Академический Документы
Профессиональный Документы
Культура Документы
BLOCK NO.
(2) Wall Load
1 B. Steel Reinforcement
2" Thick Brick wall) LOT NO.
f = 50,000 psi
y TOWNSHIP MDY
SUBJECT
B. Structural Steel
f = 36 ksi , f = 58 ksi GENERAL NOTES
B. Live Load y u
SHEET NO
SCALE
G-01
5. Structural Analysis & Design Software DATE 26-02-2020
D. Earthquake Load
12db
Bend dia = 6db
12db
4db
db
Main Reinforcement
PROJECT
(a)
PROPOSED 3 STORYED
4db R.C.C BUILDING
(b)
db db
(c)
No.8 (25mm)
BLOCK NO.
Bend dia = 4db bar or smaller
6db
No.5 (16mm)
No.6,7 or 8 bars db ldh LOT NO.
bar or smaller
(16mm to 25mm)
Bend dia = 4db
6d
b (a) 4 db for No.3 through 8 bars TOWNSHIP MDY
(A) Using Standard Hooks (B) Using Alternative Method (based on total length-less desirable and only for use
when space is not adequate for standard hook ldh )
(a) Beam - Column Connections (b) Beam - Girder Connections
( using standard hooks ) ( using standard hooks ) (a) Beam - Column Connections (b) Beam - Girder Connections OWNER/APPLICANT
( using alternative method ) ( using alternative method )
> ldh + 11 db
l a2 > l dh + 14 d b
2
lb
Column Primary beam BLOCK NO.
Note : Modification factors may be applied to lhb values to find l dh values. SUBJECT
GENERAL NOTES
Note : In case the width of column or primary beam (girder) is not large enough to
Note : In most cases under gravity loads only, for the bottom bars, a standard hook with > 6 in.
containdhl but it is desired to keep the same bar size , then , as an alternative ,
insidethe column or primary beam is recommended even though it is allowed SHEET NO
the following less desirable method of anchoring based on total length may SCALE
not to use the hooks at all ; l may be neglected for such a case. For cases
be used [ Sect. (B) ] . If it is still impossible to place the hook in the girder , b2 G-03
with possible stress reversal , l must be provided , however. DATE 26-02-2020
reduce the bar size in order to reduce the required anchorage length. b2
L.A / S.L.A / R.S.E / PE
b
l max b + h - 5.875 - 2.5 d b (in.) (for the outermost layer)
l max l max b
h
Secondary
l
2 in.(50 mm)
Ref : (1) U Nyi Hla Nge ; "Refresher Course And Field Reference Manual For Site Engineers & Inspectors " ; 1st edition, 2010.
(2) U Nyi Hla Nge ; "Reinforced Concrete Design " ; 1st edition, 2010.
L/3 L/3
3" 2" Top Bar Top Bar 2"
A
h
h
min
12"
A
Bottom Bar 2h x x x
2h
Lapping Area ( Bottom Bar Only ) Temp. & Shr. Steel x = spacing
6"min
L For slabs, Section A - A
Maximum Spacing
cut-off point cut-off point cut-off point cut-off point
L1 /4 L1 /3 L2 /3 L2 /3 = 3h (or) 18" ( one - way slab - for main steel )
OWNER/APPLICANT
= 2h (or) 18" ( two - way slab - for main steel )
L1 L2 = 5h (or) 18" ( for temp. & shr. steel )
( 1 ) Do not splice more than 50% of the total at any section Fig. SLAB TYPICAL DETAIL Note : For 40/50 ksi ,
( 2 ) Do not splice any bar within the cantilever span A s (min) = 0.002 bh ( = temp. & shr. steel )
( 3 ) Lapping length = 40 x Main bar diameter
For 60 ksi , PROJECT
0.25 x ( smaller of C 1 or C 2 ) A s (min) = 0.0018 bh ( = temp. & shr. steel ) PROPOSED 3 STORYED
C1 R.C.C BUILDING
s < 6 x longer bar diameter
s0
BLOCK NO.
N1 /2 bars on each side
12mm (both layers)
LOT NO.
C2
s
TOWNSHIP MDY
N2
LONGITUDINAL BEAM REINFORCEMENT OUTSIDE A CONFINED COLUMN CORE
min
6"
Links
6"
less than 25.4 mm. and the bars
Column 112 d b (or) 112" _
in the upper layer should be Section A-A
3h (or) 18" (one-way slab) place directly above those in the
3" lower layer .Bars in beams must
Slab/Stair (to save labour) 2h (or) 18" (two-way slab) be placed symmetrically about
Floor Level
Temp.& shr.steel : 5h (or) 18" the vertical centerline.
Width of Opening
Ref : (1) U Nyi Hla Nge ; " Refresher Course And Field Reference Manual For Site Engineers & Inspectors " ; 1st edition, 2010. LINTEL DETAIL
(2) U Nyi Hla Nge ; " Reinforced Concrete Design" ; 1st edition, 2010.
0.3 L1 0.3 L1 * Beam Splice Column Splice
D
R.C column
or R.C wall < 12 ( total +ve As ) cutoff
0.125 L1 0.125 L1 Splice Length
L1
Simplified Cutoff Points
* If adjacent spans are different in span lengths, use the larger of the two. OWNER/APPLICANT
9D
( 1 ) Do not splice more than 50% of the total at any section.
splice
Lap
>2h >2h
If 3" or more, use dowel bar LOT NO.
S
h
S
2
TOWNSHIP MDY
in exterior joints
Not more than s
Splice Zone
S
2
SUBJECT
splice
Lap
Fig. Splice Location for Top Bars
GENERAL NOTES
Top bars are not to be spliced: Offset bend
Closed tie
s
* Within joints.
* Within a distance of twice the member depth from the face of the joint. Dowel bar SHEET NO
SCALE
* At locations where analysis indicates flexural yielding caused by inelastic lateral displacements of the frame.
G-05
DATE 26-02-2020
Compression Development Length (, ldc ) Splice Length
Splice Zone
L.A / S.L.A / R.S.E / PE
ldc 0.02f y
= 0.0003f y
db
f'c
h
Modification factors ( to multiply ) :
Splice Length (i) A s, required / A s, provided
>2h
Lc /3 Lc /3 Lc /3
Lc (ii) If confined, i.e., if No.4 ties at not more than 4 in. c/c
Fig. Splice Location for Bottom Bars spacing is provided, may be modified with 0.75
Bottom bars are not to be spliced: (iii) ldc > 8 in. (in all cases)
* Within joints.
* Within a distance of twice the member depth from the face of the joint. Tension Development Length , ( ld ) Splice Length
* At locations where analysis indicates flexural yielding caused by inelastic lateral displacements of the frame. ld fy
= (for < 20mm bars) As, required
* At the beams that supporting the secondary beams, if possible. db f'c
Modification factors = (to multiply)
As, provided
* At mid span. ld fy (for > 22mm bars) l d > 12 in. (in all cases)
=
db f'c
* For top bars multiply by 1.3 (Modify if applicable)
Ref : (1) U Nyi Hla Nge ; "Refresher Course And Field Reference Manual For Site Engineers & Inspectors " ; 1st edition, 2010.
(2) U Nyi Hla Nge ; "Reinforced Concrete Design " ; 1st edition, 2010.
Special Moment - Resisting Frame Detailing
Beams
'
min
=3 c/ y 200/ y _ 34 As, reqd
; As, min < Lap splice confined and located
outside potential hinge area
_ = 0.025
max
_
M n.l Min. 2 bars continuous Mn.r _ 2h
> Hoop or spiral OWNER/APPLICANT
reinforcement
d/4
- s_
<
+ 4" PROJECT
M n.l >_ M n.l/2
PROPOSED 3 STORYED
+ - R.C.C BUILDING
M n.r >_ M n.r/2
+ _
Mn or Mn >_ (max. Mn at either joint) /4
BLOCK NO.
' Note: Transverse reinforcement not shown for clarity LOT NO.
1= 0.85 for c 4000psi
'
= 0.80 for c 5000psi
TOWNSHIP MDY
SUBJECT
Fig. Flexural requirements for beams Fig. Lap splice requirements for beams
GENERAL NOTES
SHEET NO
SCALE
Special Moment - Resisting Frame Detailing contd.
G-06
DATE 26-02-2020
A
_ 2"
< stirrups with seismic hooks
Hoops
h
Detail A Detail C
Section A
Special Moment - Resisting Frame Detailing contd. Special Moment - Resisting Frame Detailing contd.
Columns Columns
OWNER/APPLICANT
l0 A
A
6 x longitudinal bar diameter maximum spacing
S outside of l 0
6" PROJECT
PROPOSED 3 STORYED
R.C.C BUILDING
pg
BLOCK NO.
GENERAL NOTES
0.25 x (smaller of C1 or C2 )
maximum spacing
S 6 x smallest longitudinal bar diameter within l 0
S0
l0 SHEET NO
SCALE
G-07
DATE 26-02-2020
Section A-A
Fig. Transverse reinforcement requirements for columns (rectangular hoops)
Structural Integrity Requirements
Minimum (+As)/4
At least 2 Bars (+As) PROJECT
PROPOSED 3 STORYED
R.C.C BUILDING
BLOCK NO.
Ld TOWNSHIP MDY
SUBJECT
lap splice
lap splice
Max : slope = 1:6 Max : slope = 1:6
GENERAL NOTES
U.B.L U.B.L
SHEET NO
SCALE
development
Simplified Cutoff Point
tension
length
G-08
DATE 26-02-2020
2h 2h
BEAM OFFSET