Note : installation video search from the YOUTUBE, the key information will be “SUN2000 installation”
Notice
Grounding cable:first connection should be grounding cable, then other cables. It is for safety ,10mm Socket wrench is the best tool to tight
the cable. ;
Note : installation video search from the YOUTUBE, the key information will be “SUN2000 installation”
SUN2000-20/28KTL
4/6mm2
compatible
Female stamped and formed contacts Male stamped and formed contacts
Improvement
Available now
1.98mm->1.84mm
Essential Tool
String
SUN2000
Quantity
1 Any input
2 PV1, PV3
1. Special exterior or direct burial CAT5 cables should be used for outdoor runs instead of ordinary CAT5;
2. Exterior-grade Ethernet cables are waterproof &UV proof ;
3. 5-20cm (6-8 inches) and at least that far away from power lines or other sources of electrical interference;
IN OUT IN OUT
1 AC power cable port 1 (AC1) Connects phase A input and phase B input
RS485
Smartlogger
…...
PLC CCO
AC
…...
PLC PLC PLC
STA STA STA
It is not allowed to connect RS485 cables while using PLC. Also it is not allowed to connect the PLC while using RS485.
Connection AC side
Connection RS485 PLC CCO - Smartlogger
Requirement
Good!
Not recommended.
Three phases ac cables close together
Require bind together per 1m distance.
help to PLC signal transmissions.
Note:
PLC communication is just applicable for medium voltage application with transformer isolation from
the grid
The complete setup of PLC communication including inverter with PLC STA module (SUN2000-
33KTL integrated), PLC CCO decoding device and Huawei data logger
The PLC CCO can connect to a maximum of 80 inverters. Generally, a PLC CCO is configured for
one medium voltage block.
The maximum distance between inverter and PLC CCO is 400m with multi core cables or 300m
single core cables.
RS485 is integrated into inverter as default. It is not allowed to connect RS485 cables when using
PLC.
1 2 3
4 5 6
1 2 3
Open SUN2000 app Advanced user Search
Password:00000a Inverters
4 5 6
Find the Bluetooth Pairing Set parameters
device
(1) Energy yield diagram : Energy yield data within 24 hours of 1day
(2) Energy yield data: Daily yield , total yield , data and time.
(3) Power flow diagram: Numbers of strings, power flow, voltage and current both in DC and AC side
(4) Output power: Current power and peak power.
Note:
1. It really important to check the input and output data when abnormal or failure
happens. That will help to locate and solve the problem quickly.
2. It is required for failure claim in service hotline.
Note: ISO value should be stable all the time. If the value drops abnormally, operator should check the insulation .
Note: When active alarm occurs, you can press “ESC” button on the LCD to go to alarm page.
Alarm types
Type Definition Example
DC Overvoltage
Is generated when PV array exceptions occur but the SUN2000 is
PV array alarm String 1–6 Abnormal
not affected.
Sting 1-6 Reverse
Disconnect the SUN2000 from the power grid. The alarm can be Grid Voltage Abnormal
Power grid alarm
cleared automatically. Grid Frequency Abnormal
Low Array Insulation Resistance
Safety alarm Helps protect the security of the SUN2000 and safety of operators. Residual Current Abnormal
Electrical Grounding Fault
DC Bus Voltage Fault
Is generated when the internal circuit is affected by external factors
Invert Module Fault
Internal circuit alarm or misoperation. The alarm helps protect the security of the internal
Cabinet Over-Temp
circuit and can be cleared automatically.
Version Mismatch
Is generated when some functional circuits of the SUN2000 are
Minor fault alarm Internal Communication Fault
faulty but the SUN2000 continues to generate power.
Internal fault alarm Is generated when internal circuit is abnormal System Fault
Note:
More than 1 inverter and monitoring system are used
Different address from 1 to 247 should be set for
inverters
The selectable display status of the match resistance
include Disconnect and Connect.
This parameter is set to Disconnect by default. If signals
are distorted or the communication is of poor quality
because the signal cable is too long, set the parameter to
Connect.
Note:
The pic shows the default value
of the feature parameters. Note: When maintenance is required, you
Should be modified according to should power off and on the inverter
The local grid requirement. manually to ensure the maintainer’s safety .
Note:
1. DC power is necessary for Firmware upgrade
2. If problems can not be solved on site, please
export data with USB, and send all the files to
Huawei engineer for further analysis.
Blinking red at short intervals (on for0.5s The SUN2000 generates a minor alarm.
Alarm indicator and then off for 0.5s) For details, see<Alarm List>
Blinking red at long intervals (on for 1s The SUN2000 has generated a warning.
and then off for 4s) For details, see<Alarm List>
Notice
If you only want to check the connection, switch off the inverter via display(Switch off without load);
If the inverter get failure or stop, be careful. The conduct maybe is live;
Check the system and make sure it is safe to disconnect the strings or AC cables;
ISO/IEC 20000:2011
Smartlogger
2 Years’ Standard Warranty included
Any replacement Smart Logger is
guaranteed a minimum of 3 months
and a maximum for the remaining
*The Basic SLA included in the Warranty is 5dx8h
warranty period of the replaced
** Free Buffer Stock – Conditions Apply - Please speak to your local Account Manager
inverter
for more information about conditions
***Reimbursement conditions are fixed by Huawei and are available on request
HUAWEI TECHNOLOGIES CO., LTD. Page 53
HUAWEI Solar Customer Support Services, Europe
Products Covered: Solar Inverters SUN2000 range & Smart Logger
SUN2000-33KTL
DC Input AC Output
www.huawei.com
Copyright©2012 Huawei Technologies Co., Ltd. All Rights Reserved.
The information in this document may contain predictive statements including, without limitation, statements regarding the future financial and operating results, future product portfolio, new
technology, etc. There are a number of factors that could cause actual results and developments to differ materially from those expressed or implied in the predictive statements. Therefore,
such information is provided for reference purpose only and constitutes neither an offer nor an acceptance. Huawei may change the information at any time without notice.