West Qurna CS7 - MOTD Tie In - Phase 1C - Draft Copy

Activity ID Activity Name Original Duration Start Finish February


Deliverable March April May June July August September October November December January
February
Class 10 17 24 03 10 17 24 31 07 14 21 28 05 12 19 26 02 09 16 23 30 07 14 21 28 04 11 18 25 01 08 15 22 29 06 13 20 27 03 10 17 24 01 08 15 22 29 05 12 19 26 02
-2 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51
West Qurna CS7 - MOTD Tie In - Phase 1C - Draft Copy 318 17-Feb-19 31-Dec-19 31-Dec-19, West Qurna CS7 - MOTD Tie In - P

Milestone 318 17-Feb-19 31-Dec-19 31-Dec-19, Milestone

MS-1000 KO Meeting 0 17-Feb-19 KO Meeting

MS-1030 Receipt of BGC Design Data 0 04-Mar-19 Receipt of BGC Design Data

MS-1080 HAZOP 0 09-Apr-19 HAZOP

MS-1110 HAZOP Close Out 0 25-Apr-19 HAZOP Close Out

MS-1020 Detailed Design Completion 0 13-May-19 Detailed Design Completion

MS-1040 Completion of Civil Work 0 24-Sep-19 Completion of Civil Work

MS-1090 Tie In Completion 0 24-Oct-19 Tie In Completion

MS-1120 Delivery of Long Lead Item to Site 0 22-Dec-19 Delivery of Long Lead Item to Site

MS-1070 Static Commissioning 0 29-Dec-19 Static Commissioning

MS-1010 Dynamic Commissioning 0 31-Dec-19 Dynamic Commissioning

General 26 17-Feb-19 14-Mar-19 14-Mar-19, General

GEN-1000 Master Deliverable Register - IFR 2 17-Feb-19 18-Feb-19 1 Master Deliverable Register - IFR

GEN-1030 Master Deliverable Register - IFR - by BGC 7 19-Feb-19 27-Feb-19 1 Master Deliverable Register - IFR - by BGC

GEN-1010 Phase 1C - Planning Package - IFR 3 05-Mar-19 07-Mar-19 1 Phase 1C - Planning Package - IFR

GEN-1020 Phase 1C - Planning Package - IFR - by BGC 7 08-Mar-19 14-Mar-19 1 Phase 1C - Planning Package - IFR - by BGC

Engineering 72 03-Mar-19 13-May-19 13-May-19, Engineering

Process 72 03-Mar-19 13-May-19 13-May-19, Process

E-PR-1030 Design Basis - IFR 3 03-Mar-19 05-Mar-19 1 Design Basis - IFR

E-PR-1090 PFD - IFR 2 06-Mar-19 07-Mar-19 1 PFD - IFR

E-PR-1100 Heat and Mass Balance - IFR 2 06-Mar-19 07-Mar-19 1 Heat and Mass Balance - IFR

E-PR-1000 P & ID - IFR 2 07-Mar-19 10-Mar-19 1 P & ID - IFR

E-PR-1040 Line List - IFR 2 11-Mar-19 12-Mar-19 1 Line List - IFR

E-PR-1080 Update Cause and Effect Diagram - IFR 3 11-Mar-19 13-Mar-19 1 Update Cause and Effect Diagram - IFR

E-PR-1110 Design Basis - IFR by BGC 7 11-Mar-19 17-Mar-19 1 Design Basis - IFR by BGC

E-PR-1120 PFD - IFR - by BGC 7 11-Mar-19 17-Mar-19 1 PFD - IFR - by BGC

E-PR-1130 P & ID - IFR - by BGC 7 11-Mar-19 17-Mar-19 1 P & ID - IFR - by BGC

E-PR-1140 Heat and Mass Balance - IFR by BGC 7 11-Mar-19 17-Mar-19 1 Heat and Mass Balance - IFR by BGC

E-PR-1010 Operating Control Philosophy - IFR 5 12-Mar-19 18-Mar-19 1 Operating Control Philosophy - IFR

E-PR-1150 Line List - IFR - by BGC 7 13-Mar-19 19-Mar-19 1 Line List - IFR - by BGC

E-PR-1160 Update Cause and Effect Diagram - IFR - by BGC 7 14-Mar-19 20-Mar-19 1 Update Cause and Effect Diagram - IFR - by BGC

E-PR-1240 Design Basis - Update & for HAZOP 3 18-Mar-19 20-Mar-19 1 Design Basis - Update & for HAZOP

E-PR-1250 Heat and Mass Balance - Update & for HAZOP 3 18-Mar-19 20-Mar-19 1 Heat and Mass Balance - Update & for HAZOP

E-PR-1230 P & ID - Update & for HAZOP 5 18-Mar-19 22-Mar-19 1 P & ID - Update & for HAZOP

E-PR-1280 Line List - IFA 3 20-Mar-19 22-Mar-19 1 Line List - IFA

E-PR-1260 Update Cause and Effect Diagram - Update & for HAZOP 3 21-Mar-19 23-Mar-19 1 Update Cause and Effect Diagram - Update & for HAZOP

E-PR-1170 Operating Control Philosophy - IFR - by BGC 7 19-Mar-19 25-Mar-19 1 Operating Control Philosophy - IFR - by BGC

E-PR-1270 Operating Control Philosophy - Update & for HAZOP 4 26-Mar-19 29-Mar-19 1 Operating Control Philosophy - Update & for HAZOP

Actual Work
West Qurna CS7 - MOTD Tie In - Phase 1C - Draft Copy
Remaining Work
Critical Remaining Work
 
Page 1 of 7
Milestone
Summary
 
West Qurna CS7 - MOTD Tie In - Phase 1C - Draft Copy

Activity ID Activity Name Original Duration Start Finish February


Deliverable March April May June July August September October November December January
February
Class 10 17 24 03 10 17 24 31 07 14 21 28 05 12 19 26 02 09 16 23 30 07 14 21 28 04 11 18 25 01 08 15 22 29 06 13 20 27 03 10 17 24 01 08 15 22 29 05 12 19 26 02
-2 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51
E-PR-1290 Line List - IFA - by BGC 7 23-Mar-19 29-Mar-19 1 Line List - IFA - by BGC

E-PR-1050 HAZOP Report 7 09-Apr-19 17-Apr-19 2 HAZOP Report

E-PR-1180 P & ID - IFA 5 18-Apr-19 24-Apr-19 1 P & ID - IFA

E-PR-1060 HAZOP Closeout Report - IFR 6 18-Apr-19 25-Apr-19 1 HAZOP Closeout Report - IFR

E-PR-1190 P & ID - IFA - by BGC 7 25-Apr-19 01-May-19 1 P & ID - IFA - by BGC

E-PR-1220 HAZOP Closeout Report - IFR - by BGC 7 26-Apr-19 02-May-19 1 HAZOP Closeout Report - IFR - by BGC

E-PR-1200 P & ID - IFC 2 05-May-19 06-May-19 1 P & ID - IFC

E-PR-1300 HAZOP Closeout Report - IFA 4 03-May-19 06-May-19 1 HAZOP Closeout Report - IFA

E-PR-1310 HAZOP Closeout Report - IFA - by BGC 7 07-May-19 13-May-19 1 HAZOP Closeout Report - IFA - by BGC

Mechanical 16 11-Mar-19 01-Apr-19 01-Apr-19, Mechanical

E-ME-1000 Datasheet for Gas Separator 8 11-Mar-19 20-Mar-19 2 Datasheet for Gas Separator

E-ME-1010 Gas Separator GA 8 21-Mar-19 01-Apr-19 2 Gas Separator GA

Piping 59 11-Mar-19 08-May-19 08-May-19, Piping

E-PP-1070 Plot Plan (Existing Plot Plan Input from BGC) - IFR 5 11-Mar-19 17-Mar-19 1 Plot Plan (Existing Plot Plan Input from BGC) - IFR

E-PP-1040 Tie In Schedule - IFR 5 13-Mar-19 19-Mar-19 1 Tie I n Schedule - IFR

E-PP-1130 Plot Plan (Existing Plot Plan Input from BGC) - IFR - by BGC 7 18-Mar-19 24-Mar-19 1 Plot Plan (Existing Plot Plan Input from BGC) - IFR - by BGC

E-PP-1060 Key Plan 4 20-Mar-19 25-Mar-19 2 Key Plan

E-PP-1010 Stress Isometrics 6 20-Mar-19 27-Mar-19 2 Stress Isometrics

E-PP-1160 Plot Plan (Existing Plot Plan Input from BGC) - IFC 3 25-Mar-19 27-Mar-19 1 Plot Plan (Existing Plot Plan Input from BGC) - IFC

E-PP-1140 Tie In Schedule - IFR - by BGC 10 20-Mar-19 29-Mar-19 1 Tie I n Schedule - IFR - by BGC

E-PP-1170 Tie In Schedule - IFA 4 30-Mar-19 02-Apr-19 1 Tie I n Schedule - IFA

E-PP-1090 Typical Pipe Support Drawing 6 01-Apr-19 08-Apr-19 2 Typical Pipe Support Drawing

E-PP-1100 Stress Analysis Report 8 28-Mar-19 08-Apr-19 2 Stress Analysis Report

E-PP-1120 Piping MTO 4 04-Apr-19 09-Apr-19 2 Piping MTO

E-PP-1180 Tie In Schedule - IFA - by BGC 7 03-Apr-19 09-Apr-19 1 Tie In Schedule - IFA - by BGC

E-PP-1030 Piping General Arrangements 7 02-Apr-19 10-Apr-19 2 Piping General Arrangements

E-PP-1110 Isometrics - IFR 8 10-Apr-19 21-Apr-19 1 Isometrics - IFR

E-PP-1150 Isometrics - IFR - by BGC 7 22-Apr-19 28-Apr-19 1 Isometrics - IFR - by BGC

E-PP-1190 Isometrics - IFA 5 29-Apr-19 03-May-19 1 Isometrics - IFA

E-PP-1000 3D Modeling 34 21-Mar-19 07-May-19 2 3D Modeling

E-PP-1200 Isometrics - IFA - by BGC 5 04-May-19 08-May-19 1 Isometrics - IFA - by BGC

Electrical 38 25-Mar-19 01-May-19 01-May-19, Electrical

E-EL-1060 Electrical Lighting Layout - IFR 3 25-Mar-19 27-Mar-19 1 Electrical Lighting Layout - IFR

E-EL-1160 Hazardous Area Classification Layout - IFR 3 25-Mar-19 27-Mar-19 1 Hazardous Area Classification Layout - IFR

E-EL-1050 Electrical Earthing Layout - IFR 4 28-Mar-19 02-Apr-19 1 Electrical Earthing Layout - IFR

E-EL-1070 Electrical Lighting Layout - IFR - by BGC 7 28-Mar-19 03-Apr-19 1 Electrical Lighting Layout - IFR - by BGC

E-EL-1170 Hazardous Area Classification Layout - IFR - by BGC 7 28-Mar-19 03-Apr-19 1 Hazardous Area Classification Layout - IFR - by BGC

E-EL-1100 Electrical Lighting Layout - IFA 3 04-Apr-19 06-Apr-19 1 Electrical Lighting Layout - IFA

E-EL-1020 Electrical Cable Schedule 4 03-Apr-19 08-Apr-19 2 Electrical Cable Schedule

Actual Work
West Qurna CS7 - MOTD Tie In - Phase 1C - Draft Copy
Remaining Work
Critical Remaining Work
 
Page 2 of 7
Milestone
Summary
 
West Qurna CS7 - MOTD Tie In - Phase 1C - Draft Copy

Activity ID Activity Name Original Duration Start Finish February


Deliverable March April May June July August September October November December January
February
Class 10 17 24 03 10 17 24 31 07 14 21 28 05 12 19 26 02 09 16 23 30 07 14 21 28 04 11 18 25 01 08 15 22 29 06 13 20 27 03 10 17 24 01 08 15 22 29 05 12 19 26 02
-2 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51
E-EL-1180 Hazardous Area Classification Layout - IFC 3 04-Apr-19 08-Apr-19 1 Hazardous Area Classification Layout - IFC

E-EL-1080 Electrical Earthing Layout - IFR - by BGC 7 03-Apr-19 09-Apr-19 1 Electrical Earthing Layout - IFR - by BGC

E-EL-1120 Electrical Earthing Layout - IFA 3 10-Apr-19 12-Apr-19 1 Electrical Earthing Layout - IFA

E-EL-1110 Electrical Lighting Layout - IFA - by BGC 7 07-Apr-19 13-Apr-19 1 Electrical Lighting Layout - IFA - by BGC

E-EL-1040 Electrical Cable Routing Layout - IFR 4 09-Apr-19 14-Apr-19 1 Electrical Cable Routing Layout - IFR

E-EL-1030 MTO 3 15-Apr-19 17-Apr-19 2 MTO

E-EL-1000 Date Sheet for Electrical Power Cable 8 09-Apr-19 18-Apr-19 2 Date Sheet for Electrical Power Cable

E-EL-1130 Electrical Earthing Layout - IFA - by BGC 7 13-Apr-19 19-Apr-19 1 Electrical Earthing Layout - IFA - by BGC

E-EL-1090 Electrical Cable Routing Layout - IFR - by BGC 7 15-Apr-19 21-Apr-19 1 Electrical Cable Routing Layout - IFR - by BGC

E-EL-1140 Electrical Cable Routing Layout - IFA 3 22-Apr-19 24-Apr-19 1 Electrical Cable Routing Layout - IFA

E-EL-1150 Electrical Cable Routing Layout - IFA - by BGC 7 25-Apr-19 01-May-19 1 Electrical Cable Routing Layout - IFA - by BGC

Instrumentation 51 06-Mar-19 25-Apr-19 25-Apr-19, Instrumentation

E-IN-1100 Controls System Architecture Diagram - IFR 3 06-Mar-19 10-Mar-19 1 Controls System Architecture Diagram - IFR

E-IN-1010 I/O list 2 11-Mar-19 12-Mar-19 2 I/O list

E-IN-1110 Controls System Architecture Diagram - IFR - by BGC 7 11-Mar-19 17-Mar-19 1 Controls System Architecture Diagram - IFR - by BGC

E-IN-1140 Controls System Architecture Diagram - IFA 3 18-Mar-19 20-Mar-19 1 Controls System Architecture Diagram - IFA

E-IN-1150 Controls System Architecture Diagram - IFA - by BGC 7 21-Mar-19 27-Mar-19 1 Controls System Architecture Diagram - IFA - by BGC

E-IN-1000 Datasheets 14 13-Mar-19 01-Apr-19 2 Datasheets

E-IN-1090 Cable Routing 8 25-Mar-19 03-Apr-19 2 Cable Routing

E-IN-1030 Hook up drawing - IFR 3 02-Apr-19 04-Apr-19 2 Hook up drawing - IFR

E-IN-1050 Bulk MTO 5 04-Apr-19 10-Apr-19 2 Bulk MTO

E-IN-1040 Installation Drawing 6 11-Apr-19 18-Apr-19 2 Installation Drawing

E-IN-1080 Loop Drawing - IFR 5 21-Apr-19 25-Apr-19 2 Loop Drawing - IFR

Civil 60 04-Mar-19 03-May-19 03-May-19, Civil

E-CL-1000 BGC Geo Survey Report - by Company 0 04-Mar-19 2 BGC Geo Survey Report - by Company

E-CL-1060 Specification - Excavation 8 12-Mar-19 21-Mar-19 2 Specification - Excavation

E-CL-1030 Civil GA 4 26-Mar-19 31-Mar-19 2 Civil GA

E-CL-1070 Specification - Concrete 10 18-Mar-19 31-Mar-19 2 Specification - Concrete

E-CL-1080 Specification - Structural 10 24-Mar-19 04-Apr-19 2 Specification - Structural

E-CL-1040 Sleeper Design Drawing 7 01-Apr-19 09-Apr-19 2 Sleeper Design Drawing

E-CL-1050 Misc Structural Supports 4 10-Apr-19 15-Apr-19 2 Misc Structural Supports

E-CL-1090 Inlet Separator Foundation Detailed Design Drawing 16 08-Apr-19 23-Apr-19 2 Inlet Separator Foundation Detailed Design Drawing

E-CL-1100 Structural Drawing - Platform and Ladder 10 24-Apr-19 03-May-19 2 Structural Drawing - Platform and Ladder

Procurement 280 18-Mar-19 22-Dec-19 22-Dec-19, Procurement

Instrumentation 280 18-Mar-19 22-Dec-19 22-Dec-19, Instrumentation

Control Valve 280 18-Mar-19 22-Dec-19 22-Dec-19, Control Valve

PR-BL-1220 Bid, Evaluation and Award 15 18-Mar-19 07-Apr-19 Bid, Evaluation and Award

PR-BL-1230 Manufacturing 224 08-Apr-19 17-Nov-19 Manufacturing

PR-BL-1240 Delivery - Control Valves 35 18-Nov-19 22-Dec-19 Delivery - Control Valves

Actual Work
West Qurna CS7 - MOTD Tie In - Phase 1C - Draft Copy
Remaining Work
Critical Remaining Work
 
Page 3 of 7
Milestone
Summary
 
West Qurna CS7 - MOTD Tie In - Phase 1C - Draft Copy

Activity ID Activity Name Original Duration Start Finish February


Deliverable March April May June July August September October November December January
February
Class 10 17 24 03 10 17 24 31 07 14 21 28 05 12 19 26 02 09 16 23 30 07 14 21 28 04 11 18 25 01 08 15 22 29 06 13 20 27 03 10 17 24 01 08 15 22 29 05 12 19 26 02
-2 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51
ESDV 280 18-Mar-19 22-Dec-19 22-Dec-19, ESDV

PR-BL-1030 Bid, Evaluation and Award 15 18-Mar-19 07-Apr-19 Bid, Evaluation and Award

PR-BL-1040 Manufacturing 224 08-Apr-19 17-Nov-19 Manufacturing

PR-BL-1050 Delivery - ESDV 35 18-Nov-19 22-Dec-19 Delivery - ESDV

Temperature, Pressure and Level Transmitt er 137 04-Apr-19 18-Aug-19 18-Aug-19, Temperatur e, Pressur e and Level Transmitter

PR-BL-1190 Bid, Evaluation and Award 12 04-Apr-19 21-Apr-19 Bid, Evaluation and Award

PR-BL-1200 Manufacturing 84 22-Apr-19 14-Jul-19 Manufacturing

PR-BL-1210 Delivery - Transmitter 35 15-Jul-19 18-Aug-19 Delivery - Transmitter

Differential Pressure Gauge 135 02-Apr-19 14-Aug-19 14-Aug-19, Differential Pressure Gauge

PR-BL-1250 Bid, Evaluation and Award 12 02-Apr-19 17-Apr-19 Bid, Evaluation and Award

PR-BL-1260 Manufacturing 84 18-Apr-19 10-Jul-19 Manufacturing

PR-BL-1270 Delivery - Differential Pressure Gauge 35 11-Jul-19 14-Aug-19 Delivery - Differential Pressure Gauge

Temperature, Pressure and Level Gauge 135 02-Apr-19 14-Aug-19 14-Aug-19, Temperatur e, Pressur e and Level Gauge

PR-BL-1280 Bid, Evaluation and Award 12 02-Apr-19 17-Apr-19 Bid, Evaluation and Award

PR-BL-1290 Manufacturing 84 18-Apr-19 10-Jul-19 Manufacturing

PR-BL-1300 Delivery - Temperature, Press ure and Level Gauge 35 11-Jul-19 14-Aug-19 Delivery - Temperature, Press ure and Level Gauge

Fire & Gas Detector 135 02-Apr-19 14-Aug-19 14-Aug-19, Fire & Gas Detector

PR-BL-1310 Bid, Evaluation and Award 12 02-Apr-19 17-Apr-19 Bid, Evaluation and Award

PR-BL-1320 Manufacturing 84 18-Apr-19 10-Jul-19 Manufacturing

PR-BL-1330 Delivery - Fire and Gas Detector 35 11-Jul-19 14-Aug-19 Delivery - Fire and Gas Detector

PSV 163 25-Mar-19 03-Sep-19 03-Sep-19, PSV

PR-BL-1370 Bid, Evaluation and Award 12 25-Mar-19 09-Apr-19 Bid, Evaluation and Award

PR-BL-1380 Manufacturing 112 10-Apr-19 30-Jul-19 Manufacturing

PR-BL-1390 Delivery - PSV 35 31-Jul-19 03-Sep-19 Delivery - PSV

Level Trasnmitter Including Level Guage 151 21-Mar-19 18-Aug-19 18-Aug-19, Level Trasnmitter Including Level Guage

PR-BL-1460 Bid, Evaluation and Award 12 21-Mar-19 07-Apr-19 Bid, Evaluation and Award

PR-BL-1470 Manufacturing 98 08-Apr-19 14-Jul-19 Manufacturing

PR-BL-1480 Delivery - LT Including LG 35 15-Jul-19 18-Aug-19 Delivery - LT Including LG

Instrumentation Tubing and Accessories 74 21-Mar-19 02-Jun-19 02-Jun-19, Instrumentation Tubing and Accessories

PR-BL-1400 Bid, Evaluation and Award 12 21-Mar-19 07-Apr-19 Bid, Evaluation and Award

PR-BL-1410 Manufacturing 21 08-Apr-19 28-Apr-19 Manufacturing

PR-BL-1420 Delivery - Tubing and Accessories 35 29-Apr-19 02-Jun-19 Delivery - Tubing and Accessories

PLC Panel 137 21-Mar-19 04-Aug-19 04-Aug-19, PLC Panel

PR-BL-1430 Bid, Evaluation and Award 12 21-Mar-19 07-Apr-19 Bid, Evaluation and Award

PR-BL-1440 Manufacturing 84 08-Apr-19 30-Jun-19 Manufacturing

PR-BL-1450 Delivery - PLC Panel 35 01-Jul-19 04-Aug-19 Delivery - PLC Panel

Instrument Cable 72 25-Mar-19 04-Jun-19 04-Jun-19, Instrument Cable

PR-BL-1340 Bid, Evaluation and Award 12 25-Mar-19 09-Apr-19 Bid, Evaluation and Award

PR-BL-1350 Manufacturing 21 10-Apr-19 30-Apr-19 Manufacturing

Actual Work
West Qurna CS7 - MOTD Tie In - Phase 1C - Draft Copy
Remaining Work
Critical Remaining Work
 
Page 4 of 7
Milestone
Summary
 
West Qurna CS7 - MOTD Tie In - Phase 1C - Draft Copy

Activity ID Activity Name Original Duration Start Finish February


Deliverable March April May June July August September October November December January
February
Class 10 17 24 03 10 17 24 31 07 14 21 28 05 12 19 26 02 09 16 23 30 07 14 21 28 04 11 18 25 01 08 15 22 29 06 13 20 27 03 10 17 24 01 08 15 22 29 05 12 19 26 02
-2 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51
PR-BL-1360 Delivery - Instrument Cable 35 01-May-19 04-Jun-19 Delivery - Instrument Cable

Instrumentation Bulks 111 04-Apr-19 23-Jul-19 23-Jul-19, Instrumentation Bulks

PR-BL-1060 Bid, Evaluation and Award 14 04-Apr-19 23-Apr-19 Bid, Evaluation and Award

PR-BL-1070 Manufacturing 56 24-Apr-19 18-Jun-19 Manufacturing

PR-BL-1080 Delivery - Instrumentation Bulks 35 19-Jun-19 23-Jul-19 Delivery - Instrumentation Bulks

Piping 182 20-Mar-19 17-Sep-19 17-Sep-19, Piping

Valves 167 04-Apr-19 17-Sep-19 17-Sep-19, Valves

PR-BL-1150 Bid, Evaluation and Award 14 04-Apr-19 23-Apr-19 Bid, Evaluation and Award

PR-BL-1160 Manufacturing 112 24-Apr-19 13-Aug-19 Manufacturing

PR-BL-1170 Delivery - Valves 35 14-Aug-19 17-Sep-19 Delivery - Valves

Pipes and Fittings 83 10-Apr-19 01-Jul-19 01-Jul-19, Pipes and Fittings

PR-BL-1000 Bid, Evaluation and Award 14 10-Apr-19 29-Apr-19 Bid, Evaluation and Award

PR-BL-1010 Manufacturing 28 30-Apr-19 27-May-19 Manufacturing

PR-BL-1020 Delivery - Pipes and Fittings 35 28-May-19 01-Jul-19 Delivery - Pipes and Fittings

Hot Tap Material 111 20-Mar-19 08-Jul-19 08-Jul-19, Hot Tap Material

PR-BL-1680 Bid, Evaluation and Award 14 20-Mar-19 08-Apr-19 Bid, Evaluation and Award

PR-BL-1690 Manufacturing 56 09-Apr-19 03-Jun-19 Manufacturing

PR-BL-1670 Delivery - Hot Tap Mater ia l 35 04-Jun-19 08-Jul-19 Delivery - Hot Tap Mater ia l

Electrical 133 28-Mar-19 07-Aug-19 07-Aug-19, Electrical

Earthing Material 90 18-Apr-19 16-Jul-19 16-Jul-19, Earthing Material

PR-BL-1550 Bid, Evaluation and Award 14 18-Apr-19 07-May-19 Bid, Evaluation and Award

PR-BL-1560 Manufacturing 35 08-May-19 11-Jun-19 Manufacturing

PR-BL-1570 Delivery - Earthing Cable 35 12-Jun-19 16-Jul-19 Delivery - Earthing Cable

Light Fixtures 111 28-Mar-19 16-Jul-19 16-Jul-19, Light Fixtures

PR-BL-1520 Bid, Evaluation and Award 14 28-Mar-19 16-Apr-19 Bid, Evaluation and Award

PR-BL-1530 Manufacturing 56 17-Apr-19 11-Jun-19 Manufacturing

PR-BL-1540 Delivery - Light Fixture 35 12-Jun-19 16-Jul-19 Delivery - Light Fixture

Electrical Cable 109 21-Apr-19 07-Aug-19 07-Aug-19, Electrical Cable

PR-BL-1580 Bid, Evaluation and Award 14 21-Apr-19 08-May-19 Bid, Evaluation and Award

PR-BL-1590 Manufacturing 56 09-May-19 03-Jul-19 Manufacturing

PR-BL-1600 Delivery - Electrical Cable 35 04-Jul-19 07-Aug-19 Delivery - Electrical Cable

Electrical Bulk 111 18-Apr-19 06-Aug-19 06-Aug-19, Electrical Bulk

PR-BL-1610 Bid, Evaluation and Award 14 18-Apr-19 07-May-19 Bid, Evaluation and Award

PR-BL-1620 Manufacturing 56 08-May-19 02-Jul-19 Manufacturing

PR-BL-1630 Delivery - Electrical Bulks 35 03-Jul-19 06-Aug-19 Delivery - Electrical Bulks

Structural Steel 46 05-May-19 19-Jun-19 19-Jun-19, Structural Steel

PR-BL-1640 Bid, Evaluation and Award 14 05-May-19 22-May-19 Bid, Evaluation and Award

PR-BL-1650 Manufacturing 21 23-May-19 12-Jun-19 Manufacturing

PR-BL-1660 Delivery - Structural Steel 7 13-Jun-19 19-Jun-19 Delivery - Structural Steel

Actual Work
West Qurna CS7 - MOTD Tie In - Phase 1C - Draft Copy
Remaining Work
Critical Remaining Work
 
Page 5 of 7
Milestone
Summary
 
West Qurna CS7 - MOTD Tie In - Phase 1C - Draft Copy

Activity ID Activity Name Original Duration Start Finish February


Deliverable March April May June July August September October November December January
February
Class 10 17 24 03 10 17 24 31 07 14 21 28 05 12 19 26 02 09 16 23 30 07 14 21 28 04 11 18 25 01 08 15 22 29 06 13 20 27 03 10 17 24 01 08 15 22 29 05 12 19 26 02
-2 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51
Construction 140 14-Aug-19 31-Dec-19 31-Dec-19, Construction

Civil 42 14-Aug-19 24-Sep-19 24-Sep-19, Civil

CN-PP-1060 Pipe Support - Precasting 22 14-Aug-19 04-Sep-19 Pipe Support - Precasting

CN-PP-1070 Pipe Support Precast Installation 16 27-Aug-19 11-Sep-19 Pipe Support Precast Installation

Inlet Separator Foundation 29 27-Aug-19 24-Sep-19 24-Sep-19, Inlet Separator Foundation

CN-PP-1120 Excavation 1 27-Aug-19 27-Aug-19 Excavation

CN-PP-1130 Blinding 2 28-Aug-19 29-Aug-19 Blinding

CN-PP-1190 Footing - Formwork and Reinforcement 4 30-Aug-19 02-Sep-19 Footing - Formwork and Reinforcement

CN-PP-1140 Pedestal - Formwork and Reinforcement 4 06-Sep-19 09-Sep-19 Pedestal - Formwork and Reinforcement

CN-PP-1150 Pedestal - Concrete Pouring 1 10-Sep-19 10-Sep-19 Pedestal - Concrete Pouring

CN-PP-1200 Footing - Concrete Pouring and Curing 10 03-Sep-19 12-Sep-19 Footing - Concrete Pouring and Curing

CN-PP-1160 Pedestal - Curing 10 11-Sep-19 20-Sep-19 Pedestal - Curing

CN-PP-1210 Waterproofing 2 21-Sep-19 22-Sep-19 Waterproofing

CN-PP-1170 Backfilling 2 23-Sep-19 24-Sep-19 Backfilling

Mechanical 12 25-Sep-19 06-Oct-19 06-Oct-19, Mechanical

CN-ME-1000 Inlet Separator Installation 12 25-Sep-19 06-Oct-19 Inlet Separator Installation

Piping 47 04-Sep-19 20-Oct-19 20-Oct-19, Piping

CN-PP-1000 Piping - Fabrication 14 04-Sep-19 17-Sep-19 Piping - Fabrication

CN-PP-1100 Structural Support Fabrication 16 18-Sep-19 03-Oct-19 Structural Support Fabrication

CN-PP-1090 Valve Installation 5 03-Oct-19 07-Oct-19 Valve Installation

CN-PP-1180 Platform and Ladder Installation 4 07-Oct-19 10-Oct-19 Platform and Ladder Installation

CN-PP-1110 Structural Support Installation 12 04-Oct-19 15-Oct-19 Structural Support Installation

CN-PP-1010 Piping - Installation 32 19-Sep-19 20-Oct-19 Piping - Installation

Electrical 18 26-Sep-19 13-Oct-19 13-Oct-19, Electrical

CN-EL-1000 Earthing - Cable Trench Excavation 5 26-Sep-19 30-Sep-19 Earthing - Cable Trench Excavation

CN-EL-1030 Earthing Cable Pulling 3 01-Oct-19 03-Oct-19 Earthing Cable Pulling

CN-EL-1010 Lighting Cable - Cable Trench Excavation 5 01-Oct-19 05-Oct-19 Lighting Cable - Cable Trench Excavation

CN-EL-1020 Lighting Cable Pulling 3 06-Oct-19 08-Oct-19 Lighting Cable Pulling

CN-EL-1040 Lighting Pole Fixing and Terminat ion 5 09-Oct-19 13-Oct-19 Lighting Pole Fixing and Termination

Instrumentation 84 03-Oct-19 25-Dec-19 25-Dec-19, Instrumentation

CN-IN-1000 Cable Tray Installation 8 03-Oct-19 10-Oct-19 Cable Tray Installation

CN-IN-1030 Cable Pulling 4 11-Oct-19 14-Oct-19 Cable Pulling

CN-IN-1040 Install and Termin ate - J B 2 15-Oct-19 16-Oct-19 Install and Termin ate - J B

CN-IN-1070 Install and Termin ate - Transmitters 4 15-Oct-19 18-Oct-19 Install and Termin ate - Transmitters

CN-IN-1100 Install and Termin ate - Differential Pressure Gauge 4 15-Oct-19 18-Oct-19 Install and Termin ate - Differential Pressure Gauge

CN-IN-1060 Install and Termin ate - PSV 4 19-Oct-19 22-Oct-19 Install and Termin ate - PSV

CN-IN-1080 Install and Termin ate - Gauge 4 19-Oct-19 22-Oct-19 Install and Termin ate - Gauge

CN-IN-1110 Install and Termin ate - F low meter 4 19-Oct-19 22-Oct-19 Install and Termin ate - F lowmeter

CN-IN-1120 Install and Termin ate - PLC Panel 4 19-Oct-19 22-Oct-19 Install and Termin ate - PLC Panel

Actual Work
West Qurna CS7 - MOTD Tie In - Phase 1C - Draft Copy
Remaining Work
Critical Remaining Work
 
Page 6 of 7
Milestone
Summary
 
West Qurna CS7 - MOTD Tie In - Phase 1C - Draft Copy

Activity ID Activity Name Original Duration Start Finish February


Deliverable March April May June July August September October November December JanuaryFebruary
Class 10 17 24 03 10 17 24 31 07 14 21 28 05 12 19 26 02 09 16 23 30 07 14 21 28 04 11 18 25 01 08 15 22 29 06 13 20 27 03 10 17 24 01 08 15 22 29 05 12 19 26 02
-2 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51
CN-IN-1090 Install and Termin ate - F ir e and Gas Det ect ors 4 23-Oct-19 26-Oct-19 Install and Termin ate - F ir e and Gas Detect ors

CN-IN-1010 Install and Termin ate - ESDV 3 23-Dec-19 25-Dec-19 Install and Termin ate - ESDV

CN-IN-1050 Install and Termin ate - Cont rol Valve 3 23-Dec-19 25-Dec-19 Install and Termin ate - Control Valve

Tie In 6 19-Oct-19 24-Oct-19 24-Oct-19, Tie In

CN-PP-1040 Tie In - FEED Line 2 19-Oct-19 20-Oct-19 Tie In - FEED Line

CN-PP-1080 Tie In - Flare Line - Hot Tap 4 21-Oct-19 24-Oct-19 Tie In - Flare Line - Hot Tap

Static Commissioning 77 14-Oct-19 29-Dec-19 29-Dec-19, Static Commissioning

CN-IN-1130 Continuity Check 2 14-Oct-19 15-Oct-19 Continuity Check

CN-PP-1020 Hydrotest 9 15-Oct-19 23-Oct-19 Hydrotest

CN-IN-1020 Loop Check 2 26-Dec-19 27-Dec-19 Loop Check

CN-PP-1050 Leak Test 2 28-Dec-19 29-Dec-19 Leak Test

Dynamic Commissioning 2 30-Dec-19 31-Dec-19 31-Dec-19, Dynamic Commissioning

CN-PP-1220 Dynamic Commissioning 2 30-Dec-19 31-Dec-19 Dynamic Commissioning

Actual Work
West Qurna CS7 - MOTD Tie In - Phase 1C - Draft Copy
Remaining Work
Critical Remaining Work
 
Page 7 of 7