CRONOGRAMA VALORIZADO DE OBRA

MANTENIMIENTO RUTINARIO DE CAMINOS VECINALES NO PAVIMENTADOS, CUENCA LACCO YAVERO - SAN MARTIN, TRAMOS: R-187, CU-682, R-205, R-206, CU-684, R-181,
CU-683, R-186, R-182, R-183, R-184, R-185, R-186, DEL DISTRITO DE QUELLOUNO - LA CONVENCION - CUSCO

FEBRERO MARZO ABRIL MAYO


ITEM DESCRIPCION UND METRADO PRECIO S/. PARCIAL S/. TOTAL
Parcial % Parcial % Parcial % Parcial %
01 ACTIVIDADES PRELIMINARES 13,165.42 4,820.77 36.62% 4,703.35 35.73% 3,641.30 27.66% 13,165.42
01.01 MOVILIZACION Y DESMOVILIZACION DE EQUIPOS (SUBCONTRATO) est 1.00 2,000.00 2,000.00 2,000.00 2,000.00
01.02 TRAZO Y REPLANTEO (EN CARRETERAS) km 136.58 81.75 11,165.42 2,820.77 4,703.35 3,641.30 11,165.42
02 ACTIVIDADES PROVISIONALES 3,300.00 2,211.00 67.00% 613.80 18.60% 475.20 14.40% 3,300.00
02.01 CAMPAMENTOS mes 3.00 600.00 1,800.00 1,800.00 1,800.00
02.02 SALUBRIDAD glb 1.00 1,500.00 1,500.00 411.00 613.80 475.20 1,500.00
03 MANTENIMIENTO DE TRANSITO TEMPORAL Y SEGURIDAD VIAL 21,016.34 19,036.34 90.58% 1,980.00 9.42% 21,016.34
03.01 EQUIPOS DE PROTECCION PERSONAL glb 1.00 5,540.00 5,540.00 5,540.00 5,540.00
03.02 SEÑALIZACION TEMPORAL DE TRANSITO glb 1.00 1,406.00 1,406.00 1,406.00 1,406.00
03.03 PLAN DE SEGURIDAD Y SALUD EN EL TRABAJO glb 1.00 11,570.34 11,570.34 11,570.34 11,570.34
03.04 TRANSPORTE DE COMBUSTIBLE glb 1.00 2,500.00 2,500.00 520.00 1,980.00 2,500.00
04 CONSERVACION DE PLATAFORMA Y TALUDES 200,804.62 108,171.36 53.87% 89,111.08 44.38% 3,522.18 1.75% 200,804.62
04.01 ROCE Y DESBROCE DE LATERALES DE VIA m2 409,740.00 0.33 135,214.20 108,171.36 27,042.84 135,214.20
04.02 LIMPIEZA DE DERRUMBES Y HUAYCOS MAYORES m3 1,365.80 34.13 46,614.75 46,614.75 46,614.75
04.03 LIMPIEZA DE DERRUMBES MENORES (MANUAL) m3 136.58 31.01 4,235.35 3,746.66 488.69 4,235.35

04.04 CORRECCION DE PLATAFORMA EN PUNTOS CRITICOS (MURO SECO) m2 43.71 337.23 14,740.32 11,706.83 3,033.49 14,740.32

05 CONSERVACION DE DRENAJE SUPERFICIAL 34,039.06 3,139.97 9.22% 30,899.09 90.78% 34,039.06


05.01 REPOSICION DE CUNETA NO REVESTIDA m 13,658.00 1.23 16,799.34 16,799.34 16,799.34
05.02 LIMPIEZA MANUAL DE OBRAS DE ARTE und 49.00 156.31 7,659.19 7,659.19 7,659.19
05.03 ENCAUSAMIENTO DE CURSOS DE AGUA m 426.81 15.09 6,440.56 6,440.56 6,440.56
05.04 LIMPIEZA DE CAUCES m3 136.58 22.99 3,139.97 3,139.97 3,139.97
Costo Directo 272,325.44 134,239.47 99,548.20 38,537.77 0.00 272,325.44
Gastos Generales (30.73%) 83,690.05 41,253.98 30,592.79 11,843.29 0.00 83,690.05
Gastos de Inspección (9.51%) 25,898.58 12,766.39 9,467.19 3,665.00 0.00 25,898.58
Gastos de Expediente Técnico (2.69%) 7,317.75 7,317.75 7,317.75
Gastos de Liquidacion (3.12%) 8,499.27 8,499.27 8,499.27
PRESUPUESTO TOTAL DE OBRA 397,731.09 195,577.59 139,608.18 54,046.06 8,499.27 397,731.09
TOTAL ACUMULADO 195,577.59 335,185.76 389,231.82 397,731.09
PORCENTAJE DE AVANCE 49.17% 35.10% 13.59% 2.14%
PORCENTAJE ACUMULADO 49.17% 84.27% 97.86% 100.00%