Академический Документы
Профессиональный Документы
Культура Документы
0 INTRODUCTION
In an effort to prepare for the CUCSA games slated for February 2020, The Copperbelt
University invited bidders for the construction of a podium at the CBU stadium.
The procedure included pre-qualifying and enlisting prospective Contractors from among
those who submitted their tenders in accordance with the tender requirements to undertake
the assignment described herein. The Pre-qualification Tender document and the Tenderers
response were thereof the basis for pre- qualification. Tenderers were advised to familiarize
themselves with the requirements described in the document including all attachments and
took them into account while preparing the response.
BID OPENING
The tender closing date was on the 30 th September 2019. In total sixteen contractors attended
a compulsory site visit of the 12 November 2013. Out of these, only two responded giving a
33.3% response indicating a low return. (Please see attached Schedule of Tenders)
No Name of Tender Amount Tendered Duration (weeks)
1 Mwembeshi Contractors K167,727.00 8
2 Global Engineering Ltd K172,500.00 10
MWEMBESHI CONTRACTORS
Key Personnel
Mwembeshi is well resourced with well trained personnel covering all required levels of
construction expertise. They propose to deploy a Site Engineer with an approved Degree in
Civil Engineering with 7 years of experience in construction industry.
Site engineer will be vested in the hands of a qualified quantity surveyor with a post
qualification experience of 8years. This project manager has extensively been involved in
projects of this kind. The Site foreman will be qualified with a Diploma in Civil Engineering
with 10years experience in the building environment.
The staff compliment as proposed by Mwembeshi is impressive and suitable to see the
completion of this project. The bricklayers are qualified with crafts certificates in Brick
laying and Carpenters with craft certificate in carpentry.
Management Plan
The method statement as submitted is comprehensive and achievable. They have amassed
relevant experience in similar projects and should be able to execute the works within set
time. Their proposed construction duration although somewhat high is sufficient to see out
the project. Also their works program is in harmony with the quoted duration and has
addressed all critical elements as required.
Plant& Equipment
The list of plant and equipment provided is adequate to carry out this project especially that
they own some of the plant. They own 1 concrete mixer, 1 light truck, 1 site van, 1 poker
vibrator and proposed to buy small tools. We have no doubt that in the event more plant and
equipment is needed Global Engineering Ltd will be able to hire out.
PROJECT DURATION
Mwembeshi Contractors
The tenderer has proposed a construction period of 8weeks which is a reasonable time frame.
We have no doubt that the contractor will be able to deliver within the set duration
EVALUATION REMARKS
Mwembeshi Contractors
Mwembeshi Contractors submitted a tender sum of K167, 727.00 which is lower than that of
the other bidder. The difference between the two tender sums is minimal
Mwembeshi proposed to submit a bid security bond of K20, 000.00. The bid security gives
clients assurance that the selected bidder will sign the contract or otherwise forfeit their bid
security and the bid bond also gives assurance that the bidder has the financial means to
accept the job for the price quoted in the bid.
Mwembeshi proposed to construct the building in 8 working weeks. Considering that the
project needs to be complete as quickly as possible in preparation of the February 2020
games, time is of essence therefore we are assured that this bidder will be able to deliver
within the earliest possible time.
(Personnel & Equipment)
RECOMMENDATION