TO LOADING PUMP-1 CL=7.

46 KW

2x3core 6mm sq PVC/PVC Cu:Cond Cables


D.B LOADING/

+1x6mm sq as C.P.C
HOA
MCCB
20ATP
Ics:15 KA

CL=7.46 KW
UNLOADING PUMPS

TO LOADING PUMP-2
2x3core 6mm sq PVC/PVC Cu:Cond Cables
+1x6mm sq as C.P.C
HOA
MCCB
20ATP
Ics:15 KA

TO SHIFTING PUMP-1 CL=7.46 KW

2x3core 6mm sq PVC/PVC Cu:Cond Cables


+1x6mm sq as C.P.C
MCCB
Ics:15 KA

HOA
100ATP

MCCB
20ATP
Ics:15 KA

CL=7.46 KW
FROM S.M.P.B RESIN HALL

TO SHIFTING PUMP-2
2x3core 6mm sq PVC/PVC Cu:Cond Cables
+1x6mm sq as C.P.C
+1x16mm sq as C.P.C

HOA
MCCB
20ATP
Ics:15 KA

TO SHIFTING PUMP-3 CL=7.46 KW

2x3core 6mm sq PVC/PVC Cu:Cond Cables


+1x6mm sq as C.P.C
1x4core 35mm sq PVC/PVC Cu:Cond Cable

HOA
MCCB
20ATP
Ics:15 KA