OWNER REFERENCE

Project Package Originator Discipline Doc. Type Unit n° Serial n°

RAPID
FE1 TPX APC DES 0001 0004

CONTRACTOR REFERENCE
Rev. Page

PETRONAS RAPID PROJECT


Project Unit n° Doc. Type Doc. Code Sequent. n°

FEED PHASE
60987R
0001 JSD 3037 9000
0 1 / 6

Project Specification – Operator Training Simulator (OTS) System Project Execution

PROJECT SPECIFICATION

OPERATOR TRAINING SIMULATOR (OTS) SYSTEM

PROJECT EXECUTION

(Supplement to PTS 20.00.10.38 dated Jan 2011)

OWNER Approval: PETRONAS

Name:

Date (DD-MMM-YY):

Signature:

Document Class: Z

Pages modified under this revision: 1

Mathieu Sanchez
Wassim El-Osta

Jean-Marc Maurice

60987R-0001-FOR-0003_F

2012.11.12
2012.11.13

18:19:07 +01'00'

2012.11.13

10:45:14
11:25:01 +01'00'
+01'00'

0 12-NOV-12 IFD – Issued for Design M.SANCHEZ W.EL-OSTA J.M. MAURICE

B 26-OCT-12 IFA – Issued for Approval M.SANCHEZ W.EL-OSTA J.M. MAURICE

A 20-SEP-12 IFA – Issued for Approval W.EL-OSTA R. RIEUBON J.M. MAURICE

DATE
WRITTEN BY
CHECKED BY
APPROVED BY

REV.
STATUS – REVISION MEMO

DD-MMM-YY
(name & visa)
(name & visa)
(name & visa)

Sections changed in last revision are identified by a vertical line in the margin.

Subject to the provision of Article 13 of the CONTRACT, TECHNIP hereby grant PETRONAS the copyright of this document. No part of this document may be reproduced, stored in a retrieval

system or transmitted in any form or by any means (electronic, mechanical, photocopying, recording or otherwise) without the permission of the copyright owner.

CONFIDENTIAL – Not to disclose without authorization

Electronic Filename: RAPID-FE1-TPX-APC-DES-0001-0004_0.docx

OWNER REFERENCE


Project Package Originator Discipline Doc. Type Unit n° Serial n°

RAPID
FE1 TPX APC DES 0001 0004

CONTRACTOR REFERENCE
Rev. Page

PETRONAS RAPID PROJECT


Project Unit n° Doc. Type Doc. Code Sequent. n°

FEED PHASE
60987R
0001 JSD 3037 9000
0 2 / 6

Project Specification – Operator Training Simulator (OTS) System Project Execution

CONTENTS

1.
PURPOSE ............................................................................................................................................................................ 3

2.
REFERENCE DOCUMENTS ........................................................................................................................................... 3

3.
ACRONYMS AND DEFINITIONS .................................................................................................................................. 3

4.
CODES AND STANDARDS .............................................................................................................................................. 5

4.1
APPLICABLE CODES & STANDARDS .............................................................................................................................. 5

4.2
ORDER OF PRECEDENCE ................................................................................................................................................ 5

5.
AMENDMENTS TO PETRONAS TECHNICAL STANDARD .................................................................................... 5

Subject to the provision of Article 13 of the CONTRACT, TECHNIP hereby grant PETRONAS the copyright of this document. No part of this document may be reproduced, stored in a retrieval

system or transmitted in any form or by any means (electronic, mechanical, photocopying, recording or otherwise) without the permission of the copyright owner.

CONFIDENTIAL – Not to disclose without authorization

OWNER REFERENCE


Project Package Originator Discipline Doc. Type Unit n° Serial n°

RAPID
FE1 TPX APC DES 0001 0004

CONTRACTOR REFERENCE
Rev. Page

PETRONAS RAPID PROJECT


Project Unit n° Doc. Type Doc. Code Sequent. n°

FEED PHASE
60987R
0001 JSD 3037 9000
0 3 / 6

Project Specification – Operator Training Simulator (OTS) System Project Execution

1. PURPOSE

This Project Specification covers the minimum requirements for Operator Training Simulator

(OTS) System Project Execution for the RAPID (Refinery And Petrochemical Integrated

Development) Project.

It has been developed on the basis of the PETRONAS Technical Standard n° PTS 20.00.10.38

dated January 2011, amended herein (the Project Specification therefore supplements the initial

PTS).

These requirements shall be used throughout all steps of the Project and by all parties:

CONTRACTOR, SUBCONTRACTORS, LICENSORS, EPCC CONTRACTORS, VENDORS,

etc.

2. REFERENCE DOCUMENTS

RAPID-FE1-TPX-ENG-PRC-0001-0205 (60987R-0001-PP-0205), Project Procedure - Project

Specifications and Procedures supplementing PETRONAS Technical Standards (PTS)

3. ACRONYMS AND DEFINITIONS

This section defines the type of amendments to the PETRONAS Technical Specification (PTS)

named above for PETRONAS purpose:

(Dev.) Deviation - Any departure from PTS mandatory requirement that has

impact on technical integrity or safety of the facilities.

(Supp.) Supplement/ Amendment - Any addition, deletion or enhancement of

PTS requirement based on lesson learnt, engineering best practices

and experiences to enhance the technical integrity or safety of the

facilities.

(Spec.) Project Specific Requirement/ Instruction - Any specific requirement

or instruction for RAPID PROJECT as a result of particular

geography, climate, special process, etc. that is unique to the

PROJECT.

For user’s readability purpose, the words used to identify amendments to PTS are defined as

follows:

(Add.) Adds the requirement(s) tot the referenced paragraph of the PTS.

(Mod.) Changes the referenced paragraph sentence of the PTS as indicated.

(Clarif.) Provides interpretation of the referenced paragraph / sentence of the

PTS.

(New.) Indicates the addition of a new paragraph compared to the PTS.

(Canc.) Cancel the requirement to the referenced paragraph of the PTS.

Subject to the provision of Article 13 of the CONTRACT, TECHNIP hereby grant PETRONAS the copyright of this document. No part of this document may be reproduced, stored in a retrieval

system or transmitted in any form or by any means (electronic, mechanical, photocopying, recording or otherwise) without the permission of the copyright owner.

CONFIDENTIAL – Not to disclose without authorization

OWNER REFERENCE


Project Package Originator Discipline Doc. Type Unit n° Serial n°

RAPID
FE1 TPX APC DES 0001 0004

CONTRACTOR REFERENCE
Rev. Page

PETRONAS RAPID PROJECT


Project Unit n° Doc. Type Doc. Code Sequent. n°

FEED PHASE
60987R
0001 JSD 3037 9000
0 4 / 6

Project Specification – Operator Training Simulator (OTS) System Project Execution

The following terms used in this document have the meaning defined below:

CONTRACT The Form Of Agreement together with the documents in order of

priority, including the exhibits, drawings, specifications and

documents referred to and in the order of precedence listed in the

Form of Agreement.

CONTRACTOR Company(ies), joint ventures or consortium appointed by OWNER

with specified authority to perform the WORK in accordance with the

CONTRACT, here the Consortium of Technip France and Technip

Geoproduction (M) Sdn Bhd.

OWNER Petroliam Nasional Berhad (PETRONAS) which includes its

representative, successors, nominees and permitted assigns and shall

where the context so admits and requires, also include its employees,

agents and designated representative.

PROJECT Refinery And Petrochemicals Integrated Development (RAPID)

Project in the State of Johor, Malaysia.

SCOPE OF WORK The scope of work to be performed and services to be rendered by

CONTRACTOR under the CONTRACT in relation to the realization

of the PROJECT.

WORK Works, tasks and WORK to be performed by CONTRACTOR as

specified in or to be inferred from the CONTRACT, more specially

set out in the SCOPE OF WORK which may be modified by

CHANGE ORDER.

SUBCONTRACTOR Any third party Subcontractor engaged by CONTRACTOR in

connection with the WORK.

LICENSOR Process Licensors selected by OWNER for the process of LICENSED

UNITS of the FACILITIES.

EPCC CONTRACTORS The person or persons, company, join venture or consortium whose

proposal has been accepted by OWNER for Engineering,

Procurement, Construction and Commissioning Contract for the

PROJECT including its personnel, representatives, successors and

permitted assignee.

VENDOR Means any and all persons, firms, partnerships, companies, bodies,

entities or a combination thereof including Sub-Suppliers, who are

providing Equipment and Material specified by EPCC

CONTRACTOR.

The acronyms used in this document have the meaning defined below:

- DCS Distributed Control System

- FEED Front-End Engineering Design

- MOC Management Of Change

- OTS Operator Training Simulator

- PTS PETRONAS Technical Standard

- RAPID Refinery And Petrochemicals Integrated Development

Subject to the provision of Article 13 of the CONTRACT, TECHNIP hereby grant PETRONAS the copyright of this document. No part of this document may be reproduced, stored in a retrieval

system or transmitted in any form or by any means (electronic, mechanical, photocopying, recording or otherwise) without the permission of the copyright owner.

CONFIDENTIAL – Not to disclose without authorization

OWNER REFERENCE


Project Package Originator Discipline Doc. Type Unit n° Serial n°

RAPID
FE1 TPX APC DES 0001 0004

CONTRACTOR REFERENCE
Rev. Page

PETRONAS RAPID PROJECT


Project Unit n° Doc. Type Doc. Code Sequent. n°

FEED PHASE
60987R
0001 JSD 3037 9000
0 5 / 6

Project Specification – Operator Training Simulator (OTS) System Project Execution

4. CODES AND STANDARDS

4.1 Applicable Codes & Standards

Applicable Codes and Standards as referenced in the supplemented PTS 20.00.10.38 (Jan-2011).

Unless otherwise specified, the latest applicable revision of codes and standards shall be

considered.

4.2 Order of precedence

In case of conflict between Laws, Project Specifications and Codes & Standards, the following

order of precedence shall be considered:

- 1. Malaysian Laws and applicable regulatory requirements,

- 2. Project Specifications and supplemented PTS,

- 3. Applicable Malaysian Codes and Standards,

- 4. Applicable International Codes and Standards.

If a Low er Level requirem ent is m ore stringent than an upper one in the above docum ents, a

request shall be raised to OWNER for written decision before proceeding with the Design,

Manufacture or Construction.

5. AMENDMENTS TO PETRONAS TECHNICAL STANDARD

The table below defines the amendments to be considered to the PTS 20.00.10.38 dated Jan. 2011:

Operator Training Simulator (OTS) System Project Execution.

When the amended PTS refers to other PTS, please refer to the Project Procedure - Project

Specifications and Procedures Supplementing PETRONAS Technical Standards (PTS), RAPID-

FE1-TPX-ENG-PRC-0001-0205 (60987R-0001-PP-0205), that provides the equivalence with

applicable Project Specifications.

Type Word Description of Amendment

(Supp.) (Add.)
1.3.2 Abbreviations

Add the following definitions as below,

MOC: Management Of Change

(Spec.) (Sup.)
2.2 Direct Connect / Stimulation

th

6
line of Table 2-1 to be deleted since:

- OTS Project duration is dependent on resources allocated. A typical schedule

for OTS projects is given in figure 3-1,

- Stimulated OTS projects require tight synchronization between DCS

configuration and OTS development. This often results in long delivery

schedules,

- This statement is not in accordance with the chart on Page 5.

Subject to the provision of Article 13 of the CONTRACT, TECHNIP hereby grant PETRONAS the copyright of this document. No part of this document may be reproduced, stored in a retrieval

system or transmitted in any form or by any means (electronic, mechanical, photocopying, recording or otherwise) without the permission of the copyright owner.

CONFIDENTIAL – Not to disclose without authorization

OWNER REFERENCE


Project Package Originator Discipline Doc. Type Unit n° Serial n°

RAPID
FE1 TPX APC DES 0001 0004

CONTRACTOR REFERENCE
Rev. Page

PETRONAS RAPID PROJECT


Project Unit n° Doc. Type Doc. Code Sequent. n°

FEED PHASE
60987R
0001 JSD 3037 9000
0 6 / 6

Project Specification – Operator Training Simulator (OTS) System Project Execution

(Spec.) (Mod.)
3 OTS Project Execution Stages

Item f) shall be replaced as below,

f) Model Acceptance Test & Link Acceptance Test

(Spec.) (Sup.)
3.5 Simulator design and configuration

Item a), PETRONAS proprietary steady state simulation software, iCON, will be

made available to OTS VENDOR during the OTS development phase.

Subject to the provision of Article 13 of the CONTRACT, TECHNIP hereby grant PETRONAS the copyright of this document. No part of this document may be reproduced, stored in a retrieval

system or transmitted in any form or by any means (electronic, mechanical, photocopying, recording or otherwise) without the permission of the copyright owner.

CONFIDENTIAL – Not to disclose without authorization