This document outlines the maintenance safety protocol for inspecting and servicing the MBK turning gear system on three gas turbine units (GT11, GT12, GT13) at the Azura Edo-Power Plant. The inspection involves identifying maintenance equipment, checking sensors and transmitters for damage, inspecting for leaks in the MBK system, and examining the condition of the turning gear control block. Potential hazards include noise, vibration, slips, trips and falls. Required hazard controls are use of proper PPE, taking breaks, cleaning spills, and maintaining housekeeping.
This document outlines the maintenance safety protocol for inspecting and servicing the MBK turning gear system on three gas turbine units (GT11, GT12, GT13) at the Azura Edo-Power Plant. The inspection involves identifying maintenance equipment, checking sensors and transmitters for damage, inspecting for leaks in the MBK system, and examining the condition of the turning gear control block. Potential hazards include noise, vibration, slips, trips and falls. Required hazard controls are use of proper PPE, taking breaks, cleaning spills, and maintaining housekeeping.
This document outlines the maintenance safety protocol for inspecting and servicing the MBK turning gear system on three gas turbine units (GT11, GT12, GT13) at the Azura Edo-Power Plant. The inspection involves identifying maintenance equipment, checking sensors and transmitters for damage, inspecting for leaks in the MBK system, and examining the condition of the turning gear control block. Potential hazards include noise, vibration, slips, trips and falls. Required hazard controls are use of proper PPE, taking breaks, cleaning spills, and maintaining housekeeping.
MAINTENANCE SAFETY PROTOCOL UNIT NUMBER GT11 Month Start time Stop time SYSTEM MBK - Turning Gear System WO# SN Job Step Hazard Hazard controls Status Comments
1 identify maintenance equipment according to P&IDs
2 Inspect the sensors, transmitters for physical damage or abnormal conditions
Use Proper PPE Noise, Vibration, slips, trips and Take short breaks falls Clean out spilled oil Do proper house keeping 3 Check same. for any leakage in the complete MBK system. In case of leakage, arrest
4 Check condition of the Turning gear control block
General Comments:
Lead Technician Signature Date
Supervisor Signature Date AZURA EDO-POWER PLANT MAINTENANCE CHECK SHEET / JOB HAZARD ANALYSIS MAINTENANCE SAFETY PROTOCOL UNIT NUMBER GT12 Month Start time Stop time SYSTEM MBK - Turning Gear System WO# SN Job Step Hazard Hazard controls Status Comments
1 identify maintenance equipment according to P&IDs
2 Inspect the sensors, transmitters for physical damage or abnormal conditions
Use Proper PPE Noise, Vibration, slips, trips and Take short breaks falls Clean out spilled oil Do proper house keeping 3 Check same. for any leakage in the complete MBK system. In case of leakage, arrest
4 Check condition of the Turning gear control block
General Coments:
Lead Technician Signature Date
Supervisor Signature Date AZURA EDO-POWER PLANT MAINTENANCE CHECK SHEET / JOB HAZARD ANALYSIS MAINTENANCE SAFETY PROTOCOL UNIT NUMBER GT13 Month Start time Stop time SYSTEM MBK - Turning Gear System WO# SN Job Step Hazard Hazard controls Status Comments
1 identify maintenance equipment according to P&IDs
2 Inspect the sensors, transmitters for physical damage or abnormal conditions
Use Proper PPE Noise, Vibration, slips, trips and Take short breaks falls Clean out spilled oil Do proper house keeping 3 Check same. for any leakage in the complete MBK system. In case of leakage, arrest
4 Check condition of the Turning gear control block