Work Sechedule For Ventilation / AC Works Date 14-Jun-18 24-06-2018 1-Jul-18 8-Jul-18 16-Jul-18 30-07-2018 Remarks S.NO ITEM/WORK DESCRIPTION Scope of work/week Week 1 Week 2 Week 3 Week 4 Week 5 Week 6 Updated drawings as per revised scheme is Client awaited 1 Drawings & BOQ 2 Technical Submission HAPL 3 Approval of Drawings and Technical Submittal HAPL/Client 4 Site Mobilisation HAPL 5 Cutouts/Foundations for All major equipments Client 6 Building Completion/Clear Work Front Client 6 VENTILATION / AC WORKS I Ducting Delivery HAPL Installation HAPL II Grills/ Diffusers / Dampers Delivery HAPL Installation HAPL Testing and Balancing HAPL III. VRV/Split Unitts Delivery HAPL Installation HAPL Testing and Balancing HAPL IV. Electrical cables/ cable tray / Earthing Delivery HAPL Installation HAPL V. Insulation Delivery HAPL Installation HAPL VI. Axial/Propellar Fan Delivery HAPL Installation HAPL VII. Electrical Panel Delivery HAPL Installation HAPL Power for testing and commissioning Client Testing and Commissioning HAPL 6 Handing over HAPL/Client Note: 1 All given Dates are subjected to Clear Work Front Availability / Building Completion etc and any change/modifications in scheme of System / Equipments will have further time implications 2 All dates are subject to approval of drawing/documents within 2-3 days otherwise Dates shall be shifted accordingly. 3 All above dates are subject to processing of running bills and receiving of our payments within 15-30 days 4 All given dates will shift accordingly in case of any last minute changes/modifications etc 5 Any change in drawing/layout will have additional time implication