Академический Документы
Профессиональный Документы
Культура Документы
Manual
Overview
Principles of Operation
Commissioning
CMC Controls
Maintenance
Troubleshooting
Copyright Notice
2001 Ingersoll-Rand Company
PROPRIETARY NOTICES
Copyright 2001 INGERSOLL-RAND COMPANY
CONFIDENTIAL AND TRADE SECRET INFORMATION. This manual contains confidential and
trade secret information owned by Ingersoll-Rand Company (hereinafter referred to as
“Proprietary Matter”). In consideration of the disclosure of the Proprietary Matter herein to the
authorised recipient hereof, the recipient shall treat the Proprietary Matter as secret and
confidential; shall not disclose or give such Proprietary Matter to third parties without the express
written authorisation of INGERSOLL-RAND; shall not use the Proprietary Matter except to the
extent necessary to sue or service the equipment disclosed herein; and shall disclose such
Proprietary Matter only to those of its employees whose use or knowledge of the Proprietary
Matter is necessary. This manual shall be returned upon request by Ingersoll-Rand Company.
The unauthorised use of this manual may be punishable by law.
DISCLAIMERS
PROVIDED “AS IS”. THIS MANUAL AND THE CONTENTS THEREOF ARE PROVIDED “AS
IS” AND WITHOUT ANY IMPLIED WARRANTIES.
Introduction
Introduction & Index
Section 6—Commissioning
Index Pre-Start Checklist...................................... 1—3
Initial Start Preparation ............................... 4—6
Section 1—Overview Natural Surge Testing................................. 7—8
Machine Description ................................... 1—6 Installation Checklist ......................................... 9
Centrifugal Compressor Product Line ....... 7—10 Short Test ....................................................... 10
Short Test .......................................................11 Start Up Registration Form ..................... 11—16
Warranty and Limitation of Liability......... 17—19
Section 2—Principles of Operation Short Test ....................................................... 20
Basic Principles of
Centrifugal Compressors .............. 1—3 Section 7—Airend Overhaul
Characteristic Pressure verses Flow Plot ... 4—5 Disassembly of Stage Components............ 1—4
Surge .......................................................... 6—7 Disassembly of Bull Gear from the casing.. 5—6
Choke and Stonewall ........................................8 Assembly of Bull Gear into the Casing ....... 7—9
The effect of air density.....................................9 Assembly of Stage Components ............ 10—14
Compressor Operating Methodology ...... 10—12 Impeller/Diffuser Clearance
Changing Air Inlet Setting Procedure ................. 15—18
Temperature & Pressure............ 13—14 Short Test ....................................................... 19
The Centac Performance Curve ............. 15—16
Inlet Valve Control of the Throttle Range........17 Section 8—Airend Ovehaul for Models
Stopping, Starting and Un-loading Control .....18 C250/C350
The effect of changes in Air Inlet Conditions ..19 Disassembly of Stage Components.......... 1—10
Inlet Guide Vane (IGV)....................................20 Disassemble the Bullgear ....................... 11—13
Basic Multi-Staging and Intercooling...............21 Re-assemble the Bullgear ...................... 14—17
Typical (Actual) Centac Performance Curve...22 Re-assemble the Stage Components..... 18—26
Bypass Valve Control......................................23 Setting Rotor Assembly Clearances ............... 27
Short Test .......................................................24 Impeller/Diffuser Clearance
Setting Procedure ................ 28—31
Section 3—Principles of Operation Installing the Coupling .................................... 32
Inlet & Bypass Valve Operation .................. 1—7
The Actuator................................................ 8—9 Section 9—CMC Technical Reference Manual
Butterfly Inlet & Bypass Valve ................. 10—11
Regulation & Coalescing Filter................ 12—14
Inlet and Bypass Valve Positioners......... 15—23 Section 10—Maintenance
Short Test........................................................24 Scheduled Preventative Maintenance ........ 1—4
Maintenance Procedures............................ 5—6
Section 3—Lubrication Setting Impeller Clearance ......................... 7—9
Overview ..................................................... 1—4 Maintenance Procedures........................ 10—11
Lubricant Conversion Procedures............... 5—7 Short Test ....................................................... 12
Material Safety Data Sheets ..................... 8—13
Short Test........................................................14 Section 11—Troubleshooting
Troubleshooting Guide ............................... 1—6
Common Conversions and Information .... 7—12
Section 1
Description of the Machine .........................................1—6
Centrifugal Compressor Product Line ........................7—10
Short Test ...................................................................11
Thrust Bearing
Pinion
Diffuser
Plain Vibration
Bearing Probe Cross section of an IR Centac Compressor
Carbon Ring
Seals
Rotor Assembly
Seals
A single cartridge seal is mounted
in the plain bearing housing behind
each impeller. Each cartridge
consists of three, one piece, fully
floating non-contact carbon rings.
One ring is used as an air seal and
the other two rings are used as oil
seals. Clean instrument quality air
is supplied to the oil seals, as a buffer. This ensures
that the lube oil is not drawn past the seals, and that
air remains oil free.
Centac Models 1ACVII, 1ACV and 1BCV
Use an Oil Reverse Thrust Bearing without a
Diffusers
A diffuser is located between each
impeller and each cooler. The
diffusers are designed for
maximum efficiency, while limiting
physical size, thereby keeping the
compressor as compact as
possible.
Vibration Probes
A non-contacting vibration probe is mounted in each
stage, next to the
plain bearing. The
vibration probe
measures the radial vibration of each rotor
assembly. The probe is connected to a vibration
transmitter. The first stage vibration protection is
standard on all the compressors.
When the unit trips on the shutdown cycle, the All the necessary instruments and safety devices are
prelube pump will start immediately and will included in the lubrication system to protect the
continue to run until the panel is de-energized. compressor. These include:
• A pressure transmitter that senses oil pressure
After the compressor shuts down, the prelube pump and the compressor low oil pressure.
should be allow to run 20 to 30 minutes to cool
• An RTD and temperature-transmitter that senses
down the compressor bearings.
abnormal oil temperature. An interlock is also
provided to prevent the unit from being started if
oil temperature is below the minimum.
• A wet element type lube oil reservoir heater that
ensures adequate oil temperature for compressor
start-up.
• The lube oil reservoir has provisions for a lube oil
drain with plug. The customer may install a valve
on the connection to facilitate changing lubricant.
• An oil temperature control device that
automatically regulates proper oil temperature to
the bearings by mixing hot and cold lubricant.
Centac II A new version of the Centac baseplate mounted motor with barrel cooler.
2ACII
Engine
Drive
2ACII
Process
Package
with
external
coolers
2CII 3200-4500 800-1500 2, 3 stage & DF 3rd stage is high pressure
3CII 6000-9000 1000-2000 2-3 stage
Short Test
Answer each question as fully as you can, or tick the best option.
When you finish, check your answers by reading through the section again.
3 How many different types of reverse thrust (inactive) bearings are used in
Centac compressors?
5 What type of seal is used in the rotor assembly to protect against air and oil
leaks?
Intercooler Moisture
Separators
6
The steps 1-5
repeats in each
succeeding stage,
until the compressor
achieves the desired
operating pressure.
Air Filter
Inlet Valve
In this section, you will learn The terms used in describing the process of
• The basic operation of Centrifugal compressors compression in the centrifugal compressor come from
• The characteristic plot for “Pressure verses centrifugal pump theory.
Flow”
Air can be considered as a fluid, and the same
• The Actual Pressure plot thermodynamic principles and terms apply to
• Surge compressors as well as pumps. The term "head" is
• The effects of changing air inlet temperature one of these. In the centrifugal compressor, the
and pressure amount of work done to move one pound of air
through the compressor, is the "head”. The
• How the Inlet Valve controls throttle range
dimension of head is foot-pounds/per pound (ft-lbs/lb)
• How the Bypass Valve controls system low flow and is a measure of work.
demand
• Chock and Stonewall The process that air undergoes in the centrifugal
compressor (velocity slows, pressure increases) can
be re-stated as: If flow decreases, pressure increases.
The work input takes place as an increase in This is true because it is a volume-of-air that has
pressure and velocity (speed) of the air flow through velocity.
the impeller. The air flow subsequently loses
velocity in the diffuser section. The volume measurement used is cubic foot or cubic
meter of air. A volume that is moving past a point on a
Figure 1 shows the velocity, pressure and per-unit time basis has a rate. The term for rate is
temperature changes that occur in a theoretical "flow" and its dimension is cubic feet/per minute (ft 3 /
single stage centrifugal compressor. About two- min).
thirds of the pressure developed occurs in the
impeller with one-third produced in the diffuser. In a centrifugal compressor, (at constant speed and
constant inlet cfm) the amount of work required to
psia move one pound of air (head), remains constant
Pressure PSIA regardless of inlet conditions, as the following table
reveals. The Items marked (*) are changes from the
column labeled Design.
ft/sec
Item Design 1 2 3
Pre
ssu
re-F
low
Plo
t
PSIA
Pre
s su r
e-F
l ow
PSIA
Plo
t
100%
0 FLOW 100%
Surge
Surge is a momentary reversal of flow in a
compressor. Surge occurs at the peak pressure of
the characteristic curve and it exists because of the
way losses affect ideal compression. When the
compressor is in surge it is unstable and cannot
perform a useful function.
9 When pressure
reaches point P, the
surge process repeats.
4 The operating point jumps to
point J with reverse flow on
the left. The reversal of flow is 3 Surge occurs at
point P, the
accompanied by a noise that may
natural surge point.
sound like "whomp”.
8 Pressure
starts to
CYCLIC SURGE MODEL (LARGE VOLUME
increase again
along line Q - P.
J P 2 Pressure rises
toward point P, as
5 The flow the flow decreases.
reversal
causes pressure
to decrease along K Q
line J - K.
1 Assume that only a
discharge valve
PSIA
Density of air is influenced primarily by temperature, Density significantly affects how much work the
pressure, and humidity. The dimension of density is compressor is doing at any given time. It takes more
pounds-per-cubic-foot at Standard Temperature and work to move heavier air..
Pressure of air (STP) conditions.
As an example:
The values used for STP, in the gas compression
industry, are 60oF, 14.7 psia, with a relative humidity Assume a compressor will transfer 10000 ft3 per
of 0%. The STP temperature used by general minute at dry air inlet conditions.
science and industry is usually 60°F
• At 14.4 psia and 60°F, the compressor will
As air temperature increases, the density decreases. transfer {(10000 ft3 /min.) X (1 lb/13.5 ft3 )} = 749
The opposite is true for colder air; as air pressure lbs/min.
increases, the density increases. • At 14.4 psia and 100°F it will transfer 695 lbs/min.
Decreasing pressure results in decreasing density. Less work is done on the 10000 ft3 in one minute at
The more water vapor in the air, the lighter a cubic 100°F than at 60°F.
foot of air will be. On a very hot, humid day, the air is
light and on a very cold, dry day, the air is heavy. • At 60°F, the model's compression ratio is (25.4
psia +14.4 psia) =1.764.
The formula for the density of dry air is:
• At the 100°F inlet condition, the compression ratio
Density = 1.325 X (Pb+T) lbs/ft 3 is 1.698.
Compressor Operating Methodology This period allows the compressor prelube pump to
In the following description of compressor operation, circulate oil throughout the casing and prevents
the term “state” is used to indicate what the restarting while the compressor is coasting down after
compressor is doing, or mode of operation, at any an electrical interruption.
given time. These operating states exist in a
hierarchy. For example, the two highest level states Not Ready
are “Stopped” and “Rotating”. All other states exist at When in this state, the compressor is “Not Ready To
a level below these two states. Start”. This state is entered when the Waiting Timer
has expired and whenever a compressor trip has
been identified or a stop command issued. A very
Compressor Operating States common, and quite often overlooked reason for the
Motor Driven Packages compressor being “Not Ready”, is when the
Emergency Stop push button has been engaged.
+ Compressor This state can exist indefinitely.
+ Stopped
Ready
Waiting This state could be redefined as “Ready to Start”. This
state is entered after all the compressor’s permissive
Not Ready functions have been satisfied. This state can exist
indefinitely.
Ready
+ Rotating Rotating
This mode does not necessarily mean that the
Starting compressor is actually rotating. It means that it is
Unloaded possibly rotating or rotation is pending and expected.
Stopped This state exits only after the Starting Timer has
This state implies that the compressor is NOT expired. The compressor is always started
rotating. It is important to note that this may not be unloaded.
true. If the instrumentation is not working properly or
if the system is set up improperly, the compressor On exit of “Starting”, the compressor will return to the
could still be rotating. mode that it was in, the last time the compressor ran.
For example, typical operation implies that, prior to
Waiting stopping the compressor, the Unload key is pressed.
After the panel power is energized, the controller If this occurred, then the compressor will remain in
starts the Waiting Timer and does not allow further “Unload” after starting. If the compressor was running
User operation until after the timer expires. This and tripped, the compressor will automatically return
timer is set at the factory for two minutes (120 to the “Loaded” mode on exit of the Starting state.
seconds) and is not adjustable.
Loading
When a valid load command is issued, the
compressor will enter this state. This state exists
until the MinLoad state is satisfied. The duration of
this state depends upon PID settings for the inlet
valve at the MinLoad state and the demand for air.
Unloading
This state occurs when a valid Unload command is
issued and will persist until the compressor reaches
the Unloaded state.
Coasting
When a trip or any stop command is issued, and the
compressor is running, the motor will be de-
energized and the compressor will begin to coast to
Starting
Unloaded
Loading
Loaded
Loaded
Unloading
Unloaded
Coasting
Full Load
MaxLoad
MinLoad
Waiting
75 16 8 75
Stop
Unload or Trip
50 12 12 50
Tight Closure
25 8 16 25
0 4 Load 20 0
Power
On
Stopped Rotating
Discharge PSIA
In the following graphs (Figures 6, 7, and 8), no 14.4 PSIA
control valves are considered. The compressor is (Mayfield)
operating with a fully open inlet and with a fixed Low altitude
discharge resistance. Adding control valves alters
the effect that changing temperatures have on
compressor operation.
Discharge PSIA
0oF Air
plus
40oF Water
Normal
95oF Air
80oF Water
0
110oF Air
plus
110oF Water
The Centac Performance Curve The function of the Centac compressor is to provide
The Centac performance curve is an variation of the oil-free compressed air at a specified pressure over
centrifugal compressor characteristic curve. A thorough a range of user-flow requirements. Controls allow
knowledge of the Centac performance curve will the Centac to perform its function. Figure 10 is a
provide a useful tool in the actual operation and stylized sketch of a single-stage centrifugal
maintenance of the Centac. compressor that has the necessary valves for
control. This stylized Centac compressor is the
Surge model for the discussions that follow.
100% Radial
A Design Point Diffuser
appears on the
performance
Impeller
curve. A Centac Inlet Valve
e
PSIA
lin
compressor is
ge
guaranteed to
ur
rS
produce the
do
Drive
and pressure for Shaft
Unloaded specofoc inlet
conditions.
For example: a machine may be built with a design If the system flow demand decreases, as it will when
point of 100 PSIG at 1800 ICFM. The impellers and the user shuts a system air valve, the pressure will
diffusers will be configured for this specification and the rise as flow decreases. The pressure increase
head will be fixed by this configuration. The design follows the performance curve as flow decreases.
point and head determine what minimum horsepower
driver needs to be used. As additional valves in the system close, the flow
decreases and the pressure rises higher and higher
The set of graphs that make up the performance curves until the pressure reaches the surge point. At the
include the Brake Horsepower versus Capacity Chart surge pressure, the compressor will experience
and the Discharge PSIG versus Capacity Chart. The pumping until such time as the system is able to
horsepower curve moves up and down with the effects accept more flow.
of changing density.
Impeller
Inlet Valve
Drive Shaft
Inlet
Valve
Actuator
Bypass Valve
SYSTEM
Pressure
Sensor
Controller
Inlet Valve Control of the Throttle Range The dotted lines above the inlet
The control system shown in Figure 11 will provide valve minimum closure point
control of the discharge as shown in Figure 12. In have the exact same shape as
Figure 12, the compressor is operating at the the uppermost line.
minimum closure point, at 60% of capacity. As long
as inlet conditions do not change, the system will be Inlet valve
supplied with 60% capacity, at design pressure, for minimum closure Design
as long as necessary. Point
Surge
If a valve in the system is opened, the flow will 100%
increase and the pressure will decrease. The
e
lin
signal will be sent to the inlet valve, from the
ge
controller. The valve will begin to open.
ur
rS
o
ad
Additional flow can pass through the inlet valve with
Lo
a larger opening. The system will accept exactly as Unload Throttle
much flow as needed and then pressure starts to range
rise. The controller causes the valve to stop
opening when the design pressure (or set pressure) Capacity (ICFM) 60% 100%
is reached.
The movement of the inlet valve
The system now is using increased flow, at design causes the performance curve to
pressure, with more horsepower being used. This shift because the density of the inlet
process repeats up to the pressure and flow point air, between the inlet valve and the
where the inlet valve is full open. Any additional flow impeller, changes as inlet flow
demand by the system, after the inlet valve is full decreases or increases.
open, will result in decreasing pressure and
eventually choke will occur, if system demand
increases high enough.
Power at Coupling (BHP)
The process of opening and closing the inlet valve, Capacity (ICFM) 60% 100%
in response to system demand, is called
“modulation”. The inlet valve is said to be Figure 12. Inlet valve throttle range modulation curves
modulating when it is opening and closing to meet
system demand. The capacity (flow) that the inlet With less dense inlet air, the pressure developed by
valve controls, between design point and near the compressor will decrease. The flow decreases
surge, is called the compressor “throttle range”. because it is limited by the inlet opening.
Figure 12 illustrates inlet valve modulation. If air The function of the inlet valve is to control inlet flow
enters the inlet valve at a constant density, the air and inlet pressure in the throttle range of the
after the inlet valve will be at some other density. As performance curve.
the inlet valve closes from full-open, in response to
decreased system demand, the flow through the Study Figure 12. When the inlet is at minimum
valve is limited. closure (minimum throttle), the surge point is nearly
at the design pressure line. If the compressor has a
As the valve closes, the air passing through it controlled inlet valve with no other controls, as
increases its velocity, and the pressure after the system flow demand reduces below the minimum
valve, will show a corresponding decrease; the closure position, the machine will surge. A surge
volume of air entering the valve is being limited. caused by closing the inlet more than the minimum
closure point is called a throttle surge.
Centac Training Manual
Ingersoll-Rand (Asia Pacific) Service Team
Issue: 01/Australia, March, 2003 Page 17
Principles of Operation Section 2
Stopping, Starting and Un-loading Control
A control system that has just an inlet valve, while To correct these problems on start, the control
providing service in the throttle range, doesn't allow opens the inlet valve a small amount and fully opens
the air system to take advantage of the full 0%-to- the bypass valve to vent-off the starting flow.
100% flow range. Flows between 60% and 100%
can be utilized with inlet-only control and the effects Un-loading. See Figure 12, unloaded position, in
of changing inlet temperature and pressure would be the top graph. Once started, the compressor is
partially controllable. An inlet-valve-only control operating at the unloaded or start position that
system is not very useful since low system flows and corresponds to the minimum opening position of the
changing inlet conditions cannot be accommodated. inlet valve. To load the compressor into the system,
the inlet valve initially opens to the minimum throttle
Stopping, Starting and Un-loading Control point. The bypass valve begins to close once the
Stopping presents no problem. Simply turning off inlet is at minimum throttle. Depending on system
the power supply (electricity, steam, or other) to the pressure, the bypass will modulate, and when it
driver will result in the compressor slowing down and reaches fully closed, the inlet will modulate on
coming to a stop. When stopped, there is a very system pressure.
real possibility that the compressor will reverse
rotate, from a reverse flow, caused by the In Figure 12, the slanted line from the unloaded
pressurized volume remaining in the system. An capacity point to the surge point, is called the load or
attached discharge check valve (see Figure 13) will surge line. The flow and pressure, in a well tuned
prevent the pressurized air volume in the system control system, increases very close to this line as
from back-flowing through the machine. Reverse the inlet valve opens. The bypass valve is open at
rotation cannot be tolerated because it will damage the time of loading and all flow vents throught the
the Centac compressor bearings. The check valve bypass, keeping the machine from surging on
also serves to prevent a large volume reverse flow in loadup, i.e., keeping the flow to the right of the
the event of surge. Surge Line.
Starting presents a problem. If the compressor is With the inlet and bypass controls properly adjusted,
started with the inlet valve at the minimum throttle the compressor will provide 0%-to-100% of system
position, there will be a heavy starting load on the demand at designed pressure, and allow for
compressor driver. Flow would increase, along with compressor start, stop, load and unload.
the increasing speed of the motor, but the
acceleration under load forces are likely to cause The Effect of Changes in Air Inlet
damage to the compressor or the driver Conditions when the Electronic Control
components. The high starting amperage in this
type of start-up affects the electrical distribution System is used
system. The electronic control system uses a motor
amperage signal (MinLoad) to establish the inlet
A control function that causes the inlet valve to open valve minimum closure (minimum throttle) point.
to no more than about 5% to 20% on start, is
desired, to limit starting load. If flow is limited on This signal reflects the driver horsepower where
start, the starting electrical and acceleration loads (Amps X Volts X Phase factor X Power factor =
are limited. The bypass valve must be fully open on Watts) and (746 watts = 1 Horsepower). If volts,
start up. phase factor and power factor are constant, the
amperage is proportional to horsepower. In reality,
The compressor needs to have a small flow on start. the power factor is variable with motor load and this
This flow keeps the compressor from becoming a upsets the direct amperage to horsepower
vacuum pump and prevents startup-throttle surging. proportionally. Amps are nearly proportional to
Running the compressor in a vacuum has two horsepower and for normal control purposes this
detrimental effects: nearly proportional is adequate. Since horsepower
is directly proportional to flow at constant pressure,
• with no flow path, the impeller will impart energy
the throttle surge point can be related to motor
to the stagnant air in the compressor, heat will be
amperage.
generated and, over time, this could cause
damage.
The inlet valve responds to a signal based on
• the bearings are designed for a minimum load, system pressure, as does the electro-pneumatic
and running under vacuum conditions puts stress scheme. However, an amperage level, at which
on the bearings. surge will occur, is entered as a set point. If load on
the driver nears this surge set point, the inlet valve
The function of the Inlet Guide Vane (IGV) The IGV's primary use is in the degree of accuracy
An inlet guide vane arrangement is used instead of and stability that can be obtained when the
an inlet (butterfly) throttle valve in some applications. compressor is operated under conditions where
These applications are, normally, those processes control of the pounds-per-hour (lbs/hour) mass flow
that use air as a raw material for an end product or is a requirement. IGVs offer a larger and more
where precise control of the flow is required. An air- precisely controllable throttle range than the
to-nitrogen gas process or a pharmaceutical standard inlet valve.
fermentation process are examples..
Design
in e
Point
mit L
Li
rg e
Su
100%
-10o
0o
+20o
+60o +40o
Capacity
2 stage calculation:
Compressor ratio =
7.9653, Stage factor = √7.9653 = 2.8223
1st stage in X stage factor =
1st stage out, 14.4 X 2.8223 = 40.64 psia
2nd stage in X stage factor =
2nd stage out, 40.64 X 2.8223 = 114.7 psia
3 stage calculation:
Compressor ratio =
7.9653, Stage factor = 3√7.9653 = 1.9971
4 stage calculation:
Compressor ratio =
7.9653, Stage factor is 4√7.9653 = 1.6799.
Typical (Actual) Centac Performance Curve actual machine, normally indicates that the
Figure 15 is a performance curve for a typical compressor will have a corresponding larger throttle
2CV31M3 compressor. The slope of an actual range. A large throttle range is normally desirable.
Centac curve is steeper than the model curve
shapes used previously. This is a typical
general shape for actual compressors.
Any one or all of these parameters may be different An IGV has little practical use for users who
in a specific design. normally operate at near design flow . An IGV
provides power consumption advantages, as well as
The difference in discharge psia, between the surge precise flow control capabilities, where continued
pressure and the design point pressure, is called the operation near the throttle surge point is anticipated.
rise to surge pressure. A high rise to surge, in an
Diffuser
Impeller
Inlet Valve
Inlet Drive
Valve Shaft
Actuator
SYSTEM
Bypass
Valve Pressure
Actuator Sensor
Controller
1 What & how is 2/3rds of the pressure rise across a stage in a centrifugal air
compressor developed?
a) The diffuser by centrifugal force
b) The impeller by centrifugal force
c) The diffuser by dropping the velocity of the air
d) The impeller by dropping the velocity of the air
2 What is a centrifugal air compressor?
a) A dynamic compressor providing varying pressure at varying volumes.
b) Providing constant pressure a dynamic compressor at varying volumes.
c) A positive displacement compressor providing varying pressure at varying volumes.
d) A positive displacement compressor providing varying pressure at varying volumes.
3 What & how is 1/3 of the pressure rise across a stage in centrifugal air
Compressor developed?
a) The diffuser by centrifugal force.
b) The impeller by centrifugal force.
c) The diffuser by dropping the air’s velocity.
d) The impeller by dropping the air’s velocity.
4 What does the Actual Head Plot account for?
a) Energy losses in a real compressor.
b) Changes in the inlet air pressure.
c) Change in the inlet air temperature.
5 What is “ SURGE” condition?
a) A momentary reverse of flow.
b) Loose of power to the driver motor.
c) Air velocity reaches the speed of sound.
d) Air temperature reaches super heated levels
6 What is Choke?
7 What is Stonewall?
Air filter
Butterfly valve
Positioner
Diaphragm
Piston
Restriction
Beam
Force Coil
Feedback
I/A Spring
Cam Coupling
Feedback
Lever
Shaft
Span (range)
Adjustment
Positioner body
Locking wheel
Set screw
Cam
closed
20mA
Figure 4 closed
4mA Coupling
Indicator
Washer and “O” ring Gap
Figures 4 and 4A
show the position open Figure 5 Gap = Cam and body not touching. Malfunction
will occur if cam
of the lever arm 20mA and body touch.
roller for correct
cam positioning.
No dead band is
required.
Figure 4A
The anchoring position of the internal feed-back None (0) None (0) Signal wire defect.
spring is set when the assembly is tested. This is Wire not connected
done under ideal conditions with specific air supply Greater than When amps Coil connections or coil
pressures, etc. Conditions in the field at customer 4 volts = 20 mA opened.
sites may be different than the set up test conditions. 220 ohm shunt resistor
The spring may need to be re-adjusted. open
If the valve overshoots or moves too slowly during None (0) Some amp Coil or shunt resistor
operation, the spring can be moved in the ‘a’ or ‘e’ reading shorted
direction as required. If a new (replacement)
positioner is being installed on an existing
Positioner Specifications:
• Input signal [direct current from microcontroller]
4 to 20 mA or 0 to 20 mA
• Split range capability [Not used]
4 to 12 mA and 12 to 20 mA
• Input resistance Max.
190 ohms
• Turning angle of feed-back shaft max.
90 degrees
• Relationship between turning angle and signal
Linear
• Supply air pressure
60 PSIG ( 414 kPa) minimum
65 PSIG ( 448 kPa) maximum
• Supply air quality [Instrument air quality]
Clean, dry and oil free
• Ambient temperature
-13 to 185° F (-25 to 85° C)
• Construction materials:
Case Anodized aluminum
Cover Poly carbonate
Internal parts Stainless steel
Springs Aluminum an
Stainless steel
Diaphragms and seals Nitrile rubber.
• Positioner air signal output
0 to 65 PSIG (414 kPa) maximu
Proportional to 4 – 20 mA input signal
between zero and span setting
! Note
The positioner itself is capable of accepting a
maximum of 115 PSIG (793 kPa) instrument air
pressure. The actuator can withstand a maximum of
65 PSIG (448 kPa). The actuator is the limiting
device in the air supply pressure specification for the
entire Standard Valve Assembly.
! Caution
Do not exceed 65 Psig (448 kPa) Instrument air
supply to the Positioner – Actuator assembly, Inlet
and Bypass Valve Assembly
Figure 10
Adjustment procedure for the valve with its attached The valve discharge has a larger diameter than the
actuator is contained in Adjustment of the assembly inlet and the valve is flow direction sensitive. Flow is
section. against the segment as shown in Figure 12.
Figure 14
Adjusting Screw
Lock Nut
Bonnet
Spring Guide
Range Spring
Relief Seat
Vent
Diaphragm Assembly
Body
Inlet
Outlet
Pinlet Valve
Dripwell Housing
Pinlet Spring
Pelcock
Calibrating the Inlet & Bypass Valve Decrease source to 4 mA and check zero
adjustment position of the valve.
Assembly
Zero Adjustment Repeat zero and span procedure until valves are
With 4 mA supplied to the positioner. fully open and closed at their respective mA values.
CLOSED
OPEN
Air in Transducer
(I/P)
Air in
BELLOFRAM
positioner
Butterfly
valve
Actuator
There are two spring seats. The first spring seat Regardless of which compressor control valve is
should be screwed on approximately 3 turns, the being stroked, the first step in the stroke adjustment
second is screwed on 2 turns. See Figure 4. procedure is to properly stroke the I/P.
After the spring seats are installed, attach the Valve Stroke Specifications
feedback spring hook to the positioner clevis. The
next step is to screw the zero adjustment screw MP3 output 4 mA 20 mA
through both seats. The chain is attached to the I/P input signal
valve stem collar as illustrated in Figure 5. I/P output signal 3 PSIG 15 PSIG
Positioner input
To achieve proper operation, the positioner output
from the feedback spring side of the positioner Inlet valve position Just full CLOSED Just full OPEN
(Output chamber 1) must be attached to the Bypass valve position Just full OPEN Just full CLOSED
actuator in such a way that, when output pressure
4-20 mA
from MP3
BRAY positioner
Feedback spring
Pointer Diaphragm
Actuator Signal from I/P
The cam has three lobes. Each lobe is designed to In the case of the bypass valve, the power
serve a specific signal pressure and linear range. connection from the positioner is made to the right
One side of the cam is used for a direct action valve inlet connection on the actuator.
and the other for a reverse action valve. The inlet
valve is direct acting, since it opens as the signal Zero and Span Adjustment
rises. The bypass is a reverse acting valve, since it The zero and span adjustments are made in a
closes as the signal rises. The cam is marked D for manner similar to the BELLOFRAM. The coils of the
direct use and R for reverse use. The lobes are feedback spring are tensioned to achieve zero and
also lettered with their linearity and signal pressures. the number of active coils is adjusted to achieve the
The lobe that is used for both inlet and bypass is the range. An Allen wrench is provided to make the
one marked 0 - 90°, 3 - 15 psi. The inlet valve uses zero and span adjustments. It is stored on clips
the side of the cam marked D and the bypass uses within the covered area.
the side marked R. Figure 8 illustrates how the cam
is configured for inlet or bypass valve use. The zero adjustment nut is enclosed by the spring.
The Allen wrench is positioned between the spring
Inlet valve configuration Figure 8. Positioning coils and inserted into a hole provided in the nut to
of cam for Inlet or
Bypass valve turn the zero adjustment ring.
Valve rotation configuration
Open The range adjustment nut clamps to the spring with
an Allen screw located in the handle of the range
adjustment nut. The tab is made of plastic and can
easily be broken off if excessive tightening force is
applied to the screw. Do not attempt to take an
extra tightening turn on this screw because the tab
will crack or break away. Figure 9 illustrates the
major components used in setting the zero and
span of the BRAY positioner.
3-15 psi, 0-90°
Allen wrench
Cam shown in inlet valve closed position Allen set screw
Pointer Pointer hold down screw
Bypass valve cam configuration Range
adjusting
Valve rotation ring
Close
3-15 psi, 0-90°
5. Replace the Allen wrench in its holder and • the spool valve is inserted long end first.
reinstall the see-through cover. The pointer
should be aligned to the “0” mark when the inlet Use care not to drop the spring when the cap is
valve is closed and to the “90” mark on the removed.
cover, when the inlet valve is open.
! Caution
A constant rush of air, in excess of normal
exhaust venting, from under the see-through
cover indicates a diaphragm rupture. Overhaul or
replacement is required in the event of diaphragm
damage
Cap (2)
Air exhaust*
Actuator body
Shaft
TOP VIEW
Vane seal
Vane
Air in to move CW *
SIDE VIEW
Vane
Vane seal
Valve drive coupling end
16 The Bray Positioner, adjust Bypass Valve span: 20mA, just open.
True False
17 The Bray Positioner, adjust Bypass Valve zero: 4mA, just closed.
True False
Section 4
Overview.....................................................................1—4
Lubricant Conversion Procedures ..............................5—7
Material Safety Data Sheets.......................................8—13
Short Test ...................................................................14
In this section, you will learn 6. Change position of the transfer valve at 15
• Procedures to flush piping and the casing minute intervals on systems having dual oil
filters and/or coolers.
• Standard oil and filter data
• Physical and Chemical requirements for 7. Shut off the prelube pump.
Techtrol Gold III Coolant
8. Drain the oil filter and inspect the element(s).
Continue with one of the following:
a) If foreign material is found in the filter
housing or element, replace the oil filter and
repeat step 4 through 8 until filter housing and
! Note element are clean upon inspection.
b) If no foreign material is found, go to step 9.
The initial fill of lubricant for the Centac
compressor should be installed under the
9. Replace the oil filter element(s) and inspect
supervision of an authorized Ingersoll-Rand
the housing for cleanliness.
Technical representative.
! Note
The initial lubricant supply required for the
compressor installation is not normally supplied
with the compressor.
! Note
Lubrication specifications are constantly being
reviewed. Verify that correct lubricant is used by
consulting appropriate serial number manual.
Ingersoll-Rand does not endorse any other trade
name product or any individual oil company.
Reservoir Capacities
Sump Capacity
Model Number
(Gallons) (Liters)
2AC11 131 496
Actual capacities will vary with specific sumps. The
above listed values are for standard Centac
models. Review of the Specification section of the
compressor Operation Manual is recommended for
exact capacity of a specific unit. The above values
do not apply to API style sumps.
1) Operate the unit to bring the complete system 1) Operate the unit to bring the complete system
up to operating temperature. up to operating temperature.
2) Shut the unit down, and lockout/tag out power. 2) Shut the unit down, and lockout/tag out power.
Close the isolation valve and vent pressure
3) Close the isolation valve and vent pressure from
from the unit.
the unit.
3) Drain the receiver-separator tank.
4) Drain the receiver-separator tank.
4) If possible, drain the oil cooler.
5) If possible, drain the oil cooler and fluid lines.
5) Change the coolant filter element.
6) Change the coolant filter element.
6) Do a ½ (one half) machine flush.
7) Do a ½ (one half) machine flush. If the
7) Restart and run the unit for one hour. separator has a high differential pressure (> 8
8) At the end of one hour, change the fluid (repeat psi) change it also.
step 2-5), except this time fill the unit 8) Restart and run the unit for one hour.
completely with Ultra Coolant (normal fill level).
9) Start the unit and check coolant level.
If the separator has a high differential pressure
(> 8 psi) change it as well. 10) Place the unit in normal service.
9) Start the unit and check coolant level.
Fluid analysis or use of the field test kit is suggested
10) Place the unit in normal service. every 3 months to verify the condition and remaining
life of the fluid.
Fluid analysis or use of the field test kit is suggested
every 3 months to verify the condition and remaining
life of the fluid. ! Note
This IR procedure omits flushing. Diester is
Unit that has been run with Diester Coolant and more compatible with Ultra Coolant than most other
has Sludge Deposits fluid types. It would be permissible to omit flushing if
a machine was effectively drained. If you wish to
1) Operate the unit to bring the complete system have a more uniform and conservative flushing
up to operating temperature. procedure, substitute the one for PAO – no varnish
2) Shut the unit down, and lockout/tag out power. here).
Close the isolation valve and vent pressure
from the unit.
Unit that has been run on Diester/Polyglycol
3) Drain the receiver-separator tank. Blends
4) If possible, drain the oil cooler.
5) Change the coolant filter element. 1) Operate the unit to bring the complete system
6) Refill the unit with Ultra Coolant. up to operating temperature.
7) Restart and run the unit for one week. During 2) Shut the unit down, and lockout/tag out power.
this time, monitor oil filters and change when Close the isolation valve and vent pressure from
necessary, as Ultra Coolant removes sludge the unit.
and varnish left by the previous fluid. 3) Drain the receiver-separator tank.
8) At the end of one week, change the fluid again 4) If possible, drain the oil cooler and fluid lines.
(repeat step 2-5), except this time fill the unit 5) Change the coolant filter element.
completely with Ultra Coolant (normal fill level).
If the separator has a high differential pressure 6) Do a ½ (one half) machine flush. If the
(> 8 psi) change it as well. separator has a high differential pressure (> 8
psi) change it also.
9) Start the unit and check coolant level.
7) Restart and run the unit for one hour.
10) Place the unit in normal service.
8) Start the unit and check coolant level.
Fluid analysis or use of the field test kit is suggested 9) Place the unit in normal service.
every 3 months to verify the condition and remaining
life of the fluid.
! Note
This IR procedure omits flushing. Diester is
more compatible with Ultra Coolant than most other
fluid types. It would be permissible to omit flushing
if a machine was effectively drained. If you wish to
have a more uniform and conservative flushing
procedure, substitute the one for PAO – no varnish
here).
! Note
Any silicone-based fluids require a special
flushing procedure. Please consult Ingersoll-Rand
for guidance.
Answer each question as fully as you can, or tick the best option.
When you finish, check your answers by reading through the section again.
1 What must be done if the wire seals on the sump access cover are not intact?
3 What can happen if the lubricant used does not comply with IR
specifications?
Receiving
In this section, you will learn Centac compressors are shipped in first class
• What to inspect when the compressor arrives condition. They have been inspected prior to leaving
• What to do if the machine is not started for the factory. Loading of the compressor has been
more than 120 days after arrival supervised by Ingersoll-Rand personnel to ensure
• How to lift the Centac compressor that the unit has not been damaged during loading
and that all accessory equipment has been properly
documented.
Figure 2
Centac compressor 1CV lifting fixtures
Figure 1
Lifting Diagram for Standard Unit
Storage
The compressor, as it is shipped from the factory
Installation of a Centac compressor can best be (flanges blanked and desiccant bags placed at inlet
done by the use of an overhead crane. Lifting points and discharge), can be stored on a level surface in a
have been provided in the baseplate for the purpose controlled environment for up to 180 days after the
of lifting the complete unit. To facilitate lifting and ship date tagged on the compressor unit without
avoid possible damage, spreader bars are requiring long-term storage preparation. The unit
recommended. Figure 1 illustrates the lift points for a must be started within the first 180 days following
standard unit. shipment from Ingersoll-Rand to assure the full 12-
month operational warranty after start-up. Store all
An overhead rail with a chain hoist will also simplify loose/spare parts in a controlled environment for
the removal of the largest component parts when adequate protection prior to usage.
maintenance is required. If the motor is supplied with sleeve bearings, fill the
motor bearing reservoir to the level recommended
by the manufacturer. Use a good grade of rust
! inhibiting oil. The shaft should be rotated a minimum
Warning of 10 revolutions every month to keep the bearings
Do not lift the unit by the lifting eyes on the lubricated. At the end of the storage time, the motor
compressor or driver. These eyes are for lifting the should be "meggered" to ground before connecting
individual component parts only. Damage to to the power line. Specific motor start-up instructions
equipment and injury to personnel could result from provided by the motor supplier must be followed.
misuse of the lifting eyes.
If the unit is to be stored for periods longer than 180
days, or in an uncontrolled environment, the unit will
Short Test
Answer each question as fully as you can, or tick the best option.
When you finish, check your answers by reading through the section again.
1 Why is it important to know the ambient conditions that the machine will be
exposed to during storage?
2 What are some of the components that could be damaged during shipment?
Noise
In areas where noise could be a problem, it is
Inlet important to treat hard reflective surfaces in the
connection area. Avoid installing the unit in an area with low
hard ceilings and walls.
Foundation
Water connections The compressor foundation does not need to be
Condensate traps massive but should be sufficient to provide support
for the unit. Since there are no out-of-balance
Plant Layout forces (such as reciprocating or shock loads) all
The location of a packaged centrifugal compressor loads on the foundation may be considered as static
within a plant facility is very important. The loads. If the unit is to be located in an area with
compressor should be located in an area that is other machinery, it is essential that vibrations are not
accessible to operators and maintenance personnel. transmitted to the compressor. Isolation pads are
recommended in these instances.
Machinery should be installed where it is easily
accessible for observation and maintenance. For the Centac compressor package, a simple
Operation and maintenance personnel will generally continuous concrete pad or steel support structure is
give better attention to a compressor located in a recommended for each compressor. Precautions
well planned, accessible area. Compressors should be taken to ensure a reasonably uniform
installed in elevated locations or in pits should have base around the pad. Uneven settling or thermal
stairways, catwalks, etc. for easy access to the expansion could cause machinery misalignment.
machinery.
Basic Centac Reference Manual
Ingersoll-Rand (Asia Pacific) Service Team
Issue: 01/Australia, July, 2003 Page 6
Planning and Installation Section 5
Installation Planning
Appropriate bolting must be used to keep the
compressor in place. Refer to the General The unit may be leveled using a machinist level or
Arrangement drawing for location and size of anchor transit level. When a machinist level is used, start at
bolt holes. one end of the unit and work side to side toward the
opposite end, placing the level on the machined
baseplate compressor pads. The compressor should
! Note
be level from 0 to 0.1 inch/foot (0 to 8 mm/M).
The design of the foundation is the responsibility After the unit is level with snug (not tightened)
of the customer. These comments are offered as an anchor bolts, the coupling should be aligned. Some
aid to assure a successful installation, but Ingersoll- baseplate distortion may be noted but this is
Rand Company cannot assume the responsibility unimportant so long as the machine pads remain
for the design. We recommend that the customer level. Precise driver alignment is not required until
consult a specialist skilled in the design of machin- the time of start-up, but should be within 1/16 inch
ery foundations. (1.5 mm). Follow the procedures found in the
Operation Manual once the compressor arrives on
site. The General Arrangement drawing lists the
values for the coupling alignment. Record the values
Leveling obtained, but do not dowel the driver or install the
Driver, compressor, and base levels are important coupling spacer.
for the following reasons:
After the coupling has been brought into rough
• If the machine is not level longitudinally, the alignment and the alignment values have
starting and stopping weight of the driver rotor been recorded, the Centac compressor is ready for
will bear on the thrust bearings (uphill or grouting.
downhill), resulting in possible premature wear.
• The same force will burden the compressor Grouting
bullgear thrust bearings and put stress on the Grouting forms are prepared and grout is poured
coupling. after level has been verified. When the grout has set
• If the level is off, the oil sump level, demister up, the wedges or shims are removed. The void
function and the coolers high point venting could space left in the wedge or shim area is then back-
be affected. filled with grout. If the wedges or shims are not
removed, corrosion will upset the level at a future
• Motor bearing lubrication and lubrication drain-off time. A nut used on the underside for leveling of the
could be affected resulting in possible premature base is not recommended because it too will corrode
failures. over time and upset the level.
• Proper drainage of condensate and general pipe
fit up could be affected by an out of-level Grouting serves two significant purposes. The first
condition. purpose is to provide full area support for the
machine's weight-bearing base structures. The
Before level readings can be taken, the compressor second purpose is to provide the means of support
must be resting on the foundation pad in its final when a machine needs to be levelled. There are
position with the anchor bolts (or nuts) snug. If it is other non-structural purposes for grouting which
known or suspected that the pad is not level, shims have to do with housekeeping.
or wedges can be installed at
the anchor bolt positions Anchor Bolt Figure 1.3.
when the unit is set in place. Wedge and shim
Level condition is determined Baseplate placement
by using a transit level,
machinist level, or other Leveling wedges Leveling shims
higher-technology means.
Short Test
Answer each question as fully as you can, or tick the best option.
When you finish, check your answers by reading through the section again.
The importance of always operating the compressor For best performance the inlet air piping should
with clean air inlet piping must be stressed. No conform to the following recommendations:
compressor will accept the ingestion of foreign
material into the operating components without • The inlet piping, from the inlet filter to the
possible damage or loss of performance. compressor, must be clean and made from a
non-rusting material such as stainless steel,
Inlet Air Filter aluminum, or PVC, and suitably flanged so that it
An inlet air filter should be mounted by the customer may be inspected in sections.
at a suitable location. At minimum, it should be a
• Inlet piping should be short and direct, with the
high efficiency two-stage unit designed to remove
combined filter and piping pressure drop less
99.97% of all particles larger than 2 microns and
than 0.3 psi (2.1 kPa[a]).
90% of all particles larger than 0.4 microns. For
adverse environmental conditions, a more efficient • Always use long radius elbows.
inlet air filter is recommended. • Transitions in pipe diameters should be gradual.
• Any horizontal run of pipe should be installed so
The inlet filter is normally oversized to increase the that condensation in the piping will run away from
time between element changes and to reduce the the compressor.
velocity through the filter to give a lower noise level.
• Drain valves should be installed in the inlet piping
at low points to allow the removal of
Routine inspection of the filter is recommended and
condensation.
the addition of instrumentation to indicate pressure
drop across the filter elements is also suggested.
When this drop increases substantially, the elements Inlet Filter
should be cleaned or replaced..
Bypass Air Piping The bypass piping should be suitably flanged so that
Atmospheric bypass piping vents the compressed a minimum amount of pipe needs to be removed
air when the compressor is running unloaded or at during major maintenance. This will reduce
partial load. Bypass piping should be well supported maintenance time.
to minimize loading on the compressor flange. Care
should be taken in the piping design so that all The end of the pipe should be turned down or have
alignments can be made in the piping. a short run of pipe to prevent rain and snow from
entering the bypass piping. Expanded metal should
A bypass silencer should be installed in the be installed on the end of the pipe to prevent large
atmospheric bypass line to reduce noise. A suitable objects and animals from entering the pipe when the
silencer is offered as an option with the compressor compressor is stopped. To remove condensation
package and is customer mounted. The silencer has from the piping, install a drain in the lowest part.
acoustic absorption material at a controlled density.
The silencer is usually installed close to the Expansion Joints
compressor and the vent piped outside. Alternately, With proper piping layout and installation, expansion
the silencer may be installed outside the building. joints may not be required on all compressors.
Consult the certified drawings for complete details of However, expansion joints are required on:
the silencer.
• All hot air discharge compressors (no internal
For sound attenuation in piping, a straight horizontal aftercooler)
run of pipe from the compressor flange, at least 8
• All steam turbine driven
pipe diameters long, is suggested before entering a
long radius elbow (see Figure 1.5). The silencer • On the inlet and discharge
should be kept as close to the compressor as
possible and the total length of pipe kept short. In Expansion joint installers must consult the
noise critical areas, the discharge piping from the manufacturer’s instructions to ensure correct
silencer may be lagged to further reduce sound. installation.
Discharge deflector !
Warning
Roof Line Improperly applied and/or installed expansion joints
can result in severe injury, death, or property
Hanger (typ) damage due to over stressing and fatiguing of the
bellows material.
Silencer
! Note
Alt. Side wall
Long radius
While Ingersoll-Rand may recommend or even
discharge Drain
elbow Minimum supply an expansion joint, proper installation is the
8 pipe customer’s responsibility.
diameters
Figure 1.5
Bypass valve
Model Bypass Pipe
Discharge Air Piping
For the best performance, a straight run of pipe
Discharge piping from the silencer should be sized which is at least 3 pipe diameters long should be
so that the maximum backpressure on the silencer is interposed between the discharge check valve and a
5 psi or 35 kPa (a). Standard silencers are equipped long radius elbow to allow for smooth operation of
with ANSI 150# standard flanges. Bypass piping to the check valve. The piping should be the full size of
the silencer should be of the same diameter or the compressor discharge connection. Where pipe
larger than the bypass valve. Piping from the bypass diameter conversion is necessary, the transition
silencer should be of the same size or larger than should be gradual. The use of long radius elbows is
the silencer discharge. Refer to the certified drawing recommended and piping may be sized by normal
for complete details of silencer. methods.
Block valve
Figure 1.6
Model Discharge Pipe
Safety valve
Pipe hanger
Compressor Connections
Discharge Air Piping for Multi-Compressor Centac compressor connections and sizes are
located on the certified customer prints. Refer to the
Installation General Arrangement Drawing and the Process and
Instrumentation Diagram for further detail.
Parallel Operation with Positive Displacement
Compressors Receivers
The steep performance curve of the Centac Receivers store compressed air for systems in which
compressor allows for operation in parallel with air demand fluctuates over a short period of time. A
piston or rotary screw compressors (see Figure 1.7). properly sized receiver will decrease the number of
However, piping layout design should isolate the times the compressor loads and unloads. This will
Centac compressor from the pulsations in the increase the compressor's efficiency and decrease
discharge produced by these compressors. Piping wear on valve components. Receivers can be
the Centac compressor into the discharge header installed as "Wet" (before the dryer) or "Dry" (after
downstream of the pulsation bottle or receiver the dryer) receivers or in both locations. Contact
effectively eliminates pulsation problems. your local Ingersoll-Rand representative for
assistance in properly sizing and locating this
Fast valve operation allows the lagging compressors equipment.
to supply huge quantities of air at system pressure.
Proper consideration to the entry of this added A receiver may also be used to isolate centrifugal
capacity into the system will eliminate control or compressors (or other equipment) from pulsations
surging problems commonly associated with this created by positive displacement air compressors. A
type of installation. pulsation bottle may be needed to eliminate
pulsations more effectively.
Discharge piping from the compressor should enter
the system header by way of long radius elbows or
at an angle in the direction of flow. By staggering
entry into the header the added capacity will have no
detrimental effect on the other units already on line.
Recips or Recips or
Centac Centac
Screws Screws
Receiver
Flow
Long radius elbow System Header
Angle with flow
Flow
Centac Centac
Centac
Centac
Figure 1.7
Centrifugal and Positive
Seal Air
Power Air
Short Test
Answer each question as fully as you can, or tick the best option.
When you finish, check your answers by reading through the section again.
= Water Line
Valve
To Floor Drain
Figure 1.10
Standard Condensate Trap and Drain Arrangement
1 What are the minimum and maximum water pressures that piping must allow
for?
! Warning
Do not disconnect secondary wiring during
operation. Anytime secondary side of the current
transformer is disconnected from its load, a jumper
must be placed across secondary terminals to
prevent injury or death of personnel and/or damage
to equipment.
Current Transformer
This device may be required to provide a 0-5
ampere signal to one or more devices located in the
control panel. When supplied by Ingersoll-Rand, the
current transformer is often shipped loose for
installation by the customer. Refer to the unit's
electrical drawings, motor nameplate data, motor
manufacturers data sheet and starter manufacturers
data sheet to properly size the current transformer.
! Warning
An appropriate grounding strap should be
attached to the motor and a suitable ground.
Weight
Length Width Height without
motor
148
89 inches 74 inches 17,000 lb
inches
2261 mm 1880 mm 7,711 kg
3759 mm
Compressor Connections
! Note ! Note:
For all Rim Measurements
Actual measurement is 1/2 TIR (Total Indicator 1) The DBSE (Distance Between Shaft Ends)
Reading), therefore value of measurement shown on must be established when the motor shaft is
indicator reading circle should be twice the distance of magnetic centre, otherwise it is possible
indicated on plot. the motor bearings can be damaged due to
incorrect end-float.
Offset value is plus (+) if the projected centerline of 2) If a spacer coupling is used fitted with
machine that the indicator is attached to, is above phenolic disks - these must be installed to
coupling mark of the machine that the indicator is ensure correct end float.
riding on. 3) Do not carry out motor alignment if a soft
foot is present.
Refer to coupling alignment chart on TIR figures for A soft foot is movement of the motor foot
different frame sizes. when the hold down bolt is torqued down
Figure 19 Pictorial of Note 3 on Shaft Alignment Map 2C 0.030” 0.015” 0.037” 0.0185”
3C 0.050” 0.025” 0.066” 0.033”
4C 0.060” 0.030” 0.076” 0.038”
1ACII 0.010” 0.005” 0.010” 0.005”
2ACII 0.010” 0.005” 0.010” 0.005”
1CII 0.010” 0.005” 0.010” 0.005”
2CC 0.010” 0.005” 0.010” 0.005”
2CII 0.010” 0.005” 0.010” 0.005”
3CII 0.010” 0.005” 0.010” 0.005”
5CII 0.018” 0.009” 0.018” 0.009”
6CM 0.020” 0.010” 0.020” 0.010”
5CCH 0.010” 0.005” 0.010” 0.005”
Figure 20 Pictorial of Note 4 on Shaft Alignment Map 6CCH 0.010” 0.005” 0.010” 0.005”
Tolerances should not exceed +/- 0.002” T.I.R. All
values listed are for cold alignments
Reverse Indicator Method of Shaft movement exceed 2 mils (0.05mm), piping strain
is considered excessive. The reason for the strain
Alignment must be investigated and the condition corrected
1) The reverse indicator method of shaft alignment before proceeding with alignment.
should be used when distance between the shaft 6) When spanning the coupling gap with an indicator
ends is greater than one-half the coupling rig or bracket, zero sag is impractical to achieve;
diameter. therefore, the actual amount of sag should be
determined and recorded on the alignment map.
! The bracket should be sturdily constructed to
Note minimise shifting and sag during use.
For alignment purposes, the effective distance
between shaft ends can be increased by spanning
the shaft end to obtain a dial indicator location !
inboard of actual shaft ends. The key factor is to Note
spread two indicators as far apart as practical with For purposes of this explanation, the fixed machine
negligible bracket sag. (As spread increases, so (compressor) is called Shaft “A”. The shaft of
does the possibility for bracket sag.) machine to be aligned to shat “A” will be called shaft
“B” (driver). Therefore, shaft “B” belongs to the
This method of shaft alignment eliminates the machine that will be moved.
need for taking face readings.
2) The reverse indicator method involves taking 7) Attach the indicator bracket to shaft “A”.
reading from one shaft to the rim surface on the
job of the adjoining shaft and vice versa as shown 8) Attach the dial indicator to the bracket so that
in Figure 21. the button will rest on the outer rim of coupling
hub “B”. The indicator button should contact in
about 0.25 inch (6mm) from the hub face.
First Set of Readings
Read here
9) Position dial indicator at top dead center, in line
with 0o marking on coupling “B” and zero the
indicator.
10) Rotate (only if POP is running) both shafts
together and record dial readings on alignment
Shaft “A” Shaft “B” map at 90o, 180o and 270o positions. On return
to the top position, the indicator should return to
Second Set of Readings
zero. Repeat this step several times to be
certain no mistake has been made or
something has moved.
Read here 11) The accuracy of the readings may be verified
by algebraically adding the side readings and
comparing this sum to bottom reading. The
readings should be equal to or within 1mil
Shaft “A” Shaft “B”
(0.03mm).
Figure 21 Reverse Indicator Readings 12) Remove the bracket from shaft “A” and install
on shaft “B”. Using the same procedure obtain
3) Lubricate bearings before rotating shaft. indicator readings from shaft “B” to the rim of
coupling hub “A”.
4) Mark both the coupling hubs at four locations 90o
apart so that their position can easily be seen at 13) Using the two equations shown on the
all times during the alignment work. suggested shaft alignment map, calculate the
vertical offset (Vo) and the horizontal or plan
5) All piping strain must be removed from the
view offset (Ho). Plot these results in the proper
equipment. For initial alignment work during
installation, all piping should be left unconnected view and in the axial location where indicator
from machinery. After cold alignment has been readings were taken. Note 3 or 4 on the
alignment map can assist in determining the
secured, arrange dial indicators between shaft
shaft location above or below other shaft.
ends, to detect any movement of the equipment.
Connect one flange at a time and observe
indicator readings continuously. Should
!
Note
On units operating without an aftercooler, it is a
standard practice to increase the vertical center line
offsets stated above. For distance between hubs,
see the General Arrangement Drawing.
! Note
Before making alignment changes based on
hot alignment data, evaluate the setup to be sure
data is valid and logical.
Installation checks
The entire compressor installation must be checked
and pre-start adjustments must be made prior to the
initial start up. It is recommended that this be done
under the direction of an service representative.
Centac II
Frame 1/1A 0.10 0 0.05
Frame 2/2A CII 0.15 0 0.05
Frame CV2/E 0.15 0 0.05
Frame 3ACII 0.15 0 0.05
Frame 5CII 0.20 0 0.05
Centac I
Frame 0 0.10 0 0.05
Frame 1 0.15 0 0.05
Frame 2 0.20 0 0.05
Frame 3 0.25 0 0.05
Frame 4 0.35 0 0.05
4 What do the solid dark lines on the Shaft Alignment Map mean?
7 Why must the motor shaft be at magnetic center when alignment is carried out?
! Note ! Note
Remove Bullgear Antirotation Pins on Model If alignment is off by a large amount, 15 - 20
C60 to C150. thousandth of an inch, then reverse indicator
alignment needs to be run again.
Compressor R3 R4
1) Position the driver to obtain correct spacing Shaft L3 Driver Shaft
between the shafts, as specified on the general L4
arrangement drawing. Sleeve bearing motor B3 B4=0 Indicator “B”
shafts must be on magnetic center during this
step. Mechanical center and magnetic center 1)
Position Indicator 'A' on top of compressor hub
should be the same. and zero the indicator. In this position, Indicator
2) Mount the brackets as shown in the figure 'A' is reading point "T3" so "T3=0".
below. Tighten driver mounting bolts. 2) Position Indicator 'B' at the bottom of driver hub.
3) Check for a soft foot by releasing one bolt at a and zero the indicator. In this position, Indicator
time and checking indicator movement. 'B' is reading point "B4" so "B4=0".
4) Retighten the bolt before checking the Indicator 'B' shows
next foot. Each foot should have no amount of shim 3) Rotate both shafts together 90
more than .002 inch movement. needed to correct a degrees clockwise (direction of
soft foot at Foot #1 compressor rotation).
(the motor foot closest Indicator 'A' is now at the "R3"
Bracket Arm
to the shafts. It is the position and Indicator 'B' is at the
near foot). "L4" position.
Alignment
Bracket Record the "R3" and "L4" readings.
Dial
Indicator 4) Rotate both shafts together another
Hub “B” 90 degrees clockwise
Indicator 'A' is reading point "B3"
and Indicator 'B' is reading point
Compressor
Shaft Driver Shaft "T4".
Record these readings.
5) Rotate both shafts together another
Coupling
Sleeve
Dial 90 degrees
Indicator Indicator 'A' is reading point "L3"
“A”
and Indicator 'B' is reading point
"R4".
Record these readings.
Indicator “A” is the dial indicator whose
plunger touches the compressor shaft. It
indicates the amount of shim needed to You should now have six indicator readings:
correct a soft foot at Foot #2 (which is the • three off the Indicator 'A' and
motor foot furthest from the shafts. It is the • three off of Indicator 'B".
far foot).
The readings that you should have recorded are (see
5) Release all driver mounting bolts. figure above):
6) Bring the shafts into approximate horizontal
alignment using the jacking bolts and reading Indicator Indicator
Indicator 'A' and Indicator 'B' side to side. “A” “B”
T3=0 B4 = 0 Indicators zeroed in vertical position
7) Keep in mind that both shafts must be rotated
R3 L4
together and actual offset is 1/2 TIR. B3 T4
8) Correct Indicator 'B' offset by adjusting Foot #1 L3 R4
jacking screws and correct Indicator 'A' offset
by adjusting Foot #2 jacking screws. Leave all
4 jacking screws touching the driver, but not The final three inputs that you will need are "D1", "D2",
tight. and "D3". All three of these measurements must be in
inches.
9) Tighten mounting bolts.
Alignment Setup
Indicator MOTOR
“A” T3=0
Compressor Motor
Shaft Shaft
B3=0 Indicator
“B”
Feet #1 Feet #2
Near Far
D1 (inches)
D2 (inches)
D3 (inches)
Data Required for Program Calculations Desired Readings - Thermal Growth Offsets
This alignment program requires you to input nine This section answers the question, "What should the
different readings and measurements for indicators read when the machine is aligned to
calculations: compensate for thermal growth?"
• D1 is the distance in inches between the two In this alignment program, the user selects the model
plungers of the indicators. of the compressor that he will be aligning. The
program automatically inputs eight (8) numbers for
• D2 is the distance in inches from the plunger of what the two dial indicators should read when they
dial 'A' (touching the compressor shaft) to the are swept simultaneously around the shafts.
Foot #1 (near foot) of the motor. D2 is always
less than D3. These eight readings are called desired state sweep
• D3 is the distance in inches from the plunger of readings at ambient conditions. Since alignment is
dial 'A' (touching the compressor shaft) to the not done when the unit is completely hot, the dial
Foot #2 (far foot) of the motor. indicators should not read zero when swept around
• T3 is the dial reading, in thousandths inch, at the the shafts when the unit is cold.
top of the compressor shaft. T3 is set to zero!!
• R3 is the dial reading, in thousandths inch, at the If the alignment could be done when the unit was as
right side (90 deg clockwise-direction of hot as it is when running, then the desired state
compressor rotation-from top) of the compressor sweep readings would all be zero. If all the
shaft. indicators read zero when swept, when the unit is
cold, the unit would be in perfect cold alignment, but
• B3 is the dial reading, in thousandths inch, at the would be misaligned after the unit became hot and
bottom of the compressor shaft. thermal growth occurred.
• L3 is the dial reading, in thousandths inch, at the
left side (270 deg clockwise-direction of
compressor rotation-from top) of the compressor
Repairing and Compacting Database
shaft.
Repair Database menu option
• T4 is the dial reading, in thousandths inch, at the This menu option repairs and compacts the
top of the driver shaft. language and report databases. Overtime the
• R4 is the dial reading, in thousandths inch, at the databases could become fragmented and this
right side of the driver shaft (180 deg opposite fragmentation decreases performance. So, from
reading R3). Take these readings at the same time to time you should click this menu option to
time. compact the databases, this will restore performance
• B4 is the dial reading, in thousandths inch, at the lost to fragmentation.
bottom of the driver shaft. B4 is set to zero!!
Also, if the database is left invalid by an incomplete
• L4 is the dial reading, in thousandths inch, at the
write operation the Repair Database menu option will
left side of the driver shaft (180 deg opposite
validate the system tables, indexes and repair the
reading L3).
invalid record, then compact the database. An
incomplete write operation can occur if the
Take these readings at the same time.
application quits unexpectedly because of power
failure or computer hardware problems.
Rotate
Always rotate both shafts together in the direction of
rotation when the machine is running.
Section 6
Pre-Start Checklist......................................................1—3
Initial Start Preparation ...............................................4—6
Natural Surge Testing.................................................7—8
Installation Checklist...................................................9
Short Test ...................................................................10
Start Up Registration Form.........................................11—16
Warranty and Limitation of Liability.............................17—19
Short Test ...................................................................20
Checklist Summary
! Note
All systems on the Centac compressor should
be checked prior to initial start-up. This check
should be completed under the direction of an
Ingersoll-Rand customer service representative.
!
Caution
The importance of starting and operating the
compressor with clean inlet piping cannot be over-
emphasized. Loss of performance or physical
damage could result from the ingestion of foreign
material.
1 Inspect the following for corrosion and cleanliness just prior to start-up:
a. Minimum size
b. Distance to first elbow (minimum of 3 pipe diameters)
c. Piping supports
d. Facilities for moisture removal on any horizontal run of pipe
e. Safety valve (located between block valve and compressor)
f. Block valve
5 Check the following on the bypass piping:
a. Minimum size
b. Distance to first elbow (minimum of 8 pipe diameters from bypass valve)
c. Piping supports
d. Location of silencer
e. Facilities for moisture removal on any horizontal run of pipe..
a. Material
b. Minimum size
c. Attached to control panel at bulkhead fitting "CA"
d. Attached to discharge air piping a minimum of 10 pipe diameters from check valve
7 Check the following on the instrument air piping:
a. Material
b. Minimum size
c. Attached to control panel at bulkhead fitting "IA"
d. Attached to dry, clean air source, 60-120 PSIG (414-827kPa) 10 SCFM (15 Nm 3 /hr) per stage
minimum
e. Absolute air filter 0.01 micron
f. Shut-off valve
8 Check the following on the water piping
a. Minimum size
b. Attached to the compressor
c. Attached to the oil cooler
d. Water pressure between 35 (minimum)-75 (maximum) PSIG (241-517 kPa)
e. Differential pressure between inlet and outlet flanges on air coolers is normally between 12 (minimum)-5
(maximum) PSIG (83-103 kPa)
f. Check for water leaks (leave condensate trap bypass valves open)
g. Throttle valves at outlets
h. Block valve on inlet
i. Casing vents open
9 Check piping on condensate traps (piped to open drain).
10 Check compressor lubricant, motor lubricant, and coupling grease for conformance to specifications.
11 Fill oil reservoir to “Normal” level.
12 Check anchor bolts and grouting.
13 Check unit level.
14 Check all control panel connections per applicable schematics.
15 Check proper grounding of electrical power supply.
16 Manually rotate compressor and driver shafts, checking for free, uncoupled rotation with oil pump running
and seal air “on”.
17 Check driver per manufacturer's instructions found in the driver instructions.
18 Check driver electrical connections.
19 Check to see that driver bearings are properly lubricated.
20 Check direction of rotation and magnetic center of main drive on motor driven units prior to coupling to
compressor.
21 Align driver to compressor
22 Install coupling spacer and Lubricate coupling per Manufacturer’s instructions.
23 Check rotation of prelube pump (three phase only).
24 Check clearances on thrust bearings. Disregard if the access covers are wire sealed
25 Check vibration monitor per control section (if applicable).
26 Check lubrication system for oil leaks.
27 Check operation and calibration of the inlet and bypass valves, as per the Operation Manual.
28 Calibrate all temperature and pressure switches
29 Functionally test control system.
30 Check operation of main driver trip device
31 Start and run compressor
32 Correct any oil, water or air leaks
! Note
H-3 0 - 15 55 100
The preparation for and the initial start-up of *Lubricant capacities for each size and
the Centac compressor should be done under coupling style. This is the total
supervision of an Ingersoll-Rand service supervisor. lubricant required for both coupling
halves
Cenlube GL Grease
! Warning Ingersoll-Rand provides synthetic grease for
Coupling lubrication is critical. The use of lubricated couplings. This grease is a non-
proper and sufficient lubrication is part of a hazardous anti-friction bearing and coupling grease
successful installation. Do not use oil in gear designed for all speeds of machine between - 40°F
couplings. and 500°F.
Grade NLGI #1
! Warning
Do not run the Centac compressor without Base oil Viscosity Min. 3000 SSU at 100ºF
lubricating the coupling. 160 SSU at 210°F
Dropping Point, Min. 190°F
Coat the hub and sleeve gear with grease. Slide the
sleeve over the hub gear. Insert the gasket. Bolt the Four Ball Wear, ASTM D-2266: .500mm Maximum
sleeves and tighten uniformly.
Base oil content 87% Minimum
The coupling must be lubricated before operation.
Hand packing of grease in each half of the coupling K36 Factor, ASTM D-4425 KSG: K36 = 8/24 = .33
is recommended. Remove two fittings 180° apart.
Rotate the coupling to place the bottom hole 45° off Required Rust and Oxidation
horizontal. Pump or pour lubricant into the top hole Inhibitors
until excess appears at the bottom hole. Sufficient E. P. Additives
lubricant has now been added. The most reliable test of a suitable lubricant is often
the result of user experience and satisfaction. If a
lubricant has been known to sludge, separate into
! Caution heavy components or dry out, consider using other
Do not attempt to fill the coupling without lubricants that meet the minimum specifications..
venting the interior. An air lock can result in
incomplete filling or in damage to the 'o’ ring seal.
Main Driver Preparation Inlet Valve / Inlet Guide Vane and Bypass
The preparation of the main driver shall include but Valve – Current To Pressure (I/P)
not be limited to:
Transducer Adjustment
Check the bolted joints for signs of looseness.
Check to make sure the bearings have been
1 Turn off power to the panel and disconnect the
properly lubricated and the bearing reservoirs filled. current to pressure (I/P) transducer wires.
Rotate the shaft by hand to insure there is freedom 2 Connect to the I/P a DC power supply with a 4mA
of movement. to 20mA output capability. Observe for correct
Check the control device connections to make sure polarity.
they agree with the wiring diagrams.
Alternatively, the microcontroller may be used to
Refer to the manufacturer’s instructions for detailed supply the 4mA and 20mA signals to the I/P
initial starting and stopping instructions. transducers. To do this the unit must be prepared
for a simulated run. A simulated run is
accomplished with the block valve closed and the
motor controller locked open. Also, the lube oil
Control System Adjustment pressure shutdown setpoint must be adjusted to
Centac compressor control systems may be ordered zero.
with a wide variety of monitoring, control, and
protection features. Many options are available to The microcontroller will send a 4mA signal to the
meet specific needs of customer. transducers when the control panel is energized.
The microcontroller will send a 20mA signal to the
Pre-start adjustment may vary considerably transducers after the start pushbutton is depressed
depending on features ordered. Therefore, see the and the start cycle times out. (Note: mode selector
control panel instructions and electrical prints for switch should be in the "modulate" position.)
necessary adjustments.
3 Apply 80 PSIG (551 kPa) instrument air to the I/P
supply connections.
4 Apply a 4mA signal to the transducers:
• Adjust zero screw on inlet valve I/P to obtain 7
PSIG output.
• Adjust zero screw on bypass valve I/P to
obtain 3 PSIG output.
5 Apply a 20mA signal to the transducers:
• Adjust the span screw on inlet valve I/P to
obtain 15 PSIG output.
• Adjust the span screw on bypass valve I/P to
obtain 10 PSIG output.
6 Repeat steps 4 and 5 until correct outputs are
obtained at signal inputs of 4mA and 20mA. NOTE:
Readjust low oil pressure shutdown setpoint.
!
Warning
Operation of the unit without proper lubrication
can result in overheating of the bearings, bearing
failures, pump seizures and equipment failure
exposing operating personnel to personal injury.
Pre
ss ure
-Flo
w
PSIA
Plo
t
Friction
All rotating parts encounter friction of some type.
Restrictions
PSIA
0 FLOW 100%
Surge
Surge is defined as a reversal of flow through a
centrifugal compressor due to a reduction in flow.
Typically when surge occurs it is noted by a
“WHOMP” sound in the compressor.
While a single surge event is not CYCLIC SURGE MODEL (LARGE VOLUME
necessarily detrimental to centrifugal air
compressor, repeated surging (called
Pumping) can be detrimental.
J P
This should be avoided for the safe
operation of a centrifugal air compressor
K Q
PSIA
- FLOW O + FLOW
Answer each question as fully as you can, or tick the best option.
When you finish, check your answers by reading through the section again.
1 Why is it important to start and operate the compress with clean inlet piping?
2 What is the normal differential pressure range between inlet and outlet flanges on
air coolers?
MAIN DRIVER ROTATION CHECKED AND VERIFIED CORRECT TO THE ROTATION ARROW ON THE
COMPRESSOR GEAR CASE: YES NO
(If no, explain why and obtain a Release of Liability from the Customer/Contractor)
OIL PRESSURE:
LOW OIL TEMPERATURE:
HIGH OIL TEMPERATURE:
1ST STAGE VIBRATION:
2ND STAGE VIBRATION:
3RD STAGE VIBRATION:
4TH STAGE VIBRATION:
5TH STAGE VIBRATION:
S1 DISCHARGE AIR TEMP.:
S2 DISCHARGE AIR TEMP.:
S3 DISCHARGE AIR TEMP.:
S4 DISCHARGE AIR TEMP.:
FINAL DISCHARGE AIR TEMP.:
LOW SEAL AIR SWITCH (shutdown only):
X. OTHER VALUES/FUNCTIONS
OIL HEATER THERMOSTAT TEMP. SETTING:
OIL HEATER CONTACTOR CONTROLLED BY THERMOSTAT: YES NO
OPERATING OIL TEMPERATURE:
MAIN OIL PUMP PRESSURE AT OPERATING OIL TEMPERATURE:
PRELUBE PUMP PRESSURE AT OPERATION OIL TEMPERATURE:
LOW SEAL AIR PRESSURE SWITCH SHUTS OFF PRELUBE PUMP: YES NO
(If no, a detailed description is required)
IF NO, WHY?
GENERAL COMMENTS:
Send:
ORIGINAL TO QUALITY ASSURANCE DEPARTMENT - MAYFIELD
COPY TO YOUR MACHINE FILE
COPY TO CUSTOMER
FORM# 1X15785 REV. C
Revised 19 August.2002.
!
Warning
Not to be used for breathing air application.
Ingersoll-Rand company air compressors are not
designed, intended or approved for breathing air
applications. Ingersoll-Rand does not approve
specialized equipment for breathing air applications
and assumes no responsibility or liability for
compressors used for breathing air service
Answer each question as fully as you can, or tick the best option.
When you finish, check your answers by reading through the section again.
1 Tag out all service to the unit. 10 Tighten up on the inactive thrust bearing
adjusting screw.
2 Ensure that there is no power to the control
panel.
! Caution
The impeller blade is very sharp. Use
caution when handling the impeller
Removal of the Bull gear From the Casing 7 Remove the shaft seal retainer and oil feed line.
This procedure is done after removal of the stage(s).
! Note
The wave spring arrangement to ensure
proper reinstallation.
Installation of the Bull Gear into the Casing 6 Lubricate bearing and bore.
Assembly of the Stage(s): 5 Align the seal air injection hole in the bearing with
the casing hole and install the plain bearing, use a
gasket if applicable, in the casing.
!
Note
In the following procedure, DO NOT use any oil on
the parts unless instructed to do so. Lubrication will
be provided when the prelube system is started.
Lock the bull gear against rotation.
11 Push the pinion forward until it just touches the 20 Install the vibration probe. Gently seat the
plain bearing shell. vibration probe against the pinion and then back
off.
12 Stone any suspected proud spots on the casing
or the thrust bearing on the bearing flange seating
areas.
13 Start the thrust bearing into the casing bore with
the oil drain holes pointed down.
• o-rings
• cooler into the cooler casing
• cooler casing guide pins into the
compressor casing
• cooler casing to the compressor casing
38 Tighten up the bolts until the lock washers just 42 Install the inlet and bypass valves, bypass pipe
close up. and all instrumentation.
!
Caution
DO NOT FORCE THE SCREW.
Forcing the adjustment screw can damage the
inactive button bearing. Back the bolt off 1/4 to
1/3 turn and tighten the lock nut. This action
provides for a 0.008” to 0.010” total axial float
clearance setting.
! Note
The bull gear locking bolt should be removed
prior to performing this procedure.
Front View
Lock Bolt
Lock Bolt
Stud in bearing
cover bolt hole Lock Bolt
All thread
Jack Bolt
Dial
Side View
indicators
Thrust setting
bracket All thread in cover
bolt hole
9 Record the movement of the bearing shell at this 19 Pull the thrust collar back. This distance is the,
point. remaining axial float. The remaining axial float
plus the established pressure tip clearance should
10 Jack out the rotor assembly with the thrust equal the total axial float measured in step 3.
bearing until the indicator on the clearance setting (Total float = clearance + axial float).
bracket is at the required pressure tip clearance.
20 Push the rotor assembly toward the diffuser and
11 Move the assembly 0.001" at a time on each remove the indicator.
jackscrew keeping all dial indicators as even as
possible.
! Note
If the remaining axial float plus the established
pressure tip clearance does not equal the total
axial float determined above, then check the
stage components to determine the problem.
12 Tap the bearing lightly and often to keep it square Pressure tip or “Y” clearance
in the bore.
Shim
Thickness
13 At 0.005" from the desired clearance, move the
assembly 0.0005" at a time until the desired
pressure tip clearance is attained.
!
Note
• The purpose of the spring bracket impeller
clearance setting tool is to apply a positive
pressure (inward) on the R/A while the thrust
bearing is being jacked (outward) for setting the
pressure tip clearance. See Figure 4.
• The tool can be used in an end to end, or
reversed, manner as may be required by the
Centac model.
• Adjust bolt length to achieve flat position of tool.
• Material for tool is a common bar stock.
• Bracket anchoring bolt (all thread) sized to
Centac bearing cover capscrew threads.
Casing
Thrust Collar
Short Test
Answer each question as fully as you can, or tick the best option.
When you finish, check your answers by reading through the section again.
1 What are the three (3) clearances to be set when assembling the Rotor
assembly on the 1CV machine?
a)
b)
c)
2 How many diameter indicators must be used when setting Pressure Tip “Y”
clearance?
5 What must you look for when servicing the discharge check valve?
Section 8
Disassembly of Stage Components ...........................1—10
Disassemble the Bullgear...........................................11—13
Re-assemble the Bullgear ..........................................14—17
Re-assemble the Stage Components.........................18—26
Setting Rotor Assembly Clearances...........................27
Impeller/Diffuser Clearance Setting Procedure ..........28—31
Installing the Coupling ................................................32
#1 Heating Torch
Sleeve
Hub
#2 Heating Torch
15 Stage Removal.
Remove the thrust bearing cover.
Top
Left Right
Bottom
Left Right
Bottom
There is an
‘O’ Ring at
the back of
the spacer 33 Remove the impeller bolt.
plate.
Rotor Removal
40 Install the rotor removal tool in the rotor bolt.
37 Position the removal tool to tighten it to the pinion Tighten the tool until it bottoms out.
shaft; note the left-hand thread.
Stage Removal
44 Remove the bolt in the thrust bearing flange.
Slowly slide the bearing, with the pinion,
backwards out of the line bore.
To reveal the
bullgear shaft.
To reveal the
bullgear
59 Remove all
cap screws
before
removing the
buckets. 62 Remove the cap screws to remove the bullgear
bearing from the bullgear casing.
! Note
Make sure that all bolts use 271 Loctite when
re-assembling the Airend.
22 Use the special tool, that comes with the Seal Kit,
to install the bullgear seal.
Oil Side
Bullgear Shaft
Double Lip
Hydrodynamic Seal.
25 Install a dial gauge to the bullgear shaft.
The hydrodynamic
pumping effect of the
seal is created by the
rotation of the Bullgear Shaft
bullgear shaft
on the thread like
surface of the sealing
lip. Lubricant, that has migrated along the shaft,
will be forced back into the casing through this
pumping action.
24 Tighten all of the seal cover bolts.
27 Check the impeller with the Gauss Gauge. 31 Apply the Tiolube 70 Lubricant to the pinion shaft
o
28 Heat the thrust collar to about 200 F
Preload
Preload
45 Make sure the bolts are cleaned with isopropyl
alcohol and apply 217 Loctite.
46 Tighten the cap screws to the bullgear housing With no preload With preload
NOTE: This sketch illustrates the reason for pre-
loading. The impeller to pinion fit up is greatly
QC-90 (11/19/90)
51 Make sure that you do not damage the carbon 54 Install the bullgear lock bolt.
seals.
Diffuser
Deswirl Ring
Mach marks
67 Clean the diffuser housing with isopropyl alcohol 70 Install the 3 hex head cap screws with lock
before installing the diffuser and deswirl ring. washers. Snug these bolts, do not tighten them.
77 Double check all clearances, then tighten all cap 3rd Stage
screws and nuts.
80 Place a new ‘O’ Ring in the 3rd Stage.
Total Axial Float of the Pinion 3 Use a feeler gauge to check the clearance at four
points, as shown on the following diagram.
Check the total axial float of the pinion.
B a ck o f Im p elle r in con tact with C asing
The clearance must be the same at the Top, on the
Left side and on the Right side. The bottom can be
slightly tighter 0.001”.
Top
Left Right
T o ta l axia l floa t of p inion
1-Gauge
Jack Bolt
3-Gauge
Lock Bolt Lock Bolt
diffuser, and check the Volume Tip (Z) Clearance. Stud in bearing cover bolt hole
Jack Bolt
Lock Bolt
2-Gauge
Thrust setting bracket
All thread
Jack Bolt
Measure each blade tip “Z”
Dial indicators
Use 3 dial
gauges
Thrust setting bracket
All thread in
cover bolt hole
! Note
The bull gear locking bolt should be removed
prior to performing this procedure.
Front View
Lock Bolt
Lock Bolt
Stud in bearing
cover bolt hole Lock Bolt
All thread
Jack Bolt
Dial
Side View
indicators
Thrust setting
bracket All thread in cover
bolt hole
9 Record the movement of the bearing shell at this 19 Pull the thrust collar back. This distance is the,
point. remaining axial float. The remaining axial float
plus the established pressure tip clearance should
10 Jack out the rotor assembly with the thrust equal the total axial float measured in step 3.
bearing until the indicator on the clearance setting (Total float = clearance + axial float).
bracket is at the required pressure tip clearance.
20 Push the rotor assembly toward the diffuser and
11 Move the assembly 0.001" at a time on each remove the indicator.
jackscrew keeping all dial indicators as even as
possible.
! Note
If the remaining axial float plus the established
pressure tip clearance does not equal the total
axial float determined above, then check the
stage components to determine the problem.
12 Tap the bearing lightly and often to keep it square Pressure tip or “Y” clearance
in the bore.
Shim
Thickness
13 At 0.005" from the desired clearance, move the
assembly 0.0005" at a time until the desired
pressure tip clearance is attained.
Inactive
thrust
Shim
adjustment
screw and
locking nut.
Fully interchangeable, by
coupling half with other
Competitive ‘O’ Ring style gear couplings available
on the market. It has large bore capacity and the
most economical design.
Sizes 1 to 30
• ‘O’ Ring style seal
• Shrouded or exposed bolt sleeves
• Reversible hubs
• Maximum bore up to 43.5” (1.1 meter)
• Maximum Torque up to 284 million lb-in (32100
kN-m)
• Many types available: Mill motor, Slide, Shear
Pin (overload torque protection), Floating shaft,
Limited end float, Electrically insulated, Alloy
steel and other custom design styles available
• ABS and DNV approved designs.
Section 9
5 What do you do if there has been a surge and surge equals zero?
6 In CMC electronic control, what is the driver motor overload protection called?
7 In CMC electronic control, what is the minimum throttle point control function
called?
b)
b) The CPU
b) The CPU
18 What could cause a negative value to be shown for all the Analogue inputs on
the OUI display?
a) Fuse F102 has blown
19 What could cause the E-Stop pressed indication to be checked on the OUI
display and to not clear, even with the E-Stop pulled out?
a) Fuse F101 has blown
20 What can cause the OUI display to go completely dark and blank?
a) Fuse F100 has blown
b) 1.0amps
c) 1.5 amps
d) 2.0 amps
b) Fuse F103
c) Control PowerTransformer
b) VCD
Section 10
Scheduled Preventative Maintenance ........................1—4
Maintenance Procedures............................................5—6
Setting Impeller Clearance .........................................7—9
Maintenance Procedures............................................10—11
Short Test ...................................................................12
Example Yearly Planner for 13 Check to make sure the air coolers are continuously
Scheduled Preventive Maintenance venting. Vent valves are located on top of the
casing.
January February March April
S M T W T F S S M T W T F S S M T W T F S S M T W T F S
Daily Maintenance
14 Drain the condensate from the inlet air line drip leg.
Daily Daily Daily Do not open the valve with the compressor
Maintenance Maintenance Quarterly Maintenance operating.
Maintenance
May June July August
15 Drain the condensate from the discharge header
S M T W T F S S M T W T F S S M T W T F S S M T W T F S drip leg.
Daily Maintenance
Daily Daily Daily
Maintenance Semi-Annual Maintenance Maintenance 16 Drain the condensate from the bypass air line drip
Maintenance leg.
September October November December
S M T W T F S S M T W T F S S M T W T F S S M T W T F S 17 Drain the drip legs on any other horizontal run of air
Daily Maintenance Daily Maintenance piping.
Daily Daily
Quarterly Maintenance Maintenance Annual
Maintenance Maintenance 18 Check for oil leaks. Correct as necessary.
• Drain and clean the filter. 2 Lubricate the main driver coupling. Dry-type coupling
• Replace the element.
components must be inspected.
3 Change oil filter.
2 Drain control air drip leg.
• Clean element.
• Replace element as necessary.
• Inspect seams of the filter for cracks for potential
bypassing. Seal seams as needed.
13 Oil Analysis
14 Condensate Analysis
1 Inspect the main driver per the manufacturer's
instructions found in the Operation Manual.
2 Visually inspect the coupling. Lubricate as
required.
! Caution
Servicing of the internal parts is not recommended
3 Manually rotate bullgear to feel for roughness on
models with bullgear anti-friction bearings. without the presence of an Ingersoll-Rand service
supervisor. For technical assistance, please call
4 Inspect and clean the oil reservoir suction screens. your local Ingersoll-Rand representative.
WARNING
5 Visually inspect the oil cooler tubes. Clean the
water side of the oil cooler if necessary.
Main Driver
Depending upon the customer's requirements,
different drivers are used with the Centac
compressor. Consult the driver manufacturer's
literature provided in this manual to insure proper
lubrication and maintenance procedures.
Control Panel
The control panel checkout procedure is designed to
verify that a control panel is functioning properly. The
checkout can be used for initial testing or in
conjunction with routine maintenance schedules.
Refer to the control drawings and checkout
procedure included with the Control Panel
Instructions in this manual to insure proper
adjustments and calibrations.
Intake Filter
All filtration systems have a maximum recommended
pressure drop at which the filter element should be
cleaned or replaced. Because of the many types of
atmospheric conditions that exist it is difficult to
accurately determine the life of a given filter element.
It is therefore advisable and highly recommended
that a weekly pressure drop measurement be
recorded for both the primary and final stage filter
elements to determine the useful element life.
!
Note
Never attempt to set the clearances without an
impeller clearance setting tool. See the Centac
Clearance Setting Tool diagram on the next
page.
5 Install the clearance setting tool against the
thrust bolt using one of the bearing cover bolt
holes to support the other end.
6 Install (3) dial indicators on a post installed in
one of the other thrust cover bolt holes.
7 Set (1) dial indicator to contact the top of the
clearance-setting tool above the thrust bolt. The
purpose of this is to show the movement of the
rotor.
8 Set (1) dial indicator to contact the thrust bearing
flange. The purpose of this indicator is to indicate
the movement of the bearing.
9 Zero both indicators.
To back
maximum
distance
away from
the
diffuser.
PUSH
Push
forward
to
Diffuser
Inactive or reverse
thrust clearance
Shim
Shim
Thickness
Jacking Screw
!
Warning
Lube system pressure may reach 50 PSIG and
temperatures of 160°F or more. Do not penetrate
lube system while machinery is operating.
!
Warning
Hot oil can cause serious injury to personnel.
Precaution must be taken to prevent contact with hot
oil.
Answer each question as fully as you can, or tick the best option.
When you finish, check your answers by reading through the section again.
2 What are the steps to follow when changing the oil mist arrestor element?
3 What must you look for when inspecting the control panel?
4 Why should you record the pressure drop measurement on a weekly basis?
Section 11
Troubleshooting Guide ...............................................1—6
Common Conversions and Information ......................7—12
Surge
Cause Solution
1 Dirty inlet air filter. Replace filter.
3 High interstage air temperatures. Investigate. Check to see what is necessary to lower
air temperatures. Check water temperature, water
flow, water pressure, etc.
4 Increase in water temperature. Investigate. Check to see if it is possible to lower
water temperature.
5 Increase in inlet air temperature. Lower setpoint.
8 Too low CLL or LLR (throttle surge). Increase CLL or LLR setting.
9 Too low P1, PR3, or mechanical stop Increase P1, PR3 or adjust mechanical stop.
adjustment (unloaded surge).
10 Improper calibration of valve I/P, positioner, or Calibrate as necessary.
actuator.
11 Defective bypass valve. Repair or replace.
12 Too low CLH setting. Increase setting (Do not exceed FLA+SF).
13 Leaking bypass valve. Investigate and correct. Replace seat; free up sticking
valve.
14 Bypass valve stays open; inlet valve functions Lower CLL to activate bypass valve on MP3 panel.
normally. Ensure 2TR is operating properly on Electro-
Pneumatic panel.
High Vibration
Cause Solution
3 Oil not draining properly from bearings. Investigate and correct. Check for restriction, improper
venting, too high oil level.
16 Inadequate oil supply to plain bearing. Investigate and correct. Ensure oil supply groove in
plain bearing shell is aligned properly with oil supply
hole through casing.
1 Too small control air line. Replace with larger diameter pipe.
2 Moisture in control air line. Remove moisture. Provide permanent method for
moisture removal.
3 Sensing control air pressure from wrong Change location of sensing pressure.
location.
4 Leaking fittings or damaged pipe. Repair or replace.
4 Instrument air supply pressure below Increase supply pressure. Obtain a different air source
recommended pressure. of adequate pressure.
Failure to Start
Cause Solution
1 No power to motor starter. Energize power.
No Control Power
Cause Solution
1 POWER ON selector switch OFF. Turn POWER ON switch to ON.
2 Blown fuse. Replace fuse.
3 Bad control power transformer. Replace.
4 Control power transformer wired incorrectly. Correct transformer wiring.
Failure to Load
Cause Solution
1 LOAD selector switch in the wrong position. Turn switch to LOAD.
2 Inlet valve stuck. Investigate and correct.
3 Controller setpoint too low. Adjust.
4 No control air signal. Investigate and correct. Check for closed valve.
5 Surge sensor tripped. Adjust or replace.
6 Bypass valve will not close. Investigate and correct.
7 No power air to inlet or bypass valve. Investigate. Open power air shutoff valve.
8 Valve actuator or positioner malfunctioning. Repair or replace.
9 REMOTE/LOCAL switch for CEM in wrong Turn to REMOTE for CEM operation.
position.
10 10. Incorrect CLL setting. Reset to correct value.
1 Inadequate water flow. Provide adequate water flow to the oil cooler.
2 High water temperature. Lower water temperature; use a cooler water source.
5 Dirty oil cooler on water side. Clean water side of oil cooler.
7 Water/glycol mixture greater than 50/50. Adjust mixture to ensure the glycol is not greater than
50%.
8 Water temperature supply higher than oil Install larger oil cooler or additional cooler.
cooler design.
9 Heat exchanger radiating fins dirty. Clean fins.
10 Incorrect number of water passes. Investigate. Orient return bonnet correctly; replace
bonnett gasket if bypassing; install cooler with more
passes.
Temperature
To convert Formula to use
Pressure – gauge
To convert Formula to use
1 PSI to Atmosphere PSI X 0.06805
2 PSI to inches of H2O at 68°F PSI X 27.73
3 PSI to inches of mercury (in Hg) at 0°C PSI X 2.036
4 PSI to kPa PSI X 6.8948
5 PSI to Kg/cm2 PSI X 0.07031
6 Kg/cm2 to Atmosphere Kg/cm2 X 0.9678
7 Kg/cm2 to bars Kg/cm2 X 0.98066
8 Kg/cm2 to inches of mercury (in Hg) at 0°C Kg/cm2 X 28.96
9 Kg/cm2 to kPa Kg/cm2 X 98.066
10 Kg/cm2 to PSI Kg/cm2 X 14.223
11 kPa to PSI kPa X 0.145
12 bars to PSI bars X 14.504
13 inches of H2O at 68°F to inches of mercury (in Hg) at 0°C in H2O X 0.07342
14 inches of water at 68°F to psi in H2O X 0.03606
15 inches of water at 68°F to kPa in H2O X 0.2487
16 inches of water at 68°F to Kg/ cm2 in H2O X 0.002535
17 inches of water at 68°F to bar in H2O X 0.002487
18 inches of water at 68°F to standard atmosphere (atm) in H2O X 0.002454
19 inches of mercury at 0°C to inches of water at 68°F in Hg X 13.62
20 inches of mercury at 0°C to psi in Hg X 0.03606
21 inches of mercury at 0°C to kPa in Hg X 3.3864
22 inches of mercury at 0°C to Kg/cm2 in Hg X 0.034532
23 inches of mercury at 0°C to bar in Hg X 0.033864
24 inches of mercury at 0°C to standard atmospheres (atm) in Hg X 0.03342
25 atmosphere (standard) to bar atm X 1.01325
26 atmosphere (standard) to psi atm X 14.696
27 atmosphere (standard) to Kg/cm2 atm X 1.0332
28 atmosphere (standard) to Kg/m2 atm X 10332
29 atmosphere (standard) to kPa atm X 101.325
Length
To convert Formula to use
1 inches to meters (m) in. X 0.0254
2 inches to centimeters (cm) in. X 2.54
3 inches to millimeters (mm) in. X 25.4
4 meters to inches (in.) m X 39.37
5 centimeters to inches (in.) cm X 0.3937
6 millimeters to inches (in.) mm X 0.03937
7 mills (0.001") to millimeters 0.001" X 0.0254
Flow
To convert Formula to use
1 cubic feet per minute (scfm) to scfm X 0.0004719
cubic meters per second (nm3/s)
2 cubic feet per minute (scfm) to scfm X 1.699
cubic meters per hour (nm3/h)
3 cubic feet per minute (scfm) to scfm X 471.9
cubic centimeters per second (cm3/s)
4 cubic feet per minute (scfm) to scfm X 0.02832
cubic meters per minute (nm3/m).
1000 scfm = 28.32 nm3/m
5 cubic meters per hour (nm3/h) to nm3/h X 0.016667
cubic meters per minute (scfm)
6 cubic meters per hour (nm3/h) to nm3/h X 0.00027778
cubic meters per second (nm3/s)
7 cubic meters per minute (nm3/m) to nm3/m X 35.315
cubic feet per minute (scfm)
8 gallons per minute (US) to gpm X 0.0037854
cubic meters per minute (nm3/m)
9 gallons per minute (US) to cubic meters per hour (nm3/h) gpm X 0.2271
10 gallons per minute (US) to cubic feet per hour (scfh) gpm X 8.021
11 gallons per minute (US) to liters per second (L/s) gpm X 0.06309
Volume
To convert Formula to use
3
1 gallons (US) to cubic inches (in ) gal. X 231
3
2 gallons (US) to cubic meters (m ) gal. X 0.0037854
3 gallons (US) to liters (L) gal. X 3.7854
4 liters (L) to cubic inches (in3) L X 61.024
3
5 liters (L) to cubic meters (m ) L X 0.001
6 liters (L) to gallons (US) L X 0.26418
3 3
7 cubic inches (in ) to cubic meters (m ) in3 X (16.387 X 10- 6)
8 cubic meters (m3) to cubic inches (in3) m3 X 61024
9 cubic meters (m3) to cubic ft. (ft3) m3 X 35.315
10 cubic feet (ft3) to cubic meters (m3) ft3 X 0.02832
Electrical
Quantities
IR IE ( pf ) 1 . 73 IE ( pf )
KW = KW = KW =
1000 1000 1000
IE (eff ) IE ( eff )( pf ) 1.73 IE (eff )( pf )
hp = hp = hp =
746 746 746
IE IE (eff )( pf ) 1.73 IE ( eff )( pf )
J = J = J =
sec sec sec
746 ( hp ) 746 ( hp ) 746 ( hp )
Amps (hp known) = Amps (hp known) = Amps (hp known) =
E ( eff ) E ( eff )( pf ) 1 .73 E ( eff )( pf )
1000 KW 1000KW 1000KW
Amps (KW known) = Amps (KW known) = Amps (KW known) =
E E( pf ) 1.73E( pf )
1000 kva 1000 kva
Amps (kva known) = Amps (kva known) =
E 1.73 E
Vibration
2
A = Acceleration in g’s (in/sec ) = Peak
V = Velocity in in/sec = Peak
D = Displacement in mils = Peak - Peak
f = Frequency in Hz
V A
D = 318 .3 x D = 19 , 570 x
f f 2
A = 0.0000511 x D x f2 A = 0.0162 x V x f2
Definitions
Root Mean Square (RMS)
RMS = 0.707 x Peak RMS = 1.111 x average RMS = 0.354 x Pk - Pk
Average
Average = 0.637 x Peak Average = 0.900 x RMS2 Average = 0318 x Pk - Pk
Peak to Peak
Pk - Pk = 2 x Peak Pk - Pk = 2.828 x RMS Pk - Pk = = 3.142 x average
Peak
Pk = 1.414 x RMS Pk = 1.571 x average
0.707
0.637
+
0
- Average RMS Peak
Peak to Peak
12000
Total vibration (in mils) = 1.25 x
RPM