MAINTENANCE SAFETY PROTOCOL UNIT NUMBER GT11 Month Start time Stop time SYSTEM WO# SN Job Step Hazard Harzard controls Status Comments
1 identify maintenance equipment according to P&IDs
2 Inspect exhaust & diffuser thermocouples for physical damage or abnormal
conditions
3 Confirm the integrity of the electrical connection at thermocouple terminals,
JB and PCC
4 Confirm the instrument cable glands are firm and offer water ingress protection.
5 Clean equipment and the working area as required
General Coments:
Lead Technician Signature Date
Supervisor Signature Date AZURA EDO-POWER PLANT MAINTENANCE CHECK SHEET / JOB HAZARD ANALYSIS MAINTENANCE SAFETY PROTOCOL UNIT NUMBER GT12 Month Start time Stop time SYSTEM WO# SN Job Step Hazard Harzard controls Status Comments