Академический Документы
Профессиональный Документы
Культура Документы
A
NPV =
(1 + r ) t
where r = Discount Rate which measures inflation.
NPV of a future amount represents the estimated present value of the future amount with
estimated future inflation amounts removed.
Ex 1: A project is being considered which has €12,000 initial costs with estimated
benefits to be €8,000 after the first year, €7,500 after the second year and €5,000
after the third year. Calculate the NPV of the project using 18.5% as a discount
rate. What advise would you give about this investment?
Solution:
= €3,096.87
Advise: Proceed with the project because under the above conditions this project will
cover its cost and make a profit of €3,096.87 after three years.
Note:
1
1. Initial cost of the project €12,000 is not discounted because it is valued at
present but is entered in the formula as a NEGATIVE amount as it is a
EXPENSE to the business.
2. Using 18.5% as the Discount Rate yields a NPV >0. This means that if the
project goes ahead after 3 years a profit of €3,096.87 is made after the
project’s cost is covered.
3. Return on the above investment is €3,096.87.
Ex 2: A project is being considered which has €45,000 initial costs with estimated
benefits to be €12,500 after the first year, €15,500 after the second year and
€21,000 after the third year and €38,000 after the fourth year. Calculate the NPV
of the project using 28% as a discount rate. What advise would you give about
this investment?
Solution:
= - €1,604.24
Advise: Do not go ahead with this project under the above conditions as this project will
not cover its cost and make a loss of €1,604.24 after four years. Return on the above
investment is -€1,604.24
Internal Rate of Return (IRR): is the discount rate which makes the Net Present Value of
a Project equal ZERO i.e. the project breaks even.
Formula:
NPV1
IRR = D1 + ( D2 − D1 )
NPV1 − NPV2
2
Example 1:
Using the following information, calculate IRR for this project. Use 10% as the initial
discount amount.
Year 0 1 2 3 4 5
Cash (70,000) 15,000 20,000 20,000 20,000 20,000
Solution:
= €1,270.29
Let D2 = D1 + 5% = 15%
Note: D2 must be > D1 and yield a NPV < 0 so by trial and error pick a suitable D2 value.
= - €7,304.74
1270.29
IRR = 10% + (15% – 10%)
1270.29 − (7304.74)
Luckily in Ms Excel 2003 we have a Paste Function wizard displayed by the icon on
the toolbars. This function wizard contains a collection of different types of
mathematical and computing calculations e.g. The Logical Category contains the IF
function, the Statistical Category contains the AVERAGE, MODE, MEDIAN
functions. There is also a Financial Category which contains the IRR and the NPV
functions.
4
Example: Using Ms Excel 2003 to calculate the NPV for
Ex 1: A project is being considered which has €12,000 initial costs with estimated
benefits to be €8,000 after the first year, €7,500 after the second year and €5,000
after the third year. Calculate the NPV of the project using 18.5% as a discount
rate. What advise would you give about this investment?
Note: This NPV calculation has already been manually calculated which equalled
€3,096.87.
Tasks in Excel:
1. Enter in the above details – the project’s costs, estimated benefits and the given
discount rate into a spreadsheet as outlined below:
2. In cell B10, select the icon in order to construct the NPV formula.
Select the Financial category from the category drop down menu.
Then select the NPV function to insert into cell B10 as outlined below.
5
3. Use the Function Arguments dialog box to enter in the necessary details in order
to find the NPV.
Enter in the following details in the appropriate boxes of the dialog box:
• Rate Box: Select the appropriate cell which contains the discount rate. Then tab
down to next box.
• Value1 Box: Select the appropriate cell which contains the project’s benefit after
the first year. Then tab down to the next box.
• Value2 Box: Select the appropriate cell which contains the project’s benefit after
the second year. Then tab down to the next box.
• Value3 Box: Select the appropriate cell which contains the project’s benefit after
the third year.
6
4. Select the OK option and €15,096.87 appears in cell B10 as the NPV answer.
Since Excel only deals with future benefit values for NPV calculations, we must
finally subtract the project’s cost (which doesn’t have to be discounted since it is a
present value) in order to find the overall NPV for the project.
The spreadsheet below shows the final NPV answer in cell B10 with the final
formula appearing up in the formula Bar.
Note: The formula in Cell B10 contains +B5 which represents adding the contents
of cell B5 which is already NEGATIVE as it contains the project’s cost to the
NPV.
Example 1:
Using the following information, calculate IRR for this project. Use 10% as the initial
discount amount.
Year 0 1 2 3 4 5
Cash (70,000) 15,000 20,000 20,000 20,000 20,000
Note: This IRR calculation has already been manually calculated which equalled 10.74%
Tasks in Excel:
1. Enter in the above details – the project’s costs, estimated benefits and the given
initial discount rate into a spreadsheet as outlined below:
7
2. In cell B12, select the icon in order to construct the IRR formula.
Select the Financial category from the category drop down menu.
Then select the IRR function to insert into cell B12 as outlined below.
3. Use the Function Arguments dialog box to enter in the necessary details in order
to find the IRR.
Enter in the following details in the appropriate boxes of the dialog box:
• Value Box: Highlight the range of cells containing the project’s cost and all of its
future benefits. Then tab down to next box.
• Guess Box: Select the appropriate cell which contains the initial discount rate
given.
4. Select the OK option and 11% or 10.68% when rounded off to 2 decimal places
appears in cell B12 as the IRR answer.
8
Exercises: Using Ms Excel carry out the following calculations:
Calculate the internal rate of return (IRR) for the project mentioned above using
15% as the initial discount rate. (Round off your answer to 2 decimal places.)
Year 0 1 2 3 4
Net Cash Flow -50000 25500 24500 17000 14000
Calculate the internal rate of return (IRR) for the project mentioned above using
22% as the initial discount rate. (Round off your answer to 2 decimal places.)