In ity the plan is to excavate this polygon but well before it is necessary to establish the temporary
ramp and then take to this level until here.
We are waiting for the drill to be available to begin drilling this surface and clear the area and then
the one to allow us to go lower
À Bakatouo, la préparation de piste avec les blocs sur la rampe et au niveau du bassin étant terminé,
nous ouvrons le niveau 245.
Il faut noter qu'il y a 2 niveaux supérieurs qui ne sont pas au projet dans cette zone 247.5 et 250rl
In bakatouo, the preparation of track with the blocks on the ramp and at the level of the basin being
finished, we open the level 245.
It should be noted that there are 2 higher levels that are not in the project in this zone 247.5 and
250rl