REPUBLIC OF SERBIA

TRANSPORT REHABILITATION PROJECT

SERBIAN ROAD CONSTRUCTION


SPECIFICATIONS

2. SPECIAL TECHNICAL CONDITIONS

2.1 PREPARATORY WORKS

BELGRADE, 2012
Publisher: Public Enterprise Roads of Serbia, Bulevar kralja Aleksandra 282, Belgrade

Edition:

No. Date Description of amendments


1 30.04.2012 First edition
Serbian Road Construction Specifications Preparatory Works

CONTENT

2.1 PREPARATORY WORKS...................................................................................1


2.1.1 GEODETIC WORKS .................................................................................................1
2.1.1.1 Description ............................................................................................................ 1
2.1.1.2 Execution method .................................................................................................. 1
2.1.1.3 Construction quality ............................................................................................... 2
2.1.1.4 Quality control ....................................................................................................... 2
2.1.1.5 Measuring and taking over of works........................................................................ 3
2.1.1.6 Calculation of works............................................................................................... 3
2.1.2 SITE CLEARING ......................................................................................................3
2.1.2.1 Description ............................................................................................................ 3
2.1.2.2 Execution method .................................................................................................. 4
2.1.2.3 Measuring and taking over of works........................................................................ 5
2.1.2.4 Calculation of works............................................................................................... 5
2.1.3 OTHER PREPARATORY WORKS ................................................................................5
2.1.3.1 Description ............................................................................................................ 5
2.1.3.2 Execution method .................................................................................................. 6
2.1.3.3 Construction quality ............................................................................................... 7
2.1.3.4 Quality control ....................................................................................................... 7
2.1.3.5 Measuring and taking over of works........................................................................ 7
2.1.3.6 Calculation of works............................................................................................... 8

PE Roads of Serbia i
Serbian Road Construction Specifications Preparatory Works

2.1 PREPARATORY WORKS - traverse points set out in the field. The
traverse is to be linked to trigonometric
points, calculated according to Gauss-
2.1.1 GEODETIC WORKS Krüger system, with admitted deviations in
compliance with the rulebook for first-
order traverse network.
2.1.1.1 Description - levels (bench marks) determined in the
field
Geodetic works include:
- alignment design containing the following:
- the alignment and facilities setting out ,
- plan at scale 1:1000 with axis,
- all the surveying related to data transfer
mileage and indication of alignment
from the design documentation to the field
elements; the plan is to include
or from the field to the appropriate
drawings indicating connection
documentation,
between main points and traverse
- progress surveying within geotechnical
with the necessary setting out
observations, and
information
- maintenance of set out marks in the field
- calculation of main points; in case of
during the period from commencement of
electronic calculation, the
works up to taking over of all the works by
coordinates of main points with the
the Employer.
chainage
- list of traverse points with
Geodetic works also include taking over and
coordinates and topography of such
maintaining all the basic geodetic surfaces
points
and plans as well as setting out in the field
- list of bench marks with levels and
which the Employer shall submit to the
topography of bench marks.
Contractor at the beginning of works.
For additional facilities of lower importance,
The Contractor of geodetic works is to inform
such as deviations of less important roads,
the Supervising Engineer of all the works in
regulations etc. other measuring procedures
due time, as well as to provide him the
may be applied, adapted to the type of facility
participation in such works.
and field so the Contractor is free to execute
works with no disturbances.
The extent of geodetic works is to be in full
accordance with the requirements of the
After works on the formation level are
construction, work control, calculation and
completed and based on the traverse points
everything else related to the conditions for
setting out drawing, the Contractor is to
the execution of works.
renew the axis (plan and height). Soundness
of the renewed axis is to be inspected by the
Geodetic works also include preparation of
Supervising Engineer. The axis is also to be
technical documentation of finally set out and
renewed prior to incorporation of the road
constructed road and/or facility. The technical
surface wearing course.
documentation is to be prepared prior to
technical inspection of the constructed road
From the day of taking over onwards, the
and/or facility.
Contractor is to protect all the traverse points
and bench marks. If any data is lost or shifted
2.1.1.2 Execution method in the field (traverse points, bench marks),
the Contractor is to renew them at his own
2.1.1.2.1 Alignment taking over expense. Soundness of the renewed points is
to be inspected by the Supervising Engineer.
The Employer is to hand over to the
Contractor the following: 2.1.1.2.2 Protection of set out axis
- set out alignment and/or facility in the field
with all the necessary information in When the Contractor takes over the set out
written form. Only road centre line and/or road centre line or any other facility, each
facility is set out at spacing conditioned by profile (regardless of the field configuration)
the field properties, but not greater than is to be protected on both sides at such
25 m. Access points are generally set out distance from the edge of embankment or
along the edge of decelerating or excavation that he may freely remain at the
accelerating lanes or pavement, or along distance until the works are completed. Each
the edge of the access road itself. protection point is to be secured with triangle
made of 2.5/5 cm laths. The protection point

PE Roads of Serbia 1
Preparatory Works Serbian Road Construction Specifications

(5/5 cm peg) is to be equipped with a pin, Setting out of the facility is to be provided
and painted with minium or other appropriate with concrete posts set at each side of the
durable paint on the upper side. Each facility. The setting out layout for large
protection is to be levelled twice. facilities is to include calculation of elements
for plan inspection of setting out and
Next to the triangle, on the left and right sides construction of posts with sections.
of the axis, the board is to be set with number
of profiles written in large figures with minium 2.1.1.2.5 Displacement measurement
or other appropriate durable paint and the
profile mileage (chainage) is to be written In the course of construction, the Contractor
below. is to survey displacement determined in the
design documentation within the geotechnical
2.1.1.2.3 Placement of cross-profiles observations and affecting the course of
construction and calculation measures. The
If dissatisfied with the profiles proposed in the Supervising Engineer is to be immediately
main design, the Contractor is entitled to informed of surveying results.
repeat the survey of cross-profiles himself, at
the right angle to the road centre line, by
levelling or tachometric surveying. 2.1.1.3 Construction quality

At embankments and excavation slopes, the The accuracy of measurements is to be in


construction profiles are to be graded, as accordance with geodetic norms for the
specified in drawn cross-profiles. Section of appropriate types of measuring as well as in
slopes with the field is to be determined by accordance with the required quality of
calculation, taking into consideration the certain works according to the special
specified slope breaks. technical conditions.

The profiles are to be placed in the course of If the Supervising Engineer determines that
the entire incorporation of embankment the results of measuring do not guarantee the
and/or excavation and are to be extended execution of works according to the design
simultaneously with the work progress. documentation, he is entitled to halt the
measurement works. The Contractor is then
The construction profiles are generally to be to take measures for more accurate
made of 2.5/5 cm laths and 5/5 cm wooden surveying or obtaining measuring results as
pegs. At high embankments or excavations, requested by the Supervising Engineer.
they may be set at the spacing of not more
than 50 m. If necessary, the Supervising 2.1.1.4 Quality control
Engineer may order the placement of
additional construction interprofiles. In the course of construction, the Contractor
is to inspect set out alignment and regularly
At slope grades, line of embankment or renew all the marks in the field, regardless of
excavation without top soil and without the cause of the damages. In case of
rounding off at the bottom or top of the alteration to the project, the Contractor is
excavation or at the heel of embankment is to again to execute works specified in the sub-
be considered. clauses 2.1.1.4.2 to 2.1.1.4.4. The Contractor
is to submit all the information on setting out
2.1.1.2.4 Setting out of facilities to the Supervising Engineer and provide him
with the undisturbed use of all the marks he
Based on the information under sub-clause may need. If, by surveying and information
2.1.1.4.1, the Contractor is to set out all the check, the Contractor determines that
facilities to his opinion and need, but is surveying conducted by the Contractor is not
previously to propose the setting out layout to accurate, he is entitled to appoint third-party
the Supervising Engineer including all the professional institution to perform surveying
information according to sub-clauses at the actual expenses which are to be borne
2.1.1.4.2 and 2.1.1.4.3. Placement of cross- by the Contractor.
profiles, protection of set out axis and
inspection are to be performed in the same
manner as alignment marking, but adjusted
to the needs of the facility construction.

2 PE Roads of Serbia
Serbian Road Construction Specifications Preparatory Works

2.1.1.5 Measuring and taking over of borne by the Contractor, if the surveying
works results and information provided by the
Contractor are determined to be inaccurate.
2.1.1.5.1 Measuring

Geodetic works are to be measured in the 2.1.2 SITE CLEARING


following manner:
- alignment setting out in kilometres of the
set out alignment 2.1.2.1 Description
- placement of profiles in pieces of profiles
Site clearing includes:
placed on both sides
- removal of shrubs, trees, branches and
- level and displacement surveys in pieces.
stumps
- removal of traffic signs and equipment
2.1.1.5.2 Taking over
- demolition and removal of road facilities
- demolition and removal of facilities.
After completion of works, the Contractor is
obliged to provide the Employer with the
2.1.2.1.1 Removal of shrubs, trees,
technical documentation of set out
branches and stumps
constructed road and/or facility in three
copies and prior to technical inspection. The
The works include:
technical documentation is also to contain the
- cutting and removal of shrubs and trees
information on traverse points and bench
- removal of branches from the previously
marks in accordance with the sub-clause
cut trees
2.1.1.4.1. Take-over record is to be made.
- removal of stumps of old and newly cut
trees
Prior to technical inspection, the Contractor is
- clearing or excavating surfaces including
again to set out the axis or the road surface
cutting and removing shrubs, trees and
edge, and to mark the construction profiles
branches, excavation of stumps and roots,
with durable paint.
excavation of top soil stumps, removal of
organic material remained after removal
2.1.1.6 Calculation of works of shrubs, trees, branches and stumps
and transport to deposit areas outside the
Works are to be calculated in terms of unit alignment.
price or lump sum, based on the agreed bill
of quantities. The unit prices include all the The surfaces to be cleared and/or excavated
works described in this chapter with all the are to be indicated in the plans or determined
materials and internal and external transports. by the Supervising Engineer prior to
The cost also includes all additional commencement of works.
surveying and setting out, along with surveys
performed at borrow pits and in similar cases, 2.1.2.1.2 Removal of traffic signs and
necessary for the completion of works. The equipment
Contractor is not entitled to claim any
additional payment for such works. The basis The works include:
for lump sum calculation is determined as a - excavating, dismantling and dislocating
percentage of values of the completed traffic signs and information boards,
contracted works. - excavating and dismantling crush barriers,
- excavating and dismantling direction
The cost also includes: posts,
- preparation of technical documentation of - demolition and removal of safety fences.
set out and constructed road and/or
facility, which is to be submitted to the Traffic equipment, which is to be used again,
Employer by the Contractor prior to or is to be indicated in the plans. The reuse of
with the claim for technical inspection of such equipment is to be determined by the
the constructed road and/or facility, Supervising Engineer.
- setting out of the axis or the road surface
edge, and 2.1.2.1.3 Demolition and removal of road
- marking construction profiles at the road facilities
surface.
The works include:
The costs of measurement and information - demolition and removal of road surface,
check, performed by the Employer, are to be

PE Roads of Serbia 3
Preparatory Works Serbian Road Construction Specifications

- scraping and transport of asphalt All stumps and roots are to be removed from
surfacing, the new alignment excavation surfaces,
- cutting asphalt layers, except for circled slope areas, where they
- demolition and removal of curbs. may be cut at the field level. Stumps and
roots are to be removed prior to excavation of
All works within demolition and removal of humus, rolled turf and/or fertile soil.
the existing road facilities are to be specified
in detail in plans. Each deviation is to be On foundation soil surfaces where low
approved by the Supervising Engineer. bearing layers are to be removed from or
which are to be compacted, all the stumps
2.1.2.1.4 Demolition and removal of and roots are to be removed to the depth of
facilities 20 cm underneath the foundation soil
formation and/or at least 50 cm underneath
The works include: the formation level.
- demolition and removal of culverts,
sewage and shafts, When excavating low bearing soil (of lightly
- demolition and removal of bridging mouldable to light-bodied consistency) all the
facilities, roots and stumps are generally to be
- demolition and removal of buildings and removed with excavation of earth.
walls.
2.1.2.2.2 Other removals
Demolition and removal are to include all the
facilities that may disturb the execution of Removals specified in the sub-clauses
works in any way. 2.1.2.1.2 to 2.1.2.1.4 are to be performed on
all surfaces where clearing is necessary due
The works do not include various removals of to construction works or esthetical
installations that are used, such as electrical arrangement of immediate road surroundings.
installations and high/low voltage cables,
telecommunication installations and cables, Traffic equipment is to be excavated and
water supply, gas pipelines and installations dismantled with no damages to any
that are to be dislocated, and include only components so they may be used again. For
parts of the devices serving as foundations or this purpose, prior to dismantling and as
as parts of mass-material facilities, which are agreed with the Supervising Engineer, such
to be demolished after the mentioned components are to be determined, stored
installations and devices are dislocated. and protected from decay, and other ones
are to be removed. Storage area for
Treatment of waste caused by construction of dismantled traffic equipment and signs is to
works is to be in accordance with the be determined by the Supervising Engineer,
provisions specified in the waste treatment and the Contractor is to temporarily store the
rulebook. dismantled components in his storehouses
which are accessible to vehicles, until they
are taken over by the Supervising Engineer.
2.1.2.2 Execution method The take-over date is to be determined by the
Supervising Engineer.
2.1.2.2.1 Removal of shrubs, trees,
branches and stumps All the works within demolition and removal
of road and other facilities are to be executed
Shrubs, trees, branches and stumps are to with minimum damage to the adjacent
be removed from all surfaces specified in the facilities, vegetation and the remained
plans as well as from places (for some trees roadway, while the demolition area is
and stumps) determined by the Supervising functional for purposes envisaged by the
Engineer. project and provisions specified by the
Supervising Engineer.
Some trees determined by the Supervising
Engineer are to remain and must not be Removal of curbs, dismantling of crossing
damaged. To prevent remaining trees from facilities, buildings and similar obstacles is to
damages, other trees are to be carefully be performed in the manner that such
removed. When facilities, other trees or obstacles are completely removed so there
property are to be protected from damages or are no obstacles remained to disturb proper
when the danger is to be reduced or the execution of works, nor ones affecting the
property disturbance prevented, the trees are esthetical appearance of the road and
to be carefully removed from top to bottom.

4 PE Roads of Serbia
Serbian Road Construction Specifications Preparatory Works

surroundings. In the course of removal, the Works specified under sub-clause 2.1.2.4.1,
Contractor is to be careful that components item 5, are to be calculated in the course of
are not damaged and can be reused. excavation of low bearing soil.

Parts of various installations that are to be


dislocated due to road construction (such as 2.1.3 OTHER PREPARATORY WORKS
foundations or parts of mass constructions)
and which cannot be dismantled nor cut, are
2.1.3.1 Description
to be removed in the same manner as other
devices within the site clearing. Other preparatory works include:
- restricting traffic,
The manner of removal and demolition is to - facility-related preparatory works,
be determined by the Contractor. He is to act - compensations.
in compliance with the occupational health
and safety regulations and prevent any 2.1.3.1.1 Traffic restrictions
damage and disturbance of other properties.
The Contractor is responsible for any For all the works conditioning traffic
damages in the course of works. restricting, the public road Contractor is
bound to acquire permit from the authorized
The Contractor is not entitled to claim any institution in due time.
additional payment for the material. If it is in
accordance with the contracted works, all the Traffic and site protection in the course of
obtained material is to be reused. works requires partial or complete traffic
diverting or closing.
2.1.2.3 Measuring and taking over of
works 2.1.3.1.2 Facility-related preparatory works

2.1.2.3.1 Measuring The works include various temporary


measures, such as:
The extent of removal of shrubs, branches - temporary facilities
and stumps, old and newly cut trees, with all - placement of temporary movable and
the works, specified under sub-clauses fixed scaffolds and facilities
2.1.2.1.1 and 2.1.2.4.1, is to be determined - placement of temporary fences
after the work is completed. - construction pit protection
- temporary dislocation of various
The extent of other removals specified under installations.
sub-clauses 2.1.2.1.2 to 2.1.2.1.4 is to be
measured after actually completed work and Works related to temporary facilities include
indicated in the appropriate unit of actual placement, maintenance and removal of
quantity. office premises for the Employer and site
laboratory.
2.1.2.3.2 Taking over
Placement of temporary facilities for the
The completed works are to be taken over in Contractor within the site organization is
accordance with the provisions stated in the included in the preparatory works only if
general technical conditions and according to specified in the contract. Otherwise, the
the provisions stated in these special Contractor is to organize the site according to
technical conditions. the technology he provides and at his own
expense.

2.1.2.4 Calculation of works Preparatory works also include facility repairs


in terms of the following procedures:
All quantities of works, specified under sub- - removal of prefabricated elements
clause 2.1.2.7, are to be calculated and paid - demolition of monolithic elements
according to unit prices indicated in the - removal of concrete and mortar
contracted bill of quantities. - removal of dilatation elements
- concrete cutting
The unit price is a full compensation for all - concrete holing
work procedures specified under sub-clause - removal of damaged facility parts and
2.1.2.1 and/or the ones necessary for the installations
ultimate completion of works.

PE Roads of Serbia 5
Preparatory Works Serbian Road Construction Specifications

All preparatory works related to facilities are For all temporary facilities for the construction
to be specifies and executed according to the of bridging facilities, the projects are to be
appropriate projects or are to be determined adjusted to specific conditions of the subject
by the Supervising Engineer prior to the facility.
repair work and based on the current
condition of the facility. In the course of facility construction, the
construction pit is to be protected in the
2.1.3.1.3 Compensations manner that ensures safe work. Water
pumping is to provide execution of all the
Compensations required due to public road necessary work in dry construction pit.
construction works are conditioned by
- excessive use of municipal roads, and All the temporary scaffolds necessary for
- disturbance, i.e. slowdown and temporary preparatory works within the facility
closing of railway traffic. construction are to be made of appropriate
materials so the proper stability and safety of
For all the works that are to cause the the temporary scaffold are provided in the
abovementioned consequences, the course of its usage.
Contractor is to acquire consent/permit from
the relevant or control authority. When power cable installations are to be
dislocated within the preparatory works for
the facility construction, such action is too
2.1.3.2 Execution method performed in the manner that provides
undisturbed power supply for the users in the
2.1.3.2.1 Traffic restrictions course of preparatory works. Undisturbed
usage and supply for the users is also to be
Restricting public road traffic is to be provided in the course of dislocating all the
performed in accordance with the Road other installations (PTT cable installation,
Traffic Safety Act. water supply, sewage system, gas pipelines,
and optical cable). All the necessary
The site protection in the course of dislocations within the preparatory works for
construction may be performed by complete the facility construction are to be performed
or partial closing of traffic, which is to be in accordance with the appropriate projects.
regulated by traffic lights or manually in Plans for the permanent rearrangement are
special cases. to be followed to the highest possible extent.
Type and closure time are to be specified in Within the preparatory works for the
detail in the traffic arrangement plan, and construction, the Contractor is to prepare all
controlled all the time and, if necessary, the temporary facilities necessary for
supplemented or altered. undisturbed execution of works on the site.
All the facilities are to be executed according
As soon as there is no more need to protect to the appropriate projects and in the manner
the site by traffic restriction, the Contractor is that does not disturb completion of works on
bound to remove all the equipment placed for other facilities within the construction. After
the traffic closure. temporary facilities are removed, the
Contractor is generally to restore prime
Public area traffic may be restricted only for condition of the damaged surfaces.
the shortest possible and professionally
justified time and within the least possible Detailed execution procedure for the
extent. mentioned repair works on the facilities is to
be specified in the design documentation. In
2.1.3.2.2 Facility-related preparatory works case that the Supervising Engineer
determines that the actual condition of the
Within preparatory works for the facility, the damaged facilities deviates from the
Contractor is to arrange all temporary envisaged one, he is entitled to determine the
beltways, bypasses, water flow redirecting appropriate alteration to the procedure within
and traffic protection under and along the the contracted provisions.
facility, necessary for undisturbed and safe
execution of works and for traffic safety. All All the previous repair works on the facility
the above mentioned works are to be are to be executed in the manner that
executed according to the appropriate provides safe execution of works with no
projects.

6 PE Roads of Serbia
Serbian Road Construction Specifications Preparatory Works

damages to the adjacent facility surfaces or 2.1.3.3 Construction quality


to the surroundings.
All works within preparatory works specified
The Contractor is to remove the undamaged in this chapter are to be executed in
prefabricated elements and dilatation so they accordance with the required quality for
are not damaged and ready to be reused. certain elements in appropriate projects
according to these special technical
Machines are to be used as much as conditions and the Supervising Engineer's
possible for demolition of monolithic elements instructions.
and planned removal of damaged cement
concrete. The Supervising Engineer is In case that the Supervising Engineer
entitled to alter the planned procedure and determines that execution of preparatory
extent of works within the approved bill of works specified under sub-clause 2.1.3.4.2 in
quantities, if it is determined that the planned terms of quality is not in accordance with the
procedure is not to reach the aim of works. projects, he is entitled to halt the works and
demand remedy of defects.
In case that exposing the reinforcement is
necessary for the facility repair, sound middle The Contractor is to inform the Supervising
third of the reinforcing bar must not be Engineer of any problems that might occur in
damaged. the course of execution of specified
preparatory works and that might affect the
Removal of mortar from the compositions in quality of executed works. If the Contractor
stone and brick walls is to be performed to fails to do so, he is to take all the
such extent that provides necessary fitting of responsibility and possible repair expenses.
the new mortar in the composition with
cleaned stone or brick.
2.1.3.4 Quality control
Appropriate mechanical equipment (diamond
The quality of all executed preparatory works
saw or steel rope) enabling accurate
within the design documentation is to be
execution of the planned works is to be used
inspected by the Supervising Engineer. In
for cutting of plain or reinforced concrete and
case that the Supervising Engineer
stone. The same is to be taken into
determines that execution of preparatory
consideration when holing.
works specified under sub-clause 2.1.3.4.2 is
not in accordance with the design
All the other necessary removals of the
documentation, he is entitled to halt the
existing facility elements (e.g. arches,
works and demand remedy of defects.
dewatering equipment, waterproofing) are to
be performed with care and to the planned
extent. 2.1.3.5 Measuring and taking over of
works
2.1.3.2.3 Compensations
2.1.3.5.1 Measuring
The Contractor is to provide appropriate
compensation, based on the objective The extent of all the preparatory works
evaluation of damages to the existing roads described in the chapter is to be specified in
due to overloading caused by heavy vehicles detail in appropriate projects. The
in the course of transports for needs of the Supervising Engineer is to determine whether
construction works. the planned works are actually executed and
to determine the extent of actually executed
The appropriate compensation is also to be works.
provided for all disturbances of railway traffic
(slowdowns and standstills) caused by the 2.1.3.5.2 Taking over
national road construction.
Completed works within the extent specified
The Contractor is entitled to claim under sub-clause 2.1.3.7.1 are to be taken
compensation for standstill in the course of over by the Supervising Engineer in
tunnel excavation due to inadmissible accordance with provisions specified in the
concentration of explosive gases, force general and special technical conditions.
majeure or the Supervising Engineer’s
instruction.

PE Roads of Serbia 7
Preparatory Works Serbian Road Construction Specifications

2.1.3.6 Calculation of works

All completed works, specified under sub-


clause 2.1.3.7.1 and taken over according to
the sub-clause 2.1.3.7.2, are to be calculated
and paid according to the unit prices
indicated in the contracted bill of quantities.
Possible additional works are to be
calculated according to provisions specified
in the general technical conditions.

8 PE Roads of Serbia