Publisher: Public Enterprise Roads of Serbia, Bulevar kralja Aleksandra 282, Belgrade
Edition:
CONTENT
PE Roads of Serbia i
Serbian Road Construction Specifications Preparatory Works
2.1 PREPARATORY WORKS - traverse points set out in the field. The
traverse is to be linked to trigonometric
points, calculated according to Gauss-
2.1.1 GEODETIC WORKS Krüger system, with admitted deviations in
compliance with the rulebook for first-
order traverse network.
2.1.1.1 Description - levels (bench marks) determined in the
field
Geodetic works include:
- alignment design containing the following:
- the alignment and facilities setting out ,
- plan at scale 1:1000 with axis,
- all the surveying related to data transfer
mileage and indication of alignment
from the design documentation to the field
elements; the plan is to include
or from the field to the appropriate
drawings indicating connection
documentation,
between main points and traverse
- progress surveying within geotechnical
with the necessary setting out
observations, and
information
- maintenance of set out marks in the field
- calculation of main points; in case of
during the period from commencement of
electronic calculation, the
works up to taking over of all the works by
coordinates of main points with the
the Employer.
chainage
- list of traverse points with
Geodetic works also include taking over and
coordinates and topography of such
maintaining all the basic geodetic surfaces
points
and plans as well as setting out in the field
- list of bench marks with levels and
which the Employer shall submit to the
topography of bench marks.
Contractor at the beginning of works.
For additional facilities of lower importance,
The Contractor of geodetic works is to inform
such as deviations of less important roads,
the Supervising Engineer of all the works in
regulations etc. other measuring procedures
due time, as well as to provide him the
may be applied, adapted to the type of facility
participation in such works.
and field so the Contractor is free to execute
works with no disturbances.
The extent of geodetic works is to be in full
accordance with the requirements of the
After works on the formation level are
construction, work control, calculation and
completed and based on the traverse points
everything else related to the conditions for
setting out drawing, the Contractor is to
the execution of works.
renew the axis (plan and height). Soundness
of the renewed axis is to be inspected by the
Geodetic works also include preparation of
Supervising Engineer. The axis is also to be
technical documentation of finally set out and
renewed prior to incorporation of the road
constructed road and/or facility. The technical
surface wearing course.
documentation is to be prepared prior to
technical inspection of the constructed road
From the day of taking over onwards, the
and/or facility.
Contractor is to protect all the traverse points
and bench marks. If any data is lost or shifted
2.1.1.2 Execution method in the field (traverse points, bench marks),
the Contractor is to renew them at his own
2.1.1.2.1 Alignment taking over expense. Soundness of the renewed points is
to be inspected by the Supervising Engineer.
The Employer is to hand over to the
Contractor the following: 2.1.1.2.2 Protection of set out axis
- set out alignment and/or facility in the field
with all the necessary information in When the Contractor takes over the set out
written form. Only road centre line and/or road centre line or any other facility, each
facility is set out at spacing conditioned by profile (regardless of the field configuration)
the field properties, but not greater than is to be protected on both sides at such
25 m. Access points are generally set out distance from the edge of embankment or
along the edge of decelerating or excavation that he may freely remain at the
accelerating lanes or pavement, or along distance until the works are completed. Each
the edge of the access road itself. protection point is to be secured with triangle
made of 2.5/5 cm laths. The protection point
PE Roads of Serbia 1
Preparatory Works Serbian Road Construction Specifications
(5/5 cm peg) is to be equipped with a pin, Setting out of the facility is to be provided
and painted with minium or other appropriate with concrete posts set at each side of the
durable paint on the upper side. Each facility. The setting out layout for large
protection is to be levelled twice. facilities is to include calculation of elements
for plan inspection of setting out and
Next to the triangle, on the left and right sides construction of posts with sections.
of the axis, the board is to be set with number
of profiles written in large figures with minium 2.1.1.2.5 Displacement measurement
or other appropriate durable paint and the
profile mileage (chainage) is to be written In the course of construction, the Contractor
below. is to survey displacement determined in the
design documentation within the geotechnical
2.1.1.2.3 Placement of cross-profiles observations and affecting the course of
construction and calculation measures. The
If dissatisfied with the profiles proposed in the Supervising Engineer is to be immediately
main design, the Contractor is entitled to informed of surveying results.
repeat the survey of cross-profiles himself, at
the right angle to the road centre line, by
levelling or tachometric surveying. 2.1.1.3 Construction quality
The profiles are to be placed in the course of If the Supervising Engineer determines that
the entire incorporation of embankment the results of measuring do not guarantee the
and/or excavation and are to be extended execution of works according to the design
simultaneously with the work progress. documentation, he is entitled to halt the
measurement works. The Contractor is then
The construction profiles are generally to be to take measures for more accurate
made of 2.5/5 cm laths and 5/5 cm wooden surveying or obtaining measuring results as
pegs. At high embankments or excavations, requested by the Supervising Engineer.
they may be set at the spacing of not more
than 50 m. If necessary, the Supervising 2.1.1.4 Quality control
Engineer may order the placement of
additional construction interprofiles. In the course of construction, the Contractor
is to inspect set out alignment and regularly
At slope grades, line of embankment or renew all the marks in the field, regardless of
excavation without top soil and without the cause of the damages. In case of
rounding off at the bottom or top of the alteration to the project, the Contractor is
excavation or at the heel of embankment is to again to execute works specified in the sub-
be considered. clauses 2.1.1.4.2 to 2.1.1.4.4. The Contractor
is to submit all the information on setting out
2.1.1.2.4 Setting out of facilities to the Supervising Engineer and provide him
with the undisturbed use of all the marks he
Based on the information under sub-clause may need. If, by surveying and information
2.1.1.4.1, the Contractor is to set out all the check, the Contractor determines that
facilities to his opinion and need, but is surveying conducted by the Contractor is not
previously to propose the setting out layout to accurate, he is entitled to appoint third-party
the Supervising Engineer including all the professional institution to perform surveying
information according to sub-clauses at the actual expenses which are to be borne
2.1.1.4.2 and 2.1.1.4.3. Placement of cross- by the Contractor.
profiles, protection of set out axis and
inspection are to be performed in the same
manner as alignment marking, but adjusted
to the needs of the facility construction.
2 PE Roads of Serbia
Serbian Road Construction Specifications Preparatory Works
2.1.1.5 Measuring and taking over of borne by the Contractor, if the surveying
works results and information provided by the
Contractor are determined to be inaccurate.
2.1.1.5.1 Measuring
PE Roads of Serbia 3
Preparatory Works Serbian Road Construction Specifications
- scraping and transport of asphalt All stumps and roots are to be removed from
surfacing, the new alignment excavation surfaces,
- cutting asphalt layers, except for circled slope areas, where they
- demolition and removal of curbs. may be cut at the field level. Stumps and
roots are to be removed prior to excavation of
All works within demolition and removal of humus, rolled turf and/or fertile soil.
the existing road facilities are to be specified
in detail in plans. Each deviation is to be On foundation soil surfaces where low
approved by the Supervising Engineer. bearing layers are to be removed from or
which are to be compacted, all the stumps
2.1.2.1.4 Demolition and removal of and roots are to be removed to the depth of
facilities 20 cm underneath the foundation soil
formation and/or at least 50 cm underneath
The works include: the formation level.
- demolition and removal of culverts,
sewage and shafts, When excavating low bearing soil (of lightly
- demolition and removal of bridging mouldable to light-bodied consistency) all the
facilities, roots and stumps are generally to be
- demolition and removal of buildings and removed with excavation of earth.
walls.
2.1.2.2.2 Other removals
Demolition and removal are to include all the
facilities that may disturb the execution of Removals specified in the sub-clauses
works in any way. 2.1.2.1.2 to 2.1.2.1.4 are to be performed on
all surfaces where clearing is necessary due
The works do not include various removals of to construction works or esthetical
installations that are used, such as electrical arrangement of immediate road surroundings.
installations and high/low voltage cables,
telecommunication installations and cables, Traffic equipment is to be excavated and
water supply, gas pipelines and installations dismantled with no damages to any
that are to be dislocated, and include only components so they may be used again. For
parts of the devices serving as foundations or this purpose, prior to dismantling and as
as parts of mass-material facilities, which are agreed with the Supervising Engineer, such
to be demolished after the mentioned components are to be determined, stored
installations and devices are dislocated. and protected from decay, and other ones
are to be removed. Storage area for
Treatment of waste caused by construction of dismantled traffic equipment and signs is to
works is to be in accordance with the be determined by the Supervising Engineer,
provisions specified in the waste treatment and the Contractor is to temporarily store the
rulebook. dismantled components in his storehouses
which are accessible to vehicles, until they
are taken over by the Supervising Engineer.
2.1.2.2 Execution method The take-over date is to be determined by the
Supervising Engineer.
2.1.2.2.1 Removal of shrubs, trees,
branches and stumps All the works within demolition and removal
of road and other facilities are to be executed
Shrubs, trees, branches and stumps are to with minimum damage to the adjacent
be removed from all surfaces specified in the facilities, vegetation and the remained
plans as well as from places (for some trees roadway, while the demolition area is
and stumps) determined by the Supervising functional for purposes envisaged by the
Engineer. project and provisions specified by the
Supervising Engineer.
Some trees determined by the Supervising
Engineer are to remain and must not be Removal of curbs, dismantling of crossing
damaged. To prevent remaining trees from facilities, buildings and similar obstacles is to
damages, other trees are to be carefully be performed in the manner that such
removed. When facilities, other trees or obstacles are completely removed so there
property are to be protected from damages or are no obstacles remained to disturb proper
when the danger is to be reduced or the execution of works, nor ones affecting the
property disturbance prevented, the trees are esthetical appearance of the road and
to be carefully removed from top to bottom.
4 PE Roads of Serbia
Serbian Road Construction Specifications Preparatory Works
surroundings. In the course of removal, the Works specified under sub-clause 2.1.2.4.1,
Contractor is to be careful that components item 5, are to be calculated in the course of
are not damaged and can be reused. excavation of low bearing soil.
PE Roads of Serbia 5
Preparatory Works Serbian Road Construction Specifications
All preparatory works related to facilities are For all temporary facilities for the construction
to be specifies and executed according to the of bridging facilities, the projects are to be
appropriate projects or are to be determined adjusted to specific conditions of the subject
by the Supervising Engineer prior to the facility.
repair work and based on the current
condition of the facility. In the course of facility construction, the
construction pit is to be protected in the
2.1.3.1.3 Compensations manner that ensures safe work. Water
pumping is to provide execution of all the
Compensations required due to public road necessary work in dry construction pit.
construction works are conditioned by
- excessive use of municipal roads, and All the temporary scaffolds necessary for
- disturbance, i.e. slowdown and temporary preparatory works within the facility
closing of railway traffic. construction are to be made of appropriate
materials so the proper stability and safety of
For all the works that are to cause the the temporary scaffold are provided in the
abovementioned consequences, the course of its usage.
Contractor is to acquire consent/permit from
the relevant or control authority. When power cable installations are to be
dislocated within the preparatory works for
the facility construction, such action is too
2.1.3.2 Execution method performed in the manner that provides
undisturbed power supply for the users in the
2.1.3.2.1 Traffic restrictions course of preparatory works. Undisturbed
usage and supply for the users is also to be
Restricting public road traffic is to be provided in the course of dislocating all the
performed in accordance with the Road other installations (PTT cable installation,
Traffic Safety Act. water supply, sewage system, gas pipelines,
and optical cable). All the necessary
The site protection in the course of dislocations within the preparatory works for
construction may be performed by complete the facility construction are to be performed
or partial closing of traffic, which is to be in accordance with the appropriate projects.
regulated by traffic lights or manually in Plans for the permanent rearrangement are
special cases. to be followed to the highest possible extent.
Type and closure time are to be specified in Within the preparatory works for the
detail in the traffic arrangement plan, and construction, the Contractor is to prepare all
controlled all the time and, if necessary, the temporary facilities necessary for
supplemented or altered. undisturbed execution of works on the site.
All the facilities are to be executed according
As soon as there is no more need to protect to the appropriate projects and in the manner
the site by traffic restriction, the Contractor is that does not disturb completion of works on
bound to remove all the equipment placed for other facilities within the construction. After
the traffic closure. temporary facilities are removed, the
Contractor is generally to restore prime
Public area traffic may be restricted only for condition of the damaged surfaces.
the shortest possible and professionally
justified time and within the least possible Detailed execution procedure for the
extent. mentioned repair works on the facilities is to
be specified in the design documentation. In
2.1.3.2.2 Facility-related preparatory works case that the Supervising Engineer
determines that the actual condition of the
Within preparatory works for the facility, the damaged facilities deviates from the
Contractor is to arrange all temporary envisaged one, he is entitled to determine the
beltways, bypasses, water flow redirecting appropriate alteration to the procedure within
and traffic protection under and along the the contracted provisions.
facility, necessary for undisturbed and safe
execution of works and for traffic safety. All All the previous repair works on the facility
the above mentioned works are to be are to be executed in the manner that
executed according to the appropriate provides safe execution of works with no
projects.
6 PE Roads of Serbia
Serbian Road Construction Specifications Preparatory Works
PE Roads of Serbia 7
Preparatory Works Serbian Road Construction Specifications
8 PE Roads of Serbia