Академический Документы
Профессиональный Документы
Культура Документы
Copyright © 2020 Pearson Education Ltd. All Rights Reserved. Copyright © 2020 Pearson Education Ltd. All Rights Reserved.
Copyright © 2020 Pearson Education Ltd. All Rights Reserved. Copyright © 2020 Pearson Education Ltd. All Rights Reserved.
MRP for Wheeled Coach (2 of 2) Learning Objectives (1 of 2)
• Four Key Tasks When you complete this chapter you should be able to:
– Material plan must meet both the requirements of the 14.1 Develop a product structure
master schedule and the capabilities of the production
facility 14.2 Build a gross requirements plan
– Plan must be executed as designed 14.3 Build a net requirements plan
– Minimize inventory investment
14.4 Determine lot sizes for lot-for-lot, EOQ, and POQ
– Maintain excellent record integrity
Copyright © 2020 Pearson Education Ltd. All Rights Reserved. Copyright © 2020 Pearson Education Ltd. All Rights Reserved.
Copyright © 2020 Pearson Education Ltd. All Rights Reserved. Copyright © 2020 Pearson Education Ltd. All Rights Reserved.
Dependent Demand (2 of 3) Dependent Demand (3 of 3)
• Benefits of MRP • The demand for one item is related to the demand for
1. Better response to customer orders another item
2. Faster response to market changes • Given a quantity for the end item, the demand for all parts
3. Improved utilization of facilities and labor and components can be calculated
4. Reduced inventory levels • In general, used whenever a schedule can be established
for an item
• MRP is the common technique
Copyright © 2020 Pearson Education Ltd. All Rights Reserved. Copyright © 2020 Pearson Education Ltd. All Rights Reserved.
• Effective use of dependent demand inventory models • Specifies what is to be made and when
requires the following
• Must be in accordance with the aggregate production plan
1. Master production schedule
2. Specifications or bill of material • Inputs from financial plans, customer demand,
engineering, labor availability, inventory fluctuations,
3. Inventory availability
supplier performance
4. Purchase orders outstanding
• As the process moves from planning to execution, each
5. Lead times
step must be tested for feasibility
Copyright © 2020 Pearson Education Ltd. All Rights Reserved. Copyright © 2020 Pearson Education Ltd. All Rights Reserved.
Master Production Schedule (MPS)
(2 of 2) The Planning Process (1 of 3)
• MPS is established in terms of specific products, it Figure 14.1
disaggregates the aggregate plan
• Schedule must be followed for a reasonable length of time
• The MPS is quite often fixed or frozen in the near-term part
of the plan
• The MPS is a rolling schedule
• The MPS is a statement of what is to be produced, not a
forecast of demand
Copyright © 2020 Pearson Education Ltd. All Rights Reserved. Copyright © 2020 Pearson Education Ltd. All Rights Reserved.
Copyright © 2020 Pearson Education Ltd. All Rights Reserved. Copyright © 2020 Pearson Education Ltd. All Rights Reserved.
Aggregate Production Plan Master Production Schedule (MPS)
Figure 14.2 Can be expressed in any of the following terms:
1. A customer order in a job shop (make-to-order)
company
2. Modules in a repetitive (assemble-to-order or
forecast) company
3. An end item in a continuous (stock-to-forecast)
company
Copyright © 2020 Pearson Education Ltd. All Rights Reserved. Copyright © 2020 Pearson Education Ltd. All Rights Reserved.
Copyright © 2020 Pearson Education Ltd. All Rights Reserved. Copyright © 2020 Pearson Education Ltd. All Rights Reserved.
BOM Example (2 of 2)
BOM Example (1 of 2)
Copyright © 2020 Pearson Education Ltd. All Rights Reserved. Copyright © 2020 Pearson Education Ltd. All Rights Reserved.
Copyright © 2020 Pearson Education Ltd. All Rights Reserved. Copyright © 2020 Pearson Education Ltd. All Rights Reserved.
Bills of Material (4 of 4) Accurate Inventory Records
• Phantom Bills • Accurate inventory records are absolutely required for
– Describe subassemblies that exist only temporarily MRP (or any dependent demand system) to operate
– Are part of another assembly and never go into correctly
inventory • MRP systems require more than 99% accuracy
• Low-Level Coding
– Item is coded at the lowest level at which it occurs
– BOMs are processed one level at a time
Copyright © 2020 Pearson Education Ltd. All Rights Reserved. Copyright © 2020 Pearson Education Ltd. All Rights Reserved.
Copyright © 2020 Pearson Education Ltd. All Rights Reserved. Copyright © 2020 Pearson Education Ltd. All Rights Reserved.
• Starts with a production schedule for the end item – 50 • From the BOM, every Item A requires 2 Item Bs – 100 Item
units of Item A in week 8 Bs are required in week 7 to satisfy the order release for
Item A
• Using the lead time for the item, determine the week in
which the order should be released – a 1-week lead time • The lead time for the Item B is 2 weeks – release an order
means the order for 50 units should be released in week 7 for 100 units of Item B in week 5
• This step is often called "lead time offset" or "time phasing" • The timing and quantity for component requirements are
determined by the order release of the parent(s)
Copyright © 2020 Pearson Education Ltd. All Rights Reserved. Copyright © 2020 Pearson Education Ltd. All Rights Reserved.
Determining Gross Requirements
(3 of 3) Gross Requirements Plan
• The process continues through the entire BOM one level at Table 14.3 Gross Material Requirements Plan for 50
a time – often called "explosion" Awesome Speaker Kits (As) with Order Release Dates Also
Shown
• By processing the BOM by level, items with multiple
parents are only processed once, saving time and
resources and reducing confusion
• Low-level coding ensures that each item appears at only
one level in the BOM
Copyright © 2020 Pearson Education Ltd. All Rights Reserved. Copyright © 2020 Pearson Education Ltd. All Rights Reserved.
Copyright © 2020 Pearson Education Ltd. All Rights Reserved. Copyright © 2020 Pearson Education Ltd. All Rights Reserved.
Determining Net Requirements (1 of 3) Determining Net Requirements (2 of 3)
• Starts with a production schedule for the end item − 50 • Following the lead time offset procedure, the planned order
units of Item A in week 8 release for Item A is now 40 units in week 7
• Because there are 10 Item As on hand, only 40 are • The gross requirement for Item B is now 80 units in week 7
actually required − (net requirement) = (gross requirement
• There are 15 units of Item B on hand, so the net
− on-hand inventory)
requirement is 65 units in week 7
• The planned order receipt for Item A in week 8 is 40 units −
• A planned order receipt of 65 units in week 7 generates a
40 = 50 − 10
planned order release of 65 units in week 5
Copyright © 2020 Pearson Education Ltd. All Rights Reserved. Copyright © 2020 Pearson Education Ltd. All Rights Reserved.
Copyright © 2020 Pearson Education Ltd. All Rights Reserved. Copyright © 2020 Pearson Education Ltd. All Rights Reserved.
Net Requirements Plan (3 of 3) MRP Management (1 of 3)
The logic of net requirements • MRP dynamics
– Demand-driven MRP strategically alters lead times
and precisely places safety stock within the BOM
structure to improve MRP performance
– Can reduce stockouts and improve stability
Copyright © 2020 Pearson Education Ltd. All Rights Reserved. Copyright © 2020 Pearson Education Ltd. All Rights Reserved.
Copyright © 2020 Pearson Education Ltd. All Rights Reserved. Copyright © 2020 Pearson Education Ltd. All Rights Reserved.
MRP Management (2 of 3) MRP Management (3 of 3)
• MRP dynamics • MRP limitations
– Facilitates replanning when changes occur – MRP does not do detailed scheduling–it plans
– System nervousness can result from too many – Works best in product-focused, repetitive environments
changes – Requires fixed lead times and time buckets with
– Time fences put limits on replanning unlimited capacity
– Pegging links each item to its parent, allowing effective
analysis of changes
Copyright © 2020 Pearson Education Ltd. All Rights Reserved. Copyright © 2020 Pearson Education Ltd. All Rights Reserved.
Copyright © 2020 Pearson Education Ltd. All Rights Reserved. Copyright © 2020 Pearson Education Ltd. All Rights Reserved.
Lot-Sizing Techniques (3 of 3) Lot-for-Lot Example (1 of 2)
• Dynamic lot sizing techniques
– Balance lot size and setup costs
– Part period balancing (least total cost)
– Least unit cost
– Least period cost (Silver-Meal)
• Dynamic programming approach
– Wagner-Whitin
Lot-for-Lot Example (2 of 2)
EOQ Lot Size Example (1 of 2)
There are seven setups for this item in this plan Holding cost = $1/week; Setup cost = $100; Lead time = 1 week
Total ordering cost = 7 × $100 = $700
Average weekly gross requirements = 27; EOQ = 73 units
Copyright © 2020 Pearson Education Ltd. All Rights Reserved. Copyright © 2020 Pearson Education Ltd. All Rights Reserved.
EOQ Lot Size Example (2 of 2)
POQ Lot Size Example (1 of 2)
Holding cost = $1/week; Setup cost = $100; Lead time = 1 week Average
weekly gross requirements = 27; EOQ = 73 units
Annual demand D = 1,404
Holding cost = 375 units × $1 (including 57 units on
hand at end of week 10)
Ordering cost = 4 × $100 = $400 EOQ = 73 units; Average weekly gross requirements = 27; POQ
Total cost = $375 + $400 = $775 interval = 73/27 ≅ 3 weeks
Copyright © 2020 Pearson Education Ltd. All Rights Reserved. Copyright © 2020 Pearson Education Ltd. All Rights Reserved.
d a pla n with a
EOQ = 73 units; Average weekly gross requirements = 27; POQ interval e yielde
= 73/27 ≅ 3 weeks h it in w ould hav 4 5 5
Wagner-
W t of $
total cos
Setups = 3 × $100 = $300
Holding cost = (40 + 70 + 30 + 55) units × $1 = $195
Total cost = $300 + $195 = $495
Copyright © 2020 Pearson Education Ltd. All Rights Reserved. Copyright © 2020 Pearson Education Ltd. All Rights Reserved.
Lot-Sizing Summary (1 of 2) Lot-Sizing Summary (2 of 2)
• In theory, lot sizes should • Lot sizes can be modified to allow for scrap, process
be recomputed whenever constraints, and purchase lots
there is a lot size or order
• Use lot-sizing with care as it can cause considerable
quantity change
distortion of requirements at lower levels of the BOM
• In practice, this results in
• When setup costs are significant and demand is
system nervousness and
reasonably smooth, POQ or EOQ should give reasonable
instability
results
• Lot-for-lot should be used
when low-cost setups can
be achieved
Copyright © 2020 Pearson Education Ltd. All Rights Reserved. Copyright © 2020 Pearson Education Ltd. All Rights Reserved.
Copyright © 2020 Pearson Education Ltd. All Rights Reserved. Copyright © 2020 Pearson Education Ltd. All Rights Reserved.
Copyright © 2020 Pearson Education Ltd. All Rights Reserved. Copyright © 2020 Pearson Education Ltd. All Rights Reserved.
Smoothing Tactics Order Splitting (1 of 2)
1. Overlapping • Develop a capacity plan for a work cell at Wiz Products
– Sends part of the work to following operations before • There are 12 hours available each day
the entire lot is complete
– Reduces lead time • Each order requires 1 hour
Copyright © 2020 Pearson Education Ltd. All Rights Reserved. Copyright © 2020 Pearson Education Ltd. All Rights Reserved.
MRP in Services (1 of 3) MRP in Services (2 of 3)
• Some services or service items are directly linked to Figure 14.9
demand for other services
• These can be treated as dependent demand services or
items
– Restaurants
– Hospitals
– Hotels
Copyright © 2020 Pearson Education Ltd. All Rights Reserved. Copyright © 2020 Pearson Education Ltd. All Rights Reserved.
Copyright © 2020 Pearson Education Ltd. All Rights Reserved. Copyright © 2020 Pearson Education Ltd. All Rights Reserved.
Enterprise Resource Planning (ERP) Enterprise Resource Planning (ERP)
(1 of 2) (2 of 2)
• An extension of the MRP system to tie in customers and • ERP modules include
suppliers – Basic MRP
1. Allows automation and integration of many business – Finance
processes
– Human resources
2. Shares common databases and business practices
– Supply-chain management (SCM)
3. Produces information in real time – Blockchain
• Coordinates business from supplier evaluation to customer – Customer relationship management (CRM)
invoicing – Sustainability
Copyright © 2020 Pearson Education Ltd. All Rights Reserved. Copyright © 2020 Pearson Education Ltd. All Rights Reserved.
Copyright © 2020 Pearson Education Ltd. All Rights Reserved. Copyright © 2020 Pearson Education Ltd. All Rights Reserved.
ERP and MRP (3 of 5) ERP and MRP (4 of 5)
Figure 14.10 Figure 14.10
Copyright © 2020 Pearson Education Ltd. All Rights Reserved. Copyright © 2020 Pearson Education Ltd. All Rights Reserved.
Copyright © 2020 Pearson Education Ltd. All Rights Reserved. Copyright © 2020 Pearson Education Ltd. All Rights Reserved.
SAP's ERP Modules ERP in the Service Sector
Figure 14.11 • ERP systems have been developed for health care,
government, retail stores, hotels, and financial services
• Also called efficient consumer response (ECR) systems
in the grocery industry
• Objective is to tie sales to buying, inventory, logistics, and
production
Copyright © 2020 Pearson Education Ltd. All Rights Reserved. Copyright © 2020 Pearson Education Ltd. All Rights Reserved.
Copyright