Академический Документы
Профессиональный Документы
Культура Документы
ISSN 2229-5518
IJSER
Civil Engineering, Kebbi State University of respectively, amounting to #9,322,000 only.
Science and Technology, Aliero, P.M.B. Also, the comparison of flexible and concrete
1144, Nigeria. pavements was calculated as #3,753,180 and
* ybattahiru@gmail.com #9, 772,000 respectively. Considering the
figures above, it shows that, the concrete
pavement was far beyond the flexible
Key-Words: concrete, pavement,
pavement in terms of cost comparison based
aggregates, growth-rate, structural, capacity,
on the method of construction. The road was
traffic- flow.
designed using the Road Note 29 Design
method, the Sub-Base thickness was selected
Abstract based on the Sub-Grade CBR value and the
The aim of this research article is to justify cumulative number of standard axle during
the use of concrete pavement and to design a design life of the pavement structure. The
good concrete pavement that will be durable California Bearing Ratio (CBR) was found to
and serve the community, for its design life be 3% and a Sub-Base thickness of 80mm.
without any failure or problem. A traffic The surfacing thickness was 155mm which
count has been conducted to determine the was determined from the chart. From the
Annual Daily Traffic Flow (ADTF). This was design mix ratio 1:2:4, the quantities of
used to determine the growth rate at the materials (cement, water, fine and coarse
design period, which was found to be 3% aggregates) and cost were estimated. An
growth rate. The results were presented investigation was carried out recently in India
below: sub-grade type was normal; and the on the comparative economy of a flexible
minimum thickness of the Sub-Base required pavement and a concrete pavement. This has
was 80mm. While the minimum thickness of proved that on the overall economic
the concrete slab (unreinforced) required was
IJSER © 2016
http://www.ijser.org
International Journal of Scientific & Engineering Research, Volume 7, Issue 2, February-2016 1495
ISSN 2229-5518
consideration, a concrete pavement is far concrete pavement has its own failure, but it
more economical than the flexible pavement. has been proven to be more durable and
Recommendations such as: the concrete requires little or no maintenance throughout
pavement should be adequately roughened so its design life. According to a research,
as to provide skid resistance to vehicles (Hassan, 2006), the concrete pavement
plying the road, care must be taken in order (because of its rigidity and high modulus of
to ensure that the mix design of the concrete elasticity) tends to distribute the load applied
used is standard, care should be taken when on it over a relatively wide area of soil, and
constructing, so that the chamber of the the major factor considered in the design of
pavement will provide a free fall for water on concrete is the strength of concrete itself. In
the pavement surface into the drainage Nigeria, the use of concrete pavement is very
provided, care must also be taken to ensure low and where available, is only used where
that the sub-base layer is graded and flexible pavements have failed. Considering
compacted to a smooth hard surface, the fact that Nigeria is a country whereby the
effective supervision mechanism should be act of maintenance is lacking, concrete
adopted by the Federal and the State pavement will be most desirable considering
IJSER
Government, drainage should be properly its durability (Amina, 2013).
supervised, constructed, and maintained after The reference point for the design of concrete
the construction, suitable materials should be pavement is the Farm Road along Zaria-
used for pavement construction, and, quality Sokoto Road. This is due to the presence of
control test should be properly carried out. heavy traffic (Trucks, Lorries, etc.) that
plying the road in the process of transferring
1. Introduction farm produce from the farm to their place of
In developing countries like Nigeria, the use storage for consumption. This pavement type
of flexible pavement for roads both in urban is preferred due to its high modulus of
and rural areas its most commonly adopted. elasticity as well as its rigidity to the flexible
This is so because of the availability of the pavement (Khanna and Justo, 2001).
materials for the pavement and also because The use of concrete pavement has been the
of the low cost involved during construction trend in the past twenty to thirty years in the
as well as the availability of technological developed countries (Mustapha, 2005). This
know-how involved in the process of design is probably because of its durability,
and construction. But, over the years, these awareness and low cost of maintenance of the
flexible pavements have the tendency of concrete pavement. In America, where the
failing easily before they attain their design highest number of concrete pavement is
life, (Mohammed, 2007).Concrete pavement recorded, the proportion of the used of
regarded as rigid pavements are made of concrete pavement is well over 50% of the
cement, water, aggregates (fine and coarse total roadway and this pavement is used
aggregates) and sometimes admixtures are mostly at residential areas, industrial areas as
often use of (Khanna and Justo, 2001). well as major roadways whereby traffic
According to a research, (Sani, 2001), the volume is high (Amina, 2013). The
IJSER © 2016
http://www.ijser.org
International Journal of Scientific & Engineering Research, Volume 7, Issue 2, February-2016 1496
ISSN 2229-5518
challenges of the new technology associated Step 6: From the tables, obtain the sub-base
with concrete pavement design with a view thickness for the appropriate sub-grade CBR
of producing positive results on the users, and cumulative number of standard axle.
technique and materials as well as its being Step 7: Obtain from the tables the thickness
cost effective needs to be addressed in the for Base and surfacing from the appropriate
developing countries. base materials and cumulative number of
standard axles.
2. Methods
The road has been designed using the Road 3. Results
Note 29 Design Method, the sub-base Data:
thickness was selected on the basis of sub- - The CBR value of sub-grade = 13%
grade CBR (California Bearing Ratio) and - Number of commercial vehicles in
the cumulative number of standard axles both directions daily = 90
during the design of the pavement structure. - The design life = 20 years (though
A traffic count was conducted to determine RN 29 recommends a maximum
the Annual Daily Traffic Flow (ADTF). This design life of 40 years)
IJSER
was used to determine the growth rate at the - Growth Rate = 3%
design period. The traffic information Table 3.1 Classification of Sub-Grade for
collected from census data enables one to Concrete
estimate the number of commercial vehicles Type of Definition Minimum thickness
per day (either in each or in both directions). sub-grade of sub-base required
A growth rate, as specified in Road Note 29, Weak All sub-
of 3-4% was be used. grade of 150mm
2.1 Design Steps: CBR
Step 1: Find the number of commercial value 2%
vehicles per day at the construction and or less
traffic growth rate. Normal Sub-grade 80mm
Step 2: Decide on the design life. other than
Step 3: From chart for particular growth rate those
obtain cumulative number of commercial defined
vehicles for the design life. by the
Step 4: Multiply the cumulative number of other
commercial vehicles by the appropriate factor categories
from table to obtain cumulative number of Very stable All sub- 0mm
axle loads (factor is based on the type of road grade of
to be constructed). CBR
Step 5: Reduce the number of cumulative value of
axle loads to equivalent standard axles. 15% or
more
Source: Babatunde and Mahmoud (2000).
IJSER © 2016
http://www.ijser.org
International Journal of Scientific & Engineering Research, Volume 7, Issue 2, February-2016 1497
ISSN 2229-5518
IJSER
D = Conversion factor 1 Tipper = 5000kg
Therefore; T= 0.44x106 x 0.4 No. of Tippers = 325 tippers
T = 0.2x106 standard axle
From the Design Mix Ratio of 1:2:4, the For Coarse Aggregate:
quantities of materials (cement, water, fine 2.4 x 418 = 1003.2 x 2427.3 = 2435067.36kg
and coarse aggregates) needed are estimated 1 Tipper = 5000kg
below: No. of Tippers = 487 Tippers
Volume to be constructed = 1.155m x 6m x
2175m = 2022.75m3 For water
Taking shrinkage wastage to be 20% 0.5 x 418 = 209kg/m3
20 x 2022.75m3 + 2022.75m3 = 2427.30m3 209 x 2427.30 = 507305.70kg = 507.31
100 Tones
From the formula, From the above quantities, an estimate is
W + C+ AC = 1m3 done for the surfacing
1000pW 1000pC 1000pA
Where; W = Water content in kg/m3
C = Cement content
A = Aggregates content in kg/m3
p W , p C , p A= specific Gravity of W, C, A
respectively
p W = 1 , p C = 3.5, p A = 2.65
W/C = 0.5, W = 0.5C
A/C = 4; A = 4C
A = A1 + A2
IJSER © 2016
http://www.ijser.org
International Journal of Scientific & Engineering Research, Volume 7, Issue 2, February-2016 1498
ISSN 2229-5518
Table 3.3 Cost Summary of Flexible Table 3.4 Cost Comparison of Flexible and
Pavement (Labour Based Method of Concrete Pavements (Summary of Labour
IJSER
Construction) Based Method of Construction)
ITEM FLEXIBLE PAVEMENT ITEM FLEXIBLE CONCRETE
PAVEMENT PAVEMENT
Cost (#) % Cost Cost
IJSER © 2016
http://www.ijser.org
International Journal of Scientific & Engineering Research, Volume 7, Issue 2, February-2016 1499
ISSN 2229-5518
IJSER
cement, fine aggregate, coarse aggregate, and will no longer hold.
water were calculated as #15219750,
#650000, #2435000, and #50731 6. Acknowledgement
respectively, amounting to #18,355,481 only. All praise be to God, the Lord of the world,
From table 3.3, the total estimated cost of whose infinite mercy and continue guidance
labour, hand-tools, and equipment were brought us at this stage of our life and the
calculated as #3276000, #586000, and ability to successfully complete this research
#5460000 respectively, amounting to article. We`d like to thank Prof. B.G.
#9,322,000 only. Also, from table 3.4, the Danshehu, Engr. Abdullahi SB. Mohammed,
comparison of flexible and concrete Engr. Abulkareem A. Abiola, and Juwaratu
pavements was calculated as #3,753,180 and Mohammed, whose effort, support, comment,
#9, 772,000 respectively. Considering the encouragement, guidance, and adverse,
figures above, it shows that, the concrete immensely contribute towards the
pavement was far beyond the flexible accomplishment of this research article. May
pavement in terms of cost comparison based Almighty God bless and reward you all
on the method of construction. accordingly, amen.
5. Conclusion 7. References
From the cost analysis, the materials for the Amina, A.A., (2013), “An investigation into
concrete pavement are quite higher than that flexible pavements failures”, 16-38.
of the flexible pavement (because of the
availability of materials used for the asphalt Babatunde, O.S., and Mahmoud, G.A.,
concrete are cheaper). But, on the other hand, (2000), “Assessment of failures on Rigid
the use of a flexible pavement along this road and Pavements”, 21-44.
IJSER © 2016
http://www.ijser.org
International Journal of Scientific & Engineering Research, Volume 7, Issue 2, February-2016 1500
ISSN 2229-5518
IJSER
Mustapha, D., (2005), “Roles and
comparison of concrete and flexible
pavements in developing countries”, 23-56.
IJSER © 2016
http://www.ijser.org
International Journal of Scientific & Engineering Research, Volume 7, Issue 2, February-2016 1501
ISSN 2229-5518
8. Appendix
Table 8.1 Schedules of Resources and Cost
Estimate for Farm Road
IJSER
3 EQUIPMENT
Grader 1 Nil 50,000 50,000
Compacting 5 Nil 2,000 10,000 5,460,000
Machine 4 Nil 30,000 120,000
Others 4 Nil 20,000 80,000
IJSER © 2016
http://www.ijser.org
International Journal of Scientific & Engineering Research, Volume 7, Issue 2, February-2016 1502
ISSN 2229-5518
IJSER
05% 04.6%
Grand-Total #3,753,180 #9,772,000
100% 100%
IJSER © 2016
http://www.ijser.org