Вы находитесь на странице: 1из 2

G.R. No.

126619             December 20, 2006


UNIWIDE SALES REALTY AND RESOURCES CORPORATION
vs.TITAN-IKEDA CONSTRUCTION AND DEVELOPMENT CORPORATION

FACTS: Titan-Ikeda entered into 3 construction agreement with Uniwide. Titan-Ikeda


then filed with the RTC an action for a sum of money against Uniwide because the latter
failed to pay certain claims billed by Titan after the completion of the 3 projects. Uniwide
moved for the dismissal/suspension of the proceeding in order for them to proceed with
arbitration. The Arbitrators issued terms of reference which was signed by the parties.
Uniwide did not attempt to modify the TOR to accommodate its belated counterclaim on
deadlines for liquidated damages. Titan then filedthe case with CIAC.
In its decision, the CIAC declared the following: That in Project 1, Uniwide is
absolved of any liability. In Project 2, Uniwide is absolved of any liability for VAT
payment and for the account of Titan, and Titan is absolved from liability for defective
construction. In Project 3, Uniwide is held liable for unpaid balance (5,158,364.63) plus
12% interest/annum and to pay the full VAT for the additional work where no written
authorization was presented.
CIAC likewise rejected the claim on liquidated damages.
After Uniwide’s motion for reconsideration was denied by CIAC, it filed a petition
for review with CA but same was denied, thus, Uniwide filed a petition for review under
rule 45 to seek partial reversal of the decision of CA which modified the decision of
CIAC. Uniwide claims that CIAC should have applied procedural rules such as section
5, Rule 10 with more liberality because it was an administrative tribunal which free
from all rigid technicalities of regular courts because the CA held that the issue on
liquidated damages should be left for determination in future proceedings.
ISSUE: Whether or not CIAC should have applied the Rules of Court in the arbitration
proceeding.
RULING:
No. The rule of Procedure Governing Construction Arbitration promulgated by
the CIAC contains no provision on the application of the Rules of Court to arbitration
proceedings, even in a suppletory capacity. Such importation of the Rules of Court
provision on amendment to conform to evidence would contravene the spirit, if not the
letter of the CIAC rules. This is for the reason that the formulation of the Terms of
Reference is done with the active participation of the parties and their counsel
themselves. The TOR is further required to be signed by all the parties, their respective
counsel and all the members of the Arbitral Tribunal. Unless the issues thus carefully
formulated in the Terms of Reference were expressly showed to be amended, issues
outside thereof may not be resolved. As already noted in the Decision, "no attempt was
ever made by the [Uniwide] to modify the TOR in order to accommodate the issues
related to its belated counterclaim" on this issue.
Arbitration has been defined as "an arrangement for taking and abiding by the
judgment of selected persons in some disputed matter, instead of carrying it to
established tribunals of justice, and is intended to avoid the formalities, the delay, the
expense and vexation of ordinary litigation.

Вам также может понравиться