ÍTEM: 3.

ESTRUCTURAS
ACTIVIDAD: 3.1 RECEBO DE CIMENTACIONES

UNIDAD DE MEDIDA: m3

1. MATERIALES

DESCRIPCION UNIDAD CANTIDAD Vr.UNITARIO


Recebo m3 1.500 22,220.00
SUB-TOTAL

2. MANO DE OBRA

DESCRIPCION Vr. JORNAL PREST. JORNAL TOT. REND/DIA


Cuadrilla de construcción 0x1 38,184.00 90.00% 72549.600 8.00
SUB-TOTAL

3. HERRAMIENTAS - EQUIPOS

DESCRIPCION UNIDAD TARIFA/DIA REND/DIA


Vibrocompactador ( Rana) 8 h.p. DM 59000.000 15.00
Herramienta Menor %
SUB-TOTAL

TOTAL COSTO DIRECTO :

ÍTEM: 3. ESTRUCTURAS

ACTIVIDAD: 3.2 CONCRETO CICLOPEO


UNIDAD DE MEDIDA: m3

1. MATERIALES

DESCRIPCION UNIDAD CANTIDAD Vr.UNITARIO


Piedra m3 0.600 30,000.00
CONCRETO 17.5 MPa MEZCLADO EN OBRA m 3 0.630 221,297.10
SUB-TOTAL

2. MANO DE OBRA

DESCRIPCION Vr. JORNAL PREST. JORNAL TOT. REND/DIA


Cuadrilla de construcción 1x4 234,876.00 90.00% 446264.400 28.00
SUB-TOTAL

3. HERRAMIENTAS - EQUIPOS

DESCRIPCION UNIDAD TARIFA/DIA REND/DIA


Formaleta metálica de 1*0.5 M-Und Du 200.000 0.03
Paral metálico 3m Du 139.000 0.10
Cercha metálica Du 139.000 0.20
Herramienta Menor %
SUB-TOTAL

TOTAL COSTO DIRECTO :

ÍTEM: 3. ESTRUCTURAS
ACTIVIDAD: 3.3.1 VIGA DE AMARRE DE CIMENTACION 0,25x0,25 m

UNIDAD DE MEDIDA: m3

1. MATERIALES
DESCRIPCION UNIDAD CANTIDAD Vr.UNITARIO
Concreto normal 21.0 MPaTM 1 1/2" m 3 1.580 290,000.00
SUB-TOTAL

2. MANO DE OBRA

DESCRIPCION Vr. JORNAL PREST. JORNAL TOT. REND/DIA


Cuadrilla de construcción 1x3 196,692.00 90.00% 373714.800 7.00
SUB-TOTAL

3. HERRAMIENTAS - EQUIPOS

DESCRIPCION UNIDAD TARIFA/DIA REND/DIA


Vibrador (Gas/Elec) HM 49880.000 15.00
Formaleta metálica de 1 *0.25 DU 120.000 0.10
Herramienta Menor %
SUB-TOTAL

TOTAL COSTO DIRECTO :

ÍTEM: 3. ESTRUCTURAS
ACTIVIDAD: 3.3.2 VIGA CORONA 0,1x0,1 m

UNIDAD DE MEDIDA: m3

1. MATERIALES

DESCRIPCION UNIDAD CANTIDAD Vr.UNITARIO


Concreto normal 21.0 MPaTM 1 1/2" m 3 1.490 290,000.00
SUB-TOTAL
2. MANO DE OBRA

DESCRIPCION Vr. JORNAL PREST. JORNAL TOT. REND/DIA


Cuadrilla de construcción 1x2 196,692.00 90.00% 373714.800 15.00
SUB-TOTAL

3. HERRAMIENTAS - EQUIPOS

DESCRIPCION UNIDAD TARIFA/DIA REND/DIA


Vibrador (Gas/Elec) HM 49880.000 15.00
Formaleta metálica de 1 *0.25 DU 120.000 0.10
Herramienta Menor %
SUB-TOTAL

TOTAL COSTO DIRECTO :

ÍTEM: 3. ESTRUCTURAS
ACTIVIDAD: 3.3.3 VIGA CINTA 0,1x0,1 m

UNIDAD DE MEDIDA: m3

1. MATERIALES

DESCRIPCION UNIDAD CANTIDAD Vr.UNITARIO


Concreto normal 21.0 MPaTM 1 1/2" m 3 1.490 290,000.00
SUB-TOTAL

2. MANO DE OBRA
DESCRIPCION Vr. JORNAL PREST. JORNAL TOT. REND/DIA
Cuadrilla de construcción 1x2 158,508.00 90.00% 301165.200 72.00
SUB-TOTAL

3. HERRAMIENTAS - EQUIPOS

DESCRIPCION UNIDAD TARIFA/DIA REND/DIA


Vibrador (Gas/Elec) HM 49880.000 15.00
Formaleta metálica de 1 *0.25 DU 120.000 0.10
Herramienta Menor %
SUB-TOTAL

TOTAL COSTO DIRECTO :

ÍTEM: 3. ESTRUCTURAS
ACTIVIDAD: 3.4 COLUMNAS EN CONCRETO 0,1x0,25 m

UNIDAD DE MEDIDA: m3

1. MATERIALES

DESCRIPCION UNIDAD CANTIDAD Vr.UNITARIO


Concreto normal 21.0 MPaTM 1 1/2" m3 1.500 290,000.00
SUB-TOTAL

2. MANO DE OBRA

DESCRIPCION Vr. JORNAL PREST. JORNAL TOT. REND/DIA


Cuadrilla de construcción 1x2 158,508.00 90.00% 301165.200 60.00
SUB-TOTAL
3. HERRAMIENTAS - EQUIPOS

DESCRIPCION UNIDAD TARIFA/DIA REND/DIA


Formaleta metálica de 1 *0.5 M-Und Du 200.000 0.01
Vibrador (Gas/Elec) hM 49880.000 2.50
Herramienta Menor %
SUB-TOTAL

TOTAL COSTO DIRECTO :

ÍTEM: 3. ESTRUCTURAS
ACTIVIDAD: 3.5 PLACA CONTRAPISO e= 0,10

UNIDAD DE MEDIDA: m3

1. MATERIALES

DESCRIPCION UNIDAD CANTIDAD Vr.UNITARIO


Concreto normal 21.0 MPaTM 1 1/2" m 3 1.310 290,000.00
SUB-TOTAL

2. MANO DE OBRA

DESCRIPCION Vr. JORNAL PREST. JORNAL TOT. REND/DIA


Cuadrilla de construcción 1x2 158,508.00 90.00% 301165.200 18.00
SUB-TOTAL

3. HERRAMIENTAS - EQUIPOS

DESCRIPCION UNIDAD TARIFA/DIA REND/DIA


Herramienta Menor %
SUB-TOTAL
TOTAL COSTO DIRECTO :
3 ESTRUCTURAS
3.1 CIMENTACIONES
RECEBO
EJE 1(A-C)
EJE 2(A-C)
EJE 3(A-B)
EJE A(1-3)
Vr.TOTAL EJE B(2-3)
36,663.00 EJE C(1-2)
36,663.00
3.2 CONCRETO CICLOPEO
EJE 1(A-C)
EJE 2(A-C)
EJE 3(A-B)
EJE A(1-3)
EJE B(2-3)
EJE C(1-2)

Vr. TOTAL 3.3 VIGAS EN CONCRETO


9,069.00 VIGA DE AMARRE DE CIMENTACION
9,069.00 0,25m*0,25m
0,20*0,25
VIGA CORONA
0,1*0,1
VIGA CINTA

Vr. TOTAL
3933.333333333 0,1*0,1
906.90
4,840.23

3.4 COLUMNAS EN CONCRETO


0.1*0.25
50,572.23
3.5 PLACA CONTRAPISO
Vr.TOTAL
21,600.00
139,417.00
161,017.00

Vr. TOTAL
15,938.01
15,938.01

Vr. TOTAL
8000
1390
0.00
1593.80
10,983.80

187,938.82

0,25 m
Vr.TOTAL
549,840.00
549,840.00

Vr. TOTAL
53,387.83
53,387.83

Vr. TOTAL
3325.333333333
1200
5338.78
9,864.12

613,091.94

Vr.TOTAL
475,310.00
475,310.00
Vr. TOTAL
24,914.32
24,914.32

Vr. TOTAL
3325.333333333
1200
2491.43
7,016.77

507,241.09

3.3.3 VIGA CINTA

Vr.TOTAL
475,310.00
475,310.00
Vr. TOTAL
4,182.85
4,182.85

Vr. TOTAL
3325.333333333
1200
418.29
4,943.62

484,436.47

3.4 COLUMNAS EN CONCRETO

Vr.TOTAL
500,250.00
500,250.00

Vr. TOTAL
5,019.42
5,019.42
Vr. TOTAL
40000
19952
501.94
60,453.94

565,723.36

3.5 PLACA CONTRAPISO

Vr.TOTAL
436,885.00
436,885.00

Vr. TOTAL
16,731.40
16,731.40

Vr. TOTAL
1673.14
1,673.14
455,289.54
ESTRUCTURAS
CIMENTACIONES
RECEBO
EJE 1(A-C) 0,3*0,05*7,205 m^3 0.108075
EJE 2(A-C) 0,3*0,05*7,205 m^3 0.108075
EJE 3(A-B) 0,3*0,05*4,64 m^3 0.0696
EJE A(1-3) 0,3*0,05*5,3 m^3 0.0795
EJE B(2-3) 0,3*0,05*2,55 m^3 0.03825
EJE C(1-2) 0,3*0,05*2,75 m^3 0.04125

CONCRETO CICLOPEO
EJE 1(A-C) 0,3*0,3*7,205 m^3 0.64845
EJE 2(A-C) 0,3*0,3*7,205 m^3 0.64845
EJE 3(A-B) 0,3*0,3*4,64 m^3 0.4176
EJE A(1-3) 0,3*0,3*5,3 m^3 0.477
EJE B(2-3) 0,3*0,3*2,55 m^3 0.2295
EJE C(1-2) 0,3*0,3*2,75 m^3 0.2475

VIGAS EN CONCRETO
VIGA DE AMARRE DE CIMENTACION
0,25m*0,25m 12,48*0,25*0,25 m^3 0.78
0,20*0,25 9,955*0,20*0,25 m^3 0.49775
VIGA CORONA
0,1*0,1 0.1*0.1*22.435 m^3 0.22435
VIGA CINTA
0.1*0.1*6 m^3 0.06
0.1*0.1*6 m^3 0.06
0.1*0.1*3.05 m^3 0.0305
0,1*0,1 0.1*0.1*2.85 m^3 0.0285
0.1*0.1*7.15 m^3 0.0715
0.1*0.1*7.15 m^3 0.0715
0.1*0.1*4.6 m^3 0.046

COLUMNAS EN CONCRETO
0.1*0.25 0.10*0.25*2.13*10 m^3 0.5325

PLACA CONTRAPISO (87.5886-(3.05*1.51))*0.10 m^3 8.29831

TOTAL
TA
S EN CONCRETO
NTRAPISO
0.44475

134.3927

36162.3
2.6685
2.28

1.8701

0.5325

8.29831

13.814
ÍTEM: 9. MAMPOSTERIA
ACTIVIDAD: 9.1 MUROS EN BLOQUE e=0.12 m

UNIDAD DE MEDIDA: m2

1. MATERIALES

DESCRIPCION UNIDAD CANTIDAD Vr.UNITARIO


MORTERO 1:4 MEZCLADO EN OBRA m 3 0.020 217,867.48
Bloque muro Hl2 12*20*40 und 12.000 1,450.00
SUB-TOTAL

2. MANO DE OBRA

DESCRIPCION Vr. JORNAL PREST. JORNAL TOT. REND/DIA


Cuadrilla de construcción 1x1 120,324.00 90.00% 228615.600 17.60
SUB-TOTAL

3. HERRAMIENTAS - EQUIPOS

DESCRIPCION UNIDAD TARIFA/DIA REND/DIA


Herramienta Menor %
SUB-TOTAL

TOTAL COSTO DIRECTO :

ÍTEM: 9. MAMPOSTERIA
ACTIVIDAD: 9.1 MURO LADRILLO A LA VISTA e=0.12 m

UNIDAD DE MEDIDA: m2

1. MATERIALES

DESCRIPCION UNIDAD CANTIDAD Vr.UNITARIO


MORTERO 1:4 MEZCLADO EN OBRA m3 0.025 217,867.48
Ladrillo colonial 7* 12*25 und 56.000 350.00
SUB-TOTAL

2. MANO DE OBRA

DESCRIPCION Vr. JORNAL PREST. JORNAL TOT. REND/DIA


Cuadrilla de construcción 1x1 120,324.00 90.00% 228615.600 14.00
SUB-TOTAL

3. HERRAMIENTAS - EQUIPOS

DESCRIPCION UNIDAD TARIFA/DIA REND/DIA


Herramienta Menor %
SUB-TOTAL

TOTAL COSTO DIRECTO :


9 MAMPOSTERIA

9.1 MUROS EN BLOQUE


EJE 1 (12.39*2.1)+2.169+
EJE 2 (8.4*2.1)+2.169+4
EJE 3 (10.65*2.1)+1.633+
EJE A 8.758+9,291
PARTE TRASERA 2.1*6
COCINA (1.4*2.1)+(1*1.
Vr.TOTAL BAÑO 1.95*(2.1+1.31)+1.2*(
4,357.35 FACHADA (0.46*2.56)*2+(0.6
17,400.00
21,757.35 9.2 MURO LADRILLO A LA VISTA 1.9*0.6*2

Vr. TOTAL
12,989.52
12,989.52

Vr. TOTAL
1298.95
1,298.95

36,045.82
Vr.TOTAL
5,446.69
19,600.00
25,046.69

Vr. TOTAL
16,329.69
16,329.69

Vr. TOTAL
1632.97
1,632.97

43,009.34
m^2

1
(12.39*2.1)+2.169+4.398 m^2 32.586
(8.4*2.1)+2.169+4.398 m^2 24.207
(10.65*2.1)+1.633+3.064 m^2 27.062
8.758+9,291 m^2 18.049 134.3927
2.1*6 m^2 12.6
(1.4*2.1)+(1*1.08) m^2 4.02
1.95*(2.1+1.31)+1.2*(2.1+1.31) m^2 10.7415
(0.46*2.56)*2+(0.693*4) m^2 5.1272

1.9*0.6*2 m^2 2.28 2.28