
treatment, it will undergo five treatment processes which are screening, grit removal,
equalization, sedimentation (solid-liquid separation) and flotation. While for secondary
treatment, it will undergo the biological treatment that are first is activated sludge
process and second is trickling filter process.
6
Then, for the trickling filters, it consists of a bed of a highly permeable medium to
which microorganisms are attached and through which wastewater is percolated or
trickled. The examples of bed coarse material are stones, slats or plastic materials
(media), over which waste water applied. This is because the microorganism that
biodegrade the waste form a film on the media and this process is known as the attached
growth system. Wastewater is typically distributed over the surface of the rocks by a
rotating arm. The purpose of the media is to provide large amount of surface area where
the microorganism cling and grow, in the slime on the rocks as they feed on the organic
matter. It is also not primarily a filtering or straining process.
Before the study is conducted, the details information about the entire process
must be available including process flow diagram (PFD) and process and
7
instrumentation diagram (P&ID), detailed equipment specifications, material of
constructions, energy and material balance as performed in previous tasks. The full
study requires a committee of cross-section of experience plant, laboratory, technical
and safety professionals. A list of guide word is shown in Table 6.2.
NO, NOT NONE The complete negation No part of the design intention is
of the intention achieved but nothing else happens
MORE, Quantitative increase Applies to quantities such as flow
HIGHER, rate and temperature and to activities
GREATER such as heating and reaction
LESS, LOWER Quantitative decrease Applies to quantities such as flow
rate and temperature and to activities
such as heating and reaction
AS WELL AS Qualitative increase All the design and operating
intentions are achieved along with
some additional activity, such as
contamination of process streams
PART OF Qualitative decrease Only some of the design intentions
are achieved some are not
REVERSE The logical opposite of Most applicable to activities such as
flow or chemical reaction. Also
applicable to substances, for
example, poison instead of antidote
OTHER THAN Complete substitution No part of the original intention is
achieved – the original intention is
replaced by something else
SOONER THAN Too early or in the Applies to process steps or actions
wrong order
LATER THAN To late or in the wrong Applies to process steps or actions
order
WHERE ELSE In additional locations Applies to process locations, or
locations in operating procedures
In this task, HAZOP study were being carried out the all the equipment used in
the production of butadiene. The equipment are Blower, Furnace, Mixer, Reactor, Heat
Exchanger, Condenser, Pump, Quench Tower, Absorption Tower and Stripping Tower.
8
MIXER
Process: mixing the outlet feed from H-101, C-101 and H-102
Section: Mixer M-101
Item STUDY GUIDE
NOTE PARAMETER WORDS CAUSES CONSEQUENCES ACTIONS
1A • Stirrer motor malfunction • No mixing • Interlock with feed line
stirrer agitation None • Power failure • Possible accumulation of • Training should be
unreacted materials given to the operators
1B • Stirrer motor controller • None • Check motor
Higher fails functioning
• High motor speed
2A • rupture in pipeline or • pressure build up in the • Regular inspection on
equipment pipeline the pipelie
• clogging at inlet pipeline • loss of cooling, possible • By-pass pipeline is
pipeline flow None • controller fails and runaway installed
closes valve • Place controller on
critical
instrumentation list
2B • clogging at outlet stream • damage part in the reactor • maintenance on
higher
• flow control valve fail • lower conversion of pipeline
9
open butadiene • install an alarm for
warming
• installation of safety
valve to divert the flow
2C • Leakage in the pipeline • Leakage in the pipeline • Install a by-pass
• Flow control valve fail causes explosion pipeline
lower close • Maintenance on
• Partially plugged in the pipeline
pipeline
2D • Contaminants in pipeline • Incorrect operation of • Install filter with
• Impurities from the system maintenance
As well as
product • Feed stream impurities
10
backpressure inlet valve installed
• Install check valve
2G • wrong material is chosen • Depends upon the • Plant procedure to
substitution, requires provide check on
testing potential material chosen before
Other than
substitution based on charging of material
availability of other
material at site
2H • Poor communication • Corrosion in the mixer • Proper SOP follow and
between the crew is to be discussed
Faster Corrosion in the batch
mixer Proper SOP follow
and is to be discussed
2I • Operator error • Temperature rises • regular inspection on
Slower
• possible runaway the pipeline
11
Reactor
Process: Butadiene production from n-butene by using oxidative dehydrogenation process
Section: REACTOR R-101
STUDY GUIDE
Item PARAMETER CAUSES CONSEQUENCES ACTION
NOTE WORDS
1A • rupture in pipeline or • pressure build up in the • Regular inspection on
equipment pipeline the pipeline
• clogging at inlet pipeline • loss of cooling, possible • By-pass pipeline is
Inlet
flow No • controller fails and runaway installed
pipeline
closes valve • Place controller on
critical
instrumentation list
1B • clogging at outlet stream • damage part in the reactor • maintenance on
• flow control valve fail • lower conversion of pipeline
open butadiene • install an alarm for
higher
warming
• installation of safety
valve to divert the flow
1C • Leakage in the pipeline • Leakage in the pipeline • Install a by-pass
lower
• Flow control valve fail causes explosion pipeline
12
close • Maintenance on
• Partially plugged in the pipeline
pipeline
1D • Contaminants in the • More pressure in reactor • Install higher alarm
pipeline • Blockage in pipeline pressure
As well as
• Regular inspection on
the pipeline
1E • Valve leakage • The ultimate product will • Prior test is to be
Part of be of less quality than the conducted, QA/QC
desired product performed
1F • Too high pressure in the • Pressure builds up in the • Regular inspection on
mixer pipeline the pipeline
Reverse • Backflow due to high • Failure of process fluid • By-pass pipeline is
backpressure inlet valve installed
• Install check valve
1G • Water sources • May cooling ineffective • Install temperature
Other than contaminated • Effect the reaction alarm low
• Impurities in feed line
1H Faster • Wrong material is • It forms non-uniform • Discuss roles and
13
chosen from plant or mixture if the recipe not responsibilities of all
poor communication followed properly the crew members
1I • Operator error • Temperature rises • regular inspection on
Slower
• possible runaway the pipeline
2A • plugged cooling pipeline • loss of cooling, possible • Regular inspection on
• controller fails and runaway the pipelie
Cooling
flow No closes valve • By-pass pipeline is
pipeline
• cooling water service installed
failure
2B • flow control valve fail • reactor cools • maintenance on
open • reactant concentration pipeline
higher
builds • install an alarm for
warming
2C • partially plugged cooling • Leakage in the pipeline • Place valves on critical
line causes explosion instrumentation list
• partial water source
lower
failure
• control valves fail to
respond
14
2D • Contaminants in water • corrosion • install filter with
As well as
supply maintenance procedure
2E • partially plugged cooling • Leakage in the pipeline • Place valves on critical
line causes explosion instrumentation list
• partial water source
Part of
failure
• control valves fail to
respond
2F • Failure of water source • Loss of cooling • Install cooling water
resulting in backflow • Possible runaway flow meter and low
Reverse
• Backflow due to high flow alarm
pressure
2G • Cooling started early • Effect the process • Regular inspection on
Faster
the control system
2H • Operator error • Temperature rises • interlock between
Slower • possible runaway cooling flow and feed
reactor
3A • Failure of temperature • Lower conversion of • Regularly checkup the
Temperature Higher transmitter and controller butadiene control system of the
reactor
15
• Insufficient cooling water • Reactor deactivated or • Training should be
damage given to the operators
• Immediate shut down
3B • Failure of temperature • Build up reactant in the • Regularly checkup the
transmitter and controller catalyst bed control system of the
Lower • Higher heat transfer from • Incomplete reaction reactor
steam to reactor • Install low temperature
alarm
• Failure of temperature • Lower conversion of • Regularly checkup the
transmitter and controller butadiene control system of the
Reactor • Catalyst bed deactivated reactor
temperature Higher
itself or damage • Training should be
given to the operators
• Immediate shut down
4A • Failure of temperature • Build up reactant in the • Regularly checkup the
controller catalyst bed control system of the
Lower • Higher heat transfer from • Incomplete reaction reactor
steam to reactor • Install low temperature
alarm
16
5A • Inadequate volume of • Pressure build up can • Installation of relief
vents cause explosion or rupture valve
Higher
• Incorrect vent set pressure the reactor • Regular check up on the
Pressure
for vents • Exploding pipeline
• Relief valves isolated • Chemical breakdown • Pressure sensor placed
• Thermal overpressure on the inlet pipeline
5B • Low flow rate of reactant • Gas release • The control system
• Pressure drop existence in • Priming should be well designed
Lower the catalyst bed • Exploding and suits the operating
• Inadequate mixture of • Imploding requirements of
steam and butadiene equipment used.
17
QUENCH TOWER
18
• Backflow due to high • Failure of upstream • By-pass pipeline is
backpressure process units installed
• Install check valve
2A Vessel • slow flow of water input • unable to stop the • Alarm system installed
• fast flow of product gas reactions of the reactants • regular check-up and
input • undesired side reactions maintenance on the
• pump failure and side products control system (on
• Water content remains in water inlet flow)
gaseous form installed
• failure in the separation • scheduled and regular
Temperature Higher and removal of water from check-up on the
the product mixture operations and
• gaseous product with high efficiency of the pump
content of water P-101
• check valve, by-pass
valve installed
• recycle stream installed
after the pump
2B • Fast flow of water • flooded or the level of • regular check-up and
• Failure of the flow water in the vessel over maintenance on the
transmitter and controller the height limit control system (on
on the upstream inlet gas • ineffectiveness in water inlet flow)
(stream 11) separation of water from installed
• Failure of the pump P-101 the gas products • scheduled and regular
Lower
check-up on the
operations and
efficiency of the pump
P-101
• check valve, by-pass
valve installed
19
• recycle stream installed
after the pump
3A Pressure • Failure of the flow • Overpressure in the vessel • Alarm system installed
transmitter and controller due to overflow of product • Relief valve (V-24)
on the upstream inlet gas gas inlet installed
(stream 11). • Insufficient amount of • Regular check-up and
• Failure of the pump P-101 water in the vessel to cool maintenance on the
• fast flow of product gas down the product gases control system (on
(stream 11) and slow flow for water separation, water inlet flow)
of water input (stream 15) temperature increases and installed.
build up high pressure in • scheduled and regular
Higher the vessel check-up on the
operations and
efficiency of the pump
P-101
• check valve, by-pass
valve installed
• recycle stream installed
after the pump
•
3B • Failure of the flow • Excess amount of water • Relief valve (V-24)
transmitter and controller build up, flooded or installed
on the upstream inlet gas causes the level of water • Regular check-up and
(stream 11). in the vessel over the maintenance on the
Lower • Failure of the pump P-101 height limit control system (on
• slow flow of product gas • ineffectiveness in water inlet flow)
(stream 11) and fast flow separation of water from installed.
of water input (stream 15) the gas products by • scheduled and regular
limiting the time for the check-up on the
scrubbing of the gas
20
products operations and
efficiency of the pump
P-101
• check valve, by-pass
valve installed
• recycle stream installed
after the pump
4C Lower • Failure of the flow • slightly increased the • Regular check-up and
21
transmitter and controller temperature in the vessel maintenance on the
on the upstream inlet gas leads to insufficient heat level control system
(stream 11). for water removal from installed.
• Failure of the pump P-101 the gas products • scheduled and regular
• Insufficient of water input • no significant effect check-up on the
operations and
efficiency of the pump
P-101
5B • controller fails to control • pressure inside the vessel • regular check-up on the
the opening of valve (V- too low operations and
Higher
25) efficiency control
system elements
5C • controller fails to control • slow removal of water • regular check-up on the
the opening of valve (V- • Excess amount of water operations and
25) build up, flooded or efficiency control
Lower
causes the level of water system elements
in the vessel over the
height limit
5D • controller fails to control • unable to remove water • check valve and drain
Reverse the opening of valve (V- valve installed
25)
22
• vessel is under pressure
23
Heat Exchanger
24
output fluid
1F • Low pressure at the • Slower the process • Install the flow sensor
Slower water inlet
2A • The sensor of the • The flow of the fluid • Change the pressure sensor
pressure broke become faster.
25
respond column. replace the pipeline if
• Pipe leakage. • Overheating of required
• Partially clogged distillation column.
pipeline • Diminished flow rate of
mixture
4A • Failure of the • Cause the outer shell to • Replace the old sensor
High
temperature sensor have high temperature with the new sensor
Temperature
4B • Failure of the • Less heat transfer rate • Replace the old sensor
Low
temperature sensor with the new sensor
5A • The sensor of the • The flow of the fluid • Change the old pressure
pressure broke becomes faster. sensor with the new sensor
Shell
High • The efficiency of the
heat exchange becomes
Pressure
lower.
5B • The error in the sensor’s • The rate of heat • Change the old pressure
Lower signal exchanger become sensor with the new sensor
higher
6A
Chemical • Failure of the inlet valve • The desired temperature • Install the flow sensor and
None
Flow to open can’t be achieved replace the broken valve
Mixture
6B High • Failure of the inlet valve • The temperature of the • Install temperature
26
Inlet to close output stream is lower indicator before and after
than the desired the oxygen pipe.
temperature • Install the temperature
alarm loggers.
6C • Pipe leakage • Rate of heat exchanged • Set the temperature alarm
Low
become higher
7A • The sensor of the • The flow of the fluid • Change the old pressure
pressure broke become faster. sensor with the new sensor
High • The efficiency of the
heat exchange become
Pressure
lower.
7B • The error in the sensor’s • The rate of heat • Change the old pressure
Lower signal exchanger become sensor with the new sensor
higher
27
Condenser
28
1D • Incorrect operation system • Gas entrainment • Regular inspection on
As well as
• Valve leaking • leakage the operation system
2A • Failure of temperature • Effect the process • Regularly check up the
transmitter and controller • Heating medium control system of the
Inlet
Temperature Higher • Cooling water failure leak into the reactor
pipeline
process • Training should be
given to the operators
2B • Failure of temperature • Loss of heating • Regularly check up the
controller control system of the
Lower condenser
• Install low temperature
alarm
3A • Gas breakthrough • Thermal • proper maintenance and
Outlet
pressure higher • Inadequate volume to overpressure operator alert
pipeline
vents • imploding
3B • Undetected leakage • Drainage • install check valve
Lower
• Control system failure • scaling
29
Absorption Tower
30
2C Lower • pump under speed • vessel under pressure • Regular maintenance on
• low separation effect the pump
2D Reverse • upstream under pressure • spoilage of pump • Check valve installed
• downstream overpressure • Immediate shut down
• Check up and regular
maintenance on the
equipment
3A Vessel Temperature Higher • Ratio control system fails • Low separation efficiency • emergency shut down
to control the input of • Product gases wasted as • regular checkup and
absorbent to product not fully absorbed maintenance on the
gases • loss due to release of control system elements
• failures of upstream heat butadiene via flue gases • Maintenance or
exchanger and condenser replacement on wore
out equipment
3B Lower • Ratio control system fails • no significant effect • regular checkup and
to control the input of maintenance on the
absorbent to product control system elements
gases •
4A Pressure Higher • Ratio control system fails • vessel overpressure • Relief valve installed
to control the input of • insufficient amount of • regular checkup and
absorbent to product absorbent leads to low maintenance on the
gases separation effect control system elements
• fast flow of product gases • loss due to release of • by pass valve installed
input butadiene via flue gases
• Control system fails to
control the opening of
valve V-34
4B Lower • Ratio control system fails • under pressure • Relief valve installed
to control the input of • no significant effect • regular checkup and
31
absorbent to product maintenance on the
gases control system elements
• slow flow of product
gases input
5A Level Higher • Level control system • low separation efficiency • regular checkup and
(sensor and transmitter) • loss due to release of maintenance on the
fails to control the butadiene via flue gases level control system
opening of valves V-21 • flooded, exceed level limit elements
• by pass valve installed
5B Lower • Level control system • low separation efficiency • regular checkup and
(sensor and transmitter) • loss due to release of maintenance on the
fails to control and open butadiene via flue gases level control system
the valve V-21 elements
• failures on pump P-102 • maintenance and
replacement for pump
6A Waste flue low No • Pressure control system • vessel overpressure • by pass valve installed
gas outlet fails to open the valve V- • regular checkup and
(stream 34 maintenance on the
20) pressure control system
elements
6B Higher • Pressure control system • fast flow of gas reduces • emergency stop
fails to control the closing the separation efficiency • regular checkup and
of the valve • loss of butadiene via flue maintenance on the
• valve opens too wide gas pressure control system
elements
6C Lower • Pressure control system • slow flow of gas released • relief valve installed
fails to control the • vessel overpressure after a • regular checkup and
opening of the valves period maintenance on the
32
• valve opens to narrow pressure control system
elements
7A Absorbent Flow No • Flow control system • liquid absorbent build • open drain valve
outlet fails to open the valve up the level inside the installed
(stream V-36 vessel up to the limit • regular checkup and
21) and flooded maintenance on the
• vessel overpressure flow control system
elements
7B Higher • Level control system • fast flow of absorbent • regular checkup and
fails to control the out from the vessel maintenance on the
closing the valve V-36 • less absorption level control system
• Valve opens too wide efficiency elements
7C Lower • Level control system • liquid absorbent rise to • regular checkup and
fails to control the the level limit and maintenance on the
opening the valve V- flooded after some level control system
36 times elements
• Valve opens too wide • less absorption • open drain valve
efficiency installed
7D Reverse • downstream • influence and interrupt • check valve
equipment over the separation and installed
pressure absorption efficiency
33
Stripping Tower
34
(stream the valve V-38 • valve damage the pressure control
22) system elements
• by pass valve
installed
2B • Pressure control • fast flow of butadiene • regular check up
system fails to control out from the vessel and maintenance on
Higher the closing of the • lower purity of the pressure control
valve V-38 butadiene produces as system elements
• valve open widely shorten stripping time
2C • Pressure control • slow flow of butadiene • regular check up
system fails to control out from the vessel and maintenance on
the opening of the • lower purity of the pressure control
Lower valve V-38 butadiene produces system elements
• valve close widely (condensed) as
lengthen stripping
time
2D • vessel under pressure • increase striping work • check valve
load installed
• waste of fuel
Reverse
• low purity of
butadiene produced
35
system fails to control absorbent into and maintenance on
the closing of the absorption tower the temperature
valve • lower the absorption control system
• valve opens widely efficiency elements
36
Furnace
37
• Shortage of fuel usages adequate heating heating system
• Control valve failure
3A • Failure of relief valve • Pressure built up in the • Regular check-up held
• Excessive input of fuel furnace causing explosions on the valves involved
Pressure gas • High pressure gas at output • Recommend
Higher
stream consulting
• Changes in phase from gas manufactures to
to liquid establish effect
3B • Failure of pressure • Low pressure input to the • Consider diversity of
Lower
transmitter and controller mixer fuel supply
• Loss of fuel gas supply
4A • Failure of the inlet valve • The desired temperature • Install the flow sensor
None to open can’t be achieved and replace the broken
Chemical valve
4B Mixture • Failure of the inlet valve • The temperature of the • Install temperature
Flow to close output stream is lower than indicator before and
Inlet
High the desired temperature after the oxygen pipe.
• Install the temperature
alarm loggers.
4C • Pipe leakage • Rate of heat exchanged • Set the temperature
Low
become higher alarm
5A • The sensor of the pressure • The flow of the fluid • Change the old
Pressure High broke become faster. pressure sensor with
• The efficiency of the heat the new sensor
exchange become lower.
38
5B • The error in the sensor’s • The rate of heat exchanger • Change the old
Lower signal become higher pressure sensor with
the new sensor
39
Storage Tank
STUDY GUIDE
Item PARAMETER CAUSES CONSEQUENCES ACTION
NOTE WORDS
40
close pipeline
41
pressure for vents storage tank pipeline
42
compressor inlet materials in the system to trigger the
compressor feed alarm system and shut
stream, builds down the plant if there
up pressure is no flow
which might end
up in runaway
reaction
Low • Low reactant supply • Slower the • Install the flow sensor
4D pressure production line
of the plant
43
Pump
Section: Pump
STUDY GUIDE
Item PARAMETER CAUSES CONSEQUENCES ACTION
NOTE WORDS
2A Flow Higher • Pump over speed, • Possible runaway • Install a high flow
detector alarm
44
• Pressure is too high • Explosion system at the outlet
stream to alert the
operator
45
cooling process • Regular inspection
on the water supply
46
6.2 Environmental Protection
6.2.1 Waste management and treatment plant
Table 6.3: The amount of waste generated in this plant is summarized as following:
Stream Amount
Waste Source State
No. (ton/hr)
Planned Emission
• Wastewater
• Light waste
As mentioned above, wastewater is being treated before discharging. Light gas is sell
out to flue gas treatment company. In this plant, no liquid waste is produced.
47
Fugitive Emission
The light gas waste may release or leak to surrounding when the occurrence of
the pipeline leakage of valve failure. Leaks from pressurized process equipment
generally occur through valves, pipe connections, mechanical seals or related
equipment. Fugitive emission also occurs at evaporative sources such as storage tanks.
This is because of large number or potential leak sources at large facilities and the
difficulties in detecting and repairing some leaks, fugitive emission can be significant
proportion of total emissions. Even though the quantities of leaked gases may be small,
leaks of gases that have serious health or environmental impacts can cause a significant
problem.
To minimize and control leaks at process facilities operators carry out regular
leak detection and repair activities. Routine inspections of process equipment with gas
detectors can be used to identify and estimate the leak rate in order to decide on
appropriate corrective action. Proper routine maintenance of equipment reduced the
likelihood of leaks. New technologies are under development that could revolutionize
the detection and monitoring of fugitive emissions. One technology, known as
differential adsorption light detection and ranging (DIAL) can used to remotely measure
concentration profiles of hydrocarbons in the atmosphere up to several hundred meters
from facility. Portable gas leaks imaging cameras are also a new technology that can be
used to improve leak detection and repair, leading to reduced fugitive emissions.
Emergency Emission
The leakage or exposure of flammable gas such as light hydrocarbon gases and
carbon dioxide from the pipeline will cause the occurrence of explosion. The failure of
the control action of the safety or control valve will lead to uncontrollable of pressure
and temperature occur in the reactor, causing the product spill, reactor rupture and
explosion.
The maintenance of the pipeline, valve and equipment are needed to prevent fire
and explosion to happen. Safety practices are given to personnel to increase their
48
awareness and emergency knowledge. The control action of all valves must always be
well controlled to prevent any accident to occur.
By-products
Waste treatment refers to process held to ensure the waste concentration meets
the standard requirement and has least practicable impact on environment. Besides
wastes are regenerated or treated for the firm usage as energy source, thus reduces the
utility cost of the firm. Treatment is also conducted for certain materials to produce less
hazardous materials or make the waste safer to transport, store or dispose. In this plant,
the waste gas such as carbon dioxide, nitrogen and oxygen were produced as by-product
in oxidative dehydrogenation of n-butene. The quality of effluents discharged met the
specification of Environmental Quality (Sewage and Industrial Effluents) Regulation
1979 and Environmental Act (Clean Air) Regulations 1978. In fact, it has been decided
to sell out the by-products from this firm to other company which uses the material as
raw materials or to the supplier company for proper pretreatment.
Catalyst
The catalyst used in the reactor is ferric sulfate which is the most suitable catalyst for
oxidative dehydrogenation of n-butene. Typical lifetime for catalyst is from 3-5 years
(Wilkinson et al., 2008). It has been estimated that the lifetime of the catalyst reduced to
approximately 4 years as average lifetime. In this plant, the waste catalyst will not be
processed as it will be send back to the supplier company for proper treatment before
disposal.
49
Liquid Waste Management
Wastewater treatment process is used to treat the wastewater effluents from the
industries to ensure the safe disposal into water sources. Disposal of wastewater without
treatment causes severe effects to the water sources affecting most of the populations
especially for the effluent that has high COD and BOD, large amount of suspended
solid and even containing toxicants.
In this plant, large amount of water is consumed. Water is used as steam and
cooling water. Cooling water mainly refers to the use of water at the heat exchangers
and condensers for cooling effects and it can be recycled. On the other hand, steam is
mixed with n-butene and catalyst to maintain adequate heat for the oxidative
dehydrogenation process which occurs in the reactor with alternately placed with
furnace. Since the steam is cooled and condensed out throughout the process, treatment
is necessary to reduce the release condition to harmless standard level. The standard
requirements for wastewater are pH 6-9, BOD ranged from 20-50 mg/L and COD from
120-200mg/L.
Since the wastewater from this plant did not reacts with the reactants or products
and separated in liquid phase from the gas phase products, simple wastewater treatment
is applicable to treat the waste water effluent. Even though the waste water discharged
is claimed to be pure water, it should be treated before discharge to ensure there is no
harmful components or hydrocarbon residues contained.
50
treatment stages that are in use today for treating large quantities of sewage. The flow
diagram of the waste water treatment is as illustrated as attached.
Figure 6.2: Activated sludge wastewater treatment plant (Davis and Cornwell,
2008)
The flow, process unit designs and functions of wastewater treatment are as
summarized in the following table.
Table 6.4: Process units, designs and functions in activated sludge wastewater
treatment plant
Primary treatment
51
water flow to a
point
• a damp or large • improve the performance of the
basin to store treatment plant
wastewater • increase plant’s useful capacity
• pump is used to
Primary
pump wastewater
settling
to down stream
tanks
• agitator installed
to prevent odors
and deposition of
solids
• large tanks • to settle and remove settle able
• solids settle out substances
of water by • to skim off top layer of oils (if any)
Primary
gravity • 50-65% suspended solid removal
52
sludge in the
digester to
acclimatise the
incoming raw
sludge.
• could be sand or • to drain away water
Drying
Bed.
soil land • dried porous humus-like sludge cake
• rotary drum can be sold as fertiliser
Secondary treatment
For this plant, activated sludge is carried out for biological treatment on the
wastewater effluent. By using this treatment method, the microorganisms oxidize the
organic carbon in the wastewater to produce new cells, carbon dioxide and water.
Among all, the aerobic bacteria are the most common organisms, aerobic, anaerobic,
and/or nitrifying bacteria along with higher organisms can be present. The exact
composition depends on the reactor design, environment, and wastewater
characteristics. During aeration and mixing, the bacteria form small clusters, or flocs.
53
When the aeration stops, the mixture is transferred to a secondary clarifier where the
flocs are allowed to settle out and the effluent moves on for further treatment or
discharge. The sludge is then recycled back to the aeration tank, where the process is
repeated. Clearly, this wastewater treatment plant produces no harm to the environment
as no chemical absorbents, coagulants or flocculants are used. The waste sludge
produced is biodegradable and has extra benefits to be used as fertilisers shows that this
plant is able to be operated as zero discharge unit which follows the concept of green
technology.
Refer to attachment
54
6.2.2 The effect of Building and Operation on the Environment and Surrounding
In order to build this butadiene production plant, every activity involved in the
construction and operation of the plant needed to be assess to evaluate the impacts to
the environment and surrounding. Basically, the major contributors to the
environmental issues involved the plant construction and plant operation.
Plant Construction
56
Plant Operation
Table 6.6: The impacts of plant operations, causes and mitigation measures
Impacts Causes Measures
57
of water is consumed for sources like river
the reaction ( in steam) and etc.
also the quenching process
( in liquid water) other than
cooling water for heat
exchangers. This waste
water has probability to
contain the residue of
hydrocarbons even though
assumption of pure water is
discharged.
58
6.2.3 Cost of total Waste Management system
Diameter: 5.5m
59
Diameter: 5.5m
Chlorination − unaffected by pH
Chamber − nontoxic
− no secondary
pollution
Quantity: 1 Anaerobic digester 157425
60
Layout of wastewater treatment plant
Primary
Settling
Tank
Wastewater Equalization
effluent Basin
Bar Grit
rack Chamber Primary
Settling
Tank
61
6.3 Engineering Ethics in Plant Design
Based on the fundamentals principle, engineers should uphold and advance the
integrity, honor and dignity of the engineering profession by:
a. Using their knowledge and skill for the enhancement of human welfare.
b. Being honest and impartial, and serving with fidelity the public, their
employers and clients.
c. Striving to increase the competence and prestige of the engineering
profession.
d. Supporting the professional and technical societies of their disciplines.
62
Code of Ethics
Codes of ethics are written by specific groups of people for specific groups of
people, each group having its own purpose for existence and its own means of
accomplishing its purpose. Codes of ethics are to be reflections of the morally
permissible standards of conduct which members of a group make binding upon
themselves.
The ethics adopted by ICM are similar to those introduced by the Board of Engineers
Malaysia (BEM). In general, there are total of 5 ethics:
1) A Registered Engineer shall at all times hold paramount the safety, health and
welfare of the public.
2) A Registered Engineer shall undertake assignments only if he is qualified by
education & experience in the specific technical fields in which he is involved.
3) A Registered Engineer shall issue public statements only in an objective and
truthful manner.
4) A Registered Engineer shall act for each employer or clients as faithful agent or
trustee.
5) A Registered Engineer shall conduct himself honourably, responsibly, ethically
and lawfully so as to enhance the honour, reputation and usefulness of the
profession
63
6.3.1 Ethical Problem and Solution
The ethical arises when design the plant for example in calculating all the
theoretical data for every single unit due to the limited data given. The ethical problems
in plant design such as plant safety, public health and lawful in terms of allowable
parameter. The plant was design accordingly to the code of the ethics for engineer in
order to prevent the accident when the whole plant is applied or in a real industry.
As an engineer, we have to ensure that the design in black and white which can be
worked and constructed in real world as well as the efficiency in dealing with the
reliability of plant in the world. This could be done when the design of units is mostly
based on the sufficient data and information while the units that the data was limited are
no longer reliability since we lose a promoting method to scale up the whole plant in
reality and practically. Hence, we try to find all the information about the unit in library,
read the journal that have similar unit and even ask the related person who has precious
working experience in real plant in order to get a supportive data in our plant design.
On the other hand, we cooperate within our group members and try to come out
with the best solution together for example we take into account on each group
member’s opinion politely whenever there’s a conflict arises.
64
6.3.2 Ethical Issues
During design plant, we are not ignoring the ethical issues when we put the public
safety above the cost of the plant. Additionally, the safety features such as safety
blanket should be incorporated within the storage tank for safety purpose. A sensitive
and efficient control system is necessary for all the units operation that operated at
temperature and pressure higher than ambient in order to maintain the operating
condition at safe level.
Besides that, all the equipment or unit operation are built and buy according to the
standard size and material made from. There is no more lie in construct this plant in
order to reduce the capital cost of the plant construction. Even though there may need to
spend for very long period of operation just to gain back the profit, the situation are still
accepted because the plant need to compensate for huge responsible if one day have
destroyed the health of public and ecosystem due to ignoring the ethical issues to make
profit.
65
6.3.3 Good Ethics in Plant Design
Breaking the engineering ethics code could not be avoided due to lacking of time
especially when the design tasks need to be submitted in short period of time. Then, the
condition is worse as there are weekly assignments on plant design. Due to this
problem, some of the equipment is designed wrongly. Knowing that this should not be
practiced by professional engineer as it is not an act of honesty, the particular
equipment design are review back after the submission of the report so that the
correction on the equipment design could be made.
The code of ethics should be practiced when performing a plant design project.
This is because the fake value in the project can lead to the devastative consequence to
the constructed plant. The professional engineer should be responsible for the action
that he made and play an important role to conserve the environment by minimizing the
hazards of the plants towards the public health and environment. As an engineer, he will
be respected if one’s work is performed sincerely and honestly, take responsible on the
decision made, honest in writing design report without any cheating and put the public
safety and environment health on top of all stuff.
66
References
ATTACHMENT
Refer following page
67