Вы находитесь на странице: 1из 3

Control – SDLC – Pivotal – Request Tracker Matrix

Control SDLC Pivotal (& Request Tracker)


Change Requirements • Requestor / Stakeholder • Enters into Pivotal, where stored in “IceBox”
creates a Story bucket in Pivotal.
Change Requirements Further Story Elaboration • While in IceBox
User Acceptance Testing • Requestor / Stakeholder • Acceptance Criteria (test plans) is included in
defines Story Test Plans Story when it is entered into Pivotal.
Change Requirements • Estimate • While in Ice Box – sometimes
Change Requirements • Feature Prioritization occurs • Once meeting occurs, Stories move to “Backlog”
during Iteration or Release bucket in Pivotal, which is the official approval of
Planning and/or Schedule the Change Request to be worked.
Elaboration and Estimation • Backlog reflects current prioritization and is
Meeting controlled by the business.
• Development • Developer hits “Start” which means work has
begun.
• Story is moved to “Current” bucket in Pivotal.
• Once development is complete – developer hits
“Finish” button, which means it is ready for
Stakeholder review/testing.
• Email is automatically sent to Requestor
indicating ready to test.
• Remains in “Current” bucket in Pivotal, with an
indication that it is “Delivered” meaning ready for
testing by Stakeholder.
User Acceptance Testing • Stakeholder / Requestor • If “Approved,” Stakeholder/Requestor hits
tests changes usually in Dev “Approve” button, which is indication that it is ready
environment, sometimes in QA for QA team to test.
environment. • If “Reject” button is hit, the Story goes back into
a Restart state for developer to restart. See above
under Development.
• Release Markers here or sooner to indicate which
Stories are included in a Release.

1
Control – SDLC – Pivotal – Request Tracker Matrix

User Acceptance Testing • QA conducts testing – unit – • Remains in “Current” bucket through testing.
usually in Dev • If bugs are found, “Defect” Story entered into
• Regression and Integrity Pivotal, then Story is “Started,” then put back into
testing of entire Release in QA. the Release (or left in the Backlog if taken of
• Standard Critical Path Release. When testing completed, QA hits “Finish”
document for that particular button which indicates their testing sign-off for the
product is used as the QA Test Release.
Plan.
• If defects found, they are
sent back to developer to be
fixed.
• When testing is completed,
they sign off.
Implementation into • Once testing is completed, • QA creates a staging ticket in Request Tracker
Production Deployment by Infrastructure (not Pivotal) to stage the release into production.
Team can occur. Once Release is migrated to production, QA will
perform Critical Path Testing and update staging
ticket with test results. Infrastructure will then
closes ticket and email is sent to QA requestor and
appropriate management team indicating release
has been migrated.

Communication • Appropriate project manager Action Item: This email needs to be retained.
sends a communication to
business owners and users
(where appropriate) with
highlights of what was included
in the release.

2
Control – SDLC – Pivotal – Request Tracker Matrix

Post Implementation • If any problems were


Reviews encountered during the
implementation, there may be a
meeting reviewing the
challenges, so the process can
continue to be improved.
• Retrospective meetings are
scheduled on occasion, but on a
case-by-case basis as needed.
• No meetings are held if all
went fairly well.

Вам также может понравиться