Вы находитесь на странице: 1из 452

copy 249

copy 249
Ref. Title Page No. Ref. Title Page No.
1.1 Scope of Section 1-1 1.6 Control of Site 1-6
1.1.1 Description 1-1 1.6.1 Keeping Site Clear of Water 1-6
1.1.2 Standard Specifications Generally 1-1 1.6.2 Site Cleaning 1-6
1.1.3 Abbreviations, Title and Terms 1-1 1.6.2.1 Site Cleaning During Progress of Works 1-6
1.1.4 Units of Measurement 1-1 1.6.2.2  Final Clean Up on Completion 1-6 
1.6.3 Measurement and Basis of Payment 1-6
1.1.5 Standards 1-2
1.7 Control of Traffic and Access 1-6 
1.2 Project Works 1-2
1.7.1 Maintenance and Protection of Traffic 1-6
1.2.1 The Works 1-2
1.7.2 Maintenance of One-Way Traffic 1-6
1.2.2 Intent of Contract 1-2
1.7.3 Temporary Structures 1-6
1.2.3 Silence of Specifications 1-2
1.7.4 Haul Routes for Heavy Vehicles 1-6
1.3 Project Site 1-2  1.7.5 Measurement and Basis of Payment 1-7
1.7.6 Items in the Bill of Quantities 1-7
1.3.1 The Site 1-2
1.3.2 Contractor’s Work Areas 1-2 1.8 Control of Works 1-7
1.3.3 Site Survey and Investigation 1-3
1.8.1 Setting out of Works 1-7
1.3.4 Measurement and Basis of Payment 1-3
1.8.2 Surveying Equipment and Accessories 1-7
1.3.5 Items in the Bill of Quantities 1-3
1.8.3 Existing Underground Services and
1.4 Contractor’s Site Facilities 1-3  Obstructions 1-7
1.8.3.1  Notices to Concerned Authorities 1-7 
1.4.1 Contractor's Compound and Buildings 1-3
1.8.3.2 Categories of Obstructions 1-7 
1.4.2 Measurement and Basis of Payment 1-3
1.8.3.3  Existing Utilities 1-8 
1.4.3 Items in the Bill of Quantities 1-3
1.8.4 Measurement and Basis of Payment 1-8
1.5 Engineer’s Facilities 1-3
1.9 General and Contractual
1.5.1 General 1-3 Obligations 1-8 
1.5.2 Site Facilities for the Engineer/Employer: 1-3
1.9.1 Health, Safety and Environmental Program 1-8
1.5.3 Computers for the Engineer 1-4
1.9.1.1  Health, Safety and Environmental Plan 1-8 
1.5.4 Telephones for the Engineer / Employer 1-4
1.9.1.2  Health, Safety and Environment
1.5.5 Car Port for the Engineer 1-4
Representatives: 1-9 
1.5.6 Cameras for the Engineer 1-4
1.9.2 Use of Explosives 1-9
1.5.7 Thermometers 1-5
1.9.2.1  Control Measures 1-9 
1.5.8 Test Equipment 1-5
1.9.2.2  Blasting Procedures 1-9 
1.5.9 Inspection Facilities 1-5
1.9.2.3  Explosives Inventory 1-9 
1.5.10 Surveying Equipment for Engineer 1-5
1.9.3 Fire Precautions 1-9
1.5.11 Measurement and Basis of Payment 1-5
1.9.4 Measurement and Basis of Payment 1-9
1.5.12 Items in the Bill of Quantities 1-5

♦ 4-1 ♦
copy 249
Ref. Title Page No. Ref. Title Page No.
1.10 Management Procedures 1-10 1.13.2 Contractor's Schedule of Plant and
Equipment 1-17
1.10.1 Commencement, Program and Progress 1-10
1.13.3 Provision and Use of Plant
1.10.2 Records and Measurements 1-11
and Equipment 1-17 
1.10.3 Project Administration 1-11
1.13.4 Measurement and Basis of Payment 1-17
1.10.4 Progress Photographs/ Videos 1-11
1.10.5 Measurement and Basis of Payment 1-12 1.14 Contractor’s Temporary Works
1.10.6 Items in the Bill of Quantities 1-12 and Services 1-17
1.11 Submittals 1-12 1.14.1 Temporary Facilities 1-17
1.14.1.1  Generally 1-17 
1.11.1 General 1-12
1.14.1.2  Temporary Site Facilities 1-18 
1.11.2 Action Submittals 1-13
1.14.2 Scaffolding and False Work 1-18
1.11.3 Informational Submittals 1-14
1.14.3 Water Supply 1-18
1.11.4 Contractor's Review and Approval 1-14
1.14.4 Electricity Supply 1-18
1.11.5 Engineer's Action 1-14
1.14.5 Directional and Warning Signs 1-18
1.11.6 Record (As-Built) Drawings 1-15
1.14.6 Project Sign Board 1-18
1.11.7 Measurement and Basis of Payment 1-15
1.14.7 Measurement and Basis of Payment 1-18
1.11.8 Items in the Bill of Quantities 1-15
1.14.8 Items in the Bill of Quantities 1-19
1.12 Control of Materials and Standards
1.15 Commemorative Plaque and
for Sampling and Testing 1-15
Opening Ceremony 1-19
1.12.1 Storage of Materials 1-15
1.15.1 Commemorative Plaque 1-19
1.12.2 Handling Materials 1-15
1.15.2 Opening ceremony 1-19
1.12.3 Materials Supplied by Employer 1-15
1.15.3 Measurement and Basis of Payment 1-19
1.12.4 Local Material Sources 1-15
1.15.4 Items in the Bill of Quantities 1-19
1.12.5 Sources of Supply and Quality
Requirements 1-16 1.16 Measurement and Payment 1-19
1.12.6 Certificates of Guarantee and Production
1.16.1 General Method of Measurement 1-19
Plant Inspections 1-16
1.16.2 Scope of Payment 1-19
1.12.7 Sampling and Testing Procedures 1-16
1.12.7.1  Sampling 1-16 
1.12.7.2  Source Tests 1-16 
1.12.7.3  Quality Control Tests 1-16 
1.12.7.4  Control Tests 1-16 
1.12.7.5  Check Tests 1-16 
1.12.7.6  Precedence of Materials and Testing
Specifications 1-17 
1.12.8 Unacceptable Materials 1-17
1.12.9 Measurement and Basis of Payment 1-17

1.13 Contractor’s Plant


and Equipment 1-17
1.13.1 General 1-17

♦ 4-2 ♦
copy 249
1.1 Scope of Section hwy - highway
ht - height
1.1.1 Description H:V - horizontal:vertical
IEC - International Electrical Commission
1 This Section describes the general requirements IEE - Institution of Electrical Engineers (UK)
that apply to all sections of the Specification where ISO - International Organization for
relevant. All sections of the Specification are to be read Standardization
in conjunction with this Section. LEED - Leadership in Energy and Environmental
Design
1.1.2 Standard Specifications Generally L.L. - liquid limit
L.S. - lump sum
1 The Standard Specification is generic. The max - maximum
requirements of each section are intended to provide MCCB - molded case circuit breaker
sufficient information and instruction to the Contractor min - minimum (or minute)
unless additional requirements are stated in the Special MUTCD - Manual on Uniform Traffic Control
Specification. Particular requirements are stated in the Devices
Standard Special Specification, which is to be read in MV - Medium Voltage
conjunction with the sections of this Standard N.C. - Normally Closed (electrical contact)
Specification. In the event of any conflict between this NEC - National Electrical Code (UK)
Standard Specification and the Special Specification, the NEMA - National Electrical Manufacturers'
Special Specification shall govern. Association (USA)
N.O - Normally Open (electrical contact)
1.1.3 Abbreviations, Title and Terms OS - Omani Standards
pav't - pavement
1 The following abbreviations used in the
P.C. - prime cost
Specification and on the Drawings shall have the
PCC - Portland cement concrete
meanings ascribed to them below:
PE - polyethylene
AASHTO - American Association of State Highway PFA - Pulverized fly ash
and Transportation Officials P.I. - plasticity index
ABS - Acrylonitrile-Butadiene-Styrene P.L. - plastic limit
ACI - American Concrete Institute PLMCS - Public Lighting Management and Control
AISC - American Institute of Steel Construction System
AISI - American Iron and Steel Institute PTFE - Polytetrafluoroethylene
ANSI - American National Standards Institute PVC - polyvinyl chloride
API - American Petroleum Institute qty - quantity
ASTM - American Society for Testing and RC - reinforced concrete
Materials RCP - reinforced concrete pipe
AV. - average rdwy - roadway
AWG - American wire gauge ROW - right-of-way
AWS - American Welding Society SBSC - single bituminous seal coat
bit. - bitumen/bituminous SCM - Supplementary cementing material/s
BS - British Standard S.G. - specific gravity
BSSC - bituminous slurry seal coat SI - Système International D'Unités
BST - bituminous surface treatment Sta - Station (location along a survey line)
BS EN - British Standard harmonized with SWG - standard wire gauge (UK)
European Norm/ Standard TBSC - triple bituminous seal coat
CB - circuit breaker uPVC - unplasticized polyvinyl chloride
CBR - California Bearing Ratio VDE - Verband Deutscher Electrotechniker
conc - concrete wgt - weight
CIE - Commission Internationale de l'Eclairage
CISPR 15 - Limits and Methods of Measurement of
1.1.4 Units of Measurement
Radio disturbance characteristics of
Electrical Lighting and Similar Equipment Throughout the documentation units of measurement
DBSC - double bituminous seal coat are referred to by symbols as follows:
DIN - Deutsches Institute Fur Normalizieung nr - number
EN - European Norm/ Standard mm - millimeter/s
Equiv - equivalent cm - centimeter/s
FSS - Federal Standard Specification (USA) m - meter/s
GGBFS - Ground-granulated blast-furnace slag lin.m - linear meter/s
km - kilometer/s

♦ 1-1 ♦
copy 249
sq.mm - square millimeter/s 1.2 Project Works
sq.cm - square centimeter/s
sq.m - square meter/s 1.2.1 The Works
ha - hectare/s
cu.m - cubic meter/s 1 The Works comprised by the Project are as shown
gm - gram/s on the Drawings and defined in the Special Specification.
kg - kilogram/s Except where otherwise stated, the Contractor shall
t - metric ton (1,000 kg) construct and complete the whole of the Works and
ml - milliliter/s provide everything necessary for such construction and
ltr - liter/s completion.
Pa - Pascal/s
Mpa - Mega Pascal/s = N/sq.mm 1.2.2 Intent of Contract
N - Newton/s
kN - kilo Newtons 1 The intent of the Contract is to provide for the
construction and completion in every detail, and the
MN - mega Newtons
subsequent maintenance of the Works described. The
A - amperes
mA - milli amperes Contractor shall furnish all labor, materials, tools,
equipment, transportation, supplies and facilities and
V - volt/s
shall carry out all Permanent and Temporary
W - Watt
kW - kilowatt 2 Works and all other items necessary for the proper
kj - kilojoule/s completion of the Works in accordance with all
C - Celsius (Centigrade) requirements of the Contract.
Hz - Hertz (Frequency) 3 Where the Specifications or Drawings describe any
rpm - revolutions per minute portions of the Works in outline only, and not in
km/h - kilometers per hour complete detail, the best current engineering practice
sec - seconds shall prevail and only first quality materials and
min - minute/s (or minimum) workmanship shall be used.
h - hour/s
mS - milli Siemens
1.2.3 Silence of Specifications
dB - decibel/s
dBA - decibels absolute The apparent silence of the Specifications, Drawings or
ppm - parts per million other Contract Documents as to any detail or the
in. - inch/inches (1 in. = 25.4 mm) apparent omission from them of a detailed description
ft - foot/feet (1ft = 0.3048 m) concerning any Works or requirements, shall be
sq.in - square inch/inches regarded as meaning that current best engineering
sq.ft - square foot/feet practice shall apply and shall be to the approval of the
cu.ft - cubic foot/feet Engineer.
lb. - pound/s (weight)
psi - pounds per square inch 1.3 Project Site
gal - gallon/s (U.S.)
gal(Imp) - gallon/s (Imperial) 1.3.1 The Site
mph - miles per hour
HP - horsepower 1 The Site of the Works is as shown on the Drawings
USG - American gage and described in the Special Specification. The
Contractor will be given possession of such parts of the
1.1.5 Standards Site as are required to execute the Works in accordance
with the agreed Program or as are reasonably required
1 Reference to Standards and Codes of Practice shall for him to progress the Works.
be taken as those versions current at the date of issue of
the Tender Documents. 1.3.2 Contractor’s Work Areas
2 Where the Specification states that the
1 The Contractor shall make all necessary
recommendations of a Code of Practice or a Standard
arrangements, including payment if need be, regarding
must be complied with, then the recommendations
any land outside the Site that may be needed as work
become mandatory. Where there are alternative
areas. The Employer will not accept any liability in
recommendations the Contractor may adopt any of them
respect of such land.
unless otherwise instructed by the Engineer.
2 The Contractor shall locate and select sites outside
the right-of-way for the use of his plant and equipment,
and for siting his site offices, workshops, other
accommodation and Temporary Works, or any other

♦ 1-2 ♦
copy 249
uses which are essential for execution of the Contract. 1.3.5 Items in the Bill of Quantities
The Contractor shall take the necessary measures for
using these sites and shall be responsible for all i. Soil investigation and report (L.S.)
expenses that may become due in return for such use.
Prior to using any land owned by public or private 1.4 Contractor’s Site Facilities
owners outside the Site, the Contractor shall obtain the
approval of the concerned authorities and the Engineer. 1.4.1 Contractor's Compound and
3 The Contractor, if so required by the Engineer, Buildings
whether before or after completion of the Works, shall
1 The Contractor shall establish a compound for his
remove his construction plant, properly clean and
facilities at a location to be approved by the Engineer. He
remove all debris from the site and shall, wherever
shall provide, furnish and equip as necessary, all
applicable, remedy all damage and pay all money due to
buildings and facilities as required for his own and
land owners in return for using their land.
Subcontractors' use; including but not limited to site
offices and mess rooms with appropriate sanitary
1.3.3 Site Survey and Investigation facilities; workshops, sheds and stores; site toilets,
1 Before commencing work on Site, the Contractor latrines and the like.
shall carry out a topographical survey of the Site, in
conjunction with, or as directed by the Engineer. This 1.4.2 Measurement and Basis of Payment
survey shall include such parts of the Site as the
1 The Contractor shall be paid a two stage sum for
Engineer may direct, to record the Site limits,
the mobilization and demobilization of his facilities equal
dimensions, ground levels, obstructions and other
to the Lump Sum in the Bill of Quantities. 60% of the
features and the survey shall establish base lines and
sum will be paid at the completion of the mobilization
points for future setting out and also record the basis for
and the remaining 40% on issuance of the Certificate of
re-measurement of excavation and earthwork, where
Completion for the Whole of the Works.
applicable. The Contractor shall submit the site survey
drawings to the Engineer for approval. 2 The Contractor shall be paid a monthly sum for
maintaining his facilities. No payment for maintenance
2 The Contractor shall inspect the Site to identify
of the facilities will be made beyond the end of the
obstacles above and below ground such as fences,
Contract period (after approved extensions of Time for
services, walls, paved areas, underground tanks, utilities
Completion have been included).
and pits, and shall record them on the site survey
drawing and photographically if instructed.
3 The Contractor shall carry out sub-surface and
1.4.3 Items in the Bill of Quantities
other site investigations as are necessary to verify any i. Mobilization and demobilization of Contractor’s
information provided to him by the Employer and to facilities (Lump Sum)
ascertain the nature of the ground and facilitate ii. Maintenance of Contractor’s facilities
execution of the Works. It is the Contractor's (type) (nr of units) (nr of months)
responsibility to verify the stability of side slopes in cut
areas by specialized staff. The Contractor, at his own 1.5 Engineer’s Facilities
expense shall execute any required site investigation
prior to cutting in the relevant areas. The proposal for
1.5.1 General
the site investigation program as well the final
recommendation shall be approved by the Engineer. 1 All facilities provided for the Engineer's and/or
Employer's staff shall remain available until three
1.3.4 Measurement and Basis of Payment months beyond the issuance of the Certificate of
Completion or until such earlier time as the Engineer
1 No separate measurement or payment will be may decide.
made, for any part of Sub-section 1.3 except as stated
2 All buildings, equipment and utilities provided by
below. All other work is considered to be subsidiary to
the Contractor shall remain the property of the
other sections and the costs are deemed to be included
Contractor and will be returned to him on completion or
in the prices for other items stated in the Bill of
when no longer required, unless stated otherwise in the
Quantities.
Special Specifications.
2 If the Engineer specifically orders that a sub-surface
soil investigation shall be done by the Contractor,
1.5.2 Site Facilities for the
payment will be made at the rate stated in the Bill of
Quantities for the complete work, including provision of Engineer/Employer:
all equipment, performance of tests and provision of a 1 The Contractor shall provide service and maintain,
report. and remove when instructed, the offices, other
accommodation, services, surveying equipment and

♦ 1-3 ♦
copy 249
laboratory facilities for the use of the Engineer and 1.5.3 Computers for the Engineer
Employer as described below and in the Special
Specification. 1 The Contractor shall provide for the exclusive use
of the Engineer's staff, new PC equipment, original
2 Offices shall be of proprietary manufacture, of
licenses and peripheral hardware together with latest
insulated and weather tight construction, with lockable
versions of all associated Microsoft software (Excel,
entrances and operable windows, hard-wearing easy-
Word, PowerPoint and AutoCAD) Primavera and
clean surfaces and robust and secure fittings:
Antivirus programs with required regular updates and
- Incorporate sanitary facilities to the extent user licenses for software and accessories, necessary
required for the number and gender of cabling and workstation desks, all as detailed in the
personnel to be accommodated. Special Specification.
- Support on suitable foundations. 2 The Contractor shall service and maintain computer
3 The Contractor shall provide and maintain all equipment regularly and provide all associated
necessary services for the offices and facilities, including consumables, stationery and paper supplies as and
but not necessarily limited to the following: when requested.
- Heating and air-conditioning.
- Electric lighting and power. 1.5.4 Telephones for the Engineer /
- Water supply.
Employer
- Potable water supply. 1 The Contractor shall provide and maintain for the
- Drainage system. exclusive use of the Engineer's and/or Employer's staff,
appropriate and adequate telephone/fax facilities and
- Fire fighting appliances.
services as detailed in the Special Specification, for the
- Cleaning facilities and services and general duration of the project.
attendance.
2 The Contractor shall pay for all connection, service
- Telephone. and user charges and costs arising in connection with
- Computers the provision of telephone/fax facilities for the Engineer,
including the cost of all local calls.
- Camera
3 The telephone/fax service shall provide a separate
- Thermometers
exclusive connection ensuring privacy of conversation
- Colored Photocopiers. for the Engineer.
- Fax machines.
4 The Contractor shall provide new furniture and 1.5.5 Car Port for the Engineer
equipment suitable for the intended user.
1 The Contractor shall provide a car port shade structure
5 All office accommodation and facilities, services
adjacent to the Engineer's offices, sufficiently sized and
and equipment shall be continuously available to the
arranged to accommodate a minimum of 10 vehicles
Engineer in full working order within four weeks of the
unless stated otherwise in the Special Specifications.
start of the mobilization period unless otherwise stated
The Contractor shall provide appropriate hard standing
in the Special Specifications, and before any permanent
and adjoining walkways, and submit detailed proposals
construction operations are commenced. However, the
to the Engineer and obtain approval prior to fabrication
Engineer may permit work to commence before the full
and erection.
facilities are available if adequate facilities are provided
by the Contractor. If the Contractor fails to provide the
required facilities he shall bear the cost of alternative
1.5.6 Cameras for the Engineer
arrangements made by the Engineer. 1 The Contractor shall provide for the exclusive use
6 Maintenance of the offices shall include supplies of of the Engineer's staff new cameras as detailed in the
pencils, pens, drawing paper, other stationery, survey Special Specification, each equipped with the following
pegs, brushes, paint and similar consumable materials, features:
as required by the Engineer. - Digital camera minimum 8 mega pixels
7 The Contractor shall submit fully detailed proposals - Auto focus (Not fixed) lens
for all facilities to the Engineer and obtain approval prior
- Self wind and rewind
to hire or purchase and delivery to the Site.
- Built-in flash.
8 The Contractor shall service and maintain and clean
the Engineer’s offices on a daily basis; provide all 2 The Contractor shall submit a proposal for approval
consumables and supplies as and when requested, prior to purchase.
including drinking water, gas and stocks for making tea
and coffee beverages.

♦ 1-4 ♦
copy 249
1.5.7 Thermometers 1.5.12 Measurement and Basis of Payment
1 The following shall be provided on Site: 1 Provision of the Engineer’s office and other,
- Maximum and minimum thermometer for accommodation, furnished and equipped as specified,
measurement of atmospheric temperature. and provision of laboratory fully furnished and
operational as specified, shall each be measured and
- Thermometer/s for measurement of concrete,
paid for at the monthly rate per building stated in the Bill
asphalt and ground temperature.
of Quantities.
2 Maintenance of the Engineer’s office, other
1.5.8 Test Equipment accommodation, equipment and provision of the
1 The Contractor shall make available to the Engineer required services shall be measured and paid for
all test equipment required for carrying out tests on monthly during the period which the facilities are
materials, Plant or finished work required by the available in full working order.
Specification. 3 No payment for maintenance of the Engineer’s
office and accommodation will be made for any period
1.5.9 Inspection Facilities of delay beyond the Time for Completion or extended
Time for Completion if relevant.
1 The Contractor shall provide all ladders, access
4 Maintenance of the site laboratory and mobile site
lighting, facilities, etc. and such other assistance as the
laboratory shall be measured and paid for monthly and
Engineer may require enabling full access to inspect any
shall include for chemicals and other consumables. No
part of the works in a safe manner.
payment will be made for any period of delay beyond
the end of the Time for Completion or extended Time for
1.5.10 Surveying Equipment for Engineer Completion if relevant.
1 The Contractor shall supply and maintain a 5 If the Specification does not call for provision of a
separate set of surveying equipment and accessories in site laboratory, no separate payment will be made for
full working order for the sole use of the Engineer, and samples and tests on materials, the cost of which will be
shall replace any equipment and accessories whenever deemed to be included in the rates for the relevant items
directed by the Engineer during the progress of the work, in the Bill of Quantities.
as detailed in the Special Specification. 6 Provision and maintenance of surveying equipment
for the Engineer is measured as a monthly item for the
1.5.11 Laboratory whole period of the Contract.
7 No separate measurement or payment will be
1 The Contractor shall provide, furnish, equip,
made, for any other items in this Sub-section, including
maintain, staff and clear away on completion materials
computers, telephones, digital camera, thermometers,
testing laboratories in approved locations, manned by
test equipment, fax machine and colored photocopier,
suitably qualified personnel as detailed in the Special
inspection facilities and car port, all of which costs are
Specification, and shall carry out all site testing required
deemed to be included in the rates for other items stated
under the Specification or as directed by the Engineer.
in the Bill of Quantities.
2 The Contractor shall provide skilled technicians and
unskilled laborers of the types and numbers stated in the
Special Specifications. Personnel once assigned to the
1.5.13 Items in the Bill of Quantities
laboratory shall not be removed except at the direction, i Provision of Engineer’s office
or with the approval, of the Engineer. (type) (nr of units) (nr of months)
3 The laboratory shall be an approved weather tight ii Maintenance of Engineer’s office
air conditioned movable or stationary building or trailer (type) (nr of units) (nr of months)
as required by the Contract and shall be located on Site
iii Provision of surveying equipment
as agreed with the Engineer.
(type) (nr of units) (nr of months)
4 The Contractor shall provide and maintain the
laboratory equipment, apparatus and consumable iv Maintenance of surveying equipment (type)
supplies, including stationery and test forms, needed for (nr of units) (nr of months)
execution of all standard tests required by the Contract. v Provision of Engineer’s accommodation
The Contractor shall submit to the Engineer for his (type) (nr of units) (nr of months)
approval within 15 days of the start of mobilization a vi Maintenance of Engineer’s accommodation
complete listing of the equipment, apparatus and (type) (nr of units) (nr of months)
supplies. The list shall include names of the
vii Provision of laboratory
manufactures, and descriptive literature shall be
(type) (nr of months)
attached as necessary or appropriate.

♦ 1-5 ♦
copy 249
viii Maintenance of laboratory delineators, signal lights, traffic barricades and other
(type) (nr of months) facilities necessary for safe and efficient directing and
handling of traffic on or around the work site by
1.6 Control of Site diversions. Adequate safety zones and protective
barriers shall be provided around working areas.
1.6.1 Keeping Site Clear of Water 2 The Contractor shall draw up his proposals for
protection of traffic based on the provisions described in
1 The Contractor shall take all measures to keep the the Special Specification and after coordination with and
Site free from standing, flowing or tidal water, including approval of the Royal Oman Police and other Concerned
temporary drainage, pumping and dewatering if Authorities. The Contractor shall submit the proposals
necessary. with drawings and programs to the Engineer for his prior
approval.
1.6.2 Site Cleaning 3 Movement of equipment from the one part of the
Site to another along routes being used by the public
1.6.2.1 Site Cleaning During Progress of Works
(whether public highway or diversions provided by the
1 All parts of the Site, and adjacent roads affected by Contractor) shall be in accordance with the Traffic
the Works, shall be maintained in a clean and tidy Regulations. Material falling on the road as a result of
condition throughout the Works. All waste and surplus operations shall be removed immediately.
materials and other rubbish resulting from the Works or 4 The Contractor shall provide flagmen with the sole
otherwise, shall be cleared away at intervals as directed duty of directing public traffic through or around the Site.
by the Engineer.
5 Sign faces for temporary signs shall comply with
2 If the Contractor fails to remove any surplus or the Highway Design Standards.
waste materials from the Site within 3 days after being
instructed to do so by the Engineer, these materials may
1.7.2 Maintenance of One-Way Traffic
be removed by others at the Contractor's expense.
1 Whenever it becomes necessary to operate one-way
1.6.2.2 Final Clean Up on Completion
traffic along a section of road the Contractor shall
1 The entire Site shall be delivered up on completion provide a single-lane of not less than 3.5m wide and
of the Works, in a clean, neat and presentable new keep it permanently open for traffic. The length of any
condition, all as specified hereunder and as described in single-lane working shall not exceed 500m. If
the General Conditions of Contract. construction is going on at more than one adjacent
section, the Contractor shall organize the work in a way
2 Spoil tips, borrow pits and deposited materials
that results in the minimum amount of obstruction and
shall be trimmed and regularized to profiles and levels
delay to traffic. No two single lane working sections shall
as directed. Flow of water courses affected by the tips or
be closer than 1km.
pits shall be maintained without interruption and any
agreement concerning these sites, existing between the
Employer and the persons or authorities concerned, 1.7.3 Temporary Structures
shall be observed. Temporary traffic bearing structures shall be capable of
3 Temporary markings, coverings and protection carrying the same live loads as permanent structures.
shall be removed unless otherwise instructed by the
Engineer. 1.7.4 Haul Routes for Heavy Vehicles

1.6.3 Measurement and Basis of Payment 1 The Contractor shall prepare proposals for routes
to be used by heavy vehicles particularly for hauling fill
1 No separate measurement or payment will be materials. Routes shall where possible, avoid existing
made, for any part of Sub-section 1.6, all of which work roads and built-up areas. Signs shall be provided and
is considered to be subsidiary to other sections. The maintained to direct construction traffic to and from haul
costs are deemed to be included in the prices for other routes. Details of haul routes and signage shall be
items stated in the Bill of Quantities submitted to the Engineer for approval within a period
not exceeding one month prior to the commencement of
1.7 Control of Traffic and Access work in the relevant area and the signs shall be erected
prior to actual commencement of the work.
1.7.1 Maintenance and Protection of 2 Haul routes shall operate using one-way or two-
Traffic way traffic systems as required by the Engineer. If at
any time the Engineer considers that any section of the
1 In order to facilitate movement of traffic safely route needs repair work, the Engineer may withdraw his
through and around the construction area, the approval until the Contractor has executed the necessary
Contractor shall supply, erect and maintain signs, repairs to the Engineer's satisfaction.

♦ 1-6 ♦
copy 249
3 If and where it is necessary for Contractor's plant or If, in the opinion of the Engineer, modification of the
vehicles to cross public highways and where required by lines or grade is required, before or after survey, the
the Engineer, all such crossings shall be equipped with Engineer will issue detailed instructions to the
manually controlled traffic lights. During extended Contractor who shall revise the setting out accordingly.
periods when the Contractor's plant is not using the 4 Setting out utility works shall be as shown on the
crossing, the traffic signals shall be switched off and the Drawings or as instructed on Site. Stake-out shall be
advance warning signs obscured. revised if, in the opinion of the Engineer, modifications
4 Stationary vehicles, equipment, huts, stockpiles of of line or grade are required.
materials, etc., shall be kept well clear of crossing points 5 The Contractor shall be responsible for preserving
so that persons using the highway and the haul road all existing stakes, marks and monuments and if any
shall have adequate sight distance at all times. construction stakes or marks are destroyed or disturbed,
the Contractor shall replace them at his own expense.
1.7.5 Measurement and Basis of Payment 6 The Contractor shall record details of all grid lines,
1 Maintenance and protection of traffic is measured existing ground levels, setting-out stations, bench marks
as a monthly item which is deemed to cover for all costs and profiles on the site setting-out drawing. This
of this Sub-section 1.7 and to be full compensation for all drawing shall be retained on the Site throughout the
labor, materials and equipment and any other costs, duration of the Contract and handed over to the
including laying and removal of road material, unless Engineer upon completion of the Works.
stated otherwise. 7 All dimensions and levels on the Drawings and the
2 Where diversions are required by the Engineer (or Site, shall be checked particularly the correlation
by the Royal Oman Police through the Engineer) to be between components and the work in place. Materials
surfaced with bituminous materials, the bituminous and components shall not be ordered, or work carried
surfacing, the sub-base shall be paid per cubic meters out, until discrepancies have been resolved with the
(cu.m), and the prime coat will be paid by square meter Engineer.
applied (sq.m).
1.8.2 Surveying Equipment and
1.7.6 Items in the Bill of Quantities Accessories
i. Maintenance and protection 1 The Contractor shall provide sufficient and suitable
of traffic (months) surveying instruments and other equipment and
ii. Supply and compacting of accessories for his own use in setting out and leveling of
sub-base on diversions where the Works, and also to enable the Engineer to check the
ordered by the Engineer (cu.m). setting out.
iii. Supply and compacting of 2 The accuracy of survey equipment and accessories
bituminous base course on may be verified at any time by the Engineer and any
diversions where ordered by unsatisfactory equipments/instruments shall be
the Engineer (cu.m). promptly calibrated or removed and replaced by the
iv. Prime coat (rate of application) (sq.m) Contractor at its own expense.

1.8 Control of Works 1.8.3 Existing Underground Services and


Obstructions
1.8.1 Setting out of Works
1.8.3.1 Notices to Concerned Authorities
1 The Contractor shall, prior to any setting out,
submit a planned method of operations for setting out 1 Before any clearing and excavation is started, the
the Works to the Engineer for his approval. The plan Contractor shall issue suitable written notice of his
shall include the accuracy, positions of the various types intentions and work programs to all relevant authorities
of stakes, method of marking stakes, and methods to be and public bodies and in return shall obtain a permit of
used for protecting stakes, etc. No survey work shall no-objection. The respondents shall be requested to
proceed without to the Engineer's approval of the indicate on the working drawings provided by the
Contractor's plan. Contractor the position of any underground services in
2 The Contractor shall give written notice to the which they have an interest.
Engineer at least 24 hours before he intends to survey
1.8.3.2 Categories of Obstructions
and set out any portion of the Works. Such notice shall
include the time, location and type of work to be set out. Obstructions shall be classified as follows:
3 The Contractor shall set out the Works, inform the - Existing private and public owned utilities, above
Engineer when setting out is complete and obtain and below ground, which are required to be
Engineer's approval before proceeding with construction. protected, adjusted, relocated or removed.

♦ 1-7 ♦
copy 249
- Obstacles, above and below ground (other than execution of work pertaining to all utility adjustments,
utilities), which are required to be taken down, relocations and removals. The Contractor shall schedule
dismantled, demolished or excavated, relocated construction activities so as to avoid or minimize any
and removed, as appropriate. potential delays, inconvenience or damage to the Works
that may result from utility interference or the operations
1.8.3.3 Existing Utilities of adjustment, relocations and removals.

1 Utilities shall include, but are not be limited to, 6 The Contractor shall be responsible for safeguarding
existing water lines, gas lines, telephone lines, falaj, fiber and protecting all utilities and appurtenances
optics, wire lines, service connections, water and gas encountered during the Works. The Contractor shall be
and oil meters and valve boxes, light poles and masts, responsible for the costs of making good any damage
pylons, cableways, signals, and all utility appurtenances arising out of its own negligence.
within the limits of the proposed construction.
2 The costs of all work concerning verification and 1.8.4 Measurement and Basis of Payment
identification of existing utilities, including excavating 1 No separate measurement or payment will be made,
any trial pits, detection means, mapping detailing of for any part of Sub-section 1.8, which work is considered
drawings and co-ordination with respective authorities to be subsidiary to other sections. The costs are deemed
shall be fully borne by the Contractor to be included in the prices for other items stated in the
3 Utility diversions may be specified or directed by Bill of Quantities.
the Engineer to be carried out by the Contractor, or
alternatively the Employer may make arrangements for 1.9 General and Contractual
such works to be executed by other parties. Obligations
4 The Contractor shall:
i. Take into account that the diversion work 1.9.1 Health, Safety and Environmental
shall be carried out to the requirements and Program
approval of the utility authorities and/or
1 In addition to the requirements of the provisions of
under their supervision, and also, where
the General Conditions of Contract and other contract
required by the utility authorities, specialist
requirements, the Contractor shall provide the Engineer
diversion works shall be carried out by
the necessary safety personal protective equipment
accredited specialist contractors.
(PPE) in compliance with international standards
ii. Verify and identify the existing utilities by including but not limited to safety shoes, reflective vests,
excavating trial pits and other measures helmets, and safety harnesses, etc…, and shall submit
including detection means and shall liaise for the Engineer's approval, within 15 days after the
with the relevant authorities and map these effective date of the notice to proceed for the Works, a
utilities and prepare detailed and accurate proposed Safety Program covering the matters
existing utilities drawings, identifying the described below:
utilities that are in service and those that are
dead or abandoned. Submit these existing 1.9.1.1 Health, Safety and Environmental Plan
utilities drawings, which shall be accurate
1 The Health, Safety and Environmental Plan shall
and detailed, giving location of utilities in
contain but not be limited to the following:
plan and section, with all pertinent data of the
respective utility, to the Engineer and to the i. Safety Policy and Strategy.
utility authority.
ii. Statutory and Contractual Framework for
iii. Work out and develop, in coordination with Safety.
the utility authority and the Engineer, the
iii. Management Safety Responsibilities.
approved utilities diversion schemes that will
be required to enable the execution of the iv. Safety Training and awareness.
work and also maintain continued operation v. Safety Reviews.
of utilities services in the area for the users. vi. Safety Method Statements.
iv. Provide superintendence for the execution of vii. Reporting and Investigation.
the utility diversions whether they are carried
viii. Contingency Arrangements.
out by the Contractor directly or by other
parties employed by the contractor. ix. Safety Inspections and Audits.

v. Provide accurate As-Built Drawings of all x. Accident Procedures.


permanent utility diversions that are xi. Site cleanliness and removal of rubbish.
executed under the Contract. xii. Labor messing facilities.
5 The Contractor shall take into account, in his xiii. Monthly Report.
Program of Work, the time effort involved in the

♦ 1-8 ♦
copy 249
xiv. Compliance with current applicable national explosives and detonators are kept in proper and safe
and local environmental legislation and condition.
contractual environmental obligations. 4 Explosives and detonators shall always be
2 The Contractor shall take into account that the transported in separate special vehicles and kept apart
works under this Contract may be undertaken until the last possible moment. Metallic tools shall not
simultaneously with other contracts. The Contractor is to be used to open boxes of explosives.
coordinate safety procedures with the Engineer and
1.9.2.2 Blasting Procedures
Safety Representatives from other contractors to
implement and maintain a common safety strategy. 1 Ensure that blasting is only carried out by
3 If in the opinion of the Engineer there is an experienced personnel. Priming, charging, stemming
infringement or breach in the approved Health and and shot firing shall be carried out with greatest regard
Safety Plan, the Engineer reserves the right to instruct for safety and in strict accordance with the rules and
the Contractor to undertake immediate corrective action regulations of the concerned authorities. Adequate
without any liability for any additional costs or time warning of blasting shall always be given and all
implication incurred by the Contractor in undertaking the persons confirmed as clear from the area before blasting
corrective action. takes place.

4 Upon the Engineer's approval of the Safety 2 Ensure that police and other concerned authorities
Program the Contractor shall, for the full term of the are kept fully informed of the blasting program so that
Contract, operate the Safety Program, maintain accurate they may be present when blasting takes place if they so
records of safety activities and accident, and submit require.
safety and accident reports to the Engineer on the 3 Ensure that explosive charges are not excessive,
approved forms. charged boreholes are properly protected, and proper
precautions are taken for the safety of persons and
1.9.1.2 Health, Safety and Environmental property.
Representatives:
4 The Contractor shall prepare a survey report for the
1 The Contractor shall include within the Health, surroundings evident with photos for status before and
Safety and Environmental Plan the name of the after blasting.
company’s qualified Safety Officer. He shall also submit
1.9.2.3 Explosives Inventory
the name and qualification of a Health, Safety and
Environment representative on site, responsible for the 1 The Contractor shall maintain an up-to-date
implementation of the Health, Safety and Environmental inventory of all explosives and explosive devices and
Plan on site. This site representative shall remain on site shall submit a monthly report to the Engineer, detailing
during operational working hours and shall coordinate the use of all explosives by date and location.
with the safety representatives of other package
Contractors. 1.9.3 Fire Precautions
2 Appointment of the site Health, Safety and
1 The Contractor shall take all necessary measures to
Environment Manager will be subject to the Engineer’s
prevent personal injury or death or damage to the Works
approval.
or other property from fire. Fire fighting arrangements
shall be made as required by the concerned authorities.
1.9.2 Use of Explosives
2 Adequate and fully operational firefighting
1.9.2.1 Control Measures equipment shall be furnished and maintained by the
Contractor in all vulnerable areas and as instructed by
1 The Contractor shall not use explosives without the the Engineer. Workmen shall be trained in the operation
express permission from the Engineer and controlling of such equipment and provision of fire fighting facilities
authority. The Contractor shall abide by all rules and
3 Adequate water for firefighting shall be available
regulations of the concerned authorities regarding
and outlets located so as to be readily accessible.
purchasing, transportation, storing, handling and using
the explosive materials. 4 All equipment shall be regularly tested and
properly maintained.
2 Explosives and detonators shall be stored in special
buildings as approved by the concerned authorities.
These secured buildings shall be located and clearly 1.9.4 Measurement and Basis of Payment
marked in English and Arabic "DANGER - EXPLOSIVES"
1 No separate measurement or payment will be
as approved by the Concerned Authorities. Explosives
made, for any part of Sub-section 1.9, which work is
and detonators shall be stored in separate buildings.
considered to be subsidiary to other sections. The costs
3 All possible precautions shall be taken against are deemed to be included in the prices for other items
accidental fire or explosion, and to ensure that the stated in the Bill of Quantities.

♦ 1-9 ♦
copy 249
1.10 Management Procedures xi. Activities for Temporary Works to be
supplied and constructed and the dates for
1.10.1 Commencement, Program and supply, construction and removal
Progress xii. Dates for submission by the Contractor of
shop drawings/working drawings, samples
1 Commencement: After receipt of the Order to and the like and dates for approval by the
Commence, the Contractor shall inform the Engineer's Engineer, in accordance with Conditions of
Representative, at least 7 days in advance, of the Contract.
proposed date for commencing work on Site.
xiii. Dates for submission of the cross-sections.
2 Co-ordination: The Contractor shall co-ordinate the
xiv. Dates and times for work to be performed by
construction activities to assure efficient and orderly
other Contractors or for materials and plant
installation of each part of the Works. The Contractor
to be supplied by the Employer
shall co-ordinate construction operations included under
differing sections of the Specifications that are xv. Duration and earliest/latest dates for testing
dependent upon each other for proper execution. and commissioning plant and engineering
installations.
i. Where installation of one part of the work is
dependent on the installation of other xvi. Bar chart showing earliest dates and total
components, either before or after its own float of activities.
installation, schedule construction activities 4 Guidance: The Contractor shall abide by the
in the sequence required to obtain the best following:
results. i. The Engineer will guide the Contractor in the
ii. Where availability of space is limited or determination of the level of detail to
restricted by access or security, co-ordinate included in the CPN
installation of the different components to ii. Construction activities will not be scheduled
assure maximum accessibility at desired to exceed twenty-five (25) consecutive
times for required maintenance service and working days without the approval of the
repair. Engineer
iii. Make adequate provisions to accommodate iii. One day will be the smallest time unit used
items scheduled for later installation.
5 Hardware: The computer hardware shall be PC
3 Program: Unless stated in the Special Specification compatible.
that the Contractor may submit a program in bar chart
6 Computer Software: Project management software
form only, the Contractor shall provide for the Engineer's
shall be of the professional high-end type (i.e.
review in accordance with Conditions of Contract, a
"Primavera" project management software latest version
computer-based program in critical path network (CPN)
or of similar capabilities).
form, showing at least the following information:
7 Resource Schedules: The computer program used
i. Contract milestones (Engineer's Notice to
for preparing the program shall also be used for
Commence, Commencement Date, date for
preparation of resource schedules to be submitted to the
completion of Sections of the Works, date for
Engineer with the program. The resource schedules
completion of the whole of the Works, etc.)
shall show at least the following information:
ii. Duration of each construction activity in
i. Quantity of materials to be used for each
working days
activity
iii. Earliest/latest start and completion dates for
ii. Numbers and classes of workmen to be
each construction activity
employed on the Site for each activity
iv. Free float time for each activity
iii. Numbers and classes of equipment to be
v. Total float time for each activity used for each activity
vi. Cost of each activity as Contract rates iv. Histogram for workmen by class and overall
vii. Duration and earliest/latest dates for classes
procurement of materials and plant v. Histogram for equipment by class and overall
viii. Duration and earliest/latest dates for activities classes.
to be performed by Subcontractors 8 Cash Flow Estimate: The computer program used
ix. Number of working days per week for preparing the program shall also be used to prepare
x. Number of working shifts per day for each the cash flow estimate to be submitted by the Contractor.
construction activity 9 Monitoring: The Contractor shall monitor progress
of the Works and the supply of resources and cash flow
compared with the program, schedules and estimate,
update the program with actual progress data monthly

♦ 1-10 ♦
copy 249
and shall revise the program, schedules and estimate as 3 Co-ordination of Trades and Subcontractors: The
required by Conditions of Contract. Copies of revised Contractor shall co-ordinate the work of all trades and
program etc. and notices of actual and forecast delays Subcontractors so as to avoid delay and disruption or
and shortfalls shall be promptly given to the Engineer. abortive work. The Contractor shall provide all drawings,
10 Computer Program: The Contractor shall provide dimensions and other information required for the
the Engineer with a copy of the computer diskette of the proper execution of subcontract works and of associated
target program, updated and new target program, builder's work and accept responsibility for the accuracy
schedules and estimates. and fitness of subcontract works.
4 Quality Control: The Contractor shall prepare and
1.10.2 Records and Measurements submit for approval by the Engineer a proposal for the
quality control management of the project. This proposal
1 Labor Record: The Contractor shall provide each shall incorporate the requirements set out in B.S.5750 or
week a record showing the number and description of its equivalent and shall be incorporated into the
workmen employed each day on the Works including Procedures Manual and will form an integral part of the
those employed by Subcontractors. Contractor’s management procedures for the project.
2 Materials and Plant Record: The Contractor shall This proposal shall include, but not be restricted to:
provide each week a record showing the quantity and i. Provision and maintenance of a quality
description of all materials and plant delivered to the control program throughout the project,
Site complete with copies of delivery notes.
ii. Inspection and testing of products, both on
3 Equipment Record: The Contractor shall provide and off Site, by independent professional
each week a record showing the number, type and inspection and testing companies,
capacity of all Contractor's Equipment, excluding hand
iii. Provision of inspection and testing
tools, daily employed on the Works.
equipment,
4 Daily Work Record: The Contractor shall provide
iv. Verification of affidavits and certificates that
each day a record showing activities performed and
selected material meets the specified
locations in which work has been carried out and any
standards,
other matter requested by the Engineer's Representative.
v. Maintenance of quality control
5 Monthly Report: The Contractor shall provide
documentation in accordance with the
monthly reports which summarize the daily and weekly
various procedures identified in these
reports and deliver to the Engineer's Representative not
documents.
later than one week following the end of each month.
5 Procedures Manual: The Contractor shall prepare and
6 Wages Books and Time Sheets: The Contractor
agree with the Engineer a Procedures Manual for the
shall keep accurate and proper wage books and time
administration of the Project.
sheets showing wages paid to and time worked by
workmen and, when required, produce such wage books
and time sheets for inspection by the Engineer's 1.10.4 Progress Photographs/ Videos
Representative. Separate records should be kept of 1 The Contractor shall submit each month progress
Omani and expatriate staff. photographs of at least five different subjects taken from
7 Climatic Conditions: The Contractor shall measure approved locations agreed by the Engineer. A minimum
and keep an accurate daily record of and submit to the of twenty photographs shall be taken each month and
Engineer's Representative at the end of each week: five (5) colored gloss prints of each provided to the
i. Air temperatures: maximum and minimum Engineer.

ii. Humidity 2 Format: 200 x 250-mm smooth-surface color prints


on single-weight commercial-grade stock, enclosed
iii. Rainfall: total in mm and hours.
back- to-back in clear plastic sleeves that are punched for
standard ring binding.
1.10.3 Project Administration
3 Identification: On back of each print, provide an
1 Engineer’s Site Meetings: The Engineer's applied label or rubber-stamped impression with the
Representative will hold site meetings once a month or following information:
more frequently if he deems necessary for the efficient i. Name of Project.
management of the Works and he will distribute minutes.
ii. Name of Employer.
The Contractor shall attend all such meetings and secure
the attendance of Subcontractors and others if requested iii. Name of Engineer.
by the Engineer's Representative. iv. Name of Contractor.
2 Contractor’s Site Meetings: The Contractor shall hold v. Date photograph was taken.
such meetings as are necessary for co-ordination of vi. Description of vantage point, indicating
work and Subcontractors and review of progress. location, direction (by compass point), and

♦ 1-11 ♦
copy 249
elevation or area of construction, as ii. Concurrent Review: Where concurrent
applicable. review of submittals by sub-consultants, the
4 Digital Images: Submit a complete set of Employer, or other parties is required, allow a
corresponding digital image electronic files with each maximum of thirty five (35) days for initial
submittal of prints. Identify electronic media with date review of each submittal of cross sections or
photographs were taken. as-built drawings, and fourteen (14) days for
all other submissions including shop
Digital image files shall be for the Engineer's and
drawings or working drawings.
Employer's free and unrestricted use.
iii. If intermediate submittal is necessary,
5 The Contractor shall, if requested by the Engineer,
process it in the same manner as the initial
submit progress videos as required.
submittal.
iv. Allow Fourteen (14) days for processing each
1.10.5 Measurement and Basis of Payment
re-submittal.
1 No separate measurement or payment will be 3 Identification: Place a permanent label or title block
made, for any part of Sub-section 1.10 except for the on each submittal for identification.
progress photographs and videos. All other activities
i. Indicate name of firm or entity that prepared
and submittals are considered to be subsidiary to other
each submittal on label or title block.
sections and the costs are deemed to be included in the
unit rates for other items stated in the Bill of Quantities. ii. Provide a space approximately 100 x 125 mm
on label or beside title block to record the
2 Progress Photographs will be measured and paid
Contractor's review and approval markings
as an item at each month of the construction period at
and action taken by the Engineer.
the unit rate in the Bill of Quantities
iii. Include the following information on label for
3 Videos will be measured and paid as an item at
processing and recording action taken:
each month of the construction period at the rate in the
Bill of Quantities a. Contract name.
b. The Employer's name.
1.10.6 Items in the Bill of Quantities c. Date.

i. Provision of 5 sets of photos (month) d. Name and address of the Engineer.

ii. Provision of 2 sets of videos (type) (month) e. Name and address of the Contractor.
f. Name and address of subcontractor.
1.11 Submittals g. Name and address of supplier.
h. Name and address of manufacturer.
1.11.1 General i. Unique identifier, including revision
1 Submittals Schedule: Submit list of submittals and number.
time requirements for scheduled performance of related j. Number and title of appropriate
construction activities. Submittals shall include: shop/ Specification Section.
working drawings, as-built drawings, cross sections, k. Drawing number and detail references,
materials, testing, method statements and any other as appropriate.
required submittal in compliance with the Specifications
l. Other necessary identification.
and other Contract Documents.
4 Deviations: Highlight, encircle, or otherwise
2 Processing Time: Allow enough time for submittal
indicate and identify on submittals, deviations from the
review, including time for re-submittals, as follows.
Contract Documents.
Time for review shall commence on the Engineer's
receipt of submittal. 5 Additional Copies: Unless additional copies are
required for final submittal, and unless the Engineer
i. Initial Review: Allow a maximum of twenty
observes non-compliance with provisions of the Contract
one (21) days for initial review of each
Documents, initial submittal may serve as final submittal.
submittal of cross sections or as-built
drawings, and seven (7) days for all other i. For submittals requiring concurrent review,
submissions including shop drawings or submit one extra copy in addition to specified
working drawings. Allow additional time if number of copies to the Engineer.
processing must be delayed to permit 6 Transmittal: Package each submittal individually
coordination with subsequent submittals. and appropriately for transmittal and handling. Transmit
The Engineer will advise the Contractor when each submittal using a transmittal form attached to a
a submittal being processed must be delayed cover letter. The Engineer will discard, without review,
for coordination. submittals received from sources other than the
Contractor.

♦ 1-12 ♦
copy 249
i. Cover Letter: On attached, numbered, b. Final Submittal: Submit four (4) copies,
separate sheet(s), prepared on the unless otherwise indicated. Submit
Contractor's letterhead, record relevant additional copies where copies are
information, requests for data, revisions required for operation and maintenance
other than those requested by the Engineer manuals. The Engineer will retain two
on previous submittals, and deviations from copies; remainder will be returned.
requirements of the Contract Documents, Mark up and retain one returned copy
including minor variations and limitations. as a Record (As-Built) Document.
Include the same label information as the 2 Shop and Work Drawings: Produce newly prepared,
related submittal. contract-specific, information, drawn accurately to scale.
a. Include the Contractor's certification Shop drawings should not be based on reproductions of
stating that information submitted the Contract Documents or standard printed data.
complies with requirements of the i. Preparation: Include the following
Contract Documents. information, as applicable:
ii. Transmittal Form: Use a form acceptable to a. Dimensions; in SI units unless
and approved by the Engineer. Provide otherwise indicated or directed.
locations on form for the following
b. Roughing-in and setting diagrams.
information:
c. Schedules.
a. Contract name.
d. Compliance with specified standards.
b. The Employer's name.
e. Notation of coordination requirements.
c. Date.
f. Notation of dimensions established by
d. Destination (To :).
field measurement.
e. Source (From :).
ii. Sheet Size: Except for templates, patterns,
f. Names of subcontractor, manufacturer, and similar full-size drawings, submit shop
and supplier, as applicable. drawings on sheets at least A4 size, and no
g. Category and type of submittal. larger than A1 size, unless otherwise
h. Submittal purpose and description. approved.

i. Submittal and transmittal distribution iii. Number of Copies: Submit copies of each
record. submittal, as follows:

j. Remarks. a. Initial Submittal: Submit one (1)


correctable, translucent, reproducible
k. Signature of transmitter.
print and one (1) blue- or black-line
I. Distribution: Furnish copies of final print. The Engineer will return the
submittals to manufacturers, reproducible print.
subcontractors, suppliers, fabricators,
b. Final Submittal: Submit three (3) blue-
and installers, authorities having
or black-line prints, with one (1)
jurisdiction, and others as necessary for
separate electronic file, format of which
performance of construction activities.
will be advised by the Engineer, unless
Show distribution on transmittal forms.
otherwise indicated. Submit additional
7 Use for Construction: Permit only final submittals prints where prints are required for
with appropriate approved stamp, or other mark operation and maintenance manuals.
indicating action taken by the Engineer, to be used in The Engineer will retain two (2) prints;
connection with construction. remainder will be returned. Mark up
and retain one returned print as a
1.11.2 Action Submittals Record (As-Built) Drawing with two (2)
electronic files on CD-Rom.
1 General: Prepare and submit action submittals
required by individual Specification Sections. 3 Subcontract List: Prepare and submit a list
identifying subcontractor individuals or firms proposed
i. Number of Copies: Submit copies of each
for principal portions of the Works, including those who
submittal, as follows, unless otherwise
are to fabricate products or equipment to a special
indicated:
design. Include the following information in tabular
a. Initial Submittal: Submit a preliminary form:
single copy of each submittal where
i. Name, address, and telephone number of
selection of particular characteristics is
entity performing subcontract.
required. The Engineer will return
submittal with options selected. ii. Number and title of related Specification
Section(s) covered by subcontract.

♦ 1-13 ♦
copy 249
iii. Drawing number and detail references, as 1.11.4 Contractor's Review and Approval
appropriate, covered by subcontract.
1 Review each submittal and check for compliance
with the Contract Documents. Note corrections and field
1.11.3 Informational Submittals
dimensions. Mark with approval stamp before
1 General: Prepare and submit informational submitting to the Engineer.
submittals required by other Specification Sections. 2 Approval Stamp: Stamp each submittal with a
i. Number of Copies: Submit two copies of each uniform, approval stamp. Include Contract name and
submittal, unless otherwise indicated. The location, submittal number, Specification Section title
Engineer will not return copies. and number, name of reviewer, date of the Contractor's
ii. Certificates and Certifications: Provide a approval, and statement certifying that submittal has
notarized statement that includes signature of been reviewed, checked, coordinated and approved for
the Contractor, testing agency, or design compliance with the Contract Documents.
professional responsible for preparing
certification. Certificates and certifications 1.11.5 Engineer's Action
shall be signed by an officer or other
1 General: The Engineer will not review submittals
individual authorized to sign documents on
that do not bear the Contractor's approval stamp and
behalf of the company.
will return them without action.
2 Qualification Data: Prepare written information that
2 Engineer's Action: The Engineer's review is
demonstrates capabilities and experience of firm or
limited only to checking conformance with information
person. Include lists of completed projects with project
given and the design concept expressed in the Contract
names and addresses, names and addresses of
Documents. It is not conducted for the purpose of
engineers and employers, and other information
determining the accuracy and completeness of details,
specified.
dimensions or quantities, nor substantiating integrity or
3 Material Certificates: Prepare written statements compatibility, or confirming instructions for installation
on manufacturer's letterhead certifying that material or performance. The Engineer's approval does not in
complies with requirements. any way relieve the Contractor of responsibility for
4 Material Test Reports: Prepare reports written by a compliance with specified provisions and the Contract
qualified testing agency, on testing agency's standard Document requirements.
form, indicating and interpreting test results of material 3 Action Submittals: The Engineer will review each
for compliance with requirements. submittal, make marks to indicate corrections or
5 Preconstruction Test Reports: Prepare reports modifications required, and return it to the Contractor.
written by a qualified testing agency, on testing agency's The Engineer will stamp each submittal with an action
standard form, indicating and interpreting results of tests stamp and will mark stamp appropriately to indicate
performed before installation of product, for compliance action taken, as follows:
with performance requirements. i. Final Unrestricted Release: Where the
6 Compatibility Test Reports: Prepare reports written submittal is marked "APPROVED", the work
by a qualified testing agency, on testing agency's covered by the submittal may proceed
standard form, indicating and interpreting results of provided it complies with the Contract
compatibility tests performed before installation of Documents. Final acceptance of the work will
product. Include written recommendations for primers depend on that compliance.
and substrate preparation needed for adhesion. ii. Final-but-Restricted Release: Where the
7 Field Test Reports: Prepare reports written by a submittal is marked "APPROVED AS NOTED",
qualified testing agency, on testing agency's standard the work covered by the submittal may
form, indicating and interpreting results of field tests proceed provided it complies with both the
performed either during installation of product or after Engineer's notations and corrections on the
product is installed in its final location, for compliance submittal and the Contract Documents. Final
with requirements. acceptance of the work will depend on that
8 Product Test Reports: Prepare written reports compliance.
indicating current product produced by manufacturer iii. Returned for Re-submittal: Where the
complies with requirements. Base reports on evaluation submittal is marked "NOT APPROVED, REVISE
of tests performed by manufacturer and witnessed by a AND RESUBMIT", do not proceed with the
qualified testing agency, or on comprehensive tests work covered by the submittal, including
performed by a qualified testing agency. purchase, fabrication, delivery, or other
activity for the product submitted. Revise or
prepare a new submittal according to the
Engineer's notations and corrections.

♦ 1-14 ♦
copy 249
iv. Rejected: Where the submittal is marked 1.11.8 Items in the Bill of Quantities
"NOT APPROVED, RESUBMIT" or "REJECTED",
do not proceed with the work covered by the i. Provide as-built drawings, record
submittal. Prepare a new submittal for a drawings and record specifications and
product that complies with the Contract miscellaneous records as specified (Lump Sum)
Documents.
4 Submittals not required by the Contract Documents 1.12 Control of Materials and
will not be reviewed and may be discarded. Standards for Sampling and
Testing
1.11.6 Record (As-Built) Drawings
1.12.1 Storage of Materials
1 Within 1 month of completion of each section of
the Works, the Contractor shall submit 3 copies of the 1 Materials shall be so stored as to assure the
relevant drawings showing all details of permanent preservation of their quality and suitability for the Works.
works as constructed. The Engineer will approve these Stored materials, approved before storage, may again be
as ‘As-Built’ drawings or instruct corrections as inspected prior to their use in the Works. Stored
appropriate. materials shall be located so as to facilitate their prompt
2 Record Drawings: Submit copies of record inspection.
drawings as follows: 2 Where materials are stockpiled on Government or
i. Initial Submittal: Submit two sets of plots private property, such sites shall be abandoned
from record CAD drawing files and the immediately upon consumption of all stockpiled
original marked-up record prints. The materials and the natural surface shall be restored as far
Engineer will initial and date one set of plots as practicable to the original condition by the Contractor
and mark whether general scope of changes, and to the satisfaction of the Engineer.
additional information recorded, and quality
of drafting are acceptable. The Engineer will 1.12.2 Handling Materials
return one set of plots and record prints
together with review comments, for 1 All materials shall be handled in such manner as to
preserve their quality and suitability for the Works.
completing, printing, binding, and final
Aggregates shall be transported to the Works in vehicles
submittal.
which are constructed to prevent loss or undue
ii. Final Submittal: After incorporating the
segregation of materials after loading and unloading.
Engineer's initial submittal review comments,
submit original marked-up record prints set.
1.12.3 Materials Supplied by Employer
3 Submit sets of as-built drawings as follows:
One (1) set electronic format: (in CD-ROM) 1 The Contractor shall be responsible for all materials
furnished by the Employer and shall make good any
One (1) set of PDF format: (in CD-ROM)
shortages or deficiencies, from any cause whatsoever, or
One (1) bound sets of prints (A1 Size) any damage which may occur, after delivery of such
One (1) set of any other document/report about the materials.
project, Test results and any other
information/documents. 1.12.4 Local Material Sources
4 Record Specifications: Submit two (2) copies of
1 When material sources are not designated on the
record specifications, including addenda and contract
Drawings, or in other documents, the Contractor shall be
modifications.
responsible for locating and providing suitable materials
5 Miscellaneous Records: Submit two (2) sets of from approved sources.
original miscellaneous records.
2 Any information provided in the tender documents
about sources of local materials is considered as a
1.11.7 Measurement and Basis of Payment guideline only and does not relieve the Contractor of his
1 No separate measurement or payment will be responsibility in respect of investigation and supply of
made, for any part of Sub-section 1.11 except for As- suitable materials as specified.
Built Drawings. All other submittals are considered to be 3 Materials, regardless of their source, shall not be
subsidiary to other sections and the costs are deemed to incorporated in the Works until approved by the
be included in the rates for other items stated in the Bill Engineer.
of Quantities
2 The As-Built Drawings shall be measured and paid
as Lump Sum (L.S.) in the Bill of Quantities.

♦ 1-15 ♦
copy 249
1.12.5 Sources of Supply and Quality approved by the Engineer and engaged by the
Requirements Contractor.
2 After approval of any source of materials, the
1 All materials, including manufactured articles, and Contractor shall produce from such source only to the
machinery incorporated in the Works, shall meet all extent that materials produced are of substantially the
specified quality requirements and be approved by the same quality as the approved samples.
Engineer. Priority will be given to locally produced
3 The Engineer will periodically order retesting of
Omani material, where applicable.
previously approved sources to verify that they continue
2 The Contractor shall, before placing any purchase to conform to the Specifications and may order retesting
order for any materials intended for incorporation in the at the same or at a different laboratory from the one
Works, submit for approval a complete description of all performing the original source approval tests. If
such materials, names of the firms from whom he retesting indicates that a previously approved source no
proposes to purchase them and copies of all test reports longer conforms with the Specifications, the Contractor
verifying conformity with the provisions of the shall forthwith cease production from such source.
Specifications. Materials shall not be ordered without
the approval of the Engineer. When directed by the 1.12.7.3 Quality Control Tests
Engineer or otherwise specified, the Contractor shall
1 Quality control tests for materials shall be
submit suitable samples for approval.
performed by the Contractor prior to submitting any
3 The Engineer shall have the right to retest all
materials to the Engineer for approval. The Contractor
materials which have been tested and accepted at the shall submit details to the Engineer of his quality control
source of supply after delivery to the Site and prior to
testing program.
incorporation into the Works and to reject any such
2 The Engineer may declare the Contractor's quality
materials which are clearly defective or, when retested,
control testing program unacceptable if frequent
do not conform with the Specifications.
rejections of submitted materials occur when subjected
to the project control tests.
1.12.6 Certificates of Guarantee and
Production Plant Inspections 1.12.7.4 Control Tests

1 All shipments of materials shall be accompanied by 1 All control samples shall be taken jointly by the
a Manufacturer's Certificate of Guarantee or Test Engineer and the Contractor. Tests shall be performed
Certificate from an approved independent qualified in the site laboratory, or in situ as appropriate, under the
laboratory approved by the Engineer. All certified supervision of the Engineer.
materials delivered to the Site shall undergo additional 2 The Engineer may order retesting of any material if
laboratory testing if required by the Engineer. there has been a significant delay in the construction
2 Issuance of an invalid or erroneous Certificate of operations or if he determines that the material has
Guarantee shall be just cause for rejection of the deteriorated since its original acceptance. Material
materials without further testing. which does not conform to the Specifications will be
rejected and shall be removed from the Works and
1.12.7 Sampling and Testing Procedures replaced or corrected by the Contractor. The Engineer
may order additional testing to ascertain the extent of
1.12.7.1 Sampling unacceptable material.

1 Samples of all materials shall be submitted to the 1.12.7.5 Check Tests


Engineer for inspection, testing and acceptance before
1 The Engineer may periodically order check tests to
incorporation in the Works. All materials being used will
verify the accuracy of project control testing and
be subject to inspection, testing, or rejection at any time
equipment. The Engineer may direct that check tests be
prior to such incorporation.
performed by qualified persons other than those
2 Where untested and unaccepted materials have normally responsible for project control testing, or he
been used without approval of the Engineer, such use may direct that the samples be sent to the Employer's
shall be at the Contractor's risk and the work may be central laboratory or to an approved independent
rejected by the Engineer. laboratory for testing.
1.12.7.2 Source Tests 2 The Contractor shall provide the Engineer with all
necessary test report forms and expendable materials
1 All source samples shall be taken by the Contractor required to perform all required tests. Copies of all test
in the presence of the Engineer, using approved results will be issued to the Contractor.
sampling procedures. All source approval tests shall be
performed under the supervision of the Engineer or,
when so specified, by an independent laboratory

♦ 1-16 ♦
copy 249
1.12.7.6 Precedence of Materials and Testing used items, the manufacturer's brochures, catalogues
Specifications and specifications.

1 All references to methods of testing or 1.13.3 Provision and Use of Plant and
specifications of AASHTO, ASTM and others will be
Equipment
deemed to refer to the latest methods of testing as
specified in the Contract Documents. 1 The Contractor shall furnish all plant and
2 Unless otherwise specified, AASHTO methods of equipment listed in his schedule and necessary for
sampling and testing shall be adopted where available. construction of the Works. Such plant and equipment
In the case of absence of an appropriate AASHTO shall be delivered to the Site, inspected, and approved
specification, the ASTM or BS specification shall govern. by the Engineer prior to commencement of the particular
work for which it is intended. Any plant or equipment,
or part thereof, which becomes excessively worn or
1.12.8 Unacceptable Materials
defective shall be promptly repaired or replaced, as
1 All materials not conforming to the requirements of required by the Engineer.
the Specifications at the time they are used will be 2 The Contractor shall not remove from the Site and
rejected and shall be removed immediately from the Site shall not use for other projects any approved plant or
unless otherwise instructed by the Engineer. equipment without the permission of the Engineer.
2 If defect from rejected materials, has been
corrected, such remedied materials, shall not be used 1.13.4 Measurement and Basis of Payment
until Engineer’s approval has been given.
No separate measurement or payment will be made, for
any part of Sub-section 1.13, which work is considered to
1.12.9 Measurement and Basis of Payment
be subsidiary to other sections. The cost of the work is
No separate measurement or payment will be made, for deemed to be included in the unit rates for other items in
any part of Sub-section 1.12, which work is considered to the Bill of Quantities.
be subsidiary to other sections. The cost of the work is
deemed to be included in the rates for other items in the 1.14 Contractor’s Temporary Works
Bill of Quantities. and Services
1.13 Contractor’s Plant and 1.14.1 Temporary Facilities
Equipment
1.14.1.1 General
1.13.1 General 1 The Contractor shall provide all Temporary Works
1 Plant and equipment used on the Works shall be of and services and Contractor's Equipment and tools
sufficient size and in such mechanical condition as to required for the efficient and safe execution of the Works,
meet the requirements of the Contract Documents and including but not limited to:
shall be available for use when required by the Engineer. i. Temporary roads, hard standings, sleeper
The Engineer may order removal and replacement of tracks and the like.
unsatisfactory plant or equipment. ii. Temporary fences, gates and barriers.
2 Wherever plant or equipment of a particular size or iii. Temporary offices, stores, mess rooms,
type is specified, the Contractor may request permission latrines and compounds.
to use an alternative type in place of that specified. In
iv. Scaffold, ladders, hoists, cranes and the like.
such cases, the Contractor shall furnish evidence to the
Engineer that the production of the plant or equipment v. Temporary screens, chutes, coverings, roofs
proposed is at least equal to that of the specified type. and rainwater pipes for protection of the
Works and personnel.

1.13.2 Contractor's Schedule of Plant and vi. Transport and vehicles on and off Site.
Equipment vii. Fixed and movable mechanical plant and
equipment.
1 The Contractor shall submit together with his Tender,
viii. Small tools.
a detailed schedule of the numbers and types of plant
and equipment which he proposes to use on Site to ix. Temporary water and power supplies and
carry out the Works. The schedule shall contain full site lighting.
details for each item, including type, manufacturer, x. Temporary drainage.
model, identification number, year of manufacture, 2 Locations: The Engineer's approval shall be
number of years in use, and, for all new and previously obtained for the intended locations of all spoil heaps,
Temporary Works and services.

♦ 1-17 ♦
copy 249
3 Standards and details: Temporary Works shall be including supplies for commissioning engineering
constructed to recognized standards and codes of services and Plant at required voltages.
practice so that they are fit for their purpose. Drawings 2 The Contractor shall make provision for temporary
and details of proposed Temporary Works shall be connections to the public electricity system and pay all
provided by the Contractor if requested by the Engineer. charges and/or provide generators. All temporary
Consent of such arrangements by the Engineer in no electric supply and distribution shall conform with the
way relieves the Contractor from his sole responsibility requirements of the concerned authorities.
for their sufficiency and safety.
3 The Contractor shall provide and maintain
4 Temporary works: Temporary Works and services adequate efficient lighting for execution of the work and
shall be maintained, altered and adapted and as for safety and security purposes. Without prejudice to
necessary cleared away on completion or when no his liability under the General Conditions of Contract, the
longer required. Contractor shall, with respect to the supply of electricity
for power or lighting, take all necessary precautions to
1.14.1.2 Temporary Site Facilities
ensure the safety of his workmen and others.
1 Roads: Permanent roads, hard standings and
footpaths on the Site may be used provided they are 1.14.5 Directional and Warning Signs
adequately maintained and thoroughly cleaned and
made good after use and left in unimpaired condition. 1 The Contractor shall provide all signs required for
directing traffic and pedestrians around or through the
2 Trench crossings: Are to be provided for free and
Site and to provide information on location of facilities
safe passage of vehicles and pedestrians over pipe and
on the Site.
other trenches.
2 The Contractor shall provide warning and
3 Temporary site fence: The Contractor shall provide
informational signs required by law and good practice
suitable and secure temporary site fencing and gates
for the safety of all personnel.
where necessary or as directed by the Engineer. Design
of the fencing and gates, including location, construction
details, etc. is to be submitted to the Engineer for 1.14.6 Project Sign Board
approval prior to fabrication and erection.
1 Sign Boards: The Contractor shall provide suitably
sized project sign boards, bearing the names of the
1.14.2 Scaffolding and False Work Employer and Engineer together with any corresponding
logos, the name of the project, the name of the
1 The Contractor shall provide scaffolding and false
Contractor and such other names and information as the
work to facilitate carrying out construction of the Works
Engineer may request. The design and style of the sign
in the required sequence. Scaffolding and false work
boards shall be submitted to the Engineer for approval
shall be properly designed and constructed specifically
prior to fabrication. Sign boards are to be written in
for the loads intended. Full details of the proposed
Arabic and English and erected at suitable locations as
arrangements shall be submitted to the Engineer for his
directed by the Engineer.
approval. Such approval, however, shall not relieve the
Contractor of his responsibility with regard to the 2 Each sign board shall be erected in a prominent,
adequacy of all scaffolding and false work used in the approved position. Sign boards shall be maintained in
Works. good order at all times and sign boards and supports
shall be dismantled and removed from the site upon
completion of the Works.
1.14.3 Water Supply
1 The Contractor shall be deemed to have carried out 1.14.7 Measurement and Basis of Payment
adequate investigations relating to the availability of
water for the purpose of the Works and to have 1 No separate measurement or payment will be
consulted and arranged with the appropriate authorities made, for any part of Sub-section 1.14 except for project
and taken into consideration all legal aspects. sign boards as stated below. All other work in this sub-
section is considered to be subsidiary to other sections
2 The Contractor shall be responsible for the supply
and the costs are deemed to be included in the unit rates
of sufficient clean, fresh water at all times during
for other items stated in the Bill of Quantities.
progress of the Works, including making temporary
arrangements for storing and distributing the water on 2 Each project sign board is measured as an item.
the Site. The rates shall include for design, fabrication, erection,
relocation if required, maintenance and removal.
1.14.4 Electricity Supply
1 The Contractor shall make his own arrangements
for the supply of all electrical power and all lighting and
electrical equipment required for execution of the Works,

♦ 1-18 ♦
copy 249
1.14.8 Items in the Bill of Quantities 3 If the Contractor fails to measure any work, the
Engineer may, at his discretion, estimate quantities of
i. Provision, erection, relocation, such items for the monthly Payment Certificate or
maintenance and removal recommend that no payment be made for the items not
of project signboard (type) (nr). measured and quantities not computed until they are
properly measured and computed.
1.15 Commemorative Plaque and 4 All work shall be measured net and in accordance
Opening Ceremony with the General Conditions of Contract. The units of
measurement shall be in accordance with SI
1.15.1 Commemorative Plaque recommendations and the latest revision of ISO 1551.
The Contractor shall erect a commemorative plaque if 5 Structures shall be measured according to the lines
required by, and of the type and design described in, the shown on the Drawings, or as altered by direction of the
Special Specifications. The location shall be as shown on Engineer to meet site conditions.
the Drawings or agreed with the Engineer. 6 The term ‘lump sum’ when used as an item of
payment shall mean complete payment for the work
1.15.2 Opening ceremony described.
7 When a complete item or structural unit (in effect
At the location of the erected plaque the Contractor shall
‘lump sum’) is specified as unit measurement the unit
make arrangements for the opening ceremony, including
shall be taken to include all necessary fittings and
grading the designated area for the ceremony and for
accessories.
car parking, spreading with suitable gravel, marking the
area with painted stones and colored ribbons and posts, 8 Cost of rental of plant and equipment is deemed to
erecting a temporary pavilion in the national flag colors, be included in the rates and prices for the relevant work.
providing armchairs for the presiding authorities and Only when specific plant is required to perform daywork
seats for the invited guests, and providing a microphone specifically ordered by the Engineer, will payment be
and adequate amplification equipment with suitable made. Payment shall be for the hours of actual working
power supply. The Contractor shall also provide time of the equipment and travelling time within the Site.
appropriate refreshment for the guests, including Omani Where plant and equipment has to be brought
halwa and coffee. specifically to Site to carry out work paid for under day
works, travel time and transportation to the site will be
measured.
1.15.3 Measurement and Basis of Payment
9 Manufactured Items
1 The commemorative plaque shall be measured as a
Whenever standard manufactured items are specified,
Lump Sum (L.S.) item in the Bill of Quantities.
such as fence wire, plates, rolled shapes, pipe conduit,
2 The Opening Ceremony shall be measured as a etc. and these items are identified by gauge, unit weight,
Lump Sum (L.S.) item in the Bill of Quantities. section dimensions, etc., such identifications shall be
deemed to be nominal weights or dimensions. Unless
1.15.4 Items in the Bill of Quantities controlled by tolerances in cited specifications,
manufacturing tolerances established by the industries
i. Supply and erection of
involved may be accepted by the Engineer at the
commemoration plaque (Lump Sum).
recommendation of the concerned authorities.
ii. Opening ceremony
including all facilities (Lump Sum). 10 Transport
Costs of haul or transport of any material or item is
1.16 Measurement and Payment neither measurable nor payable unless specifically
stated.
1.16.1 General Method of Measurement
1.16.2 Scope of Payment
1 The method of measurement and computations to
be used in determining quantities of materials furnished 1 The Contractor shall receive and accept
and of work performed shall be as defined in the Method compensation provided for in the Contract as full
of Measurement and Basis of Payment clause for each payment for supplying materials and for performing
Sub-section and in the Preambles to the Bill of Quantities. work under the Contract in a complete and acceptable
manner and for all risks, losses, damages or expenses
2 All field measurements of quantities for monthly
arising out of the nature or execution of the work subject
certificates and for final payment shall be made by the
to the provision of the Conditions of Contract.
Contractor in the presence of the Engineer. Original
copies of the field measurement notes, signed by the 2 For detailed information on the item coverage and
Contractor, will be retained by the Engineer. costs to be included in the unit rate of the Contractor, the
Contractor should refer to the relevant clauses of each

♦ 1-19 ♦
copy 249
sub-section of the Specification and to the Preamble to
the Bill of Quantities and to the item descriptions in the
Bill of Quantities.
3 If the measurement and payment clause in the
Specification relating to a unit rate under the Contract
that the unit rate be considered compensation for certain
work or material essential to the item, this same work or
material will be neither measured nor paid for under any
other pay item appearing elsewhere in the Contract.

♦ 1-20 ♦
copy 249
Ref. Title Page No. Ref. Title Page No.
2.1  Clearing and Grubbing 2-1  2.3.4 Method of Measurement 2-6
2.3.5 Basis of Payment 2-6
2.1.1  Description 2-1 
2.3.6 Items in the Bill of Quantities 2-7
2.1.2 Construction Requirements 2-1
2.1.3 Method of Measurement 2-1 2.4  Borrow Materials 2-7 
2.1.4 Basis of Payment 2-1
2.4.1 Description 2-7
2.1.5 Items in the Bill of Quantities 2-1
2.4.2 Location of Borrow Pits 2-7
2.2  Removal of Structures and 2.4.3 Borrow Material 2-7
Obstructions 2-1  2.4.4 Method of Measurement 2-7
2.4.5 Basis of Payment 2-7
2.2.1 Description 2-1
2.4.6 Items in the Bill of Quantities 2-7
2.2.2 Construction Requirements 2-1
2.2.2.1  General 2-1  2.5  Embankments 2-7 
2.2.2.2  Removal of Bridges, Culverts
2.5.1 Description 2-7
and Ditches 2-2 
2.5.2 Materials 2-8
2.2.2.3  Removal of Pipes 2-2 
2.5.3 Construction Requirements 2-8
2.2.2.4  Removal of Walls, Rocks and Boulders 2-2 
2.5.3.1  General 2-8 
2.2.2.5  Removal of Fences and Gates 2-2 
2.5.3.2  Trial Embankments Sections 2-9 
2.2.2.6  Removal of Wells and Shafts 2-2 
2.5.3.3  Foundation Preparation 2-10 
2.2.2.7  Removal of Utilities 2-2 
2.5.3.4  Embankment Construction 2-10 
2.2.2.8  Removal of Existing Pavement 2-3 
2.5.4 Testing 2-11
2.2.3 Method of Measurement 2-3
2.5.4.1  General 2-11 
2.2.4 Basis of Payment 2-3
2.5.4.2  Standards of Compaction for Soil
2.2.5 Items in the Bill of Quantities 2-3
and Granular Materials 2-11 
2.3  Roadway Excavation 2-4  2.5.4.3  Degree of Compaction for Rock Fill
Materials 2-11 
2.3.1 Description 2-4
2.5.4.4  Monitoring Settlement of Rockfill 2-12 
2.3.2 Classification of Roadway Excavation 2-4
2.5.5 Method of Measurement 2-12
2.3.3 Construction Requirements 2-4
2.5.6 Basis of Payment 2-12
2.3.3.1  Utilization of Excavated Materials 2-4 
2.5.7 Items in the Bill of Quantities 2-12
2.3.3.2  Drainage of Excavation Areas 2-4 
2.3.3.3  Obliteration of Disused Roadways 2-4  2.6  Subgrade Construction 2-12 
2.3.3.4  Rock Blasting 2-5 
2.6.1 Description 2-12
2.3.3.5  Excavation of Unsuitable Material 2-5 
2.6.2 Materials 2-13
2.3.3.6  Slopes, Subgrade and Ditches 2-5 
2.6.3 Construction Requirements 2-13
2.3.3.7  Unstable Materials outside
2.6.3.1  Subgrade in Cut 2-13 
Right-of-Way 2-6 
2.6.3.2  Subgrade in Embankment 2-14 
2.3.3.8  Disposal of Unsuitable and Surplus
2.6.3.3  Surface Tolerances 2-14 
Material 2-6
2.6.3.4  Maintenance of Finished Subgrade 2-14

copy 249
Ref. Title Page No.
2.6.3.5 Drainage Blanket 2-14 
2.6.3.6 Subgrade Construction on Sabkha
and Gypsum Rich Soils 2-14
2.6.3.7 Subgrade Construction on top
of Dune Sand 2-15
2.6.4 Method of Measurement 2-15
2.6.5 Basis of Payment 2-15
2.6.6 Items in the Bill of Quantities 2-15

2.7  Excavation and Backfilling


for Structures 2-15 
2.7.1 Description 2-15
2.7.2 Excavation 2-15
2.7.2.1  General 2-15 
2.7.2.2  Temporary Support System 2-16 
2.7.2.3  Excavation for Major Structures 2-16 
2.7.2.4  Excavation for Box Culverts, Pipe
Culverts and Miscellaneous Structures 2-16 
2.7.3 Backfilling 2-17
2.7.3.1  General 2-17 
2.7.3.2  Backfilling for Box Culverts, Pipe
Culverts and Miscellaneous Structures 2-18 
2.7.4 Method of Measurement 2-19
2.7.5 Basis of Payment 2-19
2.7.6 Items in the Bill of Quantities 2-19

2.8  Earthwork for Pipe Trenches 2-19 


2.8.1 Description 2-19
2.8.2 Materials 2-20
2.8.2.1  Backfill Material 2-20 
2.8.3 Construction 2-20
2.8.3.1  Excavation for Pipe Trenches 2-20 
2.8.3.2  Backfilling 2-21 
2.8.3.3  Restoration of Surfaces 2-21 
2.8.4 Method of Measurement 2-21
2.8.5 Basis of Payment 2-21
2.8.6 Items in the Bill of Quantities 2-22

copy 249
2.1 Clearing and Grubbing 2.1.3 Method of Measurement
1 Clearing and grubbing is measured in square meters
2.1.1 Description of the cleared area within the limits described in Item 1 of
1 This Sub-section describes removal and satisfactory Clause 2.1.1 above and approved by the Engineer.
disposal of all vegetation, surface debris and scattered 2 Trees with a trunk diameter 300mm or more when
stones and rocks within the limits of the actual road width measured 750mm above existing ground level are
(including the toes of fill and cut slopes and an additional measured by the number removed and delivered to the
5m wide band from both sides), easement areas and Employer or disposed of as directed by the Engineer.
borrow pits.
2 Removal of structures and similar obstructions and 2.1.4 Basis of Payment
removal of utilities are specified in Sub-section 2.2 -
1 The area of completed and accepted clearing and
"Removal of Structures and Obstructions".
grubbing work measured as provided for above, will be
paid at the unit rates stated in the Bill of Quantities, which
2.1.2 Construction Requirements rates shall be full compensation for labor, equipment and
1 The Contractor shall set out the approved other items necessary for completion of the work..
construction limits and the Engineer will designate all 2 Removal of trees with trunk 300mm diameter or
trees, shrubs, plants, vegetation, etc and other items that greater will be paid for by the number removed as stated
are to remain within the right-of-way (ROW). The above. Removal of trees with trunk less than 300mm
Contractor shall carefully preserve all such items from diameter is deemed to be included in the rate for clearing
damage or defacement. Trees to be removed and and grubbing
delivered for replanting shall be carefully handled. 3 Rates for all clearing and grubbing and tree removal
2 All surface objects, trees, stumps, roots, stones and shall include for filling holes and depressions with
rocks (up to 0.2 cu.m. or 500 kg individual size or weight), material as specified
and other protruding obstructions not designated to be
retained shall be cleared or grubbed to ground level. Non- 2.1.5 Items in the Bill of Quantities
perishable solid objects (such as boulders, rocks, concrete
i. Clearing and grubbing
blocks, etc.) which will be a minimum of 2m below the
ii. Removal and delivery or disposal of trees of
sub-grade or finished ground level may be left
300mm trunk diameter or greater
undisturbed at the Engineer’s discretion. If such non-
perishable objects are encountered within 2m below the
sub-grade or finished ground level, they will be removed 2.2 Removal of Structures and
and considered as unsuitable material, paid under Obstructions
Unclassified Excavation.
3 Stump holes and other holes from which 2.2.1 Description
obstructions are removed within the limits of construction,
1 This Sub-section describes the removal, wholly or in
shall be backfilled with suitable material and compacted in
part, and satisfactory disposal of all buildings, fences,
accordance with Sub-section 2.5 - "Embankments". Small
structures, abandoned pipelines, and any other
holes that are inaccessible to compaction / tamping
obstructions, as shown on the Drawings or directed by the
equipment shall be filled and tamped manually using a
Engineer, which are not designated or permitted to remain,
steel rod with a 10-15cm diameter steel disc attached to its
including salvaging of designated materials and backfilling
end.
the resulting trenches, holes and pits.
4 Perishable material shall be disposed of or burned
2 The Contractor shall examine the Site and record for
under the constant care of competent watchmen at such
himself all obstructions and utilities before the
times and in such a manner that any vegetation or other
commencement of the Works.
items designated to remain in the ROW, or other adjacent
property, will not be jeopardized. Burning shall be carried
2.2.2 Construction Requirements
out in accordance with applicable laws and ordinances.
5 Materials, stones, rocks, and debris which cannot be 2.2.2.1 General
burned and perishable materials, shall be removed from
1 The Contractor shall raze, remove and dispose of all
the ROW and disposed of at dumping areas off the Site,
buildings, foundations, structures, fences and other
approved by the concerned authorities, provided
obstructions, any portions of which are on the ROW,
permission of the respective property owners has been
except utilities and items for which other arrangements for
obtained in writing to dump such materials on their land.
removal have been made. All designated salvageable
The Contractor shall make all necessary arrangements
material shall be removed, without causing unnecessary
with property owners for obtaining such written
damage, and in sections or pieces which may be readily
permission at his own expense.

♦ 2-1 ♦
copy 249
transported, and shall be stored by the Contractor at 2.2.2.4 Removal of Walls, Mortared and Loose Riprap,
approved locations, for later use or possession of others. Gabions, Rocks and Boulders
2 Unusable perishable material shall be destroyed.
Non-perishable material may be disposed of off the Site, 1 Masonry walls, mortared and loose riprap, gabions
provided permission of the respective property owners and accumulated stones, large rocks and boulders of
has been obtained in writing to dump such materials on individual size greater than 0.2 cu.m.or greater than 500 kg
their land. in weight which lie within the limits of the Works, shall be
removed and disposed of as directed.
3 Basements or cavities left by structure removal shall
be filled to the level of the surrounding ground and, if 2.2.2.5 Removal of Fences and Gates
within the prism of construction, shall be compacted to
the type of compaction within the range for the adjacent 1 When fences and gates enclosing pasture land or
roadway embankment as specified in Sub-section 2.5 – farm land are to be removed, the Contractor shall notify
‘Embankments’. the Engineer sufficiently in advance to permit the property
owner reasonable time to construct alternative fencing or
4 Salvaged pipe culverts and other re-usable materials
make other suitable arrangements.
shall be stored at accessible approved locations on Site
and shall become the property of the Employer. 2.2.2.6 Removal of Wells, Shafts and Falajs

2.2.2.2 Removal of Bridges, Culverts and Ditches 1 Existing wells and shafts, abandoned or active, which
lie within the limits of the Works, shall be dismantled,
1 Bridges, culverts and other drainage structures in
backfilled, and compacted. All salvageable materials shall
locations traversed by traffic shall not be removed until
be removed and stored at approved locations on Site. All
arrangements, detours and traffic management plans have
salvageable material shall become the property of the
been made by the Contractor and approved by ROP to
Employer. Wells shall be filled to the level of the
maintain the flow of traffic.
surrounding ground and, if within the prism of
2 Substructures in watercourses shall be removed construction, shall be compacted after obtaining the
down to the level of the natural stream bed. Those parts Engineer's permission to the type of compaction within
outside the stream shall be removed to 300 mm below the range designated.
natural ground surface. Where such portions of existing
structures lie wholly or in part within the limits for a new 2.2.2.7 Removal of Utilities
structure, they shall be removed to the extent necessary to
1 The Contractor shall liaise with the Engineer and
accommodate construction of the proposed structure.
shall notify all Utility Authorities and co-operate and
3 Steel bridges and timber bridges, designated to be coordinate with them in respect of removals and
salvaged shall be dismantled without causing unnecessary relocations.
damage. Steel members shall be match marked, unless
2 Unless shown otherwise on the Drawings,
this requirement is waived by the Engineer. All salvaged
realignment or relocation of active utilities will be to the
material shall be stored as previously specified for reuse
approval of the respective authorities and such work shall
or possession of others.
be coordinated by the Contractor. The Contractor shall
4 Blasting or other operations necessary for removal of perform the necessary coordination with the relevant
existing structures or other obstructions, and which may utility authorities ahead of time in order to avoid
damage new construction in the vicinity, shall be unnecessary delay to the Works.
completed prior to commencing the new construction.
3 The removal of all disconnected or abandoned
Explosives shall be used only as permitted by the
utilities within the ROW shall be performed by the
appropriate security authorities and shall be approved by
Contractor as directed by the Engineer, unless the utility
the Engineer. The Contractor shall observe the
authorities indicate their intention to carry out such
requirements of Section 1, Sub-section 1.9, Clause 1.9.2
removal and salvaging of materials, fittings, parts, etc.
for all blasting operations
4 The Contractor shall liaise with the Engineer and
5 The Contractor shall carry out a structural survey of
shall advise each affected utility authority in writing of his
all the existing buildings and structures located within the
proposed construction schedule and shall arrange for
blasting influence distance. The survey shall include
inspection, disconnection or interruption of services by the
detailed photographic records for the adjacent buildings
utility authorities as appropriate.
and structures before and after blasting, in order to avoid
later claims by public. 5 The Contractor shall be responsible for supporting
and protecting realigned utilities and existing utilities that
2.2.2.3 Removal of Pipes are to remain in place, for the duration of the Contract and
shall provide all necessary Temporary Works in this
1 All pipes unless otherwise directed shall be removed
respect, all in compliance with Section 1, Sub-section 1.8,
and precautions taken to avoid breaking or damaging the
Clause 1.8.3…..and the requirements of the relevant utility
pipes. The Contractor shall exercise utmost care during
owner. Any damage caused to utilities and attributable to
the removal of pipes so as to avoid unnecessary damage.
the Contractor shall be repaired at his expense.

♦ 2-2 ♦
copy 249
6 All excavation and backfill shall conform to the will not be paid for directly but will be considered as
requirements of Sub-sections 2.3 - ’Road Excavation‘, 2.5 – subsidiary work related to other items in the Bill of
’Embankments’ and Sub-section 2.7 - ’Excavation and Quantities.
Backfilling for Structures‘, as appropriate.
2.2.4 Basis of Payment
2.2.2.8 Removal of Existing Pavement
1 The quantities of completed and accepted work,
1 The Contractor shall remove, wholly or in part, as measured as provided for above, will be paid for at the
shown on the Drawings or directed by the Engineer, relevant unit rates stated in the Bill of Quantities , which
existing asphalt, tiles and/or concrete pavement layers, rates shall be full compensation for equipment, tools,
and any granular or stabilized base courses., including labor, materials, transporting and dumping, and for other
disposal of debris and salvaging of designated materials, items necessary for the proper completion of the work.
and backfilling the resulting holes where and as instructed
by the Engineer. 2.2.5 Items in the Bill of Quantities
2 The Contractor shall examine the Site and record all
i. Removal of existing building (type and
obstructions and utilities that may be affected by removal
description), (Nr. or Length /
of existing pavements at the commencement of the Works.
Area / Volume as appropriate).
3 The Contractor shall raze, remove and dispose of old
ii. Removal of reinforced concrete (type,
pavement of different types, (i.e. down to the bottom of location, and dimensions), (cu.m).
the base course) or as directed by the Engineer, for the
iii. Removal of mass concrete (type, location
portions which are within the limit of Works.
and dimensions), ( cu.m).
4 Unusable perishable material shall be disposed of in iv. Removal of pre-stressed concrete (type,
accordance with the applicable laws and ordinances. Non- location and dimensions), ( cu.m.)
perishable material may be disposed of off the Site, v. Removal of curbs (Type), (lin.m.)
provided permission of the concerned authorities and/or vi. Removal of Tiles (Type and Size), (sq.m).
the respective property owner has been obtained in vii. Removal of pipe culverts (type
writing to dump such materials on their land. and diameter) , (lin.m.)
5 Cavities left by pavement removal shall be filled to viii. Removal of existing pavement
the level of the surrounding ground and, if within the (description and type), (cu.m).
prism of construction, shall be compacted to the type of ix. Removal of reusable road studs, (nr).
compaction specified in Sub-section 2.6 – ‘Subgrade x. Removal of steel safety barrier including
Construction’. post and foundations (dimensions and
Type), (lin.m).
6 The Contractor shall be responsible for supporting
xi. Removal of concrete safety barrier
and protecting existing Utilities that are to remain in place,
including foundations
for the duration of the Contract and shall provide all
(dimensions and Type), (lin.m.)
necessary Temporary Works in this respect. Any damage
xii. Removal of sign boards including
caused to utilities and attributable to the Contractor shall
post and foundations (size), (nr).
be repaired at his expense.
xiii. Removal of Floodway marker posts and
7 The Contractor shall be responsible for and shall foundations (size), (nr.)
ensure that pavement removal operations are completed xiv. Removal of re-usable steel safety barrier
without applying extreme vibration and heavy loading that including post and foundations
might damage the existing underground utilities. (dimensions and Type), (lin.m.)
2.2.2.9 Removal of Existing Road Furniture xv. Removal of re-usable concrete safety
barrier including foundations (dimensions
1 Road Furniture items such as curbs, tiles, steel and and Type), (lin.m).
concrete safety barriers, lighting poles, sign boards, etc. xvi. Removal of re-usable sign board including
which lie within the limits of the Works, shall be removed post and foundations (size), (nr.)
and disposed of as directed. xvii. Removal of reusable Floodway marker
posts including foundations (size), (nr).
2.2.3 Method of Measurement xviii. Removal of drainage protection
works (type), (sq.m.)
1 Removal of structures and obstructions is measured
xix. Removal of existing fences and
by number, length, area or volume as appropriate for the
gates (description and type), (lin.m.)
relevant work, unless Item 2.2.3 (2), applies. The rates
xx. Removal of existing block and
shall include in full for the removal, storage, protection
masonry walls (Size and Type) (cu.m)
and disposal of the structure or obstruction, including
xxi. Removal of ditches (Type and
items necessary for the proper completion of the work.
width), (lin.m).
2 If the Bill of Quantities does not contain separate xxii. Removal of bridges (dimensions,
items for removal of structures and obstructions, this work

♦ 2-3 ♦
copy 249
type and description) (nr). ii. Material too wet to be compacted and where
xxiii. Removal of rocks and boulders circumstances prevent suitable in-place drying
larger than 0.2cu.m. or 500 kg prior to incorporation into the work.
(description), (cu.m). iii. Materials which are otherwise unsuitable for
xxiv. Removal of wells and shafts (description use in or under the embankment.
and location), (nr).
3 No excavation material shall be wasted without
xxv. Removal of sand dunes (location
written permission from the Engineer.
and description) (cu.m.)
xxvi. Removal of Light Poles including 4 If the Contractor chooses to excavate suitable
cabling and foundation (Size), (nr). material to waste or put it to other uses, and replace it by
borrow excavation for embankment areas, this shall be
undertaken at no extra cost to the Employer.
2.3 Roadway Excavation
5 Excavated rock which is not immediately suitable for
2.3.1 Description incorporation in the works can either be broken down to
acceptable sizes or wasted at Contractor's own expense. If
1 This Sub-section describes excavation in the cut such material is wasted or used in concrete, granular
sections of the roadway, including watercourses, ditches subbase, aggregate base, asphalt mixtures or any other
and wadi relocations (but excluding borrow pits and works, the Contractor shall replace it by borrow
structural excavation) all as and where shown on the excavation for embankment at no extra cost to the
Drawings, and hauling the excavated material either to Employer.
locations for roadway embankments or to stockpiles or to
6 Where shown on the Drawings or directed by the
waste.
Engineer, salvaged materials such as existing concrete,
2 The work also includes any necessary excavations bituminous or other pavements shall, be stockpiled for a
outside the ROW ordered by the Engineer to safeguard specific purpose or for future use. Such materials shall be
and protect the Works, including diversion of existing excavated and handled in a manner that will exclude
wadi channels; excavation of materials obstructing or foreign or undesirable material. Stockpiles shall be neatly
impairing the flow along stream channels; and excavation formed and maintained in an approved manner.
of unstable materials which may slide or encroach into
7 Where specified or directed by the Engineer, suitable
ditches or onto the ROW. Disposal of all such excavated
topsoil material shall be stockpiled during excavation
materials shall be as instructed by the Engineer.
operations and shall subsequently be spread and
compacted on embankment slopes and elsewhere as
2.3.2 Classification of Roadway Excavation directed, to facilitate re-growth of vegetation.
1 Road excavation shall be considered as ’Unclassified
2.3.3.2 Drainage of Excavation Areas
Excavation’ which includes all materials encountered of
any nature including silts, clays, sand, gravel, granular 1 During construction, surfaces in excavation areas
materials, all cohesive and fractured, jointed cohesionless shall be adequately drained at all times. Side ditches or
materials and/or massive rock and unsuitable material. gutters emptying from cut to embankment shall be so
2 Any information concerning properties of the soil constructed as to avoid damage to embankments by
which may be shown on the Drawings, in the Bill of erosion.
Quantities, in supplementary reports, or as a result of 2 The Contractor shall, at an early stage of the Works,
discussion with the Engineer or others shall be considered provide adequate drainage by scheduling ditch and other
as gratis and shall not be a basis for the Contractor's construction so as to prevent saturation or erosion of
determination of his bid prices. embankments and cut slopes. All such drainage ditches
and construction grades shall be cleaned and trimmed at
2.3.3 Construction Requirements regular intervals and when directed to maintain an
unobstructed runoff of stormwater during construction.
2.3.3.1 Utilization of Excavated Materials
3 Damage to the Works attributable to saturation or
1 All materials removed from the excavation shall be erosion of slopes during the period of execution through
used in the formation of the embankment, sub-grade, failure to provide adequate drainage shall be repaired by
shoulder, dykes, and at such other places as directed, the Contractor at his own expense.
unless it is declared unsuitable and ordered to be wasted 4 Whenever groundwater is encountered which may
by the Engineer. adversely affect construction, the Contractor shall advise
2 Unsuitable material shall include: the Engineer who will evaluate the situation and order
i. Unstable materials incapable of being necessary remedial measures.
compacted to the specified density using
mechanical compaction methods at optimum 2.3.3.3 Obliteration of Disused Roadways
moisture content for the equipment being used 1 Obliteration of roadways which are no longer in use
for compaction. shall include filling of all ditches and rough grading of the

♦ 2-4 ♦
copy 249
old roadway to produce within the ROW a neat and well for potential failure planes and the necessary remedial
drained ground surface. measures shall be taken, as approved by the Engineer, at
the Contractor’s expense.
2.3.3.4 Rock Blasting
2.3.3.5 Excavation of Unsuitable Material
1 Rock blasting explosives may comprise a diversity of
systems, including dynamite explosives, watergels, slurry 1 Unsuitable materials are materials that do not
explosives and slurry blasting agents, pumpable blasting comply with the requirements for suitable materials as
agents, emulsion explosives and aluminized explosives. described under Clause 2.5.2 below.
Whenever instructed by the Engineer, blasting shall be 2 Where excavation to finished grades and cross
carried out after pre-splitting the rock mass by using small sections exposes unsuitable material in the sub-grade,
localized charges in pre-drilled holes. slopes or ditch inverts, etc the Engineer may require the
2 When blasting of rock slopes is carried out, a Contractor to remove the unsuitable material and backfill
reasonably uniform face shall be left, regardless of the excavated areas using approved material. The
whether or not the excavation is carried beyond the Contractor shall plan his operations so that necessary
specified side slopes as shown on the Drawings. All cross section measurements are taken before such backfill
breakage and slides shall be removed and disposed of as is placed.
directed. A dust control system shall be designated by the 3 Unsuitable material shall be disposed off as directed.
Contractor and shall be implemented during rock blasting Wasted unsuitable material shall not be deposited on any
after obtaining the Engineer’s approval. cropland.
3 All drilling and blasting shall be done in such a 4 When the Contractor is directed to excavate
manner as will most nearly complete the excavation to the unsuitable material below the surface of the original
required grade lines, and produce the least possible ground in fill areas, other than that required for clearing
disturbance of the material to be left in place. Blasting by and grubbing, the depth to which unsuitable material shall
means of drill holes, tunnels, or any other methods shall be removed will be determined by the Engineer. The
be entirely at the Contractor's risk. Explosive materials Contractor shall plan the excavation so that cross sections
shall be stored and kept under the constant surveillance of are taken before and after material has been removed.
the Royal Oman Police.
2.3.3.6 Slopes, Sub-grade and Ditches
4 Where necessary or directed, the Contractor shall
provide heavy mesh blasting mats or controlled blasting 1 All excavated slopes, sub-grade and ditches shall be
for protection of persons, properties, and the Works. If, in finished true to lines, grades and cross sections as shown
the opinion of the authorities and the Engineer, blasting on the Drawings.
would be dangerous to persons or adjacent structures, or 2 Slopes, except in massive rock or other material
is being carried out in an unsafe or unacceptable manner, which require special treatment, shall be trimmed to
the Engineer may prohibit blasting and order the rock to slopes not steeper than the specified slope angles and
be excavated by other means. rounded at top and bottom to a smooth profile to blend in
5 During explosion works, traffic shall be suspended with the adjacent terrain. Material shall not be loosened
from the routes linking to the Site and all diversions and beyond the specified slope lines. High cut areas shall
other arrangements shall be carried out in full continuously be monitored by an engineering geologist or
coordination with the Royal Oman Police. The Contractor a geotechnical engineer.
shall secure approval of his schedule for such 3 In cuts where earth overlays a rock formation, slopes
interruptions and his proposed methods for safeguarding shall be benched in an approved manner.
the public and property.
4 Ditches of all types shall be excavated and trimmed
6 Excessive blasting will not be permitted. neatly in conformity with the specified grades and cross
Overbreakage and the backfilling thereof shall be at the sections. All projecting rock, stumps, roots or similar shall
Contractor’s expense. Any material outside the approved be removed. Ditches include side ditches, interception
cross section limits which may be shattered or loosened ditches in the berm of cut slopes, furrow ditches, irrigation
because of blasting shall be removed by the Contractor at ditches, wadi relocations, etc.
his own expense. All rock slopes with loose material shall
5 Where the sub-grade is composed of rock as defined
be scaled by workmen and all loose material removed at
in Sub-section 2.6 – ‘Sub-grade Construction’, it shall be
the Contractor’s expense.
undercut to a depth of 200 mm below top of sub-grade to
7 Backfilling of overbreakage shall be carried out as allow for subsequent placing and compaction of the
directed, using approved soil or crushed materials or other leveling sub-grade layer in accordance with Sub-section
special aggregate or cyclopean concrete, as shown on the 2.6 – ‘Sub-grade Construction’, paragraph 2.6.3.1.
Drawings or as directed by the Engineer. Undrained
6 The sub-grade in cut, where the soil is unsuitable for
pockets shall not be left in the surface of the rock.
retention as the sub-grade layer, shall be sub-excavated to
8 Following blasting, cleaning and scaling rock slopes, a depth of 200 mm below top of sub-grade to allow for
the face, benches and back of the slope shall be inspected subsequent placing and compaction of the sub-grade layer.

♦ 2-5 ♦
copy 249
If the material of the sub-grade is suitable for retention as 2 Unclassified Excavation shall be measured by cu.m.
sub-grade layer then it shall be scarified to the required of material excavated, hauled away and either wasted,
depth, watered and compacted in accordance with Section stockpiled, or deposited on or in vicinity of roadway
2.6 – ‘Sub-grade Construction’, paragraph 2.6.3.1. embankments and dykes. Measurements shall be of
7 The Engineer will periodically check all or any part of volumes computed from the cross sections shown on the
the work, to determine conformance to the correct lines, Drawings and the original ground elevations taken jointly
grades and elevations. Tolerances on finished sub-grade by the Engineer and the Contractor after clearing and
levels and on levels of the surface at the underside of the grubbing operations. Rates shall include for costs of
sub-grade layer shall be as specified in Sub-section 2.6 – supporting sides of excavation where necessary, keeping
‘Sub-grade Construction’, Paragraph 2.6.3.3. excavations free from water, proper formation of
embankments, trimming of slopes, preparation and
8 In cases where rock or soil excavations reveal that
completion of the roadway, sub-grade, dykes and
the adopted cut slopes are not suitable and if failures
shoulders and scarifying for suitable sub-grade material.
occur during or after completion of the excavation works
and while the Contractor is still on Site, the Engineer may 3 Excavation of unstable material (from areas outside
request the Contractor to re-excavate according to the the ROW) shall be measured by cu.m. of material
newly established cut slopes, the extra work will be excavated, hauled away and disposed of as directed,
measured and valued as Unclassified Excavation at the completed and accepted. Measurements shall be of
same rate given in the Contract. However, in such case, volumes computed from surveyed cross sections of
the Contractor may submit a proposal for any other original and final ground elevations. When cross
alternative solution for the stability of the cut slopes, for sectioning is impractical in the opinion of the Engineer,
the Engineer’s appraisal and final decision. approval may be given to measure volumes in the
vehicles removing such excavated material.
2.3.3.7 Unstable Materials outside Right-of-Way 4 Ditch excavation and excavation of unstable material
1 Materials outside the ROW or ditch slopes which, in are considered part of the unclassified excavation.
the opinion of the Engineer, are potentially unstable and 5 Rock blasting, backfilling of overbreakage, trimming
liable to slide or encroach into the ROW or into the ditches, and grading of cut slopes, ditches and of other below-sub-
shall be excavated and disposed of as specified for grade surfaces, drainage of excavation areas, obliteration
unsuitable material, unless it is approved for use as of disused roadways, and other ancillary excavation
embankment fill. Works shall not be measured for direct payment, but shall
be considered as subsidiary work the costs of which will
2.3.3.8 Disposal of Unsuitable and Surplus Material be deemed to be included in the rates for Unclassified
1 Unsuitable and surplus materials disposed of within Excavation
approved areas shall be spread, leveled and shaped as 6 Excavation under water shall be measured by cu.m.
directed so as to present a neat and tidy appearance. No of material excavated, hauled away and disposed of as
materials shall be disposed of in such a way as to directed, completed and accepted (including any side
adversely affect natural drainage courses or to cause support or other enabling works). Measurements shall be
damage to the highway or adjacent public or private of volumes computed from surveyed cross sections of
property. original and final ground elevations. When cross
2 If approved by the Employer, Government land may sectioning is impractical in the opinion of the Engineer,
be used for disposal to the maximum extent practicable. If approval may be given to measure volumes in the
private land is used for disposal, the Contractor shall vehicles removing such excavated material.
secure the consent of the landowner or tenant and, if 7 Hauling of excavated materials shall not be
necessary, and at his own expense, pay for the use of such measured for direct payment, but shall be considered as
land. The use of cropland for disposal purposes will not subsidiary work the cost of which will be deemed to be
be permitted. included in the rates for Unclassified Excavation,
regardless of the distance required for hauling the
2.3.4 Method of Measurement materials to an approved dumping area.

1 All excavated material of whatever type (except for 8 Excavation, Stockpiling and recompaction of suitable
unauthorized undercut below top of sub-grade or topsoil material shall be measured by cubic meter, laid,
excavations taken wider than required) shall be measured completed and accepted as directed by the Engineer.
as ‘Unclassified Excavation’ which shall be deemed to
include all materials encountered of any nature, including 2.3.5 Basis of Payment
silts, clays, sand, gravel and granular materials and 1 The amount of completed and accepted work,
fractured, jointed and massive rock, whether weak or measured as provided for above, will be paid for at the
strong, and unsuitable material, as approved and unit rates for the various items in the Bill of Quantities,
instructed by the Engineer. which rate shall be full compensation for equipment, tools,

♦ 2-6 ♦
copy 249
labor, materials, transporting and hauling, and for other stockpiled in the vicinity, ready for re-use prior to
items necessary for the proper completion of the work. abandonment of the pit.
7 Prior to abandonment of any borrow pit or borrow
2.3.6 Items in the Bill of Quantities area, the Contractor shall spread and level the original
overburden over the exposed surfaces and clean up, grade
i. Unclassified Excavation
and contour the pit or area and the adjoining properties
ii. Excavation of unstable material
occupied during execution of borrow operations, whether
outside Right-of-Way
Government, or privately-owned, all to the satisfaction of
iii. Unclassified Excavation under water
the Engineer.
iv. Excavate and Stockpile Suitable topsoil and
recompact as directed
2.4.3 Borrow Material
2.4 Borrow Materials 1 Borrow shall be material approved by the Engineer
as meeting the requirements for the particular
2.4.1 Description embankment, backfill or other use for which the material
is intended.
1 This Sub-section describes excavation of suitable 2 The Contractor shall submit representative samples
material from borrow pits, channels and designated of materials from each of the proposed borrow pits or
borrow areas and hauling to locations of embankments or borrow areas. A minimum of three sets of tests shall be
to stockpiles, all as shown on the Drawings, or as directed performed for each borrow area for each type of material.
by the engineer. No borrow material shall be brought to the site or used in
2 The Contractor shall be responsible for locating the Works before its approval.
suitable borrow pits and for the suitability and sufficiency 3 The Engineer will periodically require follow-up
of borrow materials to meet the specified embankment testing of borrow materials to verify that no change in
and other backfilling requirements. quality has occurred since the original approval.
3 Borrow pits shall be utilized if there is insufficient
suitable excavated material to satisfy the embankment 2.4.4 Method of Measurement
and other backfilling requirements or if the Contractor
chooses to excavate suitable material to waste or put it to 1 Borrow Excavation shall be measured by cu.m. of
other uses, and replace it by suitable material excavated suitable material excavated, hauled and used in the proper
from borrow pits at the Contractor’s expense. formation of embankments, including trimming of slopes,
preparation and completion of the roadway sub-grade,
shoulders and dykes.
2.4.2 Location of Borrow Pits
2 The quantity of borrow excavation shall be
1 Generally, the borrow pits shall not be located within determined by calculating the total quantity of filling after
50 m from the toe of embankment slope or top of cut or compaction and deducting therefrom the total quantity of
formed slope, unless otherwise approved by the Engineer. unclassified excavation less an allowance for material
2 In no case shall borrow pits be located within 200 m condemned by the Engineer as unsuitable for filling.
downstream of a drainage structure without the written
approval of the Engineer. Unauthorized borrow pits shall 2.4.5 Basis of Payment
be backfilled and compacted, as directed by the Engineer,
1 The amount of completed and accepted work,
at the Contractor's expense. measured as provided for above, will be paid for at the
3 In each case where a borrow pit is proposed within unit rates for borrow excavation in the Bill of Quantities ,
privately-owned property, the Contractor shall secure the which rate shall be full compensation for equipment, tools,
consent of the landowner in writing, if necessary, and labor, materials, transporting hauling and placing, and for
shall, pay for the use of the material and land. The other items necessary for the proper completion of the
work.
Contractor shall be solely responsible for any claims for
compensation or complaints arising out of borrow pit
operations.
2.4.6 Items in the Bill of Quantities
4 The Contractor shall be responsible for the stability i. Borrow excavation.
of the side slopes of borrow pits and channels at all times,
until the pit or channel is abandoned. 2.5 Embankments
5 Details of the Contractor's proposed haul routes and
traffic arrangements in relation to borrow pit operations 2.5.1 Description
shall be submitted for approval before any borrow
1 This Sub-section describes construction of roadway
excavation commences. embankments, including preparation of the areas upon
6 Overburden and any unsuitable top layers within which they are to be placed; placing and compacting
each borrow pit shall be completely removed and approved material within areas where unsuitable material
has been removed; and placing and compacting approved

♦ 2-7 ♦
copy 249
embankment material in holes, pits and other depressions also be used in these conditions, except for the top
within the constructed area, all in accordance with the 600mm of the embankment.
lines, grades and cross sections shown on the Drawings. 6 Where embankments are to be constructed using
material classified as A3 (AASHTO M 145) or other
2.5.2 Materials material subject to side slope erosion or requiring
confinement for stabilization purposes, the embankment
1 Materials suitable for embankment shall be of classes
plating or confining layer shall be constructed using
A-1, A-2-4, A-2-5 or A3 ‘when confined’ groups as in
AASHTO M145 and complying with Table 2.5.2.1, and AASHTO M 145 Class A-1-a, A-1-b, or A-2-4 materials or as
shall be used when available, except for rock fill otherwise approved.
embankments. If material of this character is not available, 7 The material used in rockfill embankments shall
then material from A-2-6, A-2-7, A-4, A-5, groups (AASHTO consist predominantly of rock fragments of such size that
M145) may be used provided it complies with the the material can be placed in layers of the thickness
requirements of Table 2.5.2.1; however, special attention prescribed conforming to the requirements stated in Table
shall be given to its suitability for the particular 2.5.2.2. The size distribution of rockfill shall be determined
construction according to CIRIA Special Publication 83: Manual on the
Requirements use of Rock in Coastal and Shoreline Engineering –
1 Maximum dry density not less than 1.7 Appendix 2.
(AASHTO T-180 Method D)
2 Organic matter not more than 5% (AASHTO T- Requirements
267) 1 Maximum particle size ........1/2 loose layer
3 thickness
Gypsum content not more than 5%.
2
4 Passing 0.42mm (Sieve # 40) ........25% maximum
No use of A-6, A-7 soil (AASHTO M-145)
Uniformity coefficient, Cu.......5 minimum, where
5 Maximum size not more than 1/2 of the layer Cu = D60/D10
thickness 3 D60 = the Particle size at which 60% passes
6
Plasticity Index (P.I.) less than 20% D10 = the Particle size at which 10% passes
4-day soaked C.B.R. should not be less than 8%
Table 2.5.2.2: Rock Suitable for Embankment
. 7 (AASHTO T-193) when compacted at 100%
maximum dry density in accordance with 8 Rockfill material shall be obtained from quarries and
AASHTO T-180 Method D.
shall be sound, dense, hard and durable rock capable of
Table 2.5.2.1: Soil Suitable for Embankment being spread and compacted as specified. Individual
2 The 200 mm depth of embankment sub-grade layer pieces are to be clean and angular. It shall be the
immediately below the bottom of sub base shall consist of Contractor's responsibility to excavate material from rock
selected sub-grade material having a 4-day soaked C.B.R. cuts, whether by blasting or other means, so that all
of at least 25% when tested in accordance with AASHTO excavated materials are of suitable size.
T193 and when compacted at 100% Modified Proctor 9 When suitable materials of widely divergent
Density in accordance with AASHTO T-180D, with a characteristics are drawn from different sources, such
gradation and P.I. as specified under Sub-section 2.6 – materials may, if approved, be mixed to meet the
‘Sub-grade Construction’. embankment requirements. Rock and other materials shall
3 The 600 mm depth of embankment immediately be incorporated in such manner as to avoid segregation
below the sub-grade layer shall consist of suitable and an accumulation of boulders, etc., at the toe of
material having a 4-day soaked C.B.R of at least 15% when embankment slopes.
compacted to 95% maximum dry density in accordance 10 Logs, trees, stumps, weeds, heavy grass, vegetable
with AASHTO T-180D and tested in accordance with matter or other undesirable and non compatible materials
AASHTO T-193 with a P.I. not more than 15%. If rockfill is shall not be placed in embankments.
used for the bottom 400 mm depth then these
11 Rocks larger than 100 mm in any dimension shall not
requirements shall apply to the top 200 mm depth below
be used as fill material in areas where piling works are to
the sub-grade layer.
be carried out.
4 Rockfill shall not be used in the top 200 mm of the
embankment below the sub-grade. If found necessary and 2.5.3 Construction Requirements
if approved by the Engineer, water may be added as
required to achieve maximum compaction. 2.5.3.1 General
5 In areas subject to flooding and prolonged inundation 1 Prior to placing embankment material on any area,
of the embankment, such as at bridge and culvert sites, the ground shall have been cleared and grubbed as
the material used in embankment shall conform to specified in Sub-section 2.1 – ‘Clearing and Grubbing’, and
AASHTO M 145, Class A-1-a, A-1-b, A-2-4. Rockfill can the foundation prepared as specified herein.

♦ 2-8 ♦
copy 249
2 Equipment used for foundation preparation and for 11 All embankment side slopes shall be neatly finished
placing, spreading and compacting embankment materials true to the lines and not steeper than the slope angles as
shall be of approved types and furnished in sufficient shown on the Drawings. The bottom (toe) of side slopes
numbers for the purposes intended. Provision and use of shall be graded to a well rounded, smooth profile to blend
such equipment shall conform with Section 19 ‘Plant and in with the adjacent terrain.
Equipment’ 12 Where directed by the Engineer, the side slopes of
3 Draglines shall not be used to construct embankment rockfill embankments shall be thoroughly blanketed with
unless approval is given and only when special A-1, A-2-4 material, and compacted to the satisfaction of
procedures are adopted to keep the layers uniform and the the Engineer
embankment properly graded and well-drained at all times. 13 The Engineer may permit the Contractor to utilize
4 Surfaces of embankment layers shall be kept suitable surplus material at his own expense to widen
properly shaped and drained at all times. The Contractor embankments or flatten slopes, etc within the right-of-way.
shall utilize a sufficient number of motor graders or Surplus material used in such manner shall be compacted
tractors to level and maintain the surface of each layer of to 90 per cent of maximum density. When widening
embankment during all placing and compacting embankments, the Contractor shall bear the cost of
operations. modifying the culverts and any protection work necessary.

5 Whenever feasible, trucks, scrapers, tractors, loaders 14 Rockfill shall not be used within 5m of a structural
and other heavy hauling equipment shall be routed over element (next to bridge abutments footings, etc). In some
the embankment in such a manner as will contribute specific cases, rock fragments not exceeding 75mm
effectively to compaction of the fill material. particle size may be used next to structural elements, but
only after obtaining the Engineer’s approval on the
6 Where an embankment is to be constructed over an
location and extent of the work.
area previously occupied by a building basement, cellar,
irrigation canal, well, any previous excavation, or adjacent 15 Rockfill shall not be used within 600 mm of top and
to structures, and where the proper use of normal bottom of box and pipe culverts. Subgrade material shall
compaction equipment is not practicable, the be used in these areas up to width excavated for
embankment shall be constructed and compacted in structures.
accordance with the backfilling requirements of Sub- 16 Potable or sea water can be used for all embankment
section 2.7 – ‘Excavation and Backfilling for Structures’ construction works, except that only potable water shall
until the use of normal compaction equipment is be used for compaction of fill material within 1m from all
practicable. Layers shall not exceed 200 mm thickness surfaces of structures.
(before compaction) and shall be compacted to the degree
of compaction specified for the embankment. The 2.5.3.2 Trial Embankments Sections
embankment construction under this item shall be 1 If shown on the Drawings, or if required by the
measured and paid under the requirements of Clause Engineer, a trial embankment shall be constructed. The
2.7.4.8:’“Unclassified Structural Excavation’ trial section shall be at least 2 lanes wide by 100 m long at
7 Each embankment layer shall be tested and approved approved locations at or adjacent to the Site. Compaction
prior to placing the following layer in accordance with and other equipment used shall be as specified in Section
Clause 2.5.4 ‘Testing’. 19 ‘Plant and Equipment’.
8 The Engineer may at any time order suspension of 2 The initial sections of rock embankment shall serve
delivery of materials to the embankment sites until as the trial sections for rock fill, in order to establish the
previously delivered materials have been properly placed optimum degrees of consolidation for the different layer
and preceding layers are leveled and uniformly compacted thickness. This shall be obtained by compaction trials
to the specified density. correlating number of passes of the roller with settlement
9 Unacceptable material placed in any embankment of the layer, or by different approved methods. The
shall be removed and disposed of by the Contractor at his maximum permitted layer thickness shall be related to the
own expense, immediately after receiving the Engineer’s unit weight of the vibratory roller and for compaction, as
instructions in this regard. Any expected delay with the given in Table 2.5.3.1 and shall not exceed 800 mm loose
removal of such material shall be coordinated and agreed thickness.
with the Engineer.
10 The Contractor shall be responsible for the stability
of all embankments and shall replace all embankment
sections which, in the opinion of the Engineer, have been
damaged or displaced due to carelessness or neglect on
the part of the Contractor, or due to normally occurring
natural causes, such as storms, and not attributable to the
unavoidable movement of the natural ground upon which
the embankment is constructed.

♦ 2-9 ♦
copy 249
Maximum Thickness of 6 Rockfill shall not be placed on any slopes steeper
Minimum Roller Mass*
Layer than 1:1. All slopes steeper than 1:1 shall therefore be re-
(Kg/m Width)
(Loose Thickness) graded to a slope of 1:1 or milder and all vertical faces and
400 mm 2300 - 2900 overhangs removed.
500 mm 2900 - 3600
2.5.3.4 Embankment Construction
600 mm 3600 - 4300
700 mm 4300 - 5000 1 Roadway embankment consisting of soil or granular
800 mm > 5000 material shall be placed in horizontal layers not exceeding
* For multiple rollers, this shall be assumed as 200 mm compacted thickness, compacted as specified and
approved prior to placing the next layer. The thickness of
the high axle load.
the first layer over areas of Class A-3 dune sand may
Table 2.5.3.1: Maximum Layer Thickness / Minimum Roller exceed 250 mm in order to bridge these areas.
Approximately uniform thickness of each layer shall be
Mass Requirements
achieved prior to compaction. As the compaction of each
2.5.3.3 Foundation Preparation layer progresses, continuous leveling and working of the
material shall be carried out to ensure uniform density.
1 If the original surface upon which embankment is to The correct moisture content shall be maintained at all
be placed is an existing pavement, the surface shall be times.
ploughed, scarified, or otherwise broken up regardless of
2 Where embankments are to be constructed to a
the height of the embankment to be placed thereon.
height in excess of 1.5 m above top of original ground
2 Clearing and grubbing, and removal of tree stumps, level, the Engineer may approve layers up to 250 mm
shall be undertaken. The degree of compaction for the compacted thickness if these layers are located at depths
area to be cleared shall then be determined. The top 150 greater than 1.5m from the final elevation of embankment
mm of the surface on which the embankment is to be and if the Contractor's equipment and the nature of the
placed shall be scarified, brought to a uniform moisture material result in the required density throughout the layer
content within the specified range, and compacted to the thickness.
density specified for the embankment. Hard and smooth
3 When the moisture content of the embankment
surfaces are to be roughened before filling is placed.
material does not fall within the required moisture range,
3 Where embankment is to be placed over topsoil (optimum moisture ± 2%) water shall be added and
containing unsuitable organic material which does not thoroughly mixed into the soil by approved methods or
meet the requirements of Table 2.5.2.1, the ground shall the material shall be aerated, whichever is necessary to
be stripped off to a depth of 200mm and the cleared adjust the material to the required moisture content.
surface shall be scarified to a minimum depth of 200mm
4 When water is added to embankment material, the
or as directed by the Engineer, brought to a uniform
amount added shall be sufficient to provide a moisture
moisture content within the specified range, and
content within the required range plus a reasonable
compacted to the density specified for the embankment.
additional amount to compensate for evaporation and
4 Where embankment is to be placed and compacted other unavoidable losses. Water added in excess of this
on hillsides or where new embankment is to be amount shall be removed by aeration or other approved
compacted against existing embankments or where means at the Contractor's expense. Satisfactory methods
embankment is built part width at a time, the slopes and sufficient equipment shall be used for the furnishing
steeper than 3:1 (H:V) when measured at right angles to and handling of the water in a manner that will minimize
the road centerline shall be continuously benched as the loss due to evaporation or waste.
embankment is brought up in layers. Benching shall be of
5 Embankments that consist of rock-soil material with
sufficient width to permit operation of spreading and
sufficient soil to make rolling feasible shall be placed and
compaction equipment, and in any case not less than 2 m
compacted in an approved manner and to the required
wide except where insufficient width is available between
degree of compaction. Water shall be added as and when
existing and new embankments. Each horizontal cut shall
directed to assist in the compaction of such materials.
begin at the intersection of the original ground and the
vertical sides of the previous cuts. The vertical face of 6 In the case of embankments which are to be formed
each bench shall not be less than 1 m in height and not of approved rock-soil material containing an appreciable
exceed 2 m. Approved benching shall be measured as quantity of rock fragments (normally not exceeding 30%
unclassified excavation. greater than 80mm) and which cannot be placed in layers
of the thickness prescribed without crushing, pulverizing,
5 Where embankment is to be placed and compacted
or otherwise breaking down the fragments, the
on wadi slopes, the entire slope area shall be graded and
embankment may be constructed in layers not exceeding
trimmed to remove any vertical faces and overhangs. The
in thickness twice the average size of the largest rock
final graded slope shall not be steeper than 1.5H:1V. The
fragments and in any case not exceeding 600 mm (before
slope shall then be continuously benched as the
compaction).
embankment is brought up in layers, all as described
above for embankment on hillsides.

♦ 2-10 ♦
copy 249
7 Rockfill materials shall be placed in such a manner materials. The ‘maximum density’ of soil type materials
that the larger rocks are well distributed and the voids are shall be the modified maximum density determined in
filled to the maximum practical extent by smaller particles accordance with AASHTO T 180 (Method D). The ‘relative
of rocks, gravel or approved granular materials. Each layer density’ shall be the relative density determined in
shall be bladed into a neat and homogeneous mass prior accordance with ASTM D 4254, which identifies the state
to compaction. Any rocks found protruding from the of compactness of the material with respect to its loosest
leveled surface shall be removed and replaced by smaller and densest state. The relative density shall be the
particles. Initial breakdown compaction shall be standard to which the field density is referred for
performed with heavy bulldozers. The top level of each comparison in the case of cohesionless, free draining
layer must be surveyed before and after compaction and granular materials.
approved by the Engineer before the next layer is placed. 2 Soil type materials shall be compacted to at least
Oversize rock pieces (i.e. exceeding the maximum particle 90% modified maximum density for the full depth of
size defined in Table 2.5.2.2 by not more than 10%) may embankment; except for the 600 mm of embankment
be used in high rockfill embankments to a level 3 meters material immediately below the sub-grade layer that shall
below sub-grade. be compacted to at least 95% modified maximum density.
Moisture content shall be within plus or minus 2% of
2.5.4 Testing optimum at the time of compaction.
3 Cohesionless, free draining granular materials (of 75
2.5.4.1 General
mm maximum size, with not more than 15% passing 0.075
1 For verification of material, moisture content, mm (No. 200) sieve and a plasticity index (PI) not
compaction, thickness and other properties of the exceeding 20%) shall be compacted to at least 70% of
materials or workmanship the Engineer shall at all times relative density for the full depth of embankment. The 600
have access to all parts of the Works and Site. All mm depth of such material immediately below the sub-
sampling and testing of material and work shall be carried grade layer shall be compacted to at least 75% of relative
out as specified to the satisfaction the Engineer. density.
2 Materials shall be tested in accordance with BS 930, 4 Minimum soil tests required during the construction
AASHTO T96, AASHTO T204, AASHTO T205, AASHTO of sub-grade and/or embankment are:
T104, AASHTO T176, BS 1377, AASHTO M145, ASTM - One sample for CBR, classification (AASHTO
D1556 and other applicable and relevant standards. M145), and laboratory (Moisture - density) or
3 The Engineer shall test the compaction of relative density compaction from each source
embankment materials in accordance with the prior to use. Each sample shall represent not
Specification to ensure that adequate compaction or more than 5,000 cubic meters.
consolidation has been achieved. All such tests shall be - One sample for classification representing not
fully documented by the Contractor, in an approved more than 3,000 cubic meters of the material in
manner. use.
- For every completed layer, one field density
4 In the case of cohesionless, free draining rock-soil
shall be determined for each 1500 square
materials, where maximum density tests fail to produce a
meters or 100 linear meters, whichever is less.
well defined moisture/density relationship, the relative
Testing shall be in accordance with ASTM D
density test shall be used. Alternatively an electronic
1556 or ASTM D 2167 or BS 1377 Part 9.
compaction meter or any other approved test equipment
shall be provided by the Contractor and used to determine 2.5.4.3 Degree of Compaction for Rock Fill Materials
the degree of compaction achieved.
1 To ensure proper compaction of rockfill
5 To determine the degree of compaction for
embankments, the Contractor shall conduct compaction
embankment consisting of rock fill, average differential
tests such as the plate load bearing test or other approved
settlement values shall also be determined from surveys
equivalent tests using equipment and materials available
of an adequate number of grid point elevations as directed
in order to determine the best compaction control criteria.
by the Engineer at the commencement of, during and after
embankment construction. (Refer to Item 6 of Paragraph 2 A rockfill test section shall be placed on a firm
2.5.4.3 below). surface approved by the Engineer, and the material and
layer thickness shall conform to the requirements of these
6 For rockfill embankments, the modulus of soil
specifications.
reaction shall be determined by the plate bearing test;
using the method given in AASHTO T222. 3 The test section shall be of sufficient dimensions to
permit the establishment of at least twenty leveling points
2.5.4.2 Standards of Compaction for Soil and Granular on a 5 meter (5m) square grid, and no fewer than 3 points
Materials on any one line and no point less than three meters from
the edge of the layer. The arrangement of the leveling
1 The following compaction standards shall apply to points shall be approved by the Engineer.
embankment materials other than predominantly rock

♦ 2-11 ♦
copy 249
4 Compaction shall then commence with a minimum 2 The volume of embankment displaced by pipe
of three passes of a vibratory roller, as shown in Table culverts, box culverts and associated end walls shall be
2.5.3.1. Leveling points shall then established, short deducted from the measured volume of embankment. No
lengths of painted steel bars hammered flush with the deduction shall be made for pipes less than 500 mm in
surface of the rockfill are suitable for this purpose. A level diameter and associated end walls.
reading shall be taken at each leveling point on top of a 3 Surplus materials utilized at the Contractor's option
moveable 300 mm square flat steel plate with a hole within the ROW but, beyond the cross sections shown on
drilled in the center of the plate to enable a visual check to the Drawings, are not measured as part of the
be made that the plate is located centrally over the bar. embankment.
5 Further readings shall be taken at the leveling points 4 Benching described under Item 4 of Paragraph 2.5.3.3
after two additional passes with the roller. If the average is measured as Unclassified Excavation, under Clause
settlement is less than half of one per cent (0.5%) of the 2.3.4.
average compacted layer thickness, or as determined by
5 No adjustments or allowances are made in respect of
the Engineer, the rockfill compaction test is deemed
expansion or shrinkage of earthwork volumes which may
complete.
occur during excavation and compaction..
6 If the average settlement is more than half of one
6 Embankment foundation treatment such as stripping,
percent (0.5%), two additional passes of the roller are
scarifying and re-compaction of topsoil containing
required and the leveling procedure shall be repeated. If
unsuitable organic material, as detailed in Item 3 of
the average settlement is then less than half of one
Paragraph 2.5.3.3 is not measured but shall be considered
percent (0.5%), of the average compacted layer thickness
as subsidiary work the costs of which are deemed to be
the test is deemed complete. If not, this step shall be
included in the rates for excavation and borrow excavation
repeated.
in Sub-sections 2.3 and 2.4
7 The total number of passes of the rolling equipment
7 Scarifying old pavement beds, construction of the
necessary to obtain the required result will establish the
trial embankment section if it is outside the pavement,
minimum number of passes to be used on the rock
foundation, preparation, testing, including furnishing and
embankments. However, in no case shall the number of
using an approved type electronic compaction meter and
passes be less than five (5).
grid pattern consolidation surveys, and all other ancillary
8 This verification procedure shall be conducted for embankment work are not measured, but shall be
each change of material and at least once each week considered as subsidiary work the costs of which are
during the initial stages of construction until a reliable deemed to be included in the rates for excavation and
rolling pattern is established. The frequency verification borrow excavation in Sub-sections 2.3 and 2.4
procedure can then be reduced as approved by the
Engineer. 2.5.6 Basis of Payment
9 Documentation of the rockfill compaction tests shall
1 No separate payment will be made for any work in
be maintained by the Contractor in the project records and
this Sub-section 2.5. The cost of all work for embankments
shall be copied to the Engineer.
is deemed to be included under Sub-sections2.3 and 2.4.
2.5.4.4 Monitoring Settlement of Rockfill
2.5.7 Items in the Bill of Quantities
1 On completion of the embankment, the Contractor
shall carry out precise leveling of the crest of the 1 No items are included in the Bill of Quantities. All
embankment. This shall consist of leveling transverse items under Sub-section 2.5 are subsidiary to other items.
sections (a minimum of five points) at a maximum spacing
of 30 m along the embankment. These shall be referenced 2.6 Sub-grade Construction
to a stable approved datum. Leveling shall be carried out
at suitable time intervals until the average rate of 2.6.1 Description
settlement over a period of one month does not exceed
0.1 mm per day. No permanent pavement construction 1 This Subsection describes construction of the sub-
will be permitted until the specified criteria are achieved. grade layer and preparing the sub-grade surface ready to
Adequate time shall be allowed in the construction receive the pavement structure including shoulders, all as
program for the settlement survey. shown on the Drawings.
2 The sub-grade layer is the 200 mm minimum depth
2.5.5 Method of Measurement of selected material immediately below the sub-grade
surface, or as defined in the Drawings or directed by the
1 No separate items are included in the Bill of
Engineer.
Quantities for embankments. The cost is deemed to be
included in the items for excavation and borrow 3 Wherever shallow ground water is expected under
excavation stated in Sub-sections 2.3 and 2.4.. the roadway and wherever damage to the pavement
layers is potential due to water impact, a suitable
subsurface drainage blanket shall be installed under the

♦ 2-12 ♦
copy 249
sub-grade of the roadway. Drainage blanket is a course of 5 The layer directly underneath the drainage blanket
washed granular material placed to cut off upward and the one directly above it shall satisfy the following
capillary flow of pore water under paved areas, where and filter criteria:
as shown on the Drawings.
i. The 15% size of filter (D15 Filter) shall not be
2.6.2 Materials greater than 4 times the 85% size of the
1 Sub-grade material shall consist of suitable materials surrounding material (D85 Surrounding
of Classes A-1, A-2-4 or A-2-5 having a 4-day soaked CBR material):
of not less than 25% when tested in accordance with D15 Filter < 4 D85 Surrounding material.
AASHTO T 193 when compacted at 100% of modified ii. The 15% size of filter (D15 Filter) shall not be
proctor AASHTO (T-180-D) and having a maximum P.I. of less than 4 times the 15% size of the
12% and Gypsum Content not exceeding 3%. The surrounding material (D15 Surrounding
Maximum Dry Density of Sub-grade material shall be material):
equal or greater than 1.9 t/cu.m. Sub-grade gradation shall D15 Filter > 4 D15 Surrounding material.
be reasonably smooth without gap grading. All material iii. The 50% size of filter (D50 Filter) shall not
shall pass 75 mm sieve. The percent of material passing exceed 25 times the 50% size of the
the 0.075 mm (No. 200) sieve shall not exceed 18% and surrounding material (D50 Surrounding
shall not be less than 5%. Where directed by the Engineer, material):
the Contractor shall screen the sub-grade material at his
D50 Filter < 25 D50 Surrounding material.
own expense. The top 200mm sub-grade material shall
iv. The plasticity index of the portion of all filter
not contain more than 0.2% total Sulphate content and
materials passing sieve # 40 shall not exceed
0.05% total Chloride content.
6%.
2 If a drainage blanket is shown on the Drawings to be
The filter materials shall not contain more than
installed directly underneath the sub-grade, the sub-grade
5% material passing through sieve # 200.
material shall respect the filter criteria specified under
Item 5 of this Clause 2.6.2.
2.6.3 Construction Requirements
3 Aggregate material for use in drainage blanket shall
be rapid draining crushed stone, or crushed or uncrushed 2.6.3.1 Sub-grade in Cut
gravel conforming to the properties stated in Table 2.6.2.1
1 Where the sub-grade is located in rock, the sub-grade,
below:
unless shown otherwise on the Drawings, shall be
Property Range undercut to a depth of 200 mm by drilling or blasting as
Permeability in m/day – ASTM D2434 300 - 1500 directed. No rock shall project more than 50 mm above
the undercut surface elevation. The sub-grade layer shall
Effective Porosity 0.25
then be constructed using approved sub-grade material.
% Fractured Faces – (COE Method) Min. 75%
Cu (D60/D10) > 3.5 2 Where the sub-grade is on in-situ soil which is of a
L.A. Abrasion – AASHTO T96 < 40 quality and CBR value at least equal to those specified for
California Bearing Ratio (CBR) – sub-grade, the 200 mm depth of such material
> 30% immediately below top of sub-grade shall be scarified and
AASHTO T193
Table 2.6.2.1: Properties of Rapid Draining Materials for all roots, sod, vegetable and other undesirable matter and
stones larger than 75 mm in any dimension shall be
use in Drainage Blanket
removed. The material shall then be brought to uniform
4 The gradation of the rapid draining material for use moisture content within the specified range and
in drainage blanket shall be as provided in Table 2.6.2.2 compacted to 100% AASHTO T 180 (Method D) maximum
below: density.
3 Where the sub-grade is on in-situ soil which is
Sieve Designation (mm) Percent Passing unsuitable for retention as the sub-grade layer, such
38.0 (1-1/2 in.) 100 material immediately below the top of sub-grade layer
25.0 (1 in.) 70 – 100 shall be sub-excavated to a depth of 200 mm, hauled away
19.0 (3/4 in.) 55 – 100 and disposed of unless approved for use as embankment
fill. The sub-grade layer shall then be constructed using
12.5 (1/2 in.) 40 – 80
approved sub-grade material, as specified for sub-grade in
9.5 (3/8 in.) 30 – 65 embankment. If the material below sub-grade does not
4.75 (No. 4) 10 – 50 consist of suitable materials satisfying the requirements of
2.4 (No. 8) 0 – 25 top 600mm embankment, it shall be excavated for further
1.2 (No. 16) 0–5 200mm and replaced by suitable material to satisfy the
requirements of the top 600mm of the embankment.
Table 2.6.2.2: Gradation of Rapid Draining Materials for
use in Drainage Blanket

♦ 2-13 ♦
copy 249
4 The underlying natural material shall be scarified, ii. Place drainage blanket in layers not exceeding
leveled and rolled. The surface of the natural soil shall be 150mm compacted thickness each, with no
approved by the Engineer before placement of suitable layer less than 75 mm thick when compacted.
material.
2.6.3.6 Preparation of Sub-grade Construction on
2.6.3.2 Sub-grade in Embankment Sabkha and Gypsum Rich Soils
1 The 200 mm minimum depth of embankment 1 Where the road sub-grade passes over sabkha areas
immediately below top of sub-grade shall consist of or gypsum-rich soils with a high water table the
selected, approved sub-grade material. The material shall Contractor shall take the special precautions mentioned
be spread in one layer over the full width of the top of below if the sabkha or the gypsum-rich soils are
embankment, brought to a uniform moisture content encountered within the top 1m below the sub-grade level.
within the specified range and compacted to 100%
2 These precautions shall include but shall not be
AASHTO T 180 (Method D) maximum density.
limited to the construction of suitable temporary haul
2.6.3.3 Surface Tolerances roads for all construction plant operating in the area. Such
haul roads shall be constructed, at the Contractor’s
1 All finished levels, lines and grades shall be in expense. using rock fill and geotextiles as necessary to
accordance with the details shown on the Drawings. Each ensure a safe stable surface,
cross section shall be checked at maximum intervals of 20
3 If directed by the Engineer the Contractor shall
m, at each change in cross slope and elsewhere as
construct sub-grade and embankment (where applicable)
directed.
over sabkha areas or gypsum-rich soils with a surcharge
2 The tolerances on levels of finished sub-grade, top of of excess material that shall remain in place till all
embankment under the sub-grade layer and sub- appreciable settlement has stopped. The Contractor shall
excavated (undercut) surface shall be as given in Table provide a means of monitoring the settlement. The
2.6.3.1. Engineer shall decide when appreciable settlement has
stopped.
Surface Tolerances
4 Unless a specific treatment for using geotextiles,
Finished Sub-grade Soil +10 or -30 mm geogrids or geosynthetics is described elsewhere in the
contract, work over sabkha or gypsum-rich soils shall
Rock (if approved) +50 or -50 mm
consist of initially stabilizing the existing weak soil by
Top of Embankment or Sub- laying and rolling rock fill layer type 1 according to Table
+10 or -30mm
excavated Surface Soil 2.6.3.2 below. This operation should be continued by
Table 2.6.3.1: Tolerances on Elevations of Finished Sub- adding and rolling type 1 rock fill layer with steel vibratory
grade roller till the layer is completely stabilised.
5 A layer of geotextile fabric shall be laid over the
3 If instructed by the Engineer, when the finished sub-
compacted type 1 pervious material. A layer of 50mm
grade surface is tested with a 4 m long straightedge
pervious backfill type 2 according to Table 2.6.3-2 shall be
placed parallel to, or at right angles to the centerline, the
laid over the stabilised layer to protect the geotextile fabric.
maximum depression of the surface from the straight
edge shall be 30 mm.
US Standard Percentage Passing
2.6.3.4 Maintenance of Finished Sub-grade Sieve Size Type 1 Type 2
6 inch 100 -
1 The finished and approved sub-grade shall be
5 inch 85 - 100 -
continuously maintained in a smooth, well compacted and
4 inch 75 - 90 -
properly drained condition until the sub-base (or base)
2 inch 45 - 65 -
course is constructed. Reapproval of the sub-grade will be
required if the overlying course is not constructed within 1 1/2 inch 35 - 55 -
14 days of sub-grade completion or if the sub-grade layer 3/4 inch 20 - 35 100
is damaged by traffic or any other causes prior to the 1/2 inch 10 - 25 95 - 100
placement of the sub-base layer. 3/8 inch 5 - 20 70 - 100
No.4 - 0 - 55
2.6.3.5 Drainage Blanket No.8 - 0 - 10
1 Wherever and as shown on the drawings, place No. 16 - -
drainage blanket under roadway pavements on prepared No. 200 - 0-3
sub-grade as follows: Table 2.6.3.2: Definition of Type 1 and Type 2 Rockfill
i. Compact drainage blanket to required cross Materials for Sabkha Treatment
sections and thickness to not less than 95
percent of maximum dry density according to
ASTM D 1557.

♦ 2-14 ♦
copy 249
6 A layer of 200mm thick capillary break rock fill type 1 2.6.5 Basis of Payment
shall be laid over type 2 pervious backfill to receive the
1 The amount of completed and accepted work,
required road layers after the above operation.
measured as provided for above, will be paid for at the
unit rates for the relevant items in the Bill of Quantities ,
2.6.3.7 Preparation of Subgrade Construction on top of which rate shall be full compensation for supplying
Dune Sand materials, transporting, hauling and placing, for labor,
equipment, tools and other items necessary for the proper
1 Dune sand roadbed shall be compacted only after
completion of the work.
being confined by special means and methods that shall
be approved by the Engineer. These methods may include
the construction of an edge dyke of various materials on
2.6.6 Items in the Bill of Quantities
both sides of the road to provide the necessary i. Sub-grade preparation in cut (sq.m.)
confinement. ii. Drainage blanket (cu.m.)
2 Dune sand material will be allowed to receive dry iii. Preparation of sub-grade
compaction only if the material is tested and proven to be construction on sabkha or
A-3 type and only in case where the Proctor test showed a gypsum-rich soils (sq.m.)
maximum dry density at 0 % moisture. Otherwise, the iv. Preparation of sub-grade construction on top of
material shall be brought to uniform moisture content dune sand (sq.m.)
within the specified range and shall be compacted to 100%
AASHTO T 180 (Method D) maximum density. 2.7 Excavation and Backfilling for
Structures
2.6.4 Method of Measurement
1 Sub-grade layer in embankment is not measured 2.7.1 Description
separately but is included as part of the computation for
1 This Sub-section describes excavation in any
the volume of embankment.
material for buildings and pump houses; bridges, culverts,
2 Sub-grade preparation in cut is be measured by sq.m. pipe culverts, under-drains; drainage and utility
of top width of sub-grade layer computed from cross structures; flood areas cut-off-walls; retaining walls of all
sections shown on the Drawings. The rate shall include for types; and for other major and minor structures; including
all excavation below top of sub-grade, scarifying removing all necessary clearing and grubbing; bailing; drainage;
undesirable matter and compacting of replaced matter pumping; dewatering; sheeting; temporary shoring and
where necessary. cribbing; construction of temporary cofferdams or cribs;
3 Drainage blanket shall be measured by cubic meters backfilling with suitable approved material to the level of
of aggregate materials, furnished, screened, washed, original ground or to the top level of any adjacent
placed, spread, compacted, completed and accepted. embankment; and disposal of all surplus or unsuitable
Measurement shall be of volumes computed from the excavated material, all as shown on the Drawings, or as
cross sections shown on the Drawings and of the field directed by the Engineer.
measurements of area and compacted depth of each trial 2 The work also includes removal of those portions of
section. No allowance shall be made in the measurement existing structures below ground which would in any way
for overdepth and/or overwidth construction, regardless of obstruct or interfere with construction of new structures.
the Engineer’s permission for it to remain in place.
3 The Contractor will be deemed to have satisfied
4 Sub-grade construction on sabkha or gypsum-rich himself, at the time of tendering, as to the type and nature
soils shall be measured by sq.m. of top width of sub-grade of soils and rock that will be encountered in structural
layer computed from the cross sections shown on the excavations.
Drawings The rates shall include for all excavation below
top of sub-grade, scarifying, removing undesirable matter, 2.7.2 Excavation
construction of temporary haul roads, any rockfill,
geotextile or geo-synthetics used, surcharge materials, 2.7.2.1 General
compaction and completion and any accessories all as
1 The Contractor shall notify the Engineer a sufficient
specified in Paragraph 2.6.3.6 and as shown on the
time in advance of the beginning of any excavation for
relevant drawings,.
structures so that the Engineer may, where necessary,
5 Sub-grade construction on top of dune sand shall be survey and record the cross sectional or longitudinal
measured by sq.m. of top width of sub-grade layer elevations and measurements of the existing ground and
computed from cross sections shown on the Drawings. existing structures affected by the proposed structure.
The rates shall include for all excavation below top of sub- Any materials removed or excavated before these
grade, scarifying removing undesirable matter, installation measurements have been taken and approved by the
and dismantling of the confinement structure or side Engineer will not be paid for.
embankment and compacting the soil layers as specified

♦ 2-15 ♦
copy 249
2 The Contractor shall be responsible for the safety of 2.7.2.3 Excavation for Major Structures and Bridges
all foundation and trench excavations whether supported
or not. Approval of the Contractor's support system or 1 Foundations for buildings, pump houses and other
omission of a support system for any excavations will not major structures and bridges, shall be excavated in
absolve the Contractor from his sole responsibility in this accordance with the dimensions as shown on the
regard. Drawings and shall be of sufficient size to permit placing
of the full width and lengths of the footings.
3 The Contractor shall take all necessary precautions,
including shoring or other means, to protect employees 2 Excavation shall be carried down to the levels shown
and others in the excavation and on the ground above. on the Drawings or as established by the Engineer based
on previous investigations. No concrete shall be placed
4 The sides of all foundation pits and trenches
prior to approval of the excavation pit.
shallower than 1.5m shall be vertical and adequately
supported unless otherwise shown on the Drawings. Sides 3 Unless shown otherwise on the Drawings, the
more than 1.5 m in depth shall be sloped at a stable slope bottom of all excavations shall be covered with a 75mm
or supported in an approved manner unless the material minimum depth of lean (blinding) concrete Class 15 to
through which the pit or trench is cut is deemed to be serve as a working platform.
sufficiently self-supporting and not requiring support. 4 Foundation pits or trenches shall be of sufficient size
5 Pits and trenches shall be kept free from water until and provide minimum sufficient working space to permit
footing concrete has been placed or pipes have been construction of structures or structure footings of the full
installed. The Contractor shall minimize, as far as width and length shown on the Drawings.
practicable, the length of time excavated areas are open. 5 Where footings are constructed using formwork, the
The Contractor shall be responsible for repair of damage excavations shall generally not extend more than 500 mm
due to weather, equipment, and other causes during beyond the maximum dimension on each side of the
periods when the excavations are left open. proposed footing unless additional working space is
6 The Contractor shall plan the Works so that no clearly required and approved by the Engineer. Any
excavation is left in an exposed condition for a period unauthorized overwidth of excavation beyond the lateral
greater than 30 days unless otherwise approved. limits or depths shown on the drawings or approved by
the Engineer shall be backfilled with selected fill or lean
7 Where excavation is adjacent to public highways and
concrete as directed by the Engineer at the Contractor’s
walkways, warning lights, barriers and barricades shall be
expense.
provided to the Engineer’s satisfaction. No excavation
shall be left in an exposed condition for more than 7 days 6 Where footings are located, in or adjacent to firm,
unless otherwise approved. original ground and where formwork is not required or
ordered, any unauthorized overdepth excavation below
8 For excavation in material sensitive to moisture (stiff
the approved elevation of base of footing shall be
clays, marls, etc.) the excavation shall be cleaned and a
backfilled with blinding concrete.
concrete blinding layer cast immediately on completion of
the excavation. 7 Where excavation to rock foundation is required, the
excavation shall proceed in such a manner as to allow the
9 The Contractor shall notify the Engineer of any sign
solid rock to be exposed and prepared in horizontal beds
of failure or cracks within or around the excavation
or properly serrated for receiving the concrete. All loose
immediately when such signs are noticed.
and disintegrated rock and thin strata shall be removed.
2.7.2.2 Temporary Support System 8 When unstable material or other unsuitable material
is encountered below foundation elevation, the Contractor
1 When a temporary support system is required to
shall excavate such material and replace it with suitable
protect adjacent property or to protect the public during
backfill material or concrete to the depth as directed by the
construction, the Contractor's design for such support
Engineer.
system shall be submitted for approval prior to
commencing its construction. 9 If temporary works are required for maintaining the
excavation dry, the Contractor shall be responsible for the
2 All temporary support systems shall be designed
design and execution of the works. The proposed design
with adequate factors of safety to serve with minimal
shall be submitted to the Engineer for approval but, such
maintenance, for the duration of its intended use, and
approval shall not relieve the Contractor of his sole
shall include adequate safety provisions to protect the
responsibility in this regard.
public from construction activities.
3 Notwithstanding any approval of temporary support 2.7.2.4 Excavation for Box Culverts, Pipe Culverts and
systems, the Contractor shall be solely responsible for the Miscellaneous Structures
adequacy of their design and construction and for
maintenance and all necessary safety precautions 1 Excavation shall be carried out to the limits required
associated therewith. for construction and to the depth required for bedding
material or removal of unsuitable material. All trench

♦ 2-16 ♦
copy 249
excavation shall proceed upgrade, commencing at the expense by provision of an in situ concrete cradle or
downstream end. increased thickness of concrete bedding as directed, or by
2 Foundation material supporting the bedding or the use of other approved suitable materials.
structure shall be AASHTO M 145 Class A-1-a, A-1-b or A- 10 Over width excavation for in situ concrete pipes shall
2-4 compacted to 95% AASHTO T 180 maximum density. be made good at the Contractor's expense by concrete
If the natural material does not meet the classification bedding brought up to the external haunch of the pipe or
requirements, it shall be sub-excavated to a depth of at by the use of other approved suitable materials.
least 200mm and replaced with material meeting the 11 Over depth excavation for metal pipes shall be made
specified requirements. Any rock or hard material within well by furnishing and backfilling an approved, fine
200 mm of the bottom of the pipes shall be similarly sub- granular material containing not more than 0.5% of
excavated and replaced with material meeting the combined chlorides and sulfates.
specified requirements.
3 If no special bedding material is required, the 2.7.3 Backfilling
foundation for precast and prefabricated culverts shall be
formed to the shape of the culvert, including all 2.7.3.1 General
protrusions. The shaping shall extend to 25% of the 1 The Contractor shall obtain approval for his proposed
height of culvert. method and rate of placing of backfill before work
4 Where rock is encountered in the toe wall excavation commences.
for concrete box culverts or concrete cut-off-walls for 2 Backfill materials shall be uniformly graded granular
floodway, embankment protection and pipe culverts and material, capable of being compacted to required
the rock is of such quality as will prevent erosion, part of compaction, and having adequate permeability to permit
the toe wall may be eliminated in the rock strata as free drainage through it. Backfill material shall also
directed and the toe wall shall be keyed into the rock strata conform to the requirements listed in Table 2.7.3.1 below:
in a satisfactory manner. The minimum thickness of the
key shall be as shown on Drawings or as instructed by the Surface Requirements
Engineer.
Minimum D10 value 1 mm
5 Precast concrete pipes and metal pipes shall be
installed in trenches cut into previously constructed and Maximum Plasticity Index 10 per cent
compacted embankment or from top of sub-grade. Unless
Requirements for bridges, culverts etc. shall be as
otherwise shown on the Drawings, trench width shall not
specified in subsequent sections
be greater than the external diameter of the pipe plus 500
mm on each side. Table 2.7.3.1: Requirements for Backfill Materials
6 In the case of metal pipes, the bottom of the trench 3 Backfill material shall not be placed against any
shall be shaped to a template so that at least 10% of the structure until approval is given. Unless otherwise shown
overall height of pipe or arch will be in contact with the on the Drawings structures shall be backfilled to the same
bottom of the trench as excavated. Recesses shall be requirements as specified for the adjacent embankment.
excavated to receive any parts of the pipe which extend
4 Backfill shall be placed in level layers for the full
below the outside perimeter. Where rock, hardpan or
width of the excavated area until the elevation of the
other unyielding material is encountered it shall be
original ground or surrounding embankment is reached.
removed below design grade or as ordered by the
Backfill next to walls, between columns or in other
Engineer for a depth of at least 200 mm and backfilled as
confined areas, shall be compacted by approved hand or
specified.
portable equipment.
7 Trenches for cast in-situ pipes shall be cut into
5 Each successive layer of backfill shall contain only
previously constructed and compacted embankment from
sufficient material to ensure proper compaction and in no
top of sub-grade or embankment height or twice the
case shall any layer be greater than 150 mm thickness
nominal span of the pipe whichever is less. Trench width
(after compaction). The moisture content of the backfill
shall not be greater than the external diameter or span of
material shall be uniform and within the moisture range
pipe plus 500 mm on each side when external forms are
designated. Backfill material shall be compacted to 95% of
used, or the external span of pipe including protection
the maximum density as determined by AASHTO T 180
plus 100 mm on each side when external forms are not
(Method D).
used.
6 Jetting of fills or other hydraulic methods involving
8 When excavation is required for installation of ducts,
or likely to involve liquid or semi-liquid pressure will not
the Contractor shall notify the Engineer upon completion
be permitted.
of the excavation. No duct shall be laid until the depth
and cross section of the excavation has been approved. 7 Water shall be drained from the areas to be backfilled
wherever practicable. In cases where, in the opinion of
9 Over-width or over-depth excavation for precast
the Engineer, it is not practicable to drain the areas to be
concrete pipes shall be made good at the Contractor's
backfilled, the initial backfill material shall consist of

♦ 2-17 ♦
copy 249
crushed, open graded material conforming to the 5 Unless shown otherwise on the Drawings, when
gradation given in Table 2.7.3.2 below: special permeable backfill (sheathing) is to be placed
against the back faces of retaining walls or wing walls, it
ASTM Sieve Percentage Passing Size shall consist of a continuous covering of approved type
3/8" 100 proprietary filter cloth protected by a continuous wall of
200mm minimum thickness precast, porous (no-fines)
No. 4 < 85 concrete blocks laid with dry joints. Prior to construction
of the block wall, ensure that all underdrains or perforated
No. 30 < 45
pipes are laid along the base of the wall under the
<5 sheathing, as shown on the Drawings.
No. 200
6 Backfill material for culverts, pipe culverts and
Table 2.7.3.2: Requirements for Open Graded Backfill - miscellaneous structures within 300 mm of any part of the
Gradation structure shall be Class A-1-a, A-1-b or A-2-4. The 200 mm
minimum thickness of sub-grade layer shall consist of
Such material may be deposited below the standing water
approved sub-grade material placed and compacted to
level without compaction. Above the water level normal
100% maximum density as specified under Sub-section
laying and compaction will be considered.
2.6 – ‘Sub-grade Construction’. The backfill shall be
8 Additional water to be added during placement of completed to the level of the original ground or to the top
backfill material to achieve required compaction shall be elevation of any adjacent embankment.
fresh water or brackish water approved by the Engineer.
7 Backfilling around and over pipe culverts shall not
9 Minimum tests required during backfilling operations commence until headwalls and wingwalls have been
to verify material are: constructed and attained the specified 28-day strength.
- One Proctor test for each structure.
8 Water used for compaction of backfill around metal
- One gradation of materials when materials
pipes and reinforced concrete structures shall be from an
changed.
approved source and shall not contain more than 0.5%
- One plasticity index and field density for 50%
combined chlorides and sulphates nor contain other
of the layers and for each footing and
potentially harmful minerals.
abutment as instructed by the Engineer.
9 When pipes or other structures temporarily extend
2.7.3.2 Backfilling for Box Culverts, Pipe Culverts, above the grade of the partially constructed embankment,
Bridge and Building Foundations, Walls, the Contractor shall construct the fill over the structure of
sufficient depth to protect the structure from any damage
Abutments and Miscellaneous Structures
resulting from construction or other traffic.
1 Structures shall not be subject to the pressures of 10 The Contractor shall complete the backfill around box
backfilling or to live loads until the 28-day strength of the culverts to the level of the original ground line and to the
concrete has been reached, unless a shorter period is full width of excavation area. If the top of culvert extends
approved in special circumstances where the load is above the original ground line the Contractor shall
sufficiently small as not to constitute a risk of any damage continue the backfill to the top of culvert and for a width of
to the structure in the opinion of the Engineer. This period 3 m on each side of the culvert for the full width of
may be extended if subnormal curing conditions exist. roadway embankment. If the embankment is in place at
2 Backfill placed around culverts shall be deposited on the time of backfilling, the Contractor shall backfill around
both sides to approximately the same level at the same the culvert to the top of embankment.
time. Special care shall be taken to prevent any wedging 11 Backfill around pipe culverts shall be completed to
action against the structure and slopes bounding the the level of original ground line and to the full width of
excavation shall be stepped, where necessary, to prevent excavation area. If the top of the culvert extends above
such wedge action occurring. the original ground line the Contractor shall continue the
3 All backfill intended to support false work loads, backfill to the top of culvert for a width of 1.5 times the
including temporary fills shall be selected to support the maximum external width of the culvert on each side of the
required load. As a minimum, such material shall be culvert centerline to the full width of the roadway
AASHTO M 145, Class A-1-a, A-1-b or A-2-4, compacted to embankment. If the embankment is in place at the time of
90% of the maximum density as determined by AASHTO T backfilling, the Contractor shall backfill around the culvert
180 (Method D). to the top of culvert or as shown on the Drawings.
4 Backfill around bridge and building foundations, 12 Any existing roadway pavement cut through,
abutment walls and retaining walls shall be completed to damaged or removed during excavation for pipe culvert
the level of the original ground line and to such heights installation shall be reinstated, after pipe installation and
above original ground line or to the levels as shown on trench backfilling, using approved base and surfacing
the Drawings. Care shall be exercised to prevent forward course materials at least equivalent to those in the original
movement of the wall. pavement. Materials and construction shall conform to the

♦ 2-18 ♦
copy 249
relevant requirements Sections 3 and 4 of this 7 Unless specified otherwise in the special
specification. specifications, temporary cofferdams, temporary support
13 Miscellaneous structures other than pipe culverts system, bailing, drainage, dewatering, pumping, sheeting,
shall be backfilled in accordance with the methods concrete blinding layers and all other Temporary Works
specified. Compaction of backfill when structures are shall not be measured for direct payment, but shall be
outside the roadway right-of-way or in approach roads, considered as subsidiary work the costs of which will be
minor roads or similar areas, shall be to 90% of maximum deemed to be included in the rates for structural
density as determined by AASHTO T 180 (Method D). excavation.
8 Backfilling to structural excavation shall not be
2.7.4 Method of Measurement measured separately but is considered as subsidiary work
the cost of which are deemed to be included in the rates
1 All structural excavation, of whatever type, shall be
for structural excavation
measured as ‘unclassified’ which shall be deemed to
include all materials encountered of any nature, including 9 Any blinding concrete used at the bottom of
silts, clays, sand, gravel and granular materials and excavations, as shown on the Drawings or as instructed by
fractured, jointed and solid rock. the Engineer shall be measured and paid for in accordance
with the relevant method of measurement under Clause
2 Structural excavation is measured by cubic meter of
5.1.5 of Section 5 ‘Concrete and Concrete Structures’.
material excavated for the major structures hauled away
and disposed of as directed, or stockpiled. Measurement
2.7.5 Basis of Payment
of structural excavation shall be from original ground
levels or ground levels after removal of all unclassified 1 The amount of completed and accepted work,
highway excavation. Limits shall not be greater than measured as provided for above, will be paid for at the
vertical planes 500 mm from the maximum dimension, on unit rates for the various items in the Bill of Quantities ,
each side of the footing or other controlling portion of the which rate shall be full compensation for equipment, tools,
structure. Where structures are constructed against labor, materials, transporting, hauling, placing, and for
natural ground or rock, excavation limits shall be the other items necessary for the proper completion of the
dimensions of the structure as shown on the Drawings. work.
Bottom limits shall be the ordered foundation levels. Only
material excavated from its original position shall be 2.7.6 Items in the Bill of Quantities
measured for payment. No measurements shall be made
of structural excavation in embankments previously i. Unclassified structural excavation
constructed by the Contractor. (depth 0 to 2m) (cu.m.)
3 Additional excavation in unstable material or other ii. Unclassified structural excavation
unsuitable material encountered below foundation level (2m < depth < 4m) (cu.m.)
shall be measured as part of the unclassified structural iii. Unclassified structural excavation
excavation.
(depth > 4m) (cu.m.)
4 Structural Excavation under Water shall be measured
iv. Structural Excavation under Water (cu.m.)
by cu.m. of material excavated for the major structures,
hauled away and disposed of as directed, or stockpiled on
or in the vicinity of the Works, and the excavated areas
backfilled, completed and accepted. 2.8 EARTHWORK FOR PIPE
5 Unauthorized overdepth and overwidth excavation in
TRENCHES
soil and rock and the backfill material including blinding
concrete required in such cases, shall not be measured for 2.8.1 Description
direct payment, but shall be considered as subsidiary work 1 This Sub-section describes requirements for
the costs of which will be deemed to be included in the excavation of trenches in any material for water supply,
rates for structural excavation sewage, stormwater drainage and irrigation pipes, and all
6 Structural excavation in any material or under water other associated works, including all necessary clearing
for box culverts less than one sq.m. in external cross and grubbing, bailing, draining, shoring, planking,
section, and structural excavation for pipe culverts, strutting and supporting the sides of excavation. The work
underdrains (subsoil drains), pits, catchbasins, manholes, includes backfilling with suitable approved material and
inlets, energy dissipaters, slope protection, fence posts, disposal of the excess material to designated and
guardrail posts, lighting columns, sign posts, signal approved tip locations.
supports and all other minor structures, shall not be
measured for direct payment, but shall be considered as
subsidiary work the costs of which will be deemed to be
included in the rates and prices for the relevant items..

♦ 2-19 ♦
copy 249
2.8.2 Materials i. For pipes not exceeding 65 mm diameter:
Nominal diameter plus 300 mm.
2.8.2.1 Backfill Material ii. For pipes over 65 mm and not exceeding 600
1 Initial backfill (up to 300 mm above the top of the mm diameter: Nominal diameter + 600 mm.
pipe) shall be selected fill, sand or other approved material iii. For pipes over 600 mm diameter: Nominal
and shall conform to the following: diameter + 1000 mm.
7 Where the above specified trench widths are
Standard Percent by Weight Percent by exceeded; the Contractor shall provide additional pipe
Sieve Size Passing for Pipes Weight Passing
protection or pipes of increased strength if the Engineer
(mm) other than uPVC for uPVC Pipes
calls for such measures, all at his own expense.
19 100 -
8 Excavation of trenches with battered sides will not be
4.76 25 – 100 100 permitted within 4m of any building or other structure.
9 When the pipes are to be laid in embankments or
1.19 10 – 75 25 – 75
other fill areas, the embankment or fill area shall first be
0.354 5 – 30 10 – 30 filled and compacted as specified to the proposed finished
grade or to a height of at least 300 mm above the top of
0.177 3 – 10 3 – 10
pipe whichever is lower. The trench shall then be
0.074 0–5 0–5 excavated as in undisturbed material.
10 When pipes are to be laid under existing pavements,
Table 2.8.2-1: Requirements for Initial Backfill - Gradation
trenches shall be excavated carefully and to minimum
2 For GRP pipes, graded crushed stone 2.83-8 mm shall widths. Methods that will give straight and vertical face
be used for initial backfilling. shall be used. The pavement shall be kept at its original
level and condition.
3 The remainder of the trench shall be backfilled with
suitable material either from material removed in the 11 In combined trenches where one pipe is at a lower
course of excavating the trench, or imported from level than an adjacent pipe the following shall be applied:
approved borrow pit. In either case the backfill material i. The whole trench shall have a depth related to
shall be non-plastic. The percentage by weight passing a the lower pipe and the thickness of the bedding
No. 200 (0.075 mm) sieve shall not exceed 15%. The shall be increased to the upper pipe as
percentage passing a 63 mm sieve shall be 100. necessary.
ii. The lower pipe shall be backfilled with
2.8.3 Construction thoroughly compacted granular material up to
a level of 0.30 meters above the higher pipe.
2.8.3.1 Excavation for Pipe Trenches
12 Final excavation to the correct grade level for trench
1 The Contractor shall not commence excavation of beds shall be carried out immediately before laying beds
any section of work until a full supply of pipes and fittings or pipes. Unstable material, rock projections, boulders and
is available for that section. hard spots shall be removed and replaced with approved
2 During excavation, material suitable for backfilling filling material, that will be compacted as instructed. Local
shall be piled at sufficient distance from the sides of the soft spots shall be compacted by tamping in bedding
trench as to avoid overloading and prevent cave in. All material.
excavated material not required, or unsuitable for 13 The bottoms of trenches shall be accurately graded
backfilling shall be removed and carted away to an to provide uniform bearing and support for the bottom
approved dumping area. quadrant of each section of the pipe. Bell holes shall be
3 Trenches shall be excavated to such depths as will excavated to the necessary size at each joint or coupling to
permit the pipes to be laid at elevations, slopes or depths eliminate point bearing. Any material that may cause point
of cover indicated on the drawings, and at uniform slopes bearing shall be removed.
between indicated elevations. 14 The Contractor shall report to the Engineer any
4 Where excavation depth exceeds the level indicated unsuitable or weak ground material that may be found
on the drawings and is not authorized in writing by the below the indicated excavation levels before executing
Engineer, the Contractor shall place backfill or concrete to any trimming of the excavation, pipe laying, concreting, or
the required bottom level, as instructed by the Engineer, other work. Where, in the judgment of the Engineer the
all at his own expense. bottom of the trench is unsuitable, such material shall be
removed to the width and depth ordered by the Engineer.
5 Trenches shall be excavated with vertical sides
The trench shall then be made up by backfilling with
between the bottom level and 300 mm above the top of
approved material.
the pipe.
15 Where rock is encountered, the trench shall be
6 Trench width up to 300 mm above the crown of the
excavated to 150 mm below bed level and replaced with
pipe shall not exceed the following:
granular material, concrete, or blinding grade as directed.

♦ 2-20 ♦
copy 249
2.8.3.2 Backfilling 2.8.4 Method of Measurement
1 Trenches shall not be backfilled at joints until after 1 Trench excavation and backfill shall be paid for per
that section of the pipeline has successfully passed the cu.m. measured in horizontal layers for the different depth
specified tests. categories shown in the Bill of Quantities. Trench length
shall be measured between outer surfaces of manholes or
2 Initial backfill or surround up to a level of 300 mm
chambers. Trench width shall be as specified or shown on
above top of the pipe, shall be placed and hand
Drawings. Depth of excavation shall be the depth of every
compacted in 150 mm layers. The backfill shall be brought
horizontal layer. Excavation for bedding is included as
up evenly on both sides of the pipe for the full length of
trench excavation.
the pipe. Care shall be taken to ensure thorough
compaction of the fill under the haunches of the pipe. 2 Rates for trench excavation and backfill shall include
for:
3 Suitable backfill shall be placed and well compacted
i. Excavating in any material encountered
in layers not exceeding 150 mm thick after compaction.
including rock.
Heavy compactors shall not be used until there is 600 mm
ii. Blasting, barring, wedging or other quarrying
cover over pipes.
methods for rock excavation.
4 Unless otherwise specified each layer shall be iii. Excavation at any level.
compacted to at least 95% maximum density for iv. Excavating curved on plan.
cohesionless soils and 90% maximum density for cohesive v. Allowance for working space.
soils. vi. Increase in bulk for excavating.
5 Backfilling trenches for pipes with concrete beds and vii. Excavating below water table and dewatering
or surrounds shall not start before 24 hours after placing as necessary.
concrete. Heavy compactors shall not be used and traffic viii. Keeping excavations free from water.
shall not be allowed before the elapse of 72 hours after ix. Leveling, compacting, trimming and grading
placing the concrete. bottoms and trimming sides and bottoms of
6 When the backfill material is too wet from rain or excavation.
excessive application of water, no compaction shall be x. Supporting the sides of excavation.
done. In this case the work shall be suspended until the xi. Filling with material as specified and
previously placed and new materials have dried compacting around pipes and beds multiple
sufficiently to permit proper compaction. Other measures handling of excavated material and excavation
shall be taken if necessary to obtain proper compaction. from borrows and transporting about the Site.
xii. Segregation of the various classes of excavated
7 Temporary crossing are to be provided over trenches
spoil and stock piling as may be directed by the
to prevent construction traffic damaging pipes after
Engineer.
backfilling.
xiii. Disposal of surplus excavated material
2.8.3.3 Restoration of Surfaces including depositing and consolidating where
directed on Site or removing from Site and
1 Restoration of asphalt, concrete, gravel pavements depositing at a tip to be provided and paid for
and the likes shall be of materials and thickness to match by the Contractor.
the existing pavement. Materials and workmanship shall xiv. Pipe bedding, initial backfill or gravel, and final
be in accordance with local authority requirements and as backfill.
directed by the Engineer. xv. Filling over-excavation with material as
2 Restoration of pavement shall be done according to specified
the existing pavement quality and level to ensure that new xvi. Consolidation of primary backfill (initial
pavement matches the existing to provide uniform surface backfill) material using water or hand tamping.
with the existing profile. xvii. Compaction of secondary backfill (main
3 Grassed areas shall be restored by spreading backfill) material.
approved fertile soil over affected area after backfilling. xviii. Reinstatement of unpaved surfaces.
Seeding, fertilizers and water shall be applied until grass is (Reinstatement of paved surfaces shall be
restored to its former condition. made and paid for according to Sections 4 or
12 as appropriate)
4 Surface grading shall be carried out to restore all un-
surfaced areas and any adjoining areas disturbed to
2.8.5 Basis of Payment
provide a level, smooth surface.
5 The Contractor shall proceed with restoration of 1 The amount of completed and accepted work,
surfaces as soon after completion of other work as is measured as provided for above, will be paid for at the
practicable, but in no case more than 10 days after unit rates for the various items in the Bill of Quantities,
backfilling of trenches and other excavated areas. which rate shall be full compensation for equipment, tools,
Restoration shall be completed within 20 days from the labor, materials, transporting, hauling, placing, and for
start of restoration.

♦ 2-21 ♦
copy 249
other items necessary for the proper completion of the
work.

2.8.6 Items in the Bill of Quantities


i. Trench excavation and backfilling (Depth up to 2m)
ii Trench excavation and backfilling (Depth > 2m < 3m)
iii Trench excavation and backfilling (Depth > 3m < 4m)
iv Trench excavation and backfilling (Depth > 4m)

♦ 2-22 ♦
copy 249
Ref. Title Page No. Ref. Title Page No.
3.1 Materials for Sub-Base 3.3.3.8 Maintenance of Completed Base 3-7
and Base Courses 3-1 3.3.3.9 Testing 3-7
3.3.4 Method of Measurement 3-8
3.1.1 Description 3-1
3.3.5 Basis of Payment 3-8
3.1.2 Materials 3-1
3.3.6 Items in the Bill of Quantities 3-8
3.1.3 General Requirements for Materials 3-1
3.1.3.1 Sources and Production 3-1 3.4 Stabilized Base Courses 3-8
3.1.3.2 Stockpiling 3-1
3.4.1 Description 3-8
3.1.3.3 Sampling and Testing 3-1
3.4.2 Materials 3-8
3.2 Granular Sub-Base Course 3-2 3.4.2.1 Soil for Cement Stabilisation 3-8
3.4.2.2 Cement as Stabilising Agent 3-8
3.2.1 Description 3-2
3.4.2.3 Bitumen as Stabilising Agent 3-9
3.2.2 Materials 3-2
3.4.2.4 Lime as Stabilising Agent 3-9
3.2.3 Construction Requirements 3-2
3.4.2.5 Water 3-9
3.2.3.1 Subgrade Surface Preparation 3-2
3.4.2.6 Mix Design 3-9
3.2.3.2 Equipment 3-3
3.4.3 Construction Requirements 3-9
3.2.3.3 Construction of Trial Sections 3-3
3.4.3.1 Surface Preparation 3-9
3.2.3.4 Stockpiling of Granular Material 3-3
3.4.3.2 Construction of Trial Section 3-9
3.2.3.5 Mixing and Spreading 3-3
3.4.3.3 Cement Stabilisation Procedures –
3.2.3.6 Compaction 3-3
Plant Mixing 3-10
3.2.3.7 Tolerances 3-4
3.4.3.4 Cement Stabilisation Procedures -
3.2.3.8 Maintenance of Completed Sub-base 3-4
Batch Mixing 3-10
3.2.3.9 Testing 3-4
3.4.3.5 Cement Stabilisation Procedures -
3.2.4 Method of Measurement 3-4
Continuous Mixing 3-10
3.2.5 Basis of Payment 3-4
3.4.3.6 Cement Stabilisation Procedures -
3.2.6 Items in the Bill of Quantities 3-4
Mixed in Place Procedures 3-10
3.3 Aggregate Base Course 3-5 3.4.3.7 Cement Stabilisation Procedures -
Placing of Stationary Plant Mixes 3-11
3.3.1 Description 3-5
3.4.3.8 Cement Stabilisation Procedures -
3.3.2 Materials 3-5
Compaction and Finishing 3-11
3.3.2.1 Crushed Stone Aggregate 3-5
3.4.3.9 Curing of Cement Stabilised Courses 3-12
3.3.3 Construction Requirements 3-6
3.4.3.10 Testing of Cement Stabilised Courses 3-12
3.3.3.1 Surface Preparation 3-6
3.4.3.11 Bitumen Stabilisation Procedures -
3.3.3.2 Equipment 3-6
Mix Design 3-12
3.3.3.3 Construction of Trial Sections 3-6
3.4.3.12 Bitumen Stabilisation Procedures -
3.3.3.4 Stockpiling of Aggregate Materials 3-6
Stationary Plant Mixing 3-12
3.3.3.5 Mixing and Spreading 3-6
3.4.3.13 Bitumen Stabilisation Procedures -
3.3.3.6 Compaction 3-6
Mixed in Place Procedures 3-12
3.3.3.7 Tolerances 3-7

♦ 3-0 ♦
copy 249
Ref. Title Page No.
3.4.3.14 Bitumen Stabilisation Procedures -
Placing and Spreading Stationary
Plant Mixes 3-12
3.4.3.15 Bitumen Stabilisation Procedures -
Compaction and Finishing 3-12
3.4.3.16 Bitumen Stabilisation Procedures -
Tolerances and Replacement
of Unsatisfactory Areas 3-12
3.4.3.17 Bitumen Stabilisation Procedures -
Testing of Bitumen Stabilised Courses 3-13
3.4.3.18 Lime Stabilisation Procedures -
Mix Design 3-13
3.4.3.19 Lime Stabilisation Procedures - Safety
Precautions 3-13
3.4.3.20 Lime Stabilisation Procedures -
Stationary Plant Mixing 3-13
3.4.3.21 Lime Stabilisation Procedures - Mixed
in Place Procedures 3-13
3.4.3.22 Lime Stabilisation Procedures - Placing
and Spreading Stationary Plant Mixes 3-13
3.4.3.23 Lime Stabilisation Procedures -
Compaction and Finishing 3-13
3.4.3.24 Lime Stabilisation Procedures –
Tolerances and Replacement
of Unsatisfactory Areas 3-13
3.4.3.25 Testing of Lime Stabilised Courses 3-14
3.4.4 Method of Measurement 3-14
3.4.5 Basis of Payment 3-14
3.4.6 Items in the Bill of Quantities 3-14

♦ 3-0 ♦
copy 249
3.1 Materials for Sub-Base and Base 3.1.3.2 Stockpiling
Courses 1 Stockpile areas shall be surveyed prior to stockpiling
to establish control points and to obtain a record of
3.1.1 Description existing cross sections for future use in determining
1 This Sub-section describes general requirements for stockpile quantities. The areas shall be adequately drained
materials for construction of granular sub-base, aggregate at all times.
base and stabilised base courses, all as and where shown 2 Stockpiling procedures shall not result in noticeable
on the drawings. degradation or segregation of the stockpiled material, or
introduction of foreign materials into the stockpile, or
3.1.2 Materials coning. Heights of granular material and aggregate
stockpiles shall not exceed 3 m berms.
1 Materials for use in the construction of the sub-base
and base courses for flexible and rigid pavements may 3.1.3.3 Sampling and Testing
include any or all of the following:
1 The Contractor shall submit to the Engineer, 10 days
i. Screened or partially crushed granular material,
prior to the scheduled beginning of crushing and
consisting of well graded gravel including sand
screening operations, a statement of origin indicating the
and silt, or crushed stone or crushed gravel for
aggregate source and the quarry location and
sub-base course construction.
qualifications, as well as the types and composition of all
ii. Crushed stone for base course construction.
stone and/or gravel aggregates and granular materials
2 All material sources and the quality of materials shall proposed for use in the work.
be approved prior to procuring or processing material
2 Samples for testing shall be taken by the Contractor,
from such sources. Inspection, sampling, testing and
in the presence of the Engineer. Duplicate samples shall
retesting as necessary, shall be as specified hereunder for
be submitted to the Engineer for future reference, if
specific materials.
instructed. Sampling shall be in accordance with AASHTO
3 Storage and handling of all materials shall conform T2. The Contractor shall conduct the tests in the site
to the relevant requirements of this specification and as laboratory, or have the tests carried out at an approved
approved by the Engineer. Materials shall be stored on external laboratory.
hard, clean surfaces or as directed by the Engineer.
3 In order to ascertain the properties of granular and
aggregate materials, the Contractor shall submit for
3.1.3 General Requirements for Materials
testing representative samples of all materials intended
3.1.3.1 Sources and Production for incorporation in the work, prior to starting quarry or
borrow pit operations. The representative samples shall
1 The Contractor shall be responsible for locating be taken by the Contractor in the presence of the Engineer.
sources and manufacturers of materials in accordance
4 Tests performed by the Contractor shall be utilized in
with the requirements of this Specification in the
assessing the locations, extent of deposits and quantities
quantities and rates of production needed to complete the
of materials which, when properly processed, will conform
work on time.
to this Specification, and shall in no way obviate the need
2 The Contractor shall satisfy himself as to the location, for further testing by the Engineer. Approval of specific
suitability and quantity of materials available; extent of sources of materials shall not be construed as final
work necessary to obtain the materials, and to crush, approval and acceptance of materials from such sources.
screen and wash them; and the length of haul to the Site.
5 Processed materials shall be tested and approved
3 Prior to starting quarry or borrow pit operations; the before being stockpiled on Site or incorporated in the
Contractor shall obtain written permission from the work and may be inspected and tested at any time during
authorities or owners concerned. their preparation, storage and use. Materials awaiting
4 Screening plants or crushing and screening plants testing and approval shall not be unloaded and mixed
shall not be put into operation until approved by the with materials previously approved. If the grading and
Engineer. If, after any plant is put into operation, it fails to quality of any materials delivered to the Site do not
perform as intended, the Contractor shall either rectify the conform to the grading and quality of the established
defects in the existing plant to the satisfaction of the control samples, the Engineer will reject such materials.
Engineer, or shall provide alternative approved plant. 6 The Contractor shall permit the Engineer to inspect
5 Approval of the crushing and screening plants and any and all materials used or to be used, at any time
other equipment shall in no way relieve the Contractor of during or after their preparation, or while being used..
his responsibilities in respect of producing granular Unsatisfactory materials, whether in place or not, shall be
materials and aggregates which conform to this removed promptly from the Site. The Contractor shall
Specification and in the quantities required for the furnish all necessary labor, transport, tools and equipment
completion of the work on time. required by the Engineer for such inspections.

♦ 3-1 ♦
copy 249
3.2 Granular Sub-Base Course accordance with AASHTO T 96 (Los Angeles Abrasion
Test).

3.2.1 Description 6 The granular material shall have a 4-day soaked CBR
of not less than 60% when compacted at 100% of modified
1 This Sub-section specifies standards for granular proctor AASHTO (T 180-D) and tested in accordance with
sub-base material, mixing, spreading on prepared AASHTO T 193.
subgrade, compacting and finishing.
7 When tested for soundness in accordance with
AASHTO T 104, the material shall not show signs of
3.2.2 Materials
disintegration, and the percentage loss in weight after 5
1 Granular material for use in sub-base courses shall cycles shall not exceed 12% in the case of the sodium
be naturally occurring gravel, blended as necessary with sulfate test and 18% in the case of the magnesium sulfate
fine or coarse material and screened to produce the test.
specified gradation. Crushing of natural granular material 8 The portion of granular material, including any
shall not normally be required, unless for the purpose of blended material, passing the 0.425 mm (No. 40) mesh
meeting the gradation requirements, or, when shown on sieve shall have a liquid limit (L.L.) of not more than 25
the Drawings, to produce a higher quality sub-base with and a plasticity index (P.I.) not greater than 6 when tested
improved mechanical stability. in accordance with AASHTO T 89 and T 90.
2 Gravel shall consist of hard, durable and sound 9 If additional fine material is required to correct the
stones, free from dirt, organic matter, shale or other gradation of the granular material, or for adjusting the L.L.
deleterious substances. or P.I. of the fraction passing 0.425 mm (No 40) sieve, it
3 Granular materials shall meet the requirements of shall be uniformly blended and mixed with the granular
Class A, B or C shown in Table 3.2.2.1, and as specified on material. Additional fine material for these purposes shall
the Drawings, when tested in accordance with AASHTO T- be obtained from the crushing of stone, gravel, or slag.
27 after dry mixing and just before spreading and 10 The granular material shall not contain more than
compacting. The class of granular material shall be as 3 % gypsum and shall be free from organic content.
shown on the Drawings or otherwise as selected by the
11 The granular material shall have a minimum sand
Engineer based upon the test results of the materials
equivalent value of 28, when tested in accordance with
survey, and projected traffic. The actual gradation shall, in
ASTM D2419.
all cases, be continuous and smooth within the specified
limits for each class. 12 The maximum permitted swell for the granular
material used in the sub-base courses shall be 1.0%, when
Percent by weight passing tested in accordance with ASTM D4829.
Sieve Designation
(square openings) 13 The Granular Sub-base Course material shall have
Class A Class B Class C
chloride content of less than 3.5 percent and sulphate
content of less than 2.0 percent when tested in accordance
63 mm 100 - -
with BS 812.
50 mm 90 - 100 100 - 14 Only potable water shall be used for mixing granular
sub-base material.
37.5 mm - 70 - 100 -

25 mm - 55 - 85 100 3.2.3 Construction Requirements

19 mm - 50 - 80 - 3.2.3.1 Sub-grade Surface Preparation

1 Prior to subgrade surface preparation, the sub-grade


9.5 mm - 40 - 70 50 - 85
shall be constructed in accordance with the requirements
4.75 mm 35 - 70 30 - 60 35 - 65 of Sub-section 2.6 and properly maintained and kept well
2.00 mm - 20 - 50 25 - 50 drained thereafter.

0.425 mm - 10 - 30 15 - 30 2 At all special grade control points, such as at bridge


structures, existing pavements, etc the sub-grade shall be
0.075 mm 0 - 10 5 - 15 5 - 15
lowered to a depth sufficient to permit construction of the
Table 3.2.2.1: Gradation of Granular Sub-Base Material by sub-base course to the specified elevations and thickness.
Class Transitions shall be of sufficient length to avoid abrupt
changes of grade and shall be within plus or minus 3% of
4 The material shall not contain more than 5% clay the final design grade unless otherwise directed. Surplus
content at any stage of construction when tested in the material shall be removed and disposed of.
Hydrometer Test in accordance with AASHTO T88.
3 The sub-grade shall be inspected and approved
5 The loss in weight of granular material shall not immediately prior to commencement of sub-base
exceed 40% after 500 revolutions, when tested in construction. Any soft, yielding material shall be removed

♦ 3-2 ♦
copy 249
and replaced by approved topping material. Holes, control guide wire requirements. Where the required
depressions and other irregularities shall be made good as thickness is greater than 200 mm but less than 400 mm,
directed and the subgrade re-compacted as necessary and the material shall be placed in layers of equal thickness.
finished ready to receive the sub-base course. 3 If approved by the Engineer, when heavy duty
vibratory compaction equipment is used the maximum
3.2.3.2 Equipment layer thickness may be increased up to 300 mm (after
compaction) provided compaction tests with appropriate
1 Equipment used to handle, place, spread, water, testing equipment based on successful Site trials indicate
compact and finish sub-base shall conform with the that the specified compaction standard will be attained
requirements of Section 19 of these Specifications and and will be uniform through the thickness.
with the Contractor's approved equipment list.
4 The sub-base material shall be placed to the required
3.2.3.3 Construction of Trial Sections width using an approved paver/finisher or grader if
approved by the Engineer. However, any pavers or
1 If directed by the Engineer, before commencement of graders used for placing the sub-base material shall be
sub-base construction, the Contractor shall lay and equipped with calibrated sensors to maintain the design
compact trial sections of varying thickness of sub-base. levels and thicknesses. Water shall be applied by
Each trial section shall be 2 lanes wide by 50 m long, at approved spraying equipment and thoroughly mixed with
approved locations on or close to the Site. Each trial the sub-base material.
section shall be laid using the same materials, mix
5 The material shall not be handled in such a way as to
proportions, mixing, spreading and compaction
cause segregation. If the spreading equipment causes
equipment, and construction procedures, proposed for
segregation in the material, or leaves ridges or other
use in the work.
objectionable marks on the surface which cannot be
2 The objectives of these trials shall be to determine readily eliminated or prevented by adjustment of the
the adequacy of the Contractor's equipment and the loose equipment, the use of such equipment shall be
depth measurements that will result in the specified discontinued and it shall be replaced by a spreader or
compacted layer depths, to verify the field moisture grader capable of spreading the material in a proper
content, and to identify the relationship between the manner.
number of compaction passes and the resulting density of
6 All segregated material shall be removed and
the sub-base material.
replaced with well-graded material. ‘Skin’ patching will
3.2.3.4 Stockpiling of Granular Material not be permitted. Only minor surface manipulation and
watering to achieve the required surface tolerances will be
1 Stockpiling procedures shall conform to the permitted during the compaction process.
requirements of Sub-section 3.1.
7 Neither hauling nor placement of material will be
2 Methods used for stockpiling granular material and permitted when, in the judgment of the Engineer, the
removing it from stockpiles shall not result in significant weather or surface conditions are such that hauling
degradation or segregation or the introduction of operations will cause cutting or rutting of the subgrade or
significant amounts of foreign materials or extraneous cause contamination of the sub-base material.
matter.
3 Granular material adversely affected, in the opinion 3.2.3.6 Compaction
of the Engineer, by stockpiling or handling procedures, 1 The Contractor shall plan the sequence of operations
shall not be incorporated in the work regardless of so that the least amount of water will be lost by
previous approval of such material, until the deficiencies evaporation from uncompleted surfaces. If the
have been rectified in an acceptable manner. uncompleted surface material loses water due to
evaporation, the Contractor shall apply additional water as
3.2.3.5 Mixing and Spreading
required to prevent raveling or excessive drying.
1 Mixing shall generally be performed in batching 2 The sub-base material shall be compacted by means
plants. Mixing in stockpiles shall be done only if approved of approved compaction equipment, progressing
by the Engineer and under his supervision. The amount of gradually from the outside towards the center, with each
water added, as approved by the Engineer, shall be such succeeding pass uniformly overlapping the previous pass.
that the material will be uniform and within the specified
3 Rolling shall continue until the entire thickness of
moisture content range at the time of compaction.
each sub-base layer is thoroughly and uniformly
Wetting of granular material in trucks before or during
compacted to 100% AASHTO T 180 (Method D) maximum
delivery to the Site will not be permitted. However, water
density. Final rolling of the completed course shall be by
shall be added to the material, if necessary, during placing
means of an approved self-propelled roller. Rolling shall
and compaction of sub-base material.
be accompanied by sufficient blading, to insure a smooth
2 The sub-base material shall be placed on the surface, free from ruts or ridges and having the proper
subgrade in a uniform layer or layers not exceeding 200
mm thickness (after compaction) with the necessary

♦ 3-3 ♦
copy 249
shape. When additional water is required, it shall be 3.2.3.8 Maintenance of Completed Sub-base
applied in an approved manner.
1 Following completion and acceptance of the sub-
4 Any areas inaccessible to normal compaction
base course, it shall be maintained in good condition prior
equipment shall be compacted by use of portable
to laying the base course.. The sub-base shall be bladed,
mechanical tampers until the required standard of
broomed and otherwise maintained, keeping it free from
compaction is achieved.
raveling and other defects until such time as the base
5 Each layer shall be completely compacted and course is placed. Water shall be applied at such times and
approved prior to delivery of materials for the subsequent in such quantities as directed by the Engineer.
layer.
3.2.3.9 Testing
6 Prior to placing a subsequent layer, the existing
surface shall be made sufficiently moist as directed, to 1 Every 1000 cu.m. of sub-base material, or whenever
ensure proper bond between the layers. there is a change in the material source, shall be subject to
7 The edges and edge slopes of the sub-base course a full set of tests as listed in Table 3.3.3.1 after placing and,
shall be bladed or otherwise dressed to conform to the if found satisfactory, shall be approved for compaction.
lines and dimensions shown on the Drawings and to This approval shall not be deemed to constitute
present straight, neat lines and slopes as free of loose acceptance of the sub-base course.
material as practicable. 2 Sampling and testing shall conform with the relevant
8 Material which has dried out prior to final requirements of this specification and to the satisfaction of
compaction, or which has dried and de-compacted the Engineer.
subsequent to final compaction, shall be watered and re- 3 Compaction shall be tested in accordance with
compacted using approved equipment and procedures. If AASHTO T 191 or AASHTO T 205. If there is a delay
the Contractor is unable to return the material to its between the construction of any layer and the following
original or specified condition with respect to compaction, layer, if necessary and required by the Engineer the
thickness and surface tolerances, the Contractor shall compaction of the lower layer may be re-verified to ensure
remove the material and reconstruct the sub-base course that it has not loosened due to traffic, passage of
on a re-approved subgrade. construction equipment, adverse weather conditions or
9 The water shall be clean and free from deleterious otherwise.
substances. Water from doubtful sources shall not be used
until tested in accordance with AASHTO T26 and approved. 3.2.4 Method of Measurement
10 Sea, brackish or saline water shall not be used in the 1 Granular sub-base course is measured by cu.m. of
mixing, spreading and compacting operations for compacted sub-base. Measurement shall be of volumes
aggregate sub-base course. computed from the cross sections shown on the Drawings
and shall be calculated from the top surface area of each
3.2.3.7 Tolerances
layer, excluding the tapered edges..
1 The fully compacted and completed sub-base course 2 No measurement shall be made for direct payment of
shall conform to the lines, grades and cross sections as overdepth construction, regardless of the Engineer's
shown on the Drawings. permission for it to remain in place.
2 The elevations of the finished sub-base course shall
be checked by the Contractor in the presence of the 3.2.5 Basis of Payment
Engineer at maximum intervals of 20 m and at
1 The amount of completed and accepted work,
intermediate points as directed.
measured as provided for above, will be paid for at the
3 The tolerances on elevations of finished surface shall unit rates for the various items in the Bill of Quantities,
be plus 10 mm to minus 20 mm. Minus tolerance shall be which rate shall be full compensation for equipment, tools,
compensated by the subsequent layer. labor, locating sources of supply, supplying materials,
4 When the finished surface is tested with a 3 m long sampling and testing, screening, crushing, transporting,
straightedge, placed parallel to, or at right angles to the stockpiling, laying, mixing and compacting and for extra
centerline, the maximum deviation of the surface from the material in tapered edges, and other items necessary for
testing edge between any 2 contact points shall not the proper completion of the work.
exceed 10 mm.
5 All areas which exceed the specified tolerances shall 3.2.6 Items in the Bill of Quantities
be corrected by removing the defective sections of sub-
i. Granular Sub-Base Course (Class A) cu.m
base and reconstructing them or, if approved, by
scarifying, adding new material, or removing extra ii. Granular Sub-Base Course (Class B) cu.m
material, mixing and re-compacting and finishing to the
iii. Granular Sub-Base Course (Class C) cu.m
specified standard.

♦ 3-4 ♦
copy 249
3.3 Aggregate Base Course 9 The crushed aggregate base course material shall
have a 4-day soaked CBR of not less than 80% when
3.3.1 Description compacted at 100% of modified proctor AASHTO (T180-D)
and tested in accordance with AASHTO T 193.
1 This Sub-section specifies standards for crushed
aggregate base course material, mixing, spreading on
prepared sub-base course or sub-grade, compacting and Per cent by weight passing
Sieve Designation
finishing. (square openings) Class A Class B Class C
3.3.2 Materials
63 mm 100 - -
3.3.2.1 Crushed Stone Aggregate
50 mm 90 - 100 - -
1 Aggregate for use in base course construction shall
be either crushed stone or crushed gravel. The fine 37.5 mm 60 - 90 100 -
aggregate shall consist of screenings obtained from 25 mm 42 - 77 60 - 100 100
crushed stone, gravel, or sand. Aggregate may be washed,
if directed, to remove excessive quantities of clay, silty 19 mm 35 - 70 55 - 85 80 - 100
clay or salts.
12.5 mm 25 - 60 - -
2 Crushed stone shall consist of hard, durable particles
or fragments of stone, free from dirt or other objectionable 4.75 mm 15 - 40 35 - 60 30 - 60
matter, and shall contain no more than 8% of flat, 2.00 mm 10 - 25 25 - 50 20 - 45
elongated particles when tested according to ASTM D4791
0.425 mm 5 - 15 15 - 30 -
and, soft, or disintegrated pieces when tested according to
ASTM C235 and C123. 0.075 mm 2-9 8 - 15 3 - 10
3 Crushed gravel shall consist of hard durable stones, Table 3.3.2.1: Gradation by Class of Aggregate Base
rocks, and boulders crushed to specified sizes and shall be Course
free from excess flat, elongated, soft or disintegrated
pieces, dirt, or other objectionable matter 10 When tested for soundness in accordance with
AASHTO T 104, the material shall not show signs of
4 The method used in production of crushed gravel
disintegration and the loss by weight shall not exceed 12%
shall be such that the finished product shall be as uniform
in the case of the sodium sulfate test and 18% in the case
as practicable. The crushing of the gravel shall result in a
of the magnesium sulfate test.
product, which shall have at least 90% by weight of
particles with at least one fractured face. All stones, rocks, 11 The aggregate material shall not contain more than
and boulders of inferior quality occurring in the pit shall 2% gypsum and shall be free from organic content.
be wasted. 12 The aggregate material shall have a minimum sand
5 Any material passing 4.75 mm (No. 4) sieve and equivalent value of 50, when tested in accordance with
produced in the crushing process shall be incorporated in ASTM D2419.
the base material up to the gradation limits required for 13 The maximum permitted swell for the aggregate
the base course aggregate. material used in the base courses shall be 0.5%, when
6 Crushed aggregate for base course delivered to road tested in accordance with ASTM D4829.
site shall meet the requirements of Class A, B or C 14 The portion of aggregate, including any blended
gradations as shown in Table 3.3.2.1 when tested in material, passing the 0.425 mm (No. 40) mesh sieve shall
accordance with AASHTO T 27 after mixing with water have a liquid limit (L.L.) of not more than 25 and plasticity
and just before spreading and prior to compacting. The index (P.I) of not more than 6 when tested in accordance
class of aggregate shall be as shown on the Drawings. The with AASHTO T 89 and T 90.
actual gradation shall, in all cases, be continuous and 15 If additional fine material is required to correct the
smooth within the specified limits for each class. Gap aggregate gradation, or for adjusting the L.L. or P.I. of the
graded aggregate will not be accepted. If gradation is fraction passing the 0.425 mm (No. 40) sieve, it shall be
tested after compaction a tolerance of 3% is allowed in uniformly blended and mixed with the aggregate material
upper limit for percentage of material passing sieve 200. plant at the crushing plant or by an approved plant.
7 The amount of the fraction of material passing the Reworking of the material in situ to obtain the specified
0.075mm (No. 200) mesh sieve shall not exceed one half gradation will not be permitted. Additional fine material
the fraction passing the 0.425mm (No. 40) mesh sieve. for these purposes shall be obtained from the crushing of
stone, gravel, or slag.
8 The loss in weight shall not exceed 40% after 500
revolutions, when tested in accordance with AASHTO T 96 16 The Aggregate Base Course material shall have
(Los Angeles Abrasion Test). chloride content of less than 3.5 percent and sulphate
content of less than 2.0 percent when tested in accordance
with BS 812.

♦ 3-5 ♦
copy 249
17 Only potable water shall be used for mixing 3.3.3.5 Mixing and Spreading
aggregate base material.
1 All components of base course material shall be
premixed with water in a pugmill mixing plant. The
3.3.3 Construction Requirements
amount of water added, as determined, shall be such that
3.3.3.1 Surface Preparation the material will be uniform and within the specified
moisture content range at the time of compaction. Other
1 The sub-base course shall be in accordance with the methods of mixing will be allowed only if directed by the
requirements of Sub-section 3.2 and properly maintained Engineer, provided such method(s) do not reduce the
and kept well drained thereafter. quality of work. The Contractor shall demonstrate, in the
2 The sub-base surface shall be inspected and presence of the Engineer, his ability to attain the
approved prior to commencement of base construction. requirement given in this Specification.
Holes, depressions and other irregularities shall be made 2 The premixed material shall be placed on the sub-
good as directed and the sub-base re-compacted as base in a uniform layer or layers not exceeding 200 mm in
necessary and finished ready to receive the base course. thickness (after compaction) with the necessary control
3 Where no sub-base course is required or shown on guide wire requirements. Where the required thickness is
the Drawings, and the aggregate base course is placed greater than 220 mm but less than 400 mm, the material
directly on completed sub-grade, preparation of the shall be placed in layers of equal thickness.
subgrade surface shall be as specified in Paragraph 3.2.3.1. 3 If approved by the Engineer when heavy duty
vibratory compaction equipment is used, the maximum
3.3.3.2 Equipment
layer thickness may be increased up to 300 mm (after
1 Equipment used to handle, place, spread, water, compaction) provided compaction tests with appropriate
compact and finish base course shall conform with the testing equipment based on successful Site trials indicate
requirements of Section 19 and with the Contractor's that the specified compaction standard will be attained
approved equipment list. and will be uniform through the thickness.
4 The base course material shall be placed to the
3.3.3.3 Construction of Trial Sections
required width using an approved paver/finisher. However,
1 If directed by the Engineer, the Contractor shall lay any pavers or finishers used for placing the base material
and compact trial sections of varying thickness of base. shall be equipped with calibrated sensors to maintain the
Each trial section shall be 2 lanes wide by 50 m long, at design levels and thicknesses. The material shall be
approved locations on or close to the Site. Each trial delivered such that it is ready for compaction without
section shall be laid using the same materials, mix further shaping.
proportions, mixing, spreading and compaction 5 The material shall not be handled in such a way as to
equipment, and construction procedures, proposed for cause segregation. If the spreader causes segregation in
use in the Works. the material, or leaves ridges or other objectionable marks
2 The objectives of these trials shall be to determine on the surface which cannot be readily eliminated or
the adequacy of the Contractor's equipment and the loose prevented by adjustment of the spreader operation, the
depth measurements that will result in the specified use of such spreader shall be discontinued and it shall be
compacted layer depths, to verify the field moisture replaced by a spreader capable of spreading the material
content for compaction, and to identify the relationship in a proper manner.
between the number of compaction passes and the 6 All segregated material shall be removed and
resulting density of the base course material. replaced with well-graded material. ‘Skin’ patching will
not be permitted. Only minor surface manipulation and
3.3.3.4 Stockpiling of Aggregate Materials
watering to achieve the required surface tolerances will be
1 Stockpiling procedures shall conform to the relevant permitted during the compaction process.
requirements of Sub-section 3.1. 7 Hauling or placement of material will not be
2 Methods used for stockpiling aggregate materials permitted when, in the judgment of the Engineer, the
and removing them from stockpiles shall not result in weather or surface conditions are such that hauling
significant degradation or introduction of significant operations will cause cutting or rutting of the sub-base or
amounts of foreign materials or extraneous matter. subgrade or cause contamination of the base course
material.
3 Aggregate materials adversely affected, in the
opinion of the Engineer, by stockpiling or handling 3.3.3.6 Compaction
procedures, shall not be incorporated in the work
regardless of previous approval of such material, until the 1 The Contractor shall plan the sequence of operations
deficiencies have been rectified in an acceptable manner. so that the least amount of water will be lost by
evaporation from uncompleted surfaces. If the
uncompleted surface loses water due to evaporation, the

♦ 3-6 ♦
copy 249
Contractor shall apply additional water as required to 5 The tolerances on layer thickness, after being
prevent raveling or excessive drying.. compacted and finished, shall not exceed +10mm and -
2 The base course material shall be compacted by 5mm.
means of approved compaction equipment, progressing 6 The thickness of the finished base course shall be
gradually from the outside towards the center, with each checked at 20m intervals along the road by taking levels
succeeding pass uniformly overlapping the previous pass. on the centerline and both shoulders.
3 Rolling shall continue until the entire thickness of 7 All areas which exceed the specified tolerances shall
each base layer is thoroughly and uniformly compacted to be corrected by removing the defective sections of base
100% AASHTO T 180 (Method D) maximum density. Final course and reconstructing them or if approved, by
rolling of the completed course shall be by means of an scarifying and adding new material, or removing extra
approved self-propelled roller. Rolling shall be material, and re-compacting and finishing to the specified
accompanied by sufficient blading, to ensure a smooth standard.
surface, free from ruts or ridges and having the proper
shape. When additional water is required, it shall be 3.3.3.8 Maintenance of Completed Base Course
applied in an approved manner. 1 Following completion and acceptance of the base
4 Any areas inaccessible to normal compaction course, it shall be maintained by the Contractor until the
equipment shall be compacted by use of portable subsequent pavement layers are laid.. The surface shall be
mechanical tampers until the required standard of broomed, rolled and otherwise maintained, keeping it free
compaction is achieved, or to the satisfaction of the from raveling and other defects until such time as the
Engineer. following course is placed. Water shall be applied at such
5 Each layer shall be completely compacted and times and in such quantities as directed.
approved prior to delivery of materials for the following
3.3.3.9 Testing
layer.
6 Prior to placing a following layer, the surface shall be 1 Every 1000 cu.m. of base course material, or
made sufficiently moist as directed, to ensure proper bond whenever there is a change in the material source, shall be
between the layers. subject to a full set of tests as listed in Table 3.3.3.1 after
placing and if satisfactory shall be approved for
7 The edges and edge slopes of the base course shall
compaction and use. This approval shall not be deemed
be bladed or otherwise dressed to conform to the lines
to constitute acceptance of the base course for full
and dimensions shown on the Drawings and to present
payment purposes.
straight, neat lines and slopes as free of loose material as
practicable.
8 Material which has dried out prior to final Source of Materials Control on Site (The Road)
compaction, or which has dried and de-compacted Repetition
Repetition
subsequent to final compaction, shall be watered and re- Required Required Required
Required for
compacted using approved equipment and procedures. If Tests for all Tests
all Tests in
the Contractor is unable to return the material to its (A) Tests in (B)
(B)
(A)
original or specified condition with respect to compaction,
1.Gradation Minimum 1. Proctor Minimum
thickness and surface tolerances, for the final layer only of Materials one test AASHTO one test for
the Contractor shall scarify the material and reconstruct AASHTO for each T180-D every 1000
the base course on a re-approved sub-base surface or to T27 source cu.m. of
the satisfaction of the Engineer. every layer,
2.Plasticity or
3.3.3.7 Tolerances Index whenever
AASHTO " Materials
1 The fully compacted and completed base course T89 & T90 changed,
shall conform to the lines, grades and cross sections as whichever is
shown on the Drawings. less
3.Abrasion 2.
2 The elevations of the finished base course shall be AASHTO Gradation
checked by the Contractor in the presence of the Engineer T96 " of Materials
at intervals of 20m on straight lines and of 10 m on curves, AASHTO "
and at intermediate points as directed. T27
4. C.B.R.
3 The tolerances (for final layer only) on elevations of
AASHTO
finished surface shall not exceed +5mm or -10mm. T193 " 3. Plasticity
4 When the finished surface is tested with a 4 m long Index
straightedge, placed parallel to, or at right angles to the AASHTO "
centerline, the maximum deviation of the surface from the 5.Sand T89 & T90
equivalent
testing edge between any 2 contact points shall not "
ASTM
exceed 10mm.

♦ 3-7 ♦
copy 249
Source of Materials Control on Site (The Road) 3.3.5 Basis of Payment
Repetition 1 The amount of completed and accepted work,
Repetition
Required Required Required measured as provided for above, will be paid for at the
Required for
Tests for all Tests unit rates for the various items in the Bill of Quantities,
all Tests in
(A) Tests in (B) which rate shall be full compensation for equipment, tools,
(B)
(A)
labor, locating sources of supply, supplying materials,
D2419 4. C.B.R.
sampling and testing, screening, crushing, transporting,
AASHTO "
T193 stockpiling, laying, mixing and compacting and for extra
6.Percentag material in tapered edges, and other items necessary for
e of the proper completion of the work.
fractured 5. Abrasion
Grains AASHTO 3.3.6 Items in the Bill of Quantities
T96 "
i. Aggregate Base Course (Class A) cu.m
7.Thin and
elongated 6. Sand ii. Aggregate Base Course (Class B) cu.m
pieces equivalent
ASTM ASTM " iii. Aggregate Base Course (Class C) cu.m
D4791 D2419
3.4 Stabilized Base Courses
7. Clay
lumps & 3.4.1 Description
friable
1 This Sub-section specifies stabilized base courses
particles "
ASTM C235 composed of sand, sandy gravel, sandy clay soil or similar,
and C123 stabilized with cement or bitumen or lime as appropriate
and as shown on the Drawings.
8. Field
Density " 3.4.2 Materials
3.4.2.1 Soil for Stabilization
9. Test for every
Thickness 2000 sq.m. 1 Sand and gravel soils shall have the following
and for every particle size distribution given in Table 3.4.2.1.
layer
Table 3.3.3.1: Required Tests and Minimum Repetition for AASHTO Sieve % passing (by mass)
50 mm 100
Base and Sub-Base Course Materials
4.75 mm 50 - 100
2 Sampling and testing shall conform to the 1.80 mm 37 - 80
requirements of this specification. 425 μm 15 - 50
3 Compaction shall be tested in accordance with 75 μm 0 - 20
AASHTO T 191, AASHTO T 205 or any acceptable method. 2 μm 0-3
If there is a significant delay between the construction of Table 3.4.2.1: Soil for Stabilization
any layer and the following layer, the Engineer may
require the compaction of the lower layer to be re-verified 2 The mix-in-place method of construction shall be
to ensure that it has not loosened due to traffic, passage of used only on sites with naturally occurring sand and
construction equipment, adverse weather conditions or gravel mixture. For the central plant method of
otherwise. construction, the materials shall be selected by the
Contractor from other sources complying with the
3.3.4 Method of Measurement requirements of this Clause and shall be subject to the
1 Aggregate base course shall be measured by cu.m. approval of the Engineer.
of compacted base course. Measurements shall be of 3.4.2.2 Cement as Stabilizing Agent
volumes computed from the cross sections shown on the
Drawings and shall be calculated from the top surface area 1 Cement for stabilization shall be ordinary Portland
of each layer, excluding the tapered edges.. cement or sulfate resisting cement, as shown on the
2 No measurement shall be made for direct payment of Drawings, or as instructed by the Engineer. Portland
overdepth construction, regardless of the Engineer's cement shall conform to the requirements of BS12 Part 2
permission for it to remain in place. or AASHTO M85 Type I for ordinary and rapid hardening
types, and BS4027 Part 2 or AASHTO M85 Type V for
sulfate resisting cement.

♦ 3-8 ♦
copy 249
2 At least two silos shall be used for cement storage. water to be used with the naturally occurring soil so as to
Before recharging a silo it shall be emptied completely obtain a stabilized mixture with the following properties:
and cleaned out. During the time of charging a silo shall
i. The minimum cube compressive strength shall
not be used for batching.
be 5.0 N/mm2 after molding and storage at a
3 The stored cement shall be free-flowing and free of minimum humidity of 95% for a period of 7
lumps. Cement shall not be stored for longer than 4 days. The molding shall be in accordance with
months. Cement that has remained in store for a period AASHTO T134 and the strength testing shall be
greater than 4 months, or of which there is doubt as to in accordance with BS 1881. The cement
quality shall be re-tested by standard mortar tests to content of trial mixes shall be adjusted until
determine whether it still meets the requirements of the this strength is achieved.
standards.
ii. The maximum volume change (swelling) shall
4 Curing seal shall consist of approved proprietary be 2% and the maximum loss in weight shall
curing compound, or MC-70 cutback bitumen to prime be not more than 8%, when cylinders are
coat standard as specified in Section 4. molded and tested in accordance with AASHTO
T 135, Method B.
3.4.2.3 Bitumen as Stabilizing Agent
iii. Cement content and water content of the mix
1 Bitumen may include straight run (penetration grade) on the Site shall each be within - 0.2% to +2%
bitumen; RC cutback bitumen, MC cutback bitumen, or of the approved mix design.
cationic emulsified bitumen, Type SS. Penetration grade, iv. The total salt content of the cement stabilized
cutback bitumen and emulsified bitumen shall conform to base course mixture shall meet the following
all relevant requirements herein. requirements: The total chloride content (sum
2 The selection of suitable bitumen will depend on the of both acid soluble and water soluble
properties of the material to be stabilized and shall be chlorides) expressed as chloride ion, when
subject to laboratory and field trials by the Contractor, tested in accordance with BS 1881, shall not
under the supervision of the Engineer. exceed 0.10 percent by weight of dry cement.
The total sulfate content expressed as SO3,
3 When the material moisture content is high, the
when tested in accordance with BS 1881, shall
material must be dried before the use of penetration grade
not exceed 3 percent by weight of dry cement.
bitumen or viscous cutback bitumen and plant mixing of
materials as appropriate.
3.4.3 Construction Requirements
4 When the natural moisture content of the material is
low, use cutback bitumens or emulsified bitumens as 3.4.3.1 Surface Preparation
appropriate.
1 Prior to placing of stabilized base on sub-base or
subgrade, the subgrade shall have been properly
3.4.2.4 Lime as Stabilizing Agent completed and approved as specified in Sub-section 2.6
1 Hydrated lime (calcium hydroxide) and quicklime and the sub-base shall have been properly completed and
(calcium oxide) shall conform to AASHTO M216. Mixing of approved as specified in Sub-section 3.2.
different brands of lime or use of lime from different mills
3.4.3.2 Construction of Trial Section
will not be permitted.
2 Lime slurry shall be a homogeneous pumpable 1 If instructed by the Engineer before commencement
mixture of lime and water. Slurry shall be a premixed of stabilization work and after completion of laboratory
material in which the lime solids content shall be not less mix design, the Contractor shall lay a trial section of
than 30% by weight. stabilized material 2 lanes wide by 50m long, at an
approved location on or near to the Site.
3.4.2.5 Water 2 This trial section shall be laid using the same
1 The water shall be clean and free from impurities, oil, materials, mix proportions, mixing, spreading and
acid, salts, alkali, organic matter, and other potentially compaction equipment, and construction procedures that
deleterious substances. Water from doubtful sources shall are proposed for use in the work.
not be used until tested in accordance with AASHTO T26 3 The trial section shall serve as a field verification of
and approved. the laboratory mix design. The results of the dry density
and moisture content measurements made in the trial
3.4.2.6 Mix Design for Cement Stabilized Base section will be used in association with the laboratory
1 Before starting the work of stabilization, soil-cement tests to establish the moisture content and minimum per
trial mixes shall be carried out. The proposed mix design cent compaction to be attained in the stabilization work.
shall be submitted by the Contractor for approval by the 4 The trial section shall also demonstrate the adequacy
Engineer. It shall show the percentage of cement and of mixing, spreading and compaction equipment and the
suitability of the methods and organization proposed.

♦ 3-9 ♦
copy 249
3.4.3.3 Cement Stabilization Procedures - Plant Mixing feeders which continuously supply the correct amount of
granular material in proportion to the cement and so
1 When cement and granular or crushed material are arranged that the proportion of each size of granular
to be mixed in a stationary plant, the plant shall be an material can be separately adjusted if more than one size
approved type pugmill mixing plant of either the batch is used. Storage facilities containing fine material shall be
mix type with revolving blade or rotary drum, or the equipped with vibrating units which shall vibrate the side
continuous mixing type. Proportioning of materials and of walls of the feeder to prevent any hang-up of materials
water may be by either weight or volume. while the plant is operating.
2 Cement shall be added in such a manner that it is 2 A control system shall be provided that will
uniformly distributed during the mixing operation. Safe, automatically close down the plant when the material in
convenient facilities shall be provided for sampling any storage facility approaches the strike-off capacity of
cement in the supply line to the weigh hopper or pugmill. the feed gate. The plant will not be permitted to operate
3 Means shall be provided whereby the Engineer may unless the control system is in proper working order.
verify the amount of water per batch or the rate of flow for 3 The feeder for the granular material shall be
continuous mixing. The time of the addition of water and mechanically or electrically driven. Mechanically driven
the points at which it is introduced into the mixer shall be feeders shall be directly connected with the drive on the
as approved. cement feeder. The drive shaft on the feeder shall be
4 The charge in a batch mixer, or the rate of feed to a equipped with a revolution counter reading to 0.1 of a
continuous mixer, shall not exceed that which will permit revolution. Electrically driven feeders shall be actuated
complete mixing of all of the material. Dead areas in the from the same circuit that services the motor driving the
mixer, in which the material does not move or is not cement feeder.
sufficiently agitated, shall be corrected. 4 The cement feeder and the granular material feeders
5 The moisture content of the completed mixture shall shall be equipped with devices by which the rate of feed
be not more than one per cent below optimum moisture can be determined while the plant is in full operation.
content at the point of delivery to the work area.
3.4.3.6 Cement Stabilization Procedures - Mixed in
3.4.3.4 Cement Stabilization Procedures - Batch Mixing Place Procedures
1 Batch mixing plants shall be equipped with a 1 Mixed in place procedures will normally be permitted
sufficient number of paddles of a type and arrangement to when the granular material to be stabilised is in-situ site
produce a uniformly mixed batch. material.
2 The mixer platform shall be of ample size to provide 2 Plant and equipment for pulverizing (if required) and
safe and convenient access to the mixer and other for mixing all materials will be approved on the basis of
equipment. preliminary trials to establish that such plant and
3 The mixer shall be equipped with a timing device equipment are capable of producing the specified degree
which will indicate by a definite audible or visual signal of mixing and uniformity of stabilized material for the full
the expiration of the mixing period. The device shall be thickness of each layer. Single pass or multi-pass
accurate to within 2 seconds. equipment may be used.
4 The time of mixing a batch shall begin after all 3 The mixing equipment shall be equipped with a
ingredients are in the mixer and shall end when the mixer device for controlling the depth of processing and the
is half emptied. Mixing shall continue until a mixing blades shall be maintained or reset periodically so
homogeneous mixture of uniformly distributed and that the correct depth of mixing is obtained at all times.
properly coated materials of uniform appearance is Cement shall be spread ahead of the mixer by means of a
produced. The time of mixing shall not be less than 30 cement spreader, fitted with a device to ensure a uniform
seconds. When blending of different sizes is required, the and controllable rate of spread of cement transversely and
materials shall be blended as they enter the mixer. longitudinally.
5 Cement for each batch shall be weighed on scales 4 If multi-pass equipment is utilized, the fine cohesive
separate from the aggregate batching scales. Each fraction (if any) of the material shall first be pulverized to
cement scale graduation shall be approximately 0.001 the required depth with successive passes and the
times the total capacity of the scales. The total capacity moisture content adjusted if it is more than 3% below the
shall not be greater than twice the amount of cement value required for compaction. Cement shall then be
required when the plant is operated at full capacity. No spread and mixing continued with successive passes until
scale shall be used with a capacity less than 500 kg. the required depth and uniformity have been achieved.
5 If it is necessary to adjust the moisture content of the
3.4.3.5 Cement Stabilization Procedures - Continuous
material to the optimum for compaction, water shall be
Mixing added during the mixing operation using a water sprayer
1 Continuous mixing plants shall be designed such that of such design that the water is added in a uniform and
granular materials are drawn from the storage facility by controllable manner both transversely and longitudinally.

♦ 3-10 ♦
copy 249
6 Te mixing equipment shall be set so that it cuts be provided with a fully automatic and adjustable screed
slightly into the edge of any adjoining completed lane so that strikes off and distributes the material to the full width
as to ensure that all material forming the layer has been being spread and to the surface tolerances specified.
properly processed. The Engineer may approve the use of 9 The spreader shall be equipped with grade sensing
scarifiers or preparizers ahead of the mixing equipment. controls to automatically control the longitudinal grade
The output of the mixing equipment shall be such that a and transverse slopes of the screed. Screed action
minimum rate of 20 lin.m./h measured longitudinally of includes any cutting, crowding, or otherwise that produces
completed stabilized layer can be maintained in order to a finished surface texture of uniform appearance.
permit satisfactory compaction of the mix.
3.4.3.8 Cement Stabilization Procedures - Compaction
3.4.3.7 Cement Stabilization Procedures - Placing of
and Finishing
Stationary Plant Mixes
1 Immediately upon completion of spreading or
1 Immediately prior to depositing the mix, the surface spreading and mixing in place operations, and completion
area to be covered shall be moistened and kept moist. of shaping, the mix shall be initially compacted by one
2 The cement stabilized mix shall be protected against complete pass using approved type rollers.
moisture loss during transporting, by use of suitable 2 If the finished surface after initial compaction is
covers. The mix shall be deposited on the roadbed at a outside the specified tolerance, all high spots shall be
prescribed quantity which shall provide the compacted trimmed off to within the specified tolerance. Filling of
thickness for the width being spread without resort to low areas by drifting or hauling of trimmed material will
spotting, picking up, or otherwise shifting the mixture. not be permitted.
Segregation shall be prevented and the mix shall be free
3 Following trimming, the finished surface shall be
from pockets of coarse or fine materials.
finally compacted to not less than 100% of the laboratory
3 The mix shall be spread in widths of not less than 2 density of the approved job mix specimens as determined
lanes, insofar as the width of surface permits. by AASHTO T 134. Final compaction shall be
Longitudinal construction joints shall fall within 300 mm of accomplished in such a manner that no loose material
lane lines. The mix shall be spread by one or more remains on the surface and all tear marks are eliminated.
spreaders operating in a staggered position across the
4 The surface tolerances shall conform with the
surface. If traffic conditions require that less than 2 lanes
tolerance requirements for Aggregate Base Course.
be spread, not more than 2 hours shall elapse between the
Where any areas are lower than the allowable tolerance,
times of placing the material in adjacent lanes.
the stabilised layer shall be removed and fresh stabilised
4 The compacted thickness of any one layer shall not mix placed and properly compacted and finished, unless
exceed 200 mm and shall be not less than 80 mm. When filling of the low areas with bituminous concrete or
more than one layer is placed, the surface of the lower cement concrete is approved.
layer of compacted mix shall, until covered with the next
5 If the superimposed course will be cement concrete,
layer, be kept moist with water or a curing seal as
the low areas may, if approved, be filled with concrete at
specified.
the time and during the same operation that the concrete
5 In the case of areas inaccessible to mechanical pavement is placed.
spreading equipment, the mix may be spread in one layer
6 When the superimposed course will be bituminous
by approved methods only. After spreading, the material
concrete, the low areas may, if approved, be filled with
shall be thoroughly compacted to the required lines,
bituminous concrete to the same standard. This filling
grades, and cross section by means of pneumatic tampers,
shall be carried out as a separate operation prior to
or other approved compacting equipment.
placing the bituminous concrete course (unless the
6 Use of motor graders will not be permitted during thickness to be placed is too small to make this
spreading or compacting operations. Motor graders may practicable).
be used only to trim the edges and surface after
7 Not more than 2 hours shall elapse between the time
compaction in order to finish within the specified
water is added to the mixed materials and the time of
tolerances.
completion of initial compaction. Final compaction shall
7 A motor grader may be classified as a self-propelled be completed within 30 minutes of initial compaction.
mechanical spreader if it has been equipped with end
8 At the end of each day's work and when operations
wings on the blade, has the blade locked in a position
are delayed or stopped for more than 2 hours, a vertical
perpendicular to the direction of travel, and is equipped
construction joint shall be made in the fully compacted
with cross slope and automatic grade controls that meet
layer, perpendicular to the centerline. Additional mix shall
the requirements for the specified type of spreading.
not be placed until the construction joint has been
8 Each layer of the mix shall be spread in one approved.
operation with an approved type self-propelled
9 One hour after the stabilized mix has been finally
mechanical spreader such that the layer is made ready for
compacted; vertical longitudinal joints shall be
compaction without further shaping. The spreader shall
constructed by cutting into the existing edge to a depth of

♦ 3-11 ♦
copy 249
approximately 100 mm. The mix cut away shall be 3.4.3.12 Bitumen Stabilization Procedures - Stationary
discarded. The face of the cut joints shall be moistened in Plant Mixing
advance of placing the adjacent lane.
1 When approval is given to utilize stationary plant for
3.4.3.9 Curing of Cement Stabilized Courses mixing, whether batch mixing plant or continuous type
mixing plant, the plant and equipment and handling and
1 Curing seal as specified shall be applied uniformly to
mixing procedures shall conform with the relevant
the completed surface at a rate of between 0.5 and 1.2
requirements of Section 4 - "Bituminous Pavement" and
kg./sq.m., or as determined by the Engineer. The curing
with the appropriate requirements specified herein for
seal shall be applied on the same day that final
plant mixing of cement stabilized materials.
compaction is performed and as soon as practicable
thereafter. The surface shall be kept moist until the seal is 3.4.3.13 Bitumen Stabilization Procedures - Mixed in
applied.
Place Procedures
2 Damage to the curing seal or stabilized surface shall
be promptly repaired by an approved manner. 1 Approved type multi-pass or approved type purpose-
built, single-pass equipment shall be utilized for on Site
3.4.3.10 Testing of Cement Stabilised Courses mixing and placing. Operators shall be trained and fully
experienced in the operation of such equipment.
1 For every 5,000 sq.m. of each stabilised layer or for
each day's completed area (whichever is smaller) the 2 Multi-pass equipment may consist of suitable
following sampling and testing shall be carried out: bitumen distributor and motor graders or as otherwise
- In situ density of a minimum of 3 samples approved.
(taken immediately after final compaction) 3 The process of pulverizing the fine grained cohesive
determined in accordance with AASHTO T 191 fraction (if any) of the granular material shall be as
or T 205 and which shall be not less than 100% specified for cement stabilized courses. Bitumen, of the
of the density of the approved laboratory mix. type and grade selected by the Engineer, shall then be
- Cement content in accordance with AASHTO T applied to the surface using approved type heating and
211. pressure distribution equipment. Emulsified bitumen shall
- Gradation of mix in accordance with AASHTO not normally require heating.
T 27. 4 Spreading and mixing of the bitumen and granular or
- Moisture - density relationship for mix sampled other material shall be carried out as specified for cement
fresh from the Site, in accordance with stabilized courses.
AASHTO T 134 if the source of the material is
3.4.3.14 Bitumen Stabilization Procedures – Placing and
changed.
- Compressive strength of a set of 3 test Spreading Stationary Plant Mixes.
specimens molded and cured in accordance
1 The placing and spreading of stationary plant mixes
with AASHTO T 134 and T 126, and tested in
shall be as specified for cement stabilized courses.
accordance with AASHTO T 22.
3.4.3.15 Bitumen Stabilization Procedures - Compaction
3.4.3.11 Bitumen Stabilization Procedures - Mix Design
and Finishing
1 The material to be stabilized shall be a sand, sandy
1 Compaction of bitumen stabilized courses to 100% of
gravel or silty or clayey gravel and sand material with a P.I.
laboratory density of approved job mix specimens,
not exceeding 12% and L.L. not exceeding 25% and with
finishing, and provision of longitudinal joints, shall be as
not more than 30% passing a 0.075 mm (No. 200) sieve.
specified for cement stabilized courses.
2 Bitumen-soil mix proportions shall be established by
field laboratory trial mixes, carried out in the presence of 3.4.3.16 Bitumen Stabilization Procedures - Tolerances
the Engineer. The compressive strength shall be and Replacement of Unsatisfactory Areas
determined in accordance with AASHTO T 167 and in such
a way as to ensure that the optimum composition of the 1 Finished surface tolerances and the rectification
mix is established. procedures for any areas which fail to meet such
tolerances, shall be as specified for cement stabilized
3 The laboratory trial mixes, after being air cured for a
courses.
period of 7 days and tested in accordance with AASHTO T
167, shall have a minimum compressive strength at 25 2 Where high spots require trimming after initial
degrees C, of 2 MN/sq.m. (20 kg/sq.cm.) and a Marshall compaction, raking or similar procedures may be required.
stability at 60 degrees C, of 2,000 N (204 kg). The Index of If the area is unduly damaged or pitted, the stabilized mix
Retained Strength when tested using a Marshall mould shall be removed and replaced with fresh stabilized mix
shall be not less than 70%. spread and properly compacted and finished.

♦ 3-12 ♦
copy 249
3.4.3.17 Bitumen Stabilization Procedures - Testing of operators. Working operations should take into account
Bitumen Stabilized Courses the wind direction to minimize the dust problem and
consequent eye or skin irritation to any personnel in the
1 For every 5,000 sq.m. of each stabilized layer or for vicinity.
each day's completed area (whichever is the smaller) the 3 When hydrated lime is used, precautions shall also
following sampling and testing shall be carried out: be taken against the effects of prolonged exposure to the
i. In situ density of a minimum of 3 samples skin.
(taken immediately after completion of final
compaction) determined in accordance with 3.4.3.20 Lime Stabilization Procedures - Stationary Plant
AASHTO T 191 or T 205 and which shall be not Mixing
less than 100% of the density of the approved
laboratory mix. 1 When approval is given to utilize stationary plant for
ii. Composition of the mix by extraction in mixing, whether batch mixing plant or continuous type
accordance with AASHTO T 164. The variation mixing plant, the plant and equipment and handling and
from the approved job-mix, based on results of mixing procedures shall be as specified for cement
4 tests, shall not exceed the following: stabilization and as specified herein for plant mixing of
- Aggregates passing lime stabilized materials.
No. 200 (0.075 mm) +1 percent 3.4.3.21 Lime Stabilization Procedures - Mixed in Place
- Asphalt content +0.2 percent
Procedures
iii. Compressive strength in accordance with
1 Mixed in place procedures will normally be permitted
AASHTO T 167, of samples before compaction.
when the soil to be stabilized is in-situ site material.
The minimum compressive strength value shall
be not less than the value specified under Item 2 Spreading and mixing of the lime and soil material
3 of Paragraph 3.4.3.11. shall be carried out as specified for cement stabilized
iv. Marshall stability in accordance with AASHTO courses.
T245, of samples before compaction. The
3.4.3.22 Lime Stabilization Procedures - Placing and
minimum Marshall stability value shall be not
Spreading Stationary Plant Mixes
less than the value specified under Item 3 of
Paragraph 3.4.3.11. 1 Placing and spreading of stationary plant mixes shall
be as specified for cement stabilized courses.

3.4.3.18 Lime Stabilization Procedures - Mix Design 3.4.3.23 Lime Stabilization Procedures - Compaction
and Finishing
1 The material to be stabilized shall be a clayey gravel,
clayey sand or lean clay soil with not more than 50% 1 Compaction of lime stabilized courses to 100% of
passing 0.425 mm (No. 40) sieve and plasticity index laboratory density of approved job mix specimens,
greater than 10%. finishing and provision of longitudinal joints, shall be as
2 The lime content and optimum moisture content specified for cement stabilized courses with the following
shall be determined in the field laboratory and in the modifications:
presence of the Engineer. Cylinders molded in accordance i. When quick lime is used, the layer shall not be
with AASHTO T 220 shall be cured and tested at 7 days compacted immediately after spreading the lime,
and 28 days. Load rate of application shall be in as hydration of the lime will cause damage to the
accordance with AASHTO T 22. The minimum compacted layer. The time within which the
compressive strength at 7 days after molding shall be one compaction shall be completed will be as
MN/sq.m. (10 kg./sq.cm.). estimated in the laboratory.
3 Lime content and water content of the mix shall each ii. Compaction shall not take place after lime
be within -0.2% to +2.5% of the approved mix design hydration. Any lime stabilized material that has
percentages. been mixed or deposited after lime hydration,
shall be removed and replaced with fresh
3.4.3.19 Lime Stabilization Procedures - Safety
material, mixed and treated as specified.
Precautions

1 Special precautions shall be taken when handling


3.4.3.24 Lime Stabilization Procedures - Tolerances and
quicklime as it will rapidly corrode equipment and can
inflict severe skin burns to personnel coming in contact Replacement of Unsatisfactory Areas
with it. 1 Finished surface tolerances and the rectification
2 Suitable methods for handling quicklime shall be procedures for any areas which fail to meet such
adopted, including fully mechanized or bottom dump tolerances shall be as specified for cement stabilized
handling equipment and protective clothing worn by the courses.

♦ 3-13 ♦
copy 249
3.4.3.25 Testing of Lime Stabilized Courses

1 For every 5,000 sq.m. of each stabilized layer or for


each day's completed area (whichever is the smaller) the
following sampling and testing shall be carried out:
i. In situ density of a minimum of 3 samples
(taken immediately after completion of final
compaction) determined in accordance with
AASHTO T 191 or T 205 and which shall be not
less than 100% of the density of the approved
laboratory mix.
ii. Lime content in accordance with AASHTO T
232.
iii. Gradation of mix in accordance with AASHTO
T 27.
iv. If the source of materials changes, the moisture
- density relationship in accordance with
AASHTO T 134 and gradation of the new mix in
accordance with AASHTO T27.
v. Compressive strength of a set of 3 test
specimens molded and cured in accordance
with AASHTO T 134 and T 126, and tested in
accordance with AASHTO T 22.

3.4.4 Method of Measurement


1 Cement stabilized course, bitumen stabilized course
and lime stabilized course shall each be measured by cu.m.
of compacted stabilized course. Measurements shall be of
the area and thickness dimensions shown on the
Drawings.
2 Curing seal shall be measured by sq.m. of areas
computed from the length and width of the completed
sections shown on the Drawings.

3.4.5 Basis of Payment


1 The amount of completed and accepted work,
measured as provided for above, will be paid for at the
unit rates for the various items in the Bill of Quantities,
which rate shall be full compensation for equipment, tools,
labor, locating sources of supply, supplying materials,
sampling and testing, screening, crushing, transporting,
stockpiling, laying, mixing and compacting and for extra
material in tapered edges, and other items necessary for
the proper completion of the work.

3.4.6 Items in the Bill of Quantities


i. Cement Stabilized Base Course
(thickness) cu.m

ii. Bitumen Stabilized Base Course


(thickness) cu.m

iii. Lime Stabilized Base Course


(thickness). cu.m

iv. Curing Seal sq.m

♦ 3-14 ♦
copy 249
Ref. Title Page No. Ref. Title Page No.
4.1  Materials for Bituminous 4.2.5.2  Prime Coat Application 4-11 
Construction 4-1 4.2.5.3  Tack Coat Application 4-12 
4.2.5.4  Polymer Modified Tack Coat 4-12 
4.1.1  Description 4-1 
4.2.6 Method of Measurement 4-12
4.1.2  Aggregate Materials Generally 4-1 
4.2.7 Basis of Payment 4-12
4.1.2.1  Sources and Production 4-1 
4.2.8 Items in the Bill of Quantities 4-12
4.1.2.2  Stockpiling 4-1 
4.1.2.3  Sampling and Testing 4-1  4.3 Bituminous Courses 4-12
4.1.3 Aggregates for Bituminous Paving Mixes 4-1
4.3.1 Description 4-12
4.1.4 Aggregates for Seal Coats 4-3
4.3.2 Materials 4-13
4.1.5 Bitumen Generally 4-3
4.3.3 Job Mixes and Project Mixes 4-13
4.1.5.1  Type and Grade 4-3 
4.3.4 Equipment 4-14
4.1.5.2  Transporting Bitumen 4-4 
4.3.4.1  General 4-14 
4.1.5.3  Storage of Bitumen 4-4 
4.3.4.2  Mixing Plant 4-14 
4.1.5.4  Heating of Bitumen 4-4 
4.3.4.3  Spreading and Finishing Equipment 4-14 
4.1.5.5  Sampling and Testing 4-4 
4.3.5 Construction of Trial Sections 4-15
4.1.6 Bitumen Products 4-4
4.3.6 Mixing Procedures 4-15
4.1.6.1  Penetration Graded Bitumen 4-4 
4.3.7 Surface Preparation 4-15
4.1.6.2  Bitumen Modifier and Modified
4.3.8 Delivery, Spreading and Finishing 4-16
Bituminous Material 4-5 
4.3.8.1  Delivery of Mix to Site 4-16 
4.1.6.3  Rapid-Curing (RC) Cutback Bitumen 4-7 
4.3.8.2  Setting Out and Reference Lines 4-16 
4.1.6.4  Medium-Curing (MC) Cutback Bitumen 4-7 
4.3.8.3  Spreading and Finishing 4-16 
4.1.6.5  Slow-Curing (SC) Cutback Bitumen 4-7 
4.3.8.4  Joints and Edges 4-17 
4.1.6.6  Emulsified Bitumens Generally 4-7 
4.3.8.5  Compaction 4-17 
4.1.6.7  Anionic Emulsified Bitumen 4-8 
4.3.9 Sampling and Testing 4-18
4.1.6.8  Cationic Emulsified Bitumen 4-10 
4.3.10 Surface Tolerances 4-20
4.1.7 Method of Measurement and Basis
4.3.11 Determination of Thickness of Courses 4-20
of Payment 4-10
4.3.12 Method of Measurement 4-20
4.2 Prime and Tack coats 4-10 4.3.13 Basis of Payment 4-21

4.2.1 Description 4-10 4.4 Bituminous Base Course 4-21


4.2.2 Materials 4-10
4.4.1 Description 4-21
4.2.2.1  Medium Curing Cutback Bitumen 4-10 
4.4.2 Materials 4-21
4.2.2.2  Rapid-Curing Cutback Bitumen 4-10 
4.4.3 Job Mix and Project Mix 4-21
4.2.2.3  Slow-Curing Emulsified Bitumen 4-10 
4.4.4 Equipment 4-21
4.2.3 Equipment 4-11
4.4.5 Construction of Trial Sections 4-21
4.2.4 Construction of Trial Sections 4-11
4.4.6 Mixing Procedures 4-21
4.2.5 Application Procedures 4-11
4.4.7 Surface Preparation 4-22
4.2.5.1  Medium Curing Cutback Bitumen 4-11

♦ 4-0 ♦
copy 249
Ref. Title Page No. Ref. Title Page No.
4.4.8 Delivery, Spreading and Finishing 4-22 4.6.6.3  Heating of Bitumen 4-26
4.4.8.1  General 4-22  4.6.6.4  Spreading Slurry Seal 4-26 
4.4.8.2  Rollers 4-22  4.6.6.5  Spraying of Bitumen 4-26 
4.4.8.3  Standard of Compaction 4-22  4.6.6.6  Application of Aggregate 4-26 
4.4.9 Sampling and Testing 4-22 4.6.6.7  Rolling and Brooming 4-27 
4.4.10 Surface Tolerances 4-22 4.6.6.8  Maintenance and Protection of Sealed
4.4.11 Determination of Thickness 4-22 Surfaces 4-27 
4.4.12 Method of Measurement 4-22 4.6.7 Tolerances and Records 4-27
4.4.13 Basis of Payment 4-22 4.6.8 Method of Measurement 4-28
4.4.14 Items in the Bill of Quantities 4-23 4.6.9 Basis of Payment 4-28
4.6.10 Items in the Bill of Quantities 4-28
4.5 Bituminous Binder and Wearing
Courses 4-23 4.7 Bituminous Leveling Course and
Patching Work 4-28
4.5.1 Description 4-23
4.5.2 Materials 4-23 4.7.1 Description 4-28
4.5.3 Job Mix and Project Mix 4-23 4.7.2 Materials 4-28
4.5.4 Equipment 4-23 4.7.3 Job Mix and Project Mix 4-28
4.5.5 Construction of Trial Sections 4-23 4.7.4 Equipment 4-28
4.5.6 Mixing Procedures 4-23 4.7.5 Construction of Trial Sections 4-28
4.5.7 Surface preparation 4-23 4.7.6 Mixing Procedures 4-28
4.5.8 Delivery, Spreading and Finishing 4-23 4.7.7 Surface Preparation 4-28
4.5.8.1  General 4-23  4.7.8 Delivery, Spreading and Finishing 4-29
4.5.8.2  Rollers 4-23  4.7.9 Sampling and Testing 4-29
4.5.8.3  Standard of Compaction 4-24  4.7.10 Surface Tolerances 4-29
4.5.8.4  Skid Resistance and Surface Texture 4-24  4.7.11 Determination of Thickness 4-29
4.5.9 Sampling and Testing 4-24 4.7.12 Method of Measurement 4-29
4.5.10 Surface Tolerances 4-24 4.7.13 Basis of Payment 4-29
4.5.11 Determination of Thickness 4-24 4.7.14 Items in the Bill of Quantities 4-29
4.5.12 Method of Measurement 4-24
4.8 Bituminous Cold Mix Courses 4-29
4.5.13 Basis of Payment 4-24
4.5.14 Items in the Bill of Quantities 4-24 4.8.1 Description 4-29
4.8.2 Materials 4-29
4.6 Bituminous Seal Coats – Surface
4.8.3 Job Mix and Project Mix 4-29
Dressings 4-25
4.8.4 Equipment 4-29
4.6.1 Description 4-25 4.8.5 Construction of Trial Sections 4-29
4.6.2 Materials 4-25 4.8.6 Mixing Procedures 4-30
4.6.2.1  Bitumen 4-25  4.8.7 Surface Preparation 4-30
4.6.2.2  Aggregates 4-25  4.8.8 Delivery, Spreading and Finishing 4-30
4.6.3 Equipment 4-25 4.8.9 Sampling and Testing 4-30
4.6.4 Construction of Trial Sections 4-25 4.8.10 Surface Tolerances 4-30
4.6.5 Rates of Application 4-25 4.8.11 Determination of Thickness 4-30
4.6.6 Construction Requirements 4-25 4.8.12 Method of Measurement 4-30
4.6.6.1  General 4-25 4.8.13 Basis of Payment 4-30
4.6.6.2  Surface Preparation 4-26 4.8.14 Items in the Bill of Quantities 4-30

♦ 4-0 ♦
copy 249
Ref. Title Page No. Ref. Title Page No.
4.9 Pavement Repairs and 4.12.2 Reference Documents for Profiler
Reinstatement 4-30 Rideability Testing 4-34
4.12.3 Terminology 4-34
4.9.1 Description 4-30
4.12.4 Testing Equipment 4-34
4.9.2 Materials 4-30
4.12.5 Testing Procedure 4-34
4.9.3 Equipment 4-30
4.12.6 Submittals 4-35
4.9.4 Preparation of Pavement 4-30
4.12.7 Required Rideability 4-35
4.9.5 Placing and Finishing Repair Materials 4-31
4.12.8 Method of Measurement 4-35
4.9.6 Sampling and Testing 4-31
4.12.9 Basis of Payment 4-35
4.9.7 Surface Tolerances 4-31
4.12.10 Items in the Bill of Quantities 4-35
4.9.8 Method of Measurement 4-31
4.9.9 Basis of Payment 4-31
4.9.10 Items in the Bill of Quantities 4-32

4.10 Bituminous Pavement Widening 4-32


4.10.1 Description 4-32
4.10.2 Materials 4-32
4.10.3 Construction Requirements 4-32
4.10.3.1 Construction 4-32
4.10.3.2 Traffic Control 4-32
4.10.4 Method of Measurement 4-32
4.10.5 Basis of Payment 4-32
4.10.6 Items in the Bill of Quantities 4-32

4.11 Recycled Bituminous Mixes 4-32


4.11.1 Description 4-32
4.11.2 Materials 4-33
4.11.3 Job Mix and Project Mix 4-33
4.11.4 Equipment 4-33
4.11.5 Construction of Trial Sections 4-33
4.11.6 Mixing Procedures 4-33
4.11.7 Surface Preparation 4-33
4.11.8 Delivery, Spreading and Finishing 4-33
4.11.9 Sampling and Testing 4-33
4.11.10 Surface Tolerances 4-33
4.11.11 Determination of Thickness 4-33
4.11.12 Method of Measurement 4-34
4.11.13 Basis of Payment 4-34
4.11.14 Items in the Bill of Quantities 4-34

4.12 Surface Rideability


Measurement 4-34
4.12.1 Description 4-34

♦ 4-0 ♦
copy 249
♦ 4-0 ♦
copy 249
4.1 Materials for Bituminous stockpile quantities. The areas shall be adequately drained
Construction at all times.
2 Stockpiling procedures shall not result in degradation
4.1.1 Description or segregation of the stockpiled material, or introduction
of foreign materials into the stockpile. Heights of
1 This Sub-section includes specifications for materials aggregate stockpiles shall not exceed 5 m.
for use in the construction of the various bituminous
pavement courses including the following: 4.1.2.3 Sampling and Testing
i. Coarse and fine mineral aggregates and filler.
1 Sampling and testing procedures shall conform to
ii. Bitumen products including penetration graded the relevant requirements of this Specification.
bitumens, cutback bitumens, emulsified
2 The Contractor shall submit to the Engineer, 30 days
bitumens, modified bitumens, and rejuvenating
prior to the scheduled start of crushing and screening
agents for use in bituminous courses and surface
operations, a statement of origin and composition of all
treatments.
aggregates proposed for use in the work.
iii. Polymers for bitumen modification, Elastomers
such as Styrene-Butadiene-Styrene (SBS) 3 In order to ascertain the properties of aggregate
copolymers or Plastomers such as Polyethylene materials, the Contractor shall submit for testing,
(PE) polymer, as shown on the drawings. representative samples of all materials intended for
incorporation in the work, prior to starting quarry
2 All materials sources and the quality of materials
operations. The representative samples shall be taken by
proposed for use in the work shall be approved prior to
the Contractor in the presence of the Engineer. Tests shall
procuring or processing material from such sources.
be performed by the Contractor at his laboratory or at an
Inspection, sampling, testing and retesting as necessary,
approved outside laboratory
shall be at the Contractor's expense.
4 Test results shall be utilized by the Contractor in
3 Storage and handling of all materials shall conform
assessing the locations, extent of deposits and quantities
to the relevant requirements of these specifications.
of materials which will conform to the Specification when
Materials shall be stored on hard, clean surfaces.
properly processed. Any special tests that may be required
by the Engineer shall be carried out by the Contractor, in
4.1.2 Aggregate Materials Generally his own laboratory, or an outside laboratory, approved by
4.1.2.1 Sources and Production the Engineer. Engineer’s approval of test results shall in
no way obviate the need for further testing if required by
1 The Contractor shall satisfy himself as to the location the Engineer. Approval of specific sources of materials
of the sources of aggregate materials, the length of haul to shall not be construed as final approval and acceptance of
the site, the suitability and quantity of materials available; materials from such sources.
extent of work necessary to obtain the material available; 5 Processed materials shall be tested and approved
the work required to open the quarry and to crush, screen before being stockpiled on Site or incorporated in the
and wash (if necessary) the materials to meet the specified work and may be inspected and tested at any time by the
gradation. Engineer during their preparation, storage and use.
2 Prior to starting quarry operations, the Contractor Questionable materials awaiting testing and approval,
shall obtain written permission from the authorities or shall not be unloaded and mixed with materials previously
owners concerned. approved. If the grading and quality of any materials
3 Crushing and screening plants shall not be put into delivered to the Site do not conform to the grading and
operation prior to their approval. If, after any plant is put quality of the established control samples, the Engineer
into operation, it fails to perform as intended, the will reject such materials.
Contractor shall either rectify the defects in the existing 6 Samples shall satisfy all specified test requirements.
plant to the satisfaction of the Engineer, or shall provide The Contractor shall permit the Engineer to inspect any
alternative approved plant. and all materials used or to be used, at any time during or
4 Approval of the crushing and screening plants and after their preparation, or while being used during
other equipment shall in no way relieve the Contractor of progress of the work. Unsatisfactory materials, whether in
his responsibilities in respect of producing aggregates place or not, shall be removed promptly from the Site.
which conform to the Specifications and in the quantities The Contractor shall furnish all necessary materials, labor,
required for the completion of the work. tools and equipment and transport required by the
Engineer for such inspections.
4.1.2.2 Stockpiling

1 Stockpile areas shall be surveyed prior to stockpiling


4.1.3 Aggregates for Bituminous Paving
to establish control points and to obtain a record of
Mixes
existing cross sections for future use in determining 1 Aggregates for use in bituminous base course,
binder course, leveling, wearing and cold mix courses

♦ 4-1 ♦
copy 249
shall consist of crushed stone. The coarse fraction of the 11 Combined coarse and fine aggregates for bituminous
aggregates for use in bituminous wearing course shall mixes, including mineral filler, when tested in accordance
consist of 100% crushed stone from a hard, high quality with AASHTO T 27 and T11, shall conform to the
Gabbro and/or non-vesicular Basalt. gradations shown in Table 4.1.3.3. For the Gradation of
2 Coarse aggregate shall be the fraction of crushed Leveling Course, this should be provided in the Special
aggregate material retained on 4.75 mm (No. 4) sieve. Specifications depending on the particular conditions of
Fine aggregate shall be the fraction of crushed aggregate the Project.
material passing 4.75 mm (No. 4) sieve. Mineral filler shall
Percent passing
be added when the combined grading of coarse and fine Sieve
aggregates is deficient in material passing 0.075 mm (No. Size Base course Wearing course
Binder
200) sieve. (mm) Class Class course Class Class
3 The material from hot bins passing the number 40 A B A B
sieve (0.425mm) when tested in accordance with AASHTO 25 100 100 100 - -
T 90 shall be non plastic. In addition the material from cold 90-
19 60-90 65-100 100 100
bins should not have PI greater than 4. 100
90-
4 Aggregates shall be free of gypsum and the coarse 12.5 - - - -
100
fraction of the aggregate shall not contain more than 5%
9.5 42-67 60-80 47-72 56-80 73-93
chert when tested in accordance with AASHTO T113.
5 Aggregates shall be of uniform quality, free from 4.75 25-50 40-60 30-56 35-56 51-71
decomposed stone, organic matter and shale. 2.36 - 28-48 - - 34-54
6 The percentage by weight of friable particles, clay 2.00 15-31 - 19-36 22-36 -
lumps, and other deleterious matter shall not exceed 1%
1.18 - 20-36 - - 22-38
as determined by AASHTO T 112.
0.600 - 14-26 - - 18-30
7 Aggregate particles shall be clean, hard, durable and
sound. Crushing shall result in a product such that, for 0.425 8-20 - 8-20 8-20 -
particles retained on 4.75 mm (No. 4) sieve, at least 90% 0.300 - 8-20 - - 10-22
by weight shall have 2 or more fractured faces, when
tested in accordance with ASTM D5821. 0.150 - 7-15 - - 9-17

8 The flakiness index and the elongation index test 0.075 2-15 2-8 2-8 2-8 2-8
shall be conducted in accordance with BS 812, the Table 4.1.3.3: Gradation of Aggregates for Bituminous
following are maximum limits: Mixes
Bituminous Bituminous
12 The loss in weight of aggregate after 500 revolutions,
Index Wearing Binder & Base
Course Courses when tested in accordance with AASHTO T 96, shall not
Flakiness Index F.I 25 30 exceed 35% for binder and base courses, and 25% for
Elongation Index E.I 25 30 wearing course.

Table 4.1.3.1: Flakiness and Elongation Indices of 13 When tested for soundness in accordance with
AASHTO T 104 the coarse aggregate (retained on No.4
Aggregates for Bituminous Mixes
sieve) shall not show signs of disintegration and the loss
9 Aggregates shall be washed if directed, to remove by weight after 5 cycles shall not exceed 10% in the case
any clay lumps, organic matter, adherent dust or clay films of the sodium sulfate test and 12% in the case of the
or other extraneous or deleterious matter that may magnesium sulfate test.
prevent or detract from proper adhesion of bitumen to the 14 When tested for resistance to stripping in accordance
aggregate particles. with the AASHTO T-182 at least 95% coated particles
10 Mineral filler shall consist of finely divided mineral should be achieved. If resistance to stripping is not
matter such as limestone dust, hydrated lime; other non- achieved then anti-stripping agent should be used. For
plastic mineral filler, free from clay and organic impurities; additional stripping resistance requirements for wearing
or Portland cement, conforming to AASHTO M 17. The course layer, refer to Sub-section 4.5.
gradation of the mineral filler shall comply with the 15 Polish stone value (PSV) of coarse aggregates used
requirements of Table 4.1.3.2: in the wearing course mix when tested according to BS
812 shall be at least 60%.
Sieve Size Percent Passing by Mass
16 The sand equivalent for fine aggregates, when tested
0.600 mm (No. 30) 100
in accordance with AASHTO T45, shall be a minimum of
0.300 mm (No. 50) 95 - 100
75.
0.075 mm (No. 200) 70 - 100
Table 4.1.3.2: Gradation of Mineral Filler for Bituminous
Mixes

♦ 4-2 ♦
copy 249
4.1.4 Aggregates for Seal Coats 7 The loss in weight of aggregate after 500 revolutions,
when tested in accordance with AASHTO T 96 (Los
1 Cover aggregates for bituminous seal coats shall Angeles Test), shall not exceed 35%.
consist of screenings of crushed stone. Aggregate for
8 When tested for soundness in accordance with
slurry seals shall consist of crushed stone fines or natural
AASHTO T 104, the aggregates shall not show signs of
sand blended with not less than 50% crushed stone fines.
disintegration and the loss by weight shall not exceed 10%
For heavy-duty applications slurry aggregate shall consist
in the case of the sodium sulphate test or 12% in the case
of 100% crushed fines. Wadi gravels shall not be used for
of the magnesium sulphate test.
seal coats, suitability of suggested crushed stone fines for
use in slurry seal shall be demonstrated prior to use. 9 When tested for resistance to stripping in accordance
with AASHTO T 182, at least 95% of the aggregate surface
2 Aggregates shall be free of crystalline or amorphous
area shall remain coated with a bitumen film. If resistance
gypsum (expressed as SO3), and shall not contain more
to stripping is not achieved then anti-stripping agent
than 5% chert when tested in accordance with AASHTO
should be used.
T113.
10 Polish stone value (PSV) of coarse aggregates used
3 Aggregate particles shall be clean, hard, durable and
in the upper layer of seal coats when tested according to
sound. For particles retained on 4.75 mm (No. 4) sieve, at
BS 812 shall be at least 60%.
least 90% by weight shall have 2 or more fractured faces
and 100% by weight shall have one or more fractured 11 The sand equivalent for fine aggregates, when tested
faces, when tested in accordance with ASTM D5821. in accordance with AASHTO T45, shall be a minimum of
75.
4 Flakiness index and elongation index tested in
12 Table 4.1.4.2 below summarizes the required
accordance with BS 812 shall not exceed 25% for each of
aggregate properties listed under items 7 to 11 above:
flakiness and elongation index. The percentage by weight
of clay lumps and friable particles as determined by Standard Test Specification
Aggregate Property
AASHTO T 112 shall not exceed 3%. Light weight Method Requirements
aggregate of specific gravity of 2 or less shall not exceed Loss in weight of
3% as determined by AASHTO T 113. aggregate after 500
5 If necessary aggregates shall be washed, or revolutions AASHTO T96 Max. 35%
processed by an approved alternative method, to remove (Los Angeles
any clay lumps, organic matter, adherent dust or clay films Abrasion)
or other extraneous or deleterious matter that may
Soundness in
prevent or detract from proper adhesion of bitumen to the AASHTO T 104 Max. 10%
Sodium Sulphate
aggregate particles.
6 Cover aggregates and aggregate for slurry seals, Soundness in
when tested in accordance with AASHTO T 27 and T 11, Magnesium AASHTO T 104 Max. 12%
Sulphate
shall conform to the gradations given in Table 4.1.4.1.
Resistance to
Double Bituminous Surface AASHTO T 182 Min. 95%
Sieve stripping
Treatment Aggregate Slurry
Designation Polish Stone Value
1st 2nd Aggregat
(Square Application Application e (PSV) of coarse BS 812 Min. 60%
openings) (Grading B) (Grading C) aggregates

25 mm 100 - - Sand Equivalent for


AASHTO T175 Min. 75
Fine Aggregate
19 mm 90-100 - -
12.5 mm 20-55 100 - Table 4.1.4.2: Properties of Aggregates for Seal Coats

9.5 mm 0-15 58-100 100


4.1.5 Bitumen Generally
4.75 mm 0-5 10-30 90-100
4.1.5.1 Type and Grade
2.36 mm - 0-10 65-90
1.18 mm - 0-5 45-70 1 Bitumen shall be petroleum derivative penetration
grade 60-70 (unless otherwise shown in the Special
0.60 mm - - 30-50 Specification), conforming to the requirements of
0.30 mm - - 18-30 AASHTO M20. When more than one type or grade is
specified under any item, the Engineer will select the type
0.15 mm - - 10-20
and grade to be used in the work. If the specified grade is
0.075 mm 0-0.5 0-0.5 5-15 not locally available in the market, the Contractor shall be
Table 4.1.4.1: Gradation of Aggregates for Seal Coats deemed to have considered any additional costs
associated with the import of bitumen in his contract price.

♦ 4-3 ♦
copy 249
4.1.5.2 Transporting Bitumen temperature of bitumen, weigh buckets, spray bars, and
other containers.
1 All transporting of bitumen shall be by conveyances
3 Thermometers of approved type and adequate range
that are free from contamination. Tank cars or tank trucks
(calibrated in 2 degrees C increments) for accurately
used for transporting bitumen shall be carefully inspected,
measuring the temperature of the bitumen while heating,
drained, and cleaned if necessary, before loading, to
shall be located so as to be readily visible and shall be
prevent contamination of the bitumen from residues of
kept clean and in proper working order at all times.
previous loads. Bitumen may also be delivered and
transported in metal drums. 4 Where storage tanks are required, their capacity shall
be sufficient for at least one day's production.
2 Tank trucks or trailers used to transport bitumen shall
be equipped with an approved sampling device which 5 Bitumen materials, wasted through careless handling
shall be built into the tank or re-circulating or discharge or rendered unsuitable for use by overheating shall not be
line in such a manner that a sample can be drawn during used in the work.
circulation or discharge.
4.1.5.5 Sampling and Testing
4.1.5.3 Storage of Bitumen
1 Procedures for sampling of bituminous materials
1 The Contractor shall provide an adequate storage shall conform to AASHTO T 40.
facility for bitumen, at the site of the mixing plant. This 2 General requirements and procedures for sampling
facility shall be clean and stable and provided with cover and testing of the various types of bitumen shall conform
and shelter from excessive temperatures. to the requirements of the relevant sections of these
2 No open fires or smoking shall be allowed in or specifications.
around the storage facility. 3 Testing for conformity of bitumen products shall be
3 The storage capacity shall be sufficient to maintain a carried out to AASHTO Standard Methods listed in
uniform operation while allowing for delayed shipments AASHTO M 20 and other specified standards.
and time for testing. Different batches of bitumen shall be
separated, so as to allow for easy identification. 4.1.6 Bitumen Products
4 If the bitumen is delivered to the site in metal drums, 4.1.6.1 Penetration Graded Bitumen
on arrival the drums shall be inspected for perforations,
rusting, melting or any other defects that could cause 1 The various grades of penetration graded bitumen
pollution or chemical changes to the bitumen. material shall conform generally with the requirements of
AASHTO M 20 as given in Table 4.1.6.1.
Depending on the severity of each case, the Engineer shall
decide whether to retain or reject the affected drums. Penetration Grade
5 The stored bitumen products should be protected
40 - 50 60 - 70 80 - 100
from temperatures which may exceed the range of -5 Requirement
degrees C to +50 degrees C. Min Max Min Max Min Max

4.1.5.4 Heating of Bitumen Ductility at 25 ̊C


100 - 100 - 100 -
(cm)
1 Heating equipment shall be of an approved type. Kinematic Viscosity
280 - 240 - 200 -
Any method of agitation or heating that introduces free at 135 ̊C (cSt)
steam or moisture into the bitumen will not be approved. Penetration at 25 ̊C
40 50 60 70 85 100
(0.1mm)
During the process of its manufacture, conveyance,
storage, or construction use, bitumen of whatever type Softening Point ( ̊C) 50 58 48 56 46 48
shall not be heated to temperatures more than 10 degrees Specific Gravity at
1.01 1.06 1.01 1.06 1.0 -
C above the maximum application temperature specified 25 ̊C
Loss on heating to
for the respective type of bitumen nor above 170 degrees - 0.8 - 0.8 - 1.0
163 ̊C (% wt)
C, whichever is the lower. Materials heated in excess of
Penetration of
these temperatures will be rejected and shall not be used residue % of 58 - 54 - 50 -
in the work. original
2 Tanks for heating and storage of bitumen shall be Solubility in
capable of heating the material, under effective and Trichloroethylene 99 - 99 - 99 -
(% wt)
positive control at all times, to the specified temperature.
The system shall provide uniform heating for the entire Ash content (% wt) - 1.0 - 1.0 - 1.0
contents of the tank. The circulation system shall be of Flashpoint
adequate size to ensure proper and continuous circulation (Cleveland Open 250 - 250 - 225 -
of the bitumen during the entire operating period. Cup) ( ̊C)
Suitable means shall be provided, either by steam or oil
Table 4.1.6.1: Properties of Penetration Grade Bitumen
jacketing, or other insulation, for maintaining the required

♦ 4-4 ♦
copy 249
2 Sampling and testing shall be in accordance with the i. Compatibility with original bitumen: The
AASHTO standard method listed in AASHTO M 20. modified bitumen shall be tested for
3 Penetration bitumen application temperature range compatibility with the polymer modifier to
shall be as given in table 4.1.6.2. Actual Mixing and ASTM D5892 for both softening point and
Compacting Temperature of Asphalt Concrete shall be dynamic shear (DSR). The difference in deg C
determined from Kinematic Viscosity of Bitumen as shown between the softening points of the respective
in MS-2. top and bottom portions of the tube sample
shall not exceed 4 deg C. The separation ratio
Pen 40/50 60/70 80/100 based on G* shall have an average G* value
Application [(top + bottom) / 2] within 0.8 to 1.2 of the
150-170 145-165 140-160
Temperature ( ̊C) initial G* value. Alternative compatibility test
Table 4.1.6.2: Application Temperature by Bitumen Grade according to ASTM D5841 can be carried out in
lieu of ASTM D5892, only in cases where the
4.1.6.2 Bitumen Modifier and Modified Bituminous Contractor and supplier can prove that the
Material ASTM D5892 cannot be adopted for the type of
polymer proposed.
1 An approved modifier shall be incorporated in all
penetration graded bituminous material immediately prior
to the time of use, unless otherwise shown on the ii. Mixing and compaction temperatures: The
Drawings. mixing and compaction temperatures shall be
established in the laboratory by determining
2 The types and penetration grades of the original
the Brookfield viscosity of the approved
bituminous materials shall be submitted by the polymer
polymer modified bitumen at three different
supplier/contractor for the Engineer’s approval.
temperatures 135 deg C, 165 deg C and 195
3 The Contractor shall provide evidence of his deg C. The established mixing and compaction
experience to prove that he is currently supplying and temperatures shall then be evaluated and
using polymer modified bitumen on similar projects with finalized based upon successful site trials.
successful results and performance. The Contractor shall
submit data, which indicate that the product has a proven
iii. Proportion of modifier in the mix: Depending
record of performance regarding compatibility with
upon the results of the tests specified in Table
asphaltic concrete mixtures, blending of the product with
4.1.6.3 below, the proportion of modifier to be
the asphalt cement and placing and compacting the
used and the quality control procedures during
mixture.
mixing shall be determined in accordance with
4 The modified bitumen shall demonstrate significantly the manufacturer’s recommendations to
reduced temperature susceptibility and/or improved provide the optimum characteristics of the mix
adhesive qualities. The workability of the modified as specified below.
bitumen shall be unchanged from that of unmodified
7 The minimum requirements and tests to be
bitumen.
performed on the modified bitumen shall be as follows:
5 Unless specified otherwise under this Specification,
mixing and preparation of modified bitumen shall be
carried out in accordance with the modifier manufacturer’s i. If Styrene-Butadiene-Styrene (SBS) polymer is
instructions, and to the approval of the Engineer. used, it shall have the following properties:
- Butadiene-Styrene Ratio = 70/30.
6 The Contractor shall submit a method statement for
- Block Styrene = 30%.
the preparation of polymer modified bitumen (PMB)
- Hardness Shore A = 80.
blending, including the type of polymer intended for use,
- Density ASTM D792 = 0.93 – 0.95 g/cm3.
for the Engineer’s approval. The Contractor shall propose
the type of polymer he intends to use and shall ii. If Polyethylene polymer is used, it shall be
demonstrate through testing that the modified asphalt polyolefinic, primarily low density polyethylene
meets all the specification requirements. Blending of the and shall meet the following requirements:
asphalt cement and the modifier shall be done by the
Test Property Criterion Specification
supplier of the modifier in a mobile mixing plant adjacent
to the Contractor’s asphalt plant on Site. The Contractor Density 0.910 min ASTM D 792
shall submit for the Engineer’s approval a comprehensive
0.940 max
QA/QC program to ensure that the pre-blended polymer
modified asphalt is delivered, stored in suitable conditions, Melt Index 1.0 – 15.0 ASTM D 1238
incorporated in the bitumen mix and laid in strict
accordance with the manufacturer’s instructions. The Melting Point 110° – 135° C
minimum requirements for this program shall include but iii. The ratio of modifier to bitumen in the
shall not be limited to the following: completed mix shall be between 4 and 8 parts
of modifier for 100 parts of bitumen, according

♦ 4-5 ♦
copy 249
to the manufacturer’s recommendations, which
must confirm that the modified bitumen will
meet the requirements of Table 4.1.6.3 and will
prove the optimized properties of the modified
binder at the proposed proportion of modifier.

iv. The modified bitumen properties shall comply


with the requirements of the latest revision of
AASHTO M320 specifications and to the
requirements of Table 4.1.6.3 below.

v. The Contractor shall obtain from the


manufacturer and provide to the Engineer
periodical certificates stating that the modifier
is being incorporated in the bitumen mix in
accordance with the with the approved QA/QC
program.

Frequency of
Ref Property Test Standard Requirements
Testing
to be agreed with the
1. Penetration, 25° C, 100g, 5s, dmm ASTM D5 at each batch
Manufacturer
ASTM D36,
2. Softening Point, °C Min. 65 at each batch
AASHTO T53
3. Viscosity (Brookfield) at 135° C, max °C ASTM D4402 3000 CP at each batch
4. Flash Point Temp, min °C AASHTO T48 230 °C every 500 t
Dynamic Shear before RTFOT, G*/sin ∂,
Min. 1.00 kPa, test temperature @ 10
5. AASHTO TP5 76 °C every 500 t
rad/s, °C, (Where G* = Dynamic Shear
Modulus and ∂ = phase angle)
Rolling Thin Film Oven (RTFO) Mass
6. AASHTO T240 1% at each batch
Loss, max, %
1
Elastic Recovery , 25° C, 10cm ASTM D6084,
7. 75 at each batch
elongation, % after RTFOT AASHTO T301

Dynamic Shear after Rolling Thin Film


8. Oven Test (RTFOT), G*/sin ∂, Min. 2.2 AASHTO TP5 76 °C every 500 t
kPa, test temperature @ 10 rad/s, °C
See requirements
9. Compatibility Test ASTM D5892 under Item 6 of every 500 t
Paragraph 4.1.6.2

Table 4.1.6.3: Modified Bitumen (Performance Grade)


Properties

Continued on page 4-7

♦ 4-6 ♦
copy 249
8 The elastic recovery specified under Item 7 of Table RC Cutback Spraying
4.1.6.3 above corresponds to modified bitumen with either Grade Temp °C
an elastomer or a blend of elastomer and plastomer
RC - 70 40 - 75
polymers. Should the Contractor opt to use plastomer
type polymer only, for the asphalt modification, then the RC - 250 65 - 105
elastic recovery requirement can be replaced by a set of RC - 800 90 - 115
tests that shall be carried out at the start of the project,
RC - 3000 105 - 135
with each set containing three samples, and the results
shall conform to the following Table 4.1.6.4: 4.1.6.4 Medium-Curing (MC) Cutback Bitumen

Property Test Standard Requirements 1 MC cutback shall conform to the requirements of


AASHTO M 82, which covers Grades MC-30, MC-70, MC-
Pressure Aging Vessel Residue 250, MC-800 and MC-3000 and are listed in Table 4.1.6.6.
2 Sampling and testing shall be in accordance with the
Pressure Aging AASHTO standard methods listed in AASHTO M 82.
Vessel (PAV)
AASHTO R28 110 °C 3 MC cutback bitumen spraying temperature ranges
Aging
Temperature, °C. shall be as follows:
Dynamic Shear, MC Cutback Spraying
G*sin∂,
Grade Temp °C
Maximum 5000
37 °C
kPa, AASHTO T315 MC - 30 21 - 63
Test temperature
@ 10 rad/s, °C. MC - 70 45 - 80
Physical MC - 250 70 - 110
Report
Hardening
Creep Stiffness, MC - 800 95 - 125
S, Maximum 300 MC - 3000 110 - 145
MPa m-value,
0 °C
minimum 0.300 AASHTO T313 4.1.6.5 Slow-Curing (SC) Cutback Bitumen
Test temperature
@ 60 s, °C. 1 SC cutback shall conform to the requirements of
Direct tension, ASTM D 2026 which covers Grades SC-70, SC-250, SC-800,
Failure strain, and SC-3000, and are shown in Table 4.1.6.7.
minimum 1.0%
AASHTO T314 0 °C 2 Sampling and testing shall be in accordance with the
Test temperature
appropriate ASTM standard methods.
@ 1.0 mm/min,
°C. 3 SC cutback bitumen spraying temperature ranges
Table 4.1.6.4: Additional Tests Required for Plastomer shall be as follows:
Type Polymer SC Cutback Spraying
Grade Temp °C
9 The percentage of the polymer to be mixed with the
conventional bitumen to modify the latter shall be based SC - 70 45 - 80
on tests to satisfy the job mix formula. SC - 250 70 - 110
10 The modifier shall be pre-blended into the SC - 800 95 - 125
conventional bitumen before mixing with the aggregate in
the hot mix plant. SC - 3000 110 – 145

11 Blending Equipment: The production of the modified 4.1.6.6 Slow-Setting (SS and CSS) Emulsified
bitumen shall require a specialized high shear blending Bitumens Generally
machinery to ensure complete and controlled dispersion
and chemical reaction of the modifiers with the 1 Selection and use of emulsified bitumens shall
conventional bitumen. generally be in accordance with the recommendations in
AASHTO R 5, subject to the following requirements.
4.1.6.3 Rapid-Curing (RC) Cutback Bitumen
2 The manufacturer shall furnish samples of the base
1 RC cutback shall conform to the requirements of bitumen used in the emulsion.
AASHTO M 81, which covers Grades RC-70, RC-250, RC- 3 When samples of undiluted emulsion are not readily
800, and RC-3000 and are listed in Table 4.1.6.5. available for test purposes, tests may be made on the
2 Sampling and testing shall be in accordance with the diluted emulsion and the respective specifications
AASHTO standard methods listed in AASHTO M 81. modified to reflect the changes in properties resulting
from dilution of the bitumen.
3 RC cutback bitumen spraying temperature ranges
shall be as follows:

♦ 4-7 ♦
copy 249
4 All emulsified bitumens shall adhere firmly to the
surface of the mineral aggregate or the highway surface
as appropriate. Failure of the emulsified bitumen to
perform satisfactorily on the job shall be deemed cause
for its rejection regardless of satisfactory laboratory test
results.

4.1.6.7 Anionic Slow-Setting (SS) Emulsified Bitumen

1 Anionic emulsified bitumens shall, prior to dilution,


conform to the requirements of AASHTO M 140, for Types
SS-1 and SS-1h and as listed in Table 4.11.
2 Sampling and testing shall be in accordance with
AASHTO T 59.
3 Emulsified bitumen spraying temperature range shall
be set so that appropriate viscosity for each application is
achieved, if specific viscosity curves are not available the
range values, generally considered as guidance, shall be
25 - 65 degrees C. The temperature range for pugmill
mixing for medium and slow setting types shall be 15-65
degrees C.

RC-70 RC-250 RC-800 RC-30


Parameter/Test
Min Max Min Max Min Max Min Max
Kinematic Viscosity at 60 oC
70 140 250 500 800 1600 3000 6000
centistokes
Flash Point (Tag, open-cup) oC - - 27 - 27 - 27 -
Water percent - 0.2 - 0.2 - 0.2 - 0.2
Distillation Test:
Distillate percentage by volume of total
distillate to 360 oC
To 190 oC 10 - - - - - - -
To 225 oC 50 - 35 - 15 - - -
To 260 oC 70 - 60 - 45 - 25 -
To 315 oC 85 - 80 - 75 - 70 -
Residue from distillation to 360 oC volume
55 - 65 - 75 - 80 -
percentage of sample by difference
Tests on residue from distillation:
Absolute viscosity at 600 2400 600 2400 600 2400 600 2400
60 oC poises
Ductility, 5 cm/min.
100 - 100 - 100 - 100 -
at 25 oC cm
Solubility in Trichloroethylene,
99 - 99 - 99 - 99 -
percent
Spot test with:
- Standard Naphta Negative for all grades
- Naphtha-xylene solvent,
Negative for all grades
percent xylene
- Heptane-xylene solvent,
Negative for all grades
percent xylene

Table 4.1.6.5: Properties of R.C. Cutback Bitumen

♦ 4-8 ♦
copy 249
MC-30 MC-70 MC-250 MC-800 MC-3000
Parameter/Test
Min Max Min Max Min Max Min Max Min Max

Kinematic Viscosity at 60 °C
30 60 70 140 250 500 800 1600 3000 6000
centistokes
Flash Point (Tag, open-cup) °C 38 - 38 - 66 - 66 - 66 -
Water percent - 0.2 - 0.2 - 0.2 - 0.2 - 0.2
Distillation Test:
Distillate percentage by
volume of total distillate to
360 °C
To 225 °C - 25 0 20 0 10 - - - -
To 260 °C 40 70 20 60 15 55 0 35 0 15
To 315 °C 75 93 65 90 60 87 45 80 15 75
Residue from distillation to
360 °C volume percentage of 50 - 55 - 67 - 75 - 80 -
sample by difference
Tests on residue from
distillation:
300 1200 300 1200 300 1200 300 1200 300 1200
Absolute viscosity at 60 °C
poises
Ductility, 5 cm/min. at 25 °C
100 - 100 - 100 - 100 - 100 -
cm
Solubility in Trichloroethylene,
99 - 99 - 99 - 99 - 99 -
percent
Spot test with:
- Standard Naphtha Negative for all grades
- Naphtha-xylene solvent,
Negative for all grades
percent xylene
- Heptane-xylene solvent,
Negative for all grades
percent xylene

Table 4.1.6.6: Properties of M.C. Cutback Bitumen

SC-70 SC-250 SC-800 SC-3000


Parameter/Test
Min Max Min Max Min Max Min Max
Kinematic Viscosity at 60 °C
70 140 250 500 800 1600 3000 6000
cSt
Flash Point (Cleveland open
66 - 79 - 93 - 107 -
cup) degrees °C
Distillation Test:
10 30 4 20 2 12 - 5
total distillate to 360 °C
Volume % Solubility in
99 - 99 - 99 - 99 -
trichloroethylene %
Kinematic viscosity on
4 70 8 100 20 160 40 350
distillation residue at 60°C,St
Asphalt residue:
50 - 60 - 70 - 80 -
Residue of 100 penetration, %
Ductility of 100 penetration 100 - 100 - 100 - 100 -

residue at 25°C, cm Water, % - 0.5 - 0.5 - 0.5 - 0.5

Table 4.1.6.7: Properties of S.C. Cutback Bitumen

♦ 4-9 ♦
copy 249
range values, generally considered as guidance shall be
25-65 degrees C. The temperature range for pugmill
Slow-Setting
mixing for medium and slow setting types shall be 15-65
SS-1 SS-1h degrees C.
Min Max Min Max
Viscosity, Saybolt 4.1.7 Method of Measurement and Basis of
20 100 20 100
Furol at 25 °C, s Payment
Storage stability
- 1 - 1 1 No separate measurement and no items are included
test, 24-h, %
in the Bill of Quantities for the materials described in this
Cement mixing test,
- 2 - 2 Sub-section. Measurement and payment provisions are
%
included in the appropriate Sub-sections of this Section 4.
Sieve test, % - 0.1 - 0.1
Residue by
57 - 57 - 4.2 Prime and Tack coats
distillation, %
Tests on residue
from distillation 4.2.1 Description
100 200 40 90
test: Penetration, 25
1 This Sub-section describes requirements for
°C,100 g, 5 s
furnishing and applying MC cutback bitumen prime coat
Ductility, 25°C, 5 to a previously constructed sub-base or aggregate base
cm/min, cm 40 - 40 - course, highway shoulders, or concrete pavement; and
furnishing and applying RC cutback bitumen or emulsified
Solubility in bitumen as a tack coat to a previously constructed
trichloroethylene % 97.5 - 97.5 - bituminous base or wearing surface to provide bond for a
superimposed bituminous course; all as and where shown
Table 4.1.6.8: Properties of Anionic Emulsified Bitumen on the Drawings.

4.1.6.8 Cationic Slow-Setting (CSS) Emulsified 4.2.2 Materials


Bitumen
4.2.2.1 Medium Curing Cutback Bitumen
1 Cationic emulsified bitumens shall, prior to dilution,
1 MC cutback bitumen (for prime coats) shall be as
conform to the requirements of AASHTO M 208, for Types
recommended by ASTM D 2399. Generally MC 70 shall be
CSS-1 and as listed in Table 4.1.6.9.
used unless otherwise specified.
Slow Setting
4.2.2.2 Rapid-Curing Cutback Bitumen
CSS-1
Min Max 1 RC cutback bitumen (for tack coats) shall be Grades
Tests on emulsions: RC-70 or RC-250 as appropriate and as specified in Sub-
Viscosity, Saybolt Furol at 20 100 section 4.1 – ‘Materials for Bituminous Construction’, or as
25°C, s required by the Engineer.
Storage stability test, 24-h,
1 - 4.2.2.3 Slow-Setting Emulsified Bitumen
%
Particle charge test Positive 1 Slow-setting emulsified bitumen (for tack coats)
Sieve test, % - 0.10 shall be slow setting Grades SS-1, SS-1h or CSS-1, as
Cement mixing test, % - 2.0 appropriate and as specified in Sub-section 4.1 –
Distillation: ‘Materials for Bituminous Construction’, or as required by
57 -
Residue, % the Engineer.
Tests on residue from
distillation test: 100 250 4.2.2.4 Polymer Modified Bituminous Tack Coat
Penetration, 25°C, 100 g, 5 s 1 The polymer modified tack coat material shall be as
Ductility, 25°C, 5 cm/min, cm 40 - specified in Sub-section 4.1, the original base binder
Solubility in (before polymer modification) shall be penetration grade
97.5 -
trichloroethylene % bitumen and the polymer modified bitumen binder shall
Table 4.1.6.9: Properties of Cationic Emulsified Bitumen be as specified under paragraph 4.1.6.2. The viscosity of
the binder used for the polymer modified tack coat
2 Sampling and testing shall be in accordance with
(Brookfield viscosity determined as per ASTM D4402) at
AASHTO T 59.
application temperature shall range between 200 and 400
3 Emulsified bitumen spraying temperature range shall
CP. The softening point and elastic recovery at 25° C (after
be set so that appropriate viscosity for each application is
RTFOT) of the polymer modified tack coat shall not be less
achieved, if specific viscosity curve is not available the
than 80° C and 90% respectively.

♦ 4-10 ♦
copy 249
4.2.3 Equipment 5 Traffic shall not be permitted on surfaces after they
have been cleaned and prepared for prime or tack coat
1 Equipment used for diluting emulsified bitumen,
application.
heating cutback bitumen, spraying cutback and emulsified
bitumen, and for application of blotting material to prime 6 If there are undue delays in scheduling priming or
coats, shall conform with the relevant requirements of this subsequent paving after priming, the surface tolerances
Specification and with the Contractor's approved list of and compaction of the granular course shall be re-verified
equipment. and deficient areas corrected or replaced in an approved
manner at the Contractor's expense.
7 The Contractor shall maintain prime coats and tack
4.2.4 Construction of Trial Sections coats intact until they are covered by the subsequent
1 The Engineer may require trial sections to be pavement course. Any area where the coats have been
constructed prior to the commencement of on-site prime damaged shall be cleaned of all loose material, any
or tack coat applications. The Contractor shall construct surface defects repaired and the coat re-applied at the
trial sections using varying application rates of bitumen, Contractor's expense. Traffic control measures shall
as selected by the Engineer. Each trial section shall be 2 conform to the requirements of the relevant Sections of
lanes wide by 50 m long, at approved locations on or close this Specification.
to the site.
4.2.5.2 Prime Coat Application
2 Each trial section shall be constructed using the same
materials, mixing and spraying equipment, and 1 If required by the Engineer, when the surface is an
construction procedures, proposed for use in the Works. untreated subgrade or a granular surface, the cleaned
3 The objectives of these trials shall be to determine surface shall be given a light application of water and
the adequacy of the Contractor's equipment and the most allowed to dry to the condition deemed appropriate by the
suitable application rates for cutback bitumen prime and Engineer before the bituminous material is applied.
tack coats, or emulsified bitumen tack coats. 2 Heating of MC cutback bitumen and its temperature
4 The Contractor shall not proceed with any on-site at the time of application shall conform to the relevant
coat applications until the methods and procedures requirements of Sub-section 4.1.
established in the trials have been approved. 3 Areas to be primed shall be as shown on the
Drawings and including 200 mm widths outside the edges
4.2.5 Application Procedures of the pavement line; top of embankment slopes to
pavement lines; and between curbs or gutter edges for
4.2.5.1 Medium Curing Cutback Bitumen bridge checks.
1 All equipment used for surface cleaning, heating 4 Application rates for prime coat will be determined
bitumen (if required) and application of prime and tack by the Engineer from the trial sections, and shall be
coats, shall be adequate for the purposes intended and generally within the following ranges:
shall be approved before use.
Range of Application Rates for Prime Coat
2 All surfaces to receive prime or tack coats shall
conform to the specified tolerances and compaction Type of Surface kg./sq.m.
requirements and shall be properly cleaned using power Untreated subgrade surfaces,
brooms or power blowers. The surfaces shall be 0.8 - 1.75
shoulders sub-base and base courses
approved before applying any bitumen material.
Bridge wearing surfaces, asphalt
3 Application of prime coats and tack coats shall be overlay on existing concrete 0.1- 0.4
performed only when the surface to be treated is pavements
sufficiently dry for tack coat and sufficiently moist for as determined
prime coat, and when the atmospheric temperature is Other surfaces from field tests
above 10ºC for the application of tack coat, 15ºC for the or trials
application of prime coat. No application is to be
Table 4.2.5.1: Range of Application Rates for Prime Coat
performed if there is fog, rain, strong winds, dusty
conditions, or dust storms. 5 The Engineer may order additional trial sections
4 The surfaces of all structures, curbs, gutters and and/or alter the previously established rates of application
other highway appurtenances shall be protected in an during progress of the work.
approved manner to prevent them from being splattered 6 Prime coat (MC-70) cutback, or other grade if ordered
or stained with bitumen or damaged during equipment by the Engineer, shall be applied at the rate selected by
operation. The Contractor shall be responsible for making the Engineer, using approved type pressure distributors
good any such staining or damage to the satisfaction of operated by skilled workmen. The spray nozzles and
the Engineer. spray bar shall be adjusted and frequently checked so that
uniform distribution is ensured. Spraying shall cease
immediately upon any clogging or interference of any

♦ 4-11 ♦
copy 249
nozzle, and corrective measures taken before spraying is to the satisfaction of the Engineer. The rate of application
resumed. shall be between 0.25 and 0.5 kg./sq.m.
7 Hand spraying will be approved only for priming 2 The polymer modified tack coat shall be applied at a
small patches or inaccessible areas that cannot be primed temperature ranging from 180° C to 190° C.
by normal operation of the pressure distributor.
8 Application of prime at the junction of spreads shall 4.2.6 Method of Measurement
not be excessive. Any excess shall be removed from the 1 Bituminous prime coat shall be measured by the
surface and any skipped areas or recognized deficiencies square meter of the areas shown on the cross section at
shall be corrected by use of hand sprays. the appropriate rate specified by the Engineer.
9 When required by the Engineer, a light covering of
2 Bituminous tack coat shall be measured by the
blotting material shall be applied to the prime coat 48
square meter of the areas shown on the cross section at
hours after spraying and when it has not dried sufficiently
the appropriate rate specified by the Engineer.
to withstand damage by traffic. The blotting material shall
be smooth fine sand, or other approved material. 3 Polymer Modified Bituminous tack coat shall be
measured by the square meter of the areas shown on the
10 Prime coats shall be cured for 3 days before
cross section at the appropriate rate specified by the
construction traffic is allowed on it or before the
Engineer.
succeeding pavement layer is placed, or as directed by the
Engineer, depending on weather conditions. 4 Surface preparation, protective measures to avoid
staining or damage to appurtenances, blotting of prime
4.2.5.3 Tack Coat Application coats when required, and cleaning stains and repairing
damage caused by equipment, priming or spraying tack
1 Tack coat shall be applied to the areas shown on the
coat at areas outside the edge of the pavement line, etc.,
Drawings on clean dry surface, and the rate shall be as
shall not be measured for direct payment, but shall be
ordered by the Engineer. Emulsified bitumen shall be
considered as subsidiary work, the costs of which are
diluted and thoroughly mixed with an equal amount of
deemed to be included in the rates stated in the Bill of
water before application.
Quantities.
2 Heating of RC cutback bitumen and its temperature at
the time of application shall conform to the relevant 4.2.7 Basis of Payment
requirements of Sub-section 4.1 ‘Materials for Bituminous
Construction’. Where slow-setting emulsified bitumen (SS 1 The amount of completed and accepted work,
or CSS Type) is used for tack coat, it shall not normally measured as provided for above, will be paid for at the
require heating except in temperatures below 20 degrees unit rates for the various items in the Bill of Quantities ,
C. which rate shall be full compensation for supplying
materials, transporting and placing, labor, equipment,
3 The rate of application shall be approved by the
tools and other items necessary for the proper completion
Engineer and after trial tests are carried out it shall be
of the work.
between 0.1 and 0.5 kg./sq.m, depending on whether RC
cutback or emulsified bitumen is used and on the surface
condition of the bituminous course on which the tack coat 4.2.8 Items in the Bill of Quantities
is to be sprayed. The resulting bitumen residue shall be at i. Bituminous prime coat.
least 0.35 kg./sq.m. The Engineer may alter the previously ii. Bituminous tack coat.
established rates of application during progress of the
iii. Polymer modified tack coat.
work, if he deems it necessary.
4 The tack coat shall be allowed to dry only until it is in
4.3 Bituminous Courses
a suitable tacky condition to receive the superimposed
bituminous course. Tack coat application shall not
proceed so far in advance of the following course that it
4.3.1 Description
dries out completely. 1 This Sub-section describes requirements for
5 Spraying procedures shall be as specified for prime furnishing materials, mixing at a central mixing plant, and
coat application. spreading and compacting various bituminous concrete
and other bituminous mixes, all as and where shown on
6 Blotting material shall not be applied to tack coats.
the Drawings.
4.2.5.4 Polymer Modified Tack Coat 2 Requirements with particular application to
bituminous base course, binder and wearing courses,
1 Polymer modified tack coat shall be hot applied over
leveling course, cold mix courses or recycled bituminous
the prepared polymer modified or unmodified bituminous
courses are specified in the respective Sub-sections
layers to receive the polymer modified bituminous layer,
relating to such courses.
as indicated on Drawings. The type of tack coat and its
rate of application shall be compatible with the polymer
modified bituminous layer that will be applied on top of it,

♦ 4-12 ♦
copy 249
4.3.2 Materials 7 In order to meet the requirements, an approved
additive such as Portland cement, hydrated lime or liquid
1 Bituminous plant mixes shall generally be composed anti-strip agent, may be required in the job mix. Portland
of coarse mineral aggregate, fine mineral aggregate, cement shall meet the requirements of AASHTO M 85.
mineral filler or cement if required, and penetration Hydrated lime shall meet the requirements of ASTM C 207,
graded bitumen, polymer modified bitumen (for Type N. Cement or hydrated lime will normally be
performance graded bitumens) with mix additives if required in the approximate range of 2-3% by weight of
specified, cutback bitumen or emulsified bitumen the aggregates and shall be added at the cold feed in dry
appropriate to the type of bituminous course to be or slurry form as directed. Liquid anti-striping agent, if
constructed. needed, will normally be required in the approximate
2 All materials shall conform to the relevant range of 0.6-1.0% by weight of the bitumen, or according
requirements of Sub-section 4.1. to the manufacturer’s specifications.
8 Upon receipt of approval of the job mix formula, the
4.3.3 Job Mixes and Project Mixes Contractor shall adjust his mixing plant to proportion the
1 At least 30 days prior to the date on which the individual aggregates, mineral filler and bitumen to
Contractor intends to begin production at the mixing plant, produce a final mix within the tolerances given in Table
and after receiving approval of the aggregates, and 4.3.3.1. The approved final mix that shall be used in the
delivery to the Site of the bitumen specified, the daily production is called the ’project mix’.
Contractor shall submit for approval his proposed job mix
Specified Tolerances
formula.
Sieve Designation
2 The job mix formula shall stipulate a single (square openings) Aggregate Aggregate
combined grading of all aggregate and filler materials Class A Class B
showing the specific percentage by weight passing each
9.5 mm and above + or - 5.0% + or - 5.0%
sieve size and the specific percentage by weight of each
material to be used in the total mix. 4.75 mm + or - 4.0% + or - 4.0%
3 The job mix formula shall be established by the 2.36 mm - + or - 4.0%
Contractor, under the supervision of the Engineer, in the
field laboratory. Mix design procedures shall conform to 2.00 mm + or - 4.0% -
the Marshall method of mix design and relevant
procedures contained in Asphalt Institute Manual MS-2. 0.15 mm (No. 80) - + or - 3.0%
All trial mixes shall be prepared and tested by the 0.075 mm (No. 200) + or - 1.0% + or - 1.0%
Contractor in the presence of the Engineer.
4 The job mix formula shall specify a combination of Bitumen Content + or - 0.2%
mineral aggregates, including filler and bitumen (plus Temperature of Mix
+ or - 5.0%
bitumen modifier if any) in such proportions as to produce on discharge
a job mix which is within the limits of the specified Table 4.3.3.1: Maximum Variations of Project Mix from
gradation and bitumen content ranges and which meets
Approved Job Mix
the Marshall Test requirements, as prescribed for each
particular type of bitumen course. It shall also stipulate the 9 Any deviation from these limits shall be made only
mixing temperature at discharge from the mixer which, with the approval of the Engineer.
unless otherwise directed, shall be 170 degrees C (for the 10 Conformance to gradation requirements will be
conventional unmodified asphalt). determined on the extracted aggregate in accordance with
5 The Marshall Test procedure shall be used to AASHTO T 30. The bitumen content shall be determined
determine the percentage of bitumen to be incorporated in in accordance with AASHTO T 164 or AASHTO T 308.
the mix. The job mix formula shall take into consideration 11 The Engineer will test the project mix at least twice
the absorption of bitumen into the aggregates. Air voids daily during plant operation and, if necessary, direct the
shall be calculated in accordance with the procedure given Contractor to readjust the plant to conform to the job mix
in the Asphalt Institute Manual, MS-2. The recommended formula. If, due to differing cold feed or hot bin
range of bitumen content is as follows: gradations, the Contractor cannot consistently produce a
project mix meeting the job mix requirements, production
i. Bituminous base and binder courses: 3% to shall cease, the job mix shall be redesigned and
3.8%. reapproved and the plant readjusted to produce a new job
ii. Bituminous wearing course: 3.2% to 4.0%. mix.
12 The participation of the Engineer in the preparation
6 When compacting specimens in accordance with the
of the job mix formula shall in no way relieve the
Marshall Test procedure, the number of blows applied
Contractor of responsibility for producing project mixes
with the compaction hammer shall be 75 on each side,
meeting the specified requirements.
unless otherwise specified.

♦ 4-13 ♦
copy 249
4.3.4 Equipment appropriate shall be issued to each of the Contractor's
senior staff involved in bituminous course work. At the
4.3.4.1 General end of the Contract all the copies shall become the
property of the Employer.
1 Plant and equipment for mixing, transporting,
spreading and compacting bituminous mixes, shall 4.3.4.3 Spreading and Finishing Equipment
conform with the requirements of the relevant subsections
of these specifications and to the Contractor's approved 1 Bituminous courses shall be spread and finished
equipment list. using approved type, self-contained, power-propelled
pavers of sufficient capacity to be capable of laying up to
4.3.4.2 Mixing Plant 80 ton/hr. Pavers shall be provided with electronically
controlled vibratory screed or strike-off assembly with
1 Bituminous mixes shall be produced in an approved
devices for heating the screed, and shall be capable of
batch mixing plant of adequate size with a minimum
spreading and finishing the various courses of bituminous
capacity of not less than 80 ton/hr and a mixer capacity of
plant mix to the proper thickness and in lane and shoulder
not less than 750 kg. batch. The plant shall conform to the
widths applicable to the typical cross sections shown on
relevant requirements of AASHTO M 156.
the Drawings, and in incremental widths between 2.4 m
2 A mechanical batch counter shall be installed as part and 8 m. If the geometry of the cross section allows, wider
of the timing device and shall be designed to register only pavers will be required to cover the full width of the
completely mixed batches. pavement section in order to avoid longitudinal
3 The mixing plant shall be fully equipped to control construction joints.
the gradation of hot dry aggregates and of cold damp 2 The pavers shall be equipped with calibrated sensors
aggregates. A suitable dust collection system shall be to control the road profile in accordance with the design
installed, capable of returning all dust to the mixture shown on the Drawings.
whenever required. Suitable filters shall be incorporated
3 The pavers shall employ mechanical devices such as
whenever the mixing plant is in the vicinity of town, or
equalizing runners, straightedge runners, evener arms or
whenever they are required by law.
other compensating devices, to maintain trueness of
4 The cold feed system shall be of continuous belt feed grade and confine the edges of the mix to true lines
type or other approved system. It should be easily without the use of stationary side forms. Joint leveling
modified to allow hydrated lime slurry to be added to the devices shall be provided for smoothing and adjusting
mix prior to heating, and dry powdered lime added after longitudinal joints between lanes.
heating.
4 The paver shall be equipped with a receiving hopper
5 An approved automatic weighing, cycling and having sufficient capacity for a uniform spreading
monitoring system shall be installed as part of the operation. The hopper shall be equipped with a
batching equipment. Facilities for easy sampling of the distribution system to place the mix uniformly in front of
aggregates from the hot bins whilst the plant is in the full length of the screed.
operation shall also be provided.
5 The screed or strike-off assembly and extensions
6 The Contractor shall systematically inspect and verify, shall effectively produce a finished surface of the required
in the presence of the Engineer, on a weekly basis and evenness and texture without tearing, shoving, or gouging
also whenever suspect the following key operational the mix.
aspects of the mixing plant:
6 The paver shall be capable of being operated at
- State of repair of the screens, and their frame
forward speeds consistent with satisfactory laying of the
mountings.
mix. Speed shall be fully adjustable between 3 m/min and
- Proper working of cold and hot bin gates.
6 m/min.
- Accuracy of batching scales for filler,
aggregates and bitumen. 7 The automatic controls shall consist of an automatic
- Proper working of the nozzles of the mixer linkage arrangement such that, through the process of
bitumen sprayer. automatically adjusting the screed thickness control, the
- State of repair of the paddle tips and liners of mix can be placed and finished to a predetermined grade
the mixer. and a uniform crown or cross section. Articulated
averaging beams utilized for grade control shall be at least
7 The Contractor shall furnish, for reference and
9 m in length.
retention by the Engineer, one complete set of the
8 If during construction, the spreading and finishing
manufacturer's instruction and operating manuals for the
equipment in operation leaves in the pavement surface
mixing plant intended for use.
tracks or indented areas or other objectionable
8 At the commencement of the contract, 2 copies each irregularities that are not satisfactorily corrected by
of the latest editions of Asphalt Institute Specification SS-1 scheduled operations, the use of such equipment shall be
and Manuals MS-2, MS-3, MS-8 and MS-22 shall be discontinued and other satisfactory spreading and
furnished by the Contractor for use by the Engineer's finishing equipment shall be provided by the Contractor.
supervisory staff and, in addition, one copy of each as

♦ 4-14 ♦
copy 249
9 The Contractor shall make available, for reference by Unless otherwise directed, the bitumen temperature shall
the Engineer, the manufacturer's instruction and operating be as given in Table 4.3.6.1.
manuals for each paver intended for use. Max.
Type and Temperature °C
4.3.5 Construction of Trial Sections Grade of immediately after
1 Immediately prior to finalization of the job mix Asphalt discharge from
formula, the Contractor shall lay trial sections of the Pugmill
various bituminous mixes intended for use in the work. 80 - 100 pen. 160
Each trial section shall be 2 lanes wide by 100 m long at
60 - 70 pen. 165
approved locations close to the Site. Each trial section
shall be laid using the same materials, proposed job mix, 40 – 50 pen. 170
mixing, spreading and compaction plant and spreading Table 4.3.6.1: Bitumen Temperature
and compaction procedures, proposed for use in the work.
5 Any conventional (unmodified) bituminous mix
2 Each trial section shall serve as a field verification of
subjected to higher temperature than those shown in
the job mix design. The mix density achievable and the air
Table 4.3.6.1 shall be rejected.
voids at that density shall be determined and, if less than
required, the job mix formula shall be adjusted 6 The mixing temperature for the polymer modified
accordingly. bituminous mixture shall be as determined under Sub-
section 4.1, paragraph 4.1.6.2.
3 Each trial section shall also demonstrate the
adequacy of hauling, spreading and compaction 7 The mixing time required in order to obtain a
equipment and the suitability of the construction methods homogeneous mix and adequate coating of the
and organization proposed. aggregates with bitumen shall be determined by the
Contractor in the presence of the Engineer. This time shall
4 If the trial section meets the required specification,
be determined whenever the source of aggregate for the
the job mix formula will be approved.
mix changes.
5 The trial section shall be carried out at the
8 In batch plants, mixing time shall begin upon entry of
Contractor's expense and is to be removed from Site, if
bitumen into the pugmill.
required by the Engineer.
9 Mixing time for mixing plants will be determined by
4.3.6 Mixing Procedures the following formula or other approved methods: Mixing
time (sec) = Pugmill dead capacity (kg.) divided by pugmill
1 Each aggregate ingredient shall be heated and dried output (kg./sec)
such that the temperature recorded in the hot fines bin
after screening does not exceed 170 degrees C. If any 4.3.7 Surface Preparation
aggregates contain excess moisture so as to cause
foaming in the mixture or their temperature is in excess of 1 When the bituminous mix is to be placed on a
170 degrees C, they shall be removed from the bins and prepared subbase, or base, the surface shall be prepared
disposed of as directed. to meet the appropriate specified compaction and surface
tolerance requirements. The surface shall then be primed
2 Immediately after heating, the aggregates shall be
as specified in Sub-section 4.2 – ‘Prime and Tack Coats’.
screened into at least 3 sizes and conveyed into separate
No bituminous mix shall be laid on a prime coat until it
bins ready for batching and mixing with the bitumen.
has been inspected and approved.
When the aggregates furnished are of such size and
grading that separating into 3 bins is impractical, the 2 When the bituminous mix is to be placed on an
number of required separations may, if approved, be existing bituminous surface, the surface shall be cleaned
reduced to 2 only. Screening operations shall produce, at of all foreign material and broomed free of dust. Any
plant operating capacity, gradations in each of the sizes of loose, broken or shattered bituminous material along the
heated and dried aggregates that are reasonably uniform edges of the existing surface shall be removed and the
and will result in the production of a mix conforming to exposed surface, and a sufficient width of the shoulder
the job mix requirements. adjacent to the edge of the existing surface, shall be
shaped, bladed, compacted and broomed to provide a
3 The dried and heated aggregate and (cold) mineral
uniform firm layer for the new surface course.
filler shall be combined in the plant in the proportionate
3 Broken, soft, or unstable areas of existing bituminous
amounts as determined by the job mix. Just prior to
surface, aggregate base or granular subbase shall be
bitumen entering the mixer, the anti-stripping additive, if
removed and replaced. The areas shall be excavated to a
required, shall be thoroughly mixed with the bitumen
depth as directed and refilled with the specified
which shall then be introduced into the pugmill mixer in
bituminous mix.
the proportionate amount determined by the job mix.
4 Prior to placing of the bituminous mix on an existing
4 The temperature of the bitumen upon entering the
bituminous surface when required, a tack coat as specified
pugmill shall be within 15ºC of the aggregate temperature.
in Sub-section 4.2 – ‘Prime and Tack Coats’ shall be

♦ 4-15 ♦
copy 249
applied to the existing surface at the rate determined by grade line such that conformance with the required
the Engineer. No mixture shall be laid on a tack coat until geometrics, surface tolerance and minimum thickness
it has been inspected and approved. requirements shall be ensured. The reference line shall be
supported at 8m maximum spacing unless there is
4.3.8 Delivery, Spreading and Finishing noticeable sag in the line or the pavement surface, in
which case the maximum spacing shall be 4m.
4.3.8.1 Delivery of Mix to Site 2 The reference line shall be maintained taut and free
1 A sufficient number of haul vehicles shall be from sags at all times during spreading and initial
provided so that adequate supplies of mix are delivered to compacting operations.
ensure that continuous paving will be achieved. 3 Except where the paver is matching a previously
2 Hauling equipment for aggregates and bituminous placed layer, a wire or cord reference line shall be installed
mixes shall consist of vehicles having dump bodies on both sides of the paver for the initial bituminous course
suitable for dumping materials in a windrow or in being laid. Thereafter only one reference line will
spreader boxes. The bodies shall be so constructed that normally be required, if the paver is equipped with
their volume measurement can be accurately determined. adequate automatic super elevation control.
They shall be constructed and maintained such that loss of
4.3.8.3 Spreading and Finishing
materials during hauling operations will not occur. Dump
controls shall be capable of operation from the driver's 1 Bituminous mixes shall be laid only when the air
seat. temperature is at least 5 degrees C or above, when the
3 Hauling equipment for hot bituminous mixes shall existing surface is free from moisture, and when the
have tight, clean, smooth metal beds which are weather is not foggy, rainy, dusty or excessively windy
periodically thinly coated with a lime solution or other (particularly at low temperatures).
approved material to prevent adherence of the mix. All 2 After completion of surface preparation, the
hauling units shall be equipped with a canvas or other bituminous mix shall be spread and finished true to crown
approved type of cover which shall be used to cover the and grade by approved automatically controlled
hot material upon loading at the mixing plant and shall bituminous pavers. The mix may be spread and finished
not be removed until the mix is discharged into the paver. by approved hand methods only where the Engineer
Hot mix material may be transported without such cover determines that machine methods are impracticable.
only if permitted by the Engineer in special circumstances. Hand methods include heated hand tampers of at least 10
4 The dispatching of the hauling vehicles to the Site kg. weight and approved type mechanical (vibratory)
shall be so scheduled that all material delivered is placed tampers.
at least 90 minutes before sunset to allow sufficient time 3 The paver shall spread the bituminous mix without
for compaction, unless the use of artificial light is tearing the surface and shall strike a finish that is smooth,
approved. Delivery of material shall be at a uniform rate true to cross section, uniform in density and texture and
and in an amount well within the capacity of the paving free from hollows, transverse corrugations and other
and compacting equipment. irregularities.
5 The mix at delivery to the paver shall be not more 4 The paver shall be operated at a speed which gives
than 10ºC below discharge temperature at the mixing the best results for the type of paver being used and which
plant. The minimum temperature for the commencement coordinates satisfactorily with the rate of delivery of the
of breakdown rolling is 120ºC. Mix loads of temperature mix to the paver. A uniform rate of placement shall be
less than 120ºC shall not be accepted, and the load shall achieved without repeated intermittent operation of the
be disposed of and another load used. If there is paver.
consistent failure to meet the temperature requirement the 5 The mix shall be delivered to the paver in time to
Engineer shall order paving operations to stop until permit completion of spreading, finishing and compaction
suitable measures are taken by the Contractor to ensure of the mix during daylight hours.
that temperature requirements are met.
6 If during laying, the paver is repeatedly delayed
6 Each haul vehicle shall be weighed after each loading because of lack of mix or if the paver stands at one
at the mixing plant and accurate records shall be kept of location for an extended period, resulting in the (unrolled)
the gross weight and net weight of each load, for each mat under and adjacent to the rear of the spreader falling
vehicle and dates and time of loading. below the minimum temperature for breakdown rolling,
the affected portion of mat shall be cut out and discarded
4.3.8.2 Setting Out and Reference Lines
and a transverse joint shall be constructed. Paving shall
1 The Contractor shall survey the centerline profile and not recommence until the Engineer is satisfied that paving
crown of the existing surface or base and determine a will proceed without interruptions.
reference grade line which will be submitted for approval. 7 Contact surfaces of curbing, gutters, manholes, and
A reference line of wire or suitable cord shall be installed similar structures shall be painted with a thin, uniform
at a uniform grade parallel to the approved reference coating of tack coat material. The bituminous mixture

♦ 4-16 ♦
copy 249
shall be placed uniformly high near the contact surfaces of the joint. As a minimum, the leading lane shall not be
so that after compaction it will be 10 mm above the edge laid in advance of the adjacent trailing lane by more than
of such structure. one half day of paving, and in no case shall the leading
8 If during the paving operations the spreading and lane be more than 0.5 km ahead of the trailing lane
finishing equipment in operation leaves in the pavement without approval. In the event of failure to conform to
surface tracks or indented areas or other objectionable these requirements, the Engineer may temporarily
irregularities that are not satisfactorily corrected by the suspend paving on the leading lane.
scheduled operations, the use of the equipment shall be 4 Unsupported edges of bituminous layers shall be
discontinued, until faults are corrected to the approval of rolled immediately following the rolling of the longitudinal
the Engineer. If this is not possible, other satisfactory joint. The material along the unsupported edge may, if
spreading and finishing equipment shall be provided by approved, be raised slightly by hand methods, to ensure
the Contractor. that the full weight of the roller will bear fully on the edge
9 Unless otherwise directed by the Engineer, where material.
successive bituminous layers are to be placed, the surface 5 On completion, the longitudinal edges of bituminous
of each existing layer shall be swept clean with a power pavement shall be true to the width and alignment as
broom, or by other approved means and a tack coat shown on the Drawings. The edges shall be cut back if
applied at the rate designated by the Engineer and in necessary prior to rolling, additional mix placed manually
accordance with the relevant requirements of Sub-section in a longitudinal strip adjoining each pavement edge, and
4.2. the edge rolled down to a neat 3:1 (horizontal:vertical)
10 Transverse joints in succeeding layers shall be offset slope or as shown on drawings.
by at least 2 m. Longitudinal joints shall be offset at least 6 Transverse joints shall be carefully constructed and
150 mm. thoroughly compacted to provide a smooth riding surface.
11 Bituminous mix shall be spread in one or more Joints shall be straight-edged and string-lined to assure
layers so that, after rolling, the nominal thickness of each smoothness and true alignment. If the joint is formed with
layer of the compacted bituminous material shall be a bulkhead, such as a board, to provide a straight line and
between 2 and 3 times maximum size of aggregate. This vertical face, it shall be checked with a straight edge
maximum thickness may be increased slightly when such before fresh material is placed against it to complete the
increase is more appropriate to total pavement thickness joint. If a bulkhead is not used to form the joint and the
and provided the Engineer determines that such increased roller is permitted to roll over the end of the new material,
thickness will not be detrimental to the quality of the the line shall be located back of the rounded edge a
finished bituminous course, and the Contractor can show sufficient distance to provide a true surface and cross-
that the required density is attained throughout the layer section. If the joint has been distorted by traffic or by
thickness. other means, it shall be trimmed to line. In either case, the
joint face shall be painted with a thin coating of
12 Transitions and structure approaches shall meet the
bituminous material before the fresh material is placed
design criteria for geometrics, the surface tolerance
against it.
specifications, and shall not be visually discontinuous or
abrupt in appearance. 4.3.8.5 Compaction
13 Side roads, entrances and lay-bys shall be paved in
1 Rollers shall be operated by competent and
accordance with the details shown on the Drawings.
experienced operators in accordance with the
4.3.8.4 Joints and Edges manufacturer's instructions, copies of which shall be
submitted to the Engineer. Rollers shall be kept in
1 All joints between old and new pavements or operation continuously if necessary, so that all parts of the
between successive days' work shall be such as to ensure pavement receive substantially equal compaction at the
thorough and continuous bond between the old and new time desired.
material.
2 After spreading and strike-off, and as soon as the mix
2 Before placing fresh mix against previously laid conditions permit the rolling to be performed without
asphalt layers or against old pavement, the contact excessive shoving or tearing, the mixture shall be
surface shall be saw-cut to a near vertical face, and shall thoroughly and uniformly compacted, using approved
be sprayed or painted with a thin uniform coat of tack coat types, sizes and numbers of rollers. Rolling shall not be
material unless otherwise directed. Longitudinal joints prolonged to the point where cracks appear or shoving or
shall be made by overlapping the paver screed on the displacement occurs.
previously laid material (cut back as necessary) and
depositing a sufficient amount of fresh mix so that the
joint formed will be smooth and tight.
3 The Contractor shall schedule paving operations so
as to minimize the exposure of the leading lane of
longitudinal joints prior to the completion and compaction

♦ 4-17 ♦
copy 249
3 Rollers shall be of self-propelled 2-axle tandem or successive trips by at least one half the width of the rear
three wheel steel-tired, pneumatic-tired and vibratory steel wheels. Alternate trips of the rollers shall be of slightly
wheel types, in proper operating condition, capable of differing lengths.
reversing without backlash or tearing of the surface, and 12 The speed of the rollers, rolling pattern and, in the
shall be operated at speeds slow enough to avoid case of vibratory rollers, the frequency and amplitude of
displacement of the bituminous mix. vibration, shall be approved by the Engineer. To prevent
4 Initial breakdown rolling shall be carried out by use adhesion of the mix to the rollers, the wheels shall be kept
of 2 dual-drum vibrating steel-wheeled vibratory rollers properly and lightly moistened with water. An excessive
each of minimum weight 7,000 kg. and with vibrating use of water will not be permitted.
frequency of 2,000-3,000 cycles/min. These rollers shall be 13 The rolling pattern, type and number of rollers shall
purpose made for compaction of hot bituminous courses. be established by a site trial so as to achieve the required
5 Intermediate rolling shall be carried out by use of at compaction. The approved rolling pattern shall be
least 2 self-propelled, tandem pneumatic smooth-tired followed.
rollers each capable of exerting contact pressures of up to 14 The initial or breakdown rolling shall be followed by
690 KN./sq.m. (100 psi) and ballast - adjustable to ensure intermediate rolling involving 3 coverages with
uniform wheel loadings. pneumatic-tired rollers unless otherwise specified.
6 Final rolling shall be carried out by use of two, 2-axle 15 Finishing rolling shall then be carried out by means
tandem steel-tired static rollers each of minimum weight of 2-axle tandem power steel rollers unless otherwise
10,000 kg., capable of exerting contact pressures of up to designated. If, the specified density is not achieved,
65 kg./cm2 (350 lb/in.). changes shall be made in size and number of rollers being
7 Prior to use on Site of pneumatic-tired rollers, the used to ensure the compaction requirements are met.
Contractor shall furnish, for reference and retention by the 16 The average compacted density for all bituminous
Engineer, manufacturers' charts or tabulations showing courses shall be equal to or greater than 98% of the
the contact areas and contact pressures for the full range average Marshall bulk specific gravity for each day's
of tire inflation pressures and for the full range of tire production unless otherwise directed by the Engineer. It is
loadings for each type and size of compactor tire to be also required that 90% of the results shall be greater than
used. The Contractor shall ensure that tire pressures are the minimum specification tolerance limit of 96.3%.
maintained at all times in conformity with such charts or
17 Any mix that becomes loose, broken, mixed with
tabulations. The maximum allowable tolerances shall be
foreign material, or which is in any way defective in finish
plus or minus 35 KN./sq.m. (5 psi).
or density, or which does not conform in all other respects
8 Rollers shall move at a slow but uniform speed, with the specified requirements shall be removed,
generally with the drive roll or wheels nearest to the paver. replaced with suitable material and properly finished.
Recommended speeds are shown in Table 4.3.8.1 (km/h.).
4.3.9 Sampling and Testing
Speed of Rollers (Km./hr.)
Roller Type Breakdown Intermediate Finish 1 Sampling and testing shall conform to the
Rolling Rolling Rolling requirements of the relevant Sub-sections of the
Steel Tired Specification and Table 4.3.9.1.
3 5 5
Static Rollers 2 The Marshall bulk specific gravity shall be
Pneumatic determined in accordance with AASHTO T 166. The
5 5 9
Tired Rollers Marshall specimens shall be prepared from the same
Vibratory material used in construction, taken from samples of fresh
4.5 4.5 -
Rollers bituminous mix at the mixing plant or from trucks
Table 4.3.8.1: Recommended Speeds of Rollers delivering mix to the Site. Oven heating for up to 30
minutes to maintain the heat of the sample is permissible.
9 If vibratory rollers are used, when it is required to
3 The bulk specific gravity of the mix as placed and
change direction the vibration shall be turned off before
compacted in situ shall be determined from 100 mm
the roller is stopped, and turned on after motion in the
nominal diameter core samples, or slab samples cut from
new direction begins.
each compacted layer on the road at locations designated
10 Rolling shall begin as soon as the mixture will bear by the Engineer who may require additional tests to
the roller weight without undue displacement. The determine limits of areas deficient in density, or for
minimum temperature of the mat at which rolling shall be recheck.
allowed to start is 120ºC.
4 Samples for in-situ bulk specific gravity
11 Breakdown rolling shall consist of 3 complete determinations shall be taken in sets of 2 from each
coverages of each of the 2 rollers specified in Item 4 above pavement location. Minimum frequency of sampling for
unless otherwise directed. Rolling shall be longitudinal, each bituminous layer shall be one set/lane/500 m, with a
beginning at the low side of the spread of material and minimum of one set per day of placing bituminous layers.
proceeding towards the high side, overlapping on

♦ 4-18 ♦
copy 249
Frequency of Tests Required
(A) (B)
Work item Tests at source of Frequency for all tests Tests at road site Frequency for all
material mentioned under (A) tests mentioned
under (B)
4-1
Materials used in 1. Specific gravity
bituminous mix (at & water absorption
- Test for each
batching plant)
Source
2. Abrasion Test - Test for each 1,000
cu.m of asphalt
3. Chert content
produced
4. Clay lumps & - When materials
friable materials quality changes
5. Flaky and elongated - As requested
particles
6. Soundness
4-2
Materials used in
1. Gradation
bituminous mix (from
hot bins)
2. Specific gravity - Test for each source
and water - When materials
absorption quality changes
3. Plasticity index - As requested

4. Sand equivalent
5. Stripping with
asphalt
4-3 1. Complete mix - For each project
Bituminous mix design in accordance -When results are not
design for each with American Asphalt consistent with the mix
course (from hot bins) Institute (MS2) design results.
2. Loss of stability -As requested
4-4
Bituminous Mix
At batching plant
Marshall stability for
each layer
1. Stability - Test for each day’s 1. Stability
2. Flow production 2. Flow
- Test each 3
3. Extraction (binder - Test for every 200 3. Extraction (binder working days
content & gradation) cu.m of asphalt content & gradation) - Test for each
4. Air voids produced per day 4. Air voids batching plant
- Test for each
5. Voids in mineral 5. Voids in mineral - As requested
batching plant
aggregates aggregates
- As requested
6. Daily Marshall 6. Daily Marshall
density density
-Test each 200
7. Compaction
lin.m., per lane
density
7. Loss of stability - Once a week and for batch
& thickness (after
layer
final compaction)
- As requested
- Test each 3
8. Loss of stability working days
- As requested
Table 4.3.9-1 Frequency of Testing for Bituminous 6 The Contractor shall, when necessary, furnish and
Pavement apply cold water, ice, or other cooling substance to the
surface of the pavement to prevent the sampling from
5 The Contractor shall cut the samples with an
shattering or disintegrating. The Contractor shall fill and
approved core drill in the presence of the Engineer. The
compact all test holes at his own expense.
equipment shall be capable of cutting the mixture without
shattering the edges or otherwise disturbing the density of
the specimen.

♦ 4-19 ♦
copy 249
4.3.10 Surface Tolerances 5 One core shall be taken from each section by the
Contractor at approved locations and in the presence of
1 The fully compacted and completed bituminous
the Engineer. When the measurement of the core from
course shall conform to the lines, grades and cross
any paved section is not deficient by more than 5 mm
sections as shown on the Drawings.
from the specified thickness, the core will be deemed to be
2 The elevations of the finished course shall be of the specified thickness as shown on the Drawings.
checked by the Contractor in the presence of the Engineer
6 When the measurement of the core from any paved
at maximum intervals of 10m and at intermediate points
section is deficient by more than 5 mm but not more than
as directed.
20 mm, 2 additional cores spaced at not less than 100 m
3 The finished surface is tested with a 3 m long shall be taken and used together with the first core to
straightedge, placed parallel to, or at right angles to the determine the average thickness of such section.
centerline, the maximum deviation of the surface from the
7 When the measurement of the core from any paved
testing edge between any 2 contact points shall not
section is less than the specified thickness by more than
exceed the tolerances specified for each type of
20 mm, the average thickness of such section shall be
bituminous course laid, as shown under Paragraphs
determined by taking additional cores at not less than 5 m
4.4.10.1 and 4.5.10.1 for the bituminous base and wearing
intervals parallel to the centerline in each direction from
courses, respectively. All areas which exceed the specified
the affected location until, in each direction, a core is taken
tolerances shown under Paragraphs 4.4.10.1 and 4.5.10.1
which is not deficient by more than 20 mm. Exploratory
shall be corrected by removing the defective sections of
cores for deficient thickness will not be used in average
bituminous course and reconstructing them, or if
thickness determinations.
approved by the Engineer, by increasing the thickness of
the succeeding course(s). 8 Any deficiencies in the total thickness of bituminous
courses shall be subject to a proportional reduction in the
4 The finished surface shall also be tested using the
volume of final (surface) course measured for payment, or
rolling straight edge, and the areas which exceed the
complete removal and replacement, as shown in Table
specified tolerances shown under Paragraphs 4.4.10.2 and
4.3.11.1 below. Alternatively, the Contractor shall
4.5.10.2 shall be corrected by removing the defective
construct at his own expense, a surface course overlay, if
sections of bituminous course and reconstructing them, or
practicable in the judgment of the Engineer. Any such
if approved by the Engineer, by increasing the thickness of
overlay shall be a minimum of 40 mm compacted
the succeeding course(s).
thickness and to the specified standard of the course it is
5 The tolerances specified for evenness of finished overlaying.
surfaces for all types of bituminous courses, shall not 9 If the deficiency in total thickness of the asphalt
invalidate the tolerances specified for construction layers is from 0 to 3mm, full payment will be made, on
thickness and elevations of such courses. condition that deficiencies are not found in more than 10%
of the total project. Deficiencies between 3mm and 10mm,
4.3.11 Determination of Thickness of 80% of the full payment for the bituminous courses will be
Courses made.
1 The Contractor shall compensate for minor
Deficiency in the
deficiencies in the thickness of any bituminous course in Deficiency in the
Thickness of
the pavement structure by increasing the thickness of the Thickness of Total Action
Individual Asphalt
subsequent bituminous course. After completion of the Asphalt Layers
Layers
final (wearing) course any deficiencies in the thickness of
any course which have not been compensated for by ≤ 5mm ≤ 3mm Full payment
increasing the thickness of a subsequent course, will be 5 – 20mm 3 – 10mm 80% payment
considered deficiencies in the final (wearing) course.
> 20mm (or 25% > 10mm (or 15%
2 Cylinder core samples shall be taken as specified for Remove and
of design of design
in- situ bulk specified gravity core samples. replace
thickness) thickness)
3 Thickness of bituminous courses shall be determined Table 4.3.11-1: Tolerances in bituminous concrete layer
by average caliper measurement of cores, rounded
thicknesses
upwards to the nearest mm.
4 Paved sections to be measured separately shall 4.3.12 Method of Measurement
consist of each 300 lin.m. section in each traffic lane. The
last section in each traffic lane shall be 300 m plus the 1 Conventional and polymer modified bituminous
fractional part of 300 m remaining. Other areas such as courses are measured in the respective Sub-sections for
intersections, entrances, crossovers, ramps, etc. shall be each type of bituminous course transported, furnished,
measured as one section and the thickness of each shall spread, compacted, completed and accepted.
be determined separately. Small irregular unit areas may Measurement shall not include the rolled down edge
be included as part of another section. strips of bituminous courses placed outside the edge of
paving shown on the Drawings.

♦ 4-20 ♦
copy 249
2 Bituminous prime and tack coats are measured as 4.4.3 Job Mix and Project Mix
prescribed in Sub-section 4.2. 1 The job mix formula shall be established by the
3 Bituminous overlays constructed by order of the Contractor in accordance with the procedures and
Engineer to correct deficiencies in total thickness of requirements of Sub-section 4.3.
bituminous courses or to compensate for major 2 The job mix for bituminous base course shall
deficiencies in the thickness of any underlying bituminous conform to the following composition limits as shown in
course, shall not be measured for direct payment, but Table 4.4.3.1.
shall be considered as subsidiary work the costs of which
will be deemed to be included in the respective rates for Parameter Value
bituminous courses. stated in the Bill of Quantities.
Marshall stability at 80ºC (Kg.) 1200
4 Establishment of the job mix formula, surface
preparation, construction of joints, hand painting of Flow (mms) 2- 3.5
contact surfaces, remedial treatment of surface 12%
irregularities, cutting of cores and slabs for testing or Voids in mineral aggregate, (VMA)
(minimum)
measurement purposes, reinstatement of core and slab
areas of pavement, rolled down longitudinal bituminous Air voids 4-7%
edge strips, additional thickness of bituminous course in Voids filled with bitumen, (VFB) 50 to 70%
excess of the specified thickness, and other ancillary items
Loss of Marshall stability by
shall not be measured for direct payment, but shall be
submerging specimens in water at 60°C
considered as subsidiary work the costs of which will be
for 24 h. compared to stability Max. 25%
deemed to be included in the respective rates for
measured after submersion in water at
bituminous courses stated in the Bill of Quantities.
60°C for 30 minutes

4.3.13 Basis of Payment


% Air voids at refusal Min. 2%
1 The amount of completed and accepted work,
measured as provided for above and as measured in the Table 4.4.3.1: Job Mix Requirements for Bituminous Base
various Sub-sections of Section 4, will be paid for at the Course
unit rates for the various items in the Bill of Quantities,
3 Prior to final approval, the proposed job mix, but
which rate shall be full compensation for supplying
with a bituminous content at the upper percentage limits
materials, transporting and placing, labor, equipment,
shall be compacted to refusal, (400, 500 and 600 blows)
tools and other items necessary for the proper completion
and the resulting voids in the mix shall not be less than
of the work.
2%.
4 After the job mix formula has been established and
4.4 Bituminous Base Course
approved, all mixes furnished shall conform to it within
the stated tolerances.
4.4.1 Description
5 The job mix formula shall be re-established if the
1 This Sub-section describes requirements for source of aggregate, filler or bitumen changes.
furnishing materials, mixing at a central mixing plant, and
spreading and compacting conventional or polymer 4.4.4 Equipment
modified bituminous base course on an approved
aggregate base course or granular subbase, as shown on 1 Plant and equipment for mixing, hauling, placing and
the Drawings. compacting bituminous base course material, shall
conform to the relevant requirements of Sub-section 4.3.
4.4.2 Materials
4.4.5 Construction of Trial Sections
1 All materials shall conform to the relevant
requirements of Sub-section 4.1. 1 Trial sections shall be constructed as and where
directed and in accordance with the relevant requirements
2 Unless otherwise shown on the Drawings, bitumen
of Sub-section 4.3.
for base course construction shall be 60/70 penetration
graded bitumen.
4.4.6 Mixing Procedures
3 For modified bitumen, unless otherwise shown on
the Drawings, bitumen for base course construction shall 1 Handling and mixing of bitumen (including modifier
not be lower than 60/70 penetration graded bitumen and anti-stripping agent, if any) and aggregates (including
modified with one of the polymers specified in Sub- mineral filler if required) shall be in accordance with the
section 4.1, Paragraph 4.1.6.2 and as per these same relevant requirements of Sub-section 4.3.
specification requirements.

♦ 4-21 ♦
copy 249
4.4.7 Surface Preparation 4 The longitudinal regularity of the surfaces of base
course as measured by the rolling straight-edge set at 5
1 Preparation of the surface upon which the
mm shall be such that the number of surface irregularities
bituminous base course mix is to be laid, shall be
is within the relevant limits stated in Table 4.4.10-2. No
appropriate to the type and condition of such surface and
irregularity exceeding 10 mm shall be permitted.
shall conform with the relevant requirements of Sub-
section 4.3.
Length 300m 75m
4.4.8 Delivery, Spreading and Finishing
Max. permitted number of
20 9
4.4.8.1 General surface irregularities

1 The delivery, spreading and finishing of bituminous Table 4.4.10.2: Tolerances on bituminous base course
mix for base course shall conform with the relevant surface irregularity when tested by rolling straight-edge
requirements of Sub-section 4.3 and to the following
particular requirements.
4.4.11 Determination of Thickness
4.4.8.2 Rollers 1 Procedures for determining the average compacted
1 The rollers, rolling sequence, pattern and speed shall thickness of bituminous base course shall conform with
be as stipulated in Sub-section 4.3, Paragraph 4.3.8.5. the relevant requirements of Sub-section 4.3 and to the
following particular requirements.
2 The number of rollers used for any stage of rolling
may be reduced by the Engineer to one, provided that the 2 Cores for thickness measurements shall be used to
base course width being compacted is less than 5.5 m and determine if changes are necessary in the constructed
provided an equivalent standby roller is available on Site thickness of succeeding bituminous layers to rectify any
as replacement in the event of breakdown of the operating thickness deficiencies in the bituminous base course.
roller. 3 In cases where the bituminous base course will not
be covered by superimposed binder or wearing courses,
4.4.8.3 Standard of Compaction the base course shall be deemed to be the final (wearing)
1 The compacted density of the bituminous base course for the purposes of determining the proportion of
course shall be equal to or greater than 98% of the wearing course volume measured for payment or for the
average Marshall bulk density for each day's production or purposes of any overlay ordered to correct deficiencies. In
otherwise as directed by the Engineer. such cases, the surface base course layer shall meet the
Surface Tolerance requirements specified under Clause
4.4.9 Sampling and Testing 4.5.10 for wearing courses.

1 Sampling and testing shall conform to the relevant 4.4.12 Method of Measurement
requirements of Sub-section 4.3, and Table 4.3.9.1.
1 Conventional or polymer modified bituminous base
4.4.10 Surface Tolerances course shall each be measured in cubic meters of mix
furnished, spread, compacted, completed and accepted.
1 Surface tolerances shall conform with the relevant Measurement shall be based on the areas and thickness as
requirements of Sub-section 4.3 and to the following shown on the Drawings or otherwise directed by the
particular requirements. Engineer.
2 The tolerances on elevations of finished bituminous 2 Where bituminous base course is intended to serve
base course surface shall be not greater than + 6 mm. as a wearing course, any deficiencies in thickness shall,
3 When the finished surface is tested with a 3 m long unless an overlay is constructed at the Contractor's
straightedge, placed parallel to, or at right angles to the expense, result in a proportion only of the base course
centerline, the maximum deviation of the surface from the volume being measured for payment. Proportions shall
testing edge between any two contact points shall not be determined in accordance with the thickness
exceed 5 mm (Table 4.4.10.1). deficiencies stated in Sub-section 4.3, Table 4.3.11.1.

Property Tolerance Action 4.4.13 Basis of Payment


Max. Replace (min. 15m 1 The amount of completed and accepted work,
Surface elevation measured as provided for above, will be paid for at
6mm length of road)
the unit rates for the various items in the Bill of
Surface irregularity Max. Replace (min. 15m Quantities, which rate shall be full compensation for
(3m straight edge) 5mm length of road) supplying materials, transporting and placing, for
Table 4.4.10.1: Tolerances on bituminous base course labor, equipment, tools and other items necessary for
surface elevation and straight edge irregularity the proper completion of the work.

♦ 4-22 ♦
copy 249
4.4.14 Items in the Bill of Quantities 3 After the job mix formula has been established and
approved, all subsequent mixes shall conform to it within
i. Bituminous base course (Class A, B). the allowable tolerances, as shown in Table 4.5.3.1.
ii. Polymer modified bit. base course (Class A, B). 4 The Job mix formula shall be re-established if the
source of aggregate, filler or bitumen is changed.
4.5 Bituminous Binder and Wearing 5 When tested for resistance to water damage in
Courses accordance with AASHTO T-283 ‘Resistance of Compacted
Asphalt Mixtures to Moisture-Induced Damage’, the
4.5.1 Description conventional and polymer modified bituminous wearing
course mixtures shall have a retained tensile strength
1 This Sub-section describes requirements for
greater than or at least equal to 80%. In cases where the
furnishing materials, mixing at a central mixing plant, and
anti-stripping agents are not successful in providing the
spreading and compacting bituminous binder course and
specified tensile strength ratio, the Contractor shall
bituminous wearing course on an approved base course,
consider alternative means, such as the use of hydrated
as shown on the Drawings.
lime to achieve this purpose.

4.5.2 Materials
4.5.4 Equipment
1 All materials shall conform to the relevant
1 Plant and equipment for mixing, hauling, placing and
requirements of Sub-section 4.1
compacting bituminous binder and wearing courses
2 Unless otherwise shown on the Drawings, bitumen material shall conform to the relevant requirements of
for binder and wearing courses construction shall be 60/70 Sub-section 4.3.
penetration graded bitumen, or any other suitable grade
for the climatic condition of the project. 4.5.5 Construction of Trial Sections
3 For polymer modified bitumen, unless otherwise
1 Trial sections shall be constructed as and where
shown on the Drawings, bitumen for binder and wearing
directed and in accordance with the relevant requirements
courses construction shall not be lower than 60/70
of Sub-section 4.3..
penetration graded bitumen modified with one of the
polymers specified in Sub-section 4.1, Paragraph 4.1.6.2..
4.5.6 Mixing Procedures
4.5.3 Job Mix and Project Mix 1 Handling and mixing of bitumen (including modifier
and anti-stripping agent, if any) and aggregates (including
1 The job mix formula shall be established by the
mineral filler if required) shall be in accordance with the
Contractor in accordance with the procedures and
relevant requirements of Sub-section 4.3.
requirements of Sub-section 4.3.
2 The job mix for bituminous binder and wearing 4.5.7 Surface preparation
courses shall conform to the following composition limits
as shown in Sub-section, Table 4.5.3.1. 1 Preparation of the surface upon which the
bituminous binder and wearing course mixes are to be
Binder Wearing laid, shall be appropriate to the type and condition of such
Property
Course Course surface and shall conform to the relevant requirements of
Marshall stability at 80ºC (Kg.) 1300 1400 Sub-section 4.3.

Flow (mms) 2- 4.5 2- 5 4.5.8 Delivery, Spreading and Finishing


Voids in mineral aggregate
13- 14% 14- 15% 4.5.8.1 General
(VMA)
Air voids 4- 7% 4- 7% 1 The delivery, spreading and finishing of bituminous
mix for binder and wearing courses shall conform with the
50 to 50 to
Voids filled with bitumen, (VFB) relevant requirements of Sub-section 4.3 and to the
70% 70%
following particular requirements.
Loss of Marshall stability by
submerging specimens in water 4.5.8.2 Rollers
at 60°C for 24 h. compared to Max Max
stability measured after 25% 25% 1 The rollers, rolling sequence, pattern and speed shall
submersion in water at 60°C for be as stipulated in Sub-section 4.3, Paragraph 4.3.8.5.
30 minutes 2 The number of rollers used for any stage of rolling
% Air voids at refusal Min 2% Min 2% may be reduced by the Engineer to one, provided that the
course width being compacted is less than 5.5 m in width,
Table 4.5.3-1: Job Mix Requirement for Bituminous Binder and provided an equivalent stand-by roller is available on
and Wearing Course

♦ 4-23 ♦
copy 249
Site as replacement, in the event of breakdown of the 5 The combination of the permitted tolerances in the
operating roller. levels of the different pavement layers, excluding
aggregate base and sub-base courses, shall not result in a
4.5.8.3 Standard of Compaction reduction of thickness by more than 10 mm from the
1 The compacted density of the bituminous binder and specified thickness, as shown on the Drawings, nor a
wearing courses shall be not less than 98% of the average reduction in the final wearing course thickness by more
Marshall bulk density for each day's production. than 5 mm from that specified or shown on the Drawings.

4.5.8.4 Skid Resistance and Surface Texture 4.5.11 Determination of Thickness


1 Surface Texture: Conventional and polymer modified 1 Procedures for determining the average compacted
bituminous wearing course layer shall have a texture thickness of bituminous binder and wearing courses shall
depth of at least 0.8mm tested in accordance with the conform to the relevant requirements of Sub-section 4.3,
Sand Patch Test ASTM E 965. One Test shall be done Clause 4.3.11 and the tolerances/deficiencies shall comply
every 500m length of constructed road. with the relevant requirements of Table 4.3.11.1 and with
the requirements of Item 2 following.
4.5.9 Sampling and Testing 2 Cores for thickness measurements of the binder
1 Sampling and testing shall conform to the relevant course shall be used to determine if changes are
requirements of Sub-section 4.3 and Table 4.3.9.1. necessary in the constructed thickness of the wearing
course to rectify any thickness deficiencies in the binder
4.5.10 Surface Tolerances course.

1 Surface tolerances shall conform with the relevant 4.5.12 Method of Measurement
requirements of Sub-section 4.3 and to the following
particular requirements. 1 Conventional and polymer modified bituminous
binder course and bituminous wearing courses shall each
2 Tolerances on elevations of finished bituminous
be measured by the cubic meter of mix transported,
binder and wearing course surfaces shall be not greater
furnished, spread, compacted, completed and accepted.
than + 6 mm when compared to the design profile shown
Measurement shall be based on the areas and thickness as
on the drawings.
shown on the Drawings or otherwise directed by the
3 When the finished binder or wearing course surface Engineer.
is tested with a 3 m long straightedge, placed parallel to,
2 Deficiencies in thickness of the wearing course shall,
or at right angles to the centerline, the maximum
unless an overlay is constructed at the Contractor's
deviation of the surface from the testing edge between
expense, result in a proportion only of the wearing course
any two contact points shall not exceed 3 mm (Table
area being measured for payment. Proportions shall be
4.5.10-1).
determined in accordance with the thickness deficiencies
stated– in Sub-section 4.3, Table 4.3.11.1
Property Tolerance Action
Surface Replace (minimum 4.5.13 Basis of Payment
Max. 6mm
elevation 15m length of road)
1 The amount of completed and accepted work,
Surface
Replace (minimum measured as provided for above, will be paid for at the
irregularity (3m Max. 3mm
15m length of road) unit rates for the various items in the Bill of Quantities ,
straight edge)
which rate shall be full compensation for supplying
Table 4.5.10.1: Tolerances on bituminous wearing course materials, transporting and placing, labor, equipment,
surface elevation and straight edge irregularity tools and other items necessary for the proper completion
of the work.
4 The longitudinal regularity of the surfaces of the
finished binder or wearing course as measured by the
rolling straight-edge set at 5 mm shall be such that the
4.5.14 Items in the Bill of Quantities
number of surface irregularities is within the relevant i. Bituminous binder course.
limits stated in Table 4.5.10-2. No irregularity exceeding 10 ii. Bituminous wearing course (Class A, B).
mm shall be permitted.
iii. Polymer modified bituminous binder course.
Length 300m 75m iv. Polymer modified bituminous wearing course
(Class A, B).
Max. permitted number of
15 7
surface irregularities

Table 4.5.10.2: Tolerances on bituminous wearing course


surface irregularity when tested by rolling straight-edge

♦ 4-24 ♦
copy 249
4.6 Bituminous Seal Coats – Surface 4.6.4 Construction of Trial Sections
Dressings 1 Before commencement of Site seal coat applications,
the Contractor shall construct trial sections using varying
4.6.1 Description application rates for bitumen and for aggregates, as
selected by the Engineer. Each trial section shall be two
1 This Sub-section describes requirements for
lanes wide by 50 m long, at approved locations on or close
furnishing of materials and one or more applications of
to the Site.
cutback bitumen and cover material, or a single
application of emulsified bitumen, or spreading emulsified 2 Each trial section shall be constructed using the same
bitumen slurry, to previously prepared base course or materials, mixing, spraying, spreading, rolling and
wearing course surfaces, as shown on the Drawings. brooming equipment, and construction procedures,
proposed for use in the Works. Trial sections for slurry
2 Bituminous slurry seal coat (BSSC) shall consist of
seals shall be along existing bituminous pavements in the
spreading and screeding a mixture of emulsified bitumen,
vicinity of the Site.
sand aggregate and water.
3 The objectives of these trials shall be to determine
3 Single bituminous surface treatment (SBST) shall
the adequacy of the Contractor's equipment, the most
consist of a single application of cutback or straight run
suitable application rates for cutback bitumen, emulsified
bitumen, and sand aggregate or as specified.
bitumen and the various gradations of aggregate, and the
4 Double bituminous surface treatment (DBST) shall most suitable consistency of slurry seal to fill cracks and
consist of an application of cutback or straight run leave a residual coating of 3 mm over the entire
bitumen and coarse graded cover aggregate followed not bituminous wearing surface.
less than 5 days later by a second application of cutback or
4 The Contractor shall not proceed with any seal coat
straight run bitumen and medium graded aggregate, or as
applications until the methods and procedures established
specified.
in the trials have been approved.

4.6.2 Materials
4.6.5 Rates of Application
4.6.2.1 Bitumen
1 Application rates for cutback and emulsified bitumen
1 Bitumen for SBSD and DBSD (surface dressing) and for the various cover aggregate gradations, will be
applications shall be rapid-curing RC-800 grade, determined by the Engineer from the trial sections and
conforming to the relevant requirements of Sub-section shall be generally within the ranges given in Table 4.6.5.1.
4.1 and AASHTO M-81.
2 Bitumen for BSSC (slurry) applications shall be a Approx. Rate of Application
cationic, slow setting emulsified bitumen Grade CSS-1 Types of Seal Coat
Aggregate Binder
conforming to the relevant requirements of Sub-section
(kg/sq.m.) (kg/sq.m.)
4.1.
Coarse aggregate Seal
12.5- 20.0 1.00-1.80
4.6.2.2 Aggregates coat (DBST)
Slurry aggregate Seal
1 Cover aggregates shall consist of screenings of 10.0-15.0 0.90-1.80
coat
crushed stone or crushed gravel. Aggregate for slurry
Generally 5-6 kg./sq.m.
seals shall consist of crushed stone or gravel fines or Slurry seal (SBSC)
for the mix
natural sand blended with not less than 50% crushed fines.
For heavy duty applications slurry aggregate shall consist Table 4.6.5-1: Application Rates
of 100% crushed fines. 2 The Engineer may order additional trial sections and
2 The properties of cover and slurry seal aggregates alter the previously established rates of application during
and their gradations shall be in accordance with the progress of the work.
relevant requirements of Sub-section 4.1.
4.6.6 Construction Requirements
4.6.3 Equipment
4.6.6.1 General
1 All plant and equipment used for pugmill mixing of
slurry mixes, heating and spraying of cutback and 1 Applications of bitumen and aggregate and
emulsified bitumen, spreading, rolling and brooming of subsequent rolling shall be completed between sunrise
cover aggregate, and applying and spreading slurry seals, and sunset and under favorable weather conditions as
shall conform with the requirements of the relevant determined by the Engineer. The atmospheric
sections of this Specification and with the Contractor's temperature shall be above 15 degrees C and the weather
approved equipment list. shall not be foggy, rainy, dusty or unduly windy.
2 Generally, where the seal coat is to carry traffic prior
to final sweeping, speed signs shall be erected to control

♦ 4-25 ♦
copy 249
the speed of traffic. Provision for traffic control shall be in 3 The slurry seal coat shall be uniform and
accordance with the requirements of Section 1, Sub- homogeneous after spreading and shall not show signs of
section 1.8. separation of the emulsion and aggregate after setting.
3 When bituminous coatings are applied to sections of
4.6.6.5 Spraying of Bitumen
highway which are to be promptly opened to traffic, and
the ambient temperature is contributing to slow curing 1 The bitumen cutback or emulsified bitumen for fog
and excessive pickup, the Contractor shall suspend and seal coats shall be applied by means of a pressure
operations until the Engineer approves continuation of distributor uniformly and continuously over the section to
sealing work. be treated. The rate of application shall be as designated
4 The surface to be treated shall be dry or slightly by the Engineer.
damp and the moisture content of aggregates at the time 2 A strip of building paper or heavy polyethylene
of application to the coated surface shall not exceed 3% by sheeting, at least one m in width, and with a length equal
weight. to that of the spray bar of the distributor plus 300 mm,
5 Unless otherwise directed, the minimum time shall be used at the beginning of each application. If the
interval between successive seal coats, in DBSD cut-off is not positive, the paper shall be used at the end of
applications, shall be 5 days. each spread. The paper shall be removed and disposed of
after use. The distributor shall be moving forward at
4.6.6.2 Surface Preparation proper application speed at the time the spray bar is
opened. Any skipped areas or deficiencies shall be
1 Granular surfaces shall be primed in accordance with
corrected immediately as directed.
the requirements of Sub-section 4.2 prior to application of
the surface treatment. If there are delays in scheduling the 3 The length of spray run shall not exceed that which
seal coating, which results in deterioration of the surface, can be covered by the aggregate spreading equipment.
the Engineer may order appropriate repairs or corrective 4 The application width of bitumen shall be not more
treatment prior to seal coating. than 150 mm wider than the width covered by the
2 When coatings are applied to existing pavement aggregate spreader. Under no circumstances shall
surfaces, all pavement repairs shown on the Drawings operations proceed in such a manner that the bitumen will
shall first be completed. Where applicable, the positions be allowed to chill, set up, dry, or otherwise impair
of traffic markings shall be surveyed and recorded to retention of the cover aggregate.
enable their accurate replacement after the seal coatings 5 The Contractor shall keep a complete record of
have been applied. bitumen used, based on distributor tank measurements
3 Immediately before applying any bituminous and on areas to which the bitumen has been applied.
material, all dirt, dust and other objectionable material These records shall be submitted to the Engineer as
shall be removed from the surface and cracks shall be verification of the accuracy of the tachometer as well as
repaired or sealed as directed. If required, the surface verification of application rates designated by the
shall be slightly dampened with a light application of Engineer.
water immediately prior to application of bitumen. 6 Distribution of bitumen shall be so regulated and
4 Surfaces to be slurry sealed shall be lightly sprayed, sufficient material left in the distributor at the end of each
immediately prior to spreading the slurry, with a slow- application, that there will be a uniform distribution across
setting 3:1 water/emulsion mixture applied at the rate of the spray bar. In no case shall the distributor be allowed
0.4-0.8 kg./sq.m. to expel air with the bitumen, thereby causing uneven
coverage.
4.6.6.3 Heating of Bitumen 7 The angle of the spray nozzles and the height of the
1 The temperature of cutback bitumen and of spray bar shall be adjusted and regularly checked to
emulsified bitumen at the time of application shall be as ensure uniform distribution. The height of the spray bar
specified in Sub-section 4.1. above the pavement surface should remain constant
throughout the spraying process. Distribution shall cease
4.6.6.4 Spreading Slurry Seal immediately upon any clogging or partial blocking of any
nozzle and corrective measures shall be taken before
1 Spreading of slurry seal shall be by means of an
application is resumed.
approved type spreader box which shall be capable of
spreading at least one traffic lane width. It shall have 4.6.6.6 Application of Aggregate
flexible rubber or similar strips fastened on each side to
prevent loss of slurry and shall have baffles incorporated 1 If directed, aggregates shall be washed prior to use in
in the box to ensure uniform application. A rear, flexible, order to eliminate or reduce any dust coating or salts
adjustable strike-off blade shall be fitted to the box. before delivery to the spreader.

2 Areas inaccessible to the slurry spreader box shall be 2 Operation of the aggregate spreader at speeds which
slurry sealed using hand or other approved methods. cause the particles to roll over after striking the bitumen
covered surface will not be permitted.

♦ 4-26 ♦
copy 249
3 Immediately upon application of bitumen, aggregate dislodged. This brooming shall result in uniform
of the required gradation shall be spread at the rate distribution of loose screenings over the surface which
designated by the Engineer. Spreading shall be shall then be re-rolled using pneumatic-tired rollers until
accomplished in such a manner that the tires of the at least 2 complete coverages have been achieved.
hauling units or aggregate spreader do not come in 8 Light drag brooming and re-rolling shall be repeated
contact with the uncovered bitumen surface. 24 hours after the initial brooming, if so directed.
4 Where adjacent spreads are to be made, the first 9 Excess screenings shall be salvaged and stockpiled
aggregate spread shall not extend closer than 150 mm to or disposed of as directed.
the edge of bitumen application. The adjacent spread of
bitumen shall overlap this 150 mm and complete 4.6.6.8 Maintenance and Protection of Sealed Surfaces
aggregate coverage shall be achieved on the second
1 BSSC shall be protected from traffic until such time
spread promptly upon completion of the first spread to
as the coatings have cured sufficiently and will not be
ensure a smooth riding surface.
damaged by, adhere to or be picked up by, the tires of
5 Immediately after aggregate has been spread, vehicles.
deficient areas shall be covered by additional aggregate.
2 Each coat of SBSD and DBSD shall be maintained
Humps, ridges or uneven distributions of aggregate shall
and protected from traffic for at least 3 days after
be removed and corrected to ensure that there are no
completion of rolling.
permanent ridges, bumps, or depressions in the
completed surface. Additional aggregate shall be spread 3 At the end of the 3-day maintenance period for each
in whatever quantities necessary to prevent pick-up by seal coat, or earlier if directed, the surface shall be finally
rollers or traffic, after which the surface shall be rolled as swept, using a rotary broom, to remove loose screenings.
directed. Surplus screenings shall be stockpiled or disposed of as
6 Care shall be taken to prevent aggregate from directed.
entering ditches or inlets of any type. The Contractor shall
be responsible for removing any such aggregate materials 4.6.7 Tolerances and Records
or other accumulated debris arising out of his operations.
1 The Contractor shall be responsible for ensuring the
4.6.6.7 Rolling and Brooming accurate calibration of pressure distributors and for the
correct rates of application of bitumen as designated by
1 Aggregate shall not be spread more than 150 m the Engineer.
ahead of initial rolling operations. 2 Readings shall be taken of bitumen tanker contents
2 Rollers shall not stop, start or turn on the surface and temperature immediately prior to, and immediately
being rolled. Any damage to the surface arising out of upon completion of each spraying run and the actual
non-compliance with these requirements shall be made application rate in kg./sq.m. shall be calculated. Complete
good as directed, at the Contractor's expense. records shall be maintained of all such measurements and
3 Initial breakdown rolling shall proceed behind the the specific locations, width and lengths of the respective
spreader (after any adjustments by hand methods to runs.
correct for uneven distribution, etc). One complete 3 The tolerances on temperature-adjusted application
coverage shall be achieved using 2-axle self-propelled rates of cutback bitumen shall be plus or minus 5% of the
steel-wheeled rollers of 6-8 tons weight and operating at a designated rate.
maximum speed of 5 km/h. Initial rolling shall be 4 Applications of cutback bitumen varying by more
completed within 30 minutes of spreading aggregate. than 5% but less than 10%, after temperature adjustment,
4 The Engineer may order the alternative use of below the specified rate of application shall, if accepted,
pneumatic-tired rollers for initial rolling if adequate be subject to a 10% reduction in quantity or area
embedment of the aggregate is liable to result in measurements as appropriate.
excessive crushing when steel-wheeled rollers are used. 5 Applications of cutback bitumen varying by more
5 Immediately following completion of the initial than 10%, after temperature adjustment, above or below
rolling, the surface shall be rolled using self-propelled the specified rate of application shall be rejected and the
pneumatic-tired rollers operated at a maximum speed of 8 unsatisfactory material replaced or made good as directed,
km/h, until at least 3 complete coverages have been at the Contractor's expense.
achieved. 6 The Contractor shall maintain, on a daily basis,
6 If necessary during rolling operations, additional complete records of the volumes and tonnage of each
screenings shall be lightly spread by hand methods and type of aggregate delivered to the Site and used in each
re-rolled, to make good any small areas visibly deficient in section of the Works for seal coat applications.
cover material. 7 All records and calculations of bitumen applications,
7 Light drag brooming of the surface shall be carried and aggregate delivery and use, shall be submitted to the
out 24 hours after completion of rolling and in such a Engineer at the end of each day when seal coat
manner that embedded aggregate particles will not be applications have been carried out. No measurements will

♦ 4-27 ♦
copy 249
be made of bitumen applications which are not supported 4.7.4 Equipment
by adequate, verifiable records.
1 Plant and equipment for mixing, hauling, placing and
compacting bituminous leveling course materials shall
4.6.8 Method of Measurement
conform to the relevant requirements of Sub-section 4.3.
1 Single bituminous surface treatment, double
bituminous surface treatment and bituminous slurry seal 4.7.5 Construction of Trial Sections
coat shall each be measured in square meters of net area
1 Trial sections shall be constructed as and where
covered as shown on the Drawings or directed by the
directed and in accordance with the relevant requirements
Engineer. Rates are deemed to include for all related work,
of Sub-section 4.3.
including, without limitation, trial sections, tests and
reports and wastage of materials.
4.7.6 Mixing Procedures
4.6.9 Basis of Payment 1 Handling and mixing of bitumen (including modifier
and anti-stripping agent, if any) and aggregates (including
1 The amount of completed and accepted work,
mineral filler if required) shall be in accordance with the
measured as provided for above, will be paid for at the
relevant requirements of Sub-section 4.3.
unit rates for the various items in the Bill of Quantities ,
which rate shall be full compensation for supplying
materials, transporting and placing, labor, equipment,
4.7.7 Surface Preparation
tools and other items necessary for the proper completion 1 Damaged pavement surfaces shall, where directed,
of the work. be repaired by patching prior to receiving the bituminous
leveling course. The extent of patching shall be as shown
4.6.10 Items in the Bill of Quantities on the Drawings or as directed.
2 Areas of existing pavement to be patched shall be cut
i. Single bituminous surface treatment.
out to neat lines to a depth ordered by the Engineer,
ii. Double bituminous surface treatment.
thoroughly cleaned, and the exposed edges of pavement
iii. Bituminous slurry seal coat. painted or sprayed with a thin coat of rapid curing cutback
bitumen grade RC-70 or RC-250 in accordance with the
4.7 Bituminous Leveling Course and relevant requirements of Sub-section 4.2. The cut out
Patching Work pavement shall be patched with bituminous material as
shown on the Drawings or as directed and conforming
4.7.1 Description with the relevant requirements of Sub-section 4.1.
3 Patching shall be carried out in accordance with the
1 This Sub-section describes requirements for
relevant requirements of Sub-section 4.3.
furnishing materials, mixing at a central mixing plant, and
spreading and compacting bituminous leveling course on 4 Patching shall be carried out in layers not exceeding
an existing pavement surface, as shown on the Drawings 80 mm in thickness. Each layer shall be thoroughly
or directed. compacted by means of approved pneumatic tampers
prior to placing the succeeding layer. Each layer shall be
2 Patching works shall be limited to localized deficient
protected from damage and all dirt or foreign material
areas as jointly determined by the Engineer and the
shall be removed before placing subsequent layers. The
Contractor. These areas are usually not exceeding 3m in
final layer shall be rolled with a heavy roller. Each layer
length and one lane width and the distance between two
shall be approved prior to placement of subsequent layers.
individual patches is normally not less than 5m.
5 All cut-out pavement material and surplus patching
4.7.2 Materials material shall be removed from the site and disposed of
by the Contractor prior to placing the leveling courses.
1 All materials shall conform to the requirements of
6 In areas where leveling courses are required, as
Sub-section 4.1.
shown on the Drawings or directed, the Contractor shall
take cross sections of the existing pavement after
4.7.3 Job Mix and Project Mix completing any patching. The cross sections shall be
1 The job mix formula shall be established by the taken at intervals of 12.5 meters or as directed. When the
Contractor in accordance with the procedures and survey is approved, the Engineer will determine and
requirements of Sub-section 4.3. inform the Contractor of the locations, grades and
thicknesses of leveling courses to obtain the desired
2 The job mix for bituminous leveling shall conform to
surface.
the requirements for binder course as provided in Sub-
section 4.5. 7 Prior to placing the leveling courses, the existing
pavement surface shall be prepared in accordance with
the relevant requirements of Sub-section 4.3, including the
use of prime and tack coats as appropriate.

♦ 4-28 ♦
copy 249
4.7.8 Delivery, Spreading and Finishing tools and other items necessary for the proper completion
of the work.
1 Delivery, spreading and finishing of leveling courses,
including compaction, shall conform to the relevant 4.7.14 Items in the Bill of Quantities
requirements of Sub-section 4.5.
i. Bituminous Leveling Course.
2 In areas where a specific grade and super-elevation
ii. Bituminous Patching Work.
are to be achieved by the leveling courses, setting out and
level control shall be based on a reference line installed in
accordance with the relevant requirements of Sub-section 4.8 Bituminous Cold Mix Courses
4.3. In areas of minor leveling such as filling of pits or
small isolated areas, a mobile reference line or alternative 4.8.1 Description
control system may be approved.
1 This Sub-section describes requirements for
furnishing materials, mixing manually or at a central
4.7.9 Sampling and Testing
mixing plant, or in a travel-mix plant and spreading and
1 Sampling and testing of leveling courses shall compacting bituminous cold mix courses comprising
conform to the relevant requirements of Sub-section 4.3 - unheated mineral aggregate or cut-back asphalt on a
and Table 4.3.9.1. prepared surface, as shown on the Drawings or directed
2 Where sampling and testing are not feasible due to by the Engineer.
thickness or other constraints, the Engineer will determine
specification compliance based on an approved rolling 4.8.2 Materials
pattern or other basis. 1 All materials shall conform to the relevant
requirements of Sub-section 4.1.
4.7.10 Surface Tolerances
2 The type and grade of bitumen for the paving
1 Surface tolerances for leveling courses shall conform mixture shall be as shown on the Drawings or as directed.
to the relevant requirements for binder courses in Sub- The bitumen shall conform to the relevant requirements of
section 4.5. AASHTO M 81,M 82, M 140 or M 208.

4.7.11 Determination of Thickness 4.8.3 Job Mix and Project Mix


1 The Engineer may use thickness measurements, 1 The job mix formula shall be established by the
spread rates, cross section or other methods to verify Contractor in accordance with the procedures and
quantities placed. Thickness measurements shall be in requirements of Sub-section 4.3.
accordance with the relevant requirements of Sub-section 2 The job mix shall conform to the relevant
4.3. requirements of Sub-section 4.4 or Sub-section 4.5, as
appropriate.
4.7.12 Method of Measurement
1 Bituminous leveling courses shall be measured by 4.8.4 Equipment
the cu.m. of mix furnished, spread, compacted, completed 1 Plant and equipment for mixing, hauling, placing and
and accepted. Measurements shall be based on the areas compacting bituminous cold mix courses shall conform to
and thicknesses shown on the Drawings or as directed. the relevant requirements of Sub-section 4.3. In the
2 Bituminous patching work shall be measured by the continuous mixing plant, the devices feeding bituminous
cu.m. of mix furnished, spread, compacted, completed material, aggregate and water shall be interlocked to
and accepted. Measurements shall be based on the areas maintain automatically the correct proportions. In a travel
and thicknesses shown on the Drawings or as directed. No mix plant, the equipment used may be either a hopper
measurements will be made of unauthorized areas or type, or a rotary type mixer. Both types of equipment
extra thickness. shall be capable of thoroughly mixing the bituminous
3 The rates for bituminous leveling course and for material and aggregate, uniformly dispersing the
patching work shall be deemed to include for all incidental bituminous material, and adequately coating the
costs as stated in Sub-section 4.3, Clause 4.3.12. aggregate particles to produce a uniform mix.

4.7.13 Basis of Payment 4.8.5 Construction of Trial Sections

1 The amount of completed and accepted work, 1 Trial Sections shall be constructed as and where
measured as provided for above, will be paid for at the directed and in accordance with the relevant requirements
unit rates for the various items in the Bill of Quantities , of Sub-section 4.3.
which rate shall be full compensation for supplying
materials, transporting and placing, for labor, equipment,

♦ 4-29 ♦
copy 249
4.8.6 Mixing Procedures 4.8.12 Method of Measurement
1 Handling and mixing of bitumen and aggregate shall 1 Bituminous cold mix courses shall be measured by
be in accordance with the relevant requirements of Sub- the cubic meter of mix furnished, spread, compacted,
section 4.3, with the following exceptions: completed and accepted. Measurements shall be based
on the areas and thicknesses as shown on the Drawings.
i. Aggregates shall not be heated but shall be fed 2 Deficiencies in thickness of bituminous cold mix
cold to the plant. The temperature of the wearing course shall, unless an overlay is constructed at
bitumen upon entering the pugmill shall be the Contractor's expense, result in a proportion only of the
adequate to ensure uniform application to the wearing course volume being measured for payment.
cold aggregate. The bitumen temperature shall Proportions shall be determined in accordance with the
be designated by the Engineer and shall thickness deficiencies and volume proportions stated Sub-
generally be in accordance with the relevant section 4.3, Table 4.3.11.1.
requirements of Sub-section 4.1.
ii. Mixing time shall be the shortest time necessary 4.8.13 Basis of Payment
to remove excess volatiles or water and to
1 The amount of completed and accepted work,
produce a satisfactory mixture.
measured as provided for above, will be paid for at the
unit rates for the various items in the Bill of Quantities ,
4.8.7 Surface Preparation
which rate shall be full compensation for supplying
1 Preparation of the surface upon which bituminous materials, transporting and placing, labor, equipment,
cold mix courses are to be laid, and the use of prime and tools and other items necessary for the proper completion
tack coats shall be appropriate to the type and condition of of the work.
such surfaces and shall conform to the relevant
requirements of Sub-section 4.3. 4.8.14 Items in the Bill of Quantities
i. Bituminous cold mix course.
4.8.8 Delivery, Spreading and Finishing
1 Delivery, spreading and finishing of bituminous cold 4.9 Pavement Repairs and
mix courses shall conform to the relevant requirements of
Reinstatement
Sub-section 4.3.
2 Requirements for rolling and compaction shall 4.9.1 Description
comply with the relevant requirements of Sub-section 4.4 -
or Sub-section 4.5, as appropriate. 1 This Sub-section describes requirements for surface
milling, removing defective bituminous pavement,
4.8.9 Sampling and Testing preparing surfaces to receive repairs, furnishing materials,
placing and finishing new pavement, as shown on the
1 Sampling and testing shall conform to the relevant Drawings or directed.
requirements of Sub-section 4.3 and Table 4.3.9.1.
4.9.2 Materials
4.8.10 Surface Tolerances
1 Subgrade materials shall conform to the relevant
1 Surface Tolerances shall conform to the relevant requirements of Sub-section 2.6.
requirements of Sub-section 4.4.
2 Aggregate sub-base and base course materials shall
2 Finished elevations and straight edge tolerances shall conform to the relevant requirements of Sub-section 3.1.
conform to the relevant requirements of Sub-section 4.4 -
3 Bituminous pavement materials shall conform to the
or Sub-section 4.5, as appropriate.
relevant requirements of Sub-section 4.1.

4.8.11 Determination of Thickness


4.9.3 Equipment
1 Procedures for determining the average compacted
1 All plant and equipment shall conform to the
thickness of bituminous cold mix courses shall conform to
requirements of the relevant Sections of this Specification.
the relevant requirements of Sub-section 4.3.
2 Cores for thickness measurements of bituminous 4.9.4 Preparation of Pavement
cold mix courses shall be used to determine if changes are
necessary in the thickness of succeeding layers in 1 Cracks in bituminous pavement which, in the opinion
accordance with the relevant requirements of Sub-section of the Engineer, do not require reconstruction shall be
4.4 or Sub-section 4.5, as appropriate. prepared by wire brushing and blowing out with
compressed air.
2 Prior to the application of bituminous overlays, the
existing pavement shall be planed or milled out by

♦ 4-30 ♦
copy 249
approved equipment to the depth shown on the Drawings be compacted by steel wheeled roller, first compacting the
to remove the asphalt surface that contains hardened 150 mm strips adjacent to the traffic edges, then rolling in
asphalt, contaminated material, fuel spots, rubber the direction of traffic.
deposits, laitance and any undesirable material that 6 New utility trenches shall be backfilled to the details
prevents proper bonding and adhesion with the new shown on the Drawings, or ordered, including any
asphalt overlay. surrounds, haunching or protective materials.
3 Defective bituminous pavement which, in the opinion Construction of subgrade and pavement shall be as for
of the Engineer, requires reconstruction shall be cut back pavement repairs.
to good material using pneumatic cutting tools. The cut 7 No excavated areas shall remain open overnight
area shall be square or rectangular and in line with the without adequate safety and protection measures subject
direction of traffic. The depth of cut shall be determined to the approval of authorities.
by the Engineer and may include bituminous layers, base
and sub-base layers and subgrade layers (in the case of 4.9.6 Sampling and Testing
failed pavement, excavation shall include a minimum of
300 mm of subgrade material). All excavated materials 1 Testing of repair materials shall conform to the
shall be removed and disposed of off-site. When the relevant requirements of Sub-section 3.3 and Table 4.3.9.1.
bottom of the excavation consists of earth or granular Sampling shall be as ordered by the Engineer.
material it shall be thoroughly compacted using
mechanical compactors to the satisfaction of the Engineer. 4.9.7 Surface Tolerances
Exposed bituminous surfaces shall be thoroughly cleaned
1 Levels shall be checked by straight edge in relation to
and wire brushed prior to receiving repair materials.
the adjacent existing pavement.
4 Utility trench reinstatements in bituminous pavement
2 Surface tolerances for bituminous layers shall
shall be prepared in the same way as defective bituminous
conform to the relevant requirements of Sub-section 4.4
pavement. Excavation depth shall be a minimum of 300
and Sub-section 4.5 as appropriate.
mm from the top of subgrade layer.
3 Any deficiency in the wearing course surface shall be
4.9.5 Placing and Finishing Repair corrected by cutting out and replacing.
Materials
4.9.8 Method of Measurement
1 Cracks of 3 mm to 7mm width or wider shall be filled
with clean, coarse sand then saturated with 1:1 diluted 1 Sealing of cracks shall be measured by lin.m. of
emulsified bitumen, or as directed by the Engineer. Cracks cracks sealed and approved by the Engineer.
of less than 3 mm shall be filled with emulsified bitumen, 2 Milling shall be measured by the sq.m. of the area
or as directed. Cracks shall be filled to the road surface. milled to the specified depth, including equipment,
Any excess bitumen shall be removed with a squeegee application, removal and disposal of the milled material
and the bitumen surface shall be sprinkled liberally with off the site.
coarse sand. 3 Pavement repairs shall be measured by the sq.m. of
2 Excavations below subgrade level shall be filled to a repair, prepared, filled, compacted, completed and
level specified by the Engineer with subgrade material in accepted. Measurement shall be of the areas shown on
layers not exceeding 150 mm and compacted using the Drawings or ordered.
mechanical compactors to conform to the requirements of 4 Trench reinstatements shall be measured by the
Sub-section 2.6 and to the satisfaction of the Engineer. sq.m. of reinstatement prepared, filled, compacted,
3 Subbase and/or base course, if required, shall be completed and accepted. Measurement shall be of the
placed in layers not exceeding 150 mm and compacted areas shown on the Drawings or ordered. New utility
using mechanical compactors. They shall conform with trench construction will not be measured under this item.
the relevant requirements of Sub-section 3.2 or Sub- 5 No separate measurement will be made for
section 3.3, - as appropriate, and shall be to the grading excavation, prime or tack coats, pavement materials,
shown on the Drawings or specified by the Engineer. subgrade, subbase, or base courses.
4 Prior to receiving bituminous material, the 6 All other incidental items shall not be measured for
excavations shall be thoroughly cleaned. Subgrade, sub- direct payment, as prescribed in Sub-section 4.3 - but
base or base course material shall be primed with a light shall be considered as subsidiary work, the costs of which
coating of MC cutback bitumen and existing bituminous will be deemed to be included in the rates and prices
surfaces shall be lightly painted with emulsified bitumen, stated in the Bill of Quantities.
all in accordance with the requirements of Sub-section 4.2
5 The excavation shall be filled with bituminous 4.9.9 Basis of Payment
pavement materials placed in layers not exceeding 70 mm
1 The amount of completed and accepted work,
and compacted using vibratory compactors. Unless
measured as provided for above, will be paid for at the
ordered to the contrary by the Engineer, the top layer shall
unit rates for the various items in the Bill of Quantities ,

♦ 4-31 ♦
copy 249
which rate shall be full compensation for supplying 5 Quality control tests for density, thickness and mix
materials, transporting and placing, labor, equipment, properties shall be performed as instructed by the
tools and other items necessary for the proper completion Engineer.
of the work. 6 Any work needed to road shoulders, earthworks, side
slopes, road drainage and services shall be carried out as
4.9.10 Items in the Bill of Quantities shown on the Drawings and in accordance with the
i. Surface milling. relevant clauses of Sections 2, 8 and 18.

ii. Crack sealing. 4.10.3.2 Traffic Control


iii. Pavement repairs (overlay and surface
preparation). 1 Traffic control arrangements shall be implemented in
accordance with Section 1, Sub-section 1.8.
iv. Pavement repairs (complete reconstruction).
v. Trench reinstatement. 2 Widening shall be carried out only on one side of the
pavement at a time. The work shall be programmed to
permit continuity of excavation, placing widening material,
4.10 Bituminous Pavement Widening
rolling and finishing with minimum time of disruption to
traffic flow.
4.10.1 Description
3 Reflector barricades shall be placed along open
1 This Sub-section describes requirements for trenches. Lighting shall be placed at each barricade at
widening existing pavements, including excavation night Adequate provision shall be made to enable traffic to
adjacent to existing bituminous pavements and placing a cross at intersecting roads and at commercial, industrial
mixture of aggregates and bituminous binder in and private entrances.
compacted layers.
4.10.4 Method of Measurement
4.10.2 Materials
1 The approved work shall be measured in square
1 Materials for the construction of pavement widening meters of new asphalt surface. Excavation and removal of
shall conform to the requirements of Sub-sections 4.1, 4.2 curb and road drainage elements will not be measured
and 4.3 as appropriate. separately but will be considered subsidiary work, the cost
of which is deemed to be included in the rates for
4.10.3 Construction Requirements pavement widening.

4.10.3.1 Construction 2 Relocation of services will be measured separately


under the relevant items of Sub-section 18.2.
1 The edge of the existing road pavement shall be
excavated to the extent and depth shown on the Drawings, 4.10.5 Basis of Payment
Existing curbs, gullies and drain pipes shall be removed as
shown on the Drawings or instructed by the Engineer. The 1 The amount of completed and accepted work,
bottom of the excavation shall be compacted with suitable measured as provided for above, will be paid for at the
rollers or power rammers to the density specified in Sub- unit rate for Pavement Widening in the Bill of Quantities,
sections 2.5 and 2.6. Adequate provisions shall be made which rate shall be full compensation for excavation,
for drainage of the trench to prevent damage to the trimming, compacting of the excavation, shoulders and
existing road subgrade. side slopes, mixing, placing and compacting bituminous
material and for supplying materials, labor, equipment,
2 The excavation shall be cleaned of loose material and
tools and other items necessary for the proper completion
the edge of the existing pavement shall be cleaned. The
of the work.
excavated base shall be approved by the Engineer prior to
placement of bituminous material. If unsuitable or
4.10.6 Items in the Bill of Quantities
unstable soil is exposed on the excavation bottom it shall
be replaced with suitable material and compacted to the i. Pavement widening.
depth instructed.
3 Prior to placing bituminous material, the edge of the 4.11 Recycled Bituminous Mixes
existing asphalt road layers shall be painted or sprayed
with a thin coat of cut-back bitumen RC-70 or bitumen 4.11.1 Description
emulsion SS-1.
1 This Sub-section describes requirements for
4 Bituminous material shall be placed in the prepared
recycling existing pavement material, including removal,
excavation in layers not exceeding 80mm thick. Machine
crushing and stockpiling existing bituminous pavement,
laying shall be used except for confined areas where the
mixing with new aggregate, bitumen (and, if specified, an
use of a machine would be impracticable. Completion
approved modifying agent) at a central hot mixing plant,
shall be by roller as specified in Sub-sections 4.3, 4.4 or
and spreading and compacting recycled bituminous base
4.5.

♦ 4-32 ♦
copy 249
course on a prepared surface, as shown on the Drawings required) shall be in accordance with the relevant
or directed. requirements of Sub-section 4.3.
2 Crushing of existing pavement materials for recycling
4.11.2 Materials may be accomplished by portable or stationary crushers
1 Recycled material shall consist of existing or may be the direct result of the pavement removal
bituminous pavement, processed such that 100% will pass method such as cold milling.
a 38 mm (1.5 inch) sieve. 3 Crushed pavement material shall be separated into a
2 If the Engineer determines that recycled bituminous minimum of two sizes prior to heating and mixing. The
material is causing degradation of the aggregate, he shall fine size shall have a minimum of 80% passing a 4.75mm
revise the job-mix as required. (No.4) sieve. The coarse size shall have a minimum of
60% retained on a 4.75mm (No.4) sieve.
3 New materials shall conform to the relevant
requirements of Sub-section 4.1. 4 Heated and dried new aggregate shall be combined
in the appropriate proportions and gradations with the
4 Unless shown otherwise on the Drawings, bitumen
recycled bituminous material and mixed at such
for recycled bituminous base course shall be graded to
temperature and for such time necessary to achieve a
suit the project climatic condition and type of work. If not
thorough coating of the new aggregate. New bitumen
specified, or shown on the Drawings, grade 60-70
and/or modifier shall then be incorporated into the
penetration conforming to the requirements of AASHTO M
mixture and mixed to produce a homogenous mixture
20 shall be used.
with satisfactory coating of all aggregate.
5 Modifying agent used to soften the old bitumen shall
be used in accordance with the manufacturer’s 5 If both bitumen and modifier are used they shall be
instructions and approved by the Engineer. introduced into the mixing area through separate
metering devices.
6 Existing pavement shall be removed in such a
manner as to prevent unnecessary intermixing with the 6 Preheating of the crushed recycled bituminous
underlying base, sub-base or subgrade material. material immediately before introduction to the mixer may
be permitted subject to the approval of the Engineer.
7 The stockpile height shall not be greater than 3
Preheating methods shall not result in loss of bitumen
meters. Construction equipment will not be permitted on
from the recycled material.
the stockpiles.

4.11.7 Surface Preparation


4.11.3 Job Mix and Project Mix
1 Preparation of the surface upon which the recycled
1 The job mix formula shall be established by the
bituminous base course is to be laid shall be appropriate
Contractor in accordance with the procedures and
to the type and condition of such surface and shall
requirements of Sub-section 4.3..
conform to the relevant requirements of Sub-section 4.3.
2 The properties of the new modified mix shall meet all
the requirements of Sub-sections 4.1, 4.3 and 4.4, as 4.11.8 Delivery, Spreading and Finishing
appropriate.
1 The delivery, spreading and finishing of recycled
4.11.4 Equipment bituminous base course shall conform to the relevant
requirements of Sub-section 4.4
1 Plant and equipment for recycled bituminous base
course shall conform to the relevant requirements of Sub- 4.11.9 Sampling and Testing
section 4.4, subject to any modifications by the Engineer.
1 Sampling and testing of recycled bituminous base
2 Plant and equipment for mixing, hauling, placing and
course shall conform to the relevant requirements of
compacting recycled bituminous base course materials
Section 4.3, and Table 4.3.9.1.
shall conform to the relevant requirements of Sub-section
4.3.
4.11.10 Surface Tolerances
4.11.5 Construction of Trial Sections 1 Surface tolerances shall conform to the relevant
requirements of Sub-section 4.4.
1 Trial sections shall be constructed as and where
directed and in accordance with the relevant requirements
4.11.11 Determination of Thickness
of Sub-section 4.3.
1 Procedures for determining the average compacted
4.11.6 Mixing Procedures thickness of recycled bituminous base course shall be in
accordance with the requirements of Sub-section 4.4.
1 Handling and mixing of bitumen (including modifier
and anti-stripping agent, if any) and aggregate (including
recycled material, new aggregate and mineral filler if

♦ 4-33 ♦
copy 249
4.11.12 Method of Measurement v. AASHTO Designation PP 52-02: Standard
Practice for Operating Inertial Profilers and
1 Recycled bituminous base course shall be measured
Evaluating Pavement Profiles.
by the cubic meter of mix furnished, spread, compacted,
vi. AASHTO Designation PP 53-02: Standard
completed and accepted. Measurement shall be based on
Practice for a Pavement Ride Quality
the areas and thickness shown on the Drawings or as
Specification when Measured Using Inertial
directed.
Profiling System.
2 Removal and crushing of existing pavement
materials for incorporation in recycled bituminous base 4.12.3 Terminology
course shall not be measured for direct payment, but shall
be considered as subsidiary work, the costs of which will 1 The current rideability specifications are based on
be deemed to be included in the rates for recycled International Roughness Index (IRI). As an internationally
bituminous base course stated in the Bill of Quantities. accepted scale for ride quality, IRI is a standardized
3 Bituminous prime and tack coats shall be measured measure of the response of a standard vehicle to
as prescribed in Sub-section 4.2 "Bituminous Prime and pavement profile. IRI is an index computed from a single
Tack Coats". longitudinal profile using a quarter-car model at a
simulated travel speed of (80 km/h). Lane IRI is the
4 All other incidental items shall not be measured for
average of the left and right wheel path IRI values.
direct payment, but shall be considered as subsidiary work,
the costs of which will be deemed to be included in the
4.12.4 Testing Equipment
rates and prices stated in the Bill of Quantities.
1 The rideability testing shall be conducted using a
4.11.13 Basis of Payment high-speed profiler (HSP). The HSP should conform to the
requirements of Class I equipment as defined in ASTM E
1 The amount of completed and accepted work, 950 and to the requirements specified in AASHTO
measured as provided for above, will be paid for at the Designation PP 50-02 and PP 51-02.
unit rates for the various items in the Bill of Quantities ,
2 Prior to testing, calibration and verification
which rate shall be full compensation for supplying
procedures should be in accordance with the
materials, transporting and placing, for labor, equipment,
recommendations provided by the profiler manufacturer.
tools and other items necessary for the proper completion
The equipment should be operated in accordance with the
of the work.
recommendations provided by the manufacturer and
AASHTO PP 52-02.
4.11.14 Items in the Bill of Quantities
i. Recycled bituminous base course 4.12.5 Testing Procedure
1 Continuous and rigorous scrutiny of profiler output is
4.12 Surface Rideability Measurement required. A constant testing speed shall be maintained
through the lead-in distance (100 m minimum) and the
4.12.1 Description test section. Two driving speeds of 65 to 95 km/h are
required.
1 This Sub-section summarizes testing procedures and
road surface rideability specifications for asphalt and 2 The profiles measured for each run should be used to
concrete surfaced pavements. The specifications are compute the IRI value for each wheel path of each 150m
based on the International Roughness Index (IRI) values subsection within the test section. After three runs, the
(average value from three runs and in units of m/km) test data (IRI values) should be reviewed by calculating the
measured using a high-speed profiler tugged by a utility average, standard deviation, and coefficient of variance
vehicle. A minimum lead-in distance of 100 m and a (COV) for each subsection wheel path. If a value of
segment length of 150 m are suggested. standard deviation is greater than 0.016m/km or COV is
greater than 5%, then the test shall be repeated. Additional
4.12.2 Reference Documents for Profiler testing should be done until standard deviation is less
Rideability Testing than 0.016m/km or COV is less than 5% (with obvious
outliers excluded).
i. ASTM E 867 Terminology Relating to Vehicle-
3 After five runs, if a value of standard deviation is
Pavement Systems.
larger than 0.016 m/km or COV is greater than 5%,
ii. ASTM E 950 Test Method for Measuring compare the profiles from the five runs and attempt to
Pavement Roughness Using a Profiler. identify possible equipment or operational problems.
iii. AASHTO Designation PP 50-02: Standard Recalibrate if necessary. Record all data.
Equipment Specification for an Inertial Profiler.
iv. AASHTO Designation PP 51-02: Standard
Practice for Certification of Inertial Profiling
System.

♦ 4-34 ♦
copy 249
4.12.6 Submittals 4.12.9 Basis of Payment
1 Data for each test shall be stored on media such as 1 The amount of completed and accepted work,
CDs. measured as provided for above, will be paid for at the
2 Hard copy reports shall be provided for each test unit rates for the various items in the Bill of Quantities ,
section. The following information be reported and stored: which rate shall be full compensation for labor, equipment,
tools, materials, transportation and other items necessary
i. Date and time of day.
for the proper completion of the work.
ii. Operator(s) and equipment used.
iii. Weather conditions: temperature, cloud cover,
4.12.10 Items in the Bill of Quantities
and wind.
iv. Surface description: type of pavement and i. International Roughness Index (IRI)
condition. for asphalt pavement (length)
v. Location and description of section: Job ID, ii. International Roughness Index (IRI)
lane, beginning and ending stationing (or other for concrete pavement (length)
location information), and direction.
vi. Total section length.
vii. Data filter settings: High-pass filter setting =
100m.
viii. IRI value of each wheel path and the average of
the two wheel paths for each 150 m subsection.
ix. Raw data.

4.12.7 Required Rideability


1 The IRI value representing the rideability of each
road subsection shall not exceed 1.2 m/km.
2 The schedule provided in Table 4.12.7.1 shall be used
for payment adjustments to the final quantities of the top
layer of the bituminous wearing course paid under Clause
4.5.14 or the final quantities of concrete pavement paid
under Clause 5.7.6. Price adjustments are based on the
average IRI value of the two wheel paths (lane IRI) for each
150m subsection.

Final Roughness
Price Adjustment
IRI (m/km)
≤ 1.2 100%
1.2 – 1.4 98%
1.4 – 1.6 96%
1.6 – 1.9 92%
1.9 – 2.4 85%
Mill, remove and replace the top
2.4 and above wearing course layer
Plane concrete surface
Table 4.12.7.1: Wearing Course Price Adjustment for
Rideability

4.12.8 Method of Measurement


1 The IRI test shall be measured in linear meters for the
total length of pavement tested in each pavement lane
(covering two wheel paths per lane).The rates shall be
deemed to include for all costs including testing
equipment, calibration, interpretation of data and
reporting of results.

♦ 4-35 ♦
copy 249
copy 249
Ref. Title Page No. Ref. Title Page No.
5.1 Concrete Materials and Mixes 5-1 5.1.4.2  Job-Site Mixing 5-9 
5.1.4.3  Ready-Mixed Concrete 5-9 
5.1.1  Description 5-1 
5.1.4.4  Quality Control and Testing – General 5-10 
5.1.1.1  Definitions 5-1 
5.1.4.5  Quality Control – Testing
5.1.1.2  References 5-1 
on Fresh Concrete 5-10 
5.1.1.3  Submittals 5-2 
5.1.4.6  Quality Control – Testing on Hardened
5.1.1.4  Quality Assurance 5-2 
Concrete 5-11 
5.1.2  Materials 5-3 
5.1.5  Method of Measurement 5-12 
5.1.2.1  Portland Cement 5-3 
5.1.5.1  Measured Items 5-12 
5.1.2.2  Silica Fume 5-3 
5.1.5.2  Items Not Measured 5-12 
5.1.2.3  Supplementary Cementing
5.1.6  Basis of Payment 5-12 
Material (SCM) 5-4 
5.1.7  Items in the Bill of Quantities 5-13 
5.1.2.4  Blended Hydraulic Cement 5-4 
5.1.2.5  Aggregates 5-4  5.2 Reinforcing Steel 5-13
5.1.2.6  Water 5-5 
5.2.1  Description 5-13 
5.1.2.7  Admixtures 5-5 
5.2.1.1  References 5-13 
5.1.2.8  Fiber Reinforcement 5-6 
5.2.1.2  Submittals 5-13 
5.1.3  Concrete Mixes 5-6 
5.2.1.3  Quality Assurance 5-13 
5.1.3.1  Design Mixes 5-6 
5.2.1.4  Delivery, Storage and Handling 5-13 
5.1.3.2  Testing Agency 5-6 
5.2.2  Materials 5-13 
5.1.3.3  Reports 5-6 
5.2.2.1  Steel Reinforcement 5-13 
5.1.3.4  Concrete Classes 5-6 
5.2.2.2  Reinforcement Accessories 5-14 
5.1.3.5  Threshold Values for Supplementary
5.2.2.3  Fabricating Reinforcement 5-14 
Cementing Materials (SCM) 5-6 
5.2.3  Construction Requirements 5-14 
5.1.3.6  Limit Values for Supplementary
5.2.3.1  General 5-14 
Cementing Materials (SCM) 5-7 
5.2.3.2  Shipping, Storage and Cleaning 5-14 
5.1.3.7  Water-Cementitious Materials Ratio 5-7 
5.2.3.3  Placing 5-15 
5.1.3.8  Slump Limits 5-7 
5.2.3.4  Concrete Cover 5-15 
5.1.3.9  Total Salt Content 5-7 
5.2.4  Method of Measurement 5-15 
5.1.3.10  Initial Setting Time 5-8 
5.2.5  Basis of Payment 5-15 
5.1.3.11  Test Mixes – Structural Grade
5.2.6  Items in the Bill of Quantities 5-16 
Concrete 5-8 
5.1.3.12  Test Mixes – Blinding and Plain 5.3 Reinforced Concrete
Concrete 5-8  Structures 5-16
5.1.3.13  Adjustments to Concrete Mixes 5-8 
5.3.1  Description 5-16 
5.1.3.14  Absorption Test 5-8 
5.3.1.1  Definitions 5-16 
5.1.3.15  Permeability Tests 5-8 
5.3.1.2  References 5-16 
5.1.3.16  Synthetic Fiber 5-9 
5.3.1.3  Submittals 5-16 
5.1.3.17  Admixtures 5-9 
5.3.1.4  Quality Assurance 5-17 
5.1.4  Construction Requirements 5-9 
5.3.2  Materials 5-17
5.1.4.1  Concrete Mixing 5-9 

copy 249
Ref. Title Page No. Ref. Title Page No.
5.3.2.1  Form Materials 5-17  5.4.3.3  Placement of Anchorages 5-31 
5.3.2.2  Waterstops 5-18  5.4.3.4  Identification and Testing 5-31 
5.3.2.3  Concrete Curing Cover Sheets 5-18  5.4.3.5  Protection of Prestressing Steel 5-32 
5.3.2.4  Curing Compounds 5-19  5.4.3.6  Ducts 5-32 
5.3.2.5  Concrete Accessories 5-19  5.4.3.7  Grout 5-33 
5.3.2.6  Repair Materials 5-19  5.4.3.8  Tensioning 5-34 
5.3.3  Construction Requirements 5-19  5.4.3.9  Pretension Construction 5-35 
5.3.3.1  Formwork 5-19  5.4.3.10  Post-Tension Construction 5-36 
5.3.3.2  Falsework 5-20  5.4.3.11  Grouting 5-37 
5.3.3.3  Embedded Items 5-20  5.4.4  Method of Measurement 5-39 
5.3.3.4  Removing and Reusing Forms 5-20  5.4.5  Basis of Payment 5-40 
5.3.3.5  Vapor Retarders 5-21  5.4.6  Items in the Bill of Quantities 5-40 
5.3.3.6  Construction Joints 5-21 
5.5 Concrete Bridges and Erection
5.3.3.7  Contraction and Expansion Joints 5-21 
Procedures 5-40
5.3.3.8  Waterstops 5-22 
5.3.3.9  Concrete Placement 5-22  5.5.1  Description 5-40 
5.3.3.10  Hot-Weather Concreting 5-24  5.5.1.1  Scope 5-40 
5.3.3.11  Finishing Plastic Concrete 5-25  5.5.1.2  References 5-40 
5.3.3.12  Curing Concrete 5-25  5.5.2  Materials 5-40 
5.3.3.13  Formed Finishes 5-26  5.5.3  Construction Requirements 5-41 
5.3.3.14  Tolerances 5-26  5.5.3.1  Balanced Cantilever Construction
5.3.4  Method of Measurement, Basis with In-Situ Concrete 5-41 
of Payment and Bill of Quantities 5-27  5.5.3.2  Glued Precast Segmental
Construction 5-42 
5.4 Prestressed Concrete
5.5.3.3  Precast Beam and slab Construction 5-43 
Structures 5-27
5.5.3.4  In-Situ Construction 5-43 
5.4.1  Description 5-27  5.5.4  Method of Measurement, Basis of
5.4.1.1  Scope 5-27  Payment and Items in the Bills
5.4.1.2  Definitions 5-27  of Quantities 5-43 
5.4.1.3  References 5-27 
5.6 Vehicular and Pedestrian
5.4.1.4  Submittals 5-28 
Underpasses and Animal
5.4.2  Materials 5-28 
Crossings 5-44
5.4.2.1  Concrete 5-28 
5.4.2.2  Reinforcing Steel 5-29  5.6.1  Description 5-44 
5.4.2.3  Prestressing Steel 5-29  5.6.1.1  Scope 5-44 
5.4.2.4  Post-Tensioning Anchorages 5.6.1.2  References 5-44 
and Couplers 5-29  5.6.2  Materials 5-44 
5.4.2.5  Epoxy-Bonding Agents for Precast 5.6.3  Construction Requirements 5-44 
Segmental Construction 5-29  5.6.3.1  Excavation 5-44 
5.4.3  Construction Requirements 5-29  5.6.3.2  Structural Concrete 5-45 
5.4.3.1  Placement of Ducts 5-29  5.6.3.3  Concrete Piles 5-45 
5.4.3.2  Placement of Prestressing Steel 5-30  5.6.3.4  Waterproofing 5-45

copy 249
Ref. Title Page No. Ref. Title Page No.
5.6.3.5  Concrete Pavement Construction 5-45  5.7.3.20  Pavement Marking 5-57 
5.6.3.6  Bituminous Pavement Construction 5-45  5.7.3.21  Field Quality Control 5-57 
5.6.3.7  Electrical Works 5-45  5.7.3.22  Repairs and Protection 5-58 
5.6.4  Method of Measurement 5-45  5.7.3.23  Determination of Concrete Thickness 5-59 
5.6.5  Basis of Payment 5-45  5.7.4  Method of Measurement 5-59 
5.6.6  Items in the Bill of Quantities 5-45  5.7.5  Basis of Payment 5-59 
5.7.6  Items in the Bill of Quantities 5-59 
5.7 Cement Concrete Pavement 5-45
5.8 Joint Sealers for Concrete
5.7.1  Description 5-45 
Pavement 5-59
5.7.2  Materials 5-45 
5.7.2.1  Forms 5-46  5.8.1  Description 5-59 
5.7.2.2  Steel Reinforcement 5-46  5.8.2  Materials 5-59 
5.7.2.3  Concrete Materials 5-46  5.8.2.1  Materials, General 5-59 
5.7.2.4  Admixtures 5-47  5.8.2.2  Elastomeric Hot-Poured Joint Sealants 5-60 
5.7.2.5  Curing Materials 5-47  5.8.2.3  Joint Sealant Backing 5-60 
5.7.2.6  Related Materials 5-47  5.8.2.4  Miscellaneous Materials 5-60 
5.7.2.7  Concrete Mixes 5-47  5.8.3  Construction Requirements 5-60 
5.7.2.8  Concrete Mixing 5-48  5.8.3.1  Examination 5-60 
5.7.2.9  Limitations of Mixing: 5-48  5.8.3.2  Preparation 5-60 
5.7.3  Construction Requirements 5-48  5.8.3.3  Installation of Joint Sealers 5-60 
5.7.3.1  Preparation 5-48  5.8.3.4  Cleaning 5-61 
5.7.3.2  Edge Forms and Screed Construction 5-49  5.8.3.5  Protection 5-61 
5.7.3.3  Steel Reinforcement 5-49  5.8.4  Method of Measurement, Basis
5.7.3.4  Placement of Reinforcement 5-49  of Payment and Bill of Quantities 5-61 
5.7.3.5  Joints 5-49 
5.9 Reinforced Concrete Box Culverts
5.7.3.6  Conditioning of Underlying Course,
and Headwalls, Wingwalls,
Slip-Form Construction 5-52 
Cut-Off Walls and Aprons 5-61
5.7.3.7  Conditioning of Underlying Course,
Side-Form Construction 5-52  5.9.1  Description 5-61 
5.7.3.8  Handling, Measuring, and Batching 5.9.2  Materials 5-61 
Material 5-52  5.9.3  Construction Requirements 5-61 
5.7.3.9  Concrete Protection and Curing 5-53  5.9.4  Method of Measurement 5-62 
5.7.3.10  Concrete Placement 5-53  5.9.5  Basis of Payment 5-62 
5.7.3.11  Concrete Finishing 5-55  5.9.6  Items in Bill of Quantities 5-62 
5.7.3.12  Final Strike-Off, Consolidation
5.10 Waterproofing for Structures 5-62
and Finishing 5-55 
5.7.3.13  Surface Texture 5-56  5.10.1  Description 5-62 
5.7.3.14  Skid Resistant Surfaces 5-56  5.10.1.1  Scope 5-62 
5.7.3.15  Surface Test 5-56  5.10.1.2  References 5-62 
5.7.3.16  Removing Forms 5-57  5.10.2  Materials 5-62 
5.7.3.17  Sealing Joints 5-57  5.10.2.1  Asphalt 5-62 
5.7.3.18  Opening to Traffic 5-57  5.10.2.2  Bitumen 5-62 
5.7.3.19  Pavement Tolerance 5-57  5.10.2.3  Waterproofing Fabric 5-62

copy 249
Ref. Title Page No. Ref. Title Page No.
5.10.2.4  Self-Adhesive Polyethylene Sheet 5-62  5.11.4  Method of Measurement, Basis
5.10.2.5  Tar for Absorptive Treatment 5-62  of Payment and Bill of Quantities 5-67 
5.10.2.6  Tar Seal Coat 5-63 
5.12 Bridge Load Testing 5-67
5.10.2.7  Proprietary Waterproofing Systems 5-63 
5.10.2.8  Epoxy Coating System 5-63  5.12.1  Description 5-67 
5.10.3  Construction Requirements 5-63  5.12.2  Load Application 5-67 
5.10.3.1  Surface Preparation 5-63  5.12.2.1  Composition of Applied Load 5-67 
5.10.3.2  Inspection, Delivery and Storage 5-63 5.12.2.2  Testing by Static Load 5-68 
5.10.3.3  Asphalt and Bitumen Waterproofing 5.12.2.3  Testing by Moving Load 5-68 
Fabric 5-63  5.12.3  Visual Inspection 5-68 
5.10.3.4  Proprietary Waterproofing 5.12.4  Measurements 5-68 
Membranes 5-64  5.12.5  Method of Measurement 5-68 
5.10.3.5  Damage Patching of Waterproofing 5.12.6  Basis of Payment 5-68 
Fabrics 5-64  5.12.7  Items in the Bill of Quantities 5-68 
5.10.3.6  Dampproofing 5-64 
5.10.3.7  Protection of Waterproofing and
Dampproofing 5-64 
5.10.3.8  Testing 5-65 
5.10.4  Method of Measurement 5-65 
5.10.5  Basis of Payment 5-65 
5.10.6  Items in the Bill of Qquantities 5-65 

5.11 Protective Coating for Concrete 5-65


5.11.1  Description 5-65 
5.11.1.1  Scope 5-65 
5.11.1.2  Submittals 5-65 
5.11.1.3  Performance Requirements 5-65 
5.11.1.4  Quality Assurance 5-65 
5.11.1.5  Testing 5-66 
5.11.2  Materials 5-66 
5.11.2.1  General 5-66 
5.11.2.2  Primer 5-66 
5.11.2.3  Topcoat 5-66 
5.11.2.4  Specifications 5-66 
5.11.3  Construction Requirements 5-66 
5.11.3.1  General 5-66 
5.11.3.2  Inspection of Concrete 5-66 
5.11.3.3  Surface Preparation 5-67 
5.11.3.4  Approval Prior to Coating Application 5-67 
5.11.3.5  Application 5-67 

copy 249
5.1 Concrete Materials and Mixes ASTM C 114 Standard Test Methods for Chemical
Analysis of Hydraulic Cement
5.1.1 Description ASTM C 117 Standard Test Method for Materials
Finer Than 75 Micrometer (No. 200)
5.1.1.1 Definitions Sieve in Mineral Aggregates by
1 Concrete shall consist of a mixture of cementitious Washing
materials, aggregates, water and additives. ASTM C 127 Standard Test Method for Density,
2 Cementitious Materials: Portland cement alone or in Relative Density (Specific Gravity) and
combination with one or more of blended hydraulic Absorption of Coarse Aggregate
cement, fly ash and other pozzolans, ground granulated ASTM C 128 Standard Test Method for Density,
blast-furnace slag and silica fume. Relative Density (Specific Gravity) and
Absorption of Fine Aggregate
5.1.1.2 References
ASTM C 131 Standard Test Method for Resistance to
AASHTO T26 Standard Method of Test for Quality of Degradation of Small-Size Coarse
Water to be used in Concrete Aggregate by Abrasion and Impact in
1 American Association of State Highways and the Los Angeles Machine
Transportation Officials (AASHTO): ASTM C 142 Standard Test Method for Clay Lumps
2 American Concrete Institute (ACI): and Friable Particles in Aggregates

ACI 117 Specifications for Standard Tolerances ASTM C 143 Standard Test Method for Slump of
for Concrete Construction and Hydraulic Cement Concrete
Materials ASTM C 150 Standard Specification for Portland
ACI 301 Specifications for Structural Concrete Cement
for Buildings ASTM C 172 Standard Practice for Sampling Freshly
ACI 304 Guide for Measuring, Mixing, Mixed Concrete
Transporting, and Placing Concrete ASTM C 186 Standard Test Method for Heat of
3 American National Standards Institute (ANSI): Hydration of Hydraulic Cement

ANSI Q9001 Quality Systems – Model for Quality ASTM C 191 Standard Test Method for Time of
Assurance in Design, Development, Setting of Hydraulic Cement by Vicat
Production, Installation, and Servicing Needle

ANSI Q9002 Quality Systems – Model for Quality ASTM C192/C192M Standard Practice for Making
Assurance in Production, Installation, and Curing Concrete Test Specimens in
and Servicing the Laboratory (AASHTO T126)

4 American Society for Testing and Materials (ASTM): ASTM C 219 Standard Terminology Relating to
Hydraulic Cement
ASTM A 820 Standard Specification for Steel Fibers
for Fiber-Reinforced Concrete ASTM C 227 Standard Test Method for Potential
Alkali Reactivity of Cement-Aggregate
ASTM C31/C31M Standard Practice for Making and
Combinations (Mortar-Bar Method)
Curing Concrete Test Specimens in the
Field (AASHTO T23) ASTM C 289 Standard Test Method for Potential
Reactivity of Aggregates (Chemical
ASTM C 33 Standard Specification for Concrete
Method)
Aggregates
ASTM C 295 Standard Guide for Petrographic
ASTM C39/C39M Standard Test Method for Compressive
Examination of Aggregates for
Strength of Cylindrical Concrete
Concrete
Specimens (AASHTO T22)
ASTM C 311 Standard Test Methods for Sampling
ASTM C 40 Standard Test Method for Organic
and Testing Fly Ash or Natural
Impurities in Fine Aggregates for
Pozzolans for Use as a Mineral
Concrete
Admixture in Portland-Cement
ASTM C 42 Standard Test Method for Obtaining Concrete
and Testing Drilled Cores and Sawed
ASTM C 494 Standard Specifications for Chemical
Beams of Concrete
Admixtures for Concrete
ASTM C 88 Standard Test Method for Soundness of
ASTM C 586 Standard Test Method for Potential
Aggregates by Use of Sodium Sulfate
Alkali Reactivity of Carbonate Rocks for
or Magnesium Sulfate
Concrete Aggregates (Rock Cylinder
ASTM C 94 Standard Specifications for Ready- Method)
Mixed Concrete

♦ 5-1 ♦
copy 249
ASTM C 595 Standard Specifications for Blended BS EN 12350 Testing Fresh Concrete
Hydraulic Cements BS EN 12390 Testing Hardened Concrete
ASTM C 618 Standard Specifications for Coal Fly BS EN 12620 Specification for Aggregates
Ash and Raw or Calcined Natural
BS EN 197 Cement Specification
Pozzolan for Use as a Mineral
Admixture in Concrete Part 1: Composition and specification

ASTM C 989 Standard Specification for Ground Part 2: Conformity evaluation


Granulated Blast-Furnace Slag for Use 6 Commercial Standards (CS):
in Concrete and Mortars Concrete Plant Manufacturers Bureau - Concrete Plant
ASTM C 1064 Standard Test Method for Temperature Standards
of Freshly Mixed Portland Cement National Ready-Mixed Concrete Association (NRMCA) -
Concrete Check List
ASTM C 1077 Standard Practice for Laboratories 7 Corps of Engineers (CE):
Testing Concrete and Concrete
CE CRD-C119 Test for Flat and Elongated Particles
Aggregates for Use in Construction and
Criteria for Laboratory Evaluation 8 National Standard of Canada:
ASTM C 1105 Standard Test Method for Length CAN/CSA A23.5-M86 Supplementary Cementing
Change of Concrete Due to Alkali- Materials
Carbonate Rock Reaction
5.1.1.3 Submittals
ASTM C 1116 Standard Specification for Fiber-
Reinforced Concrete and Shotcrete 1 Product Data: For proprietary materials and items.
ASTM C 1202 Test Method for Electrical Indication of 2 Design Mixes: For each concrete mix. Include
Concrete’s Ability to Resist Chloride Ion alternative mix designs when characteristics of materials,
Penetration (AASHTO T 277) project conditions, weather, test results, or other
circumstances warrant adjustments.
ASTM D 512 Standard Test Methods for Chloride Ion
in Water 3 Qualification Data: For firms and persons specified in
Paragraph 5.1.1.4 "Quality Assurance" to demonstrate
ASTM D 516 Standard Test Method for Sulfate Ion in
their capabilities and experience. Include lists of
Water
completed projects with project names and addresses,
ASTM E 329 Standard Specification for Agencies names and addresses of engineers and owners, and any
Engaged in the Testing and/or other information required by the Engineer.
Inspection of Materials used in
4 Material Test Reports: From a qualified testing
Construction
agency indicating and interpreting test results for
ASTM E 548 Standard Guide for General Criteria compliance of the following with requirements indicated,
Used for Evaluating Laboratory based on comprehensive testing of current materials:
Competence
5 Material Certificates: Signed by manufacturers and
5 British Standards: Contractor certifying that each of the following items
BS 812 Testing Aggregates complies with specified requirements:
BS 1881 Methods of Testing Concrete i. Cementitious materials and aggregates.
BS 1199 and 1200 Specification for Building Sands from ii. Fiber reinforcement.
Natural Sources iii. Admixtures: Material certificates in lieu of
material laboratory test reports when permitted
BS 4027 Specification for Sulfate-Resisting
by the Engineer. Material certificates shall be
Portland Cement
signed by the manufacturer and the Contractor,
BS 5328 Methods for Specifying Concrete certifying that each material item complies with
Including Ready-Mixed Concrete specified requirements. Provide certification
BS EN 932 Tests of Aggregates for General from admixture manufacturers that chloride
Properties content complies with specified requirements.
BS EN 933 Tests of Aggregates for Geometric 6 Minutes of pre-installation conference.
Properties
5.1.1.4 Quality Assurance
BS EN 1097 Tests of Aggregates for Mechanical
Properties 1 Quality System: Comply with ISO 9001/9002 Quality
BS EN 1367 Tests of Aggregates for Thermal and System and ISO 14001 Environmental Management
Weathering Properties Systems as a minimum. Incorporate all the standard
procedures supplied by the Engineer and the Employer.
BS EN 1744 Tests of Aggregates for Chemical
Properties

♦ 5-2 ♦
copy 249
2 Codes and Standards: Comply with the latest version submittals, status of coordinating work, and availability of
of ACI Manual of Concrete Practice Parts 1, 2, 3, 4 & 5, and materials. Establish preliminary work progress schedule
CRSI "Manual of Standard Practice” except where more and procedures for materials inspection, testing, and
stringent requirements are shown or specified. certifications. Require representatives of each entity
3 Concrete Quality Control Engineer: Appoint a full- directly concerned with cast-in-place concrete to attend
time Concrete Quality Control Engineer (CQCE) to ensure conference, including, but not limited to, the following:
that concrete is properly produced, placed, cured and - Contractor’s superintendent.
protected. The CQCE shall be equivalent to a Member of - Agency responsible for concrete design mixes.
the Institute of Concrete Technology (MICT) or as
- Agency responsible for field quality control.
approved by the Engineer and shall be responsible for the
maintenance and submission of all specified records. The - Ready-mix concrete producer.
CQCE shall not report to the site construction - Concrete subcontractor.
management but to the Contractor’s management and to - Primary admixture manufacturers
the Engineer. The CQCE shall set standards of quality and
insist that these standards be followed, prepare a Quality
5.1.2 Materials
Control Program for the inspection and testing of concrete
and the maintenance of all reports and records to meet the 5.1.2.1 Portland Cement
specified requirements and requirements of the Engineer.
Depending on the quantity of concrete works in specific 1 Portland Cement: Cement shall be low alkali with
project, the Special Specifications may waive this chemical composition in accordance with Table 1 of ASTM
requirement. C 150 or BS EN 197: Part 1. The magnesia content shall be
limited to 4 percent by weight of cement, as tested in
4 The Contractor shall operate a Quality Assurance
accordance with ASTM C 114. Use one brand of cement
System in accordance with ANSI Q9002. The Quality
throughout Project unless otherwise approved by the
Assurance Manager shall be responsible for the
Engineer. Manufacturer’s test certification shall be
preparation of a Quality Plan for approval of the
supplied for each delivery of cement and shall confirm
operations specified in this Section. The Quality Plan shall
that the cement complies with the above requirements
include, among other things, the list and schedule of the
and shall be submitted by the Contractor not later than the
Quality Control audits that the Quality Assurance Manager
day of delivery of the cement. The Engineer shall have the
shall make.
right to call for tests, the cost of which is to be borne by
5 Concrete Manufacturer Qualifications: A firm the Contractor, on each delivery of cement to confirm that
experienced in manufacturing ready-mixed concrete the cement meets the following requirements.
products complying with ASTM C 94/C94M requirements
i. Ordinary Portland cement (OPC) conforms to
for production facilities and equipment.
ASTM C 150, Type I or BS EN 197. The heat of
6 Engage an independent testing agency acceptable to hydration shall not exceed 325 kj/kg when tested
the Engineer to perform material evaluation tests and in accordance with ASTM C 186. C3A content
qualified according to ASTM C 1077 and ASTM E 329 to shall be a minimum of 5 percent and a maximum
conduct the testing indicated, as documented according to of 13 percent.
ASTM E 548 and to design concrete mixes. ii. Sulfate-resisting Portland cement conforms to
i. Personnel conducting field tests shall be ASTM C 150, Type V or BS 4027; C3A content
qualified as ACI concrete field testing technician, shall not be more than 3.5 percent.
Grade 1 according to ACI CP-1 or an equivalent iii. Moderate Sulfate: conforms to ASTM C 150 type
certification program approved by the Engineer. II or BS EN 197. C3A content shall be a minimum
of 3.5 percent and a maximum of 8 percent.
7 Materials and installed work may require testing and
retesting at any time during progress of work, if instructed 2 Sampling shall be carried out in accordance with BS
by the Engineer. Tests, including retesting of rejected EN 196: Part 7.
materials for installed work, shall be done at the 3 Test cement for fineness by air permeability
Contractor’s expense. apparatus in accordance with ASTM C 204 to meet the
8 Source Limitations: Obtain each type or class of requirements of ASTM C 150.
cementitious material of the same brand from the same 4 Test cement for soundness. Autoclave expansion in
manufacturer's plant, each aggregate from one source, accordance with ASTM C 151.
and each admixture from the same manufacturer.
5.1.2.2 Silica Fume
9 Pre-installation Conference: Conduct conference at
Project site to comply with requirements as follows: 1 Silica fume (SF), also referred to as microsilica, used
At least 35 days prior to submitting design mixes, conduct as a cement replacement shall be in accordance with
a meeting to review detailed requirements for preparing Type U, specified in Canadian National Standard
concrete design mixes and to determine procedures for CAN/CSA-A23.5 - M86. The silica fume shall be
satisfactory concrete operations. Review requirements for obtained from an approved supplier.

♦ 5-3 ♦
copy 249
2 The approved supplier shall provide documentation source and shall not contain substances that cause
to establish the following: spalling. Only aggregates not susceptible to alkali
i. That the silica fume complies with Type U of aggregate reaction shall be used. The Contractor shall
CAN/CSA-A23.5 - M86. supply samples of the materials for approval by the
ii. The silica fume results from the production of Engineer and each aggregate source shall be subject to
silicon or ferro-silicon alloys containing at least monitoring by the Engineer. Grading of aggregate shall be
85 percent silicon dioxide. That source of supply to the compliance of BS EN 12620.
shall remain the same for the construction 2 Coarse aggregate for structural concrete shall be
period of the project. 20mm nominal size, free from material passing a 5mm
iii. That the supply shall be adequate to meet the sieve, and shall consist of crushed stone, selected, re-
anticipated peak requirement. crushed, finish screened and washed with water meeting
iv. Chemical analyses to give the percentages of the the requirements of Paragraph 5.1.2.6 as necessary, and
following materials: shall comply with the following:
Si O2 C
Freq. of
Ca O Fe2 O3 Tests Test Description Standard Limit
Al2 O3 Na2 O (min)

K2 O Mg O Los Angeles ASTM 25%


Initial Abrasion Loss
SO3 C 131 maximum
(Grading A or B)
v. Loss on ignition. Ratio of Los
vi. Percentage of particles greater than 44 μm. Angeles Abrasion ASTM
vii. Specific surface area and method of test, Loss at 100 & 500 0.25%
Initial C 131
together with corresponding particle size. Revolutions maximum
(100/500 Note 6
3 Delivery of silica fume to the concrete batching plant
Revolutions Value)
shall be in dry powder form, with a bulk density between
200 and 650 kg/cu m. Clay Lumps and ASTM 1.0%
1 per day
Friable Particles C 142 maximum
4 Manufacturer's test certification shall be supplied for
each delivery of silica fume and shall confirm that the Material Finer than ASTM 1.0%
1 per day
silica fume complies with the above requirements and 75 Microns C 117 maximum
shall be submitted by the Contractor no later than the day 1 per 7 ASTM 2.0%
of delivery of the silica fume. Water Absorption
days C 127 maximum
5 The Engineer shall have the right to call for tests, the 1 per 3 0.03%
cost of which are to be borne by the Contractor, on each Chlorides as Cl BS 812
days max *
delivery of silica fume, if necessary to establish or confirm
1 per 3 0.3% max
that the silica fume meets the above requirements. Sulfates as SO3 BS 812
days *
5.1.2.3 Supplementary Cementing Material (SCM) Magnesium ASTM
1 per 30 12%
Sulfate Soundness
1 Supplementary cementing materials, if permitted by days C 88 maximum
Loss (5 cycles)
the Engineer, shall be selected from subparagraphs below.
1 per 3 25%
Blending of fly ash or slag with Portland cement shall be Flakiness Index BS 812
days maximum
done at mixing plant.
1 per 3 25%
i. Pulverized Fly Ash: ASTM C 618, Class C or F. Elongation Index BS 812
days maximum
ii. Ground Granulated Blast-Furnace Slag: ASTM C
Per
989, Grade 100 or 120. Each Appendix
ASTM
production Reactive Silica X1.3.7 of
5.1.2.4 Blended Hydraulic Cement C 227
sample ASTM C
1 Blended Hydraulic Cement: conforming to ASTM C 33
595 shall be used solely for grouts if specified or approved 1 per 7 ASTM Minimum
Specific Gravity
by the Engineer. It shall not to be used for making days C 127 2.6
structural concrete. 1 per 2 BS EN
Moisture Content
days 1097-5
5.1.2.5 Aggregates
Each
1 Aggregates shall be normal-weight and shall be from 3%
production Shell Content BS812
maximum
approved sources and shall conform to the requirements sample
of ASTM C 33 and BS EN 12620. Petrographic analyses
Table 5.1.2.1: Coarse Aggregate Specifications and Testing
shall be made in accordance with ASTM C 295.
Aggregates for exposed concrete shall be from a single

♦ 5-4 ♦
copy 249
* Additionally, the limits specified in Paragraph 5.1.3.9 for tons of fine aggregate and every 80 tons
total salt content shall not be exceeded of coarse aggregate.
3 Fine aggregate, shall pass a 5mm sieve and shall - Chemical analyses shall be carried out on
consist of crushed gravel, crushed stone or natural sand every 100 tons of aggregate.
with rounded or surrounded particles, washed as ii. The Engineer shall have the right to call for
necessary, and shall comply with the following: additional samples at any time for testing of
aggregates delivered to the Site or of aggregates
Test Description Standard Limit at the source of supply in order to confirm that
Clay Lumps and the aggregates meet the above requirements.
ASTM C 142 1.0% maximum
Friable Particles 6 Transportation: During transportation to the Site, all
maximum 3% for aggregates shall be protected from wind-borne
Material Finer natural sand and 5% contaminants. If these contaminants are present at time
ASTM C 117
than 75 Microns for crushed sand of delivery, the aggregates shall be washed with water
with no plastic fines meeting the requirement of Paragraph 5.1.2.6. Transport
Water vehicles shall be cleaned to remove possible
ASTM C 128 1.0% maximum
Absorption contamination due to previous use.
Chlorides as Cl BS 812 0.06% maximum* 7 Storage: Aggregates shall be stored (under shade) on
hard concrete floors or other approved surface having
Sulfates as SO3 BS 812 0.30% maximum*
sufficient slope to ensure adequate drainage of aggregate
Organic Lighter than before being used for concrete. Each size and type shall be
ASTM C 40
Impurities Standard stored in separate heaps without intermixing. Storage
Sand Equivalent AASHTO T176 75% minimum shall prevent contamination of the aggregates by foreign
material including windblown dust. Fine and coarse
Five Cycles of
aggregates shall be separated by permanent substantial
Soundness in
BS 812 15% maximum partitions. Methods of storing, shading and cooling
Magnesium
Sulfate aggregates shall be approved by the Engineer.

Table 5.1.2.2: Fine Aggregate Specifications and Testing 8 Plums used in cyclopean concrete shall consist of
non-reactive broken stone spalls or boulders ranging in
* Additionally, the limits specified in Paragraph 5.1.3.9 for size from 200mm to 300mm. They shall be free from sharp
total salt content shall not be exceeded or angular edges and shall not form more than 30 percent
4 Certification: Obtain from each proposed source of of the total volume of concrete. They shall be evenly
supply test certification to confirm that the aggregates graded and shall be soaked in water prior to incorporation
comply with the above requirements. The following in the mix. Plums shall be evenly distributed in the
information shall be provided: concrete mix with a minimum cover of 100mm.
i. Quarry location. 5.1.2.6 Water
ii. Aggregate type.
iii. Petrographic analysis report. 1 Water used for mixing concrete, ice production,
iv. Grading curve. washing and cooling aggregates, and curing concrete
v. Shape and surface texture. shall be free from impurities, oil, acid, salts, alkali, organic
vi. Flakiness index. matter, and other potentially deleterious substances when
vii. 10 percent fines value. tested in accordance with AASHTO T26, ASTM D 512 and
viii. Impact test. ASTM D 516. Additionally, the limits specified in
ix. Shell content. Paragraph 5.1.3.9 for the total salt content of the concrete
x. Chloride and sulfate content. shall not be exceeded.
xi. Relative density. 2 Once a source of satisfactory supply has been
xii. Water absorption value and moisture content. established, further tests shall be made daily with a
xiii. Silt, clay, and dust content. portable electrical conductivity probe calibrated against
xiv. Results of reactive silica tests. the satisfactory supply. If the conductivity exceeds that of
xv. Organic impurities (fine aggregate only). the satisfactory supply, then further chemical tests shall be
5 Testing: performed.
i. When a source of supply for each aggregate type 5.1.2.7 Admixtures
has been established, samples of materials
delivered to the Site shall be taken for testing in 1 Admixtures containing chlorides shall not be used.
accordance with BS 812 as follows: 2 No admixture shall be used in the concrete without
- Tests for clay, silt and dust, and sieve the Engineer's written approval and under no
analysis shall be carried out for every 40 circumstances shall admixtures containing chlorides or

♦ 5-5 ♦
copy 249
other corrosive agents be allowed. Admixture i. Fiber: Type 1, cold-drawn wire, or Type 2, cut
compatibility with the type of cement used shall be proven. sheet.
3 The Contractor shall perform a trial batch and casting 2 Synthetic Fiber: Fibrillated or monofilament
to substantiate the manufacturer’s claims of workability, polypropylene fibers engineered and designed for use in
retardation as specified in Clause 5.1.3 Admixtures shall concrete, complying with ASTM C 1116, Type III. Project to
comply with the following standards: ASTM C494/C494 M, specify length.
BS EN 934 and BS EN 480. Also, admixture shall comply
with BS EN 12878 for pigments of cement. 5.1.3 Concrete Mixes
4 Air-Entraining Admixture: No air entraining agent
5.1.3.1 Design Mixes
shall be used.
5 Admixtures shall be incorporated into the mix design 1 Prepare design mixes for each type and strength of
strictly in accordance with the manufacturer’s written concrete determined by either laboratory trial mix or field
instructions. test data bases, according to ACI 211.1 and ACI 301.
6 High-Range Water-Reducing Admixture 5.1.3.2 Testing Agency
(Superplasticizer): ASTM C 494, Type G.
1 Use a qualified independent testing agency
i. If necessary, and only with the Engineer’s
acceptable to the Engineer for preparing and reporting
approval, a naphthalene sulphonate retarding
proposed mix designs for the laboratory trial mix basis.
superplasticizer shall be used to increase
workability of the concrete and retard the initial 2 Do not use the same testing agency for field quality
set. control.
ii. Products: Superplaticizer shall produce fluid,
5.1.3.3 Reports
easily flowing concrete with a slump value at
least 200 mm, but free from segregation, and 1 Submit written reports to the Engineer of each
having the same water/cement ratio as that of a proposed mix for each class of concrete at least 15 days
no slump concrete with admixture. The product prior to start of work. Do not begin concrete production
shall result in concrete that remains workable for until proposed mix designs have been reviewed and
a minimum of 3 hours at +20 deg.C and for a approved by the Engineer.
minimum of 1.5 hours at +40 deg. C.
iii. Obtain from the retarding superplasticizer 5.1.3.4 Concrete Classes
supplier, details of the material for review by the
Concrete class

Engineer and confirmation that it is in Minimum Cement Maximum


accordance with specified requirements. compressive content Water-
Confirmation shall be obtained that the retarding strength at 28 (kg/m3) Cementitious
superplasticizer is compatible with any pozzolan days (MPa) Minimum Materials
that is used. Cylinder / cube / Maximum Ratio

7 Water-Reducing Admixture (Plasticizer): ASTM C 494,


15 15 / 18.5 250 / 350 0.70
Type A.
25 25 / 31 300 / 400 0.52
8 Water-Reducing and Accelerating Admixture: ASTM
C 494, Type E. 30 30 / 37.5 350 / 450 0.50
9 Water-Reducing and Retarding Admixture: ASTM C 35 35 / 43.5 425 / 475 0.48
494, Type D. 40 40 / 50 425 / 500 0.45
10 Corrosion-Inhibiting Admixture: Commercially 45 45 / 56 450 / 500 0.42
formulated, mixed cathodic and anodic inhibitor based on
50 50 / 62.5 450 / 500 0.40
amines and alcohol; capable of forming a protective
barrier and absorbed on the reinforcement surface of 60 60 / 75 450 / 500 0.38
concrete for protecting steel bars and minimizing chloride Table 5.1.3.1: Concrete Classes
reactions with steel reinforcement in concrete.
5.1.3.5 Threshold Values for Supplementary
11 Glare-Reducing Agent: For landscape concrete
paving, provide material for reducing glare. Comply with Cementing Materials (SCM)
ASTM D 209.
1 Add SCM to the mix as necessary to achieve the
5.1.2.8 Fiber Reinforcement strength and durability requirements of the concrete
classes with due account of the maximum water-
1 Carbon-Steel Fiber: ASTM A 820, deformed, cementitious materials ratios specified in Table 5.1.3.1 and
minimum 60 mm long, and of diameter or effective Paragraph 5.1.3.7.
diameter indicated. 2 All the supplementary cementing materials (SCM)
have threshold values of addition below which significant

♦ 5-6 ♦
copy 249
durability or strength parameters do not develop. Nominal
(Equation 2)
threshold addition values are indicated in Table 5.1.3.2 for:
i. Silica fume
5.1.3.7 Water-Cementitious Materials Ratio
ii. Ground granulated blast-furnace slag (GGBFS)
iii. Pulverized fly ash (PFA) 1 The maximum water-cementitious materials ratio
shall be the lower of the values listed in Table 5.1.3.1 for
SCM Nominal threshold value
the concrete classes and the following values for the
01 Silica fume 7% on [cement + silica fume] exposure:
02 GGBFS 50% on [cement + GGBFS] i. 0.45 for concrete required to have low water
03 PFA 25% on [cement + PFA] permeability.
ii. 0.40 for corrosion protection of steel
Table 5.1.3.2Threshold Addition Values for SCM
reinforcement in concrete exposed to chlorides
3 The actual amount will depend on the quality of the from salt, saltwater, brackish water, seawater, or
supplementary cementing material and mix design spray from these sources.
parameters. iii. 0.45 for concrete subject to moderate sulfate
exposure.
5.1.3.6 Limit Values for Supplementary Cementing iv. 0.42 for concrete subject to severe or very severe
Materials (SCM) sulfate exposure.

1 The upper limiting addition percentage values for 2 The water-cementitious materials ratio shall be
each supplementary cementing material shall be as Table continuously checked at the mixer with due allowance
5.1.3.3. made for water contained in the aggregates. Under no
circumstance shall water be added between the mixer and
Max. the place of concrete placement. The Engineer may
SMA Applicable conditions
% require that the water-cementitious materials ratio be
Silica checked during tests performed on fresh concrete samples
01 10 For all exposures taken at the time of placement as specified in Paragraph
fume
For permanent dry [RH ≤ 50%] 5.1.4.4.
02 GGBFS 55 or damp [RH ≥ 85%]
conditions 5.1.3.8 Slump Limits
For underground damp
03 PFA 30 1 The slump of concrete mixes shall be such that the
exposures [RH ≥ 85%]
concrete can be transported, placed into the forms, and
04 GGBFS 70
For concrete buried in compacted without segregation in accordance with Sub-
05 PFA 45 permanently wet conditions Section 5.3. If no superplasticizer is required, the slump at
time of placement shall be 50-75 mm as measured in
Table 5.1.3.3: Limit Addition Values for SCM accordance with ASTM C 143. The concrete shall be
RH is the relative humidity. sufficiently workable to enable placement in its position
with minimum difficulty.
2 When mixtures of supplementary cementing
materials are designed into the same mix, calculations 5.1.3.9 Total Salt Content
based on proportionate replacement based on the limiting
values shown in Table 5.1.3.3 shall be derived by the use 1 Chlorides: The total chloride content (sum of both
of Equations 1 and 2. acid soluble and water soluble chlorides) of the concrete
from all sources, expressed as chloride ion, shall not
The following equations shall be used for calculating the
exceed the following percentages by weight of dry cement,
limiting partial proportions of each mineral additive in the
inclusive of pozzolan, when tested in accordance with BS
mix design:
1881:
Where
i. Unreinforced concrete 0.60%
x is the % of Silica fume incorporated ii. Concrete made with sulfate resisting
y is the % of GGBFS incorporated and cement 0.15%
z is the % of PFA incorporated iii. Concrete containing embedded metal (reinforced
concrete) made with ordinary Portland
For normal concrete (Table 5.1.3.3: conditions 01, 02 and
cement 0.30%
03)
iv. Prestressed concrete 0.06%
v. Heat cured concrete containing embedded metal
(Equation 1) (reinforced concrete) 0.10%
2 Sulfates: The total sulfate content of the concrete
For wet or dry situations (Table 5.1.3.3: conditions 01, 04 from all sources, expressed as SO3, when tested in
and 05) accordance with BS 1881, shall not exceed the lesser of 0.4

♦ 5-7 ♦
copy 249
percent by weight of aggregates or 3 percent by weight of Laboratory test data for revised mix design and strength
dry cement, inclusive of pozzolan. results shall be submitted to and approved by the
Engineer before using in the work.
5.1.3.10 Initial Setting Time
5.1.3.14 Absorption Test
1 The initial setting time shall be not less than 90
minutes after the production concrete is discharged into 1 Hardened concrete from the trial mixes for structural
the form. With a maximum time between mixing and grades shall be tested for absorption to establish the
placing concrete of 90 minutes, the total time between concrete’s ability to resist the ingress of aggressive salts.
mixing and initial set shall be a minimum of 2 hours. No absorption tests shall be required for blinding, plain
Maximum setting time shall be 6 hours. concrete or cyclopean concrete. Absorption tests shall be
2 When trial mixes are made to determine the in accordance with modified BS 1881: Part 122 as follows:
workability of the concrete, the initial setting time of the i. After trial mixes have been accepted, three 150
cement paste shall be determined using the method mm cylinders shall be cast from each grade of
defined in ASTM C 191 at the maximum allowable concrete and immersed in water at 20 deg. C for
temperature and with same proportions of pozzolan and 7 days.
retarding superplasticizer as specified in this Specification. ii. At the end of the curing period, 75 mm diameter
core specimens shall be cut along the
5.1.3.11 Test Mixes – Structural Grade Concrete longitudinal axis of each cylinder to a depth of
1 When the proposed workability, proportions of 75 mm.
aggregates and superplasticizer, and strength for each iii. The specimens shall be dried in an oven at 105
grade of concrete have been established, test concrete deg. C for 72 hours.
shall be produced for approval by the Engineer. The iv. The specimens shall be cooled in a dry airtight
following shall be performed for each grade of concrete: vessel for 24 hours, weighed, and then
immediately immersed in a tank containing
i. Six separate test mixes shall be made and cured
water at 20 deg. C with the longitudinal axis of
in accordance with ASTM C 192 and tested in
the cores horizontal, and with 25 mm depth of
accordance with ASTM C 39.
water over the specimens.
ii. The 36 cylinders for each grade of concrete shall
v. The specimens shall be immersed for 24 hours,
be tested for compressive strength at 28 days
then removed, shaken, surface dried, and
and the mean strength and standard deviation
reweighed. The water absorption shall be
established for each grade. The test mixes shall
calculated as the increase in mass resulting from
be accepted provided that:
immersion, expressed as a percentage of the dry
- The mix proportions and workability are mass.
in accordance with this Specification. vi. If the cores lengths differ from 75 mm, a
- The standard deviation for each grade is correction factor (graph given in BS 1881) shall
3.5 MPa or less. be applied.
- The mean strength for structural concrete vii. The mean of the corrected absorption figure for
exceeds the specified design strength by each concrete grade shall be calculated and the
6 MPa. absorption of the concrete mixes shall be
acceptable if the mean absorption is less than 2
5.1.3.12 Test Mixes – Blinding and Plain Concrete percent at 30 minutes. The mean absorption
figure and the lowest absorption figure shall be
1 Concrete for blinding, plain concrete or cyclopean
recorded for each grade and used for
concrete shall be a designed mix with design strength of
comparison purposes with absorption tests
15 MPa. The trial mix proportions shall be at the
carried out on cores cut from in-situ concrete, as
discretion of the Contractor. Once they have been chosen,
scheduled in Paragraph 5.1.4.6.
three separate test mixes shall be made with those
proportions and three test cylinders shall be made from 5.1.3.15 Permeability Tests
each mix for testing at 28 days. The trial mix proportions
and water/cement ratio shall be approved if the average 1 Depth of penetration tests shall be carried out to
strength of the nine cylinders is not less than 14 MPa. establish the water permeability of concrete on prototype
samples of different components of the structure before
2 No production test shall be made for this grade of
the mix design or manufacturing method are approved.
concrete but the Engineer will monitor the mix
The prototype samples shall be short sections of not less
proportions and water/cement ratio.
than 1.0m x 1.0m x full thickness. The samples shall be
5.1.3.13 Adjustments to Concrete Mixes fully reinforced and cast in similar environment as the
actual structure. The tests shall be carried out in
1 Mix design adjustments may be required by the accordance with DIN 1048 at age 28 days and the
Engineer when characteristics of materials, job conditions, maximum value of penetration shall not exceed the
weather, test results, or other circumstances warrant. following limits:

♦ 5-8 ♦
copy 249
In-situ construction: Less than 25 mm. 5.1.4 Construction Requirements
Precast units: Less than 20 mm.
5.1.4.1 Concrete Mixing
2 Chloride permeability of the concrete shall be
determined using cores taken from the prototype samples, 1 Concrete production shall be in accordance with ACI
in accordance with AASHTO T277 ‘Rapid Determination of 304. A checklist for concrete production shall be produced,
the Chloride Permeability of Concrete’. The following such as that used by the NRMCA or approved equal.
limits shall not be exceeded: 2 Batching of materials shall be by weight. All
In-situ construction: 1500 coulombs. weighing equipment shall be calibrated and
documentation shall be provided to establish that the
Precast units: 1000 coulombs.
accuracy is continuously maintained in accordance with
3 The concrete will be deemed to comply with the the requirements of ACI 304. Batching scale accuracy
permeability requirements of this specification if all test shall be in accordance with the Concrete Plant Standards
results comply with the limits indicated in Points 1 and 2. of the Concrete Plant Manufacturers Bureau, or approved
4 If any of the DIN 1048 and the rapid chloride equal.
permeability test results of unprotected surfaces of a 3 Furnish equipment and establish accurate
sample fail to meet the above requirements, then all the procedures for determining the quantities of free moisture
concrete work represented by such sample shall be in the aggregates. Moisture determinations shall be made
deemed not to comply with the permeability requirements. daily and whenever there is an apparent change in the
5 If, in the opinion of the Engineer, the concrete that moisture content. The moisture content shall be recorded
has failed to meet the permeability requirements of this and shall be taken into account in adjusting the weight of
Specification is likely to cause durability problems, three aggregate and the quantity of water incorporated in the
cores shall be cut from the area represented by failed mix.
samples for additional DIN 1048 and rapid chloride
permeability testing. The location of the cores shall be 5.1.4.2 Job-Site Mixing
decided by the Engineer. 1 All concrete mixed on Site shall be in a batch mixer
of approved size and design complying with ACI 304 and
5.1.3.16 Synthetic Fiber
producing a uniform distribution of the materials
1 Uniformly disperse in concrete mix at manufacturer's throughout the mixed concrete in accordance with ASTM
recommended rate, but not less than 0.60 kg/cu. m. C 94 uniformity test. The contents of the drum shall be
completely discharged before re-charging. After all the
5.1.3.17 Admixtures materials are in the mixer, mixing shall continue until the
1 Use admixtures according to the manufacturer's whole of the materials are uniformly distributed and the
written instructions and in the proportions recommended. mass is of uniform color and consistency. In the case of
concrete that contains silica fume with a density between
2 Use water-reducing admixture or high-range water-
400-650 kg/cu.m, the mixing time shall be 50 percent
reducing admixture (superplasticizer) in concrete, as
greater than the requirement for concrete without silica
required, for placement and workability.
fume.
3 Use water-reducing and retarding admixture when
2 Whenever mixing is to be suspended for half an hour
required by high temperatures, low humidity, or other
or longer, the drum of the mixer shall be thoroughly
adverse placement conditions.
washed out with clean water. Provide a competent
4 Use water-reducing admixture in pumped concrete, operator who shall be in continuous control of the mixer.
concrete required to be watertight, and concrete with a No re-tempering of concrete, which has partially hardened,
water-cementitious materials ratio below 0.50. by the addition of cement, aggregate, or water shall be
5 Use corrosion-inhibiting admixture in concrete mixes allowed.
where indicated. 3 Provide batch ticket for each batch discharged and
6 All admixtures shall be used as required and used in the work, indicating Project identification name
approved by the Engineer for placement and workability and number, date, mix type, mix time, quantity, and
of concrete, and shall be used in accordance with the amount of water introduced as well as the load printout,
manufacturer’s instructions. The equipment used for delivery printout, temperature readout and measured
dispensing and the method of incorporating the admixture slump.
into the concrete shall be subject to approval. The
5.1.4.3 Ready-Mixed Concrete
dispensing unit shall be translucent so that the operator
can see the discharge of the admixture. 1 Ready-mixed concrete shall comply with the
requirements of ASTM C 94 or BS EN 206 and as follows:
i. Concrete shall be centrally mixed off site and
transported in an agitator truck. Truck mixing
shall not be permitted.

♦ 5-9 ♦
copy 249
ii. The plant and trucks shall be certified as meeting i. Sampling, curing and testing shall be performed
the requirements of the NRMCA Check List, or using the relevant procedures in ASTM C 31,
approved equal. ASTM C 39, and ASTM C 172 or BS EN 12350.
iii. Details and information regarding the supplier - Samples for production concrete cylinders
proposed by the contractor shall be submitted to (or cubes if approved by the Engineer) shall
the Engineer for approval. be taken at the point of placement at the
iv. The approved supplier of ready mixed concrete average rate of one per 100 cu. m of concrete
shall not subsequently be changed without placed or one for each major placement, with
further approval of the Engineer. a minimum of one sample taken every day
2 When air temperature is between 30 deg. C and 32 that the mix is used. A sample shall consist
deg. C, delivery time from the time that water is added to of eight 150 mm cylinders molded and stored
the mix until it is placed in its final position in the form for laboratory-cured test specimens except
shall not exceed 90 minutes. When air temperature is when field-cured test specimens are required.
above 32 deg. C, delivery time shall not exceed 45 minutes. Three cylinders are for testing at 7 days after
Further time extension may be given if approved by the casting, three for testing at 28 days after
Engineer. casting, and two reserved for later testing if
3 Before discharging concrete at the point of delivery, required.
provide the Engineer with a delivery ticket for each batch - If frequency of testing provides fewer than 5
of concrete containing the following information as a strength tests for a given class of concrete,
minimum: conduct testing from at least 5 randomly
i. Name or number of off-site concrete depot. selected batches or from each batch if fewer
ii. Serial number for ticket. than 5 are used.
iii. Date. - When total quantity of a given class of
iv. Time of dispatch. concrete is less than 100 cu. m, the Engineer
v. Truck number. may waive strength testing if adequate
vi. Name of supplier. evidence of satisfactory strength is provided
vii. Grade or mix description of concrete. but not less than one sample per day.
viii. Type of cementitious materials. - When strength of field-cured cylinders is less
ix. Cementitious materials content and constitution. than 85 percent of companion laboratory-
x. Water/cementitious materials ratio. cured cylinders, re-evaluate current on-site
xi. Nominal maximum size of aggregate. operations and provide corrective procedures
xii. Source of aggregate, maximum size, weight of for protecting and curing the in-place
fine and coarse aggregate. concrete.
xiii. Type or name of admixture, if included.
ii. Records shall be kept of the mix details and
xiv. Percentage variation between design and actual
position in the works of all batches of concrete
values for all ingredients.
and of all samples taken for cylinders and other
xv. Quantity of concrete in cubic meters.
specimens and of their test results. A copy shall
xvi. Certifying that chlorides and sulfate contents are
be supplied to the Engineer within 24 hours after
within specified limits and stating their values.
recording/testing. Records shall contain, but not
5.1.4.4 Quality Control and Testing – General be limited to, the following information:
- Date, time, location, and volume of pour.
1 Testing Laboratory:
- Ambient temperature and humidity.
i. Employ an independent testing agency to
perform tests and to submit test reports. - Concrete temperature (at time of placement).
ii. Be responsible for taking, identifying and - Cementitious materials content and
delivering to the test laboratory all test samples constitution.
called for in this Specification. The testing - Types of manufacturers of cementitious
laboratory shall be responsible for the testing. materials.
Collect all test results and deliver them to the
- Concrete type and class.
Engineer in the format and detail as specified.
- Aggregate type and source.
2 Testing Laboratory Qualifications: The testing
laboratory shall be approved by the Engineer and shall - Admixture details.
have a Quality System in accordance with ANSI Q9001. - Water/cementitious materials ratio.
- Identification of test cylinder.
5.1.4.5 Quality Control – Testing on Fresh Concrete
- Name of concrete testing service.
1 Compressive Strength Test for Structural Concrete:
- Date and time of sampling.
- Method of compaction.

♦ 5-10 ♦
copy 249
- Date of testing and results of test. 4 Cementitious Materials Content and Water/
- Age of sample in days, weight in grams, Cementitious Materials Ratio: Samples of freshly mixed
density in kg/cu. m. concrete shall be chosen by the Engineer at least once per
month from each structural grade and determination
- Crushing load in Newtons and crushing
made of cement content and water/cement ratio in
strength in MPa.
accordance with BS 1881. If the cement content is less
- Signatures of person preparing cylinder and than 90 percent of the requirement in Paragraph 5.1.3.4 or
of person crushing cylinder. the water/cement ratio is greater than 110 percent of the
- Results of testing. requirement in Paragraphs 5.1.3.4 and 5.1.3.7 the
iii. For the 28 day tests, the concrete will be deemed Contractor and the Engineer shall investigate to establish
to comply with the specified design strength if the cause and the Engineer may reject the cast concrete
the average strength determined from all sets of for the pour from which the samples were taken. The
3 consecutive tests is at least equal to the Engineer may request an analysis of fresh concrete from
specified design strength and no individual any pour. No analysis of freshly mixed concrete is
strength test falls below the specified design required for blinding or plain concrete.
strength by more than 3.5 MPa. Any concrete 5 Salt Content: The total concentration of sulfates and
not complying with the specified design strength chlorides in fresh concrete shall be measured at least once
shall be at risk for removal and replacement at a week for all structural grades of concrete. Tests shall be
the Contractor’s expense. in accordance with BS 1881. Concentrations of each ion
iv. The 28-day cylinder crushing results shall be shall not exceed the limits specified in Paragraph 5.1.3.9. If
grouped consecutively in groups of 40 and each these limits are exceeded, the concrete pour from which
group shall have a standard deviation less than the samples were taken shall be rejected and further tests
3.5 MPa. If the standard deviation is greater than performed on the cast concrete in accordance with
or equal to 3.5 MPa, then concrete production paragraph 5.1.4.6 to determine the total extent of the
shall be investigated by the Engineer and further problem.
tests on trial mixes may be required. 6 Slump: Slump tests shall be performed in accordance
v. Tests shall be carried out at 7 days to establish a with ASTM C 143. A minimum of one test shall be done at
relationship between the 7 day and 28 day the point of discharge for each day's pour for each type of
strengths. This relationship shall be used to concrete. Additional tests shall be performed when
interpret future test results in order to predict the concrete consistency appears to have changed.
corresponding 28 day strength. The Engineer
shall be advised without delay if any 7 day test 5.1.4.6 Quality Control – Testing on Hardened
result indicates that the corresponding 28 day Concrete
strength is likely to fail to meet the specified
strength so that any necessary action can be 1 General: The Engineer may instruct samples to be
taken to minimize the effect of such possible taken and tests carried out on any hardened structural
failure. grade concrete as specified below if he suspects that the
concrete does not meet the specified requirements. If the
2 Compressive Strength Test for Blinding or Plain
tests confirm that the concrete does not meet the
Concrete: No production tests on blinding or plain
requirements of this Specification, then the Engineer may
concrete are required. The Engineer may require
require the concrete to be removed at the Contractor’s
compressive strength tests if it is believed that the
expense. If the tests confirm that the concrete meets the
characteristic strength is below 15 MPa. Characteristic
requirements of this Specification, then the cost of taking
strength is defined as the minimum value of cube strength
the samples shall not be at the Contractor’s expense.
achieved by 95 percent of all possible test results. If the
tests confirm that the characteristic strength is less than 15 2 Compressive Strength Tests: The Engineer may
MPa, then the Engineer will require revisions to the mix instruct cores to be drilled from a particular pour. 100 mm
design to ensure that the concrete meets the specified diameter cores shall be drilled as requested, in accordance
requirements. with ASTM C 42, and sent for crushing. If the cores from
that pour have an average compressive strength less than
3 Measurement of Concrete Temperature: Temperature
85 percent of the characteristic strength or if any
measurements shall be in accordance with ASTM C 1064.
individual core has a compressive strength less than 75
Concrete temperature shall be measured 50 mm below
percent of the characteristic strength, it shall be evidence
the surface prior to and at the point of placement and
that the concrete from which it was taken is not in
recorded on the pour card for each pour. One reading
accordance with the specified requirements.
shall be taken each hour when air temperature is 4 deg.C
and below and when air temperature is 27 deg.C and 3 Concrete Cover: The Engineer may check the
above, and one reading for each set of compressive- concrete cover over the reinforcement with a cover meter.
strength specimens. Concreting shall stop if the Any indication that the cover is generally less than the
temperature of the concrete does not meet the requirements specified in Paragraph 5.2.3.4 shall be
requirements of Paragraph 5.3.3.10 checked by limited surface concrete removal. If it is

♦ 5-11 ♦
copy 249
confirmed that the actual cover is generally less than 5 Concrete of the same class requiring the same
specified, then the concrete shall be removed at the falsework but with a different class of surface finish are
Contractor’s expense. In the case of localized lack of cover each measured separately.
and where appearance is not important, a repair shall be 6 Voids, openings or gaps 0.05 cubic meters or more
effected by removal of the inadequate cover and cutting shall be deducted from the volume of concrete in which
back of concrete for 50 mm behind the reinforcement. they occur.
Resurfacing of the concrete with the specified cover shall
7 All service ducts, irrespective of diameter, shall be
be carried out as a repair by a specialist subcontractor.
measured and deducted from the volume of concrete in
4 Absorption: A sample of three 75 mm diameter cores, which they are located.
75 mm long, shall be taken from hardened concrete if
directed by the Engineer and tested in accordance with 5.1.5.2 Items Not Measured
Paragraph 5.1.3.14. Should the absorption of any core
1 Volume of reinforcing bars is not deducted from the
exceed by more than 1 percent the highest approved test
measured volume of concrete.
result, the concrete from which it was cut shall be
removed. No absorption test shall be required for 2 Volume of prestressing ducts, anchors, cones,
blinding or plain concrete. couplers and grouting tubes is not deducted from the
measured volume of concrete.
5 Salt Content: Engineer may request samples to be
taken from two 20 mm diameter drillings into the concrete 3 Volume of embedded metals, bolts, nuts, anchorages,
surface, spaced 75 mm apart. Each drilling shall proceed hooks etc. is not deducted from the measured volume of
in 25 mm increments for a total depth of 100 mm and the concrete.
dust from the 4 samples in each hole shall be sent for 4 Holes introduced, with the consent of the Engineer,
sulfate and chloride content analysis in accordance with by the Contractor for the convenience of transportation,
BS 1881. Should the tests show that the limits specified in erection or construction shall not be deducted from the
Paragraph 5.1.3.9 are exceeded, the concrete shall be measured volume of concrete irrespective of the size of
removed. the holes and whether or not the holes are made good.
6 Nondestructive Testing: Impact hammer, sonoscope, 5 Additional concrete placed, with the consent of the
or other nondestructive device may be used but shall not Engineer, by the Contractor solely for the purpose of
be used as the sole basis for acceptance or rejection of facilitating his work shall not be measured for payment.
cast concrete.
7 Additional Tests: The testing agency shall make 5.1.6 Basis of Payment
additional tests of in-place concrete, as directed by the
1 The amount of completed and accepted work,
Engineer, when test results indicate that specified concrete
measured as provided above, will be paid for at the unit
strengths or other characteristics have not been attained
rate for the types and classes of concrete in the Bill of
in the structure. Testing agency may conduct tests to
Quantities, which rate shall be full compensation for:
determine adequacy of concrete by cored cylinders
complying with ASTM C 42, or by other methods as - Cement and other cementitious materials,
directed. aggregates, water and admixtures including
their testing, storage, handling and
transportation.
5.1.5 Method of Measurement
- Washing of aggregates, if required.
5.1.5.1 Measured Items
- Ice, if required, added in the mix water.
1 Concrete is measured by the cubic meter for each - Plant, machinery and equipment required for
type and class, based on dimensions shown on the the production of concrete.
Drawings or as otherwise directed by the Engineer. - Design of mixes, taking samples and testing.
2 Concrete works shall include mass, reinforced and - Transportation and delivery of concrete to work
prestressed concrete of both in-situ and precast areas.
construction of a general nature, but shall not include
- Placing, compacting, vibrating and finishing of
specific components of highway structures, such as
concrete.
concrete pavement, concrete piles, concrete parapets and
safety barriers, precast concrete curbs and tiles etc., which - All formwork irrespective of the material used
are separately prescribed for measurement and payment and the quality of surface finish specified.
in other Sections. - All falsework supporting and stabilizing
3 Different classes of concrete are measured separately. formwork.
4 Concrete formed by different types of form and/or - Curing of concrete.
falsework are each measured separately. - Tooling, if required, to achieve the specified
surface finish.

♦ 5-12 ♦
copy 249
- Corrective measures and the means of carrying 3 British Standards (BS):
them out required in the event of the concrete BS 4449 Specification for Carbon Steel Bars for
being not in accordance with the Drawings the Reinforcement of Concrete
and/or specification.
BS 4483 Steel Fabric for the Reinforcement of
- Handling, transportation and erection of Concrete
precast concrete members.
4 Concrete Reinforcing Steel Institute (CRSI):
- Grout and/or epoxy used in precast
CRSI Manual of Standard Practice
construction including material and equipment
for temporary prestress, if required. 5.2.1.2 Submittals
- Material, plant and equipment associated with
1 Steel Reinforcement Shop Drawings: Details of
particular methods of construction.
fabrication, bending, and placement, prepared according
- Joint fillers, joint sealants, weep holes, water to ACI 315, ‘Details and Detailing of Concrete
stops, dowel bars and other accessories as Reinforcement.’ Include material, grade, bar schedules,
shown on the Drawings including material, stirrup spacing, bent bar diagrams, arrangement, and
plant handling, transportation testing, storage, supports of concrete reinforcement. Include special
workmanship and associated ancillaries. reinforcement required for openings through concrete
- Protective coating. structures.
- All labor, materials and equipment. 2 Welding Certificates: Copies of certificates for
welding procedures and personnel.
5.1.7 Items in the Bill of Quantities 3 Material Certificates: Signed by manufacturers and
Contractor certifying that the following items comply with
i Concrete (class) in (type of structure),
specified requirements:
(location) and (finish) cu.m.
i. Steel reinforcement and reinforcement
accessories: a copy of the manufacturer’s test
5.2 Reinforcing Steel certificate for ultimate strength, elongation and
cold bending, together with the chemical
5.2.1 Description analysis of the steel shall be submitted to the
Engineer for each consignment of reinforcing
5.2.1.1 References
steel delivered to the Site.
1 American Concrete Institute (ACI):
5.2.1.3 Quality Assurance
ACI 315 Standard Practice for Detailing
Reinforced Concrete Structures 1 Welding: Comply with AWS D1.4, ‘Structural Welding
ACI 318 Building Code Requirements for Code--Reinforcing Steel’ for procedures and qualification
Reinforced Concrete of personnel for welding operations.

2 American Society for Testing and Materials (ASTM): 5.2.1.4 Delivery, Storage and Handling
ASTM A 82 Standard Specification for Steel Wire
1 Deliver, store, and handle steel reinforcement to
Reinforcement, Plain, for Concrete
prevent bending and damage. Avoid damaging coatings
Reinforcement
on steel reinforcement.
ASTM A 185 Standard Specification for Steel Welded
Wire Fabric, Plain, for Concrete 5.2.2 Materials
Reinforcement
ASTM A 496 Standard Specification for Steel Wire, 5.2.2.1 Steel Reinforcement
Deformed, for Concrete Reinforcement 1 Reinforcing Bars: ASTM A 615M, Grade 60 (420 MPa)
ASTM A 497 Standard Specification for Steel Welded specified yield strength, or BS 4449 grade 460 Type 2
Wire Reinforcement, Deformed, for deformed, uncoated. One test per 5000 m length
Concrete Reinforcement delivered to site.
ASTM A 615M Standard Specification for Deformed 2 Higher strength reinforcement bars may be used
and Plain Billet- Steel Bars for Concrete subject to approval of the Engineer.
Reinforcement 3 Low-Alloy-Steel Reinforcing Bars: ASTM A 706M,
ASTM A 706M Standard Specification for Low-Alloy deformed.
Steel Deformed and Plain Bars 4 Plain-Steel Wire: ASTM A 82, as drawn.
ASTM A 780 Practice for Repair of Damaged and 5 Plain-Steel Wire: ASTM A 82, galvanized.
Uncoated Areas of Hot-Dip Galvanized
6 Deformed-Steel Wire: ASTM A 496 and Steel welded
Coatings.
wire reinforcement to ASTM A 497.

♦ 5-13 ♦
copy 249
7 Welded Wire Fabric: ASTM A 185, welded steel wire 5.2.2.3 Fabricating Reinforcement
fabric.
1 Fabricate steel reinforcement according to CRSI's
8 All reinforcement shall be new material on delivery
‘Manual of Standard Practice’.
to the Site and at time of installation, material shall be free
from loose rust and loose mill scale, deleterious amounts
of salts and coatings that reduce or destroy bond. Tight
5.2.3 Construction Requirements
rust and mill scale or surface irregularities are acceptable 5.2.3.1 General
if the weight and dimensions, including height of
deformations and tensile properties, of a test specimen 1 Accurately position, support, and secure
that has been wire-brushed by hand, are not less than reinforcement against displacement. Locate and support
those required by the applicable standards. reinforcement with bar supports to maintain minimum
concrete cover. Do not tack weld crossing reinforcing bars.
9 Galvanized steel shall not be used
2 Shop- or field-weld reinforcement according to AWS
10 Reinforcement shall be accurately bent, cut or
D1.4, where indicated.
formed to the dimensions and configuration shown on
Drawings and within the tolerances specified in ACI 315. 3 Set wire ties with ends directed into concrete, not
Reinforcement shall be bent cold using approved bending toward exposed concrete surfaces.
equipment in accordance with ACI 318. Bars may be 4 Install welded wire fabric in longest practicable
preheated only if prior approval is given by the Engineer. lengths on bar supports spaced to minimize sagging. Lap
Reinforcement shall not be rebent or straightened without edges and ends of adjoining sheets at least one mesh
prior approval. spacing. Offset laps of adjoining sheet widths to prevent
i. Reinforcement having a reduced section, kinks, continuous laps in either direction. Lace overlaps with
visible transverse cracks at bends, or otherwise wire
damaged in any way shall not be used. 5 Avoid cutting or puncturing vapor retarder/barrier
ii. Reinforcement shall not be welded unless and waterproofing membranes during reinforcement
specifically shown on Drawings or permitted as placement and concreting operations. Repair damages
an exception and then only after approval of the before placing concrete.
welding method appropriate to the grade of steel
and the type of welding rod to be used. 5.2.3.2 Shipping, Storage and Cleaning

5.2.2.2 Reinforcement Accessories 1 Reinforcement shall be handled and shipped in a


manner to avoid bending or other damage to the bars.
1 Provide and fix bar supports: bolsters, chairs, spacers, Bars shall be bundled, separated in sizes and clearly
and other devices for spacing, supporting, and fastening marked by diameter size preferably for one placement, in
reinforcing bars and welded wire fabric in place. Provide accordance with the placement schedule and as follows:
bar supports according to CRSI's ‘Manual of Standard i. Bars for separate structures shall not be bundled
Practice’ from steel wire, plastic, or precast concrete or together. Bars for small structures may be
fiber-reinforced concrete of greater compressive strength bundled together but each bar or group of bars
than concrete, and as follows: that have the same piece mark shall be tagged
i. For concrete surfaces exposed to view where and coded.
legs of wire bar supports contact forms, use ii. Metal tags or approved equal shall be provided
CRSI Class 1 plastic-protected or CRSI Class 2 and labeled with legible markings.
stainless-steel bar supports. iii. All bundles shall be tagged at each end. Tags
ii. Other reinforcement supports shall consist of shall show piece marks corresponding to the
concrete spacer blocks made of the same mark numbers on the placement drawings and
materials, to the same specified requirements on the bar list.
and with the same inherent properties as the iv. Bars shall be bundled in the largest size practical
parent material with the exception that the for handling and shipping.
maximum aggregate size shall be appropriate for 2 Reinforcement shall be stored 1m above ground on
the thickness of cover to the reinforcement. platforms, skids or other approved supports and suitably
2 Joint Dowel Bars: Plain-steel bars, ASTM A 615M, spaced. Contact with the soil shall be avoided. Proper
Grade 60 (420 MPa). Cut bars true to length with ends drainage and protection from the elements shall be
square and free of burrs. provided to minimize corrosion.
3 Mechanical splices (couplers) of deformed high yield 3 Clean reinforcement of loose rust and mill scale,
steel bars are to consist of two seamless steel sleeves and earth, ice, and other materials that reduce or destroy bond
interconnecting high tensile steel stud with plastic with concrete.
protection caps for threaded section of sleeve and shall
be tested to exceed 135% of the specified yield strength of
grade 60 bar (or higher if higher strength bars are used).

♦ 5-14 ♦
copy 249
5.2.3.3 Placing 5.2.4 Method of Measurement
1 Comply with CRSI's ‘Manual of Standard Practice’ for 1 Bar and mesh reinforcement is measured by the
placing reinforcement. theoretical quantity in metric tonnes complete in place as
shown on the Drawings or placed as ordered by the
2 Accurately position, support, and secure
Engineer. No allowance is made for clips, wire or other
reinforcement against displacement. Locate and support
fastening devices, reinforcement chairs to separate slab
reinforcement on concrete blocks of a size to give the
steel or similar reinforcement or to retain wall steel or
correct cover to the reinforcement
similar. The rates in the Bill of Quantities shall be deemed
3 Where cathodic protection is utilized, reinforcement to cover for the above.
shall be isolated from the electrical grounding system.
2 Measurement of splices or laps in reinforcement
4 Chairs made of reinforcement shall be used to not shown on the Drawings will not be made.
support the top mats of slab reinforcement and shall be so
3 Calculated weights for high tensile and mild steel
dimensioned as to be stable during concreting operations.
reinforced bars shall be based upon the following Table:
The chairs shall themselves be supported on concrete
blocks as specified in Clause 5.2.2.2.
5 Place reinforcement to maintain minimum coverage

Diameter

Diameter

Diameter
Weight

Weight

Weight
as indicated for concrete protection. Arrange, space, and

Kg/m

kg/m

kg/m
mm

mm

mm
securely tie bars and bar supports to hold reinforcement in
position during concrete placement operations. Ties at
intersections shall be made with 1.5 mm diameter
annealed wire with wire ends directed into concrete, not 5 0.154 18 2.000 34 7.130
toward exposed concrete surfaces. 6 0.222 20 2.470 36 7.990
6 All lap splices shall be in accordance with ACI 318 7 0.302 22 2.980 38 8.900
class B tension lap splice unless otherwise shown on
8 0.395 24 3.550 40 9.870
Drawings. All reinforcement bars shall be cut bent and
fixed in accordance with ACI 318 unless otherwise shown 10 0.617 26 4.170 45 12.500
on Drawings. 12 0.888 28 4.830 50 15.400
7 Welded wire fabric shall be lapped 1.5 mesh 14 1.210 30 5.550
(opening size) plus the extension on the wires unless 16 1.580 32 6.310
otherwise shown on Drawings. Table 5.2.4.1 Reinforcing Bars Weights

5.2.3.4 Concrete Cover 4 No separate measurement is made for bars of


different diameters. The unit rates in the Bill of Quantities
1 Concrete cover to reinforcement shall be as indicated
shall be deemed to cover for all diameters.
on Drawings but shall not be less than the following:
5 Fabric mesh reinforcement is measured separately
i. Concrete exposed to salt water and
by weight based on the theoretical quantity of metric
splash zone 100 mm
tonnes complete in place as shown on the Drawings or
ii. Concrete of all substructure elements cast
placed as ordered by the Engineer. No separate
against earth 100 mm
measurement is made for different mesh sizes or different
iii. Concrete of all substructure elements exposed to
wire diameters. For standard fabric, the weight will be
weather 75 mm
based on the mass in kg/sq.m. listed in Table A.1 of BS
iv. Apron slabs 60 mm
4483.
v. Superstructure cast-in-situ concrete exposed to
weather 60 mm 6 The quantity of steel reinforcing bars and fabric mesh
vi. Interior faces of superstructure cast-in-place reinforcement shall be calculated to the nearest three
concrete except slabs 40 mm decimal places.
vii. Cast-in-situ slabs 30 mm
viii. Precast superstructure elements, exposed 5.2.5 Basis of Payment
surfaces 40 mm
1 The amount of completed and accepted material,
ix. Precast superstructure elements, interior
measured as provided above, will be paid for at the unit
faces 30 mm
rate for reinforcing steel (bar and mesh), in the Bill of
x. Precast parapets, concrete barriers, curbs,
Quantities, which rate shall be full compensation for
etc. 30 mm
supplying, fabricating, transporting, delivering, erecting
2 Cover to reinforcement shall be checked before any and fixing, materials, labor, equipment, tools and other
concrete is cast. The bending of reinforcement at a cold items necessary for the proper completion of the work as
joint is not permitted. Concrete cover shall be checked specified in Sub-Section 5.2.
with a cover meter as soon as formwork is removed.

♦ 5-15 ♦
copy 249
5.2.6 Items in the Bill of Quantities ASTM C 171 Standard Specification for Sheet
Materials for Curing Concrete (AASHTO
i Mild steel bar reinforcement of any
M 171)
diameter t.
ASTM C 219 Standard Terminology Relating to
ii High tensile steel bar reinforcement
Hydraulic Cement
of any diameter t.
ASTM C 309 Standard Specification for Liquid
iii Fabric wire mesh reinforcement of
Membrane-Forming Compounds for
any size t.
Curing Concrete (AASHTO M 148)
ASTM C 881 Standard Specification for Epoxy-Resin-
5.3 Reinforced Concrete Structures Base Bonding Systems for Concrete
ASTM C 920 Standard Specification for Elastomeric
5.3.1 Description
Joint Sealants
5.3.1.1 Definitions ASTM C 1315 Specification for Liquid Membrane –
Forming compounds having Special
1 Forms and Formwork: Temporary works used to give
Properties for Curing and Sealing
the required shape and support to poured concrete,
Concrete
constructed mainly of sheet material, such as wood,
plywood, metal sheet or plastic sheet, in direct contact ASTM C 1059 Specification for Latex Agents for
with the concrete, and joists or stringers to support the Bonding Fresh To Hardened Concrete
sheeting. For bridges it is recommended to use only metal ASTM D 448 Classification for Sizes of Aggregates
sheets. for Road and Bridge Construction
2 Falsework: Temporary structure used to support a ASTM D 1751 Standard Specification for Preformed
permanent concrete structure while it is not self- Expansion Joint Filler for Concrete
supporting. Paving and Structural Construction
3 Scaffold: Temporary structure to provide access, to (AASHTO M213)
work under construction. ASTM D 1752 Specification for Preformed sponge
4 Tower: Composite structure to provide access to high Rubber and Cork Expansion Joint Fillers
work under construction and to carry vertical loading. for Concrete Paving and Structural
Construction (AASHTO M153).
5 Camber: Upward curvature of the formwork,
designed to compensate for subsequent deflection under ASTM D 994 Specification for Preformed Expansion
load. Joint Filler for Concrete (AASHTO M33).
ASTM D 4397 Specification for Polyethylene Sheeting
5.3.1.2 References
for Construction, Industrial, and
1 American Association of State Highway and Agricultural Applications
Transportation Officials (AASHTO): ASTM E 154 Test Methods for Water Vapor
AASHTO M182 Standard Specification for Burlap Cloth Retarders used in Contact with Earth
Made from Jute or Kenaf under Concrete Slabs, on Walls or as
Ground Cover.
2 American Concrete Institute (ACI):
ASTM E 1745 Specification for Plastic Water Vapor
ACI 117 Specifications for Standard Tolerances
Retarders used in Contact with Soil or
for Concrete Construction and Materials
Granular Fill under Concrete Slabs.
ACI 304 Guide for Measuring, Mixing,
4 Corps of Engineers (CE):
Transporting, and Placing Concrete
CE CRD-C300 Curing Compound
ACI 305 Hot Weather Concreting
CE CRD-C513 Rubber Waterstops
ACI 309 Guide for Consolidation of Concrete
CE CRD-C572 PVC Waterstops
ACI 347 Formwork for Concrete
ACI 504R Guide to Joint Sealants for Concrete 5.3.1.3 Submittals
Structures
1 Formwork Shop Drawings: Prepare shop drawings
3 American Society for Testing and Materials (ASTM): for formwork indicating fabrication and erection of forms
ASTM C 33 Specification for Concrete Aggregates for specified finish concrete surface. Show form
ASTM C 109/C109M Test Method for Compressive construction including jointing, especial form joints or
Strength of Hydraulic Cement Mortars reveals, location and pattern of form tie placement.
(Using 2-in. or 50 mm Cube Specimens i. Design of formwork includes design of
ASTM C 150 Standard Specification for Portland falsework, scaffold and towers as defined in
Cement Paragraph 5.3.1.1.

♦ 5-16 ♦
copy 249
ii. Prepare formwork drawings by or under the i. Without prejudice to the Engineer’s rights to
supervision of a qualified professional engineer inspect, approve or reject or suspend any work,
detailing fabrication, assembly, and support of the CQCE shall be authorized to:
formwork. - Postpone concreting operations until
iii. Design and engineering of formwork for outstanding requirements are corrected.
structural stability and efficiency are the
- Reject materials or workmanship that do
Contractor's responsibility.
not conform to this Specification.
iv. Indicate proposed schedule and sequence of
stripping formwork, removing supports and re- - Prevent the use of equipment that could
shoring. cause improper construction relative to
v. If the Contractor intends to use readymade this Specification.
proprietary formwork and falsework, he shall - Stop any work that is not being done in
submit all relevant data, including independent accordance with specified requirements.
test certificates, to enable the Engineer to - Report within 24 hours and provide
determine if the proposals are acceptable. records to and as required by the
Engineer’s review of formwork design is limited Engineer upon discovery of non-
to architectural aspects only and shall not be compliance.
construed as approval of structural or other
3 Implement a Quality Assurance System as specified
matters, all of which are the Contractor’s sole
in Paragraph 5.1.1.4.
responsibility
4 Mockups: Before casting concrete that is exposed to
2 Material Certificates: Signed by manufacturers and
view in the completed structure, cast a mockup for each
Contractor certifying that each of the following items
exposed element to demonstrate typical joints, surface
complies with specified requirements:
finish, texture, color, tolerances, quality of materials and
i. Waterstops. standard of workmanship in the completed work. Where
ii. Curing materials. specified or directed by the Engineer, the mock up shall be
iii. Bonding agents. a trial construction representative of the actual structure
iv. Adhesives. (pier, cross-head, part of deck) in dimensions and all
v. Vapor retarders. details including reinforcement, using the Contractor’s
vi. Epoxy joint filler. proposed construction technique, concrete mix, formwork,
vii. Joint-filler strips. cutting and placing of reinforcement, etc.
viii. Repair materials.
i. Build mockups in the location and of the size
3 Samples: Samples of materials as requested by the indicated or, if not indicated, as directed by the
Engineer, with names, sources, and descriptions, Engineer.
including, but not limited to, the following: ii. Notify the Engineer seven days in advance of
i. Color finishes. dates and times when mockups will be
ii. Reglets. constructed.
iii. Waterstops, reinjectable hosing, water swelling iii. In the presence of the Engineer, damage parts of
gaskets. exposed surfaces as selected by the Engineer,
iv. Vapor retarder/barrier. and demonstrate materials and techniques
v. Form liners. proposed for repairs to match adjacent
vi. Joint fillers. undamaged surfaces.
vii. Sealants. iv. Obtain the Engineer's approval of mockups
before starting cast-in-place concrete elements
5.3.1.4 Quality Assurance exposed to view.
1 Codes and Standards: Comply with the latest edition v. If the Engineer determines that any mockup does
of not meet requirements, demolish and remove
from the site and cast another until the mockup
i. AASHTO LRFD Bridge Construction
is approved.
Specifications.
vi. Maintain mockups during construction in an
ii. ACI Manual of Concrete Practice Parts 1, 2, 3, 4 &
undisturbed condition as a standard for judging
5.
the completed work.
iii. CRSI "Manual of Standard Practice” except
vii. Demolish and remove mockups when directed.
where more stringent requirements are shown
or specified.
5.3.2 Materials
2 Concrete Quality Control Engineer: Appoint a full-
time Concrete Quality Control Engineer (CQCE) as 5.3.2.1 Form Materials
specified in Paragraph 5.1.1.4
1 Forms for Exposed Finish Concrete: Plywood, metal,
metal-framed plywood faced, or other acceptable panel-

♦ 5-17 ♦
copy 249
type materials to provide continuous, straight, smooth, 5.3.2.2 Waterstops
exposed surfaces. Furnish in largest practicable sizes to
minimize number of joints and to conform to joint system 1 Waterstops: Provide flat, dumbbell-type waterstops
shown on Drawings. at construction joints and other joints in accordance with
AASHTO LRFD Bridge Construction Specifications Article
i. Use overlaid plywood complying with U.S.
8.9.2.6 or as specified herein. Waterstops shall be sized to
Product Standard PS-1 "A-C or B-B High Density
suit joints and shall be of the profiles shown on the
Overlaid Concrete Form," Class I.
Drawings or as directed or appropriate for the particular
ii. Use plywood complying with U.S. Product
application. Fittings for angles junctions etc shall be
Standard PS-1 ‘B-B (Concrete Form) Plywood,’
factory formed.
Class I, Exterior Grade or better, mill-oiled and
edge-sealed, with each piece bearing legible i. Flexible Rubber Waterstops: CE CRD-C 513, for
inspection trademark. embedding in concrete to prevent passage of
fluids through joints.
2 Forms for Unexposed Finish Concrete: Plywood,
ii. Flexible PVC Waterstops: CE CRD-C 572, for
lumber, metal, or another acceptable material. Provide
embedding in concrete to prevent passage of
lumber dressed on at least two edges and one side for
fluids through joints.
tight fit.
2 Self-Expanding Strip Waterstops: Proprietory
3 Forms for Textured Finish Concrete: Units of face
rectangular or trapezoidal strip, sodium bentonite or other
design, size, arrangement, and configuration to match the
hydrophylic material for adhesive bonding to concrete.
Engineer's control sample. Provide solid backing and
form supports to ensure stability of textured form liners. 3 Re-injectable Hosing: Proprietary re-injectable hosing
complying with the following requirements:
4 Forms for Cylindrical Columns and Supports: Metal,
glass-fiber-reinforced plastic, or paper or fiber tubes that - The hose shall consist of a hollow PVC core
will produce smooth surfaces without joint indications. with lateral openings covered by neoprene
Provide units with sufficient wall thickness to resist wet valves. The hose shall be laid and injected by
concrete loads without deformation. an approved applicator. in 10 to 12 m lengths
with entry port and vent ends terminating in
5 Pan-Type Forms: Glass-fiber-reinforced plastic or
junction boxes.
formed steel, stiffened to support weight of placed
concrete without deformation. - Joints shall be hydraulically tested to a
pressure at least 2.0 bar higher than the
6 Carton Forms: Biodegradable paper surface, treated
expected local conditions. If the hose fails to
for moisture-resistance, structurally sufficient to support
hold the pressure for 10 minutes, it shall be
weight of plastic concrete and other superimposed loads.
injected with a vinyl ester based flexible resin
7 Form Release Agent: Proprietary form release agent as required to seal the joint and then retested.
with a maximum of 350 g/L volatile organic compounds
(VOCs) that will not bond with, stain, or adversely affect 5.3.2.3 Concrete Curing Cover Sheets
concrete surfaces and will not impair subsequent
1 Vapor retarding sheet materials shall be one of the
treatments of concrete surfaces.
types specified in paragraphs 2 to 5 below or as directed
i. Release agent for steel faced formwork shall by the Engineer.
incorporate rust inhibitor.
2 ASTM E 1745, Class C, of one of the following
8 Form Ties: Factory-fabricated, adjustable-length, materials; or polyethylene sheet 0.25mm thick
removable or snap-off metal form ties designed to prevent
i. Nonwoven, polyester-reinforced, polyethylene
form deflection and to prevent spalling of concrete upon
coated sheet; 0.25 mm thick.
removal. Provide units that leave no embedded metal
ii. Three-ply, nylon- or polyester-cord-reinforced,
closer than 38 mm to the surface of the exposed concrete.
laminated, high-density polyethylene sheet; 0.18
No permanent metallic part shall have less concrete cover
mm thick.
than the reinforcement. Provide ties that, when removed,
will not leave holes larger than 25 mm in diameter in the 3 Vapor retarder: ASTM E 1745, Class B, five-ply,
concrete surface. Provide ties with integral water-barrier nylon- or polyester-cord-reinforced, high-density
plates for walls indicated to receive damp-proofing or polyethylene sheet; 0.25 mm thick.
waterproofing. 4 Vapor retarder: ASTM E 1745, Class A, three-ply,
9 Void Forms: Biodegradable paper surface, treated for nylon- or polyester-cord-reinforced, high-density
moisture resistance structural sufficient to support weight polyethylene sheet; laminated to a nonwoven geotextile
of plastic concrete and other superimposed loads. fabric, 0.76 mm thick.

10 Chamfer Strips: Wood, metal, PVC, or rubber strips of 5 Vapor retarder: 2.8 mm thick, semi-flexible, seven-ply
the size indicated on the Drawings. sheet membrane consisting of reinforced core and carrier
sheet with fortified asphalt layers, protective
weathercoating, and removable plastic release liner.

♦ 5-18 ♦
copy 249
Furnish manufacturer's accessories including bonding 7 Reglets: Fabricated from not less than 0.55 mm thick
asphalt, pointing mastics, and self-adhering joint tape. galvanized steel sheet. Temporarily fill or cover face
i. Water-Vapor Permeance: ASTM E 154. opening of reglet to prevent intrusion of concrete or debris.

ii. Tensile Strength: 24.5 kN/m; ASTM E 154. 8 Dovetail Anchor Slots: Hot-dip galvanized steel sheet,
not less than 0.85 mm thick, with bent tab anchors.
iii. Puncture Resistance: 400 N; ASTM E 154.
Temporarily fill or cover face opening of slots to prevent
6 Absorptive Cover: Burlap cloth made from jute or intrusion of concrete or debris.
kenaf weighing approximately 0.29 kg/sq.m and
complying with AASHTO M182, Class 2. 5.3.2.6 Repair Materials
7 Moisture Retaining Cover: ASTM C 171. polyethylene 1 Repair Underlayment: Cement-based, polymer-
sheet, polyethylene coated burlap or Kraft paper. modified, self-leveling product that can be applied in
thicknesses from 3 mm and that can be feathered at edges
5.3.2.4 Curing Compounds
to match adjacent floor elevations.
1 Curing compounds shall be one of the types i. Cement Binder: ASTM C 150, Portland cement
specified in paragraphs 2 to 6 below, or as directed by the or hydraulic or blended hydraulic cement as
Engineer defined in ASTM C 219.
2 Evaporation Retarder: Waterborne, monomolecular ii. Primer: Product of underlayment manufacturer
film forming, manufactured for application to fresh recommended for substrate, conditions, and
concrete application.
3 Clear, solvent-borne, membrane-forming curing iii. Aggregate: Well-graded, washed gravel, 3 to 6
compound: ASTM C 309, Type 1, Class B. mm or coarse sand as recommended by
4 Clear, waterborne, membrane-forming curing underlayment manufacturer.
compound: ASTM C 309, Type 1, Class B. iv. Compressive Strength: Not less than 30 MPa at
5 Clear, solvent-borne, membrane-forming curing and 28 days when tested according to ASTM C
sealing compound: ASTM C 1315, Type 1, Class A. 109M.
6 Clear, waterborne, membrane-forming curing and 2 Repair Topping: Traffic-bearing, cement-based,
sealing compound: ASTM C 1315, Type 1, Class A. polymer-modified, self-leveling product that can be
applied in thicknesses from 6 mm.
5.3.2.5 Concrete Accessories
i. Cement Binder: ASTM C 150, Portland cement
1 Joint-Filler Strips: ASTM D 1751, asphalt-saturated or hydraulic or blended hydraulic cement as
cellulosic fiber. defined in ASTM C 219.
2 Joint-Filler Strips: ASTM D 1752, cork or self- ii. Primer: Product of topping manufacturer
expanding cork. recommended for substrate, conditions, and
3 Joint-Filler Strips: ASTM D 1751, asphalt-saturated application.
cellulosic fiber, or ASTM D 1752, cork or self-expanding iii. Aggregate: Well-graded, washed gravel, 3 to 6
cork. mm or coarse sand as recommended by
4 Epoxy Joint Filler: Two-component, semi-rigid, 100 topping manufacturer.
percent solids, epoxy resin with a Shore A hardness of 80 iv. Compressive Strength: Not less than 40 MPa at
per ASTM D 2240. 28 days when tested according to ASTM C
5 Bonding Agent: ASTM C 1059, Type II, non- 109M.
redispersible, acrylic emulsion or styrene butadiene.
5.3.3 Construction Requirements
6 Epoxy-Bonding Adhesive: ASTM C 881, two-
component epoxy resin, capable of humid curing and 5.3.3.1 Formwork
bonding to damp surfaces, of class and grade to suit
requirements, and as follows: 1 Design, erect, shore, brace, and maintain formwork,
according to ACI 301, to support vertical, lateral, static,
i. Type II, non-load bearing, for bonding freshly
and dynamic loads, and construction loads that might be
mixed concrete to hardened concrete.
applied, until concrete structure can support such loads.
ii. Types I and II, non-load bearing, for bonding Design of formwork shall be the sole responsibility of the
hardened or freshly mixed concrete to Contractor.
hardened concrete.
2 Construct formwork so that concrete members and
iii. Types IV and V, load bearing, for bonding structures are of size, shape, alignment, elevation, and
hardened or freshly mixed concrete to position indicated, within tolerance limits of ACI 117.
hardened concrete.
3 Limit concrete surface irregularities, designated by
ACI 347R as abrupt or gradual, as follows:
i. Class A, 4 mm.

♦ 5-19 ♦
copy 249
ii. Class B, 6 mm. load. Falsework shall not be supported on any part of the
iii. Class C, 10 mm. structure, except the footings, without the written
permission of the Engineer. The number and spacing of
iv. Class D, 25 mm.
falsework columns, the adequacy of sills, caps and
4 Construct forms rigid and tight enough to prevent stringers and the amount of bracing in the falsework
loss of concrete mortar. framing shall be subject to approval of the Engineer.
5 Fabricate forms for easy removal without hammering 2 Timber for falsework shall be sound, in good
or prising against concrete surfaces. Provide crush or condition and free from defects that might impair its
wrecking plates where stripping may damage cast strength. If the vertical members are of insufficient length
concrete surfaces. Provide top forms for inclined surfaces to cap at the desired elevation for the horizontal members,
steeper than 1.5 horizontal to 1 vertical. Kerf wood inserts they shall preferably be capped and frames constructed to
for forming keyways, reglets, recesses, and the like, for the proper elevation. Ends of the vertical members shall
easy removal. be cut square for full bearing to preclude the use of
i. Do not use rust-stained steel form-facing wedges. If vertical splices are necessary, the abutting
material. members shall be of the same approximate size, the ends
6 Set edge forms, bulkheads, and intermediate screed shall be cut square for full bearing, and the splices shall be
strips for slabs to achieve required elevations and slopes scabbed in a manner approved by the Engineer.
in finished concrete surfaces. Provide and secure units to 3 The Contractor shall compute falsework settlement
support screed strips; use strike-off templates or and deflection for bridges so that when the final
compacting-type screeds. settlement is complete, the structure will conform to the
7 Provide temporary openings for cleanouts and required camber, section and grade as shown on the
inspection ports where interior area of formwork is Drawings.
inaccessible. Close openings with panels tightly fitted to 4 The Contractor shall provide means for accurately
forms and securely braced to prevent loss of concrete measuring settlement in falsework during placement of
mortar. Locate temporary openings in forms at concrete, and shall provide a competent observer to
inconspicuous locations. observe and correct the settlement.
8 Chamfer exterior corners and edges of concrete 5 Screw jacks, if used, shall be designed for use with a
receiving applied waterproofing membranes. slenderness ratio not exceeding 60. The slenderness ratio
9 Unless otherwise indicated, provide 20x20 mm shall be taken as the ratio of the clear distance between
chamfer on all exposed corners and edges of concrete. effective bracing in both horizontal directions to the
diameter of the screw jack measured at the root of the
10 Form openings, chases, offsets, recesses, keyways,
thread. The manufacturers' certificate showing the
grooves, blocking, screeds, and bulkheads required in the
ultimate load capacity of the screw jack shall be submitted
work.
with the design calculations for the falsework. If directed
11 Clean forms and adjacent surfaces to receive by the Engineer, the Contractor shall furnish a test
concrete. Remove chips, wood, sawdust, dirt, and other certificate carried out at an approved independent
debris just before placing concrete. laboratory.
12 Retighten forms and bracing before placing concrete, 6 Props and towers supporting forms or partially
to prevent mortar leaks and maintain proper alignment. completed structures shall be interconnected in plan
13 Coat contact surfaces of forms with specified form orthogonally at levels to be determined in the design.
release agent approved by the Engineer, according to the They shall also be interconnected by diagonal bracings in
manufacturer's written instructions, before placing orthogonal vertical planes.
reinforcement Petrol oil may be used. 7 If the concrete is required to be post-tensioned in the
14 Where it is required to use internal ties and spacers, field, the falsework shall be designed to support any
their type, spacing and use shall be to the approval of the increased or readjusted loads caused by the prestressing
Engineer. In no circumstances shall these ties protrude out forces.
of the finished concrete, all ties must be cut back into the
5.3.3.3 Embedded Items
structural concrete and the surface made good to satisfy
the requirements of the minimum spacing and cover. 1 Place and secure anchorage devices and other
embedded items required for adjoining work that is
5.3.3.2 Falsework
attached to or supported by cast-in-place concrete. Follow
1 Falsework and centering shall be designed to provide templates, diagrams, instructions, and directions
the necessary rigidity to support all vertical and horizontal furnished with items to be embedded.
loads placed upon it without settlement or deformation in
5.3.3.4 Removing and Reusing Forms
excess of the permissible tolerance for the structure given
in the Specifications. Falsework columns shall be 1 General: Formwork, for sides of beams, walls,
supported on hardwood, concrete pads or metal bases if columns, and similar parts of the work, that does not
the underlying ground is liable to sink under the column

♦ 5-20 ♦
copy 249
support weight of concrete may be removed after 5.3.3.6 Construction Joints
cumulatively curing at not less than 10 deg.C for 24 hours
after placing concrete provided concrete is hard enough to 1 Follow the requirements of AASHTO LRFD Bridge
not be damaged by form-removal operations and Construction Specifications Sub-Section 8.8 as
provided curing and protection operations are maintained. complemented herein.

2 The Engineer shall be notified when the Contractor 2 Construct joints true to line with faces perpendicular
intends to remove any formwork at least 6 hours in to surface plane of concrete.
advance 3 Construction joints shall be made only where
i. Leave formwork, for beam soffits, joists, slabs, specified in the contract documents, or shown in the
and other structural elements that supports pouring schedule, unless otherwise approved by the
weight of concrete in place until concrete has Engineer.
achieved: At least 70 percent of 28-day design 4 Unless otherwise specified in the contract documents,
compressive strength but not less than 7 days horizontal joints may be made without keys, and vertical
after casting. joints shall be constructed with shear keys in accordance
ii. Determine compressive strength of in-place with AASHTO LRFD Bridge Construction Specifications
concrete by testing representative field- or Article 8.8.2.
laboratory-cured test specimens according to 5 All construction joints shall be cleaned of surface
ACI 301. laitance, curing compound, and other foreign materials
iii. Remove forms only if shores have been before fresh concrete is placed against the surface of the
arranged to permit removal of forms without joint. Abrasive blast or other approved methods shall be
loosening or disturbing shores. used to clean horizontal construction joints to the extent
that clean aggregate is exposed. All construction joints
3 Clean and repair surfaces of forms to be reused in
shall be flushed with water and allowed to dry to a surface
the work. Split, frayed, delaminated, or otherwise
dry condition immediately prior to placing concrete.
damaged form-facing material will not be acceptable for
exposed surfaces. Apply new form release agent. 6 Bonding and doweling to existing structures shall be
as specified in AASHTO LRFD Bridge Construction
When forms are reused, clean surfaces, remove fins and
Specifications Article 8.8.3.
laitance, and tighten to close joints. Align and secure
joints to avoid offsets. Do not use patched forms for 7 The use of expanded metal or other perforated
exposed concrete surfaces unless approved by the material is prohibited in construction joints.
Engineer. 8 Place construction joints perpendicular to main
reinforcement. Continue reinforcement across
5.3.3.5 Vapor Retarders construction joints except as indicated otherwise. Do not
1 Vapor Retarder: Place, protect, and repair vapor continue reinforcement through sides of strip placements.
retarder sheets according to ASTM E 1643 and 9 Where needed, unscheduled, construction joints shall
manufacturer's written instructions. Cover with fine be placed as directed by the Engineer and, if directed,
graded granular material or fill as specified in paragraphs additional reinforcement steel dowels shall be placed
2 or 3 below. across the joint. Such additional steel shall be furnished
2 Fine-Graded Granular Material: Cover vapor retarder and placed at the Contractor’s expense.
with fine-graded granular material, moisten, and compact 10 Space vertical joints in walls as indicated, or as
with mechanical equipment to elevation tolerances of plus required by the Engineer.
0 mm or minus 20 mm. 11 Use a bonding agent at locations where fresh
3 Granular Fill: Cover vapor retarder with granular fill, concrete is placed against hardened or partially hardened
moisten, and compact with mechanical equipment to concrete surfaces.
elevation tolerances of plus 0 mm or minus 20 mm. 12 Use epoxy-bonding adhesive at locations where
i. Place and compact a 15 mm thick layer of fine- fresh concrete is placed against hardened or partially
graded granular material over granular fill. hardened concrete surfaces.
4 Place vapor retarder/barrier sheeting in position with 13 Waterstops/Re-injectable Hoses: Provide waterstops
longest dimension parallel with direction of pour. or re-injectable hoses in construction joints as indicated.
Lap joints 150 mm and seal with manufacturer's Install waterstops to form a continuous diaphragm in each
recommended mastic or pressure-sensitive tape. Cover joint. Support and protect exposed waterstops during
vapor retarder/barrier with sand cushion and compact to progress of work. .
depth indicated.
5.3.3.7 Contraction and Expansion Joints

1 Follow the requirements of AASHTO LRFD Bridge


Construction Specifications Sub-section 8.9 as
complemented herein.

♦ 5-21 ♦
copy 249
2 Expansion and contraction joints shall be constructed iii. Polyethylene foam strip, for use when shown
at the locations and in accordance with the details in the contract documents, shall be of
specified in the contract documents. Such joints include commercial quality with a continuous,
open joints, filled joints, joints sealed with sealants or impervious, glazed top surface, suitable for
waterstops, and joints with combinations of these features. retaining the liquid sealant at the proper
3 Contraction Joints in Slabs-on-Grade: Form elevation in the joint while hardening.
weakened-plane contraction joints, sectioning concrete
5.3.3.8 Waterstops
into areas as indicated. Construct contraction joints for a
depth equal to at least one-fourth of concrete thickness, as 1 Install waterstops in accordance with AASHTO LRFD
follows: Bridge Construction Specifications Sub-section 8.9.3.4.
i. Grooved Joints: Form contraction joints after 2 Flexible Waterstops: Install in construction joints as
initial floating by grooving and finishing each indicated to form a continuous diaphragm. Install in
edge of joint to a radius of 3 mm. Repeat longest lengths practicable. Support and protect exposed
grooving of contraction joints after applying waterstops during progress of work.
surface finishes. Eliminate groover tool marks 3 Self-Expanding Strip Waterstops: Install in
on concrete surfaces. construction joints and at other locations indicated,
ii Sawed Joints: Form contraction joints with according to manufacturer's written instructions, bonding
power saws equipped with shatterproof or mechanically fastening and firmly pressing into place.
abrasive or diamond-rimmed blades. Cut 3 Install in longest lengths practicable.
mm wide joints into concrete when cutting
action will not tear, abrade, or otherwise 5.3.3.9 Concrete Placement
damage surface and before concrete develops
1 General: Comply with AASHTO LRFD Bridge
random contraction cracks.
Construction Specifications Sub-sections 8.6 and 8.7 as
4 Isolation Joints in slabs-on-grade: After removing complemented herein for protection from environmental
formwork, install joint-filler strips at slab junctions with conditions during placing and curing and for handling and
vertical surfaces, such as column pedestals, foundation placement of concrete.
walls, grade beams, and other locations, as indicated.
2 Concrete shall be handled, placed, and consolidated
i. Extend joint-filler strips full width and depth of by methods that will not cause segregation of the mix and
joint, terminating flush with finished concrete will result in a dense homogeneous concrete that is free of
surface, unless otherwise indicated. voids and rock pockets. The methods used shall not cause
ii. Terminate full-width joint-filler strips not less displacement of reinforcing steel or other materials to be
than 12 mm or more than 25 mm below embedded in the concrete. Concrete shall be placed and
finished concrete surface where joint sealants, consolidated prior to initial set and in no case more than
are indicated. 1.5 hours after the water was added to the mix. Concrete
iii. Install joint-filler strips in lengths as long as shall not be re-tempered.
practicable. Where more than one length is 3 Inspection: Before placing concrete, inspect and
required, lace or clip sections together. complete formwork installation, reinforcing steel, and
5 Dowel Joints: Install dowel sleeves and dowels or items to be embedded or cast in. Notify other trades to
dowel bar and support assemblies at joints where permit installation of their work. Concrete shall not be
indicated. placed until the condition of the reinforcement, other
embedded items, and the formwork has been inspected
i. Use dowel sleeves or lubricate or asphalt-coat
and approved by the Engineer. All mortar from previous
one-half of dowel length to prevent concrete
placements, debris, and foreign material shall be removed
bonding to one side of joint.
from the forms and steel prior to commencing placement.
6 Pourable sealants for placement along top edges of The forms and subgrade shall be thoroughly moistened
contraction or filled expansion joints shall be one of the with water immediately before concrete is placed against
following: them. Temporary form spreader devices may be left in
i. Hot-poured sealants shall conform to ASTM D place until concrete placement precludes their need, after
3406 (AASHTO M 282), except when the which they shall be removed.
sealant will be in contact with asphaltic 4 Transportation: Concrete, after being discharged
material, it shall conform to AASHTO M 301. from the mixer, shall be transported as rapidly as possible
ii. Cold-poured sealant shall be silicone type, as to its final position in the Work by agitator trucks, which
specified in AASHTO LRFD Bridge Construction shall prevent adulteration, segregation, loss of workability
Specifications Article 8.9.2.4. The sealant shall or contamination of the ingredients. The containers that
be a one-part, low-modulus silicone rubber convey the concrete shall be kept clean and free from
type with an ultimate elongation of 1200 hardened or partially hardened concrete.
percent.

♦ 5-22 ♦
copy 249
i. The addition of water at the point of discharge i. Concrete for T-beam or deck girder spans
is prohibited and trucks shall have the water whose depth is less than 1200 mm may be
tank completely disconnected from the drum. placed in one continuous operation or may be
ii. The use of chutes, spouts, skips and pumps placed in two separate operations; first, to the
shall be permitted if approval is obtained. top of the girder stems, and second, to
Under no circumstances shall any aluminum completion. For T-beam or deck girder spans
pipe or other conveying equipment containing whose depth is 1200 mm or more, and unless
aluminum be allowed to contact fresh concrete the falsework is non-yielding, such concrete
when it is conveyed to its point of placement. shall be placed in two operations, and at least
five days shall elapse after placement of stems
iii. Method of pouring and pouring sequence shall
before the top deck slab is placed.
be submitted by the Contractor to the
Engineer’s approval. ii. Concrete for box girders may be placed in two
or three separate operations consisting of
5 Concrete exposed to salt or brackish water shall
bottom slab, girder stems, and top slab. In
follow the requirements of AASHTO LRFD Bridge
either case, the bottom slab shall be placed
Construction Specifications Sub-section 8.6.6.
first and, unless otherwise permitted by the
6 Do not add water to concrete during delivery, at Engineer, the top slab shall not be placed until
Project site, or during placement, unless approved by the the girder stems have been in place for at least
Engineer. five days.
7 Placement of concrete for each section of the 12 Placement of Box Culverts: In general, the base slab
structure shall be done continuously without interruption or footings of box culverts shall be placed and allowed to
between planned construction or expansion joints. The set before the remainder of the culvert is constructed. For
delivery rate, placing sequence, and methods shall be culverts whose wall height is 1500 mm or less, the
such that fresh concrete is always placed and consolidated sidewalls and top slab may be placed in one continuous
against previously placed concrete before initial set has operation. For higher culvert walls, the requirements for
occurred in the previously placed concrete. vertical members shall apply.
8 During and after placement of concrete, care shall be 13 Placement of Precast Elements: The sequence of
taken not to damage the concrete or break the bond with placement for concrete in precast elements shall be such
reinforcing steel. Workers shall not walk in fresh concrete. that sound, well-consolidated concrete that is free of
Platforms for workers and equipment shall not be settlement or shrinkage cracks is produced throughout the
supported directly on any reinforcing steel. Once the member.
concrete is set, forces shall not be applied to the forms or
14 Placing Methods: Concrete shall be placed as nearly
to reinforcing bars which project from the concrete until
as possible in its final position, and the use of vibrators for
the concrete is of sufficient strength to resist damage.
extensive shifting of the weight (mass) of fresh concrete
9 Sequence of Placement: Whenever a concrete will not be permitted.
placement plan or schedule is specified or approved, the
i. Concrete shall be placed in horizontal layers of
sequence of placement shall conform to the plan.
a thickness not exceeding the capacity of the
10 Placement of Vertical Members: Concrete for vibrator to consolidate the concrete and merge
columns, substructure and culvert walls, and other similar it with the previous lift. In no case shall the
vertical members shall be placed and allowed to set and depth of a lift exceed 600 mm. The rate of
settle for a period of time before concrete for integral concrete placement shall not exceed that
horizontal members, such as caps, slabs, or footings, is assumed for the design of the forms as
placed. Such period shall be adequate to allow completion corrected for the actual temperature of the
of settlement due to loss of bleed water and shall be not concrete being placed.
less than 12 h for vertical members over 4500 mm in
ii. When placing operations would involve
height and not less than 30 min for members over 1500
dropping the concrete more than 1500 mm, the
mm but not over 4500 mm in height. When friction collars
concrete shall be dropped through a tube fitted
or falsework brackets are mounted on such vertical
with a hopper head or through other approved
members and unless otherwise approved, the vertical
devices, as necessary to prevent segregation of
member shall have been in place at least seven days and
the mix and spattering of mortar on steel and
shall have attained its specified strength before loads from
forms above the elevation of the lift being
horizontal members are applied
placed.
11 Placement of Superstructure: Unless otherwise
15 Equipment:
permitted, no concrete shall be placed in the
superstructure until substructure forms have been i. All equipment used to place concrete shall be
stripped sufficiently to determine the character of the of adequate capacity and designed and
supporting substructure concrete. operated so as to prevent segregation of the
mix or loss of mortar. Such equipment shall

♦ 5-23 ♦
copy 249
not cause vibrations that might damage the degree that the concrete ceases to be plastic
freshly placed concrete. No equipment shall under vibration. Vibrators shall not be used to
have aluminum parts which come in contact transport concrete in the forms.
with the concrete. Between uses, the mortar vii. Vibration shall be supplemented by such
coating inside of placing equipment which sets spading as is necessary to ensure smooth
or dries out shall be cleaned from the surfaces and dense concrete along form
equipment before use is resumed. surfaces and in corners and locations
ii. Chutes shall be lined with smooth watertight impossible to reach with the vibrators.
material and, when steep slopes are involved, viii. When approved by the Engineer, concrete for
shall be equipped with baffles or reverses. small noncritical elements may be consolidated
iii. Concrete pumps shall be operated such that a by the use of suitable rods and spades.
continuous stream of concrete without air 17 Underwater Concreting:
pockets is produced. When pumping is
i. Only concrete used in cofferdams to seal out
completed, the concrete remaining in the
water may be placed under water, unless
pipeline, if it is to be used, shall be ejected in
otherwise specified in the contract documents
such a manner that there will be no
or specifically approved by the Engineer.
contamination of the concrete or separation of
the ingredients. ii. If other than concrete class 50 or 60 is to be
placed under water, the minimum cement
16 Consolidation:
content of the mix shall be increased by ten
i. All concrete, except concrete placed under percent to compensate for loss due to wash.
water and concrete otherwise exempt, shall be
iii. A tremie shall consist of a watertight tube
consolidated by mechanical vibration
having a diameter of not less than 250 mm and
immediately after placement.
fitted with a hopper at the top. The tremies
ii. Except as noted herein, vibration shall be shall be supported so as to permit free
internal. External form vibrators may be used movement of the discharge end over the entire
for thin sections when the forms have been top surface of the work and so as to permit
designed for external vibration. rapid lowering when necessary to retard or
iii. Vibrators shall be of approved type and design stop the flow of concrete. The discharge end
and of a size appropriate for the work. They shall be sealed closed at the start of work so as
shall be capable of transmitting vibration to the to prevent water from entering the tube before
concrete at frequencies of not less than 75 Hz. the tube is filled with concrete.
iv. The Contractor shall provide a sufficient iv. After placement has started, the tremie shall be
number of vibrators to properly compact each kept full of concrete to the bottom of the
batch of concrete immediately after it is placed hopper. If water enters the tube after
in the forms. The Contractor shall also have at placement is started, the tremie shall be
least one spare vibrator immediately available withdrawn, the discharge end resealed, and the
in case of breakdown. placement restarted.
v. Vibrators shall be manipulated so as to v. When a batch is dumped into the hopper, the
thoroughly work the concrete around the flow of concrete shall be induced by slightly
reinforcement and embedded fixtures and into raising the discharge end, always keeping it in
the corners and angles of the forms. Vibration the deposited concrete. The flow shall be
shall be applied at the point of deposit and in continuous until the work is completed. When
the area of freshly deposited concrete. The cofferdam struts prevent lateral movement of
vibrators shall be inserted and withdrawn out tremies, one tremie shall be used in each bay.
of the concrete slowly. The vibration shall be of vi. Concrete pumps used to place concrete under
sufficient duration and intensity to thoroughly water shall include a device at the end of the
consolidate the concrete but shall not be discharge tube to seal out water while the tube
continued so as to cause segregation. Vibration is first being filled with concrete. Once the flow
shall not be continued at any one point to the of concrete is started, the end of the discharge
extent that localized areas of grout are formed. tube shall be kept full of concrete and below
Application of vibrators shall be at points the surface of the deposited concrete until
uniformly spaced and not farther apart than 1.5 placement is completed.
times the radius over which the vibration is
visibly effective. 5.3.3.10 Hot-Weather Concreting
vi. Vibration shall not be applied either directly to, 1 When hot weather conditions exist that would impair
or through the reinforcement, or to sections or quality and strength of concrete, place concrete complying
layers of concrete which have hardened to the with ACI 305 and as specified.

♦ 5-24 ♦
copy 249
2 Cool ingredients before mixing to maintain concrete Hand-finishing methods may be used if
temperature at time of placement to below 25 deg.C. approved by the Engineer for short bridges 15
Mixing water may be chilled or chopped ice may be used m or less in length or for irregular areas where
to control temperature, provided water equivalent of ice is the use of a machine would be impractical.
calculated to total amount of mixing water. ii. Straightedging, Sub-section 8.10.2.2.
3 Concrete temperature shall not exceed 32 degree C iii. Texturing, Sub-section 8.10.2.3
and the temperature differential shall not exceed 25
iv. Surface testing and correction, Sub-section
degree C.
8.10.2.4.
4 No concreting operation shall be carried out at
3 Pedestrian Walkway Surface Finish: comply with
ambient temperature of 40 deg. C or more.
AASHTO LRFD Bridge Construction Specifications Sub-
5 For bridge decks that are located over or adjacent to section 8.10.3.
salt water the maximum temperature of the concrete at
4 Troweled and Brushed Finish: comply with AASHTO
time of placement shall be 27 deg. C.
LRFD Bridge Construction Specifications Sub-section
6 Cover reinforcing steel with water-soaked burlap if it 8.10.4.
becomes too hot, so that steel temperature will not exceed
5 Surface under Bearings: comply with AASHTO LRFD
the ambient air temperature immediately before
Bridge Construction Specifications Sub-section 8.10.5.
embedding in concrete.
7 Fog spray forms, reinforcing steel, and subgrade just 5.3.3.12 Curing Concrete
before placing concrete. Keep subgrade moisture uniform
1 All newly placed concrete shall be cured so as to
without puddles or dry areas.
prevent loss of water by use of one or more of the
8 Use water-reducing retarding admixture when
methods specified in AASHTO LRFD Bridge Construction
required by high temperatures, low humidity, or other
Specifications Sub-section 8.11. Unless otherwise
adverse placing conditions, as acceptable to the Engineer.
specified in the contract documents, curing shall
9 Shade mixing plant and trucks, aggregates, water commence immediately after the free water has left the
tank, and cement silo. surface and finishing operations are completed. If the
10 Paint the mixing plant, trucks, water tank, and surface of the concrete begins to dry before the selected
cement silo with white or reflective paint curing method can be applied, the surface of the concrete
11 Insulate the water tank and supply piping. shall be kept moist by a fog spray applied so as not to
damage the surface.
12 Protect concrete during pouring, and formwork, from
direct sunlight by use of shades and keep shades in 2 Curing shall continue uninterrupted for seven days
position for 7 days from time of pouring, . except for when pozzolans in excess of ten percent, by
weight (mass), of the Portland cement are used in the mix.
13 Concrete placing shall be completed as quickly as
When such pozzolans are used, the curing period shall be
possible to reduce transit time.
ten days.
14 Curing of exposed concrete shall be immediately
3 For other than top slabs of structures serving as
carried out.
finished pavements, the above curing periods may be
5.3.3.11 Finishing Plastic Concrete reduced and curing terminated when test cylinders cured
under the same conditions as the structure indicate that
1 General: Unless otherwise specified in the contract concrete strengths of at least 70 percent of that specified
documents, after concrete has been consolidated and have been reached but not in any case less than 3 days.
prior to the application of cure, all surfaces of concrete
4 When directed by the Engineer during periods of hot
that are not placed against forms shall be struck-off to the
weather, water shall be applied to concrete surfaces being
planned elevation or slope and the surface finished by
cured by the liquid membrane method or by the forms-in-
floating with a wooden float sufficiently to seal the surface.
place method, until the Engineer determines that a cooling
While the concrete is still in a workable state, all
effect is no longer required. Such application of water will
construction and expansion joints shall be carefully tooled
be paid for as extra work.
with an edger. Joint filler shall be left exposed.
5 Methods:
2 Roadway Surface Finish: All bridge decks, approach
slabs, and other concrete surfaces for use by traffic shall i. Forms-in Place Method: Formed surfaces of
be finished to a smooth skid-resistant surface in concrete may be cured by retaining the forms
accordance with AASHTO LRFD Bridge Construction in place for the required time without
Specifications Sub-section 8.10.2 for the following loosening.
sequence of operations: ii. Water Method: Concrete surface shall be kept
i. Striking-off and floating, Article 8.10.2.1. Bridge continuously wet by ponding, spraying, or
decks or top slabs of structures serving as covering with absorptive materials that are
finished pavements shall be finished using kept continuously and thoroughly wet.
approved power-driven finishing machines.

♦ 5-25 ♦
copy 249
iii. Liquid Membrane Curing Compound Method: as fins and surface discoloration shall, however, be made
The liquid membrane method shall not be good as and when required by the Engineer,
used on surfaces where a rubbed finish is 4 Class F4. No special requirements. To be used in the
required or on surfaces of construction joints earth-face or below ground structures if no waterproofing
unless it is removed by sand blasting prior to membrane will be applied.
placement of concrete against the joint. Type 2,
5 Permanently exposed concrete surfaces to classes F1,
white pigmented, liquid membranes may be
F2 and F3 finish shall be protected from rust marks and
used only on the surfaces of bridge decks, on
stains of all kinds. Internal ties and embedded metal parts
surfaces that will not be exposed to view in the
will not be permitted.
completed work, or on surfaces where their
use has been approved by the Engineer. 5.3.3.14 Tolerances
Details of the application are set in AASHTO
LRFD Bridge Construction Specifications Sub- 1 In-Situ Construction
section 8.11.3.3. i. Length: The horizontal and vertical dimensions
iv. Waterproof Cover Method: This method shall of in-situ concrete members, but not cross-
consist of covering the surface with a sections, shall be within the following
waterproof sheet material so as to prevent tolerances:
moisture loss from the concrete. This method Length (mm) Tolerance (mm)
may be used only when the covering can be Up to 3000 ±3
secured adequately to prevent
3001-4500 ±6
moisture loss. Details of the application are set
in AASHTO LRFD Bridge Construction Vertical lines out of plane ± 5 + (1 for every 3000 out
Specifications Sub-section 8.11.3.4. of true line)
v. Steam or Radiant-Heat Curing Method: This ii. Cross-Section: Slab and wall thicknesses and
method may be used only for precast concrete the cross-sectional dimensions of beams,
members manufactured in established plants. columns, piers etc., shall be within the
Details of the application are set in AASHTO following tolerances:
LRFD Bridge Construction Specifications Sub- Member Dimensions (mm) Tolerance (mm)
section 8.11.3.5. Up to 500 ±6
6 Bridge Decks: The top surfaces of bridge decks shall 501-750 ± 10
be cured by a combination of the liquid membrane curing
Additional for every subsequent
compound method and the water method. The liquid
100 mm ± 1 mm
membrane shall be Type 2, white pigmented, and shall be
applied from finishing bridges progressively and 2 Precast Construction
immediately after finishing operations are complete on i. Length: The horizontal and vertical dimensions
each portion of the deck. The water cure shall be applied of members, but not cross-sections, shall be
not later than 4 h after completion of deck finishing or, for within the following tolerances:
portions of the decks on which finishing is completed.
Length (mm) Tolerance (mm)
5.3.3.13 Formed Finishes Up to 3000 ±2
3000 and over ±5
1 Class F1. This class of surface finish denotes a
special finish required from aesthetic considerations as ii. Cross-Section: Slab and wall thicknesses and
stated in the Special Specification. the cross-sectional dimensions of beams,
columns, piers etc., shall be within the
2 Class F2. Formwork shall be lined with a material
following tolerances:
approved by the Engineer to provide a smooth finish of
uniform appearance. This material shall leave no stain on Member Dimensions (mm) Tolerance (mm)
the concrete and shall be so joined and fixed to its backing Up to 500 ±6
so that it imparts no blemishes. It shall be of the same
501-750 ±9
type and obtained from only one source for any one
structure. The Contractor shall make good any Additional for every subsequent
imperfections in the finish as directed by the Engineer. 250 mm ± 3 mm
Internal ties and embedded metal parts will not be 3 Squareness: For in-situ and precast construction the
permitted unless otherwise approved by the Engineer. tolerance between the short side and the long side shall
3 Class F3. Irregularities in the finish shall be no be within the following limits:
greater than those resulting from the use of wrought thick Member Size (mm) Tolerance (mm)
square edged boards arranged in a uniform pattern. The Up to 3000 ±3
finish is intended to be left as struck. Imperfections such
3000 and over ±6

♦ 5-26 ♦
copy 249
4 Straightness: For in-situ and precast construction the 3 Pretensioning: The process when the prestressing
straightness or bow, defined as deviation from the steel is tensioned against independent anchorages before
intended line, shall be within the following tolerances: the concrete is placed round it. The prestressing strand or
Member Length (mm) Tolerances (mm) tendons are stressed prior to casting the concrete. After
the concrete has attained the required strength, the
Up to 3000 ±3
prestressing force is released from the external
3000 and over ±6 anchorages and transferred, by bond, into the concrete.
5 Alignment: The alignment of members shall be 4 Combined Method: Part of the reinforcement is
within the following tolerances: pretensioned and part post-tensioned.
Columns and piers. : 1:400 of column or pier 5 Cable and Tendon: Cable and tendon both refer to a
length. bundle of prestressing steel of the same type and size
Others. : 1:600 of length bundled together to be contained within a duct and
6 Flatness: The flatness of a surface, measured with a stressed, individually or collectively, from the same
straight edge of 1.5 meter, shall be not greater than 6 mm anchorage.
at any point. 6 Prestressing System: A proprietary system of
7 Twist: Twist, measured as the deviations of any applying prestress and includes anchorages, couplers and
corner from the plane containing the other three corners, jacks but does not necessarily include prestressing steel
shall be within the following limits: and cable ducts.
Member Length (mm) Tolerance (mm)
5.4.1.3 References
Up to 6000 ± 6
1 American Association of State Highway and
Above 6000 ± 12
Transportation Officials (AASHTO):
AASHTO 2008 AASHTO LRFD Bridge Construction
5.3.4 Method of Measurement, Basis of
Specifications, 2nd Edition, 2004, 2008
Payment and Bill of Quantities
Interim Revisions.
1 No separate items are measured or included in the AASHTO 2008 AASHTO LRFD Bridge Design
Bill of Quantities for any part of Sub-section 5.3 and no specifications, 3rd Edition, 2004, 2008
separate payment will be made therefore. The costs are Interim Revisions.
deemed to be covered in the rates and prices in the Bill of
AASHTO 1999 Guide Specifications for Design and
Quantities for Sub-sections 5.1 and 5.2.
Construction of Segmental Concrete
Bridges, 2nd Edition.
5.4 Prestressed Concrete Structures
2 American Society for Testing and Materials (ASTM):

5.4.1 Description ASTM A 416/A 416 M Specification for Steel Strand,


Uncoated Seven-Wire for Prestressed
5.4.1.1 Scope Concrete (AASHTO M 203).

1 This Sub-section specifies the requirements for ASTM A 421/A 421 M Specification for Uncoated
prestressing precast or cast-in-situ concrete by furnishing, Stress-Relieved Steel wire for
placing, and tensioning of prestressing steel. It includes Prestressed Concrete (AASHTO M 204).
prestressing by either the pre-tensioning or post- ASTM A 722/ A 722 M Specification for Uncoated
tensioning methods or by a combination of these methods. High-Strength Steel Bars for
2 This work includes furnishing and installation of any Prestressing Concrete (AASHTO M 275).
appurtenant items necessary for the particular ASTM C 939 Test Method for Flow of Grout for
prestressing system to be used, including but not limited Preplaced-Aggregate Concrete (Flow
to ducts, anchorage assemblies, and grout used for Cone Method).
pressure grouting ducts. ASTM C940 Test Method for Expansion and
Bleeding of Freshly Mixed Grouts for
5.4.1.2 Definitions
Preplaced-Aggregate Concrete in the
1 Prestressing Steel: Steel wire, strand or bars used for Laboratory.
prestressing of concrete. ASTM C1202 Test Method for Electrical Indication of
2 Post-Tensioning: The process when the prestressing concrete’s Ability to Resist Chloride Ion
steel is tensioned after the concrete has hardened. The Penetration (AASHTO T 277)
tendons are installed in voids or ducts within the concrete 3 British Standards:
and are stressed and anchored against the concrete after
BS4447 Specification for the Performance of
the development of the required concrete strength. As a
Prestressing Anchorages for Post-
final operation under this method, the voids or ducts are
Tensioned Construction
pressure-grouted.

♦ 5-27 ♦
copy 249
BS EN 5896 Specification for High Tensile Steel Engineer and correction by the Contractor of
Wire and Strand for the Prestressing of the drawings without delaying the work.
Concrete. iv. Shop drawings for post-tensioning and other
embedments, such as expansion joints,
5.4.1.4 Submittals
bearings, and anchor bolts submitted by
1 Design: suppliers shall be reviewed and approved by
i. Where the design for the prestressing work is the Engineer for conformance with the design
not fully detailed in the contract documents, concept and compliance with the design
the Contractor shall determine the details or drawings and Specifications.
type of prestressing system for use and select v. Where contract-document information on post-
materials and details conforming to this tensioning systems is modified by the
Specification as needed to satisfy the Contractor, or where contract drawings do not
prestressing requirements specified. The provide detailed dimensional information on
system selected shall provide the magnitude the post-tensioning system, it is the
and distribution of pre-stressing force and Contractor's responsibility to coordinate the
ultimate strength required by the contract placement of the post-tensioning system with
documents without exceeding allowable other embedments, and to correct any
temporary stresses. interferences created by the Contractor-
ii. Unless otherwise shown in the contract supplied prestressing system or other
documents, all design procedures, coefficients substitutions. The post-tensioning layout shall
and allowable stresses, friction, and prestress govern the layout of the secondary
losses, as well as tendon spacing and nonprestressed reinforcement. Where
clearances, shall be in accordance with either necessary, location of nonpre-stressed
or both the AASHTO LRFD Bridge Design reinforcement should be adjusted to clear
Specifications. tendons, subject to the approval of the
Engineer.
2 Working Drawings and Shop Drawings
3 Integrated Drawings: Where required by the contract
i. Where the contract documents do not include
documents, in addition to all required working drawings,
complete details for a prestressing system and
the Contractor shall prepare composite placing drawings
its method of installation, or where complete
to scale and in sufficient detail to show the relative
details are provided in the contract documents
positions of all items that are to be embedded in the
and the Contractor wishes to propose any
concrete, and their embedment depth, for the portions of
change, the Contractor shall prepare and
the structure that are to be prestressed. Such embedded
submit to the Engineer working drawings of
items shall include the prestressing ducts, vents,
the prestressing system proposed for use.
anchorage reinforcement and hardware, reinforcing steel,
Fabrication or installation of prestressing
anchor bolts, earthquake restrainers, deck joint seal
material shall not begin until the Engineer has
assemblies, drainage systems, utility conduits, and other
approved the drawings.
such items. Such drawings shall be in sufficient detail to
ii. The working drawings of the prestressing confirm that there will be no conflict between the planned
system shall show complete details and positions of any embedded items and that concrete cover
substantiating calculations of the method, will be adequate.
materials, and equipment the Contractor
4 Material Certificates: Signed by manufacturers and
proposes to use in the prestressing operations,
contractor certifying that each of the following items
including any additions or rearrangement of
complies with specified requirements:
reinforcing steel and any revision in concrete
dimensions from that specified in the contract i. Prestressing steel
documents. Such details shall outline the ii. Prestressing system.
method and sequence of stressing and shall iii. Records for the anchorage device acceptance
include complete specifications and details of test as specified in AASHTO LRFD Bridge
the prestressing steel and anchoring devices, Construction Specifications Article 10.3.2.3.12.
working stresses, anchoring stresses, tendon
elongations, type of ducts, and all other data 5.4.2 Materials
pertaining to the prestressing operation,
including the proposed arrangement of the 5.4.2.1 Concrete
prestressing steel in the members.
1 Concrete for prestressed construction shall be
iii. Working drawings shall be submitted produced and supplied in accordance with the relevant
sufficiently in advance of the start of the requirements of Section 5.1 “Concrete Materials and
affected work to allow time for review by the Mixes”.

♦ 5-28 ♦
copy 249
5.4.2.2 Reinforcing Steel strength greater than the concrete. In addition, the epoxy
bonding agents shall function as a lubricant during the
1 Non-prestressed reinforcing steel shall be supplied, joining of the match cast segments, as a filler to accurately
cut, bent and fixed in accordance with the relevant match the surface of the segments being joined, and as a
requirements of Section 5.2 “Reinforcing Steel”. durable, watertight bond at the joint.
5.4.2.3 Prestressing Steel 3 The physical, chemical and mechanical properties of
epoxy bonding agents shall satisfy the recommendations
1 Steel Wire: Steel wire shall comply with ASTM A of the AASHTO LRFD Bridge Design Specifications or the
421/A 421 M (AASHTO M 204), or with BS 5896. Federation Internationale de la Precontrainte (FIP)
2 Stress-Relieved Seven-Wire Strand: Stress-Relieved "Proposals for a standard for acceptance tests and
Seven-Wire Strand shall comply with ASTM A 416/A416 M verifications of epoxy bonding agents for segmental
low relaxation (AASHTO M 203) or with BS 5896 low construction".
relaxation.
3 High Tensile Steel Bar: High tensile steel bars for 5.4.3 Construction Requirements
prestressed concrete shall comply with ASTM A 722/A 722
M (AASHTO M 275) or with BS 4486. 5.4.3.1 Placement of Ducts

5.4.2.4 Post-Tensioning Anchorages and Couplers 1 Ducts shall be rigidly supported at the proper
Iocations in the forms by ties to reinforcing steel which are
1 Post-tensioning anchorages and couplers shall be in adequate to prevent displacement during concrete
accordance with the requirements of AASHTO LRFD placement. Supplementary support bars shall be used
Bridge Construction Specifications Article 10.3.2. where needed to maintain proper alignment of the duct.
2 Prestressing components, such as cable ducts, Hold-down ties to the forms shall be used when the
anchorages and couplers, shall be of approved types buoyancy of the ducts in the fluid concrete would lift the
suitable for types of cables and bars used. reinforcing steel.
3 All anchorages and couplers shall develop at least 96 2 Polyethylene duct and metal duct for longitudinal or
percent of the actual ultimate strength of the prestressing transverse post-tensioning in the flanges shall be
steel, when tested in an unbonded state, without supported at intervals not to exceed 600 mm. Polyethylene
exceeding anticipated set. duct in webs for longitudinal post-tensioning shall be tied
to stirrups at intervals not to exceed 600 mm, and metal
4 The coupling of tendons shall not reduce the
duct for longitudinal post-tensioning in webs shall be tied
elongation at rupture below the requirements of the
to stirrups at intervals not to exceed 1200 mm.
tendon itself. Couplers and/or coupler components shall
be enclosed in housings long enough to permit the 3 Joints between sections of duct shall be coupled with
necessary movements. Couplers for tendons shall be used positive connections which do not result in angle changes
only at locations specifically indicated in the contract at the joints and will prevent the intrusion of cement paste.
documents and/or approved by the Engineer. Couplers Joints in adjacent ducts shall be staggered by at least 300
shall not be used at points of sharp tendon curvature mm.
5 If the Engineer is not satisfied with the testing 4 After placing of ducts, and reinforcement and
certificates submitted for the prestressing system, he may forming is complete, an inspection shall be made to locate
request post-tensioning anchorages and couplers to be possible duct damage. All unintentional holes or openings
tested in accordance with AASHTO LRFD Bridge in the duct shall be repaired prior to concrete placing.
Construction Specifications Article 10.3.2 at no extra cost. 5 Grout openings and vents shall be securely anchored
to the duct and to either the forms or to reinforcing steel
5.4.2.5 Epoxy-Bonding Agents for Precast Segmental
to prevent displacement during concrete-placing
Construction operations.
1 Epoxy bonding agents for match cast joints shall be 6 After installation in the forms, the ends of ducts shall
thermosetting 100 percent solid compositions that do not at all times be sealed as necessary to prevent the entry of
contain solvent or any nonreactive organic ingredient water or debris.
except for pigments required for coloring. Epoxy bonding 7 Where members are made up of precast units
agents shall be of two components, a resin and a hardener. stressed together, the ducts in the joints between the units
The two components shall be distinctly pigmented, so that shall be in perfect alignment and joined securely so as to
mixing produces a third color similar to the concrete in the allow unimpeded cable threading and pulling and prevent
segments to be joined, and shall be packaged in pre- the ingress of the epoxy mortar used for gluing the several
portioned, labeled, ready-to-use containers. units together before stressing. Details of such joints shall
2 Epoxy bonding agents shall be insensitive to damp first be approved by the Engineer. The tolerance in the
conditions during application and, after curing, shall location of the sheath shall be plus or minus 3 mm.
exhibit high bonding strength to cured concrete, good 8 Additionally the following shall apply:
water resistivity, low creep characteristics, and tensile

♦ 5-29 ♦
copy 249
i. Entrance and exit angles of tendon paths at pressurize the tendon to 345 kPa and lock-off the outside
anchorages and/or at faces of concrete shall be air source. Record pressure loss for 1 minute. A pressure
within ± 3 degrees of desired angle measured loss of 170 kPa is acceptable for tendons having a length
in any direction and any deviations in the of equal to or less than 45 m and a pressure loss of 100
alignment are accomplished with smooth kPa is acceptable for tendons longer than 45 m. If the
transitions without any kinks. pressure loss exceeds the allowable, repair the leaking
ii. Angle changes at duct joints shall not be connections using methods approved by the Engineer and
greater than ±3 degrees in any direction and re-test.
must be accomplished with smooth transitions 13 The ends of all ducts shall be sealed and protected until
without any kinks. the tendon is threaded through and the stressing
iii. Locate anchorages within ± 3 mm of desired operations are commenced. Where tendons in sheaths or
position laterally and ±25 mm along the tendon sheath on its own are left exposed to atmosphere, rust
except that minimum cover requirements shall inhibitors shall be used as per the maker's specification to
be maintained. prevent rusting and corrosion of the inside of sheaths.
They shall be flushed with clean water before the tendons
iv. Position anchorage confinement reinforcement
are grouted. The Contractor is responsible for carrying
in the form of spirals, multiple U-shaped bars
out these measures at his own expense
or links to be properly centered around the
duct and to start within 12 mm of the back of 5.4.3.2 Placement of Prestressing Steel
the main anchor plate.
1 General:
v. If conflicts exist between the reinforcement and
post-tensioning duct, position the post- i. All wires or strands stressed at the same time
tensioning duct and adjust the reinforcement shall be taken from the same parcel. Each
locally with the Engineer's approval. cable shall be tagged with its number and the
coil number of the steel used.
9 Ducts shall be kept free of any matter detrimental to
the bond between the sheath and the grout and, except for ii. Tendons shall not be welded within the length
material sealing a sheath joint, between the sheath and to be tensioned and, unless other methods of
the concrete. cutting are approved by the Engineer, tendons
shall be sawn or cropped using an abrasive
10 All ducts for continuous structures shall be supplied
disc cutter.
with outlets at the high and low points of the duct profile,
except where the profile changes are small, as in iii. Tendons shall be built into the work strictly in
continuous slabs, and at additional locations as specified accordance with the system which is being
in the contract documents. Low-point outlets shall remain employed.
open until grouting is started. iv. Tendons shall not be kinked or twisted and
11 Upon completion of concrete placement, the individual wires or strands shall be readily
Contractor shall prove that the post-tensioning ducts are identifiable at each of the members. No strand
free and clear of any obstructions or damage and are able which has become unravelled shall be used in
to accept the intended post-tensioning tendons by passing the work.
a torpedo through the ducts. The torpedo shall have the 2 Placement for Pretensioning:
same cross-sectional shape as the duct, and 6 mm smaller i. Prestressing steel shall be accurately installed
all around than the clear nominal inside dimensions of the in the forms and held in place by the stressing
duct. No deductions shall be made to the torpedo section jack or temporary anchors and, when tendons
dimensions for tolerances allowed in the manufacture or are to be draped, by hold-down devices. The
fixing of the ducts. For straight ducts, a torpedo at least hold-down devices used at all points of change
600 mm long shall be used. For curved ducts, the length in slope of tendon trajectory shall be of an
shall be determined so that when both ends touch the approved low-friction type.
outermost wall of the duct, the torpedo is 6 mm clear of
ii. Prestressing steel shall not be removed from
the innermost wall. If the torpedo will not travel
its protective packaging until immediately prior
completely through the duct, the Engineer shall reject the
to installation in the forms and placement of
member, unless a workable repair can be made to clear
concrete. Openings in the packaging shall be
the duct, to the satisfaction of the Engineer. Upon
resealed as necessary to protect the unused
completion of the repairs, the torpedo shall pass through
steel. While exposed, the steel shall be
the duct easily, by hand, without resorting to excessive
protected as needed to prevent corrosion.
effort or mechanical assistance.
3 Placement for Post-Tensioning:
12 Before stressing and grouting internal or external
tendons, install all grout caps, inlets and outlets and test i. All prestressing steel preassembled in ducts
the tendon with compressed air to determine if duct and installed prior to the placement of concrete
connections require repair. In the presence of the Engineer, shall be accurately placed and held in position
during concrete placement.

♦ 5-30 ♦
copy 249
ii. When the prestressing steel is installed after iv. When steam curing is used, unless anchorage
the concrete has been placed, the Contractor systems mandate its installation, steel for post-
shall demonstrate to the satisfaction of the tensioning shall not be installed until the steam
Engineer that the ducts are free of water and curing is completed.
debris immediately prior to installation of the v. Such tendons shall be protected against
steel. The total number of strands in an corrosion by means of a corrosion inhibitor
individual tendon may be pulled into the duct placed in the ducts or on the steel, or shall be
as a unit, or the individual strand may be stressed and grouted within seven days after
pulled or pushed through the duct. steam curing.
iii. Anchorage devices or block-out templates for vi. Whenever electric welding is performed on or
anchorages shall be set and held so that their near members containing prestressing steel,
axis coincides with the axis of the tendon and the welding ground shall be attached directly
anchor plates are normal in all directions to the to the steel being welded. All prestressing steel
tendon. and hardware shall be protected from weld
iv. The prestressing steel shall be distributed so spatter or other damage.
that the force in each girder stem is equal or as
5.4.3.3 Placement of Anchorages
required by the contract documents, except as
provided herein. 1 The Contractor is responsible for the proper
v. For box girders with more than two girder placement of all materials according to the design
stems, at the Contractor's option, the documents of the Engineer and the requirements
prestressing force may vary up to five percent stipulated by the anchorage device supplier. The
from the theoretical required force per girder Contractor shall exercise all due care and attention in the
stem provided the required total force in the placement of anchorage hardware, reinforcement,
superstructure is obtained and the force is concrete and consolidation of concrete in anchorage zones.
distributed symmetrically about the centerline 2 Modifications to the local zone details verified under
of the typical section. provisions of AASHTO LRFD Bridge Design Specifications
4 Protection of Steel after Installation: Article 5.10.9.7.3 and AASHTO LRFD Bridge Construction
Specifications Article 10.3.2.3, ‘Special Anchorage Device
i. Prestressing steel used in post tensioned
Acceptance Test’, shall be approved by both the Engineer
concrete members that is not grouted within
and the anchorage device supplier.
the time limit specified below, shall be
continuously protected against rust or other 5.4.3.4 Identification and Testing
corrosion by means of a corrosion inhibitor
placed in the ducts or directly applied to the 1 All wire, strand, or bars to be shipped to the site shall
steel. The prestressing steel shall be so be assigned a lot number and tagged for identification
protected until grouted or encased in concrete. purposes. Anchorage assemblies to be shipped shall be
Prestressing steel installed and tensioned in likewise identified.
members after placing and curing of the 2 Before approval, at least two samples of the
concrete and grouted within the time limit prestressing steel shall be tested at the Contractor's
specified below will not require the use of a expense, at an approved independent laboratory for
corrosion inhibitor described herein and rust chemical composition, mechanical strength, relaxation
which may form during the interval between and physical characteristics.
tendon installation and grouting will not be 3 Subsequently, each lot of wire or bars and each reel
cause for rejection of the steel. of strand reinforcement shall be accompanied by a
ii. The permissible interval between tendon manufacturer's certificate of compliance, a mill certificate,
installation and grouting without use of a and a test report. The mill certificate and test report shall
corrosion inhibitor for various exposure include:
conditions shall be taken as follows: i. Chemical composition (not required for strand),
- Very Damp Atmosphere or over saltwater ii. Cross-sectional area,
(Humidity > 70 percent) 7 days
iii. Yield and ultimate strengths,
- Moderate Atmosphere (Humidity from 40
iv. Elongation at rupture,
percent to 70 percent) 15 days
v. Modulus of elasticity, and
- Very Dry Atmosphere (Humidity < 40
percent) 20 days vi. Stress strain curve for the actual prestressing
steel intended for use.
iii. After tendons are placed in ducts, the openings
at the ends of the ducts shall be sealed to All values certified shall be based on test values and
prevent entry of moisture. nominal sectional areas of the material being certified

♦ 5-31 ♦
copy 249
4 The Contractor shall furnish to the Engineer for type packaging material, or when permitted by the
verification testing samples selected at random from each Engineer, may be applied directly to the steel. Packaging
lot as follows. The actual strength of the prestressing steel or forms damaged from any cause shall be immediately
shall not be less than specified by the applicable ASTM replaced or restored to original condition.
Standard stated in Paragraph 5.4.2.3. 3 The shipping package or form shall be clearly marked
i. Pretensioning Tendons: one sample at least with a statement that the package contains high-strength
1500 mm long shall be furnished in accordance prestressing steel, and the type of corrosion inhibitor used,
with the requirements of Sub-Section 9.1 of including the date packaged.
ASTM A 416/A 416M. 4 All anchorages, end fittings, couplers, and exposed
ii. Post-Tensioning Tendons: for 20 tonnes, or tendons, which will not be encased in concrete or grout in
portion thereof, lot of material used in the the completed work, shall be permanently protected
work: against corrosion.
- For wires not requiring heading: sufficient 5 Corrosion Inhibitor:
length to make up one parallel-lay cable 1500 i. The corrosion inhibitor shall have no
mm long consisting of the same number of deleterious effect on the steel or concrete or
wires as the cable to be furnished. bond strength of steel to concrete or grout.
- For strand to be furnished with fittings: 1500 ii. Corrosion inhibitor shall consist of a vapor
mm between near ends of fittings. phase inhibitor (VPI) powder conforming to the
- For bars to be furnished with threaded ends provisions of Federal Specification MIL-P-
and nuts: 1500 mm between threads at ends. 3420F-87 or as otherwise approved by the
5 Anchorages: Engineer.

i. Before approval, at least two anchorages shall iii. When approved, water soluble oil may be used
be tested at the Contractor's expense, at an on tendons as a corrosion inhibitor.
approved laboratory to BS 4447. Subsequently,
5.4.3.6 Ducts
the Engineer may require additional samples,
selected at random from materials on site, to 1 Ducts formed by sheath left in place shall be a type
be similarly tested. that will not permit the intrusion of cement paste. They
ii. For each anchorage type used in the Works, the shall transfer bond stresses as required and shall retain
characteristic value of anchorage efficiency, shape under the weight (mass) of the concrete and shall
determined in accordance with BS 4447, shall have sufficient strength to maintain their correct
be not less than 90%. alignment without visible wobble during placement of
concrete.
6 For prestressing systems previously tested and
approved on projects having the same tendon 2 Metal Ducts:
configuration, the Engineer may waive the anchorage i. Sheathing for ducts shall be metal, except as
testing. provided herein. Such ducts shall be
7 Epoxy Bonding Agents: Epoxy bonding agents shall galvanized ferrous metal and shall be
be tested for and satisfy the requirements of all the tests fabricated with either welded or interlocked
listed in the recommendations of FIP "Proposal for a seams. Galvanizing of welded seams will not
standard for acceptance tests and verification of epoxy be required.
bonding agents for segmental construction". ii. Rigid ducts shall have smooth inner walls and
shall be capable of being curved to the proper
5.4.3.5 Protection of Prestressing Steel configuration without crimping or flattening.
1 All prestressing steel shall be protected against iii. Semi-rigid ducts shall be corrugated and, when
physical damage and rust or other results of corrosion at tendons are to be inserted after the concrete
all times from manufacture to grouting. Prestressing steel has been placed, their minimum wall thickness
shall also be free of deleterious material such as grease, shall be as follows: 0.45 mm for ducts less than
oil, wax or paint. Prestressing steel that has sustained or equal to 65 mm diameter 0.60 mm for ducts
physical damage at any time shall be rejected. The greater than 65 mm diameter.
development of pitting or other results of corrosion, other iv. When bar tendons are preassembled with such
than rust stain, shall be cause for rejection. ducts, the duct thickness shall not be less than
2 Prestressing steel shall be packaged in containers or 0.25 mm.
shipping forms for the protection of the strand against 3 Plastic Ducts:
physical damage and corrosion during shipping and
i. For locations in saltwater environment, plastic
storage. A corrosion inhibitor which prevents rust or other
duct material shall be considered and is
results of corrosion shall be placed in the package or form,
recommended.
or shall be incorporated in a corrosion inhibitor carrier-

♦ 5-32 ♦
copy 249
ii. Corrugated plastic duct to be completely metal polyolefin (polyethylene or
embedded in concrete shall be constructed polypropylene), and shall be air and watertight
from either polyethylene or polypropylene. The and of sufficient strength to prevent distortion
minimum acceptable radius of curvature shall or displacement of the ducts during concrete
be established by the duct supplier according placement and/or tendon grouting.
to standard test methods. The duct shall have a ii. All ducts or anchorage assemblies shall be
thickness as below: provided with pipes or other suitable
Duct Shape Duct Diameter Duct Thickness connections at each end of the duct for the
in millimeters in millimeters injection of grout after prestressing. As
specified in Article 5.4.3.1(10), ducts shall also
Flat any size 2.0
be provided with ports for venting or grouting
Round 23 2.0 at high points and for draining at intermediate
Round 60 2.0 low points.
Round 75 2.5 iii. Vent and drain pipes shall be at least 20 mm
Round 85 2.5 diameter for strand and at least 12 mm
diameter for single-bar tendons and three or
Round 100 3.0
four strand flat duct tendons. Connection to
Round 115 3.5 ducts shall be made with metallic or plastic
Round 130 4.0 structural fasteners. The vents and drains shall
Round 145 4.0 be mortar tight, taped as necessary, and
constructed with either mechanical or shrink
iii. Ducts shall have a white coating on the outside
wrap connections. Vents and drains shall
or shall be of white material with ultraviolet
provide means for injection of grout through
stabilizers added.
the vents and for sealing to prevent leakage of
iv. Polyethylene duct shall be fabricated from grout.
resins meeting or exceeding the requirements
of ASTM D 3350 with a cell classification of 5.4.3.7 Grout
345464A.
1 Grout shall be in accordance with the requirements
v. Polypropylene duct shall be fabricated from of AASHTO LRFD Bridge Construction Specifications Sub-
resins meeting or exceeding the requirements section 10.9.
of ASTM D 4101 with a cell classification range
2 Grouts may be either a unique design for the project
of PP0340B14541 to PP0340B67884.
or supplied in a pre-bagged form by a grout manufacturer.
vi. Use resin containing antioxidant(s) with a
3 Unless otherwise directed or agreed as a result of
minimum Oxidation Induction Time (OIT)
grouting trials, uniquely designed grouts shall consist only
according to ASTM D 3895 of not less than 20
of ordinary Portland cement and water. The water-cement
minutes. The OIT test shall be performed on
ratio shall be as low as possible consistent with necessary
samples taken from the finished product.
workability and under no circumstances be higher than
vii. Rigid smooth black polyethylene ducts for use 0.45 and not be subject to bleeding in excess of 2 percent
where the tendon is not embedded in concrete after 3 hours, or 4 percent maximum. When measured at
shall be rigid pipe manufactured from 100 18 degrees C in a covered glass cylinder approximately
percent virgin polyethylene resin meeting the 100 mm water shall be reabsorbed after 24 hours.
requirements of ASTM D 3350 with a minimum
4 Grout shall be mixed for a minimum of two minutes
cell class of 344464C. A resin containing
and until a uniform consistency is obtained. The
antioxidant(s) with a minimum oxidation
pumpability of the grout may be determined in
induction time (OIT) according to ASTM D 3895
accordance with the US Corps of Engineers Method CRD-
of not less than 40 min shall be used. The OIT
C79 in which case the efflux time of the grout sample
test shall be performed on samples taken from
immediately after mixing shall not be less than 11 seconds.
the finished product. The duct shall be
manufactured with a dimensional ratio (DR) of 5 Admixture containing chlorides or nitrates shall not
17.0 as established by either ASTM D 3350 or be used. Other admixtures may be used only with the
ASTM F 714 as appropriate for the written permission of the Engineer and shall be applied
manufacturing process used. strictly in accordance with the manufacturer's instruction.

4 Duct Area: The provisions of AASHTO LRFD Bridge 6 The design for grout mix shall be tested in
Design Specifications, Article 5.4.6.2, ‘Size of Ducts,’ shall accordance with ASTM C 49 for longitudinal change. Each
apply. design mix and each batch mix shall be tested for vertical
dimensional change.
5 Duct Fittings:
7 Daily field testing of the grout for the following
i. Coupling and transition fittings for ducts
properties shall be required:
formed by sheathing shall be of either ferrous

♦ 5-33 ♦
copy 249
i. Fluidity to ASTM C 939 or the modified test iii. Documentary proof shall be provided
described in AASHTO LRFD Bridge confirming that all jacks have been fully
construction Specification Table 10.9.3-2, overhauled and checked by an agent approved
ii. Bleed at 3 h to ASTM C 940 as modified in by the manufacturer of the equipment. Each
AASHTO LRFD Bridge construction jack shall be accompanied by a test certificate
Specification Table 10.9.3-2, indicating that it has been tested and calibrated
by the manufacturer or by an approved testing
iii. Permeability to ASTM C1202 (AASHTO T 277).
laboratory up to a load equal to the full
8 Manufacturers of pre-bagged post-tensioning grout capacity of the jack within a period of six
shall submit for approval certified test reports from an months prior to the commencement of
audited and independent Cement Concrete Research prestressing.
Laboratory (CCRL) which shows the material meets all the
iv. The jacking system shall provide an
requirements specified herein.
independent means by which the tendon
9 Preapproved pre-bagged grout shall be mixed in elongation can be measured. The pressure
accordance with the Manufacturer's recommendations. gage shall have an accurate reading dial at
10 Grouts shall achieve a non-bleeding characteristic. least 150 mm in diameter or a digital display,
Grout shall not contain aluminum powder or gas and each jack and its gage shall be calibrated
generating system that produces hydrogen, carbon as a unit with the cylinder extension in the
dioxide, or oxygen. Cementitious grout shall meet or approximate position that it will be at final
exceed the specified physical properties stated herein as jacking force, and shall be accompanied by a
determined by the following standard and modified ASTM certified calibration chart or curve.
test methods. v. All gages, load cells, dynamometers and other
11 Grout Classes shall be taken as specified in AASHTO devices used for measuring the stressing force
LRFD Bridge Construction Specifications Table 10.9.3-1 shall have an accuracy of within plus or minus
and Grout Properties shall be as specified in AASHTO 1.5 percent. Pressure gages shall have a
LRFD Bridge Construction Specifications Table 10.9.3-2. capacity and calibrated cell such that the
working pressure required to stress the
5.4.3.8 Tensioning tendons to the fully stated load lies within the
1 Tensioning may be accomplished by pre-tensioning, central half of the range of the gage.
post-tensioning, or the combined method; as specified in vi. Each gage shall have a calibration certificate
the contract documents, or on the approved working issued by an approved test laboratory. All
drawings, or approved in writing by the Engineer. pressure gages shall be so constructed that
2 During stressing of strand, individual wire failures they may be calibrated, either directly by an
may be accepted by the Engineer, provided not more than approved testing laboratory, or by
one wire in any strand is broken and the area of broken compressing with a meter gage which has
wires does not exceed two percent of the total area of the itself been calibrated by an approved testing
prestressing steel in the member. laboratory.

3 Concrete Strength: Prestressing forces shall not be vii. All pressure gages shall be re-calibrated before
applied or transferred to the concrete until the concrete use and at intervals of 14 days during the
has attained the strength specified for initial stressing. In prestressing operation. The Engineer will
addition, cast-in-place concrete for other than segmentally order re-calibration of any pressure gage at any
constructed bridges shall not be post-tensioned until at time should he have reason to suspect damage
least ten days after the last concrete has been placed in to or faulty operation of the gage.
the member to be post-tensioned. viii. The accuracy of all prestressing and load
4 Prestressing Equipment: measuring equipment shall be checked
whenever required by the Engineer. The
i. Hydraulic jacks used to stress tendons shall be
Contractor shall provide a rig suitable in the
capable of providing and sustaining the
opinion of the Engineer, for all checking and
necessary forces and shall be equipped with
calibration of any jacking system consisting of
either a pressure gage or a load cell for
jacks and associated load devices, pressure
determining the jacking stress.
gages and dynamometers.
ii. All jacks used for prestressing shall be of the
5 Sequence of Stressing: When the sequence of
type applicable to the system adopted. The
stressing individual tendons is not otherwise specified in
accuracy of the load metering equipment shall
the contract documents or on the approved working
be checked to the satisfaction of the Engineer
drawings, the stressing of post-tensioning tendons and
at the start of the work each day it has to be
the release of pretensioned tendons shall be done in a
used and whenever the equipment is moved to
sequence that produces a minimum of eccentric force in
a different job.
the member.

♦ 5-34 ♦
copy 249
6 Measurement of Stress: the length of the casting bed and the size and number of
i. A record of gage pressures and tendon tendons in the group to be tensioned.
elongations for each tendon shall be provided 5 Draped Pretensioned Tendons:
by the Contractor for review and approval by i. Draped pretensioned tendons shall either be
the Engineer. Elongations shall be measured to tensioned partially by jacking at the end of the
an accuracy of 1.5 mm. Stressing tails of post- bed and partially by uplifting or depressing
tensioned tendons shall not be cut off until the tendons, or they shall be tensioned entirely by
stressing records have been approved. jacking, with the tendons being held in their
ii. The stress in tendons during tensioning shall draped positions by means of rollers, pins, or
be determined by the gage or load-cell other approved methods during the jacking
readings and shall be verified with the operation.
measured elongations. Calculations of ii. Approved low-friction devices shall be used at
anticipated elongations shall utilize the all points of change in slope of tendon
modulus of elasticity, based on nominal area, trajectory when tensioning draped
as furnished by the Manufacturer for the lot of pretensioned strands, regardless of the
steel being tensioned, or as determined by a tensioning method used.
bench test of strands used in the work.
iii. If the load for a draped strand, as determined
iii. All tendons shall be tensioned to a preliminary by elongation measurements, is more than five
force as necessary to eliminate any take-up in percent less than that indicated by the jack
the tensioning system before elongation gages, the strand shall be tensioned from both
readings are started. This preliminary force ends of the bed, and the load as computed
shall be between 5 and 25 percent of the final from the sum of elongation at both ends shall
jacking force. The initial force shall be agree within five percent of that indicated by
measured by a dynamometer or by other the jack gages.
approved method, so that its amount can be
6 When ordered by the Engineer, prestressing steel
used as a check against elongation as
strands in pretensioned members, if tensioned
computed and as measured. Each strand shall
individually, shall be checked by the Contractor for loss of
be marked prior to final stressing to permit
prestress not more than 3 hours prior to placing concrete
measurement of elongation and to ensure that
for the members. The method and equipment for checking
all anchor wedges set properly.
the loss of prestress shall be subject to approval by the
5.4.3.9 Pretension Construction Engineer. All strands that show a loss of prestress in
excess of three percent shall be retensioned to the original
1 The strand stress prior to seating (jacking stress) computed jacking stress.
shall not exceed 80 percent of the minimum ultimate
7 Stress on all strands shall be maintained between
tensile strength of the prestressing steel. This allowable
anchorages until the concrete has reached the
stress, which slightly exceeds the values allowed in
compressive strength required at time of transfer of stress
AASHTO LRFD Bridge Design Specifications, Article 5.9.3,
to concrete.
may be permitted to offset seating losses and to
accommodate compensation for temperature differences 8 When prestressing steel in pretensioned members is
specified below. tensioned at a temperature more than 14 deg. C lower
than the estimated temperature of the concrete and the
2 In pretensioned members where tendons are
prestressing steel at the time of initial set of the concrete,
specified as debonded from the concrete, they shall be
the calculated elongation of the prestressing steel shall be
covered with sleeves of PVC or other material approved by
increased to compensate for the loss in stress due to the
the Engineer. The ends of the sleeves shall be taped to
change in temperature, but in no case shall the jacking
the tendon to prevent the ingress of grout.
stress exceed 80 percent of the specified minimum
3 Stressing shall be accomplished by either single- ultimate tensile strength of the prestressing steel.
strand stressing or multiple-strand stressing. The amount
9 Members shall be free to accommodate the
of stress to be given to each strand shall be as shown in
horizontal and vertical movements due to the application
the contract documents or on the approved working
of prestress. Side and flange forms that restrain deflection
drawings.
shall be removed before release of pre-tensioning
4 All strands to be stressed in a group (multiple-strand reinforcement.
stressing) shall be brought to a uniform initial tension
10 When the concrete has attained the specified
prior to being given their full pre-tensioning. The amount
strength, the load shall be transferred gradually without
of the initial tensioning force shall be within the range
severance of the tendons
specified in Article 5.4.3.8 (6) Measurement of Stress, and
shall be the minimum required to eliminate all slack and to 11 Except when otherwise shown in the contract
equalize the stresses in the tendons as determined by the documents, all pretensioned prestressing strands shall be
Engineer. The amount of this force will be influenced by cut off flush with the end of the member, and the exposed

♦ 5-35 ♦
copy 249
ends of the strand and a 25 mm strip of adjoining concrete iv. The tendons shall be stressed at a gradual and
shall be cleaned and painted. Cleaning shall be by wire steady rate until they attain the force and
brushing or abrasive blast cleaning to remove all dirt and extension specified.
residue that is not firmly bonded to the metal or concrete v. If the measured extension differs by more than
surfaces. The surfaces shall be coated with one thick coat 5 percent from the estimated extension,
of zinc-rich paint conforming to the requirements of U.S. corrective action shall be taken as directed by
Military Specification MIL-P-24441/20. The paint shall be the Engineer.
thoroughly mixed at the time of application, and shall be
vi. The force in the tendons shall be obtained from
worked into any voids in the strands.
reading on a load cell or pressure gage, and
12 All members shall be indelibly marked to show the the extension of the tendons measured. Due
specified member mark, the production line on which they allowance must be made for taking up slack in
were manufactured, the date on which the concrete was the tendons.
cast, the load applied and, if they are of symmetrical
vii. Stressing shall be from both ends unless
section, the face which will be uppermost when the
otherwise specified or agreed by the Engineer.
member is in its correct position in the work. The
markings shall be so located that they are not exposed to viii. Where stressing from one end only, the pull-in
view when the member is in its permanent position. at the end remote from the jack shall be
accurately measured and the appropriate
5.4.3.10 Post-Tension Construction allowance made in the measured extension at
the jacking end.
1 The standard stress prior to seating (jacking stress)
and the stress in the prestressing steel immediately after ix. When the specified force, including any
seating shall not exceed the values allowed in AASHTO overload of short duration, has been applied, to
LRFD Bridge Design Specifications, Sub-section 5.9.3. the satisfaction of the Engineer, the tendons
shall be anchored. The jack pressures shall
2 Immediately before tensioning, the Contractor shall
then be released in such a way as to avoid
demonstrate to the satisfaction of the Engineer that all
shock to the anchorage of tendons.
tendons are free to move between jacking points and that
members are free to accommodate the horizontal and x. If the pull-in of the tendons at completion of
vertical movements due to the application of prestress. anchoring is greater than that stipulated by the
Engineer, tensioning shall be carried out afresh.
3 Unless otherwise specified, concrete shall not be
stressed until it has reached the age at which at least 2 test xi. If it is necessary to cut the tendons to enable
specimens taken from it attain the specified transfer the ducts to be grouted, this shall be delayed
strength. The test specimens shall be cured in similar as long as practicable up to the time of
conditions to the concrete to which they relate. The grouting. In all other cases, unless agreed
Contractor shall cast sufficient specimens to demonstrate otherwise by the Engineer, the tendons shall
that the required strength of the concrete at transfer has not be cropped less than 3 days after grouting.
been reached. 6 Records: A record of the following post-tensioning
4 Where members consist of jointed elements the operations shall be kept for each tendon installed:
strength at transfer of the jointing material shall be at least i. Project name, number,
equivalent to the specified transfer strength of the ii. Contractor and/or subcontractor,
member.
iii. Tendon location, size and type,
5 Tension Procedures:
iv. Date tendon was first installed in ducts,
i. The Contractor shall establish the datum point
v. Coil/reel number for strands or wires and heat
for measuring extension and jack pressure to
number for bars and wire,
the satisfaction of the Engineer.
vi. Assumed and actual cross-sectional area,
ii. The Contractor shall add to the specified forces
an allowance where necessary for anchorage vii. Assumed and actual modulus of elasticity,
friction, wedge pull-in, jack losses and friction viii. Date stressed,
due to duct alignment and curvature. The total ix. Jack and gage numbers per end of tendon,
forces and calculated extensions shall be
x. Required jacking force,
agreed with the Engineer before stressing is
commenced. xi. Gage pressures,
iii. Immediately after anchoring, the stresses in the xii. Elongations (anticipated and actual),
tendons shall not exceed 75 percent of their xiii. Anchor sets (anticipated and actual),
ultimate tensile strength or as defined in the xiv. Stressing sequence (i.e., tendons before and
contract documents. During stressing the after this tendon),
value shall not exceed 80 percent.
xv. Stressing mode (one end/two
ends/simultaneous),

♦ 5-36 ♦
copy 249
xvi. Witnesses to stressing operation (Contractor viii. Mixing and pumping procedures;
and Inspector), ix. Direction of grouting;
xvii. Date grouted, days from stressing to grouting, x. Sequence of use of the inlets and outlet pipes;
grouting pressure applied, and injection end,
xi. Procedures for handling blockages; and
xviii. Record any other relevant information
xii. Procedures for possible post grouting repair.
including pour back and bitumastic installation
dates. Before grouting operations begin, a joint meeting of
the Contractor, grouting crew and the Engineer shall
The Engineer shall be provided with a complete copy of
be conducted. At the meeting, the grouting operation
stressing operations, and the jack calibration forms within
plan, required testing, corrective procedures, and any
24 hours of each tensioning operation.
other relevant issues shall be discussed.
7 Protection of Tendons: Within 4 hours after stressing
5 Preparation of Ducts:
and prior to grouting, tendons shall be protected against
corrosion or harmful effects of debris by temporarily i. Each duct shall be air pressure tested prior to
plugging or sealing all openings and vents; cleaning rust the installation of the prestressing steel into the
and other debris from all metal surfaces which will be ducts. If leaks are indicated during the test, the
covered by the grout cap; and placing the grout cap, duct shall be repaired to eliminate the leakage
including a seal, over the wedge plate until the tendon is or minimize the consequences of the leakage.
grouted. ii. All ducts shall be clean and free of deleterious
materials that would impair bonding or
5.4.3.11 Grouting interfere with grouting procedures.
1 Grout should be injected from low points pumping iii. Ducts with concrete walls (cored ducts) shall be
toward the high-point vent. For segmental, span-by-span flushed to ensure that the concrete is
construction, grout shall be injected through a grout inlet thoroughly wetted. Metal ducts shall be flushed
at midspan. if necessary to remove deleterious material.
2 Ducts shall be grouted as soon as practicable after iv. Water used for flushing ducts may contain
the tendons have been stressed and the Engineer's slack lime (calcium hydroxide) or quicklime
permission to commence has been obtained. The ducts (calcium oxide) in the amount of 0.012 kg/l.
shall be completely filled with grout. Grout shall be v. After flushing, all water shall be blown out of
injected in one continuous operation and allowed to flow the duct with oil-free compressed air.
from the vents until the consistency is equivalent to that
6 Equipment:
being injected or more than 11 seconds.
i. The grouting equipment shall include a high-
3 Grout shall not be above 32 deg. C during mixing or
speed shear mixer capable of continuous
pumping. If necessary, cool the mixing water.
mechanical mixing which will produce a grout
4 A grouting operation plan shall be submitted for free of lumps and undispersed cement, a grout
approval at least 45 days in advance of any scheduled pump, and stand-by flushing equipment with
grouting operations. Written approval of the grouting water supply. The equipment shall be able to
operation plan by the Engineer shall be required before pump the mixed grout in a manner which will
any grouting of the permanent tendons in the structure comply with all requirements.
takes place. At a minimum, the following items shall be
ii. The equipment shall be as per ASTM LRFD
provided in the grouting operation plan:
Bridge Construction Specification Article
i. Provide names, and proof of training and 10.11.3.
experience records for the grouting crew and
7 Mixing of Grout:
the crew supervisor in conformance with this
Specification; i. Water shall be added to the mixer first,
followed by cement grout.
ii. Type, quantity, and brand of materials used in
grouting including all required certifications; ii. Grout shall be mixed in accordance with the
manufacturer's instructions using a colloidal
iii. Type of equipment furnished, including
mixer to obtain homogeneous mixture. A
capacity in relation to demand and working
fluidity test shall be performed on the mixed
condition, as well as back-up equipment and
grout prior to beginning the injection process.
spare parts;
Target flow rates as a function of mixer type
iv. General grouting procedure; used and ambient temperatures shall be
v. Duct pressure test and repair procedures; obtained from the grout manufacturer. The
vi. Method to be used to control the rate of flow
within ducts;
vii. Theoretical grout volume calculations;

♦ 5-37 ♦
copy 249
grouting process shall not be started until the
proper grout properties have been obtained. Property Test Value Test Method
iii. Mixing shall be of such duration as to obtain a Max. 0.08% by
uniform, thoroughly blended grout, without Total Chloride weight of ASTM
Ions cementitious C1152/C1152M
excessive temperature increase or loss of
material
expansive properties of the admixture. The Fine Aggregate Max. Size ≤ No. ASTM C 33
grout shall be continuously agitated until it is (if utilized) 50 Sieve
pumped. Volume
0.0% to+0.2% at ASTM C 1090*
iv. Water shall not be added to increase grout Change at 28
24 h and 28 days
days
flowability which has been decreased by
≤2.0% for up to 3
delayed use of the grout. Expansion ASTM C 940
h
8 Injection of Grout: Compressive
i. All grout vents shall be opened before grouting Strength ASTM C 942
≥6 ksi
28 day (average
starts. Injection and ejection vents with
of 3 cubes)
positive shut-offs shall be provided. Grout shall
Initial Set of Min. 3 h ASTM C 953
be allowed to flow from the first injection vent
Grout Max. 12 h
until any residual flushing water or entrapped
Fluidity Test**
air has been removed prior to closing that vent.
Efflux Time
Remaining vents shall be closed in sequence in from Flow Min 11 s
the same manner. A continuous flow of grout ASTM C 939
Cone Max. 30 s or
at a rate between 10 000 mm and 15 000 mm ASTM C
a) Immediately Min. 9 s
939***
of duct per minute shall be maintained. after Mixing Max. 20 s
ASTM C 939
b) 30 min after Max. 30 s or
ii. The pumping pressure at the injection vent ASTM C
Mixing with Max. 30 s
should not exceed 1.0 MPa. Normal operations 939***
Remixing
shall be performed at approximately 0.5 MPa. for 30 s
If the actual grouting pressure exceeds the ASTM C
Bleeding at 3 h Max. 0.0%
maximum allowed, the injection vent shall be 940****
closed and the grout shall be injected at the Permeability at Max. 2500 AASHTO T 277
next vent that has been, or is ready to be 28 days coulombs at 30 (ASTM C 1202)
closed, as long as a one-way flow is volts for 6 h
maintained. Grout shall not be injected into a Table 5.4.3.1 Grout Properties for
succeeding vent from which grout has not yet Volume Change at 28 Days
flowed. Table 5.4.3-1 Notes
*Modify ASTM C 1090 to include verification at both
Iii Grout shall be pumped through the duct and
24 h and 28 days.
continuously wasted at the ejection vent until
no visible slugs of water or air are ejected. A **Adjustments to flow rates will be achieved by strict
fluidity test shall be performed on each tendon compliance with the manufacturer’s
recommendations.
in accordance with paragraph 5.4.3.7 (7)
measuring the grout fluidity from the discharge ***Grout fluidity shall meet either the standard ASTM
outlet. The measured grout efflux time shall C 939 flow cone test or the modified test described
not be faster than the efflux time measured at herein. Modify the ASTM C 939 test by filling the cone
the inlet or the minimum efflux time to the top instead of to the standard level. The efflux
time is the time to fill a 1.0 liter container placed
established in Table 5.4.3.1. If the grout efflux
directly under the flow cone.
time is not acceptable, additional grout shall be
discharged from the discharge outlet. Grout ****Modify ASTM C 940 to conform with the wick
efflux time shall be tested. This cycle shall be induced bleed test described below:
continued until acceptable grout fluidity is a) Condition dry ingredients, mixing water,
achieved. To ensure that the tendon remains prestressing strand and test apparatus overnight
filled with grout, the ejection and injection at 21 to 25 deg. C.
vents shall be closed in sequence, respectively, b) Insert 800 milliliters of mixed conditioned grout
with conditioned water into the 1000 milliliters
under pressure when the tendon duct is
graduated cylinder. Mark the level of the top of
completely filled with grout. The positive shut- the grout.
offs at the injection and ejection vents shall not c) Wrap the strand with 50 mm wide duct or
be removed or vents opened until the grout electrical tape at each end prior to cutting to
has set. avoid splaying of the wires when it is cut.
iv. The maximum allowable ambient temperature
to start grouting is 32 degrees C.

♦ 5-38 ♦
copy 249
Degrease (with acetone or hexane solvent) and be used to construct all pour-backs located at
wire brush to remove any surface rust on the anchorages of expansion joints or other areas
strand before temperature conditioning. Insert exposed to the elements.
completely a 500 mm length of conditioned,
cleaned, ASTM A 416/A 416M seven wire strand ii. All laitance, grease, curing compounds, surface
12.7 mm diameter into the 1000 milliliter treatments, coatings, and oils shall be removed
graduated cylinder. Center and fasten the strand by grit blasting or water blasting using a
so it remains essentially parallel to the vertical minimum 70.0 MPa nozzle pressure. The
axis of the cylinder (possibly using a centralizer). surface shall be flushed with water and blown
Mark the level of the top of the grout. dry. Surfaces shall be clean, sound, and
d) Store the mixed grout at the temperature range
without any standing water. In case of dispute,
listed above in (a).
e) Measure the level of the bleed water every 15 min ACl 503 shall be followed for substrate testing
for the first hour and hourly afterward for 2 h. and a minimum of 1.2 MPa tension (pull-off
f) Calculate the bleed water, if any, at the end of the value) be developed.
3 h test period and the resulting expansion per
iii. Epoxy shall be mixed and applied as
the procedures outlined in ASTM C 940, with the
quantity of bleed water expressed as a percent of manufacturer's current standard technical
the initial grout volume. Note if the bleed water guidelines. All pour-backs shall be in leak proof
remains above or below the top of the grout. forms creating neat lines. The pumping of
9 Vertical Grouting: In lieu of a positive shut-off, epoxy grout shall be permitted for proper
vertical or near vertical tendon ducts for grouting shall installation. Forms shall be constructed to
terminate in reservoirs at the upper-most point. The maintain a liquid head to insure intimate
reservoir shall have sufficient capacity to store excess contact with the concrete surface. Vents shall
grout bleed water. Visible grout level shall be maintained be used as needed to provide for the escape of
in the reservoirs. The reservoirs shall be maintained until air to insure complete filling of the forms.
the grout has set. Grout shall be injected at a rate of 5000 iv. The exposed surfaces of pour-backs or grout
mm of duct per minute. caps, except on transverse tendons, shall be
10 Post-Grouting Inspection: Vacuum grouting shall be coated with an elastomeric coating system
used to fill any voids that expose strands discovered in the having a thickness of 760 to 1140 μm. Concrete,
grouting process. Where possible, all anchorages and grout caps or other substrates shall be
high-point vents shall be drilled and probed 48 hours after structurally sound, clean, and dry. Concrete
grouting, until the Engineer is assured that no bleed water shall be a minimum of 28 days old. Laitance,
or subsidence (settlement) voids exist. After the Engineer grease, curing compounds, surface treatments,
is assured that voids do not exist, only one or two coatings, and oils shall be removed by grit
anchorages per span shall be drilled and probed to ensure blasting or water blasting using a minimum
quality grouting. Any voids discovered should be filled 70.0 MPa nozzle pressure to establish the
immediately with the approved grout. anchor pattern. Surfaces shall be blown with
compressed air to remove the dust or water.
11 Finishing:
v. A 600 x 1200-mm concrete test block shall be
i. Valves, caps and vent pipes shall not be
constructed with a similar surface texture to
removed or opened until the grout has set.
the surfaces to be coated and a vertical face
ii. The ends of vents shall be removed at least 25 shall be coated with the elastomeric coating
mm below the concrete surface after the grout system chosen. The number of coats required
has set. to achieve a coating thickness between 760 to
iii. The void shall be filled with epoxy grout. All 1140 μm without runs and drips shall be
miscellaneous material used for sealing grout determined. The elastomeric coating shall be
caps shall be removed before carrying out mixed and applied as per Manufacturer's
further work to protect end anchorages. current standard technical specifications. Spray
or roller application may be permitted; spray
12 Protection of End Anchorages: Permanent grout caps
application is preferred. Coatings shall be
constructed from either stainless steel or polymer shall be
applied using approved and experienced
specified. The following requirements apply:
personnel with a minimum of 3 years
i. Within seven days upon completion of the
experience applying similar polyurethane
grouting, the anchorage of post-tensioning
systems. Credentials of these persons shall be
bars and tendons shall be protected as
submitted to the Engineer for review and
indicated in the contract documents. The
consideration for approval.
application of the elastomeric coating may be
delayed up to 90 days after grouting. Plastic or
5.4.4 Method of Measurement
stainless steel threaded caps shall be used to
plug all grout inlets/outlets. A sand-filled epoxy 1 Concrete shall be measured under the provisions of
grout suitable for machinery base plate shall Section 5.1.

♦ 5-39 ♦
copy 249
2 Non-prestressed reinforcing steel shall be measured iv. Plant, equipment and labor for all stressing and
under the provisions of Section 5.2 . grouting operations, including making good all
3 Prestressing steel shall be measured by the weight in anchorage pockets as shown on the Drawings
metric tonnes for each size and quality of wire, strands or or as directed by the Engineer.
bar furnished, installed, completed and accepted. The v. All testing required in the Specifications.
weight shall be calculated based on the nominal mass of
each diameter wire, strand or bar as stated in the 5.4.6 Items in the Bill of Quantities
standards listed in Paragraph 5.4.21.3.
i Prestressing wires
4 In post-tensioning work, the prestressing steel shall
(state size and type) t.
be measured in t based on the actual length between the
ii Prestressing strands
outermost surfaces of the anchorages except where
(state size and type) t.
couplers are used in which case, the prestressing steel
shall be assumed to be continuous, without any flares, iii Prestressing bars
through the coupler. (state size and type) t.
5 In pre-tension work, the prestressing steel shall be
measured in t based on the actual length between the 5.5 Concrete Bridges and Erection
outermost faces of the member. Procedures
6 Items not measured: Measurement of prestressed
concrete is restricted to the items stated in items 1, 2 and 3 5.5.1 Description
above. No separate measurement is made for any other
5.5.1.1 Scope
component or work.
i. Cable ducts, duct couplers, grout tubes and 1 This Sub-section describes requirements for erection
steel chairs for the correct duct/tendon location of concrete bridge structures and decks in conformity with
are not measured for payment. the lines, grades and dimensions shown on the Drawings
ii. Anchor blocks for use in pre-tension work are and in accordance with the Specifications. These
not measured for payment. requirements are additional to the requirements for
concrete work generally as specified in the preceding Sub-
iii. Prestressing steel used in connection with
sections of this Section
temporary works is not measured for payment
even if such steel is left permanently in the 5.5.1.2 References
member.
1 American Association of State Highway and
iv. Epoxy bonding agent used in precast
Transportation Officials (AASHTO):
segmental construction shall not be measured
for payment. AASHTO 2008 AASHTO LRFD Bridge Construction
Specifications, 2nd Edition, 2004, 2008
v. Shear keys and location dowels used in precast
Interim Revisions.
segmental construction shall not be measured
for payment. AASHTO 2008 AASHTO LRFD Bridge Design
specifications, 3rd Edition, 2004, 2008
vi. Prestressing steel and anchorages used for
Interim Revisions.
applying temporary prestress to glued
segments shall not be measured for payment. AASHTO 1999 Guide Specifications for Design and
Construction of Segmental Concrete
vii. Anchorages and couplers shall not be
Bridges, 2nd Edition.
measured for payment.
2 Fédération Internationale de la Précontrainte (FIP)
5.4.5 Basis of Payment FIP Proposal for a Standard for Acceptance
Tests and Verification of Epoxy Agents
1 The amount of completed and accepted work for Segmental Construction.
measured as provided for above shall be paid at the rates
in the Bill of Quantities. These rates shall be full
5.5.2 Materials
compensation for the provision of materials, equipment,
labor, tools, testing and other items necessary for proper 1 Materials shall conform to the relevant requirements
completion of the Work. The rates shall include: of the following Sub-sections of the Specification:
i. Items not measured as described in Item 5.4.4 - Concrete Sub-section 5.1 Concrete
(6). Materials and
ii. Cement, water and additive used in making the Mixes
grout. - Reinforcing Steel Sub-section 5.2 Reinforcing
iii. All prestressing equipment and its calibration. Steel

♦ 5-40 ♦
copy 249
- Pre-stressing Sub-section 5.4 Pre-stressed each stage of construction at the check points
Concrete listed below, or an alternative of his choice and
Structures submit the same for the Engineer's approval.
The check points are:
5.5.3 Construction Requirements - One of the lowest corners at the top surface
of any temporary bearing pad which is to
5.5.3.1 Balanced Cantilever Construction with In-Situ
be used as datum during construction.
Concrete
- All four corners of the top slabs of the pier
1 General: units to establish grade and top levels.
i. This work consists of installing temporary - Two points on the longitudinal center line
bearings, casting concrete units in-situ and of each pier unit, one on each end to
setting the superstructure on permanent establish alignment.
bearings. The Contractor shall submit - One point on the longitudinal center line,
complete details and descriptions of all and at least on one corner of each unit
methods, arrangements and equipment which along every joint between cast-in-place
he intends to adopt, for approval before units to establish elevations and
construction work is started. alignments at every stage of construction.
ii. The construction method statement shall ii. The alignment and elevations of the cantilever
include casting of units, method of the tie- shall be checked by the Contractor and the
down of superstructure during cantilever Engineer independently within 1 hour of
construction, method of application of all sunrise on each day that the units are to be
temporary forces to be used for adjusting cast. The measurements made by the Engineer
horizontal and vertical alignment and to place and the Contractor shall agree to within 5 mm.
the structure on permanent bearings, details of
iii. The temporary bearing pads at the piers shall
work plans and safety measures. It shall also
be carefully placed. The top surface of these
include control methods to ensure the accuracy
pads must have the correct elevations,
of alignments of the constructed superstructure.
alignments and slopes as required by the
iii. Work equipment includes all machinery, working drawings and as established by the
devices, labor and material which are to be procedure described above. Shims may be
used for construction but which will not used underneath the pads to accomplish
become a permanent part of the completed accuracy. The Contractor shall check
superstructure. Construction equipment and elevations and alignment of the structure at
other loads shall not be placed upon any part every stage of construction and shall maintain
of the superstructure at any stage of a record of all these checks and of all
construction other than that which specifically adjustments and corrections made.
meets the requirements of total working load
3 Casting Procedures:
per unit, or has the approval of the Engineer.
This includes the post-tensioning, jointing, i. Casting of the units shall not begin until
jacking, grouting equipment, any other approval of the shop drawings, calculations
equipment whatsoever, workmen and and the post-tensioning system has been given.
materials of any kind. ii. Sequence. The units shall be match cast
iv. Unbalanced Load: During construction the beginning with each pier unit. After the pier
cantilever may be unbalanced by only one unit unit is cast all units on either side of the pier
at any time and be consistent with the holding- unit may be cast in order so long as match
down method adopted. In addition to the casting is maintained.
unbalanced load due to one unit, 0.5 kN/m2 iii. Care shall be taken in the set-up of each unit.
load is permissible anywhere on the cantilever. All materials to be encased within the concrete
This load includes workmen, miscellaneous of the segment shall be properly positioned
equipment and stored materials. The and supported. Before any concrete is placed,
Contractor shall take care to ensure that this the set up will be inspected and checked by the
allowable load is not exceeded. Engineer. All ducts shall be located within
2 Construction Schedule: 3mm of the location given on approved
drawings. The top surface of the units shall be
i. The Contractor shall submit a construction
free of depressions or high spots.
schedule showing the order of every phase and
stage of erection and construction of the iv. Forms shall not be removed until the concrete
superstructure. The Contractor shall prepare a has achieved the specified compressive
table of elevations and alignments required at strength has been proved by test cylinders
made and cured in the same manner as the

♦ 5-41 ♦
copy 249
unit. Care shall be taken in removing the forms iv. Each batch of resin mixed shall be tested for
to prevent spalling and chipping of the setting by compression and shear tests as
concrete. described below. No permanent prestress
4 Tolerances: shall be applied to a joint until the epoxy has
achieved the required strength. Should this
i. Formwork for box girder segments must satisfy
test show that the resin is not setting the joint
the following tolerances:
shall be broken and the resin removed. Set
- Web thickness, +10 mm or -5 mm. resin shall be removed by grit blasting. Further
- Thickness of bottom slab +5 mm, but 0 tests may be requested by the Engineer at
reduction in depth. various times to ensure that the material as
- Thickness of top slab +5 mm, but 0 mixed is complying with the Specification.
reduction in depth. v. All the instructions of the manufacturer and/or
- Overall width of unit, ±5 mm. the formulator shall be submitted to the
Engineer for agreement. Such agreed
- Overall depth of unit, ±5 mm.
instructions shall be adhered to in all respects.
- Length of match cast unit, ±10 mm, but not
vi. The supplier shall carry out a program of
cumulative and a maximum of 50 mm per
testing as described in FIP "Proposal for a
span.
standard for acceptance tests and verification
- Diaphragm dimensions, +10 mm or -5 mm. of epoxy bonding agents for segmental
- Grade at top and bottom flanges, ±3. construction", after consultation with the
ii. After erection, final post-tensioning, final Engineer on the range of temperatures and
corrections and adjustments are completed work cycles that are to be considered in the
and the structure has been placed on its tests. The Engineer may require the tests to be
permanent bearings, the superstructure shall witnessed either in person or by an approved
conform to the grade and alignment shown on independent authority.
the Drawings with due consideration for creep 3 Surface Preparation: The interface of the units shall
and superimposed load and dead load be lightly grit blasted before erection to remove laitance.
deflections within a tolerance of ± 5 mm Before applying the epoxy the interfaces must be clean
horizontally and ± 10 mm vertically. and free from laitance or any bond breaking material. Any
oil or grease which may be harmful shall be removed.
5.5.3.2 Glued Precast Segmental Construction The surface shall have no free moisture.
1 Where bridge decks are precast in segments and 4 Application of Epoxy: Application shall begin
assembled in position for glueing and stressing, the immediately after a batch has been mixed. Application
Contractor shall satisfy the Engineer that his proposed shall be to both interfaces to a total nominal thickness of 2
construction method will achieve the required standard of mm with a spatula or by hand. No epoxy may be applied
workmanship and finish. The Contractor shall submit within 25mm of any duct.
details for approval of all his forms, falsework, precasting 5 Preliminary Prestress: Immediately after the
factory and his method of lifting, transporting, assembling, interfaces are coated with epoxy, the unit shall be brought
supporting, threading cables, glueing and stressing the into position and the preliminary prestress applied. This
precast units before commencement of any work. preliminary prestress is to be just sufficient to start
2 Epoxy Adhesive: squeezing epoxy resin out of the joint. The amount of
i. The epoxy resin adhesive shall be supplied by prestress required will depend on the formulation of resin
an approved manufacturer. chosen by the Contractor. If this operation is not
completed within the life time of the first batch of epoxy to
ii. It shall be made up and packaged by approved
be applied, the units shall be moved apart. All the epoxy
formulators and to specifications agreed by the
on both interfaces shall be removed with spatulas and an
Engineer.
approved solvent. No epoxy may be applied to the joint
iii. The material shall be supplied in accurately until 24 hours after a solvent has been used. The life time
measured packs with the pack containing the shall be reckoned from the end of the pot life unless the
hardener clearly distinguished by both size and manufacturer's instructions direct otherwise. All excess
labelling. The pack containing the resin shall epoxy shall be cleaned off from the outer faces of the
be large enough to permit the addition of the webs and the soffit in such a way as not to smear the
hardener. Resin and hardener shall be concrete face.
pigmented with dissimilar colours to indicate
6 Records of Joining: The Contractor shall keep a
when even mixing has been completely
record of each joint with the following details:
attained and to produce an even gray colour to
match the concrete. i. Joint Number
ii. Date and Time of jointing

♦ 5-42 ♦
copy 249
iii. Batch number of resin and hardener containing the other 3 corners) 6 mm
iv. Weather conditions (temperature and - Flatness (the maximum deviation
humidity) continuously recorded from a 1.5 meter straight-edge
v. Results of tests. placed in any position on
nominally plane surface) 6 mm
7 Tolerances: These shall be similar to those
prescribed for balanced cantilever construction. - Cover to reinforcement +5 or -0 mm
- Prestressing tendons 3 mm in any direction
5.5.3.3 Precast Beam and slab Construction
- Dowel holes 3 mm in any direction
1 Manufacture of Prestressed Beams: 4 Composite Slab Construction:
i. The details of method of manufacture shall be i. Where in-situ concrete deck is cast to act
approved by the Engineer before work is compositely with precast beams, the beams
started. No changes shall subsequently be shall be installed to correct line and level,
made without the consent of the Engineer. starting from the outermost beam and working
ii. The Contractor shall inform the Engineer in inwards progressively. When the beams are
advance of the date of commencement of laid side by side just before erection the
manufacture and the dates when tensioning of difference in soffit level between adjacent
tendons, casting of members and transfer of beams shall nowhere exceed 6 mm. Where
stress will be undertaken for the first time for permanent soffit shutters are used, they shall
each type of beam. be to the approval of the Engineer and they
iii. The Contractor shall submit to the Engineer, shall be fixed securely so that there is no
not more than 7 days after the transfer of movement or grout loss during deck
stress, a certificate showing the force and concreting.
strain in the tendons immediately after they ii. The in-situ concrete deck over any one span
were anchored, the strength and age of the test shall be poured in one continuous operation
cylinders cast in accordance with this and shall be placed in such a sequence that the
Specification, and the minimum age in hours advancing edge of the freshly deposited
of the concrete at the time stress was applied concrete over the full width of deck or between
to the members. Copies of all 28 day cylinder longitudinal construction joints is
test results relating to the work shall be kept so approximately parallel to the deck supports.
that the identity of those who stressed the Lateral displacement of beams shall be
tendons, cast the concrete and transferred the prevented during the placing of in-situ concrete.
stress, on any member or line of members, can iii. The width of the in-situ deck shall be within
be traced. +25 mm of that specified. On curved bridge
iv. Where the Engineer requires tests to be carried deck, the in-situ deck may be in a series of
out on beams, the beams to which these tests straights such that the width is within +25 mm
related, shall not be dispatched to Site until the of that specified.
tests have been satisfactorily completed.
5.5.3.4 In-Situ Construction
2 Storage and Handling of Prestressed Members:
Members shall be firmly supported at such bearing 1 Where bridge decks are constructed in-situ, the
positions as will ensure that the stresses induced in them details of all forms and falsework shall first be approved
are always less than the permissible design stresses. by the Engineer. Dimensional variations shall not exceed
Members shall be lifted or supported only at the points the following tolerances:
specified and shall be handled and placed without impact. - Length ± 12 mm
3 Tolerance in Precast Members: - Width ± 10 mm
i. Dimensional variations shall not exceed the - Thickness ± 6 mm
tolerances given below:
- Levels + 10 mm or -0 mm
- Length ±12 mm
- Void Location 6 mm in any direction
- Width and depth ± 6 mm
- Cover to reinforcement + 5 mm or -0 mm
- Bow in the vertical plane +15 mm or -0 mm
- Prestressing tendons 5 mm in any direction
- Bow in the horizontal plane ±12 mm
- Difference between longest and 5.5.4 Method of Measurement, Basis of
shortest dimensions (check for Payment and Items in the Bills of
squareness of beam) in any plane 6 mm Quantities
- Twist (measured by the deviation
1 Concrete bridge construction is measured and
of any corner from the plane
identified in the Bill of Quantities in accordance with

♦ 5-43 ♦
copy 249
Clause 5.1.7. Measurement and basis of payment will be in 2 Finishes to floors and walls, including tiles, plaster
accordance with the stipulations for the corresponding paint and special finishes shall be as described in the
items in Sub-sections 5.1, 5.2 and 5.4. No direct payment Special Specification.
will be made for the stipulations of this Sub-section 5.5,
which work is considered to be subsidiary to the 5.6.3 Construction Requirements
requirements of Sub-sections 5.1, 5.2 and 5.4. The rates
and prices for the relevant items of Sub-sections 5.1, 5.2 5.6.3.1 Excavation
and 5.4 shall be deemed to include for all the stipulations
1 The Contractor shall provide the Engineer with
of this Sub-section 5.5. detailed written proposals of construction methods of
temporary and permanent works for the underpass
5.6 Vehicular and Pedestrian excavation. Details of ground water lowering, excavation
Underpasses and Animal support and support of adjacent existing structures shall
Crossings be accompanied by relevant shop drawings and
calculations. The work shall not proceed until the
Engineer has given approval to these construction
5.6.1 Description
proposals together with the relevant construction program
5.6.1.1 Scope for these works. Such approval, when given, shall not
relieve the Contractor of his responsibility for the
1 This Sub-section specifies the requirements for
correctness, safety and adequacy of such proposal.
concrete underpasses and animal crossings. These
2 Excavation and earthwork shall comply with the
requirements are additional to the requirements for
requirements of Section 2.
concrete generally, as described in the preceding Sub-
sections of this Section. 3 The Contractor shall comply with arrangements to
maintain the flow of pedestrian and vehicular traffic as
5.6.1.2 References stated in Section 1 of the Specification and as detailed on
the Drawings or as instructed by the Engineer. The
1 The relevant stipulations of the following Sections or
Contractor's attention is specifically drawn to his
Sub-sections of this Specification shall apply to this Sub-
responsibilities regarding the safety of such traffic near to
section.
open excavations for the works and the operation of heavy
Section 2 Earthworks plant and equipment and the provision and maintenance
Section 5 Concrete and Concrete Structures of adequate fences and barriers.
Section 6 Structural Steel and Other Metalwork 4 The Contractor shall protect and support existing
Section 8 Drainage statutory services during the excavation works as stated in
Section 1 and Section 18 of the Specification and co-
Section 10 Piling
operate with all statutory services to ensure efficiency of
Section 12 Sidewalks, Paved Areas and Curbs diversion of such services where necessary. In the event
Section 15 Road Lighting and Electrical that services are uncovered during excavation that have
Installations not been previously located on Drawings, the Engineer's
attention shall be drawn to the matter without delay.
5.6.2 Materials 5 Particular care shall be taken by the Contractor to
1 Materials shall conform to the relevant requirements minimize noise, dust and vibration caused by excavation
of the following Sections and Sub-sections of the operations especially where such nuisances prove
Specification: hazardous to existing structures.

Piles Section 10 6 Where ground water lowering operations prove


necessary the phasing of pumping operations and their
Concrete Sub-section 5.1
termination on completion of the underpass structure
Reinforcing Steel Sub-section 5.2 shall be approved by the Engineer.
Structural Steel and Other Metal Section 6 7 Where the Drawings show the use of piles or
Backfilling Sub-section 2.7 diaphragm walls to support the underpass structure or
Road Pavement Sections 3, 4 retain the subsoil the Contractor shall submit to the
Engineer for his approval a detailed method statement
Concrete Pavement Sub-section 5.7
and work program for this work together with the names
Waterproofing Sub-section 5.10 of any specialist firms he intends to use for this work.
Pipe culverts Sub-section 8.1
Drainage Section 8
Sidewalks, Paved Areas Section 12
Electrical Installations Section 15

♦ 5-44 ♦
copy 249
5.6.3.2 Structural Concrete 5.6.3.6 Bituminous Pavement Construction

1 The Contractor shall provide the Engineer with 1 Bituminous pavement construction shall be in
detailed written proposals for the formwork design of all accordance with all relevant requirements of Section 4
major parts of the underpass structure together with “Bituminous Pavement”.
proposals for transporting, placing and curing concrete 2 Drainage works shall be constructed in accordance
and sizes of pours. The works shall not proceed until the with all relevant requirements of Sub-Section 8.4
Engineer has given approval to these proposals; such “Drainage of Structures”.
approval when given shall not relieve the Contractor of his
responsibility for the efficacy of such proposals. 5.6.3.7 Electrical Works
2 The structural concrete work shall generally comply 1 The installation of lighting and electrical works for
with the relevant requirements of the following sections: shall be in accordance with details shown on the Drawings
Section 5.1 Concrete Materials and Mixes and the general requirements of Section 15 "Electrical
Section 5.2 Reinforcing Steel Installations".

Section 5.3 Reinforced Concrete Structures


5.6.4 Method of Measurement
Section 5.4 Prestressed Concrete Structures
1 Excavation, backfilling, piling, concrete,
5.6.3.3 Concrete Piles reinforcement, road pavement, sidewalks and paved areas,
drainage, ducts, waterproofing of concrete and electrical
1 The reinforced concrete construction of piling works
work shall be measured in accordance with the relevant
shown as the Drawings to support the underpass structure
Sections of this Specification.
or retain the subsoil shall comply with the relevant
requirements of Section 10. 2 Floor and wall finishes shall be measured in
accordance with the Special Specification for the
5.6.3.4 Waterproofing particular work.
1 The waterproofing of the underpass structure shall
be generally carried out in compliance with Section 5.10 5.6.5 Basis of Payment
"Waterproofing for Structures". 1 The amount of completed and accepted work,
2 Where membrane materials are specified on the measured as provided for above, will be paid for at the
Drawings for special use, such as P.V.C. membranes, the unit rates for the various items in the Bill of Quantities,
manufacturer's instructions for storage, handling and which rate shall be full compensation for supplying
installation of such membranes shall be strictly complied materials, transporting and placing, labor, equipment,
with. Where special details of junctions of such tools and other items necessary for the proper completion
membranes with walls and piles are necessary, drawings of the work.
shall be submitted to the Engineer for approval before
work commences. 5.6.6 Items in the Bill of Quantities
3 Tucks and seals for waterproofing shall be provided All work in underpasses and animal crossings is
at points of discontinuity such as edges, expansion joints separately identified in the Bill of Quantities and the
and rainwater drains. Sharp internal and external edges relevant items, as stated in the respective Sections of the
shall be chamfered with minimum 40mm x 40mm fillets. Specification are included.
The waterproofing membrane shall be protected from
damage during the execution of the work.
5.7 Cement Concrete Pavement
4 Where the Drawings show the use of waterstops in
concrete walls and slabs at construction joints and
5.7.1 Description
expansion joints the Contractor shall supply samples of
waterstop material for approval and provide details of 1 This Sub-section specifies the requirements for
waterstop assembly for approval. cement concrete pavement, with or without reinforcement,
5 The standard of acceptance of waterproofing shall be on a prepared base all as and where shown on the
that there shall be no damp patches or visible leaks on the Drawings. These requirements are additional to the
inside face of walls, roof or floor of the underpass requirements for concrete generally contained in the
structure. preceding Sub-sections of this Section

5.6.3.5 Concrete Pavement Construction 5.7.2 Materials


1 Concrete pavement construction shall be in 1 Cementitious Materials: Portland cement alone or in
accordance with all relevant requirements of Section 5.7 combination with one or more of blended hydraulic
“Concrete Pavement”. cement, expansive hydraulic cement, fly ash and other
pozzolans, ground granulated blast-furnace slag, and silica
fume.

♦ 5-45 ♦
copy 249
2 Base Course: Cement treated base course or throughout the work, unless otherwise accepted by
aggregate base course placed beneath the concrete Engineer.
pavement. 2 Portland Cement: ASTM C 150, Type I. In particular
cases, where the design requires the use of Sulfate
5.7.2.1 Forms
Resistant Cement (SRC), the Contractor shall submit to the
1 Form Materials: Plywood, metal, metal-framed Engineer’s approval an SRC material complying with the
plywood, or other approved panel-type materials to requirements of ASTM C 150, Type II.
provide full-depth, continuous, straight, smooth exposed 3 Aggregate: ASTM C33 or BS EN 12620, shall consist
surfaces. Use flexible or curved forms for curves of a of crushed stone, crushed or uncrushed gravel, or natural
radius 30 m or less. sand. The aggregate shall be composed of sound, tough,
2 Form-Release Agent: Commercially formulated durable particles and shall meet the requirements for
form-release agent that will not bond with, stain, or deleterious substances given in ASTM C33 or BS EN 12620.
adversely affect concrete surfaces and will not impair The aggregate in any size group shall not contain more
subsequent treatment of concrete surfaces. than 8 percent by weight of flat or elongated pieces when
tested in accordance with ASTM D4791. A flat or
5.7.2.2 Steel Reinforcement elongated particle is one having a ratio between the
1 Reinforcement Bars: ASTM A 615, Grade 60, maximum and the minimum dimensions of a
deformed. circumscribing rectangular prism exceeding 5 to 1.
Uniformly graded, from a single source, with coarse
2 Plain Steel Wire: ASTM A 82, cold-drawn steel.
aggregate as follows:
3 Welded Deformed Steel Wire fabric: ASTM A497.
4 Fine Aggregate: Conform to the requirements of
4 Joint Dowel Bars: Plain steel bars, ASTM A 615, ASTM C33 (Table 5.7.2.1) or BS EN 12620.
Grade 60. Cut bars true to length with ends square and
free of burrs. Sieve Designation Percentage by Weight
5 Dowel Bars: High tensile plain steel bars conforming (square openings) Passing Sieves
to BS 4449, ASTM A615, ASTM A616, or ASTM A617, and 3/8 in (9.5 mm) 100
shall be free from burring or other deformation restricting No. 4 (4.75 mm) 95-100
slippage in the concrete. Before delivery to the
No. 8 (2.36 mm) 80-100
construction site, a minimum of two-thirds of the length of
each dowel bar shall be painted with one coat of zinc- No. 16 (1.18 mm) 50- 85
chromate. If plastic or epoxy-coated steel dowels are used, No. 30 (600 micro-m) 25- 60
no zinc-chromate coating is required, except when No. 50 (300 micro-m) 10- 30
specified for a particular situation on the contract plans. No. 100 (150 micro-m) 2- 10
Coated dowels shall conform to the requirements given in
No. 200 (75 micro-m) 0- 3
AASHTO M254.
6 Tie Bars: ASTM A 615M, Grade 60, deformed. Table 5.7.2.1: Gradation for Fine Aggregate ASTM C33

7 Sleeves: Metal, of an approved design to cover 50 1 Coarse Aggregate: Conform to the requirements of
mm to 75 mm of the dowel, with a closed end and with a ASTM C33 (Table 5.7.2.2) or BS EN 12620.
suitable stop to hold the end of the bar at least 25 mm
from the closed end of the sleeve. Sleeves shall be of Sieve Designation Percentage by Weight
such design that they will not collapse during construction. (square openings) Passing Sieves
in (mm) 19 mm – 2.36 mm
8 Hook Bolts: ASTM F 568M, Property Class 4.6,
internally and externally threaded. Design hook-bolt joint 1 (25) 100
assembly to hold coupling against pavement form and in 3/4 (19) 90 - 100
position during concreting operations, and to permit
1/2 (12.5) -
removal without damage to concrete or hook bolt.
3/8 (9.5) 20 - 55
9 Bar Supports: Bolsters, chairs, spacers, and other
devices for spacing, supporting, and fastening No. 4 (4.75) 0 – 10
reinforcement bars, welded wire fabric, and dowels in
No. 8 (2.36) 0–5
place. Use wire bar type supports complying to CRSI's
"Manual of Standard Practice". Table 5.7.2.2: Gradation for Coarse Aggregate ASTM C33
10 Epoxy Repair Coating: Liquid two-part epoxy repair The percentage of wear shall be no more than 30% when
coating, compatible with epoxy coating on reinforcement. tested in accordance with ASTM C131.

5.7.2.3 Concrete Materials 6 Water: Water used in mixing or curing shall be as


clean and free of oil, salt, acid, alkali, sugar, vegetable, or
1 General: Use the same brand and type of other substances injurious to the finished product as
cementitious material from the same manufacturer possible. Water will be tested in accordance with the

♦ 5-46 ♦
copy 249
requirements of AASHTOT26, ASTM C94. Water known to cellulosic fiber, or ASTM D 1752 for cork or self-expanding
be of potable quality may be used without testing. cork.
2 Joint filler shall be furnished in a single piece for the
5.7.2.4 Admixtures
full depth and width required for the joint, unless
1 General: Admixtures certified by manufacturer to otherwise specified by Engineer. When the use of more
contain not more than 0.1 percent water-soluble chloride than one piece is authorized for a joint, the abutting ends
ions by mass of cement and to be compatible with other shall be fastened securely and held accurately to shape by
admixtures. stapling or other positive fastening means satisfactory to
2 Approval Process: The use of any material added to Engineer.
the concrete mix shall be approved by Engineer. Submit 3 Joint sealer shall: meet the requirements of Sub-
certificates indicating that the material to be furnished section 5.8 of the Specification and shall be of the type(s)
meets all of the requirements indicated below. In addition, specified on drawings.
the Engineer may require the submittal of complete test 4 Dowels: Galvanized steel, to the dimensions shown
data from an approved laboratory showing that the on drawings.
material to be furnished meets all of the requirements of
5 Bonding Agent: ASTM C 1059, Type II, non-re-
the cited specifications. Subsequent tests will be made of
dispersible, acrylic emulsion or styrene butadiene.
samples taken by Engineer from the supply of the material
being furnished or proposed for use on the work to 5.7.2.7 Concrete Mixes
determine whether the admixture is uniform in quality
with that approved. 1 Prepare design mixes, proportioned according to ACI
211.1 and ACI 301, for each type and strength of normal-
3 Chemical Admixtures: Water reducing, set-retarding,
weight concrete determined by either laboratory trial
and set-accelerating admixtures shall meet the
mixes or field experience.
requirements of ASTM C494.
2 Use a qualified independent testing agency for
i. Water-Reducing Admixture: ASTM C 494,
preparing and reporting proposed mix designs for the trial
Type A. batch method. Do not use Employer’s field quality-control
ii. High-Range, Water-Reducing Admixture: testing agency as the independent testing agency.
ASTM C 494, Type F. 3 Proportion mixes to provide concrete with the
iii. Water-Reducing and Accelerating Admixture: following properties using test specimens prepared in
ASTM C 494, Type E. accordance with ASTM C31 and tested with ASTM C78:
iv. Water-Reducing and Retarding Admixture: i. Flexural Strength (28 Days): 4.6 MPa
ASTM C 494, Type D. ii. Compressive Strength (28 Days): 35 MPA.
5.7.2.5 Curing Materials iii. The minimum cementitious material content
shall be 300 kg. per cubic meter. The ratio of
1 Absorptive Cover: AASHTO M 182, Class 2, burlap water to cementitious material, including free
cloth made from jute or kenaf, weighing approximately. surface moisture on the aggregates but not
305 g/sq.m. dry. including moisture absorbed by the aggregates
2 Moisture-Retaining Cover: ASTM C 171, shall not be more than 0.50 by weight.
polyethylene film or white burlap-polyethylene sheet. 4 Slump Limit:
3 Water: Potable. i. The mix determined shall be workable concrete
4 Evaporation Retarder: Waterborne, monomolecular having a slump for side-form concrete between
film forming, manufactured for application to fresh 25 mm and 50 mm as determined by ASTM
concrete. C143.
5 Clear Solvent-Borne Liquid-Membrane-Forming ii. Slump Limit for Concrete Containing High-
Curing Compound: ASTM C 309, Type 1, Class B. Range Water-Reducing Admixture: Not more
6 Clear Waterborne Membrane-Forming Curing than 200 mm after adding admixture to plant-
Compound: ASTM C 309, Type 1, Class B. or site-verified, 50- to 75-mm slump.

7 White Waterborne Membrane-Forming Curing iii. Absorption and permeability tests on hardened
Compound: ASTM C 309, Type 2, Class B. concrete shall be carried out in accordance
with ASTM C642.
5.7.2.6 Related Materials 5 Chemical Admixtures: Water-reducing and set-
1 Pre-molded joint filler shall conform to the controlling admixtures shall be added to the mix in the
requirements of ASTM D1751 and shall be punched to manner recommended by the manufacturer and in the
admit the dowels where called for on the plans. amount necessary to comply with the specification
Expansion and isolation joint-filler strips shall conform to requirements. Tests shall be conducted on trial mixes,
the requirements of ASTM D 1751 for asphalt-saturated during the mix design, in accordance with ASTM C494.

♦ 5-47 ♦
copy 249
6 Slip-form Construction: A high degree of uniformity iii. An overload up to 10 percent above the mixer's
in the plastic concrete is required. Some edge slump of nominal capacity may be permitted provided
the wet concrete behind the side form on the paving concrete test data for segregation and uniform
machine will occur, even with low slump concrete. This consistency are satisfactory, and provided no
may continue, though very slowly, until initial set has spillage of concrete takes place.
taken place. 5 Batch: Constituents shall be charged into the drum so
that a portion of the mixing water enters in advance of the
5.7.2.8 Concrete Mixing
cement and aggregates. The flow of water shall be
1 Ready-Mixed Concrete: Comply with requirements uniform, and all water shall be in the drum by the end of
and with ASTM C 94 and ASTM C 1116. Discharge of the the first 15 seconds of the mixing period. The throat of the
concrete shall be completed within a maximum of 1½ drum shall be kept free of such accumulations as may
hours, or before the drum has revolved 300 revolutions, restrict the free flow of materials into the drum.
whichever comes first. Mixing time shall be measured 6 Mixed Concrete:
from the time all materials, except water, are emptied into
i. Central mixing plant concrete shall be
the drum. However, when air temperature is between 30
transported in truck mixers, truck agitators, or
deg. C and 32 deg. C, reduce mixing and delivery time
non- agitating trucks. Non-agitating trucks are
from 1½ hours to 75 minutes; and when air temperature is
allowed to be used only when the location of
above 32 deg. C, reduce mixing and delivery time to 60
the mixing plant is very close to the site and to
minutes.
the approval of the Engineer.
i. The minimum required revolutions of the
ii. The time elapsing from the time water is added
mixing speed for transit mixed concrete may
to the mix until the concrete is deposited in
be reduced to not less than that recommended
place at the work site shall not exceed 30
by the mixer manufacturer.
minutes when the concrete is hauled in non-
ii. The number of revolutions recommended by agitating trucks, nor 45 minutes when the
the mixer manufacturer shall be indicated on concrete is hauled in truck mixers or truck
the manufacturer's serial plate attached to the agitators. All these operations must be
mixer. performed within 45 minutes after the initial
2 Concrete: mixing operations and the water-cement ratio
i. Concrete may be mixed at the work site must not be exceeded.
location in a central mix plant approved by the iii. Admixtures for increasing the workability or for
Engineer and shall be transported in truck accelerating the set will be permitted only
mixers. The mixer shall be of an approved when specified for in the contract.
type and capacity.
5.7.2.9 Limitations of Mixing:
ii. Furnish test data acceptable to Engineer
verifying that the model of the mixer will 1 No concrete shall be mixed, placed, or finished when
produce uniform concrete conforming to the the natural light is insufficient, unless an adequate and
provisions of ASTM C 94 at the reduced approved artificial lighting system is operated.
number of revolutions shown on the serial 2 During periods of hot weather when the maximum
plate. daily air temperature exceeds 30 deg. C, the following
3 When mixed at the work site or in a central mixing precautions shall be taken: the forms and/or the
plant, the mixing time shall not be less than 50 seconds underlying material shall be sprinkled with water
nor more than 90 seconds. Mixing time ends when the immediately before placing the concrete. The concrete
discharge chute opens. Transfer time in multiple drum shall be placed at the coolest temperature practicable, and
mixers is included in mixing time. The contents of an in no case shall the temperature of the concrete when
individual mixer drum shall be removed before a placed exceed 32 deg, C. The aggregates and/or mixing
succeeding batch is emptied therein. water shall be cooled as necessary to maintain the
4 Mixer: concrete temperature at or not more than the specified
max. Refer to ACI 305 R-77 for Hot Weather Concreting.
i. The mixer shall be operated at the drum speed
recommended by the manufacturer as stated
nameplate on the mixer. Any concrete mixed
5.7.3 Construction Requirements
less than the specified time shall be discarded 5.7.3.1 Preparation
at Contractor’s own expense.
1 Proceed with pavement layers only after
ii. The volume of concrete mixed per batch shall
nonconforming conditions have been corrected and
not exceed the mixer's nominal capacity, as
subgrade is ready to receive pavement.
shown on the manufacturer's standard rating
plate on the mixer. 2 Remove loose material from compacted sub-base
surface immediately before placing concrete.

♦ 5-48 ♦
copy 249
5.7.3.2 Edge Forms and Screed Construction matter that may adversely affect or reduce
bond. Reinforcing steel with rust, mill scale, or
1 Set, brace, and secure edge forms, bulkheads, and a combination of both will be considered
intermediate screed guides for paving to required lines, satisfactory, provided the minimum
grades, and elevations. Install forms to allow continuous dimensions, weight, and tensile properties of a
progress of work and so that forms can remain in place at hand wire-brushed test specimen are not less
least 24 hours after concrete placement. than the applicable ASTM specification
2 Forms shall be securely set so that they can requirements.
withstand impacts and vibration of consolidating and ii. Accurately position, support, and secure
finishing equipment without visible spring or settlement. reinforcement against displacement by
Extend flange braces on the base outward for not less formwork, construction, or concrete placement
than two thirds of the height of the form. Remove bent, operations. Locate and support reinforcing
twisted or broken forms, and forms with damaged top bars by metal chairs, runners, bolsters, spacers,
surfaces. Use repaired forms only with inspection and and hangers, as required.
approval. Built-up forms will not be allowed, unless
iii. Arrange, space, and securely tie bars and bar
specifically approved. The top faces of forms are not to
supports to hold reinforcement in position
vary from a true plane by more than 3 mm in 3m. The
during concrete placement operations. Set wire
upstanding leg shall be perpendicular to the base and is
ties so ends are directed into concrete, not
not to vary horizontally from true alignment by more than
toward exposed concrete surfaces.
6 mm at any point. The ends of abutting sections lock
together tightly for secure setting. Local defects, such as iv. Install welded wire fabric in as long lengths as
kinks in steel forms, will not be allowed. practicable. Lap adjoining pieces at least one
full mesh and lace splices with wire. Offset end
3 Setting: Forms shall be set ahead of concrete
laps in adjacent widths to prevent continuous
placement and staked into place with at least three pins
laps in either direction.
for each 3 m section. A pin shall be placed at each side of
every joint. Form sections shall be tightly locked and free 5.7.3.5 Joints
from movement in any direction. Excessive settlement or
springing from operation of the finishing machine will not 1 General: Form construction, expansion, and
be allowed. Forms shall be cleaned and oiled before contraction joints and tool edgings true to line with faces
concrete placement. The alignment and grade elevations perpendicular to surface plane of concrete. Construct
of the forms shall be checked, and corrections made transverse joints at right angles to centerline, unless
immediately before placing concrete. Reset and recheck otherwise indicated. When joining existing pavement,
forms when they have been disturbed, or when the grade place transverse joints to align with previously placed
has become unstable. joints, unless otherwise indicated.
4 Clean forms after each use and coat with form 2 Construction Joints: Set construction joints at side
release agent as required, to ensure separation from and end terminations of pavement and at locations where
concrete without damage. pavement operations are stopped for more than one-half
hour, unless pavement terminates at isolation joints.
5 Removal: Do not remove forms until the concrete
has set for at least 12 hours, unless otherwise approved or 3 Expansion Joints: Form expansion joints of
where auxiliary forms are used temporarily in widened preformed joint-filler strips abutting concrete curbs, catch
areas. Remove forms carefully to avoid damaging the basins, manholes, inlets, structures, walks, other fixed
pavement, and after removal, the side of the slab shall be objects, and where indicated.
cured by the method specified in the current specification. i. Locate expansion joints at intervals indicated
on drawings.
5.7.3.3 Steel Reinforcement
ii. Extend joint fillers full width and depth of joint.
1 General: Comply with CRSI's ‘Manual of Standard
iii. Terminate joint filler not less than 12 mm or
Practice’ for fabricating reinforcement and with
more than 25 mm below finished surface if
recommendations in CRSI's "Placing Reinforcing Bars" for
joint sealant is required.
placing and supporting reinforcement.
iv. Place top of joint filler flush with finished
5.7.3.4 Placement of Reinforcement concrete surface if joint sealant is not indicated.
v. Furnish joint fillers in one-piece lengths.
1 Reinforced Concrete Pavement: Comply with
Concrete Reinforcing Steel Institute's recommended Where more than one length is required, lace
practice for ‘Placing Reinforcing Bars’, for details and or clip joint-filler sections together.
methods of reinforcement placement and supports, and as vi. Protect top edge of joint filler during concrete
herein specified: placement with metal, plastic, or other
i. At the time concrete is placed the reinforcing temporary preformed cap. Remove protective
bars shall be free of mud, oil or other organic

♦ 5-49 ♦
copy 249
cap after concrete has been placed on both 7 Dowel Bars: Dowel bars or other load-transfer units
sides of joint. of an approved type shall be placed across transverse or
4 Longitudinal and Transverse Joints: Construct as other joints in the manner as specified on the Drawings.
indicated on the Drawings and in accordance with the i. They shall be of the dimensions and spacing as
following requirements: shown and held rigidly in the middle of the
i. All joints shall be constructed true to line with slab depth in the proper horizontal and vertical
their faces perpendicular to the surface of the alignment by an approved assembly device left
pavement. permanently in place.

ii. Joints shall not vary more than 12mm from a ii. The dowel or load-transfer and joint devices
true line or from their designated position. shall be rigid enough to permit complete
assembly as a unit ready to be lifted and placed
iii. The vertical surface of the pavement adjacent
into position.
to all expansion joints shall be finished to a
true plane and edged to a radius of 6mm or as iii. A metal, or other type dowel expansion cap or
shown on the plans. sleeve shall be furnished for each dowel bar
used with expansion joints.
iv. The surface across the joints shall be tested
with a 3m straightedge as the joints are iv. These caps shall be substantial enough to
finished and any irregularities in excess of prevent collapse and shall be placed on the
6mm shall be corrected before the concrete has ends of the dowels as shown on the Drawings.
hardened. v. The caps or sleeves shall fit the dowel bar
v. Transverse joints shall be at right angles to the tightly and the closed end shall be watertight.
centerline of the pavement and shall extend the 8 Fix dowel bars and support assemblies at joints
full width of the slab. where indicated. Lubricate or asphalt-coat one-half of
vi. The transverse joints in succeeding lanes shall dowel length to prevent concrete bonding to one side of
be placed in line with similar joints in the first joint.
lane. All joints shall be so prepared, finished, 9 Joints Installation:
or cut to provide a groove of the width and i. The top of an assembled joint device shall be
depth shown on the plans. set at the proper distance below the pavement
5 Slip-Form Construction: Transverse joints with surface and the elevation shall be checked.
dowels shall be carefully placed to ensure the dowels are Such devices shall be set to the required
accurately placed and not disturbed during concrete position and line and shall be securely held in
placement. place by stakes or other means during the
i. Transverse dowels will require use of an pouring and finishing of the concrete. The pre-
apparatus to firmly hold the dowels molded joint material shall be placed and held
perpendicular to the joint and parallel to the in a vertical position; if constructed in sections,
slab surface. there shall be no offsets between adjacent
units. Dowel bars shall be checked for exact
ii. During the concrete placement operation, it is
position and alignment as soon as the joint
advisable to place plastic concrete directly on
device is staked in place, and the device shall
the dowel assembly immediately prior to
be tested to determine whether it is firmly
passage of the paver to help maintaining dowel
supported. The maximum permissible
alignment.
tolerance on dowel bar alignment in each plane,
6 Tie Bars: Deformed bars shall be fixed in longitudinal horizontal and vertical, shall not exceed 2
joints as shown on the Drawings. percent or 6mm per 300 mm of a dowel bar.
i. Tie bars shall be placed at right angles to the The most effective way to obtain proper
centerline of the concrete slab and shall be alignment is with well-fabricated dowel baskets
spaced at intervals shown on Drawings. and dowel assemblies.
ii. Tie bars shall be held in position parallel to the ii. When joints in concrete pavements are sawed,
pavement surface and midway between the the joints shall be cut as shown on the
surfaces of the slab. Drawings. The circular cutter shall be capable
iii. When tie bars extend into an unpaved lane, of cutting a groove in a straight line and shall
they may be bent at right angles against the produce a slot at least 3mm wide and to the
form at longitudinal construction joints, unless depth shown on the plans. When shown on the
threaded bolt or other assembled tie bars are plans or required by the specifications, the top
specified. portion of the slot groove shall be widened by
means of a second shallower cut or by suitable
iv. Tie bars shall not be painted, greased, or
and approved beveling to provide adequate
enclosed in sleeves.
space for joint sealers. Sawing of the joints

♦ 5-50 ♦
copy 249
shall commence as soon as the concrete has material is used, the installation and edge
hardened sufficiently to permit cutting without finish shall be according to the manufacturer's
chipping, spalling, or tearing. Sawing shall be instructions. The sawed groove shall be
carried on both during the day and night as straight and of uniform width and depth. In
required. The joints shall be sawed at the either case, the groove shall be clean cut so
required spacing consecutively in sequence of that spalling will be avoided at intersections
the concrete placement, unless otherwise with transverse joints. Tie bars shall be
approved by Engineer. installed across these joints where indicated on
10 Contraction Joints: Form weakened-plane the plans.
contraction joints, sectioning concrete into areas as iii. Expansion type: longitudinal joints shall be
indicated. Construct contraction joints for a depth equal to informed as indicated on the Drawings. The
at least one-fourth of the concrete thickness, as follows: pre-molded filler, of the thickness shown shall
i. Grooved Joints: Form contraction joints after extend for the full depth and width of the slab
initial floating by grooving and finishing each at the joint, except for space for sealant at the
edge of joint with groover tool to the radius top of the slab. The filler shall be securely
shown on drawings. Repeat grooving of staked or fastened into position perpendicular
contraction joints after applying surface to the proposed finished surface. A metal cap
finishes. Eliminate groover marks on concrete shall be provided to protect the top edge of the
surfaces. filler and to permit the concrete to be placed
and finished. After the concrete has been
ii. Sawed Joints: Form contraction joints with
placed and struck off, the cap shall be carefully
power saws equipped with shatterproof
withdrawn leaving the space over the pre-
abrasive or diamond-rimmed blades. Cut
molded filler. The edge of the joint shall be
joints into concrete to the width shown on
finished and tooled while the concrete is still
drawings, when cutting action will not tear,
plastic.
abrade, or otherwise damage surface and
before developing random contraction cracks. 12 Transverse Joints:

11 Longitudinal Joints: i. Expansion Type:

i. Construction type: longitudinal construction - Transverse expansion joints shall be


joints necessary for lane construction shall be installed at the locations and spacing as
formed against suitable side forms as indicated shown on the plans. The joints shall be
in the plans. Wooden forms may be used installed at right angles to the centerline
under special conditions, when approved by and perpendicular to the surface of the
Engineer. Where butt-type joints with dowels pavement. The joints shall be formed and
are designated, the dowels for this type shall finished to ensure complete separation of
be painted and greased. The edges of the joint the slabs. Joint filler shall be of a pre-
shall be finished with a grooving tool or edging molded type as specified and shown on the
tool, and a space or slot shall be formed along Drawings and shall extend the full width of
the joint of the dimensions, as indicated, to the pavement strip.
receive the joint sealing material. Longitudinal - All concrete shall be cleaned from the top
construction joints shall be sawed to provide a of the joint material. Before the pavement
groove at the top conforming to the details and is opened to traffic, it shall be swept clean
dimensions indicated on the plans. Provisions and filled with approved joint sealing
shall be made for the installation of tie bars as material.
noted on the plans. - All devices used for the fixing expansion
ii. Contraction or weakened - plane type: joints shall be approved by the Engineer.
longitudinal groove-formed or sawed joints in They shall be easily removable without
the top of the slab shall be formed where disturbing the concrete and held in proper
indicated on the Drawings. The groove shall transverse and vertical alignment.
be formed in the plastic concrete with suitable Immediately after forms are removed, any
tools or material to obtain the width and depth concrete bridging the joint space at the
specified, or it shall be sawed with approved ends shall be removed for the full width
equipment in the hardened concrete to the and depth of the joint.
dimensions required. When the groove is - When specified, expansion joints shall be
formed in plastic concrete, it shall be true to equipped with dowels of the dimensions
line with not more than 6mm variation in 3m; it and at the spacing and location indicated
shall be uniform in width and depth; and the on the Drawings. The dowels shall be
sides of the groove shall be finished even and firmly supported in place and accurately
smooth with an edging tool. If an insert aligned parallel to the subgrade and the

♦ 5-51 ♦
copy 249
centerline of the pavement by means of a 2 If damage occurs to the base course, it shall be relaid
dowel assembly, which will remain in the for the full depth, or the damaged areas filled with
pavement and will ensure that the dowels concrete integral with the pavement.
are not displaced during construction. 3 A multiple-pin template weighing not less than 454
ii. Transverse contraction joints, weakened-plane kg. per 6 m or other approved template shall be provided
joints, or both, shall be formed at the locations and operated on the forms immediately in advance of the
and spacing as shown on the Drawings by placing of the concrete. The template shall be propelled
forming a groove or cleft in the top of the slab only by hand and not attached to a tractor or other power
while the concrete is still plastic or by sawing a unit. Templates shall be adjustable so that they may be
groove into the concrete surface after the set and maintained at the correct contour of the
concrete has hardened in the same manner as underlying course. The adjustment and operation of the
specified. Dowel bar assemblies shall be template shall be such as to provide an accurate re-test of
installed as shown on the Drawings. the grade before placing the concrete thereon. All excess
iii. Transverse construction joints shall be formed material shall be removed. Low areas may be filled with
at the end of each day's placing operations and concrete integral with the pavement.
at any other points within a paving lane when
5.7.3.8 Handling, Measuring, and Batching Material
concrete placement is interrupted for more
than 30 minutes or it appears that the concrete 1 Batch plant site: layout, equipment, and provisions
will obtain its initial set before fresh concrete is for transporting material shall assure a continuous supply
placed. Construction joints planned in advance of material to the work.
shall be located at a contraction or expansion 2 Stockpiles: Build up stockpiles in layers of not more
joint where possible but they shall not be than 900 mm in thickness. Each layer shall be completely
located within 2500 mm of a regular spaced in place before beginning the next layer and shall not be
transverse joint. If the pouring of the concrete allowed to "cone" down over the next lower layer.
is stopped, causing a joint to fall within this Aggregates from different sources and of different grading
limit, it shall not be formed, and the fresh shall not be stockpiled together. Improperly placed
placed concrete shall be removed back to the stockpiles will not be accepted by Engineer.
2500 mm limit.
3 Aggregates: Handle from stockpiles or other sources
13 Edging: Tool edges of pavement, gutters, curbs, and to the batching plant in such manner to secure the
joints in concrete after initial floating with an edging tool specified grading of the material. Aggregates that have
to the radius shown on drawings. Repeat tooling of edges become segregated or mixed with earth or foreign
after applying surface finishes. Eliminate tool marks on material shall not be used. All aggregates produced or
concrete surfaces. handled by hydraulic methods, and washed aggregates,
shall be stockpiled or binned for draining at least 12 hours
5.7.3.6 Conditioning of Underlying Course, Slip-Form
before being batched.
Construction
4 Cement: Store in weather tight structures with raised
1 The base course on which the pavement will be floors or in suitable silos. Different consignments of
placed shall extend approximately 900 mm beyond the bagged cement shall be used separately and in the order
paving machine track, or wider if required, to support the of delivery. Cement manufactured more than twelve
paver without any noticeable deformation. months prior to proposed use on site shall not be used. If
2 If damage occurs to the base course, it shall be relaid cement becomes partially set or contains lumps of caked
for the full depth or the damaged areas filled with concrete cement, it shall be rejected. Cement salvaged from
integral with the pavement. If traffic is allowed to use the discarded or used bags shall not be used.
prepared grade, the grade shall be checked and corrected 5 Aggregate: Fine and coarse aggregate shall be
immediately before the placement of concrete. separately weighed into hoppers in the respective
3 The prepared grade shall be well moistened with amounts approved by Engineer in the job mix. Cement
water, without saturating, immediately ahead of concrete shall be measured by weight. Separate scales and hopper,
placement to prevent rapid loss of moisture from concrete. with a device to positively indicate the complete discharge
of the batch of cement into the batch box or container,
5.7.3.7 Conditioning of Underlying Course, Side-Form shall be used for weighing the cement.
Construction 6 When required by the contract or when permitted,
batching plants shall be equipped to proportion
1 The prepared grade shall be well moistened with
aggregates and bulk cement, by weight, automatically
water, without saturating, immediately ahead of concrete
using interlocked proportioning devices of an approved
placement to prevent rapid loss of moisture from the
type.
concrete.
7 Water shall be measured either by volume or by
weight accurately measured to within plus or minus 1

♦ 5-52 ♦
copy 249
percent of required amounts. Unless the water is to be application of curing compound by hand-operated
weighed, the water-measuring equipment shall include an pressure sprayers will be permitted only on small widths
auxiliary tank from which the measuring tank shall be or shapes of slabs as approved, and on concrete surfaces
filled. The measuring tank shall be equipped with an exposed by removal of forms. When application is made
outside tap and valve to provide for checking the setting, by hand-operated sprayer, apply the second coat in a
unless other means are provided for readily and direction approximately at right angles to the direction of
accurately determining the amount of water in the tank. the first coat. The compound shall form a uniform,
The volume of the auxiliary tank shall be at least equal to continuous, cohesive film that will not check, crack or peel,
that of the measuring tank and is free of pinholes and other discontinuities. Apply an
8 Methods and equipment for adding air-entraining additional coat, if pinholes, abrasions or other
agent or other admixtures to the batch, when required, discontinuities exist, to the affected areas within 30
shall be approved by Engineer. All admixtures shall be minutes. Re-spray concrete surfaces that are subjected to
measured into the mixer with an accuracy of plus or heavy rainfall or abrasive wind-blown sand within three
minus 3 percent. hours after the curing compound has been applied. Re-
spray areas where the curing membrane is damaged by
5.7.3.9 Concrete Protection and Curing subsequent construction operations within the curing
period.
1 General: Protect concrete against loss of moisture
and rapid temperature changes for at least seven days i. Precautions shall be taken to ensure that
from beginning of the curing operation. Unhardened concrete is properly cured at sawed joints, but
concrete shall be protected from rain and flowing water. that no curing compound enters the joints.
All equipment needed for adequate curing and protection Tightly seal top of joint opening and joint
of the concrete shall be on hand, ready to use before groove at exposed edges before concrete
concrete placement begins. A standby water truck adjacent to the joint is re-sprayed. Seal joint
capable of dispensing a fine spray of water shall be groove by using method that will prevent loss
continuously available during paving operations to keep of moisture from the joint during the specified
the concrete moist until the curing compound has been curing period.
applied. Provide protection as necessary to prevent ii. Provide approved standby facilities for curing
cracking of the pavement due to temperature changes concrete pavement at an accessible location at
during the curing period. the jobsite for use in the event of failure of the
2 Membrane Curing: Apply a uniform coating of white spraying equipment, or other conditions that
pigmented-type membrane curing compound to the entire might prevent correct application of curing
exposed surface of the concrete by means of an approved compound at the proper time.
automatic spraying machine as soon as free water has iii. Protect concrete surfaces to which curing
disappeared from the finished surface. Coat formed compounds have been applied from pedestrian
surfaces immediately after the forms are removed and in and vehicular traffic and from any other
no case longer than one hour after removal of forms. Do possible damage to the continuity of the
not allow concrete to dry before application of the membrane, during the curing period except as
membrane. If any drying has occurred, moisten the required for joint-sawing operations and
surface of the concrete with a fine spray of water and surface testing.
apply curing compound as soon as the free water 3 Protection: Protect pavement and its appurtenances
disappears. The spraying machine shall be self-propelled from damage caused by traffic. The Engineer will decide
and shall ride on the side forms, or previously constructed when the pavement may be cleaned and opened to traffic,
pavement straddling the newly paved lane. The machine but not earlier than 14 days after concrete placing. Protect
shall have one or more spraying nozzles that can be freshly placed concrete from premature drying and
controlled and operated to completely and uniformly excessive cold or hot temperatures. Comply with the
cover the pavement surface with the required amount of recommendations of ACI 306R for cold weather protection
curing compound. The curing compound shall be and ACI 305R for hot weather protection during curing.
thoroughly and continuously mechanically agitated in the
drum used for the spraying operation throughout the full 5.7.3.10 Concrete Placement
depth of the drum during application. Air agitation may
1 Inspection: Before placing concrete, inspect and
be used only to supplement mechanical agitation. Provide
complete formwork installation, reinforcement steel, and
sufficient spraying pressure to produce a fine spray to
items to be embedded or cast in. Notify other trades to
cover the surface thoroughly and completely with a
permit installation of their work.
uniform film. Maintain spray equipment in good
mechanical condition, and provide adequate wind guard 2 Moisten subbase to provide a uniform dampened
to the spray nozzle. Apply curing compound with an condition at the time concrete is placed. Do not place
overlapping coverage that will give a two-coat application concrete around manholes or other structures until they
at a coverage rate of not more than 0.1 Liter per/sq.m. for are at the required finish elevation and alignment.
each coat or as recommended by the manufacturer. The

♦ 5-53 ♦
copy 249
3 Comply with requirements and with joint assemblies by means of vibrators inserted
recommendations in ACI 304R for measuring, mixing, in the concrete. Vibrators shall not be
transporting, and placing concrete. permitted to come in contact with a joint
4 Do not add water to concrete during delivery, at Site, assembly, the grade, or a side form. In no case
or during placement. shall the vibrator be operated longer than 15
seconds in any one location, nor shall the
5 Deposit and spread concrete in a continuous
vibrators be used to move the concrete.
operation between transverse joints. Do not push or drag
concrete into place or use vibrators to move concrete into iv. Concrete shall be deposited as near to
place. expansion and contraction joints as possible
without disturbing them but shall not be
6 Consolidate concrete by mechanical vibrating
dumped from the discharge bucket or hopper
equipment supplemented by hand-spading, rodding, or
onto a joint assembly unless the hopper is well
tamping. Use equipment and procedures to consolidate
centered on the joint assembly.
concrete according to recommendations in ACI 309R.
Consolidate concrete along face of forms and adjacent to v. Should any concrete materials fall on or be
transverse joints with an internal vibrator. Keep vibrator worked into the surface of a completed slab,
away from joint assemblies, reinforcement, or side forms. they shall be removed immediately by
Use only square-faced shovels for hand-spreading and approved methods.
consolidation. Consolidate with care to prevent 10 Slip-Form Method:
dislocating reinforcement, dowels, and joint devices. i. The concrete shall be placed with an approved
7 Following the placing of the concrete, it shall be crawler-mounted, slip-form paver designed to
struck off to conform to the cross section shown on the spread, consolidate, and shape the freshly
Drawings and to level such that when the concrete is placed concrete in one complete pass of the
properly consolidated and finished, the surface of the machine so that a minimum of hand finishing
pavement shall be at the level shown on the Drawings. will be necessary to provide a dense and
8 Screed pavement surfaces with a straightedge and homogeneous pavement in conformance with
strike off. Commence initial floating using bull floats or requirements of the plans and specifications.
darbies to form an open textured and uniform surface The concrete should be placed directly on top
plane before excess moisture or bleed water appears on of the joint assemblies to prevent them from
the surface. Do not further disturb concrete surfaces moving when the paver moves over them. Side
before beginning finishing operations or spreading dry- forms and finishing screeds shall be adjustable
shake surface treatments. to the extent required to produce the specified
pavement edge and surface tolerance. The side
9 Side Form Method:
forms shall be of dimensions, shape, and
i. The concrete shall be deposited on the strength to support the concrete laterally for a
moistened grade to require as little re-handling sufficient length of time so that no appreciable
as possible. Unless truck mixers, truck agitators, edge slumping will occur. Final finishing shall
or non agitating hauling equipment are be accomplished while the concrete is still in
equipped with means for discharge of concrete the plastic state.
without segregation of the materials, the
ii. In the event that slumping or sloughing occurs
concrete shall be unloaded into an approved
behind the paver or if there are any other
spreading device and mechanically spread on
structural or surface defects, which, in the
the grade to prevent segregation of the
opinion of the Engineer, cannot be corrected
materials. Placing shall be continuous between
within permissible tolerances, the Engineer
transverse joints without the use of
may halt paving operations until proper
intermediate bulkheads. Necessary hand
adjustment of the equipment or procedures
spreading shall be done with shovels - not
have been made. In the event that satisfactory
rakes. Workmen shall not be allowed to walk in
pavement procedures are not achieved after
the freshly mixed concrete with boots or shoes
more than 600 m of single lane paving, the
coated with earth or foreign substances.
balance of the work shall be completed with
ii. When concrete is to be placed adjoining a the use of standard metal forms and the
previously constructed lane of pavement and formed method of placing and curing.
when mechanical equipment will be operated
11 Slip-Form Pavers: When automatic machine
upon the existing lane of pavement, the
placement is used for pavement, submit revised mix
concrete shall be at least 7 days old and at a
design and laboratory test results that meet or exceed
flexural strength approved by Engineer.
requirements. Produce pavement to required thickness,
iii. Concrete shall be thoroughly consolidated lines, grades, finish, and jointing as required for formed
against and along the faces of all forms and pavement. Compact subbase and prepare subgrade of
along the full length and on both sides of all

♦ 5-54 ♦
copy 249
sufficient width to prevent displacement of paver machine 5.7.3.12 Final Strike-Off, Consolidation and Finishing
during operations.
1 Sequence: The sequence of operations shall be the
12 When adjoining pavement lanes are placed in
strike-off and consolidation, floating and removal of
separate pours, do not operate equipment on concrete
laitance, straight edging, and final surface finish. The
until pavement has attained 85 percent of its 28-day
addition of superficial water to the surface of the concrete
compressive strength.
to assist in finishing operations generally will not be
13 Hot-Weather Placement: Place concrete according to permitted. If the application of water to the surface is
recommendations in ACI 305R and as follows when hot- permitted, it shall be applied as a fog spray by means of
weather conditions exist: approved spray equipment.
i. Cool ingredients before mixing to maintain 2 Strike-Off of Concrete: Following the placing of the
concrete temperature at time of placement concrete, it shall be struck off to conform to the cross
below 32 deg. C. Chilled mixing water or section shown on the plans and to an elevation such that
chopped ice may be used to control when the concrete is properly consolidated and finished,
temperature, provided water equivalent of ice the surface of the pavement shall be at the elevation
is calculated to total amount of mixing water. shown on the plans.
Using liquid nitrogen to cool concrete is
3 Finishing at Joints:
Contractor's option.
i. Concrete adjacent to joints shall be compacted
ii. Cover reinforcement steel with water-soaked
or firmly placed without voids or segregation
burlap so steel temperature will not exceed
against the joint material; it shall be firmly
ambient air temperature immediately before
placed without voids or segregation under and
embedding in concrete.
around all load-transfer devices, joint assembly
iii. Fog-spray forms, reinforcement steel, and / or units, and other features designed to extend
stabilized base just before placing concrete. into the pavement.
Keep aggregate base moisture uniform without
ii. Concrete adjacent to joints shall be
standing water, soft spots, or dry areas.
mechanically vibrated. After the concrete has
iv. Concreting shall not be permitted when the been placed and vibrated adjacent to the joints,
rate of evaporation exceed 1.0 kg./sq.m./h. (ACI the finishing machine shall be operated in a
305R "Hot Weather Concreting"). The rate of manner to avoid damage or misalignment of
evaporation can be estimated from Fig. 2.1.5 of joints.
ACI 305R with the prevailing temperature,
iii. If uninterrupted operations of the finishing
relative humidity, and wind speed. The
machine, to, over, and beyond the joints, cause
evaporation rate can also be determined more
segregation of concrete, damage to, or
accurately by evaporating water from a cake
misalignment of the joints, the finishing
pan having an area of approximately 1 ft2
machine shall be stopped when the screed is
(0.093 sq.m.). The pan is filled with water and
approximately 200mm from the joint.
the mass determined every 15 to 20 min to
iv. Segregated concrete shall be removed from
determine .the evaporation rate, which is equal
the front of and off the joint, the screed shall be
to the loss of water mass from the pan. A
lifted and set directly on top of the joint, and
balance of at least 2500 g capacity is
the forward motion of the finishing machine
satisfactory.
shall be resumed. Thereafter, the finishing
v. No concreting shall take place when the
machine may be run over the joint without
ambient temperature exceeds 40 deg. C.
lifting the screed, provided there is no
5.7.3.11 Concrete Finishing segregated concrete immediately between the
joint and the screed or on top of the joint.
1 General: Wetting of concrete surfaces during 4 Machine Finishing:
screeding, initial floating, or finishing operations is
i. The concrete shall be spread as soon as it is
prohibited.
placed, and it shall be struck off and screeded
2 Float Finish: Begin the second floating operation by an approved finishing machine. The
when bleed-water sheen has disappeared and the machine shall go over each area as many times
concrete surface has stiffened sufficiently to permit and at such intervals as necessary to give the
operations. Float surface with power-driven floats, or by proper consolidation and to leave a surface of
hand floating if area is small or inaccessible to power units. uniform texture.
Finish surfaces to true planes. Cut down high spots, and
ii. Excessive operation over a given area shall be
fill low spots. Refloat surface immediately to uniform
avoided. When side forms are used, the tops
granular texture.
of the forms shall be kept clean by an effective
device attached to the machine, and the travel

♦ 5-55 ♦
copy 249
of the machine on the forms shall be iii. Any depressions shall be immediately filled
maintained true without lift, wobbling, or other with freshly mixed concrete, struck off,
variation tending to affect the precision finish. consolidated, and refinished. High areas shall
During the first pass of the finishing machine, a be cut down and refinished.
uniform ridge of concrete shall be maintained iv. Special attention shall be given to assure that
ahead of the front screed for its entire length. the surface across joints meets the
iii. When in operation, the screed shall be moved requirements for smoothness. Straightedge
forward with a combined longitudinal and testing and surface corrections shall continue
transverse shearing motion, always moving in until the entire surface is found to be free from
the direction in which the work is progressing, observable departures from the straightedge
and so manipulated that neither end is raised and until the slab conforms to the required
from the side forms during the striking-off grade and cross section.
process. If necessary, this shall be repeated v. The use of long-handled wood floats shall be
until the surface is of uniform texture, true to confined to a minimum; they may be used only
grade and cross section, and free from porous in emergencies and in areas not accessible to
areas. finishing equipment.
5 Hand Finishing: Hand finishing methods will not be
permitted, except under the following conditions: 5.7.3.13 Surface Texture

i. In the event of breakdown of the mechanical 1 Brush or Broom Finish:


equipment, hand methods may be used to i. A brush or broom finish shall be formed on all
finish the concrete already deposited on the newly constructed concrete pavements when
grade; the water sheen has practically disappeared,
ii. In areas of narrow widths or of irregular using mechanical texturing equipment.
dimensions where operation of the mechanical ii. The equipment shall operate transversely
equipment is impractical. across the pavement surface, providing
Concrete, as soon as placed, shall be struck off and corrugations that are uniform in appearance
screeded. An approved portable screed shall be used. A and approximately 2 mm in depth.
second screed shall be provided for striking off the bottom iii. The equipment must not tear or unduly
layer of concrete when reinforcement is used. roughen the pavement surface during the
The screed for the surface shall be at least 600 mm longer operation. Any imperfections resulting from
than the maximum width of the slab to be struck off. It the texturing operation shall be corrected.
shall be of approved design, sufficiently rigid to retain its
shape, and shall be constructed either of metal or of other 5.7.3.14 Skid Resistant Surfaces
suitable material covered with metal. Consolidation shall 1 Wire Combing: A skid resistant surface shall be
be attained by the use of a suitable vibrator. provided by wire combing in plastic concrete. The wire
6 Floating: After the concrete has been struck off and combing technique shall use steel combs or tines of
consolidated, it shall be further smoothed, trued, and various dimensions to form groove-like texture in the
consolidated by means of a longitudinal float, using plastic concrete pavement and shall provide grooves that
approved hand or machine methods. are approximately 3 mm by 3 mm spaced 13 mm center-
7 Straight-Edge Testing and Surface Correction: to-center.

i. After the pavement has been struck off and 5.7.3.15 Surface Test
consolidated and while the concrete is still
plastic, it shall be tested for trueness with a 1 As soon as the concrete has hardened sufficiently,
4.8m straightedge. Furnish and use an the pavement surface shall be tested with a 4.8 m
accurate 4.8m straightedge swung from straightedge or other specified device. Areas in a slab
handles 900 mm longer than one-half the width showing high spots of more than 6 mm but not exceeding
of the slab. 12 mm in 4.8 m shall be marked and immediately ground
down with an approved grinding machine to l within the
ii. The straightedge shall be held in contact with
tolerance of 6 mm or less. Where the departure from
the surface in successive positions parallel to
correct cross section exceeds 12 mm, the pavement shall
the centerline and the whole area gone over
be removed and replaced when so directed by Engineer.
from one side of the slab to the other, as
necessary. Advancing shall be in successive 2 Any area or section so removed, shall not be less
stages of not more than one-half the length of than 3 m in length, nor less than the full width of the lane
the straightedge. Any excess water and involved. When it is necessary to remove and replace a
laitance shall be removed from the surface of section of pavement, any remaining portion of the slab
the pavement. adjacent to the joints that is less than 3 m in length shall
also be removed and replaced.

♦ 5-56 ♦
copy 249
5.7.3.16 Removing Forms shall submit for the Engineer’s approval the appropriate
testing instrument(s) and test methodology for the surface
1 Unless otherwise specified, forms shall not be roughness test.
removed from freshly placed concrete until it has set for at
3 Tolerances. The following tolerances are applicable:
least 12 hours, except where auxiliary forms are used
temporarily in widened areas. Forms shall be removed i. Lateral deviation from established alignment of
carefully to avoid damage to the pavement. After the the pavement edge shall not exceed plus or
forms have been removed, the sides of the slab shall be minus 30 mm in any lane.
cured. Major honeycombed areas shall be considered as ii. Vertical deviation from established grade shall
defective work and shall be removed and replaced. Any not exceed plus or minus 12 mm at any point.
area or section so removed shall not be less than 3 m in iii. Surface smoothness deviations shall not
length nor less than the full width of the lane involved. exceed 6 mm from a 4.8 m straightedge placed
When it is necessary to remove and replace a section of in any direction, including placement along and
pavement, any remaining portion of the slab adjacent to spanning any pavement joint or edge.
the joints that is less than 3 m in length shall also be
removed and replaced. 5.7.3.20 Pavement Marking

5.7.3.17 Sealing Joints 1 Do not apply pavement marking paint until layout,
colors and placement have been verified by the Engineer.
1 The joints in the pavement shall be sealed as shown
2 Allow concrete pavement to harden and gain
on Drawings and as specified in Sub-Section 5.8.
strength for 28 days and be dry before starting pavement
5.7.3.18 Opening to Traffic marking.
3 Sweep and clean surface to eliminate loose material
1 The Engineer shall decide when the pavement shall
and dust.
be opened to traffic. The pavement will not be opened to
traffic until test specimens molded and cured in 5.7.3.21 Field Quality Control
accordance with ASTM C31 have attained the specified
flexural strength when tested in accordance with ASTM 1 Slump: Minimum one test at point of discharge for
C78, unless otherwise acceptable to Engineer. each day's pour of concrete. Additional tests when
concrete consistency seems to have changed.
5.7.3.19 Pavement Tolerance
2 Concrete Temperature: Test hourly when air
1 Comply with tolerances of ACI 117 and as follows: temperature is 4 deg C and below, and when 27 deg C and
above, and each time a set of flexural test beams are
i. Level: Plus 6 mm, no minus.
made.
ii. Thickness: Plus 9 mm, minus 6 mm.
3 Flexural Strength:
iii. Surface: Gap below 3-m long, unleveled
i. Flexural test beams shall be made for each
straightedge not to exceed +6 mm.
day's pour exceeding 4 cu.m, plus additional
iv. Lateral Alignment and Spacing of Tie Bars and sets for each 40 cu.m. over and above the first
Dowels: +/-25 mm. 20 cu.m. Each group of test beams shall be
v. Vertical Alignment of Tie Bars and Dowels: molded from the same batch of concrete and
+/-6 mm. shall consist of a sufficient number of
specimens to provide two flexural strength
vi. Alignment of Tie-Bar End Relative to Line
tests at each test age. The specimens shall be
Perpendicular to Pavement Edge: +/-13 mm.
made in accordance with ASTM C31. At the
vii. Alignment of Dowel-Bar End Relative to Line start of paving operations and when the
Perpendicular to Pavement Edge: Length of aggregate source, aggregate characteristics, or
dowel +/-6 mm per 300 mm. mix design is changed, additional groups of
viii. Joint Spacing: +/-75 mm. test beams may be required until Engineer is
ix. Contraction Joint Depth: Plus 6 mm, no minus. satisfied that the concrete mix complies with
the strength requirements of these
x. Joint Width: Plus 3 mm, no minus.
specifications. Test ages shall be 7 days and
2 Surface Roughness: The International Roughness 28 days.
Index (IRI) for roads shall be complied with on all concrete
ii. The flexural strength of the concrete shall meet
finished surfaces. The acceptable range of IRI test results
the following requirements:
shall vary between 0 and 1.5 mm/m for highways and
primary roads and between 0 and 3.0 mm/m for secondary, - The average of any 4 consecutive strength
tertiary and other access roads. Adopt contact type test tests, tested at the end of 28 days, shall be
instruments for test stretches not exceeding 400 m in equal to or greater than the specified
length and non-contact test instruments (optical or sonic) flexural strength;
for stretches exceeding 400 m in length. The Contractor

♦ 5-57 ♦
copy 249
- Not more than 20 percent of the beams vi. When frequency of testing will provide fewer
tested at the end of 28 days shall have a than five compressive-strength tests for a given
flexural strength less than the specified class of concrete, testing shall be conducted
strength; from at least five randomly selected batches or
- No specimen shall have a flexural strength from each batch if fewer than five are used.
less than 90% of the specified flexural vii. When strength of field-cured cylinders is less
strength. than 85 percent of companion laboratory-cured
iii. Specimens, which are obviously defective, cylinders, current operations shall be evaluated
shall not be considered in the determination of and corrective procedures shall be provided for
the strength. When it appears that the test protecting and curing in-place concrete.
specimens will fail to conform to the viii. Strength level of concrete will be considered
requirements for strength, Engineer shall have satisfactory if averages of sets of three
the right to order changes in the concrete mix consecutive compressive-strength test results
sufficient to increase the strength to meet the equal or exceed specified compressive strength
requirements. When a satisfactory relationship and no individual compressive-strength test
between 7-days and 28-day strengths has been result falls below specified compressive
established and approved, the 7-day test strength by more than 3.4 MPa.
results may be used as an indication of the 28- 6 Test results shall be reported in writing to Engineer,
day strengths. However, the 7-day test results concrete manufacturer, and Contractor within 24 hours of
will not replace the results of the 28-day tests if testing. Reports of compressive-strength tests shall
the 28-day results fall below the requirements. contain Project identification name and number, date of
4 Testing Agency: Engage a qualified independent concrete placement, name of concrete testing agency,
testing and inspection agency to sample materials, concrete type and class, location of concrete batch in
perform tests, and submit test reports during concrete pavement, design compressive strength at 28 days,
placement according to requirements specified in this concrete mix proportions and materials, compressive
Clause. breaking strength, and type of break for both 7- and 28-
5 Testing Services: Testing shall be performed day tests.
according to the following requirements: 7 Nondestructive Testing: Impact hammer, sonoscope,
i. Sampling Fresh Concrete: Representative or other nondestructive device may be permitted by
samples of fresh concrete shall be obtained Engineer but will not be used as the sole basis for
according to ASTM C 172, except modified for approval or rejection.
slump to comply with ASTM C 94. 8 Additional Tests: Testing agency shall make
ii. Slump: ASTM C 143; one test at point of additional tests of the concrete when test results indicate
placement for each flexural and/or slump, air entrainment, concrete strengths, or other
compressive-strength test, but not less than requirements have not been met, as directed by Engineer.
one test for each day's pour of each type of Testing agency may conduct tests to determine adequacy
concrete. Additional tests will be required of concrete by cored cylinders complying with ASTM C 42,
when concrete consistency changes. or by other methods as directed.

iii. Concrete Temperature: ASTM C 1064; one test 5.7.3.22 Repairs and Protection
hourly when air temperature is 4 deg C and
below and when 27 deg C and above, and one 1 Remove and replace concrete pavement that is
test for each set of flexural and/or compressive- broken, damaged, or defective, or does not meet
strength specimens. requirements in the Specification

iv. Compression Test Specimens: ASTM C 31/C 2 Drill test cores where directed by Engineer when
31M; one set of four standard cylinders for necessary to determine magnitude of cracks or defective
each compressive-strength test, unless areas. Fill core holes in satisfactory pavement areas with
otherwise indicated. Cylinders shall be molded Portland cement concrete bonded to pavement with epoxy
and stored for laboratory-cured test specimens adhesive.
unless field-cured test specimens are required. 3 Protect concrete from damage. Exclude traffic from
v. Compressive-Strength Tests: ASTM C 39; one pavement for at least 14 days after placement. When
set for each day's pour of each concrete class construction traffic is permitted, maintain pavement as
exceeding 4 cu.m., but less than 19 cu.m., plus clean as possible by removing surface stains and spillage
one set for each additional 38 cu.m. One of materials as they occur.
specimen shall be tested at 7 days and two 4 Maintain concrete pavement free from stains,
specimens at 28 days; one specimen shall be discoloration, dirt, and other foreign material. Sweep
retained in reserve for later testing if required.

♦ 5-58 ♦
copy 249
concrete pavement not more than two days before date the joint shall be removed and replaced at the Contractor's
scheduled for Substantial Completion inspections. expense.

5.7.3.23 Determination of Concrete Thickness


5.7.4 Method of Measurement
1 Thickness of concrete pavement shall be determined
1 Unreinforced concrete pavement shall be measured
by average caliper measurement of cores taken from in cubic meters computed as the paved area multiplied by
sections of the pavement as stated in Item 2 below,
the executed slab thickness as approved by the Engineer.
rounded upwards taken to the nearest mm.
2 Reinforced concrete pavement shall be measured in
2 Pavement sections shall consist of each 300 lin.m.
cubic meters of the paved area multiplied by the executed
length in each paver lane. The last section in each lane
slab thickness (as approved by the Engineer) and shall
shall be 300 m plus the fractional part of 300 m remaining. include the same items detailed in Item 1 of Clause 5.7.4
Other areas such as intersections, entrances, ramps, etc
above plus the reinforcement steel material furnished,
shall be measured as one section each and the thickness
spliced, jointed and placed all as shown on the
of each shall be determined separately. Small irregular Contractor’s shop drawings that are approved by the
unit areas may be included as part of another section,
Engineer.
3 One core shall be taken from each section by the
3 The rates in the Bill of Quantities shall be deemed to
Contractor at approved locations and in the presence of
include furnishing of all associated concrete and joint
the Engineer. When the measurement of the core from component materials, preparation of bases, concrete
any pavement section is not deficient by more than 5 mm
mixing, placing, compacting, finishing and curing, as well
from the specified thickness, the core will be deemed to be
as all joint sawing, cutting and cleaning operations,
of the specified thickness as shown on the Drawings. drilling and installing dowels and deformed tie bars and
4 When the measurement of the core from any other joint accessories, and all tests, all as detailed on
pavement section is deficient by more than 5 mm but not Drawings and in the Specifications.
more than 20 mm, 2 additional cores spaced at not less
than 100 mm shall be taken and used together with the 5.7.5 Basis of Payment
first core to determine the average thickness of such
section. 1 The amount of completed and accepted work,
measured as provided for above, will be paid for at the
5 When the measurement of the core from any
unit rates for the various items in the Bill of Quantities,
pavement section is less than the specified thickness by
which rate shall be full compensation for supplying
more than 20 mm, the average thickness of such section
materials, transporting and placing, for labor, equipment,
shall be determined by taking additional cores at not less
tools and other items necessary for the proper completion
than 5 m intervals parallel to the centerline in each
of the work.
direction from the affected location until, in each direction,
a core is taken which is not deficient by more than 20 mm.
Exploratory cores for deficient thickness will not be used
5.7.6 Items in the Bill of Quantities
in average thickness determinations. i. Unreinforced Cement Concrete
6 Where the average thickness of concrete pavement is Pavement (cu.m.)
deficient by more than 5 mm but not more than 20 mm ii. Reinforced Cement Concrete
adjustments shall be made in the area measurements as Pavement (cu.m.)
shown in Table 5.7.3.1.

Deficiency in Thickness as Proportion of Area 5.8 Joint Sealers for Concrete


Determined by Cores (mm) Measured for Payment Pavement
0.0 to 5.0 100%
5.1 to 10.0 90% 5.8.1 Description
10.1 to 15.0 75%
1 This Sub-section describes joint sealers for concrete
15.1 to 20.0 50%
pavement as shown on Drawings.
> 20.0 0%
Table 5.7.3.1: Concrete Thickness Deficiency 5.8.2 Materials
7 When the pavement is more than 20 mm deficient in 5.8.2.1 Materials, General
thickness, the Contractor shall remove such deficient areas
and replace them with concrete pavement of the specified 1 Compatibility: Provide joint sealers, joint fillers and
quality and thickness, all at his own expense. other related materials that are compatible with one
another and with joint substrates under conditions of
8 When the limits of a deficient area to be removed
service and application, as demonstrated by sealant
and replaced are within 3 m of an expansion, contraction
manufacturer based on testing and field experience.
or construction joint, the entire concrete pavement up to

♦ 5-59 ♦
copy 249
5.8.2.2 Elastomeric Hot-Poured Joint Sealants i. Remove all foreign material from joint
substrates which could interfere with adhesion
1 ASTM D 3569 - Joint Sealants, Hot-Poured, of joint sealer, including dust; paints, except for
Elastomeric, Jet-Fuel-Resistant type, for Portland Cement permanent, protective coatings tested and
Concrete Pavements. approved for sealant adhesion and
compatibility by sealant manufacturer; old joint
5.8.2.3 Joint Sealant Backing
sealers; oil; grease; waterproofing; water
1 General: Provide sealant backings of material and repellants; water and surface dirt.
type which are non-staining; are compatible with joint ii. Remove laitance and form release agents from
substrates, sealants, primers and other joint fillers; and are concrete.
approved for applications indicated by sealant
2 Joint Priming: Prime joint substrates where
manufacturer based on field experience and laboratory
indicated or where recommended by joint sealer
testing.
manufacturer based on preconstruction joint sealer-
2 Plastic Foam Joint Fillers: Preformed, compressible, substrate tests or prior experience. Apply primer to
resilient, non-waxing, non-extruding strips of flexible, non- comply with joint sealer manufacturer's recommendations.
gassing plastic foam of material indicated below; Confine primers to areas of joint sealer bond, do not allow
nonabsorbent to water and gas; and of size, shape and spillage or migration onto adjoining surfaces.
density to control sealant depth and otherwise contribute
3 Masking Tape: Use masking tape where required to
to producing optimum sealant performance.
prevent contact of sealant with adjoining surfaces which
3 Bond-Breaker Tape: Polyethylene tape or other otherwise would be permanently stained or damaged by
plastic tape as recommended by sealant manufacturer for such contact or by cleaning methods required to remove
preventing sealant from adhering to rigid, inflexible joint sealant smears. Remove tape immediately after tooling
filler materials or joint surfaces at back of joint where such without disturbing joint seal.
adhesion would result in sealant failure. Provide self-
adhesive tape where applicable. 5.8.3.3 Installation of Joint Sealers

5.8.2.4 Miscellaneous Materials 1 General: Comply with joint sealer manufacturers'


printed installation instructions applicable to products and
1 Primer: Provide type recommended by joint sealer applications indicated, except where more stringent
manufacturer where required for adhesion of sealant to requirements apply.
joint substrates indicated, as determined from
2 Hot poured Sealants:
preconstruction joint sealer substrate tests and field tests.
i. The joint sealant shall be applied solid,
2 Cleaners for Nonporous Surfaces: Provide non-
uniformly from bottom to top and shall be
staining, chemical cleaners of type which are acceptable to
filled without formation of entrapped air or
manufacturers of sealants and sealant backing materials,
voids. A backing material shall be placed as
which are not harmful to substrates and adjacent
shown on the plans and shall be non-adhesive
nonporous materials, and which do not leave oily residues
to the concrete or the sealant material. The
or otherwise have a detrimental effect on sealant adhesion
heating kettle shall be an indirect heating type,
or in-service performance.
constructed as a double boiler. A positive
3 Masking Tape: Provide non-staining, nonabsorbent temperature control and mechanical agitation
type compatible with joint sealants and to surfaces shall be provided. The sealant shall not be
adjacent to joints. heated to more than 11°C below the safe
heating temperature. The safe heating
5.8.3 Construction Requirements temperature can be obtained from the
manufacturer's shipping container. A direct
5.8.3.1 Examination
connecting pressure type extruding device with
1 Examine joints for compliance with requirements for nozzles shaped for insertion into the joint shall
joint configuration, installation tolerances and other be provided. Any sealant spilled on the surface
conditions affecting joint sealer performance. Do not of the pavement shall be removed immediately.
proceed with installation of joint sealers until ii. Backup materials and bond breakers shall be
unsatisfactory conditions have been corrected. compatible with the sealant, shall not adhere to
the sealant, shall be compressible without
5.8.3.2 Preparation
extruding the sealant, and shall recover to
1 Surface Cleaning of Joints: Clean out joints maintain contact with the joint faces when the
immediately before installing joint sealers to comply with joint is open.
recommendations of joint sealer manufacturers and the
following requirements:

♦ 5-60 ♦
copy 249
5.8.3.4 Cleaning 5.9.3 Construction Requirements
1 Clean off excess sealants or sealant smears adjacent 1 Construction work shall comply with the relevant
to joints as work progresses by methods and with requirements of the following sections:
cleaning materials approved by manufacturers of joint Section 2 Earthwork
sealers and of products in which joints occur. Sub-section 5.2 Reinforcing Steel
5.8.3.5 Protection Sub-section 5.3 Reinforced Concrete Structures.
2 Box culverts, headwalls, wing walls, cut-off walls and
1 Protect joint sealers during and after curing period
aprons shall be to the lines and levels shown on the
from contact with contaminating substances or from
Drawings. Unless otherwise shown, culverts shall have a
damage resulting from construction operations or other
constant fall of 1:100 along their centerline.
causes so that they are without deterioration or damage at
time of Substantial Completion. If, despite such protection, 3 Box culverts shall be constructed in sections such
damage or deterioration occurs, cut out and remove that expansion joints are located at intervals which shall
damaged or deteriorated joint sealers immediately and be so spaced as to prevent the box culvert from behaving
reseal joints with new materials to produce joint sealer as a long beam unless such structural action has been
installations with repaired areas indistinguishable from allowed for in the design. Unless shown on the Drawings
original work. or directed by the Engineer, the spacing of expansion
joints shall be no greater than 35 meters.
5.8.4 Method of Measurement, Basis of 4 Unless otherwise indicated, expansion joints shall
Payment and Bill of Quantities also be used at the culvert ends where the culvert meets
the wing walls and apron slabs.
1 No separate measurement is made for joint sealers
and no items are included in the Bill of Quantities. The 5 Where box culverts are located in road embankments,
work is considered as subsidiary to the concrete pavement the embankments shall first be constructed in accordance
and its cost is deemed to be included under payment for with Paragraph 2.5.3.4 "Embankment Construction". The
concrete pavement items as measured under Clauses 5.7.4, compacted embankments shall then be excavated in
5.7.5 and 5.7.6. trenches for the culverts. This requirement may be
dispensed with by a written permission from the Engineer
to so do. Where a culvert is to be constructed under a
5.9 Reinforced Concrete Box Culverts high embankment, this requirement may be relaxed or
and Headwalls, Wingwalls, Cut- dispensed with provided the fill is designed to arch over
Off Walls and Aprons the culvert or the culvert is specially designed for an
increased surcharge load from the embankment.
5.9.1 Description Embankments may be constructed to within 1 m above
the culvert then construction carried out as above.
1 This Sub-section describes the requirements for
construction of reinforced concrete box culverts, in-situ or 6 For culverts located below firm ground, the
precast, and headwalls, wing walls, cut-off walls and excavation shall be carried out in trenches in accordance
aprons for box and pipe culverts, including earthworks, with Section 2 “Earthwork”.
structural concrete and all other ancillary items necessary 7 Backfilling and compaction shall be carried out in
for the completion of the structures to the lines, grades layers not exceeding 150 mm compacted thickness and
and dimensions as shown on the Drawings. These the difference in the levels of backfill on either side of the
requirements are additional to the requirements of culvert shall at no time exceed 500 mm. Start backfilling
preceding Sections of the Specification. after having attained 75 percent of the culvert 28-day
concrete strength.
5.9.2 Materials 8 All concreting shall be carried out in dry conditions.
1 Materials shall conform to the relevant requirements 9 Unless otherwise shown on the Drawings or
of the following Sub-sections of the Specification: instructed by the Engineer, the base slab of the box culvert
for its entire length shall first be completed before
- Concrete Sub-section 5.1
proceeding with the walls and roof slab. The construction
“Concrete Materials and Mixes” joints in the walls shall be located at not less than 100 mm
- Reinforcing Steel Sub-section 5.2 above the top of the base slab. Unless shown otherwise
“Reinforcing Steel” on the Drawings or directed by the Engineer, the walls and
roof slabs shall be concreted in one pour between
2 Concrete classes shall be those prescribed on the
expansion joints.
relevant Drawings.
10 Unless otherwise shown on the Drawings or
3 Backfill shall be as specified in Section 2 “Earthwork”.
instructed by the Engineer, the cut-off wall shall be cast
against earth.

♦ 5-61 ♦
copy 249
11 Concrete placing, forms, finishing, curing and ASTM D 173 Specification for Bitumen-Saturated
jointing shall be done in accordance with Section 5.3 Cotton Fabrics Used in Roofing and
“Reinforced Concrete Structures”. Waterproofing (AASHTO M 117)
ASTM D 449 Specifications for Asphalt Used in
5.9.4 Method of Measurement Dampproofing, and Waterproofing
(AASHTO M 115)
1 The work shall be measured according to the
dimensions shown on the Drawings in accordance with ASTM D 450 Specification for Coal-Tar Pitch Used in
the rules for measurement stated in Sub-section 5.1 Roofing, Dampproofing, and
‘Concrete Materials and Mixes’ and Sub-section Waterproofing (AASHTO M 118)
5.2 ’Reinforcing Steel’. ASTM D 490 Specifications for Road Tar (AASHTO M
2 Where the Contractor uses precast units as an 52)
alternative, any extra material and quantity necessary
shall not be measured. 5.10.2 Materials
3 All other work such as excavation for the cut-off walls
5.10.2.1 Asphalt
formwork, construction and expansion joints and the like,
shall be included as subsidiary work whose costs are 1 Waterproofing asphalt shall conform to AASHTO M
deemed to be included in the rates and prices for concrete 115 (ASTM D 449); Type I for use below ground, and Type
and reinforcement. II for use above ground.
2 Primer for use with asphalt in waterproofing shall
5.9.5 Basis of Payment conform to AASHTO M 116 (ASTM D 41).
1 The amount of completed and accepted work, 5.10.2.2 Bitumen
measured as provided for above, shall be paid for at the
unit rates in the Bill of Quantities, which rates shall be full 1 Waterproofing bitumen shall conform to AASHTO M
compensation for supplying, curing, finishing concrete 118 (ASTM D 450); Type II unless otherwise specified.
and cutting, shaping and fixing reinforcing steel and for 2 Primer for use with coal-tar bitumen in dampproofing
labor, materials, equipment, tools and other items and waterproofing shall conform to AASHTO M 121
necessary for the proper completion of the works. (ASTM D 43). It shall be a distillate of coal-gas tar or coke-
oven tar.
5.9.6 Items in Bill of Quantities
5.10.2.3 Waterproofing Fabric
1 Reinforced concrete box culverts, head walls, wing
walls and cut-off walls are separately identified in the Bill 1 Waterproofing fabric shall conform to AASHTO M
of Quantities and the relevant items as stated in Sub- 117 (ASTM D 173).
sections 5.1 and 5.2 are included.
5.10.2.4 Self-Adhesive Polyethylene Sheet

5.10 Waterproofing for Structures 1 Flexible, preformed waterproof membrane


comprising strong, high-density polyethylene film with
5.10.1 Description self-adhesive rubber/bitumen compound, and having the
following minimum properties:
5.10.1.1 Scope - Total thickness : 1.5 mm
2
1 This Sub-section describes waterproofing membrane, - Weight : 1.6 kg/m
sand dampproofing courses to external concrete surfaces 2
- Tensile strength : 42 N/mm
in contact with earth and epoxy coating to internal
- Elongation : 210% long.; 160% trans.
surfaces of concrete walls, slabs, and beds, all as shown
on the Drawings or as directed by the Engineer. - Tear resistance : 340 N/mm long.; 310
N/mm trans.
5.10.1.2 References - Puncture resistance : 220 N 65 mm
1 American Society for Testing and Materials (ASTM):
5.10.2.5 Tar for Absorptive Treatment
ASTM D 41 Specification for Asphalt Primer Used in
Roofing, Dampproofing, and 1 Tar for absorptive treatment shall be a liquid water-
Waterproofing (AASHTO M 116) gas tar that conforms to the following requirements:

ASTM D 43 Specification for Coat Tar Primer Used - Specific gravity, 25ºC 1.030 to 1.100
in Roofing, Dampproofing, and - Specific viscosity at 40ºC (Engler),
Waterproofing (AASHTO M 121) not more than 3.0
- Total distillate, percent by
weight, to 300ºC, not more than 50.0

♦ 5-62 ♦
copy 249
- Bitumen (soluble in carbon disulfide) When necessary the Engineer may require the surface to
not less than, percent 98.0 be scrubbed with water and a stiff brush, after which the
- Water, not more than, percent 3.0 surface shall be allowed to dry before application of the
primer.
5.10.2.6 Tar Seal Coat
5.10.3.2 Inspection, Delivery and Storage
1 Tar seal coat shall conform to AASHTO M 52, Grade
RTCB-5 (ASTM D 490). 1 All waterproofing materials shall be tested before
shipment. Unless otherwise ordered by the Engineer, they
5.10.2.7 Proprietary Waterproofing Systems shall be tested at the place of manufacture, and, when so
tested, a copy of the test results shall be sent to the
1 Proprietary waterproofing systems shall be
Engineer by the chemist or inspection bureau which has
bituminous membranes reinforced with layers of suitable
been designated to make the tests, and each package shall
reinforcement, bituminous coated polythene sheet,
have affixed to it a label, seal, or other mark of
plasticized polyvinyl chloride sheet, other approved
identification, showing that it has been tested and found
membranes or applications of resinous reinforced
acceptable, and identifying the package with the
coatings. The type to be used shall be as indicated on the
laboratory tests.
Drawings and shall be chosen according to its location
and serviceability. The specific system shall be approved 2 Factory inspection is preferred, but in lieu thereof
after site trials, should the Engineer decide these to be and/or addition thereof, the Engineer may order that
necessary. representative samples, properly identified, be sent to him
for test prior to shipment of the materials. After delivery
5.10.2.8 Epoxy Coating System of the materials, representative check samples shall be
taken which shall determine the acceptability of the
1 An approved epoxy coating system shall be
materials.
furnished and applied to the internal concrete surfaces of
culverts and open channels as shown on the Drawings or 3 All materials shall be delivered to the work in original
as directed by the Engineer. The thickness of the epoxy containers, plainly marked with the manufacturer's brand
coating shall be at least 400 microns in accordance with or label.
the manufacturer's recommendations. 4 Waterproofing and dampproofing material shall be
stored in a dry, protected place. Rolls of waterproofing
5.10.3 Construction Requirements fabric and membranes shall not be stored on end.

5.10.3.1 Surface Preparation 5.10.3.3 Asphalt and Bitumen Waterproofing Fabric

1 Waterproofing: 1 Asphalt shall be heated to a temperature between


150 degrees C and 175 degrees C and tar for hot
i. All concrete surfaces to be waterproofed shall
application shall be heated to a temperature between 93
be reasonably smooth and free from
degrees C and 120 degrees C with frequent stirring to
projections or holes which might cause
avoid local overheating. The heating kettles shall be
puncture of the membrane. The surface shall
equipped with thermometers.
be dry, so as to prevent the formation of steam
when the hot asphalt or tar is applied, and, 2 In all cases, the waterproofing shall begin at the low
immediately before the application of the point of the surface to be waterproofed, so that water will
waterproofing, the surface shall be thoroughly run over and not against or along the laps.
cleaned of dust, projecting tying wire and loose 3 The first strip of fabric shall be of half-width; the
material. second shall be full-width, lapped the full-width of the first
ii. No waterproofing shall be done in wet weather, sheet; and the third and each succeeding strip shall be full-
nor when the temperature is below 4 degrees C, width and lapped so that there will be two layers of fabric
without special authorization from the Engineer. at all points with laps not less than 50 mm wide. All end
Should the surface of the concrete become laps shall be at least 300 mm.
temporarily damp, it shall be covered with a 50 4 Beginning at the low point of the surface to be
mm layer of hot sand, which shall be allowed waterproofed, a coating of primer shall be applied and
to remain in place from 1 to 2 hours, or long allowed to dry before the first coat of asphalt is applied.
enough to produce a warm and surface-dried The waterproofing shall then be applied as follows.
condition, after which the sand shall be swept
5 Beginning at the low point of the surface to be
back, uncovering sufficient surface for
waterproofed, a section about 500 mm wide and the full
beginning work, and the operation repeated as
length of the surface shall be mopped with the hot asphalt
the work progresses.
or tar. Immediately following the mopping, the first strip
2 Dampproofing: The surface to which the of fabric, or half-width, shall be rolled and pressed into
dampproofing coating shall be applied shall be cleaned of place so as to eliminate all air bubbles and obtain close
all loose and foreign material and dirt and shall be dry. conformity with the surface. This strip and an adjacent

♦ 5-63 ♦
copy 249
section of the surface of a width equal to slightly more 5.10.3.4 Proprietary Waterproofing Membranes
than half of the width of the fabric being used shall then
1 Proprietary waterproofing membranes shall be
be mopped with hot asphalt or tar, and a full width of the
installed strictly in accordance with the manufacturer's
fabric shall be rolled into this, completely covering the first
instructions and shall be laid so that no air is trapped
strip, and pressed into place as before. This second strip
between it and the concrete surface or between successive
and an adjacent section of the concrete surface shall then
layers of sheeting.
be mopped with hot asphalt or tar and the third strip of
fabric "shingled" on so as to lap the first strip not less than 2 Unless otherwise specified, joints between sheets
50 mm. This process shall be continued until the entire shall be lapped with end laps of at least 150 mm and side
surface is covered, each strip of fabric lapping at least 50 laps of at least 100 mm. The joints shall be arranged so
mm over the last strip. The entire surface shall then be that, at no points, are there more than three thicknesses of
given a final mopping of hot asphalt or tar. sheeting and, as far as possible so that water will drain
away from the exposed edge.
6 The completed waterproofing shall be a firmly
bonded membrane composed of two layers of fabric and 5.10.3.5 Damage Patching of Waterproofing Fabrics
three moppings of asphalt or tar, together with a coating
of primer. Under no circumstances shall one layer of 1 Care shall be taken to prevent injury to the finished
fabric touch another layer at any point or touch the surface, fabric membrane by workmen or wheelbarrows, or by
as there must be at least three complete moppings of throwing any material on it. Any damage which may
asphalt or tar. occur shall be repaired by patching. Patches shall extend
7 In all cases the mopping on concrete shall cover the at least 300 mm beyond the outermost damaged portion
surface so that no gray spots appear, and on cloth it shall and the second ply shall extend at least 75 mm beyond the
be sufficiently heavy to completely conceal the weave. On first.
horizontal surfaces not less than 49 liters of asphalt or tar 2 Proprietary waterproofing membranes shall be
shall be used for each 10 square meter of finished work, repaired according to the manufacturer's specifications
and on vertical surfaces not less than 61 liters shall be and as directed by the Engineer.
used for each 10 square meter. The work shall be so
5.10.3.6 Dampproofing
regulated that, at the close of a day's work, all cloth that is
laid shall have received the final mopping of asphalt or tar. 1 Concrete, brick, or other surfaces to be protected by
Special care shall be taken at all laps to see that they are dampproofing shall be thoroughly cleaned before the
thoroughly sealed down. primer is applied. The surfaces shall then be brush or
8 At the edges of the membrane and at any points spray painted with two or more coats (as indicated on the
where it is punctured by such appurtenances as drains or Drawings) of tar or asphalt for absorptive treatment.
pipes, suitable provisions shall be made to prevent water Below ground not less than two coats shall be applied,
from getting between the waterproofing and the using 0.56 L/square meter of surface. On the well-primed
waterproofed surface. surface one application of tar or asphalt seal coat shall be
9 All flashing at curbs and against girders, spandrel applied by brush, using 0.45 L/square meter.
walls, etc., shall be done with separate sheets lapping the 2 Care shall be taken to confine all paints to the areas
main membrane not less than 300 mm. Flashing shall be to be waterproofed and to prevent disfigurement of any
closely sealed either with a metal counter-flashing or by other parts of the structure by dripping or spreading of the
embedding the upper edges of the flashing in a groove tar or asphalt.
poured full of joint filler.
5.10.3.7 Protection of Waterproofing and Dampproofing
10 Joints which are essentially open joints but which are
not designed to provide for expansion shall first be 1 Waterproofing membranes and dampproofing
caulked with oakum and lead wool and then filled with hot courses shall be covered by a protective layer which,
joint filler. unless otherwise specified or shown on the Drawings,
11 Expansion joints, both horizontal and vertical, shall shall be a 50 mm coat of mortar composed of one part
be provided with sheet copper or lead in "U" or "V" form in Portland cement and two parts sand, reinforced midway
accordance with approved details. After the membrane between its top and bottom surfaces with wire netting of
has been placed, the joint shall be filled with hot joint filler. 150 mm mesh and No. 12 gauge, or an approved
The membrane shall be carried continuously across all equivalent. The top surface shall be troweled to a smooth,
expansion joints. hard finish and, where required, true to grade.

12 At the ends of the structure the membrane shall be 2 The protection course shall follow the waterproofing
carried well down on the abutments and suitable so closely that the latter will not be exposed without
provision made for all movement. protection for more than 24 hours.
3 Unless otherwise shown on the Drawings or directed
by the Engineer, vertical faces waterproofed or
dampproofed shall be protected by a porous concrete
block wall of not less than 225 mm thickness. If approved

♦ 5-64 ♦
copy 249
by the Engineer, a proprietary synthetic sheeting may be construction in corrosive or marine environments or other
used as the protective layer in lieu of the porous concrete severe exposure conditions as shown on the Drawings.
block wall. 2 The coating system shall be used for the protection
of reinforced concrete structures against carbonation or
5.10.3.8 Testing
chloride induced corrosion. Work includes, but not
1 Unless otherwise agreed by the Engineer in writing, necessarily limited to coating for:
at least one site trial application of the waterproofing - Piers, columns, frames and exposed surfaces
system shall be carried out to determine the suitability of of abutments and retaining walls.
the surface preparation, method of application and
- Deck soffit and sides and other exposed
effectiveness of the protective layer. The size of
surfaces of deck.
membrane laid shall be not less than 2.0 meters wide and
5.0 meters long. - Precast concrete girders and other precast
concrete elements.
5.10.4 Method of Measurement - Concrete parapets.

1 Waterproofing membrane shall be measured by the 5.11.1.2 Submittals


square meter of each type, furnished, laid, completed and
accepted. 1 Proprietary special coating system for the protection
of exposed concrete surfaces shall be proposed by the
2 Tar or bituminous painting to surfaces permanently
Contractor and shall be subject to the Engineer's approval.
in contact with backfilled material shall be measured by
Submittal shall include the details of the coating type and
the square meter of surface area so painted.
coating manufacturer and a list of projects, executed in
3 Epoxy coating to internal surfaces of concrete shall environmental conditions similar to those experienced in
be measured by the square meter of the surface area so the project site, in which the same protective coating
coated. system was successfully used.
4 Protection to waterproofing membrane and 2 The Contractor's submittal shall be accompanied by
dampproofing course shall not be measured for direct the manufacturer's detailed product specifications
payment but shall be deemed to be included in the rates together with application instructions, and guarantee that
for waterproofing and dampproofing. the product is suitable for use at the operating
5 Site trials of waterproofing membranes shall not be temperatures in the Sultanate.
measured for direct payment but shall be deemed to be 3 Trial Panels as specified in Paragraph 5.11.1.4 (1)
included in the rates for waterproofing. shall be provided.

5.10.5 Basis of Payment 5.11.1.3 Performance Requirements

1 The amount of completed and accepted Work 1 The coating system shall provide in-depth protection
measured as provided for above will be paid at the unit against carbonation and chloride penetration while
rates as specified in the Bill of Quantities, which unit rates permitting water vapor transmission from the concrete.
shall be full compensation for furnishing all materials, 2 Final color shall be selected by the Engineer.
labor, equipment, tools, supplies and all other items
necessary for the completion of the Work. 5.11.1.4 Quality Assurance

1 Trial Panels:
5.10.6 Items in the Bill of Qquantities
i. Prior to applying the system, trial applications
i Tar or bituminous paint sq.m. shall be carried out on trial panels made by the
(State type, number of coats) Contractor to the specified finishes. The trial
ii Membrane waterproofing sq.m. shall demonstrate the method proposed for
(State type, thickness) applying the system, coverage, coating
thickness, color and final appearance of the
iii Epoxy coating to internal
coating. Representatives of the coating
surfaces of concrete
manufacturer shall be present at the trials and
(State type, thickness) sq.m.
the surface preparation and application of the
coating shall be carried out under their
5.11 Protective Coating for Concrete direction. The Contractor shall, at his own
expense, coat as many panels as required by
5.11.1 Description the Engineer until a trial panel has been
accepted by the Engineer as satisfactory. The
5.11.1.1 Scope coated panel, when accepted, will form the
1 This Sub-section describes protective coating on standard against which the corresponding
exposed surfaces of reinforced and prestressed concrete coating in the works shall be judged. No

♦ 5-65 ♦
copy 249
application of the coating in the works shall be 5.11.2.3 Topcoat
undertaken until trials have been completed to
1 The topcoat shall be a pure aliphatic acrylic resin,
the Engineer’s satisfaction.
decorative, high performance water based, pigmenting
ii. Trial panels shall be tested for permeability in coating. It shall have resistance to water, carbon dioxide
accordance with DIN 1048 and AASHTO T 277 and other air-borne acids and have the ability to allow
as defined in Paragraph 5.1.3.15 as a check on passage of water vapor from within the structure. The
the effectiveness of the coating. Acceptance of topcoat shall have elastomeric and flexural capabilities.
the coating shall be based on compliance with The color shall be selected by the Engineer.
the following acceptance limits. Based on this
result, the Engineer may reject the work or 5.11.2.4 Specifications
require additional coating.
1 The material employed for the coating shall comply
- DIN 1048 results for coated surfaces: one with the following requirements:
fifth of the limits for the unprotected
- Wet film thickness 650 microns
surfaces defined in Paragraph 5.1.3.15.
- Dry film thickness 400 microns
- AASHTO T 277 test results for coated
surfaces: charge passed should be less - Carbon dioxide diffusion
than 500 coulombs. resistance R value at 325μ
greater than 161
5.11.1.5 Testing m
1 Testing of the coating shall conform to the following: - Water vapor transmission greater than 13
g/m2.day
- Carbon dioxide diffusion resistance (R
value) - Chloride ion diffusion 3.63 x 10-10
Taywood Engineering Laboratories cm2/sec
- Water vapor transmission - Reduction in chloride ion
Taywood Engineering Laboratories penetration minimum 94 %
at 28 days
- Chloride ion diffusion
- Tear resistance 7.3 kN/mm2
Taywood Engineering Laboratories
- Crack bridgeability 1.5 mm
- Reduction in chloride ion penetration
BS 1881: Part 124 - Adhesion minimum 1.0
N/mm2
- Tear resistance
ASTM D624 - Reduction in water absorption minimum 82
(measured against a control % at 28 days
- Crack bridgeability concrete sample) when tested at a
BRE method water-cement
2 Where test methods are not specified, the procedure ratio 0.5
for establishing compliance with the specification
requirements shall be agreed with the Engineer. 5.11.3 Construction Requirements
5.11.3.1 General
5.11.2 Materials
1 The Contractor shall adhere strictly to the
5.11.2.1 General
manufacturer's recommendations regarding the use,
1 The coating system shall consist of a penetrating, storage, application and safety rules in respect of the
reactive primer and an acrylic topcoat system to minimize approved materials.
ingress of acidic gases, chlorides and water. 2 During storage, mixing and application, the
Contractor shall comply with the health and safety and
5.11.2.2 Primer
environmental protection recommendations of the
1 The primer shall be a low viscosity silane-siloxane manufacturer and governing authorities.
acrylic blend dissolved in a penetrating organic carrier.
5.11.3.2 Inspection of Concrete
The primer shall have the capability to penetrate and
produce a chemically bound hydrophobic barrier to 1 The Contractor shall not proceed with the surface
prevent the passage of chloride and sulfate ions. The finish or making good of concrete surfaces until he has
primer shall also be film forming to condition and stabilize received the Engineer’s permission to do so and he shall
the substrate prior to the application of the topcoat. The not apply cement slurry or mortar or any other coating to
primer shall be applied in full accordance with the the concrete surfaces from which the formwork has been
manufacturer’s instructions. struck until the Engineer has inspected and approved the
concrete.

♦ 5-66 ♦
copy 249
5.11.3.3 Surface Preparation 5.12 Bridge Load Testing
1 Before application, all surfaces must be dry and free
from oil, grease, loose particles, decayed matter, moss or
5.12.1 Description
algae growth and general curing compounds. 1 All bridges shall be load tested unless otherwise
2 All such contamination and laitance must be agreed by the Engineer.
removed by the use of sweep sand blasting, high pressure 2 The aim of the testing is not to measure the actual
jetting or equivalent mechanical means. factor of safety of the bridge but intended to verify the
3 Before proceeding to apply the protective coatings, design and construction of the bridge under normal
all surfaces which are not to be coated, but which may be loading conditions. Measurements are, accordingly, meant
affected by the application of the coating shall be fully to give an order of magnitude and fine precision is not
masked. required.
4 Blow holes and areas of pitting shall be made good 3 The date of conducting the load testing shall be fixed
with a one part modified cementitious material and by the Engineer and shall be at least 90 days after all
allowed to cure in accordance with the manufacturer’s concrete structural elements are constructed. Load testing
recommendations. In particular, the application shall be in may be carried out before or after opening the bridge for
accordance with the manufacturer’s recommendations, traffic.
with respect to the maximum application thickness. 4 If the bridge is open to traffic before being load
tested, the Engineer may impose restrictions on highway
5.11.3.4 Approval Prior to Coating Application
loading over the bridge until testing is satisfactorily
1 The Engineer’s approval must be obtained prior to completed, such as banning the passage of heavy traffic
applying the coating system in the works. Before giving loading of the order of the Oman Special Truck, or any
the approval, the Engineer will need to be satisfied as to other measures.
the following: 5 Load testing comprises:
i. All construction work in the immediate vicinity of i. Application of load as described in Clause 5.12.2.
the structure to be coated has been completed. ii. Detailed visual inspection before, during and
ii. The surface preparation of the structure has after the testing as described in Clause 5.12.3.
been completed. iii. Measurement of deflections and other quantities
iii. The whole of the structure can be coated in a as described in Clause 5.12.4.
continuous operation. 6 If the Works include a number of similar bridges
iv. Adequate measures have been taken to protect testing may be limited as follows:
the property of third parties, including vehicles,
i. At least one bridge shall be tested for all the
from coating splatters.
tests specified in this Sub-Section.
v. The weather conditions accord with the coating
ii. The other bridges may be subject only to testing
manufacturer’s directions for coating application.
by static loads.
5.11.3.5 Application iii. The latter test may be further simplified by
reducing the number of tests. It is
1 The exposed concrete surfaces shall be conditioned recommended, however, to measure the
by the application of the penetrating hydrophobic primer. deflection at, at least, one point per span.
The primer shall be allowed to dry in accordance with the
7 Bridges are considered similar when their
manufacturer’s requirements.
superstructures have the same design, same material
2 The Contractor shall then apply two coats of the specifications and are constructed by the same contractor.
pigmented topcoat in accordance with the manufacturer’s
8 If the results of the load testing are unfavorable, and
instructions. The finished coating shall be pinhole free.
leave some doubt as to the ability of the bridge to
The color and finish shall be agreed with the Engineer.
withstand the loads it is supposed to carry, more elaborate
3 The coating shall be applied by spray, roller or brush testing shall be considered, including non-destructive full-
to achieve a finish acceptable to the Engineer. scale testing.

5.11.4 Method of Measurement, Basis of 5.12.2 Load Application


Payment and Bill of Quantities
5.12.2.1 Composition of Applied Load
1 No separate measurement is made for protective
coating and no items are included in the Bill of Quantities 1 The applied load shall consist of a number of loaded
for direct payment. The work is considered as subsidiary trucks sufficient to satisfy the requirements of this Clause.
work, the cost of which will be deemed to be included in 2 The loads shall be applied in two types of tests: by
the unit rates for the relevant BOQ Items for concrete static loads and moving loads.
described and measured for payment under the provisions
3 The loads shall be restricted to the carriageways and
of Section 5.1 “Concrete Materials and Mixes”.
no load is applied on the sidewalks.

♦ 5-67 ♦
copy 249
4 The stipulations of this Clause are set as minimum 3 After the completion of testing, a detailed visual
requirements. In particular cases, when there is doubt inspection shall also be carried out to all accessible parts
about the quality of the bridge, the Engineer may impose of the bridge.
more severe loads. 4 Visual inspections shall be complemented with
photographs.
5.12.2.2 Testing by Static Load

1 The loaded trucks shall be positioned on the 5.12.4 Measurements


carriageways and grouped together in the longitudinal
1 As a minimum the deflections of each span and the
and transverse directions such that the straining actions
deformation of the bearings shall be measured.
they develop are between 67 and 75 percent of the
maximum straining actions developed by all unfactored 2 Measurement of the deflections will be carried out by
loading cases. topographic equipment or by deflectometers installed on
scaffoldings independent of the structure as instructed by
2 The straining actions considered do not include any
the Engineer.
load factor magnification.
3 If specified or instructed by the Engineer, additional
3 The test starts by loading the bearings before
measurements may be requested such as the strains in
applying any loads on the spans in order to activate
the steel reinforcement and/or concrete surface.
immediately the bearing deformation, and then the
measured deflections will be significant. 4 Digital recording of measurements by electronic
means is encouraged for important structures, particularly
4 Bridges with simply supported spans shall have the
for strain measurements and moving load testing. It may
loads applied independently on every span.
be imposed by instruction of the Engineer.
5 Bridges with continuous spans shall have the loads
5 The ambient temperature shall be recorded with
applied independently on every span, then on every two
every measurement made.
adjacent spans, with no loads on the others, to obtain the
maximum hogging (negative) bending moment over the 6 A report shall be prepared by the Contractor
support. The latter loading shall be repeated for every including the testing procedure, measurements,
intermediate support. interpretation and conclusion.
6 The loads shall be applied gradually, one truck at a
time. After each load increment, there will be a 5.12.5 Method of Measurement
consolidation period of one hour, or as instructed by the 1 Load testing of the bridge shall be measured by the
Engineer, during which no load is applied. Measurements number of bridges tested as instructed by the Engineer,
shall be recorded at the beginning and end of the loading inclusive of all static load cases and moving load testing
increment period and of the consolidation period. and inclusive of the provision and operation of the loaded
7 Removal of the load shall also be done by equal trucks, measuring and recording equipment of any type
decrements with a consolidation period of one hour, or as and their calibration, platforms and scaffoldings for visual
instructed by the Engineer. Measurements shall be inspection and of accepted testing report.
recorded at the beginning and end of the loading
decrement period and of the consolidation period. 5.12.6 Basis of Payment
5.12.2.3 Testing by Moving Load 1 The amount of completed and accepted work
measured as provided for above shall be paid at the unit
1 Out of the loaded trucks used for static loading of the
rates in the Bill of Quantities. These rates shall be full
bridge, a number shall be selected equal to the number of
compensation for the provision of labor, materials,
traffic lanes. The selection shall consider those with the
equipment, tools and other items necessary for proper
heaviest axle loads. The trucks shall travel in one direction
completion of the Work.
along the whole length of the bridge at the largest
possible speed with due consideration of safety measures.
5.12.7 Items in the Bill of Quantities
2 Measurements shall be recorded during passage of
the moving load. i Bridge loading test nr.

5.12.3 Visual Inspection


1 All parts of the structure that can be accessed by
platforms, scaffoldings or other means shall be visually
inspected jointly by the Engineer and the Contractor
before start of testing.
2 During static load testing, visual inspection shall also
be carried out in the consolidation periods at reasonable
at intervals.

♦ 5-68 ♦
copy 249
Ref. Title Page No.
6.1 Description 6-1
6.1.1 Summary 6-1
6.1.2 Definitions 6-1
6.1.3 Submittals 6-1
6.1.4 Quality Assurance 6-1
6.1.5 Delivery, Storage, and Handling 6-2
6.1.6 Coordination 6-2

6.2 Materials 6-2


6.2.1 Structural-Steel Materials and Steel
Railings 6-2
6.2.2 Bolts, Connectors, and Anchors 6-2
6.2.3 Grout 6-3
6.2.4 Fabrication 6-3
6.2.5 Shop Connections 6-4
6.2.6 Source Quality Control 6-4

6.3 Construction Requirements 6-4


6.3.1 Examination 6-4
6.3.2 Preparation 6-5
6.3.3 Erection 6-5
6.3.4 Orthotropic-Deck Super Structure 6-5
6.3.5 Field Connections 6-6
6.3.6 Field Quality Control 6-6

6.4 Method of Measurement 6-6


6.5 Basis of Payments 6-7
6.6 Items in the Bill of Quantities 6-7

copy 249
copy 249
6.1 Description Show backing bars that are to be removed and
supplemental fillet welds where backing bars are
6.1.1 Summary to remain.
iv. Indicate type, size, and length of bolts,
1 This Section describes:
distinguishing between shop and field bolts.
i. Structural steel.
Identify pre-tensioned and slip-critical high-
ii. Grout. strength bolted connections.
iii. Steel pipe and tube railings.
v. Identify members and connections of the
seismic-load-resisting system.
6.1.2 Definitions vi. Indicate locations and dimensions of protected
1 Structural Steel: Elements of structural-steel frame, zones.
as classified by AISC 303, ‘Code of Standard Practice for vii. Identify demand critical welds.
Steel Buildings and Bridges.’ 4 Welding Procedure Specifications (WPSs) and
2 Seismic-Load-Resisting System (SLRS): Elements of Procedure Qualification Records (PQRs): Provide details
structural-steel frame shown on the Drawings, designated according to AWS D1.1/D1.1M, ‘Structural Welding Code -
as ‘SLRS’ or along grid lines designated as "SLRS" on Steel’ for each welded joint qualified by testing, including
Drawings, including columns, beams, and braces and their the following:
connections. i. Power source (constant current or constant
3 Heavy Sections: Rolled and built-up sections as voltage).
follows: ii. Electrode manufacturer and trade name, for
i. Shapes included in ASTM A 6/A 6M with demand critical welds.
flanges thicker than 38 mm. 5 Qualification Data: Submit details for qualified
ii. Welded built-up members with plates thicker Installer, fabricator, professional engineer, and testing
than 50 mm. agency.
iii. Column base plates thicker than 50 mm. 6 Welding certificates.
4 Protected Zone: Structural members or portions of 7 Paint Compatibility Certificates: Submit certificates
structural members indicated as ‘Protected Zone’ on from manufacturers of topcoats applied over shop primers,
Drawings. Connections of structural and nonstructural certifying that shop primers are compatible with topcoats.
elements to protected zones are limited.
8 Mill test reports for structural steel, including
5 Demand Critical Welds: Those welds, the failure of chemical and physical properties.
which would result in significant degradation of the
9 Product Test Reports: Submit reports for the
strength and stiffness of the Seismic-Load-Resisting
following:
System and which are indicated as ‘Demand Critical’ or
‘Seismic Critical’ on Drawings. i. Bolts, nuts, and washers including mechanical
properties and chemical analysis.
6.1.3 Submittals ii. Direct-tension indicators.
iii. Tension-control, high-strength bolt-nut-washer
1 Product Data: Submit data for each type of product
assemblies.
specified or shown on the Drawings or as directed by the
iv. Shear stud connectors.
Engineer.
v. Shop primers.
2 LEED (Leadership in Energy and Environmental vi. Non-shrink grout.
Design) :Submit the following as directed by the Engineer
10 Source quality-control reports.
i. Product data for Credit MR 4.1 and
Credit MR 4.2. For products having recycled 6.1.4 Quality Assurance
content, include documentation indicating
1 Fabricator Qualifications: A qualified fabricator who
percentages by weight of post-consumer and
participates in the AISC Quality Certification Program and
pre-consumer recycled content and a statement
is designated an AISC-Certified Plant or approved by the
indicating costs for each product having recycled
Engineer.
content.
2 Installer Qualifications: A qualified installer who
3 Shop Drawings: Submit shop drawings as required
participates in the AISC Quality Certification Program and
by the specification and directed by the Engineer to show
is designated an AISC-Certified Erector, Category ACSE or
fabrication of structural-steel components.
approved by the Engineer.
i. Include details of cuts, connections, splices,
camber, holes, and other pertinent data. 3 Shop-Painting Applicators: Qualified according to
ii. Include embedment drawings. AISC's Sophisticated Paint Endorsement P1 or SSPC-QP 3,
iii. Indicate welds by standard AWS symbols, "Standard Procedure for Evaluating Qualifications of Shop
distinguishing between shop and field welds, Painting Applicators’ or approved by the Engineer.
and show size, length, and type of each weld.

♦ 6-1 ♦
copy 249
4 Welding Qualifications: Welding procedures and 6.2 Materials
personnel shall be qualified according to
AWS D1.1/D1.1M, ‘Structural Welding Code - Steel". 6.2.1 Structural-Steel Materials and Steel
i. Welders and welding operators performing work Railings
on bottom-flange, demand-critical welds shall 1 Recycled Content of Steel Products: Provide
pass the supplemental welder qualification products with an average recycled content so that the
testing, as required by AWS D1.8 or shall be post-consumer recycled content plus one-half of pre-
approved by the Client Authority. FCAW-S and consumer recycled content is not less than 25 percent.
FCAW-G shall be considered separate processes
2 W-Shapes shall comply, as appropriate, with
for welding personnel qualification.
ASTM A 992/A 992, ASTM A 572/A 572M Grade 5
5 Comply with applicable provisions of the following ASTM A 529/A 529M Grade 50, and ASTM A 913/
specifications and documents: A 913M, Grade 50.
i. AISC 303. 3 Channels, angles , M shapes and , S-shapes shall
ii. AISC 341 and AISC 341s1. comply, as appropriate, with ASTM A 36/A 36M,
iii. AISC 360. ASTM A 572/A 572M Grade 50, ASTM A 529/A 529M
iv. RCSC's "Specification for Structural Joints Using Grade 50 and ASTM A 913/A 913M Grade 50.
ASTM A 325 or A 490 Bolts."
4 Plate and bar shall comply, as appropriate with
6 Pre-installation Conference: Conduct conference at ASTM A 36/A 36M, ASTM A 572/A 572M Grade 50, and
Site. ASTM A 529/A 529M Grade 50.
7 Source Limitations: Obtain each type of railing or 5 Corrosion-resisting low-alloy structural-steel shapes,
similar product from single source, from single plates, and bars shall comply with ASTM A 588/A 588M,
manufacturer. Grade 50.
6 Cold-formed hollow structural sections shall comply
6.1.5 Delivery, Storage, and Handling
with ASTM A 500, Grade B or C, structural tubing.
1 Store materials to permit easy access for inspection
7 Corrosion-resisting cold-formed hollow structural
and identification. Keep steel members off ground and
sections shall comply with ASTM A 847/A 847M,
spaced by using pallets, dunnage, or other supports and
structural tubing.
spacers. Protect steel members and packaged materials
from corrosion and deterioration. 8 Steel Pipe shall comply with ASTM A 53/A 53M,
i. Do not store materials on a structure in a manner Type E or S, Grade B.
that might cause distortion, damage, or overload i. Weight Class: Standard.
to members or supporting structures. Repair or ii. Finish: Black except where indicated to be
replace damaged materials or structures as galvanized.
directed. 9 Steel castings shall comply with
2 Store fasteners in a protected place in sealed ASTM A 216/A 216M, Grade WCB with supplementary
containers with manufacturer's labels intact. requirement S11.
i. Fasteners may be repackaged only with the 10 Steel Forgings shall comply with
Engineer’s approval and under his supervision. ASTM A 668/A 668M.
ii. Clean and re-lubricate bolts and nuts that 11 Welding Electrodes shall comply with AWS
become dry or rusty before use. requirements.
iii. Comply with manufacturers' written
12 Woven-wire mesh shall be intermediate-crimp,
recommendations for cleaning and lubricating
diamond or square pattern, 50-mm woven-wire mesh,
ASTM F 1852 fasteners and for retesting
made from 3.5-mm nominal diameter wire complying with
fasteners after lubrication.
ASTM A 510M.

6.1.6 Coordination 6.2.2 Bolts, Connectors, and Anchors


1 Coordinate selection of shop primers with topcoats
1 High-Strength Bolts, Nuts, and Washers:
to be applied over them. Comply with paint and coating
ASTM A 325 (ASTM A 325M), Type 1, heavy-hex steel
manufacturers' recommendations to ensure that shop
structural bolts; ASTM A 563, Grade C, (ASTM A 563M,
primers and topcoats are compatible with one another.
Class 8S) heavy-hex carbon-steel nuts; and ASTM F 436
2 Coordinate installation of anchorage items to be (ASTM F 436M), Type 1, hardened carbon-steel washers;
embedded in or attached to other construction so as not to all with plain finish.
delay the work. Provide setting diagrams, sheet metal i. Direct-Tension Indicators: ASTM F 959,
templates, instructions, and directions for installation. Type 325 (ASTM F 959M, Type 8.8),
compressible-washer type with plain finish.
High-Strength Bolts, Nuts, and Washers: ASTM A 490
(ASTM A 490M), Type 1, heavy-hex steel structural bolts;

♦ 6-2 ♦
copy 249
ASTM A 563, Grade DH, (ASTM A 563M, Class 10S) 9 Eye Bolts and Nuts: Made from cold-finished carbon
heavy-hex carbon-steel nuts; and ASTM F 436 steel bars, ASTM A 108, Grade 1030.
(ASTM F 436M), Type 1, hardened carbon-steel washers 10 Sleeve Nuts: Made from cold-finished carbon steel
with plain finish. bars, ASTM A 108, Grade 1018.
i. Direct-Tension Indicators: ASTM F 959,
11 Structural Slide Bearings: Low-friction assemblies, of
Type 490 (ASTM F 959M, Type 10.9),
configuration indicated, that provide vertical transfer of
compressible-washer type with plain finish.
loads and allow horizontal movement perpendicular to
2 Zinc-Coated High-Strength Bolts, Nuts, and Washers: plane of expansion joint while resisting movement within
ASTM A 325 (ASTM A 325M), Type 1, heavy-hex steel plane of expansion joint.
structural bolts; ASTM A 563, Grade DH (ASTM A 563M, i. Manufacturers: Subject to compliance with work
Class 10S) heavy-hex carbon-steel nuts; and ASTM F 436 requirements.
(ASTM F 436M), Type 1, hardened carbon-steel washers. ii. Basis-of-Design Product: Subject to compliance
i. Finish: Hot-dip or mechanically deposited zinc with requirements, provide product indicated on
coating. Drawings or comparable product.
ii. Direct-Tension Indicators: ASTM F 959, iii. Mating Surfaces: PTFE and mirror-finished
Type 325 (ASTM F 959M, Type 8.8), stainless steel.
compressible-washer type with mechanically iv. Coefficient of Friction: Not more than 0.03.
deposited zinc coating v. Design Load: Not less than 41 MPa.
3 Tension-Control, High-Strength Bolt-Nut-Washer vi. Total Movement Capability: 50 mm.
Assemblies: ASTM F 1852, Type 1, heavy-hex head 12 Fasteners for Interconnecting Railing Components:
assemblies consisting of steel structural bolts with splined i. Provide concealed fasteners for interconnecting
ends, heavy-hex carbon-steel nuts, and hardened carbon- railing components and for attaching them to
steel washers. other work, unless otherwise indicated.
i. Finish: Mechanically deposited zinc coating. ii. Provide concealed fasteners for interconnecting
4 Shear Connectors: ASTM A 108, Grades 1015 railing components and for attaching them to
through 1020, headed-stud type, cold-finished carbon other work, unless exposed fasteners are
steel; AWS D1.1/D1.1M, Type B. unavoidable or are the standard fastening
method for railings indicated.
5 Unheaded Anchor Rods: ASTM F 1554, Grade 36 or
iii. Provide square or hex socket flat-head machine
ASTM F 1554, Grade 55, weldable
screws for exposed fasteners unless otherwise
i. Configuration: Hooked.
indicated.
ii. Nuts: ASTM A 563 (ASTM A 563M) heavy-hex
carbon steel.
6.2.3 Grout
iii. Plate Washers: ASTM A 36/A 36M carbon steel.
iv. Washers: ASTM F 436 (ASTM F 436M), Type 1, 1 Metallic, Shrinkage-Resistant Grout: ASTM C 1107,
hardened carbon steel. factory-packaged, metallic aggregate grout, mixed with
v. Finish: Hot-dip zinc coating, water to consistency suitable for application and a 30-
ASTM A 153/A 153M, Class C. minute working time.

6 Headed Anchor Rods: [ASTM F 1554, Grade 36] 2 Non-metallic, Shrinkage-Resistant Grout:
[ASTM F 1554, Grade 55, weldable] [ASTM A 354] ASTM C 1107, factory-packaged, nonmetallic aggregate
[ASTM A 449], straight. grout, noncorrosive and non-staining, mixed with water to
i. Nuts: ASTM A 563 (ASTM A 563M) heavy-hex consistency suitable for application and a 30-minute
carbon steel. working time.
ii. Plate Washers: ASTM A 36/A 36M carbon steel.
iii. Washers: ASTM F 436 (ASTM F 436M), Type 1, 6.2.4 Fabrication
hardened carbon steel. 1 Structural Steel: Fabricate and assemble in shop to
iv. Finish: Hot-dip zinc coating, greatest extent possible. Fabricate according to AISC's
ASTM A 153/A 153M, Class C. "Code of Standard Practice for Steel Buildings and
7 Threaded Rods: ASTM A 36/A 36M and Bridges" and AISC 360.
A 572/A 572M, Grade 50 (345). i. Camber structural-steel members where
i. Nuts: ASTM A 563 (ASTM A 563M) heavy-hex indicated.
carbon steel. ii. Fabricate beams with rolling camber up.
ii. Washers: [ASTM F 436 (ASTM F 436M), iii. Identify high-strength structural steel according
Type 1, hardened]. to ASTM A 6/A 6M and maintain markings until
iii. Finish: Hot-dip zinc coating, structural steel has been erected.
ASTM A 153/A 153M, Class C. iv. Mark and match-mark materials for field
assembly.
8 Clevises and Turnbuckles: Made from cold-finished
carbon steel bars, ASTM A 108, Grade 1035.

♦ 6-3 ♦
copy 249
v. Complete structural-steel assemblies, including Using ASTM A 325 or A 490 Bolts" for type of bolt and
welding of units, before starting shop-priming type of joint specified.
operations. i. Joint Type: Slip critical.
2 Thermal Cutting: Perform thermal cutting by 2 Weld Connections: Comply with AWS D1.1/D1.1M
machine to greatest extent possible and AWS D1.8/D1.8M for tolerances, appearances,
i. Plane thermally cut edges to be welded to welding procedure specifications, weld quality, and
comply with requirements in AWS D1.1/D1.1M. methods used in correcting welding work.
3 Bolt Holes: Cut, drill, or punch standard bolt holes i. Assemble and weld built-up sections by methods
perpendicular to metal surfaces. that will maintain true alignment of axes without
4 Finishing: Accurately finish ends of columns and exceeding tolerances in AISC 303 for mill
other members transmitting bearing loads. material.

5 Cleaning: Clean and prepare steel surfaces that are


6.2.6 Source Quality Control
to remain unpainted according to SSPC-SP 3, "Power Tool
Cleaning" 1 Testing Agency: The Employer may engage an
independent testing and inspecting agency to perform
6 Shear Connectors: Prepare steel surfaces as
shop tests and inspections and prepare test reports.
recommended by manufacturer of shear connectors. Use
i. Provide testing agency with access to places
automatic end welding of headed-stud shear connectors
where structural-steel work is being fabricated or
according to AWS D1.1/D1.1M and manufacturer's written
instructions. produced to perform tests and inspections.
2 Correct deficiencies in work that test reports and
7 Holes: Form holes required for securing other work
inspections indicate does not comply with the
to structural steel and for other work to pass through steel
Specification or Drawings.
framing members.
i. Cut, drill, or punch holes perpendicular to steel 3 Bolted Connections: Shop-bolted connections will
surfaces. Do not thermally cut bolt holes or be tested and inspected according to RCSC's
enlarge holes by burning. "Specification for Structural Joints Using ASTM A 325 or
ii. Base plate holes: Cut, drill, mechanically thermal A 490 Bolts."
cut, or punch holes perpendicular to steel 4 Welded Connections: In addition to visual inspection,
surfaces. shop-welded connections will be tested and inspected
iii. Weld threaded nuts to framing and other according to AWS D1.1/D1.1M and the following
specialty items indicated to receive other work. inspection procedures, at testing agency's option:
8 Steel pipe and tube railings: i. Liquid Penetrant Inspection: ASTM E 165.
i. Fabricate connections that will be exposed to ii. Magnetic Particle Inspection: ASTM E 709;
weather in a manner to exclude water. Provide performed on root pass and on finished weld.
weep holes where water may accumulate. Cracks or zones of incomplete fusion or
ii. Connections: Fabricate railings with either penetration will not be accepted.
welded or non-welded connections unless iii. Ultrasonic Inspection: ASTM E 164.
otherwise indicated. iv. Radiographic Inspection: ASTM E 94.
iii. Connect members with concealed mechanical 5 In addition to visual inspection, shop-welded shear
fasteners and fittings. connectors will be tested and inspected according to
iv. Form changes in direction by bends of radius requirements in AWS D1.1/D1.1M for stud welding and as
indicated or by inserting prefabricated elbow follows:
fittings of radius indicated. i. Bend tests will be performed if visual inspections
v. Close exposed ends of railing members with reveal either a less-than-continuous 360-degree
prefabricated end fittings. flash or welding repairs to any shear connector.
vi. Provide inserts and other anchorage devices for ii. Tests will be conducted on additional shear
connecting railings to concrete or masonry work. connectors if weld fracture occurs on shear
Fabricate anchorage devices capable of connectors already tested, according to
withstanding loads imposed by railings. requirements in AWS D1.1/D1.1M.
Coordinate anchorage devices with supporting
structure. 6.3 Construction Requirements
9 Galvanization: The minimum average thickness of
coating for all galvanized specimens shall conform to the 6.3.1 Examination
requirements of ASTM A 123/A 123M. 1 Verify, with steel erector present, elevations of
concrete- and masonry-bearing surfaces and locations of
6.2.5 Shop Connections anchor rods, bearing plates, and other embedments for
1 High-Strength Bolts: Shop install high-strength bolts compliance with requirements.
according to RCSC's "Specification for Structural Joints

♦ 6-4 ♦
copy 249
i. Prepare a certified survey of bearing surfaces, 6 Do not use thermal cutting during erection unless
anchor rods, bearing plates, and other approved by Engineer. Finish thermally cut sections
embedment, showing dimensions, locations, within smoothness limits in AWS D1.1/D1.1M.
angles, and elevations. 7 Do not enlarge unfair holes in members by burning
2 Proceed with installation only after unsatisfactory or using drift pins. Ream holes that must be enlarged to
conditions have been corrected. admit bolts.
i. Shear Connectors: Prepare steel surfaces as
6.3.2 Preparation recommended by manufacturer of shear
1 Provide temporary shores, guys, braces, and other connectors. Use automatic end welding of
supports during erection to keep structural steel secure, headed-stud shear connectors according to
plumb, and in alignment against temporary construction AWS D1.1/D1.1M and manufacturer's written
loads and loads equal in intensity to design loads. instructions.
Remove temporary supports when permanent structural
steel, connections, and bracing are in place unless 6.3.4 Orthotropic-Deck Super Structure
otherwise indicated.
1 Protection of Deck Plate after Sandblasting: If
i. Do not remove temporary shoring supporting sandblasting to a white metal, or an equivalent method, is
composite deck construction until cast-in-place used to prepare the deck plate to receive a wearing
concrete has attained its design compressive surface, a protective coating shall be applied to the plate
strength. immediately after cleaning.

6.3.3 Erection 2 Dimensional Tolerance Limits:

1 Set structural steel accurately in locations and to i. Dimensional tolerance limits for orthotropic-deck
elevations indicated and according to AISC 303 and bridge members shall be applied to each
AISC 360. completed but unloaded member and shall be as
specified in the AWS Structural Welding Code
2 Base Bearing and Leveling Plates: Clean concrete-
except as superseded hereinafter. The deviation
and masonry-bearing surfaces of bond-reducing materials,
from detailed flatness, straightness, or curvature
and roughen surfaces prior to setting plates. Clean
at any point shall be the perpendicular distance
bottom surface of plates.
from that point to a template edge which has the
i. Set plates for structural members on wedges, detailed straightness or curvature and which is in
shims, or setting nuts as required. contact with the element at two other points.
ii. Weld plate washers to top of base plate. The term element as used herein refers to
iii. Snug-tighten anchor rods after supported individual panels, stiffeners, flanges, or other
members have been positioned and plumbed. pieces. The template edge may have any length
Do not remove wedges or shims but, if not exceeding the greatest dimension of the
protruding, cut off flush with edge of plate element being examined and, for any panel, not
before packing with grout. exceeding 1.5 times the least dimension of the
iv. Promptly pack grout solidly between bearing panel; it may be placed anywhere within the
surfaces and plates so no voids remain. Neatly boundaries of the element. The deviation shall
finish exposed surfaces; protect grout and allow be measured between adjacent points of contact
curing. Comply with manufacturer's written of the template edge with the element; the
installation instructions for shrinkage-resistant distance between these adjacent points of
grouts. contact shall be used in the formulas to establish
3 Maintain erection tolerances of structural steel and the tolerance limits for the segment being
steel railing within AISC's "Code of Standard Practice for measured whenever this distance is less than the
Steel Buildings and Bridges." applicable dimension of the element specified for
4 Align and adjust various members that form part of the formula.
complete frame or structure before permanently fastening. ii. The term panel as used in this paragraph means
Before assembly, clean bearing surfaces and other a clear area of steel plate surface bounded by
surfaces that will be in permanent contact with members. stiffeners, webs, flanges, or plate edges and not
Perform necessary adjustments to compensate for further subdivided into such elements. The
discrepancies in elevations and alignment. provisions of this paragraph apply to all panels
in the bridge; for plates stiffened on one side
i. Level and plumb individual members of structure.
only such as orthotropic-deck plates or flanges of
ii. Make allowances for difference between
box girders, this includes the total clear width on
temperature at time of erection and mean
the side without stiffeners as well as the panels
temperature when structure is completed and in
between stiffeners on the side with stiffeners.
service.
The maximum deviation from detailed flatness
5 Splice members only where indicated. or curvature of a panel shall not exceed 5 mm.

♦ 6-5 ♦
copy 249
The maximum deviation from detailed - Radiographic Inspection: ASTM E 94.
straightness or curvature in any direction 4 In addition to visual inspection, test and inspect field-
perpendicular to its length of a longitudinal welded shear connectors according to requirements in
stiffener subject to calculated compressive stress, AWS D1.1/D1.1M for stud welding and as follows:
including each orthotropic-deck rib, shall not
i. Perform bend tests if visual inspections reveal
exceed L/480, where L = the length of the
either a less-than-continuous 360-degree flash or
stiffener or rib between cross members, webs, or
welding repairs to any shear connector.
flanges, in millimeters.
ii. Conduct tests on additional shear connectors if
iii. The maximum deviation from detailed
weld fracture occurs on shear connectors already
straightness or curvature in any direction
tested, according to requirements in
perpendicular to its length of a transverse web
AWS D1.1/D1.1M.
stiffener or other stiffener not subject to
calculated compressive stress shall not exceed 5 Correct deficiencies in work that test reports and
L/240, where L = the length of the stiffener or rib inspections indicate does not comply with the
between cross members, webs, or flanges, in Specification or Drawings.
millimeters.
6.4 Method of Measurement
6.3.5 Field Connections
1 Structural steel is measured by weight in tonnes.
1 High-Strength Bolts: Install high-strength bolts
Except for rolled steel sections and plates whose weights
according to RCSC's "Specification for Structural Joints
are computed from nominal weight as paragraphs 2 and 3
Using ASTM A 325 or A 490 Bolts" for type of bolt and
below, the weight shall be calculated on the basis that 1.0
type of joint specified.
cu. meter weighs 7850 kg.
i. Joint Type: Slip critical.
2 The weights of rolled shapes shall be computed on
2 Weld Connections: Comply with AWS D1.1/D1.1M the basis of their nominal weights per meter as shown on
and AWS D1.8/D1.8M for tolerances, appearances, the Drawings, or listed in the handbooks.
welding procedure specifications, weld quality, and
3 The weights of plates shall be computed on the basis
methods used in correcting welding work.
of the nominal weight for their width and thickness as
i. Comply with AISC 303 and AISC 360 for bearing,
shown on the Drawings, plus an estimated overrun
alignment, adequacy of temporary connections,
computed as one-half the ‘Permissible Variation in
and removal of paint on surfaces adjacent to
Thickness and Weight’ as tabulated in Specification,
field welds.
‘General Requirements for Delivery of Rolled Steel Plates,
ii. Remove backing bars or runoff tabs, back gouge,
Shapes, Steel Piling, and Bars for Structural Use’,
and grind steel smooth.
AASHTO M 160.
iii. Assemble and weld built-up sections by methods
that will maintain true alignment of axes without 4 The weight of castings shall be computed from the
exceeding tolerances in AISC's "Code of dimensions shown on the approved shop drawings,
Standard Practice for Steel Buildings and deducting for open holes. To this weight shall be added 5
Bridges" for mill material. percent allowance for fillets and over-run. Scale weights
may be substituted for computed weights in the case of
6.3.6 Field Quality Control castings or of small complex parts for which accurate
computations of weight would be difficult.
1 Testing Agency: The Employer may engage a
qualified independent testing and inspecting agency to 5 The weight of temporary erection bolts, shop and
inspect field welds and high-strength bolted connections. field paint, boxes, crates, and other containers used for
shipping, and materials used for supporting members
2 Bolted Connections: Bolted connections will be
during transportation and erection, shall not be included
tested and inspected according to RCSC's "Specification
in the rate and is subsidiary to the rate of structural steel.
for Structural Joints Using ASTM A 325 or A 490 Bolts."
6 In computing pay weight on the basis of computed
3 Welded Connections: Field welds will be visually
net weight the following stipulations in addition to those
inspected according to AWS D1.1/D1.1M.
in the foregoing paragraphs shall apply:
i. In addition to visual inspection, field welds will
i. The weight shall be computed on the basis of the
be tested and inspected according to
net finished dimensions of the parts as shown on
AWS D1.1/D1.1M and the following inspection
the approved shop drawing, deducting for copes,
procedures, at testing agency's option:
cuts, clips, and all open holes, except bolt holes.
- Liquid Penetrant Inspection: ASTM E 165. ii. The weight of heads, nuts, single washers, and
- Magnetic Particle Inspection: ASTM E 709; threaded stick-through of all high-tensile
performed on root pass and on finished weld. strength shop bolts, both shop and field, shall be
Cracks or zones of incomplete fusion or included on the basis of the following weights:
penetration will not be accepted.
- Ultrasonic Inspection: ASTM E 164.

♦ 6-6 ♦
copy 249
Diameter of Bolt Weight per 100 bolts 6.5 Basis of Payments
mm kg
12 9.0 1 The prices for fabrication and erection of structural
16 14.4 steel and railings shall include all labor, materials,
19 23.8 equipment, transportation, and shop and field painting
22 36.5 necessary for the proper completion of the work in
25 53.0 accordance with the contract. The prices for fabrication
29 75.0 without erection shall include all labor and materials
32 96.4 necessary for the proper completion of the work.
35 127.3
38 154.5 6.6 Items in the Bill of Quantities
Table 6.4-1 Bolt Weights
1 Payment will be made under one or more of the
iii. The weight of weld metal shall be computed on following:
the basis of the theoretical volume from
dimensions of the welds. i. Structural Steel (grade) (t.)
7 In computing pay weight on the basis of computed
ii. Railings (Type) (height) (lin. m.)
gross weight, the following stipulations in addition to the
above shall apply.
i. The weight shall be calculated on the basis of
rectangular dimensions for all plates, and
ordered over-all lengths for all structural shapes;
except that (A) when parts can be economically
cut in multiples from material of larger
dimensions, the computed weight shall be that
of the material from which the parts are cut, and
(B) all material shall be ordered to produce as
little waste as practicable when cut and finished
by modern shop methods.
ii. No deductions from the computed weight of
rolled steel shall be made for the copes, clips,
sheared edges, punchings, borings, milling or
planning; or from the computed weight of
castings to allow for drillings or borings.
iii. The weight of weld metal shall be computed on
the basis of the theoretical volume of the
dimensions of the welds. To this weight shall be
added 50 percent allowance for overrun.
8 In computing pay weight on the basis of scale
weights, the pay quantity of structural steel will be the
shop scale weight of the fabricated members, which shall
be weighed on satisfactory scales in the presence of the
Inspector. If the shop paint has been applied to the
completed member when weighed, 0.4 percent of the
weight of the member shall be deducted from the scale
weight of the member to compensate for weight of shop
paint. The weight of field bolts shall be based on the
approved shipping list. No payment will be made for any
weight in excess of 1.5 percent above the computed net
weight of the whole item.
9 Steel railings are measured in lin. meters as the
actual length fixed in position according to type and
height, without differentiation for straight, curved, raking
and stepped railings The rates are deemed to include for
all accessories and fixings and finishes.

♦ 6-7 ♦
copy 249
copy 249
Ref. Title Page No. Ref. Title Page No.
7.1 Description 7-1 7.2.5.11  Brushing Properties  7‐3 
7.2.5.12  Spraying Properties  7‐3 
7.1.1  Summary  7‐1 
7.2.5.13  Drying Time  7‐3 
7.1.1.1  Description  7‐1 
7.2.6 Zinc Dust-Zinc Oxide Primer 7-4
7.2 Materials 7-1 7.2.6.1  Description  7‐4 
7.2.1 General 7-1 7.2.6.2  Zinc Oxide Vehicle  7‐4 
7.2.1.1  References and Warranties  7‐1  7.2.6.3  Zinc Dust-Zinc Oxide Mixed Primer  7‐4 
7.2.1.2  Composition and Mixing  7‐1  7.2.7 Aluminum Paint 7-5
7.2.1.3  Compatibility  7‐1  7.2.7.1  Description  7‐5 
7.2.1.4  Covering Qualities  7‐1  7.2.7.2  Proportions  7‐5 
7.2.1.5  Containers  7‐1  7.2.7.3  Mixing 7‐5 
7.2.1.6  Delivery  7‐1  7.2.8 Tinted Aluminum Paint 7-5
7.2.1.7  Storage and Handling  7‐1  7.2.8.1  Description  7‐5 
7.2.2 Pigments and Pastes 7-1 7.2.8.2  Proportions  7‐5 
7.2.3 Paint Oils, Thinners and Dryers 7-2 7.2.9 Basic Lead Silico-Chromate Maroon
7.2.4 Red Lead Paint 7-2 Field Coat 7-5
7.2.4.1  Description  7‐2  7.2.9.1  Description  7‐5 
7.2.4.2  Composition  7‐2  7.2.9.2  Composition  7‐5 
7.2.4.3  Weight per Liter  7‐2  7.2.9.3  Weight per Liter  7‐5 
7.2.4.4  Coarse Particles  7‐2  7.2.9.4  Coarse Particles  7‐5 
7.2.4.5  Consistency  7‐2  7.2.9.5  Consistency  7‐5 
7.2.4.6  Condition in Container  7‐2  7.2.9.6  Condition in Container  7‐5 
7.2.4.7  Skinning  7‐2  7.2.9.7  Skinning  7‐5 
7.2.4.8  Dilution Stability  7‐2  7.2.9.8  Dilution Stability  7‐5 
7.2.4.9  Brushing Properties  7‐2  7.2.9.9  Brushing Properties  7‐5 
7.2.4.10  Spraying Properties  7‐2  7.2.9.10  Spraying Properties  7‐6 
7.2.4.11  Drying Time  7‐3  7.2.9.11  Drying Time  7‐6 
7.2.4.12  Tinting  7‐3  7.2.10 Basic Lead Silico-Chromate Dark Green
7.2.5 Basic Lead Silico-Chromate Primer 7-3 Finish Coat 7-6
7.2.5.1  Description  7‐3  7.2.10.1  Description  7‐6 
7.2.5.2  Composition  7‐3  7.2.10.2  Composition  7‐6 
7.2.5.3  Weight per Liter  7‐3  7.2.10.3  Weight per Liter  7‐6 
7.2.5.4  Coarse Particles  7‐3  7.2.10.4  Coarse Particles  7‐6 
7.2.5.5  Consistency  7‐3  7.2.10.5  Consistency  7‐6 
7.2.5.6  Flash Point  7‐3  7.2.10.6  Color  7‐6 
7.2.5.7  Condition in Container  7‐3  7.2.10.7  Condition in Container  7‐6 
7.2.5.8  Skinning  7‐3  7.2.10.8  Skinning  7‐6
7.2.5.9  Dilution Stability  7‐3 7.2.10.9 Dilution Stability 7-6
7.2.5.10  Appearance  7‐3 7.2.10.10 Brushing Properties 7-6

copy 249
Ref. Title Page No. Ref. Title Page No.
7.2.10.11  Spraying Properties  7‐6  7.3.8 Painting Existing Structures 7-12
7.2.10.12  Drying Time  7‐6  7.3.9 Painting Steel Piling and Steel Pile
7.2.11 Zinc Dust Paint 7-7 Shells 7-13
7.2.11.1  Description  7‐7  7.3.10 Painting Steel Pile Enclosures
7.2.11.2  Requirements  7‐7  and Tubular Steel Piers 7-13
7.2.12 Gloss Enamel 7-7
7.4 Method of Measurement 7-13
7.2.12.1  Description  7‐7 
7.2.12.2  Requirements  7‐7 
7.5 Basis of Payments 7-13
7.2.13 Sampling and Testing 7-7 7.6 Items in the Bill of Quantities 7-13
7.2.14 Portland Cement Paint 7-7
7.2.14.1  Description  7‐7 
7.2.14.2  Composition  7‐7 
7.2.14.3  Colors  7‐7 
7.2.15 Polymer Latex Paint 7-8
7.2.15.1  Description  7‐8 
7.2.15.2  Composition  7‐8 
7.2.15.3  Colors  7‐8 
7.2.16 Polymer Paint 7-8
7.2.16.1  Description  7‐8 
7.2.16.2  Composition  7‐8 
7.2.16.3  Colors  7‐8 
7.2.17 Acrylic Emulsion Paint 7-8

7.3 Construction Requirements 7-8


7.3.1 General 7-8
7.3.2 Application 7-9
7.3.2.1  General  7‐9 
7.3.3 Concrete Surfaces 7-9
7.3.3.1 Preparation 7-9
7.3.3.2 Painting  7‐10 
7.3.4 Structural Steel ,Requirements 7-11
7.3.5 Shop Coat (Prime) 7-11
7.3.5.1 Shop Cleaning  7‐11 
7.3.5.2 Shop Painting  7‐11 
7.3.6 Field Coat 7-12
7.3.6.1 Field Cleaning  7‐12 
7.3.6.2 Field Painting  7‐12 
7.3.7 Bridge Railings and Guardrails 7-12
7.3.7.1 Bridge Railings  7‐12 
7.3.7.2 Guardrail  7‐12

copy 249
7.1 Description 7.2.1.4 Covering Qualities

1 All mixed paint shall have satisfactory protective and


7.1.1 Summary covering qualities. Mixed paint shall not run, streak, break
7.1.1.1 Description or sag when brushed on a clean one hundred fifty (150)
millimeters by two hundred fifty (250) millimeter glass
1 This Section describes painting to steel and concrete panel placed in a vertical position. The paint shall dry to a
structures and painting to railings and other metalwork. smooth, uniform finish, free from roughness, grit,
2 The work described herein includes protective and unevenness and other surface imperfections.
decorative painting to new and existing structures and
7.2.1.5 Containers
metalwork to meet the ambient conditions.
3 The paints, primers and ancillary products included 1 Paint containers shall be sufficiently strong and
in this Section include a full range of products. The actual durable to withstand shipment and normal handling
products to be used for the particular project shall be as procedures without damage. Paint containers shall be
specified in the Special Specification for each project or as equipped with lids which positively prevent the entrance
directed by the Engineer. of air into the container.

7.2.1.6 Delivery
7.2 Materials
1 All paint shall be delivered to the site in original
7.2.1 General manufacturer's metal containers with labels which give
type, color, quantity, gross and tare, and paint ingredient
7.2.1.1 References and Warranties proportions of every item of the contents.

1 Where reference is made to specifications and 7.2.1.7 Storage and Handling


standards issued by named organizations, such
specifications and standards are hereby made a part of 1 All paints and painting products shall be stored and
this specification to the same extent as if fully set out protected and used in environmental conditions that
herein. ensure that the paint is not affected by extremes of
temperature.
2 The paint manufacturer(s) shall supply evidence that
the proposed products have performed satisfactorily for a
7.2.2 Pigments and Pastes
minimum of five (5) years in conditions similar to those of
Oman as to ultraviolet light exposure and intensive 1 When specified in mixed paints, the following
climatic conditions. pigments and pastes shall comply with the requirements
of the ASTM designations indicated below:
7.2.1.2 Composition and Mixing

1 Paints shall be factory-mixed or in paste form. Mixing Pigments and Pastes ASTM
of dry pigment and a vehicle by the Contractor will not be Zinc Oxide D 79
permitted, except as specifically required by the White Lead, Basic Carbonate D 81
specifications. Mixed paints shall be mixed with a paddle White Lead, Basic Sulfate D 82
to a smooth and homogenous condition. Pigments and Red Lead, ninety-seven (97) percent D 83
insoluble ingredients shall be finely ground to a smooth Grade
uniform consistency Mixed paints or pastes which have Iron Oxide, Class II Type A D 84
hardened, thickened or otherwise deteriorated during Lampblack D 209
storage or shipment will not be accepted. Chrome Oxide Green D 263
2 Thinners for a particular type of paint must mix Titanium Dioxide, Type I D 476
readily with that type of paint. Carbon Black D 561
3 When paint is tinted, the tinting material shall be Magnesium Silicate Pigment D 605
thoroughly mixed into the paint to form an even, uniform Aluminum Pigments, Type II Class B D 962
shade. (except coarse particles may be two
(2) percent maximum)
7.2.1.3 Compatibility Copper Phtalocyanine Blue D 963
1 Finish paint for factory-primed items shall be of a Basic Lead Silico-Chromate D 1648
type compatible with the primer. Primers for unprimed Copper Phthalocyanine Green D 3021
items shall be as recommended by the manufacturer for Table 7.2.2-1: Specifications for Pigments and Paste
use with the finish paint.
2 Siliceous red iron oxide shall meet the following
2 Primers, sealers, undercoat and finishing coat paint
requirements:
shall be compatible in composition and color and, for any
one paint system, shall be the products of the same
manufacturer.

♦ 7-1 ♦
copy 249
Total Iron Oxide, Eighty-five percent (85%) ii. Pigment: The extracted pigment shall conform
Calculated as Fe2O3 min. to the following by weight:
Coarse particles, on One percent (1%) True red lead Sixty-two and Five-tenths (62.5)
Number 325 mesh sieve maximum percent min.
Calcium Oxide Five-tenths percent (0.5%) Ferric oxide siliceous Twelve and Five-tenths (12.5)
max. matter and percent min.
Moisture and other Two percent (2%) max. remainder
volatile material Other oxides of lead
Water soluble matter One and five-tenths
Table 7.2.4-2: Composition of Pigment for Red Lead Paint
percent (1.5%) max.
Oil absorption Sixteen (16%) percent min. 7.2.4.3 Weight per Liter
Siliceous matter Balance
1 Red lead paint shall weigh not less than two (2)
Organic colors None Permitted
kilograms per liter.
Table 7.2.2-2: Requirements of Siliceous Red Iron Oxide
7.2.4.4 Coarse Particles
7.2.3 Paint Oils, Thinners and Dryers
1 Coarse particles and skins retained on a forty-five
1 When specified in mixed paints or vehicles the thousandths (0.045) millimeter (No. 325) sieve shall not
following paint liquids shall comply with the designations exceed one percent (1%) by weight based on pigment.
indicated below:
7.2.4.5 Consistency
Component ASTM
Turpentine, steam distilled D 13 1 Consistency shall be not less than seventy-three (73)
Pine Oil, Type 1 FSS LLL-P-400 nor more than eighty-six (86) Krebs Units (K.U.).
Raw linseed oil D 234 7.2.4.6 Condition in Container
Mineral spirits D 235
Mineral spirits, Grade 1 and Grade FSS TT-T-291 1 The paint shall be thoroughly ground and mixed; it
2 shall not be settled, caked or thickened to such a degree
Boiled linseed oil, Type 1 D 260 that it cannot be redispersed easily with a paddle to a
Dryers, liquid paint, Class B D 600 uniform and homogenous state.
Alkyd resin solutions, Type I, II and FSS TT-R-266 7.2.4.7 Skinning
III
Table 7.2.3-1: Specifications for Paint Liquids 1 Skinning shall be entirely absent from a sample that
has been stored forty-eight (48) hours in a dark place in a
7.2.4 Red Lead Paint three-quarters-filled tightly-closed container.

7.2.4.1 Description 7.2.4.8 Dilution Stability

1 Rapid-dry red lead paint shall consist only of lead 1 The paint shall remain stable and uniform after
pigment, iron oxide pigment, magnesium silicate pigment, reduction with mineral spirits in the proportions of eight
raw linseed oil, linseed oil modified alkyd resin, thinners (8) parts by volume of paint to one (1) part by volume of
and dryers. The paint shall not contain more than four- mineral spirits.
tenths (0.4) percent aluminum stearate to produce loose 7.2.4.9 Brushing Properties
suspension of the pigment during storage.
1 The paint, after thorough mixing, shall have
7.2.4.2 Composition satisfactory brushing and leveling properties and show no
1 Rapid-dry red lead paint shall conform to the running or sagging tendencies when brushed on a vertical
following composition by weight: steel surface.
i. Paint. 7.2.4.10 Spraying Properties
Pigment Sixty-six (66) percent min. 1 The paint, when thinned, shall spray satisfactorily,
Vehicle Thirty-four (34) percent max. show no tendency to orange-peel, sag, creep, or run, and
Non-volatile Fifty-six (56) percent min. shall show satisfactory spraying properties in all other
material in vehicle respects. The mineral spirits used as a reducer shall
Phthalic anhydride Fifteen (15) percent min. conform to FSS TT-T-281 Grade 1, and shall be tested and
based on vehicle approved prior to use.
solids
Water Five-tenths (0.5) percent max.
Table 7.2.4-1: Composition of Red Lead Paint

♦ 7-2 ♦
copy 249
7.2.4.11 Drying Time 7.2.5.5 Consistency

1 The paint shall be touch-dry in not more than four (4) 1 Consistency shall be not less than seventy (70) or
hours and dry-through in not more than sixteen (16) hours more than eighty-three (83) Krebs Units (K.U.).
when applied as in FSS Test Method, Standard Number
141, Method 4061. 7.2.5.6 Flash Point

1 The flash point shall be not less than thirty degrees


7.2.4.12 Tinting
Celsius (30 C) when tested in accordance with Federal Test
1 When used for the shop (prime) and second coat, Method, Standard Number 141, Method 4293 using
sufficient black synthetic or magnetite iron oxides shall be Pensky-Martens Closed Cup Tester.
added to the second coat paint as a tinting agent for
identification of the coated surfaces. 7.2.5.7 Condition in Container

1 The paint shall be thoroughly ground and mixed; it


7.2.5 Basic Lead Silico-Chromate Primer shall not be settled, caked or thickened to such a degree
that it cannot be dispersed easily with a paddle to a
7.2.5.1 Description
uniform and homogenous state.
1 Primer shall be suitable for use as a structural metal,
shop or spot primer. It shall consist only of basic lead 7.2.5.8 Skinning
silico-chromate, and red iron oxide eighty-five (85) percent, 1 Skinning shall be entirely absent from a sample that
linseed-soya oil modified alkyd resin, raw linseed oil, has been stored forty-eight (48) hours in a dark place in a
thinners and dryers. The primer shall not contain more three-quarters-filled tightly-closed container.
than seven-tenths (0.7) percent pigment suspended agent.
The alkyd resin shall conform to FSS TT-R-266, Type III. 7.2.5.9 Dilution Stability

7.2.5.2 Composition 1 The paint shall remain stable and uniform after
reduction with mineral spirits in the proportions of eight
1 Basic lead silico-chromate primer shall conform to (8) parts by volume of paint to one (1) part by volume of
the following by weight: mineral spirits.
i. Paint:
7.2.5.10 Appearance
Pigment Fifty-seven (57) percent min.
Non-volatile material Fifty-two (52) percent min. 1 After a flow-out panel of the paint on one hundred
in vehicle (100) millimeters by three hundred (300) millimeter clean
Phthalic anhydride Fifteen (15) percent min. glass plate has dried in a nearly vertical position at room
based on vehicle temperature, it shall show no streaking or separation.
solids
7.2.5.11 Brushing Properties
Water Five-tenths (0.5) percent max.
Table 7.2.5-1: Composition of Basic Lead Silico-Chromate 1 The paint, after thorough mixing, shall have
Primer Paint satisfactory brushing and leveling properties and show no
running or sagging tendencies when brushed on a vertical
ii. Pigment: The extracted pigment shall conform steel surface at a spreading rate of twelve and three-tenths
to the following by weight: (12.3) square meters per liter.

Basic lead Silico- Ninety-three and two-tenths 7.2.5.12 Spraying Properties


chromate (93.2) percent minimum
Ferric oxide Four and eight-tenths (4.8) to 1 The paint, when thinned, shall spray satisfactorily,
five and eight-tenths (5.8) show no tendency to orange-peel, sag, creep, or run, and
percent shall show satisfactory spraying properties in all other
respects. The mineral spirits used as a reducer shall
Table 7.2.5-2: Composition of Pigment for Basic Lead
conform to FSS TT-T-291, Grade 1 and shall be tested and
Silico-Chromate Primer
approved prior to use.
7.2.5.3 Weight per Liter 7.2.5.13 Drying Time
1 Basic lead silico-chromate primer shall weigh not 1 The paint shall dry to a smooth uniform surface, free
less than one and six-tenths (1.6) kilograms per liter. from roughness, grit, unevenness, and other surface
7.2.5.4 Coarse Particles imperfections. The paint shall be touch-dry in not more
than four (4) hours and shall dry-through in not more than
1 Coarse particles and skins retained on a forty-five sixteen (16) hours when applied as in FSS Test Method,
thousandths (0.045) millimeter (No. 325) sieve shall not Standard Number 141, Method 4061.
exceed one (1) percent by weight based on pigment.

♦ 7-3 ♦
copy 249
7.2.6 Zinc Dust-Zinc Oxide Primer 2 Weight per Liter: Zinc dust-zinc oxide mixed primer
shall weigh not less than one and eight-tenths (1.8)
7.2.6.1 Description kilograms per liter.
1 Type II zinc dust-zinc oxide-phthalic alkyd resin 3 Coarse Particles: Coarse particles and skins retained
primer, conforming to FSS TT-P-641d Type II, shall be a on a forty-five thousandths (0.045) millimeter (No. 325)
ready-to-mix paint for use on galvanized metal surfaces, sieve shall not exceed four (4) percent by weight based on
with the zinc oxide mill-ground into the entire vehicle in pigment.
one (1) container and the dry zinc dust in a separate 4 Consistency: Consistency shall be not less than sixty-
container. The zinc dust shall show an analysis of not less seven (67) nor more than eight-six (86) Krebs Unit (K.U.).
than ninety-four percent (94%) metallic zinc by weight. The
5 Dilution Stability: The mixed primer shall remain
zinc oxide vehicle shall consist of zinc oxide and a vehicle
stable and uniform after reduction with mineral spirits in
containing long oil, linseed-modified alkyd resin of the air
the proportions of eight (8) parts by volume of paint to
drying type, petroleum or terpene thinners, dryers and
one (1) part by volume of mineral spirits. After standing
anti-skimming agents.
twenty-four (24) hours there shall be no curdling or
7.2.6.2 Zinc Oxide Vehicle precipitation on the vehicle.
6 Flexibility: After air-drying eighteen (18) hours,
1 Composition: Zinc oxide vehicle shall conform to the
baking for twenty-four (24) hours at one hundred five
following by weight:
degrees Celsius (105°C) and cooling to twenty-three
Zinc oxide in the extracted Ninety-eight (98) degrees Celsius (23°C), a film of the mixed primer applied
and ignited pigment percent min. to flat tin panel with a five-hundredths (0.05) millimeter
Non-volatile material in the Forty-three (43) percent Bird Film Applicator shall show no cracking after bending
vehicle min. double over a three (3) millimeter mandrel. This test shall
Phthalic anhydride based on Twenty-three(23) be conducted according to FSS Test Method Number 141,
vehicle solids percent min. Method 2012.
None 7 Adhesion: After air-drying for eighteen (18) hours,
Rosin or rosin derivatives
baking for three (3) hours at one hundred twenty-one
Table 7.2.6-1: Composition of Zinc Oxide Vehicle degrees Celsius (121°C), a film of the mixed primer
brushed on a clean new galvanized iron panel, seventy-
2 Condition in Container: The zinc oxide vehicle shall five (75) millimeters by one hundred fifty (150) millimeters,
be thoroughly ground and mixed. It shall not be settled, shall cut loose in the form of a ribbon without flaking or
caked, or thickened to such a degree that it cannot be otherwise loosening from the panel when tested with a
redispersed easily with a paddle to a uniform and knife blade.
homogenous state. It shall be readily incorporated with
8 Brushing Properties: The mixed primer, after
the zinc dust to form a smooth uniform paint of good
thorough mixing, shall have satisfactory brushing and
brushing consistency.
leveling properties and show no running or sagging
7.2.6.3 Zinc Dust-Zinc Oxide Mixed Primer tendencies when brushed on a vertical surface three
hundred (300) millimeters by six hundred (600) millimeters
1 Composition.: Zinc dust-zinc oxide mixed primer of smooth, clean, untreated galvanized iron.
shall conform to the following by weight when mixed in
9 Spraying Properties: The mixed primer when thinned
the proportions as submitted in the original containers:
with not more than one (1) part by volume of mineral
i. Primer.
spirits to eight (8) parts by volume of paint shall spray
Pigment Sixty-two (62) to sixty-five (65) percent satisfactorily, show no tendency to orange-peel, sag, creep,
Vehicle Thirty-five (35) to thirty-eight (38) percent or run, and shall show satisfactory spraying properties in
Water Three-tenths (0.3) percent max. all other respects.
Table 7.2.6-2: Composition of Zinc Dust-Zinc Oxide Mixed 10 Drying Time: The mixed primer shall be touch-dry in
Primer not less than thirty (30) minutes nor more than four (4)
hours and dry-hard in not more than eighteen (18) hours
ii. Pigment: The extracted pigment shall conform when applied as in FSS Test Method, Standard Number
to the following by weight: 141, Method 4061.

Metallic zinc Seventy-four (74) percent min.


Zinc oxide Eighteen (18) percent min
Metallic zinc plus zinc Ninety-seven (97) percent
oxide min.
Sulfide sulfur None
Table 7.2.6-3: Composition of Pigment for Zinc Dust-Zinc
Oxide Mixed Primer

♦ 7-4 ♦
copy 249
7.2.7 Aluminum Paint Pigment Fifty-nine and five tenth
(59.5) percent min.
7.2.7.1 Description
Vehicle Forty and five tenths (40.5)
1 Aluminum paint shall be composed of aluminum percent max.
paste and aluminum vehicle and shall conform to the Non-volatile material in Fifty two (52) percent min
requirements specified in AASHTO M 69, Type 1. The vehicle
paste and vehicle shall be delivered to the project Phthalic anhydride Fourteen and nine tenths
unmixed and in separate containers. (14.9) percent min.
Water Five tenths percent max.
7.2.7.2 Proportions
Table 7.2.9-1: Composition of Maroon Field Coat Paint
1 The mixed paint shall be prepared for use on the
ii. Pigment: The extracted pigment shall conform
project by combining the aluminum paste and aluminum
to the following by weight:
vehicle in the proportions of twenty-four hundredths (0.24)
kilogram paste per liter of vehicle. Basic lead silico- Sixty-six and five-tenths (66.5)
chromate percent minimum
7.2.7.3 Mixing
Siliceous red iron oxide Thirty-three (33) percent max.
1 The paste and vehicle shall be thoroughly mixed Table 7.2.9-2: Composition of Pigment for Maroon Field
before use. The quantity of paint mixed shall not be Coat Paint
greater than will be used within twenty-four (24) hours
after mixing. 7.2.9.3 Weight per Liter

1 Maroon field coat paint shall weigh not less than one
7.2.8 Tinted Aluminum Paint
and sixty-seven hundredths (1.67) kilograms per liter.
7.2.8.1 Description
7.2.9.4 Coarse Particles
1 Tinted aluminum paint shall consist of a mixture
1 Coarse particles and skins retained on a forty-five
containing aluminum paint that conforms to the
thousandths (0.0450) millimeter (No. 325) sieve shall not
requirements of Clause 7.2.7 and Prussian Blue Paste or
exceed one (1) percent by weight based on pigment.
Chrome Green paste, conforming to the requirements
specified in ASTM D 212 or D261. 7.2.9.5 Consistency

7.2.8.2 Proportions 1 Consistency shall be not less than seventy (70) or


more than eighty-two (82) Krebs Units (K.U.).
1 Tinted aluminum paint shall be prepared by mixing
one (1) liter of aluminum paint meeting this specification 7.2.9.6 Condition in Container
with between thirty (30) and forty-five (45) grams of either
Prussian Blue paste or Chrome Green paste in oil or 1 The paint shall be thoroughly ground and mixed; it
varnish. shall not be settled, caked, or thickened to such a degree
that it cannot be redispersed easily with a paddle to a
7.2.9 Basic Lead Silico-Chromate Maroon uniform and homogenous state.
Field Coat 7.2.9.7 Skinning
7.2.9.1 Description 1 Skinning shall be entirely absent from a sample that
1 This paint is intended for use as a field coat over a has been stored forty-eight (48) hours in a dark place in a
properly primed surface. Hiding power shall be sufficient three-quarters-filled tightly-closed container.
to obtain a complete hiding when applied at normal
7.2.9.8 Dilution Stability
spreading rates and shall have a good contrast with the
primer coat. This paint shall consist only of basic lead 1 The paint shall remain stable and uniform after
silico-chromate, siliceous red iron oxide, raw linseed oil, reduction with mineral spirits in the proportions of eight
linseed-soya oil modified alkyd resin, thinners, dryers, and (8) parts by volume of paint to one (1) part by volume of
from five tenths (0.5) to seven-tenths (0.7) percent mineral spirits.
suspending agent, based on the pigment, to insure soft
settlement of the pigment during storage. The alkyd resin 7.2.9.9 Brushing Properties
shall conform to FSS TT-R-266, Type III and the thinner to 1 The paint, after through mixing, shall have
FSS TT-T-291, Grade 2. satisfactory brushing and leveling properties, and show no
running or sagging tendencies, when brushed on a
7.2.9.2 Composition
vertical steel surface.
1 Maroon field coat paint shall conform to the
following composition by weight:
i. Paint:

♦ 7-5 ♦
copy 249
7.2.9.10 Spraying Properties 7.2.10.4 Coarse Particles

1 The paint, when thinned, shall spray satisfactorily, 1 Coarse particles and skins retained on a forty-five
show no tendency to orange-peel, sag, creep or run, and thousandths (0.045) millimeter (No. 325) sieve shall not
shall show satisfactory spraying properties in all other exceed one (1) percent by weight based on pigment.
respects. The mineral spirits used as a reducer shall
conform to FSS TT-T-291 Grade 1, and shall be tested and 7.2.10.5 Consistency
approved prior to use. 1 Consistency shall be not less than seventy-two (72)
nor more than eighty (80) Krebs Units (K.U.).
7.2.9.11 Drying Time

1 The paint shall be touch-dry in no more than four (4) 7.2.10.6 Color
hours and dry-through in not more than twenty-four (24) 1 Dark green finish coat paint color shall be as
hours. approved by the Engineer. The Contractor shall submit to
the Engineer, for approval, color chips of the paint
7.2.10 Basic Lead Silico-Chromate Dark proposed for the work.
Green Finish Coat
7.2.10.7 Condition in Container
7.2.10.1 Description
1 The paint shall be thoroughly ground and mixed; it
1 This paint is intended for use as a finish coat over a shall not be settled, caked, or thickened to such a degree
properly primed and field-coated surface. Dark green that it cannot be redispersed easily with a paddle to a
finish coat paint shall consist only of basic lead silico- uniform and homogenous state.
chromate, chromium oxide green, phthalocyanine green
and/or phthalocyanine blue, lampblack, soya oil modified 7.2.10.8 Skinning
alkyd resin, raw linseed oil, thinners, dryers and from six-
1 Skinning shall be entirely absent from a sample that
tenths (0.6) to seven-tenths (0.7) percent suspended agent,
has been stored forty-eight (48) hours in a dark place in a
based on the pigment, to insure soft settlement of the
three-quarters-filled tightly-closed container.
pigment during storage. The alkyd resin solution shall
conform to FSS TT-R-266, Type I, and the thinner shall 7.2.10.9 Dilution Stability
conform to FSS TTT-291, Grade 2.
1 The paint shall remain stable and uniform after
7.2.10.2 Composition reduction with mineral spirits in the proportions of eight
(8) parts by volume of paint to one (1) part by volume of
1 Dark green finish coat paint shall conform to the
mineral spirits.
following by weight:
i. Paint: 7.2.10.10 Brushing Properties
Pigment Forty-one (41) percent min. 1 The paint, after through mixing, shall have
Vehicle Fifty-nine (59) percent max. satisfactory brushing and leveling properties, and show no
Non-volatile material in Fifty-three (53) percent min. running or sagging tendencies when brushed on a vertical
vehicle steel surface.
Phthalic anhydride Twenty & five-tenths (20.5)
based on vehicle solids percent max. 7.2.10.11 Spraying Properties
Water Five-tenths (0.5) percent max. 1 The paint, when thinned, shall spray satisfactorily,
Table 7.2.10-1: Composition of Dark Green Finish Coat show no tendency to orange-peel, sag, creep or run, and
Paint shall show satisfactory spraying properties in all other
respects. The mineral spirits used as a reducer shall
ii. Pigment.: The extracted pigment shall conform conform to FSS TT-T-291 Grade 1, and shall be tested and
to the following by weight: approved prior to use.
Basic lead silico- Eighty-six (86) percent min.
7.2.10.12 Drying Time
chromate
Chromium oxide green Nine (9) percent min. 1 The paint shall be touch-dry in not less than twenty
Table 7.2.10-2: Composition of Pigment for Dark Green (20) minutes or more than four (4) hours and dry-through
in not more than twenty-four (24) hours.
Finish Coat Paint

7.2.10.3 Weight per Liter

1 Dark green finish coat paint shall weigh not less than
one and thirty-three hundredths (1.33) kilograms per liter.

♦ 7-6 ♦
copy 249
7.2.11 Zinc Dust Paint Method Standard No. 141, for the material to be analyzed
or tested.
7.2.11.1 Description
4 No paint or paint materials shall be used which have
1 Zinc dust paint shall be a ready-mixed, high zinc dust not been approved by the Engineer. Paint or paint
content paint suitable for repairing damaged spelter materials for which samples and/or certificates of
coating on galvanized steel. guarantee of the same paint or paint materials have
previously been submitted to the Engineer and approved
7.2.11.2 Requirements thereby may be used if the additional shipments are
1 The paint shall comply with all the requirements of accompanied by the manufacturer's guarantee that the
U.S. Military Specification MIL-P-21035 (Ships), Paint, High product is equal in all respects to the previously approved
Zinc Dust Content, Galvanizing Repair, dated August 23, materials.
1957, with the following additions and exceptions: 5 The required color, and, if applicable, texture of the
i. The paint shall be supplied ready-mixed. coating shall be as specified on the Drawings or as
Material supplied in two (2) compartment cans directed by the Engineer and the coating shall be selected
to be mixed on the job will not be accepted. by the Engineer on the basis of trial panels prepared by
ii. Pigment content expressed as a weight percent the Contractor.
of total nonvolatile content may be a minimum 6 The Contractor shall supply manufacturer's samples,
of ninety-two (92) instead of the ninety-four specifications and chemical compositions of paint(s)
(94) minimum required by the Military meeting the requirements of these specifications and
Specification. which correspond to the color and texture specified. A
iii. Percent metallic zinc by analysis in the pigment minimum of five (5) samples per pay item shall be
may be minimum of ninety-four (94) instead of provided, of which not more than three (3) shall be from
the ninety-seven and five-tenths (97.5) any one manufacturer. The Engineer shall select a
minimum required by the Military Specification. maximum of three (3) coatings per pay item for which trial
panels shall be constructed by the Contractor as specified
7.2.12 Gloss Enamel herein.

7.2.12.1 Description 7.2.14 Portland Cement Paint


1 Gloss paint shall be a high-grade synthetic-type high 7.2.14.1 Description
gloss enamel for use on exterior and interior metal. It shall
be highly weather-resistant and characterized by easy 1 Cement paint shall conform to the US Federal
brushing, good color and gloss retention, good drying and Specification TTP- 0035(1) - Paint, Cementitious, Powder,
flexibility, with freedom from after-tack. White and Colors and is intended for use on properly
prepared concrete surfaces; this paint shall not be applied
7.2.12.2 Requirements over old paint or other types of surfaces. Portland cement
paint is suitable for use on interior and exterior concrete
1 The paint shall conform to Federal Specification TT-
surfaces, below and above grade, under normal service
E-489, Class A, Air Drying. This enamel may be thinned
and climatic conditions. Where more stringent
with Thinner; Federal Specification TT-T-291E, Type II,
requirements are anticipated, preference shall be given to
Grade A (Mineral Spirits).
solvent based polymer paints, described below under
Clause 7.2.15.
7.2.13 Sampling and Testing
1 All materials shall be accompanied by the 7.2.14.2 Composition
manufacturer's certificate of guarantee. The certificate 1 Portland cement paint shall be a water-based
shall give the quantity of paint in the shipment and shall pigmented cement wash coating, having properties
identify the paint by order number, project location and similar to the concrete surface itself. Portland cement
destination. Materials not accompanied by a certificate of paint shall be supplied as dry powder to be mixed with
guarantee shall be sampled in the field and samples water prior to using. After addition of water, thorough
submitted to an approved independent laboratory for mixing shall follow to obtain a creamy consistency to
testing. facilitate a uniform application, and paint shall thereafter
2 The Engineer will approve materials on the basis of be used within the time limits specified by the
the certificates of guarantee and/or laboratory tests, but manufacturer.
reserves the right to resample and have retested any
materials used during the progress of the work. Should 7.2.14.3 Colors
the paint not conform to the specifications, it shall be 1 Portland cement paint colors shall be as shown
rejected, previous approval notwithstanding. on the Drawings or as directed by the Engineer.
3 Materials and paints shall be analyzed or tested by
the methods specified in the ASTM, AASHTO, or FSS Test

♦ 7-7 ♦
copy 249
7.2.15 Polymer Latex Paint 7.2.16.2 Composition

7.2.15.1 Description 1 Single-component polymer paints shall be


pigmented solvent-based solutions of resins, such as
1 Polymer latex paint shall conform to the US Federal chlorinated rubber, styrene butadiene and vinyl chloride-
Specifications TT-P-0033 - Paint, Latex Base, Exterior, or vinyl acetate copolymers. Such ‘rubber-based’ paints shall
TT-P-96D - Paint Latex Base, for Exterior Surfaces and is be of a formulation so as to possess a considerable degree
intended for use on properly prepared concrete surfaces, of flexibility and extensibility when applied to the specified
not less than 3 weeks old, with normal, high or varying thickness, in order to maintain a continuous coating over
moisture content, on masonry surfaces, and on other minor cracks which may exist or develop in the concrete
types of old paints. Application over other types of paint is substrate.
subject to the manufacturer's written instructions and
2 The paint formulation shall have a potential to resist
limitations, and to the approval of the Engineer. Polymer
soiling and be cleanable with commercial detergents.
latex paint is suitable for use on interior and exterior
Thermoplastic formulations and formulations soluble in
concrete and masonry surfaces, below and above grade,
organic solvents shall not be approved for use on surfaces
under normal service and climatic conditions. Where more
that need to be cleaned with steam cleaning or strong
stringent requirements are anticipated, preference shall be
detergents and aggressive solvents.
given to solvent-based polymer paints, described under
Clause 7.2.16. 3 Two-component polymer paints: One of the
components shall be a pigmented solution of a
7.2.15.2 Composition compounded polymer, with or without solvent, such as
epoxy, urethane or polyester; the other component shall
1 Polymer latex paint shall be a water-based dispersion
contain a reactive chemical, the hardener. After mixing the
of pigments and polymeric film-forming materials. Film
two components to the manufacturer's instructions,
formers may be butadiene-styrene, chlorinated rubber,
application to the substrate and curing, the painted
vinyl acetate or butyrate, or acrylic resins. Exterior grade
surface shall be a hard, strong, chemical- and moisture-
shall be used in all cases, with a flat or semi-gloss mildew-
resistant film with excellent adhesion to the protected,
resistant finish, as shown on the Drawings or as directed.
properly prepared surface. The finished surface shall be
7.2.15.3 Colors easy to clean, resistant to fungus and strong detergents,
and inert to heat and steam in order to be used as anti-
1 Polymer latex paint colors shall be as shown on the graffiti paint, when required. Two-component epoxy
Drawings or as directed by the Engineer. formulations shall not be used on surfaces that are
exposed to sunlight. In such cases, two-component
7.2.16 Polymer Paint exterior grade urethane formulations (aliphatic grades)
shall be approved for use.
7.2.16.1 Description
7.2.16.3 Colors
1 Polymer paint shall conform to the requirements of
the US Federal Specifications TT-P-1411A-Paint, 1 Polymer paint colors shall be as shown on the
Copolymer Resin, Cementitious; TT-P-95CPaint, Rubber for Drawings or as directed by the Engineer.
Swimming Pools and Other Concrete and Masonry
Surfaces; TT-P-97DPaint, Styrene-Butadiene Solvent Type, 7.2.17 Acrylic Emulsion Paint
White; TT-P-1181A(1)-Paint, Styrene-Acrylate Solvent
Types, Tints and Deep Tones; TT-C-545 D(1) - Coating : 1 Acrylic emulsion paint shall comply in all respects
Polyester-Epoxy (Two Component), High-Build, Gloss and with the following Master Painters Institute Detailed
Semigloss, White and Tints; TT-C-1659A – Coatings : Performance Standards:
Epoxy Emulsion, Two-Component Gloss and Semigloss; i. MPI #10 for flat paint,
TT-C-535B(1) - Coating, Epoxy, Two Component; TT-C- ii. MPI #11 for semi-gloss, or
542D - Coating, Polyurethane, Oil Free, Moisture Curing; or
MIL-C-22750C - Coating, Epoxy-Polyamide. Polymer paint iii. MPI #119 for gloss.
is intended for use on properly prepared interior or
2 The paint may be tinted by using ‘universal’ or ‘all
exterior concrete and masonry surfaces, with low or
purpose’ concentrates.
relatively stable moisture content, below and above grade,
under normal or adverse service conditions and normal,
humid or wet climatic conditions; and on certain types of 7.3 Construction Requirements
old paints, subject to the manufacturer's written
instructions/ limitations, to the approval of the Engineer, 7.3.1 General
and as herein specified. 1 Painting of steel and concrete structures and other
metal, concrete and masonry shall include proper cleaning
and preparation of the substrate surfaces; application,
protection, drying, and curing of the paint coatings;

♦ 7-8 ♦
copy 249
protection of pedestrian, vehicular or other traffic upon or between ten and thirty-two degrees
underneath or near the work; and protection of other Celsius (10o- 32o C).
completed work against disfigurement by spatters, - Solvent-based paints shall be applied
splashes and smirches, of paint or of paint material. when the temperatures of the surfaces to
be painted and of the surrounding air are
7.3.2 Application between seven and thirty-five degrees
Celsius (7o-35o C).
7.3.2.1 General
- Paint shall not be applied in fog, mist,
1 The paint shall be applied in accordance with the rain or when the relative humidity
following procedures: exceeds eighty-five percent (85%).
i. Paint may be applied with brushes or by Painting operations shall not start when
spraying, except for aluminum paint, which rain is anticipated to strike the painted
shall be applied by spraying. All spraying surface within twenty-four (24) hours of
equipment shall be subject to the Engineer's application.
approval. If work done by spraying is not
7.3.3 Concrete Surfaces
satisfactory to the Engineer, hand brushing will
be required, 7.3.3.1 Preparation
ii. Paint shall be applied only when the air 1. Concrete surfaces to receive paint shall be prepared
temperature is at or above five degrees Celsius to ensure complete adhesion of the coating material.
(5oC.). It shall not be applied upon damp
surfaces or when the air is misty or otherwise i. Preparation of concrete and masonry surfaces
unsatisfactory for the work. shall comply with the requirements of this
iii. Paint shall not be applied in the open on metal Specification. Due to the continuous
or other surfaces that are too hot and which development of new products, absolute
will cause the paint to blister and produce a adherence to the paint manufacturer's
porous paint film. Material painted under cover recommendations and written instructions is
shall remain under cover until dry and when critical for the proper performance of the work.
weather conditions permit its exposure in the The Engineer may, at any time, require the
open. presence of the manufacturer's technical
representative on site, for as long as the
iv. When brushes are used, the paint shall be
Engineer deems necessary, to ensure proper
spread to produce a uniform even coating in
execution of the work.
close contact with the substrate, or with
previously applied paint. To secure a ii. The concrete and masonry surfaces shall not
maximum thickness of paint film upon rivet be contaminated by chemicals, such as form
heads, the edges of plates, angles, or other release agents or curing compounds that can
rolled shapes, these areas shall be ‘striped’ in prevent good adhesion between the paint
advance of the general painting, and shortly material and the substrate. The surfaces shall
afterwards shall be given a second or ‘wash’ be newly exposed, free of loose, weak and
coat when the general coat is applied. The unsound materials. laitance, efflorescence,
paint shall be well-worked into all joints and inadequately cured concrete, and condensed
open spaces. surface moisture are conditions objectionable
to paint application. The dryness or dampness
v. Power spraying equipment shall apply the
of the surface shall be compatible with the
paint in a fine, even spray, without the addition
paint type to be used as per the manufacturer's
of thinner. Paint, when applied with spray
instructions.
equipment shall be immediately followed by
brushing, when necessary, to secure uniform iii. Preparation of repaired concrete surfaces may
coverage and to eliminate wrinkling, blistering include chemical cleaning and mechanical
and air holes. cleaning. Acid etching shall be employed only
at the recommendation of the paint
vi. On all surfaces which are inaccessible for paint
manufacturer and upon approval by the
brushes, the paint shall be applied with
Engineer, and shall be performed by crews
sheepskin daubers specially constructed for the
experienced in its use.
purpose.
iv. Chemical cleaning shall be employed prior to
vii. Unless otherwise permitted or required by the
mechanical cleaning or acid etching when
manufacturer's printed instructions, the
removal of surface contaminants such as oil,
following shall apply:
grease and dirt is required. Solutions of caustic
- Water-based paints shall be applied
soda or tri-sodium phosphate may be used, as
when the temperatures of the surfaces to
well as proprietary detergents specially
be painted and of the surrounding air are
formulated for use on concrete. Solvents shall

♦ 7-9 ♦
copy 249
not be used for this purpose. The approved applicable only to solvent-based paints. Water-
detergent shall be applied with vigorous based paints may be required to be applied on
scrubbing, followed by flushing with water to damp surfaces to promote adhesion; however,
remove all traces of both the detergent and the free-standing water on the surface to be
contaminant. painted shall not be acceptable.
v. Mechanical cleaning may include scarification Moisture content is considered excessive on a
and grinding when small areas are involved. tested surface, if moisture collects at the bond
For larger areas, wet sandblasting and, plane between the concrete and the paint
preferably, high-pressure water jetting shall be material before the paint has cured. Tape a one
employed. Conventional dry sandblasting shall and two tenths by one and two tenths (1.20 x
not be permitted. 1.20) meters clear, polyethylene sheet to the
vi. Acid to be used for etching, when approved, tested surface and determine the time required
shall be a 10/90 maximum dilution ratio of for moisture to collect on the underside of the
commercial grade phosphoric acid in water sheet. Compare the time required for moisture
solution, applied at a rate of one (1.0) liter per to collect, (1), with the time required for the
square meter of surface to be prepared. paint to cure, (2), as supplied by the paint
Hydrochloric acid solutions shall not be manufacturer. If (1) is greater than (2), the
permitted for this purpose. For small areas, surface is adequately dry.
plastic sprinkling cans may be used for xi. Strength of Surface, when laitance is present:
dispensing the acid solution. Larger areas shall Unless otherwise specified by the paint
be sprayed with low pressure automatic spray manufacturer, this test is applicable to water-
equipment. Upon subsidy of the foaming based paints and to two-component, solvent-
action of the acid (3 to 5 minutes) the entire based paints.
treated surface shall be thoroughly flushed
Where loose powdery material is readily observed
with water, while scrubbed with stiff bristle or
following the scraping of the surface with a putty knife,
wire brushes to remove the salts formed on the
excessive laitance is present that could adversely affect
surface and to dislodge loose particles. The
the adhesion of the paint. The paint manufacturer should
adequacy of the flushing operation shall be
be consulted as to the intensity of mechanical cleaning
checked at several points within the cleaned
required.
area by placing litmus or pH paper on the wet
surface to determine whether the acid has been 7.3.3.2 Painting
completely neutralized. Further flushing may
be necessary to ensure an absolutely 1 Portland cement paint shall be applied to damp
neutralized surface. surfaces without any free surface water. After application,
vii. When forced drying of wet surfaces is the paint shall be cured by keeping it moist for forty-eight
necessary, as approved by the Engineer, heat (48) to seventy-two (72) hours. For two-coat applications,
may be applied or dry, oil-free air may be the second coat shall be applied within twenty-four (24)
blown over the surface. hours from completion of the first coat. Dry film thickness
shall be not less than three hundred eighty (380) microns
viii. Concrete and masonry surfaces to be painted
per coat. One coat shall be applied, unless otherwise
shall be tested for surface quality prior to
shown on the plans.
application of paint. Tests shall include
cleanliness, dryness and strength qualities of 2 Polymer latex paint shall be applied to damp
the substrate as specified below. concrete surfaces, so water will not be absorbed from the
ix. Cleanliness of Surface. paint before it has a chance to properly cure, unless
- Dusty condition: wipe the surface with a otherwise specified by the manufacturer. When latex paint
dark cloth; if a white powder is on the does not properly adhere to chalky surfaces, the prior
cloth, the surface is unsatisfactory. application of a low viscosity penetrant primer will be
- Oily condition: Sprinkle water on the required, per the manufacturer's instructions. Any
dried suspect surface; if the water embedded or adjacent steel work shall be coated with a
spreads out immediately instead of rust inhibitive primer as specified in this Section, before
standing as droplets, the surface is not application of any water-based paint. Dry film thickness
contaminated by oils. shall be not less than sixty-five (65) microns per coat. Two
- Acid condition: Use pH paper to coats shall be applied, excluding sealer or primer, unless
determine the acidity at the concrete otherwise shown on the plans.
surface; a pH value below four (4) is 3 Polymer paint shall be applied to dry surfaces, unless
unacceptable. otherwise specifically permitted by the paint manufacturer
in writing. Two-component paints require the mixture of
x. Dryness of Surface: Unless otherwise specified
the two components supplied as a kit, in the correct
by the paint manufacturer, this test is
proportions as per the manufacturer's instructions. To

♦ 7-10 ♦
copy 249
ensure a complete chemical reaction between the as the Engineer may require until a coating satisfactory to
hardener and the polymer, power stirrers shall be used for the Engineer is obtained.
thorough mixing. The paint shall be used after expiration 8 Acrylic emulsion paint for concrete shall be applied
of the required induction period and within the expected in not less than two applications to produce a uniform
pot-life period of the mixed system, as specified by the appearance. The paint shall be applied only when the
manufacturer. Should thinning or viscosity reduction be ambient temperature is 10 degree C or above. Painting
necessary, only thinners recommended by the shall not be permitted when it can be anticipated that the
manufacturer shall be used. Thinners shall be added only ambient temperature will drop below 10 degree C during
after the two components are blended. the application and drying of the paint.
Dry film thickness shall be not less than forty (40) microns
per coat. A minimum of two coats shall be applied, 7.3.4 Structural Steel Requirements
excluding primer, unless otherwise shown on the plans or
1 Unless otherwise specified on the Drawings, or in the
recommended by the paint manufacturer for the intended
Special Specification, all new structural steel shall be
purpose.
given three (3) coats of paint. The first coat shall be
4 All finished coatings shall be uniform in color and applied immediately after shop fabrication is complete.
texture, free from runs, drops, ridges, waves, laps, etc., The second and third coats shall be applied after all
and shall match the color and texture of the approved erection is complete, except that immediately following
sample panel to the Engineer's satisfaction. the field riveting or bolting of members, the heads of field
5 Should any coating, in the Engineer's opinion, be rivets, bolts, and all abrasions of the shop coat due to
non-uniform in color and/or texture or should there be handling at the shop, shipment, erection, etc., and all field
runs, drops, ridges, waves, laps, etc., in the coating, the erection marks shall be thoroughly covered with one (1)
Contractor shall propose remedial works for the coat of primer as specified for shop coat and permitted to
Engineer's approval. Should the Contractor's proposals be become thoroughly dry before the first field coat is applied.
unacceptable, or should the remedial works result in an 2 All metal coated with impure or unauthorized paint
unsatisfactory finish, the Engineer shall require the shall be thoroughly cleaned and repainted to the
Contractor to: satisfaction of the Engineer. Prime coats of paint shall be
- Recoat the complete area affected; or at least four hundredths (0.04) millimeter thick when dry
- Remove, to the extent possible, the coating and each intermediate and finish coat of paint shall be at
from the affected area and reapply the coating. least three hundredths (0.03) millimeter thick when dry.
The Engineer shall notify the Contractor which option he No portion of the paint films shall be less than these
requires and, in the case of a re-coating being specified thicknesses. The film thickness shall be not so
unsatisfactory, the Engineer shall require the Contractor to great that either the appearance or service life of the paint
remove, to the extent possible, the re-coating and the will be detrimentally affected.
original coating and re-apply a new coating. All re-coating
works and removal and re-application of coatings shall be 7.3.5 Shop Coat (Prime)
at the Contractor's expense.
7.3.5.1 Shop Cleaning
6 If the color of the coating departs from that of the
1 All surfaces of metal to be painted shall be
approved trial panel color to a degree which, in the
thoroughly cleaned of rust, loose mill scale, dirt, oil or
opinion of the Engineer, is unacceptable, the Contractor
grease, and all other foreign substances. The removal of
shall stop application and shall demonstrate to the
rust, scale and dirt shall generally be done by the use of
Engineer's satisfaction that the coating formulation and/or
metal brushes, scrapers, chisels, hammers, sandblasting,
application method can be suitably adjusted to produce a
or other effective means. Oil and grease may be removed
color matching that of the trial panel. If considered
by the use of gasoline or benzene. Bristle or wood fiber
necessary by the Engineer, the Contractor shall produce
brushes shall be used for removing loose dirt. Unless
additional trial panel(s) at his own expense to demonstrate
cleaning is to be done by sandblasting, all weld areas,
that a color match can be obtained.
before cleaning is done, shall be neutralized with a proper
7 If, in the opinion of the Engineer, a satisfactory color chemical, after which they shall be thoroughly rinsed with
match cannot be obtained, the Engineer, at his option, water. All cleaning shall conform to the requirements of
may require the Contractor to remove, to the extent AASHTO Standard Specifications for Highway Bridges.
possible, the unacceptable coating applied to the
permanent works and/or to apply an alternative coating. 7.3.5.2 Shop Painting
Such an alternative coating will be selected by the
1 Shop painting shall be done in accordance with the
Engineer on the basis of the previously prepared trial
following procedures:
panels, except that where in the opinion of the Engineer
i. When all fabrication work is complete and has
such trial panels are unacceptable, the Contractor shall
been accepted, all surfaces not painted before
supply additional manufacturer's samples and trial panels
assembling shall be given an approved shop
coat of paint. Steel members shall not be

♦ 7-11 ♦
copy 249
loaded for shipment until thoroughly dry. No of paint used in the shop, and allowed to become dry
painting shall be done after loading. before the first field coat is applied.
ii. Structural steel which is to be welded shall not 2 When the paint for ‘touching up’ coat has become
be painted before welding is complete. If it is to dry, the first and second field coats may be applied. In no
be welded only in the fabricating shop and case shall a succeeding coat be applied until the previous
subsequently erected by bolting, it shall receive coat has dried through the full thickness of the paint film.
one (1) coat of paint after shop welding is
3 All small cracks and cavities which have not become
finished. Steel which is to be field welded shall
sealed by the first coat shall be filled with a paste mixture
be given one (1) coat of boiled linseed oil or
of red lead and linseed oil before the second coat is
other approved protected coating after shop
applied.
welding and shop fabrication are completed.
4 Contractor shall, take precautions to prevent dust
iii. Surfaces of metal to be in contact when
and dirt from coming in contact with freshly painted
assembled shall not be painted. Surfaces of
surfaces or with surfaces before the paint is applied.
field connections gusset plates of trusses and
areas of girders or plates where floor beam or
stringer connections are to come in contact
7.3.7 Bridge Railings and Guardrails
shall not be painted. 7.3.7.1 Bridge Railings
iv. With the exception of pins and pinholes in
bearings, unless otherwise shown in the 1 Metal bridge railing shall be painted as specified in
Drawings, all surfaces except those described the Special Specification.
in Subparagraph iii, whether machine finished 2 Aluminum hand rails shall not be painted except for
or otherwise, shall be given the regular coat of the portion of posts to be inserted in concrete which shall
shop paint, and those parts inaccessible after first be painted with one (1) coat of zinc dust-zinc oxide
erection shall be given two (2) coats of field primer (Clause 7.2.6) to a point two (2) centimeters above
paint. Pins and pinholes shall be coated, as the concrete line. The aluminum hand rail after erection
soon as practicable after being accepted, with a shall be wiped with a rag saturated with lacquer thinner to
hot mixture of white lead and tallow before remove stains.
removal from the shop.
7.3.7.2 Guardrail
v. The composition used for coating machine
finished surfaces shall be mixed in the 1 Guardrail posts and beams shall be painted if
following proportions: specified in the Special Specifications. Under no
- One and eight-tenths (1.8) kilograms of circumstances shall any paint other than zinc dust-zinc
pure tallow oxide primer (Clause 7.2.6) be used for the shop or prime
- Nine-tenths (0.9) kilograms of pure white coat on galvanized guardrails.
lead
- Ninety-five hundredths (0.95) liters of 7.3.8 Painting Existing Structures
pure linseed oil
1 The painting of existing structures shall be done in
vi. Erection marks for field identification of accordance with the following procedures:
members shall be painted upon previously i. Preparation shall include the removal of the
painted surfaces. rust, scale, dead paint, dirt, grease or other
foreign matter from all parts of existing bridge
7.3.6 Field Coat structures.

7.3.6.1 Field Cleaning ii. The requirements and methods e for cleaning
and painting shall be the same as specified for
1 When the erection work is complete, including all shop and field painting herein.
riveting, bolting, welding, straightening of bent metal, etc., iii. All metal surfaces not in close contact with
all adhering rust, scale, dirt, grease, or other foreign other metal surfaces or truss members,
matter shall be removed as specified under Paragraph concrete, stone masonry, or other structure
7.3.5.1, ‘Shop Cleaning’. materials shall be considered as exposed to
deterioration by rusting and shall be
7.3.6.2 Field Painting
thoroughly cleaned and given the number of
1 As soon as the field cleaning is done to the coats of designated paint stated in the Special
satisfaction of the Engineer, the heads of field rivets and Specification.
bolts, welded surfaces, and any surface from which the iv. Unless otherwise stated, the metal shall be
shop paint has worn off, or has otherwise become given at least two (2) coats of paint.
defective, and all shipping and erection marks, shall be v. When repainting with the same type of paint as
touched up by covering with one (1) coat of the same type that on an existing surface, the surface shall be
thoroughly washed with commercial

♦ 7-12 ♦
copy 249
detergents, or, where approved, with solvents, 3 Trial panels made by the Contractor to determine
to remove any dirt, chalk and grime suitability of surface preparation methods and of the
accumulation, along with dead paint. finished coating color and/or texture shall not be
vi. When repainting with a different type of paint measured for payment.
from that on an existing surface, the Contractor
shall ensure that the paint is compatible with 7.5 Basis of Payments
the existing paint.
vii. Loose paint, curled edges and blistered paint 1 Painting or repainting in whole or in part of existing
shall be removed before repainting. Light wet structure(s) shall rank for payment of the amount of
sandblasting, water-jet blasting, machine completed and accepted work as measured, at the unit
sanding, or paint strippers may be utilized. rate(s) bid per square meter as specified in the Bill of
viii. Filling of cracks and holes in the concrete shall Quantities.
be done in the same manner as for new 2 Unit rates shall be full compensation for furnishing
concrete. If the old paint has become partially all labor, transport, materials, equipment, tools, tackle,
removed, but that remaining is in good scaffolding and any other equipment, and for performing
condition, the bare areas shall be painted first, all surface preparation and cleaning and all other items
followed by two coats over all. If the old paint necessary for the proper completion of the work.
is blistered or peeling due to efflorescence, the
cause shall be investigated and the Engineer 7.6 Items in the Bill of Quantities
will instruct corrective measures or, the type of
paint may be changed.
1 Payment will be made under one or more of the
following:
7.3.9 Painting Steel Piling and Steel Pile
i Painting of existing concrete structure
Shells
(state type) (sq.m.)
1 Unless otherwise provided in the Drawings or ii Painting of existing steel structure
Special Specification, steel bearing piles, steel sheet piles, (state type) (sq.m.)
and steel pile shells need not be painted if they are to be iii Painting of existing railing
encased in concrete or other solid waterproof materials (state type) (lin.m.)
from six hundred (600) millimeters below the water line or
ground line to the tops of the piles.
2 When steel bearing piles, and steel pile shells are not
to be encased, or when provided in the plans, they shall
be painted in accordance with the requirements stated
hereinbefore, except that three (3) coats of shop paint
shall be applied from the tops of the piles to an elevation
three (3) meters below the water line or finished ground
line before driving, and then two (2) field coats of paint as
specified for structural steel shall be applied to each steel
bearing pile, or steel pile shell which extends above the
low water line or finished ground line after driving.

7.3.10 Painting Steel Pile Enclosures and


Tubular Steel Piers
1 The exterior surfaces of steel pile enclosures and
tubular steel piers shall be painted in accordance with the
requirements of Clause 7.3.8, Painting Existing Structures.

7.4 Method of Measurement

1 No separate measurement is made for painting of


new structures and miscellaneous metalwork, and piling
which work is considered subsidiary to other sections. The
rates stated in the Bill of Quantities for the work of the
relevant section shall be deemed to include for painting.
2 Painting of existing structures shall be measured in
square meters of the actual area painted..

♦ 7-13 ♦
copy 249
copy 249
Ref. Title Page No. Ref. Title Page No.
8.1 Pipe Culverts 8-1 8.2.2.4 uPVC Pipe 8-4
8.2.2.5 Polyethylene (PE) Gravity Pipe 8-4
8.1.1 General 8-1
8.2.2.6 GRP Pipes 8-4
8.1.1.1 Description 8-1
8.2.2.7 Vitrified Clay Pipes 8-5
8.1.1.2 Submittals 8-1
8.2.2.8 Joints for Concrete Beds and Pipe
8.1.1.3 Installation and Checking 8-1
Surrounds 8-5
8.1.2 Materials 8-1
8.2.2.9 Bitumen Emulsion 8-5
8.1.2.1 Delivery, Storage and Handling 8-1
8.2.2.10 Pumping Plant 8-5
8.1.2.2 Precast Reinforced Concrete Pipe 8-1
8.2.3 Construction Requirements 8-5
8.1.2.3 Unreinforced Concrete Pipe 8-1
8.2.3.1 Excavation, Bedding and Backfilling 8-5
8.1.2.4 Reinforced Concrete Arch Culvert 8-1
8.2.3.2 Pipe Laying 8-5
8.1.2.5 Reinforced Elliptical Culvert 8-1
8.2.3.3 Jointing of Pipes 8-5
8.1.2.6 Corrugated Steel Circular Pipe
8.2.3.4 Line and Gradient 8-6
and Pipe Arches 8-1
8.2.3.5 Floatation 8-6
8.1.2.7 Bituminous Coated Corrugated Steel
8.2.3.6 Pipe Built Into Structures 8-6
Circular Pipe and Pipe Arches 8-2
8.2.3.7 Cleaning and Inspecting of Storm
8.1.2.8 Polymer Coated Steel Circular Pipe
Sewer Pipes 8-6
and Pipe Arches 8-2
8.2.3.8 Field Testing: Generally 8-6
8.1.2.9 Concrete and Steel 8-2
8.2.3.9 Air Testing of Pipelines 8-6
8.1.3 Construction Requirements 8-2
8.2.3.10 Hydrostatic Testing of Pressure
8.1.3.1 Excavation, Bedding and Backfilling 8-2
Pipelines 8-7
8.1.3.2 Pipe Laying 8-2
8.2.3.11 Infiltration Test for Gravity Pipes 8-7
8.1.3.3 Precast Concrete Pipe and Pipe Arches 8-2
8.2.3.12 Deflection Tests for GRP Pipes 8-7
8.1.3.4 Corrugated Metal Pipe and Pipe Arches 8-2
8.2.3.13 Hydraulic Individual Joint Test for Pipes
8.1.3.5 Cast-in-Situ Concrete Pipe
Exceeding 1000 mm 8-7
and Pipe Arches 8-3
8.2.4 Method of Measurement 8-7
8.1.4 Method of Measurement 8-3
8.2.5 Basis of Payment 8-7
8.1.5 Basis of Payment 8-3
8.2.6 Items in the Bill of Quantities 8-8
8.1.6 Items in the Bill of Quantities 8-3
8.3 Manholes, Inlets and
8.2 Storm Sewers 8-3
Chambers 8-8
8.2.1 General 8-3
8.3.1 Description 8-8
8.2.1.1 Description 8-3
8.3.2 Materials 8-8
8.2.1.2 Installation and Checking 8-3
8.3.3 Construction Requirements 8-9
8.2.1.3 Submittals 8-3
8.3.3.1 Manholes 8-9
8.2.2 Materials 8-4
8.3.3.2 Chambers for Grated Inlets, Curb Inlets
8.2.2.1 Delivery and Storage 8-4
and Ditch Inlets and Outlets 8-9
8.2.2.2 Concrete and Steel 8-4
8.3.3.3 Ironwork 8-9
8.2.2.3 Concrete Pipes 8-4

copy 249
Ref. Title Page No.
8.3.3.4 Cleaning 8-9
8.3.4 Method of Measurement 8-9
8.3.5 Basis of Payment 8-10
8.3.6 Items in the Bill of Quantities 8-10

8.4 Drainage of Structures 8-10

8.4.1 Description 8-10


8.4.2 Materials 8-10
8.4.2.1 Gully and Channel Gratings
and Frames 8-10
8.4.2.2 Pipes 8-10
8.4.2.3 Drainage Backfilling 8-10
8.4.3 Construction Requirements 8-10
8.4.4 Method of Measurement 8-12
8.4.5 Basis of Payment 8-12
8.4.6 Items in the Bill of Quantities 8-12

copy 249
8.1 Pipe Culverts 8.1.2.2 Precast Reinforced Concrete Pipe

1 Reinforced concrete pipe shall meet the requirements


8.1.1 General of Volume 2 of the Highway Design Standards and shall
8.1.1.1 Description comply with BS 5911-1, BS EN 1916 Class H, ASTM C76-02
Class IV or DIN V 1201 and DIN EN 1916. Cement used in
1 This Sub-section describes requirements for manufacture shall be ordinary Portland cement to BS EN
furnishing all materials, constructing and installing 197-1.
concrete and steel pipe culverts including excavation,
2 Joints shall be gasket type with flexible spigots and
bedding and backfilling and all work described in this
sockets. The shape of the joint shall be designed to
Section of the Specification and as shown on the
prevent any movement of the gasket during assembly and
Drawings.
to produce full water-tightness. Rubber gasket shall be to
8.1.1.2 Submittals ISO 4633 or BS EN 681-2.
3 Manufactured pipe shall, if required by the Engineer,
1 Coordination Drawings: Submit drawings showing
be tested, prior to delivery to site, for structural strength,
culverts and major system components. Indicate interface
crushing strength and absorption. The manufacturer's
and spatial relationship between culverts, system
specification and certificate shall be submitted for prior
components, adjacent utilities, and proximate structures.
approval before pipes are delivered to the site.
2 Shop Drawings: Submit shop drawings of culverts
4 Pipes that fail to meet the strength requirements may,
including plan layout and locations, types, sizes, capacities,
with the approval of the Engineer, be incorporated in the
and flow characteristics in accordance with the
work provided the following requirements are met.
requirements of this Specification Sub-section 1.11.
i. The strength does not fall below 80% of that
3 As-Built Drawings: At project close-out, submit specified.
record drawings of installed culverts, in accordance with ii. The pipes are clearly marked and stored
requirements of this Specification, Sub-section 1.11. separately from pipes which fully comply with
4 Certificate of Compliance: Submit certificates of strength requirements.
compliance required by the Client Authority and as iii. The pipes are bedded in Class 15 concrete.
directed by the Engineer.
5 If under-strength pipes are installed with pipes fully
8.1.1.3 Installation and Checking complying with the strength requirements, the whole run
shall be classified as under-strength for record purposes.
1 The work shall be supervised by qualified
representatives of the Contractor and full facilities and 8.1.2.3 Unreinforced Concrete Pipe
assistance shall be provided by the Contractor to enable
1 Unreinforced concrete pipe shall meet the
the Engineer to inspect or check the work at any time.
requirements of the Highway Design Standards and shall
Such inspection or checking shall in no way relieve the
comply with BS 5911-1, AASHTO M 86M / M 86, DIN V
Contractor from any of his obligations.
1201 and DIN EN 1916 or ASTM C14M and with Paragraph
2 The Contractor shall be responsible for making minor 8.1.2.2 items 2 to 5. Class shall be as designated on
adjustments to the location of work as necessary to suit drawings. Cement used in manufacture shall be ordinary
site constraints and road alignment and profile subject to Portland cement to BS EN 197-1.
the approval of the Engineer.
8.1.2.4 Reinforced Concrete Arch Culvert
8.1.2 Materials
1 Reinforced concrete arch culvert shall comply with
8.1.2.1 Delivery, Storage and Handling AASHTO M 206M / M 206 or ASTM C506-02. Unless
otherwise specified Class A-IV shall be used for spans of
1 Deliver piping with factory-applied end caps. 1300mm or less, and Class A-III for larger spans.
Maintain end caps through shipping, storage, and
handling to prevent pipe-end damage and to prevent 8.1.2.5 Reinforced Elliptical Culvert
entrance of dirt, debris, and moisture.
1 Reinforced concrete elliptical culverts shall be to
2 Protect stored piping from moisture and dirt. Elevate AASHTO M 207M / M 207 or ASTM C507M-02. Their Class
above grade. Do not exceed structural capacity of floor shall be as designated on drawings.
when storing inside.
3 Protect flanges, fittings, and specialties from 8.1.2.6 Corrugated Steel Circular Pipe and Pipe Arches
moisture and dirt. 1 Corrugated steel culvert pipe shall comply with the
4 Manufacturer’s recommendations on handling, requirements of AASHTO M36 and be zinc coated.
repairing, laying, jointing, anchoring, cutting and other 2 A certificate of guarantee from an approved pipe
works for pipes and fittings are to be strictly followed. fabricator shall be submitted by the Contractor for each
shipment of pipe delivered to the Site. The Certificate

♦ 8-1 ♦
copy 249
shall show the quantities of material and state that the barrel of pipe to bear evenly on solid ground for its full
listed materials conform to the specified requirements. length.

3 The Engineer may test any material for compliance 7 Pipe on granular bedding: The Contractor shall scoop
with the Specification at any time and reject any material out locally at sockets/couplings to enable the pipe to rest
which does not meet the requirements even though it has uniformly on the barrel and adjust to the exact line and
received prior approval based on a Certificate of level. After testing, the Contractor shall lay and compact
Guarantee. further granular material in 150 mm layers or as approved
to levels shown on the Drawings.
8.1.2.7 Bituminous Coated Corrugated Steel Circular
8.1.3.3 Precast Concrete Pipe and Pipe Arches
Pipe and Pipe Arches
1 Pipes shall be laid with hub, bell or groove ends
1 Bituminous coated corrugated steel circular pipe and
upstream.
pipe arches shall comply with AASHTO M 190, and with
Paragraph 8.1.2.6. 2 Where lift holes have been used, they shall be filled
with an approved cement-sand mortar to provide a
8.1.2.8 Polymer Coated Steel Circular Pipe and Pipe watertight section. Mortar shall be finished flush on the
Arches inside of the pipe.
3 Pipe joints shall be sealed with flexible watertight
1 Polymer coated metal pipe and pipe arches shall
elastomeric or rubber gaskets, approved bituminous
comply with AASHTO M 246 and with Paragraph 8.1.2.6.
sealers or plastic sealants. Bituminous or plastic sealants
8.1.2.9 Concrete and Steel shall be applied at the time pipe is being laid. Sealants
shall be installed in accordance with the sealant
1 Concrete, reinforcing steel and reinforced concrete manufacturer's instructions so that the joint is completely
shall conform to the requirements of Sub-sections 5.1, 5.2 filled.
and 5.3 respectively. Structural steel and other metalwork
4 Multiple pipe culverts, unless otherwise shown on
shall conform to Sub-section 6.2.
the Drawings, shall be laid with one-half diameter of pipe
or a minimum of 300mm, whichever is greater, between
8.1.3 Construction Requirements
the pipes.
8.1.3.1 Excavation, Bedding and Backfilling
8.1.3.4 Corrugated Metal Pipe and Pipe Arches
1 All excavation and backfill shall conform to the
1 Metal pipe shall be laid with outside laps of
requirements of Sub-Sections 2.3 and 2.8.
circumferential joints pointing upstream and with
8.1.3.2 Pipe Laying longitudinal laps along the sides. If pipe sections are
jointed on the Site, the ends shall be butted as closely as
1 Pipes shall not be placed until the foundation has corrugations will permit and shall be joined with a firmly
been approved by the Engineer. Pipes shall be laid bolted coupling band of the same material as the pipe.
accurately to line and level and shall have a uniform Camber shall be built into the pipe structure to
bearing at each joint and along the entire length of pipe. compensate for settlement from fill loads,
Pipe laying shall begin at the downstream end and
2 Multiple culverts, unless shown otherwise on the
progress upstream.
Drawings, shall be laid with one-half span of pipe or a
2 Manufactured pipe shall be handled and assembled minimum of 300mm whichever is the greater, between
in accordance, with the manufacturer's instructions. When pipes.
pipe laying is not in progress, the Contractor shall close
3 The Contractor shall examine material to ensure
open ends of pipes with properly fitted temporary wooden
internal coating or lining and outer coating or sheathing
plugs or standard caps as directed
are undamaged. If damaged, the Contractor shall make
3 The Contractor shall use ropes, wire slings, band good or dispose of as directed. Damage to bituminous or
slings, spreader beams etc. for lowering pipes as epoxy resin coatings may be repaired on site by
recommended by manufacturer for each type of pipe and application of a repair material of a brand and type
as approved. approved by the Engineer. Pipes having any localized
4 All material shall be carefully examined for damage bends in excess of 5% of the nominal pipe diameter or
and tested in accordance with manufacturer's instructions dents in excess of 13mm depth will be rejected. Pipes
before laying, to the satisfaction of Engineer. rejected because of these defects may be used if
5 The Contractor shall remove dirt and other materials satisfactorily repaired and approved by the Engineer.
before lowering the pipe into the trench and verify the
pipe inside is clear from construction debris before
making joints.
6 Pipe on solid ground: The Contractor shall cut holes
in the bottom of trench to allow proper jointing and for

♦ 8-2 ♦
copy 249
8.1.3.5 Cast-in-Situ Concrete Pipe and Pipe Arches 8.1.6 Items in the Bill of Quantities
1 Cast-in-situ pipes shall be constructed in accordance i. Unreinforced precast concrete
with the Drawings, or in a manner proposed by the pipe culvert (diameter) (lin.m.)
Contractor and approved by the Engineer. ii. Reinforced precast concrete
pipe culvert (diameter) (lin.m.)
2 When the Contractor elects to construct the pipe in a
iii. Reinforced precast concrete arch
trench with no external vertical forms, 40mm of additional
culvert (size) (lin.m.)
concrete cover to the reinforcement steel shall be
iv. Reinforced precast concrete
provided.
elliptical culvert (size) (lin.m.)
3 Longitudinal construction joints will only be v. Corrugated steel pipe culvert
permitted as shown on the Drawings. Transverse (diameter) (coating) (lin.m.)
construction joints will be permitted provided prior vi. Corrugated steel pipe arch
approval is obtained from the Engineer. culvert (size) (coating) (lin.m.)
4 Forms for cast-in-situ pipe shall be approved prior to vii. Cast in-situ concrete pipe and
their use. Inside pipe forms shall be suitably unyielding pipe arches (size, type) (lin.m)
during placement of concrete. Interior arch forms may be
removed after 72 hours if approved by the Engineer. The 8.2 Storm Sewers
Contractor shall take precautions when removing forms to
protect the culvert from damage. Backfilling shall not
8.2.1 General
commence until tests indicate the concrete has attained
strength of 50% of the requirement for its Class. 8.2.1.1 Description

8.1.4 Method of Measurement 1 This Sub-section describes requirements for


constructing pipes for the removal of surface water from
1 Pipe culverts shall be measured by the linear meter roads, including connections to rainwater inlets and
of culvert laid or constructed as per the contract Drawings. discharge to suitable outfall. The work shall include
Culverts of each type, class and size shall be measured furnishing all materials, installing pipes, excavation,
separately. For pipe culverts without headwalls, bedding and backfilling.
measurement shall be taken from end to end along the
centerline of the pipe. For pipes connected to structures, 8.2.1.2 Installation and Checking
measurement shall be taken between the inside faces of
1 Installation and checking shall comply to the
parapet or wall along the centerline of the pipe.
requirements of Paragraph 8.1.1.3.
2 The measured length of corrugated metal pipe shall
2 Collect site information by performing site survey,
include the length of bends (elbows) installed.
researching public utility records, and verifying existing
3 Headwalls, wing walls, aprons and cut-off walls that utility locations.
are part of a pipe culvert installation are measured
separately in accordance with Sub-Section 5.9. 8.2.1.3 Submittals

4 Trench excavation, bedding and backfilling for 1 Coordination Drawings: Submit drawings showing
culvert pipe runs is measured separately under Sub- pipes and major system components. Indicate interface
section 2.8, Clause 2.8.4 and spatial relationship between pipes, system
5 No separate measurement or payment will be made components, adjacent utilities, and proximate structures.
for connection to drainage structures or to existing pipes. 2 Shop Drawings: Submit shop drawings of storm
Nor for additional reinforcing steel, cover and protection sewers systems including plan layout and locations, types,
to in-situ concrete pipe culverts and pipe arches, all of sizes, and capacities of pipes, manholes and stormwater
which are considered subsidiary work. inlets in accordance with the requirements of the
Specification Sub-section 1.12.
8.1.5 Basis of Payment 3 As-Built Drawings: At project close-out, submit
1 The quantity of completed and accepted work. record drawings showing the installed pipes and related
measured as provided for above, will be paid for at the components with sufficient details to allow for locating the
unit rate per linear meter in the Bill of Quantities for 'the pipes for future maintenance. The As-Built drawings shall
various types, classes and sizes of pipe and arch culverts, be in accordance with requirements of the Specification,
which rate shall be full compensation for the cost of Sub-section 1.12.
supply, transport, handling, installation of pipe, joints, 4 Certificate of Compliance: Submit certificates of
materials, labor, equipment, tools and other items compliance as required by the Client Authority and as
necessary for proper completion of the work. directed by the Engineer.

♦ 8-3 ♦
copy 249
8.2.2 Materials 3 Materials used shall have a standard PE code
designation 2406 and a minimum hydrostatic design basis
8.2.2.1 Delivery and Storage of 1250 psi (8.6MPa) for water at 73.4°F (23°C) according to
1 Delivery, storage and handling shall comply to the AWWA C906 Table 1.
requirements of Paragraph 8.1.2.1.
8.2.2.6 GRP Pipes
2 During storage plastic pipes shall be protected from
sunlight and supported to prevent sagging and bending. 1 Pipes and fittings shall conform to BS EN1796 & BS
EN14364 or American Water Works Association AWWA
8.2.2.2 Concrete and Steel C950.

1 Concrete, reinforcing steel and reinforced concrete 2 Pipe and fittings shall include a corrosion resistant
shall conform to the requirements of Sub-sections 5.1, 5.2, liner, a structural wall and a resin rich exterior surface.
and 5.3 respectively. Structural steel and other metalwork 3 The liner shall have a nominal thickness of 1.0 mm.
shall conform to Sub-section 6.2. The liner surface shall be reinforced with C glass. The
remainder of the liner thickness shall be reinforced with an
8.2.2.3 Concrete Pipes acid resistant chopped E glass strand or mat.
1 Reinforced and unreinforced concrete pipes shall 4 The pipe structural wall shall consist of glass
comply with the requirements of Paragraphs 8.1.2.2 and reinforcement, and fine silica sand, all impregnated with
8.1.2.3, respectively. resin. The fine silica sand shall be added to the structural
layer to achieve the design thickness for the required
8.2.2.4 uPVC Pipe stiffness specified such that the overall hoop flexural
1 Pipes shall conform to DIN 8061 / 8062 Class 6 kg/cm2 modulus (E) for pipe is not less than 24 GN/m2. Silica sand
or Class 10 as indicated on the Drawings or the Bill of and filler content shall not exceed 50%.
Quantities. Use concrete encasement if cover is less than 1 5 Pipes shall be provided with a resin rich outer layer
meter or greater than 5 meters. reinforced with one layer of C glass veil. The exterior layer
2 Fittings shall be to DIN 8061 / 8062 fabricated from shall have a minimum thickness of 0.2 mm. The layer shall
pipe. be resin rich and reinforced with one layer of C glass.

3 Joints shall be to DIN 8061 / 8062, socket spigot with 6 The resin used for the corrosion resistant liner of the
rubber sealing rings to BS EN 681-2. pipe and fittings shall be high grade polyester resin
(isophthalic or better) type. For the structural wall and
4 Under-drain pipes shall be perforated plastic pipe
exterior layer of the pipe a high grade isophthalic
conforming to DIN 8061 Class 10 kg/cm2 or equivalent.
polyester resin shall be used. No dark pigments shall be
Perforations may be circular holes or slots. Different filter
used in the pipe or fittings.
requirements shall apply to each type of perforation.
7 Pipes shall be designed for a life of not less than 50
5 Circular perforations shall be between 5 mm and 10
years. Contractor shall submit calculations for initial and
mm in diameter arranged symmetrically in a minimum of
long term deflection with truck loads, buckling, vacuum,
4 rows parallel to the axis of the pipe. All rows shall be in
pressure class, and strain in accordance with Appendix A
the lower half of the pipe but no row shall be closer than
of AWWA C-950 or equivalent. The maximum calculated
36 degrees to the invert. Perforations in each row shall be
long term deflection should not exceed 3%. Copies of the
at a maximum distance of 100 mm centre to centre.
design calculations shall be submitted to the Engineer for
6 Slotted perforations shall be between 1.5 mm and 3 approval..
mm in width, and between 25 mm and 40 mm in length i. Stiffness: Minimum 5,000 N/m2. Suitability of
measured on the inside of the pipe. Perforations shall be stiffness shall be verified by Contractor for the
in 2 rows parallel to the axis of the pipes on each side of various trench and pipe laying conditions and
the invert. Each row shall be approximately 45 degrees as recommended by the manufacturer.
from the invert. Perforations shall be spaced between 20 Pressure Class; 6 kg/cm2 minimum or as shown
and 30 times the average slot width along each row. on Drawings.
7 Pipes and fittings shall be protected from the direct ii. Longitudinal Strength: Conform to BS EN1796
rays of the sun at all times by means of reflective cover & BS EN14364 or ASTM D3262 table 7.
sheets. iii. Hoop strength shall be according to ASTM
D3517 Table 8.
8.2.2.5 Polyethylene (PE) Gravity Pipe iv. Strain corrosion resistance tests shall be
1 Polyethylene (PE) pipes and fittings shall conform carried out as per ASTM D 3681 or to BS
with ASTM D3035-01, ASTM F894. and installation shall be EN1796 & BS EN14364 strain corrosion value at
in accordance to ASTM D2321-00 and manufacturer’s 50 years to equal or exceed 0.7%.
recommendations. v. Markings shall be to BS EN1796 & BS EN14364
Clause 11.
2 Jointing system should be in accordance with ASTM
vi. Joints shall be GRP double socket couplings
F894.
with rubber rings to ISO 4633 or BS EN 681-2

♦ 8-4 ♦
copy 249
. The allowable angular deflection shall set and boned into the correct level on the trench
conform to the requirements of BS EN1796 & formation bottom and will lay the pipe properly centered
BS EN14364. and socketed.
3 The Contractor shall insert two hardwood folding
8.2.2.7 Vitrified Clay Pipes
wedges (of a width equal to the width of the concrete
1 Vitrified clay pipes and fittings shall be to BS EN 295 block) between the body of the pipe and block, and drive
and shall be marked accordingly. them together until the pipe is brought to the exact level
2 Unless otherwise indicated, pipes and fittings shall required. The Contractor shall leave blocks and wedges
be Extra Strength and shall comply with absorption tests undisturbed while pipes are being jointed and the
made in accordance with BS 65. concrete bed and haunch or surround are being placed.
The Contractor shall ensure blocks and wedges are of
3 Pipes shall be supplied with approved flexible and
sufficient size and strength to prevent settlement of pipes.
telescopic rubber ring joints which shall be capable of
The Contractor shall leave sufficient space to enable joints
withstanding the specified tests pressures applied both
to be made, tested and inspected.
internally and externally.
4 The Contractor shall lay pipes on an even formation
4 Junctions on clay pipe sewers shall be of similar
true to grade and line, with sockets facing up the gradient.
material and suitable for use with flexibly jointed pipes.
5 Tolerances shall be 6 mm in level and 25 mm in line
5 Before any length of pipe is laid, it shall be inspected
between manholes or access points unless otherwise
and stood or slung vertically at the side of the trench
specified. Where pipe is to be constructed in straight lines
and ’rung’ with a wooden mallet. Any damaged or cracked
between manholes the length will not be accepted if a
pipe shall be rejected.
light at each manhole cannot be seen from adjacent
6 Where shown on the Drawings, pipes for use in the manholes.
construction of drains shall be British Standard Surface
Water pipes glazed or unglazed manufactured in 8.2.3.3 Jointing of Pipes
accordance with the requirements of BS 65, with Type 2
1 Unless otherwise specified, the manufacturer's
sockets or plain ended supplied with sleeve couplings.
instructions shall be followed regarding placement of
7 Perforated pipes shall be Type 1 socketed and sleeve bedding and backfilling, cleanliness of joint surfaces,
coupled pipes. lubricant used, correct location of components, provision
8 Field drain pipes shall comply with the requirements of correct gaps between end of spigot and back of socket
of BS EN 295-5 and BS 1196. for flexible joints etc.
2 Concrete pipes shall have watertight joints sealed
8.2.2.8 Joints for Concrete Beds and Pipe Surrounds
with approved rubber rings or flexible gaskets. Joints
1 Flexible joints in concrete beds and surrounds to shall have a gap formed between the end of the spigot
pipes shall be formed with compressible fibrous board, or and the base of the bell of not less than 6mm and not
similar approved material, 20mm thick. greater than 20mm. The gap shall then be filled with a
cement mortar composed of 1 part Portland cement and 3
8.2.2.9 Bitumen Emulsion parts fine aggregate, mixed with sufficient water to form a
1 Bitumen emulsion shall be to BS 434 and shall workable paste. As each section of pipe is laid, the bell or
contain not less than 53% of prime bitumen. hub of the preceding pipe shall be wetted and cleaned and
the bottom portion filled with mortar. After the pipe is
8.2.2.10 Pumping Plant placed, the remaining top part of the gap shall be filled.

1 Pumping plant is as specified in Section 17. 3 The inside of the joint shall be finished smooth and
wiped clean. The mortar on the outside shall, after its
initial set, be protected from the sun. Plastic joint
8.2.3 Construction Requirements
compound may be used in lieu of Portland cement mortar,
8.2.3.1 Excavation, Bedding and Backfilling in which case it shall be prepared in accordance with the
manufacturer’s recommendations.
1 All excavation and backfill shall conform to the
4 Synthetic or rubber joint rings shall be stored until
requirements of Sub-Sections 2.3 and 2.8.
needed in a cool place away from direct sunlight.
8.2.3.2 Pipe Laying 5 Properly fitted temporary wooden stoppers shall be
used to close the ends of uncompleted pipe lines. The
1 Pipe laying shall comply with the requirements of
stoppers shall only be removed when pipes are being laid
Paragraph 8.1.3.2.
and jointed.
2 For pipe on a concrete bed or surround, the
6 The Contractor shall not deflect flexible joints beyond
Contractor shall provide rectangular blocks of concrete
maximum permissible angles given by manufacturer
Class 25, made in approved moulds at least 14 days before
and/or relevant Standards.
use, and approved hardwood folding wedges. The
Contractor shall provide two concrete blocks for each pipe,

♦ 8-5 ♦
copy 249
7 The Contractor shall strictly comply with special Contractor shall provide a suitable personnel trolley for
instructions issued by manufacturers of proprietary joints this purpose.
when laying and jointing. 3 Pipelines less than 700 mm diameter and larger pipes
8 The Contractor shall joint differing pipe and fitting which cannot be inspected from the inside shall have a
material with adaptors as recommended by the pipe mandrel formed from a cylinder, of diameter 25mm
manufacturer. smaller than the pipe diameter and of length not less than
the internal diameter of the sewer, passed through.
8.2.3.4 Line and Gradient
4 On completion the drains and sewer pipes shall be
1 In open excavation: The Contractor shall provide and flushed from end to end with water and left clean and free
maintain sight rails and boning rods properly painted to from obstructions and debris.
ensure correct alignment of pipe runs. Sight rails shall be
positioned either vertically above the lines of pipes or 8.2.3.8 Field Testing: Generally
immediately adjacent thereto. At no time shall there be 1 All test equipment and related items shall be
less than three sight rails in position on each length of provided on site before the test. i.e. pressure gauges,
pipeline under construction to any one gradient. instruments, water etc...
2 Where pipes are laid in headings, the Contractor shall 2 The Contractor shall carry out tests in the presence of
provide and maintain marks to establish line and level of the Engineer's Representative.
pipeline. Marks shall be fixed in each working shaft and
3 Fittings and joints shall be permanently anchored
two further marks established in each length of heading.
before testing and all joints shall be exposed for checking.
8.2.3.5 Floatation 4 Sections of pipeline under test shall not exceed 500m
in length for any one test.
1 Prevention: Whenever water is excluded from interior
of pipe, the Contractor shall place sufficient backfill above 5 Test plugs at the ends of each section shall be
pipe to prevent floatation. secured by struts.

2 The Contractor shall remove: any pipe that has 6 The Contractor shall apply pressure by manually
floated, correct the bedding and relay. operated test pump or, in the case of large diameter mains,
by power driven test pump, if approved.
8.2.3.6 Pipe Built Into Structures 7 The Contractor shall examine exposed joints and
1 The Contractor shall thoroughly clean outside repair visible leaks.
surface of pipes to be built-in immediately before 8 Should a test fail, the Contractor shall locate leak and
installation. Remove protective coating to metal pipes, replace or make good defective pipe or replace and make
and roughen clay and concrete pipes as directed. Plastic good faulty joint and retest main.
pipes shall be painted with appropriate solvent cement 9 The Contractor shall keep test records in an approved
and sprinkled with dry coarse sand whilst wet. The form and hand original copy to the Engineer immediately
Contractor shall cut away sheathing from sections to be after completion of test.
built-in and after installation restore protection up to
10 The Contractor shall carry out hydrostatic test while
external face of structure with approved bituminous
pipeline is partially backfilled.
material.
2 Install two flexible joints or flexible patented joints 8.2.3.9 Air Testing of Pipelines
adjacent to structures. The Contractor shall place first
1 As soon as practicable after a length of pipe has been
joint not more than one pipe diameter from face of
completed it shall be subjected to an air test to BS EN
structure and second not more than the following
1610. The length shall be plugged and sealed and air
distances away from first:
pumped into the pipe by approved method (ie. hand
i. Pipelines not exceeding 450 mm: 2 pipe
pump) until a pressure 100 mm head of water is indicated
diameters.
on a U-tube connected to the system
ii. Pipelines over 450 mm and not exceeding 1000
mm: 1.2 m. 2 The Contractor shall allow 5 minutes for stabilization
iii. Pipelines over 1000 mm: 1.8 m. of air temperature and adjust pressure to 100 mm. The
section will not be considered satisfactory if the air
8.2.3.7 Cleaning and Inspecting of Storm Sewer Pipes pressure fails from 100mm to 75mm head of water in 5
minutes or less.
1 After backfilling and completion of connections to
manholes, etc, but before the trench surfaces are 3 Failure to pass the air test is not conclusive and if no
permanently reinstated, the interior of the sewers shall be leakage can be traced by external application of soapy
cleaned out and ready for inspection by the Engineer. water to all sealing areas then a hydrostatic test shall be
carried out before final rejection.
2 Pipelines of 700 mm or more diameter will, where
practicable, be inspected from the inside and the

♦ 8-6 ♦
copy 249
8.2.3.10 Hydrostatic Testing of Pressure Pipelines 2 Pipes not passing the deflection tests at Stage 2 or
Stage 3 will be removed and replaced.
1 The pipeline shall be filled slowly with water from the
lowest point. After filling with water, absorbent pipes shall 8.2.3.13 Hydraulic Individual Joint Test for Pipes
be allowed to stand for at least 24 hours before testing to Exceeding 1000 mm
allow for complete absorption.
1 The Contractor shall carry out procedures to BS 5886,
2 Entrapped air shall be bled and pressurizing shall
Type 2 testing after backfilling, or equivalent. The
then proceed until the specified test pressure is reached in
Contractor shall pressurize the joint to 2 bars and wait for
the lowest part of the pipeline section under test. Further
10 minutes then re-pressurize to 2 bars and again wait for
quantities of entrapped air shall be bled while the pressure
5 minutes. No pressure drop should be observed at the
is being raised.
end of the latter period. If a pressure drop is observed, the
3 Unless otherwise specified, the test pressure shall be Contractor shall remedy the failed joint to the Engineer’s
equal to 1.0 m head of water above pipe soffit at highest approval.
point and not greater than 6 m head of water at lowest
point of section under test but shall in no case exceed 75% 8.2.4 Method of Measurement
of the factory hydrostatic test pressure. If maximum head
is exceeded, the Contractor shall test section in stages. 1 Trench excavation, bedding and backfilling are
measured under Sub-section 2.8, Clause 2.8.4.
4 The test pressure shall be maintained for one hour by
pumping using a separate test pump. Pumping shall then 2 Pipes shall be measured in linear meters; each type,
be stopped for 2 hours, at the end of which time the line class and size is measured separately. Measurement shall
shall be re-pressurized to the original test pressure and the be as a straight line between the inside wall faces of
volume of water pumped into the line recorded. manhole, inlet, sump or gully connection. No allowance
will be made for cut ends and waste.
5 The pipeline shall be deemed to have failed the test if
visible leaks are detected (regardless of leakage being 3 No separate measurement will be made for jointing
within the allowable specified limit) or if the volume of materials, junctions and pipe fittings, nor for ancillary
water pumped to restore original test pressure after the work such as breaking into existing pipelines or chambers,
period when pumping was stopped exceeds 0.05 cleaning, protection and testing of pipelines, or any other
liter/linear meter/meter diameter/30 minutes. item necessary for the proper completion of the work, but
shall be considered subsidiary work the costs of which
8.2.3.11 Infiltration Test for Gravity Pipes shall be deemed to be included in the rates and prices for
pipes stated in the Bill of Quantities.
1 The Contractor shall carry out infiltration test after
total backfilling of length under test.
8.2.5 Basis of Payment
2 All inlets to the section under test shall be plugged
and the residual flow measured by an approved method. 1 The amount of completed and accepted work.
measured as provided for above, will be paid for at the
3 The following limits are not to be exceeded:
unit rates listed in the Bill of Quantities, which unit rates
i. Pipelines not exceeding 700 mm: 0.02
shall be full compensation for installation, fitting,
liters/hour/100 linear meters/mm diameter,
supplying materials, transport, labor, equipment, forms,
ii. Pipelines over 700 mm: 0.03 liters/hour/100
tools and other items necessary for the proper completion
linear meters/mm diameter.
of the work as specified in Section 1.
5 The section shall be deemed to have failed if
2 Excavation, bedding and backfilling shall be paid for
allowable infiltration of water is exceeded. The Contractor
as indicated in Sub-section 2.8, Clause 2.8.5.
shall locate source of excessive infiltration by approved
means i.e. traversing light and mirrors or inflated rubber 3 Rates for pipes shall include for the following:
plug etc, make good, and repeat tests until successful. i. Staking out, field surveying and preparation of
shop and coordination drawings.
8.2.3.12 Deflection Tests for GRP Pipes ii. Pipe fittings, specials and couplings.
1 The Contractor shall conduct deflection tests for GRP iii. Transportation to and hauling about the Site,
pipes (as % of overall pipe diameter) as required by the loading, unloading and lowering materials in
Engineer at three stages. Deflection shall be measured at the trench.
the spigot end at mid point and at socket end. iv. Lubricating agent used for assembling the pipe
i. Stage 1: at completion of primary backfill sections.
(deflection at this stage should be below 0.5%). v. Cutting, machining, chamfering, etc. of
ii. Stage 2: at final backfill (maximum allowable standard length pipes.
deflection 2.5%). vi. Assembling the pipes and couplings and
iii. Stage 3: six months after final backfill connecting to inlets, manholes and/or
(maximum allowable deflection 4.0%). structures as applicable.
vii. Testing as per the specification.
viii. Ancillary works and materials.

♦ 8-7 ♦
copy 249
ix. Flushing, cleaning, painting, lining and coating. 9 GRP ladders shall be obtained from an approved
experienced manufacturer, fabricated to an approved
8.2.6 Items in the Bill of Quantities pattern and purpose made to suit the depth of each
installation as shown on the Drawings. The ladders shall
i. Storm sewer (type) (diameter) (lin.m.)
be drilled for wall fixing at both ends and additional
intermediate fixing connections shall be provided at
8.3 Manholes, Inlets and Chambers centers not greater than 1.5 meters. Rungs shall be at 300
mm centers and at a distance of not less than 150 mm
8.3.1 Description from the wall.
i. The resins, glasses and synthetic fabrics used
1 This Sub-section specifies works related to manholes,
in the manufacture of the ladders shall be
grate inlets, chambers, grated channels, curb inlets, ditch
chosen to produce a chemically resistant
inlets and ditch outlets.
product with a resin-rich surface layer suitable
for use in aggressive atmospheres likely to the
8.3.2 Materials
encountered in sewers and sewage pumping
1 Concrete, reinforcing steel and reinforced concrete stations.
shall conform to the requirements of Sub-sections 5.1, 5.2 ii. Rungs of tubular construction shall be no less
and 5.3 respectively. Structural steel and other metalwork than 30 mm outer diameter and stringers shall
shall conform to Sub-section 6.2. be of a rectangular or channel section, no less
2 Plain (blinding) and reinforced concrete shall be than 70 mm x 25 mm in size. The upper face of
Class 15 and 25, respectively. Cement shall be ordinary non-tubular rungs shall be finished with a non-
Portland cement to BS EN 197. slip surface such as silica sand. All remaining
3 Concrete manholes shall comply with BS EN 1917 surfaces shall be free of sharp edges,
and BS 5911 Part 3. Thickness shall be as indicated on the protrusions etc.
Drawings. iii. Each rung shall be able to withstand a point
load of 5000 N.
4 Manholes and chambers covers, gratings and frames
shall comply with BS EN 124 or equivalent. Two sets of iv. When supported horizontally over a span of 1
lifting keys shall be supplied with each removable cover. m with the climbing face uppermost and with a
Covers and frames shall be non-rock, locking, solid top. load of 1000 N applied at the centre of the span
Grades shall be as follows: the ladder shall not deflect more than 15 mm at
the point of application of the load and shall
i. For roadways: heavy duty test load 40 tons.
show no permanent deflection after removal of
ii. For sidewalks, carriage drive and cycle tracks:
the load. Each ladder fixing shall be capable of
medium duty test load 25 tons.
withstanding shear and pull-out loads of 5000
iii. For footpaths and fields: light duty, test load 7
N.
tons.
v. All ladders shall comply with BS 5395: Part 3.
5 Manhole covers shall be of circular pattern unless
All fixings shall be stainless steel.
otherwise indicated on Drawings with a clear opening of
not less than 560 mm diameter. Frames shall be provided 10 Fixing bolts shall be steel, type suitable for particular
with openings for fixing bolts which ensure solid frame purpose and use and to approval. When used to fix
embedment into the concrete manhole neck. Covers and galvanized material, washers are to be galvanized and
frames shall be coated to BS 3416, Minimum thickness 250 fixing bolts and nuts cut to pre-plating limits and
microns. Manholes covers shall have the words electroplated with zinc to BS ENISO 2081.
“Stormwater Drainage" inserted, unless instructed 11 Steel castings shall be mild to medium strength
otherwise by the Concerned Authority. castings and shall conform to AASHTO M103M/M103.
6 Grated inlets and channel gratings and frames shall Unless otherwise shown on the Drawings or instructed by
comply with BS EN 124 or equivalent. Grated inlet grating the Engineer, castings shall be grade 65-35 fully annealed.
shall have a clear open area of not less than 600x600 mm Steel castings shall conform to the dimensions shown on
and shall be coated to BS 3416. Minimum thickness 250 the Drawings. Test bars shall be prepared and tested as
microns. The Contractor shall submit manufacturer's specified in AASHTO M103M/M103.
details of the proposed grated inlet grating and frame for 12 Mortar for masonry shall be mixed in the proportions
prior approval by the Engineer. 1:3 (cement::sand) by volume, or 1:4:4 (cement:lime: sand).
7 Bricks shall be to BS EN771-1. Net volume of clay The sand shall be well graded.
masonry units shall be determined according to BS EN 13 The Contractor shall submit to the Engineer
772:3. Water absorption of clay masonry shall be manufacturers' Certificates of Guarantee for steel, cast
determined according to BS EN 772:7. iron cast steel and wrought iron parts, stating that the
8 Steel ladders shall be mild steel to BS 4211, materials supplied meet the applicable AASHTO or ASTM
galvanized to BS EN ISO 1461 with 200 grams of zinc per specification and Standards. The submission of such test
square meter. certificates shall not relieve the Contractor of his

♦ 8-8 ♦
copy 249
obligations to carry out independent tests at an approved iv. Allowable leakage over 24 hours shall not to
laboratory, as directed by the Engineer, at his own exceed 1% of total volume of manhole,
expense. otherwise necessary repair and re-testing shall
be carried to achieve the required results.
8.3.3 Construction Requirements
8.3.3.2 Chambers for Grated Inlets, Curb Inlets and
1 All excavation and backfill shall conform to the Ditch Inlets and Outlets
requirements of Sub-Sections 2.3 and 2.7. -
1 Construction shall be in situ concrete, precast
2 Formwork for cast in place concrete chambers, and
concrete or blockwork as indicated on the Drawings.
the placing, curing, and protection of the concrete shall
conform to the requirements of Sub-section 5.3, Clause 2 Brick and blockwork shall be laid on a full bed of
5.3.3. mortar. Whole bricks and blocks shall be used except
where closers must be cut.
8.3.3.1 Manholes
3 Courses shall be stepped back and not raised above
1 Precast units shall be cast in steel watertight forms at the general wall level more than 900 mm. Courses shall
least 3 weeks before sections are used. Lowest unit shall be horizontal. Reinforcement in the masonry shall be fully
be bedded on in situ concrete base and bed and haunch in embedded in the mortar joint.
cement mortar. Joints of units shall be liberally coated 4 If pointing is required, the joint shall be raked out to a
with approved bituminous material of trowelling grade depth of 12mm after completion of the entire face.
prior to fixing. Joints shall be filled solid and neatly
5 Brick and blockwork shall be protected by
stroked off surplus compound. Work shall remain
impermeable sheeting or damp cloth for 3 days after
undisturbed for 7 days thereafter. Alternatively joints may
completion of laying.
be sealed with approved preformed jointing strip in
6 The nearest pipe line joint to any chamber or grated
accordance with manufacturer's instructions. The precast
inlet shall be not more than 500mm from the inner wall
concrete cover slab shall be bedded in cement mortar on
face and shall not be restricted by concrete or masonry
the top unit.
from the structure.
2 Channels in bottom of manhole shall be smooth,
semi-circular and sized equal to diameter of adjacent 8.3.3.3 Ironwork
sewers. For straight through manholes, channels of half
pipe sections shall be installed. Changes in direction of 1 Frames for covers and gratings shall be solidly
flow shall be made with smooth curves as large as bedded in mortar and fixed firmly using fixing bolts. They
manholes permit. Changes in size and grade of channels shall be positioned centrally over the opening and level
shall be gradual and even. and square with surrounding finishes. Covers shall be set
in position to prevent twisting.
3 Benching shall be formed with sulfate resisting
concrete Class 250/20 to rise vertically from top of 2 The upper surface of grated inlet gratings shall be flat.
channels to a height not less than soffit of outlet pipe, then Slots shall not be parallel to traffic flow unless the slots
it shall be sloped upwards 1 in 10 to walls. Floating shall are less than 150mm long or less than 20mm wide.
then be carried out within 3 hours with a coat of sulfate 8.3.3.4 Cleaning
resisting cement-sand mortar 1:2. Smooth finishing shall
then be accomplished with a steel trowel. 1 Manholes, grated inlets, grated channels, curb inlets,
4 Manholes and chambers shall be coated externally ditch inlets and ditch outlets shall be thoroughly cleaned
with three layers of asphaltic composition that shall be on completion, and shall be free from dirt and debris at
applied by brush in accordance with manufacturer's the time of final inspection.
instructions. Minimum thickness shall be 600 microns.
5 Internal faces of manholes and chambers shall be 8.3.4 Method of Measurement
coated with four coats of coal tar epoxy paint, 70% epoxy 1 Manholes and inlets shall be measured by the
and 30% coal tar. The coating shall be applied by brush in number of each structure constructed and installed
accordance with manufacturer's instructions. Minimum including the supply and installation of chambers, frames,
thickness shall be 1000 microns. grates, covers and ladders as applicable. Grated channels
6 Adjustment of level shall be accomplished with top shall be measured per linear meter.
courses of brickwork or concrete rings after completion of 2 No separate measurement or payment shall be made
surrounding levels. Final levels shall be even and accurate. for any other concrete works, excavation, shoring,
7 The Contractor shall test manholes as follows: sheeting or backfilling, or for breaking into existing pipes
i. Plug manhole inlets and outlets. or culverts in order to install new manholes, chambers,
ii. Fill manhole with water and allow it to stand inlets and the like. All such work prescribed in this Sub-
for at least 24 hours or such longer period to section shall not be measured for direct payment, but shall
allow for complete absorption. be considered as subsidiary work, the costs of which shall
iii. Re-top with water.

♦ 8-9 ♦
copy 249
be deemed to be included in the unit rates for manholes
etc stated in the Bill of Quantities.
3 No separate payment shall be made for blinding,
painting, equipment, forms, tools, furnishing and placing
materials, labor, transport, or any other item necessary for
the proper completion of the work. All such items Pipe Material Pipe Standard
prescribed in this Sub-section shall not be measured for Ductile Iron BS EN 545 [1]
direct payment, but shall be considered as subsidiary work,
BS EN 1452 [9] or to DIN 8061/8062,
the costs of which shall be deemed to be included in the uPVC
Series 4 and 5
unit rates for manholes etc stated in the Bill of Quantities.
Polyethylene ISO 4427, DIN 8074/8075 or AWWA
(PE) C906 Class 10
8.3.5 Basis of Payment
Table 8.4.2-1: Drainage Pipe Standards for Bridge Deck
1 The amount of completed and accepted work
measured as provided for above, will be paid for at the 2 Pipes for filter drains shall be to the standards listed
unit rates of 'Manholes', ‘Grated Inlets’, 'Curb Inlets’, in Table 8.4.2.2 or equivalent and as specified in Clause
‘Grated Channels’, 'Ditch Inlets' and 'Ditch Outlets' in the 8.2.2.
Bill of Quantities, which rates shall be full compensation
for excavation, installation, fitting, testing, backfilling, Pipe Material Pipe Standard
supplying materials, labor, transport, equipment, forms, DIN 8061 Class 10
uPVC
tools and other items necessary for the proper completion kg/cm2
of the work. ASTM D3035and ASTM
Polyethylene (PE)
F894
8.3.6 Items in the Bill of Quantities
Vitrified clay BS 65
i. Manholes (size and type) nr.
AASHTO M175M/M175
Concrete
ii. Grated Inlet (type) nr. or ASTM C444M
Table 8.4.2.2: Drainage Pipe Standards for Filter Drains
iii. Curb inlet (type) nr.

iv. Ditch inlet (type) nr. 8.4.2.3 Drainage Backfilling

v. Ditch outlet (type) nr. 1 Permeable backfilling to structures shall be crushed


rock or precast porous concrete blocks to BS 6073-2 laid in
vi. Grated Channel (width and depth) lin.m. stretcher bond with dry joints. The minimum thickness of
backfilling shall be 225mm.
8.4 Drainage of Structures 2 Granular backfill to structures shall be natural sand
and gravel or with a particle size distribution as given in
8.4.1 Description Table 8.4.2.3.
1 This Sub-section describes requirements for gully
AASHTO sieve size % passing (by mass)
and channel gratings and frames on bridge decks,
subways and underpasses with the associated pipework. It 75.0 mm 100
includes the supply and placing of permeable drainage 37.5 mm 85-100
backfilling to structures.
9.5 mm 45-100
8.4.2 Materials 4.75 mm 25-85

8.4.2.1 Gully and Channel Gratings and Frames Table 8.4.2.3: Granular Backfill to Structure

1 Gully and channel gratings and frames shall be 8.4.3 Construction Requirements
heavy duty and shall conform to the requirements of BS
1 Drainage pipes cast into the concrete structure shall
EN 124 or equivalent. Integral hoppers shall be of the
be firmly supported to prevent their displacement during
same grade and quality as the gully or channel grate and
the concreting operation. Pipes located within the cellular
frame. Molded uPVC or GRP shall be to the approval of the
sections of a bridge deck where access after completion of
Engineer who may require material and load testing.
the deck is limited, shall be installed, tested and approved
8.4.2.2 Pipes by the Engineer before the deck construction is allowed .to
proceed to the stage where access to the pipes will not be
1 Pipes used in bridge decks shall be to the possible
standards listed in Table 8.4.2.1 or equivalent
with a minimum internal diameter of 100mm.

♦ 8-10 ♦
copy 249
2 Pipe joints in bridge decks shall be flexible and
watertight Seals and gaskets shall be appropriate for the
pipe material- used.
3 Joints between bridge deck waterproofing and
drainage components shall be watertight and the sealants
shall be compatible with the waterproofing system.

♦ 8-11 ♦
copy 249
4 Granular drainage backfill shall be placed and
compacted in accordance with Sub-section 2.5, Paragraph
2.5.4.2.
5 Drainage pipes and connections in bridge decks shall
be tested for water tightness on completion in accordance
with Clause 8.2.3.
6 All excavation and backfill shall conform to the
requirements of Sub-Sections 2.3 – ‘Roadway Excavation’
and 2.7 – ‘Excavation and Backfilling for Structures.
7 PE pipes installation shall be in accordance to ASTM
D2321 and manufacturer’s recommendations.

8.4.4 Method of Measurement


1 Gully gratings and frames shall be measured by
number; each type shall be measured separately
2 Pipework shall be measured in linear meters,
measured as the actual length installed, including nominal
length of bends and fittings; each type and size shall be
measured separately.
3 Permeable backfilling shall be measured in cubic
meters of the volume placed in position.
4 Granular backfill shall be measured in cubic meters
of the volume placed in position.
5 No separate measurement shall be made for blinding,
painting, equipment, forms, tools, furnishing and placing
materials, labor, or any other item .necessary for the
proper completion of the work. All such items prescribed
in this Sub-section shall be considered as subsidiary work,
the costs of which shall be deemed to be included in the
rates and prices stated in the Bill of Quantities.

8.4.5 Basis of Payment


1 The amount of completed and accepted work
measured as provided for above, will be paid for at the
unit rate for the various items of 'Drainage for Structures'
in the Bill of Quantities, which rate shall be full
compensation for supplying, fabricating, connecting and
testing, and for labor, transport, materials, equipment,
tools, and other items necessary for the completion of the
work.

8.4.6 Items in the Bill of Quantities


i. Gully grate and frame (type) nr.

ii. Drainage pipe in structure

(type) (diameter) (location) lin.m.

iii. Permeable backfilling cu.m.

iv. Granular backfill cu.m.

♦ 8-12 ♦
copy 249
Ref. Title Page No. Ref. Title Page No.
9.1 Riprap 9-1 9.4.3.3 Pull Out Tests for Anchored Bolts 9-6
9.4.3.4 Pull Out Tests for Untensioned Bolts 9-7
9.1.1 Description 9-1
9.4.3.5 Rock Anchoring Procedures 9-7
9.1.2 Materials 9-1
9.1.3 Construction Requirements 9-1 9.4.3.6 Tensioning Tendons 9-7
9.4.3.7 Grouting for Rock Anchors 9-8
9.1.4 Method of Measurement 9-2
9.4.3.8 Testing of Rock Anchors 9-8
9.1.5 Basis of Payment 9-2
9.1.6 Items in the Bill of Quantities 9-2 9.4.3.9 Application of Sprayed Concrete
and Mortar 9-8
9.2 Gabions 9-2 9.4.3.10 Reinforcement Mesh 9-9
9.2.1 Description 9-2 9.4.3.11 Paint 9-9
9.2.2 Materials 9-2 9.4.3.12 Wire Netting 9-9
9.2.3 Construction Requirements 9-2 9.4.4 Method of Measurement 9-10
9.2.4 Method of Measurement 9-3 9.4.5 Basis of Payment 9-10
9.2.5 Basis of Payment 9-3 9.4.6 Items in the Bill of Quantities 9-10
9.2.6 Items in the Bill of Quantities 9-3 9.5 Rock Grouting 9-10
9.3 Slope Netting 9-5 9.5.1 Description 9-10
9.3.1 Description 9-3 9.5.2 Materials 9-10
9.3.2 Materials 9-3 9.5.3 Construction Requirements 9-10
9.3.3 Construction Requirements 9-3 9.5.4 Method of Measurement 9-11
9.3.4 Method of Measurement 9-3 9.5.5 Basis of Payment 9-12
9.3.5 Basis of Payment 9-3 9.5.6 Items in the Bill of Quantities 9-12
9.3.6 Items in the Bill of Quantities 9-4 9.6 Reinforced Concrete Slope
9.4 Rock Bolts, Anchors Protection 9-12
and Sprayed Concrete 9-4 9.6.1 Description 9-12
9.4.1 Description 9-4 9.6.2 Materials 9-12
9.4.2 Materials 9-4 9.6.2.1 Concrete 9-12
9.4.2.1 Cement Grout 9-4 9.6.2.2 Reinforcement 9-12
9.4.2.2 Rock Bolts Generally 9-4 9.6.3 Construction Requirements 9-12
9.4.2.3 Resin-Anchored Rock Bolts 9-4 9.6.4 Method of Measurement 9-12
9.4.2.4 Mechanically Anchored Rock Bolts 9-4 9.6.5 Basis of Payment 9-12
9.4.2.5 Drain Holes 9-4 9.6.6 Items in the Bill of Quantities 9-12
9.4.2.6 Rock Anchors 9-4 9.7 Sacked Concrete Revetment 9-12
9.4.2.7 Sprayed Concrete and Mortar 9-5
9.4.2.8 Wire Netting 9-5 9.7.1 Description 9-12
9.7.2 Materials 9-12
9.4.3 Construction Requirements 9-5
9.7.2.1 Sacks 9-12
9.4.3.1 General 9-5
9.4.3.2 Rock Bolting Procedures 9-5 9.7.2.2 Concrete 9-12

copy 249
Ref. Title Page No. Ref. Title Page No.
9.7.3 Construction Requirements 9-12 9.11.3.2 Stabilization with Bituminous
9.7.4 Method of Measurement 9-13 Materials 9-16
9.7.5 Basis of Payment 9-13 9.11.3.3 Stabilization with Vegetative
9.7.6 Items in the Bill of Quantities 9-13 Treatment 9-16
9.11.3.4 Blankets 9-16
9.8 Paving Tile Slope Protection 9-13
9.11.4 Method of Measurement 9-16
9.8.1 Description 9-13 9.11.5 Basis of Payment 9-16
9.8.2 Materials 9-13 9.11.6 Items in the Bill of Quantities 9-16
9.8.3 Construction Requirements 9-13
9.8.4 Method of Measurement 9-13
9.12 Mechanically Stabilized Earth
9.8.5 Basis of Payment 9-13
Retaining Walls 9-16
9.8.6 Items in the Bill of Quantities 9-13
9.12.1 Description 9-16
9.9 Ditch Lining 9-13
9.12.1.1 General 9-16
9.9.1 Description 9-13 9.12.1.2 Standards and Codes 9-17
9.9.2 Materials 9-13 9.12.2 Materials 9-17
9.9.3 Construction Requirements 9-13 9.12.2.1 General 9-17
9.9.3.1 General 9-13 9.12.2.2 Concrete Face Panels 9-17
9.9.3.2 Precast Slabs 9-14 9.12.2.3 Concrete Footings 9-18
9.9.3.3 Stone Ditch Lining and Wash Checks 9-14 9.12.2.4 Steel Reinforcing and Tie Strips 9-18
9.9.4 Method of Measurement 9-14 9.12.2.5 Reinforced (Polymer) Grids 9-18
9.9.5 Basis of Payment 9-14 9.12.2.6 Fasteners 9-19
9.9.6 Items in the Bill of Quantities 9-14 9.12.2.7 Non Metallic Friction Ties and Fixings 9-19

9.10 Filter Layers 9-14 9.12.2.8 Joint Filler (For Use with Concrete Face
Panels) 9-19
9.10.1 Description 9-14
9.12.2.9 Joint Filler (For Use with Concrete Face
9.10.2 Materials 9-14 Panels 9-19
9.10.3 Construction Requirements 9-14
9.12.3 Construction Requirements 9-20
9.10.3.1 Granular Filter 9-14
9.12.3.1 Wall Excavation 9-20
9.10.3.2 Fabric Membrane 9-15 9.12.3.2 Foundation Preparation 9-20
9.10.4 Method of Measurement 9-15
9.12.3.3 Erection of Concrete Face Panels 9-20
9.10.5 Basis of Payment 9-15
9.12.3.4 Backfill Placement 9-20
9.10.6 Items in the Bill of Quantities 9-15 9.12.3.5 Trial Embankment 9-20
9.11 Barriers for Sand Dunes 9-15 9.12.4 Monitoring 9-21
9.12.4.1 General 9-21
9.11.1 Description 9-15
9.12.4.2 Selected Backfill 9-21
9.11.2 Materials 9-15
9.12.4.3 Settlements 9-21
9.11.2.1 Fences 9-15
9.12.4.4 Horizontal Displacements 9-21
9.11.2.2 Bituminous Materials 9-15
9.12.4.5 Durability 9-21
9.11.2.3 Vegetative Materials 9-15
9.12.4.6 Testing Frequency 9-21
9.11.2.4 Water 9-15
9.12.5 Method of Measurement 9-22
9.11.2.5 Blanket Covers 9-15
9.12.6 Basis of Payment 9-22
9.11.3 Construction Requirements 9-15
9.12.7 Items in the Bill of Quantities 9-22
9.11.3.1 Fencing 9-15

copy 249
Ref. Title Page No.
9.13 Coastal Protection 9-22
9.13.1 Description 9-22
9.13.2 Materials 9-23
9.13.2.1 Quarried Stone for Armour Layers and
Underlayers 9-23
9.13.2.2 Core Material 9-23
9.13.2.3 Filter Fabric – Geotextiles 9-24
9.13.3 Construction Requirements 9-24
9.13.3.1 General 9-24
9.13.3.2 Placement of Core Material 9-24
9.13.3.3 Placement of Armour and Underlayer
Stones 9-25
9.13.3.4 Surveying Technique 9-25
9.13.3.5 Storage, Handling, and Laying of
Geotextiles 9-25
9.13.4 Method of Measurement 9-26
9.13.4.1 Marine Works Generally 9-26
9.13.4.2 Underlayer, rock armour, quarry run and
bedding layer 9-26
9.13.4.3 Dredging for embedded toe protection 9-26
9.14.4.4 Fabrics and membranes ( Geotextile) 9-26
9.13.5 Basis of Payment 9-26
9.13.5.1 Marine Works Generally 9-26
9.13.5.2 Underlayer, rock armour, quarry run and
bedding layer 9-26
9.13.5.3 Dredging for embedded toe protection 9-26
9.13.5.4 Fabrics and membranes ( Geotextile) 9-26
9.13.6 Items in the Bill of Quantities 9-26

copy 249
copy 249
9.1 Riprap ASTM Standard D1751, Specification for Preformed
Expansion Joint Fillers for Concrete Paving and Structural
9.1.1 Description Construction.

1 The Sub-section describes requirements for 9.1.3 Construction Requirements


construction of loose or mortared riprap slope protection
and riprap Cut-off walls or watercourse channel protection. 1 The stones shall be wetted and hand-laid with the
flattest face uppermost and parallel to the prepared slope,
9.1.2 Materials starting from the toe and progressing upwards. Stones
shall be arranged in close contact so as to minimize voids,
1 Stone for loose and mortared riprap shall consist of the largest being placed in the lower courses. Spaces
natural stones of broad flat shapes as far as practicable. between large stones shall be filled with smaller stones of
All stone shall be hard, sound, durable, and highly suitable size. The surface of the riprap protection shall be
resistant to weathering and shall be suitable as protection trimmed and prepared as shown on the Drawings.
material for the intended purpose.
2 The mortar bed shall be progressively spread ahead
2 Samples of the stone material proposed for use shall of stone placing. Stones faces in contact with the mortar
be submitted to the Engineer for approval prior to its use shall be clean and free from any defects that will impair
in the work. the bond with the mortar. Stones shall be washed to
3 The minimum apparent specific gravity of the stone remove any dirt or dust immediately before applying
material shall be 2.5 and the maximum absorption shall be mortar. Mortar shall be spaded and rodded between the
6% when tested in accordance with AASHTO T 85. The stones until the voids are completely filled.
stone shall have an abrasion loss not greater than 45% 3 Expansion joints shall be constructed where the
when tested in accordance with AASHTO T 96. riprap is placed against any structure, or where directed
4 The weight of individual stones for the various by the Engineer. A 13 mm thick fiber joint filler (as
classes of riprap shall be as follows: specified in Item 8 of Clause 9.1.2) shall be installed in
expansion joints. The fiber joint shall extend from the base
% of Total
of the grout layer up to 13 mm below the grout surface. A
Weight
Weight of Stone (kilograms) Smaller than bond breaker, as approved by the Engineer, shall be
Weight placed along the bottom of the 13 mm deep by 13 mm
Shown wide notch, and the top shall be filled with flexible joint
Class sealant in accordance with the manufacturer's
Class B Class C Class D
A recommended procedures, as approved by the Engineer.
50 200 1,000 5,000 95-100
4 The completed work shall be cured for at least 7 days
20 100 400 2,000 50-100
5 20 100 500 0-50 by a curing method approved by the Engineer. After the
1 5 20 100 0-10 expiry of this period, the exposed surfaces shall be cleared
of loose mortar and broken stone fragments.
Table 9.1.2.1: Classes of riprap stones and rocks
5 Loose riprap stone shall be placed in the same
5 Unless otherwise indicated on the Drawings or manner as for mortared riprap. The stones shall be
directed by the Engineer, stones for loose and mortared properly selected and placed so as to minimize voids
riprap shall conform to Class B gradation. Stones shall which shall be filled with pieces of the largest possible size.
generally weigh between 20 and 70 kg. with at least 60%
6 After completion and approval of the loose riprap
weighing more than 45 kg.. Nevertheless, any of the
placement, the surface voids of the riprap in the footing
classes shown in Table 9.1.2.1 above can be used for loose
trench and on the lower portions of the slope shall be
riprap, as indicated on the drawings. For mortared riprap,
filled with excavated material, compacted to 95% max. dry
stones of classes A or B only can be used, as indicated on
density and dressed to the satisfaction of the Engineer.
the Drawings.
7 Unless otherwise shown on the Drawings, the
6 Mortar for mortared riprap shall consist of 1 part
thickness of the loose or mortared riprap layer shall not be
Portland cement to 3 parts sand by volume. Water added
less than 1.5 times the nominal stone size and is
shall be the least amount which will yield a workable mix.
commonly 1.8 - 2.0 times the nominal stone size.
Sand and cement shall conform to the relevant
requirements of Sub-section 5.1. The 28 day compressive 8 Where shown on the Drawings, a filter layer (as
strength of the mortar shall be not less than 15 MPa specified in Sub-section 9.10) or an approved construction
measured in accordance with BS 1881, Part 108. fabric shall be laid on the prepared surface to receive
loose riprap. Thickness of filter layer shall be as shown on
7 Filter material for use under loose or mortared riprap,
the Drawings or directed by the Engineer. The slope shall
as shown on the Drawings shall comply with the
be prepared, trimmed and excavated to the surface
requirements of Sub-section 9.10 “Filter Layers”.
approved by the Engineer and as the cross sections and
8 Expansion joint filler shall be rot-proof and of the
levels shown on the Drawings. The filter material shall
preformed, non-extruding, resilient type made with a
bituminous fiber and shall conform to the requirements of

♦ 9-1 ♦
copy 249
then be laid and compacted to 95% max. dry density, to Engineer’s approval. Samples and manufacturer’s
the satisfaction of the Engineer. certificates shall accompany the proposal.
4 Gabion dimensions shall be as shown on the
9.1.4 Method of Measurement Drawings. A tolerance of ±5% on width and height, and
1 Riprap work shall be measured by the cubic meter of ±3% on length shall be allowed. Gabion shall have
material placed in position. Measurement shall be based diaphragms at 1m centers.
on the dimensions shown on the Drawings. 5 The edges of gabion panels shall be selvedged to
2 Filter material shall be measured by square meter of prevent unraveling of the mesh. Steel wire core used for
the thickness placed in position. Measurement shall be selvedges shall have a nominal diameter of not less than
based on the dimensions shown on the Drawings. 3.5mm. Lacing wire shall have a nominal diameter of not
less than 2.2mm for the wire core. Wire for selvedges and
3 Filter membrane shall be measured in square meter
lacing shall otherwise comply with the same specification
of the material placed in position. Measurement shall be
for the wire used in the mesh.
the area shown on the Drawings.
6 Where shown on the Drawings wire shall be coated
9.1.5 Basis of Payment with a minimum thickness of 0.55mm of dark green or
black PVC, or any other color to the approval of the
1 The amount of completed and accepted work Engineer, which shall be capable of resisting the effects of
measured as provided for above will be paid for at the unit immersion in sea water and exposure to ultra violet light
rates indicated in the Bill of Quantities, which rate shall be and abrasion, when tested for a period not less than 3000
full compensation for selection of materials and removal hours in accordance with ASTM Test G23.
of discarded material, slope preparation, excavation, 7 Stones for gabion filling shall be hard, sound,
backfilling, placing, trimming, finishing and protection of durable and highly resistant to erosion, to the approval of
finished work and expansion joints and for materials, the Engineer. The specific gravity of the stones shall be
transportation, hauling, labor, equipment, tools, supplies not less than 2.5. The stone size distribution in each
and other items necessary for the proper completion of individual box shall be as given in Table 9.2.2.1.
the works.
Size of stones (mm) % of total (by no.)
9.1.6 Items in the Bill of Quantities
80-125 7% maximum
i. Loose stone riprap (class). (cu.m)
ii. Mortared stone riprap (class) (cu.m) 125-200 88% minimum
iii. Filter material (thickness) (sq.m) 200-250 5% maximum
iv. Filter membrane (sq.m)
Table 9.2.2.1: Stones for Gabions

9.2 Gabions 8 Mastic asphalt constituents shall be sand,


penetration grade bitumen and filler. The mastic shall
have the characteristics given in Table 9.2.2.2.
9.2.1 Description
% of total (by
1 This Sub-section describes requirements for gabions Constituents Material Type
mass)
consisting of supplying, building and placing of stone- Sand (5mm Natural sand or
filled galvanized steel wire mesh baskets (or other 55-72
nominal size) crushed rock
approved types of heavy duty plastic mesh) as slope or
Bitumen 80-100 Pen 15-18
watercourse channel protection.
Portland
Filler cement or 13-16
9.2.2 Materials
hydrated lime
1 Gabion boxes shall be made of a hexagonal woven Table 9.2.2.2: Characteristics of Mastic Asphalt
mesh of double twisted hot-dip galvanized steel wire. The Constituents
nominal mesh size shall be 80mm x 100 mm. details of the
type of mesh proposed for use shall be submitted to the 9 Sand-cement grout shall be composed of one part of
Engineer for approval. Portland cement and four parts of sand measured by
volume, mixed with sufficient water to a consistency so
2 Wire used in the fabrication of the gabion shall be
that the grout can flow into and completely fill the voids.
mild steel to ASTM A390 Class 3 or to BS 1052 having an
average tensile strength, before coating of 380 to
500N/mm2. The core wire diameter shall be 3.00 mm 9.2.3 Construction Requirements
before galvanizing. Galvanizing shall comply with BS 443. 1 Gabions shall be placed and built to the lines, levels
3 Non-metallic material for gabion boxes, such as and patterns shown on the Drawings, on a prepared
extruded polypropylene, may be proposed for the

♦ 9-2 ♦
copy 249
horizontal foundation surface for gabion boxes and 9.2.6 Items in the Bill of Quantities
mattresses and/or sloping foundation surface for gabion
i. Gabions (size). (cu.m)
mattresses, excavated as required, and compacted as
ii. Mastic asphalt grout. (cu.m)
instructed by the Engineer.
iii. Sand-cement grout. (cu.m)
2 Gabion cages shall be securely wired together at
corners and edges, and where there is more than one
course of gabions, the upper course cages shall be laced
9.3 Slope Netting
to the lower course. Before filling, the cage shall be in its
permanent position and laced to adjoining previously 9.3.1 Description
filled cages. 1 This Sub-section describes requirements for
3 Non-metallic gabion cages of proprietary type shall supplying and installing steel wire mesh netting as rock
be constructed according to the manufacturer’s slope protection.
instructions.
4 Stones shall be packed by hand inside the cages as 9.3.2 Materials
tight as practicable with the minimum of voids. The wires 1 Wire slope netting shall consist of a hexagonal
shall be fixed inside the compartments and the units woven mesh of double twisted hot-dip galvanized steel
tensioned in accordance with the manufacturer’s wire. The nominal mesh size shall be 80mm x 100mm.
instructions.
2 All wires shall be mild steel conforming to BS 1052,
5 The cages shall be overfilled with stones to allow for having a minimum nominal diameter of 2.7mm. The wire
subsequent settlement and the lid laced down with shall be hot-dip galvanized in accordance with ASTM A
binding wire to the top of each of the four sides and to the 767, Class II (610g Zinc/sq.m., 2.0 oz. Zinc psf), after
top of the diaphragm panels. fabrication and bending.
6 Where shown on the Drawings, the Contractor shall 3 Spikes for wire slope netting attachment shall be as
grout gabions with hot poured mastic asphalt. The mastic shown on the Drawings and the steel shall comply with
shall be mixed at a temperature of 160-200˚C and poured the relevant requirements of Section 6.
to fill the voids between the stones for the depth shown.
The actual rate of application shall be as approved by the 9.3.3 Construction Requirements
Engineer during construction.
1 The wire netting shall be securely anchored to the
7 Where shown on the Drawings, the Contractor shall
rock face with the driven steel spikes spaced at an average
grout gabions with sand-cement grout. Immediately
of not more than 5m vertically and horizontally around the
before pouring the grout, the stones should be wetted by
perimeter of each section.
sprinkling. The grout shall be poured to fill the voids
between the stones for the depth shown. The actual rate 2 For rock slope faces in excess of 5m high, the netting
of application shall be as approved by the Engineer during shall be hung from hooked rock bolts installed
construction. The grout shall be allowed to set and harden untensioned as specified in Sub-section 9.4 at spacing
before any stormwater is received. The grout shall be kept between 5m and 10m horizontally and vertically.
moist with water for a period of not less than 72 hours. 3 The rock slope face shall be trimmed to the profile
shown on the Drawings and in accordance with the
9.2.4 Method of Measurement relevant requirements of these specifications. The
proposed new section dimensions and fixing points shall
1 Gabions shall be measured by the cubic meter of
be submitted for prior approval by the Engineer. Intact
installed gabion, based on the dimensions shown on the
sound rock masses shall be selected for the bolts and
Drawings. Rates shall be deemed to include for provision
spikes positioning.
and installing all materials, protection of finished work and
all preparatory work including excavation and preparation
9.3.4 Method of Measurement
of ground.
2 Where grouting is required, it shall be measured by 1 The approved wire netting slope protection work
the cubic meter of sand-cement or of mastic asphalt shall be measured by the square meter of the area
applied. installed. Preparation of the rock face and spikes and
fixation accessories shall not be separately measured, but
9.2.5 Basis of Payment shall be deemed included in the rate for wire netting slope
protection.
1 The amount of completed and accepted work
measured as provided for above will be paid at the unit 9.3.5 Basis of Payment
rate for “Gabion” in the Bill of Quantities, which rate shall
be full compensation for slope preparation, protection, 1 The amount of completed and accepted work
drainage, excavation, backfilling, and for materials, labor, measured as provided for above will be paid for at the unit
equipment, tools, supplies and other items necessary for rate for “Wire Slope Netting” in the Bill of Quantities
the proper completion of the work. which rates shall be full compensation for slope and

♦ 9-3 ♦
copy 249
foundation preparation, drilling, fixing and for materials, shall be flat mild steel plate 150 by 150 by 8mm thick with
labor, equipment, tools, supplies and other items free fit holes. Nuts shall conform to BS 490 and washers
necessary for the proper completion of the work. shall conform to BS 4320.
3 Rock bolts may consist of tensioned or untensioned
9.3.6 Items in the Bill of Quantities dowel bars anchored by resin or grout or mechanically
i. Wire netting slope protection (sq.m) anchored.
4 Protection of rock bolts against corrosion shall be as
9.4 Rock Bolts, Anchors and Sprayed shown on Drawings.

Concrete 9.4.2.3 Resin-Anchored Rock Bolts

9.4.1 Description 1 The point resin anchor shall be formed using a


cartridge system. The remaining length of the bolt shall be
1 This Sub-section describes stabilization of cut or grouted with cement if required by the Engineer. The
natural slopes in soil or rock by one or combination of the grout may be injected after the installation of the bolt and
following methods: rock bolting, rock anchoring and anchor, or the resin and cement grout may be placed in
grouting, shotcreting or guniting, and wire netting. the hole and the bar pushed through the cement grout
into the resin.
9.4.2 Materials 2 If the Engineer so directs, rock bolts shall be de-
9.4.2.1 Cement Grout bonded along the length of bar which is not required for
anchorage purposes by means of a suitable plastic sheath
1 Grout for use in rock bolting and rock anchors, shall preventing the formation of a bond between the grout and
normally consist of a mixture of cement and water only. the bar.
Fine sand aggregate passing No. 16 sieve may be added, if
3 If untensioned dowel bars are used, all voids shall be
approved, for grouting of large holes, etc.
completely filled with grout.
2 Admixtures and filler may be used only if approved
4 If resin-anchored rock bolts are used, the tests
by the Engineer and shall be free from chlorides..
specified in ASTM D4435 shall be carried out. The
3 Cement, sand and water shall conform to the Contractor shall ensure that the resin is not adversely
requirements of Section 5. Sulfate resisting and rapid affected by the cement grout.
hardening cements shall be used only if specified and
approved. 9.4.2.4 Mechanically Anchored Rock Bolts
4 The compressive strength of 150 x 150 mm cubes 1 These shall be of the expansion shell type and full
made of grout and measured in accordance with BS1881 details of the type of bolt and anchorage to be used shall
shall not be less than 17 MPa. at 7 days. Cubes shall be be submitted for approval prior to installation. If approved,
cured in a moist atmosphere for the first 24 hours and mechanical anchorage bolts shall be used in accordance
subsequently under water. with the manufacturer's instructions as approved or
5 Grout mixes shall have good fluidity and low modified by the Engineer who may require mechanically
sedimentation or bleeding in the plastic state, good anchored rock bolts to be cement grouted.
durability and density with low shrinkage in the hardened
state, in order to bond with the side of boreholes and to 9.4.2.5 Drain Holes
provide protection for bolts and anchors, etc. Mix 1 Drain holes shall be drilled into the rock slope to
proportions shall be as specified for the various relieve water pressure buildup in the rock slope. The drain
applications of grout, and grouting trials shall be holes shall be lined with slotted PVC drain pipe and
undertaken as directed by the Engineer. plumbing systems shall be installed to direct water flows
6 All materials shall be proportioned by weight. away from the rock slope, as shown on the Drawings or as
directed by the Engineer.
9.4.2.2 Rock Bolts Generally
9.4.2.6 Rock Anchors
1 All bolts, required to provide support for excavated
or natural rock faces, shall be deformed high tensile steel 1 Rock anchors required to provide support for
bars conforming to the relevant requirements of Sub- excavated or natural rock faces, and at tunnel portals, shall
section 5.2 "Reinforcing Steel" or other type in accordance consist of steel tendons in excess of 10 m in length and
with Drawings. shall conform to AASHTO M204: "Uncoated Stress
2 Rock bolts can be continuously threaded or threaded Relieved Wire for Pre-stressed Concrete".
to allow extension to be fitted as required. One end of the 2 Corrosion protection shall be as shown on the
bolt shall be threaded for a tensioning locking nut, Drawings.
sufficient to ensure that a 10 to 50mm thread length
extends beyond the locking nut. The thread on the bolt
shall be ISO metric coarse series to BS 4190. The washer

♦ 9-4 ♦
copy 249
9.4.2.7 Sprayed Concrete and Mortar 8 Prior to proceeding with the shotcreting works, the
Contractor shall prepare three test panels for approval,
1 Sprayed concrete (Shotcrete) shall be a mixture of
using the proposed materials, mix design and equipment.
water, cement, sand and aggregate, projected onto the
Each test panel shall be approximately 750mm square,
area of placement, without interruption, by means of a
using plywood or other similar material for the back form
purpose made machine. Sprayed concrete (Shotcrete)
against which the shotcrete is to be sprayed. The
with 28 day cube compressive strength of 25 MPa with an
thickness of sprayed material shall be a minimum of
aggregate smaller than 12.5 mm particle size shall be used.
75mm or the thickness that is to be used in the structure,
2 Sprayed mortar (Gunite) shall be a mixture of water, whichever is greater.
cement and sand projected onto the area of placement
9 After curing the test panels, cores shall be taken for
without interruption, by means of a purpose - made
compression testing at 7 and 28 days. The cores shall be
machine Sprayed mortar (Gunite) with 28 day cube
at least 75mm in diameter and shall be measured and
compressive strength of 25 MPa with sand of maximum
tested in accordance with AASHTO T 22. In addition to
particle size 7mm shall be used.
compression testing, the cores shall be carefully examined
3 Materials, equipment and application procedures visually for soundness or evidence of non-uniformity in
shall generally conform to the latest revision of ACI 506.2 - the consistency of the concrete or mortar.
"Specifications for Shotcreting" unless otherwise specified
hereunder. 9.4.2.8 Wire Netting
4 Portland cement, fine aggregate, coarse aggregate 1 All wires shall be mild steel conforming to BS 1052,
and mixing water shall conform to the requirements of having a minimum nominal diameter of 2.7mm. The
Sub-section 5.1 - "Concrete Materials and Mixes”. The maximum mesh shall be 100mm x 80mm, the wire shall
mixture of coarse and fine aggregate for applications up to be hot-dip galvanized in accordance with ASTM A 767,
250 mm in thickness and applications exceeding 250 mm Class II (610g zinc/sq.m., 2.0 oz. zinc psf), after fabrication
in thickness shall conform to the following grading and bending.
requirements:
2 The hexagonal wire mesh netting shall be triple
Percent Passing By Weight twisted and suitably woven to produce a flexible uniform
net pattern, free of any damage. Both longitudinal sides
Standard Sieve Size Thickness of the netting sheets shall be edged with a wire of
Thickness up
exceeds 250 equivalent standard to that of the netting but greater in
to 250 mm diameter. The lacing-wire used for fixing adjacent netting
mm
sheets shall also be of equivalent standard.
12.5 mm (1/2 in.) 100
9.4.3 Construction Requirements
9.5 mm (3/8 in.) 100 90-100
9.4.3.1 General
4.75 mm (No. 4) 95-100 65-82
1 Before any of the works is commenced, the
2.36 mm (No. 8) 80-95 45-68 Contractor shall submit a detailed method statement to
the Engineer for his approval. The method statement shall
1.18 mm (No. 16) 45-80 30-53 include adequate details concerning the materials, work
procedures, means and methods and frequency of testing
0.600 mm (No. 30) 30-60 20-38 for grouts and anchors; intended by the Contractor, to
carry out the work and achieve the specified requirements.
0.300 mm (No. 50) 10-30 7-22
9.4.3.2 Rock Bolting Procedures
0.150 mm (No. 100) 2-10 2-10
1 After drilling holes of the required diameter and
0.075 mm (No. 200) 0-3 0-3 depth, and after inspection and approval of the holes and
their locations, rock bolts shall be installed and anchored
Table 9.4.2.1: Gradation of Sprayed Concrete Combined
by one of the approved means as described below,
Aggregates depending upon the type of rock bolts being installed.
5 The Cement content per cu.m. of aggregate shall be 2 Grouting equipment shall be of a type capable of
not less than 375 kg.. producing a grout of colloidal consistency by means of
6 If approved by the Engineer, water-reducing, non- high local turbulence while imparting only a slow motion
chloride accelerator admixture, complying with ASTM to the body of the grout. The injection equipment shall be
C494, Type E, and containing not more than 0.1 percent capable of continuous operation with little variation of
chloride ions, may be used. pressure and shall include a system for re-circulating the
grout while actual grouting is not in progress.
7 Reinforcement shall conform to the requirements of
Sub-section 5.2 – “Reinforcing Steel”.

♦ 9-5 ♦
copy 249
Compressed air shall only be used if approved. an even bearing surface for the cover plate. Where this
Equipment shall have a delivery pressure not exceeding 1 procedure is not possible, a conical aligning seating shall
MN/sq.m. All baffles to the pump shall be fitted with 1.2 be used. Epoxy mortar packing between the bearing plate
mm sieve strainers. All equipment and piping shall be and rock shall be used where directed.
thoroughly washed with clean water after every series of 9 Anchored rock bolts shall be tensioned by either
operations and more frequently if directed. Intervals applying a specified torque to the nut or by using a
between washings shall not exceed 3 hours. hydraulic jack. The Engineer shall instruct the Contractor
3 Mixing of grout shall proceed by water being added as to which method is to be used in particular cases.
to the mixer first, followed by the cement. When these are 10 Where the torque method of tensioning is used, the
thoroughly mixed any admixture or sand shall be added. required tension shall be agreed by the Engineer and tests
Mixing shall continue for at least 2 minutes until a uniform shall be carried out to establish the applied torque
consistency is obtained. The water: cement ratio of the required to achieve this load. Care shall be taken to
mix shall not exceed 0.45 by weight. Mixing by hand will ensure that the threads on the bar and nut are clean and
not be permitted. free from obstructions.
4 Grout shall be injected continuously and in such 11 Where tension is to be applied by hydraulic jack, the
manner as to avoid causing segregation of the grout. The Engineer may require tests to establish the jack gauge
method of injection shall ensure complete filling of the calibration. In calculating the initial load to be applied,
boreholes and complete immersion of the bolt in the grout. loss of tension due to the transfer of load to the locking
The volume of the spaces to be filled by the injected grout nut and washer shall be allowed for.
shall be compared with the quantity of grout injected.
12 Permanent load measuring instruments shall be
Grout shall be allowed to flow from the free end of the
incorporated in selected rock bolts as directed and the
borehole until its consistency is equivalent to that of the
tension in these bolts shall be monitored. Monitoring
grout injected. The opening shall then be firmly closed.
shall be carried out at hourly intervals for the first 4 hours,
Injection tubes shall be sealed off under pressure until the
then at 4-hour intervals up to the first 24 hours, then at
grout has set.
daily intervals up to 20 days after tensioning or at such
5 Polyester resin gel and cure times shall be suited to other times as may be directed.
the working temperature and method of installation of the
13 Where the Engineer directs that the lengths or part of
bolt. The main resin and filler content shall be enclosed in
the length of a rock bolt shall be de-bonded from the
an outer sheath or skin and the catalyst shall be enclosed
surrounding grout, this de-bonding shall be achieved by
in a separate container within the main sheath. The resin
means of a plastic sheath closely fitting around the steel
and catalyst shall be mixed by rotating the bolt by means
bolt.
of a power tool for such time and at such speed as will
ensure the thorough intermixing of the two constituents. 14 All relevant data shall be recorded and presented in
The viscosity of the resin shall be such that complete an approved form. If the Engineer is not satisfied that the
disintegration of the resin sheath is achieved and the anchorage of the bolt is adequate, the Contractor shall
pieces of sheath material do not have a detrimental effect take approved remedial measures to ensure adequate
on the final strength of the anchorage. anchorage.

6 Expansion shells for mechanical anchorage shall be 9.4.3.3 Pull Out Tests for Anchored Bolts
of an approved type and shall be installed in accordance
with the manufacturer's instructions as approved or 1 Before commencement of any work requiring rock
modified by the Engineer. Where such bolts are used in bolts, pull out trials shall be carried out to measure the
close proximity to a rock face where blasting is taking ultimate load carrying capacity of all types of bolts to be
place, the security of the anchorages shall be checked used. Pull out tests shall be carried out according to ASTM
after blasting and the bolts re-tightened or replaced, if Standard method D4435 or BS equivalent.
necessary in a new hole. 2 Trials shall be carried out in rock of a similar nature
7 Each hole shall be drilled straight and each bar shall to that in which the rock bolts will be used. The
lie centrally in the hole and not be in contact with the rock. deformation of rock bolts and the load shall be continually
The diameter shall be 10 mm greater than the bolt monitored until failure. A minimum of 4 tests on each
diameter if grouted with cement. For resin anchored bolts, type of bolt to be used shall be performed. Details of
the hole size shall be determined according to the proposed procedures shall be submitted for approval
anchorage or cartridge size and in accordance with the before commencement of the trials. The anchorage must
manufacturer's recommendations. Allowance shall be be capable of carrying twice the specified working load.
made for the hole size to be slightly greater than the bit 3 These tests will be used to assess the suitability of
size. Tolerance on the diameter of hole shall be plus or proposed anchorage systems in the particular location
minus 2 mm. The hole shall be thoroughly flushed and where the bolts are to be used. Where rock conditions
cleaned after drilling. change, such that anchorage characteristics are affected,
8 The rock surface around each hole shall be trimmed further trials shall be carried out as directed.
flat in a plane normal to the axis of the rock bolt to ensure

♦ 9-6 ♦
copy 249
4 During construction approximately 5% of all bolt 6 Pre-stressing bars as delivered shall be straight. Any
types shall be tested to twice the specified working load. If small adjustments for straightness necessary on Site shall
significant failures are obtained in the tests results, the be made by hand under the supervision of the Engineer.
Contractor shall carry out further tests and shall take Bars bent in the threaded portion will be rejected. Any
approved remedial measures as directed by the Engineer. straightening of bars shall be carried out cold.
5 A protective barrier (wire netting) shall be erected 7 All cutting to length and trimming of ends shall be by
around the testing equipment to protect and safeguard high speed abrasive cutting wheel, friction saw or any
against any injury to any personnel involved in the testing other mechanical method approved by the Engineer. In
works and any other measures as deemed necessary by rock anchor systems, the cutting action shall be not less
the Engineer. than one diameter from the anchor, and the heating effect
on the tendon shall be kept to a minimum.
9.4.3.4 Pull Out Tests for Untensioned Bolts
8 The tendon or tendons shall be accurately located
1 The efficiency of grouting shall be checked by pulling and maintained in position. Spacers are to be used to
out the bolts (according to ASTM D4435) after such time keep the tendons in their correct position in the borehole.
as will ensure that the cement grout or mortar remains 9 The tendon or tendons shall terminate at the back of
bonded to the bolt when the bolt is withdrawn from its the hole in the rock secured in a ribbed steel cylindrical
hole. A total of 10% of all untensioned bolts shall be anchorage block or be grouted into place over the
tested in this way. The grouted boreholes shall then be 'anchorage length' defined for the working load required.
cleaned out and bolts free from hardened grout reinstalled The end of the borehole shall be filled with a polyester
to the Engineer's satisfaction. resin or cement mortar. The length of anchorage shall be
2 If, in the Engineer's opinion, an unacceptably high sufficient to take the load on the tendons with a safety
percentage of the initial 10% selection of bolts is not fully factor of 2. The remaining length of tendon, (the free
grouted along their length, the Engineer will require length) shall be encased in a corrosion-protected grease-
further tests to be carried out. packed, plastic de-bonding sheet.

9.4.3.5 Rock Anchoring Procedures 9.4.3.6 Tensioning Tendons

1 Care shall be taken to avoid mechanically damaging, 1 All wires or strands stressed in one operation shall
work hardening or heating tendons while handling. All be taken, where possible, from the same parcel. Each
tendons shall be stored clear of the ground and protected cable shall be tagged with its number and the coil number
from the weather, from any other materials and from or numbers of the steel used. Cables shall not be kinked
splashes from the cutting operation of an oxy-acetylene or twisted, and individual wires and strands shall be
torch, or arc-welding processes in the vicinity. In no readily identifiable at the end of the member. No strand
circumstances shall tendons be subjected to any welding that becomes unraveled shall be used.
operation, or on-site heat treatment or metallic coating 2 A tendon when tensioned contains a considerable
such as galvanizing. amount of stored energy, which, in the event of any failure
2 When tendons have been stored on site for a of the tendon, anchorage or jack, may be released
prolonged period, the Engineer may require tests to show violently. The Contractor shall ensure that adequate
that the quality of the tendons has not been significantly precautions are taken during and after tensioning to
impaired by corrosion, stress-corrosion, loss of cross- safeguard persons from injury and equipment from
sectional area or changes in any other mechanical damage which may be caused by the sudden release of
characteristics. this energy.
3 All tendons shall be free from loose mill scale, loose 3 Hydraulic jacks shall be used for tensioning tendons.
rust, oil, paint, grease, soap or other lubricants, or other The tensioning apparatus shall meet the following general
harmful matter at the time of incorporation in the rock requirements:
anchor. Cleaning of tendons shall be carried out either by i. The means of attachment of the tendon to the
wire brushing or by passing through a pressure box jack shall be safe and secure.
containing carborundum powder. Solvent solutions shall ii. Where two or more wires or strands are
not be used for cleaning without approval. stressed simultaneously, care shall be taken
4 Low relaxation and normal relaxation wire shall be in that they are of approximately equal lengths
sufficiently large diameter coils to ensure that the wire between anchorage points at the datum of load
pays off straight. In cases where, in the opinion of the and extension measurement. The degree of
Engineer, straight as-drawn wire is not essential, wire in variation shall be small compared with the
small diameter coils corresponding to the diameter of the expected extension.
blocks in the drawing machine may be used. iii. Tensioning shall be such that a controlled total
5 Pre-stressing strand, however manufactured, shall be force is imposed gradually and no dangerous
in sufficiently large diameter coils to ensure that the secondary stresses are induced in the tendons,
strand pays off straight. anchorage or concrete.

♦ 9-7 ♦
copy 249
iv. The force in the tendons during tensioning 3 Grouting procedures, injection of grout and strength
shall be measured by direct reading load cells of grout shall be as specified for rock bolting.
or obtained indirectly from gauges fitted in the
hydraulic system to determine the pressure in 9.4.3.8 Testing of Rock Anchors
the jacks. Facilities shall be provided for the 1 Before commencement of any part of the permanent
measurement of the extension of the tendon anchorage works, two trial anchors shall be installed and
and of any movement of the tendon in the tested to ensure that they can carry the specified load with
gripping devices. The load-measuring device a safety factor of 2. Anchor pull tests shall be performed
shall be calibrated to an accuracy within plus according to ASTM D4435 Standard method or BS
or minus 2% and checked at frequent intervals equivalent
agreed with the Engineer. Elongation of the
2 Load/elongation curves shall be plotted and
tendon shall be measured to an accuracy
interpreted by the Contractor and presented with all
within 22% or 2 mm, whichever is more
relevant data in a form approved by the Engineer.
accurate.
v. Complete records shall be kept of all tensioning 3 If either of the trial tests shows that the anchor has a
operations, including the measured extensions, safety factor of less than 2, then the anchorage length and
pressure-gauge, or load-cell readings and the formation shall be modified and two further tests shall be
amount of pull-in at each anchorage. carried out.

vi. Anchorage of the tendons at the rock face end 9.4.3.9 Application of Sprayed Concrete and Mortar
of the borehole shall conform to BS 4447.
vii. The form of anchorage system shall facilitate 1 Carry out shotcreting in a sequence and according to
the even distribution of stress in the concrete a program to be approved by the Engineer
bearing pad. 2 Provide good lighting, rigid and sufficiently wide
viii. Split wedge and barrel-type anchors shall be of working platforms in area where shotcreting is taking
such material and construction that, under the place
loads imposed during the tensioning operation, 3 Protect properly surfaces which are not to be coated
the strain in the barrel will not allow such and keep them free from sprayed concrete.
movement of the wedges to reach the limit of 4 Clean and wet all surfaces thoroughly with a strong
their travel before causing sufficient lateral blast of air and water, immediately prior to the application
force to grip the tendon, or before the limit of of sprayed concrete.
travel of the wedges causes an excessive force
5 Safety: if the exposed rock profile is considered by
in the tendon.
the Engineer to be unsafe, then ensure that the personnel
ix. If proprietary forms of anchorage are used, the
manning the sprayed concrete operation are protected
anchoring procedure shall be in accordance
from falling rock. In this respect the Contractor is advised
with the manufacturer's instructions and
to consider the use of a remote controlled-sprayed
recommendations and as approved by the
concrete machine.
Engineer.
6 Control the thickness and the alignment of the
x. All bearing surfaces of the anchorages of
sprayed material by either guide wires, mortar spotting or
whatever form shall be clean prior to the
plastic studs, to indicate depth. Drill through the concrete
tensioning operation.
lining to establish the thickness of the lining at points
xi. Any allowance for draw-in of the tendon during
selected by the Engineer. Build up each layer of sprayed
anchoring shall be in accordance with the
concrete or mortar by making several passes of the nozzle
Engineer's instructions and the actual slip
over the working area. Project the sprayed concrete or
occurring shall be recorded for each individual
mortar from the nozzle in a steady uninterrupted flow.
anchorage.
Should the flow become intermittent for any reason, the
xii. After tendons have been anchored, the force nozzle man shall direct it away from the work until it again
exerted by the tensioning apparatus shall be becomes constant.
decreased gradually and steadily so as to avoid
7 Layer thickness is governed mainly by the
shock to the tendon or the anchorage.
requirement that the concrete or mortar should not sag.
xiii. Provision shall be made for the protection of
Where thick layers are applied it is important that the top
anchorages against corrosion.
surface be maintained at approximately a 45 degree slope.
9.4.3.7 Grouting for Rock Anchors The minimum allowable thickness of layer according to
the American Shotcrete Association ASA
1 The space in the borehole around the tendons shall recommendations is 25mm. There is no stated maximum
be grouted with a cement grout such that the void shall be thickness for shotcrete layer.
completely filled.
2 Grouting shall be carried out as soon as practicable
after the tendons have been stressed.

♦ 9-8 ♦
copy 249
8 Where necessary a layer of sprayed concrete or Paragraph 9.4.2.7) shall be made on a daily basis and shall
mortar may be covered by succeeding layers, but it shall represent each application crew, change in mix design, or
first be allowed to take its initial set. All laitance, loose change in procedure. After curing along with and in the
material and rebound must first be removed. Remove any same manner as the structure, the panels shall be cored in
laitance, which has taken final set by grit blasting. Finally the same manner as described for preliminary testing and
clean and wet the surface using adequate blast of air and shall be tested in accordance with AASHTO T 22. Should
water. The time between applications of successive layer cores from any of the test panels fail to meet strength
shall not exceed 24 hours. A longer break may be requirements, the materials in the structure itself shall be
accepted if it can be shown by tests that sufficient bond cored, taking at least 4 cores for each 100 sq.m.
can be achieved represented by the failed test panel. If the average
9 Under no circumstances shall rebound material be strength of these cores meets strength requirements and
worked back into the construction. Keep the work no single core is less than 75% of design strength, the
continually free of rebounded material, by use of a high materials shall be accepted; otherwise the materials in the
pressure air jet or any other necessary means. structure shall be cut out and replaced.

10 The distance of the nozzle from the work shall be 19 Cut and replace any work which is not accepted by
between 600mm and 1000mm. It shall be, as a general the Engineer
rule, aimed perpendicular to the application surface.
9.4.3.10 Reinforcement Mesh
Commence application for vertical or near vertical
surfaces, at the bottom. Embed completely the 1 The reinforcing mesh shall be made up from 5mm
reinforcement, at least, in the first layer. diameter steel bars. Weld the bars to form a 150mm
11 Provide suitable screening of the nozzle and the square grid and fix it firmly to the rock by an approved
application surface during windy and draughty conditions. means such that it is rigidly held during the subsequent
application of sprayed concrete. Ties, anchors and
12 Keep the spraying equipment in good condition by
supports shall be of a material approved by the Engineer.
cleaning frequently. This shall be done at least once per
shift. The spraying nozzle shall be in such condition that 2 Avoid spraying through the reinforcement as the
an even and continuous flow of material is obtained. reinforcement can make hollows and arching effect, which
Change nozzle cover as soon as excessive wear is found in hinder the production of a homogeneous concrete layer.
the cover. The arrangement for the addition of water at Fix reinforcement as late as possible. If a number of
the nozzle must give a uniform wetting of the material. If reinforcement layers are used then they shall be fixed and
the dry mix process is used, add liquid admixtures, if concreted one at a time. When shooting through bars is
approved, with the mixing water at the nozzle. If dry unavoidable, hold the nozzle closer than usual and at a
admixture is used, add it into the dry mix at the latest slight angle in order to permit better encasement, and
possible time. In either case, employ accurately calibrated facilitate the removal of rebound. Clean reinforcement of
and adjustable mechanical means to dispense the any previously deposited rebound material which may
admixture in the correct approved proportions. prevent a proper bond.

13 The capacity of the compressor plant and water 3 The method of fixing shall be such that sprayed
supply shall be large enough to ensure a constant and concrete can be compacted soundly behind the
sufficiently high pressure. The water pressure should be reinforcement at all points.
somewhat higher than the air pressure. Manometers 4 The minimum cover of mesh reinforcement to the
should be provided to measure the air and water pressure. rock surface is to be 25mm. The minimum cover to mesh
14 Damp cure sprayed concrete or mortar for at least 7 reinforcement from the required finished surface of the
days. sprayed concrete is to be 20mm.

15 Make the profile of the finished surface even. Fill any 9.4.3.11 Paint
area of excessive overbreak with sprayed concrete, or
other approved cavity filler, to bring the finished surface 1 Wherever shown on the Drawings, sprayed concrete
level with the general profile of the surrounding finished shall be painted with the indicated material type and color,
sprayed concrete or mortar. to the Engineer’s approval.

16 Sprayed concrete or mortar surfaces shall not be 9.4.3.12 Wire Netting


trowelled, screeded or disturbed in any way unless
specified otherwise. 1 Wire netting is to be used to secure loose rock on the
cut slopes it may be used in conjunction with rock bolts
17 Construction joints shall be tapered to a thin edge
and sprayed concrete. The netting is to be secured to the
over a width of approximately 300mm, unless specifically
rock face in a manner approved by the Engineer.
instructed by the Engineer. No square joints are allowed.
Clean and wet the entire joint thoroughly prior to the
placement of adjacent sprayed material.
18 Testing of sprayed concrete: During the work, three
test panels as described for preliminary testing (under

♦ 9-9 ♦
copy 249
9.4.4 Method of Measurement 9.5 Rock Grouting
1 Rock bolts shall be measured by lin.m. of each
9.5.1 Description
category installed, including borehole drilling, grouting
and de-bonding if required.. 1 This Sub-section describes installation, drilling and
2 Rock anchors shall be measured by lin.m. of each grouting rock as slope stabilization.
specified capacity installed including borehole drilling,
tensioning, securing and grouting. 9.5.2 Materials
3 Drilling boreholes, de-bonding of rock bolts, trial 1 Grout shall consist of a mixture of cement and water.
bolts and trial rock anchors, testing and monitoring of rock For grouting of large holes fine sand aggregate passing
bolts and rock anchors, grouting of rock bolts and rock 1.18mm AASHTO standard sieve may be added if
anchors, and other ancillary items and work shall not be approved by the Engineer. Chemical admixture and filler
measured separately for direct payment, but shall be may only be used with prior approval of the Engineer.
considered as subsidiary work the costs of which will be
2 The compressive strength of the grout measured in
deemed to be included in the rates for rock bolts and
accordance with BS 1881 shall exceed 15 MPa at 7 days.
anchors.
3 Grout mixes shall have the minimum cement content
4 Shotcrete (concrete) or gunite (mortar) shall be
consistent with the required workability. The grout shall
measured by the cubic meter, applied, The area and
not be subject to bleeding in excess of 2% after 3 hours,
thickness shall be computed from the Drawings unless
nor 4% maximum, when measured at 18˚C in a covered
otherwise directed by the Engineer. The rates shall be
cylinder approximately 100 mm diameter with a height of
deemed to include for all ancillary work, including
grout of approximately 100 mm, and the water shall be
preparation of rock surfaces, provision and maintenance
reabsorbed by the grout during the 24 hours after mixing.
of spraying equipment, finishing and protection of
surfaces and all tests.
9.5.3 Construction Requirements
5 Reinforcing mesh shall be measured by the sq.m of
net area, installed, based on the Drawings unless 1 Rock grouting is the injection under pressure of grout
otherwise directed by the Engineer. Rates are deemed to to consolidate areas of fractured rock. Grouting shall
include for all fixings and laps at joints in the mesh normally proceed from the bottom of the rock slope
upwards.
6 Painting of the shotcrete (if required) shall be
measured by the sq.m. of area painted, based on the 2 Details of methods to be adopted and materials to be
Drawings unless otherwise directed by the Engineer. Rates used, sequence, spacing, diameter and depth of holes to
shall include for all primers and preparatory work. be adopted shall be submitted to the Engineer for prior
approval before proceeding with any pressure grouting.
7 Wire netting shall be measured by the sq.m. of net
Grouting work shall be under the direct control of skilled
area , installed, based on the Drawings unless otherwise
and experienced operatives.
directed by the Engineer. Rates are deemed to include for
all fixings and laps at joints.. 3 The rock slope shall be trimmed and prepared as
specified in Section 2, Paragraph 2.3.3.6 before grouting is
9.4.5 Basis of Payment begun.
4 Clean water shall be used as the flushing medium for
1 The amount of completed and accepted work
drilling, with flows not less than 15 l/minute.
measured as provided for above will be paid for at the unit
rates for the various items stated in the Bill of Quantities 5 The Contractor shall ensure that, at all times,
which rates shall be full compensation for slope and grouting work is under the direct control of skilled and
foundation preparation, drilling, fixing and for materials, experienced operatives. The Engineer may vary the
labor, equipment, tools, supplies and other items methods, materials and grouting pressures if, in his
necessary for the proper completion of the work. opinion, the conditions dictate a change of technique. All
holes to be grouted shall be numbered, as directed and
grouting operations shall take place in the following order:
9.4.6 Items in the Bill of Quantities
i. Rock Bolts (lin.m) i. Drilling of holes
ii. Rock Anchors (lin.m) ii. Washing of holes
iii. Shotcrete (cu.m) iii. Water testing
iv. Gunite (cu.m) iv. Pressure grouting
v. Wire Netting for Shotcrete (sq.m)
6 The hole spacing shall normally be 1.6m to 5.0m with
vi. Reinforcing Mesh (sq.m)
additional holes as required to intersect individual weaker
vii. Painting (sq.m)
areas. Hole depth shall be limited to the range 3-10m and
hole diameter shall be within the range 38-78mm, drilled
with either rotary or rotary-percussive drilling equipment.

♦ 9-10 ♦
copy 249
Water or air flush may be used unless otherwise directed 12 Grouting can be considered complete when the
by the Engineer. absorption of grout at the required pressure is less than 2 l
7 Holes shall be jetted using a water flow, under such per min over a period of 10 minutes.
pressure as may be directed. The injection of water shall 13 Grouting shall proceed with caution until experience
be followed by injection of air under pressure, these of the ground conditions has been gained. Thereafter, if
operations alternating until air bubbles appear at an conditions allow, injection shall proceed at high pressure
adjacent hole. All other holes shall be capped and water to achieve maximum flow from the start of injection.
forced under pressure into the first hole, until unwanted Grout pressure, as measured at the mouth of the hole,
material from fissures washes out from the uncapped hole. shall correspond to 0.4 bar/ per meter depth of hole for
This process shall continue until no more fine material is those areas where the strata to be treated have no
removed, or until directed. The outlet hole shall then be structures in the vicinity. In the vicinity of structures the
capped and the other holes opened. The sequence shall pressure shall be 0.25 bar per meter depth. Uplift gages
be repeated until connections between all holes have been shall be installed and continuously monitored as grouting
established and all fine material removed. After washing, proceeds.
all holes shall be capped. 14 If the required grouting pressure is not attained using
8 Holes shall be water tested in stages or as the a sand-cement mix, grouting shall be suspended and the
Engineer may require. For stage testing, a twin packer hole washed. After several hours, grouting may proceed
and nozzle pipe system shall be used. Water testing again using the sand-cement mix until the desired
equipment shall be capable of ensuring steady pressures pressure is achieved. Should there be any grout leakage
and a delivery of water of 100 l/min at the required between two holes occurs, both holes shall be grouted
pressure. The equipment shall include all necessary tanks, concurrently or the initial hole grouted whilst the second
gauges and water meters. Water shall be pumped at the hole is capped. When injection is interrupted before it is
proposed grouting pressure into the hole to be tested and complete, the hole shall be washed using not less than
the flow measured for 5 or 10 minutes as directed. The 500 liters of clean water.
Contractor shall keep a record of the water flow expressed 15 After grout consumption has reached the limits
in l/min for each stage tested. Additional testing may be previously specified, the Engineer will require additional
required as the grouting operation proceeds. holes to be core drilled. The diameter of the retrieved
9 All grout mixes shall be prepared using high speed, grouted rock cores shall not be less than 50 mm. Three
high shearing action mixers to ensure uniform consistency. representative samples for each 3 m of core shall be taken
When storing mixed grout for short periods, prior to and unconfined compression tests shall be carried out on
pumping, only purpose made agitator tanks shall be used. each core sample. The mean strength of each group of
Where clay or bentonite are incorporated in the grout, cores shall not be less than 3 MN/sq.m. If this value is not
separate mixing tanks shall be provided in which the reached then additional grouting of the rock shall be
bentonite-water mix can be prepared and kept agitated performed until further tests indicate that the strength of
until required. grouted rock cores achieves 3 MN/sq.m. For every 8
10 Ram type pressure pumps shall be used for grouting. treatment holes or at the Engineer's discretion, at least
Precise control of pump pressure and delivery over the one hole shall be cored and the cores tested as outlined
whole range of pressures and volumes are required. above. In the core drilled hole the Engineer may require a
Valves shall be readily accessible for ease of maintenance. water test to be carried out.
All hoses and piping should be of small diameter to 16 Complete details of drilling, water testing and
ensure high velocity flow without segregation. Injection grouting operations including pressures, mixes and grout
may be carried out by either the single line or circulating takes, shall be recorded on daily progress sheets. A
system. Each borehole shall be provided with a short graphical record of such results shall be compiled and
standpipe threaded at its outer end to accept a manifold copies of all progress sheets and records shall be
with a pressure gauge, relief valve and valve enabling submitted promptly for approval.
delivery from the pump to be cut off from the hole.
Pressure gauges shall also be provided at pumps. 9.5.4 Method of Measurement
11 Once grouting has commenced, it shall be continued
1 Rock grouting shall be measured by the volume of
without interruption until completion. Grouting shall
grout used and the linear meter of rock drilling carried out
commence with a mix of 8:1 water: solids ratio. The mix
at the diameter required. Measurement shall be based on
shall be thickened progressively until pressure begins to
the actual quantities of grout material used and boreholes
build up. If pressure build up occurs too quickly, the mix
drilled, as approved by the Engineer. The rates shall be
may be thinned again. The final injection shall use a 1.5:1
deemed to include for water jetting of rock faces and
water: solids mix. If no pressure build up occurs with a
boreholes, and any other ancillary work.
1.5:1 mix, sand may be mixed with the grout, provided
that the sand: cement ratio does not exceed 2:1 by weight.
When the desired pumping pressure is achieved, with
extremely low grout flows, final injection shall take place
with a neat 1:1 water: solids mix

♦ 9-11 ♦
copy 249
9.5.5 Basis of Payment 7 Concrete shall be cured using water curing with wet
burlap for 7 days. Curing compound can be used in
1 The amount of completed and accepted work
urgent conditions only, to the approval of the Engineer.
measured as provided for above will be paid for at the unit
rate in the Bill of Quantities for ‘Rock Grouting’, which rate
9.6.4 Method of Measurement
shall be full compensation for drilling, pumping, testing,
and materials, labor, equipment, tools supplies and other 1 Reinforced concrete slope protection shall be measured
items necessary for the proper completion of the work. by cu.m. Measurement shall be based on the area and
thickness shown on the Drawings.
9.5.6 Items in the Bill of Quantities
9.6.5 Basis of Payment
i. Drillholes for grouting rock (dia) (lin.m)
ii. Rock grout (cu.m) 1 The amount of completed and accepted work
measured as provided for above will be paid for at the unit
9.6 Reinforced Concrete Slope rates indicated in the Bill of Quantities, which rate shall be
full compensation for slope preparation, excavation,
Protection backfilling, supply, mixing, testing, laying, finishing,
curing, protection of concrete, provision and fixing of
9.6.1 Description reinforcement, and for materials, transportation, hauling,
1 This Sub-section describes requirements for labor, equipment, tools, supplies and other items
construction of reinforced concrete slope protection. necessary for the proper completion of the works.

9.6.2 Materials 9.6.6 Items in the Bill of Quantities

9.6.2.1 Concrete i. Reinforced concrete slope protection (cu.m)

1 Concrete for reinforced concrete slope protection 9.7 Sacked Concrete Revetment
shall be Class 25 as specified in Sub-section 5.1 and
Clause 5.1.3. The slump limits shall comply with the
9.7.1 Description
requirements stipulated in Sub-section 5.7, Paragraph
5.7.2.7. 1 This Sub-section describes requirements for
construction of sacked concrete revetments at
9.6.2.2 Reinforcement embankment slopes, bridge abutments and similar
1 Reinforcement for reinforced concrete slope locations.
protection and elsewhere if required, shall conform to the
relevant requirements of Sub-section 5.2 - “Reinforcing 9.7.2 Materials
Steel ".
9.7.2.1 Sacks

9.6.3 Construction Requirements 1 Sacks for sacked concrete revetments shall be made
from burlap of minimum 200 gm per sq.m. . Sack
1 Reinforced concrete slope protection shall be
dimensions shall be approximately 0.6 m by 0.9 m
constructed at the locations shown on the Drawings.
measured when empty. Relatively clean reclaimed sacks
Placing, finishing and curing of concrete shall conform to
may be used if approved.
all relevant requirements of Section 5, except that only
hand finishing methods will be required.
9.7.2.2 Concrete
2 After the slopes have been properly trimmed and
prepared according to the Drawings, and before laying 1 Concrete for sacked concrete revetments shall be
concrete , the Contractor shall furnish screed rails or other Class 15 as specified in Sub-section 5.1.
grade-indicating devices to control the minimum depth of
concrete and uniformity of the top surface. 9.7.3 Construction Requirements
4 Reinforcing steel shall be cut and fixed in accordance 1 The sacks shall be filled with concrete loosely
with the requirements of Sub-section 5.2. (uncompacted) placed so as to leave room for tying and
5 Joints shall be laid out or referenced accurately. sewing. Approximately 0.035 cu.m. of concrete shall be
Construction joints shall be placed at designated placed in each sack. The sacks shall be closed by sewing,
contraction joints where possible. or at expansion joints if tied with strong twine. Immediately after closing, the
the construction joint falls within 5 m from a free edge or sacks shall be placed and trampled lightly to cause them
expansion joint. Joints for poured joint filler may be
formed in place or sawn in the fresh concrete.
6 Surface finish shall be either a uniform floated or
broomed finish, as directed by the Engineer..

♦ 9-12 ♦
copy 249
to conform to the earth surface and the adjacent sacks 2 Embankment slopes at bridge abutments and
already in place. elsewhere as shown on the Drawings shall be trimmed to
2 After the slopes have been properly prepared and proper line and grade. A blinding layer of Class 15
approved, the sacked concrete elements shall be placed. concrete, as specified in Sub-section 5.1, shall be placed
The sacks shall be laid in accordance with the details over the full area of surface to be paved, to a minimum
shown on the Drawings. All dirt and debris shall be depth of 50 mm. Precast tiles shall then be laid to the
removed from the top of the sacks before the next course lines and levels shown on the Drawings, on a bedding of
is laid. Sacks shall be placed so that the tied ends will not 20 mm thick, 1:3 cement: sand mortar and joints shall be
be adjacent to one another. Not more than 6 courses of properly aligned and finished, all as specified in Section 12.
sacks shall be placed in any tier until initial set in the first
course of any such tier has taken place. 9.8.4 Method of Measurement
3 Care shall be taken in placing and shaping the sacks 1 Paving tile slope protection shall be measured by
so that the minimum dimensions shown on the Drawings sq.m. of tiles, laid, including all necessary base course,
are obtained, and the finished sacked concrete revetment bedding, blinding and joint filling. Measurement shall be
has minimum voids. based on the dimensions shown on the Drawings.

9.7.4 Method of Measurement 9.8.5 Basis of Payment


1 Sacked concrete revetment shall be measured by 1 The amount of completed and accepted work
cu.m. of concrete filled sacks , installed. Measurement measured as provided for above will be paid for at the unit
shall be based on the dimensions shown on the Drawings. rates indicated in the Bill of Quantities, which rate shall be
full compensation for slope preparation, excavation,
9.7.5 Basis of Payment backfilling, and for materials, transportation, labor,
equipment, tools, supplies and other items necessary for
1 The amount of completed and accepted work
the proper completion of the works.
measured as provided for above will be paid for at the unit
rates indicated in the Bill of Quantities, which rate shall be
9.8.6 Items in the Bill of Quantities
full compensation for slope preparation, excavation,
backfilling, and for materials, transportation, labor, i. Paving Tile Slope Protection (sq.m)
equipment, tools, supplies and other items necessary for
the proper completion of the works. 9.9 Ditch Lining
9.7.6 Items in the Bill of Quantities 9.9.1 Description
i. Sacked concrete revetment (cu.m)
1 This Sub-section describes requirements for stone,
concrete and concrete paving slabs laid as linings to
9.8 Paving Tile Slope Protection ditches and water courses.

9.8.1 Description 9.9.2 Materials


1 This Sub-section describes requirements for paving 1 Paving slabs for channel and ditch lining shall be
tiles, laid as protection to embankments, bridge Class 25 concrete fabricated in accordance with the
abutments and similar locations. relevant requirements of Sub-section 5.1 and to the
dimensions shown on the Drawings.
9.8.2 Materials 2 Stone for ditch lining and wash checks shall be as
1 Precast paving tiles (slabs) used for slope protection specified for riprap in Sub-section 9.1.
shall be manufactured as specified in Section 12. 3 Grout for ditch lining and wash checks shall consist
2 Preformed joint filler shall conform to AASHTO M 33: of 1:3 cement:sand mortar, by volume.
"Preformed Expansion Joint Filler for Concrete". Hot- 4 In situ concrete for ditch lining and wash checks shall
poured joint filler shall conform to AASHTO M 282: "Joint be Class 25, as specified in Section 5.
Sealants, Hot Poured, Elastomeric Type, for Portland
Cement Concrete Pavements". 9.9.3 Construction Requirements

9.8.3 Construction Requirements 9.9.3.1 General

1 Embankment slopes where precast tiles are to be laid 1 Ditch and watercourse channel sides shall be
shall first be rolled. Close to any structures, to prevent trimmed to profiles as shown on the Drawings.
possible damage, a hand rammer shall be used; otherwise
use of a mechanical roller shall be permitted.

♦ 9-13 ♦
copy 249
9.9.3.2 Precast Slabs shall have a loss on abrasion value of no more than 40%
measured by AASHTO T 96.
1 Precast concrete slabs shall be laid to the lines and
levels shown on the Drawings, on a bedding of 20mm 2 Filter material particle size distribution shall be as
thick 1:3 cement:sand mortar. Joints shall be 10mm wide given in Table 9.10.2.1.
and filled with 1:3 cement:sand mortar. Joints shall be
AASHTO Sieve % passing (by mass)
cured by an approved method for at least 4 days.
50 mm 100
9.9.3.3 Stone Ditch Lining and Wash Checks
37.5 mm 95 - 100
1 Ditch lining and wash check stones shall be placed
with ends and sides abutting and the joints between each 19 mm 50 - 100
row breaking with the joints in the preceding row. The 9.5 mm 15 - 55
larger spaces between stones shall be filled with
4.75 mm 0 - 25
fragments. The stones shall be rammed and compacted.
2.36 mm 0 - 10
2 After the stone surface has been approved the spaces
between stones shall be completely filled with grout, 75 μm 0-5
brushed or broomed into the spaces. The grout shall be Table 9.10.2.1: Filter Material Gradation
cured as specified in Sub-section 9.1.
3 Filter membrane shall be a thermally bonded non-
9.9.4 Method of Measurement woven fabric produced from continuous filament synthetic
fibers. The hydraulic properties shall allow water passage
1 The approved ditch lining works shall be measured of 50-100 l per sq.m.per sec under a 100mm head. The
by the square meter of lining of paving slabs or wash pore size distribution shall be 50% not greater than 70 μm.
checks installed. Measurement of slabs or wash checks
4 The mechanical properties of the membrane fabric
shall be made perpendicular to the ditch centerline along
(that will have a minimum thickness of 1.0mm) shall be as
the top surface at the upstream edge of each wash check.
given in Table 9.10.2.2.
Blinding and bedding will not be separately measured, but
shall be deemed included with the rate for ditch lining. Allowable
Property Test Method
Value
9.9.5 Basis of Payment
Grab Strength 82Kg. ASTM D 4632
1 The amount of completed and accepted work
measured as provided for above will be paid for at the unit Seam Strength 73Kg. ASTM D 4632
rate for ‘Ditch Lining’ in the Bill of Quantities, which rate Puncture Strength 36Kg. ASTM D 751
shall be full compensation for slope preparation, laying, 2
Burst Strength 2N/mm ASTM D 3766
grouting, blinding, bedding, and for materials, labor,
equipment, tools, supplies and other items necessary for Trapezoid Tear 23 Kg. ASTM D 4533
the proper completion of the work.
Apparent Opening Size ASTM D 4571

9.9.6 Items in the Bill of Quantities 1. Soil with 50% or less


particles by mass <0.6mm
i. Paving slab protection and ditch
lining (type, thickness) (sq.m) passing 75 μm sieve
ii. Grouted stone ditch lining 2. Soil with more than
(type, thickness) (sq.m) <0.927mm
50% particles by
iii. Grouted stone wash checks
weight
(type, thickness) (sq.m)
passing 75 μm sieve KFabric>KSoil ASTM D 4491

9.10 Filter Layers Permeability, K 70% ASTM D 4355


Strength
Ultraviolet Degradation
9.10.1 Description at 150 hours
Retained

1 This Sub-section describes requirements for granular


Table 9.10.2.2: Fabric Filter Membrane Properties
filter material or filter membrane as an underlayer to loose
riprap or gabions.
9.10.3 Construction Requirements
9.10.2 Materials 9.10.3.1 Granular Filter
1 Granular filter material shall be a mixture of sand and 1 Sand and gravel filter material shall be spread evenly
hard, clean gravel or crushed rock. The coarser material on a prepared bedding avoiding segregation of particle
sizes. The layer shall be lightly compacted and finished to

♦ 9-14 ♦
copy 249
an even surface. Bedding and filter layer shall be of the plastic sheets bound together and attached to vertical or
thickness shown on the Drawings. horizontal supports, and presenting up to 50 percent
openings. Samples of the fencing material shall be
9.10.3.2 Fabric Membrane submitted to the Engineer for approval.
1 The surface to receive the fabric membrane shall be
9.11.2.2 Bituminous Materials
smooth and free from sharp projections. The membrane
shall be loosely laid with its long dimension parallel to the 1 Petroleum resin emulsion shall be 1 part petroleum
length of the protection work. Adjoining sheets of fabric resin emulsion diluted with 4 parts of water.
membrane shall be overlapped a minimum of 0.5m or 2 Asphalt emulsion: The proportion of water to dilute
15% of the sheet width, whichever is less. To prevent an asphalt emulsion shall be according to the
slippage of the fabric the areas of overlap shall be secured manufacturer’s recommendation for the type of asphalt
as recommended by the manufacturer and approved by emulsion to be used.
the Engineer.
3 The technical data sheet of the proposed emulsion
shall be submitted to the Engineer for approval.
9.10.4 Method of Measurement
9.11.2.3 Vegetative Materials
1 Granular filter layers shall be measured by the
square meter, of the thickness installed on the basis of the 1 Slow growing perennial shrubs shall be drought
area shown on the Drawings.. Rates are deemed to resistant and adapted to the climate and soil and shall be
include for preparation of the ground. as described in Section 16”
2 Fabric membrane filter that shall be measured by the 2 Long-lived trees shall be of species recommended in
square meter of net area laid, based on the dimensions “Planting list for proposed highway landscape”.
shown on the Drawings. Rates are deemed to include for
preparation of the ground and overlaps at joints. 9.11.2.4 Water

1 Water shall be clean and free of deleterious


9.10.5 Basis of Payment
substances.
1 The amount of completed and accepted work
9.11.2.5 Blanket Covers
measured as provided for above will be paid for at the unit
rate for ‘Filter Layers’ in the Bill of Quantities, which rate 1 Blanket covers shall be made of bituminous or
shall be full compensation for ground preparation, placing concrete pavements, prefabricated landing mats,
and fixing and for materials, labor, equipment, tools membranes, aggregate, and seashells, as shown on
supplies and other items necessary for the proper Drawings.
completion of the work.
9.11.3 Construction Requirements
9.10.6 Items in the Bill of Quantities
9.11.3.1 Fencing
i. Granular filter layer (thickness) (sq.m)
1 The fence bottom shall be installed about 30cm
ii. Fabric membrane. (sq.m)
above ground level
2 The entire windward surface of the dune shall be
9.11 Barriers for Sand Dunes stabilized with dust-control materials, such as bituminous
material (refer to Paragraph 9.11.2.2), prior to erecting the
9.11.1 Description first fence.
3 To maintain the effectiveness of the fencing system,
1 This Sub-section describes requirements for
a second fence shall be installed on the crest of the sand
construction of barriers for sand dunes, to protect against
accumulation.
wind erosion and adverse weather conditions, formed of
fences, bituminous blankets and vegetation generally as 4 Existing old fences shall not be removed during or
shown on the Drawings or as directed by the Engineer. after the addition of new fences.

2 The Engineer will determine the types and locations 5 The proper spacing and number of fences required to
of the protective barriers to be constructed in particular protect a specific area shall be determined by trial and
areas, based on trials and studies of the prevailing observation.
conditions. 6 Mock-ups of the proposed fencing system shall be
constructed to the Engineer’s satisfaction prior to final
9.11.2 Materials approval of the fencing system.

9.11.2.1 Fences

1 Fences shall be made of rolled prefabricated bundles


made of wood slats, slender poles, stalks or perforated

♦ 9-15 ♦
copy 249
equipment, tools supplies and other items necessary for
9.11.3.2 Stabilization with Bituminous Materials
the proper completion of the work.
1 Trial section shall be laid over an area of 25 square
meters, using approved bituminous material, at the 9.11.6 Items in the Bill of Quantities
specified rate below and to the satisfaction of the Engineer, i. Fences for dune stabilization
prior to commence the actual works.
(height, type). (lin.m)
2 Destroy the dune symmetry by spraying the
ii. Bituminous stabilization of dunes. (sq.m)
bituminous materials at either the center or the ends of
the dune. iii. Vegetative stabilization of dunes. (sq.m)

3 Spray the bituminous emulsion at the rate of 2.25 iv. Dune stabilization with blankets. (sq.m)
liters per meter square to obtain the desired stickiness of
the sand.
9.12 Mechanically Stabilized Earth
9.11.3.3 Stabilization with Vegetative Treatment Retaining Walls
1 The upwind boundaries of the vegetated area shall
be protected by fences or dikes, to prevent the engulfment 9.12.1 Description
of the vegetation.
9.12.1.1 General
2 Selected seed shall be spread as directed and
protected by mulch sprayed with a bituminous material. 1 This work shall consist of constructing retaining walls
using a proprietary system of precast concrete panels
3 Seed on slopes shall be anchored by mulch or restrained by tie-backs into a compacted earth fill, as
matting. approved by the Engineer. They shall be constructed in
accordance with the manufacturer’s drawings and
9.11.3.4 Blankets
specifications and be within the tolerances for lines,
1. After placement of blanket covers, a spray grades and dimensions shown in the Contract Documents
application of bituminous material shall be required to or as established by the Engineer. The wall shall consist of
prevent blanket decomposition and subsequent dust. a type of mechanically stabilized earth wall system
acceptable to the Engineer, and which must be
9.11.4 Method of Measurement constructed by a specialized firm having a minimum of
five years of documented successful experience in the
1 Fencing shall be measured by the linear meter
design and construction of such wall systems. The
installed.
Contractor shall provide a complete set of typical detailed
2 Stabilization with bituminous materials shall be
shop drawings and complete specifications of the
measured by the square meter of area sprayed.
proposed wall system for the approval of the Engineer 90
3 Stabilization with vegetative treatment shall be days prior to ordering materials to construct these walls.
measured by the square meter of area, installed (to the
approved frequency by the Engineer), watered, completed, 2 The design shall address the climate and soil
and accepted. All trials ordered by the Engineer prior to conditions existing in Oman and provide a minimum
the final vegetative treatment works shall not be paid design life of seventy-five years. The specification as
separately, but shall be deemed to be included in the rate presented to the Engineer shall also state any
for the approved final treatment works.
requirements for the thickness of reinforcing strips and/or
4 Stabilization with blankets shall be measured by the limitations on the backfill used in the structure to ensure
square meter of area, installed, using the specified the design life. The final thickness shall be subject to the
materials and to the dimensions shown on the Drawings, approval of the Engineer.
or ordered by the Engineer. All trials ordered by the
Engineer prior to the installation of the final blanket works 3 The term “reinforced soil wall” shall be deemed to
shall not be paid separately, but shall be deemed to be have the same meaning as “mechanically stabilized earth
included in the rate for the approved final blanket works. retaining walls”.

9.11.5 Basis of Payment 4 The works shall include the following:


1 The amount of completed and accepted work i. Reinforced Earth components (panels, high
measured as provided for above will be paid for at the unit adherence galvanized steel strips, connection
rate for ‘Barriers for Sand Dunes’’ in the Bill of Quantities, and joint materials)
which rate shall be full compensation for ground ii. Selected backfill
preparation, placing and fixing and for materials, labor, iii. Pre-casting panels
iv. Leveling pads

♦ 9-16 ♦
copy 249
v. Wall erection 2 Materials and construction of reinforced earth
vi. Monitoring components shall comply with Section 5 of these
Specifications.
5 Only materials supplied by accredited sub-contractor
or supplier shall be used as Reinforced Earth Components. 9.12.2.2 Concrete Face Panels

6 The Contractor shall submit for prior approval a 1 Concrete shall be Class 30 in accordance with Section
detailed Method Statement that describes all means, 5 of these Specifications, except as specified herein.
method and techniques to be adopted for construction
and installation of the “mechanically stabilized earth 2 All appurtenances and lifting and handling devices
retaining walls”. The Method Statement shall include shall be set in place to the dimensions and tolerances
details of equipment to be used, method of installation of shown on the approved shop drawings prior to casting.
each reinforced earth component taking into consideration
the manufacturer’s recommendations, backfill materials to i. Reinforcing steel shall comply with Sub-
be used backside of wall, testing and reporting, work Section 5.2 of the Specifications.
program and any other information required by the ii. Concrete Finish – The concrete surface
Engineer. pattern and finish for the exposed faces
shall conform to Section 5 of the
9.12.1.2 Standards and Codes Specifications. The rear face of the panel
shall be roughly screeded to eliminate
1 The following standards and codes in their latest surface distortions in excess of 6.5 mm. The
edition shall be particularly applied to works covered color and texture of the finish shall be
by this Specification. approved by the Engineer based on three
trial panels provided by the Contractor prior
i. A 36M (AASHTO M183) - Structural Steel to producing the final panels.
ii. A 123M - Zinc (Hot Galvanized) Coating on iii. Tolerances – All units shall be
Products Fabricated from Rolled, Pressed manufactured within the following
and Forged Steel Shapes, Plates Bars and tolerances:
Strips a- All dimensions within +5 mm.
iii. A 153M - Zinc Coating (Hot Dip) on Iron and b- Angular distortion with regard to the
height of the panel shall not exceed 7
Steel Hardware
mm in 2 m.
iv. A 325 - High Strength Bolts for Structural
iv. Compressive Strength – Acceptance of the
Steel Joints Including Suitable Nuts and
concrete face panels with respect to
Plain Hardened Washers
compressive strength will be determined in
v. A 1011M - Standard Specification for Steel,
accordance with Section 5 of the
Sheet and Strip, Hot-Rolled, Carbon,
Specifications, except that a minimum of
Structural, High-Strength Low-Alloy and one set of test cubes shall be taken from
High-Strength Low-Alloy with Improved each lot of 50 panels or part thereof.
Formability v. Additional Compressive Tests: An
vi. A 615 - Deformed and Plain Billet-Steel Bars additional 4 specimens shall be field-cured
for Concrete Reinforcement in the same manner as the concrete facing
vii. D 1752 - Preformed Sponge Rubber and panels. Compression tests on these
Cork Expansion Joint Fillers for Concrete specimens shall be used to determine the
Paving and Structural Construction length of curing time required and
viii. AASHTO T90 - Determining the Plastic Limit acceptability. Panels will be accepted after
and Plasticity Index of Soils 7 days, provided the compressive strength
of field-cured cylinders exceeds 65% of the
required 28-day strength. Panels with
9.12.2 Materials defects that indicate imperfect molding,
honeycombing, or open texture concrete, or
9.12.2.1 General that do not correspond with the quality of
the approved test panel will be rejected.
1 The Contractor shall make his own arrangements to vi. Rejection – Units shall be subject to
provide the face panels, reinforcing and tie strips, rejection by the Engineer if not in
fasteners, joint filler, and all necessary attachments as conformance with these Specifications or if
recommended by the Manufacturer and approved by the any of the following defects are evident by
Engineer. visual inspection:
a- Defects that indicate imperfect
moulding.

♦ 9-17 ♦
copy 249
b- Defects indicating honeycombed or carefully inspected to ensure they are true to size and free
open texture concrete. from defects that may impair their strength and durability.
vii. Marking – The date of manufacture shall be 4 The Contractor shall furnish the Engineer with a
clearly scribed on the rear face of each Certificate of Compliance certifying that these materials
panel. comply with the applicable Specifications.
viii. Handling, Storage and Shipping – All units
5 Physical and Mechanical Properties: Reinforcing
shall be handled, stored and shipped in
strips and tie strips shall have a minimum yield point of
such manner as to eliminate the danger of
2,400 kg/sq.cm (235 MN/sq.m); minimum tensile strength
chipping, cracks, fractures and excessive
of 3,700 - 4,500 kg/sq.cm (363-441 MN/sq.m); 0.06%
bending stresses. Panels in storage shall be
maximum phosphorus; and 0.05% maximum sulfur. The
supported on firm blocking located
weight of zinc coating shall be not less than 500 gm/sq.m.
immediately adjacent to tie strips or toggles
to avoid damage to these tie strips and 9.12.2.5 Reinforced (Polymer) Grids
toggles. Any panels, including fastening
hardware, damaged during handling, 1 General: Shapes and dimensions of these elements
storage, or shipping shall be rejected by the shall conform to the dimensions and tolerances shown on
Engineer. the Drawings.
ix. Joint spacing and details for expansion,
contraction, construction and control joints 2 Grid reinforcing elements shall be manufactured by
in the coping and the concrete barrier stretching a punched polyethylene sheet in one direction
parapet shall be as recommended by the under controlled conditions to produce a high tensile
manufacturer and as approved by the
strength orientated structure.
Engineer.
x. Test Panels: The Contractor shall construct 3 Mechanical Properties: The grid shall have a short
and submit at least 3 test panels. The
term strength of not less than 79 kN/m width, determined
materials, including formwork, used in
from tensile testing at 20 degrees Celsius under a constant
construction of all test panels shall be as for
rate of extension of 50 mm/minute. For each batch of
those proposed for use in the Works. The
reinforcing material delivered to Site, or at such other
test panel finish shall be approved by the
times as may be required by the Engineer, the Contractor
Engineer prior to production of any panels
shall submit a test certificate from an approved
for incorporation in the Works. The rear
face of each panel shall have a dense, independent testing laboratory confirming that the
rough texture without honeycombed areas. required strength characteristics have been met. The
The approved panels shall remain available 120 year characteristic strength shall be not less than
on Site throughout the duration of the 29 kN/m width.
Contract, as a standard for judging the
completed works. 4 Physical Properties: The weight of grid shall not be
less than 0.85 kg/sq.m. It shall be immune to attack from
9.12.2.3 Concrete Footings ultra-violet light for a minimum period of 3 years and shall
be immune to attack from all chemicals naturally found in
1 The class of concrete shall be as shown on the soils and to biological attack from micro-organisms. The
approved shop drawings and shall conform to Section 5 of Contractor shall furnish the Engineer with the
these Specifications. manufacturer's warranty to this effect. The minimum roll
width shall be 1 m. Methods of joining reinforcing
9.12.2.4 Steel Reinforcing and Tie Strips
material shall be approved and in accordance with the
1 Tie strips shall be shop fabricated of hot rolled steel manufacturer's instructions.
conforming to the minimum requirements of ASTM A-
1101M, Grade 36 or equivalent. Reinforcing strips shall be 5 Upon manufacture, the reinforcing elements shall be
hot rolled steel and shall conform to the requirements of placed in approved wrapping material which shall prevent
ASTM A-36M or equivalent. The tie strips and reinforcing ultra-violet light from reaching the reinforcing elements.
strips shall be hot dip galvanized conforming to the The reinforcing elements shall be identified with their date
requirements of ASTM A-123M. of manufacture. Upon delivery to Site the Contractor shall
2 The properties of the backfill material to be used provide the Engineer with copies of the manufacturer's
shall be one of the main factors in determining the strip certificates clearly stating the dates of manufacture of the
thickness required to meet the specified design life. reinforcing elements. No reinforcing elements shall be
3 Prior to galvanizing, the tie strips and reinforcing incorporated into the Works if at the time of proposed
strips shall be cut to length and tolerances shown on the incorporation the elements are more than three years old.
plans and the holes for bolts shall be punched in the
locations shown. All reinforcing and tie strips shall be

♦ 9-18 ♦
copy 249
9.12.2.6 Fasteners Sieve Size % Passing
250 mm 100
1 Fasteners: Bolts and nuts shall have hexagonal heads
100 mm 75-100
and conform to AASHTO M 164, Type 2, except as
0.075 mm 0-15
modified hereunder. Bolts shall be 12 mm in diameter,
30 mm in length with 20 mm of thread length. Fasteners
ii. The Contractor may request that the
shall be hot dip galvanized to AASHTO M 232, Class C. acceptance limits be increased for material
Bolts shall have a minimum yield point of 6,400 kg/sq.cm not meeting the requirement for % passing
(627 MN/sq.m); minimum tensile strength of a 0.075 mm sieve provided an analysis is
8,000 kg/sq.cm (784 MN/sq.m); and minimum elongation submitted, showing that the material
of 12%. passing the 0.075 mm sieve is less than
10% smaller than 0.015 mm, or
9.12.2.7 Non Metallic Friction Ties and Fixings
alternatively that the material is less than
20% smaller than 0.015 mm and the angle
1 The stabilized earth wall structure shall be reinforced
of internal friction as determined by ASTM
with friction strips of polyethylene coated polyester fiber
D 2850 is 25 degrees minimum.
strips or similar material approved by the Engineer. The
iii. Materials shall have a minimum resistivity
reinforcing strips shall have the ultimate strength
when measured in accordance with
indicated on the Drawings, and manufacturer’s test ASTM G 57 of 5,000 ohm-cm.
certificates shall be provided to verify this. iv. Materials having a resistivity less than the
above but greater than 1,000 ohm-cm may
2 Reinforcing strips shall be fixed to the facing panels be acceptable provided that the pH value of
using plastic coated steel anchor loops and toggles, unless the material measured in water extracted
otherwise noted on the approved shop drawings and in from a water-soil mixture is between 5 and
accordance with approved samples. The Contractor shall 10 when tested in accordance with
furnish the Engineer with a Certificate of Compliance ASTM G 51, and that the water extracted
certifying that these materials comply with the applicable from the water-soil mixture has a chloride
Specifications. content of less than 200 ppm and a
sulphates content of less than 1,000 ppm
9.12.2.8 Joint Filler (For Use with Concrete Face Panels)
when tested in accordance with AASHTO T
1 Filler for vertical joints between panels shall be 26.
flexible open cell polyethylene foam strips, unless v. The total sulphide content of the fill shall be
otherwise noted on the approved shop drawings. less than 0.3 gm/kg.
vi. Organic matter content, (difference
2 Filler for horizontal joints between panels shall be between total carbon content and mineral
resin bonded cork filler conforming to ASTM D 1752 (Type carbon content) shall not be greater than
II) unless otherwise noted on the approved drawings. 100 ppm.
vii. If required by the Engineer, the Contractor
9.12.2.9 Joint Filler (For Use with Concrete Face Panels)
shall carry out a test for Biochemical
1 Reinforced Earth selected backfill material can be Oxygen Demand (BOD). The BOD value
either natural soil or material of industrial origin. Backfill shall not exceed 0.004 gm/liter.
shall not contain chalk, unburnt colliery shale, pulverized
full ash, material from swamps, marshes or bogs, organic 4 Backfill for Reinforcing Polymer Grid System
or other materials which, in the opinion of the Engineer,
would result in the structure becoming unfit for its i. Frictional Fill: This material shall contain a
intended use. Prior to placing the granular fill, the maximum of 10% passing the 0.075 mm
Contractor shall certify to the Engineer that the material (No.200) sieve.
conform to the requirements as per specifications and ii. Gradation Requirements: Backfill material
drawings. shall conform to the following gradations:
Sieve Size %(byweight Passing
2 Selected Filter Material for Drainage Layers: Filter
backfill material shall conform to the relevant 125 mm 100
requirements of Section 2. 90 mm 85-100

3 Backfill for Steel Reinforcing Strip System 9.5 mm 25-100


0.600 mm 10-65
i. The selected fill shall conform to the
0.075 mm 0-10
following gradation and shall have a
coefficient of uniformity not less than 2
(Cu=D60/D10 2) :

♦ 9-19 ♦
copy 249
9.12.3 Construction Requirements 3 Backfill shall be placed in accordance with Section 2
of these Specifications and compacted in accordance with
9.12.3.1 Wall Excavation
the requirements shown below and on the Drawings. The
1 Structure excavation shall be in accordance with the maximum lift thickness shall not exceed 250 mm (before
requirements of Section 2. Limits and construction stages compaction) and shall closely follow panel erection. The
shall be as shown on the Drawings. Contractor shall decrease this lift thickness if necessary to
obtain the specified density.
9.12.3.2 Foundation Preparation
4 At the end of each day’s operations, the Contractor
1 The foundation for the structure shall be graded level shall shape the last level of backfill so as to permit run-off
for a width equal to or exceeding the length of reinforcing of rainwater away from the wall face.
material or as shown on the plans. Prior to wall
construction, except where constructed on rock, the 5 Backfill outside roadway embankment areas shall be
foundation shall be compacted with a smooth wheel compacted to at least 90% AASHTO T 180 maximum
vibratory roller. density. Backfill within roadway embankment areas shall
be compacted to 95% AASHTO T 180 maximum density
2 Any foundation soils found to be unsuitable shall be except for backfill in sub-grade zones which shall be
removed and replaced in accordance with the procedures compacted to 100% AASHTO T 180 maximum density.
in Section 2.
6 The acceptance criteria for control of compaction
3 When concrete face panels are specified, at each shall be given by first the equivalent Relative Density as
panel foundation level a concrete leveling footing shall be determined by ASTM D-2049. Then by large-scale plate
provided as shown on the plans. The footing shall be bearing test, which defines the type of the equipment,
cured a minimum of 24 hours before placement of wall energy, lift thickness, etc ... before beginning compaction,
panels. it is necessary to check that the moisture of the backfill
material is the optimum (± 1.5%) value of modified
9.12.3.3 Erection of Concrete Face Panels
AASHTO standard.
1 Precast concrete panels shall be aligned vertically
using inserts cast into the top edge of panels. Panels shall 7 The compaction shall be carried out in such a way as
be placed in successive horizontal lifts in the sequence to obtain a uniform density, rollers shall move to and from,
shown on the approved plans as backfill placement always parallel to the wall and assuring that the
proceeds. As fill material is placed behind a panel, the overlapping between one run and the next shall not be
panels shall be maintained in vertical position by means of less than 10% of the roller width. Backfill compaction shall
clamps placed at the junction of adjacent panels and be accomplished without disturbance or distortion of
temporary wooden wedges placed in the horizontal or reinforcements and panels. Compaction in a strip one
vertical joint at the junction of the two adjacent panels on meter wide adjacent to the backside of the wall shall be
the external side of the wall. External bracing may also be achieved using an approved manually operated vibrating
required for the initial lift. Vertical tolerances (plumbness) compactor.
and horizontal alignment tolerances shall not exceed 25
8 If a reinforcing polymer grid and connections are
mm when measured along a three meter straight edge.
used, they shall be handled and installed in accordance
The maximum allowable offset in any panel joint shall be
with the manufacturer's instructions and
25 mm. The overall vertical tolerance of the wall
recommendations, copies of which shall be submitted to
(plumbness from top to bottom) shall not exceed 25 mm
the Engineer before commencement of these Works. The
per three meter of wall height.
reinforcing grid shall not contain any cuts, kinks, twists,
9.12.3.4 Backfill Placement blisters or other defects which, in the opinion of the
Engineer, would render it unsuitable for its intended use.
1 Backfill placement shall closely follow the erection of
each lift of panels. The filling material will be graded and 9.12.3.5 Trial Embankment
compacted before the placement of a new layer. The
1 If shown on the Drawings, or if required by the
gradation of the selected granular backfill should be tested
Engineer, a trial embankment shall be constructed prior to
periodically during construction to assure compliance with
start filling. The Contractor shall perform a full scale trial
specifications. This gradation testing should be performed,
compaction test.
at least once for every 500 cubic meter of material placed
and/or whenever the appearance or behavior of the 2 The allocation of the testing area, the system for the
material changes noticeably. Material shall be laid with execution of the embankment and the testing program
layers of uniform thickness, taking care to avoid shall be fixed by the Engineer considering the following:
segregation and water content variations.
i. The equipment shall be the same to be
2 As shown on the shop drawings, reinforcements used during all the construction.
shall be placed normal to the face of the wall.

♦ 9-20 ♦
copy 249
ii. The trial area shall be leveled and 4 Foundation settlements shall be monitored using
compacted, at approved locations or at steel bars fixed on concrete at a distance of 1-2 meters
locations adjacent to the Site. from the wall facing. The vertical steel bar is to be
protected by means of pipes. Measurements shall be
3 The Engineer shall approve the materials and
taken from the top of the steel bars.
procedures on the basis of the trial results.
9.12.4.4 Horizontal Displacements
9.12.4 Monitoring
1 Possible horizontal displacements will be measured
9.12.4.1 General
within the foundation soil and on the wall surface.
1 The scope of the required monitoring is related to Inclinometers shall be placed in similar locations to the
verifying and certifying the compliance of the work with settlements devices. They shall be installed within the
the design assumptions and construction procedures. In solid bedrock. The measurements shall be frequent and
the meantime, some monitoring is devoted to guide the related to the construction program. Possible horizontal
construction phases of the embankment in order to displacements can easily be checked by a pendulum
minimize the effect of settlements. Those aspects will (plumb bob).
control the following:
9.12.4.5 Durability
i. Selected backfill
1 These investigations are only related to reinforcing
ii. Settlements
strips and are generally carried out at the time of the
iii. Horizontal displacements and overall
regular detailed inspections of the structure, with a
stability
frequency of approximately 10 to 15 years. It may also be
iv. Material durability
opportune to make such investigations if the structure has
9.12.4.2 Selected Backfill serious anomalies, the origin of which is likely to be
sought in the mechanical failure of the strips.
1 Each layer must be subjected to control tests and
meet the requirements before placement of the following 2 The investigation method may vary according to
layer. whether the structure is or is not equipped with durability
test samples. This monitoring and investigation is
2 The testing frequency, as specified, must be performed with special techniques and investigation
considered as a minimum and must be increased method. In order to collect reliable and complete
whenever the appearance and/or behavior of the material information in long term, it is vital that these operations
noticeably changes, be entrusted to a qualified specialist laboratory.

3 The location of testing and/or sampling will be 3 At every investigation, a certain number of test
determined by the Engineer, Test certificates in proper samples are extracted and the backfill sample is taken in
forms shall be promptly sent to the Engineer during the the vicinity of these test samples. Durability test samples
construction, are samples of reinforcing strips of 60 cm long, of the
same type as those used in the structure. They are placed
4 As indicated in the following table, the frequency of
3 in the backfill of the Reinforced Earth mass during the
the testing can be reduced after 5000 m . However, this
construction and can be extracted for the monitoring of
can be done only when the gradation and physical
corrosion phenomena.
properties of the material becomes practically constant.
4 As a general rule, durability test samples are located
9.12.4.3 Settlements
either at the lower part of the structure or, if the latter is at
1 Survey of settlements will be done during the considerable height, at each change in the section of the
construction, particularly where the embankments lay on strips.
compressive soils intending to settle. Settlements shall be
5 At every investigation, one indicator is extracted
monitored by means of two different procedures:
from each zone in which test samples are located. In case
i. Topographic measurements on the wall of abnormal corrosion development, complementary
face investigations must be made; excavations must be opened
ii. Vertical settlements on the foundation for examining the first beds of reinforcements.

2 Topographic measurements will be performed with 9.12.4.6 Testing Frequency


leveling instruments and reference points installed on the
Testing shall be as follows in Table 9.12.4.1:
wall face and with benchmarks located in stable areas.

3 An appropriate quantity of fixed reference points


(steel plates) shall be installed on the panels every 7.5
meters elevation within each selected cross-section, For
those measurements, a tolerance of ± 2 mm is required.

♦ 9-21 ♦
copy 249
ii. Standard Coping on MSERW (lin.m)
TEST Within first After first iii. Conc. Barrier Parapet on MSERW (lin.m)
3 3
5000 m 5000 m
Grain Size 500 5000 9.13 Coastal Protection
Resistivity 500 5000
9.13.1 Description
pH 500 5000
1 Quarried stone shall consist of natural rock imported
Soluble Salt Content 500 5000
to site from approved quarry sites complying with the
In-situ Density 500 5000 requirements of this section.
Plate Bearing 250 1000 2 Quarry run shall consist of natural rock fragments
Water Content 1000 5000 and complying with the requirements of this section.

Table 9.12.4.1 – Testing Requirements 3 Armour rock shall be the quarried stone placed in the
top or outer layer(s) of the structure exposed to sea
9.12.5 Method of Measurement conditions.

4 Underlayer shall be the quarried stone placed under


1 Mechanically Stabilized Earth Retaining Walls,
the armour rock layer(s)
including concrete face panels and footings shall be
measured by the sq.m of net area of as shown on the 5 Core means the quarry run material forming the bulk
Drawings. portion of the slope and erosion protection fill sections
protected by underlayers and/or armour rock.
2 Vertical limits of each wall for measurement
6 Filter fabric (geotextile) shall be a membrane placed
purposes shall be between the top of the foundation on
between the underlayer and the seabed soil or the core
the outer face (low side) of the stabilized earth wall and
stone that shall allow passage of water while retaining of
the top of the proposed grade at the backside (high side)
seabed soil or core stone in place without clogging.
of such walls. Horizontal limits for measurement purposes
shall be from end of wall to abutment or from end to end 7 The Contractor shall submit for the Engineer’s
of walls. approval a Quality Control Manual for the proposed slope
and erosion protection construction.
3 Standard coping, including concrete, reinforcement,
joint filler, incidentals and erection shall be measured by 8 The Contractor shall submit the following method
linear meter, complete and in place. statements for the Engineer’s approval at least 45 days
prior to the commencement of work on site:
4 Concrete barrier parapet (on stabilized earth walls),
including concrete, reinforcement, fasteners, joint filler i. Method for preparation of seabed as the base.
and incidentals and erection shall be measured by linear ii. Method for placement of core material,
meter of concrete barrier, complete and in place. underlayers and rock armour protection.
iii. Method for surveying procedures to establish
9.12.6 Basis of Payment lines and levels of the various slope and erosion
protection components.
1 The amount of completed and accepted work
iv. Method of quarry selection and armour stone
measured as provided for above will be paid for at the unit
production.
rate for ‘Mechanically Stabilized earth Retaining Walls’ in
the Bill of Quantities, which rate shall be full
compensation for ground preparation, placing and fixing 9 The Contractor shall submit the following test reports
of reinforcement, fasteners, joint filler, material testing directly to Engineer from approved testing services:
and certificates, trial embankment, excavation, backfill,
compaction, waterproofing, integral incidentals (such as i. grading size of material
light pole foundations, sign structure foundations, ii. aspect ratio of material
drainage structures and appurtenances), erection, and for iii. apparent oven dry density of quarried stone
materials, transportation, hauling, labor, equipment, tools, iv. Los Angeles abrasion
supplies and other items necessary for the proper v. water absorption
completion of the work. vi. sodium sulphate soundness
vii. unconfined compressive strength
9.12.7 Items in the Bill of Quantities viii. methylene blue absorption

i. Mechanically Stabilised Earth


Retaining Walls (MSERW) (sq.m)

♦ 9-22 ♦
copy 249
10 The Contractor shall submit detailed design drawings, 7 Sodium sulphate soundness carried out in
plans, longitudinal profiles and cross-sections across the accordance with BS 812: Part 121 using the 63-125mm
slope and erosion protection at 50m intervals and at crushed rock and a 50mm sieve to determine losses shall
transition zones between the different design sections. be less than 12%.
The drawings shall be based on the up-dated survey
8 The average point load index Is (50) in the planar
carried out at the slope and erosion protection area.
direction of the most pronounced layering, should any
11 The Contractor shall submit bathymetric charts at the visible anisotropy exist, and for sampling testing and
slope and erosion protection at suitable scales of 1:1000 reporting in accordance with ISRM 1986 recommended
and 1:500 including ACAD computer file diskettes in the method, shall be not less than 4.0 MPa with the average
form of point No., x, y, z. minus the standard deviation of the point load index at
least 3.0 MPa; where at least ten valid test results obtained
12 The work shall be performed in accordance with:
from pieces originating from ten randomly selected stones
i. The requirements of the Authorities have been used to calculate the average and standard
ii. BS 6349, BS 812 and ASTM D 1557. deviation.
iii. Recommendations of Construction Industry
9 Methylene blue absorption tests shall be carried out
Research and Information Association (CIRIA)
in accordance with CIRIA SP 83, Appendix 2, in order to
Special Publication No.83 (SP 83).
indicate the presence of deleterious clay minerals, the
13 The Contractor shall employ and pay for a competent results of this test shall not exceed 1.0g/100g.
independent geotechnical testing laboratory with proven
10 The contractor shall carry out for each quarry the
track records to perform testing on rock material to be
three sets of tests as listed in the relevant Clauses above.
placed in the core, underlayers and armour layers of the
The contractor shall submit the results for the Engineer's
structure.
approval of the source of quarried stone for underlayers
and armour layers.
9.13.2 Materials
11 The contractor shall carry out at least three sets of
9.13.2.1 Quarried Stone for Armour Layers and the tests listed in the above Clauses on each consignment
Underlayers of quarried stone for under-layers and armour layers
1 The Contractor shall use armour and underlayer imported to site. A higher frequency of testing may be
stones consisting of quarried rock, dense, sound, fresh, required as instructed by the Engineer, if this, in the
strong, free from weathering, mechanical weaknesses or opinion of the Engineer, is deemed necessary.
chemical decomposition. The stones shall not be liable to 12 Materials failing to comply with any of the
decomposition under the action of sea water. They shall requirements listed above shall not be used in the Works
also be free from any visible defects such as joints, and shall be considered not in compliance with this
discontinuities, fractures, clay seams or bands and water specifications.
soluble material.
9.13.2.2 Core Material
2 The contractor shall use rock materials in armour
layers and underlayers conforming to the classes defined 1 The contractor shall use core material consisting of
by the engineer well graded quarry run complying with the gradation
defined by the engineer.
3 The contractor shall use quarry stone containing no
more than 5% of stones with a length to thickness (l/d) 2 The used fill material shall be quarry run material
ratio greater than 3, where the length (1), is defined as the with percentage of fines (passing sieve 0.075mm) shall not
greatest distance between two points on the stone and the be more than 20%.
thickness,(d), as the minimum distance between two
3 The contractor shall use selected quarry run with
parallel straight lines through which the stone can just
material percentage lighter than 1.0 kg (80mm of
pass. Carry out the test in accordance with CIRIA SP 83,
equivalent diameter) not exceeding 10% and complying
Appendix 2.
with the size gradation defined by the engineer.
4 The contractor shall use quarry stone for armour and
4 The contractor shall use quarry run material
underlayers for testing having a minimum apparent oven
3 complying with the following requirements:
dry density of 2560 kg/m with 90% of the stones having a
density of at least 2600 kg/m3 in accordance with CIRIA SP i. Apparent oven dry density > 2.3 t/m3
83. ii. Water Absorption < 3.0 %
iii. Sodium Sulphate Soundness < 12.0 %
5 The loss of material using the Los Angeles Abrasion
iv. Los Angeles Abrasion < 35.0 %
test in accordance with ASTM C-131 shall not exceed 35%.

6 The water absorption of quarry stone, carried out in


accordance with BS 812: Part 2 shall be less than 3%.

♦ 9-23 ♦
copy 249
v. Methylene blue absorption < 1.0g/100g 9.13.3 Construction Requirements
5 The contractor shall carry out for each quarry three 9.13.3.1 General
sets of the tests as listed in the above Clauses. The
1 The contractor shall carry out sounding of the seabed
selection of the quarry source will be based on the results
at the slope and erosion protection site in order to
submitted and subject to Engineer's approval.
produce a detailed seabed profile using echo sounder or
6 During construction, the contractor shall take side-scan sonar together with a surface-towed sub-bottom
sufficient sample for every 5000 t of material produced or or similar seismic profiler and a tide gauge and collecting
production for a working day whichever is greater. Three seabed samples. Obtain approval of the Engineer on the
sets of the tests as listed in the above Clauses shall be results of soundings and bathymetry as well as seabed
carried out and submitted to the Engineer. A higher samples before the works commence, and finally
frequency of testing may be required as instructed by the incorporate the same in the drawings.
Engineer, if this, in the opinion of the Engineer, is deemed
2 Seabed clearances: Remove prior to commencing
necessary.
filling works, all unsuitable material, wrecks, floating
7 Materials failing to comply with any of the debris, silt, clay, loose sand and loose material over the
requirements listed above shall not be used in the Works whole area of the slope and erosion protection. Dispose of
and shall be considered not in compliance with this unsuitable material as directed by the Engineer.
specification.
3 The contractor shall remove, in accordance with the
9.13.2.3 Filter Fabric - Geotextiles instructions of the Engineer any silt, loose sand or clay
that exists in the top layers of the seabed. Remove any silt,
1 The work shall consist of furnishing and placing a
loose sand and clay layers to the levels and areas as
geotextile. The geotextile is designed to allow passage of
instructed by Engineer.
water while retaining seabed soil without clogging. The
suitability of used geotextile should be checked against 4 The contractor shall relocate or redirect, at his own
these functional requirements before laying taking into expense, all underwater services, installations etc. that
consideration the seabed soil conditions. may lie in the area to receive rockfilling. He shall carry out
all such redirection or relocation in accordance with
2 Non-woven TERRAM 4000 or equivalent material can
requirements of the relevant local authorities.
be used with the following properties:
2 5 The contractor shall ensure that the founding bed for
i. Weight : 350 g/m
2 slope and erosion protection is natural seabed material
ii. Tensile strength : 23 kN/ m
when working in the sea, consisting of sand, a mixture of
iii. O85 (diameter of holes in a fabric): a suitable
sand and gravel or rock. No filling on silt, loose sand or
hole diameter to prevent the wash out of seabed
clay layers shall be allowed.
and core material ant to retain them in place
without clogging. 6 The contractor shall make his own arrangements for
the supply and transport of slope and erosion protection
3 The contractor shall provide evidence of the
material either by land or sea or both and use appropriate
resistance to deterioration of the geotextiles from
marine and/or land operated plants for filling.
exposure to ultraviolet light and seawater.
7 The contractor shall protect all placed material from
4 The contractor shall carry out sampling of geotextiles
erosion by the action of sea during construction. The
for testing in accordance with sampling procedures
Contractor shall be held responsible for all loss of material
indicated in ASTM - D4354-99.
and displacements that may arise, and shall make good
5 The contractor shall carry out for geotextiles three such losses and displacements at his own expense.
sets of tests to certify the required properties and submit Furthermore, the Contractor shall be responsible for any
the results for the approval of the Engineer. obstruction that may be caused by the deposition of any
material washed out from the filling and remove the same
6 The contractor shall carry out at least three sets of in accordance to the instructions of the Engineer.
tests to verify the required properties on each
consignment of geotextile imported in the site. A higher 8 The contractor shall take all the necessary
frequency of testing may be required as instructed by the precautions to protect the environment and any damage
Engineer, if this, in the opinion of the Engineer is deemed to the environment arise from the Works shall be the
necessary. Contractor's responsibility.

7 Materials failing to comply with any of the 9.13.3.2 Placement of Core Material
requirements listed above shall not be used in the works 1 The contractor shall place materials used to form the
and shall be considered not in compliance with these core to the profiles and levels shown on the Drawings with
specifications. a tolerance of zero above the theoretical level.

♦ 9-24 ♦
copy 249
2 The contractor shall take measurement of each
material profile as placed before any subsequent layer of All Armour
Design
material is placed to ensure compliance with the specified Depth of Placing Layers and
Profile to
tolerances. Below Low Water Individual
Actual Mean
3 The contractor shall carry out placement of core Level Measurements
Profile(m)
material underwater in such a manner to minimize (m)
segregation of material and to ensure its proper mixing.
The placement methods are subject to Engineer's Dry: above water + 0.35 Dn 50
approval. ± 0.3 Dn 50
level - 0.25 Dn 50
4 The contractor shall place core material 0.75m above
mean sea level and higher in layers not more than 1.0m in + 0.6 Dn 50
loose depth and compact as specified. Less than 5m ± 0.5 Dn 50
5 Before compaction, the contractor shall moisten each - 0.4 Dn 50
layer as necessary. He shall compact each layer with the
More than 5m ± 0.5 Dn 50 ± 1.0m
minimum number of roller passes as agreed with the
Engineer. Where, Dn50 is the diameter of a placement with
6 The contractor shall carry out compaction by heavy equivalent volume to the block with median weight.
vibratory compactor not less than 12 t capacity.
Table 9.13.3.1: Vertical Placing Tolerances
9.13.3.3 Placement of Armour and Underlayer Stones
5 The tolerance on two consecutive mean actual
1 For placing above high low water level, the
profiles shall not be negative. Notwithstanding any
contractor shall place the stone to grade and in such a
accumulation of positive tolerances on underlying layers,
manner to ensure that the larger rock fragments are
the thickness of the layer shall not be less than 80% of the
uniformly distributed and the smaller rock fragments fill
nominal thickness when calculated using mean actual
the spaces between the larger fragments to achieve a well
profiles
keyed, densely packed structure of the specified
dimensions. Hand placing or barring will be required only 9.13.3.4 Surveying Technique
to the extent necessary to secure the results specified.
1 The contractor shall carry out survey measurements
2 The contractor shall not drop or tip into position
using a probe with a spherical end of diameter 0.5 (Dn 50).
quarried stone, but shall place them individually into the
For land-based survey this shall be connected to a staff;
structure in order to achieve an adequate stability and
for underwater survey it will be a weighted ball on the end
deformation to maintain lines and levels shown on
of a sounding chain.
Drawings. He shall tightly pack the stones together so as
to achieve as near as possible a target unit weight of stone 2 The contractor shall carry out measurement profiles
placed of 1.6 t/m3 and do not place them so that they can at intervals of 25m along the length of the structure and at
rock or obtain their stability on a plane by frictional intervals of 3m across the measurement profile.
resistance alone prior to placing further stones.
3 The contractor shall make provisions for diving
3 The contractor shall fill any void below finished
inspections for any part of the structure where
profile level in excess of mean rock size with an
achievement of tolerances may otherwise appear in doubt.
appropriate stone or stones.
4 The contractor shall place rock materials to the levels, 9.13.3.5 Storage, Handling, and Laying of Geotextiles:
dimensions and slopes shown on drawings, and the
1 The contractor shall store and handle geotextile in
surface profile measured in accordance with the surveying
accordance with ASTM D4873-02
procedure outlined in Paragraph 9.13.3.4, to be within the
vertical placing tolerances given in Table 9.13.1.1. 2 For Geotextiles placement, the contractor shall use
overlaps in accordance with manufacture requirements,
and in no case less than 50 cms.

3 The contractor shall place bedding layer as soon as


possible after placement of the geotextile, according to the
approved method statement of the construction procedure.

4 Where seams are required, the contractor shall make


them in accordance with the manufacture requirements.
All seams shall be subjected to the approval of the
Engineer.

5 The contractor shall remove and replace any


damaged or punctured section before or after laying.

♦ 9-25 ♦
copy 249
9.13.4 Method of Measurement supply of materials, fabrics and membranes, sampling and
testing, ground preparation for laying on horizontal,
1 Underlayer, Rock Armour, Quarry Run and Bedding
sloping, vertical and curved planes, transportation, placing,
Layer shall be measured by the Cu.m of BUND material
protection, labor, equipment, tools, supplies and other
and rubble base (Quarry run), rock armour, and bedding
items necessary for the proper completion of the works.
layer, placed to the lines and levels as shown on the
Drawings.
9.13.6 Items in the Bill of Quantities
2 Dredging for embedded toe protection shall be
measured by the cu.m of material dredged in sand, clay or i. Underlayer (cu.m)
any other material except rock to the lines and levels as ii. Quarry Run (cu.m)
shown on Drawings. Rates inserted by the Contractor shall iii. Rock Armour (cu.m)
be deemed to include for all over cutting in width and iv. Dredging (cu.m)
depth and for sweeping the dredged areas. v. Fabrics and Membranes(type) (sq.m)

3 Fabrics and membranes (geotextile) shall be


measured by the sq.m of the area covered to any width or
girth including extra material for lapping and jointing. No
deduction is made for voids not exceeding 1.00 m2.

9.13.5 Basis of Payment


1 General: In addition to basis of payment of each
particular item, all marine works are also deemed to
include:
i. all surveying works and seabed sounding
ii. clearance of the seabed; removal of unsuitable
material, objects or obstructions,
iii. inspection for and relocation of any existing
underwater services,
iv. protection from sea action,
v. losses due to erosion or damage,
vi. losses/damage due to wave conditions which
may occur during the Contract period including
the Period of Maintenance.
2 The amount of completed and accepted work
measured as underlayer, quarry run, rock armour, and
bedding layer will be paid for at the unit rates indicated in
the Bill of Quantities which rate shall be full compensation
for selection and supply of materials, stone/rockfill,
crushing, screening, testing, transportation, hauling,
stockpiling, relocation, placing, compacting, trimming the
underlying material and slope preparation, removal of
discarded material, excavation and backfilling, finishing
and protection, labor, equipment, tools, supplies and other
items necessary for the proper completion of the works.
3 The amount of completed and accepted work
measured as Dredging for Embedded Toe Protection will
be paid for at the unit rates indicated in the Bill of
Quantities which rate shall be full compensation for
supply and installation of all plant and equipment required
to carry out dredging, pumping and transportation of
dredged material to whatever distance required, hauling,
stockpiling, disposal of discarded material to approved
locations, protection, labor, equipment, tools, supplies and
other items necessary for the proper completion of the
works..
4 The amount of completed and accepted work
measured as Fabric and Membranes (Geotextile) will be
paid for at the unit rates indicated in the Bill of Quantities
which rate shall be full compensation for selection and

♦ 9-26 ♦
copy 249
Ref. Title Page No.
10.1 Piling: General 10-1
10.1.1 Description 10-1
10.1.2 Materials 10-1
10.1.3 Construction Requirements 10-1
10.1.3.1 General 10-1
10.1.3.2 Cast in Place Piles 10-3
10.1.3.3 Placing Concrete 10-4
10.1.3.4 Preliminary Drilled Piles 10-4
10.1.3.5 Precast Concrete Piles 10-4
10.1.3.6 Steel piles 10-5
10.1.3.7 Tolerances 10-5
10.1.4 Method of Measurement 10-5
10.1.5 Basis of Payment 10-5
10.1.6 Items in the Bill of Quantities 10-5

10.2 Pile Testing 10-5


10.2.1 Description 10-5
10.2.2 Submittals 10-5
10.2.3 Execution 10-6
10.2.3.1 Preparation 10-6
10.2.3.2 Static-Load Testing 10-6
10.2.3.3 Non-Destructive, Low-Strain Integrity
Testing 10-6
10.2.3.4 Test Records 10-7
10.2.4 Method of Measurement 10-7
10.2.5 Basis of Payment 10-7
10.2.6 Items in the Bill of Quantities 10-7

♦ 10-0 ♦
copy 249
♦ 10-0 ♦
copy 249
10.1 Piling: General adequate notice of any intention to work outside normal
site hours.
10.1.1 Description 3 The Contractor shall engage an experienced installer
who has specialized in installing drilled or driven piles
1 This Section describes requirements for supplying similar to those required for the Project.
and installing precast concrete, cast in-situ concrete and
4 The Contractor shall protect structures, utilities,
steel piles by boring and/or driving.
sidewalks, pavements and other facilities, on or adjacent
to the Site, from damage caused by settlement, lateral
10.1.2 Materials
movement, vibration, and other hazards created by drilled
1 Concrete and steel reinforcement shall be as or driven pile operations.
specified in the relevant Clauses of Section 5. 5 The Contractor shall carry out the piling work in such
2 Concrete mixes, mixing and curing procedures shall a manner and at such times to minimize noise and
be as specified in the relevant Clauses of Section 5. disturbance to the general public. If, during execution of
Concrete mixes for use in piles shall be capable of the work, damage is likely to be caused to utilities or
maintaining a slump of 200 mm for 2 hours after adjacent structures, the Contractor shall submit to the
placement. Concrete mixes shall be designed to resist Engineer proposals for the repair or avoidance of such
aggressive soils and ground water if encountered in damage.
compliance with the requirements of the Construction 6 Piles shall be installed to the tolerances given in
Industry Research and Information Association – CIRIA Table 10.1.3.1.
‘Guide to the Construction of Reinforced Concrete in the
Arabian Peninsula’. Characteristic Allowable Limit
3 Steel pipe casings shall comply with the 75mm in any direction at the
Position
requirements of ASTM A 283M, Grade C; or ASTM A 36M pile head
carbon-steel plate, with vertical joints full-penetration
welded according to AWS D1.1. Verticality 1 in 75 deviation

4 Welds for fabricating steel piles and connecting steel Rake


1 in 25 deviation
pile lengths shall be as specified in the relevant Clauses of (for raked piles only)
Section 6. Table 10.1.3-1: Pile Installation Tolerances.
5 Sand-cement grout shall consist of Portland cement
manufactured according to ASTM C 150, Type I; and clean 7 The Contractor shall submit daily records to the
natural sand complying with ASTM C 404. Unless Engineer within 24 hours giving the information listed in
otherwise indicated, mix at ratio of 1 part cement to 2-1/2 Table 10.1.3.2.
parts sand, by volume, with sufficient water to permit flow 8 On completion of piling, the Contractor shall deliver a
during placement. final schedule of installed piles giving the information
6 Slurry shall consist of pulverized sodium bentonite, required by Table 10.1.3.2.
pulverized attapulgite, or polymers, mixed with potable
water to form a stable colloidal suspension; complying
with ACI 336.1, and the values indicated for density,
apparent viscosity (in centipoise), gel strength (in N/sq.m.),
sand content, and pH.

10.1.3 Construction Requirements


10.1.3.1 General

1 The Contractor shall submit for prior approval a


detailed method statement that describes all means,
methods and techniques to be adopted for construction
and installation of the drilled or driven piles. The method
statement shall include details of equipment to be used,
method of excavation, slurries to be used method of
concrete placement to ensure removal of slurry from sides
of boring, quality control, testing and report procedures,
work program, and any other information required by the
Engineer.
2 The Contractor shall inform the Engineer each day of
the work program for the following day and shall give

♦ 10-1 ♦
copy 249
Driven Hollow Cast-
Driven Precast Concrete & Steel Bored Cast-in-Place Concrete
All piles in-Place Concrete
Piles Piles
Piles

1. Date 1. Cross-sectional dimensions. 1. Cross section 1. Diameter of completed


2. Contract 2. Total length of preformed dimensions of pile.
identification, pile. driving tube 2. Diameter of any enlarged
3. Pile identification. 3. Driven length of preformed (temporary base.
4. Pile type. pile. casing). 3. Length of temporary
5. Working load. 4. Sequence of driving in 2. Cross-sectional casing.
6. Ground level at groups. dimensions of 4. Length of permanent
commencement of 5. Final set. completed pile. casing.
operations. 6. Sections and joints used. 3. Length of 5. Length of finished pile
7. Working platform permanent including any enlarged
level. casing. base.
8. Pile toe level. 4. Length of 6. Type of boring.
9. Details of any finished pile 7. Time of commencement
obstructions. excluding any of boring.
10. Delays or other enlarged base. 8. Details of soil strata
interruptions to penetrated.
the sequence of 9. Details of soils samples
work including 1. Time of commencement and completion of driving
taken and in-situ tests
times. or re-driving.
carried out.
11. Cut-off level. 2. Type, weight, drop and mechanical condition of
10. Details of any
12. Head level of hammer used.
interruption in boring.
completed pile. 3. Number, type and condition of the packing on the
11. Standing ground water
13. Ground heave. pile head.
level and water strikes
4. Type and condition of the dolly in the helmet.
during boring.
5. For a single acting hammer, the final drop.
6. For a double acting hammer, the final frequency of
blows.
7. The sets taken at intervals during the last 3 m of
driving, if required.
8. Details of any interruption in driving.
9. Details of re-driving.

1. Method of placing concrete.


2. Concrete mix details:
3. Grade of concrete
4. Nominal maximum aggregate size
5. Cement content
6. Type and quantity of admixtures
7. Water/Cement ratio.
8. Measured slumps.
9. Batch times.
10. Time of commencement of concrete pour.
11. Time of completion of concrete pour.
12. Volume of concrete placed in enlarged base.
13. Volume of concrete placed in pile shaft.
14. Reinforcement details:
15. Number, type and size of main reinforcing bars.
16. Type, size and pitch or spacing of helical binding
or link bars.
17. Length of individual reinforcement cages.
18. Total reinforced length of pile

Table 10.1.3-2: Piling Records.

Notes:

1. The 24 hour clock shall be used. 3. For driving operations not using a piling hammer,
2. For any pile not completed in the working day equivalent information to that required on type,
the date shall be entered in the records together weight, drop etc of hammer, packing and dolly
with the times of commencement and shall be provided.
completion.

♦ 10-2 ♦
copy 249
10.1.3.2 Cast in Place Piles Test Method
and Apparatus
1 Temporary casings or linings shall be used when complying
needed to maintain the stability of the pile borehole with the
during excavation. Casings shall be free from distortion American Samples
Petroleum from
and projections, and shall be uniform section throughout
Institute (API) Sample as excavation
their length. recommended supplied to
Property prior to
2 In case where permanent steel casings is required, practice for excavation placing
steel pipe casings of minimum wall thickness indicated Field Testing concrete
with inside clear diameter not less than diameter of pile of Water-
Based Drilling
shall be installed as follows:
Fluids – API RP
i. Install casings as excavation proceeds, to 13B-1
maintain sidewall stability.
Less than Less than
ii. Fabricate bottom edge of lowest casing section Density Mud balance
1.10 g/ml 1.15 g/ml
with a cutting shoe capable of penetrating rock
Fluid
and achieving a water seal. Low Less than Less than
loss
iii. Connect casing sections by continuous temperature 30 mil 40 mil
(30 min.
test fluid loss (0.762mm) (1.016mm)
penetration welds to form a watertight, test)
continuous casing. 30 to 40 Less than
Viscosity Marsh Cone
iv. Remove and replace, or repair, casings that seconds 60 seconds
have been damaged during installation and Fann
viscometer
that could impair strength or efficiency of Plastic Less than Less than
(material
drilled pile. viscosity 10 cP 20 cP
passing sieve
v. Fill annular void between casing and shaft wall No. 200)
with sand-cement grout. Shear
vi. Corrugated casings formed from zinc-coated strength
Fann 4 to 25 4 to 25
steel sheet may be delivered in sections or (10 min.
viscometer N/m2 N/m2
panels of convenient length, and field gel
strength)
connected according to manufacturer's written
Sand Sand screen Less than Less than
instructions.
content set 1% 3%
3 The drilling fluid shall be maintained at an adequate Electrical pH
viscosity and density. Action shall be taken to prevent the PH meter range 9.5 to 10.8 9.5 to 11.7
spillage of bentonite slurry onto the site. Disposal of used pH 7 to 14
slurry shall be made to a tip approved by the Engineer. Table 10.1.3-3: Tests and Compliance of Slurry.
4 When drilled shafts are to be stabilized with slurry,
the slurry shall be maintained a minimum of 1500 mm iv. Drilled pile shaft shall be excavated and
above ground-water level and above unstable soil strata to completely concreted on same day or the shaft
prevent caving or sloughing of shaft. Excess slurry head is shall be re-drilled, cleaned, re-circulated, de-
to be related to performance of on-going dewatering and sanded, or slurry replaced.
to allow for fluctuations in depressed water levels. v. Bottom of each shaft shall be cleaned before
i. Each batch of freshly prepared or reconstituted concreting.
slurry shall be sampled and tested. Test results 5 Pumping of ground water from boreholes will only
of samples and from excavation shall reflect be permitted where there is no risk of removal of fines
the amount of contamination with saline from the subsoil. Water which cannot be sealed off shall
ground water. be maintained in the borehole at a level above the
ii. At least one sample from the base and one standing ground water.
sample from the top of each shaft shall be
6 On completion of boring, loose soil and debris shall
tested immediately prior to placing steel and
be removed from the base of the pile and the Contractor
concrete. The Engineer may subsequently vary
shall provide facilities required by the Engineer to facilitate
frequency of sampling and testing when a
inspection of the pile base. The method of descent and the
working pattern has been established.
equipment used shall comply with BS 5573.
iii. Tests and Compliance: Values measured at 20
7 If reinforcement cages are used they shall be rigid
deg C shall be as Table 10.1.3.3
and installed and maintained in the correct position during
concreting.

♦ 10-3 ♦
copy 249
head of the pile. Each pile shall be marked at intervals of
10.1.3.3 Placing Concrete 250mm along the top 3m of its length before being driven.
1 The concrete shall be placed without interruption. 2 Only the designed lifting and support points shall be
Records shall be kept of the workability of the approved used during transport and piles shall be stored on
mix. Under water concrete shall be placed only by tremie. adequate supports located under these lifting points of the
The tremie pipe shall be clean and watertight throughout piles. Piles within a stack shall be in groups of the same
and not less than 200 mm internal diameter. Concreting length. Packing of uniform thickness shall be provided
shall start only after the tremie reaches the bottom of the between piles at the lifting points.
pile shaft and concreting shall then proceed with the end 3 During driving, piles shall be adequately supported
of tremie pipe kept immersed in the concrete for a and restrained by means of leaders, trestles, or other
minimum depth of 1 m. Spacer blocks shall be installed as guide arrangements to maintain position and alignment
appropriate to maintain the minimum concrete cover to and to prevent buckling. The Contractor shall satisfy the
the reinforcement steel as specified and/or shown on Engineer regarding the suitability, efficiency and energy of
Drawings. the driving equipment. Piles shall be driven continuously
2 Permanent casing shall be checked for damage. If until the prescribed set or depth has been reached.
necessary the casing shall be withdrawn, repaired, re- 4 The final set of the pile shall be recorded either as the
driven, or other action taken to allow the construction of penetration in millimeters per 10 blows or as the number
the pile. of blows required to produce a penetration of 25mm.
3 Temporary casings shall be extracted while the 5 When a final set is being measured, the following
concrete remains sufficiently workable. While the casing is requirements shall be met:
being extracted a sufficient head of concrete shall be i. The exposed part of the pile shall be in good
maintained within it to avoid necking in the pile. No condition without damage or distortion.
concreting shall be done once the casing has been lifted ii. The dolly and packing, if any, shall be in sound
above the top of the concrete. Withdrawal of temporary condition.
casing shall be coordinated with concrete placement iii. The hammer blow shall be in line with the pile
operations to maintain a head of concrete no less than axis and the impact surfaces shall be flat and at
1500 mm above casing bottom. right angles to the pile and hammer axis.
4 Casings for driven cast-in-place piles shall be iv. The hammer shall be in good condition and
installed to the approved set or specified depth and in the operating correctly.
sequence approved by the Engineer. Each length shall be v. The temporary compression of the pile shall be
driven continuously. Levels shall be taken immediately recorded if required.
when the final depth is approved, before concreting has
6 Piles shall be driven in an approved sequence to
begun. The casings shall be watertight.
minimize the detrimental effects of heave and lateral
10.1.3.4 Preliminary Drilled Piles displacement of the ground. When a pile has risen as a
result of adjacent piles being driven, the contractor shall
1 Construct preliminary drilled piles of diameter and submit to the Engineer proposals for correcting this and
depth and at location indicated or if not indicated, as its avoidance in subsequent work.
directed by the Engineer, of same diameter and depth as
7 If repairs are needed during driving to the head of a
permanent drilled piles, located at least 3 diameters clear
pile, it shall be cut off square at sound concrete, and loose
of permanent drilled piles, to demonstrate Installer's
material removed by wire brushing, followed by washing
construction methods, equipment, standards of
with water. If the pile is to be subjected to further driving,
workmanship, and tolerances.
the head shall be replaced by concrete of an approved
i. Install casing or use bentonite slurry, excavate
class.
bell if applicable, excavate rock socket, all as
required for permanent drilled piles. 8 Piles shall be lengthened, if required, by stripping off
ii. Install reinforcement, fill with concrete, remove concrete from the reinforcement and lapping, coupling or
temporary casings, if applicable, and terminate welding additional steel in place. Laps shall be at least 40
preliminary drilled pile as instructed by the x bar diameter. Couplers shall be approved by the
Engineer. Engineer. Steel to be welded shall be free of concrete for
iii. If Engineer determines that a preliminary drilled at least 300 mm below the weld. Welded joints shall be
pile does not meet requirements, excavate for made in accordance with the relevant Clauses of Section 6.
and cast another until preliminary drilled pile is 9 Repaired or lengthened piles shall not be driven until
accepted. the added concrete has reached the specified
characteristic strength of the concrete of the pile.
10.1.3.5 Precast Concrete Piles

1 After a pile has been cast, the date of casting and


reference number shall be permanently inscribed on the

♦ 10-4 ♦
copy 249
10.1.3.6 Steel piles length shown in the approved Drawings or as per the
modifications approved by the Engineer. Any
1 Piles shall be clearly marked in white paint with their unauthorized extra length cast by the Contractor shall not
number and overall length. In addition, each pile shall be be measured for payment.
marked at intervals of 250mm along the top of 3m of its
3 Expendable piles (non-working piles) that are
length before being driven.
constructed for the purpose of carrying out preliminary
2 If steel piles are to be pre-coated, the preparation of load tests shall be measured in linear meters of actual
surfaces and the application of the coating shall be carried length, ordered and tested.
out by experienced specialist labor.
3 Surface preparation, priming and protective coats 10.1.5 Basis of Payment
shall conform to the requirements of Section 7 “Paint for
Steelwork”. 1 The amount of completed and accepted work
measured as provided for above will be paid for at
4 Rolled steel sections shall be within the tolerances
the unit rates for the various types of piles in the Bill
specified in BS 4. For steel piles and proprietary rolled
of Quantities, which rate shall be full compensation
sections, the deviation from straightness shall not exceed
for supplying and installing piles and for materials,
1/1000 of the length of the section.
labor, equipment, tools, records and other items
5 Cylindrical steel piles shall not deviate from
necessary for the proper completion of the work.
straightness by more than 1/600 for the length up to 10m
and 1/1000 for lengths greater than 10m. The actual mass
of each section shall be within +5% and -2.5% of the
10.1.6 Items in the Bill of Quantities
theoretical mass computed in accordance with Section 6. i. Setting up at each pile location nr.
6 Sheet piles shall be pitched and supported as a panel
ii. Piling (type)(length)(size) lin.m.
before driving and securely interlocked. Piles shall not
overlap each other and no pile in a panel shall be more iii. Expendable piles (type)(length)(size) lin.m.
than 1 m in advance of another.
7 Sheet piles previously driven shall not be used in the 10.2 Pile Testing
Permanent Works unless approved.
8 Steel piles shall be driven to a prescribed set or 10.2.1 Description
depth in a sequence approved by the Engineer. Driving
1 This Sub-section describes requirements for testing
shall be continuous.
of concrete piles as follows:
9 If approved, piles shall be lengthened by full i. Static-load testing: ASTM D1143 and ASTM
penetration butt welding. Lengthening sections shall be of D3689.
the same rolling. Longitudinal and spiral seam welding of ii. Non-destructive, sonic or low-strain integrity
cylindrical piles shall be staggered. testing: ASTM D5882.
10.1.3.7 Tolerances
10.2.2 Submittals
Vertical piles shall be constructed to remain within the
1 The Contractor shall submit a method statement for
following tolerances:
each type of testing specified and provide details of
i. Maximum variation from location: Not more specific techniques and processes proposed to be adopted
than 75 mm from design center location. for testing. The method statement shall include details of
ii. Out-of-plumb: 1 in 75 deviation or not more than equipment and instrumentation, quality control and report
1.5 percent of pile length, whichever is less. procedures, work program, and any other information or
iii. Concrete cutoff level: Plus 25 mm or minus 75 special data required by the Engineer.
mm from level indicated. i. The method statement shall include details of
iv. Bottom area of pile: Not less than 96 percent of loading and arrangement of reaction frame,
pile area required. reaction piles or anchors. Due consideration
v. Shaft diameter for drilled pile: Not less than 98 shall be given to the effect of diameters of piles,
percent or more than 110 percent of shaft socket length, type of bedrock, strain
diameter indicated. measurement in steel reinforcement and effect
of dewatering. The structural analysis data shall
10.1.4 Method of Measurement be supervised, signed and sealed by the
qualified professional independent engineer
1 Setting up at each pile shall be measured by number.
responsible for their preparation.
2 Piles shall be measured in linear meters of actual
length placed in the Permanent Works. The measured 2 The Contractor shall submit daily work progress
length shall be from the tip to the underside of the reports, identifying individual piles and type of testing
foundation, plus the penetration into the foundation carried out.
specified on the Drawings. The payment shall be made for

♦ 10-5 ♦
copy 249
3 For non-destructive integrity testing, the Contractor times working load. The Contractor shall perform
shall qualify and engage an experienced independent at least two preliminary pile tension load tests
testing agency, acceptable to the Engineer, who has and two preliminary pile compression load tests
specialized in non-destructive testing of drilled piles to cover the different rock configurations or as
similar to that required for the Project. specified on the Drawings or in the Special
Specification.
10.2.3 Execution ii. Working piles in tension or compression load
tests: Apply test loads up to 1.5 times working
10.2.3.1 Preparation load, as specified on the Drawings or in the
1 The Contractor shall protect structures, utilities, Special Specifications.
sidewalks, pavements, and other facilities from damage 6 In the event of a pile continuing to displace under
caused by settlement, lateral movement, vibration, and constant load before the maximum test load has been
shall verify the feasibility of testing the loads reached, take readings at 15 minute intervals for a period
corresponding to each pile diameter. The pile load tests of one hour while the load is being maintained. Unload
shall not be carried out until all shrinkage of the concrete the pile in approximately 4 to 6 equal decrements at 15
is complete. The reinforcement in the rock socket shall be minute intervals and allow recovering for 3 hours. Take
strain-gauged to provide confirmation of the tensile force one set of displacement readings after each decrement of
reaching the socket. load and a further set of readings at the end of the
i. Dynamic formulas will not be permitted in place recovery period.
of load tests to determine bearing values of the
piles. 10.2.3.2 Non-Destructive, Low-Strain Integrity Testing
ii. Perform and complete testing, and obtain
1 Non-destructive, integrity testing by sonic logging
approval of preliminary pile test before
shall be performed on all piles, or as specified on the
proceeding with installation of permanent
Drawings and \special Specification, recorded, interpreted
working piles in the Works.
and reported by an approved experienced independent
iii. Select the pile to be tested based on the results
testing agency that has specialized in non-destructive
of pile integrity tests and pile construction
testing of piles similar to that required for the Project.
records subject to the approval of the Engineer.
Submit proposed test result and report formats to the
iv. The same piles that will be tested in working
Engineer for approval before starting integrity testing.
compression loading shall be among the
i. Provide all available details of the ground
selected piles for the working load test in
conditions, pile dimensions and construction
tension.
method to the testing agency before the
2 Pile Tests: Arrange and perform the following static- commencement of integrity testing, in order to
load tests on piles as and when directed in the field: facilitate interpretation of test results.
i. Axial Tension Static-Load Test: ASTM D 3689. ii. Allow a minimum of seven days to elapse after
ii. Axial Compression Static-Load Test: ASTM D casting before performing integrity testing on a
1143. pile.

3 Provide pile reaction frame, equipment and 2 Perform low-strain integrity testing according to
instrumentation with sufficient reaction capacity to ASTM D5882 by the stress wave method, seismic method
perform tension tests and compression tests. On or other method approved by the Engineer, based on the
completion of testing, remove testing structure, measurement of the axial shaft point mobility at the pile
equipment and instrumentation. head.
i. Notify Engineer at least 48 hours in advance of i. Where the method of testing requires the
performing tests. positioning of sensing equipment on the pile
ii. Provide facilities to enable Engineer to observe head, break down the pile head to expose sound
and check testing. clean concrete, free from water, laitance, loose,
overspill or blinding concrete, and readily
4 Apply test loads by jacking against beams or accessible for the purpose of testing.
equivalent reaction system.
i. Center to center spacing of vertical reaction piles 10.2.3.3 Test Records
from a test pile shall be not less than 3 times the
1 General: Maintain accurate test records for each pile,
diameter of the test pile or the reaction piles or 2
compiled and attested to by a qualified professional
m whichever is the greater.
engineer, and submit to the Engineer at the conclusion of
5 Test Loads: Maximum loads to be applied in each pile test. Include the following data:
maintained load test shall be as follows: i. Project name and number.
i. Expendable preliminary piles in tension or ii. Pile number and date of testing.
compression load test: Apply test loads up to 2.5 iii. Pile dimensions.
iv. Type and method of pile testing.

♦ 10-6 ♦
copy 249
v. Test results. 10.2.6 Items in the Bill of Quantities
2 Prepare static load test results in the form of i. Static load testing of expendable piles
tabulated field observations, including the following data: (type) (length) (size). nr.
i. Time vs. displacement curves. ii. Static load testing of working piles (type)
ii. Time vs. load curves. (length) (size). nr.
iii. Load vs. displacement curves. iii. Non-destructive integrity test (type) nr.
iv. Displacement vs. log time for each stage.

The Engineer will review test results and determine if a


pile is acceptable, taking into account the acceptable total
and differential displacements of the superstructure, the
foundation geometry, the pile type and the soil conditions,
etc.

10.2.3.4 Static-Load Testing

1 General: Static-load tests will be used to verify and


confirm design load capacity of piles. Each pile diameter
shall be tested as shown on the Drawings. The Contractor
displacement characteristics compared to preliminary test
piles will not be accepted.
2 Non-Destructive Integrity Testing:
i. All piles shall be subjected to integrity testing.
ii. Submit preliminary test results to the Engineer
within 24 hours of carrying out the tests.
iii. Submit test reports to the Engineer within 10
days of the completion of each phase of testing.
iv. Test reports shall contain test results and
conclusions, together with a summary of the
method of interpretation including all
assumptions, calibrations, corrections,
algorithms and derivations used in the analyses.
Where results are presented in a graphical form,
the same scales are to be used consistently
throughout the report and the units on all scales
clearly marked.
v. If any anomaly in acoustic signal test results
indicates a possible defect in a pile, report such
anomalies to the Engineer immediately.
Demonstrate to the Engineer that the pile is
satisfactory for its intended use or carry out
remedial works to the Engineer’s satisfaction.
vi. Grout sonic logging tubes only after piles have
been demonstrated to the Engineer’s
satisfaction, to be satisfactory.

10.2.4 Method of Measurement


1 Pile loading tests shall be measured per number.
2 Pile integrity tests shall be measured per number.

10.2.5 Basis of Payment


1 The amount of completed work of “Pile testing” will
be paid for at the unit rate in the Bill of Quantities which
rate shall be full compensation for setting up, carrying out,
reporting and for labor, transport, equipment, tools,
materials and other item necessary for the proper
completion of the work.

♦ 10-7 ♦
copy 249
copy 249
Ref. Title Page No. Ref. Title Page No.
11.1  Bearings – General 11-1  11.3.2.7  Polytetrafluorethylene (PTFE) Sheet
and Strip 11-6 
11.1.1  Description 11-1 
11.3.3  Construction Requirements 11-6 
11.1.1.1  Definitions 11-1 
11.3.3.1  General 11-6 
11.1.1.2  References 11-1 
11.3.3.2  Sampling and Testing 11-7 
11.1.1.3  Design and Construction Standards 11-1 
11.3.3.3  Installation 11-8 
11.1.1.4  Submittals 11-2 
11.3.4  Method of Measurement 11-8 
11.1.1.5  Quality Assurance 11-2 
11.3.5  Basis of Payment 11-8 
11.1.2  Materials 11-2 
11.3.6  Item in the Bill of Quantities 11-8 
11.1.2.1  Steel 11-2 
11.1.2.2  Material Testing 11-3  11.4 Bridge Expansion Joints 11-8
11.1.2.3  Bedding Material 11-3 
11.4.1  Description 11-8 
11.1.3  Construction Requirements 11-3 
11.4.1.1  Scope 11-8 
11.1.3.1  Manufacture 11-3 
11.4.1.2  Types of Joints 11-8 
11.1.3.2  Manufacture Tolerances 11-3 
11.4.1.3  References 11-9 
11.1.3.3  Testing of Complete Bearings 11-3 
11.4.1.4  Submittals 11-9 
11.1.3.4  Packaging, Handling and Storage 11-4 
11.4.1.5  Quality Assurance 11-9 
11.1.3.5  Construction and Installation 11-4 
11.4.2  Materials 11-9 
11.1.4  Method of Measurement 11-4 
11.4.2.1  General 11-9 
11.1.5  Basis of Payment 11-5 
11.4.2.2  Asphaltic Plug Joints 11-9 
11.1.6  Items in the Bill of Quantities 11-5 
11.4.3  Construction Requirements 11-9 
11.2 Elastomeric Bearings 11-5 11.4.3.1  General 11-9 
11.4.3.2  Nosings 11-9 
11.2.1  Description 11-5 
11.4.3.3  Installation 11-10 
11.2.2  Materials 11-5 
11.4.4  Method of Measurement 11-10 
11.2.3  Construction Requirements 11-5 
11.4.5  Basis of Payment 11-10 
11.2.4  Method of Measurement 11-5 
11.4.6  Items in the Bill of Quantities 11-10 
11.2.5  Basis of Payment 11-5 
11.2.6  Items in the Bill of Quantities 11-5  11.5 Joint Seals and Fillers 11-10
11.3 Pot Bearings 11-6 11.5.1  Description 11-10 
11.5.2  Materials 11-10 
11.3.1  Description 11-6 
11.5.3  Construction Requirements 11-11 
11.3.2  Materials 11-6 
11.5.4  Method of Measurement, Basis
11.3.2.1  General 11-6 
of Payment and Bill of Quantities 11-11 
11.3.2.2  Steel 11-6 
11.3.2.3  Stainless Steel 11-6  11.6 Bridge Parapets and Railings 11-11
11.3.2.4  Elastomeric Rotational Element 11-6 
11.6.1  Description 11-11 
11.3.2.5  Sealant 11-6 
11.6.2  Materials 11-11 
11.3.2.6  Sealing Rings 11-6
11.6.2.1  Materials of Construction 11-11 

♦ 11-0 ♦
copy 249
Ref. Title Page No.
11.6.2.2 Aluminum Alloy 11-11
11.6.2.3  Structural Steel 11-11 
11.6.2.4  Reinforced Concrete 11-11 
11.6.2.5  Anchorage System 11-11 
11.6.3  Construction Requirements 11-11 
11.6.4  Method of Measurement 11-11 
11.6.5  Basis of Payment 11-12 
11.6.6  Item in the Bill of Quantities 11-12 

♦ 11-0 ♦
copy 249
11.1 Bearings – General accommodates movement by rolling of one surface with
respect to the other. It consists essentially of one or more
steel rollers between upper and lower plates.
11.1.1 Description
14 Rocker bearing: A bearing that carries vertical load by
1 This Sub-section describes the requirements for direct contact between two metal surfaces and that
designing, testing, furnishing and installing replaceable accommodates movement by rocking of one surface with
bridge bearings as shown on the Drawings or in the respect to the other. It consists essentially of a curved
Special Specification or as required to complete the work. surface in contact with a flat or curved surface and
constrained to prevent relative horizontal movement. The
11.1.1.1 Definitions
curved surface may be cylindrical or spherical.
1 Bearing: A structural device that transmits loads 15 Longitudinal: Parallel with the main span direction of
while facilitating translation and/or rotation. the bridge.
2 Elastomer: A compound containing natural or 16 Transverse: The horizontal direction normal to the
chloroprene rubber with properties similar to those of longitudinal axis of the bridge.
rubber.
17 Translation: Horizontal movement of the bridge in
3 Elastomeric bearing: A bearing comprising a block of the longitudinal or transverse direction.
elastomer that may be reinforced internally with steel
18 Rotation about the longitudinal axis: Rotation about
plates.
an axis parallel to the main span direction of the bridge.
4 Plain pad bearing: An unreinforced elastomeric
19 Rotation about the transverse axis: rotation about an
bearing. It provides limited translation and rotation.
axis parallel to the transverse axis of the bridge.
5 Strip bearing: A plain pad bearing for which the
length is at least ten times the width. 11.1.1.2 References
6 Laminated elastomeric bearing or steel-reinforced 1 American Association of State Highway and
elastomeric bearing: A bearing made from alternate Transportation Officials (AASHTO):
laminates of steel and elastomer bonded together during
AASHTO 2008 AASHTO LRFD Bridge Construction
vulcanization. Vertical loads are carried by compression of
Specifications, 2nd Edition, 2004, 2008
the elastomer. Movements parallel to the reinforcing
layers and rotations are accommodated by deformation of Interim Revisions.
the elastomer.
AASHTO 2008 AASHTO LRFD Bridge Design
7 Pot bearing: A bearing consisting essentially of a
Specifications, 3rd Edition, 2004, 2008
metal piston supported by a disc of unreinforced
Interim Revisions.
elastomer that is confined within a metal cylinder.
Rotations are accommodated by deformation of the 11.1.1.3 Design and Construction Standards
elastomer. It may be movable, guided, unguided or fixed.
Movement is accommodated by sliding of polished 1 Bearings shall be designed in accordance with the
stainless steel on PTFE. latest edition of AASHTO LRFD Bridge Design
8 Disc bearing: A bearing that accommodates rotation Specifications, Sub-Section 14.7, as complemented or
by deformation of a single elastomeric disc molded from a modified herein.
urethane compound. It may be movable, guided, 2 Bearings shall be constructed as specified in the
unguided or fixed. Movement is accommodated by sliding latest edition of AASHTO LRFD Bridge Construction
of polished stainless steel on PTFE. Specifications, Section 18, as complemented or modified
9 PTFE (polytetrafluoroethylene): Also known as Teflon. herein.

10 Fixed bearing: A bearing that prevents differential 3 Alternatively, the bearings may be designed and
translation of abutting structural elements. It may or may constructed in accordance with Eurocode as described in
not provide for differential rotation. the following documents, as complemented or modified
herein.
11 Movable bearing: A bearing that facilitates
differential horizontal translation of abutting structural i. BS EN 1337-1 Structural Bearings - Part 1:
elements in a longitudinal and/or lateral direction. It may General Design Rules.
ii. BS EN 1337-2 Structural Bearings - Part 2: Sliding
or may not provide for rotation. Translation may be
Elements.
constrained to a specified direction by guide bars. iii. BS EN 1337-3 Structural Bearings - Part 3:
12 Sliding bearing: A bearing that accommodates Elastomeric Bearings.
movement by translation of one surface relative to iv. BS EN 1337-5 Structural Bearings - Part 5: Pot
another. Translation may be constrained to a specified Bearings.
v. BS EN 1337-9 Structural Bearings - Part 9:
direction by guide bars.
Protection.
13 Roller bearing: A bearing that carries vertical load by vi. BS EN 1337-10 Structural Bearings - Part 10:
direct contact between two metal surfaces and that Inspection and Maintenance.

♦ 11-1 ♦
copy 249
vii. BS EN 1337-11 Structural Bearings - Part 11: quality and performance of bearings and
Transport, Storage and Installation. ancillary items.
− Records of an installation trial for each type
4 Definitions of bearing types and bearing components
of bearing in accordance with the method of
shall be in accordance with AASHTO LRFD Bridge Design
installation which shall take full account of
Specifications, Third Edition, 2004, Section 14.2. Relevant
restrictions that may be imposed on the
definitions are reported in Paragraph 11.1.1.1.
operations by the location of the bearings in
5 Detailed specifications for elastomeric bearings and the Works. A photographic record of the
Pot Bearings are given in Sub-Sections 11.2 and 11.3, trial shall be made. Subject to the successful
these two types being the most common and most completion of the trial the method of
suitable types. installation shall not subsequently be varied
6 Other types of bearings shall follow AASHTO LRFD unless approved by the Designer.
Bridge Design Specifications, Section 14 for design, and x. Certificates (not older than 12 months):
AASHTO LRFD Bridge Construction Specifications for
− Certificates as specified in the standards in
construction requirements, as follows:
respect of the specified materials.
i. Disc Bearings Sub-Section 18.3 − Certificates for all materials used in the
ii. Rocker and Roller Bearings Sub-Section 18.4 manufacture of bearings shall be obtained
iii. Spherical Bearings Sub-Section 18.5 from the manufacturers or suppliers. These
shall state the type and grade of material,
11.1.1.4 Submittals the relevant standard and the results of all
tests carried out.
1 The Contractor shall submit the following to be
xi. Test Reports:
approved by the Engineer prior to fabrication of the
bearings. Such approval shall not relieve the Contractor of − Reports of the specified material tests.
any responsibility under the contract documents for the − Reports of the specified tests on bearings.
successful completion of the work. xii. Replacement procedures.
i. Working drawings as defined in AASHTO LRFD xiii. Inspection and Maintenance Plan.
Bridge Construction Specifications Article 18.1.1.
The drawings shall, additionally, show transit 11.1.1.5 Quality Assurance
restraints and lifting points as necessary. 1 Codes and Standards: AASHTO LRFD Bridge
Construction Specifications.
ii. Details of protective coatings with data sheets
2 The Contractor shall ensure that direct site
and painting drawings showing the venue and
supervision of the first of each type of bearing is provided
timing of the application of shop and site applied
by an experienced technical representative of the
coatings.
manufacturer and thereafter, by competent persons who
iii. Method statements. have been trained in the proper installation of bearings.
iv. Evidence that the manufacturer has at least ten
years experience in manufacturing bearings 11.1.2 Materials
comparable with those required for the Project,
and that the proposed types of bearings have 11.1.2.1 Steel
been incorporated in structures in similar
1 Unless otherwise specified, rolled steel shall conform
environmental conditions.
to AASHTO M 270M/M 270 (ASTM A 709/A 709M), Grade
v. Design calculations. 36 (Grade 250), and shall cause no adverse electrolytic or
vi. Construction drawings of any additional or chemical reaction with other components of the bearing
revised reinforcement and modified concrete and shall be free of all rust and mill scale.
details and/or steelwork details required at the 2 Unless otherwise specified, steel laminates shall be
abutting structural elements. made from rolled mild steel conforming to AASHTO M
vii. Details of fixings to superstructures and 270M/M 270 (ASTM A 709/A 709M), Grade 36 (Grade 250),
substructures including tolerance requirements. ASTM A 1011/A 1011M, or equivalent. Laminates shall
viii. Program of manufacture, testing and delivery, have a minimum nominal thickness of (1.6 mm). Holes in
including the name, address and accreditation of plates for manufacturing purposes shall not be permitted
the testing laboratory. unless they have been accounted for in the design and are
in accordance with the contract documents.
ix. Samples:
3 Cast steel shall satisfy the requirements of ASTM
− All samples required to perform the tests
A802/A802M and be free of all blow-holes and impurities
specified for the verification of material
larger than 3.2 mm the inside wall of the pot in pot
bearings and the contact surface of metal rocker or roller

♦ 11-2 ♦
copy 249
bearings shall be free of blow-holes or impurities of any 5 When nonshrink mortar or grout is specified, a
size. nonshrink admixture of a type approved by the Engineer
4 Forged steel shall satisfy the requirements of ASTM shall be used.
A 788. 6 Only sufficient water shall be used to permit placing
5 Stainless steel shall conform to the requirements of and packing.
ASTM A167, Type304 or ASTM A240/A240M, Type 304 7 Mixing shall be done by either hand methods or with
and shall have a minimum thickness of 0.91 mm and a rotating paddle-type mixing machines and shall be
surface finish in the finished bearing better than or equal continued until all ingredients are thoroughly mixed. Once
to 0.2 μm. Stainless steel in contact with PTFE sheet shall mixed, mortar or grout shall not be retempered by the
be polished to a finish no less than 0.50 μm. addition of water and shall be placed within one hour.
6 Where ASTM is referred, equivalent specifications,
Eurocode for example, may be accepted. 11.1.3 Construction Requirements
11.1.2.2 Material Testing 11.1.3.1 Manufacture

1 Material certification tests to determine the physical 1 The manufacturer shall certify that each bearing
and chemical properties of all materials shall be satisfies the requirements of the contract documents and
conducted in accordance with the appropriate this Specification, and shall supply the Engineer a certified
specification governing the material. The test certificates copy of material test results. Each bearing shall be marked
shall be submitted to the Engineer. in indelible ink or flexible paint. The marking shall consist
2 Material friction test for sliding surfaces shall be of the location in the structure, the orientation, the order
conducted either on samples taken from the same batch of number, lot number, bearing identification number, and
materials as those used in the prototype bearings, or on elastomer type and grade number. Unless otherwise
finished bearings. The testing procedure shall be in specified in the contract documents, the marking shall be
accordance with AASHTO LRFD Bridge Construction on the face that is visible after erection of the bridge.
Specifications Article 18.1.5.2.3. The bearing or specimen Bearing assemblies shall be preassembled in the shop by
shall show no appreciable sign of wear, bond failure, or the supplier and checked for proper completeness and
other defects. geometry before shipping to the site.

3 Long-term deterioration test shall either be 2 The design of the bearing shall include necessary
conducted on samples or on a pair of bearings placed provision to facilitate the replacement of the bearing with
back-to-back. The testing procedure shall be in accordance minimum interruption to traffic. The Special Specification
with AASHTO LRFD Bridge Construction Specifications defines, where appropriate, the maximum lifting of bridge
Article 18.1.5.2.7. The following shall be cause for rejection decks to remove existing and install new bearings.
of the bearing: 3 Performance for the system for protection against
i. Damage visible to the naked eye on disassembly corrosion shall not be less than 15 years to first
of the bearing, such as excessive wear, cracks, or maintenance unless otherwise specified in the contract
splits in the material. documents. The system for corrosion protection shall be
ii. A coefficient of friction which exceeds two-thirds subject to test in accordance with Table 1, Clause 5.3, BS
the value used in design. EN 1337-9 or other such criteria as may be additionally
recommended by the corrosion protection system
11.1.2.3 Bedding Material
manufacturer as being adequate to demonstrate the ability
1 Bedding material shall be of the type specified in the of the protection system to achieve life to first
contract documents or as ordered or approved by the maintenance as specified for the steelwork.
Engineer and shall be installed to provide full bearing on
11.1.3.2 Manufacture Tolerances
contact areas. Grout and mortar used for filling under
bearing or masonry plate shall conform to the 1 Bearings shall be fabricated within the tolerances of
requirements of AASHTO LRFD Bridge Construction Table 18.1.4.2-1 of AASHTO LRFD Bridge Construction
Specifications Sub-Section 8.14. Specifications. The Special Specification defines, where
2 Materials for mortar and grout shall conform to the appropriate, the class of tolerances A, B or C.
requirements of Sub-Section 5.1 as complemented and/or
11.1.3.3 Testing of Complete Bearings
modified herein.
3 When the width or depth of the void to be filled is 1 Dimension Check: the dimensions of the bearings
less than 20 mm, the grading of sand for use in the grout shall be checked in accordance with AASHTO LRFD Bridge
shall be modified so that all material passes the 2.36 mm Construction Specifications Article 18.1.5.2.4.
sieve. 2 Clearance Test: in accordance with AASHTO LRFD
Bridge Construction Specifications Article 18.1.5.2.5.
4 Unless otherwise specified or ordered by the
Engineer, the proportion of cement to sand shall be one to 3 Bearing Friction Test: in accordance with AASHTO
one. LRFD Bridge Construction Specifications Article 18.1.5.2.6.

♦ 11-3 ♦
copy 249
In addition to the compression of 100 percent of the full Bearings shall not be opened or dismantled at the site
service dead load plus live load, the bearings shall be except under the direct supervision of or with the approval
checked for 50 percent and 80 percent of the full service of the manufacturer.
dead load plus live load.
11.1.3.5 Construction and Installation
4 Bearing Horizontal Force Capacity: in accordance
with AASHTO LRFD Bridge Construction Specifications 1 Bearings shall be installed by qualified personnel to
Article 18.1.5.2.8. Failure or excessive deflection of any of the positions shown in the contract documents. Bearings
the components shall be cause for rejection. shall be set at time of installation to the dimensions and
5 Vertical Load Test: bearings shall be tested for offsets prescribed by the manufacturer, by the Engineer,
vertical load equal to one and a half (1.5) times the full and as shown in the contract documents and shall be
service dead load plus live load. The test shall be applied adjusted as necessary to take into account the
in five equal increments and the test load held for one (1) temperature and future movements of the bridge due to
hour or until deformation ceases, whichever is the greater. temperature changes, release of falsework, and shortening
The load shall then be removed in equal decrements as due to prestressing.
the load increments. A second cycle of load increment and 2 Each bridge bearing shall be located within ±3 mm of
decrement shall be applied with the maximum test load its correct position in the horizontal plane and oriented to
being held for (30) minutes. The load-deformation graph within an angular tolerance of 1 degree. Guided bearings
shall be plotted for both load cycles and the set and bearings which rotate about only one axis shall be
determined. If the set exceeds a value deemed to be oriented in the direction specified in the contract
excessive by the Engineer, the Engineer may require all documents to within a tolerance of 0.25 degree. All
bearings to be pre-loaded before installation. At the end of bearings except those which are placed in opposing pairs
the vertical load test, the bearing shall be dismantled and shall be set horizontal to within an angular tolerance of
the bearing surfaces examined. Damage visible to the 0.25 degree, and must have full and even contact with
naked eye on disassembly of the bearing, such as load plates, where these exist. The superstructure
excessive wear, cracks, or splits in the material shall be supported by the bearing shall be set so that, under full
cause for rejection. dead load, its slope lies within an angular tolerance of 0.25
6 If one bearing of the sample fails, all the bearings of degree of the design value. Any departure from this
that lot shall be rejected, unless the manufacturer elects to tolerance shall be corrected by means of a tapered plate or
test each bearing of the lot at his expense. In lieu of this by other means approved by the Engineer. If shim stacks
procedure, the Engineer may require every bearing of the are needed to level the bearing, they shall be removed
lot to be tested. after grouting and before the weight of the superstructure
acts on the bearing.
7 Testing of the complete bearings shall be at the
Contractor’s expense and will be witnessed by 3 Metallic bearing assemblies not embedded in the
representatives of the Engineer and the Employer. The concrete shall be bedded on the concrete with a filler or
cost for providing facilities to the Engineer or his fabric material as specified in Paragraph 11.1.2.3.
representative for witnessing the test shall be borne by the 4 Where bearings are seated directly on steel work, the
Contractor. The Contractor shall ensure access to the supporting surface shall be machined so as to provide a
manufacturer plant for the Engineer’s representatives. level and planar surface upon which the bearing is placed.
8 The Engineer may waive any or all of the bearing 5 Bearings or masonry plates which rest on steel
tests. supports may be directly installed on the supports,
provided the support is flat within a tolerance of 0.002
11.1.3.4 Packaging, Handling and Storage times the nominal dimension and is sufficiently rigid so as
1 Prior to shipment from the point of manufacture, not to deform under specified loads.
bearings shall be packaged in such a manner to ensure
that during shipment and storage, the bearings will be 11.1.4 Method of Measurement
protected against damage from handling, weather, or any
1 Measurement of bridge bearings shall be by the
normal hazard. Each completed bearing shall have its
number of each type of bearing furnished, installed,
components clearly identified, be securely bolted,
completed in place and accepted. Bearings of the same
strapped, or otherwise fastened to prevent any relative
type but of different load or movement capacities shall be
movement, and be marked on its top as to location and
measured separately.
orientation in each structure in the Project.
2 Bearing tests, installation trials, bedding, nuts and
2 All bearing devices and components shall be stored
bolts, grout injection where applicable, and temporary
at the work site in an area that provides protection from
restraint of bearings where necessary due to the sequence
environmental and physical damage. When installed,
of deck construction, measuring devices for movement
bearings shall be clean and free of all foreign substances.
and/or load, as well as plinths, downstands, masonry
3 Dismantling of bearings at the site shall not be done plates and all elements between the substructure and
unless absolutely necessary for inspection or installation. superstructure shall not be measured for direct payment

♦ 11-4 ♦
copy 249
but shall be considered as subsidiary works the costs of 4 Short-duration compression tests on bearings shall
which shall be deemed to be included in the rates for be as described in AASHTO LRFD Bridge Construction
bridge bearings. Specifications Article 18.2.5.6 except that the compression
load shall be 200 percent of the rated service load.
11.1.5 Basis of Payment 5 Shear testing on finished bearings shall be as
described in AASHTO LRFD Bridge Construction
1 The amount of completed and accepted work Specifications Article 18.2.5.8 at constant compression
measured as provided above, will be paid for at the rate loads of 50 and 100 percent of the rated service load.
for each type of “Bridge Bearing” as specified in the Bill of
6 Where elastomeric bearings are equipped with
Quantities, which rate shall be full compensation for
sliding surface of polytetrafluorethylene (PTFE) and
furnishing all materials, labor, equipment, tools, supplies
stainless steel mating surface, the PTFE shall be as
and other items necessary for proper completion of the
specified in AASHTO LRFD Bridge Construction
Work.
Specifications Article 18.8.2 and the stainless steel as
specified in Article 11.1.2.1 of these Specifications.
11.1.6 Items in the Bill of Quantities
i) Bridge bearing (type), vertical and 11.2.3 Construction Requirements
1 Installation of elastomeric bearings shall be in
horizontal loads (kN), movement (mm) (nr.)
accordance with AASHTO LRFD Bridge Construction
Specifications Article 18.2.6.
11.2 Elastomeric Bearings
2 Where elastomeric bearings are equipped with
sliding surface of PTFE and stainless steel mating surface,
11.2.1 Description the fabrication requirements shall be as specified in
1 Elastomeric bearings as defined herein shall include AASHTO LRFD Bridge Construction Specifications Article
unreinforced pads (consisting of elastomer only) and 18.8.3.
reinforced bearings with steel laminates.
2 Design of steel-reinforced elastomeric bearings shall 11.2.4 Method of Measurement
be in accordance with AASHTO LRFD Bridge Design 1 Measurement of elastomeric bearings shall be by the
Specifications Method B defined in Article 14.7.5 or number of each type of bearing furnished, installed,
Method A defined in Article 14.7.6 where the provisions of completed in place and accepted. Bearings of the same
the appropriate article are used. type but of different load capacities shall be measured
3 Bearings shall be constructed as specified in the separately.
latest edition of AASHTO LRFD Bridge Construction 2 Bearing tests, installation trials, bedding, grout
Specifications, Section 18, as complemented or modified injection where applicable, measuring devices for
herein. movement and/or load, as well as plinths, downstands,
4 Alternatively elastomeric bearings may be designed masonry plates and all elements between the substructure
and constructed in accordance with Eurocode BS EN 1337- and superstructure shall not be measured for direct
3 Structural Bearings - Part 3: Elastomeric Bearings. payment but shall be considered as subsidiary works the
costs of which shall be deemed to be included in the rates
11.2.2 Materials for bridge bearings.

1 The raw elastomer shall be either virgin Neoprene


11.2.5 Basis of Payment
(polychloroprene) or virgin natural rubber (polyisoprene)
satisfying the testing requirements in Tables 18.2.3.1-1 1. The amount of completed and accepted work
and 18.2.3.1-2 of AASHTO LRFD Bridge Construction measured as provided above, will be paid for at the rate
Specifications. Test requirements may be interpolated for for each type of elastomeric bearing as specified in the Bill
intermediate hardness. of Quantities, which rate shall be full compensation for
2 Unless otherwise specified in the contract documents, furnishing all materials, labor, equipment, tools, supplies
the elastomer shall be Grade 0, 60-durometer. and other items necessary for proper completion of the
Work.
3 Materials for elastomeric bearings and the finished
bearings themselves shall be subjected to the tests
described in AASHTO LRFD Bridge Construction 11.2.6 Items in the Bill of Quantities
Specifications Article 18.2.5. Material tests shall be in
i) Elastomeric Bearing (type), vertical and
accordance with either Table 18.2.3.1-1 or Table 18.2.3.1-2,
as appropriate. Frequency of testing shall be as specified horizontal loads (kN) (nr.)
in Article 18.2.5.2.

♦ 11-5 ♦
copy 249
11.3 Pot Bearings ii. Samples for compression set tests shall be
prepared using a Type 2 die.

11.3.1 Description
11.3.2.5 Sealant
1 Pot bearings shall:
1 The elastomer shall be lubricated between the steel
i. be adequate for the design loads and pot and the top steel bearing plate with a silicon grease
movements shown in the contract documents or which does not react chemically with the elastomer and
specified.
does not alter its properties within the range of
ii. be tested at the appropriate level.
environmental conditions expected at the site or as
recommended by the manufacturer.
2 Bearings shall be designed in accordance with the
latest edition of AASHTO LRFD Bridge Design 11.3.2.6 Sealing Rings
Specifications, Section 14.7, as complemented or modified
herein. 1 The sealing rings between the steel piston and the
elastomeric rotational element of pot bearings shall be
3 Bearings shall be constructed as specified in the
made of brass conforming to ASTM B 36 / B 36M for rings
latest edition of AASHTO LRFD Bridge Construction
of rectangular cross-section and ASTM B 121 / B 121M for
Specifications, Section 18, as complemented or modified
circular sections. The Engineer may, at his discretion,
herein.
approve other sealing ring material on the basis of test
4 Alternatively, the bearings may be designed and evidence conforming to Article 14.7.4.5 of the AASHTO
constructed in accordance with BS EN 1337-5 Structural LRFD Bridge Design Specifications.
Bearings - Part 5: Pot Bearings, as complemented or
modified herein. 11.3.2.7 Polytetrafluorethylene (PTFE) Sheet and Strip
5 All pot bearings including sliding bearing shall be 1 PTFE sheet and strip requirements for pot bearings
attached to the substructure and superstructure by shall conform to the provisions of AASHTO LRFD Bridge
mechanical fixings or other approved methods. Construction Specifications Article 18.8.1 or BS EN 1337-2
6 The capacity of bolts fixing the bearings to the Sub-Section 5.2.
substructure and superstructure shall be adequate to
11.3.2.8 Other Sliding Materials
resist solely the entire horizontal force without
consideration of any friction forces.
1 Other sliding materials shall conform to the provisions of
BS EN 1337-2 Section 5.
11.3.2 Materials
11.3.2.1 General 11.3.3 Construction Requirements
1 All materials shall be new and unused, with no 11.3.3.1 General
reclaimed material incorporated in the finished bearing.
1 Comply with AASHTO LRFD Bridge Construction
11.3.2.2 Steel Specifications as complemented or modified herein.
2 The Contractor shall provide the Engineer with
1. All steel except stainless steel components of the pot
written notification 30 days prior to the start of bearing
and disc bearing shall conform to the requirements of
fabrication.
Section 6 for carbon steel or high-strength, low-alloy
structural steel for welding. 3 The finish of the mold used to produce the
elastomeric rotational element shall conform to good
11.3.2.3 Stainless Steel machine shop practice.
1 Stainless steel shall conform to the requirements of 4 The PTFE sheet shall be bonded to a grit-blasted steel
Paragraph 11.1.2,1 item (5) of this Specification. substrate using an epoxy resin adhesive under controlled
factory conditions in accordance with the instructions of
11.3.2.4 Elastomeric Rotational Element the adhesive manufacturer. The PTFE sheet shall be
recessed into its steel substrate for at least one-half of its
1 The elastomeric rotational element used in the
thickness. If on a vertical surface, the PTFE sheet may be
construction of pot bearings shall contain only virgin,
mechanically fastened to the substrate. The attachment of
crystallization-resistant polychloroprene (Neoprene),
the PTFE sheet to its substrate shall be done in accordance
AASHTO M251 (ASTM D4014) or virgin natural
with the manufacturing requirements of AASHTO LRFD
polyisoprene (natural rubber), AASHTO M 251 as the raw
Bridge Construction Specifications Article 18.8.2,
polymer. The physical properties of Neoprene and natural
"Materials”.
rubber shall conform to the standards stated herein with
modifications as follows: 5 After fabrication, steel surfaces exposed to the
atmosphere, except stainless steel surfaces, shall be shop
i. The Shore A durometer hardness shall be 50 ±
painted or coated to protect against corrosion as specified
10 points.

♦ 11-6 ♦
copy 249
in Section 7. Surface preparation shall be as AASHTO i. Shall not exceed a single contract document or
LRFD Bridge Construction Specifications Article 18.3.3.1. project quantity.
6 Stainless steel sheet shall be attached to a steel ii. Shall not exceed 25 bearings.
substrate with an approved epoxy to ensure complete iii. Shall consist of those bearings of the same type
contact and then sealed with a continuous seal weld. All regardless of load capacity. Bearing types may
welding shall conform to and all welders shall be qualified be fixed or sliding types. Guided and non-guided
in accordance with the requirements of the current sliding bearings shall be considered to be a
AASHTO/AWS D1.5 M / D1.5 Bridge Welding Code. Except single type.
as noted, all bearing surfaces of steel plates shall be 2 Material Certification Tests: The manufacturer shall
finished or machined flat within 0.0008 mm/mm. Out-of- select, at random, samples for material certification tests
flatness greater than 0.0008 mm/mm on any plate shall be as defined in Paragraph 11.1.2.2 of this Specification,
cause for rejection. The bottom surfaces of lower bearing bearings from completed lots of bearings for testing. The
plates (masonry plates) designed to rest on bearing pads manufacturer shall complete the required testing and
shall not exceed an out-of-flatness value of 0.005 mm/mm. determine compliance with this specification before
Oxygen-cut surfaces shall not exceed a surface roughness submitting the lot(s) for quality-assurance inspection,
value 25 m, as defined by ANSI B 46.1. testing, and acceptance consideration. The results of the
7 Gross bearing dimensions shall have a tolerance in manufacturer's tests shall be furnished to the Engineer.
accordance with Paragraph 11.1.3 .2. of this specification Certification shall be provided for all elastomeric elements.
8 Every bearing shall have the project identification Their material properties shall satisfy the requirements
number, lot number, and individual bearing number as specified and the tests described in Paragraph 11.1.3.3.
well as its location on the structure indelibly marked with Additional tests may be required by the Engineer.
ink on a side that will be visible after erection. 3 Testing by the Engineer’s instruction:
9 Fabrication Requirements for the Pot: i. The manufacturer shall furnish to the Engineer
i. The pot shall be manufactured by welding or the required number of complete bearings and
machining from a single piece of plate. component samples to perform quality-
ii. The piston shall be machined from a single piece assurance testing on the expense of the
of steel. The outside diameter of the piston shall Contractor in accordance with the following:
be no more than 0.760 mm less than the inside − For Proof Load Test: one production bearing
diameter of the pot at the level of interface per lot.
between the piston and elastomeric rotational − For Coefficient of Friction Test: one
element. The sides of the piston shall be beveled production bearing per lot.
to facilitate rotation.
− Physical Properties of Elastomeric
iii. If guides are used, they shall be attached to the
Rotational Element: one elastomeric
piston by welding or bolting.
element per lot.
10 Fabrication Requirements for Sealing Rings: The − Physical Properties of PTFE Sheet: one
sealing rings shall be recessed into the elastomeric disc 250x400 mm sheet of PTFE material per
and shall fit snugly against the pot wall. Rings of project.
rectangular cross-section shall be installed with their gaps
− Bearing Horizontal Force Capacity as
equally spaced round the circumference. The gap between
Paragraph 11.1.3.3: one production bearing
the ring and the wall shall nowhere exceed 0.25 mm. The
per lot for each of (a) fixed type and (b)
gap between the cut ends of the ring shall not exceed 1.25
guided sliding type (guide test).
mm.
− Vertical Load Test as Paragraph 11.1.3.3:
11 Fabrication Requirements for Elastomeric Rotational
one production bearing per lot of each type.
Element: The elastomeric pad shall have the same
nominal diameter as the pot. The elastomeric pad shall be ii. At least one elastomeric element shall be tested
individually molded or cut from sheet and shall be made per lot of bearings. All exterior surfaces of
of no more than three separate layers, of which none may sampled production bearings shall be smooth
have a nominal thickness of less than 13 mm. The sealing and free from irregularities or protrusions that
ring recess depth shall be the same as the total ring might interfere with testing procedures.
thickness if rectangular rings are used. iii. A minimum of 30 days shall be allowed for
inspection, sampling, and quality-assurance
11.3.3.2 Sampling and Testing testing of production bearings and component
1 Lot Size: Sampling, testing, and acceptance materials.
consideration shall be made on a lot basis. A lot shall be iv. The Engineer may select, at random, the
the smallest number of bearings as determined by the required sample bearing(s) from completed lots
following criteria: of bearings and samples of the elastomeric and
PTFE materials for quality-assurance testing.

♦ 11-7 ♦
copy 249
v. The Contractor shall bear the cost of transporting 11.3.3.3 Installation
all samples from the place of manufacture to the
1. Pot bearings shall be installed in accordance with the
test site and back or, if applicable, to the Site.
contract documents and on the approved working
4 Performance Characteristics for Proof-Load Test: drawings. Upon final installation of the bearings, the
i. Critical dimensions shall include the clearance Engineer, in the presence of the manufacturer's
between the piston and the pot and shall be representative, shall inspect the bearing components to
verified by the clearance test described in assure that they are level and parallel to within 2.6 mm/m.
Paragraph 11.1.3.3. Any deviations in excess of the allowed tolerances shall be
ii. A long-term deterioration test, as described in corrected.
Paragraph 11.1.2.2 item (3) shall be performed
on one bearing of each lot of pot bearings with 11.3.4 Method of Measurement
the sealing rings with rectangular cross-section
1 Measurement of pot bearings shall be by the number
and sealing rings with circular cross-sections.
of each type of bearing furnished, installed, completed in
The bearing shall be load-tested to 150 percent
place and accepted. Bearings of the same type but of
of the specified rated capacity at 0.02 rad. If the
different load capacities shall be measured separately.
size of the bearing prohibits adequate testing
with available equipment, the Engineer may 2 Bearing tests, installation trials, bedding and epoxy
agree to test a prototype bearing with injection where applicable shall not be measured for direct
comparable requirements. payment but shall be considered as subsidiary works the
costs of which shall be deemed to be included in the rates
iii. During the test, the steel bearing plate and steel
for bridge bearings.
piston shall maintain continuous and uniform
contact for the duration of the test.
11.3.5 Basis of Payment
iv. The bearing shall be visually examined both
during the test and upon disassembly after the 1 The amount of completed and accepted work
test. Any resultant visual defects, such as measured as provided above, will be paid for at the rate
extruded or deformed elastomer, or PTFE; for each type of “Pot Bearing” as specified in the Bill of
damaged seals or limiting rings; evidence of Quantities, which rate shall be full compensation for
metal-to-metal contact between the pot wall and furnishing all materials, labor, equipment, tools, supplies
the top plate; or cracked steel, shall be cause for and other items necessary for proper completion of the
rejection of the lot. Work.
5 Sliding Coefficient of Friction Test:
i. For all guided and non-guided sliding type
11.3.6 Item in the Bill of Quantities
bearings, the sliding coefficient of friction shall i) Pot Bearing (type), vertical and horizontal
be measured at the bearing's design capacity in
loads (kN), movement (mm) (nr.)
accordance with Paragraph 11.1.3.3 and
additionally on the fifth and fiftieth cycles, at a
sliding speed of 25 mm per min. 11.4 Bridge Expansion Joints
ii. The sliding coefficient of friction shall be
calculated as the horizontal load required to 11.4.1 Description
maintain continuous sliding of one bearing,
11.4.1.1 Scope
divided by the bearing's vertical design capacity.
iii. The test results shall be evaluated as follows: 1 This Sub-section describes furnishing materials and
installation of expansion joints for bridge decks, all as and
− The measured sliding coefficients of friction
where shown on the Drawings.
shall not exceed three percent.
− The bearing will be visually examined both 11.4.1.2 Types of Joints
during and after the test. Any resultant
1 The joint construction shall be as described on the
visual defects, such as bond failure, physical
Drawings and may be one of the following types:
destruction, cold flow of PTFE to the point of
debonding, or damaged components, shall − Buried joint within the bridge deck
be cause for rejection of the lot. − Elastomeric sealed joints
− Bearings not damaged during the − Modular joints using neoprene box or band
testing of performance characteristics may sections
be used in the work. − Metallic finger joints
− Asphaltic plug joint.

2 Unless otherwise shown on the Drawings, expansion


joints shall be fully waterproof type.

♦ 11-8 ♦
copy 249
3 The bedding and nosings of expansion joints shall be i. The binder used in the construction of an
considered integral parts of the joint and the joint asphaltic plug joint must have the following
manufacturer shall be responsible for the supply of all characteristics:
constituent materials required for bedding and nosing of − remain flexible in cold conditions,
joints at the time of supplying the joint. − be stable in hot conditions,
− be flow resistant.
11.4.1.3 References
ii. The following tests shall be performed by an
1 American Association of State Highway and approved laboratory at the temperatures
Transportation Officials (AASHTO): expected in use,, and a test certificate issued
before the asphaltic plugs are delivered to Site:
AASHTO 2008 AASHTO LRFD Bridge Construction
− Extension Test,
Specifications, 2nd Edition, 2004, 2008
− Softening Point Test,
Interim Revisions.
− Flow Resistance Test.
AASHTO 2008 AASHTO LRFD Bridge Design
Specifications, 3rd Edition, 2004, 2008 2 Aggregate: The aggregate shall be single-sized 20
Interim Revisions. mm aggregate to BS 63. It shall be a clean, dry stone with
a polished stone value of 60, and a maximum flakiness
11.4.1.4 Submittals index of 25, and shall bagged to avoid contamination.

1 If the type of expansion joints for a particular


11.4.3 Construction Requirements
application is not shown in the contract documents, the
Contractor shall submit, for the Engineer’s approval, a 11.4.3.1 General
report well in advance, identifying the type of expansion
joint he intends to use for every structure. 1 The positioning of holding down bolts and
anchorage systems shall be checked for accuracy and
2 The Contractor shall furnish detailed drawings of the
agreed by the Engineer before the casting of the concrete
joint and method of assembly and installation procedure
for the joint and to locate holding down bolts or
for the approval of the Engineer.
anchorage pockets. The templates or forms shall only be
3 Material certificates, signed by manufacturers and removed with the Engineer's consent. Threaded parts
Contractor shall be provided, certifying that the joints are shall be protected, kept clean and protected from
designed in accordance with AASHTO LRFD Bridge Design corrosion by a grease coating.
Specifications or equivalent standard and AASHTO LRFD
2 Where the carriageway surfacing is removed to
Bridge Construction Specifications or equivalent and that
accommodate the bridge joint it shall be cut to a clear
they comply with the requirements of this specification.
straight line for the full depth of the surfacing without
11.4.1.5 Quality Assurance damage to the concrete substrate or the waterproofing.
3 Before installation of the joint, the concrete surfaces
1 Codes and Standards: AASHTO LRFD Bridge
shall be free from laitance, sand, clear and comply strictly
Construction Specifications.
with the joint manufacturer's requirements.
2 The Contractor shall ensure that direct site
supervision of the first of each type of joint is provided by 11.4.3.2 Nosings
an experienced technical representative of the
1 Construction of nosings at joints using epoxy mortar
manufacturer and thereafter, by competent persons who
and epoxy concrete shall be formed under the direction of
have been trained in the proper installation of expansion
a competent supervisor experienced in the use of the
joints.
material. The work shall be carried out preferably in the
warm weather. The air temperature around the joint shall
11.4.2 Materials be not less than 10 degrees C, which shall be achieved
artificially if necessary. Concrete surfaces to which
11.4.2.1 General
nosings are applied shall be dry, sound and free from
1 Storage of joints, jointing materials, sealants and laitance. Before application of the primary coat, loose
other associated items shall be in accordance with the material and dust shall be removed by an air jet tested to
manufacturer's recommendations. ensure that no oil is carried over from the compressor.
2 The elastomeric, metallic, bituminous, cementitious 2 Unless otherwise specified, surfacing shall be carried
and resin based components used in the joint construction across the joint and then cut back to accommodate the
shall all be strictly in accordance with the description in nosing. The cutting shall be done with a diamond saw to
the contract documents and the manufacturer's give a clean edge throughout the depth of the material to
specifications. be removed. Masking material shall be provided to
prevent surfacing materials adhering to the deck where
11.4.2.2 Asphaltic Plug Joints nosings are to be formed and shall be adequately located
1 Binder: to prevent displacement by the paving machine.

♦ 11-9 ♦
copy 249
3 A primary coat of unfilled epoxy resin composition cross the joints only by means of the ramps until the
shall be well worked in by brush to all surfaces with which bedding and nosing have reached full strength.
the nosings will be permanently in contact, at a uniform
rate of not less than 300 gm/square meter. The mortar 11.4.4 Method of Measurement
shall then be applied as quickly as possible while the
primary coat is still tacky. 1 Bridge expansion joints shall be measured by the
linear meter of each joint type and size (measured by
4 The epoxy mortar and epoxy concrete composition
movement range). Measurement shall be made from
shall be approved by the Engineer. Aggregate shall be
outside face of parapet to outside face of parapet whether
either silica sand, calcined bauxite or other approved
or not the joint types over carriageway, verges and
synthetic or natural aggregate of suitable grading. The
walkways for a particular joint type are similar. Special
particle size distribution shall be that which produces a
curb units, cover plates over walkways, epoxy mortar
mortar with adequate strength and workability and
bedding and epoxy concrete nosing shall not be measured
minimum voids. Aggregate shall be clean and completely
for direct payment, but shall be considered as subsidiary
dry. Whichever type of aggregate is used, the epoxy
works the costs of which will be deemed to be included in
mortar or epoxy concrete constituents shall be thoroughly
the unit rates.
mixed in a suitable mechanical mixer. The sequence,
duration and temperature of mixing shall be in accordance
with the manufacturer's instructions. 11.4.5 Basis of Payment
5 The mixed constituents shall be placed in position 1 The amount of completed and accepted work
within the time recommended by the manufacturer, well measured as provided above, will be paid for at the rates
worked against the primed surfaces and trowelled flush identified in the Bill of Quantities, which rates shall be full
with the adjacent road surface to form a dense solid compensation for furnishing, installing, fixing and for
nosing to the required profiles. Epoxy mortar shall materials, labor, equipment, tools, supplies and all other
generally be compacted in layers not exceeding 50 mm items necessary for the proper completion of the work.
thick. Where an underlying layer is more than one hour
old it shall, unless otherwise agreed by the Engineer, be 11.4.6 Items in the Bill of Quantities
primed with an unfilled epoxy resin priming coat before
placing the next course. (i) Buried Joint
movement range ( ) (lin.m.)
11.4.3.3 Installation
(ii) Elastomeric (waterproof) Joint
1 The gap width shall be set, in relation to the
movement range ( ) (lin.m.)
prevailing deck temperature, with the joint gap sides
parallel as described on the Drawings and within the joint (iii) Modular joint with neoprene
manufacturer's installation instructions. Seals shall insert, movement range ( ) (lin.m.)
remain in compression for the full range of joint
movement. (iv) Metallic finger joint with
2 Expansion joints shall be of uniform width and shall neoprene insert
be accurately set or finished and aligned flush with the movement range ( ) (lin.m.)
finished carriageway surface. Care shall be given to
ensure that metallic components are not bent or deformed (v) Metallic finger joint no insert
during handling and installation. movement range ( ) (lin.m.)
3 The installation process shall strictly comply with
(vi) Asphaltic Plug Joint
instructions given on the Drawings and by the joint
manufacturer. movement range ( ) (lin.m.)
4 The expansion joint and the waterproofing shall be
formed so that a watertight seal is provided. 11.5 Joint Seals and Fillers
5 During the placing and hardening of the bedding and
bonding materials, movement between the joint and the 11.5.1 Description
substrate shall be prevented.
1 This Sub-section describes requirements for
6 When one half of the expansion joint is being set, the furnishing and installing joint sealing and preformed
other half shall be completely free from longitudinal expansion joint filler materials as shown on the Drawings,
restraint. In particular, where templates are used to locate or as directed by the Engineer.
the two sides of a joint, they shall not be fixed
simultaneously to both sides. 11.5.2 Materials
7 Ramps shall be provided and maintained to protect
all expansion joints from vehicular loading. Vehicles shall 1 For preformed joint filler strips, refer to Section 5,
Paragraph 5.3.2.6.

♦ 11-10 ♦
copy 249
2 For joint sealants, refer to Section 5, Paragraph 11.6.2.5 Anchorage System
5.3.3.7 (7).
1 The anchorage system of parapets and rails, shall be
as shown on the Drawings and shall be subject to the
11.5.3 Construction Requirements approval of the Engineer. It shall be such that damaged
1 For construction joints, refer to Section 5, Paragraph metal posts and rails can be readily replaced without the
5.3.3.6. need for cutting the bridge deck or copings or edge units
into which the anchorages are located.
2 For contraction and expansion joints, refer to Section
5, Paragraph 5.3.3.7.
11.6.3 Construction Requirements
3 For waterstops, refer to Section 5, Paragraph 5.3.3.8.
1 During erection, the parapet units shall be securely
held in their correct positions until all connections and
11.5.4 Method of Measurement, Basis of fixings are complete and the post fixings have gained
Payment and Bill of Quantities adequate strength to develop the full holding down
moment. The assessment of the adequacy of the post
1 No separate measurement is made for joint sealers fixing shall be subject to the Engineer's approval. The
and fillers and no items are included in the Bill of finished parapets shall be true to line and level throughout
Quantities. The work shall be considered subsidiary to their length.
other items of work in the Bill of Quantities.
2 Welding of aluminum shall comply with the
requirements of BS 3019 Part 1 and BS 3571 Part 1 and all
11.6 Bridge Parapets and Railings welding shall be carried out in the factory under controlled
environment. Welding of steel parapet units shall be
11.6.1 Description carried out in factory or at site in compliance with Section
6
1 This Sub-section describes requirements for
3 The Contractor shall ensure the proper installation of
furnishing and installing bridge parapets and railings as
the posts and rails for metal bridge parapets by competent
shown on the Drawings or as directed by the Engineer.
persons who have been trained in the proper installation
of the type of bridge parapets to be installed, using tools
11.6.2 Materials and procedures recommended by the manufacturer.
11.6.2.1 Materials of Construction 4 The rails and posts of parapets shall be closed
sections, presenting no visible seam welds or exposed
1 The materials of construction of the parapet shall be bolt heads. The shape and texture of the posts and rails
aluminum alloy or structural steel or reinforced concrete. and the protective treatment to be applied shall be as
11.6.2.2 Aluminum Alloy indicated on the Drawings and no deviations and/or
alterations to these shall be permitted.
1 Aluminum alloys used for bridge parapets and 5 The standard of finish of reinforced concrete parapet
railings shall conform with the requirements of AASHTO units shall conform to finish of approved sample units
M 193 and AASHTO M 219 or BS 1470, BS 1474 and BS made before main production commences. Where minor
1490. blemishes and discolorations occur on production units,
11.6.2.3 Structural Steel making good with an approved epoxy mortar compound
will be permitted only with the express approval of the
1 Structural steel used for bridge parapets and railings Engineer. Units which are considered unacceptable for
shall conform to the requirements of Section 6 "Structural use in the works by the Engineer shall be destroyed.
Steel and Other Metal Work". The anchorage system shall Considerable care shall be given during erection of
be as shown on the Drawings or of a type approved by the parapet units to avoid cracking or otherwise damaging the
Engineer. concrete unit or its finish.

11.6.2.4 Reinforced Concrete


11.6.4 Method of Measurement
1 Reinforced concrete used for bridge parapets shall
1 Bridge parapets and railings shall be measured by
conform to the requirements of:
the linear meter of each type of parapet and railing, based
− Sub-Section 5.1 Concrete Materials and Mixes upon the lengths and dimensions shown on the Drawings
− Sub-Section 5.2 Reinforcing Steel or ordered by the Engineer
− Sub-Section 5.3 Reinforced Concrete Structures
2 Full scale dynamic testing or any other testing that
The anchorage system shall be as shown on the Drawings or may be required, expansion joints, specially fabricated
of a type approved by the Engineer. units of posts and rails for nosing areas, special
requirements at junctions with transition walls, or guard
rails, grit blasting to produce the required surface texture

♦ 11-11 ♦
copy 249
anchorages and holding down assemblies stitching and
making good to concrete and other ancillaries, will all be
considered as subsidiary works the cost of which shall be
deemed to be included in the rates for bridge parapets and
railings.

11.6.5 Basis of Payment


1 The amount of completed and accepted work
measured as provided for above shall be paid at the rates
in the Bill of Quantities, which rate shall be full
compensation for furnishing and installing all materials,
labor, equipment, tools, tests, records and all other items
for completing the works as specified.
2 Where a concrete parapet is mounted with a metal
rail, both components will be measured as one item
completely furnished and installed.

11.6.6 Item in the Bill of Quantities


(i) Concrete bridge parapet
(state type) (lin.m.)

(ii) Concrete bridge parapet with


metal rail (state type) (lin.m.)

(iii) Steel bridge parapet (lin.m.)

(iv) Aluminum bridge parapet (lin.m.)

(v) Steel pedestrian railing (lin.m.)

(vi) Aluminum pedestrian railing (lin.m.)

♦ 11-12 ♦
copy 249
12.1  General 12-1 
12.1.1  Description 12-1 
12.1.2  References 12-1 
12.1.3  Materials 12-1 
12.1.4  Construction and Installation
Requirements 12-2 
12.1.4.1  Sub-grade and Sub-base 12-2 
12.1.4.2  Curbs 12-2 
12.1.4.3  Precast Concrete Tile Paving 12-2 
12.1.4.4  Block Paving 12-4 
12.1.4.5  Cast In-situ Concrete Paving/Curbing 12-4 
12.1.5 Method of Measurement 12-4
12.1.6 Basis of Payment 12-5
12.1.7 Items in the Bill of Quantities 12-5

♦ 12-1 ♦
copy 249
♦ 12-2 ♦
copy 249
12.1 General BS 7263-1:2001 PC concrete flags, curbs, channels,
edgings and quadrants, PC
unreinforced concrete paving slabs and
12.1.1 Description
complimentary fittings:- Requirements
1 This Sub-section describes requirements for paving and test methods.
and curbs for sidewalks and other paved areas, including
precast concrete and natural stone paving, aggregate 12.1.3 Materials
bases, granular sub-bases and sub-grade, all as shown on
the Drawings. 1. Portland cement concrete shall conform to the
requirements of Section 5 and as shown on the Drawings,
2 Paving includes, as appropriate and shown on the
including HDS Section 16, SD16.20.
Drawings, hydraulically pressed precast concrete elements,
clay pavers, granite, basalt and cobbled paving, sub-bases 2. Precast concrete curbs, edgings and channels shall
and related accessories such as movement joints. In be hydraulically pressed units to conform to BS 7263,
limited cases, and only if specifically ordered by the obtained from an approved manufacturer, and of the
Engineer, cast in situ concrete paving and curbs may be sections and sizes shown on the Drawings
permitted, provided trial sample work is approved by the i. Straight units shall generally be 900mm long but
Engineer. shall be shorter where used for curves of radius
down to 12 meters,
12.1.2 References ii. Radius curb units shall be used for curves of
radius less than 12 meters
1 American Association of State Highway and
Transportation Officials (AASHTO) 3 Precast concrete paving slabs (tiles) shall be
hydraulically pressed slabs to conform to BS 7263,
M-33-99 Preformed Expansion Joint Filler for
obtained from an approved manufacturer, and of the sizes,
Concrete (Bituminous Type)
shapes, colors and surface finish shown on the Drawings.
M 235M Standard Specification for Epoxy Resin
4 Granite blocks shall conform to BS EN 1342 and 1343,
Adhesives
approved natural local granite with sawn finish, and be
2 American Society for Testing and Material (ASTM) obtained from one strata of one quarry, free from faults
D994-98 Standard Specification for Preformed and to the shapes, sizes and patterns shown on the
Expansion Joint Filler for Concrete (Bituminous Type) Drawings.
C936M – 09 Standard Specification for Solid 5 Basalt blocks shall be approved natural basalt sets to
Concrete Interlocking Paving Units BS EN 1342 and 1343 with various finishes, obtained from
3 British/European Standards one strata of one quarry, free from faults and to the
shapes, sizes, and patterns shown on the Drawings.
BS 7533-3:2005/A1 2009
6 Interlocking concrete blocks shall conform to BS
Pavements constructed with clay,
6717 [ASTM C 936], precast concrete interlocking block
natural stone or concrete pavers. Code
pavers, obtained from an approved manufacturer and to
of practice for laying precast concrete
the shapes, sizes, colors, finishes and patterns shown on
paving blocks and clay pavers for
the Drawings.
flexible pavements.
7 Interlocking clay pavers shall conform to BS6677, be
EN 1342:2001 Setts of natural stone for external
obtained from an approved manufacturer and to the
paving. Requirements and test methods
shapes, sizes, colors, finishes and patterns shown on the
EN 1343:2001 Curbs of natural stone for external Drawings.
paving. Requirements and test methods
8 Stone cobbles: selected hard smooth, egg-shaped
BS 6717:2001 Precast, unreinforced concrete paving beach or river cobble stones obtained from an approved
blocks. Requirements and test methods source and to the sizes shown on the Drawings.
BS EN197-1:2000 Cement. Composition, specifications 9 Base, sub-base and sub-grade courses for paving
and conformity criteria for low heat shall comply with requirements of Section 3 of these
common cements standard specifications and as shown on the Drawings,
EN 13139:2002 Aggregates for mortar including HDS Section 16, SD16.20.
BS 882:1992 Specification for aggregates from 10 Preformed expansion joint filler shall meet the
natural sources for concrete requirements of AASHTO M-33-99 or ASTM D994-98
EN 998-1:2003 Specification for mortar for masonry - 11 Cement-sand mortar mix for bedding of block pavers
Rendering and plastering mortar shall, unless otherwise specified, be composed of:
EN 998-2:2003 Specification for mortar for masonry - i. Ordinary Portland cement to BS EN 197-1 or, if
Masonry mortar instructed, white Portland cement to BS EN197-1.
ii. Sand to BS 882, Table 5.

♦ 12-1 ♦
copy 249
iii. Mix composition shall be Type “ii” as BS 998 3 Where specified or instructed by the Engineer curbs
1&2, to give a 28 day compressive strength of shall be bedded in adhesive. The adhesive shall be placed
not less than 5 MPa. Cement sand ratio shall not uniformly on the cleaned pavement surface or on the
be less than 1: 3 or 1:4 by volume; submit details bottom of the curb sections in a quantity sufficient to
of proposed mix for approval. result in complete coverage of the area of contact of the
curb and the pavement, with no voids present and with a
12 Where approved by the Engineer, factory premixed
slight excess after the curb has been pressed in place. The
mortar to BS EN 998-1 & 2, compressive strength at 28
curb shall be placed in position and pressure applied until
days not less than 5 MPa, may be used.
firm contact is made with the pavement. Excess adhesive
13 Bedding sand for block paving shall be clean sharp around the edge of the marker, excess adhesive on the
sand, free from deleterious salts and contaminants with pavement, and adhesive on the exposed surfaces of the
clay, silt and fine dust content of not more than 3% by marker shall be immediately removed. The curb shall be
mass. They shall be obtained from a single source, protected against impact until the adhesive has hardened.
consistently graded according to the requirements of BS
4 Mixing of adhesive shall be performed in limited
7533-3, Table 2. Sand that will stain paving should not be
quantities such that the curb sections shall be aligned and
used. Bedding sand should be maintained at an even
pressed into place within five (5) minutes after mixing the
moisture content which will give maximum compaction
adhesive components. Any mixed batch of adhesion,
during block laying.
which becomes so viscous that the adhesive is not readily
14 Epoxy adhesive shall conform to the requirements of extruded from under the curb on application of slight
AASHTO M 235M, Standard Specifications for Epoxy pressure, shall not be used.
Resin Adhesive, for the type of application required.
12.1.4.3 Precast Concrete Tile Paving
12.1.4 Construction and Installation 1 Tiled sidewalks shall be constructed in accordance
Requirements with the dimensions and levels shown on the Drawings or
as directed by the Engineer. All areas inside channelizing
12.1.4.1 Sub-grade and Sub-base islands shall also be provided with a sidewalk pavement,
1 The sub-grade shall be excavated to the required unless otherwise shown on the Drawings or as directed by
depth and to the width to receive sub-base and paving and the Engineer.
to permit installation and bracing of the forms where 2 Precast tiles shall be manufactured by an automatic
needed. The foundation shall be shaped and compacted to plant of the central batch high pressure type, erected in a
an even surface conforming to the sections shown on the special yard reserved specifically for this purpose. The
Drawings. All soft and yielding material shall be removed plant shall be equipped with a double feeding system, one
and replaced with acceptable material. for the upper layer, and another for the lower layer of the
2 Prior to commencing laying paving blocks, paving tile. Manual intervention shall be a minimum.
tiles and stone paving, the prepared sub-grade surface 3 Operation of the plant shall be such that it shall first
shall be cleared of loose and waste material and prepared discharge enough mortar materials into the form for the
to receive sub-base as per Section 3, Clause 3.2.3. upper layer, and after preliminary vibration and uniform
3 Granular sub-base shall be constructed where shown leveling, the coarse mixture for the lower layer shall then
or directed by the Engineer, and shall be placed in layers be discharged into the tile form. The high pressure
not exceeding one hundred fifty (150) millimeters in depth automatic device shall be used only after a second
and each layer shall be compacted to at least 95% of dry vibration and leveling of the material has taken place. Tiles
density. shall not be disturbed during setting of the concrete.
4 Curing of the tiles shall take place in a closed curing
12.1.4.2 Curbs room where the Contractor shall provide an automatic
1 Curb sections shall be hydraulically pressed in steam curing system to be operated as approved by the
approved molds under conditions of controlled Engineer. The capacity of the curing room shall permit
temperature and humidity. Sections shall be water or acceptance and complete curing of the daily plant
steam cured until the concrete attains one hundred (100) production of tiles.
percent of specified strength. Curbs shall have a clean 5 The period of curing shall be at least one full day at a
finish with smooth surfaces. Segregation, honeycombing temperature of fifty-five to seventy-five degrees Celsius
or broken corners will not be allowed and remedial (55 o to 75o C). This period may be subject to changes and
measures will not be accepted. adjustments after direct tests have been made on the
2 Curbs shall be placed to the lines shown on the production or as directed by the Engineer.
Drawings or established by the Engineer. The Contractor 6 Tiles shall not be imperfectly finished, and shall be
shall mark the location where each section is to be placed free from segregation, honeycombing, broken or damaged
and the marks shall be approved by the Engineer prior to corners and imperfect plan faces. Correction of defects by
beginning work. No curb sections shall be placed over polishing, retouching or any other means will not be
longitudinal or transverse joints of the pavement surface. permitted. Approval of the tiles given by the Engineer at

♦ 12-2 ♦
copy 249
any stage of the work shall not prejudice the Engineer's run of the grinding wheel of five hundred (500) meters. For
right to later discard any imperfect tiles. Final approval materials with a surface wearing layer different from the
shall be given only after the tiles have been completely rest of the tile, the distance run must be such that the disc
positioned in-situ. Rejected tiles shall be removed from does not penetrate into the lower layer. The thickness of
the site and replaced. the layer abraded in millimeters with a pressure of three-
tenths (0.3) kilogram per square centimeter for a distance
7 The following tests shall be carried out on sidewalk
run of one thousand (1000) meters is taken as the
to tiles to ascertain their suitability for the Work:
Abrasion Factor. This factor is determined by assuming
i. Impact Strength that the consumption is proportional to the distance run.
ii. Flexural Strength The limit acceptance value for the Abrasion Factor shall be
iii. Abrasion Resistance twelve (12) millimeters maximum

8 Impact Strength Test; this test establishes the 11 Tiles shall be laid with joints between tiles and
minimum height of fall of a steel ball weighing one kg. between tiles and curbs nominally 10mm wide,
which, when striking the tile in the middle, breaks it. The completely filled with 1:2 cement/sand mortar or a grout
product of the height of the fall by the weight of the ball is for the full thickness of the tile by use of proper tools,
taken as the Impact Strength, limiting value: 0.5 kg -meters during and after positioning of the tiles. All transverse and
minimum. longitudinal joints shall be in proper line and in the correct
pattern, to ensure a neat and workmanlike appearance.
9 Flexural Strength; this test is carried out by placing a
tile on two knife supports, with edges rounded with a 12 As soon as the mortar or grout has partially set, the
radius of one (1) centimeter, arranged parallel to the side Contractor shall rake all mortar material from the groove
of the tile and ten (10) centimeters apart. The load is formed by the two adjacent bevels, and from the first
gradually transmitted to the tile top surface, along the three mm. depth of the joint, using appropriate tools.
centerline, by a third knife arranged parallel to the other 13 When the mortar has sufficiently set, the Contractor
two. shall sprinkle the sidewalk with water and shall cover it
The unit maximum bending stress = fifteen (15) Phb ,
2 with plastic or nylon sheets to avoid evaporation of water
during the curing period. The sheets shall be left in place
where :
until completion of setting of the mortar and concrete, or
'P' is the total breaking load in kilograms, 'b' is the as ordered by the Engineer. The Contractor shall then
width of the tile in centimeters and 'h' is the remove all foreign matter, wood, concrete or mortar
thickness of the tile in centimeters. lumps, etc., leaving the sidewalk in a neat, clean and tidy
The limit acceptance value for Flexural Strength shall be condition.
thirty (30) kilograms per square centimeter minimum. 14 In cases where tiles are required to be cut, due to the
10 Abrasion Resistance; this test is carried out with a presence of obstacles, poles, hydrants, etc., or in the
machine composed of a horizontal cast-iron disc, rotating construction of driveways or side roads, etc., the
about its vertical central axis at uniform speed; a Contractor shall cut the tiles and/or substitute in-situ
horizontal diametrical crosspiece by means of which two concrete of at least the same quality as the tiles. The
samples are pressed on the disc, at such a distance from Engineer shall decide, after trials, on the method to be
the center of the disc that the relative speed with respect adopted. This operation shall be kept to a minimum. The
to the disc, is one meter per second; a second horizontal Contractor shall complete as much as practicable of the
diametrical cross-piece orthogonal to the first, which is sidewalk using precast tiles.
carried at either end; appropriate devices to let the 15 Where the sidewalk crosses the entrance to a shop or
moistened abrasive flow onto the track; two pairs of a house the level of which is higher than the sidewalk, the
conveniently arranged brushes to guide the abrasive that Contractor shall construct steps, formed by a curb and a
tends to escape under the samples. The samples, pressed complete or partial tile. The steps shall be backfilled with
against the disc, rotate by means of a special mechanical concrete of the same quality as specified for tile
device, around their own vertical central axis, at the rate of foundations.
one turn of the specimen for fifty (50) turns of the disc.
16 A step shall be constructed wherever the difference
Carborundum grit sufficiently coated with liquid mineral
in elevation between the entrance and the sidewalk is
oil with an Engler viscosity between five (5) and seven (7)
more than three hundred (300) millimeters. The Contractor
at fifty degrees Celsius (50o C.) shall be used as an
shall submit to the Engineer, prior to commencing any
abrasive. The grit shall pass Sieve No. 60 and be retained
sidewalk construction, a list of locations where steps will
on Sieve No. 100. Consumption of carborundum and oil
be required, together with design details for construction
should be approximately twenty (20) and twelve (12)
of such steps.
grams, respectively, per minute. The square sample, with
a surface area of fifty (50) square centimeters shall be 17 Driveway pavements shall be constructed to the
pressed against the disc by a total of fifteen (15) kilograms same standards as specified for sidewalks.
unit pressure of three tenths (0.3) kilograms per square
centimeter. The test is normally carried out with a distance

♦ 12-3 ♦
copy 249
18 The tolerances for sidewalk, drive way and median all joints shall be edges with a five (5) millimeter radius
paving construction shall be plus or minus six (6) edging tool.
millimeters from the designed grade elevation. 5 Expansion joints for paving shall be in the locations
and of the dimensions specified, and shall be filled with
12.1.4.4 Bedded and Interlocking Block Paving approved pre-molded expansion joint filler. Sidewalks
1 Bedded block paving shall be bedded in mortar and shall be divided into sections by weakened plane joints
laid to the pattern shown on the Drawings or directed by formed by a jointing tool or other acceptable means as
the Engineer. A bed of stiff mortar should be spread and directed. These joints shall extend into the concrete for
leveled. Blocks shall be individually laid and hammered about one fourth (¼) to one fifth (1/5) of the depth and
down so that tops are level, leaving joints open. Joints shall be approximately three (3) millimeters wide. Joints
shall be carefully and thoroughly filled flush with the shall match as nearly as possible adjacent joints in curb or
surface of the blocks using mortar of stiff plastic pavements. Weakened plane joints may be sawed in lieu
consistency. Finishing shall be neat and cleaned of any of forming with a jointing tool.
mortar from the face of blocks before it sets. Joint widths 6 Construction joints in paving shall be formed around
in stone block paving are to be a nominal 10 mm. all appurtenances such as manholes, utility poles, etc,
2 Interlocking block paving shall be laid and bedded in extending into and through the sidewalk, drive way, or
accordance with the Drawings. Unless otherwise specified, median. Pre-molded expansion joint filler one (1)
paving shall not be commenced until adjacent curbs, centimeter thick shall be installed in these joints.
edgings and channels have been installed and sufficiently Expansion joint filler of the thickness indicated shall be
matured. Blocks shall be laid to the required pattern on the installed between concrete construction and any fixed
sand bed and thoroughly compact with a vibrating plate structure such as a building or bridge. This expansion joint
compactor as the work proceeds. After infilling at the material shall extend for the full depth of the concrete
restraining edges; the same compacting effort shall be construction.
applied over all areas, avoiding damage to edges and 7 Concrete shall be cured by membrane or water in
adjacent work. Compaction shall not be conducted within accordance with Section 5, ‘Curing and Protection’.
1 m of any working face. Un-compacted areas of paving
shall not be left at the end of working periods, except 12.1.5 Method of Measurement
within 1m distance of an unrestrained edge. Compacted
paving shall be checked initially and at frequent intervals 1 Precast concrete tiled paving, concrete and clay block
to ensure surface levels are correct. Where unsatisfactory, paving and natural stone paving shall each be measured
blocks shall be lifted, the bedding adjusted and blocks re- separately by the square meter for each type, authorized,
laid as necessary. Dry bedding sand shall be brushed into completed, and accepted by the Engineer based on the
the joints, followed by the re-vibration of the surfaces. horizontal dimensions shown on the Drawings or ordered
This shall be repeated until all joints are completely filled. by the Engineer.
2 In-situ concrete paving, where specifically instructed
12.1.4.5 Cast In-situ Concrete Paving/Curbing
by the Engineer, shall be measured by the square meter of
1 In situ concrete paving and curbing, where directed the area shown or instructed, stating the thickness. In-situ
by the Engineer, shall conform to the appropriate concrete paving for irregular shapes or in locations where
requirements of Section 5. other paving types are used, will not be measured
separately but will be deemed to be included in the area of
2 Forms shall be of metal, wood, or other suitable
the adjacent paving.
material and shall extend for the full depth of the concrete.
All forms shall be geometrically accurate, free from warp, 3 In-situ concrete curbs, where specifically instructed
and of sufficient strength to resist the pressure of the by the Engineer, shall be measured by the linear meter of
concrete without displacement. Bracing and staking of completed and accepted work.
forms shall be such that the forms remain in both 4 Precast concrete curbs of each type, including all
horizontal and vertical alignment until their removal. All blinding and haunching, shall be measured by linear
forms shall be cleaned and oiled before concrete is placed meters. Depressed curbs at driveway entrances and the
against them. like will not be measured separately but will be included
3 Mixing and Placing Concrete. The foundation shall be as a normal length of standard curb as specified.
thoroughly moistened immediately prior to the placing of 5 Excavation for paving and curb shall not be
the concrete. The proportioning and mixing of the measured separately for payment but will be considered
concrete shall be in accordance with the requirements for as subsidiary work, except when such excavation is a part
the class of concrete specified. The concrete shall be of, and is measured in conjunction with, the roadway
deposited in one course in such a manner as to prevent excavation. In such instances, the excavation shall be
segregation and consolidation by vibrators. measured and included in the quantity of roadway
4 The surface of paving shall be finished with a excavation as per Section 2.
wooden float and light brooming. No plastering of the 6 Preparation of sub-grade, supply, transport and laying
surface will be permitted. All outside edges of the slab and sub-base and bedding courses, concrete bases incidental

♦ 12-4 ♦
copy 249
to curbs and the like, finishing, cleaning and protecting
paving, and tests on materials shall not be measured
separately but shall be considered subsidiary work, the
cost of which is deemed to be included in the rates stated
in the Bill of Quantities for the relevant items.

12.1.6 Basis of Payment


1 The completed and accepted work, as measured
above, will be paid for at the unit rates in the Bill of
Quantities, which shall be full compensation for supply,
transport and installation of all required materials,
equipment, tools, labor, and all other items necessary for
the proper completion of the Work as specified.

12.1.7 Items in the Bill of Quantities


1 Payment for the work will be made under one or
more of the following items:
i. Precast concrete tile paving (type) (sq.m.)
ii. Block paving (type) (sq.m.)
iii. Natural stone paving (type) (sq.m.)
iv. Cast in-situ concrete paving (type;
thickness) (sq.m.)
v. Precast concrete curb (type) (lin.m.)
vi. Cast in situ concrete curb (type) (lin.m.)

♦ 12-5 ♦
copy 249
copy 249
Ref. Title Page No.
13.1 Roadside Barriers 13-1
13.1.1 Description 13-1
13.1.2 References 13-1
13.1.3 Materials 13-1
13.1.3.1 Metal Components 13-1
13.1.3.2 Concrete Components 13-2
13.1.3.3 Delineators 13-2
13.1.3.4 Other Materials 13-2
13.1.4 Construction and Installation
Requirements 13-2
13.1.4.1 Metal Guardrails 13-2
13.1.4.2 Concrete Barriers 13-3
13.1.4.3 Impact Attenuators 13-3
13.1.5 Method of Measurement 13-4
13.1.6 Basis of Payment 13-4
13.1.7 Items in the bill of Quantities 13-4

13.2 Fence 13-4


13.2.1 Description 13-4
13.2.2 References 13-4
13.2.3 Materials 13-5
13.2.4 Construction and Installation
Requirements 13-5
13.2.5 Method of Measurement 13-6
13.2.6 Basis of Payment 13-6
13.2.7 Items in the Bill of Quantities 13-6

♦ 13-0 ♦
copy 249
copy 249
13.1 Roadside Barriers 13.1.3 Materials
13.1.3.1 Metal Components
13.1.1 Description
1 Metal beams, guardrail elements and backup plates
1 This Sub-section describes roadside barriers and
for W-beam or Thrie-beam rail shall conform to the
fences, including crashworthy metal beam, concrete
requirements of AASHTO M180, Class A, Type 2.
barriers and other safety barriers, barrier terminals, and
Galvanized rail elements shall be designed to be
portable and permanent impact attenuators. This Sub-
spliced at intervals not to exceed either four (4) or
section applies also to reinstallation/retrofitting of metal
eight (8) meters and such splices shall be made at
beam guardrail, concrete barriers and guardrail terminals,
posts, unless otherwise shown on the Drawings. Rail
impact attenuators and steel safety railings.
elements to be erected on a radius of forty-five (45)
meters or less shall be shaped in the shop and the
13.1.2 References radius of curvature shall be stenciled on the back of
1 American Association of State Highway and each section of rail.
Transportation Officials (AASHTO) 2 Posts and miscellaneous barrier rail hardware; unless
otherwise indicated on the Drawings, all steel posts,
AASHTO M160 Standard Specification for General
plates, angles, channels, brackets, and anchor
Requirements for Steel Plates, Shapes,
assembly units shall conform to the requirements of
Sheet Piling, and Bars for Structural
ASTM A 36. Cold rolled post sections shall conform
Use.
to the requirements of ASTM A 653M, Grade B.
AASHTO M180 Standard Specification for Corrugated 3 Swage fittings for anchor terminals shall be
Sheet Steel Beams for Highway machined from hot-rolled carbon steel conforming
Guardrail to the requirements of ASTM A 576, Grade 1035, and
shall be annealed suitable for cold swaging. A lock
AASHTO M237 Standard Specification for Epoxy-Resin
pin hole shall be drilled through the swage fitting
Adhesives for Bonding Traffic Markers
head to accommodate a seven (7) millimeter, plated,
to Hardened Portland Cement and
spring steel pin to retain the stud in position. The
Asphalt Concrete
stud shall be steel conforming to the requirements of
2 American Society For Testing and Material ASTM A 449. Prior to galvanizing, a ten (10)
millimeter slot for the locking pin shall be milled into
ASTM A36 Standard Specification for Carbon
the stud end. The swage fitting, stud, and nut shall
Structural Steel
develop the full breaking strength of the wire cable.
ASTM A653M Standard Specification for Steel Sheet, 4 All bolts shall conform to the requirements of ASTM
Zinc-Coated (Galvanized) or Zinc-Iron A 307, except those designated on the Drawings as
Alloy-Coated (Galvannealed) by the high strength shall conform to the requirements of
Hot-Dip Process. ASTM A 325 or A 449. All nuts shall conform to the
ASTM A576 Standard Specification for Steel Bars, requirements of ASTM A 563M, Grade A or better,
Carbon, Hot-Wrought, Special Quality except those designated on the Drawings as high
strength shall conform to the requirements of ASTM
ASTM A449 Standard Specification for Hex Cap A 563M, Grade C or better.
Screws, Bolts and Studs, Steel, Heat 5 Galvanizing for all ferrous materials for guardrail,
Treated, 120/105/90 ksi Minimum
guardrail anchor terminals, impact attenuators, glare
Tensile Strength, General Use screens, and delineators shall be galvanized after
ASTM A325 Standard Specification for Structural fabrication unless otherwise specified. Galvanization
Bolts, Steel, Heat Treated, 120/105 ksi shall be in accordance with ASTM A 123M or ASTM
Minimum Tensile Strength. A 153M as appropriate.
6 All components shall be fabricated and galvanized
ASTM A563 Standard Specification for Carbon and
for installation without further drilling, bending,
Alloy Steel Nuts
cutting or welding. When field modifications are
ASTM A123M Standard Specification for Zinc (Hot- approved by the Engineer, or when minor damage to
Dip Galvanized) Coatings on Iron and the galvanized coating occurs, the exposed surface
Steel Products shall be repaired by thoroughly cleaning and
applying two (2) applications of paint as specified in
ASTM A153M Standard Specification for Zinc Coating
Section 7, Clause 7.2.6, "Zinc Dust-Zinc Oxide
(Hot-Dip) on Iron and Steel Hardware
Primer."
ASTM A413M Standard Specification for Carbon Steel 7 Impact Attenuators:-
Chain i. Rail elements for Thrie beam rail (used in Guard
Rail Energy Absorbing Terminal - G.R.E.A.T.

♦ 13-1 ♦
copy 249
Impact Attenuators) shall conform to AASHTO 2 Reinforcing steel shall be of the size and grade
M180, Class B, Type galvanized. Rail element shown on the Drawings and shall conform to the
joints shall be fabricated to lap not less than provisions of Sections related to "Reinforcing Steel" in
thirty (30) centimeters and be bolted. The rail Section 5 of these Standard Specifications.
metal, in addition to conforming to the
13.1.3.3 Barrier Reflectors
requirements of AASHTO M 180, shall withstand
a cold bend, without cracking, of two hundred 1 Guardrail Reflectors: Metal W-beam and Thrie-beam
(200) grads around a mandrel of a diameter guardrail reflectors and associated hardware shall
equal to two and one half (2½) times the conform to the requirements of the Drawings, Special
thickness of the sheet metal plate. Specifications and M.U.T.C.D. (Manual of Uniform Traffic
ii. Restraining chains for G.R.E.A.T. impact Control Devices). When shown on the Drawings or stated
attenuators shall be twelve (12) millimeter in the Special Specifications, reflective sheeting shall be
nominal size and shall conform to the fixed to the approach ends of metal beam guardrail
requirements of ASTM A 413M, Grade 28. terminals and be Type IV (microprismatic) high intensity
iii. QuadGuard metal work shall be fabricated from retro-reflective sheeting.
either M1020 Merchant Quality or ASTM A-36 2 Concrete barrier reflectors shall conform to the
steel. After fabrication, metal work shall be requirements of the Drawings, Special Specifications, and
galvanized in accordance with ASTM A-123M. All M.U.T.C.D. Epoxy resin adhesives for bonding delineators
welding shall be done by or under the direction to hardened Portland cement concrete shall conform to
of a certified welder. AASHTO M 237.
iv. The QuadGuard system shall be assembled with
galvanized fasteners. All bolts, nuts and washers 13.1.3.4 Other Materials
shall be Commercial Quality “American National
1 Other Materials: Other materials shall be as shown
Standard” unless otherwise specified.
in the Drawings, stated in the Special Specifications or in
v. The QuadGuard diaphragms shall be made from
the U.S. American Road Builders Transportation
10 gauge steel Quad-beam sections. The
Association (ARBTA) Bulletin No. 268 "A Guide to
diaphragms shall be available in widths of 610,
Standardized Highway Barrier Rail Hardware.” Special
760 and 910 mm [2', 2'-6" and 3']. Two support
materials for impact attenuators shall be as specified by
legs shall be welded to the Quad-beam. Ski-
the manufacturer.
shaped plates shall be welded to the bottom of
the support legs. The diaphragms shall be
designed to lock onto and be guided by a
13.1.4 Construction and Installation
ground-mounted, center monorail support Requirements
structure.
13.1.4.1 Metal Guardrails
vi. The QuadGuard fender panels shall be fabricated
from 10 gauge steel Quad-beam sections. Each 1 Metal W-beam and Thrie-beam guardrail. shall be
fender panel shall be drilled and slotted in installed at the locations shown on the Drawings or as
accordance with the manufacturer’s ordered by the Engineer. Posts shall be installed by
specifications so that when assembled in the driving plumb to the required grades or set in concrete as
field, the front end shall be bolted to a shown or directed by the Engineer. When the pavement is
diaphragm by means of the three (3) 15.9 mm within one (1) meter of the guardrail, the posts shall,
(5/8") bolts. unless otherwise directed by the Engineer, be set before
vii. Impact attenuation devices with cartridges filled placing the pavement.
with liquids, such as antifreeze agents, that may
2 If ground conditions are such that pilot holes are
become a skid hazard when impacted, shall not
necessary to prevent damage to posts during driving, all
be used; replaceable cartridges with foam-filled
space around steel posts after driving shall be filled with
cardboard, lightweight concrete and similar
dry sand or fine gravel.
materials will be acceptable. All units shall be
3 When posts are set in concrete, the concrete shall be
identified by identification labels fastened at a
placed against the excavated earth unless otherwise
protected but conspicuous location.
permitted.
13.1.3.2 Concrete Components 4 Continuous lengths of rail or cable shall be installed
1 Concrete for post supports, buried footings, and and alignment checked and adjusted before final
anchors and for concrete barriers and terminal sections tightening of bolts, etc. Unless otherwise specified, bolted
shall conform to the requirements for concrete as connections shall be torque to six (6) to seven (7)
described in Section 5. Types and strength of concrete kilogram-meters. Bolts that extend at least six (6)
shall be as stated on the Drawings and in the Special millimeters but not more than twenty-five (25) millimeters
Specification. beyond the nuts shall be used. Rail elements shall be
erected in a smooth continuous line with the laps in the
direction of traffic flow.

♦ 13-2 ♦
copy 249
5 Posts may be erected by driving with approved be indicated by an offset guide line set by the Contractor
mechanical devices. The method of driving shall not and approved by the Engineer.
substantially alter the cross-sectional dimensions of the 4 The forming portion of the extrusion machine shall
posts or materially damage the galvanization / coating. be readily adjustable vertically during the forward motion
Battered tops shall not be accepted. Posts which, in the of the machine to conform to the predetermined grade
opinion of the Engineer, are bent or otherwise damaged line. A grade line gauge or pointer shall be attached to the
during or after erection, shall be removed and replaced at machine in such a manner that a continual comparison
the Contractor’s expense. can be made between the barrier being placed and the
6 Damaged galvanized surfaces may be repaired, only established grade line as indicated by the offset guide line.
if so approved by the Engineer. Such surfaces shall be Other means of controlling barrier grade may be
repaired by thoroughly wire brushing and then applying permitted by the Engineer. Expansion joints of the width
two coats of primer in accordance with Section 7, Clause shown on the plans shall be constructed by sawing
7.2.6. through the barrier section to its full width. If sawing is
performed before the concrete has hardened, the adjacent
7 Guardrail anchor terminals shall be installed at the
portions of the barrier shall be firmly supported with close
locations shown on the plans or ordered by the Engineer
fitting shields. When sawing is performed after the
all in accordance with the Drawings and Special
application of curing compound, the exposed faces of the
Specifications.
barrier in the vicinity of the joint shall be treated with
13.1.4.2 Concrete Barriers curing compound after sawing the joint.
5 If stationary forms for concrete barriers are used,
1 Construction of concrete barriers and terminal
they shall be removed as soon as possible after the
sections shall conform to the Drawings and Special
concrete has set enough to maintain the shape of the
Specification. Concrete barriers shall present a smooth,
barrier without support in order to facilitate finishing. The
uniform appearance in their final position, conforming to
surface shall be free from pits larger than one (1)
the horizontal and vertical lines shown on the Drawings or
centimeter in diameter. The surface shall be given a final
as ordered by the Engineer, and shall be free of lumps,
soft brush finish with strokes parallel to the line of the
sags, or other irregularities. The top and exposed faces of
barriers. Finishing with a brush application of grout will
the barrier shall not vary more than more than six (6)
not be permitted. Surfaces shall be finished as necessary
millimeters between any two (2) contact points when
to produce smooth, even surfaces of uniform texture and
tested with a four (4) meter straightedge laid on the
appearance, free from bulges, depressions, and other
surfaces. Transverse expansion joints of one (1)
imperfections. The use of power sanders, carborundum
centimeter thick pre-molded filler shall be provided in all
stones, or disks may be required to remove bulges or
concrete barriers at spacing not exceeding fifteen (15)
other imperfections.
meters center to center. All transverse expansion joints
will be weather sealed with a smooth and uniform bead of 6 Exposed surfaces of concrete barriers shall be cured
durable sealant approved by the Engineer. by the "water method" in accordance with the provisions
of “curing and protection" in Section 5 Paragraph 5.3.3.12.
2 Concrete barriers may be precast, cast-in-place with
The Engineer may permit the concrete barriers to be cured
fixed forms, or extruded with slip forms at the Contractor's
by use of "curing compound" in accordance with the
option and approval of the Engineer. Concrete barriers
provisions of Section 5, Paragraph 5.3.3.12 of these
constructed by casting-in-place with fixed forms shall
Standard Specifications.
conform to the provisions of Section 5. Concrete shall be
Class 25 as per Paragraph 5.1.3.4. 13.1.4.3 Impact Attenuators
3 Concrete barriers constructed by means of an
1 G.R.E.A.T. system and other impact attenuators shall
extrusion machine or other similar type equipment shall
be installed in accordance with the requirements
be of thoroughly consolidated concrete, and the exposed
/recommendations / instructions provided by the
surfaces shall conform to the requirements of Section 5.
manufacturers and all to the approval and satisfaction of
The Contractor shall furnish evidence of successful
the Engineer. A copy of these recommendations and
operation of the extrusion machine or other equipment by
instructions shall be furnished to the Engineer upon
constructing a trial section of barrier or by other evidence
delivery of the materials.
suitable to the Engineer. Concrete shall be fed to the
extrusion machine at a uniform rate. The machine shall be 2 The QuadGuard System shall consist of crushable
operated under sufficient uniform restraint to forward cartridges surrounded by a framework of steel Quad-beam
motion to produce a thoroughly consolidated mass of guardrail which can telescope rearward during head-on
concrete free from surface pits larger than two (2) impacts. The QuadGuard System shall have a center
centimeters in diameter and requiring no further finishing. monorail which will resist lateral movement during side
The concrete shall be of such consistency that, after angle impacts. The nose shall consist of a formed plastic
extrusion, it will maintain the shape of the barrier without nose wrap.
support. The grade for the top of the concrete barrier shall 3 A bay describes a section of the QuadGuard System
consisting of a cartridge, a diaphragm and two fender

♦ 13-3 ♦
copy 249
panels. Each bay shall be fitted with an energy absorbing 6 Guardrail and concrete barrier reflectors shall not be
cartridge. The outside of the cartridge shall be fabricated measured for separate payment. Their installation will be
from a weather resistant plastic. The front portion of the considered subsidiary to the construction of the guardrail
system shall be fitted with Type I cartridges. The rear or concrete barriers.
portion of the system shall be fitted with Type II cartridges. 7 Terminals, terminal end sections, and impact
All cartridges shall include a cartridge replacement attenuators shall be measured by the unit for each type
indicator. authorized, completed and accepted by the Engineer,
4 The rear end of each Quad-beam fender panel shall based on the number of units shown on the Drawings or
overlap and be connected to the diaphragm of the next ordered by the Engineer.
bay by means of a bolt and enlarged “mushroom” washer.
The bolt fits through the long horizontal slot in the forward 13.1.6 Basis of Payment
fender panel. This permits the movement, front to back, of
1 The completed and accepted work, as measured
one set of fender panels relative to the panels in the
above, will be paid for at the contract unit rates in the Bill
underlying-rearward bay. The back portion of each fender
of Quantities. There will be no separate payment for posts.
panel shall be tapered to help maximize performance
Payments in accordance with the unit rates shall be full
during wrong-way, re-directive impacts.
compensation for all required materials, transport,
5 The monorail support structure shall be made of equipment, tools, labor, and all other items necessary for
steel and be anchored to a specified concrete pad. The the proper completion of the work.
monorail shall prevent lateral movement, vertical
movement and overturning movement of the diaphragms
13.1.7 Items in the Bill of Quantities
during design impacts.
6 The nose section shall contain a nose cover and a 1 Payment for the work will be made under one or
crushable cartridge and is not counted as a bay. The nose more of the following items:
cover shall be made from a plastic material formulated to
resist weathering. The nose shall attach to the front (i) W-Beam G/rail, standard section (type) (lin.m.)
diaphragm. Standard colors shall be gray or yellow. (ii) W-Beam G/rail, transition section (type) (lin.m.)
(iii) W-Beam G/rail, terminal (end type) (nr.)
(iv) Thrie Beam G/rail, standard section (lin.m.)
13.1.5 Method of Measurement
(v) Thrie Beam G/rail transition
1 Guardrails of each type and, reinstallation of section (type) (lin.m.)
guardrails, are each measured by the linear meter along (vi) Thrie Beam G/rail, terminal( end type) (nr.)
the front face, excluding terminal sections. Measurement (vii) Concrete Barrier, single face (type) (lin.m.)
shall be based on the dimensions as shown on the (viii) Concrete Barrier, double face(type) (lin.m.)
Drawings or ordered by the Engineer. (ix) Concrete Barrier, transition
2 No separate measurement is made for posts, blocks, Section (type) (nr.)
plates, splices, bolts , nuts, screws, studs and other fixing (x) Impact Attenuator (type) (nr.)
accessories nor for excavation and concrete post bases, all (xi) Guardrail Re-installation (type) (lin.m.)
of which work is considered as subsidiary to the guardrail
and their cost is deemed to be included in the rates for 13.2 Fences
guardrail.
3 Guardrail transition sections, including hardware 13.2.1 Description
necessary to meet the requirements of the installation,
1 This Sub-section describes furnishing and installing
shall be measured separately only when the transition
fences, gates, and guards in accordance with the Drawings
section is shown on the Drawings and listed in the Bill of
and Special Specification, at the locations and to the lines
Quantities. Otherwise such work shall be considered
and grades shown on the plans or ordered by the
subsidiary to the standard guardrail section.
Engineer. The work shall include all foundation or/ and
4 Concrete barriers of each type are measured by additions needed to have a fully operational system.
linear meters, based on the dimensions shown on the
Drawings or ordered by the Engineer
13.2.2 References
5 No separate measurement is made for the barrier
base, reinforcement bars, dowel bars or concrete filling, 1 American Society For Testing and Material
Excavation for the concrete barriers shall not be measured ASTM A 392 Specification for Zinc-Coated Steel
separately but will be considered as subsidiary work Chain Link Fence Fabric
except when such excavation is part of and is measured in
conjunction with the roadway excavation. In such ASTM A 53M -07 Standard Specification for Pipe, Steel,
instances, the barrier excavation shall be measured and Black and Hot-Dipped, Zinc-Coated,
included in the quantity of unclassified excavation as Welded and Seamless
provided for in Section 2.

♦ 13-4 ♦
copy 249
ASTM A501 - 07 Standard Specification for Hot-Formed 9 Tie wire shall conform to ASTM A112 (withdrawn
Welded and Seamless Carbon Steel 1990 with no replacement), and shall be minimum three
Structural Tubing and five tenths (3.5) millimeters diameter unless otherwise
shown.
ASTM A618M - 04 Standard Specification for Hot-Formed
Welded and Seamless High-Strength 10 Concrete for setting posts shall conform to the
Low-Alloy Structural Tubing requirements of Section 5, Sub-section 5.1.3.4.
11 Reinforcing steel shall be of the size and grade
ASTM A123M-09 Standard Specification for Zinc (Hot-
shown on the plans and shall conform to Section 5, Sub-
Dip Galvanized) Coatings on Iron and
section 5.2
Steel Products
12 Materials for gates shall be of the sizes, dimensions
ASTM A153M-09 Standard Specification for Zinc Coating and types indicated in the Drawings.
(Hot-Dip) on Iron and Steel Hardware
13 Gate perimeter frames shall be fabricated of tubular
2 British Standards members. Additional horizontal and vertical members
shall be provided to ensure proper gate operation and for
BS 4360 HR Steel for general engineering purposes attachment of fabric, hardware and accessories. Space so
that frame members are not more than two and forty five
13.2.3 Materials hundredths (2.45) meters apart.

1 Chain Link Fence. Chain link fabric shall conform to 14 Gate frames shall be assembled by welding or with
ASTM A 392 (galvanized). Mesh size shall be fifty (50) special malleable or pressed steel fittings and rivets for
millimeters nominal, and wire size shall be three and rigid connections. Same fabric as for the fence shall be
seventy-six hundredths (3.76) millimeters diameter (No. 9 used, unless otherwise directed by the Engineer. Fabric
American Wire Gauge, AWG) before galvanizing. If shall be installed with stretcher bars at vertical edges. Bars
required by the Drawings or Special Specification, fabric may also be used at top and bottom edges. Attach
shall be plastic coated. stretchers to gate frame at not more than three hundred
eighty (380) mm on centers. Attach hardware with rivets
2 Tension wire for chain link fence and industrial fence
or by other means which will provide security against
shall be a minimum of four and five tenths (4.5)
removal or breakage.
millimeters diameter. Tension wire for other fences shall
be of the minimum diameter shown on the Drawings. 15 Diagonal cross-bracing consisting of ten (10) mm
diameter adjustable length truss rods shall be installed on
3 Posts and Braces. Circular steel posts and braces
gates, where necessary to ensure frame rigidity without
shall be galvanized, conforming to ASTM A 53M-07,
sag or twist, as approved by the Engineer.
Schedule 40 and shall be of the dimensions shown on
the Drawings. At the option of the Contractor, alternate
galvanized steel shapes having the minimum equivalent 13.2.4 Construction and Installation
bending strength in both directions may be substituted for Requirements
circular posts and braces.
1 The Contractor shall stake all sections of fence as
4 Rectangular hollow sections shall conform to ASTM shown on the Drawings or ordered by the Engineer prior
A 501, BS 4360 Grade 43C. to beginning work. Top elevations of all posts shall be
5 End corner posts, straining posts and line posts, computed to follow a smooth grade with curves at
along with braces and stretcher bars thereof, shall be of transitions. Cutting the tops from posts after installation
the sizes and dimensions indicated in the Drawings. Line shall not be permitted. The required line of the fence shall
posts shall be spaced at three (3.0) meters on centers be cleared of all obstacles and debris which would
maximum, unless otherwise directed by the Engineer. interfere with the line of the fence. Minor grading may be
Gate posts shall conform to the requirements of this required to achieve a smooth line.
specification and shall be of the sizes and dimensions 2 Posts shall be set plumb to the required line and
shown on the Drawings. grade in concrete footings. No wire or fabric shall be
6 Post tops shall be pressed steel, wrought iron, strung taut until line posts have been set for at least one
malleable iron, or plastic caps to manufacturer’s standard (1) day and corner posts for at least three (3) days. In
as approved by the Engineer, designated as a weather sandy areas or other areas of poor soil support, the
tight closure cap for each post. Contractor shall enlarge the footings as required by the
7 Posts and braces for high tension wire fence shall Engineer to maintain adequate fence tension.
conform to ASTM A 618M-04, Grade 1.0 Material shall be 3 Wire or fabric shall be strung uniformly at the
of the shapes and dimensions shown on the Drawings and required tension and attached to corner posts and brace
shall be galvanized in accordance with ASTM A 123M-09. posts before permanently attaching to line posts. Any
8 All miscellaneous hardware shall conform to the significant sags or de-tensioning which occurs after
requirements shown on the plans, and shall be galvanized installation shall be corrected by the Contractor.
in accordance with ASTM A153M-09.

♦ 13-5 ♦
copy 249
4 When fencing crosses ravines or other discontinuities
in the terrain causing gaps under the fence, the Contractor,
if so ordered by the Engineer, shall modify the installation
to the extent practical by adding strands or additional
fabric so as to provide the required access control without
interfering with drainage.
5 Galvanized gates or fencing materials which are
constructed or repaired by welding, cutting, or other work
which damages the coating shall be repaired by grinding
smooth all damaged surfaces and painting with two (2)
coats of paint specified in Section 7, Clause 7.2.6, "Zinc
Dust-Zinc Oxide Primer" .
6 The materials incorporated into the fences and gates
shall be sampled, tested and evaluated in accordance with
the standards stated in Clause 13.2.2, all to the approval
and acceptance of the Engineer. The Contractor shall
adjust, redo or complement any test result ordered by the
Engineer.

13.2.5 Method of Measurement


1 Each type of fence is measured by the linear meter,
based on the horizontal length shown on the Drawings or
ordered by the Engineer. Measurement shall be from
center to center of end or corner posts. Gates and other
gaps shall be deducted from the total length.
2 Gates shall be measured by the square meter for
each type, based on the nominal height of the gate
multiplied by the required distance between the adjacent
fence end/gate support posts.
3 No separate measurement shall be made for
excavation, backfill, grading, concrete footings /
foundations, or for any other material and work required,
all of which shall be considered subsidiary to fence or gate,
and whose costs are deemed to be included in the rates
for these items.

13.2.6 Basis of Payment


1 The amount of completed and accepted work as
measured above will be paid at the contract unit rates
specified in the Bill of Quantities, which rates shall be full
compensation for furnishing all materials, for all labor,
transport, installation, equipment, tools, supplies, and all
other items necessary for the proper completion of the
Work.

13.2.7 Items in the Bill of Quantities


1 Payment for the work will be made under one or
more of the following items:

(i) Chain Link Fence (type)(height) (lin.m.)


(ii) Pedestrian/Animal Fencing
(type) (height) (lin.m.)
(iii) Wire Fence(type) (height) (lin.m.)
(iv) Sand Dune Fence (type) (lin.m.)
(v) Gate (type) (sq.m.)

♦ 13-6 ♦
copy 249
Ref. Title Page No. Ref. Title Page No.
14.1  Traffic Signs 14-1  14.1.4.4  Sign Faces for Permanent Traffic
Signs 14-4 
14.1.1 Description 14-1 
14.1.4.5  Manufacture and Assembly of
14.1.2 General 14-1
Permanent Traffic Signs 14-4 
14.1.2.1  Standards 14-1 
14.1.4.6  Location and Erection of Permanent
14.1.3 Materials 14-1
Traffic Signs 14-4 
14.1.3.1  References 14-1 
14.1.4.7  Covering of Permanent Traffic Signs 14-5 
14.1.3.2  Sign Classification 14-1 
14.1.4.8  Temporary Traffic Signs 14-5 
14.1.3.3  General Requirements for Permanent
14.1.5 Method of Measurement 14-5
Traffic Signs 14-1 
14.1.6 Basis of Payment 14-5
14.1.3.4  Posts for Permanent Traffic Signs 14-1 
14.1.7 Items in the BilI of Quantities 14-5 
14.1.3.5  Foundations for Permanent Traffic
Signs and Signals 14-2  14.2  Road Markings 14-5 
14.1.3.6  Sign Plates for Permanent Traffic
14.2.1 Description 14-5
Signs 14-2 
14.2.2 Materials 14-5
14.1.3.7  Sign Faces for Permanent Traffic
14.2.2.1  Thermoplastic Material 14-5 
Signs 14-2 
14.2.2.2  Liquid Paint 14-7 
14.1.3.8  Manufacture and Assembly of
14.2.2.3  Testing 14-8 
Permanent Traffic Signs 14-2 
14.2.2.4  Painting of curbs 14-8 
14.1.3.9  Covering of Permanent Traffic Signs 14-2 
14.2.3 Construction Requirements 14-8 
14.1.3.10  Depth and Marker Posts
14.2.3.1  Raised Rib (Profiled) Road Markings 14-9 
(for Floodways) 14-2 
14.2.3.2  Temporary Road Markings 14-9 
14.1.3.11  Kilometer Posts (5km spacing) and
14.2.3.3  Removal of Road Markings 14-9 
Kilometer Reference Posts
14.2.3.4  Masking of Road Markings 14-9 
(1km spacing) 14-2 
14.2.3.5  Longitudinal Road Markings Lateral
14.1.3.12  Delineator Posts (for edge of
Tolerances 14-9 
carriageway or right-of-way marking) 14-3 
14.2.4 Method of Measurement 14-9 
14.1.3.13  Traffic Signs on Cantilevers
14.2.5 Basis of Payment 14-9 
and Gantries 14-3 
14.2.6 Items in the Bill of Quantities 14-9 
14.1.3.14  Preparation and Finish of Metal
and Other Surfaces 14-3  14.3  Road Studs 14-9 
14.1.3.15  Traffic Cones 14-3 
14.3.1 Description 14-9 
14.1.3.16  Flashing Beacons 14-3 
14.3.2 Materials 14-10 
14.1.3.17  Temporary Traffic Signs 14-3 
14.3.2.1  Permanent Retroreflecting
14.1.4 Construction Requirements 14-3 
Road Studs 14-10 
14.1.4.1  Posts for Permanent Traffic Signs 14-3 
14.3.2.2  Temporary Retroreflecting
14.1.4.2  Foundations for Permanent Traffic
Road Studs 14-10 
Signs and Signals 14-3 
14.3.2.3  Ceramic Buttons 14-10 
14.1.4.3  Sign Plates for Permanent
14.3.3 Construction Requirements 14-10
Traffic Signs 14-3 

copy 249
Ref. Title Page No.
14.3.3.1  Permanent Retroreflecting
Road Studs 14-10 
14.3.3.2  Temporary Retroreflecting
Road Studs 14-10 
14.3.3.3  Non retroreflecting Road Studs 14-10 
14.3.4 Method of Measurement 14-10
14.3.5 Basis of Payment 14-10
14.3.6 Items in the Bill of Quantities 14-10

copy 249
14.1 Traffic Signs remain in position at the completion of the
Permanent Works.
14.1.1 Description 14.1.3.3 General Requirements for Permanent Traffic
1 This Sub-section describes requirements for supply Signs
and erection of sign assemblies, comprising posts, clips,
1 Permanent traffic sign materials, construction,
post caps, gantries, sign faces and foundations.
assembly, test, location and erection shall comply with BS
EN 12899 where applicable and the requirements shown
14.1.2 General
on the Drawings or Schedules.
14.1.2.1 Standards 2 The sign plate shall be manufactured using 3mm
thick alloy aluminium sheet stiffened with alloy aluminium
1 All traffic signs, whether permanent or temporary,
rails or galvanized steel frame and designed to accept the
shall be of the size, shape, color and type described in the
fastening clips. The sign face material shall be retro-
Highway Design Standard, Section 19, unless otherwise
reflective sheeting applied to the aluminium sheet in
approved by The Engineer. Signs that are not described in
accordance with the manufacturer’s instructions. The
the Highway Design Standard must be specially approved
supporting posts may be galvanized steel or alloy
by the Employer and the Engineer. Where the use of
aluminium, as approved by the Engineer, specifically
temporary traffic signs is proposed, the Contractor shall
designed to cope with the wind conditions of the location.
obtain the approval of the Engineer and the agreement of
The sign plate shall be fixed to the post with stainless steel
the ROP and the Concerned Authority for the use of the
clips and fasteners that do not pierce the face of the sign.
signs at the locations proposed.
The posts shall be fixed to the concrete foundation as
2 Signs that are changeable by means other than described in Paragraph 14.1.3.5 of this specification.
manual operation require approval of their construction
3 Before the commencement of manufacture the
and operating mechanisms by the Engineer. This
Contractor shall submit for the approval of The Engineer
requirement is in addition to the need for the design of the
three copies of:
sign to be described in the Highway Design Standards or
otherwise approved by the Employer. i. a detailed schedule (including location) of all
traffic signs.
14.1.3 Materials ii. fabrication and sign face drawings for
‘directional’ signs and ‘informative’ signs.
14.1.3.1 References iii. fabrication and sign face drawings for any gantry
mounted signs.
1 BD 94/07 Design of Minor Structures (UK Design
iv. fabrication and sign face drawings for any
Manual for Roads and Bridges).
illuminated signs.
2 BS EN 12899 Part 1 Fixed Vertical Road Traffic Signs.
4 The back of each traffic sign shall have an indelible
3 BS 8408 Road Traffic Signs - Specification for label showing manufacturer, year of erection, sheeting
Microprismatic Sheeting Materials. material class, sign face product. The text for the label
4 EN 1993 Design of Steel Structures. shall be in English and Arabic with a character height of 5
5 EN 1999 Design of Aluminium Structures. to 10mm.

6 BS EN 13422 includes Cones and cylinders. 5 Traffic signs shall be carefully handled at all times to
prevent damage and transported and stored in accordance
7 BS EN 12352 includes Flashing Beacons.
with the sign face or sign sheeting manufacturer’s
14.1.3.2 Sign Classification instructions.

1 The following classifications of signs apply: 14.1.3.4 Posts for Permanent Traffic Signs
i. Permanent Traffic Signs:- 1 Posts for permanent traffic signs shall be as shown in
Traffic signs described in the Highway Design the Drawings or Schedules, shall comply with BS EN
Standard, or specially approved by the 12899-1, and shall be either:
Employer, designed to remain in position at the
i. galvanized steel posts of tubular or rectangular
completion of the Permanent Works.
hollow section complying with EN 1993
ii. Temporary Traffic Signs :-
(Design of Steel Structures).
a) Traffic signs defined in the Highway Design
Standards that comply with all the ii. aluminium posts of tubular or rectangular
requirements of a permanent traffic sign, hollow section complying with EN 1999
but which will not remain in position at the (Design of Aluminium Structures).
completion of the Permanent Works 2 Where, exceptionally, traffic signs are illuminated,
b) Traffic signs designed by the Contractor and base compartments for electrical equipment shall be as
specially approved but which will not shown in the Drawings or schedules and shall be fitted
with vandal and weather resistant locks to the approval of

♦ 14-1 ♦
copy 249
the Engineer. Keys, in the quantities stated in the 14.1.3.8 Manufacture and Assembly of Permanent
Drawings or Schedules, shall be provided. Wherever Traffic Signs
practicable, access doors shall be on the side of the
compartment furthest from approaching traffic. In the case 1 Manufacture and assembly of traffic signs shall
of signs supported by more than one post, the comply with BS EN 12899-1.
compartment shall normally be in the post furthest from 14.1.3.9 Covering of Permanent Traffic Signs
the carriageway.
3 Flange mounted sign posts, where specified on the 1 Where traffic signs are to be covered prior to use or
Drawings or Schedules, shall have holes or slots in the to show a new message, the following method shall be
flange plate to accommodate the anchorage system. adopted:
Structural design of flange mounted sign assemblies shall i. Permanent changes to permanent signs
comply with Section 6 (Structural Steel and Other Metal A permanent self adhesive plastic film overlay
Work) shall be used to display the new legend. The
overlay shall be compatible with the original sign
14.1.3.5 Foundations for Permanent Traffic Signs and
face sheeting and match the appearance of the
Signals original sign face and shall be applied in full
1 The type and size of foundations for permanent compliance with the sheeting manufacturer’s
traffic signs shall be as shown in the Drawings or recommendations.
Schedules and shall comply with BD 94/07 (Design of ii. Temporary covering of permanent signs (prior to
minor structures, UK Design Manual for Roads and use)
Bridges). A temporary opaque self adhesive plastic film
2 Posts should be flange mounted to foundations as overlay shall be used to cover the sign face. The
shown on the Drawings or Schedules. overlay shall be compatible with the original sign
3 Concrete foundations for multiple posts should face and shall be applied and removed in full
consist of a single long composite block. compliance with the sheeting manufacturer’s
recommendations.
14.1.3.6 Sign Plates for Permanent Traffic Signs iii. Use of spray applications to temporarily cover
1 Permanent sign plates shall be as shown in the sign faces can be used, subject to the approval of
Drawings or Schedules and shall comply with BS EN the Engineer, provided that the material is
12899-1 compatible with the sign face material and is
used strictly in compliance with the
14.1.3.7 Sign Faces for Permanent Traffic Signs manufacturer’s instructions.

1 Faces for permanent traffic signs shall be as shown


iv. Temporary changes to permanent signs
in the Drawings or Schedules, and shall comply with BS
EN 12899-1. A temporary self adhesive plastic film overlay
shall be used to display the new legend. The
2 Sign face material shall comply with ASTM D4956-01
overlay shall be compatible with the original sign
Type III (encapsulated lens sheeting) (also known as High
face sheeting and match the appearance of the
Intensity), or ASTM D4956-01 Type IV (microprismatic
original sign face and shall be applied and
sheeting). In locations where increased conspicuity is
removed in full compliance with the sheeting
required, such as chevrons and similar hazard warning
manufacturer’s recommendations.
signs, sign face material shall comply with ASTM D4956-
01 Type VII material (microprismatic sheeting). 2 The method of application and removal of temporary
covering is manufacturer specific and their instructions
3 Testing of sign face materials shall comply with BS
must be followed exactly to avoid damage to the
8408 and BS EN 12899-1.
permanent sign face material.
4 A warranty statement from the sign face sheeting
manufacturer must be provided stating that there is a 14.1.3.10 Depth and Marker Posts (for Floodways)
100% replacement guarantee for the effective shelf life and
1 Depth and marker posts shall be constructed to
performance life of the material being supplied of 9 years.
withstand permanent immersion in water and, in other
Failure to supply the warranty statement shall be cause for
respects, shall be constructed as for permanent traffic
rejection.
signs and be installed in the locations shown in the
5 Deliveries of sign face material shall be accompanied Drawings or Schedules.
by certification that all specifications are met.
14.1.3.11 Kilometer Posts (5km spacing) and Kilometer
Reference Posts (1km spacing)

1 Kilometer posts and kilometer reference posts shall


be constructed as for permanent traffic signs and

♦ 14-2 ♦
copy 249
materials, construction, assembly, testing, location and 14.1.3.17 Temporary Traffic Signs
erection shall be as shown on the Drawings or Schedules
and shall comply with BS EN 12899-1. 1 Temporary traffic sign materials, construction,
assembly, testing, location and erection shall comply with
14.1.3.12 Delineator Posts (for edge of carriageway or the requirements for permanent traffic signs, and with BS
right-of-way marking) EN 12899 as applicable, and shall be as shown on the
Drawings or Schedules.
1 Delineator posts shall comply with BS EN 12899 Part
2 Where a temporary sign is to be erected it may be
3. Post construction and color and type of reflective
fixed or frame mounted so that it can be easily relocated
marker shall be as shown in the Drawings or Schedules.
or reused. Fabricated frames shall conform to Section 6
14.1.3.13 Traffic Signs on Cantilevers and Gantries (Structural Steel and Other Metal Work).
3 Temporary traffic signs include all vertical sign types
1 Where traffic signs are erected on cantilevers or
and bollards and marker, depth, kilometer, kilometer
gantries the sign plates and sign faces shall comply with
reference and delineator posts.
the requirements for permanent signs specified in this
Section and the Drawings or Schedules.
14.1.4 Construction Requirements
2 Cantilevers and gantries shall be in accordance with
the Drawings or Schedules. Fabricated steel gantries shall 14.1.4.1 Posts for Permanent Traffic Signs
be in accordance with Section 6 (Structural Steel and other
1 Posts shall not protrude above the top of the sign.
Metal Work) and Section 7 (Paint) of this Specification.
2 Signs erected on a single post shall be positioned so
14.1.3.14 Preparation and Finish of Metal and Other that the post is in the center of the sign, unless otherwise
Surfaces shown on the Drawings.
3 The fasteners used for fixing the sign to the post
1 Permanent traffic signs (and temporary traffic signs
shall have shear heads so that the hexagonal head of the
where specified in the Drawings and Schedules) shall be
bolt shears off when the fixing is tightened, leaving a
protected against corrosion and finished in compliance
tamper proof fixing.
with Section 6 (Structural Steel and other Metal Work) and
Section 7 (Paint) of this Specification as applicable. 4 As an alternative for item 3 above, theft resistant
2 Posts, frames, purlins (stiffeners) and general fittings methods of fixing can, with the approval of the Engineer,
and fixings shall be protected against corrosion as consist of welding up appropriate areas of fastening.
specified, in compliance with Section 6 (Structural Steel
14.1.4.2 Foundations for Permanent Traffic Signs and
and other Metal Work) and Section 7 (Paint) of this
Signals
Specification.
3 To prevent specular reflection, the backs of 1 Pits for post foundations shall be excavated to the
aluminium alloy sheets forming plate signs shall be dulled sizes shown on the Drawings and cleared of all loose
using a method to be agreed by the Employer or be material before placing of concrete and backfilling.
coated as follows: Concrete shall conform to the requirements of Section 5 of
i. painted matt traffic grey, using a paint system these Specifications and the Drawings, and where steel
specified in Section 7. reinforcement is used, be protected with two coats of
bitumen material in accordance with paragraph 5.10.3.6 of
ii. covered with matt grey non-retro-reflective
these Specifications
sheeting.
2 Posts for all traffic signs shall be installed centrally in
4 Electrical equipment cabinets and metal components
circular or square concrete foundations to the dimensions
of electrical equipment in base compartments shall be
shown in the Drawings or Schedules and finished with a
protected against corrosion as specified in Section15 of
minimum ground cover of 150 mm.
this Specification.
3 Where, exceptionally, traffic signs are illuminated,
5 Unless otherwise specified on the Drawings or
provision shall be made for cable entry through the
Schedules, stainless steel shall be left untreated except
foundation by means of ducting as shown on the
where the component is visible against the sign face when
Drawings.
it shall be covered by a compatible material of a color to
match that part of the face. 4 Surfaces above foundations shall be reinstated to
match the existing surrounding surface construction and
14.1.3.15 Traffic Cones finish in accordance with the Drawings.

1 Traffic cones shall comply with BS EN 13422. 14.1.4.3 Sign Plates for Permanent Traffic Signs

14.1.3.16 Flashing Beacons 1 Fabricated plate signs up to 1.2m in height and 2.4m
width shall be made of a single substrate sheet. Above
1 Flashing beacons shall comply with BS EN 12352.
this size, the number of sheets shall be kept to a minimum

♦ 14-3 ♦
copy 249
and the separate sheets shall be rectangular and of Connections shall be made at every point where a purlin
comparable size and shape. crosses a post.
2 Fabricated plate signs up to 2.4m wide shall have no 4 Where purlins are not adopted the sign stiffening and
vertical joints. Above 2.4m wide, joints in the stiffening framing shall be continuous in the horizontal direction.
extrusions shall preferably be positioned at a vertical 5 Rivets and other devices used for fixing sign plates to
support. If not, then the vertical joints in the stiffening their stiffeners or framework, or in the construction of
extrusions shall be staggered so that joints are not less housings, shall be of a material compatible with the
than 1.0 m apart. Only one such joint in each horizontal materials being joined. Spacing of rivets or other fixing
stiffening extrusion shall be permitted and all joints shall devices shall be uniform and shall not exceed 150 mm
be reinforced. around the outside edge of any sheet or section of sheet,
3 Sign face plates shall have all corner points rounded and shall not exceed 300mm on cross braces. Hollow
as shown in the Drawings. These should match cleanly rivets shall not be used. Where sign plates need to be
with the associated corner radius of sign face sheeting to stiffened this shall be achieved in a manner such that the
be fitted. sign face material is not punctured or otherwise damaged
to accommodate the stiffening.
14.1.4.4 Sign Faces for Permanent Traffic Signs
6 Rivets or other fixings must not protrude through the
1 Sign substrates shall be prepared to receive sign face sign face sheeting
sheeting materials in compliance with the sheeting 7 An additional washer of neoprene, nylon or plastic
manufacturer’s recommendations. shall be used between the sign face and any metal nuts,
2 All sign face sheeting shall be fixed in accordance bolts, washers and screws to protect it from corrosive or
with the sheeting manufacturer’s instructions. other damaging effects.
3 Only vertical and horizontal joints shall be permitted 8 Where traffic sign posts are required to have flange
and all joints in plastic sheeting shall be overlapped by not plates these shall be secured by anchorages and
less than 6mm. The overlap in the horizontal joints shall attachment systems in accordance with the Drawings. The
be from the top. Butt joints in plastics sheeting shall not bolts shall be lightly greased before final installation and
be used, except in overlay film, or if recommended by the they and their anchorages shall be installed so as to
sheeting manufacturer. achieve the loadings, torque settings and other
4 All materials comprising the sign face, including the requirements in accordance with the Drawings and the
background, border and legends shall be carefully manufacturer’s instructions.
matched for color at the time of sign fabrication to provide 9 Sheet signs shall be connected to posts (or lighting
uniform appearance both by day and night. The sheeting columns where permitted) by correctly sized stainless
manufacturer’s recommendations on color matching steel clips.
methods shall be observed. 10 Where ferrous components are permitted any
5 Letters, numerals, symbols and borders shall be clear drilling of them shall be completed before the application
cut, sharp edged and without cracks. of any finish.
6 Any cut-out letters, numerals, symbols and borders 11 Prior to fitting any sign to any lighting column, the
shall be of material compatible with the sheeting to which Contractor shall seek the approval of the Engineer to
they are applied. They shall be applied in accordance with ensure that the column loading is acceptable. No holes
the sheeting manufacturer’s instructions. shall be drilled in the lighting column except those whose
7 Sheeting materials including letters, numerals, location and size are specified on the Drawings.
symbols and borders shall be fully adhered and there shall 12 Traffic signs to be erected on lighting columns shall
be no air bubbles, creases, cracks or other blemishes. have fixings compatible with the column cross section and
finish.
14.1.4.5 Manufacture and Assembly of Permanent
14 Variable message traffic signs shall also comply with
Traffic Signs
these paragraphs.
1 All sign plates, frames, purlins, posts and other
14.1.4.6 Location and Erection of Permanent Traffic
components shall have rough edges smoothed prior to
assembly. Signs

2 Where framing and stiffening are not an integral part 1 The approximate location of each traffic sign is
of the sign plate their joints shall be welded or joined with shown in the Drawings and Schedules. Exact locations will
suitable brackets utilizing nuts, bolts and washers. be as directed on Site by the Engineer and shall be
3 Where purlins are adopted they shall be attached to recorded as-built.
each vertical member of the sign frame and the sign 2 All posts shall be erected plumb and where two or
stiffening and framing shall be continuous in the vertical more posts are provided for any one sign, the faces of the
direction. Purlins shall be spaced equally apart. posts shall be aligned.

♦ 14-4 ♦
copy 249
3 Signs erected on two posts shall have each post tools, and other items necessary for the proper completion
positioned so that the distance from the center of the post of the work as specified.
to the edge of the sign plate is 300mm unless otherwise
shown in the Drawings or Schedules. 14.1.7 Items in the BilI of Quantities
4 Traffic signs mounted on posts, except those on i. Highway sign, triangular, (height -mm). (nr.)
gantries, shall be erected to have their face plumb vertical ii. Highway sign, circular, (diameter -mm). (nr.)
and be orientated at 95 degrees from the carriageway iii. Highway sign, rectangular, size
centerline to reduce specular reflection. (finished sign area) (sq m).
5 The Contractor shall provide full proposals for the iv. Highway sign, octagonal,
erection of traffic signs mounted on gantries or cantilevers (height - mm) (nr.)
for approval by the Engineer. v. Sign post support assembly
6 No traffic sign shall be dismantled, re-sited or including foundation (type). (nr.)
removed without the prior approval of The Engineer. vi. Breakaway sign post support
assembly including foundation
14.1.4.7 Covering of Permanent Traffic Signs (type). (nr.)
vii. Overhead sign support including
1 Any traffic sign erected at such a time that its legend
Foundation (type). (nr.)
does not relate either wholly or in part to the traffic
movement and route in operation, shall have its sign face
covered as specified in Paragraph 14.1.3.9 until such time 14.2 Road Markings
as its legend is applicable.
2 Under no circumstances shall adhesive tape or other 14.2.1 Description
non approved adhesive material be applied to the face of
1 The Sub-section describes requirements for road
any sign.
marking consisting of white or yellow lines, chevron
3 Removal of any covering shall be carried out with the hatching, arrows, lettering and painting of curbs.
minimum disturbance to traffic.

14.1.4.8 Temporary Traffic Signs


14.2.2 Materials
1 The material for markings on the carriageway shall
1 Removal of temporary traffic signs shall be carried
be either of the following, as shown on the Drawings or
out as soon as they become superfluous or a hazard to
directed by the Engineer:
traffic. Methods of removal shall ensure the minimum
disturbance to traffic consistent with safety. Making good i. Thermoplastic material to British Standard BS
shall be carried out immediately after removal of the EN1436: 2007, or
traffic sign. ii. Liquid paint to British Standard BS EN1871: 2000
and BS EN1436: 2007.
14.1.5 Method of Measurement 14.2.2.1 Thermoplastic Material
1 Rectangular signs shall be measured by the area in
1 Type I road markings do not necessarily have special
square meters of the sign face installed. The rates shall
properties that enhance retroreflection in wet or rainy
include sign substrate, sign face and all fixing devices.
conditions. Type II road markings, on the other hand, are
2 Triangular, circular and other shapes of signs shall road markings with special properties intended to enhance
be measured by the number of each type as installed. the retroreflection in wet or rainy conditions. Type III road
3 Sign posts support assemblies shall be measured by markings are profiled markings designed for use on the
the number of each type installed. The rates shall include edges of major, heavily trafficked highways. Type I
for the foundation and all fixings and painting or other markings shall not be used without special instruction
protection. from the Employer.
4 Temporary signs are not measured separately. Their 2 Thermoplastic road markings shall consist of binder,
cost shall be included as part of the traffic management resin, intermix beads, pigment, plasticizing oil and such
requirements stated in Section 1, Sub-section 1.7 of the other constituents as necessary to reach the performance
Specification. level required. The objective of BS EN1436 2007 is to set
the performance level that the thermoplastic road marking
14.1.6 Basis of Payment must reach; it does not lay down specific percentages of
binder, resin, intermix beads, pigment or other
1 The amount of completed and accepted work constituents. Subject to the restrictions stated in this
measured as provided for above will be paid for at the unit Specification, the manufacturer is free to achieve the
rate for highway signs in the Bill of Quantities which rate required performance level in any way suited to his
shall be full compensation for supplying, fabrication, manufacturing techniques. However, because pavement
erection, painting, fixing, foundation, excavation temperatures in Oman are very high over prolonged
backfilling, and for materials, transport, labor, equipment, periods, and because hydrocarbon resins are a proven

♦ 14-5 ♦
copy 249
cause of blackening in road markings on hot pavements, White
hydrocarbon resins shall not be used. The Contractor shall
submit a certificate from the manufacturer stating that the Type I Road Markings Qd ≥ 100 mcd/m²/lx
thermoplastic road marking contains no hydrocarbon
Type II Road Markings Qd ≥ 130 mcd/m²/lx
resins.
3 The softening point of the thermoplastic road Type III Road Markings Qd ≥ 160 mcd/m²/lx
markings shall be not less than the figures shown in Table
Yellow
14.2.2.1. The flashpoint for thermoplastic materials must
o
be greater than or equal to 240 C and drying (tack free) Type I Road Markings Qd ≥ 80 mcd/m²/lx
time should be between 2 and 10 mins. dependent on
Type II Road Markings Qd ≥ 100 mcd/m²/lx
ambient road surface temperature and wind.
Type III Road Markings Qd ≥ 130 mcd/m²/lx

Type I Road Markings 95°C minimum Table 14.2.2-5: Luminance coefficient

Type II Road Markings 95°C minimum 8 The luminance factor (β) for dry road markings shall
be greater than the figures shown in Table 14.2.2.6.
Type III Road Markings 110°C minimum
Table 14.2.2-1: Softening point White

4 The skid resistance of the thermoplastic road Type I Road Markings β = 0.30 minimum
markings (assisted if necessary by the application of drop- Type II Road Markings β = 0.40 minimum
on beads) shall be not less than the figures shown in Table
14.2.2.2. (Note: Tested using the pendulum test as Type III Road Markings β = 0.50 minimum
specified in EN 1341 for external paving. Skid resistance Yellow
has no units.)
Type I Road Markings β = 0.20 minimum
Type I Road Markings 45 minimum
Type II Road Markings β = 0.30 minimum
Type II Road Markings 45 minimum Type III Road Markings β = 0.40 minimum
Type III Road Markings 55 minimum Table 14.2.2-6: Luminance factor
Table 14.2.2-2: Skid resistance
9 The luminance coefficient (Qd) under diffuse
5 The flow resistance of the thermoplastic road illumination under dry conditions, measured in
marking shall not be more than the figures shown in Table millicandellas (mcd) shall after one year in use conform to
14.2.2.3. the figures shown in Table 14.2.2.5.
10 The luminance factor (β) for dry road markings shall
Type I Road Markings 5% maximum after one year in use be greater than the figures shown in
Table 14.2.2.6.
Type II Road Markings 5% maximum
11 For the measurement of reflection under vehicle
Type III Road Markings 5% maximum
headlamp illumination, the coefficient of reflected
Table 14.2.2-3: Flow resistance luminance RL is used. RL is expressed in mcd/m²/lx. Road
markings in the dry under vehicle headlamp illumination
6 The relative density of the thermoplastic road
shall conform to the figures shown in Table 14.2.2.7.
markings, measured in grams per cubic centimeter, shall
be within the range shown in Table 14.2.2.4.
White
Type I Road Markings 1.9 to 2.1 g/cm³ Type I Road Markings RL ≥ 100

Type II Road Markings 1.9 to 2. 1 g/cm³ Type II Road Markings RL ≥ 150

Type III Road Markings 1.9 to 2. 1 g/cm³ Type III Road Markings RL ≥ 200

Table 14.2.2-4: Relative density Yellow

7 The luminance coefficient (Qd) under diffuse Type I Road Markings RL ≥ 80


illumination under dry conditions measured in Type II Road Markings RL ≥ 150
millicandellas (mcd) shall conform to the figures shown in
Table 14.2.2.5. Type III Road Markings RL ≥ 200
Table 14.2.2-7: Reflectorization under vehicle headlamp
illumination (dry)

♦ 14-6 ♦
copy 249
12 Road markings in rain under vehicle headlamp considered necessary for the acceptance of the materials
illumination shall conform to the figures shown in Table or for the control of their application.
14.2.2.8.
14.2.2.2 Liquid Paint
White
1 The daytime visibility of road marking paint shall be
Type I Road Markings RL ≥ 25 defined by the luminance factor β. The classes shown in
Type II Road Markings RL ≥ 35 Table 14.2.2.10 shall apply.

Type III Road Markings RL ≥ 50 Colour Class Luminance factor β


Yellow LF5 ≥0.30
White LF6 ≥0.40
Type I Road Markings RL ≥ 25 LF7 ≥0.50
Type II Road Markings RL ≥ 35 LF1 ≥0.30
Yellow
LF2 ≥0.40
Type III Road Markings RL ≥ 50
Table 14.2.2-10: Luminance factor
Table 14.2.2-8: Reflectorization under vehicle headlamp
2 The x, y chromaticity co-ordinates for dry road
illumination (rain)
markings shall lie within the regions defined by the corner
13 The x, y chromaticity co-ordinates for dry road points as shown in Table 14.2.2.11.
markings shall lie within the regions defined by the corner
points as shown in Table 14.2.2.9. Corner White Yellow
Point No X Y X Y
Corner White Yellow 1 0.355 0.355 0.443 0.399
Point No X Y X Y 2 0.305 0.305 0.545 0.455
1 0.355 0.355 0.443 0.399 3 0.285 0.325 0.465 0.535
2 0.305 0.305 0.545 0.455 4 0.335 0.375 0.389 0.431
3 0.285 0.325 0.465 0.535 Table 14.2.2-11: Color
4 0.335 0.375 0.389 0.431
3 The contrast ratio (hiding power) for white and
Table 14.2.2-9: Color yellow paints shall be not less than 96% for white and 90%
for yellow when tested in accordance with ISO 2814 when
14 In order to prevent cracking of thermoplastic when
applied with a doctor blade of 300μm.
the plasticizing oil content is reduced to prevent
blackening of the road marking, good quality resins (such 4 The paint shall be free from skin and settlement that
as alkyd resins, rosin esters and maleic-modified resins) cannot be reincorporated by stirring. Drying (tack free)
shall be used in the manufacture of thermoplastic material time should be between 5 and 7 minutes dependent on
instead of the hydrocarbon resins. Road markings ambient road surface temperature and wind.
showing more than minimal cracking during the 5 The skid resistance of the painted road markings
warranted life of the markings will be deemed to have (assisted if necessary by the application of drop-on beads)
failed. shall be not less than 50.
15 The Contractor shall warrant that Type I and Type II 6 For the measurement of reflection under vehicle
markings will continue to achieve all performance headlamp illumination, the coefficient of reflected
requirements of this Specification for a minimum period luminance RL is used. RL is expressed in mcd.m-2.lx-1.
of 1 (one) year from the time of application and that Type Road markings in the dry under vehicle headlamp
III markings will continue to achieve all similar applicable illumination shall conform to the figures shown in Table
performance requirements for a minimum period of 3 14.2.2.12.
(three) years from the time of application, when used on
White RL ≥ 100
the edges of the highway as yellow edge marking.
Yellow RL ≥ 80
16 In no case shall any materials be laid more than 6
mm thick. Unless specified, all white markings shall be Table 14.2.2-12: Reflectorization under vehicle headlamp
reflectorized by means of spherical glass beads to BS EN illumination (dry)
1424 premixed during compounding and additionally by
7 Road markings in rain under vehicle headlamp
spherical glass beads to BS EN 1423 wet surface applied
illumination shall conform to the figures shown in Table
during application. The glass beads shall not have more
14.2.2.13.
than 1,000 ppm of Arsenic Trioxide, 200 ppm of Lead and
1,000 ppm of Antimony. The Contractor shall supply test White RL ≥ 35
certificates showing compliance with these requirements. Yellow RL ≥ 35
17 Before delivery to site, or during the course of the Table 14.2.2-13: Reflectorization under vehicle headlamp
work, the Engineer may call for any tests that are
illumination (rain)

♦ 14-7 ♦
copy 249
8 Testing of spherical glass beads shall be done to 2 Application of road marking material shall generally
conform with BS EN 1423 for drop on materials and BS EN be by mechanized spraying equipment consisting of a
1424 for premix glass beads. The Contractor shall warrant motor powered self propelled machine with compressor.
that markings will continue to achieve all performance A minimum line width of 100mm shall be sprayed in one
requirements of this Specification for liquid paint for a pass. The separate bead gun shall be synchronized to
minimum period of 1 (one) year from the time of spray glass spheres immediately onto the surface of the
application. road marking. An automatic mechanism shall be fitted to
9 Liquid paint is unsuitable for forming raised rib edge produce broken or dotted lines as shown on the Drawings
line markings and should not be used for this purpose. without the need for pre-measurement.
3 If material is applied by hand methods,, the
14.2.2.3 Testing Contractor shall provide stencils, specialized labor and all
1 Testing for liquid paint shall comply with BS EN 1436 necessary equipment to ensure that results match the
2007. The softening point, flow resistance and density of quality and finish of the sprayed work, to the satisfaction
road marking material should be carried out by a roads of the Engineer. Drop on spherical glass beads shall be
testing laboratory. The manufacturer of the road marking hand applied to give a consistent covering over the whole
material shall provide a certificate for the material stating of the surface of the road marking between 350 to 400
these values. The responsibility for the accuracy of the grams per square meter.
figures remains with the Contractor. 4 All road markings shall comply with the dimensions,
2 Testing of skid resistance shall be by use of a angles and proportions stated in the Highway Design
portable skid resistance tester designed to carry out the Standards.
Pendulum test. This is common equipment for use in the 5 Where indicated on the Drawings, curbs shall be
field or in a roads testing laboratory. painted alternately black and yellow to cover the entire
3 Determination of the luminance coefficient (Qd) and exposed surface. Changes in colors shall be made at joints
the reflectorization (RL) shall be by use of a road marking between curbs.
retro-reflectometer which is a portable unit suitable for 6 Obsolete or existing markings to be replaced shall be
use on site. removed by a purpose designed line removal machine
4 Determination of the luminance factor (β) shall be capable of operating between 600 and 2500 meters/hour. It
tested using a Reflectometer which is a portable unit should not cause damage to the road surface. The working
suitable for use on site. width shall be adapted to the width of the marking line up
to a maximum of 400mm. Hand operated machines used
5 Before delivery to site, or during the course of the
for removal of small areas of marking shall have a work
work, the Engineer may call for any tests that are
rate of 3 meters/minute.
considered necessary for the acceptance of the materials
or for the control of their application. 7 The pavement shall be prepared in accordance with
the following:
14.2.2.4 Painting of curbs i. Where the marking is to be applied on concrete
1 Chlorinated rubber paint for painting curbs shall be carriageways, the transverse texturing shall be
plasticized and drying shall be solvent evaporation alone. freed from all traces of curing compound by wire
It shall have the properties give in Table 14.2.2.14. brushing or other approved means. Prior to the
application of thermoplastic material a tack coat
Property Allowable Limits compatible with the road surface and the
marking material shall be applied in accordance
Relative density 1.48 minimum
with the manufacturer’s instructions.
Viscosity at 21°C 65 to 70 ii. On surface dressed carriageways, all loose
chippings where the marking is to be applied
Drying time Approx 10-15 minutes shall be removed prior to application. The
surface to be marked shall be clean and dry.
Coverage 3m² per litre maximum
8 Road marking materials shall only be applied to
Luminance surfaces which are clean and dry. Markings shall be free
80 mcd/m²/lx minimum
coefficient
from raggedness at their edges and shall be uniform and
Passes around 12mm diameter
Flexibility free from streaks. Longitudinal road markings shall be laid
mandrel
Chlorinated to a regular alignment.
9.0%
rubber content 9 Pre-marking shall be carried out manually on straight
Table 14.2.2-14: Paint for Curbs lines and curves using a 100m long string. On straights the
pre-marking shall consist of 1 dot mark every 3m, and on
14.2.3 Construction Requirements curves every 1m. The pre-marking dot shall be a circle of
40mm diameter cut into 2 equal parts by a gap of 10mm.
1 Traffic shall be kept off markings until the installation
has fully cured.

♦ 14-8 ♦
copy 249
Longitudinal changes in line types shall be within 300mm BS 7962. The total thickness of original and masking
of the location specified on the Drawings. materials shall not exceed 6 mm.

14.2.3.1 Raised Rib (Profiled) Road Markings 14.2.3.5 Longitudinal Road Markings Lateral Tolerances

1 Raised rib road markings shall only be used on 1 For longitudinal road markings, the lateral tolerance
National and Arterial roads with full width hard shoulders shall be within ± 25mm from the designed position. Any
or other high speed roads (both single and dual discontinuities between road markings shall be replaced
carriageway) with at least 1 meter wide hard strips. with a smooth taper from one road marking to the other.
2 Raised rib road markings shall be yellow lines which The length of the transition shall be derived from Table
are continuous over the sections where they are specified 14.2.3.1.
on the Drawings. Gaps shall be provided for drainage
Speed (km/h) Taper
purposes only where specified on the Drawings.
3 Raised rib road markings shall be in accordance with Up to 60 1 in 40
the Highway Design Standards. Spacing of the transverse
80 1 in 45
raised ribs shall be 500 mm.
4 Raised rib road markings shall not be used adjacent 100 1 in 50
to hatched areas or central reserve crossings.
120 1 in 55
14.2.3.2 Temporary Road Markings
Table 14.2.3-1: Marking transition taper
1 Temporary road markings shall only be adopted with
2 Where studs are to be placed within the line the
the prior approval of the Engineer. They shall comply with
centre line of the marking and the center line of the studs
the same clauses as permanent road markings, or if
must not be displaced by more than 15mm.
required to be removable, be constructed only from a
proprietary preformed road marking material complying
with BS EN 1790.
14.2.4 Method of Measurement
2 When temporary road markings are used on surfaces 1 Road markings of each type shall be measured by
that will continue to be used by public traffic after their square meters marked. Removal of road markings shall be
removal, any shadow trace remaining after their removal measured by square meters removed.
shall be permanently obliterated. Preformed materials
shall not be used for this obliteration. 14.2.5 Basis of Payment
3 Temporary road markings constructed from a 1 The amount of completed and accepted work
proprietary preformed road marking material shall only be measured as provided for above will be paid for at the unit
adopted in locations and on types of road surface as rate for Road Marking in the Bill of Quantities which rate
shown on the Drawings and shall comply with any other shall be full compensation for supplying, applying, surface
requirement therein. The marking material shall be new preparation, and for materials, labor, equipment, tools,
and together with any primer shall be stored and installed supplies and other items necessary for the proper
in accordance with the manufacturer’s instructions and completion of the work as specified.
within the recommended shelf life.
4 Temporary preformed road markings shall only be 14.2.6 Items in the Bill of Quantities
applied to surfaces that are clean and dry. Upon removal
i. Traffic lines (type) (material)
they shall be disposed of off Site and if any making good
(mechanical application). (sq.m.)
is necessary to the road surface it shall be satisfactorily
ii. Raised rib road markings. (sq.m.)
carried out before the road is opened to traffic to the
iii. Special road markings
satisfaction of the Engineer.
(type), (material) ;(hand applied). (sq.m.)
14.2.3.3 Removal of Road Markings iv. Curb painting (sq.m.)
v. Removal of road markings (sq.m.)
1 The removal of road markings on surfaces that will
continue to be used by traffic shall be undertaken in a
manner that will avoid damage to the surface. The
14.3 Road Studs
removal of road markings shall be by mechanical means
only. The Contractor shall submit details of the system he 14.3.1 Description
proposes to use to the Engineer for approval. 1 This Sub-section describes requirements for the
supply and installation of road studs.
14.2.3.4 Masking of Road Markings

1 When black masking materials are required to cover


existing permanent road markings, they shall comply with

♦ 14-9 ♦
copy 249
14.3.2 Materials studs shall be removed from the carriageway on
completion of the Works to the satisfaction of the Engineer.
14.3.2.1 Permanent Retroreflecting Road Studs
14.3.3.3 Non retroreflecting Road Studs
1 All retroreflecting road studs shall comply with BS
EN 1463-1 and 1463-2, and shall be installed in accordance 1 All non retroreflecting road studs shall be installed in
with the manufacturer’s instructions accordance with the manufacturer’s instructions in
2 Retroreflecting road studs and components which do locations, and complying with any other requirements, as
not fall into a category of BS EN 1463, but which have type shown on the Drawings.
approval of the Employer may be used if specifically
permitted by the Engineer. 14.3.4 Method of Measurement
3 The bodies of the studs shall be aluminium or high 1 Road studs of each type shall be measured by the
impact plastic and shall incorporate an integral plug at number of studs installed.
least 60mm deep.
4 Fixing of studs shall be by epoxy resin adhesive in 14.3.5 Basis of Payment
accordance manufacturers requirements.
1 The amount of completed and accepted work
5 The Contractor shall submit details of the road studs measured as provided for above will be paid for at the unit
he proposes to use together with the method of fixing to rate for Road Studs in the Bill of Quantities which unit rate
the Engineer for approval. shall be full compensation for supplying, fixing, surface
preparation, and for materials, labor, transport, equipment,
14.3.2.2 Temporary Retroreflecting Road Studs
tools, and other items necessary for the proper completion
1 Temporary retroreflecting road studs shall be of the of the work as specified.
fluorescent yellow type to BS EN 1463-1.
14.3.6 Items in the Bill of Quantities
14.3.2.3 Ceramic Buttons
i. Reflecting road studs (type/color). (nr.)
1 Ceramic buttons may be used only in exceptional
ii. Non-reflecting road studs. (nr.)
circumstances to supplement road marking only with the
approval of the Employer and Engineer.

14.3.3 Construction Requirements


14.3.3.1 Permanent Retroreflecting Road Studs

1 Traffic shall be kept off studs until the resin adhesive


has fully cured.
2 Permanent retroreflecting road studs shall be
installed in the locations and to any other requirements as
shown on the Drawings.
3 Road studs shall be fixed so that the displacement to
the left or right of the correct line does not exceed 10mm.
The angular displacement of road studs shall not exceed
5°.
4 Where studs are to be placed within the line the
centre line of the marking and the centre line of the studs
must not be displaced by more than 15mm.
5 Studs shall be installed after the completion of the
wearing course and the installation shall be carried out to
accordance with the manufacturer’s instructions and as
agreed by the Engineer.
6 Studs shall be applied on clean, sound, dry surfaces.
Air temperature shall be greater than 5° at the time of
installation and when it will remain above 5° for the time
taken for the adhesive to cure.

14.3.3.2 Temporary Retroreflecting Road Studs

1 They shall not be used for a second application.


Adhesive used for the temporary retroreflecting road

♦ 14-10 ♦
copy 249
Ref. Title Page No. Ref. Title Page No.
15.1 General 15-1 15.3.4 Method of Measurement 15-7
15.3.5 Basis of Payment 15-7
15.1.1 Scope 15-1
15.3.6 Items in the Bill of Quantities 15-7
15.1.2 Design 15-1
15.1.3 Regulations and Standards 15-1 15.4 Package Medium Voltage
15.1.4 Factory Tests 15-1 Switching Stations 15-7
15.1.5 Field Tests 15-1
15.4.1 Description 15-7
15.1.5.1 General 15-1
15.4.2 Materials 15-8
15.1.5.2 Insulation Resistance Test 15-2
15.4.3 Construction Requirements 15-8
15.1.6 Lighting Columns Tests – Pre-shipment 15-2
15.4.4 Method of Measurement 15-8
15.1.7 Switchgear Tests 15-2
15.4.5 Basis of Payment 15-8
15.1.8 Completed Tests 15-2
15.4.6 Items in the Bill of Quantities 15-8
15.1.9 General Technical Conditions 15-2
15.1.10 Approval 15-3 15.5 33kV and 11 kV Pole Mounted
15.1.11 Erection 15-3 Transformer Sub-Stations 15-8
15.1.12 Manuals 15-4
15.5.1 Description 15-8
15.1.13 Handling 15-4
15.5.2 Materials 15-8
15.1.14 Spares 15-4
15.5.3 Construction Requirements 15-9
15.1.15 Road Lighting 15-4
15.5.4 Method of Measurement 15-9
15.1.16 Sign Lighting 15-4
15.5.5 Basis of Payment 15-9
15.1.17 Medium Voltage and Substation Work -
15.5.6 Items in the Bill of Quantities 15-9
Generally 15-5
15.1.18 Method of Measurement 15-5 15.6 Feeder Pillars 15-9
15.1.19 Basis of Payment 15-5 15.6.1 Description 15-9
15.1.20 Items in the Bill of Quantities 15-5 15.6.2 Materials 15-9
15.2 Medium Voltage Intake 15.6.3 Construction Requirements 15-11
Switching Stations 15-5 15.6.4 Method of Measurement 15-11
15.6.5 Basis of Payment 15-11
15.2.1 Description 15-5
15.6.6 Items in the Bill of Quantities 15-11
15.2.2 Materials 15-5
15.2.3 Construction Requirements 15-6 15.7 Electrical Cables 15-11
15.2.4 Method of Measurement 15-6
15.7.1 Description 15-11
15.2.5 Basis of Payment 15-6 15.7.2 Materials 15-12
15.2.6 Items in the Bill of Quantities 15-6
15.7.2.1 Low Voltage Cables 15-12
15.3 Package Sub-stations 15-6 15.7.2.2 Medium Voltage (M.V) Cables 15-12
15.7.2.3 Metal Gland Parts 15-12
15.3.1 Description 15-6
15.7.2.4 Cable Trays 15-12
15.3.2 Materials 15-6
15.7.3 Construction Requirements 15-12
15.3.3 Construction Requirements 15-7
15.7.3.1 Cable Jointing and Termination 15-13

♦ 1-0
copy 249
Ref. Title Page No. Ref. Title Page No.
15.7.3.2 Field Quality Control 15-13 15.11.2.2 Controllers 15-21
15.7.3.3 Earthing 15-13 15.11.2.3 Signal Equipment 15-22
15.3.4 Protection 15-14 15.11.2.4 Signal Operation 15-23
15.7.4 Method of Measurement 15-14 15.11.3 Construction Requirements 15-23
15.7.5 Basis of Payment 15-14 15.11.3.1 Cables 15-23
15.7.6 Items in the Bill of Quantities 15-14 15.11.3.2 Controller Root 15-23
15.11.3.3 Ducts 15-23
15.8 Road Lighting Masts, Columns
15.11.3.4 Draw Pits 15-24
and Luminaires 15-14
15.11.3.5 Pole installation 15-24
15.8.1 Description 15-14 15.11.3.6 Miscellaneous 15-24
15.8.2 Materials 15-14 15.11.3.7 Completion 15-24
15.8.2.1 Masts and Columns - General 15-14 15.11.4 Method of Measurement 15-24
15.8.2.2 Columns 15-15 15.11.5 Basis of Payment 15-25
15.8.2.3 High Masts 15-15 15.11.6 Items in the Bill of Quantities 15-25
15.8.2.4 Road Lighting Luminaires and Lamps 15-16
15.12 Overheight Vehicle Detection
15.8.2.5 Flood Lights 15-18
System 15-25
15.8.3 Construction Requirements 15-18
15.8.4 Method of Measurement 15-19 15.12.1 Description 15-25
15.8.5 Basis of Payment 15-19 15.12.2 Design Criteria for Materials
15.8.6 Items in the Bill of Quantities 15-19 and Components 15-25
15.12.3 Operational Requirements 15-25
15.9 Overhead Sign Illumination 15-19
15.12.4 Physical Requirements 15-26
15.9.1 Description 15-19 15.12.5 Construction Requirements 15-27
15.9.2 Materials 15-19 15.12.6 Method of Measurement 15-27
15.9.3 Construction Requirements 15-19 15.12.7 Basis of Payment 15-27
15.9.4 Method of Measurement 15-20 15.12.8 Items in the Bill of Quantities 15-27
15.9.5 Basis of Payment 15-20
15.13 Emergency Roadside
15.9.6 Items in the Bill of Quantities 15-20
Telephone System 15-27
15.10 Under Bridge Lighting 15-20
15.13.1 Description 15-27
15.10.1 Description 15-20 15.13.2 Regulations and Standards 15-28
15.10.2 Materials 15-20 15.13.3 Definitions and Mode of Operation 15-28
15.10.2.1 Surface Mounted Luminaires 15-20 15.13.4 Products and Materials 15-29
15.10.2.2 Recessed Mounted Luminaires 15-20 15.13.4.1 Pillar Design and Manufacture 15-29
15.10.3 Construction Requirements 15-21 15.13.4.2 Pillar Dimensions and Weight 15-29
15.10.4 Method of Measurement 15-21 15.13.4.3 Frangibility 15-29
15.10.5 Basis of Payment 15-21 15.13.4.4 Pillar Materials and Color 15-29
15.10.6 Items in the Bill of Quantities 15-21 15.13.4.5 IP Rating 15-29
15.13.4.6 Vibration and Shock 15-29
15.11 Traffic Signals 15-21
15.13.4.7 Wind 15-29
15.11.1 Description 15-21 15.13.4.8 Temperature 15-29
15.11.2 Materials 15-21 15.13.4.9 Lightning Protection 15-30
15.11.2.1 General 15-21 15.13.4.10 Vermin Ingress 15-30

♦ 1-0
copy 249
Ref. Title Page No. Ref. Title Page No.
15.13.4.11 Vandalism 15-30 15.16.3.1 Labeling 15-37
15.13.4.12 Pillar Identification 15-30 15.16.3.2 Testing and Commissioning 15-38
15.13.4.13 Concrete 15-30 15.16.4 Method of Measurement and Basis
15.13.4.14 Steelwork 15-30 of Payment 15-38
15.13.5 Power Supply 15-30
15.17 Civil Works for Electrical
15.13.5.1 Power Supply 15-30
Installations 15-38
15.13.5.2 Battery 15-30
15.13.5.3 Battery Charging 15-30 15.17.1 Description 15-38
15.13.5.4 Solar Panel 15-30 15.17.2 Materials 15-38
15.13.6 Construction Requirements 15-31 15.17.3 Construction Requirements 15-39
15.13.6.1 Drawings 15-31 15.17.3.1 Bases for Poles and Equipment 15-39
15.13.6.3 Anchor Bolt Assembly 15-31 15.17.3.2 Cable Trenches and Ducts 15-39
15.13.6.4 Pillar Mounted Telephone 15-31 15.17.4 Method of Measurement 15-40
15.13.6.5 Grouting of Pillar Base 15-31 15.17.5 Basis of Payment 15-40
15.13.7 Method of Measurement 15-31 15.17.6 Items in the Bill of Quantities 15-40
15.13.8 Basis of Payment 15-31
15.13.9 Items in the Bill of Quantities (Unit) 15-31

15.14 Public Lighting Management


and Control System 15-31
15.14.1 Description 15-31
15.14.2 General Requirements 15-31
15.14.3 Detailed Technical Specification 15-32
15.14.4 Remote Control Management Software 15-33
15.14.5 Hardware 15-35
15.14.6 Method of Measurement 15-35
15.14.7 Basis of Payment 15-35
15.14.8 Items in the Bill of Quantities 15-36

15.15 Earthing 15-36


15.15.1 Description 15-36
15.15.2 Materials 15-36
15.15.3 Construction Requirements 15-36
15.15.4 Earth Resistance Test 15-37
15.15.5 Method of Measurement 15-37
15.15.6 Basis of Payment 15-37
15.15.7 Items in the Bill of Quantities 15-37

15.16 Labeling, Testing and


Commissioning 15-37
15.16.1 Description 15-37
15.16.2 Materials 15-37
15.16.3 Construction Requirements 15-37

♦ 1-0
copy 249
♦ 1-0
copy 249
15.1 General such quality may not be stated specifically in this
Specification.
15.1.1 Scope 3 All materials and products shall be new and
manufactured by manufacturers approved by the
1 This Sub-section describes general requirements for
concerned authority. Furthermore, they shall be sound
electrical systems, including medium voltage substations,
and uniform in quality, size, shape, color and texture and
packaged substations, cables and feeder pillars, road and
free from cracks, warpage or other defects.
under-bridge lighting, traffic signals, illuminated signs,
detection system and emergency telephone system, and 4 All warranties as applicable that are available from
all associated work. Specific requirements for each system the manufacturers shall be submitted to the Engineer in
are given in the relevant Sub-sections of this Section. original documents.

2 Subsidiary (complementary) items which are not


15.1.4 Factory Tests
expressly specified but are necessary for completion of
the work shall be supplied and installed by the Contractor 1 All equipment and materials shall be subject to pre-
and their costs are deemed to be included in the rates and shipment inspection and testing at the manufacturers’
prices for the relevant work. premises. The Contractor, in coordination with the
3 The power supply connection for the lighting manufacturers of relevant materials shall arrange for the
systems shall be coordinated with and obtained from a pre-shipment inspection and testing by the authorized
nearby source assigned by the concerned local power representative of the Engineer at the manufacturers’
authority. premises.

4 The Contractor shall pay all power connection 2 The Contractor shall make all necessary
charges and fees imposed by the Local Power Authorities arrangements and pay all expenses in this regard
and Municipalities, including execution of all civil works including representation, travelling and transportation,
(trench, ducts). boarding, lodging and any other associated cost for the
pre-shipment inspection procedures and witnessing of
5 The work shall be complete in every respect for
the tests at the manufacturer’s premises. In lieu of the
satisfactory operation in compliance with the
above tests the Engineer, at his sole discretion, may
specifications and standards laid down by the respective
accept test certificates by an approved laboratory of
authority and as given herein.
international standards.

15.1.2 Design 3 The Contractor shall obtain from the manufacturer


and submit to the Engineer for approval, the complete
1 The location of light fittings, poles, feeder pillars, details of tests to be performed describing the procedures,
distribution transformers and cables, etc. are shown for test observations and expected results. All test certificates
guidance on the Drawings. Final locations shall be subject shall be in compliance with recognized international
to the road configuration, lighting calculations and standards as approved by the Engineer and the Concerned
approval by the Concerned Authorities. Authority.
2 The Contractor shall coordinate with the Engineer 4 The Contractor shall ensure availability of all tools,
and shall determine the exact position and location of all instruments, test equipment, materials etc., and all
lighting and electrical equipment with respect to other qualified personnel required for the testing, setting and
services and site requirements. adjustment of all equipment and materials including
3 The Contractor shall be responsible for proper putting the same into operation.
lighting distribution on the road surface from the 5 The Contractor shall inform the Engineer of the date
proposed luminaires and other equipment after and time of test for each piece of equipment at least two
installation and commissioning and shall be fully weeks in advance. The witnessing of tests by the Engineer
responsible for maintaining the entire road lighting or his representative shall not absolve the Contractor from
system during the maintenance period of the Works. his responsibility for the proper functioning of the
equipment, and for furnishing the guarantees. All test
15.1.3 Regulations and Standards results shall be supplied in triplicate.
1 The Contractor shall comply with the regulations and
requirements of the concerned authorities, and shall get
15.1.5 Field Tests
all necessary approvals of the shop drawings from the 15.1.5.1 General
respective authority after obtaining approval of the
Engineer. If the road lighting works are executed by a Sub- 1 Upon completion of the installations, the Contractor
Contractor, the Contractor has to ensure that the Sub- shall perform field tests on all equipment, materials and
Contractor is approved by the Concerned Authority. systems. All tests shall be conducted in the presence of
2 The quality of equipment shall be of the best grade the Engineer for the purpose of demonstrating equipment
for each type as approved by the Engineer, even though and system’s compliance with the Specification. The
Contractor shall submit for Engineer’s approval, complete

♦ 15-1 ♦
copy 249
details of tests to be performed, equipment used, permanent set test and breaking load test. When the
describing the procedure, test observations and expected columns in the Works are limited in number, the
results. manufacturer may supply result of tests already done for
prototype testing on such columns, or supply calculation
15.1.5.2 Insulation Resistance Test based results, in lieu of carrying out deflection, permanent
1 Before making connections at the ends of each cable set and breaking load tests.
run or joint between cables, the insulation resistance test 3 Passive Safety of Support Structures:
of each cable section shall be made. Each conductor of a If requested by the Concerned Authority, tests shall be
multicore cable shall be tested individually with each of carried out on each type of column in accordance with BS
the other conductor of the group and also with earth. If EN12767: 2007 level 4. Costs of such tests for
insulation resistance test readings are found to be less columns/high masts will be included under separate items
than the specified minimum in any conductor, the entire in the Bill of Quantities.
cable shall be replaced and tests repeated on the new
cables. If cable joints are provided, then each cable 15.1.7 Switchgear Tests
section shall be tested and joints made only after the tests
have been made satisfactorily. Finally the completed 1 Each circuit breaker shall be operated electrically and
cable length including the joints shall be tested. mechanically or only mechanically if it is not electrically
operated. All interlocks and control circuits shall be
2 All switchgear shall be given an insulation resistance
checked for proper connections in accordance with the
test after installation, but before any wiring is connected.
wiring diagrams furnished by the manufacturer and
Insulation tests shall be made between open contacts of
approved by the Engineer
circuit breakers, switches and between each phase and
earth. Refer to Sub-section 15.16 for details. 2 The Contractor shall properly identify the phases of
all switchgear and cables for connections to give proper
3 If the insulation resistance of the circuit under test is
phase sequence.
less than the specified value, the cause of the low reading
shall be determined and rectified. Corrective measures 3 Trip circuits shall be checked for correct operation
shall include dry-out procedure by means of heaters, if and rating of equipment served. The correct size arid
equipment is found to contain moisture. Where corrective function of fuses, disconnect switches, number of
measures are carried out, the insulation resistance interlocks, indicating lights, alarms and remote control
readings shall be taken after the correction has been made devices shall be in accordance with approved
and repeated twice at 12 hours interval. manufacturer drawings. Name plates shall be checked for
proper designation of equipment served.
4 The maximum range for each reading in the three
successive tests shall exceed 20% of the average value.
After tests have been made, the equipment shall be
15.1.8 Completed Tests
reconnected as required. 1 After any equipment has been tested, checked for
operation, etc., and is accepted by the Engineer, the
15.1.6 Lighting Columns Tests – Pre- Contractor shall be responsible for the proper protection
shipment of that equipment so that subsequent testing of other
equipment does not cause any damage to the already
1 The tubular steel columns shall be tested and the
tested equipment.
results recorded for each test by the manufacturer in the
presence of an authorized representative of the Engineer
in the manufacturer’s premises. The material weight and
15.1.9 General Technical Conditions
dimensions of columns as specified shall be certified by 1 Electrical work shall include the submission by the
the manufacturer. The columns shall be inspected for Contractor of shop drawings and calculations required by
compliance and will be rejected if they are found to be the Specification, as well as the provision of literature and
outside the specified tolerances. samples for the approval process.
2 Loading Test: 2 All plant and equipment shall be supplied with the
The columns shall be cantilevered horizontally, rigidly necessary fittings, accessories and parts for the complete
supported at base plate and loads applied at right angle to installation, irrespective of whether all such fittings and
the axis of the pole at the required point, i.e. at some accessories are listed in the Specification and Drawings.
distance from top. Tests shall be as follows: 3 Installations shall be complete, tested, ready for
• Deflection test. operation and fully integrated with other parts of the
construction and the utility supply. The Contractor shall
• Permanent set test
make available facilities for utility providers during
• Breaking load test
commissioning.
A sample comprising four columns shall be selected at
4 Electrical work shall comply with the concerned
random out of each lot of 1000 and subjected to deflection
authority rules and regulations, and be carried out in
test. One column per thousand shall be tested for accordance with the recommendations of the International

♦ 15-2 ♦
copy 249
Electro-technical Commission (IEC) and in compliance plasticizer and shrinkage of the PVC due to high
with the following: temperature (uPVC).
i. Relevant standards issued by the appropriate
authorities in the Sultanate of Oman including 15.1.10 Approval
the Ministry of Transport and Communications 1 Details of the manufacturers of proposed plant and
(MOTC). equipment shall be submitted for prior approval of the
ii. BS 7671:2008, Requirements for electrical Concerned Authority and Engineer. Approval of any
Installations; (IEE Wiring Regulations (UK) as manufacturer will not constitute approval of his products.
published by the Institution of Electrical The Contractor shall ascertain that the approved
Engineers, London, 17th Edition (or the latest manufacturers are capable of supplying the required
edition). equipment and in conformity with the Specification.
iii. Engineering and safety recommendations of G39
2 The Contractor shall submit to the Engineer for his
‘Model Code of Practice’ of the IEE.
approval, in particular, the following luminaire criteria
iv. Recommendations for the Lighting of Roads for
before placing an order:
Motor and Pedestrian Traffic – CIE-115 or
equivalent and equal standards. i. Detailed literature on each luminaire, lamp and
control gear including manufacturer’s name,
5 Electric power will be supplied by the concerned
catalogue number, rating, material specification,
power authority at a defined voltage, 3-phase, 3 or 4 wires,
overall dimensions, operating characteristics and
50Hz. It shall be distributed from sub-station feeder pillars
principles
at 415/240 V, 3-phase, 4-wire having solidly grounded
ii. Details of changes to standard luminaires if
neutral at the transformer neutral point. Single phase
proposed for adaptation to conditions of
equipment shall be connected between phases and
installation or to meet the Specification
neutral in a way to balance the three phases.
requirements.
6 The voltage at any point in an installed power iii. Photometric data for lighting calculations
distribution network shall not deviate from nominal including polar light distribution curves,
voltage level by more than 5% under normal system coefficient of utilization, glare classification,
operating conditions. efficiency, depreciation factors etc.
7 The equipment shall be capable of giving continuous iv. Calculations of luminance and illumination levels
and trouble-free service in the conditions given in Table and glare, as recommended, using approved
15.1.9-1. It shall be designed and constructed to withstand software and methods
full load operation when exposed to sun, dust storms, 3 Fully equipped samples of any item requested by the
corrosive agents, occasional heavy rain and a high level of Concerned Authority or Engineer shall be delivered as
ultra violet radiation. soon as possible to the Concerned Authority before
placing of orders for the material or products, without
Maximum ambient shade hindering the planned program and progress of work.
50°C
temperature 4 The Contractor shall not order any electrical
Minimum ambient equipment or part, plant or fitting before receiving
-2°C
temperature approval for it. The Engineer may verify the performance
Maximum temperature of and quality of the samples submitted by instructing tests
80°C
metal surface in direct sunlight to be carried out. Approval of samples shall not relieve
the Contractor of his obligations regarding the suitability
Humidity 100%
of the equipment and their performance, once installed.
As per project 5 The Contractor shall submit for prior approval by the
Altitude
requirement Engineer detailed working drawings and shop drawings
Table 15.1.9.1: Operating Conditions for Equipment showing the physical layout of equipment, location of
masts and columns, foundation details, erection and
8 The component parts of each electrical system or installation details, and wiring diagrams. Details shall
piece of equipment shall be the latest product of a single include bolts, nuts, brackets, rods and any small or large
manufacturer, of standard design and dimensions, and item that is necessary for the construction, all to the
similar parts shall have been in satisfactory service for at satisfaction of the Engineer and Concerned Authority.
least two years
15.1.11 Erection
9 The maximum gust speed at 10m above ground level
in open level country for a 1 in 50 year return period shall 1 The Contractor shall submit to the Engineer a
be taken as: 55m/s (198 km/h) schedule of the parts and equipment to be erected. If
10 PVC sleeves where used, shall be of the long chain requested by the Engineer the Contractor shall open up for
high molecular mass type capable of reducing the loss of inspection before erection any plant or equipment which
has been delivered to the Site partly assembled.

♦ 15-3 ♦
copy 249
2 The Contractor shall satisfy himself as to the 15.1.15 Road Lighting
correctness of the electrical and mechanical connections
1 The Contractor shall provide detailed computerized
to plant and equipment installed before it is
calculations to demonstrate that the luminaires proposed
commissioned.
meet the criteria for illumination and luminance given in
3 Operation of plant and equipment still under the the Specification, standards and shown on the Drawings.
control of the Contractor but which is made live shall be
2 Upon completion of a lighting installation as
subject to a ‘Permit to Work’ procedure in a format agreed
specified the Contractor shall carry out measurements of
with the Engineer and the respective authorities.
the illumination levels on the Site in accordance with
clause 15.16 and submit the results to show that the
15.1.12 Manuals
design levels and uniformities have been achieved. The
1 Prior to the final acceptance of the installation the maintained illumination and luminance levels shall be as
Contractor shall submit to the Engineer six sets of given in Table 15.1.15.1.
operation and maintenance manuals for the installed plant 3 Illumination lighting levels shall be measured for all
and equipment. The manuals shall be A4 size in loose leaf the traffic lanes.
binders containing the following:

Secondary

Distributor
i. Single line diagrams of the complete network

National

Arterial

Access
Routes

Routes

Routes

Routes

Routes
properly labeled
Characteristic
ii. Control, protection and circuit diagrams for all
equipment.
iii. Setting up, commissioning and operating
Average
instruction.
Luminance level
iv. Trouble shooting procedures. 2 2 1.5 1.5 0.75
Lav (cd/m2)
v. Maintenance instructions including schedules for (maintained)
preventative maintenance. Overall
vi. Complete recommended spare parts list uniformity 0.4 0.4 0.4 0.4 0.4
including part numbers and the manufacture’s UO = LMin/ Lav
name, address, telephone and fax numbers. Longitudinal
vii. Name of the manufacturer’s local authorized uniformity
0.7 0.7 0.7 0.7 0.6
of each lane
representative and service agent.
UL = LMin/LMax
Maximum
15.1.13 Handling threshold 10% 10% 15% 15%
-
Increment (TI)
1 The Contractor shall provide slings, lifting tackle and
Road surface
cranes for the safe handling of items supplied and shall be
characteristics
responsible for obtaining and keeping up to date the R3* R3 R3 R3 R3
CIE classification
necessary test certificates for this handling equipment. with qo = 0.07
Protection of surfaces and floors during installation shall Average
be the responsibility of the Contractor. Horizontal
Illuminance 35 35 25 25 12
15.1.14 Spares E av. (Lux)
(maintained)
1 Spare parts indicated in the Bill of Quantities shall be Illuminance
supplied suitably packed for transportation to Site and Uniformities 1:3 1:3 1:3 1:3 1:3
long term storage. They shall include fastenings, lugs, and EMin/Eav
screws needed for their attachment. Identification labels EMin/EMax 1:6 1:6 1: 6 1: 6 1: 6
shall be attached to the outside and also enclosed within
*(R3: asphalt road surface with rough texture, slightly
the storage case.
specular)
2 Spares for routine maintenance shall be listed and
Table 15.1.15.1: Maintained Road Illumination and
supplied in quantities equal to 5% (rounded up to the next
Luminance Levels
whole unit) of installed quantities of each type of column,
cable, joint, lamp, control gear, circuit breaker, fuse,
luminaire, luminaire cover and associated bolts, nuts, 15.1.16 Sign Lighting
lampholders, etc. 1 The illuminance level and uniformity shall be
3 Any additional spare parts recommended by the calculated and measured on the sign surface at the
manufacturers, but not named above, shall be included in vertices of the grids defined by dividing it into 1m x 1m
the list. squares and shall be better than the following:
Average illuminance (EAV) : 200-400 lux
Uniformity (EMin: EMax) : 1:6

♦ 15-4 ♦
copy 249
2 The luminaires or floodlights shall be of purpose i. Danger High Voltage.
built design incorporating the specified size and type of ii. Keep Out.
lamps.
iii. Telephone number of emergency
3 The luminaires or floodlights shall be of pleasing contact.
aesthetic appearance with high quality finish, and shall
Additionally, instruction plates shall be posted inside high
comply with BS EN 12899-1, IEC 60598-1, IEC 60598-2-3,
voltage rooms and shall help operating staff to evacuate in
IEC 60598-2-5 and other related parts of this standard as
case of emergency.
applicable.

15.1.18 Method of Measurement


15.1.17 Medium Voltage and Substation
Work - Generally 1 The provision of power supply from the Concerned
Authority to the assigned position of the feeder pillar,
1 Medium-voltage switchgear and control gear
including cable, (KWh-meter), connections at both ends
standards and substation work, equipment and
and all necessary related civil works shall be given as a
component parts are to comply with the following
unit.
standards:
Common specifications: IEC 62271-1 2 Spare parts for routine maintenance and any special
Metal-enclosed switchgear and control gear for rated spare parts ordered by the Engineer shall each be given as
voltages above1 kV and up to and including 52kV items.
IEC 62271-200
High-voltage alternating current circuit- breakers 15.1.19 Basis of Payment
IEC 62271-100 1 The provision of power supply to the feeder pillar
Insulation coordination IEC 60071 shall be paid by number of units, which shall include
Alternating current switch-fuse combinations coordination with the Concerned Authority and for them
IEC 62271-105 to provide power supply to the feeder pillars, including
High-voltage A C. disconnectors and earthing switches subscription fees, supply and installation of breakers,
IEC 62271-102 cables, KWh metering, execution and completion of all the
Switches for rated voltages above 1 kV and less than related civil works.
52 kV IEC 62271-103
2 Spare parts shall be paid for according to the
Metering and protective current transformers (CTs)
completely delivered items by type and quantities as per
IEC 60044-1
the approved list.
Metering and protective voltage transformers (VTs)
Capacitive IEC 60044-5(IEC 60186)
Inductive IEC 60044-2 15.1.20 Items in the Bill of Quantities
Relays IEC 60255 i Power supply connection to the feeder pillar. (nr)
Surge arrestors IEC 60099-5
ii Spare parts (5% as per the approved list. (L.S)
Reading instruments IEC 60051
Watt-hour meters IEC 60521, 62052-11
62053-21,-22,-23 15.2 Medium Voltage Intake Switching
Power transformers IEC 60076, 60354, Stations
60076-11,-10
60156 15.2.1 Description
Insulating oil IEC 60296
1 This Sub-section describes requirements for
Sulphur hexafluoride IEC 60376
supplying, installing, testing and putting into operation the
Fuses IEC 60282-1
M.V. switchgear which shall be in accordance with
Climate conditions IEC 60721-3-3
concerned authority specifications and approval, at
and IEC 60721-3-4
locations indicated on Drawings.
Neutral earthing resistance (when required)IEEE std 32.
For all substations, switching and package stations, the 15.2.2 Materials
short circuit capacity rating, the low voltage control and
1 Medium voltage intake and switching units shall
power supply where needed or other provisions, have to
comprise panels containing the following equipment as
be coordinated with the Concerned Authority and
shown on the Drawings and as required by the concerned
provided accordingly.
authority:
2 Contractor shall provide danger signs in both Arabic
i. Circuit breakers for network control.
and English according to Omani standards made of heavy
ii. Circuit breakers for outgoing circuits.
duty corrosion proof metal, each of not less than 200mm x
300mm installed on all sides of substations, to clearly The panels shall be equipped with floor mounting
indicate to approaching people the hazard. These signs framework, skid bases, internal wiring, labels and cable
shall include:

♦ 15- 5♦
copy 249
sockets. The assembly shall allow for cable access from 15.2.5 Basis of Payment
below without dismantling any structural members.
1 The amount of completed and accepted work
2 The network control circuit breakers shall be measured as provided for above will be paid for at the unit
manually charged, spring operated, fitted with integral rate stated in the Bill of Quantities and shall be full
earthing of the characteristics given by the Concerned compensation for equipping, supplying materials,
Authority. installation, testing and putting into operation, labor,
3 Voltage transformers shall be installed and transport, equipment, tools, spare parts and other items
connected to the primary side of the breaker, to supply the necessary for the proper completion of the work.
lighting and small power for the switching station.
Voltage transformers shall be isolatable and fused on 15.2.6 Items in the Bill of Quantities
primary and secondary sides.
i Medium voltage intake switching station
4 The outgoing circuit breakers shall be manually
(type) (voltage) (rating) (reference drawings) (nr)
charged, spring operated, fitted with integral earthing of
the characteristics given by the concerned authority and
as shown on the drawings. 15.3 Package Sub-stations
5 Tripping of breakers shall be by direct acting primary
trip coil or by current transformer operated direct acting 15.3.1 Description
trip coils. A neon indicator connected to a voltage
1 This Sub-section describes requirements for
capacitor divider indicating voltage presence shall be
supplying, installing, testing and putting into operation,
fitted on each circuit breaker.
factory assembled package sub-stations and connecting to
6 Intake stations shall be supplied with the necessary the medium voltage supply and the low voltage
accessories to form complete operating installations, distribution network.
including the following:
i. Rubber gloves 15.3.2 Materials
ii. Rubber mat extending the full length of the
1 Package sub-stations shall be completely self-
equipment
contained, factory assembled in a totally enclosed, vandal
iii. KV potential testers
and weather resistant housing, ready for placing into
iv. Spare fuses
position upon a concrete base pad.
v. Test plugs
vi. Safety and operating instructions 2 Package sub-station shall comprise of a single
vii. Framed and glazed medium voltage line integrated metal housing, with three totally segregated
diagrams compartments, accommodating MV switch-gear, MV/LV
viii. Wall mounted cupboards, with mortice lock and distribution transformer and LV switchgear. Degree of
three keys each. protection shall be IP 54 for switchgear (MV or LV)
enclosures and IP 23 for transformer housing. MV and LV
15.2.3 Construction Requirements connections to corresponding transformer terminals are to
be insulated and inaccessible without the use of tools.
1 The Contractor shall coordinate with and get
3 The MV live parts shall be completely enclosed in
approval from the selected manufacturer of the switching
lockable compartments, which shall be segregated for
plant on the proposed civil works before starting
maximum safety, but give the necessary access for
construction.
cabling and connections, IP5X minimum, in accordance
2 The construction of the buildings shall comply with with IEC 62271. Cables shall enter and leave the
the requirements of Subsection 15.17. compartments from below. A chain link fence 2m high
3 The equipment shall be lifted into position within the shall be provided around the sub-station with a lockable
station upon prepared foundations. The station gate.
switchboards may be installed complete or in sections. 4 The medium voltage switchgear shall consist of two
The units shall then be tested before and after incoming (2) ring main SF6 switches and one switch-fuse (sealed for
and outgoing cables are connected. life), with fuses mounted in a separate compartment.
Handle design is to ensure delay between closing and re-
15.2.4 Method of Measurement opening of main switch or earthing switch, to provide an
1 The approved work shall be measured by the number anti-reflex operation. It shall be impossible to move earth
of medium voltage intake switching stations, installed in switch inadvertently into or from earth position except
station building (excluding building) and put into when main switch is in the open position. Indication of
operation after testing, and acceptance by the concerned switch position shall be mechanical, directly connected to
authority. moving contacts. Each switch shall have a padlocking
device in the open, closed and earth positions. Semaphore
type indicators shall be provided to indicate on, off, earth-
on earth off positions, protected with polycarbonate

♦ 15- 6♦
copy 249
covers. The fuse access shall be interlocked to prevent it with a compartment housing the accessories to form a
being opened unless the switch is off and earthed at both complete operating installation as follows:
ends. i. Rubber gloves.
5 The ring main switches shall be fitted with cable ii. Spare fuses.
boxes and glands. The cables shall be connected to the iii. Safety and operating instructions.
fixed mating contacts by flexible connectors provided with iv. Medium voltage line diagram.
a slotted hole. v. Low voltage circuit diagram with designations.
Alternatively, MV switchgear compartment cable terminal vi. kV potential tester
connectors shall be conical stress-relieving, epoxy sealed vii. Kilowatt hour metering as per requirements
end, bolted, straight/elbow, molded rubber, plug-in, or Additionally, instruction plates shall be posted inside high
other type, complete with all accessories as may be voltage rooms and shall help operation staff to evacuate in
suggested by manufacturer and approved by the case of emergency.
concerned authority.
6 MV switchgear compartment potential indicators 15.3.3 Construction Requirements
shall be neon indicators, provided at front of each unit, 1 The Contractor shall agree with the selected
one per phase, using capacitive potential divider to manufacturer of the package sub-station on details for the
indicate voltage at switch-disconnector cable terminals. proposed civil works and shall have shop drawings
7 MV switchgear compartment accessories are to approved before construction starts.
include the following: 2 The Contractor shall install the package sub-station
i. Two N.C. and two N.O. auxiliary contacts on unit upon the concrete base using the appropriate lifting
each switch. gear to prevent damage. When correctly located, the unit
ii. Earth fault indicator, operated by core-balance shall be bolted in position and tested before and after
type current transformer, located near and connecting the incoming and outgoing cables.
outside cable box/ terminations with indicator
visible from the front and with automatic reset. 15.3.4 Method of Measurement
iii. Shunt trip release on switch-fuse combination.
1 Package sub-stations shall be measured by the
8 The transformer feeder switch shall have a trip
number of complete units supplied, installed, tested, put
button or shall trip automatically by fuse operation. An
into operation and accepted by the Concerned Authority,
interlock shall be provided so that the switch-fuse cannot
including time switch and connection.
be put back into service until the faulty fuse has been
replaced.
15.3.5 Basis of Payment
9 The low voltage switchboard shall be a separately
enclosed metal compartment with lockable doors within 1 The amount of completed and accepted work measured
the package housing and shall be of equal construction to as provided for above will be paid for at the unit rate
the feeder pillar. It shall consist of a triple pole and neutral stated in the Bill of Quantities and shall be considered as
manually operated main circuit breaker of the molded full compensation for supplying and installing the sub-
case pattern of the required ampere interrupting capacity. station, testing, putting into operation, handing over,
Overload and short circuit release mechanisms including all materials, labor, transport, equipment, tools
comprising thermal and magnetic trips and earth leakage and other items necessary for the proper completion of
protection (30mA), shall be provided. the work.

10 Three ammeters fitted with selector switch,


15.3.6 Items in the Bill of Quantities
maximum demand indicator and current transformers
shall be incorporated along with a voltmeter with selector i Package sub-station (type) (reference)
switch and protection fuse. (rating) (voltage) (nr)
11 A single phase socket outlet of 16-250 DIN rating
complete with plug top and a 12W fluorescent lighting 15.4 Package Medium Voltage
fitting of the integral battery/inverter emergency type, with
Switching Stations
switching facility to allow emergency light to be initiated
shall be mounted adjacent to the low and medium voltage
switchgear panels and shall be prewired at the factory.
15.4.1 Description
12 The low voltage panel circuits serving the lighting 1 This Sub-section describes requirements for
shall be supplied through triple pole circuit breakers and supplying, installing, testing and putting into operation
triple pole contactors (one set per circuit) which shall be factory assembled package medium voltage switching
dual photo-electric cell controlled. The low voltage panel stations, and connecting to the medium voltage electrical
and components shall meet the requirements specified in supply network.
Subsection 15.6. The package sub-station shall be fitted

♦ 15- 7♦
copy 249
15.4.2 Materials Engineer. The transformers and all accessories shall
conform to the requirements, standards and specifications
1 Package switching stations shall be self-contained;
of the concerned authority and the Contractor shall obtain
factory assembled conforming to MV Switchgear
all necessary approvals from the Concerned Authority in
specification in Sub-section 15.3.
this regard.
2 The switching station shall contain 3 extensible SF6
switch units with space for one additional SF6 switch. The 15.5.2 Materials
switches shall be fitted with cable boxes and glands
suitable to receive the incoming cables and shall have 1 Metal work shall be hot-dipped galvanized to BS EN
operating positions at the front of the unit. The switching ISO 1461 and ASTM A123 and ASTM A153, whichever is
mechanisms shall be independent manual type. more stringent, after fabrication.

3 Switching stations shall be supplied with accessories 2 Transformers shall be painted by the manufacturer.
as for sub-stations with the exception of the low voltage Standard identification plates shall be fixed.
circuit diagrams. 3 Bushings and insulators shall have a minimum
4 Emergency lighting if required by the Concerned Creepage value of 40mm/kV.
Authority, shall be coordinated with the Concerned 4 The transformer station supports shall be ‘H’ type
Authority and be provided as specified in Sub-section 15.3, construction, using 11m long, preservative treated,
Clause 15.3.2 (11). wooden (Pinus Sylvestris) poles type. The support system
shall be fitted with 4 stay sets, each comprising tubular
15.4.3 Construction Requirements stay-rods, wood stay insulators, galvanized steel wire of
minimum diameter 4mm and pole clamps. The poles
1 Construction requirements shall be as specified in
shall be fitted with galvanized mild steel cross arms to
Sub-section 15.3, Clause 15.3.3.
support the transformer.

15.4.4 Method of Measurement 5 The 11kV fuse units shall be 3 phase expulsion drop-
out type with 900mm phase to phase spacing and fitted
1 Package medium voltage substations work shall be with re-wireable fuse elements.
measured by the number of units supplied, installed, put
6 The 33kV switch fuse units shall be 3 phase, vertical
into operation, accepted by and handed over to the
mounting, with 1050mm phase to phase spacing. The
concerned authority, including connection to the MV
switch shall include a treated wooden, insulated,
supply, fees, and the cost of power connection from the
operating handle at 1.2m from ground level. The fuses
assigned source.
shall be of the expulsion drop-out type, fitted with re-
wireable fuse elements.
15.4.5 Basis of Payment
7 The transformers shall be the pole mounted type
1 The amount of completed and accepted work with outdoor bushings on both medium and low voltage
measured as provided for above will be paid for at the unit sides and shall have the characteristics given in Table
rate stated in the Bill of Quantities, which rate shall be full 15.5.2-1.
compensation for supplying, installing the station, testing 8 The low voltage units shall be 3 outdoor pole mount
and putting into operation, connection labor, transport, porcelain cut-outs fitted with appropriately rated HRC
equipment, tools and other items necessary for the proper fuses.
completion of the work.
Rating As indicated on drawings
15.4.6 Items in the Bill of Quantities Phases 3
i Package medium voltage switching Winding Connections: Delta 3 wire primary
station (type) (reference) (voltage). (nr) Star 4 wires sld earthed
neutral secondary
15.5 33kV and 11 kV Pole Mounted Tappings Dyn 11
Transformer Sub-Stations Impedance Medium voltage off-circuit
+5% to -5% in 2.5%steps
15.5.1 Description
Cooling Oil filled natural
1 This Sub-section describes requirements for
Temperature Rise:
supplying, installing, testing and putting into operation
pole mounted transformer sub-stations and connecting to Oil 40°C
the medium voltage supply on one side and the low Windings 50°C
voltage distribution network on the other side. Table 15.5.2.1: Pole Mounted Transformer Characteristics
2 The capacity of pole mounted transformers shall be
as shown on the Drawings and or as directed by the

♦ 15- 8♦
copy 249
15.5.3 Construction Requirements testing and putting into satisfactory operation feeder
pillars for road lighting networks as shown on Drawings.
1 The Contractor shall coordinate and agree the
location of pole mounted transformer stations with the 2 The Contractor shall submit data for approval,
Engineer prior to commencing the installation. The poles including but not limited to the following:
shall be installed in concrete at 2.2m centers for the 33kV i. Construction details, standards to which pillars
system and 1.8m centers for the 11kV system. comply, current carrying capacities of bus bars,
2 The Contractor shall install the equipment using the de-rating factors employed for breakers and bus
appropriate lifting gear to prevent damage. The medium bars.
and low voltage connections shall be made only after the ii. Manufacturer’s catalogue cuts for all
equipment is correctly installed and tested. components.
iii. Dimensional and electrical characteristics and
15.5.4 Method of Measurement samples of breakers used
3 The Contractor shall submit drawings for approval,
1 Pole mounted transformer sub-stations shall be
including but not limited to the following:
measured by the number of units supplied, installed, put
into operation and accepted by the Concerned Authority. i. External dimensions of feeder pillars
ii. Details of base foundation
2 The rate shall include for transformer, 11m long
iii. Details of breaker ratings, bus bars
preservative treated supporting wooden poles, platform
iv. Glands, joints, etc
for mounting transformer, galvanized mild steel cross
v. Mounting details
arms, stay sets, insulators, post insulators and support
assembly, 4mm diameter galvanized steel wire, 33kV or
15.6.2 Materials
11kV fuse units, low voltage HRC fuses and all other
necessary hardware, GI guards and anti-climbing device, 1 Feeder pillars shall comply with IEC 60439-1 and /or
earthing with or without chamber, 33kV or 11kV other equally approved standards
connections, connection to the medium voltage supply 2 The feeder pillar shall be a totally enclosed cabinet,
and low voltage distribution network and all other fully self-contained, dust proof, weather proof, vermin
accessories. proof and suitable for mounting outdoors exposed to dust,
rain and direct sunlight (IP55).
15.5.5 Basis of Payment
3 The cabinets shall be reinforced free standing
1 The amount of completed and accepted work structures, manufactured from 2mm thick steel with bolted
measured as provided for above will be paid for at the unit reinforced corner construction. They shall be of the dwarf
rate stated in the Bill of Quantities, which rate shall be type with a bolting down base for mounting on a pre-
considered full compensation for supplying and installing formed concrete pad suitably furnished for all incoming
the complete sub-station, including supporting poles and and outgoing cables from below ground level within a
platform, earthing, testing, connecting, putting into duct system.
operation, and for materials, labor, transport, equipment, 4 Cabinets shall have two hinged lockable doors to
tools, supplies and other items necessary for the proper provide full front access. The roof of the cabinets shall be
completion of the work as specified. slanted and have water drip edges.

15.5.6 Items in the Bill of Quantities


Moulded case Four pole, equipped with overload
i Pole mounted transformer sub-station, Circuit Breakers andshort circuit release mechanism
(…KVA), 33KV/415V/240V, 3-phase, 4-wire, MCCB’s comprising thermal and magnetic
(to IEC 60947-2) trips(IEC 60947-2 sequence III).
solidly earthed neutral, (Ref. as
Triple-pole, magnetic type , to
Contactors
shown on dwgs). (nr) interrupt an inductive load equal
(to IEC 60947-4-
to the indicated rating.
ii Pole mounted transformer sub-station, 1)
Utilization Cat. AC-5a and AC- 5b
(…KVA), 11KV/415V/240V, 3-phase, Fully insulated, rated 1.25 the main
4-wire, solidly earthed neutral, incoming molded case breaker frame
size at 50 degrees C, with three
(Reference as shown on drawings). (nr) Bus bars, 3 ammeters each fitted with maximum
phase + full demand indicator with associated
15.6 Feeder Pillars neutral current transformers, and voltmeter
with selector switch and protection
fuse.
15.6.1 Description PVC/PVC single core 1000 v grade,
Internal
1 This Sub-section describes requirements for with copper conductors, rated as
Cabling
required and suitably laced or clipped.
supplying, complete feeder pillar(s), installing, mounting,
Table 15.6.2.1: Feeder pillar fittings

♦ 15- 9♦
copy 249
5 Feeder pillars shall be complete with equipment and welding silver alloy with arc quenching metallic devices of
fittings incorporating molded-case circuit breakers approved construction. Cable terminals shall be solderless
controlling the main supply and the outgoing circuits. anti-turn box lug or clamp type with set screws suitable
Feeder pillars shall have the fittings given in Table 15.6.2.1. for copper or aluminum cables.
6 Equipment, busbars, and conductors within the pillar 11 MCCBs generally shall be thermal-magnetic type for
shall be fully insulated such that there are no live parts or ratings below 600 A frame size, unless otherwise shown
connections exposed. The feeder pillar shall have a 50mm on the Drawings. MCCBs 600 A and larger shall be
x 6mm high conductivity copper main earth bar for electronic solid-state trip type. All circuit breakers shall be
grounding purposes. A distribution diagram showing 3-pole unless otherwise shown on Drawings.
circuit connections, MCCB ratings, cables sizes and 12 Thermal magnetic circuit breakers shall include, on
references shall be suitably fixed to the inside of the each pole, a bi-metallic inverse time-delay over-current
cabinet door. Feeder pillars shall be secured against trip element for small overloads and instantaneous
unauthorized access by means of wedge locks protected magnetic over-current trip element for operation under
by brass plugs and operated by a special key. short-circuit conditions. Circuit breakers 250 A frame size
7 A single phase socket outlet of 16-250 DIN rating and larger shall have adjustable instantaneous trips.
complete with plug top and a 12W fluorescent lighting
13 Thermal over-current trips shall be compensated to
fitting of the integral battery/inverter emergency type, with
allow for ambient temperature higher at breaker than at
switching facility to allow emergency light to be initiated
protected circuit or device. Compensation shall be
shall be mounted adjacent to the low panels and shall be
applicable between 25 and 50 deg. C. Where thermal
prewired at the factory.
settings are adjustable, range of adjustment shall not
8 Feeder pillars shall be finished with the following exceed maximum trip rating shown on the Drawings.
internal and external treatments:
14 When tripped automatically by over-current
i. De-rust. condition, operating mechanism of circuit breaker shall
ii. De-grease. assume an intermediate position clearly indicated by the
iii. One coat of sprayed zinc chromate primer. handle between on and off positions.
iv. Two coats exterior paint, dark grey to BS 381C
15 Circuit breakers 250 A to 600/630 A frame size shall
shade 632.
have interchangeable thermal and electronic trip units.
9 The low voltage distribution circuits serving the
16 Non-interchangeable trip circuit breakers shall have
street lighting installation shall be supplied through a
sealed covers. Circuit breakers with interchangeable trips
triple-pole contactor which shall be dual photo-electric cell
shall have trip unit covers sealed to prevent tampering.
controlled by two photocells connected and mounted in
parallel with a timer .as specified below. An override 17 Circuit breaker ratings shall be non-current limiting,
facility shall be provided for maintenance. fully rated (100%) with continuous duty at site conditions,
and with frame size and interrupting capacity to IEC 60947-
a) Contactors shall be, electro-magnetic type,
2, sequence III (rated ultimate short-circuit breaking
class AC 5a or AC 5b to IEC 60947-4, designed
capacity), and maximum trip rating as shown on the
to withstand large initial currents of discharge
Drawings. Interrupting capacities at specified voltage and
lamps or tungsten lamp loads respectively, and
frequency shall meet IEC 60947-2 test sequence I, II, III and
rated not less than overload setting of
IV for circuit breakers of utilization category B.
protective device upstream. Contacts are to be
double break, silver cadmium plated, having 18 Circuit breaker design shall allow addition of
self-cleaning wiping action. Control is to be electrical operator, control and interlocking functions,
provided by phase-neutral (maximum 240 V) under-voltage release, shunt-trip coils, alarm and auxiliary
split-coil, for on/off activation by local and/or switches, padlocking devices, key-lock devices, and the
by remote direct-wired means. Contactor is to like. Such accessories shall be provided where shown on
be mechanically latched. Control circuit is to the Drawings.
be fused. Auxiliaries are to include local pilot 19 The photo-electric control shall consist of omni-
lights, parallel remote indicating circuit, 2 N.O. directional cadmium cell thermal relay of high quality,
and 2 N.C. auxiliary contacts. employing solid state photo-variable conductance
10 Circuit breakers shall be totally enclosed, molded elements giving a 2:1 on/off ratio with sensitivity to switch
case, (MCCBs) constructed from high quality, high on lights when the daylight illumination reduces to 70 lux.
temperature resistant, tropicalized, moulded insulating This allows for the high pressure sodium lights striking
materials, for normal operation at 70 deg. C within time, taking into account of the rather fast rate of daylight
enclosures, to approved standards, provided with quick- intensity drop off in the region.
make, quick-break, trip-free switching mechanism The photo electric cells shall be mounted at the top of the
manually operated by front toggle type handle and nearest column or high mast or at the top of the feeder
automatically tripped under overcurrent conditions. Multi- pillar and connected to the feeder pillar.
pole breakers shall have common integral trip bar for 20 A solar dial time switch shall be of the quartz,
simultaneous operation of all poles. Contacts shall be non- electronic type, capable of operating for at least 100 hours

♦ 15- 10♦
copy 249
in case of power failure. Timer shall be of settable type 15.6.4 Method of Measurement
once throughout the year and to be set at definite periods
1 Feeder pillars shall be measured by the number of
for switching on and off.
units supplied, installed, put into operation after testing
21 Instruments shall be housed in enameled, square, and acceptance by the concerned authority.
metal cases for flush installation. Scale and markings shall
be protected and sealed. Accuracy of instruments shall be 15.6.5 Basis of Payment
within 2% unless otherwise specified.
1 The amount of completed and accepted 'work
22 Voltmeters shall be the moving iron type, with centre
measured as provided for above will be paid for at the unit
zero adjuster, range 1.25 times nominal system voltage 90
rate stated in the Bill of Quantities which rate shall be full
degree angle, size 76x76 mm.
compensation for supplying, installing feeder pillar,
Voltmeter selector switch shall be 7-position rotary type. testing, putting into operation the pillar, and for labor,
23 Ammeters (Number = 3) shall be moving iron type, transport, material, equipment, tools, photo-electric cells,
with centre zero adjuster, range 2 times nominal circuit timer, supplies and other items necessary for the proper
amperage, 90 degree angle size 76x76mm. completion of the work as specified.
Ammeter selector switch shall be 7-position rotary type.
24 Current transformers, shall be suited to the nominal
15.6.6 Items in the Bill of Quantities
current of plant protected, short circuit level and burden. i Feeder pillar, (size, rating (A))
Current transformers shall be of the indoor dry type, rated
(No. of ways, type and reference)
secondary 5A. Rated primary current core size and
accuracy shall be determined from circuit data. (415/240V). (nr)

25 Voltage transformers shall be provided where


required, complete with primary and secondary fuses and 15.7 Electrical Cables
disconnecting device.
15.7.1 Description
26 The feeder pillar shall have a separate compartment
containing a three phase kWH meter. 1 This sub-section describes requirements for
27 Wiring supplying and installing cables into trenches or through
pre-installed ducts, including connecting, terminating and
i. Wiring shall be modular and neatly arranged on
circuit testing.
master terminal boards with suitable numbering
strips and appropriate cartridge type fuses where 2 The Contractor shall submit data for approval
required including, but not limited to, the following:
ii. Connections shall be made at front of terminal i. Constructional details, standards to which cables
board and with no live metal exposed. comply, current carrying capacities, derating
iii. Metal cases of instrument, control switches, factors for grouping and temperature.
relays, etc… shall be connected, by bare copper ii. Manufacturer's catalogue cuts.
conductors not less than 2.5 mm2 section, to iii. Dimensional and electrical characteristics.
nearest earthing bar. iv. Samples of each cable and wire and, if requested
iv. Control wiring shall be copper, PVC insulated, 85 by the Engineer, other accessories.
degrees C, 600V grade, and PVC sheathed v. Voltage drop calculations for each circuit in
cables. Finely stranded copper conductor, silicon schedule form.
rubber insulated cables shall be used in 3 Unless otherwise specified or shown on the
proximity to higher temperature components Drawings, cables and other feeders shall have copper
and as flexible cable. conductors. Cable conductors shall be stranded for
v. Wires shall be fitted with numbered ferrules of sections 4 mm2 and above, based on IEC 60228 Class 2.
approved type at each termination Signal and control cables shall have solid conductors
28 Anti-condensation heaters with disconnect switch unless otherwise specified. Flexible cords shall have
and pilot lamp shall be provided in feeder pillars finely stranded conductors. Conductors of single-core
controlled by thermostat and/or humidistat where cables 25 mm2 and above shall be compacted. Multi-core
required. cables 35 mm2 and above shall be sectoral shape.
4 Conductor sizes shall be as shown on the Drawings.
15.6.3 Construction Requirements Conductors with cross-sectional area smaller than
1 Construction requirements shall be as specified in specified will not be accepted.
Sub-section 15.3, Clause 15.3.3 for package substation 5 Wiring insulation shall be color coded or otherwise
work. identified as required by the applicable regulations as
follows:
Neutral: blue.
Protective earth: green-and-yellow striped.

♦ 15- 11♦
copy 249
Phase colors: brown, black and grey as appropriate. 15.7.2.2 Medium Voltage (MV) Cables
6 Maintain color coding throughout installation.
1 Medium voltage cables, insulation and rating shall
Phase-conductors for which outer jacket is not color-coded
comply with BS 6622 and IEC 60502-2 for voltages up to 33
shall have engraved alphanumeric marks (L1, L2, L3) or
kV and IEC 60840 for voltages above 30kV up to 150 kV
color coded heat-shrinkable sleeves.
(Um=170 kV). MV cables shall be capable of a conductor
operating temperature of 90°C under worst ambient
15.7.2 Materials conditions at full load rating. Each phase shall be
15.7.2.1 Low Voltage Cables identified by a distinctive marking on the cable. The cable
insulation grade (voltage designation) and manufacturer
1 Unarmored cable shall be PVC insulated and shall shall be embossed on the cable over the sheath. The
comply with BS 6004. Conductors shall be not less than semi-conductive layer shall be removable without the use
2.5mm² cross section. of tools.
2 Single core PVC insulated (85 deg. C.) non-sheathed
2 MV cables shall be in accordance with the concerned
single conductor cables for wiring in conduit shall have
authority specification (MEW Standard OES 2 -
annealed copper conductors, compacted, generally with
Underground Cable Installations).
concentric strands and insulated with flame retardant,
moisture and heat resistant PVC/C to IEC 60227 and 15.7.2.3 Metal Gland Parts
IEC60332-1, suitable for wet locations and for conductor
temperature of 85 deg. C. 450/750 V grade. 1 Metal gland parts shall be brass, bright dipped, and
shall have a polychloroprene inner sheath, sealing ring,
3 Multi-core PVC insulated (85 deg. C.) cables (0.6/1
armor clamping cone, armor nut and captive
kV): shall have annealed, copper conductors, compacted,
polychloroprene outer sheath sealing ring. During
insulated with PVC/C to IEC 60227, moisture and heat
assembly the gland shall not induce torque in the cable
resistant, suitable for wet locations and fully rated
sheath or armor. A polychloroprene shroud shall be fitted
conductor temperature of 85 deg. C, laid up, bedded with
over the gland.
suitable filler and sheathed with flame retardant PVC/ST2,
general purpose sheathing to international standards (IS 15.7.2.4 Cable Trays
5831: 1984 and IEC 60502-1).
1 Medium cable trays shall be galvanized steel, flanged
4 Cables within lighting columns, high masts and
with heavy duty folded reinforced edge, and slotted. Cable
signs shall comply with BS 6004 and shall have separate
channel shall be galvanized steel.
PVC (green striped yellow) insulated earthing cable
installed. Cables for recessed lighting shall be 3 core
15.7.3 Construction Requirements
copper, utilizing one core for earthing.
5 Armored cable shall be PVC/SWA/PVC to BS 6346 or 1 Before any underground and ducted cabling is
BS 5467 and IEC60502-1, IEC 60811 and IEC 60332-1. installed, copies of the test certificates from the
Directly buried cables shall be armored type unless manufacturer shall be submitted to the Engineer for
otherwise indicated on the Drawings. approval. The certificate shall show that the supplied
cable satisfies the appropriate standards.
6 Armored cables shall have single layer of galvanized
steel wire armor with flame retardant PVC/ST2 over- The sizes of low voltage copper conductor cables shall be
sheath. Armoring shall comply with BS 1442 and shall as shown on the Drawings. Care shall be taken so that
provide 50% conductivity of phase conductor conductivity voltage drop at the far end of the cable does not exceed
as a minimum. 5% of the nominal voltage. Cables manufactured only by
reputed firms shall be used, provided they fulfill all the
7 Cable covers for underground directly buried cable
requirements of the Specification and the concerned
protection shall be to BS 2484, with sand cushion around
authority standards.
cable and a layer of 200 mm wide protective concrete
bricks over the sand along the entire route of the cable. 2 Cable joints and terminations shall be completed
The bricks shall be laid in such a way as to provide equal with the correct specified materials, tapes, stress cones,
margin of cover on both sides of the cable. A warning tape glands, sleeves and bonds. Joints shall be made in
shall be laid throughout the length of the trench. accordance with the cable manufacturer's
recommendations and BS 6910-1. No through joints shall
8 Cables shall be terminated at equipment
be allowed in low voltage cables where adequate
switchboards, and isolators, using mechanical cable
manufacturer's lengths are available.
glands, in accordance with the manufacturer's
recommendations. 3 A sample site-constructed cable termination and
through-joint shall be submitted to the Engineer prior to
9 Buildouts with cable lengths are required from
any jointing commencing on site.
designers.
4 Termination of cables shall be either crimped or
soldered. Through-joints shall be complete with

♦ 15- 12♦
copy 249
manufacturer's recommended metal sleeves and shall be 2 Perform the following in advance of independent
located in a cable draw-pit tests:
5 For underpass luminaires PVC insulated, PVC i. Test cables insulation resistance.
sheathed, SWA cable shall be pulled through already ii. Test circuits continuity.
laid/buried uPVC ducts or conduits in underpass slabs or iii. Furnish a set of applicable specifications and
concrete structures. manufacturer’s recommendations to test
6 The pulling of cables through ducts or conduits shall organization.
be started only after the conduit (uPVC) system is iv. Make power available at test locations.
completely installed and all outlet boxes, junction boxes 3 Schedule tests and notify Engineer at least one week
etc. are fixed in position. in advance of schedule for test commencement.
7 The contractor where not in conflict with these 4 Provide megger testers of various ranges as
Specifications shall carry out the requirements and abide applicable, and HV test equipment as necessary for testing
where necessary with Series 1400 (Electrical Work for MV installations. Use 1000 V megger on installations with
Road Lighting and Traffic Signs) and Series 1500 nominal voltage over 500 V up to 1000 V, and 5000 V
(Motorway Communications) of the DMRB found under megger for initial checks on MV installations (up to 15 kV).
UK Standards for highways. 5 On installations of medium-voltage cables and before
electrical circuitry has been energized, demonstrate
15.7.3.1 Cable Jointing and Termination
product capability and compliance with requirements.
i. Through joints will not be allowed in feeder 6 MV Cable Testing: Provide cable test set with D.C.
cables where adequate manufacturer's lengths output voltage and ampere range sufficient to test MV
are available. Where a joint is necessary, it shall cables. Cables are to be laid in position (trench or duct
be made inside boxes, handholes or manholes. bank), jointed where applicable, but left uncovered, with
ii. Through joints and terminations shall be carried ends free of equipment and clear of ground.
out strictly in accordance with cable
7 MV Cable Testing: D.C. test voltage is to be applied
manufacturer's recommendations, and made
between core under test and the screen in steps, pausing
with correct specified materials, boxes, tapes,
one minute or more each step (first step being the A.C.
compounds or mixtures, stress cones, glands
rms rated voltage of the cable, followed by two equal
and bonds as applicable.
steps) up to maximum test voltage. At each step, and for
iii. Qualifications of operatives shall be submitted to
the last 5-15 minutes duration at maximum test voltage,
the Engineer prior to work commencing on site.
the ammeter (normally a micro-ammeter) is to be
Joints are to be filled with epoxy resin after
monitored closely and recorded. If, except as voltage is
taping unless contrary to cable manufacturer's
increased, the current starts to increase, test is to be
recommendations. Sample site constructed
stopped and the installation inspected and tested for the
cable terminations and through-joints shall be
fault.
submitted to the Engineer prior to commencing
work on site. Samples are to be constructed in i. Each cable/core is to be tested independently.
the presence of the Engineer and shall be Maximum D.C. test voltage for grounded neutral
available for test and inspection in accordance system is to be 3 times rated A.C. rms voltage of
with manufacturer's recommendations. cable.
iv. Cutting tools for jointing and terminating cables ii. Alternative test if approved by the Engineer, is to
are to be purpose made, to prevent damage to apply A.C. rms voltage up to 1.5 times A.C. rms
insulation in general, and to cable shielding of rating of cable (26 kV for 17.5 kV cable), applied
MV cables. for 15 minutes, by an approved A.C. test set.
v. Cleaning of lacquer on conductors shall be by Readings are to be within same range and in
use of non-scratch scouring sponge and white accordance with IEC 60502.
spirit or equal approved. iii. Replace or correct malfunctioning cables and
vi. Tighten electrical connectors and terminals, accessories at Project site, and retest to
including screws and bolts, in accordance with demonstrate compliance until reaching
manufacturers published torque-tightening satisfactory conditions as per international
values. Where manufacturer’s torque standards/ regulations; otherwise, remove and
requirements are not indicated, tighten replace with new units and retest.
connectors and terminals to comply with
15.7.3.3 Earthing
international standards.
1 The armoring on cables shall be bonded to the
15.7.3.2 Field Quality Control metalwork and to the earthing system in accordance with
1 Cable tests shall be carried out in accordance with the applicable regulations.
the requirements of the applicable regulations and 2 Shielded cable shall be earthed at terminations,
standards. splices and separable insulated connectors. Earth metal

♦ 15- 13♦
copy 249
bodies of terminators, splices, cable and separable 15.8.2 Materials
insulated connector fittings and all hardware to be in
accordance with manufacturer’s written instructions. 15.8.2.1 Steel Masts and Columns - General

1 Steel Masts and columns shall be fabricated from


15.7.3.4 Protection
steel, in accordance with Section 6, and hot dip galvanized
1 Provide final protection and maintain conditions, in a to BS EN ISO 1461 (inside and outside) or in accordance
manner acceptable to manufacturer and installer, to with ASTM A123 and A385 to Engineers approval. They
prevent entrance of moisture into the cables and to ensure shall be in sections not less than 10m in length, and shall
medium-voltage cables are without damage or be joined on site by pressure over-lapping or slip joints
deterioration at hand-over. which shall have a minimum length of 1.5 times the
diameter of the joint. Columns up to 12m high shall be
15.7.4 Method of Measurement supplied in one piece.

1 Road lighting cable shall be measured in linear 2 The walls of columns shall be a minimum thickness
meters for each size and type of cable as shown on the of 3mm with a minimum ultimate strength of 370N/mm²
Drawings or as directed by the Engineer, installed in duct and a minimum yield strength of 240N/mm². Masts and
(excluding duct) or directly buried in trench (excluding columns over 13m in height shall have a minimum wall
trench), complete with required accessories, including all thickness of 4mm, a minimum ultimate strength of
types of cable jointing and terminations, accessories such 520N/mm² and a minimum yield strength of 360N/mm².
as clamps, channels, clips, connectors, tugs, tapes and any 3 Masts and columns when installed and fully
other item which is not stated above but is considered equipped, shall have safety factors in accordance with
necessary for completion of the work. Technical Report No. 7 of the Institution of Public Lighting
2 Underpass lighting cable shall be measured in linear Engineers (UK): 2003 or latest edition. They shall be
meters for each size and type of cable as shown on the capable of withstanding the gust wind velocity stated in
Drawings or as directed by the Engineer, complete with Clause 15.1.9 blowing in the most unfavorable direction at
required accessories including cable trays, pulling of cable a height of ten meters above ground level. The deflection
in already installed/buried conduit or uPVC ducts in slab, at the top of the mast or column shall not exceed 1/40 of
all type of jointing and terminations and any other item the height.
which is not stated above but is considered necessary for With a wind velocity of 198km/hr on the full projected area
completion of the work. of column, bracket and luminaire(s) a factor of safety of 3
3 The approved cable work shall be measured by the on minimum tensile strength shall be maintained and
linear meter of cable installed plus an allowance of 2m at horizontal deflection at lantern position shall not exceed
each end for termination and jointing. 1/40.

4 Trenches, ducts, warning tapes, and markers for 4 The Contractor shall submit to the Engineer detailed
cables are measured separately under Sub-section 15.17. manufacturer’s design calculation sheets and supporting
data to show that the masts and columns and foundation
15.7.5 Basis of Payment designs respectively are safe and meet the above
requirements. The submitted calculations shall include the
1 The amount of completed and accepted cable work following:
as provided for above will be paid for at the unit rates
i. The deflection at the top of the mast or column at
stated in the Bill of Quantities which rate shall be full
the designed wind speed.
compensation for supplying materials, installing, testing,
ii. The natural frequency of the mast or column.
putting into operation, and for labor, transport, equipment
iii. The critical wind speed for resonance.
tools, supplies and other work items necessary for the
iv. The damping characteristics of the mast or
proper completion of the work as specified.
column.
v. The steel stresses under resonant conditions.
15.7.6 Items in the Bill of Quantities vi. The value of acceleration at the top of the mast
i Electrical cable (type) (voltage) (size) (lin.m) or column under resonant conditions.
vii. Welding procedure details.
viii. Procedure details ensuring that the flange plate
15.8 Road Lighting Masts, Columns
is not laminated.
and Luminaires ix. Details of the joints between the mast or column
sections and between the bottom section and
15.8.1 Description flange plate.
1 This Sub-section describes requirements for supply, x. Details of the base compartment with the
erection upon prepared foundations and putting into method of reinforcement at the door area and
service road lighting masts and columns complete with means adopted for making the door
operating mechanisms, brackets, luminaires, control gear weatherproof and tamper-proof.
and cabling.

♦ 15- 14♦
copy 249
All the above shall be submitted for approval by the terminals, and for incoming and outgoing 3 phase 4 wire
Engineer before manufacturing commences. cable. Terminal blocks shall be high temperature, non-
Delivery shall not be done until factory tests are inflammable, non-toxic material with high quality fixing
completed to the satisfaction of the Engineer. screws and individual terminal for each termination.

5 A hot dip galvanized steel flange base plate of 4 One circuit breaker, single pole 15 A shall be
sufficient (20mm minimum) thickness, free from provided for each phase leading to a luminaire. Circuit
laminations, shall be welded to the base of the mast or breakers shall be compensated and rated for 50 deg. C
column, fully developing the strength of the section. ambient temperature with interrupting capacity as
Supplementary gussets shall be provided between the specified under other Sub-sections of the Specification,
bolt holes drilled in the flange, if necessary. The underside and shall be mounted in weatherproof enclosure at
of the flange and the inside of the pole to a height of baseboard. Wiring shall be PVC insulated 3 core or 4 core
500mm shall be painted with bitumen. The outside of the 85 deg. C conductor temperature. Cable shall be at least 4
pole and the flange if under ground level shall also be mm² copper conductor.
painted with bitumen up to ground level.
15.8.2.3 Steel High Masts
6 A door shall be provided in the masts and columns to
permit access to the circuit breaker assembly, junction box, 1 Masts shall be of the height specified on the
and winch (where provided) mounted on a backboard Drawings, hot dipped galvanized of multi-sided cross-
made of durable non-hygroscopic material. The door shall section with a continuous taper made of formed sheet
be weatherproof and fitted with a heavy duty lock. A steel, electrically welded. They shall be delivered to site in
stainless steel 12mm diameter earthing bolt shall be sections and be the slip joint type. Masts shall be
welded inside near the access door. assembled on site by means of pressure over-lapping or
slip joints which shall have a minimum length of 1.5 times
7 Where indicated on drawings and covered in the
the diameter of the joint. Site welding will not be allowed.
BOQ. masts and columns shall be painted with two (2)
coats of epoxy resin paint to an approved color or high 2 The luminaire rings or brackets shall be constructed
gloss finish as required by the Concerned of galvanized steel in accordance with Section 6. Where
Authority/Engineer. necessary, they shall be in two halves joined by bolted
flanges to permit removal. For masts with a moveable
8 The Contractor shall produce a certificate from a
luminaire ring, rollers with a serf canting mechanism shall
structural engineering authority that columns and masts
be provided made of water resistant non-marking material
meet the above requirements. In addition, an agreed
with oil-impregnated bronze bushings.
official testing authority’s certificates shall be presented to
guarantee the life-time and resistance of the products 3 The weatherproof wiring chambers shall have
under worst climatic conditions. terminal blocks, neutral bars, grounding bolts for electrical
connections, and facilities on the luminaire ring to allow
9 The Contractor shall submit a guarantee from the
testing of luminaires while in the lowered position.
manufacturer stating that the design lifetime of the
Cabling shall be in accordance with Sub-section 15.7. The
columns and masts is a minimum of twenty five (25) years
high mast cables shall conform to Technical Report No. 7
after installation under the worst site conditions in Oman.
as given in Paragraph 15.8.2.1, Item 3.
If any column or mast or any part thereof fails within the
guarantee period, subject to corrosion, the Contractor 4 The luminaire raising and lowering lead assembly if
shall replace them free of charge. Without this guarantee fitted shall be manufactured of non-corrosive metals and
the lighting columns and/or masts will not be the operating cable sleeves shall be enclosed and run on
approved/accepted. stainless steel shafts. The luminaire ring or bracket shall
be supported by a 3-cable winching system. Flexible
15.8.2.2 Steel Columns stainless steel stranded aircraft cables entirely suitable for
the application, with factor of safety 5 times safe working
1 Columns shall carry either single or double
load of the winch, shall support the luminaire ring
luminaires or any combination up to six luminaires as
assembly. Nylon or similar stops installed on the steel
shown on the Drawings and shall be of circular cross
cable shall support the luminaire ring assembly in extreme
section. Any special requirement for octagonal cross
lower position to within 900 mm above the base of the
section will be shown on Drawings or in design schedules.
mast. Provisions shall be made to prevent the power cable
2 The luminaires shall be rigidly fixed and bolted to the from winding around the steel hoisting cable.
column or column arms to prevent wind rotation or Arrangements shall be provided for the electricity and
vibration. support cables to be separated before passing over their
3 Columns with one or two luminaires shall be respective pulleys, and close fitting guides shall be
connected over one phase and neutral. Columns with provided so that the cables cannot disengage from the
three or more luminaires shall be connected over 3 phases pulleys during operation. A steadying system shall keep
and neutral, unless otherwise shown on the Drawings. the luminaire ring in the correct top position preventing
Bolted terminals and cable lugs of the sizes shown on rotation around its vertical axis.
Drawings shall be provided with 3 phase and neutral

♦ 15- 15♦
copy 249
5 Winching systems shall have a lifting capacity of at zone of protection for the mast head frame and luminaires.
least double the weight of the luminaire ring assembly The terminal shall be bonded to the mast to ensure the
and shall be fitted with an approved safety system to discharge is dissipated via the earth and ground terminal
control the ring assembly in the event of a suspension without damage to the steel winch cables or electric cable.
cable failure.
15.8.2.4 Glass Reinforced Polyester (GRP) Columns
6 Winches shall be capable of normal operation using
either a portable power tool or by hand, and shall 1 This specification is for columns applicable to coastal
incorporate a torque limiter which can be adjusted and roads in general, where heights of 4m to 14m are required
locked. Winches shall be self-sustaining without brakes or and as shown on layout drawings.
clutches which require maintenance and shall be totally 2 GRP columns shall be manufactured by the
enclosed and self-lubricating. centrifugal casting process and shall withstand wind
7 Termination of winch cables shall not involve speeds up to 220km/hr.
distortion or twisting of the cable structure. One full layer 3 GRP columns shall be highly resistant to impact,
of turns shall remain on the drum when the luminaire ring deflection and bending, and shall be highly safe in case of
is fully lowered or alternatively the drums shall be a collision, fire resistant (using special resins), electrically
grooved to ensure a tidy cable lay. non-conductive and safe without grounding.
8 The head frame shall be covered by a shaped 4 GRP columns shall be corrosion proof, resistant to
protective aesthetic canopy as shown on the Drawings chemical reactions, with UV protection against
and designed to give a coordinated appearance of head weatherability and shall have a guaranteed lifetime of 25
frame with the luminaire ring when the latter is in the years. A reinforced lockable hinged access door of
raised position. minimum height of 300mm at a height from ground level
9 Two red aircraft obstruction lights within cast of 600mm shall be provided.
aluminium bodies shall be fitted at the top of each high 5 The columns shall be either of the burial type or the
mast attached to the luminaire ring and arranged to flanged base type, with suitable cable access as shown on
project through the canopy. A transformer and relay shall drawing/details. Flanged base plates shall be of galvanized
automatically connect the second lamp in the event of steel equal in construction to flange plates used on steel
lamp failure. columns (15mm to 20mm thickness) with four anchor
10 High mast distribution equipment shall be mounted bolts and convenient cable entry, bitumen coated on the
in a weatherproof enclosure on the baseboard of the lower inside and outside. Pigment color range shall be
compartment of the high mast and shall comprise a back submitted with the proposal and color shall be selected by
plate chassis complete with: the Engineer before approval is granted on the
i. 1 x 60 Amperes triple pole main incoming manufacturer.
molded case circuit breaker (MCCB) and neutral 6 Standards for GRP columns shall be as follows:
assembly for luminaire circuits. i. Specific Gravity: 1.65 Kg / dm3 (UNI 7092/72)
ii. 1 x 20 Amperes single pole MCCB and neutral ii. Glass Fiber Content (% by weight): 45-55 %
assembly for each luminaire circuit. iii. Water Absorption: 0.5 % (UNI ISO 62)
iii. 1 x 15 Amperes single or triple pole MCCB and iv. E-Modulus: 22000 ± 2000 MPa (UNI 5819/66)
neutral assembly connected to the incoming v. Tensile Strength: 400 ± 50 MPa (UNI 5819/66)
supply and serving a 16A-250V DIN or 16A-415V vi. Flexural Strength: 350 ± 50 MPa (UNI 7219/73)
DIN socket outlet complete with 3-pin plug to suit vii. Compressive Strength: 200 ± 50 MPa (UNI
the raising and lowering mechanism. 4279/72)
iv. A multi-pin plug and socket outlet with guard viii. Impact Strength: > 180 kJ / m2 (UNI 6062/67)
ring. ix. Dielectric Strength: 3 – 7 kV / mm (UNI 4291/72)
11 The breakers shall be designed, manufactured and x. Surface Insulation Resistance: 1010 – 1013 (UNI
tested in compliance with IEC 60947-2 sequence III, 4288/72)
calibrated at 50 degrees C. The breakers shall have xi. Thermal Conductivity: 0.2 – 0.3 kCal / m⁰C (UNI
interrupting capacity exceeding 10 kA. 7891)
12 The 16A-250 V or 16A-415 V socket outlet for supply xii. Coefficient of Linear Expansion: 15 – 17
to the portable raising and lowering power tool shall be 1/(⁰C*106) (UNI 6061/67)
connected to the MCCB via a flexible connection to ensure xiii. Temperature Class: F
accessibility. xiv. Overall Length: 3 – 14 m
xv. Top Diameter (3 – 7 m poles): 60 mm
13 Each high mast supplying ground sign lighting shall
xvi. Top Diameter (8 – 14 m poles): 94 mm
be equipped with an additional 15 amp circuit breaker to
xvii. Conicity (slope to determine the bottom): 18 mm
supply the sign lighting installation. The circuit breaker
per linear meter length
shall be installed inside the mast distribution box.
xviii.Steel fortification (at the top): required
14 Masts shall be equipped with a lightning protection xix. Steel base plate: optional
air terminal of the correct height to provide the required xx. GRP base plate cover: available

♦ 15- 16♦
copy 249
7 Tests and approvals for GRP columns shall conform 6 Luminaire protectors shall be heat and shock
to the following Standards: resistant glass, mounted into suitable frame assembly
i. General Outdoor Lighting Pole Specifications: fixed to body by captive screws, and secured by extra
ASTM – D4923-01 safety clamps to allow replacement of protector and
ii. Tensile Strength: DIN EN ISO 527-2 reflector, for maintenance purposes without danger of the
iii. Elongation: DIN EN ISO 527-2 cover falling to the ground. Ozone resistant ethylene
iv. Flextural Test. (bending): DIN EN ISO 14125 propylene or approved equivalent rubber shall ensure
v. Impact Bending Test: DIN 53435 sealing of the front glass, to maintain the required degree
vi. Rate of Burning: ASTM – D635-03 of protection IP65.
vii. Dielectric Breakdown Voltage: ASTM – D149-97a 7 Lamp sockets shall be high grade porcelain, mounted
viii. DC Resistance: ASTM – D257-99 in support brackets with provision to adjust lamps
ix. Outdoor Weathering: ASTM – D1435-99 vertically and axially. Lamp support and locking system
8 Mechanical properties for GRP columns shall shall grip and prevent lamp movement in operation.
conform to the following Standards: 8 Ballast and control gear shall be mounted in
i. Tensile Strength: DIN EN ISO 527-2 luminaire in separate compartment isolated to protect the
ii. Elongation at break: DIN EN ISO 527-2 electrical accessories from the direct radiant heat emitted
iii. Bending Strength: DIN 53390 by the lamp, and with enclosed terminal blocks fitted with
iv. E-modulus: DIN EN ISO 14125 quick-disconnect electrical leads. Where required, control
v. Impact Strength: DIN 53435 gear shall be contained in the prewired box, having an
enclosure of IP 54, and mounted on luminaire ring
15.8.2.5 Road Lighting Luminaires and Lamps separately from luminaires.

1 Luminaires shall be of the totally enclosed type, 9 Control gear shall be plug in type for operation at 240
complying with IEC 60598-1, IEC 60598-2-1, and IEC 60598- V, A C. single phase, 50 Hz. Ballast shall be tropicalized
2-3 (or latest version), dust protected and splash proof, class H insulated, specially selected for particular type of
divided into two compartments. The first compartment lamp used, and lamps shall be able to start with at least +/-
shall be protected by clear glass or acrylic polycarbonate 10% variation of nominal voltage and continue in normal
sealed to the frame and hinged and shall house the optical operation with dips attaining 20% for four seconds.
system with polished and anodized pressed aluminum Control gear losses shall not exceed 10% of normal lamp
reflector, conforming to at least degree IP 66 of IEC 60529, wattage. RFI suppression device shall be provided. Refer
under all operating conditions. The second compartment to CISPR. Power factor shall be compensated to at least
shall consist of the electrical accessories (control gear), 0.9 lagging or better.
cable feed terminals and side entry mounting socket to at 10 Control gear (choke, capacitor, ignitor, etc.) shall be
least IP 54. suitable to stand up to 85 degrees C. ambient temperature
2 Luminaires shall be shock resistant and specially of the enclosure.
designed to house required lamps, electrical gear and 11 Internal connections shall be with high quality heat
accessories. Body shall be corrosion resistant, extruded, resistant wire insulated for 105 deg. C and with porcelain
pressure die-cast or fabricated aluminum alloy, optically connectors. Control gear shall comply with the IEC 60947-
sealed, mechanically strong and easy to maintain. 3 or relevant equivalent British Standard specification or
Luminaire housing made from glass reinforced plastic or other acceptable International equivalent.
other synthetic material shall not be acceptable. 12 HRC fuse cartridges, suitably rated and conforming
3 Luminaire bodies constructed of fiber reinforced with IEC 60269, shall be provided, complete with base, for
polyester or pressed aluminum may be accepted subject protection of the luminaire. Fuse shall be rated to
to approval of the Engineer and the quality of the product withstand starting current and shall be preferably located
and its resistance to heat from direct sunlight and/or heat in control gear enclosure.
emitted from the lamp/control gear. The decision of the 13 Terminal blocks shall be of the suitable screw-tunnel
Engineer in this respect is final and not subject to type, clearly marked with arrangement to facilitate
discussion. maintenance, quick replacement and easy disconnection
4 Exposed metal parts of luminaires shall be factory of individual components.
finished, stove enamelled, with suitable corrosion 14 Types of lamps are to be as follows:
resisting paint capable of resisting heat emitted by lamp a) High pressure sodium lamps shall be type
during continuous operation, and under full sunlight SON-T (tubular), in accordance with IEC60662
conditions. Color shall be agreed with the Engineer. for dimensions and characteristics, and IEC
5 Mirror reflectors shall be single piece, with 99.5% 62035 for safety, with guaranteed average
purity, anodized and glazed aluminium or die cast with rated life (down to 80% output) above 12,000
super-purity aluminium vapor-deposited, and coated with hours, and having initial luminous output equal
transparent layer of silicon protection against wiping. to or above the following:

i. 16500 lumens for 150 W lamps.

♦ 15- 17♦
copy 249
ii. 31500 lumens for 250 W lamps. and to the luminance and illuminance results achieved.
iii. 55000 lumens for 400 W lamps. The decision of the Engineer in this respect is final and not
iv. 135000 lumens for 1000 W lamps subject to discussion.
17 Luminaires shall provide a distribution generally in
b) High pressure mercury vapor lamps shall be to accordance with IEC 60598-1, IEC 60598-2-2, IEC 60598-2-3,
IEC 60188, and shall include quartz discharge cut-off or semi-cut-off classification, as required by the
tube in an internally coated ovoid outer tube. design standards for type and class of road.
Coating shall be ytrium vanadate phosphur
with color temperature of 3300 deg. K. 15.8.2.6 Flood Lights
Guaranteed rated life (down to 80% output)
1 Flood lights shall be totally enclosed type, weather,
shall be above 8000 hours and initial luminous
dust and shock resistant, IP 65 to IEC 60529, and shall
output above the following:
conform to the requirements and types shown on
i. 3800 lumens for 80 W lamps drawings or be of approved equal make.
ii. 6500 lumens for 125 W lamps 2 Housing shall be of high pressure die-cast aluminium
iii. 14000 lumens for 250 W lamps. alloy, closed on front by hinged framed glass protector
highly resistant to thermal and mechanical shocks, and set
c) Metal halide lamps shall comprise quartz
in position by at least eight heavy duty stainless steel
discharge tube enclosed in clear tubular hard-
spring clamps with silicon rubber sealing gasket.
glass outer bulb, operating on same principle
Enclosure shall be in accordance with IEC Publication
as all gas discharge tubes with iodide additives,
60598-2-5.
indium, thalium and sodium in the mercury
discharge, to increase intensity in three 3 Reflectors shall be high purity (over 99% reflectance)
spectral bands; blue, green and yellow-red with anodized aluminium, secured in precision aligned internal
high color rendering. Lamps up to 150 W shall tracks to provide beam distribution required.
be provided with electronic ballast. Lamps shall 4 Connection box shall be located at rear of floodlight
be to IEC 61167 with E40 base. Guaranteed 2
body with gland connections to accept 4 mm PVC/PVC
average life shall not be less than 10000 hours three core cables. Lamp and control gear shall be
and luminous outputs, after 100 hours burning, mounted in two separate and isolated compartments.
shall be above the following:
5 Control gear shall be plug-in type, 240 V, 50 Hz,
i. 32500 lumens for 400 W lamps power factor compensated to at least 0.9 lagging. Ballasts
ii. 90000 lumens for 1000 W lamps and ignitors shall be of type specially adapted for make of
iii. 190000 lumens for 2000 W lamps lamps selected. Ignitors shall be electronic thyristor type.
Lamp shall be able to start with at least +/-10% from line
d) Low pressure sodium lamps shall be type SOX voltage, and with normal operation dips up to 20% for four
or SOX (E) and shall conform to IEC 60192:2001, seconds. Compensation shall ensure that there is no large
with guaranteed average life above 18000 hrs increase in operating current during starting. Control gear
and having initial luminous output equal to or losses shall not exceed 10%. Cables for internal wiring in
above the following: control gear compartments shall be single core 2.5 mm2
SOX type: copper conductors with suitable high temperature
insulation and sheath.
i. 4800 lumens for 35W lamp
ii. 8100 lumens for 55W lamp 6 Exposed metal parts of floodlights shall be painted
iii. 13500 lumens for 90W lamp with corrosion and heat resistant paint, resisting operating
iv. 22500 lumens for 135W lamp temperatures attained in direct sunlight while lamp is
v. 33000 lumens for 185W lamp burning.
7 Floodlights shall be located as shown on the
SOX E type:
Drawings and mounted on specially designed brackets to
i. 1800 lumens for 18W lamp allow swiveling in any desired direction and locking firmly
ii. 3600 lumens for 26W lamp in final position. Protractor scale shall be provided for
iii. 5800 lumens for 36W lamp accurate setting.
iv. 10500 lumens for 66W lamp 8 Bolted earthing terminal shall be provided in each
v. 17000 lumens for 91W lamp fitting.
vi. 26000 lumens for 131W lamp

15 Permissible base temperature shall not be greater 15.8.3 Construction Requirements


than 250 deg. C, and maximum bulb temperature not 1 Lighting masts/columns shall be handled,
greater than 550 deg. C. Lamp burning position for 2000 transported and erected in such a way so as to avoid any
W, 240 V lamp is to be possible up to 75 degrees. damage. Any damage to pole or galvanizing shall be made
16 Multi-piece mirror reflectors may be accepted subject good to the satisfaction of the Engineer.
to satisfaction of the Engineer of the quality of the product,

♦ 15- 18♦
copy 249
2 The lighting masts/columns shall be stored clear of into operation, and for erecting material, labor, equipment
soil, ground water or other rust producing materials. The tools, supplies and other work items necessary for the
fixing of poles shall be carried out in accordance with proper completion of the work as specified.
manufacturer’s instructions and good engineering practice.
3 Masts/columns shall be bolted to concrete bases 15.8.6 Items in the Bill of Quantities
constructed in accordance with Sub-section 15.17 and i. High mast assembly (type) (height) (No
erected in accordance with the mast manufacturer's and type of luminaires) (reference dwg.) (nr)
instructions. The column or mast shall be vertical to within ii. Lighting columns (type) (number
0.1% of its height. Final setting and adjustment of the of arms) (height) (type of luminaire)
luminaires shall be carried out after the masts are erected (reference drawing.) (nr)
and operational. iii. Column/high mast testing (Lump Sum)
4 The Contractor shall be responsible until final hand-
over for correcting the alignment of any column or bracket 15.9 Sign Illumination
to its original position except where it is due to vehicle
impact.
15.9.1 Description
5 Where lighting columns/masts are to be installed in
the vicinity of overhead power lines, the Contractor shall 1 This Sub-section describes requirements for
inform the Engineer and act as directed. He shall maintain supplying, installing and putting into operation the
clearances from the power lines as the Concerned illumination of overhead and roadside signs where shown
Authority’s requirements. on the Drawings or directed by the Engineer.

6 Masts/columns shall be erected to the height and


15.9.2 Materials
with the luminaires as shown on the Drawings. Each
luminaire shall house the required lamp oriented to give 1 Luminaires where used to illuminate signs shall be
the illumination and luminance on the road surfaces as wide angled floodlights of the totally enclosed type
stated in Clause 15.1.15, (3) and Table 15.1.15.1. conforming to IEC 60598-1, -2-5( Luminaires – Floodlights)
7 Luminaires on columns shall be aligned parallel with and BS EN 12899-1:2001 (Fixed Vertical Road Traffic Signs,
the longitudinal profile of the road and set at 90° to the Fixed Signs). The body of the floodlight shall be
centre line. composed of an extruded aluminum alloy box closed on
the front by a protector of vandal resistant glass. The
8 High masts incorporating mobile luminaire rings
protection rating shall be IP 65 to IEC 60529.
shall be capable of supporting a portable personnel cage
for maintenance. The Contractor shall provide the cage 2 The lamp and control gear shall be mounted in two
which shall be capable of safely carrying two persons plus separate compartments. Alternatively, the control gear
servicing equipment. may be housed remotely. Power factor compensation
shall be 0.9 or better.
9 The Contractor shall number all the columns/masts
with high quality paint using stencil for 50mm high 3 Photo-electric control units shall be of the plug-in
lettering. The numbering shall be at 1200mm from the type. The control unit losses shall not exceed 10% of the
bottom of pole towards the road. The numbering shall be nominal lamp wattage. A device shall be provided for the
in a manner as directed by the Engineer. suppression of radio and television interference to CISPR
15 requirements.
15.8.4 Method of Measurement
15.9.3 Construction Requirements
1 Each type of high mast assembly and lighting
column shall be measured separately and shall include 1 The signs shall be adjusted and set correctly relative
brackets luminaires/ floodlights, lamps, terminal blocks, to the vertical plane and the road axis before the electrical
circuit breakers and switchgear, internal wires and cabling, installation work is started. Floodlights and associated
control gear, obstruction lights (if needed), and earthing, fixings shall not obstruct the sign face viewed from the
cable entries, mounting brackets/arms, complete as road. Screening shall be added to the top or bottom
specified, erected, tested and put into operation. edges of the sign to prevent glare to oncoming traffic.

2 Testing of high masts and lighting columns, at the 2 Sign supports and gantries are specified in Sub-
factory and on Site, is given as an item, to cover for all section 14.1.
tests and reports and test certificates. 3 Overhead gantry or cantilever sign lighting shall be
located and mounted as shown on the drawings.
15.8.5 Basis of Payment Mounting shall be provided for each floodlight allowing it
to be swiveled in any direction and locked.
1 The amount of completed and accepted work
measured as provided for above will be paid for at the unit 4 Feeder cable shall be routed via a duct in the
rates stated in the Bill of Quantities which rate shall be full supporting frame or gantry up to platform height and
compensation for supplying, installation, testing, putting terminated into a non-automatic isolator switch. A circuit

♦ 15- 19♦
copy 249
breaker board within the enclosure shall distribute power accessories. Body shall be one piece extruded aluminium
to the individual floodlights. (magnesium - silicon alloy) having a wall thickness of not
5 Roadside sign lighting shall be as described in Items less than 2.5 mm.
3 and 4 above, but with the adjustable mountings on top 2 Exposed metal parts of luminaires shall be factory
of support poles. The poles shall be positioned 1.8m in finished, stove enamelled, with corrosion resisting paint
front of the signs and parallel with the sign face and shall capable of resisting heat emitted by lamp during
be checked and shimmed to be perpendicular before continuous operation. The whole assembly shall be
tightening down. treated against corrosion by anodizing the aluminium.
6 The cable from the sub-station or feeder pillar shall 3 Mirror reflectors shall be 99.5% purity, polished
be routed into the pole via the duct in the base and looped aluminium reflectors and coated with transparent layer of
into a circuit breaker located behind the pole access cover. silicon protection against wiping.
7 Lighting where required for signs located in 4 Control gear shall be mounted on a "plug-in" type
sidewalks in urban areas shall be mounted on the top of control gear tray, and shall be housed in a self contained
the sign supporting poles, projecting in front of the top sealed box.
edge of the sign and braced. 5 Earth wire shall be connected through the plug and
8 The earth of the cables shall be bonded to the earth socket connector to ensure that the earth potential is
terminal of each enclosure. maintained on the gear tray when it is being removed
from the luminaire for maintenance purposes.
15.9.4 Method of Measurement 6 Luminaires shall have a hinged front glass with at
1 Each type of overhead or roadside lighting assembly least 2 hinges assembly which shall comprise a clear
shall be measured separately by the number of complete toughened glass plate, not less than 5.0 mm thick, capable
floodlight installations supplied, erected and put into of swinging to the vertical position. The front glass
operation, complete with lamps, supporting steel work, assembly shall seat on to a neoprene non rotting type
switchgear, control gear, interconnecting cables and gasket and once seated shall provide the required degree
earthing as necessary. of protection. Glass used shall be shatter proof (of the type
which once broken, no part of the glass will fall on the
15.9.5 Basis of Payment carriageway). Each luminaire shall have an HRC fuse for
protection.
1 The amount of completed and accepted work 7 Luminaires shall be complete with their mounting
measured as provided for above will be paid for at the unit accessories and shall be supported from uni-strut
rates stated in the Bill of Quantities which rates shall be galvanized steel channel fixed to the soffit of the bridge.
full compensation for supplying, installation, testing, Fixing details shall be submitted to the Engineer for
putting into operation, for materials, labor, transport, approval.
equipment tools, supplies and other work items necessary
8 Lamp sockets shall be high grade porcelain, mounted
for the proper completion of the work as specified.
in support brackets with provision to adjust lamps
vertically and axially. Lamp support and locking system
15.9.6 Items in the Bill of Quantities
shall grip and prevent lamp movement during operation.
i. Overhead sign lighting (gantry or cantilever) 9 Ballast and control gear shall be mounted in
(reference drawing.) (nr) luminaire in separate compartment isolated from the lamp
ii. Roadside sign lighting (sign ref. no.) and with enclosed terminal blocks fitted with quick-
(reference. drawing.) (nr) disconnect electrical leads. Where required, control gear
shall be contained in the prewired box, having an
15.10 Under Bridge Lighting enclosure of IP 65, and mounted on luminaire ring
separately from luminaires. Control gear shall be plug in
15.10.1 Description type for operation at 240 V, A.C. single phase, 50 Hz.
Ballast shall be specially selected for particular type of
1 This Sub-section describes requirements for
lamps used, and lamps shall be able to start with at least
supplying, and installing under bridge surface luminaires
+/-10% variation of nominal voltage and continue in
and/or recessed lighting in prepared cutouts such as in
normal operation with dips attaining 20% for four seconds.
concrete structures.
Control gear losses shall not exceed 10% of normal lamp
wattage. RFI suppression device shall be provided. Power
15.10.2 Materials factor shall be compensated to at least 0.9 lagging.
15.10.2.1 Surface Mounted Luminaires 15.10.2.2 Recessed Mounted Luminaires
1 The fitting shall be totally enclosed, dust and jet 1 Luminaires shall comply with IEC 60598-1, IEC 60598-
proof, conforming to at least IP65 of IEC 60529, and 2-2, and IEC 60598-2-3
conforming with IEC 60598-1, shock resistant and specially
designed to house the required lamps, electrical gear and

♦ 15- 20♦
copy 249
2 Luminaires shall be recessed flush mounted 15.11 Traffic Signals
weatherproof type including lamps, a frame for the
concrete opening and a housing for the control gear. 15.11.1 Description
3 The luminaire body shall be made from epoxy 1 This Sub-section describes requirements for the
powder coated galvanized sheet steel or from extruded or design, supply, installation, commissioning and
pressure die-cast corrosion resistant aluminium alloy. monitoring/review of traffic signal installations and all
Aluminium shall be anodized and painted grey. associated signal equipment.
4 Luminaires within 4m of finished ground level shall 2 The terms used are as defined in the Highway Design
be vandal resistant. Standards.
5 The luminaires shall have a hinged front glass
assembly of prismatic toughened glass, not less than 15.11.2 Materials
6.5mm thick, fixed and sealed into a metal frame which
15.11.2.1 General
shall have a rapid closing device They shall be fitted with
'trimming plates' to provide a flush appearance. 1 The equipment shall function satisfactorily for an
6 The protection rating shall be IP65 to IEC 60529 for all input voltage of 240v ±15% and input frequency 50Hz ±4%.
luminaires in the underside of bridge superstructures and If required a form of automated stabilizer shall be
luminaires in walls. incorporated.
7 The optical system, electrical control gear and lamp 2 All signal equipment should be suitable for operation
shall be mounted on a 'plug-in' type reflector gear tray. in the climatic conditions of Oman. The equipment should
The ground wire connection shall be taken through the be operational between -15°C and +60°C, and resistant to
plug and socket connector. dust/sand contamination. A minimum of 5 years operation,
with routine maintenance, should be expected from any
15.10.3 Construction Requirements installed equipment.
3 The equipment shall comply with the requirements
1 The luminaire shall be fixed surface mounted or flush
of the Highway Design Standards for timings, signal
with the concrete surface into a preformed non- corrodible
sequence and associated detectors.
framed opening as pertaining to the lighting unit specified.
4 All signal equipment shall comply with the
2 Wiring shall be ducted in conduits embedded in the
interference limits given in BS EN 55015:2006 (Limits and
structure or hidden from view within the structure and
Methods of Measurement of radio disturbance
shall loop in and out of conduit boxes serving the
characteristics of electrical lighting or similar equipment).
luminaires.
15.11.2.2 Controllers
15.10.4 Method of Measurement
1 Controllers shall be fully programmable and modular
1 Each type of lighting assembly shall be measured in design to allow the replacement of faulty components
separately by the number of lighting units (luminaire, or the addition of extra circuit boards and features as and
lamp, control gear, terminal blocks) supplied, installed and when required.
put into operation.
2 Controllers should have at least the following inbuilt
modes of operation available for use:
15.10.5 Basis of Payment
i. Manual
1 The quantity of completed and accepted work
ii. Fixed time
measured as provided for above will be paid for at the unit
iii. Vehicle actuated
rates stated in the Bill of Quantities which rate shall be full
iv. Urban traffic control
compensation for supplying, installing, testing and putting
v. Pedestrian fixed vehicle period
into service, and for materials, labor, equipment, tools,
vi. Pedestrian vehicle actuated
supplies and other work items necessary for the proper
vii. Bus/light rail transit priority
support and completion of the work as specified.
viii. Part-time
ix. Cable-less linking facility
15.10.6 Items in the Bill of Quantities x. Hurry call
i. Under bridge surface mounted luminaire xi. Emergency priority
(type) (reference drawing.) (nr) xii. Standby software flash mode
ii. Under bridge recessed lighting luminaire
(type) (reference drawing) (nr) 3 Controllers shall utilize solid state lamp switching
cards, with a maximum load per lamp switch card of 20A.
The switch cards should be able to support both ELV and
LV configurations.
4 Standard 240v Low Voltage (LV) Controllers:

♦ 15- 21♦
copy 249
i. Shall be able to support between 24 and 36 require manual on-site intervention of a maintenance
phase outputs, arranged on up to 4 separate engineer before normal operation is resumed.
phase driver cards, used as required. 15 The controller shall have a fused master switch to
ii. Shall be able to support dimming facilities of isolate the controller. This fuse shall be of a rating
120v, 140v or 160v RMS. calculated from the cumulative load of all signal
iii. Each output lamp switch shall be able to support equipment attached to the controller and done on a site by
a 4A load, with a maximum total lamp load on site basis. A fault on any signal circuit shall not cause
the controller of 20A - 30A. damage to the controller.
16 The electrical supply to the controller shall have its
5 Extra Low Voltage (ELV) controllers:
own fused system which should not be isolated by the
i. Shall be able to support between 24 and 36 controller switch.
phase outputs, arranged on up to 6 separate 17 It shall be possible to isolate all signal lamps by use
phase driver cards, used as required. of a switch and fuse whilst retaining supply to the
ii. Each output lamp switch shall be able to support controller.
a 2A load, with a maximum total lamp load on
18 Controller cabinets shall be housed in weather
the controller of 20A - 40A.
resistant, dust resistant corrosion resistant cabinet. The
iii. Shall have a lamp supply voltage of 48v RMS
front of the cabinet shall have a full length locking door to
with a signal dimming option of 27.5v RMS
allow access to the control equipment. A swing frame
shall be provided to allow access to the rear wiring of
6 Controllers shall provide visual displays of the components. Smaller flap doors can be used to give
current mode of operation and current stage / timings. access to manual panel, telecommunication and electricity
7 Controllers shall have the facility to allow testing to connections as required.
be carried out via a handset port. This shall allow minor
amendments to the controller configuration to be made, 15.11.2.3 Signal Equipment
and allow artificial demands and extensions to be placed 1 Signal poles shall be constructed of galvanized steel,
in the controller for testing purposes. covered by seamless high density polythene. A terminal
8 Controllers shall have the facility to allow for on-site block assembly shall be mounted on the top of the mast,
adjustments to be made to the signal timings, via the covered by a polythene cap.
connection of a handset. These timings should include, 2 Standard signal poles shall be 4m in length. 4.75m
but not be limited to, VA maximum green times, poles may be used when the extra height would enable
intergreens, detector extension timings, detector fault better signal visibility.
management (DFM) values, and the controller’s timetable.
3 6m poles, with two signal heads mounted at different
All signal timings inputted this way shall be subject to pre-
heights, may be used on roads with high speed limits or
determined limits, imposed for safety reasons during the
where a 4m or 4.75m pole would not provide sufficient
initial design.
signal visibility. However, they should not be considered
9 It shall not be possible, through any hardware or as a preferred solution for signal installations where other
software failure of any component of the controller, to options exist.
give a right of way to two conflicting signal phases.
4 Short 2m poles may be used at crossing points to
10 The controller shall have the facility to monitor all house a single pedestrian push button.
equipment connected to it, reporting failures as and when
5 Signal heads shall meet the requirements set out in
they occur.
BS EN 12368:2006. They shall be lightweight, modular
11 The controller shall have an integral lamp monitoring designs with a minimum lens diameter of 200mm to
unit that allows safety critical signal aspects to be 300mm. All signal heads shall contain anti sun-phantom
monitored for lamp failure and appropriate reporting technology. LED signal heads may be utilized as well as
action taken when this occurs. traditional tungsten bulbs.
12 Should any single approach suffer a single red lamp 6 Backing boards shall be provided on all signal heads
failure, then the controller shall report a red lamp failure with an East-West alignment, to enhance signal visibility.
warning (RLF1) On other alignments backing boards are recommended
13 Should two or more red lamps fail on any single and shall be provided if instructed by the Concerned
approach, the controller shall report a second red lamp Authority.
failure (RLF2) and inhibit conflicting pedestrian phases 7 For vehicle detection purposes on a vehicle actuated
from gaining right of way. On standalone pedestrian control strategy, above ground vehicle detectors may be
crossings, the facility shall shut down all signals when this used instead of inductive loop facilities.
condition arises.
8 Where the 85th percentile approach speed is over
14 A single red lamp failure condition can be self-reset if 4km/h, it is recommended that microwave, radar or optical
the controller detects the lamp to be working again, devices be utilized. For stop-line detection of vehicles,
however a two or more red lamp failure condition shall

♦ 15- 22♦
copy 249
pedestrian detection or where the 85th percentile speed of However, stage skipping must not occur to service a
vehicles is below 4km/h, infra-red or optical detection is demand, unless the stage is demand dependant. In the
recommended. event of a stage being terminated by the expiry of a
9 Inductive loops may be utilized where it is felt that maximum green period, a revertive demand shall be
above ground detection is not suitable for site operation. introduced for that stage.
Where loops are to be installed they shall be 2 meters 8 In fixed time mode, the controller shall cycle through
apart in the direction of traffic flow, and consist of 3 cable all (or pre-defined) stages in a pre-set timing sequence.
turns. 9 In manual control mode, the operation of the stage
buttons shall cause the controller to move to, and to
15.11.2.4 Signal Operation
remain on, the selected stage (subject to the expiration of
1 The signal timing ranges shall be as stated in Table the minimum green period of the current stage and the
15.11.2.1. associated inter-green). An indicative light shall be
provided to show the current state of the controller under
Standard Period Length (s) manual mode.
Minimum Green 4 – 50 (in 1s steps)
15.11.3 Construction Requirements
Vehicle Extension 0.4 – 31.8 (in 0.2s steps)
15.11.3.1 Cables
Maximum Green 0 – 255 (in 1s steps)
1 The wiring of all cables shall meet the IEE Wiring
Leaving Amber 3 (fixed)
Guidelines, 17th Edition (BS 7671).
Starting Amber 2 (fixed)
2 All signal heads on a single traffic phase shall not be
Inter-greens 0 – 254 (in 1s steps) connected to the traffic signal controller on the same cable
Starting Inter-green 8 – 12 (in 1s steps) run.

Phase Delays 0 – 20 (in 1s steps) 3 For new cable runs, 16 core cables with 1.5mm2
cores shall be used for both ELV and LV applications. In all
Pedestrian Blackout 3 – 20 (in 1s steps)
cable runs, 4 cores should be left disconnected for
Table 15.11.2.1: Traffic Signal Timing Ranges redundancy purposes.

2 Provision shall be made for inter-green times 4 All cables shall be tagged in the controller to easily
between stages, and the circuitry shall include safety identify which equipment or pole a cable is connected to.
features to prevent simultaneous display of conflicting 5 Cable tags shall be colored red for cables carrying a
green indications. low voltage (LV) and yellow for cables carrying an extra
3 Manual operation may override all modes, except low voltage (ELV).
UTC control. If manual operation is required at a UTC
15.11.3.2 Controller Root
controlled site, then the UTC computer shall remotely
disconnect its link with the controller. 1 The controller cabinet shall be set on a concrete
4 The modes of operation available by manual plinth, if it is above ground, or in a waterproof pit if below
selection shall be: ground. Design of the plinth or pit shall be submitted to
the Engineer for approval before the plinth or pit is
i. Cableless linking facility (CLF) constructed. The cabinet shall be secured to the plinth or
ii. Vehicle actuated (VA) pit base by suitable anchoring devices. Provision shall be
iii. Fixed time made for ducts and conduits embedded in the plinth or pit
iv. Manual for easy access for cables. Adequate permanent protection
5 Under vehicle actuated mode, when there is an shall be provided to keep the cabinet and its contents free
absence of demands, it shall be possible to revert to an all from damp, dust, vermin and any other harmful
red condition, flashing ambers, or a specified stage. conditions.

6 If the flashing amber is to be used during periods of 2 Alternative materials may be proposed for the
low or no demand, such as night-time, then the flashing Engineer’s approval, such as standard heavy duty plastic
mode shall be preceded by a steady amber and the other underground pits and precast concrete plinths, which
vehicle and pedestrian signals extinguished. The flashing satisfy the requirements for stability and proof against all
rate shall be between 55 and 85 per minute, with equal on environmental conditions.
and off intervals. The flashing mode sequence shall be
15.11.3.3 Ducts
ended by the signals reaching an ‘all red’ period for 3
seconds, followed by the normal start up sequence 1 A system of ducting shall be provided so that all the
leading to a right of way being shown on a pre-defined signal poles and the controller are inter-connected by a
start up stage. duct network. Duct paths should be straight lines, linking
7 Under vehicle actuated mode the controller shall each draw pit in the network. Where a straight line is not
honor vehicle demands as and when they appear.

♦ 15- 23♦
copy 249
possible, due to sub-surface obstructions, a radius bend of ducts shall be fixed within the base to connect to the
no more than 35° may be used. signals.
2 Ducts shall be laid a minimum of 600mm below the 2 Where conditions prevent construction of the pole
carriageway surface or 450mm below the footway surface. base as stipulated above, the Contractor shall provide
3 Whenever a duct network crosses a road, at least 3 poles with welded steel base plates and anchor bolts to
ducts shall be provided under the carriageway. provide stability, all as approved by the Engineer.

4 Ducts shall be 100mm internal diameter as standard, 3 For high masts, the design of the concrete base and
however, separate 50mm internal diameter ducts may be anchoring devices shall be proposed by the Contractor,
used to carry the electricity supply and telecommunication based on structural calculations for the ambient conditions,
cables to the controller, but no other cables shall be and shall be approved by the Engineer before construction.
installed inside these ducts.
15.11.3.6 Cantilevers and Gantries
5 Spur ducts to the signal pole location, from the
nearest draw-pit shall be provided. These can be 50mm or 1 Where traffic signals need to be mounted on
100mm diameter depending on the number of cables to cantilevers or gantries, those structures should be in
be installed. accordance with the drawings and schedules. Fabricated
steel structures shall be in accordance with Section 6
6 Polypropylene draw cords, break weight 5.5kN shall
(Structural steel and other metal work) and Section 7
be provided in each duct; these draw cords shall be
(Paint) of this Specification.
continuous over their entire length with no joints or knots
and shall extend one meter from each end of the duct. 15.11.3.7 Miscellaneous
They shall be replaced on each cable draw through so that
they can be reused. 1 Upon completion of the work the controller base
shall be filled with a base sealant that dries hard to
7 Cable duct route identification markers in accordance
prevent vermin infestation into the controller cabinet.
with MEW Standard OES 2 shall be provided at 25m
maximum spacing throughout the entire installation and 2 Ducts shall be sealed with a foam substance or wire
at terminations and bends in the route. wool to prevent vermin infestation through the duct
network.
8. Refer to subsection 15.17 – civil works for electrical
and communication installations for any other conditions. 3 Road markings at all installations shall be in
accordance with the Oman Highway Design Standards
15.11.3.4 Draw Pits and Section 14 of these Specifications.

1 Draw pits shall be either constructed of pre-cast 4 On approaches to all pedestrian crossing points,
concrete rings; brick built or reinforced high density special anti-skid road surfacing shall be laid 50m from the
polyethylene. Draw pits shall comply with BS EN 124. crossing studs in the direction of on-coming traffic. The
surfacing shall have a minimum skid resistance value of
2 Draw pits shall not be placed in the carriageway. If
55 when tested in compliance with BS EN 3262-12:2001.
this is unavoidable, then a higher specification draw pit
shall be used, capable of withstanding the loading of 15.11.3.8 Completion
traffic.
1 All signal equipment shall be assessed on site after
3 A master draw pit, minimum size 600mm x 600mm x
installation is completed by use of a commissioning check
600m deep, shall be constructed in front of the controller
list to ensure that the installation is complete and
location to allow the cables to be easily fed into the
complies with the quality and functional requirements of
controller housing.
the Specification.
4 When ducts cross a road, draw-pits, size 1200mm x
2 The Contractor shall submit final close-down
900mm x 900mm deep, shall be installed on either side of
paperwork, to include:
the carriageway and in central islands and medians, to
assist with cable pulling. They should not be installed in i. Site layout drawings (as installed)
the carriageway or installed in a location that would ii. Timing sheets
interfere with any pedestrian movement. iii. Signals hand-over certificate, including test and
5 On longer cable runs, draw pits shall not be more commissioning reports
than 50m apart. iv. Operation and maintenance manuals.

6 Where possible, drawpits shall be located adjacent to


signal poles to allow cables to be spurred off to the pole
15.11.4 Method of Measurement
installation easily. 1 Traffic signal installations shall be measured by the
number of completed sets of signaling equipment and
15.11.3.5 Pole installation
materials installed, modified or modernized at any one
1 Standard 4 meter high poles shall normally be set in location and shall cover all requirements including
a concrete base minimum 600mm x 600mm x 650mm controllers, sensors, signal poles, signal heads, cables,
deep. The depth shall be increased for longer poles. Cable

♦ 15- 24♦
copy 249
drawpits, ducts, foundations, all completely installed and operation exposed to sun, dust storms, corrosive elements
commissioned. and the adverse climatic conditions at the location.
2 Cantilever and Gantry supports for traffic signal 3 Electronic equipment shall use components of
heads shall be measured by type and number installed, assessed quality in accordance with the system outlined in
and shall include foundations, fixings and mounting. BS 9000 General Requirements for a System for Electronic
3 The unit rates shall be deemed to cover for all work Components of Assessed Quality, or other approved equal.
at each installation location, including design, submission 4 All equipment shall be to the approval of the
of drawings, obtaining approvals from all Concerned Concerned Authority. It shall have a proven in service
Authorities, the supply, construction and installation, record, and documentary evidence of this shall be
transport, and all civil work and miscellaneous items and submitted. Full environmental tests shall be carried out
close-out procedures. on a production sample by an independent testing
authority and a certificate supplied to show the suitability
15.11.5 Basis of Payment of the equipment for use in the specified environment.

1 The amount of completed and accepted work as 5 Materials and components shall be the latest
provided for above, will be paid for at the unit rate stated technology and best of their respective kind and modern
in the Bill of Quantities, which rate shall be full practice, selected and treated so that no corrosion will
compensation for supplying materials, installation, testing occur during the lifetime of the installation estimated at 20
and putting into operation, for labor, transport, equipment, years.
tools supplies and other items necessary for the proper 6 All wiring shall be neatly and securely fixed in
completion of the work. position in an approved manner. The wiring shall be in
high temperature PVC insulated cables or silicon rubber,
15.11.6 Items in the Bill of Quantities color coded for ease of identification. All terminals shall
be of adequate size.
i Traffic Signal Installation
7 NEMA 3R (IP 66 of IEC 60529) rated metallic
(location and designation equipment enclosures shall be provided with terminals for
shown on drawings) (Lump Sum) attachment of ground safety circuit.
ii Overhead Traffic Signal Support 8 Masts shall be designed and constructed to provide
including foundation (type) (nr) adequate support and stability for the sign and shall be
suitable to support more than one assembly. They shall
be complete with base compartment and pole top
15.12 Overheight Vehicle Detection
compartment complete with terminal chambers for
System connecting incoming cables.
9 Masts shall be constructed from seamless steel,
15.12.1 Description
tubular, with a wall thickness not less than 4.5mm and a
1 This Sub-section describes requirements for the tensile strength of 520 MN/sq.m hot dipped galvanized.
design and installation of the system to detect over-height No machining operation shall be allowed after completion
vehicle/trucks approaching underpass and to display a of the galvanizing process. Masts shall be painted with 2
warning to alert drivers not to enter the underpass. coats of epoxy resin paint to an approved color finish after
completion of the galvanizing process as required by the
15.12.2 Design Criteria for Materials and Concerned Authority / Engineer.
Components 10 Signs shall be mounted on -brackets supporting both
1 The equipment shall be designed to operate on A.C. top and bottom of the sign. Attachment shall be of
240 volts single phase 50 Hz with a voltage variation of stainless steel clamps and mounting brackets which shall
plus 15 percent or minus 20 percent and frequency incorporate a wiring duct for the sign wiring. The
variation of plus or minus four percent. If the equipment is attachment shall allow vertical and angular adjustment of
sensitive to voltage fluctuations within the above stated the sign assembly and shall be suitable for the sign
limits, an automatic voltage stabilizer shall be presentation.
incorporated in the system, along with a stand-by 11 Mounting heights of sign, the type of sign and the
uninterruptible power supply system for maintaining signal presentation shall be as will be detailed by the
system memory. Concerned Authority.
2 Equipment shall be designed and derated for
continuous operation under operating conditions 15.12.3 Operational Requirements
stipulated in Sub-section 15.1. The variation in light 1 All over-height vehicles or vehicle loads traveling
intensity caused by the shadow of passing clouds shall not toward the tunnel shall be detected and a warning signal
interfere with the proper operation of the equipment. The given. Vehicles traveling away from the tunnel shall be
equipment shall be suitable for uninterrupted full load ignored by the detection equipment. Detection of vehicles

♦ 15- 25♦
copy 249
traveling toward the tunnel shall be counted and recorded 4 Two 1/8 inch (.32 cm) boresight holes are to be
on an installed electronic counting device. located at Top-Middle of each housing. Front and rear
2 The detection system shall consist of visible red or screws are to be installed in these holes so as to insure a
infra red source(s) spectrally matching detector(s) weather tight enclosure, and should be removed to allow
mounted on poles positioned on opposite sides of the alignment of units. Looking through boresight hole from
approach roadway. The alignment and height of the rear of unit so as to see through the boresight hole in front
visible red or infra red beam shall be preset to identify of unit gives the installer a basic means of aiming the unit
vehicles over 4.25m above the roadway at the line of in the proper direction. Focusing the unit on opposite
detection or as requested by the Concerned Authority. sides of the road in the center of the front boresight while
looking through the rear boresight hole ensures that a
3 Positive measures shall be introduced to warn
general alignment is accomplished. This step should be
drivers of a potential accident if they proceed and to
done from both Transmitter and Receiver Unit locations.
instruct them not to continue, whilst causing the least
Fine tuning of alignment can then be done electronically.
possible disturbance or distraction to other motorists.
5 The transmitter unit and the receiver units shall each
4 Warning and instructions for drivers of over-height
be provided with a barrier to protect the operating
vehicles shall be stated on the face of the warning sign
equipment. The enclosure shall maintain its structural
which shall be illuminated internally, i.e., nature of danger
integrity for the operational life of the equipment and shall
“OVERHEIGHT” and action to be taken (“STOP” or “TURN
allow ready access for control adjustment and electrical
RIGHT” or “EXIT RIGHT” or “USE RIGHT (LEFT) LANE,” or
interconnection without the use of any tools except a
“DO NOT ENTER” etc) if the driver proceeds. The action
Phillips head screwdriver.
must cause the driver to become alert to the extent that he
should react as instructed. 6 Each of the equipment units shall be provided with
means for rigidly attaching the unit to a vertical cylindrical
5 Warning Sub-system shall consist of a flashing light,
pole without requiring any machining operation. The
an audible alarm, and an electronic message board.
attachment means shall not stress or deform the unit and
Upon receiving the control signal from the detection shall prevent the movement of the unit in any direction by
subsystem, this warning subsystem is to be activated and the force developed by wind. The mounting means shall
shall respond by alerting the driver to either stop the allow adjustment of the vertical position on the pole. The
vehicle or take an alternative route. The warning mounting means for the transmitter unit and the receiver
subsystem shall comprise the following: unit shall have the capability of adjusting the angular
i. Warning message on LED display orientation of the optical axis in both the horizontal and
ii. Loud audible alarm, 111 dB@ 3m vertical plane over an angular range of plus or minus five
iii. Flashing Red warning light degrees from horizontal. The transmitter and receiver unit
shall be mounted to detect the presence of vehicles that
15.12.4 Physical Requirements exceed the specified vertical height.
7 Warning sign shall meet all electrical /electronic
1 The detector unit shall be solid state with printed
specifications and shall conform, in all essential elements,
circuit boards and regulated power supply. The unit shall
with the provisions of the U.S. D.Q.T, F.H.A. Manual on
be of modular construction. It shall have an effective
Uniform Traffic Control Devices. Plastics on sign faces
range of 3m to 38m with a reaction speed range of one
shall be protected by LEXAN or other material providing
(1)MPH (1.61 km/h) to seventy-five (75) MPH (121 km/h) for
equal or greater defense against flying object damage or
a 2 inch (5 cm) diameter object 1 inch (3 cm) above the
vandalism. Signs shall be activated and time controlled
detection height. It shall provide a fault reporting output
by the Detection unit. Lighting shall be provided by high
upon loss of space/detector power or total failure.
output fluorescent bulbs for message and incandescent
2 Sensors are to have NEMA 6P rated enclosures, bulbs with parabolic reflectors for arrows at the top and
direction selection to be from a selection switch. No tools bottom of sign. Flashers on LED signs should be of
or adjustment is required. 300mm diameter.
3 Four LEDs and meter shall be provided for ease of 8 Sign housing shall be as indicated on drawings and
alignment and testing. Provision shall be made for the provided with rectangular (shape) reinforced aluminum
elimination of the effect of ambient light and an internal capable of withstanding wind loading up 95 km/h and
environmental control element that reduces operational provided with a sun shield projecting at least 36 cm.
failure from fog, condensation and insects. Dimensions Letters and arrows shall be normally blanked out. When
shall not exceed a maximum overall size of 18 x 15 x 10 illuminated, arrows shall be red in color, but can be made
inches (46 x 38 x 25 cm). The housing shall be of high in any color specified (IP 65 rating).
grade extruded aluminum and sheet aluminum of not less
9 Unit mounting poles (shaft) shall be one or two piece,
than 1/8 ″ thickness, and weather sealed for rugged
adjustable height, seamless, round aluminum tube. Poles
durability and extended life. The mounting shall allow for
shall include a handhole centered 46 cm above the bottom
directional adjustment and aiming after initial installation.
of the shaft with a cover secured with stainless steel
screws. Base flange for the attachment of the shaft to the

♦ 15- 26♦
copy 249
foundation shall be a one piece cast socket of aluminum shall be inserted in the excavation supported at the correct
alloy, with 4 anchor bolts for fixing to the concrete base. level and grouted in. In-situ foundations shall be
10 Single core cables for internal wiring shall be 450/750 constructed as shown on the Drawings with the concrete
volt flexible PVC insulated copper in accordance with BS poured around the reinforcing and holding down bolts
6004:1984 or approved equal standard with high and consolidated in one operation.
temperature insulation where operating in high ambient 7 The position of the anchor bolts and the level of the
temperature conditions. The conductor size shall be in top surface shall be exactly determined and adjusted. PVC
accordance with the circuit requirements. Cables shall be ducts of sizes shown on the drawings shall be installed in
bunched, clipped and properly secured to form a complete the bases for cable access.
wiring loop.
11 Power and signal cabling shall be provided between 15.12.6 Method of Measurement
the receiver unit electronics and the junction box adjacent 1 Over-height vehicle detection systems shall be
to the mounting pole foundation. Power for the receiver measured as the number of completed systems. The rate
and transmitter units will be made available at the junction shall include for supply and installation, testing and
box located adjacent to the mounting pole foundation. commissioning of transmitter and receiver units, warning
12 A solar panel shall be supplied with the OVDS to signs, masts with interconnecting cables and earthing as
make use of solar energy for stand-by power to enable the necessary, cables, including all foundations, ducts,
system to remain powered even under power failure drawpits and associated civil work.
conditions for limited periods.
13 A fault reporting function would be incorporated in 15.12.7 Basis of Payment
the system to detect any malfunctions in the system and
1 The quantity of completed and accepted work
alert the authorities.
measured as provided for above will be paid for at the unit
14 All non current carrying parts of the equipment and rate for a complete operational system stated in the Bill of
installation shall be earthed. Quantities, which rate shall be full compensation for
15 The armoring and screens of all multi-core cables supplying, installing, testing and putting into service, all
installed directly in the ground shall be bonded and materials, transport, labor, equipment, tools, supplies and
connected to the earth bar together with the earth core of other work items necessary for the proper support and
the electricity supply cable. A separate single core copper completion of the work as specified.
PVC insulated (green/yellow) installed back to the
electricity supply point shall be provided if the incoming 15.12.8 Items in the Bill of Quantities
cable does not include the earth.
i Overheight vehicle detection and

15.12.5 Construction Requirements warning system (system complete)


(location shown on drawings) (nr)
1 Associated civil work for ducts, draw pits and pole
bases shall conform to Clause 15.17.3 – Construction
Requirements.
15.13 Emergency Roadside Telephone
2 The Contractor shall supply and install the
System
underground ducts, construct the cable drawpits as
indicated on the Drawings or as required on site for 15.13.1 Description
installation of the cables. The Contractor shall be 1 This Sub-section describes requirements for
responsible for all excavation, draining trenches, forming emergency roadside telephone systems, including
of duct assembly, backfilling, and removal of excess earth detailed engineering, coordination, manufacture, supply,
and restoring finished grade to its original condition. transportation, delivery, installation, jointing, connecting
3 Ducts shall be as specified under Clause 15.7.2. They up, testing, commissioning, setting to work, training and
shall be laid in trenches in close cluster formation. maintenance services during the warranty period. Work
4 Concrete pole bases shall be designed to take into includes:
account the nature of the ground and the dead and i. Coordination with Concerned Authority, existing
imposed loads of the pole and all attachments. They may contractors, and providers of interfaced
be pre-cast or cast in-situ as detailed on the Drawings or systems.
as instructed by the Engineer. ii. Project management.
5 The excavated hole for the pole base shall be well iii. Planning management.
cleaned and its sides compacted and the base and sides of iv. Detailed functional analysis until approval by
the excavation shall be lined with a heavy duty sheet Concerned Authority.
bitumen or polythene waterproof membrane before work v. Finalization of system to the approval of
on the foundation properly commences. Concerned Authority.
6 Where pre-cast foundations are to be installed they vi. Supply of needed system equipment and
components.

♦ 15- 27♦
copy 249
vii. Transport, unloading, and storage on the Site of xi. BS EN 60118-4:2006 - Hearing aids - Magnetic
the required equipment and components. field strength in audio-frequency induction
viii. Equipment installation. loops for hearing aid purposes.
ix. System installation and configuration. xii. BS EN 60529:2004 - Degrees of protection
x. System integration with interfaced and existing provided by enclosures (IP Code).
systems. xiii. BS 6305:1992 - Analogue inter working and non-
xi. Complete testing of the system (unit tests, interference requirements for Customer
integration tests, final acceptance tests, users’ Equipment for connection to the Public
tests, etc.). Switched Telephone Network.
xii. Training. 3 Other Standards - International Electro-technical
xiii. System implementation, Commission (IEC):
xiv. System roll-out,
i. IEC60068 Environmental Testing
xv. System maintenance after successful initial
ii. Specification for Concrete works, shall be as per
proving period during Warranty,
subsection: Civil Works for Electrical
xvi. Supply of spare parts for 2 years,
Installations
xvii. System maintenance tools delivery,
xviii. Writing and delivering of documentation (user’s 4 Product Data: For each component including
manual, maintenance manual, test reports, etc.) descriptions, colors, complete technical specifications, and
xix. Testing of emergency roadside telephones in manufacturer catalogues for all equipment and materials.
the field. 5 Factory Tests: All equipment and cables are to be
xx. Commissioning of the installation. tested at manufacturer premises, and test certificates, are
xxi. Connection of emergency roadside telephones to be submitted to Engineer before shipping and delivery
to control center to site.
6 Shop Drawings: Submit drawings for approval
15.13.2 Regulations and Standards including, but not limited to, the following:
1 British Standards and Codes of Practice shall apply to i. Detailed system schematic diagram.
the design and installation of the system ii. Detailed layout, locations, and installation of all
2 The following BS are generally applicable and are equipments.
mandatory: iii. Exact routing of all cabling and wiring.
iv. Equipment assemblies and indicate dimensions,
i. BS3573: 1990 - Polyethylene-insulated copper-
weights, required clearances, method of field
conductor telecommunication distribution
assembly, components, and location of each
cable.
field connection.
ii. BS EN60529: 1992 - Specification for
v. Wiring Diagrams: Detail wiring for power,
classification of degrees of protection provided
signal, and control systems and differentiate
by enclosures.
between manufacturer-installed and field-
iii. BS 1363 - Specification for 13 A plugs, switched
installed wiring. Identify terminals to facilitate
and un-switched socket-outlets and boxes.
installation, operation, and maintenance.
iv. BS EN 60898 - Specification for miniature and
Include a single-line diagram showing cabling
moulded case circuit breakers.
interconnection of components.
v. BS 4293 - Specification for residual current-
operated circuit-breakers.
15.13.3 Definitions and Mode of Operation
vi. BS EN ISO 14713: 1999 - Protection against
corrosion of iron and steel in structures - Zinc 1 Description of emergency telephone operation
and aluminum coatings – Guidelines and ASTM i. The principle of this operation is that when a
123. call is initiated in the field, the emergency
vii. BS EN 10327/2004 - Hot dip zinc coatings on roadside telephone automatically calls the
steel sheet. phone number unique to that particular
viii. BS EN ISO 1461: 1999 - Hot dip galvanized telephone. This unique called number is known
coatings on fabricated iron and steel articles - as the ‘indial’ number.
Specifications and test methods. ii. The indial number is connected to control
ix. EN50082-1 - Electromagnetic compatibility center CC (defined by the Concerned Authority).
(EMC) - Generic standards - Immunity for iii. The PABX (private automatic branch exchange)
residential, commercial and light-industrial is programmed to display on a screen:
environments.
a. The pillar number of the calling emergency
x. BS EN 60068-2-78:2002 - Environmental testing -
roadside telephone
Tests - Test Cab: Damp heat, steady state.
b. Its location
c. Any other information as required.

♦ 15- 28♦
copy 249
i. From the pillar number and other information i. Button to initiate an emergency call to CC.
programmed into the PABX the CC operator ii. Button to annunciate recorded information.
answering the call is able to identify the location iii. Speaker to broadcast the ring tone and voice
of the phone being used, including which side communications.
of the carriageway, without the caller giving any iv. Two microphones to record and monitor voice
details. communication, respectively.
ii. The CC operators and the caller are able to v. IrDA interface with infra red port for
communicate clearly in a two way (duplex) programming the telephone features in the
manner. vicinity of the unit.
iii. In the event of a failure, the emergency roadside vi. Two (2) locks with different keying to secure the
telephone can detect the listed defects and will emergency roadside telephone module to the
automatically initiate a call to the CC manager enclosure (pillar). Keying must be keyed alike
and log the details of the defect. across the manufacturers’ telephones.
iv. The emergency roadside telephone must have
facilities for it to be called remotely by the CC 15.13.4.2 Pillar Dimensions and Weight
manager and perform the listed self-diagnostics 1 The pillar dimensions shall be:
and report the results accordingly.
i. Height 1400mm ± 100mm
2 Supply of network facilities and equipment ii. Width 200mm ± 50mm
i. Network supplier iii. Depth 130mm ± 50mm
2 The pillar weight, including the phone equipment,
a. Telephone equipment shall be
shall weigh less than 60 Kg.
coordinated with the mobile
telecommunications service provider. 15.13.4.3 Frangibility
b. It is mandatory that the local operator be
1 The pillar and solar cell support combination shall be
used for the services.
so designed as to be frangible in the event that it is hit by
ii. Each Emergency Roadside Telephone is to have an errant vehicle. The frangibility requirements must
a unique series of numbers : comply with the definition and requirements of BS EN 40-
2:2004.
a. Pillar number
b. The indial telephone number 15.13.4.4 Pillar Materials and Color
programmed to call the CC phone
1 The pillar shall be constructed from marine grade
number
aluminum with a minimum thickness 3 mm or extruded
c. CC manager phone number aluminum with a minimum thickness 5mm.
d. Phone service number (SIM Card)
15.13.4.5 IP Rating
e. Serial number
1 The pillar shall be designed to IP55 (IEC 60529)
f. A four-digit Personal Identification
Number (ID) 2 The electronics enclosure shall be designed to IP66
(IEC 60529).
g. The Pillar number shall be allocated
based on local authority guidelines. 15.13.4.6 Vibration and Shock
3 Monitoring of emergency roadside telephones
1 The emergency phone must remain operable under
iii. Calls from the emergency roadside telephones the following conditions of vibration: Three axes to: +/-
are handled and monitored by CC. 1.5mm 5-13Hz and+/-1g 13-150Hz tested.

15.13.4 Products and Materials 15.13.4.7 Wind

1 The emergency phone must remain operable after


15.13.4.1 Pillar Design and Manufacture
withstanding wind speeds of up to 198 km/h.
1 The emergency roadside telephone shall be hands-
free, vandal resistant and weather resistant. 15.13.4.8 Temperature

2 The emergency roadside telephone shall be housed 1 The emergency telephone shall comply with the
in a pillar with only the solar cell being pole mounted. following temperature requirements:
3 The emergency roadside telephone shall be housed i. Storage temperatures range -10ºC to +70ºC.
in a plinth mounted pillar of dimensions described in ii. A minimum start up temperature of -5ºC.
Paragraph 15.13.4.2 iii. An operating temperature range -10ºC to +70ºC
4 The emergency roadside telephone shall have as a continuous.
minimum the following features: iv. Storage temperature shock changes up to 10ºC
± 5ºC per minute.

♦ 15- 29♦
copy 249
15.13.4.9 Lightning Protection 15.13.5 Power Supply
1 Primary protection shall be provided using fitted gas 15.13.5.1 Power Supply
arrestors.
1 The emergency telephone shall operate from either
2 Secondary protection shall be provided using fitted of the following, as shown on the Drawings or instructed
metal oxide varistors. by the Engineer:
3 Earth stake shall be fitted with a conductor no less i. Powered by a 240 V AC mains available from
than 6 mm bonding the earth stake to the base of the the nearest light pole, where possible.
phone pole and to an earth point within the electronics ii. A fitted solar panel and battery combination,
enclosure. supplied by the Contractor.
15.13.4.10 Vermin Ingress 2 Short circuit protection shall be provided.

1 The pillar shall be pest and vermin proof, including 15.13.5.2 Battery
termites, ants, bees, rats and mice.
1 The battery shall have the following characteristics:
15.13.4.11 Vandalism i. Operating temperature range, -10º C - +70º C
ii. Sealed lead acid rechargeable
1 The pillar shall be vandal and impact resistant to
iii. Sealed and operational in any orientation
prevent unauthorized access to the internal equipment.
iv. Maintenance free
Vandal and impact resistance can be defined as being able
v. Minimum 3 years float service life.
to remain functional while withstanding moderate to
vi. Recyclable
severe blows by hand held objects in most circumstances
vii. No memory effect
without suffering more than cosmetic damage.
viii. To provide a minimum of 7 days normal
2 The pillar shall be fitted with an automatic operation under a primary source failure
tilt/vandalism alert feature with configurable sensitivity condition. Normal operation is based on 6 calls
settings with provision for the emergency roadside phone per day at 10 minutes per call for 7 days, the
to make maintenance call and log its location and remaining time being Idle time.
condition with the CC manager.
3 Access to the fixing bolts attaching the phone to the 15.13.5.3 Battery Charging
concrete pad shall only be obtained from inside the 1 The battery shall be charged with a solar cell or from
emergency telephone pillar. a 240V AC mains supply.
15.13.4.12 Pillar Identification 2 Thermal management of the battery charging to
prevent thermal runaway of the battery shall be
1 International telephone symbols and pillar numbers incorporated.
shall be installed on each side of the pillar.
3 The power supply and charging system shall
2 The International telephone symbols and emergency incorporate battery management to monitor the status of
telephone pillar number shall be manufactured using the battery charge and maintain it at its rated float voltage.
British Standard.
4 Should the battery voltage fall below 90% of its
3 The telephone symbol shall be 150mm in height with nominal float voltage an alarm shall be raised.
a spacing of 150mm from the top of the pillar to the top of
the telephone symbol. 15.13.5.4 Solar Panel
4 The pillar number shall consist of 80 D N numerals 1 The solar panel shall be of sufficient size and wattage
installed vertically down the pillar with a spacing of to ensure that the battery receives sufficient charge under
150mm from the bottom of the telephone symbol to the all weather conditions.
top of the first pillar numeral.
2 A bird guard shall be fitted to the solar cell to
15.13.4.13 Concrete discourage birds from sitting on the cell.
3 The solar cell support shall provide a minimum of 4.0
1 All concrete and reinforcement for the bases and
meters clearance between the ground and the solar cell,
anchor bolt assemblies shall be in accordance with Sub-
such that the solar cell is not accessible without a ladder.
section 15.17
4 The solar cell shall be vandal resistant and attached
15.13.4.14 Steelwork to the mounting such that it cannot be removed without
special tools provided by the supplier.
1 All steelwork for the anchor bolt assemblies shall be
hot dipped galvanized in accordance with BS EN ISO 5 The solar panel shall be installed facing North and be
14713: 1999 and BS EN ISO 14761: 1999. angled towards the sun, with the angle being dependant
on the latitude of the location.

♦ 15- 30♦
copy 249
15.13.6 Construction Requirements 15.13.6.5 Grouting of Pillar Base

15.13.6.1 Drawings 1 After the installation of the emergency telephone, the


Contractor shall impact mortar grout under the pillar base.
1 The Contractor shall prepare drawings to scale and
diagrams as follows:
15.13.7 Method of Measurement
i. Emergency roadside telephone system
schematic diagrams, detailed design, 1 The emergency roadside telephone system shall be
connection diagrams, etc. measured by number of the complete systems, supplied
ii. Construction drawings, including civil works installed tested and put into operation. The unit rates shall
iii. As-built drawings include for all work, including design, supply and
installation, per road; testing, commissioning,
2 All design development drawings, construction
maintenance provision of all drawings and manuals and
drawings, and as-built drawings shall be submitted in hard
all necessary civil works as specified.
copy format as well as in electronic format in the
quantities specified below.
15.13.8 Basis of Payment
3 Quantity of submittals
1 The emergency roadside telephone system shall be
i. Electronic Files: 1 set.
paid for as a lump sum per completed system including
ii. Reproducible hardcopies: 1 set.
transportation, at the unit rate(s) stated in the Bill of
iii. Prints: 3 sets.
Quantities, which shall be full compensation for the
15.13.6.2 Concrete Pad and Pillar Foundation complete system supplied including the roadside
equipment, the network facilities (mobile telecom service)
1 A concrete pad, complete with anchor bolt assembly implementation and putting into operation after testing in
and steel mesh, shall be constructed as detailed in the accordance with the Specification.
Drawings, at each emergency telephone location.

15.13.6.3 Anchor Bolt Assembly 15.13.9 Items in the Bill of Quantities (Unit)
i Emergency Roadside Telephone System
1 The anchor bolt assembly shall include four (4) nuts
and four (4) washers per assembly (Road Ref. No.) (Lump Sum)
2 Sufficient thread shall be provided on each bolt to
allow for the leveling of the pillar when installed. This 15.14 Public Lighting Management and
shall be not less than twice the sum of the nut, washer and Control System (PLMCS)
pillar base plate thickness.
3 All bolts shall be the same length with respect to the 15.14.1 Description
vertical axis of the assembly. The anchor bolt assembly
1 This Sub-section describes requirements for design,
shall be such that the pillar may be mounted parallel to
supply, installation, testing and commissioning of a
the road center line.
complete PLMCS installed in feeder pillars, with individual
15.13.6.4 Pillar Mounted Telephone phase voltage stabilization, dimming, monitoring, remote
control and remote surveillance suitable for later
1 An emergency telephone shall be installed on a connection to server based software for decentralized
concrete pad at each location indicated on the Drawings. operation.
2 Each pillar shall be installed on the anchor bolt 2 The PLMCS comprises:
assembly and adjusted so as to be vertical. The pillar shall
i. Feeder pillar power controller
comply with the requirements of the applicable British
ii. Switching functions
code for structural design for utility services poles for
iii. Remote control management software and
stability.
hardware
3 The emergency telephone shall be installed such that
the buttons, speaker and microphones are facing away 15.14.2 General Requirements
from the direction of traffic flow such that a person using
the emergency telephone is facing the phone and 1 The PLMCS shall control the function of the ordinary
oncoming traffic. feeder pillars (FP).

The pole for the solar cell shall be installed on the side of 2 The PLMCS shall be installed at each feeder pillar
the pillar further away from the curb such that it does not position and control all luminaries of that FP.
obstruct the view of the pillar number when viewed by 3 The PLMCS shall be capable of being upgraded later
drivers approaching the pillar. to have full remote control, including remote servicing,
4 Refer to Series 1500 of the DRMB UK Standards for communication of alarms, down-loading of recorded
highways for all these works. information. and reporting malfunctioning to a control
center.

♦ 15- 31♦
copy 249
4 The PLMCS shall work with all luminaires; HPS and 19 The transition from lamp warming to planned stage,
HPMV type, equipped with standard magnetic ballast, or any intermediate level regulation process, shall be done
ignitor and PFC capacitor. without disconnection and shall be applied in maximum
5 The PLMCS shall be capable of dimming HPS and steps of 2.2V. The process of dimming shall be even,
HPMV lamps in a range of 100% - 50% and stabilize the without visible steps in luminance.
voltage for MH and FL lamps. It shall be capable of 20 The PLMCS shall incorporate a high accuracy
stabilizing the output voltage for each phase individually astronomical time clock which can be remotely controlled
to +/-1% for input voltage fluctuations from 175V to 264V from the control center.
and shall be able to increase the output voltage by at least 21 Programming and reading of the parameters shall be
30V to compensate for low input voltage. done via PC software, able to read the real time
6 The PLMCS shall be designed to save between 15% measurement and to change all the parameters of the
and 35% of energy on average and shall ensure up to feeder pillar, operable through either a direct cable
double the lamp life. connection between the PC and feeder pillar or with GSM.
7 The PLMCS shall be completely static, that is with no 22 The supplier shall be responsible for installation,
moving parts such as ‘variac-type’ transformers and it testing and commissioning of the system and shall
shall not contain triac based equipment. organize a local 5-days seminar for training.
8 The PLMCS shall be a universal system to work with 23 The PLMCS shall monitor power, voltage, current
any brand of HPS, HPMV, MH or FL lamps, mixed in the and power factor of each lighting circuit and additionally it
same system or circuit of the FP. It shall be independent of shall monitor all other inputs from the FP.
the brand of luminaires used.
24 Communication to the PLMCS shall be via fiber optic
9 The PLMCS shall be operated via, and conform to, interface on TCP/IP protocol.
the local 3-phase 4 wire, solidly earthed neutral, 415 V A C.
25 Future optional features may include the following:
electrical system.
i. The PLMCS shall have the optional capability in
10 The kVa rating installed shall be based on full load
future to add communication with each
shown on the Drawings at pf of 0.8 and a spare capacity
individual lighting point by means of power line
of 30% for future connection of additional loads. In
carrier (no additional cables). With this option it
addition each unit shall be de-rated by 30%.
shall monitor the proper functioning of each
11 Each FP shall have an automatic by-pass system. The lamp, ballast, ignitor and capacitor.
by-pass shall be activated automatically in case of any ii. The PLMCS shall have the capability in future to
malfunction of the PLMCS. switch on and off each individual lighting point
12 The local agent for the PLMCS shall have factory or advertising panel by means of power line
trained and certified personnel to perform commissioning carrier (no additional cables).
and all servicing tasks. iii. Communication to the PLMCS shall be possible
13 The PLMCS shall be a field proven system with at via telephone modem, GSM modem, GPRS
least 1000 similar products installed worldwide. The modem, radio modem, RS232 interface or
chosen supplier shall have similar systems installed in at RS485 interface.
least 5 major cities in the Middle East.
15.14.3 Detailed Technical Specification
14 The PLMCS shall use the latest technology, and
comply with international standards such as CE-mark, CEI 1 Power controller enclosure shall have the following
17-13/1, EN 60439-1 and UL916. PLMCS shall be CE features:
marked and conform to such standards. Under no i. Housing fabricated of fiber-glass reinforced
circumstance shall the system induce harmonic currents polyester or equally approved material
to the supply grid. ii. Protection level: IP54 in accordance with IEC
15 The PLMCS enclosure shall be for outdoor 60529 Standard
installation, IP 54 minimum to IEC 60529, for both the iii. Color: RAL 7032 - 7035
power and electronic parts. iv. Base frame made of hot dipped galvanized steel
16 All system components shall be suitable for v. Safety lock.
operation within a temperature range from -10deg C to 2 Main technical features of power controller shall
+60deg C include:
17 Materials shall be certified to ISO 9002 quality i. Supporting frame made of galvanized steel
standard. ii. Voltage control circuits as provided by
18 Load must be started at each switching on under manufacturer.
nominal conditions (230/240V RMS +-1% each phase) even iii. Serial port RS232 or RS485 for communication
if the input voltage is at 175V for a programmable time, with PC and GSM, and up-to-date software of all
(this is very important to conserve the lamp life and units.
conform to the lamp manufacturer’s warranty).

♦ 15- 32♦
copy 249
iv. Microprocessor unit (PLC) for control of work xiii. Lithium battery for buffering of RAM memory
cycles, made of high-grade components, and of the time clock, with 2 (two) year
suitable to operate within the temperature autonomy under disconnected mains
range -10°C to +70°C - Printed circuits with conditions; control of charging status, with
galvanic insulation of the tracks. analogue measurement of battery voltage;
v. Regulation and stabilization of voltage on load push-button for disconnection during storage
side through static system without wave period; hot replacement.
dimming (wave-form shall remain perfectly 5 Features for future functions (upgradeable) shall
sinusoidal) for each phase independently. include:
vi. Four pole main breaker, thermal and magnetic
i. Alarms programming menu for values above or
protection, with rated current to suit the size of
below the preset thresholds of input voltage,
controller with a short circuit capacity 50 kA.
output voltage, total current, power and PF.
vii. Indicator lights: mains voltage phase colors.
ii. Display of the following information:
3 Connections:
a. Input voltage of each phase
i. Feeder terminals shall be 5 x 35mm2
b. Output voltage of each phase
ii. Each FP shall have at least 4 outgoing circuits,
each terminated with 5 terminals 16mm2. c. Active power of each phase
Configuration, quantity and circuit current rating d. Reactive power of each phase
of each circuit shall be as indicated on the e. Power factor of each phase
Drawings.
f. Frequency of each phase
4 Functional features of power controller shall include:
g. Analogue input value (m A)
i. Static by-pass, no break execution, suitable to
h. Analogue output value (m A)
operate any combination of mixed types of
lamps iii. Recording of the following statistical data:
ii. Power saving of up to 40% depending on the a. Hours of operation on line
type of lamps connected. b. Hours of operation in the by-pass mode
iii. Efficiency 98.5% (at full load, PF=1)
c. Number of switching cycles of control
iv. Stabilization of output voltage with accuracy +/-
relays
1% with input voltage 200 to 245 V independent
for each phase. d. Stability of mains (steps/minute)
v. Stabilization of changes in mains voltage in e. Total energy consumption
extra-rapid time.
f. Number of black-outs
vi. Setting of the following parameters, separate
g. Number of resets
for each phase: starting voltage, full light
voltage, reduced light voltage, warm-up time, h. Possibility to download the historical data
ramp-up speed, ramp-down speed. recorded in the controller, via portable PC
vii. Selection of dimming percentage and of the or modem or from the control center.
corresponding time zones, up to 10 time zones. iv. Provision for connection to a remote control
viii. Availability of one preset yearly program, with network designed for diagnostic and control of
starting and operating cycles configurable in the whole unit (remote servicing).
accordance with seasonal factors and location.
ix. Availability of one customizable yearly cycle 15.14.4 Remote Control Management (RCM)
with different settings for each season and the Software
possibility to set up to ten time zones over night
time. Software shall be designed to operate a remote control
x. Availability of five customized periodical cycles station for supervision and management of lighting
with possibility to set the requested time, the systems, with the features and functions listed in items 1
days of the week and up to ten time zones over to 8, below:
night time. 1 General features:
xi. Availability of one cycle controlled by analogue i. Standard language is English; further local
input (4 - 20 ma) suitable for dimming from languages with text import during program start
signal sent from a luminance sensor or any up later on, should be possible
other equivalent apparatus. ii. Installation on single PC (stand-alone) or in the
xii. Astronomical time clock with precision of ± 4 Concerned Authority’s server configuration in
minutes/year in a temperature range of -10 to future.
+70°C, or, alternatively, high accuracy clock, iii. Facility to share and to display data via internet
with precision ±1 minutes/year in a temperature iv. SQL database
range -10 to +70°C.

♦ 15- 33♦
copy 249
v. Safety system for control of all accesses, ix. Remote reading of operative parameters
configurable for the function and the Concerned (technical data, working cycles, clocks, alarms,
Authority’s control. l/0 state, MEM modules settings), active alarms,
vi. Customization of program options records of alarms (in partial or total mode),
vii. Facility to import and export data, already record of measures, monthly data, etc.
present in external database, without the need x. Facility to download the last "n" records
of manual fill-in xi. Facility to program in advance the operation to
viii. Manual backup utility be performed during the connection with the
ix. Window preference for simple access to the controller in field
most-used functions. xii. Remote writing and modification of the
x. Creation of log files of the performed operative parameters
operations. xiii. Real time remote reception of alarms from the
xi. Wide flexibility in customization plants
2 Data list management: xiv. Alarms notification to the technician via SMS or
e-mail, based on customizable rules
i. Loading of data list of plant and components
xv. Utility to plan the automatic calls of the
(FP's, cables, luminaires, lamps, ballasts,
controllers, including the possibility to choose
ignitors, capacitors)
the operation to be performed, and the
ii. Management of data list by means of a tree
management of errors in the communication
structure
xvi. Remote plant override to switch the lighting
iii. Fill-in of plant and component data list from the
system on and off
tree structure or directly from the maps
xvii. Remote control of input/output relay
iv. Utility functions such as copy, cut, paste, paste
special 4 Plant management by active maps:
v. Management capacity up to 30 towns, 300 FPs i. Map management on three levels in case of a
and more than 30,000 objects with possibility to wide area or on two levels in case of
extend without limit. medium/small area
vi. Identification (object can belong to more than Up to 324 maps
one group) and without limitation in numbers
Maps in whatever graphic format (JPG, BMP,
vii. Management of groups by means a tree
WMF, TIF, GIF)
structure; data searching and selection via
appropriate filters (with logic addresses) Simple insertion of object in the map
viii. Data replicate tool to revise and modify the Facility to choose the objects to be displayed in
data list of elements the map, only one object type at a time
ix. Facility to personalize the screen and ii. Active objects which light-on because of alarms
background iii. Color light indication in the quadrants at levels
x. Control panel for easy access to the different one and two, indicating the presence of one or
program functions more objects in alarm condition inside the area
3 Communication: iv. Facility to add, delete, remove, new objects
i. Communication via serial cable or via modem directly from the map
(standard telephone PSTN, GSM, GPRS, radio v. Utility functions such as copy, cut, paste, paste
modem, TCP/IP protocol on Ethernet) special
ii. Management of 5 modems at the same time or vi. Full interactivity of the objects to open data list,
5 TCP/ IP channels. to display a mimic panel or alarms or records of
iii. Facility to configure the interface modems for maintenance activities or set-up , directly from
only incoming calls, only outgoing calls, only the map
manual calls, only automatic calls vii. Zoom function in the detailed map
iv. Full automatic management of the connections viii. Tools to navigate into the maps
(automatic disconnection only when required) ix. (As an alternative to normal maps) chart
v. Emulation in remote mode to enable all the module, to interface and interact with drawing
operations as if in front of the controller Autocad and/or shop files, with facility to import
vi. Manual connection to verify the controller state, automatically elements of chart system used
to perform a data-download, to synchronize the 5 Mimic panel application:
clock, to program the operative parameters i. Remote diagnostic identification by displaying
vii. Monitoring and recording on log files of the the operational state of the controller and
communications procedure and errors relevant components on an interactive on-line
viii. Diagnostics of communication based on the diagram
errors and faulty answers from the field, with
activation of alarm to signal the most critical
connections

♦ 15- 34♦
copy 249
ii. Display of the state of equipment in real time xiii. Print out of log messages
mode (when on-line) or by records (from 8 Maintenance module
database)
i. Automatic elaboration of programmed
iii. Identification by color code of alarms and
maintenance plan, according to user's needs
operational state of: breakers, limit switches,
and settable parameters
contactors, relays etc…
ii. Facility to customize maintenance operations
iv. Display of all measures done by the local
iii. Print out of plan of activities
control module (voltage, current, power, power
iv. Recording of failures and unplanned activities
factor etc.)
v. Recording of real activity done
v. Manual override commands, in ON-LINE mode,
vi. Management of historical data
controlled directly from the mimic panel
6 Events and data analysis: 15.14.5 RCM Hardware
i. Events shall be able to be programmed in four
1 Personal computers shall be latest models and have
priority levels:
the following features:
Table, to display the events with predefined
i. Processor: Intel 2.0Ghz or over
customizable filters for each PC
ii. RAM memory: 1 GB
Bar graph for the analysis of the types of iii. Multi-serial with 5 ports COM (or in alternative
events and the objects involved USB hub with converters) (if not used by TCP/IP)
Events in cases of: override controls, iv. Parallel port
communication problems, automatic call v. Printer with continuous paper form
results, etc. vi. Double HD with indicative capacity 40GB each
Management of an appropriate printer for one (IDE or SCSI; same type)
recording alarms vii. If the HD is SCSI type, the controller must be
ii. Each alarm/event shall able to be configured to SCSI U/160.
send a message via SMS or e-mail viii. Color video card that grants a definition of
iii. Display of data of the plant (measures, monthly 1024x765 at least.
measures, alarms) through tables, graphs, ix. Minimum video memory card 32 Mb
active mimic panel of the selected unit x. Compatible back-up system
iv. Table to display data with predefined 2 Operative system shall be as stated below or as
customizable filters for each PC selected by the Concerned Authority:
v. Creation of customizable graphs for the analysis i. MS Windows 2000® Professional or Windows
of the most interested values XP® Professional, or latest system (up-to-date)
vi. Availability of different types of graphs (line, complete.
steps, cake, etc.)
3 Modems shall be:
7 Working parameters of controllers
i. Modem standard for wired telephone line
i. Data replicate tool, to revise and modify the (PSTN)
parameters of controllers ii. Modem GSM for SMS alarms
ii. Facility to transfer and read each parameter iii. Modem GSM/GPRS for SMS alarm
iii. Automatic control of errors during the
parameter transfer 15.14.6 Method of Measurement
iv. Facility to program in automatic mode each
controller or groups of them 1 The public lighting management and control system
v. Tool for automatic calculation of switch-on shall be measured by the number of completed feeder
hours of the plant, depending on astronomical pillars controlled by the PLMCS, installed and
clock parameters (for season and for year) commissioned. The rate per feeder pillar shall include for
vi. Print out of data list and the groups of objects the remote control and management software and
vii. Print out of all related tables (streets, supports, hardware, and any transmission/ communication media
lamps) between the feeder pillar and the control center. Rates are
viii. Table and graph print out, with filters, of events deemed to include for all work, including design supply,
ix. Table and graph print out, with filters, of transportation and installation, testing and commissioning
measures and instruction of the Concerned Authority’s personnel in
x. Table and graph print out, with filters, of operation of the system.
monthly data
xi. Report of the energy (theoretical, actual and 15.14.7 Basis of Payment
saving)
1 The amount of completed and accepted work
xii. Detailed print out of the working parameters of
measured as provided for above, will be paid for at the
the controllers
unit rate for PLMCS powered and controlled feeder pillar

♦ 15- 35♦
copy 249
stated in the Bill of Quantities, which rate shall be full specified, all earthing materials and components shall be
compensation for supplying materials, installation, testing of copper.
and putting into operation, for labor, equipment, tools,
supplies, earthing, training, and other items of work 15.15.3 Construction Requirements
necessary for the completion of the system(s) to the
1 Exposed non-current carrying metallic parts of each
satisfaction of the Concerned Authority, as specified.
electrical installation and the neutral point of the
distribution system shall be earthed. The earthing of the
15.14.8 Items in the Bill of Quantities
distribution system shall be made at the neutral point of
i PLMCS installation at each feeder pillar the transformers.
and all related communication and central 2 A separate 50mm x 6mm high conductivity earth bar
control facilities. (nr) shall be mounted on porcelain connectors in each
substation and feeder pillar housing. The bar shall be pre-
drilled with a minimum distance of 75mm between holes
15.15 Earthing
and connected as follows:
i. Insulated cable:
15.15.1 Description
a. Transformer neutral
1 This Sub-section describes requirements for b. Earth mat
supplying, installing, and testing earthing connections in ii. Bare cable:
electrical installations, including transformer neutral a. Switchgear frame earth
earthing, main earthing terminals or bars, exposed b. Transformer frame earth
conductive parts of electrical equipment, extraneous
3 The insulated cable shall be green–yellow striped
conductive parts, and standby generator neutral earthing
50mm² single core PVC fixed at regular intervals with non-
where installed.
magnetic insulating cleats and terminated with suitably
2 The Contractor shall carry out work in accordance sized lugs. The bare conductors shall be 35mm x 6mm or
with the following: 50mm² high conductivity copper tape or conductor fixed at
BS 7671 chapter 54 (seventeenth edition) regular intervals with purpose made brass saddles.
or IEC 60364-5-54 (2004) 4 Each sub-station and feeder pillar earth mat shall
3 Prior to ordering materials, the Contractor shall have two 16mm diameter copper covered steel earth rods
submit data for the Engineer’s approval including, but not of 2.5m length, connected together and to the earth bar.
limited to, manufacturer’s catalogues for earth rods, Each rod shall be housed inside a concrete inspection box
connecting clamps, earthing conductors, protective recessed into the ground and fitted with a removable
conductors, bonding conductors, connectors and other metal lid with the inscription ’Earthing Rod’. An earth
accessories, exothermic welding kits and tools etc,, and resistance test shall be carried out on the earth bar at each
samples of conductors as requested. sub-station and feeder pillar. Three readings shall be
obtained on each of the two earth paths connected
4 The Contractor shall submit drawings for approval by
individually and in parallel. The results shall be tabulated
the Engineer, including, but not limited to the following:
and submitted to the Engineer for approval.
i. exact location of earth pits, rods and details of
5 The earth bar shall be labeled and the connections
installation and connections
identified. The insulated earthing cables for high mast and
ii. exact routing of buried earthing conductors with
lighting column circuits shall be earthed at the low voltage
indication of cross-section, depth of laying and
supply position at the earth bar.
covering
iii. cross sectional area of all earthing ,protective 6 At the masts and each last column on a circuit,
and bonding conductors earthing shall be by connecting the earthing bolt to a
iv. layout and details of earthing provisions at 16mm diameter copper covered steel rod of 2.5 m length
substations, switchgear, distribution minimum, driven into the ground adjacent to the mast or
panelboards etc., indicating fittings used, column to achieve the required resistance (1 ohm
insulation, plates and markings, passage and maximum). Bonding is to be by means of a 16mm2
routing of earthing conductors, conduit, sleeves, stranded bare copper conductor. Each mast and column
grooves, niches etc. giving sizes and shall be bonded to the earthing cable. Where the supply
dimensions of component parts. cable is looped into the column the earthing cable shall
not be cut. The final column in each distribution circuit
15.15.2 Materials shall be bonded to a separate earth rod.
7 The earthing system at sign lighting installations
1 Fittings, plant, equipment, ducts and cables used for
shall be as specified for masts and columns.
each earthing installation shall be as specified in other
pertinent Clauses of this Section 15. Unless otherwise 8 Connections between rods and earthing tape or
cables shall be made by the ’Cadweld’ process to produce

♦ 15- 36♦
copy 249
a fused joint. Bolted connections may be used for 15.16 Labeling, Testing and
removable items of equipment only. Commissioning
9 Protective conductors shall not be formed by conduit,
trunking, ducting or the like. Where armored cable is 15.16.1 Description
specified and armor is steel, it may be used as a protective
conductor, if approved and if not otherwise shown on the 1 This Sub-section describes requirements for labeling,
Drawings. In general a protective conductor shall be run testing and commissioning of electrical and
together with the lighting power circuit unless otherwise communication systems installations and equipment. The
waived by the concerned authority. work is supplementary to the work specified in the
respective parts of this Section 15.
10 Connection of every earthing conductor to earthing
electrode and every bonding conductor to extraneous
15.16.2 Materials
conducting parts shall be labeled in accordance with the
applicable regulations, as follows: 1 Labels shall be manufactured from sheet aluminum,
‘SAFETY ELECTRICAL CONNECTION - DO NOT REMOVE’. plastics or other approved non-corrosive inert material.
Text shall be die-stamped, engraved, painted or printed
15.15.4 Earth Resistance Test with a legible life expectancy of 20 years. Finished labels
shall be permanently bonded, screwed, riveted, bolted or
1 Earth resistance tests shall be made by the wire-locked to the part as appropriate.
Contractor on the earthing system, separating and
reconnecting each earth connection. 15.16.3 Construction Requirements
2 If it is indicated that soil treatment or other corrective
measures are required to lower the ground resistance 15.16.3.1 Labeling
values, the Contractor shall submit proposals for
1 The Contractor shall submit for approval a
corrective measures to the Engineer for approval prior to
comprehensive labeling and marking plan before work is
working on such measures.
started. This shall include all factory labeled items as well
3 The electrical resistance of the earthing circuit (ECC) as field labeling.
together with the resistance of the earthing leads,
2 Plant and equipment not labeled to the Engineer's
measured from the connection with earth electrode to any
approval by the manufacturer shall be labeled by the
other position in the complete installation, shall not
Contractor on the Site.
exceed one ohm.
3 Equipment labels shall be simply and clearly written
5 Earth resistance test shall be performed as the
in black on white or white on black in English and Arabic,
Engineer’s requirements. The earth resistance of each
in accordance with the schematic diagram on the
electrode shall be measured by means of resistance
installation drawings. Warning labels shall be red on
bridge instrument and results recorded.
white or white on red lettering a minimum 15mm in height

15.15.5 Method of Measurement 4 Each item of plant, including individual parts of a


package sub-station or control panel, shall be labeled on
1 Earthing shall be measured by the number of the exterior of the respective casings.
completed sets of earthing rods supplied, installed, and
5 Lighting columns and masts shall be fitted with
tested. The interconnecting work within the circuit shall
identification labels of black lettering 50mm high on a
not be measured separately.
white background. The labels shall be attached to the
columns by means of galvanized nuts and bolts positioned,
15.15.6 Basis of Payment just above the access openings and facing approaching
1 The amount of completed and accepted work traffic.
measured as provided for above will be paid for at the unit 6 Control switchgear labels shall indicate the voltage,
rate stated in the Bill of-Quantities which rate shall be full current rating and phase color, together with the
compensation for supplying, installing, testing, manufacturer's distinguishing mark. A separate label shall
transportation, putting into operation and for materials, state the service controlled by the switch.
labor, equipment, tools, supplies and other items
7 Switchgear, distribution boards and apparatus shall
necessary for the proper completion of the work as
be included in an overall identification scheme and labeled
specified.
accordingly.
8 ’Danger High Voltage’ labels in English and Arabic
15.15.7 Items in the Bill of Quantities
with red lettering and electrical flash shall be fixed to the
i. Twin rod earthing installation (location) (nr) doors of each sub-station and switch station and be clearly
ii. Single rod earthing installation (location) (nr) visible from the fence access gates.
9 The interior of each item of electrical equipment shall
indicate the phases by means of colored plastic sleeving
or discs.

♦ 15- 37♦
copy 249
10 Circuit lists shall be mounted on the inside of appropriate and have current calibration certificates issued
distribution board lids or doors. The list shall comprise a by an approved laboratory.
printed sheet heat-sealed into a semi-rigid clear plastic 4 Advance notice shall be given to the Engineer of the
cover. testing program proposed together with a list of the
11 Power cable cores shall be identified at their equipment to be used.
terminations by colored sheaths of the heat or chemically 5 The Contractor shall re-test any item that fails. No
shrinkable type to indicate the respective phases and repeat test shall be carried out until the cause of failure
neutral. Where the core insulation is suitably colored has been identified and removed.
during manufacture the colored sleeve may be omitted. 6 After satisfactory completion of the tests the
12 Local switches, switch-fuses, isolators, lighting Contractor shall obtain authorization from the Engineer
fittings, and similar accessories shall carry engraved and the Concerned Authority to connect the power supply
identification plates to indicate the circuit number and to the installation.
phase to which the accessory is connected.
13 Medium voltage cables shall be clearly labeled 15.16.4 Method of Measurement and Basis of
'DANGER HIGH VOLTAGE' in English and Arabic every 2m Payment
of exposed length. 1 No separate measurement shall be made and no
14 Prior to final testing the Contractor shall obtain the separate payment made for work of labeling, testing and
Engineer's approval that the labeling is intact over the Site commissioning of the electrical and telecommunication
and that circuit markers have been fitted wherever cables installations. The cost of this work is deemed to be
emerge from the duct system or enter a building. included in the unit rates for the respective items stated in
the Bill of Quantities.
15.16.3.2 Testing and Commissioning
15.17 Civil Works for Electrical and
1 Testing of the installations shall be carried out in
Telecommunication Installations
accordance with the relevant regulations and standards
after completion of the work. The tests shall be carried
out to the satisfaction of the Engineer and the concerned
15.17.1 Description
authority. Manufacturer’s test certificates shall be included 1 This Sub-section describes requirements for civil
in the documented results submitted for approval. work, including excavation, concrete, building work, and
2 Tests shall comprise the following: duct work, associated with the electrical and telecoms
- Insulation resistance on MV equipment installations.
including busbars, bushings, through
insulators and feeder terminations, using a 15.17.2 Materials
5000 V megger, between phases, and between 1 Backfill material for excavations shall be as specified
phase and earth, with control and protection in Section 2, Sub-section 2.7 of these Specifications.
circuits, lamps and similar components
2 Concrete for column and pole bases, equipment
disconnected.
foundations and other structures shall be Class 30 as
- Insulation resistance on every cable and specified in Sub-section 5.1. Reinforcement for concrete
insulator, power, control and relay circuit of the shall be mild steel in accordance with Section 5, Sub-
LV systems, using appropriate megger range; section 5.2 of these Specifications.
500 V for installations rated below 500 V and
3 Anchor bolts shall be as specified and shown on the
1000 V for installations rated up to 1000 V, in
Drawings and as instructed by the Engineer.
accordance with the IEE Wiring Regulations
(BS 7671) Subsection 612. Minimum standard shall be ASTM F1554, Grade 55,
minimum thread length of 10 inches, galvanized for a
- HV test, using power frequency HV test set, to
minimum of 12 inches on the threaded end to the
80% of IEC withstand voltage ( 2.5 rated
requirements of ASTM A153. Each is to be supplied with
voltage) for one-minute, between phases and
too hexagonal nuts and two flat washers, all to be hooked
phase to earth for each MV switchgear and
end on the embedded side.
transformer, disconnected.
4 Buildings to house switchgear for the medium
- MV cable tests as Sub-section 15.7, Paragraph
voltage switching station shall be as shown on the
15.7.3.2.
Drawings. They shall have adequate space for the
- Any other tests required by the concerned concerned Authority’s equipment. If buildings are not
authority standards, unless waived in writing defined on the Drawings, they shall be constructed of
by the Concerned Authority, conventional materials with concrete foundations and
3 The test and measuring apparatus provided by the floor, blockwork walls, rendered internally and externally,
Contractor to carry out the testing shall be sealed as and suitable waterproof roof. Doors shall be painted steel,

♦ 15- 38♦
copy 249
lockable, and complete with ventilation louvers and sand 3 When cables cross road, paved area or other services
traps. Foundations and floors shall incorporate trenches or are buried in slab, they shall be laid in protective ducts
and ducts for cables and bases for equipment. of adequate size. The duct/ conduit ends after installation
5 Cable ducts shall be uPVC Schedule 40, UL listed, or of cable shall be plugged to make them watertight by
equivalent standard as specified or shown on the means of bituminized hessian or equivalent material.
Drawings. Minimum requirements shall be non-sparking 4 Cables shall be laid without sharp bends or kinks,
type, suitable for direct burial in ground, minimum tensile and if within 500mm of drainage ware, shall be contained
strength 500 kg/cm2, impact strength 5 kg/cm2, supplied in in a duct.
standard 6 m lengths. 5 Slack shall be left in cables for which purpose the cut
6 Unless otherwise indicated on the Drawings, lengths of cables shall allow about 3% more in the
columns 8m through 16m shall incorporate a cast measured length between terminations (Engineer will
aluminium breakaway transformer base and electrical verify the lengths of cables). At junction boxes, ample
breakaway quick disconnect. The base shall be designed slack shall be left to prevent straining of cable joints due to
and constructed so that when used with the size and settlement of cable trench.
weight of the column, the assembly shall meet the 6 Cables shall be pulled in uPVC ducts or conduits with
requirements of AASHTO Standard Specifications for care, preferably without the use of any lubricant. Where
Structural Supports for Highway Signs, Luminaires and necessary, and after approval of the Engineer, the cable
Traffic Signals. manufacturer’s recommended lubricant shall be used. Use
7 Transformer base and column combination shall be of any kind of oil or soap will not be permitted.
designed, fabricated and tested to withstand the wind 7 Sharp bends or tees shall not be allowed. At road
loads described in Clause 15.1.9, and Paragraph 15.8.2.1. crossings the duct shall have a bedding and surround of
8 The transformer base shall meet the following concrete Class 30 and shall be laid at 800 mm below road
standards: surface or as shown on drawings and directed by the
ASTM B108 alloy 5G70-T6 or alloy 356-T6 for the base Engineer.
ASTM A-325 for the bolts, ASTM A-563 Grade A for the 8 Prior to backfilling at duct location, the following
nuts, both galvanized to ASTM A-153. shall be completed:
i. Placement of the approved type of draw cord in
15.17.3 Construction Requirements each duct section
ii. Capping ducts at both ends
15.17.3.1 Bases for Poles and Equipment
iii. Recording the coordinates of both ends
1. Excavations for foundations shall be carried out in 9 Where ducts rest over rocky soil, a layer of 200 mm
accordance with Sub-section 2.7. Foundations located on dune sand shall be spread, compacted and rammed in
old backfill shall have the ground bearing material re- order to create proper bedding for the duct. In water-
compacted to the Engineer’s requirements. The sides of logged or unstable soil, a concrete base 200mm thick shall
excavations for foundations that will be subject to uplift or be laid, followed by 100mm layer of dune sand on top of
lateral forces shall be compacted and approved before any the concrete as a base for the duct.
concrete is poured.
10 Spare ducts shall be provided wherever ducts are
2. The position of anchor bolts in the concrete bases used for MV or LV cable routing. 30% spare ducts or at
shall be set by means of templates. The top of foundation least one duct per run, whichever is greater, shall be
bases shall be horizontal to a tolerance ±0.25mm across provided.
the width of an individual base.
11 Cables, whether installed in bare ground or in uPVC
Where shown on the Drawings duct stubs 300mm long ducts or conduits shall not be bent to a radius less than
and to the diameter shown shall be provided in the that recommended by the cable manufacturers.
structural concrete. uPVC ducts shall be cast into lighting
i. Install cables as indicated, according to
column, mast and feeder pillar bases to run the incoming
manufacturer's written instructions.
and outgoing power cables.
ii. Use manufacturer-approved pulling compound
15.17.3.2 Cable Trenches and Ducts or lubricant where approved; compound used
must not deteriorate conductor or insulation.
1 The depth of low voltage cable trench excavation Do not exceed manufacturer's recommended
shall provide a minimum cover to the cable of 500mm in maximum pulling tensions and sidewall
open ground and sidewalks. pressure values.
2 Cables shall be ducted where they run under or cross iii. Use pulling means, including fish tape, cable,
below roads and shall not be at less than 800mm deep, rope, and basket-weave wire/cable grips, that
with a concrete cover of 100mm all around. Duct ends will not damage cables or raceways. Do not use
shall extend minimum 600mm beyond road structure or rope hitches for pulling attachment to cable.
embankment where ducts cross the road iv. Install exposed cables, parallel and
perpendicular to surfaces of exposed structural

♦ 15- 39♦
copy 249
members, and follow surface contours where the number and size of duct, including all bends,
possible. couplings and bushings. Concrete encasement shall not
v. Install direct-buried cables on leveled and be measured for direct payment but shall be considered as
tamped 100-mm bed of clean sand at bottom of subsidiary item, the cost of which will be deemed to be
trench. Separate cables crossing other cables included in rates for the duct.
or piping from those items by a minimum of 9 Cable markers, drawpits, handholes and manholes,
100 mm of tamped earth. shall be measured by detail shown on drawings, and
vi. Install permanent markers at ends of cable runs, number completed including all civil work and finishing
changes in direction, and buried splices. work.
vii. Install ‘buried cable’ warning tape 305 mm
above cables. 15.17.5 Basis of Payment
viii. Cable identification/route markers shall be
erected at 25m maximum spacing throughout 1 The quantity of completed and accepted work
the entire length of the cable trench route and at measured as provided for above will be paid for at the unit
each bend or intersection. Refer to MEW rates for the items stated in the Bill of Quantities, which
Standard OES 2 for all details. rates shall be full compensation for supplying all materials,
ix. In manholes, hand-holes, pull boxes, drawpits, formwork, construction, installation, testing and putting
junction boxes, and cable vaults, train cables into service, and for labor, equipment, tools, supplies,
around walls by the longest route from entry to transportation, and other work items necessary for the
exit and support cables at intervals adequate to proper completion of the work as specified.
prevent sag.
x. Seal around cables passing through fire-rated 15.17.6 Items in the Bill of Quantities
elements using approved fire-stopping material.
i Building for medium voltage intake
xi. Identify cables according to Section 15.16-
Labelling, Testing and Commissioning. switching station (reference drawing
and detail) (nr.)
15.17.4 Method of Measurement ii Concrete foundation for package
1 Buildings for the medium voltage switching stations substation (reference drawing
shall be measured by the number of the constructed block and detail) (nr.)
work buildings, including foundations, concrete roof,
iii Building for package
fence, and all necessary related civil works.
medium voltage switching station
2 Bases for package substations shall be measured by
the number of concrete foundations including fence and (reference drawing and detail) (nr.)
other builder’s works, as per the approved related shop iv H type concrete foundation for
drawings. 33kV/low voltage pole mounted
3 Buildings for package medium voltage switching transformer station (reference
stations shall be measured by the number of the
drawing and detail) (nr.)
constructed block work buildings, including foundations,
concrete roof, fence, and all necessary related civil works. v H type concrete foundation for

4 Bases for the 33kV/11kV pole mounted transformer 11kV/low voltage pole mounted
station shall be measured by the concrete base H type transformer station (reference
construction for 11m poles, to the detail of Concerned drawing and detail) (nr.)
Authority, including all related civil works.
vi Concrete base for feeder pillar
5 Bases for the feeder pillars shall be measured by the
(ref.dwg) (nr.)
number of concrete bases, including incoming and
outgoing ducts for cables and other builders work. vii Trench for low voltage cable for:

6 Trenches for directly buried cables shall be measured - one cable (lin.m)
by linear meter completed, including concrete tile, - two cables (lin.m)
warning tape and excavation and backfilling to levels and - three cables (lin.m)
dimensions as specified in the Drawings.
viii Trench for medium voltage cable for:
7 Bases for lighting columns/high masts shall be
- one cable (lin.m)
measured separately each by the number of concrete base
and other related civil works, including all related civil - two cables (lin.m)
work as the column detail approved. ix Lighting column concrete foundation
8 uPVC ducts shall be measured in linear meters of (Type, ref. dwg) (nr.)
multiple duct run installed in trench or in concrete x High mast concrete foundation
encasement, completed and accepted with reference to
(Type, ref. dwg) (nr.)

♦ 15- 40♦
copy 249
xi uPVC duct (size and nr) (lin.m)
xii uPVC duct, in concrete encasement
(size and nr) (lin.m)
xiii Cable marker as per MEW details (nr.)
xiv Manhole (type, dimension, ref. dwg) (nr.)
xv Handhole or drawpit (type,
dimension, ref. dwg) (nr.)
xvi Cast aluminium breakaway transformer
base for column (height) (details,
ref. dwg) (nr.)

♦ 15- 41♦
copy 249
copy 249
Ref. Title Page No. Ref. Title Page No.
16.1 Landscape 16-1 16.1.3.15 Requirements for Satisfactory Grass 16-8
16.1.3.16 Planting Ground Cover and Plants 16-8
16.1.1 General 16-1
16.1.3.17 Mulching 16-8
16.1.1.1 Summary 16-1
16.1.3.18 Installation of Edgings 16-8
16.1.1.2 Related Documents 16-1
16.1.3.19 Installation of Miscellaneous Materials 16-8
16.1.1.3 Definitions 16-1
16.1.3.20 Cleanup and Protection 16-8
16.1.1.4 Submittals 16-1
16.1.3.21 Disposal of Surplus and Waste
16.1.2 Materials 16-2
Materials 16-8
16.1.2.1 Trees and Shrubs 16-2
16.1.4 Warranty and Maintenance 16-8
16.1.2.2 Ground Cover 16-2
16.1.4.1 Warranty 16-8
16.1.2.3 Palms 16-2
16.1.4.2 Maintenance 16-9
16.1.2.4 Grass Seed 16-2
16.1.5 Method of Measurement 16-9
16.1.2.5 Grass Sod (Turf) 16-2
16.1.5.1 Excavation, Soiling, Cultivating
16.1.2.6 Grass Plugs 16-2
and Grading 16-9
16.1.2.7 Grass Sprigs 16-2
16.1.5.2 Grass Planting and Seeding 16-10
16.1.2.8 Topsoil 16-2
16.1.5.3 Tree, Shrub and Ground Cover
16.1.2.9 Soil Amendments 16-3
Planting 16-10
16.1.2.10 Fertilizer 16-3
16.1.6 Basis of Payment 16-10
16.1.2.11 Mulches 16-3
16.1.7 Items in Bill of Quantities 16-10
16.1.2.12 Stakes and Guys 16-3
16.1.2.13 Landscape Edgings 16-4 16.2 Irrigation System 16-10
16.1.2.14 Erosion-Control Materials 16-4
16.2.1 Description / General 16-10
16.1.2.15 Miscellaneous Materials 16-4
16.2.1.1 Scope 16-10
16.1.3 Construction Requirements 16-4
16.2.1.2 Schedules of Proposed Equipment 16-11
16.1.3.1 General 16-4
16.2.1.3 Approval of Equipment 16-11
16.1.3.2 Preparation 16-4
16.2.1.4 Submittals 16-11
16.1.3.3 Planting Soil Preparation 16-5
16.2.1.5 Delivery, Storage and Handling 16-12
16.1.3.4 Ground Cover and Plant Bed
16.2.1.6 Installation and Checking 16-12
Preparation 16-5
16.2.1.7 Spares 16-12
16.1.3.5 Preparation for Grassed Areas 16-5
16.2.1.8 Equipment Labels and Charts 16-12
16.1.3.6 Excavation for Trees and Shrubs 16-5
16.2.1.9 Operation and Instruction Manuals 16-12
16.1.3.7 Planting, Palms, Trees and Shrubs 16-6
16.2.2 Material 16-13
16.1.3.8 Tree and Shrub Pruning 16-7
16.2.2.1 Pipes, Fittings and Accessories 16-13
16.1.3.9 Tree and Shrub Guying and Staking 16-7
16.2.2.2 Valves and Penstocks 16-15
16.1.3.10 Grass Seeding 16-7
16.2.2.3 Irrigation Equipment 16-17
16.1.3.11 Hydro-Seeding 16-7
16.2.2.4 Valve Operators and Accessories 16-19
16.1.3.12 Sodding 16-7
16.2.2.5 Jointing Material 16-20
16.1.3.13 Plugging 16-7
16.2.2.6 Concrete and Metal Work 16-21
16.1.3.14 Sprigging 16-8
16.2.2.7 Pumping Plant 16-21

♦ 16-1 ♦
copy 249
Ref. Title Page No.
16.2.3 Construction Requirements 16-21
16.2.3.1 Excavation, Bedding and Backfilling 16-21
16.2.3.2 Pipe Laying - Generally 16-21
16.2.3.3 Jointing 16-22
16.2.3.4 Line and Gradient 16-22
16.2.3.5 Floatation 16-22
16.2.3.6 Pipe Built Into Structures 16-22
16.2.3.7 Field Testing: Generally 16-22
16.2.3.8 Hydrostatic Testing of Pressure
Pipelines 16-23
16.2.3.9 Visual Inspection Test 16-23
16.2.3.10 Deflection Tests for GRP Pipes 16-23
16.2.3.11 Flushing 16-23
16.2.3.12 Field Protection and Coating 16-23
16.2.3.13 Irrigation Control 16-24
16.2.3.14 Contract Requirements 16-24
16.2.3.15 Documentation 16-24
16.2.3.16 Maintenance Program 16-24
16.2.4 Method of Measurement 16-24
16.2.5 Basis of Payment 16-25
16.2.6 Items in the Bill of Quantities 16-25

♦ 16-2 ♦
copy 249
16.1 Landscape 2 Sub grade: Surface of subsoil after completing
excavation, or top surface of a fill or backfill immediately
beneath planting soil.
16.1.1 General
3 Manufactured Soil: Soil produced off-site by
16.1.1.1 Summary homogeneously blending mineral soils or sand with
stabilized organic soil amendments to produce topsoil or
1 This Section describes requirements for soft
planting soil.
landscaping and irrigation, including the following:
4 Planting Soil: Native or imported topsoil,
i. Trees and shrubs.
manufactured topsoil, or surface soil modified to become
ii. Ground cover. topsoil; mixed with soil amendments.
iii. Palms.
16.1.1.4 Submittals
iv. Seed.
v. Turf-grass sod. 1 General: Submit the certificates, samples and other
information stated in this paragraph to the Engineer
vi. Plugs.
before ordering materials or starting the relevant work.
vii. Sprigs.
2 Certification of product compliance to specified
viii. Topsoil. requirements signed by manufacturer.
ix. Soil amendments. i. Manufacturer's certified analysis for standard
x. Fertilizers. products.
xi. Mulches. ii. Analysis for other materials by a recognized
xii. Stakes and guys. laboratory made according to approved
international standards.
xiii. Landscape edgings.
iii. Label data substantiating that plants, trees,
xiv. Erosion-control materials.
shrubs, and planting materials comply with
xv. Miscellaneous materials. specified requirements.
xvi. Irrigation iv. Certification of grass seed from seed vendor
2 Requirements for hard landscaping, paving and for each grass-seed or mixture stating the
curbs of sidewalks and areas adjacent to soft landscaping botanical and common name and percentage
are described in Section 12. by weight of each species and variety and
3 Landscape work shall be carried out by an percentage of purity, germination and weed
experienced landscape contractor whose qualifications seed. Include the year of production and date
and resources are approved by the Engineer, including his of packaging.
operatives and supervisors and equipment. v. Certification of each seed mixture for turf grass
4 Where tests and analysis on soil and products are sod, plugs and sprigs, identifying source,
required by this Specification, they shall be carried out by including name and telephone number of
an agency approved by the Engineer. supplier.
vi. Certification of all soil amendments and
16.1.1.2 Related Documents fertilizers signed by product manufacturer.
1 Drawings and other Specification Sections, apply to 3 Samples of each of the following:
this Section. i. 2 kg of mineral mulch for each color and
2 Related Sections: The following Sections contain texture of stone t, in labeled plastic bags.
requirements that relate to this Section: ii. Edging materials and accessories to verify
i. Section 1 for protection of existing trees and color selected.
planting, topsoil stripping and stockpiling, and 4 Qualification data for firms and persons employed in
site clearing. the work to demonstrate their capabilities and experience.
ii. Section 2 for excavation, filling, rough grading Include lists of completed projects with project names and
and subsurface aggregate drainage and addresses, names and address of architects/engineers and
drainage backfill. owners, and other information specified.
iii. Section 8 for subsurface drainage. 5 Material test reports from qualified independent
iv. Section 12 sidewalks, paving areas and curbs”. testing agency indicating and interpreting test results
relative to compliance of the following materials with
16.1.1.3 Definitions requirements indicated:

1 Finish Grade: Elevation of finished surface of planting i. Analysis of existing surface soil.
soil. ii. Analysis of imported topsoil.

♦ 16-1 ♦
copy 249
6 Planting schedule indicating planned dates and of palms is measured from nursery ground line to base of
locations for each type of planting. first frond.
7 Maintenance instructions recommending procedures 2 Heights of palms are to be as indicated in the Plant of
to be established by the Employer for maintenance of Material Schedules shown on Drawings and shall have
landscaping during an entire year. Submit before corresponding root-ball diameters as follows:
expiration of required maintenance periods. Palm Height Root-ball Diameter
1.5 m 0.75 - 0.90 m
16.1.2 Materials
2.0 m 0.90 - 1.10 m
16.1.2.1 Trees and Shrubs 2.5 m 1.10 - 1.30 m

1 Provide nursery-grown trees and shrubs conforming 3.0 m 1.30 - 1.50 m


to ANSI Z60.1, with healthy root systems developed by 3.5 m 1.50 - 1.80 m
transplanting or root pruning. Provide well-shaped, fully- 4.0 m 1.80 - 2.00 m
branched, healthy, vigorous stock free of disease, insects,
eggs, larvae, and defects such as knots, sun scald, injuries, 16.1.2.4 Grass Seed
abrasions, and disfigurement.
1 Grass seed shall be fresh, clean, dry, new-crop seed
2 Provide trees and shrubs of sizes and grades l complying with AOSA's "Journal of Seed Technology;
conforming to ANSI Z60.1 for type of trees and shrubs Rules for Testing Seeds" for purity and germination
specified and shown on the Drawings. tolerances.
3 Label each tree and shrub with securely attached 2 Seed species shall be as stated in the Special
waterproof tag bearing legible designation of botanical Specification or shown on the Drawings for the particular
and common name. use and location, with not less than 95 percent
4 Provide balled and burlapped trees and shrubs. germination, not less than 85 percent pure seed, and not
Container-grown trees will be acceptable in lieu of balled more than 0.5 percent weed seed.
and burlapped subject to meeting ANSI Z60.1 limitations
for container stock. 16.1.2.5 Grass Sod (Turf)

5 Shade trees shall be single-stem trees with straight 1 Grass sod (turf) shall be first quality, complying with
trunk, well-balanced crown, and conforming to ANSI Z60.1 TPI's ‘Specifications for Sod (Turf) Materials’ in its
for type of trees required. ‘Guideline Specifications to Sodding’, including limitations
i. Branching Height: 1/3 to 1/2 of tree height. on thatch, weeds, diseases, nematodes, and insects,
Provide viable sod of uniform density, color, and texture,
6 Small trees shall be small upright or spreading type,
strongly rooted, capable of vigorous growth and
branched or pruned naturally according to species and
development when planted. Sods shall be nominal size
type and with relationship to caliper, height, and
750mm x 300mm.
branching recommended by ANSI Z60.1 and stem form as
follows: 2 Grass sod species shall be as stated in the Special
Specification or shown on the Drawings with not less than
i. Form: Multi-stem, clump, with 2 or more main
95 percent germination, not less than 85 percent pure seed,
stems.
and not more than 0.5 percent weed seed:
7 Deciduous shrubs shall have no less than the
minimum number of canes required by and measured 16.1.2.6 Grass Plugs
according to ANSI Z60.1 for type, shape, and height of
1 Grass plugs shall be as specified in paragraph
shrub.
16.1.2.5 but with a nominal size 100mm x 100mm.
8 Broad-leafed evergreens shall be: normal-quality,
well-balanced, broadleaf evergreens of type, height, 16.1.2.7 Grass Sprigs
spread, and shape conforming to ANSI Z60.1.
1 Grass sprigs shall be healthy living stems, rhizomes,
16.1.2.2 Ground Cover or solons with a minimum of two nodes and any attached
roots free of soil, of the species stated in the Special
1 Ground cover plants shall be established and well Specification or shown on the Drawings.
rooted in removable containers or integral peat pots and
with not less than the minimum number and length of 16.1.2.8 Topsoil
runners required by ANSI Z60.1 for the pot size indicated.
1 Topsoil shall conform to ASTM D 5268, pH range of
16.1.2.3 Palms 5.5 to 7, 4 percent organic material minimum, free of
stones 25 mm or larger in any dimension, and other
1 Palms shall have a crown of new leaves, proper color extraneous materials harmful to plant growth, obtained
of leaves of adult palms and sufficient hardiness. Palms from any of the sources stated below.
shall be supplied earth balled and hessian covered. Height

♦ 16-2 ♦
copy 249
i. Topsoil Source: Reuse surface soil stockpiled 2 Superphosphate shall be commercial, phosphate
on site. Verify suitability of surface soil to mixture, soluble; minimum of 20 percent available
produce topsoil meeting requirements and phosphoric acid.
amend when necessary. Supplement with 3 Commercial fertilizer shall be commercial-grade
imported topsoil when quantities are complete fertilizer of neutral character, consisting of fast-
insufficient. Clean topsoil of roots, plants, sods, and slow-release nitrogen, 50 percent derived from natural
stones, clay lumps, and other extraneous organic sources of urea-form, phosphorous, and
materials harmful to plant growth. potassium in the proportions recommended in reports
ii. Topsoil Source: Imported topsoil from off-site from a qualified soil testing agency.
sources, obtained from naturally well--drained 4 Slow-release fertilizer shall be granular fertilizer
sites where topsoil occurs at least 100mm consisting of 50 percent water-insoluble nitrogen,
deep; do not obtain from bogs or marshes. phosphorus, and potassium in the proportions
iii. Topsoil Source: Amend existing surface soil to recommended in reports from a qualified soil testing
produce topsoil. Supplement with imported agency.
topsoil when required. Topsoil shall have a
physical and chemical analysis before any 16.1.2.11 Mulches
amendments are added. 1 Mineral mulch shall be hard, durable stone, washed
free of loam, sand, clay, and other foreign substances, of
16.1.2.9 Soil Amendments
following type, size range, and color:
1 Lime shall be dolomite limestone conforming to i. Type: Crushed stone or gravel.
ASTM C 602, Class T, agricultural limestone, containing a
ii. Size Range: 20 mm maximum, 6 mm
minimum 80 percent calcium carbonate equivalent, with a
minimum.
minimum 99 percent passing a 2.36 mm sieve and a
minimum 75 percent passing a 250 micrometer sieve. iii. Color: Uniform tan-beige color range,
acceptable to the Engineer.
2 Aluminum sulfate shall be commercial grade,
unadulterated. 2 Straw mulch shall be air-dry, clean, mildew- and
seed-free, salt hay or threshed straw of wheat, rye, oats, or
3 Sand shall be cleaned, washed, natural or
barley.
manufactured sand, free of toxic materials.
3 Peat mulch shall be peat humus as specified in
4 Perlite shall be horticultural perlite, soil amendment
paragraph 16.1.2.9, items 5 or 6 as appropriate.
grade.
4 Compost mulch shall be well-composted, stable, and
5 Peat Humus shall be finely divided or granular
weed-free organic matter, pH range of 5.5 to 8; moisture
texture, with a pH range of 6 to 7.5, composed of partially
content 35 to 55 percent by weight; 100 percent passing
decomposed moss peat or reed-sedge peat.
through 1-inch (25-mm) sieve; soluble salt content of 5 to
6 Peat Humus for acid-tolerant trees and shrubs, shall 10 decisiemens/m; not exceeding 0.5 percent inert
be moss peat, with a pH range of 3.2 to 4.5, coarse fibrous contaminants and free of substances toxic to plantings;
texture, medium-divided sphagnum moss peat or reed- and as follows:
sedge peat.
i. Organic Matter Content: 50 to 60 percent of
7 Sawdust or ground bark humus shall be decomposed, dry weight.
nitrogen-treated, of uniform texture, free of chips, stones,
ii. Feedstock: Agricultural, food, or industrial
sticks, soil, or toxic materials.
residuals; biosolids; yard trimmings; or source-
i. When site treated, mix with at least 2.4 kg of separated or compostable mixed solid waste.
ammonium nitrate or 4 kg of ammonium
5 Fiber mulch shall be biodegradable, dyed-wood,
sulfate per cu. m of loose sawdust or ground
cellulose-fiber mulch; nontoxic; free of plant-growth or
bark.
germination inhibitors; with maximum moisture content
8 Manure shall be well-rotted, unleached stable or of 15 percent and a pH range of 4.5 to 6.5.
cattle manure containing not more than 25 percent by
6 Non asphaltic tackifier shall be colloidal tackifier
volume of straw, sawdust, or other bedding materials; free
recommended by fiber-mulch manufacturer for slurry
of toxic substances, stones, sticks, soil, weed seed, and
application; nontoxic and free of plant-growth or
material harmful to plant growth.
germination inhibitors.
9 Herbicides shall be EPA registered and approved, of
7 Asphalt emulsion shall conform to ASTM D 977,
type recommended by the manufacturer.
Grade SS-1; nontoxic and free of plant-growth or
16.1.2.10 Fertilizer germination inhibitors.

1 Bone-meal shall be commercial, raw, finely ground; 16.1.2.12 Stakes and Guys
minimum of 4 percent nitrogen and 20 percent phosphoric
1 Upright and Guy Stakes: Rough-sawn, sound, new
acid.
hardwood, redwood, or pressure-preservative-treated

♦ 16-3 ♦
copy 249
softwood, free of knots, holes, cross grain, and other performance of work. Do not proceed with installation
defects, 50 by 50 mm by length indicated, pointed at one until unsatisfactory conditions have been corrected.
end. 2 Topsoil Analysis: Furnish a soil analysis made by a
2 Guy and Tie Wire: ASTM A 641M, Class 1, qualified independent soil-testing agency stating
galvanized-steel wire, 2 strands, twisted, 2.7 mm in percentages of organic matter, inorganic matter (silt, clay,
diameter. and sand), deleterious material, pH, and mineral and
3 Guys for Palms: 5 mm diameter, 7-strand galvanized plant-nutrient content of topsoil. Report suitability of
wire in suitable lengths, with chafing guards of 13 mm topsoil for growth of applicable planting material. State
diameter PVC pipe, wire adjustments or turn buckles as recommended quantities of nitrogen, phosphorus, and
approved and 15 mm malleable iron ground anchors. potash nutrients and limestone, aluminum sulfate, or
other soil amendments to be added to produce
4 Guy Cable: 5 strand, 4.8 mm diameter, galvanized-
satisfactory topsoil.
steel cable, with zinc-coated turn buckles, 75 mm long
minimum, with 2 10 mm galvanized eyebolts. 3 Deliver packaged materials in containers showing
weight, analysis, and name of manufacturer. Protect
5 Hose Chafing Guard: Reinforced rubber or plastic
materials from deterioration during delivery and while
hose at least 13 mm in diameter, black, cut to lengths
stored at site.
required to protect tree trunks from damage.
4 Deliver trees, shrubs, ground covers, and plants after
6 Flags: Standard surveyor's plastic flagging tape,
preparation for planting has been completed and plant
white, 150 mm long.
immediately. If planting is delayed more than 6 hours
7 Burlap: Jute of 0.20 kg/m2 or cloth having same after delivery, set planting materials in shade, and protect
strength and resistance to tearing and capable of rotting in from weather and mechanical damage, and keep roots
the ground. moist.

16.1.2.13 Landscape Edgings i. Heel-in bare-root stock. Soak roots in water for
2 hours if dried out.
1 Polyethylene edging shall be proprietary standard--
ii. Set balled stock on ground and cover ball with
black polyethylene edging, 3 mm thick by 125 mm deep,
soil, peat moss, sawdust, or other acceptable
unless otherwise indicated, extruded in standard lengths,
material.
with 225 mm steel angle stakes.
iii. Do not remove container-grown stock from
i. Top Profile: Straight, with top 50 mm, 6 mm
containers until time of planting.
thick.
iv. Water root systems of trees and shrubs stored
ii. Top Profile: Rounded.
on site with a fine-mist spray. Water as often
16.1.2.14 Erosion-Control Materials as necessary to maintain root systems in a
moist condition.
1 Erosion-Control Blankets: Biodegradable wood
5 Coordinate installation of planting materials during
excelsior, straw, or coconut-fiber mat enclosed in a
normal planting seasons for each type of plant material
photodegradable plastic mesh. Include manufacturer's
required.
recommended steel wire staples, 150 mm long.
6 Coordinate planting periods with maintenance
2 Erosion-Control Fiber Mesh: Biodegradable twisted
periods to provide required maintenance from date of
jute or spun-coir mesh, a minimum of 0.5 kg/sq.m. with 50
handing over.
to 65 percent open area. Include manufacturer's
recommended steel wire staples, 150 mm long. 7 Proceed with planting only when existing and
forecast weather conditions permit.
16.1.2.15 Miscellaneous Materials
16.1.3.2 Preparation
1 Anti-desiccant: Water-insoluble emulsion, permeable
moisture retarder, film forming, for trees and shrubs. 1 Lay out individual tree and shrub locations and areas
Deliver in original, sealed, and fully labeled containers and for multiple planting. Stake locations, outline areas, and
mix according to the manufacturer's instructions. secure the Engineer's acceptance before the start of
planting work. Make minor adjustments as may be
2 Trunk-Wrap Tape: Two layers of crinkled paper
required.
cemented together with bituminous material, 100 mm
wide minimum, with stretch factor of 33 percent 2 Protect structures, utilities, sidewalks, pavements,
and other facilities, trees, shrubs, and plantings from
damage caused by planting operations.
16.1.3 Construction Requirements
3 Provide erosion-control measures to prevent erosion
16.1.3.1 General or displacement of soils and discharge of soil-bearing
water runoff or airborne dust to adjacent properties and
1 Examine areas to receive landscaping for compliance
walkways.
with requirements and for conditions affecting

♦ 16-4 ♦
copy 249
16.1.3.3 Planting Soil Preparation iii. Spread planting soil mix to a depth of 150 mm
but not less than required to meet finish grades
1 Before mixing, clean topsoil of roots, plants, sods, after light rolling and natural settlement. Do
stones, clay lumps, and other extraneous materials not spread if planting soil or sub-grade is
harmful to plant growth. muddy or excessively wet.
2 Mix soil amendments and fertilizers with topsoil at a. Spread approximately one-half the
rates indicated following soil physical and chemical thickness of planting soil mix over
analysis. Delay mixing fertilizer if planting does not follow loosened sub-grade. Mix thoroughly into
placing of planting soil within a few days. top 100 mm of sub grade and then spread
3 For palms and tree pit or trench backfill, mix planting remainder of planting soil mix.
soil before backfilling, and stockpile at site ready for use. b. Reduce elevation of planting soil to allow
4 For planting beds, mix planting soil either prior to for soil thickness of sod.
placing or apply on surface of topsoil and mix thoroughly 3 If grass is to be sown or planted in areas unaltered or
before planting. undisturbed by excavating, grading, or surface soil
i. Mix lime with dry soil prior to mixing fertilizer. stripping operations, prepare surface soil as follows:
Prevent lime from contacting roots of acid- i. Remove existing grass, vegetation, and turf.
tolerant plants. Do not mix into surface soil. Remove stones
ii. Apply phosphoric acid fertilizer, other than that larger than 25 mm in any dimension and sticks,
constituting a portion of complete fertilizers, roots, trash, and other extraneous matter.
directly to sub-grade before applying planting ii. Loosen surface soil to a depth of at least of 150
soil and tilling. mm. Apply soil amendments and fertilizers
according to planting soil mix proportions and
16.1.3.4 Ground Cover and Plant Bed Preparation
mix thoroughly into top 150 mm. of soil. Till
1 Loosen sub-grade of planting bed areas to a soil to a homogeneous mixture of fine texture.
minimum depth of 150 mm. Remove stones larger than 40 iii. Dispose of waste material, including grass,
mm in any dimension and sticks, roots, rubbish, and other vegetation, and turf, off site.
extraneous materials.
4 Grade planting areas to a smooth, uniform surface
2 Spread planting soil mixture to depth required to plane with loose, uniformly fine texture. Grade to within
meet thickness, grades, and elevations shown, after light plus or minus 13 mm of finish elevation. Roll and rake,
rolling and natural settlement. Place approximately one remove ridges, and fill depressions to meet finish grades.
half the thickness of planting soil mixture required. Work Limit fine grading to areas that can be planted in the
into top of loosened sub-grade to create a transition layer immediate future.
and then place remainder of planting soil mixture.
5 Moisten prepared lawn area before planting if soil is
3 Till soil in beds to a minimum depth of 200 mm and dry. Water thoroughly and allow surface to dry before
mix with specified soil amendments and fertilizers. planting. Do not create muddy soil.
4 Remove existing unsuitable soil to a minimum depth 6 Restore areas if eroded or otherwise disturbed after
of 200 mm and replace with prepared planting soil mixture. finish grading and before planting.
16.1.3.5 Preparation for Grassed Areas 16.1.3.6 Excavation for Trees and Shrubs
1 Limit sub-grade preparation to areas to be planted. 1 Pits and Trenches: Excavate with vertical sides and
2 Newly prepared sub grade: Loosen newly prepared with bottom of excavation slightly raised at center to
sub grade to a minimum depth of 150 mm. Remove assist drainage. Loosen hard subsoil in bottom of
stones larger than 25 mm in any dimension and sticks, excavation.
roots, rubbish, and other extraneous matter and dispose i. Bare-root trees and shrubs: Excavate at least
off site. 300 mm wider than root spread and deep
i. Apply superphosphate fertilizer directly to sub- enough to allow setting of roots on a layer of
grade before loosening. planting soil and with collar set at same grade
ii. Thoroughly blend planting soil mix off-site as in nursery, but 25 mm below finish grade.
before spreading, or spread topsoil, apply soil a. Shrubs setting layer: Allow 75 mm of
amendments and fertilizer directly to the planting soil.
surface, and thoroughly blend planting soil b. Trees setting layer: Allow 225 mm of
mix. planting soil.
a. Delay mixing fertilizer with planting soil if ii. Balled and burlapped trees and shrubs:
planting will not proceed within a few days. Excavate approximately 1½ times as wide as
b. Mix lime with dry soil before mixing ball diameter and equal to ball depth, plus the
fertilizer. following setting layer depth:

♦ 16-5 ♦
copy 249
a. Shrubs setting layer: Allow 75 mm of 3 Set balled and bur lapped stock plumb and in center
planting soil. of pit or trench with top of ball raised above adjacent
b. Trees setting layer: Allow 225 mm of finish grades as indicated.
planting soil. i. Place stock on setting layer of compacted
iii. Container-grown trees and shrubs: Excavate to planting soil.
container width and depth, plus the following ii. Remove burlap and wire baskets from tops of
setting-layer depth: balls and partially from sides, but do not
a. Shrubs setting layer: Allow 75 mm of remove from under balls. Remove pallets, if
planting soil. any, before setting. Do not use planting stock
if ball is cracked or broken before or during
b. Trees setting layer: Allow 150 mm of
planting operation.
planting soil.
iii. Place backfill around ball in layers, tamping to
iv. Pits for palms excavate to a depth not less than
settle backfill and eliminate voids and air
1.6m below finished grade and to a diameter of
pockets. When the pit is approximately half
not less than 1.5 m and at least 1 m greater
backfilled, water thoroughly before placing the
than diameter of root ball. Break up bottom of
remainder of backfill. Repeat watering until no
pits to a depth of 300 mm.
more is absorbed. Water again after placing
2 Dispose of subsoil removed from excavations. Do not and tamping the final layer of backfill.
mix with planting soil or use as backfill.
4 Set container-grown stock plumb and in center of pit
3 Notify the Engineer if unexpected rock or or trench with top of ball raised above adjacent finish
obstructions detrimental to trees or shrubs are grades as indicated.
encountered in excavations.
i. Carefully remove containers so as not to
i. Hardpan layer: Drill 150 mm diameter holes damage root balls.
into free-draining strata or to a depth of 3 m,
ii. Place stock on setting layer of compacted
whichever is less, and backfill with free-
planting soil.
draining material.
iii. Place backfill around ball in layers, tamping to
4 Notify the Engineer if subsoil conditions show
settle backfill and eliminate voids and air
unexpected water seepage or retention in tree or shrub
pockets. When the pit is approximately half
pits.
backfilled, water thoroughly before placing
5 Fill excavations with water and allow to percolate out, remainder of backfill. Repeat watering until no
before placing setting layer and positioning trees and more is absorbed. Water again after placing
shrubs. and tamping the final layer of backfill.

16.1.3.7 Planting, Palms, Trees and Shrubs 5 Set bare-root stock on cushion of planting soil.
Spread roots without tangling or turning toward surface,
1 Measure trees and shrubs according to ANSI Z60.1 and carefully work backfill around roots by hand. Puddle
with branches and trunks or canes in their normal position. with water until backfill layers are completely saturated.
Do not prune to obtain required sizes. Take caliper Plumb before backfilling, and maintain plumb while
measurements 150 mm above ground for trees up to 100 working backfill around roots and placing layers above
mm caliper size, and 300 mm above ground for larger roots. Remove injured roots by cutting cleanly; do not
sizes. Measure main body of tree or shrub for height and break.
spread;
i. Set collar 25 mm below adjacent finish grades,
2 Deliver freshly dug and container grown palms, trees unless otherwise indicated.
and shrubs to the site just before planting. Do not prune
6 Dish and tamp top of backfill to form a 75 mm high
before delivery, except as approved by the Engineer.
mound around the rim of the pit. Do not cover top of root
Protect bark, branches, and root systems from sun scald,
with backfill.
drying, sweating, whipping, and other handling and tying
damage. Do not bend or bind-tie trees or shrubs in such a 7 Wrap trees of 50 mm caliper and larger with trunk-
manner as to destroy natural shape. Maintain protective wrap tape. Start at base of trunk and spiral cover trunk to
covering during delivery. Do not drop trees and shrubs height of first branches. Overlap wrap, exposing half the
during delivery. width, and securely attach without causing girdling.
Inspect tree trunks for injury, improper pruning, and insect
i. Immediately after digging bare-root stock, pack
infestation and take corrective measures required before
root system in wet straw, hay, or other suitable
wrapping.
material to keep root system moist until
planting. 8 Remove suckers, flowering and fruiting parts and
approximately 30% of fronds from palms before planting.
ii. Handle balled and bur lapped stock by the root
Leave sufficient fronds to enclose and protect growing
ball
bud, trim to 65% of original length, lift to surround

♦ 16-6 ♦
copy 249
growing bud and burlap wrap and securely tie them in ii. Bond straw mulch by spraying with asphalt
position and leave on palm for around one year after emulsion at the rate of 38 to 49 L/92.9 sq.m.
planting. Special attention is required to protect palm Take precautions to prevent damage or
roots from being bruised during digging and bur lapping. staining of structures or other plantings
adjacent to mulched areas. Immediately clean
16.1.3.8 Tree and Shrub Pruning damaged or stained areas.
1 Prune, thin, and shape trees and shrubs according to 6 Protect seeded areas from hot, dry weather or drying
standard horticultural practice. Prune trees to retain winds by applying compost mulch, peat mulch or planting
required height and spread. Unless otherwise directed by soil within 24 hours after completing seeding operations.
the Engineer, do not cut tree leader; remove only injured Soak and scatter uniformly to a depth of 4.8 mm and roll
or dead branches from flowering trees Prune shrubs to to a smooth surface.
retain natural character. Shrub sizes indicated are size
after pruning. 16.1.3.11 Hydro-Seeding

1 Mix specified seed, fertilizer, and fiber mulch in


16.1.3.9 Tree and Shrub Guying and Staking
water, using equipment specifically designed for hydro
1 Stake all trees of 50 to 125 mm caliper; stake trees seed application. Continue mixing until uniformly blended
less than 50 mm caliper only if required to prevent into homogeneous slurry suitable for hydraulic application.
displacement by wind. Use a minimum of 2 stakes of i. Mix slurry with no asphaltic tackifier.
length required to penetrate at least 450 mm below
ii. Apply slurry uniformly to all areas to be seeded
bottom of backfilled excavation and to extend at least 1800
in a one-step process. Apply mulch at a
mm above grade. Set stakes vertical and spaced to avoid
minimum rate of 15.3-kg/92.9 sq. m dry weight
penetrating balls or root masses. Support trees with 2
but not less than the rate required to obtain
strands of tie wire encased in hose sections at contact
specified seed-sowing rate.
points with tree trunk. Allow enough slack to avoid rigid
restraint of tree. iii. Apply slurry uniformly to all areas to be seeded
in a two-step process. Apply first slurry
2 Guy and stake trees exceeding 4.2 m high and more
application at a minimum rate of 5.1-kg/92.9
than 75 mm caliper. Securely attach no fewer than 3 guys
sq.m. dry weight but not less than the rate
to stakes 750 mm long, driven to grade. Attach flags to
required to obtain specified seed-sowing rate.
each guy wire, 750 mm above finish grade.
Apply slurry cover coat of fiber mulch at a rate
3 Support palms with 4 guy wires secured to ground of 10.2 kg/92.9 sq.m.
anchors and attached to palm at approximately two thirds
height. Adjust tension as necessary with wire adjusters or 16.1.3.12 Sodding
turn buckles.
1 Lay sod within 24 hours of harvesting. Do not lay
16.1.3.10 Grass Seeding sod if dormant or if ground is muddy.
2 Lay sod to form a solid mass with tightly fitted joints.
1 Sow seed with spreader or seeding machine. Do not
Butt ends and sides of sod; do not stretch or overlap.
broadcast or drop seed when wind velocity exceeds 8
Stagger sod strips or pads to offset joints in adjacent
km/h. Evenly distribute seed by sowing equal quantities in
courses. Avoid damage to sub grade or sod during
two directions at right angles to each other.
installation. Tamp and roll lightly to ensure contact with
i. Do not use wet seed or seed that is moldy or sub grade, eliminate air pockets, and form a smooth
otherwise damaged. surface. Work sifted soil or fine sand into minor cracks
2 Sow seed at the rate of 2.3 to 3.6 kg/92.9 sq.m. between pieces of sod; remove excess to avoid
3 Rake seed lightly into top 3 mm of topsoil, roll lightly, smothering sod and adjacent grass.
and water with fine spray. i. Lay sod across angle of slopes exceeding 1:3.
4 Protect seeded areas with slopes exceeding 1:6 with ii. Anchor sod on slopes exceeding 1:6 with wood
erosion-control fiber mesh and slopes exceeding 1:4 with pegs or steel staples spaced as recommended
erosion-control blankets installed and stapled according to by sod manufacturer but not less than 2
manufacturer's written instructions. anchors per sod strip to prevent slippage.
5 Protect seeded areas with slopes not exceeding 1:6 3 Saturate sod with fine water spray within two hours
by spreading straw mulch. Spread uniformly at a of planting. During first week, water daily or more
minimum rate of 42 kg/92.9 sq.m. to form a continuous frequently as necessary to maintain moist soil to a
blanket 38 mm in loose depth over seeded areas. Spread minimum depth of 38 mm below sod.
by hand, blower, or other suitable equipment.
16.1.3.13 Plugging
i. Anchor straw mulch by crimping into topsoil
with suitable mechanical equipment. 1 Plant plugs in holes or furrows, spaced 300 mm apart
in both directions. On slopes, contour furrows to neat
levels.

♦ 16-7 ♦
copy 249
16.1.3.14 Sprigging 16.1.3.18 Installation of Edgings

1 Plant freshly shredded sod sprigs in furrows 63 to 75 1 Install plastic edging where indicated, according to
mm deep. Place individual sprigs with roots and portions the manufacturer's recommendations. Anchor with steel
of stem in moistened soil, 150 mm apart in rows 250 mm stakes spaced approximately 600 mm apart, driven
apart, and fill furrows without covering growing tips. through upper base grooves of edging.
Lightly roll and firm soil around sprigs after planting.
16.1.3.19 Installation of Miscellaneous Materials
2 Broadcast sprigs uniformly over prepared surface at
a rate of 0.28 cu. m/92.9 sq.m. and mechanically force 1 Apply antidesiccant using power spray to provide an
sprigs into lightly moistened soil. adequate film over trunks, branches, stems, twigs, and
i. Spread a 6-mm thick layer of compost mulch, foliage. When deciduous trees or shrubs are moved in full-
peat mulch, planting soil or topsoil on sprigs. leaf, spray with anti-desiccant at nursery before moving
and again 2 weeks after planting.
ii. Lightly roll and firm soil around sprigs after
planting. 2 Set tree grate segments with adjoining surfaces as
shown on the Drawings. Shim up from supporting
iii. Water sprigs immediately after planting and
substrate with soil-resistant plastic. Maintain a 75 mm
keep moist by frequent watering until well
minimum growth radius around base of tree; break away
rooted.
units of casting, if necessary, according to the
16.1.3.15 Requirements for Satisfactory Grass manufacturer's instructions.

1 Seeded areas: At end of maintenance period, a 16.1.3.20 Cleanup and Protection


healthy, uniform, close stand of grass has to be
1 During landscaping, keep pavements clean and work
established, free of weeds and surface irregularities, with
area in an orderly condition.
coverage exceeding 90 percent over any 0.92 sq.m and
bare spots not exceeding 125 by 125 mm. 2 Protect landscaping from damage due to landscape
operations, operations by other contractors and trades,
2 Sodded areas: At end of maintenance period, a
and trespassers. Maintain protection during installation
healthy, well-rooted, even-colored, viable lawn has been
and maintenance periods. Treat, repair, or replace
established, free of weeds, open joints, bare areas, and
damaged landscape work as directed.
surface irregularities.
3 Promptly remove soil and debris created by planting
3 Plugged areas: At end of maintenance period, the
work from paved areas. Clean wheels of vehicles before
required number of plugs has been established as well-
leaving site to avoid tracking soil onto roads, walks, or
rooted, viable patches of grass; and areas between plugs
other paved areas.
are free of weeds and other undesirable vegetation.
4 Erect barricades and warning signs as required to
4 Sprigged areas: At end of maintenance period, the
protect newly planted areas from traffic. Maintain
required number of sprigs has been established as well-
barricades throughout maintenance period and remove
rooted, viable plants; and areas between sprigs are free of
when instructed. Remove erosion-control measures after
weeds and other undesirable vegetation.
grass or plants are established.
5 Reestablish grassed areas that do not comply with
requirements and continue maintenance until lawns are 16.1.3.21 Disposal of Surplus and Waste Materials
satisfactory.
1 Disposal: remove surplus soil and waste material
16.1.3.16 Planting Ground Cover and Plants including excess subsoil, unsuitable soil, trash, and debris,
and legally dispose of it off site.
1 Space ground cover and plants as indicated.
2 Dig holes large enough to allow spreading of roots, 16.1.4 Warranty and Maintenance
and backfill with planting soil. Work soil around roots to
eliminate air pockets and leave a slight saucer indentation 16.1.4.1 Warranty
around plants to hold water. Water thoroughly after
1 General Warranty: The special warranty specified in
planting, taking care not to cover plant crowns with wet
this Clause shall not deprive the Client Authority of other
soil.
rights that it may have under other provisions of the
16.1.3.17 Mulching Contract and shall be in addition to, and run concurrent
with, other warranties given by the Contractor under
1 Mulch backfilled surfaces of pits, trenches, planted requirements of the Contract.
areas and other areas with mulch material as indicated on
2 Special Warranty: Warrant the following living
the Drawings or as directed by the Engineer.
planting materials for a period of one year after date of
2 Lay the mineral mulch where shown or directed, Completion, against defects including death and
average 75mm deep, and finish level with adjacent finish unsatisfactory growth, except for defects resulting from
grades. Do not place mulch against trunks or stems. lack of adequate maintenance, abnormal weather

♦ 16-8 ♦
copy 249
conditions unusual for warranty period, or incidents that Lay out temporary watering system to avoid
are beyond the Contractor's control. walking over muddy or newly planted areas.
i. Trees. ii. Water grass at a minimum rate necessary to
ii. Shrubs. ensure uniform moisture and growth.

iii. Ground cover. 5 Mow grass as soon as top growth is tall enough to
cut. Repeat mowing to maintain grass at a height of 38 to
iv. Palms.
50 mm. Remove no more than 40 percent of grass-leaf
v. Lawns and grasses. growth in initial or subsequent mowing. Do not delay
3 Remove and replace dead planting materials mowing until grass blades bend over and become matted.
immediately unless required to plant in the succeeding Do not mow when grass is wet. Schedule initial and
planting season. subsequent mowing to maintain the following grass
4 A limit of one replacement of each plant material will height:
be required, except for losses or replacements due to 6 Apply fertilizer after initial mowing and when grass
failure to comply with requirements. is dry. Use fertilizer that will provide actual nitrogen of at
least 0.45 kg/92.9 sq.m. to lawn area.
16.1.4.2 Maintenance
7 Maintain ground cover by watering, weeding and
1 Maintain trees, palm and shrubs by pruning, fertilizing to establish healthy viable planting for a period
cultivating, watering, weeding, fertilizing, restoring of 6 months after the date of Completion
planting saucers, tightening and repairing stakes and guy
supports, and resetting to proper grades or vertical 16.1.5 Method of Measurement
position, as required to establish healthy, viable plantings.
Spray as required to keep trees and shrubs free of insects 16.1.5.1 Excavation, Soiling, Cultivating and Grading
and disease. Restore or replace damaged tree wrappings.
1 Excavation and filling to reduce or make up levels
Maintain palms, trees and shrubs for a period of 12
specifically required for landscaping shall be measured in
months following the date of Completion.
cubic meters as the volume shown on the Drawings or
2 Begin maintenance of grassed areas immediately directed on site. Other excavation related to construction
after each area is planted and continue until acceptable is measured under Section 2.
lawn is established, but for not less than the following
2 Excavation for tree and shrub planting and for
periods:
ground cover plants is not measured separately but is
i. Seeded areas: 90 days from date of deemed to be part of the planting items
Completion.
3 Planting soil for grassed and planted areas, whether
When full maintenance period has not elapsed manufactured or imported, shall be measured together in
before end of planting season, or if lawn is not cubic meters as the volume specified or shown on the
fully established, continue maintenance during Drawings or as directed on site.
next planting season.
4 Planting soil for trees and shrubs and ground cover
ii. Sodded areas: 45 days from date of plants is not measured separately but is deemed to be part
Completion. of the planting item.
iii. Plugged areas: 45 days from date of 5 Rates for excavation, filling and soiling shall be
Completion. deemed to include, but not be limited to:
iv. Sprigged areas: 45 days from date of i. marking boundaries of planting areas,
Completion.
ii. excavating by machine or hand, supporting
3 Maintain and establish grass by watering, fertilizing, sides, trimming to slopes and finished levels
weeding, mowing, trimming, replanting, and other and keeping excavated areas free from water,
operations. Roll, re-grade, and replant bare or eroded and disposal of surplus material,
areas and remulch to produce a uniformly smooth lawn.
iii. applying fertilizers and herbicides to surfaces
i. In areas where mulch has been disturbed by to receive filling,
wind or maintenance operations, add new
iv. supplying planting soil from any source, laying
mulch. Anchor as required to prevent
and cultivating and final grading of in situ
displacement.
topsoil and topsoil filling,
4 Watering: Provide and maintain temporary piping,
v. additional cultivation and application of
hoses, and watering equipment to convey water from
herbicides during the fallow period,
sources and to keep grass uniformly moist to a depth of
100 mm. vi. prevention of erosion.

i. Schedule watering to prevent wilting, pudding,


erosion, and displacement of seed or mulch.

♦ 16-9 ♦
copy 249
16.1.5.2 Grass Seeding and Planting 16.1.7 Items in Bill of Quantities
1 Each kind of grass shall be measured separately in Excavation, Soiling, Seeding and Cultivating:
square meters as the area shown on the Drawings or i. Excavating to reduce levels (cu.m.)
instructed on site.
ii. Excavating topsoil for preservation (cu.m.)
2 Rates for grass seeding or planting are deemed to
iii. Filling to make up levels (cu.m.)
include, but not limited to, the costs of:
iv. Topsoil filling to make up levels
i. final cultivation and weeding of soil, watering
and for planting (cu.m.)
and application of pre-seeding or planting
fertilizer, Grass Seeding and Planting:
ii. applying fertilizer after planting or seeding, v. Grass seeding (sq.m.)
iii. watering during establishment of grass, vi. Grass sods (turf) (sq.m.)
iv. first and subsequent cuts, including fertilizing vii. Grass plugs (sq.m.)
and watering, viii. Grass sprigs (sq.m.)
v. temporary protection,
Trees, Palms and Shrubs
vi. maintenance and making good defects.
ix. Trees (Type; Size) (nr.)
16.1.5.3 Tree, Palm, Shrub and Ground Cover Planting x. Palms (Type; Size) (nr.)
1 Each type of tree, shrub, palm and plant is measured xi. Shrubs (Type; Size) (nr.)
separately by number, stating the species, height or size Ground Cover and Other Planting:
where appropriate. Botanical names are given in
xii. Ground cover plants (Type) (nr.)
descriptions
xiii. Climbers (Type) (nr.)
2 Rates for trees, shrubs, palms and plants are deemed
to include, but not limited to, the costs of:
16.2 Irrigation System
i. Re-cultivating topsoil in planting areas,
ii. Setting out planting beds, 16.2.1 Description / General
iii. Drainage of planted areas,
16.2.1.1 Scope
iv. Excavating pits and holes including disposal
and breaking up bottoms, 1 This Sub-section describes requirements for
v. Cutting and treating roots, pruning and the like, furnishing, installing, testing and putting into service,
including anti-desiccant and tree wound complete irrigation systems to provide water for the trees,
dressings, shrubs and grassed and planted areas around and
vi. Planting, including backfilling hole with adjacent to the highway system, all as and where shown
on the Drawings.
planting soil and firming,
vii. Watering and fertilizing after planting, 2 The work includes all civil, mechanical and electrical
Works, pipelines, pumping stations, water tanks, filters,
viii. Supports to trees and palms including stakes,
fertilizer injection equipment, control valves, pressure
guys, ties and chafing guards,
regulators and gauges, water meters, automatic or manual
ix. Trunk wrapping, controllers, and all incidentals and spare parts specified
x. Labeling, and as appropriate for the particular irrigation system
specified.
xi. Forking and/or raking soil at completion
3 The irrigation system shall be as specified in the
xii. Applying mulches,
Special Specification for the particular Project and shall be
xiii. Temporary protection, of a type which will supply the quantities of water required,
xiv. Maintenance and making good defects. on a "programmable" basis. The irrigation system shall, in
general, be either drip irrigation utilizing drip emitters
16.1.6 Basis of Payment and/or sprinkler irrigation using either bubblers or
sprayheads.
1 The landscape work, completed, and accepted by the
4 When access to the domestic water supply is
Engineer will be paid for at the unit rates for the relevant
intended, the Contractor shall liaise with the appropriate
items stated in the Bill of Quantities, which unit rates shall
authorities regarding the planning, design, construction of
be deemed to be full compensation for supply of all
the works and the subsequent operation of the irrigation
materials, labor, transport, tools and equipment and
network. Back flow preventers (of the double check valve
provision of all other items and services and maintenance
type) shall be installed at points of connection to the
for the complete work as specified.
domestic water supply network.

♦ 16-10 ♦
copy 249
5 The control head for each irrigation branch system 4 The Engineer may verify the performance and quality
shall include all components as shown on the Drawings, of any samples by arranging for such tests as he deems
as required for the complete operation of the system. The appropriate to be carried out, at the Contractor's expense.
final size of all components of each control head for each Approval of samples by the Engineer shall not relieve the
irrigation branch system shall be a minimum of 20% Contractor of his obligations with respect to the suitability
greater than the demand load as submitted by the of equipment or its final performance once installed, and
Contractor, with the working drawings, in tabular form coordination of elements into a fully operational irrigation
drawn up as follows for approval: system. The Contractor shall not be entitled to any
compensation for the rejection of any sample by the
Control Irrigation Capacity Peak Approx.
Head Controller at Water Working Engineer and shall be held responsible for any delay
No. Control Demand Pressure resulting from such rejection.
Head (lit/24 hr) at Control
(lit/hr) Head 16.2.1.4 Submittals
(MN/sq.m)
1 Product Data: Include pressure rating, rated capacity,
settings, and electrical data of selected models for the
following:
16.2.1.2 Schedules of Proposed Equipment
i. Pipes and fittings.
1 Schedules containing full details of all principal items
ii. Pumps/motor and related mechanical and
of the irrigation system shall be submitted by the
electrical works
Contractor together with his Tender. The Contractor shall
ensure conformity of the equipment with the requirements iii. Water hammer arresters.
of the Specification. Any additional information required iv. Valves. Include aboveground and
by the Engineer shall be provided promptly by the underground; general-duty, pressure-reducing,
Contractor. manual and automatic control, and quick-
2 A summary of irrigation equipment manufacture coupler types.
including description, manufacturer, country reference v. Valve boxes.
and catalog origin in a tabular format shall be included in vi. Sprinklers and devices.
the Contractor's submission.
vii. Specialties. Include emitters, drip tubes, and
3 The Contractor shall supply equipment from the other devices.
manufacturer's lists with the characteristics indicated in
viii. Controllers. Include wiring diagrams.
his Tender unless otherwise agreed.
2 Shop Drawings: Show irrigation system, including
4 Approval of a manufacturer does not necessarily
plan layout and locations, types, sizes, capacities, and flow
constitute approval of his product as equal to that
characteristics of piping components. Include water
specified. The Contractor shall ascertain that the approved
meters, backflow preventers, valves, piping, sprinklers and
manufacturers are capable of supplying the required
devices, specialties, accessories, controls, and wiring.
materials and/or equipment and shall ensure conformity
Show areas of sprinkler spray and overspray in
with the Specification in all respects.
accordance with the requirements of the Specification.
16.2.1.3 Approval of Equipment 3 Coordination Drawings: Show piping and major
system components. Indicate interface and spatial
1 Equipment shall not be ordered until approved by the
relationship between piping, system components,
Engineer. All documentation submitted regarding
adjacent utilities, and proximate structures.
equipment shall be in English except if otherwise
indicated in the Contract Documents. 4 Test Reports: Submit reports of tests on materials
and installations as directed by the Engineer.
2 Promptly upon signing the Contract, the Contractor
shall submit to the Engineer 3 copies of the detailed 5 Maintenance Data: Include in maintenance manuals
characteristics of all irrigation equipment proposed, data for the following:
including catalogs (originals not copies) with identification i. Valves / surge control devices.
references. Particulars shall be given of any ii. Automatic, pressure-reducing control valves.
manufacturer's deviations from the Specification. The
iii. Sprinklers.
Contractor shall also confirm that the selected irrigation
system equipment is robust, able to withstand rough iv. Specialties.
handling, and capable of supplying the specified v. Controllers.
quantities of water on a programmable basis.
6 As-Built Drawings: At project close-out, submit
3 The Contractor shall, at his own expense, present record drawings of installed pipework and products, in
samples to the Engineer of the various valves, pipes, accordance with the requirements of the Specification,
fittings and other products proposed for use. Such Section 1, Sub-section 1.12. The drawings shall show the
samples will be required only after approval of their location, with respect to the highway and other pipelines
technical characteristics. and other permanent features, of all pumping stations,

♦ 16-11 ♦
copy 249
water tanks, irrigators, valves, pipelines, fittings and other 3 The Contractor shall be responsible for the
items incorporated in the Works. They shall also show the correctness and safety of all electrical and mechanical
sizes of all pipes, their pressure class or rating, and the connections for the irrigation system, before the system is
actual pressures as measured on the highest and lowest brought into service, including checking the proximity of
spray heads commanded by each control valve. different metals to ensure no chemical reaction or
7 Submit certificates of compliance from manufactures. corrosion will occur.

16.2.1.5 Delivery, Storage and Handling 16.2.1.7 Spares

1 Preparation for Transport: Prepare valves according 1 At the commencement of the Contract the Contractor
to the following: shall submit a detailed list of minimum essential spares
recommended by the irrigation system manufacturer,
i. Ensure that valves are dry and internally
together with current prices and catalog identifications.
protected against rust and corrosion.
2 Lists of any additional spares recommended by the
ii. Protect valves against damage to threaded
manufacturers shall also be submitted, referenced to each
ends and flange faces.
major item of equipment and showing the current prices
iii. Set valves in best position for handling. Set and catalog identifications.
valves closed to prevent rattling.
3 The Engineer will select the types and numbers of
2 During Storage: Use precautions for valves spares he requires and will instruct the Contractor to
according to the following: proceed with their purchase and delivery to the
i. Do not remove end protectors unless Employer's store or depot. The spares shall be supplied
necessary for inspection; then, reinstall for and suitably packed for transportation to the Site and for
storage. long term storage and shall include all fastenings, lugs,
ii. Protect from weather. Store indoors and screws, etc. Identification labels shall be attached to the
maintain temperature higher than ambient outside and also enclosed within the package.
dew-point temperature. Support off ground or
16.2.1.8 Equipment Labels and Charts
pavement in watertight enclosures when
outdoor storage is necessary. 1 Each piece of equipment shall have a certified
3. Deliver piping with factory-applied end caps. nameplate, permanently attached at the factory and in a
Maintain end caps through shipping, storage, and readily accessible location, printed or stamped clearly with
handling to prevent pipe-end damage and to prevent the name and address of the manufacturer, equipment
entrance of dirt, debris, and moisture. model number, serial number, date of manufacture,
performance rating or duty, pressure, temperature, or
4. Protect stored piping from moisture and dirt. Elevate
other limitations and other relevant data.
above grade. Do not exceed structural capacity of floor
when storing inside. 2 Aluminum tags 50 mm diameter and 1.5 mm thick
with stamped lettering filled with black print and with
5. Protect flanges, fittings, and specialties from
heavy aluminum or brass hooks and chains shall be
moisture and dirt.
provided in lieu of labels wherever the latter cannot easily
6. Store plastic piping protected from direct sunlight. identify the equipment.
Support to prevent sagging and bending.
3 Charts indicating the schedules for equipment
7. Manufacturer’s recommendations on handling, lubrication, maintenance and essential operating
repairing, laying, jointing, anchoring, cutting and other instructions shall be prepared, mounted on wooden or 6
works for pipes and fittings are to be strictly followed. mm dense hardboard back boards, covered with heat
bonded clear plastic laminate or framed under glass.
16.2.1.6 Installation and Checking
These charts shall be permanently fixed with four brass
1 The irrigation work shall be supervised by qualified screws at approved locations as directed.
representatives of the Contractor and full facilities and 4 Prior to preparing labels and tags, and maintenance
assistance shall be provided by the Contractor to enable charts, a preliminary schedule shall be submitted for
the Engineer to inspect or check the Works at any time. approval, showing the equipment to be labeled or tagged
Such inspection or checking shall in no way relieve the with suggested nomenclature, and proposed maintenance
Contractor from any of his obligations. He may be schedules.
required to open up for inspection any equipment that has
been delivered to the Site partly assembled. 16.2.1.9 Operation and Instruction Manuals
2 The Contractor shall be responsible for making minor 1 Prior to final acceptance, the Contractor shall submit
adjustments to the location of sprinklers and specialties as to the Engineer 6 sets of operation, maintenance and
necessary to avoid plantings and obstructions such as instruction manuals relating to the irrigation system. The
signs and light standards subject to the approval of the manuals shall be A4 size, bound in loose leaf binders or
Engineer.

♦ 16-12 ♦
copy 249
booklets suitably enclosed and shall include the following to BS 4164 or hot applied bitumen to BS
information: 3416, Type 1, grade d, minimum
i. Setting up, putting into service and operating thickness 10 mil.
instructions. 2 uPVC Pressure Pipes
ii. Fault location and repair procedures. i. Pipes shall conform to BS EN 1452 or to DIN
iii. Maintenance instructions, including schedules 8061/8062, Series 4 and 5 or ISO 161 Class 10 &
for preventive maintenance, and 16. Concrete encasement shall be used if cover
recommended lubricants and equivalents. is less than 1 meter or greater than 5 meters.

iv. Complete recommended spares list, including ii. Fittings shall be to BS EN 1452 part 3 or DIN
manufacturers' names and catalog numbers. 8063 part 1 fabricated from pipe.

v. Names and addresses of manufacturers' local iii. Joints shall be to DIN 8063 part 1, socket spigot
authorized representatives and service agents. with rubber sealing rings shall be to BS EN
681-2.

16.2.2 Material iv. Pipes and fittings shall be protected from the
direct rays of the sun at all times by means of
16.2.2.1 Pipes, Fittings and Accessories reflective cover sheets.

1 Ductile iron pipe 3 Polyethylene PE Pressure Pipe

i. Ductile iron pipe for water shall be to BS EN i. Pipes and fittings with 110 mm (4”) diameter
545 or equivalent. Unless otherwise indicated and larger shall be to ISO 4427, DIN 8074/8075
in the Bill of Quantities or the Drawings, Class or AWWA C906. Pipe shall be supplied in
K9 shall be used for diameters up to 500 mm, straight pieces and not rolled on a drum. The
Class K8 for diameters 500 to 800 mm and ends of each pipe shall be plain and suitable
Class K7 for diameters greater than 800 mm. for heat fusion. Pipe and fittings shall be
minimum class 12 kg/cm2, Dimension Ratio 9.3,
ii. Spigot and socket ended pipes shall be used
according to AWWA C906 Table 9 or ISO 3126.
for straight runs and adjacent to elbows or
fittings. These joints shall be provided with ii. Irrigation pipes smaller than 110 mm (4”) in
rubber gaskets, and an external thrust block is diameter shall be according to ISO 4427, BS EN
required at elbows or fittings. Anchored or self 12201-2 (PN12) or to DIN 8074/8075 class
restrained joints shall be used for sections 12Kg/cm2.
adjacent to elbows in areas where space is iii. Materials used shall have a standard PE codes
restricted or indicated on the Drawings or BOQ. designation 3408 and 3406 with respective
Anchored joints are to be push-in, self minimum hydrostatic design basis of 1600 and
anchored type able to take up the axial forces 1250 psi according to AWWA C906 Table 1. PE
thus allowing concrete thrust blocks to be Pipes shall contain a minimum 2% carbon
dispensed with. The Contractor shall submit black well dispersed and shall be constructed
calculations verifying the number of restrained with UV stabilizer material according to ASTM
joints required noting that pipe pressure D2239.
testing will be made when pipes are partially iv. Manufacturers shall provide certification that
backfilled. stress regression testing has been performed
iii. Flanged pipes wherever specified shall have on the pipe products. Materials shall also meet
screwed-on or cast-on flanges to sustain elevated temperature requirements as given in
working pressure of NP 16 minimum. Table 2 AWWA C906.
iv. Flanges shall conform to BS EN 1092-2. v. Fittings shall be to AWWA C906, extruded or
v. Factory protection for pipes and fittings: injection moulded suitable for class of pipe
required:
a. Pipes shall be internally cement lined to
BS EN 545 with ordinary Portland cement a. For irrigation pipes with diameters equal
to BS EN 197-1 to specified thicknesses or larger than 50 mm (2”) the following
fittings shall be used:
b. Externally, pipe shall be coated with
metallic zinc to BS EN 545 and followed • for similar size PE pipes joining use
by a bitumen coat to BS 3416 of PE butt-weld fittings: to ASTM D3261.
minimum thickness 6 mils. A hot applied • for dissimilar pipes sizes use PE
coal tar based material to BS 4164 may socket fittings that uses the electrical
replace the bitumen coat.
c. Fittings shall be coated internally and
externally by dipping, or other method,
using hot applied coal tar based material

♦ 16-13 ♦
copy 249
heating with the appropriate pipe viii. Pipes and fittings shall show no porosity when
clamps according: to ASTM D2683. tested in accordance with ASTM D 2444 or BS
b. For irrigation pipes with diameters less EN 1796 and BS EN 14364.
than 50 mm (2”) use PVC/PP ix. Samples made from pipe or fitting laminates
compression fittings. The compression shall show no evidence of delaminating or
fittings shall conform to BS 5114 with other impairment when tested in accordance
minimum 12 kg/cm2 nominal pressure. with ASTM D 570.
c. The use of insert and/or solvent welded x. The axial modulus of elasticity of pipes shall be
fittings for PE irrigation pipes shall not be tested in accordance with ASTM D 2925.
allowed thicknesses. xi. The short-time hydraulic failure strength of
vi. Joints for pipes and fittings shall be by heat pipe and fittings, shall be tested in accordance
fusion and in strict accordance with pipe with ASTM D 1599.
manufactures recommendations. Joints shall xii. The axial tensile stress for pipes shall be tested
have a tensile strength equal to that of the pipe. in accordance with ASTM D 2105.
Fusion temperature, interface pressure,
xiii. The hoop tensile strength of pipes shall be
alignment and cooling time, shall be according
tested in accordance with ASTM D 2290.
to manufactures recommendations.
xiv. The indentation hardness of pipes and fittings
vii. Pipes must be marked at intervals of not more
shall be tested in accordance with ASTM D
than 2 m. with legible cast, stamped lettering to
2583.
show the following, as appropriate:
xv. The glass content of the reinforced wall of
a. nominal pipe size,
pipes and fittings, will be determined in
b. type of plastic material in accordance accordance with ASTM D 2584.
with designation code,
xvi. The hydrostatic design stress for pipes and
c. standard dimension ratio SDR, fittings will be obtained from the extrapolated
d. pressure rating, long term hydrostatic tests in accordance with
e. Initials and number of relevant standard, ASTM D 2992.

f. manufacturer name or trademark, xvii. Joints shall be GRP double socket couplings
with rubber rings to ISO 4633 or BS EN 681-2.
g. date of manufacturer:
The allowable angular deflection shall conform
4 GRE Pipes and Fittings to the requirements of BS EN 1796 and BS EN
i. Pipes and Fittings: Conform to AWWA C950-07 14364 Table 3.
or BS EN 1796 and BS EN 14364 or equivalent xviii. Transition couplings for underground piping
suitable for 10 bar working pressure with a shall be to AWWA C219, metal, sleeve-type
minimum stiffness of 10000 N/m2. coupling same size as, with pressure rating at
ii. Resin: Use epoxy resin. The resin-curing agent
mixture will have sufficient chemical and
mechanical resistance to meet the imposed
requirements.
iii. The reinforcement of thermosetting resin shall
consist of two types of glass with a low alkali
content.
iv. C-glass or polyester non-woven shall be used
as reinforcing material for the chemically
resistant inner layer (liner).
v. E-glass shall be used as reinforcing material for
the structural wall. The reinforcing material is
to be provided with a special finish to assure a
good adhesion with the matrix.
vi. GRE pipe and fittings shall have a resin-rich
exterior surface having a minimum thickness of
0.5 mm.
vii. Flexible tensile resistant rubber seal lock joint
shall be used with a O-ring seal and a locking
device on all end connections except those
adjacent to flanged fittings when rigid tensile
resistant flanges are required.

♦ 16-14 ♦
copy 249
least equal to and ends compatible with, piping ii. Construction: Non-rising stem, straight pattern
to be joined with flanged connections.
iii. Material of Component Parts: Cast iron with
16.2.2.2 Valves and Penstocks
stainless steel trim.
1 Gate Valves: Cast Iron. iv. Operation: Manual operated valves are to have
i. Type: Size 50 mm and smaller to BS 5154 hammer type hand-wheel and electric operated
inside screw, solid wedge, rising stem and valves are to have motor actuator.
screwed bonnet. 4 Ball Valves
ii. Type: Size 65 mm and larger to BS 5163, inside i. Ball valves 50 mm and under shall be full port
screw, solid wedge, resilient seated, for valves of 2-piece construction, lever operated with
350 mm and smaller and metal seated for bronze body and stem, chrome-plated brass
valves 400 mm and larger, bolted bonnet, non- ball, replaceable PTFE seats and packing,
rising stem type, suitable for NP 16 for plastic coated steel handle, threaded end
irrigation networks. connection for steel piping, and copper
iii. Material of component parts from basic or compression or solder end connections for
alternative materials listed in BS 5163. copper piping.
iv. End Connections: Size 50 mm and smaller ii. Ball valves 150mm to 1200mm shall comply
screwed end to BS 21. with the requirements of AWWA C 507.
v. End Connections: Size 65 mm and larger 5 Check Valves
flanged end connection to BS EN 1092-2. i. Check valves shall be to BS EN 12334, swing,
vi. Operation: Valves larger than 400 mm diameter straight, for horizontal use and suitable for
are to have spur gear drive operated by working pressure of 16 bars.
removable key. Valves smaller than 400 mm ii. Material of Component Parts: Ductile iron from
are to be operated by hand-wheel. basic materials listed in BS EN 12334 Table 5,
vii. Factory Protection: Casting surfaces are to be under 'copper alloy faced' column.
given an initial coat of protective paint iii. Special Requirements: Seating or facing rings
immediately after shot blasting and a second are to be renewable. An arrow showing
coat on assembly. Protective coating is to be direction of flow is to be visible from outside
hot applied coal tar or bitumen to BS 4164 or and cast integral with the valve housing.
BS 3416 respectively. Thickness of coat to be
iv. End Connections: Either flanged to BS EN
250 microns.
1092-2, or screw ended to BS 21 to suit joints
2 Butterfly Valves: Cast Iron. specified for adjoining pipes.
i. Type: To BS EN 593, double flange with v. Factory Protection: Casting surfaces are to be
resilient seating, for horizontal use and suitable given an initial coat of protective paint
for NP 16. immediately after shot blasting and a second
ii. Size: For 350 mm and larger. coat on assembly. Protective coating is to be
iii. Material of component parts shall be from hot applied coal tar or bitumen to BS 4164 or
basic materials listed in BS EN 593 Table 3. BS 3416 respectively. Minimum thickness of
coating shall be 250 microns.
iv. End Connections: Flanged to BS EN 1092-2.
6 Float Valves
v. Operation by hand wheel. Maximum shut off
pressure against which valve is operated is to i. Type: Globe pattern, with two operating
2 chambers, sealed through piston disc.
be 15 kg/cm .
vi. Factory Protection: Casting surfaces are to be ii. Operation: Valves shall operate with a
given an initial coat of protective paint mechanical compensating float valve
immediately after shot blasting and a second controlling flow to tank by modulating in direct
coat on assembly. Protective coating is to be ratio to minimum fall in water level. Control of
hot applied coal tar or bitumen to BS 4164, or valve is to be through mechanically operated,
BS 3416 respectively. Thickness of coat shall three-position, four-way valve. Moving four-
be 250 microns. way valve control in one direction is to open
valve and moving lever in other direction is to
3 Globe Valves
close-out valve. When lever is moved to centre,
i. Type: To ASTM A48/A48M grade 30B with valve will throttle in an intermediate position.
valve disc to ASTM A276 type 430, valve seat
iii. Valve positioning control consists of float
to ASTM A276 type 420 and stem to ASTM
operated linkage mechanism for remote
A276 type 403. Valve is to be suitable for a
mounting which feeds water level changes
working pressure of 16 bars.
back to main valve through low friction,

♦ 16-15 ♦
copy 249
flexible push-pull cable supplied by same stop valves. Valves are to be suitable for
manufacturer. working pressures up to NP16.
iv. Valve operating control consists of secondary 8 Sluice Gates / Penstock
linkage mechanism functioning off common i. Type: To AWWA C560, rising stem, having a
lever connected to both main valve position flat back for bolting to wall, suitable for 10
indicator rod and control valve position meters seating pressure and 4 meters off-
indicator rod and control valve operating lever. seating pressure, with standard conventional
Minute changes in water level are transmitted closure and rectangular or circular aperture.
through push-pull cable to three-position, four-
ii. Material of Component Parts: Unless otherwise
way control valve.
specified on the Drawings, any materials listed
v. Construction: Cast iron body to ASTM A126, in Section 2 of AWWA C560 may be used in
bronze valve trim and valve operating manufacture except that materials identified as
mechanism to ASTM B62 and all stainless steel being subject to de-zincification or de-
valve float and pilots. aluminumization are not to be used.
vi. Factory Protection: Internal coating of epoxy to iii. Operation: By floor pillar with gear box.
a thickness of 250 microns and external coating Maximum operating head from surface of
of epoxy and nickel plating to a thickness of water to centre line of gate is to be 10 meters.
250 microns.
iv. Factory Testing: Leakage test to meet the
7 Air Valves requirements of Section 6.3 of AWWA C560 is
i. Generally: Valves are to have cast iron body to be carried out on all sluice gates.
and bolted cover to BS EN 1561 grade 14 v. Factory Protection: Casting surfaces are to be
minimum, rubber outlet seat, plastic or ebonite given an initial coat of protective paint
ball, forged bronze screws and guide for ball immediately after shot blasting and a second
acting under pressure. Valves are to be coat on assembly. Protective coating is to be
dynamic type where there is no possibility of hot applied coal tar or bitumen to BS 4164 or
ball being drawn into orifice due to high air BS 3416 respectively. Thickness of coat to be
velocities. Valves are to be factory tested to 1.5 at least 250 microns.
times working pressure and factory coated with
9 Pressure Reducing Valves
coal tar or bituminous coating to BS 4164 or BS
3416 respectively. Thickness of coat to be 250 i. Types: Installed where shown on the Drawings
microns. to pressure ratings and pressure settings
indicated, to automatically reduce higher inlet
ii. Double Air Valves (or Combination Air Valves):
pressure to steady lower downstream pressure
These are required for relieving air under
regardless of changing flow rate and/or varying
pressure and in bulk. Large orifice releases or
inlet pressure. Valves are to be high pressure
admits air during charging or emptying of
rating piston type and hydraulic pilot operated
mains while small orifice releases air
type.
accumulated at summits of mains under
pressure. Large orifice area is to be equal to or ii. Accessibility: Maintenance is to be possible
greater than inlet of valve. Valves are to be without removing valve from pipeline.
fitted with nitrite rubber lined butterfly valve iii. End Connections: Flanged to BS EN 1092-2 to
with nylon coated disc on stainless steel shaft pressure rating of 10, 16 or 25 as appropriate
operated by lever handle with indicator and and provided from factory with necessary bolts,
locking thumb screw. Valves are to be flanged washers, nuts and gaskets.
to BS EN 1092-2 and suitable for working iv. Factory Protection: Internal coating of epoxy to
pressures up to NP16. a thickness of 250 microns and external coating
iii. Single Air Valves: Type 1 (or air vacuum valve) of epoxy and nickel plating to a thickness of
for releasing or admitting air during filling or 250 microns.
emptying of pipes. Type II (or air release valve) v. Piston Pressure Reducing Valves shall be of the
for automatically releasing, under pressure, spring loaded type, balanced out against
accumulated air at summits of mains. Air upstream pressure by high resistance piston
valves larger than 50 mm are to be flanged to action. Valve shall control a constant
BS EN 1092-2 and are to have nitrite rubber downstream pressure to a maximum variation
lined butterfly valve with nylon coated disc on of +/- 10% and close tight with zero flow rate.
stainless steel shaft operated by lever handle Accessories shall include two pressure gauges
with indicator and locking thumb screw. Air with isolation cocks, one fitted upstream and
valves 50 mm and smaller are to have B.S.P. one downstream.
thread with brass or gun metal male screwed

♦ 16-16 ♦
copy 249
vi. Diaphragm Pressure Reducing Valves shall be valve operating pressure range shall be
pilot controlled, single seated, hydraulically between 1.5 and 14 bars.
operated, diaphragm type globe valve. Control ii. Material: The valve body and bonnet shall be
system is to be sensitive to slight pressure constructed of heavy-duty glass-filled UV-
changes and is to immediately control main resistant nylon and have stainless steel studs
valve to maintain desired downstream and flange nuts; diaphragm shall be of nylon
pressure. Pressure setting adjustment is to be reinforced rubber.
made with single adjustment screw protected
iii. Operation: The valve shall have manual
by a housing that can be sealed. Body and
open/close control (internal bleed) for manual
cover are to be cast iron, ductile iron or cast
opening and closing of valve without
steel depending upon operating pressure.
electrically energizing the solenoid.
Main valve trim is to be stainless steel and
pilot system all stainless steel. Main valve is to iv. Operation: The valve shall have a brass flow
have single removable seat and resilient disc. control stem for accurate manual regulation
and/or shut off of outlet flow.
vii. Diaphragm valve assembly shall be fully
guided by a precision machined stem with v. Construction: The valve construction shall be
bearings at both ends in the valve cover and such as to provide for all internal parts to be
seat. Diaphragm is to be nylon bonded with removable from the top of the valve without
synthetic rubber. Valve is to have necessary disturbing the valve installation.
factory fitted pilot valves, small interconnecting 12 Electric Remote Control Valves with Pressure
piping and accessories to perform required Regulation
functions. Pilot control is to be direct acting, i. Type: Electric remote control valve as specified
adjustable spring loaded, normally open, above shall have a pressure regulating module
diaphragm valve designed to permit flow when capable of regulating outlet pressure between
controlled pressure is less than spring setting. 1 and 7 bars (15 and 100 psi).
Control system is to include Y-strainer, fixed
ii. Operation: Module shall have an adjusting
orifice and isolation cocks. Pilot control system
screw for setting pressure and Schrader valve
is also to include flow control device to
connection for monitoring pressure. The
regulate closing speed of valve. Valve is to
pressure shall be adjustable from the pressure
close tight at zero flow rate.
regulating module when the valve is manually
10 On-Off Solenoid Operated Valves bled.
i. Type: Pilot controlled, single seated,
hydraulically operated, diaphragm type globe 16.2.2.3 Irrigation Equipment
valve fitted with solenoid control valve to keep 1 Pop-Up Spray Sprinkler
main valve open when energized and to close
i. Type: Fixed, non-rotating spray or stream
tight main valve once de-energized.
spray adaptable for full circle, part circle, or
ii. Construction: Cast iron valve body and cover, strip wetting pattern, suitable for installation
stainless steel main valve trim and all stainless on a pop-up mechanism. Spray head to have
steel pilot system. built in check valve and pressure regulated
iii. Controls: These shall comprise auxiliary stem.
controls to permit adjustment of valve opening ii. Material: The sprinkler body, stem, nozzle, and
and closing speeds of up to 2 minutes for screen shall be constructed of heavy duty,
opening and for closing. ultra-violet resistant plastic, with a heavy-duty
iv. Accessories shall include the following: stainless steel retract spring.
a. Adjustable opening speed control. iii. Construction: Spray head to retract flush with
b. Adjustable closing speed control. the finished ground level when not in
operation. When spraying, net pop-up height
c. No-return check valves.
to be 150 mm from finished ground level.
d. Y-strainers.
iv. Performance: This shall meet requirements of
e. Interconnecting stainless steel tubing and discharge and spray radius as specified on the
unions. Drawings for the given nozzle pressure. The
v. Factory Protection: Internal and external sprinkler shall have a matched precipitation
coating of epoxy as described for float valves. rate nozzle with an adjusting screw capable of
11 Electric Remote Control Valves regulating the radius of flow.

i. Type: Normally closed 24 VAC 50/60 cycle v. Tests: The Contractor shall provide test results
solenoid actuated globe pattern with a carried out at factory substantiating required
balanced pressure diaphragm design. The performance (discharge and radius of throw at

♦ 16-17 ♦
copy 249
prescribed operating pressure and height other components in the control head.
above ground) and giving actual precipitation Backflow preventers shall only be installed in
rate and its uniformity as obtained for locations where they are readily accessible for
uniformity test carried out using catch cans. maintenance and testing and shall not be
2 Pop-Up Rotor Sprinkler located where any part of the device can
become submerged at any time.
i. Type: Full or part circle pop-up rotor sprinkler,
single nozzle. The part circle sprinkler shall ii. Backflow preventers shall be of the reduced
have adjustable arc coverage from 25° to 360°. pressure type.
The sprinkler shall have a built in check valve iii. Backflow preventers shall be evaluated and
and pressure regulated stem. tested by an approved authority and certified
ii. Material: The sprinkler body, stem, nozzle, and by the American Society of Sanitary
screen shall be constructed of heavy duty, Engineering Standards 1013 (latest edition) for
ultra-violet resistant plastic, with a heavy duty reduced pressure principle backflow preventers.
stainless steel retract spring. Such valves shall also meet the performance
requirements of AWWA C 511.
iii. Construction: Sprinkler head to retract flush
with the finished ground level when not in iv. Backflow preventers up to 75 mm in size shall
operation. When operating, net pop-up height be of machined cast bronze body construction
to be 100 mm from finished ground level. and up to 150 mm in size shall be of cast iron
body construction with internal waterways
iv. Performance: This shall meet the requirements
epoxy coated, stainless steel and/or brass
of discharge, radius and rotation angle as
internal parts and stainless steel flange bolts,
specified on the Drawings for the given nozzle
durable, tight-seating rubber check valve
pressure. The sprinkler shall have a matched
assemblies.
precipitation rate nozzle, with an adjusting
screw capable of regulating the radius and the v. Backflow preventers shall be suitable for
flow. supply pressure up to 1.2 MN/sq.m (12
kg/sq.cm) and for water temperature up to 44
v. Tests: The Contractor shall provide test results
degrees C. The operating range for flow and
carried out at factory substantiating required
pressure loss shall be as shown on the
performance (discharge and radius of throw at
Drawings.
prescribed operating pressure and height
above ground) and giving actual precipitation vi. The backflow preventer assembly shall consist
rate and its uniformity as obtained for of a pressure differential relief valve located in
uniformity test carried out using catch cans. a zone between two positive seating check
valves. The relief valve shall contain a
3 Bubblers
separate means whereby free air will enter the
i. Type: Pressure compensating, of the full circle zone, and contained water will be discharged
umbrella or trickle discharge, with inlet screen. to the atmosphere, when the valve is fully open.
ii. Construction: Bubbler shall be of a vii. The backflow assembly shall include 2 gate
permanently assembled design constructed of valves for isolating unit, and 3 test cocks for
durable ultra-violet resistant plastic. testing the device to ensure proper operation.
iii. Performance: Bubbler to operate at constant viii. Backflow preventers shall be designed for
flow discharge over a pressure range specified inline servicing.
on the Drawings.
6 Quick Couplings Valve
4 Emitters
i. Type: The quick coupling valve shall be a two-
i. Type: Pressure compensating, single outlet. piece type.
ii. Construction: Emitter shall have self-piercing ii. Construction: The valve body shall be
inlet barb constructed of durable ultra-violet constructed of heavy cast brass.
resistant plastic.
iii. Cover: The cover shall be a durable, protective
iii. Performance: The emitter shall have a self- self-closing, locking rubber cover.
flushing action to minimize clogging, and shall
iv. Valve Operating Key: The valve shall be
operate at a constant flow discharge over a
opened and closed by a brass key supplied by
pressure range specified on the Drawings.
valve manufacturer having a 25 mm male top
5 Backflow Preventers pipe threads and 19 mm female top pipe
i. Backflow preventers shall be installed in the threads outlet. The valve throat shall have a
locations shown on the Drawings. Normally keyway with detent positions for regulating
for each control head in the system a backflow water flow. Operating keys are to be supplied
preventer shall be installed upstream of all

♦ 16-18 ♦
copy 249
at the rate of 1 per five valves installed or to include output surge protection to protect
fraction thereof. controller from power surges; to include one
arrestor for each valve wire and one for the
16.2.2.4 Valve Operators and Accessories common or ground wire; to include a master
1 General on-off switch.

i. Gate, butterfly and ball valves are to be vi. The Controller without exception shall be of
manually or electrically operated depending the same manufacturer as the remote control
upon size, torque applied on valve stem or as valve.
shown on the Drawings. 3 Cabling for Irrigation Control
ii. Valves 350 mm and smaller are to be operated i. Low voltage wiring from automatic controllers
manually with a maximum applied torque on to remote control valves shall be direct burial
handwheel of 100 Nm. type, 600 volt solid copper single conductor
iii. Valves 400 – 500 mm are to be operated wire with heat resistant insulation minimum of
manually with a maximum applied torque of 0.4 mm thickness. The Contractor shall submit
150 Nm. proposed low voltage wire routing shop
drawing for the Engineer's approval prior to
iv. Valves of higher torque are to have appropriate
installation. The low voltage wire shall be
thrust bearings, slides and gearboxes to fulfill
encased in 5 mm diameter conduit.
these requirements.
ii. Medium voltage cables shall conform to the
v. Gate valves 600 mm and larger and ball valves
requirements of BS 5467, IEC 502, or other
are always electrically operated using thrust
approved comparable international standards
bearings, gearboxes and motor actuators.
as applicable. Cables shall be 600/1000 volt
vi. Butterfly valves 600 mm and larger are to be grade, multicore, stranded copper conductor,
either manually or electrically operated as cross-linked polyethylene (XLPE) insulated,
shown on the Drawings. uPVC oversheather type. The service cable for
2 Programme Controllers irrigation controllers shall be 3 core 10 mm2
i. Type: Solid state or hybrid (combining electro- minimum.
mechanical and micro-electronic circuiting), iii. Conductors shall be annealed stranded copper
capable of fully automatic or manual operation in accordance with BS EN60228. Conductor
of the remote solenoid valves, with dual insulation shall be moisture and heat resistant,
programme, independent station timing, 14- 90 degrees C, grade conforming to the relevant
day calendar dial for every day or every other parts of BS EN 50363. The cable cores unless
day or any sequence starts, time-setting otherwise approved shall be colored as
control up to 60 minutes per station in 2 follows: Single Phase System: Red (phase),
minutes increments 23 starts per day. The black (neutral), green or green/ yellow (ground).
number of stations to be as indicated on the 4 Valve Chambers, Boxes and Markers
Drawings or in the Bill of Quantities. Maximum
i. Valves shall be installed in chambers or boxes
number of 24 VAC solenoid valves that can be
of suitable size as shown on drawings for easy
controlled by a station is 4. Controller is to
access. Chambers and boxes shall be complete
allow for valve power output to be interrupted
with access covers, ladder rungs and other
without affecting the controller timers.
incidental works.
ii. Operation: The controller shall have a remote
ii. Unless shown otherwise on the Drawings all
pump start circuit to activate a remote pump
chambers shall be installed on a suitable base
start relay to run the pump during the irrigation
for proper foundation and easy leveling to
cycle.
proper grade, and also to provide for sufficient
iii. Operation: The controller shall allow for drainage.
opening the first remote control valve before
iii. Valve markers showing the reference numbers
operating the pump and also for closing the
of the valves shall be of materials and to the
last remote control valve within 15 seconds
dimensions, shapes and details as shown on
after stopping the pump.
the Drawings.
iv. Installation: Controller shall be installed in
5 Valve Accessories
pedestal weatherproof, heavy-duty, locking,
steel cabinet adequately protected. Pedestal i. Hand-wheels shall be to BS 5163, of cast iron
mount shall include terminal strips for the to BS EN 1561. Hand-wheels are to be marked
quick connection of cables. 'CLOSE' with an arrow to indicate clockwise
direction of closure. Diameters and other
v. Electrical Features: Accept 220 V 50/60 cycle
constructional details shall be to
current; to command 24 VAC solenoid valves;

♦ 16-19 ♦
copy 249
manufacturer's standards. Hand-wheels are to thermosetting resin and is to incorporate a
be supplied at a rate of 1 in 5 valves. corrosion resistant liner. Glass fibers are to be
ii. Valve caps shall be to BS 5163, of cast iron or compatible with the resins used. Liner is to
malleable iron to BS EN 1561 and BS EN 1562 comprise an inner face being a smooth hard
respectively. Set screw of valve cap is to be suitably reinforced resin rich layer. Exterior
mild steel M12. surface of valve box is to be resin rich.

iii. Operation Keys: Combination prizing bar and iii. Inside surface of valve box is to be hard,
lifting key type, with 1.5 m vertical bar and 0.5 durable, free of tackiness and free of bulges,
m horizontal bar. Keys are to be supplied at a dents, ridges or other defects that result in a
rate of 1 in 5 valves. variation of inside dimensions of more than 3
mm from that obtained in adjacent unaffected
iv. Extension Spindles for Gate Valves: Steel to BS
portions of the surface.
2470 - M12, hot dip galvanized to BS EN 10240,
size 18 x 18 mm for valves up to 200 mm iv. No glass fiber reinforcement is to penetrate
diameter and 24 x 24 mm for valves 250 mm to interior surface of valve box wall, and any
400 mm diameter. Length for each valve size is glass fiber reinforcement on exterior surface
to suit excavation requirements. Spindles are must be thoroughly impregnated with resin.
to have cast iron or malleable iron cap and v. Glass content will be determined by ignition
coupling, to BS EN 1561,and BS EN 1562, loss analysis in accordance with ASTM D 2584
respectively, on both sides of extension spindle or BS EN ISO 1172.
(cap for operating spindle and coupling for vi. Plastic valve boxes are to be manufactured
connecting to valve). Set screws of caps and from high impact, acid and heat resistant, self-
couplings are to be mild steel M12. extinguishing, hard, durable, low coefficient of
v. Protection Tubes: Either uPVC or cast iron. expansion PVC compound.
Shape, sizes and other constructional details
are to be to manufacturer's standards and/or as 16.2.2.5 Jointing Material
shown on the Drawings. Tubes are to have 1 Generally
caps circling extension spindles.
i. Gaskets: Elastomeric full face 3 mm thick joint
vi. Surface boxes shall be to BS 5834 Part 2. rings to ISO 4633 or BS EN 681-2 with
Frames and lids are to be cast iron to BS EN dimensions to BS 3063.
1561, studs, bolts, nuts and hinge pins are to
ii. Rings: Elastomeric to ISO 4633 or BS EN 681-2
be mild steel M12, chains are to be mild steel
with dimensions to manufacturer's
or wrought iron and lid is to have a suitable
recommendations to suit type of joint required.
identification marking cast on in accordance
with details given on the drawings or as iii. Bolts and Nuts: ISO metric black hexagon to BS
instructed by the Engineer. Boxes are to be of 4190, minimum tensile strength 433 MN/m2,
the following types: maximum elongation 17%. After fixing, bolt
projection shall to be maximum 6 mm,
a. Heavy grade type A for carriageways
minimum 3 mm.
(wheel loads up to 11.5 tons).
iv. Washers: Black steel shall be to BS 4320 or ISO
b. Medium grade type M for use where
887.
heavy commercial vehicles are
exceptional. v. Dielectric joints shall have insulating gasket
between flanges and Teflon sleeves and
c. Light grade type L for use in places
washers between bolts and nuts and flanges.
inaccessible to wheeled vehicles
Joints are to be suitable for operating pressure
vii. Lifting Key Sets: Malleable iron, supplied at the of system.
rate of 1 per 5 covers installed or fraction
2 Flexible Couplings
thereof.
i. Type: Gasketed sleeve type, to allow angular
viii. Guards for Underground Stop Valves: PVC,
deflection and axial movement of two joined
shape and size and other constructional details
pipe ends and to maintain permanent, leak-
to manufacturer's standards and/or as shown
tight joint.
on the Drawings.
ii. Components comprise one centre sleeve, two
6 Plastic Valve Boxes
end followers or flanges, two rubber-
i. Generally: Valve boxes may be glass reinforced compounded wedge-section gaskets and
plastic (GRP) or plastic. sufficient draw bolts and nuts to properly
ii. GRP valve boxes are to be designed to suit site compress gaskets. Tightening of bolts to draw
conditions and loadings. GRP is to be end followers together is to compress gaskets
manufactured from E-glass type fibers and

♦ 16-20 ♦
copy 249
in recess between centre sleeve and followers iii. Construction: All steel with flanges class PN 10,
onto pipe ends to effect positive seal. PN 16 or PN 25 depending upon coupling
iii. Size: Couplings are to have diameter location on pipework.
specifically supplied for and to properly fit type iv. Size: Couplings shall have diameter specifically
of joined pipe ends. Center sleeve is to be of supplied for and to properly fit type of joined
adequate thickness and whole coupling ends of pipes and valves. Coupling shall
suitable for minimum working pressures permit tightening of end flanges without risk of
shown on the Drawings. misalignment. Seal shall be locked after end
iv. Centre sleeve and followers shall be true joints are tightened.
circular sections, free from irregularities, flat 4 Flanged Adaptor: Ferrous
spots or surface defects and formed from steel i. Material: Cast iron to BS EN 545.
mill sections with space between sleeve and
ii. Length of adaptor shall be 200 mm for
follower designed to provide confinement of
diameters up to 150 mm, 250 mm for
gasket.
diameters between 200 and 300 mm and as
v. Bolts shall be special steel having minimum approved for diameters larger than 300 mm.
2
yield strength of 2800 kg/cm (40,000 psi) and
2 iii. Factory Protection: Coated with bitumen or
ultimate strength of 4200 kg/cm (60,000 psi).
coal tar to BS 3416 or 4164 respectively.
Bolts shall be track-head design to prevent
turning when nut is drawn up and threads are 16.2.2.6 Concrete and Metal Work
to be rolled with a nominal diameter larger
than diameter of shank. Manufacturer shall 1 Concrete shall conform to the requirements of
supply information regarding recommended Section 5, clause 5.1.2, reinforcing steel to Clause 5.2.2
torque to which bolts are to be tightened. and reinforced concrete to Clause 5.3.2. Structural steel
and other metalwork shall conform to Section 6, Sub-
vi. Gaskets shall be synthetic rubber-base
section 6.2 and as shown on the drawings. Structural steel
compound with other products to produce
and other metalwork shall be painted and protected in
material which will not deteriorate from age,
accordance with Section 7.
heat or exposure to air and which is resilient
and able to resist cold flow of material so that 16.2.2.7 Pumping Plant
joint will remain sealed and tight indefinitely
when subjected to shock, vibration, pulsation, 1 Refer to Section 17 of the Specification.
temperature and adjustment of connected
pipes. 16.2.3 Construction Requirements
vii. Factory Protection: Coupling shall be factory
16.2.3.1 Excavation, Bedding and Backfilling
painted internally with 10 mils coating of epoxy
and externally with red primer to AWWA C203 1 All excavation and backfill shall conform to the
Type B chlorinated rubber solution compatible requirements of Sub-Sections 2.3 - ’Road Excavation’ and
with bitumen, coal tar and general paints. 2.7 - ’Excavation and Backfilling for Structures’.
viii. Installation: Couplings are to be assembled on 2 All piping under pavements shall be installed in pipe
site in accordance with manufacturer's sleeves (ducts) to permit replacement at a later date.
instructions to ensure permanently tight joints Sleeves for irrigation piping shall be sulfate resistant
under all conditions of expansion, contraction, reinforced concrete pipe as specified in Section 8, Clause
shifting and settlement.]. 8.1.2. Locations and sizes of pipe sleeves are as shown on
3 Dismantling Couplings the Drawings. Pipe and sleeves, or sleeves only, shall be
placed prior to or during construction of the highway. Any
i. Type: Couplings shall ensure extensible
piping installed after completion of the highway
connection between sections of pipework, to
construction shall be placed after jacking a pipe sleeve
be mounted next to valves to enable easy
under the pavement. The Contractor will not be permitted
dismantling from pipework or to permit joining
to cut into the pavement for pipe installation.
pipework when butterfly valve is removed for
maintenance. 16.2.3.2 Pipe Laying - Generally
ii. Components: Dismantling piece shall be
1 Lowering: The Contractor shall not lower pipe into
flanged type composed of two parts, one
trench until pipe bed is brought to grade and approved. He
sliding into the other, and a free flange to
shall use ropes, wire slings, band slings, spreader beams
compress a trapezoidal section seal to ensure
etc. as recommended by manufacturer for each type of
water tightness. Coupling shall have locking
pipe and as approved.
devices to provide elements of complete
rigidity. 2 Manufactured pipe shall be handled and assembled
in accordance, with the manufacturer's instructions. When

♦ 16-21 ♦
copy 249
pipe laying is not in progress, the Contractor shall close manufacturer's of proprietary joints when laying and
open ends of pipes with properly fitted temporary wooden jointing.
plugs or standard caps as directed 4 Differing pipe and fitting material: The Contractor
3 All material shall be carefully examined for damage shall joint with adaptors as recommended by pipe
and tested in accordance with manufacturer's instructions manufacturer.
before laying to the satisfaction of Engineer.
16.2.3.4 Line and Gradient
4 The Contractor shall examine material to ensure
internal coating or lining and outer coating or sheathing 1 In open excavation: The Contractor shall provide and
are undamaged. If damaged, the Contractor shall make maintain sight rails and boning rods properly painted to
good or dispose of as directed. ensure correct alignment of pipe runs. Sight rails shall be
positioned either vertically above the lines of pipes or
5 The Contractor shall remove dirt and other materials
immediately adjacent thereto. At no time shall there be
before lowering the pipe into the trench and verify the
less than three sight rails in position on each length of
pipe inside is clear from construction debris before
pipeline under construction to any one gradient.
making joint.
2 In heading: The Contractor shall provide and
6 Pipe on solid ground: The Contractor shall cut holes
maintain marks to establish line and level of pipeline.
in bottom of trench to allow proper jointing and for barrel
Marks are to be fixed in each working shaft and two
of pipe to bear evenly on solid ground for its full length.
further marks established in each length of heading.
7 Pipe on granular bedding: The Contractor shall scoop
out locally at sockets/couplings to enable pipe to rest 16.2.3.5 Floatation
uniformly on barrel and adjust to exact line and level.
1 Prevention: Whenever water is excluded from interior
After testing, the Contractor shall lay and compact further
of pipe, the Contractor shall place sufficient backfill above
granular material in 150 mm layers or as approved to
pipe to prevent floatation.
levels shown on the Drawings.
2 The Contractor shall remove: any pipe that has
8 The Contractor shall lay pipe on an even formation
floated, correct the bedding and relay.
true to grade and line, with sockets (if any) facing up the
gradient. 16.2.3.6 Pipe Built Into Structures
9 Pipe on concrete bed or surround: The Contractor
1 Treatment of external surface: The Contractor shall
shall provide rectangular blocks of concrete Class 30,
thoroughly clean outside surface of pipes to be built-in
made in approved moulds at least 14 days before use, and
immediately before installation. The Contractor shall
approved hardwood folding wedges. The Contractor shall
remove protective coating to metal pipes, where ordered.
provide two concrete blocks for each pipe, set and bone
The Contractor shall roughen clay and concrete pipes as
into correct level on formation bottom and lay pipe
directed. The Contractor shall paint plastic pipes with
properly centered and socketed.
appropriate solvent cement and sprinkle with dry coarse
10 The Contractor shall insert two hardwood folding sand whilst wet. The Contractor shall cut away sheathing
wedges of width equal to width of concrete block between from sections to be built-in and after installation restore
body of pipe and block and drive together until pipe is protection up to external face of structure with approved
brought to exact level required. The Contractor shall leave bituminous material.
blocks and wedges undisturbed while pipes are being
2 Flexible joints: The Contractor shall provide two
jointed and concrete bed and haunch or surround are
flexible joints or flexible patented joints adjacent to
being placed. The Contractor shall ensure blocks and
structures. The Contractor shall place first joint not more
wedges are of sufficient size and strength to prevent
than one pipe diameter from face of structure and second
settlement of pipes. The Contractor shall leave sufficient
not more than the following distances away from first:
space to enable joints to be made, tested and inspected.
i. Pipelines not exceeding 450 mm: 2 pipe
16.2.3.3 Jointing diameters.

1 Manufacturer's instructions shall be followed ii. Pipelines over 450 mm and not exceeding 1000
regarding placement of bedding and backfilling, mm: 1.2 m.
cleanliness of joint surfaces, lubricant used, correct iii. Pipelines over 1000 mm: 1.8 m.
location of components, provision of correct gaps
between end of spigot and back of socket for flexible joints 16.2.3.7 Field Testing: Generally
etc. 1 Provision of test equipment: All items for tests shall
2 Deflection of joint: The Contractor shall not deflect be provided on site before the test i.e. pressure gauges,
flexible joints beyond maximum permissible angles given instruments, water etc...
by manufacturer and/or relevant Standards. 2 The Contractor shall carry out tests in the presence of
3 Patent detachable and flexible joints: The Contractor the Engineer's Representative.
shall strictly comply with special instructions issued by

♦ 16-22 ♦
copy 249
3 Fittings and joints: The Contractor shall permanently 16.2.3.9 Visual Inspection Test
anchor fittings before testing and leave all joints exposed
for checking. 1 Timing: The Contractor shall carry out test after total
backfilling of length under test.
4 Test sections: The Contractor shall limit test sections
to not more than 500 m. 2 Limit of length to be tested at one time is three full-
length pipes unless otherwise approved.
5 Test sections: The Contractor shall test pressure lines
between valve chambers whenever possible. 3 Apparatus: The Contractor shall use rubber tyred
bogies which do not damage lining of pipe and an
6 Test sections: No testing shall be carried out against
adequate supply of electric lamps.
or through the pressure reducing valves. The setting of the
pressure reducing valves shall not be changed for testing 4 The Contractor shall check joints by means of feelers
purposes. to ensure rubber rings are correctly located.

7 Test plug: The Contractor shall secure end of main 5 The Contractor shall check pipe barrel for visible
and test plug by struts. cracks.

8 Closed valve: The Contractor shall not test against a 16.2.3.10 Deflection Tests for GRP Pipes
closed valve unless there is no acceptable alternative.
1 The Contractor shall conduct deflection tests for GRP
9 The Contractor shall apply pressure by manually
pipes as required by the Engineer at 3 stages. Deflection
operated test pump or, in the case of large diameter mains,
shall be measured at the spigot end at mid point and at
by power driven test pump, if approved.
socket end.
10 The Contractor shall examine exposed joints and
2 Stage 1: at completion of primary backfill (deflection
repair visible leaks.
at this stage should be below 0.5%).
11 Failure: Should a test fail, the Contractor shall locate
3 Stage 2: at final backfill (Maximum allowable
leak and replace or make good defective pipe or replace
deflection 2.5%).
and make good faulty joint and retest main.
4 Stage 3: six months after final backfill (maximum
12 Records: The Contractor shall keep test records in an
allowable deflection 4.0%).
approved form and hand original copy to the Engineer
immediately after completion of test. 5 Pipes not passing the deflection tests at Stage 2 or
Stage 3 will be removed and replaced.
13 The Contractor shall carry out hydrostatic test while
pipeline is partially backfilled. 16.2.3.11 Flushing

16.2.3.8 Hydrostatic Testing of Pressure Pipelines 1 Procedure shall be to AWWA C651.

1 The pipeline shall be filled slowly with water from the 2 The Contractor shall provide equipment, gauges,
lowest point. After filling with water, absorbent pipes shall temporary connections needed for flushing. The
be allowed to stand for at least 24 hours before testing to Contractor shall arrange with the Employer to draw water
allow for complete absorption. from existing sources.

2 Entrapped air shall be bled and pressurizing shall 3 The Contractor shall flush mains in sections as
then proceed until the specified test pressure is reached in directed by the Engineer.
the lowest part of the pipeline section under test. Further 4 The Contractor shall use washout valves and fire
quantities of entrapped air shall be bled while the pressure hydrants to drain flushing water.
is being raised. 5 The Contractor shall flush main until effluent is clean
3 Unless otherwise specified, the test pressure shall be and then clean as directed. 1 to 2 times volume of pipe is
equal to 1.5 times the maximum working pressure of the usually required for such flushing.
pipeline as shown on the Drawings or as determined by
the Engineer on Site, but shall in no case exceed 75% of 16.2.3.12 Field Protection and Coating
the factory hydrostatic test pressure. 1 Iron pipes: Polyethylene encasement shall be to
4 The test pressure shall be maintained for one hour by ANSI/AWWA C105, Section 4.1 minimum thickness 200
pumping using a separate test pump. Pumping shall then microns and/or in accordance with the manufacturer's
be stopped for 2 hours, at the end of which time the line instructions.
shall be re-pressurized to the original test pressure and the 2 Patented detachable and flexible joints and flanged
volume of water pumped into the line recorded. connections: The Contractor shall protect metal joints with
5 The pipeline shall be deemed to have failed the test if mastic compound and protective tape in accordance with
visible leaks are detected (regardless of leakage being the manufacturer's instructions and provide a minimum
within the allowable specified limit) or if the volume of overlap of 55%. The Contractor shall press out firmly all
water pumped to restore original test pressure after the folds and irregularities.
period when pumping was stopped exceeds 0.1 liter/day
per km of pipe per mm of pipe diameter for each 3 kg/cm2
of applied pressure for other pipe material.

♦ 16-23 ♦
copy 249
16.2.3.13 Irrigation Control 16.2.3.16 Maintenance Program

1 The 24V electrically operated irrigation solenoid 1 The Contractor shall submit a detailed Maintenance
valves shall be controlled by the irrigation program Program for approval, at least 2 months prior to putting
controller and positioned as shown on the Drawings. the irrigation system into service. This Program shall
2 The controllers shall be interlocked with the pumping include an Operation and Maintenance Organization Chart
system to ensure that the pumps operate after the and all activities incidental thereto.
irrigation valves are open. 2 During the Period of Maintenance, the Contractor
3 The irrigation control electric cables, connecting the shall maintain in proper operating condition all irrigation
irrigation program controller to the solenoid valves shall equipment, pipes, valves, pumping stations, and
be copper PVC insulated and PVC sheathed. The sizes of appurtenances. A record shall be kept of all maintenance
cables shall be commensurate with the distances between and repair activities throughout the Period of Maintenance,
the controller and valves, operating pressure and including the date, location and type of work performed,
manufacturer's recommendations. The cables shall be all repairs and replacement, activities and equipment
approved for ground feeders directly buried and rated for relevant to the Maintenance works. This record shall be
600/1,000V. They shall be clipped to the main water complete and acceptable to the Engineer.
pipework. Multi-runs of cables shall be bunched and tied
together at one m intervals using PVC tape and clipped to 16.2.4 Method of Measurement
the underside of the water pipework at 2 m intervals using
1 Trench excavation and backfilling shall be measured
plastic straps.
and paid for as indicated in Section 2, Clause 2.8.4.
4 To allow full flexibility of the system, each valve shall
2 Pipes shall be measured in linear meters of laid pipe
have a separate control cable such that any valve
of each type, class and size, measured as a straight line
sequence control may be re-adjusted.
between the centers of consecutive coupling sections. The
5 Where required, cable junction boxes shall be fitted. distance between the two centers of the couplings on both
These shall be purpose made boxes fitted with fixed sides of any fitting or valve shall be included as pipe
connectors and suitably labeled. The boxes shall be fitted length. No allowance will be made for cut ends and waste.
with glands and gasketed lid to ensure a fully dust tight
3 No separate measurement will be made for setting
and weatherproof enclosure to IP65.
out laying and bedding in trenches or fixing to structures,
6 Each solenoid valve shall be fitted with fixed thrust blocks, sleeves and ducts, jointing material,
terminals inside an IP65 box and suitable for wiring from couplings of any type, special fittings, connecting to
the valve to be connected. equipment and chambers, testing, lining and painting and
7 All cable cores shall be fitted with marker ferrules at all other items and work to provide a fully functional
each end for ease of identification, and all valves shall be system as specified, all of which is considered to be
fitted with identification labels. subsidiary work , the cost of which is deemed to be
included in the rates stated in the Bill of Quantities for
16.2.3.14 Contract Requirements pipes
1 The Contractor shall prepare working drawings of the 4 Valves shall be measured by the number of each type
irrigation electrical system including all necessary and size installed completed and accepted. No separate
calculations and these shall be submitted in triplicate for measurement shall be made for connections to pipes or
approval prior to commencing the Works on Site. equipment, ancillary fittings, bolts nuts and gaskets, lining
2 The Contractor shall submit, in triplicate, full details and painting, loose keys spindles and hand wheels, valve
of all equipment to be supplied for approval before firm boxes or any other items required for a fully functional
orders for the equipment are placed. unit, all of which is considered to be subsidiary work, the
cost of which is deemed to be included in the rates and
3 The Contractor shall submit "As-Built" drawings of
prices for the relevant items.
the installation on completion.
5 Irrigators, including sprinklers, bubblers and emitters
4 The Contractor shall maintain the installation
(excluding drip emitter distribution tubing) shall be
throughout the Period of Maintenance and shall keep a
measured by the number of each type and size installed,
detailed record of all maintenance and repair action taken.
completed and accepted. The rates stated in the Bill of
16.2.3.15 Documentation Quantities are deemed to include, as appropriate, the
costs stated in item 4, above.
1 On completion of the Works, the Contractor shall
6 Drip emitter distribution tubing shall be measured by
supply record, operation and maintenance data. A single
the linear meter of each size installed, completed and
line diagram of the electrical installation shall be framed
accepted. The rates stated in the Bill of Quantities shall be
and mounted in each pumping station.
deemed to include, as appropriate, the costs stated in item
2 All equipment and circuits shall be properly labeled 3 above.
and reference shall be included on the single line diagram,

♦ 16-24 ♦
copy 249
7 Irrigation program controllers shall be measured by
the number of each type or specification reference
installed. The rates stated in the Bill of Quantities shall be
deemed to include for all items and work required for a
fully operational system, including transport, electrical
installations and civil work.
8 Where spares are ordered by the Engineer, they will
be measured by number and paid for at the rates stated in
the Bill of Quantities for each type, size and class of spare
part authorized by the Engineer, purchased by the
Contractor, handed over, and accepted.

16.2.5 Basis of Payment


1 The amount of completed and accepted work
measured as provided for above, will be paid for at the
unit rates for the various items listed in the Bill of
Quantities, which unit rates shall be full compensation for
supplying, fabricating, connecting and testing, and for
labor, transport, materials, equipment, tools, and other
items necessary for the completion of the Work as
specified in Sub-section 16.2.

16.2.6 Items in the Bill of Quantities


i Pipe (type, class and diameter) lin.m.
ii Valves (type and diameter) nr.
iii Irrigation Program Controller (type) nr.
iv Irrigators (type and size) nr.
v Drip Emitter Distribution Tubing
(type and diameter) lin.m.
vi Spares for Irrigation System (type,
class and size) nr.

♦ 16-25 ♦
copy 249
copy 249
Ref. Title Page No. Ref. Title Page No.
17.1 Scope 17-1 17.3.5 Fertilization Equipment 17-11
17.3.5.1 Fertilizer Injection Equipment 17-11
17.1.1 Description 17-1
17.3.6 Instrumentation and Controls 17-11
17.2 Materials 17-1 17.3.6.1 General 17-11
17.3.6.2 Level Controller Type LC-1 17-11
17.2.1 Metalwork Generally 17-1
17.3.6.3 Pressure Gauges 17-11
17.2.2 Bolts, Inserts and Cushions 17-1
17.3.7 Method of Measurement 17-11
17.2.3 Covers and Frames 17-1
17.3.8 Basis of Payment 17-12
17.2.4 Painting Metalwork 17-1
17.3.9 Items in the Bill of Quantities 17-12
17.2.5 Piping and Appurtenances 17-1
17.2.5.1 General Requirements 17-1 17.4 Construction Requirements 17-12
17.2.5.2 Pipes and Fittings 17-1
17.4.1 Pipe Laying and Jointing 17-12
17.2.5.3 Pipe Accessories 17-2
17.4.2 Valve Installation 17-12
17.2.5.4 Jointing Material 17-2
17.4.3 Pump Installation 17-13
17.2.6 Valves and Accessories 17-3
17.4.4 Method of Measurement and Basis of
17.2.6.1 Gate Valves 17-3
Payment 17-13 
17.2.6.2 Butterfly Valves 17-3
17.2.6.3 Check Valves 17-3
17.2.6.4 Control Valves 17-4
17.2.6.5 Sundries 17-5
17.2.7 Method of Measurement 17-5
17.2.8 Basis of Payment 17-5
17.2.9 Items in the Bill of Quantities 17-5

17.3 Equipment 17-5


17.3.1 General Requirements 17-5
17.3.2 Pumps 17-6
17.3.2.1 Submersible Drainage Pump 17-6
17.3.2.2 Horizontal Pumps 17-7
17.3.2.3 High Pressure Booster Pumping Set
Employing Membrane Tank 17-7
17.3.2.4 High Pressure Booster Pumping Set
Employing Variable Speed Pumps 17-8
17.3.2.5 Duplex Sump Pumps 17-9
17.3.3 Surge Tanks 17-10
17.3.4 Overhead Material Handling
Equipment 17-10
17.3.4.1 Monorail System 17-10

copy 249
copy 249
17.1 Scope 17.2.5 Piping and Appurtenances
17.2.5.1 General Requirements
17.1.1 Description
1 Materials shall be supplied with the manufacturer's
1 This Section describes requirements for the supply
certificate for each delivery, stating that products comply
and installation of the pumping stations, including pipe
with and have been factory tested in accordance with
works, pumps and other equipment, motor, control
specified Standards.
centers, automatic controls, structural steel and other
supports, connections, valves, appurtenances and 2 Unless otherwise specified in the relevant Standard,
ancillary materials, as shown on the Drawings or as products must have legibly cast, stamped or indelibly
ordered by the Engineer. painted on, the following marks, as appropriate:

2 The descriptions of materials, equipment and - Manufacturer's name, initials and identification
construction requirements given in this Section are mark.
generic. Particular requirements for each pumping station - Nominal diameter.
shall be as stated in the Special Specification and on the - Class designation.
Drawings.
- Initials and number of relevant Standard.

17.2 Materials - Length of pipe if shorter than standard length.


- Angle of bends in degrees.
17.2.1 Metalwork Generally - Date of manufacture.

1 Metalwork includes all purpose-made items shown 3 Whenever required by the Engineer, the Contractor
on the Drawings, including stairs, ladders, equipment shall arrange to collect samples of the materials selected
supports and the like. by the Engineer, and transport them to, and have them
tested by an independent Laboratory.
2 Staircases, ladders and safety cages, shall be
fabricated from galvanized mild steel or aluminum alloy 17.2.5.2 Pipes and Fittings
as shown or stated in the Special Specification..
Submersed steel structures shall be fabricated from 1 Ductile iron pressure pipe: flanged pipe shall
stainless steel. conform to BS EN 545, Class K 9.

i. Fittings shall conform to BS EN 545, pressure


17.2.2 Bolts, Inserts and Cushions rating suitable to sustain the system working
1 Masonry expansion bolts approved types and shall pressure.
be installed in accordance with manufacturer's ii. Flanged pipes shall have screwed-on or cast-on
instructions. flanges to sustain the system working pressure.
iii. Flanges shall conform to BS EN 1092 with
2 U-bolts shall be welded to pipes at points of contact
pressure rating suitable for the system working
and bolted to structural angle frame securely fixed to
pressure.
structure.
3 Embedded inserts shall be installed during 2 Factory protection for water supply pipe and fittings:
concreting. i. Coated internally and externally by dipping, or
4 Spring cushions shall be used where a horizontal other method, using hot applied coal tar based
pipe is subject to considerable vertical movement or material to BS 4164 or hot applied bitumen
vibration. based material to BS EN 13000.

3 Factory protection for sewerage pipe and fittings:


17.2.3 Covers and Frames
i. Internally: epoxy lined to ASTM C541. Lining
1 Cast iron covers and frames shall be to BS EN 124
shall be held by centrifugal action.
Grade B, heavy duty rectangular cover and frame, coated,
ii. Externally: coated using hot applied coal tar
locking, solid top.
based material to BS 4164 or cold applied
2 Steel covers and frames shall be fabricated steel bitumen coating to BS 3416.
checkered plate, single seal lift out type, zinc protected,
and capable of supporting a load of 5 tonnes. 4 uPVC pressure pipe: pipe shall conform to BS 3506
Class C with outside diameters to BS ISO 11922-1.
17.2.4 Painting Metalwork i. Fittings shall conform to BS EN 1452, injection
1 All ferrous metal surfaces shall be given one shop molded type joints shall be solvent welded to BS
coat of rust preventative paint primer and two coats of an EN 1452 Part 1.
approved oil base or alkyd paint applied on Site, as
directed by the Engineer.

♦ 17-1 ♦
copy 249
17.2.5.3 Pipe Accessories iii. Center sleeve and followers shall be true circular
sections, free from irregularities, flat spots or
1 Ferrous flexible pipe couplings: types shall be surface defects and formed from steel mill
straight couplings to bridge two plain ended pipes of sections with space between sleeve and follower
same outside diameter and stepped couplings for pipes of designed to provide confinement of gasket.
large diametrical differences. Couplings shall be with iv. Bolts shall be special steel having minimum yield
center register. strength of 2800 kg/cm2 and ultimate strength of
2
i. Material shall be malleable iron conforming to 4200 kg/cm . Bolts shall be track-head design to
BS EN 1562 grade 20/10 or rolled steel to BS 970- prevent turning when nut is drawn up and
060A12 with bolts to BS 970-EN3A and rubber threads shall be rolled with a nominal diameter
rings to BS EN 681. larger than diameter of shank. Manufacturer
ii. Couplings shall be able to take 6 deg. angular must supply information regarding
deflections for sizes up to 600 mm diameter recommended torque to which bolts must be
reducing to 2 deg. for sizes up to 1800 mm tightened.
diameter. v. Gaskets shall be synthetic rubber-base
iii. Couplings shall be factory coated with cold compound with other products to produce
applied bitumen or hot applied coal tar material which will not deteriorate from age,
conforming to BS 3416 or BS 4164 respectively, heat or exposure to air and which is resilient and
thickness 1 mil. able to resist cold flows so that the joint will
remain sealed and tight indefinitely when
2 Ferrous flanged adaptors: material shall be cast iron subjected to shock, vibration, pulsation,
body conforming to BS EN 1561 grade 14 or mild steel temperature and adjustment of connected pipes.
plate to BS 10025 and malleable cast iron flange to BS EN vi. Coupling shall be factory painted internally with
1562 grade 20/10 or rolled steel to BS 970-EN3A and 200 microns coating of epoxy and externally with
rubber rings to BS EN 681. red primer conforming to AWWA 203 Type B
chlorinated rubber solution compatible with
i. Length of adaptor shall be 200 mm for diameters
up to 150 mm, 250 mm for diameters between bitumen, coat tar and general paints.
vii. Couplings shall be assembled on site in
200 and 300 mm and as approved by Engineer
accordance with manufacturer's instructions to
for diameters larger than 300 mm.
ii. Adaptors shall be factory coated with cold ensure permanently tight joints under all
conditions of expansion, contraction, shifting
applied bitumen or hot applied coal tar
and settlement.
conforming to BS 3416 or BS 4164 respectively.

3 Flexible pipe connections: flexible connections shall 5 Dismantling couplings shall have an extensible
connection between pipe sections, and be mounted next
be seamless bronze tubing with annular corrugations
to valves to enable easy dismantling from pipe work or to
covered with high tensile bronze braid suitable for the
system working pressure. permit pipe joining when butterfly valve is removed for
maintenance.
i. Connections shall have screwed ends for pipes
i. Dismantling piece shall be flanged type
50 mm diameter and under and flanged ends for
pipes over 50 mm diameter. composed of two parts, one sliding into the
other, and a free flange to compress a
4 Flexible couplings: gasket sleeve type, shall allow trapezoidal section seal to ensure water
angular deflection and axial movement of two joined pipe tightness. Coupling shall have locking devices to
ends and to maintain permanent, leak-tight joint. provide elements of complete rigidity.
ii. Construction shall be all steel with flanges
i. Components shall comprise one center sleeve,
having rating matching adjoining pipes.
two end followers or flanges, two rubber-
iii. Couplings shall have diameter specifically
compounded wedge-section gaskets and
supplied for and to properly fit type of joined
sufficient draw bolts and nuts to properly
ends of pipes and valves. Coupling shall permit
compress gaskets. Tightening of bolts to draw
tightening of end flanges without risk of
end followers together must compress gaskets in
misalignment. Seal shall be locked after end
recess between center sleeve and followers onto
joints are tightened.
pipe ends to affect positive seal.
ii. Couplings shall have diameter specifically 17.2.5.4 Jointing Material
supplied for and to properly fit type of joined
pipe ends. Center sleeve shall be of adequate 1 Gaskets shall be elastomeric full face 3 mm thick
thickness and whole coupling suitable for joint rings conforming to BS EN 681 with dimensions
minimum working pressures shown on the conforming to BS 3063.
Drawings.

♦ 17-2 ♦
copy 249
2 Rings shall be elastomeric conforming to BS EN 681. i. Cast iron body shall conform to ASTM 126 Class
Dimensions to manufacturer's recommendations to suit B or cast steel body to ASTM 216 Class WCB
type of joint required. depending upon working pressure and with
3 Bolts and nuts shall be ISO metric black hexagon stainless steel seat ring to ASTM A157 C9 non-
conforming to BS 4190, minimum tensile strength 433 corrosion shaft for attachment of weight and
MN/m2, maximum elongation 17%. After fixing, bolt lever and complete non-corrosion shock less
projection shall be maximum 6 mm, minimum 3 mm. chamber to ASTM B 62. Valve shall be tight
seating and seat ring shall be removable.
4 Washers shall be black steel conforming to BS 4320.
Cushion chamber shall be attached to side of
5 Dielectric Joints shall have insulating neoprene or valve body and constructed with a piston
phenol gasket between flanges and phenol or operating in a chamber to permit valve to
polyethylene sleeves and washers between bolts, nuts operate without hammering action. Shock
and flanges. Joints shall be suitable for the operating absorption shall be by dry air and cushion
pressure of the system. chamber shall be arranged for closing speed to
be adjustable to meet service requirements.
17.2.6 Valves and Accessories Valve disc shall be of same material as valve
body and shall be suspended from a stainless
17.2.6.1 Gate Valves
steel type 303 shaft connected to the cushion
1 Cast iron gate valves: type shall conform to BS 5163, chamber through a stuffing box.
inside screw, solid wedge, resilient seated, bolted bonnet, ii. End connections shall be as shown on the
non-rising stem type, suitable for the system working Drawings. Flanged end connections shall
pressure. conform to BS EN 1092.
2 Material of component parts shall be from basic or iii. Valves shall be factory protected with an internal
alternative materials listed in BS 5163. coating of epoxy to a thickness of 120 microns
and external coating of epoxy and nickel plating
3 End connections shall be as shown on the Drawings.
to a thickness of 120 microns.
Flanged end connections shall conform to BS EN 1092.
Plain end connections shall be machined to suit joints 2 Cast iron check valves: type shall conform to BS EN
specified for adjoining pipes. 12334, swing straight pattern, for vertical use and with
4 Casting surfaces shall be given an initial coat of pressure rating suitable for the system working pressure.
protective paint immediately after shot blasting and a i. Material of component parts shall be from basic
second coat on assembly. Protective coating shall be hot materials listed in BS EN 12334 Table 5, under
applied coal tar or cold applied bitumen conforming to BS 'copper alloy faced'.
4164 or BS 3416 respectively. Thickness of coat shall be 1 ii. Seating or facing rings shall be renewable. An
mil. arrow showing direction of flow shall be visible
from outside and cast integral with the valve
17.2.6.2 Butterfly Valves
housing.
1 Cast iron butterfly valves: type shall conform to BS iii. End connections shall be as shown on the
EN 593 with resilient seating suitable for system working Drawings. Flanged end connections shall be to
pressure. Component parts shall be from basic materials BS EN 1092.
listed in BS EN 593 Table 3. iv. Casting surfaces shall be given at factory an
2 For valves 100 mm and smaller, operation shall be by initial coat of protective paint immediately after
lever arm. For sizes above 100 mm and up to 250 mm, that blasting and a second coat on assembly.
operation shall be by hand wheel. For valves 300 mm and Protective coating shall be hot applied coal tar or
larger shall be gear operated. cold applied bitumen to BS 4164 or BS 3416
respectively. Thickness of coat shall be 1 mm.
3 Casting surfaces shall be given an initial coat of
protective paint immediately after shot blasting and a 3 Silent check valves: type shall be non-slam, spring
second coat on assembly. Protective coating shall be hot loaded and suitable for installation in any position.
applied coal tar or cold applied bitumen conforming to BS
i. Valves 50 mm diameter and under shall be
4164 or BS 3416 respectively. Thickness of coat shall be 25
screwed, with bronze body, seat and disc, 18-8
microns.
stainless steel spring, with pressure rating
17.2.6.3 Check Valves suitable for the system working pressure.
ii. Valves over 50 mm diameter shall be flanged,
1 Cushioned check valves: type shall be cushioned with cast iron body, bronze seat and disc, 18-8
type, counter-weighted metal seated check with attached stainless steel spring, with pressure rating
cushion chamber to permit valve to close without slam or suitable for the system working pressure.
bang. Valve shall have a pressure rating suitable for the iii. Valves shall have straight guided disc with two-
system working pressure. point bearing. Wearing parts including discs,

♦ 17-3 ♦
copy 249
seats and other guide bushings shall be 2 Surge control valves: type shall be straight pattern,
replaceable. specifically designed to prevent excessive surge pressures
iv. Valves shall have flow area in excess of pipe area in event of power failure. Valve shall have pilots to cause
for minimum pressure drop. valve to open on either low pressure or high pressure
wave. Under normal operation, valve acts as relief valve
17.2.6.4 Control Valves which can be set to open at any pressure above normal
1 General: pump control valves, and surge control operating pressure. At the same time, valve shall open at
valves, shall be automatic, hydraulically operated, pilot any set pressure below its normal operating pressure.
controlled, piston actuated, single seated, globe or angle i. Function shall be such that on power failure,
pattern as shown on the Drawings, consisting of valve valve opens on initial down-surge in pressure (if
body, piston assembly and cover with the piston assembly this surge is not already controlled by surge
as the only moving part. Valves shall be sized for pressure chamber) and remains open until high pressure
rating shown on the Drawings and shall be the product of wave returns and passes through valve without
a reputable, approved manufacturer. generating a large up-surge in pressure. After
i. Valve body shall be cast steel to ASTM A216 high pressure wave has passed, valve closes
WCB standard, flanged, with flange rating as slowly in 2 minutes to prevent further pressure
shown on the Drawings and containing a surges. Valve also opens on high pressure
removable seat insert. Main valve trim shall be unless surge has been attenuated by surge
bronze to ASTM B 61. chambers.
ii. Piston assembly shall be fully guided on its ii. Operation shall be on differential piston principle
outside diameter by long stroke stationary V- such that area on underside of piston is no less
ports downstream of seating surface to minimize than pipe area, and area on upper surface of
consequence of throttling. Piston shall be piston is of greater area. Valve shall operate in
bronze to ASTM B 62 with seal of stainless steel any position without assistance of springs.
to AISI 140. iii. Valve size shall be as shown on the drawings and
iii. Repairs shall be possible without removing valve pressure rating shall be suitable for system
from line. Valve shall have no external packing operating and anticipated maximum surge
glands or stuffing boxes. pressure. Valve shall be of extra heavy
iv. Valve shall be supplied complete with factory construction throughout with body of cast steel
fitted pilot valves, small interconnecting piping to ASTM A216 WCB and flanges conforming to
and accessories to perform required functions. ANSI standards. Internal trim shall be bronze to
Pilot control system shall be stainless steel to ASTM B 62. Piston shall be guided on its outside
AISI type 303. diameter by long-stroke stationary V-ports
v. Factory protection shall be internal coating of downstream of seating surface to minimize
epoxy to a thickness of 120 microns and external consequence of throttling. Piston shall be
coating of epoxy and nickel plating to a thickness bronze and pilots stainless steel. Valve shall
of 120 microns. contain rubber removable seat insert.
vi. Provide manufacturer with necessary and iv. Repairs shall be possible without removing valve
pertinent data for setting control valves, at from line. Valve shall have no external packing
factory, to required settings to suit individual glands or stuffing boxes.
conditions of different pumping stations. v. Pilots and accessories shall include the following:
vii. Prior to shipping valves from factory, submit - Low pressure pilot.
shop drawings for approval giving factory - Pressure relief pilot.
settings, range of adjustments, control diagram,
- Flow limiting device.
wiring diagram, size, arrangement and other
pertinent data necessary for approval by the - Needle valves.
Engineer of every control valve in the system. - Strainer.
Submit with the shop drawings detailed - Check valve.
instructions for field adjustment and setting,
- Valve position indicator.
installation, start-up and proper operation.
viii. Each control valve shall be tested individually at - Pipe plug for pressure gauge.
factory and certified test results submitted. - Shut-off cocks.
ix. Provide the services of a specialized factory - Interconnecting copper tubing and unions.
technician or engineer to set, test, adjust and
- Pilot mounting bracket.
commission the control valves as specified.
x. Control valve pressure rating shall be suitable to - Other accessories recommended by
system working pressure. manufacturer.

♦ 17-4 ♦
copy 249
vi Factory protection shall be complete epoxy (iii) uPVC pressure pipe
coating for protection against corrosion. (state size) (lin.m.)

17.2.6.5 Sundries (iv) Gate Valves (state


size) (nr.)
1 Hose Bibb: shall be a chrome plated metal bibcock,
15 mm male back inlet connection and 15 mm male, hose (v) Butterfly Valves (state
thread outlet, with 15 mm chrome plated metal hose size) (nr.)
coupling female threaded. (vi) Check Valves (state
size) (nr.)
17.2.7 Method of Measurement
(vii) Silent Type Check
1 Metalwork including but not limited to staircases, Valves (state size) (nr.)
ladders, and safety cages; bolts, inserts and cushions;
covers and frames; shall each be measured by number of (viii) Control Valves (state
each item installed. Rates shall include for factory and on- size) (nr.)
site tests, fixings, preparing, priming and painting.
(ix) Surge Control Valves
2 Pipes shall be measured by linear meter of each type (state size) (nr.)
and size of pipe. Measurement shall be of the center line
of pipes (overall), couplings, fittings and branches. Rates (x) Cushioned Type Check
for pipes shall be deemed to include all related pipe work, Valves (state size) (nr.)
including but not necessarily limited to:
- Flexible pipe couplings adaptors and
connections. 17.3 Equipment
- Header pipes and dismantling couplings,
- Purpose made pipes and purpose made fittings.
17.3.1 General Requirements
- Everything necessary for jointing.
- Bends, tees, joints, unions, flanges, and pipe 1 Materials and products: materials for pumps shall be
fittings including cutting and jointing pipe to suitable for pump operating conditions and adequate for
fittings, valves and equipment. total heads to which pumps are subjected. Corrosion
- Pipe supports and support assemblies, hangers, resistant materials shall be used. Assembly arrangements
clips, anchors and guides. shall include isolation of dissimilar metals to avoid
- Wrapping and waterproofing of underground galvanic interaction.
and or exposed pipes. 2 Pumps shall have factory plugged connections for
- Pipe sleeves and packing. casing vent, drain and suction and discharge pressure
- Pipe cleaning priming and painting. gauges.
- All other pipe and pipe work ancillaries’
3 Impellers and rotating assemblies shall be statically
necessary required or reasonably inferred.
and dynamically balanced at factory.
3 Valves shall be measured by the number of each 4 Packing rings shall be installed in alternate layers
type installed. Rates shall be deemed to include for factory staggered 90 degrees. Packing shall be tightened for seal
and on-site test, tests at independent laboratories, all while permitting prescribed amount of leakage for
fixing and jointing accessories. lubrication.
5 Pumps shall have shaft packing or mechanical seals
17.2.8 Basis of Payment compatible with pump design and nature of liquid
1 The amount of completed and accepted work as pumped in accordance with manufacturer's
provided above shall be paid for at the unit rates for the recommendations or as specified.
items describes in the Bill of Quantities and shall include 6 Pump operating point of specified flow and head
for furnishing all materials, installation, civil, mechanical, shall fall near the point of maximum efficiency as obtained
electrical, piping and miscellaneous works, testing, from manufacturer's published data.
commissioning, and putting into operation, maintenance
7 Horsepower rating of pump drive motor shall ensure
and all labor, transport, equipment, tools, supplies and
non-overloading of motor throughout capacity range of
other items necessary for the proper completion of the
pump for impeller diameter selected.
work as specified.
8 Electric motors shall be suitable for available electric
17.2.9 Items in the Bill of Quantities current voltage and frequency. Motor speeds shall not
exceed 1450 rpm for 50 Hz. Motors shall be designed to
(i) Metal works (Type) Lump Sum operate in 50oC ambient temperature.

(ii) Ductile Iron pressure pipe


(state size) (lin.m.)

♦ 17-5 ♦
copy 249
9 Shop drawings: The Contractor submit shop 17.3.2 Pumps
drawings for each pump for approval, prior to shipment
from factory, as follows: 17.3.2.1 Submersible Drainage Pump

- Certified performance curves showing job 1 Non-clog, centrifugal, submersible, with guide-rails,
number, customer and customer order number, quick-disconnect type, suitable for drainage water
pump designation number shown on the application and designed to permit quick and easy ground
drawings, date of manufacture, model number, level removal of pump from pit for service or inspection
pump size, impeller diameter, impeller type, without disconnecting or disturbing discharge piping and
maximum impeller diameter pump can electrical connection. Pump design shall permit pump to
accommodate, rpm, noise data, flow-head be automatically connected to discharge elbow in a tight
characteristic curve, consumed horsepower and leak-proof manner without axial or lateral movement
curve and pump efficiency curve. and without further adjustment. Pump shall be designed
- Pump cross-sectional drawings showing major to withstand dry running.
components with parts numbers and parts list. 2 Each pump shall be supplied complete with the
- Pump outline dimensional drawing showing following:
overall dimensions, location of foundation bolt - Close-coupled submersible vertical electric
holes and sizes, location and rating of suction motor.
and discharge nozzles. - Required length of durable multi-conductor
- Recommended list of spare parts, where not waterproof electric cable.
specified elsewhere. - Special quick disconnect flange elbow with
- Installation, operation and maintenance integral bracket for floor mounting and lower
instruction manual. guide rail holder.
- Details and wiring diagrams of factory supplied - Required length of stainless steel guide rails.
pump controllers, starters, controls or other - Upper guide rail bracket.
electrical device or accessory.
- Rail guided lifting assembly.
- Special instructions for field installation and
- Lifting yoke and stainless steel chain for raising
connection of factory or field supplied electrical
and lowering pump.
device, control or accessory.
3 Casing shall be cast iron volute, to ASTM A48 Class
10 Shop tests: The Contractor shall submit for each
35B or BS EN 1561 Grade 260, horizontally split.
pump, certified results of shop tests made by
Passageways shall permit smooth flow of liquid served
manufacturer, prior to shipment from factory, as follows:
and shall be free from sharp turns and projections. Pump
- Performance test throughout capacity range of volute bottom and impeller shall have easily replaceable
pump with specified design operating point stainless steel wear rings.
clearly indicated on pump flow-head
4 Impeller shall be cast iron to ASTM A48 Class 35B or
characteristic curve.
BS EN 1561 Grade 260, single channel type running in
- Hydrostatic pressure test to 1-1/2 times shut-off volute, capable of passing solids with 75mm diam.,
pressure of pump. suitable for service required, non-clog and dynamically
11 Pump test report shall include the following balanced for smooth operation. Impeller parts and
information: internal parts including studs, nuts and screws shall be
- Pump data: pump designation number shown on stainless steel.
the Drawings, model number, serial number, 5 Mechanical seal system shall consist of two
customer order number, flow, suction and independent seal assemblies and of materials suitable for
discharge pressures, shut-off pressure, rpm and the application.
brake horsepower. 6 Motor shall have Class F insulation, designed for use
- Motor data: make, model number, serial number, in hazardous locations, suitable for continuous duty, with
horsepower rating, rpm, voltage, phase, horsepower to ensure non-overloading of motor
frequency, class of insulation, allowable throughout capacity range of pump. Motor shall have cast
temperature rise, full load amperes, locked rotor iron frame, stainless steel shaft, double mechanical shaft
amperes and actual voltage and amperes at all face seals of carbon/tungsten carbide, built-in thermal
test points. overload protection and moisture sensing probes. Motors
- Starter data: make, model number, size, heater shall be dimensioned to be sufficiently cooled by
sizes, ampere rating, line voltage, control voltage surrounding environment or pumped media.
and frequency. 7 Pump and motor bearings shall be heavy-duty,
permanently lubricated and sealed ball bearing type, not
requiring re-lubrication on site.

♦ 17-6 ♦
copy 249
8 Pump shall be supplied from factory with required i. Casing: Cast iron, with integral feet or other
number of level regulators of the pear-shaped type, with means on volute to support weight of casing and
internal coated type switch and weighted to be vertical in attached piping.
air and horizontal in water without floating. Regulator ii. Impeller: ASTM A48 Class No 25 A or higher cast
shall have three contacts to make it suitable for either iron, statically and dynamically balanced, closed,
starting or stopping motors. Regulators shall have single suction, keyed to shaft, and secured by
necessary lengths of three-core electric cable and both locking cap screw.
regulator case and cable insulation shall be non-corrosive iii. Wear Rings: Replaceable type with material
material resistant to and for application in liquid served. suitable for the application.
Level regulators shall be supplied from factory with iv. Shaft and Sleeve: High grade stainless steel shaft
special cable holder bracket designed to guide and and rated for minimum 1.5 times the working
support power and level regulator cable. Level regulators pressure, and high-grade stainless steel sleeve.
shall start and stop pumps at pre-set levels through the v. Seals: Mechanical, with carbon-steel rotating
control panel. Levels shall be shown on the Drawings. In ring, stainless-steel spring, ceramic seat, and
the event of a fault in one pump, control panel shall switch flexible bellows and gasket.
off defective pump give an alarm signal and start stand by vi. Coupling: Flexible-spacer type, capable of
pump. Starting sequence of pumps shall be automatically absorbing torsion vibration and shaft
alternated through the control panel. misalignment; with flange and sleeve section
9 Pump motor control panel shall be weatherproof and that can be disassembled and removed without
suitable for outdoor installation, minimum IP 55 enclosure removing pump or motor.
protection, with lockable cover and completely assembled, vii. Coupling Guard: Galvanized steel, removable,
wired and tested at factory ready for installation with and attached to mounting frame.
simple external electrical connections. Panel shall contain, viii. Mounting Frame: Factory coated welded-steel
but is not necessary limited to, the following: frame and cross members, factory fabricated
from ASTM A36/A36M channels and angles.
- Motor starters.
Fabricate for mounting pump casing, coupling
- Over-riding starter buttons. guard, and motor. Field-drill motor-mounting
- Indicating lamps for pump in operation. holes for field-installed motors.
- Reset buttons for overload relays.
6 Motor: Secured to mounting frame, with adjustable
- Electric alternator for required number of pumps.
alignment. Motors: IP 55, squirrel cage induction type, and
- 24 V control circuit transformer. fan cooled. Cooling fans shall be bi-directional so that
- Running hour meters to record time each pump cooling is independent of direction of rotation and shall be
is in operation. fabricated from non-rusting and non-sparking material.
- Accessories required for automatic operation of 7 Motors shall have high efficiency and high power
pumps. factor at full load. All motors shall meet or exceed the
- Auxiliary volt free contacts for remote minimum efficiencies stated in the highest level in the EU
monitoring and alarms. agreement of the LV motors (EFF1/EFF2). All motors shall
bear the IEC reference and CE marking on the motor
- Water level meter for water level in well.
nameplate.
10 Impeller and pump outer casing shall be factory 8 All motors shall be suitable for continuous heavy-
protected by shot blasting and priming with epoxy duty application with a minimum service factor of 1.25;
suitable for duty. Casing shall then be given two coats of alternatively, the next larger IEC motor size shall be
epoxy resin, to 125 microns thickness each coat. selected.

17.3.2.2 Horizontal Pumps 9 Motors shall be full voltage direct-on-line start.


10 Motor Insulation shall be class F, non-hygroscopic,
1 Description: Horizontal, base-mounted, centrifugal,
Class H varnish.
flexible-coupled, rated for minimum 1.5 times the working
pressure. 11 Motor temperature rise shall be limited to 70°C
above the maximum ambient temperature of 50°C, as
2 Pumps shall be end suction, horizontal multi-stage,
measured by resistance
or split case pumps, type as required by the Drawings.
3 End suction pumps: shall be back-pull-out, radial split 17.3.2.3 High Pressure Booster Pumping Set Employing
case design. Membrane Tank
4 Split case pumps: shall be of axially split casing
1 Packaged type, comprising multiple close-coupled
design.
pumps, membrane tank, interconnecting pipe work, valves,
5 Construction Features pressure switches and electrical control panel all
completely assembled on steel frame, piped, wired and
delivered as a complete packaged unit ready for

♦ 17-7 ♦
copy 249
installation and operation with simple piping and electrical - Mounting and Wiring: Factory installed and
connections. One of the pumps shall be stand-by pump connected as an integral part of unit.
2 Pumps shall be close-coupled, centrifugal, single or - Enclosure: IP 55.
multiple stage type, horizontally or vertically mounted and - Motor Controller: Full-voltage, combination-
driven by electric motor at specified rpm. Pumps shall magnetic type with under-voltage release feature,
have self-adjusting mechanical seals with carbon rotating motor-circuit-protector-type, and short-circuit
face running against stationary ceramic seat. Pumps shall protective device.
have close-grain cast iron or stainless steel casing and
- Motor Overload Protection: Overload relay in
mechanical seal housing, gunmetal, cast bronze, or
each phase.
stainless steel impeller and stainless steel shaft.
- Starting Devices: Hand-off-automatic selector
3 When the duty pumps are running together, they
switch in cover of control panel, plus pilot device
shall supply the maximum demand specified, with the
for automatic control.
remaining pump acting as stand-by. Under low demand
conditions one pump shall supply sufficient water, with - Multi-pump, Sequence (Lead-Lag-Lag) Starter:
remaining duty pumps acting as back up. Controls shall Switches lead pump to one lag main pump and
automatically start second duty pump when one pump is to multi-pump operation.
unable to supply demand and shall cut in stand-by pump - Instrumentation: Unit suction and discharge
on failure of any of the duty pumps. pressure gauges.
4 Motor shall be totally enclosed, fan cooled, drip proof, - Alarm Signal Device: Sounds alarm when
squirrel cage type, weatherproofed construction for backup pumps are operation.
operation in specified ambient temperatures. Motor - Pump Duty Alternation Device: Switches the lead
horsepower shall ensure non-overloading of motor pump.
throughout capacity range of pump.
10 Mounting frame shall be mild steel hollow section
5 Membrane tank shall be welded mild steel plate, members reinforced against deflection and with bolt holes.
suitable for system operating pressure constructed in Steel surfaces shall be factory protected by shot blasting,
accordance with BS EN 286-1, Part 1, with cylindrical shell zinc sprayed to 75 microns thickness and given one coat of
and convex dished ends. Membrane tank shall contain priming paint. External steelwork shall have one
removable rubber bag and shall be pressurized with air at undercoat and one top coat chlorinated rubber paint of
factory to correct system operating pressure to provide approved color to 75 microns thickness each coat. Internal
sealed air cushion eliminating use of air compressor. steelwork shall have two coats black bitumastic paint, 125
Tank shall have air valve of type permitting recharging on microns thickness each coat and suitable for service.
site by small hand compressor or simple car type pump.
Rubber bag shall be guaranteed suitable for intended use 17.3.2.4 High Pressure Booster Pumping Set Employing
without deterioration and without bursting. Variable Speed Pumps
6 Membrane tank shall be complete with factory
1 Packaged type, comprising multiple close-coupled
fabricated steel legs welded to tank before testing, air-
pumps, membrane tank, interconnecting pipe work, valves,
charges connection, pressure relief valve and pressure
pressure switches and electrical control panel all
gauges.
completely assembled on steel frame, piped, wired and
7 Pumping set shall be automatically controlled by delivered as a complete packaged unit ready for
pressure switches to start pumps on fall of pressure in installation and operation with simple piping and electrical
tank and stop pumps on rise of pressure. connections. One of the pumps shall be stand-by pump
8 Interconnecting pipe work shall be galvanized steel 2 Pumps shall be close-coupled, centrifugal, single or
pipe and fittings to ASTM A53 schedule 40. Valves shall be multiple stage type, horizontally or vertically mounted and
threaded, with bronze body and trim and have a pressure driven by electric motor at specified rpm. Pumps shall
rating suitable for system working pressure. Each pump have self-adjusting mechanical seals with carbon rotating
shall have swing type, non-return valve at discharge, face running against stationary ceramic seat. Pumps shall
adjustable pilot-operated pressure regulating value at have close-grain cast iron or stainless steel casing and
discharge, adjustable individual suction and discharge mechanical seal housing, gunmetal, cast bronze, or
shut off valves, Discharge manifold shall have pressure stainless steel impeller and stainless steel shaft.
switches, pressure gauge and vent cock.
3 When the duty pumps are running together, they
9 Control panel shall be heavy gauge mild steel sheet shall supply the maximum demand specified, with the
finished with stove hammer paint internally and externally, remaining pump acting as stand-by. Under low demand
with minimum IP 55 enclosure rating. Control panel shall conditions one pump shall supply sufficient water, with
be automatic, with load control and protection function remaining duty pumps acting as back up. Controls shall
and shall contain, but shall not be necessarily limited to, automatically start second duty pump when one pump is
the following:

♦ 17-8 ♦
copy 249
unable to supply demand and shall cut in stand-by pump plus pilot device for automatic control. Retain
on failure of any of the duty pumps. one of first two subparagraphs below.
4 Motors: Variable speed, with pre-greased, a. For duplex boosters, Automatic, Alternating
permanently shielded, ball-type bearings. Select motors Starter: Switches lead pump to lag main
that will not overload through full range of pump pump and to two-pump operation.
performance curve.
b. For triplex or multiplex boosters, Sequence
5 Membrane tank shall be welded mild steel plate,
(Lead-Lag-Lag) Starter: Switches lead pump
suitable for system operating pressure constructed in
to one lag main pump and to three-pump
accordance with BS EN 286-1, Part 1, with cylindrical shell
operation.
and convex dished ends. Membrane tank shall contain
removable rubber bag and shall be pressurized with air at vi. Pump Operation and Sequencing: Pressure-
factory to correct system operating pressure to provide sensing method.
sealed air cushion eliminating use of air compressor.
Tank shall have air valve of type permitting recharging on a. Time Delay: Controls pump on-off
site by small hand compressor or simple car type pump. operation; adjustable from 1 to 300 seconds.
Rubber bag shall be guaranteed suitable for intended use vii. VFC: Voltage-source, pulse-width, modulating-
without deterioration and without bursting. frequency converter for each pump.
6 Membrane tank shall be complete with factory
viii. Manual Bypass: Magnetic contactor arranged to
fabricated steel legs welded to tank before testing, air-
transfer to constant-speed operation upon VFC
charges connection, pressure relief valve and pressure
failure.
gauges.
7 Pumping set shall be automatically controlled by ix. Instrumentation: Suction and discharge pressure
pressure switches to start pumps on fall of pressure in gages.
tank and stop pumps on rise of pressure. x. Lights: Running light for each pump.
8 Interconnecting pipe work shall be galvanized steel
xi. Alarm Signal Device: Sounds alarm when
pipe and fittings to ASTM A53 schedule 40. Valves shall be
backup pumps are operating.
threaded, with bronze body and trim and having a
pressure rating suitable for system working pressure. a. Time Delay: Controls alarm operation;
Each pump shall have swing type, non-return valve at adjustable from 1 to 300 seconds, with
discharge, adjustable pilot-operated pressure regulating manual reset.
value at discharge, adjustable, individual suction and
discharge shut off valves, Discharge manifold shall have xii. Thermal-bleed cutoff.
pressure switches, pressure gauge and vent cock. xiii. Low-suction-pressure, Water-storage-tank, low-
9 Control Panel: Factory installed and connected as an level cutout.
integral part of booster pump; automatic for multiple-
10 Where shown on the Drawings or Schedules, motor
pump, variable-speed operation, with load control and
control panels shall any or all of the following:
protection functions.
i. High-suction-pressure cutout.
i. Control Logic: Solid-state system with
transducers, programmable microprocessor, ii. Low-discharge-pressure cutout.
VFC, and other devices in controller. Install VFC
iii. High-discharge-pressure cutout.
for pump motors larger than 25 Hp in separate
panel; same type as motor control panel 17.3.2.5 Duplex Sump Pumps
enclosure.
1 Components shall comprise two pumps, float switch
ii. Motor Controller: NEMA ICS 2, variable- assembly with mechanical alternator, high water alarm
frequency, solid-state type. Some manufacturers and electric control panel.
may offer low-voltage controls. Revise "Control
2 Pump shall be vertical, centrifugal, wet pit type, self
Voltage" Subparagraph below if required.
lubricating, to rest directly on sump floor, with vertical
motor connected to pump with steel tubular shaft housing.
a. Control Voltage: 220 V AC, with integral
control-power transformer. 3 Pump shall be supplied complete with the following,
factory assembled to form a self-contained, compact unit
iii. Enclosure: NEMA 250. ready for operation with simple discharge piping and
iv. Motor Overload Protection: Overload relay in electrical connections:
each phase. - Cast iron combination base and suction strainer.

v. Starting Devices: Hand-off automatic selector - Cast iron motor head box.
switch for each pump in cover of control panel,

♦ 17-9 ♦
copy 249
- Cast iron motor adaptor flange designed to carry - Electric alternator between duty and stand-by.
motor and float switch. - High and low level alarms.
- Steel tubular shaft housing. - 24 V control circuit transformer.
- Electric motor. - Manual reset fail-safe alarm circuits.
- Unsinkable plastic float and stainless steel rod. - Pilot lights.
- Adjustable stops and counter-weight. - Moisture sensing relay.
4 Casing and cover shall be close grained cast iron - Loss of power alarm unit.
volute of uniform quality, free from blow-holes, porosity
- Auxiliary, volt free, contracts for remote
shrinkage defects, cracks and other defects.
monitoring and alarms.
5 Impeller shall be cast iron volute to ASTM A 48 Class
14 Cables, wiring and conduits shall be provided as
35B or BS EN 1561 grade 260, heavy open non-clog type
necessary for connecting control panel to pumps, float
design, statically and dynamically balanced, over hung,
switch assembly and alarm unit. Make connection as per
single suction, keyed and securely locked to stainless steel
manufacturer's wiring diagram.
shaft of size to transmit required power without distortion
or vibration. Pump shaft shall be directly connected to 15 Impeller and pump outer casing shall be factory
motor shaft through a flexible coupling. Motor adaptor protected by shot blasting and priming with suitable
flange shall be machined to close tolerances to ensure epoxy. Casing shall then be given two coats of epoxy resin,
permanent alignment between pump and motor. to 125 microns thickness each coat.

6 Pump shall be fitted at drive end of shaft with grease


packed, deep groove, self-aligning, radial thrust ball
17.3.3 Surge Tanks
bearing, mounted in dust-proof housing machined in 1 The membrane tank shall contain an interchangeable
motor support base and having moisture proof seal bladder and be pre-charged with air at the factory to
protection from sump vapors. Pump shall also have correct pressure to provide a sealed air cushion
bottom column bearing of renewable water-lubricated eliminating use of an air compressor. Tank shall have air
type. valve to permit recharging on site by small compressor.
7 Motor shall be vertical, totally enclosed, squirrel cage, Bladder shall be guaranteed by manufacturer for use on
induction type, permanently lubricated with sealed ball pumped fluid without deterioration with time, and without
bearings. Motor horsepower shall ensure non-overloading bursting. Tank shall be welded mild steel plate for
of motor throughout capacity range of pump. Motor shall operating pressure of 16, 25, and 40 bars (as shown on
be suitable for continuous operation in ambient drawings), with cylindrical shell and convex dished ends,
temperature specified. shot blasted and painted internally with bitumastic paint
and externally with zinc primer and hammer enamel paint.
8 Operation shall be automatic, float switch operated,
alternating start-up sequence. One pump shall be 2 The tank shall be horizontally installed and shall be
intended for normal operation, while the other for backup. supplied from factory complete with the following
Standby pump shall start if abnormal flow exceeds one accessories:
pump capacity and in the event of a fault in other pump.
i. Access manholes.
Fault condition in a pump or if flow exceeds pumping
capacity shall actuate an alarm. ii. Hoisting hooks.
9 Float switches shall be base mounted, contact type, iii. Inflator valve.
enclosed in drip-proof and splash-proof enclosure.
iv. Flange and counter flange for fixing of the
10 Starters shall be totally enclosed, wall mounted,
bladder.
direct on-line type with no-volt and overload protection
and suitable for automatic operation. v. Flanged water connection.
11 Control panel shall be wall mounted, watertight, vi. Pressure gauge.
completely assembled, wired and tested at the factory and
ready for installation with simple connections. vii. Level gauge system.
12 Control panel shall have minimum IP 55 enclosure.
17.3.4 Overhead Material Handling
13 Control panel shall contain all necessary accessories
Equipment
for duplex pump operation, including, but not necessarily
limited to the following: 17.3.4.1 Monorail System
- Main incoming isolating switch.
1 System shall comprise a carrier with electric hoist
- Magnetic trip circuit-breakers. attached, for picking up the load at one point and
- Magnetic starters. transporting it to destination on overhead tracking system
without re-handling.
- Overload relays with thermal unit
- Hand- off automatic selector switches.

♦ 17-10 ♦
copy 249
2 Suspension system shall comprise hanger rod as to allow the required quantity of fertilizer to be
assemblies with ball-and-socket or T-type joints, flexibly dissolved and dispersed in 45 minutes with normal group
constructed so that carrier wheels always contact rail on operation.
each side. Rail shall be sufficiently thick to carry load and 2 All parts in contact with fertilizer shall be in corrosion
provide for wear with safety factor of 5. resistant material.
3 Hoist and trolley shall be of low head- room 3 The Contractor shall provide spares suitable for a
construction to permit maximum lifting and shall period of 5 years pumping operations in accordance with
comprise standard assemblies with interchangeable parts. the manufacturer’s recommendations.
Hoist ropes shall be retained in position in drum grooves
by encircling spring-loaded steel rope bands and high 17.3.6 Instrumentation and Controls
grade gunmetal rope guards. Rotating shafts shall be
splined to receive gears and mounted on ball journals. 17.3.6.1 General
Gears shall be protected by readily removable sheet steel
1 The Contractor shall submit complete control and
covers.
wiring diagrams for control systems for approval showing
4 System shall be medium duty with 5 tonnes lifting control instruments, auxiliaries and accessories.
capacity, 10 meters standard lift and lifting speed 8 meters
2 The Contractor shall provide accessories and
per minute with 10% creep speed.
appurtenances as necessary and appropriate to
5 Trolley hoist shall be electrically operated, self- accomplish intended control functions, irrespective of
aligning, low head-room type comprising hoist and trolley whether or not shown or specified, including switches,
in compact unit designed to run on lower flange of I-beam relays, transformers etc.
with travelling speed of trolley 20 meters per minute.
3 The Contractor shall provide control wiring and
6 Lifting mechanism shall comprise shock resistant conduits as necessary and appropriate for complete
steel frame, with suspension members and covers, gear control systems, to the requirements of this Section as
drive system, positive action load brake, lifetime directed by the Engineer.
lubricated and sealed bearings and drop forged alloy
4 Indicating instruments including pressure gauges
swivelling and rocking load safety hook.
and level indicators shall each have a range such that
7 Trolley shall be electrically driven, with size to fit I- normal readings are indicated in middle of instrument
beam girder and with alloy cast iron wheels, heat treated range.
and machined to uniform diameter, mounted on sealed
5 Pressure gauges shall have a brass cock on inlet.
heavy duty precision-machined anti-friction roller or ball
bearings lubricated for life. Trolley brakes shall have 50% 17.3.6.2 Level Controller Type LC-1
torque.
1 Controller shall be electrode type, using semi-
8 Hoist motion brakes shall stop motion under all
conductor technology, designed to be installed in wet
service and weather conditions, with lining material
sump, to start and stop pump or to give high or low level
producing constant coefficient of friction, not wearing
alarm signal.
rapidly and not scoring. Brakes shall have 150% torque of
nameplate rating of hoist motor. 2 Components shall include rigid electrode and control
head with power supply/relay circuit board and heavy
9 Controls shall be selective push-button control for
duty housing.
floor operation with emergency stop button, and designed
to NEMA Standards. 17.3.6.3 Pressure Gauges
10 Electric motors shall be totally enclosed, fan cooled,
1 Pressure gauges shall be Bourdon tube type,
squirrel cage type, weatherproof and tropicalized (IP56
minimum 100mm dial diameter, with flangeless back and
Class F insulation) for operation in ambient temperatures
12 mm male threaded bottom connection, and graduated
up to 50 deg. C.
in bars with 0.1 bar divisions.
11 Steel surfaces shall be factory painted with one coat
2 Components shall include black finished cast
etch primer and one coat gloss finish paint.
aluminium case; threaded black epoxy cast aluminium
12 Safe working load shall be clearly marked in large ring with gasketed flash face, type 316 stainless steel
print on unit in English and Arabic. spring tube, stainless steel precision movement and
micrometer adjustment on needle.
17.3.5 Fertilization Equipment
17.3.5.1 Fertilizer Injection Equipment 17.3.7 Method of Measurement
1 Equipment and ancillaries are given separately and
1 Injector shall be of the Venturi type bypassed on the
measured by the number of each type installed. Rates for
main pipeline. The system shall consist of a fertilizer tank
equipment and ancillaries are deemed to include, but not
with a minimum capacity of 1000 kg of dry chemical
limited to :
fertilizer, having a hinged pressure-tight cover. The
connections from the tank to the pipeline shall be sized so - Factory assembled components and controls.

♦ 17-11 ♦
copy 249
- Loose equipment supplied by the manufacturer. 17.4 Construction Requirements
- Electrical connection and wiring.
- Supports and fixation including supporting steel
17.4.1 Pipe Laying and Jointing
work or concrete work. 1 General: examine materials carefully for damage.
- Valves, strainers, flexible connections, controls, Test for soundness in accordance with manufacturer's
instruments and fittings as shown on the instructions before laying the pipe.
Drawings. 2 The Contractor shall examine materials to ensure
- Loose keys, tools and spare parts as specified. coating or lining and outer coating or sheathing is
undamaged. If damaged, make good or dispose of and
- Factory and on-site tests and test reports
replace, as directed.
- Shop drawings, diagrams, instruction and
3 The Contractor shall remove dirt and foreign matter
maintenance manuals
from pipe before lowering.
2 Monorail system shall be measured as a Lump Sum,
4 The Contractor shall clear construction debris from
complete, installed, tested, and accepted.
inside of pipe before making joint.
3 Fertilizer injection system shall be measured as a
5 When pipe lying is not in progress, the Contractor
Lump Sum, complete, installed, tested, and accepted.
shall close open ends of pipes with properly fitted
4 Electrical work in connection with pumping stations temporary wooden plugs or standard caps as directed
is given separately and measured as a Lump Sum,
6 Jointing: manufacturer’s instructions shall be
furnished, installed, tested and accepted and is deemed to
followed regarding cleanliness of joint surfaces, lubricant
include all electrical work shown or the Drawings,
used, correct location of components, provision of correct
described in the Specification or reasonably to be implied
gaps for flexible joints etc.
as necessary for the proper execution of the work.
7 Flexible joints shall not be deflected beyond
17.3.8 Basis of Payment maximum permissible angles given by manufacturer
and/or relevant standard.
1 The amount of completed and accepted work as
8 For patent detachable and flexible joints strictly the
provided above shall be paid for at the unit prices for the
Contractor shall comply with special instructions issued by
items describes in the Bill of Quantities and shall include
manufacturers of proprietary joints when laying and
for furnishing all materials, installation, civil, mechanical,
jointing.
electrical, piping and miscellaneous works, testing,
commissioning, and putting into operation, maintenance 9 The Contractor shall joint differing pipe and fitting
and all labor, equipment, tools, supplies and other items material with adaptors as recommended by pipe
necessary for the proper completion of the work as manufacturer.
specified.
17.4.2 Valve Installation
17.3.9 Items in the Bill of Quantities 1 General: prior to installation, inspection for
(i) Submersible Drainage Pumps (nr.) cleanliness of bores, seating surfaces etc. and for handling
damage, cracks, missing parts and tightness of pressure-
(ii) Horizontal Pumps (nr.) containing bolting shall be performed.
(iii) High Pressure Booster Pumping 2 The Contractor shall ensure that valves are in the
Set Employing Membrane Tank (nr.) closed position before installation.

(iv) High Pressure Booster Pumping 3 Valves must be operated through one complete
Set Employing Variable Speed opening and closing cycle in the position in which they
Pumps (nr.) shall be installed to ensure proper functioning.
4 Joint between valve and pipe must be set in the
(v) Duplex Sump Pumps (nr.)
manner specified for laying and jointing pipe and to
(vi) Monorail System Lump Sum manufacturer's instructions.
5 Valves shall be provided with concrete pads as
(vii) Fertilizer Injection System Lump Sum
shown on the Drawings so that pipes do not support
(viii) Electrical Works Lump Sum weight of valve.

(ix) Instrumentation and Controls Lump Sum 6 Valves without concrete pads shall be placed on firm
footings to prevent settling and excessive strain on
connection to pipe.
7 Valves shall not be used to bring misaligned pipe
into alignment during installation.

♦ 17-12 ♦
copy 249
8 All pressure-containing bolting (bonnet, seal plate
and end connections) must be inspected for adequate
tightness after installation but prior to field testing.

17.4.3 Pump Installation


1 Installation: realign pump and motor in the field after
grouting in base and connecting piping.
2 Support piping independently of pump nozzles.
3 Drains for packing glands and base shall be piped to
nearest floor drain or sump.
4 Before operation, the Contractor shall ensure pump
is properly lubricated, rotating element rotates freely by
hand, casing is vented and full of water, direction of
rotation is correct, strainer is clean and suction and
discharge valves are open.

17.4.4 Method of Measurement and Basis of


Payment
1 No separate items are measured for the work
described in this Sub-section and no separate payment
will be made.
2 All work related to installation of pumping stations
and all general requirements and builder's work in
connection with the installation, including all work shown
on the Drawings, described in the Specification or
reasonably to be implied as necessary for the proper
execution of the work shall be considered as subsidiary
Work, which shall not to be measured for direct payment,
the cost of which will be deemed to be included in rates
for the items in the Bill of Quantities.

♦ 17-13 ♦
copy 249
copy 249
Ref. Title Page No.
18.1 Locating and Protecting
Existing Utilities 18-1 
18.1.1  Description / General 18-1 
18.1.1.1  Submittals 18-1 
18.1.2  Materials 18-1 
18.1.3  Construction Requirements 18-1 
18.1.4  Method of Measurement 18-1 
18.1.5  Basis of Payment 18-1 
18.1.6  Items in the Bill of Quantities 18-2 

18.2  Removing and Disposing of or


Relocating Existing Utilities 18-2 
18.2.1  General 18-2 
18.2.1.1  Submittals 18-2 
18.2.2  Materials 18-2 
18.2.3  Construction Requirements 18-2 
18.2.4  Method of Measurement 18-3 
18.2.5  Basis of Payment 18-3 
18.2.6  Items in the Bill of Quantities 18-3 

18.3 Future Utility Crossing 18-3 


18.3.1  Description / General 18-3 
18.3.2  Materials 18-3 
18.3.3  Construction Requirements 18-3 
18.3.4  Method of Measurement 18-3 
18.3.5  Basis of Payment 18-3 
18.3.6  Items in the Bill of Quantities 18-4

copy 249
copy 249
18.1 Locating and Protecting Existing other forms as instructed by the Engineer or the
Utilities concerned authorities.
3 Before commencing any work on site, the Contractor
18.1.1 Description / General shall send a ‘Notice of Intent’ including two sets of
drawings, plan work, construction method and safety
1 This Sub-section describes requirements for locating measured to all Concerned Authorities and shall obtain
and protecting existing underground services and plant information in the form of a formal notice and/or signed
that are affected by execution of the Works but to remain drawing showing the location of all underground utility
in their position, such as utility lines and underground plant and Falajs. The Contractor shall search for and
water streams (Falajs) etc. The full scope of the protection ascertain the exact location of the plant on site by making
work required will be determined after investigation by the trial pits and shall repair, at his own expense, any damage
Contractor, and he shall prepare working drawings for caused to the plant by his works, to the satisfaction of the
such work as directed by the Engineer. Engineer and the Concerned Authorities.
2 Existing utility services and plant, and Falajs will not 4 Whenever, in the course of the work, water pipes,
be considered as obstructions as defined in Section 1. The irrigation pipes, drainage pipes, sewers, oil, gas pipes,
Contractor shall liaise with the utility owners and other electrical or telephone cables, or other unforeseen items
concerned authorities regarding such utility services, plant are encountered, the Contractor shall inform the Engineer,
and Falajs in all aspects of the work. The cost of locating who shall issue the appropriate instruction for each
and recording their positions and of working around or in individual case.
proximity to them is deemed to be included in the
5 The precise location of existing utilities and Falajs
Contractor’s allowance for his obligations under Section 1.
shall be investigated and established by the Contractor in
18.1.1.1 Submittals consultation with the relevant Utility Operator. Service
supply lines damaged in the course of the search shall be
1 Submit coordination drawings showing pipes and replaced with equivalent approved materials at the
major system components. Indicate interface and spatial Contractor’s expense.
relationship between pipes, system components, adjacent
utilities, and proximate structures. 18.1.4 Method of Measurement
2 Submit shop drawings of existing underground
1 Excavation and backfilling, whether by hand or
services and plant to be protected including plan layout
machinery, for searching and protection of existing utility
and locations, types and sizes.
plant and Falajs including making trial pits shall be
3 At project close-out, submit record drawings measured as described in Sub-section 2.8, Clause 2.8.4.
showing the protected pipes and related components with and 1.8.3.
sufficient details to allow for locating the pipes for future
2 Split pipes shall be measured in linear meters of laid
maintenance.
pipe of the various sizes, measured as a straight line. No
allowance will be made for cut ends and waste.
18.1.2 Materials
3 Concrete surround to pipes and ducts and concrete
1 Concrete shall conform to the requirements of Sub- for inverted box culverts and for blinding shall be
section 5.1 and shall be of the class instructed by the measured as described in Sub-section 5.1, Clause 5.1.5.
Engineer. Reinforcing steel shall comply with Sub-section The volume occupied by the pipe including pipe wall shall
5.2. Reinforced concrete shall comply with the appropriate be deducted from the gross volume of the concrete
requirements of Sub-section 5.3. Metalwork should surround and only the net volume of the concrete
comply with Section 6. surround so calculated shall be paid for.
4 Reinforcing steel shall be measured as described in
18.1.3 Construction Requirements
Sub-section 5.2, Clause 5.2.4.
1 All excavation and backfill shall conform to the
requirements of Sub-Sections 2.3 – ‘Roadway Excavation’ 18.1.5 Basis of Payment
and 2.8 – ‘Earthwork for pipe trenches’.
1 The quantity of completed and accepted work for
2 The protection of existing underground plant and split pipes measured as provided for above will be paid for
Falajs shall be carried out in strict compliance with the at the unit rate in the Bill of Quantities. The unit rate per
requirements of the Concerned Authorities and utility linear meter shall include labor, materials, markers and
owners. The protection shall normally be in the form of warning tape, equipment, transportation to and hauling
encasing the services or plant with a split 100 or 300 mm about the Site, loading, unloading and cutting, machining,
diameter uPVC pipe wrapped with polyethylene sheets etc. of standard length pipes.
and surrounded by concrete Class 15/20 or enclosing such
2 Excavation and backfilling shall be paid for as
plant of large diameter such as oil or water pipes or Falajs
indicated in Clause 2.8.5.
with an inverted concrete box culvert or slab or in any
3 Concrete shall be paid for as indicated in Clause 5.1.6.

♦ 18-1 ♦
copy 249
4 Reinforcing steel shall be paid for as indicated in 5.2. Reinforced concrete shall comply with the appropriate
Clause 5.2.5. requirements of Sub-section 5.3.
3 Gravity pipes and pressure pipes shall conform to the
18.1.6 Items in the Bill of Quantities requirements of Sub-section 8.2, Clause 8.2.2.

(i) Split pipe (diameter) lin.m 4 Electricity poles, ducts, handholes/manholes and
overhead and underground electricity cables, shall
conform to the requirements of Section 15 and of the
18.2 Removing and Disposing of or Concerned Authority.
Relocating Existing Utilities
5 Telecommunication ducts, handholes/manholes and
cables related to telephone works, shall conform to the
18.2.1 General telecommunication authority specifications and details.
1 This Sub-section describes requirements for removal, 6 Sand and sieved backfill material free from stones or
disposal or relocation/diversion of existing utilities. Full other debris shall be provided for reinstating the trenches
scope of the relocation work required will be determined after the laying of ducts.
after investigation by the Contractor and he shall prepare,
shop/working drawings for the work, as directed by the 18.2.3 Construction Requirements
Engineer. The Contractor shall liaise with the utility
owners and other Concerned Authorities in all aspects of 1 Prior to commencing the work, the Contractor shall
the work. prepare layout drawings, proposed working method and
the time schedule for disconnecting and reconnecting of
2 Permanent removal and, relocation or diversion of
the affected services and shall obtain approval of these
any existing utilities will be ordered by the Engineer where
from the Engineer and Concerned Authorities. During the
they obstruct the permanent work and where such utilities
work, the Contractor shall exercise great care not to cause
need to be maintained in operation as required by the
any damage to the exiting utilities.
utility owner. The Engineer may also order permanent or
temporary diversion of utilities when in his opinion it is 2 Electricity, gas, oil, water, sewage, drainage,
reasonable that this should be done for carrying out the irrigation and telephone service lines which are identified
proposed work, but such orders will not normally be given to be relocated shall be shown on the drawings, along
where the services concerned cross the work area and are with the required re-routing. The full scope of the services
either redundant or can be dealt with by the Contractor in to be relocated cannot be determined at tender stage and
the normal course of work. The diversions ordered by the the Contractor shall allow in his rate for verifying or
Engineer shall be paid for in the Contract, but any other revising the services that should be re-routed and
temporary diversion or removal required shall be at the adjusting the proposed re-routing alignment and for any
Contractor's own expense. variation in quantities, preparation of revised working
drawings, design, etc.
3 No service diversion shall be made without the
approval of the Engineer and the Concerned Authority. 3 The precise locations of existing utilities shall be
investigated and established by the Contractor in
18.2.1.1 Submittals consultation with the relevant utility owner. The
Contractor shall notify and obtain permission from the
1 Submit coordination drawings showing pipes and
Concerned Authority before interrupting any service.
major utility components. Indicate interface and spatial
Service supply lines damaged in the course of the search
relationship between pipes, system components, adjacent
shall be replaced with equivalent approved materials at
utilities, and proximate structures.
the Contractor’s expense.
2 Submit shop drawings of existing underground
4 All excavation and backfill shall conform to the
utilities and plant affected by the work including plan
requirements of Sub-Sections 2.3 – ‘Road Excavation’, 2.7
layout and locations, types and sizes.
– ‘Excavation and Backfilling for Structures’ and 2.8 –
3 At project close-out, submit record drawings ‘Earthwork for Pipe Trenches’.
showing the relocated services and related components
5 Removal of existing utilities shall conform to the
with sufficient details to allow for locating the utility for
requirements of Sub-section 2, Clause 2.2.2. Designated
future maintenance.
salvageable material shall be removed without
unnecessary damage, in sections or pieces, transported or
18.2.2 Materials stored by the Contractor as instructed by the Engineer.
1 All material for relocation/diversion of utilities shall Other material shall be disposed of off-site.
comply with the specifications of the Concerned Authority 6 Utility lines which should remain, but with added
and shall conform to the following listed requirements. protection, shall be shown on the drawings. Cavities left
2 Concrete shall conform to the requirements of Sub- by utilities removal shall be backfilled to the level of the
section 5.1 and shall be of the class instructed by the surrounding ground and compacted.
Engineer. Reinforcing steel shall comply with Sub-section

♦ 18-2 ♦
copy 249
7 During excavation, warning tiles or tape shall be 2 The Contractor shall be responsible for preparation
retrieved carefully and may be reused. The damaged of shop/working drawings, procurement of material and
warning tiles or tape shall be replaced by the Contractor at for following-up/co-ordination with the concerned
his own cost. Concreting and backfilling operations shall authorities in all matters relating to this work.
be carefully executed to ensure that there shall be no
damage to the utilities. 18.3.2 Materials
1 Concrete shall conform to the requirements of Sub-
18.2.4 Method of Measurement
section 5.1 and shall be of the class instructed by the
1 Removal and disposal of existing redundant utilities Engineer. Reinforcing steel shall comply with Sub-section
ordered by the Engineer under Clause 18.2.1, Item (2), 5.2. Reinforced concrete shall comply with the appropriate
shall be measured in linear meters of the length removed. requirements of Sub-section 5.3.
The rates shall include for all work except excavation as 2 Sleeves/ducts shall be uPVC for small pipes less than
stated in Item (4), below. 400 mm in diameter and concrete for larger pipes. Pipes
2 Removal and relocation of existing utilities shall be shall conform to the requirements of Sub-section 8.2,
measured in linear meters of the length of the relocated Clause 8.2.2.
work. Rates shall include for all work except excavation as 3 Locations and sizes of pipe sleeves are as shown on
stated in Item (4) below. the Drawings.
3 Provision and installation of new utility services shall
be measured in linear meters of the length of new service 18.3.3 Construction Requirements
installed. Rates shall include for all work except excavation
1 Before commencing any work on site, the Contractor
as stated in Item (4) below.
shall send a ‘Notice of Intent’ including two sets of
4 Excavation and backfilling whether by hand or drawings, plan of work, construction method and safety
machinery for removal, relocation/diversion of existing measures to all Concerned Authorities and shall obtain
utilities shall be measured as indicated in Sub-section 2.8, information in the form of a formal notice and/or signed
Clause 2.8.4. drawing showing the required location of sleeves for
5. No work will be measured and no payment made for future connection.
work carried out by the Concerned Authorities nor for any 2 Sleeves/ducts shall be placed prior to or during
work in connection therewith by the Contractor unless construction of the highway. Any piping installed after
prior approval for payment is given by the Engineer completion of the highway construction shall be placed
after jacking (thrust boring) a pipe sleeve under the
18.2.5 Basis of Payment pavement. The Contractor will not be permitted to cut into
1 The amount of completed and accepted work the pavement for pipe installation.
measured as provided for above shall be paid for at the 3 Markers should be placed on both ends of the
unit rate for each service stated in the Bill of Quantities, sleeves/ducts. In addition a rope should be installed inside
which rate shall be considered full compensation for the pipe and tied at both ends to the markers underground
locating, removing, relocating, installing and jointing of concrete support block or to an adjacent landmark.
utilities and for materials, labor, transport, equipment, 4 All excavation and backfill shall conform to the
tools supplies and all other items necessary for the proper requirements of Sub-sections 2.3 – ‘Roadway Excavation’
completion of the work, except excavation which is and 2.7 – ‘Excavation and Backfilling for Structures’.
measured as stated in Clause 18.2.4, Item (4).
18.3.4 Method of Measurement
18.2.6 Items in the Bill of Quantities
1 Sleeves/ducts shall be measured in linear meters of
(i) Remove and dispose of (utility) pipe of the various types, classes and sizes laid, measured
(size/description) lin.m. as a straight line. No allowance will be made for cut ends
(ii) Remove and relocate (utility) (size/ and waste. The rates shall be deemed to include for all
description) lin.m. work including the laying of markers and concrete
(iii) Provide and install new (utility) surrounds, but does not include excavation as stated in
(size/description) lin.m. Item (2) below.
2 Trench excavation and backfilling shall be measured
18.3 Future Utility Crossings and paid for as indicated in Clause 2.8.4 Item (4).

18.3.1 Description / General 18.3.5 Basis of Payment


1 This Sub-section describes requirements for 1 The quantity of completed and accepted work for
provision of pipe sleeves/ducts under pavements for sleeves/ducts pipes measured as provided for above will
future utility crossings. Full scope of the work will be be paid for at the unit rate in the Bill of Quantities, which is
determined according to conditions on Site.

♦ 18-3 ♦
copy 249
deemed to cover all costs except excavation as stated in
Clause 18.3.4, item (2).

18.3.6 Items in the Bill of Quantities


(i) Sleeves/ducts (type) (diameter) lin.m.

♦ 18-4 ♦
copy 249
Ref. Title Page No. Ref. Title Page No.
19.1 General 19-1 19.10 Heating Equipment 19-6
19.1.1 Description 19-1 19.11 Mixers for Concrete Pavements 19-6
19.2 Compaction Plant 19-1 19.12 Portable Concrete Mixers 19-7
19.2.1 General 19-1 19.13 Truck Mixers and Agitators 19-7
19.2.2 Pneumatic-Tired Rollers 19-1
19.14 Concrete Batch Plants 19-7
19.2.3 Heavy Pneumatic-Tired Rollers 19-1
19.2.4 Self-Propelled Pneumatic-Tired Rollers 19-1 19.14.1 General 19-7
19.2.5 Tamping Rollers 19-1 19.14.2 Automatic Concrete Batching Plants 19-8
19.2.6 Tandem Two and Three-Wheeled
19.15 Equipment for Concrete
Rollers 19-1
Pavement 19-9
19.2.7 Vibrating Rollers 19-2
19.2.8 Trench Rollers 19-2 19.15.1 General 19-9
19.15.2 Subgrade Preparation Equipment 19-10
19.3 Miscellaneous Equipment 19-2 19.15.3 Mechanical Concrete Spreaders
19.3.1 Disc Harrows 19-2 and Finishers 19-10
19.3.2 Mechanical Sweepers 19-2 19.15.4 Miscellaneous Minor Equipment
19.3.3 Mechanical Rammers 19-2 for Concrete Pavements 19-11
19.3.4 Motor Graders 19-2
19.16 Method of Measurement
19.3.5 Rotary Speed Mixers 19-2
and Basis of Payment 19-11
19.3.6 Travelling Mixing Plant 19-2

19.4 Hauling Equipment 19-2


19.5 Weigh Bridges 19-2
19.6 Water Distribution Equipment 19-3
19.7 Hot Mix Asphalt Equipment 19-3
19.7.1 General 19-3
19.7.2 Additional Requirements
for Batch-Type Plants 19-4
19.7.3 Additional Requirements
for Continuous Mixing Plants 19-5

19.8 Spreading and Finishing


Machines 19-5
19.8.1 Asphalt Pavers 19-5
19.8.2 Aggregate Spreaders 19-5

19.9 Pressure Distributors 19-6

copy 249
copy 249
19.1 General wheels shall be staggered so that they cover the entire
area over which the roller travels. Under working
conditions rollers shall develop a compactive effort of not
19.1.1 Description
less than 10kN per wheel.
1 The plant and equipment used for the Works shall be
as proposed and itemized in the Contractor’s approved 19.2.3 Heavy Pneumatic-Tired Rollers
detailed program and equipment list, unless otherwise
permitted by the Engineer. 1 These rollers shall have a mass of not less than 25
tonne and shall consist of not less than 4 pneumatic-tired
2 The plant and equipment shall be of sufficient power
wheels revolving in one transverse line. The width of the
and size and in sound and well maintained mechanical
roller shall be not less than 2.4m and it shall be
condition to meet the requirements and produce a
constructed in 2 or more sections in such a manner that
satisfactory quality of work. All items shall be ready for
each section is free to oscillate or move independently.
use when required by the Engineer, The Engineer may
Under working condition the roller shall develop a
order removal of unsatisfactory plant and equipment and
compactive effort of not less than 25kN per wheel.
require replacements meeting his approval. Assessment
of capacity and efficiency shall be based on the actual
performance on Site. 19.2.4 Self-Propelled Pneumatic-Tired
3 Whenever either the Specification or the Engineer Rollers
requires use of plant and equipment of a particular size or 1 These rollers shall be of the oscillating wheel type
type the Contractor may request in writing, permission to having not less than 7 pneumatic-tired wheels revolving
use alterative equipment. The proposal shall contain on two axles, and capable of being ballasted to the mass
evidence satisfactory to the Engineer that the output of the required.
alterative proposed is at least equal to that of the specified
2 Tires on front and rear wheels shall be staggered so
item.
that tire sidewalls have a minimum overlap of 12mm.
4 The purpose of this provision is to encourage the Rollers shall operate smoothly and without jerking when
development of new or improved plant and equipment. starting, stopping or reserving direction. Tires under
The Engineer may require trials in advance of the use of working conditions shall be inflated to pressures between
the item in works construction. 2
0.4 and 0.8 N/mm . The roller shall be fitted with a water
5 If permission is granted, it shall be on the system to keep all tires uniformly wet it necessary.
understanding that it may be withdrawn at any time the
Engineer determines that results are not satisfactory. 19.2.5 Tamping Rollers
Upon withdrawal of permission the Contractor shall use
plant and equipment originally specified and shall remove 1 These rollers under working conditions shall have a
and dispose of or otherwise remedy at his own expense minimum mass of 4000 kg per meter width of drum, and
defective or unsatisfactory work produced with the each individual tamping foot shall develop a compactive
alternative. No compensation will be allowed for any effort of not less than 0.7N/mm2 of tamping face area. The
delay or additional costs incurred by the Contractor as a width of the roller shall be not less than 2.4m and shall be
result of implementation of this provision. constructed in 2 or more sections so that each section is
free to move independently. It shall be fitted with cleaning
teeth at the rear.
19.2 Compaction Plant

19.2.1 General 19.2.6 Tandem Two and Three-Wheeled


Rollers
1 No item of plant shall be used that has in any way
been thrown out of its original balance by the application 1 These rollers shall be self-propelled or towed and
of attachments not approved by the Engineer. capable of being operated smoothly and without jerking
when starting, stopping, or reversing directions. The
2 The Contractor shall provide the means of readily
steering shall permit the roller to be accurately directed on
determining the effective mass of each roller or wheel of
the alignment desired. Roller drum wheels shall be
plant being operated. Any ballasting shall be included in
smooth steel and free from openings or projections which
the weighing.
will mar the surface on which the roller is operated.
3 The mass and compactive effort, or load, applied by Rollers shall be equipped with drip pans designed to
the roller shall be as specified, or as appropriate to the prevent oil, grease or petrol from dripping onto the work
work being undertaken. surface. They shall be provided with adjustable scrapers
to keep the surface of the wheels clean.
19.2.2 Pneumatic-Tired Rollers 2 When used on a bituminous surface, rollers shall be
1 These rollers shall have not less than 9 pneumatic fitted with water tanks and sprinkling devices which shall
tires revolving on 2 axles. Tires on the front and rear

♦ 19-1 ♦
copy 249
be used when necessary to wet the wheels and prevent 19.3.4 Motor Graders
the bituminous mixture from sticking to them.
1 Motor graders shall be self-powered and equipped
3 Rear wheels may be crowned at a rate of not more
with an adjustable mold board. The cutting blade shall be
than 1 in 288 for two wheeled, and 1 in 320 for three
straight.
wheeled rollers,
4 Rear wheels of three-wheel rollers, shall be propelled
19.3.5 Rotary Speed Mixers
with a differential gear. The front wheel shall show no
noticeable crown and shall overlap the compacted area of 1 Rotary speed mixers shall be either of the power
each rear wheel by not less than 60mm. take-off or self-powered type, equipped with a hydraulic
lift.
19.2.7 Vibrating Rollers
19.3.6 Travelling Mixing Plant
1 These shall be self-propelled or towed and have a
means of applying mechanical vibration to one or more 1 Travelling or stationary mixing plant shall be either
smooth steel-drum wheels. They shall be fitted with a of the type which will pulverize the material to be treated
device, or provided with the means for, indicating the and mix it with the binder and the proper amount of water
frequency at which the roller is operating, which will be as without picking up material from the roadway, or the type
recommended by the manufacturer. which elevates roadway material into a pugmill for mixing.
Plant shall be fitted with a device which will accurately
19.2.8 Trench Rollers control and measure the quantity of water used.

1 These shall be self-propelled, steel wheel rollers,


19.4 Hauling Equipment
capable of being operated smoothly and without jerking
when starting, stopping or reversing direction. The width
1 Hauling equipment for construction materials shall
of the wheel shall be not more than 500mm and diameter
be vehicles having hydraulically operated dump bodies
of the compaction rolls shall be not more than 1.5m.
suitable for depositing loose materials in a windrow or
2 Wheels shall be smooth and free from openings or into spreader boxes. Bodies shall be so constructed that
projections which will mar the surface on which the roller volume measurement can be accurately carried out. They
is operated. Rollers shall be equipped with drip pans shall be constructed and maintained to prevent loss of
designed to prevent oil, grease, or gasoline from dripping materials during hauling operations. Dump controls that
onto the work surface, and shall be provided with can be operated from the driver's seat shall be fitted.
adjustable scrapers to keep the outface of the wheels
clean. The balance wheel of the roller shall be adjustable
in height to provide the slope of surface required.
19.5 Weigh Bridges

1 Weighing equipment tor truck-hauled material shall


19.3 Miscellaneous Equipment consist of platform scale accurate to 0.5% throughout the
range of use. Scales shall have a platform of adequate
19.3.1 Disc Harrows length to weigh, in one operation, the longest truck or
truck-trailer combination which is in use on the works.
1 Disc harrows shall be of the tandem type and shall be
of sufficient size, mass and number of discs to perform the 2 Scales shall be inspected and certified by an
manipulation required approved company as often as the Engineer deems
necessary. Each certification shall show the date of the
inspection and the name of the Company making the
19.3.2 Mechanical Sweepers
inspection.
1 Sweepers shall be constructed in a manner which 3 If no suitable company exists, or if instructed by the
will permit the revolution of the broom to be adjusted in Engineer, the Contractor shall check and adjust the scale
relation to its progression and permit adjustment of the in the presence of the Engineer, using the method
broom height in relation to the surface being cleaned. recommended by the manufacturer and approved by the
Broom bristles shall be stiff enough to sweep clean Engineer. The Contractor shall provide a minimum of ten
without cutting into the surface. Brooms with steel bristles 25kg standard test weights for each scale on Site for
shall not be used. checking purposes.
4 The Contractor shall, when instructed by the
19.3.3 Mechanical Rammers Engineer, make mass comparisons with other
1 Mechanical or power rammers shall have a mass permanently located scales that meet the approval of the
between 100 kg and 750 kg. Engineer. The comparisons shall be for the purpose of
providing information on the performance of the
Contractor’s scale and will not be used as a basis for
adjusting the scale.

♦ 19-2 ♦
copy 249
5 Access to the scale platform shall be maintained by sampling equipment and other similar equipment from
the Contractor to the satisfaction of the Engineer and a the ground to the mixer platform and return. Gears,
suitable weathertight building shall be provided to enclose pulleys, chains, sprockets and other dangerous moving
the indicating mechanism. Adequate lighting for the scale parts shall be properly guarded. Ample and unobstructed
operator's use shall be installed. space shall be provided on the mixing platform. Clear and
unobstructed passage shall be maintained in and around
19.6 Water Distribution Equipment the truck loading area which shall be kept free from
droppings from the mixing platform.
1 Equipment for the distribution of water shall consist 5 The plant shall be equipped with a dust collecting
of self propelled or towed tanks equipped with spray bars system. Collected dust shall be stored in a hopper and
and, when required, pumps to operate under pressure. shall be fed to the boot of the hot elevator at a uniform
Pumps shall be of sufficient capacity to provide uniform rate by a variable speed vane feeder or mechanical feeder
and adequate distribution. The tanks shall be mounted on during the period when a full stream of aggregate is being
pneumatic-tired trucks or on pneumatic-tired trailers fed from the drier to the hot elevator. The accuracy of the
pulled by pneumatic-tired equipment. The minimum feeder shall not be affected by the head of material in the
capacity of a tank shall be 4000 liters. collected dust storage hopper. A 'low bin' indicator shall
be required ahead of the feeder.
2 Distribution equipment shall be constructed so as to
permit accurate and uniform distribution of the desired 6 The plant shall be located where it can be supplied
quantities of water, Control valves shall fully close with no with adequate storage and vehicle movement space.
leakage and shall be constructed to operate from the Separate stockpiles of each size of aggregate shall be
driver's seat, or provision made for an additional operator arranged, with rigid partitions to prevent intermixing of
to work control valves while the equipment is travelling. different materials between adjacent stock piles. In
general, fine aggregates to be used in bituminous
19.7 Hot Mix Asphalt Equipment mixtures shall be placed in separate stock piles before
they are placed in the cold bins. Aggregates shall be kept
separated until they are fed in proper proportions onto a
19.7.1 General belt conveyor or into the boot of the cold aggregate
1 Hot-mix plant shall be either of the batch-type or elevator. Aggregates shall be handled as to prevent
continuous-type. Plant shall not be used to produce contamination and degradation.
mixtures concurrently for more than one contract unless 7 When compartment aggregate feeders are used, the
permission is granted by the Engineer. Plant units shall width of the crane bucket shall not be more than half the
be designed and operated so that they will function minimum width of the top of bin compartments and the
properly and produce bituminous mixture of uniform maximum length of the bucket when fully open shall be at
temperature and composition within the tolerances least 300mm less than the length of the top of the bin
specified. compartment, When an end loader is used to charge cold
2 The plant shall be approved by the Engineer before bins the maximum discharge width of the bucket shall be
production begins. It shall be fitted with adequate and safe 600mm less than the width of the top of the bin
stairways to the mixer platform and sampling points plus compartment.
a room of 8 The plant shall be provided with accurate mechanical
3 The plant shall be complete with a control room of means for feeding each aggregate in proper proportion
2 into the drier so that uniform production shall be
approximately 18m floor area for performing tests for
control of the mixture. The room shall be provided with maintained. Control of the total quantity of combined
sufficient heat, natural and artificial light and air aggregates fed to the drier shall be by a variable speed
conditioning, and be equipped with a desk, chair, drafting system. Other methods may be proposed for approval by
stool, work bench 1m by 3m by 1m high with drawers and the Engineer. Gates shall be capable of being locked or
cabinets below, service sink, water supply and electric bolted securely in the required position. A minimum of 4
power outlets. First aid equipment, telephone, fire bins and feeders will be required.
extinguisher (having a minimum Underwriters Laboratory 9 The plant shall be equipped with revolving cylindrical
rating of 2A10BC), and sanitary facilities shall be provided. drier or driers for heating aggregates to the temperatures
When approved by the Engineer a room conforming to the required when the plant is operating at its full rated
above requirements, in a separate building, may be capacity.
substituted. 10 Screens used in separating aggregates shall be the
4 Guarded ladders shall be placed at all points where vibrating type. The system shall be equipped with a
access to plant operation is required. Access to the top of scalping screen having openings not more than 12.5mm
truck bodies shall be provided by a platform or other greater than the largest size of aggregate used in
suitable device to enable the Engineer to obtain samples preparing the bituminous mixture. The screening system
and mixture temperature data. A hoist or pulley system shall have a tailing pipe for removal of oversized
shall be provided to raise scale calibration equipment,

♦ 19-3 ♦
copy 249
aggregate. The discharge point of the tailing pipe shall be 2 If aggregates are measured by volume in calibrated
located so that it will not create a hazard. compartments these shall form the weigh hopper and
11 Hot aggregate storage bins at sufficient capacity to shall be arranged so that the volume measurement of
supply the mixer when it is operating at full capacity shall each compartment and each batch may be checked by
be provided. Bins shall be arranged to give separate mass. Means of checking the volume measurement shall
storage of the appropriate proportions of mineral meet the approval of the Engineer.
aggregates. Separate dry storage shall be provided for 3 The weigh scale shall be a springless dial type with a
mineral filler and the plant shall be equipped to feed capacity of not more than twice the mass of the capacity
material into the mixer. Each bin shall be provided with of the mixer.
overflow pipes to prevent backing up of material into 4 The mineral filler shall be weighed in the aggregate
other compartments or bins. Each compartment shall be hopper or measured by volume in a calibrated
provided with an individual outlet gate constructed so that compartment and shall be conveyed by means of a dust
when closed there shall be no leakage. Gates shall cut off elevator and screw conveyor system. The system shall be
quickly and completely. Bins shall be so constructed that so arranged that the accuracy of the feed will not be
samples can be readily obtained. affected by the head of material in the mineral filler bin.
12 Temperature recording shall be done either by The screw conveyor shall operate at such a speed that
recording pyrometer or recording thermometer having at small fractions of material to be weighed may be added
least 2 terminals when a single drier is used and at least 3 accurately. The chute used to introduce mineral filler into
terminals when a dual drier is used. The type and accuracy the weigh hopper shall be so constructed that no material
of the recording instrument shall be approved by the is retained in it after the required amount has been
Engineer. Unless otherwise approved, one terminal shall deposited in the weigh hopper.
be installed at a suitable location at the discharge of each 5 Equipment for weighing and measuring bitumen
drier and the others near the discharge gate in each bin shall consist either of a weigh bucket or a metering device.
compartment used for fine aggregate. The temperature If a weigh bucket is used it shall be a non-tilting type and
recording instrument shall be capable of producing shall be completely suspended from a springless dial scale
accurate temperature charts for submission to the accurate to ±0.4%. The weigh bucket, discharge valve or
Engineer after each day's operation. valves and spray bar shall be heated and shall have a
13 The recording instrument shall be installed in a capacity of at least 15% in excess of the mass of material
position free from dust and vibration. If the instrument is required in the batch. Heated, quick-acting, non-drip
not located to indicate clearly to the drum fireman the valves shall be used in charging the bucket.
temperature of the mineral aggregates at the discharge of 6 Metering devices shall have a capacity at least 15% in
each drier, a non-recording pyrometer shall also be excess of the quantity of bitumen used in a batch. Controls
installed in view of the fireman. shall be constructed so that they may be locked at any dial
14 Storage tanks for bitumen shall be equipped to heat setting and will automatically reset to that reading after
and hold material at the required temperatures. Heating the addition of bituminous material. The amount of
shall be accomplished by steam coils, hot oil coils, material which the Contractor will be permitted to mix per
electricity or other approved means so that no flame shall batch shall be determined by the Engineer. The mixer
be in contact with the tank. Lines and fittings shall be shall be a twin-shaft type. Drip pans shall be used under
steam, electric or hot oil jacketed. Provision shall be made the mixer where necessary to prevent moisture from
for sampling from the line leading to the weigh bucket if dripping onto truck loads of freshly prepared asphalt. Pipe
more than one grade of bitumen is required for concurrent fittings shall be tight. The mixer platform shall be
operations, adequate storage and separate piping to the sufficiently rigid and of ample size to provide safe and
weigh bucket for each grade shall be provided to prevent convenient access to the mixer and other equipment.
intermingling. An armored thermometer or pyrometer 7 The mixer shall be equipped with an accurate time
which will accurately show temperatures between lock to control the operations of a complete mixing cycle.
100°Cand 200°C shall be located in the line or within the It shall lock the weigh box gate after the charging of the
tank. mixer until the closing of the mixer gate on completion of
the cycle. It shall lock the bitumen bucket throughout the
19.7.2 Additional Requirements for Batch- dry mixing period and shall lock the mixer gate
Type Plants throughout both dry and wet mixing periods. The dry
mixing period is defined as the interval of time between
1 Equipment for weighing and measuring aggregate the opening of the weigh box gate and the start of the
shall include means for accurately weighing each size in a introduction of bitumen. The wet mixing period is the
weigh box or hopper suspended on scales and of ample interval of time between the start of the introduction of
size to hold a full batch without hand raking or bitumen and the opening of the mixer gate. Control of the
overflowing. The gate shall close lightly so that no timing shall be flexible and capable of being set at
material is allowed to leak into the mixer while a batch is intervals of 5 seconds or less throughout a total cycle.
being weighed. Setting of time intervals shall be performed in the

♦ 19-4 ♦
copy 249
presence of the Engineer who shall then lock the case several heights inscribed on a permanent gauge. Charts
covering the timing device until such time as a change is shall be provided showing the rate of feed of aggregate
to be made in the timing periods. A mechanical batch per minute.
counter shall be installed as part of the time lock device. It 7 Unless otherwise agreed by the Engineer the mixing
shall register only upon actuation of the asphalt weigh time shall be determined using the following formula. The
bucket or valve release. It shall not register any dry mass shall be determined for the job by tests made in the
batches or any material released during the operation of presence of the Engineer.
filling the bins.

Mixing time in seconds = Pugmill dead capacity (kg)


19.7.3 Additional Requirements for Pugmill output (kg/s)
Continuous Mixing Plants
8 The pugmill shall be equipped with a discharge
1 A gradation control unit shall be included for hopper having a minimum capacity of 900kg.
accurately proportioning each size of aggregate and
mineral filler. 19.8 Spreading and Finishing
2 Feeders shall be mounted under each compartment Machines
bin. Each compartment bin shall have an accurately
controlled individual gate to form an orifice for
19.8.1 Asphalt Pavers
volumetrically measuring the material drawn. The feeding
orifice shall be rectangular with one dimension adjustable 1 Asphalt pavers shall be self-contained, power-
by positive mechanical means provided with a lock. propelled units provided with an activated screed or
Indicators marked in millimeters shall be provided on each strike- off assembly, heated if necessary and capable or
gate to show the gate opening. Bins shall be equipped spreading and finishing courses of bituminous plant-mix
with tell-tale devices to indicate the position of aggregates material in widths appropriate to the typical sections and
in bins at the lower quarter points. The condition of the thicknesses shown on the Drawings.
conveyor belt shall be continuously checked and adjusted 2 Automatic controls of the paver shall be by a linkage
to avoid segregation of the aggregates. arrangement so that through the process of automatically
3 A cutoff system shall be provided which shall adjusting the screed thickness control, the asphalt can be
automatically stop mixing operations when any bin placed and finished to a predetermined grade and uniform
becomes empty or when the bitumen reaches a level in slope and cross-section. Manually controlled pavers may
the tank where the specified quantity is not delivered to be used if approved by the Engineer. Such pavers shall be
the pugmill. capable of spreading the mix in such a manner that no
4 The plant shall include means for calibration of the supplemental shaping will be required.
gate openings by weighing test samples. Provision shall 3 Pavers shall be equipped with a receiving hopper of
be made so that materials fed out of individual orifices sufficient capacity for the spreading operation. The hopper
may be bypassed to individual test boxes. The plant shall shall be equipped with a distribution system to place
be equipped to conveniently handle individual test mixture uniformly in front of the screed. The screed or
samples weighing not less than 100kg. Accurate scales strike-off assembly shall produce a finished surface of the
shall be provided by the Contractor to weigh lest samples. required evenness and texture without tearing, pushing or
5 Interlocking mechanical controls or other positive gouging the mixture. When laying the mixture, the paver
methods approved by the Engineer shall be provided to shall be capable of being operated at forward speeds
synchronize the flow of aggregates from the bins and the consistent with satisfactory placement.
flow of bitumen from the meter or other proportioning
device. A revolution counter graduated in 0.01 revolutions 19.8.2 Aggregate Spreaders
shall be visibly located on the plant. Means shall be
provided for checking by mass the flow of bitumen. 1 Spreaders used in placing aggregates in layers shall
contain a strike-off plate capable of being adjusted so as
6 The heated mixer shall be capable of producing a
to place material in uniform layers from 10 to 300mm in
uniform mixture within job-mix tolerances. It shall be
thickness. They shall be fitted with two end gates or cut-
equipped with a discharge hopper with dump gates which
¬off plates so that aggregates may be spread in widths
will permit rapid and complete discharge of the mixture.
varying up to the full lane width.
Paddles shall be adjustable for angular position on shafts
and reversible to retard the flow of mix. The spray bar of 2 Spreaders used for surface treatment, shall be of a
the mixer shall be equipped with a pressure gauge. An mechanical type approved by the Engineer. They shall
adjustable baffle or dam which can be locked or bolted in distribute aggregate uniformly and shall be capable of
position shall be placed at the discharge end of the being adjusted so that spreading rate will not vary by
pugmill. The mixer shall have a nominal capacity of not more than ±1kg/m2.
less than 50t/h and shall have a manufacturer's plate
giving the net volumetric contents of the mixer at the

♦ 19-5 ♦
copy 249
19.9 Pressure Distributors that it will provide a clear view of the operation of the
spray bars.
1 Pressure distributors used for applying bitumen or 9 A tachometer shall be attached to the truck so as to
bituminous emulsions shall be mounted on self-propelled be visible to the truck operator and to enable him to
trucks which shall be capable of operating smoothly at maintain the constant speed necessary for application of
speeds down to 1.0km/h when used on construction and the specified quantity of bitumen. Suitable charts shall be
at road speeds from 50 to 70km/h when used for prepared showing the truck speeds necessary to obtain
transporting bitumen. the required results. Alternatively, a synchronizer can be
2 The bitumen tank shall have a capacity between 2000 used. The synchronizer shall deliver the specified quantity
liters and 9500 liters. Approval shall be obtained from the of bitumen onto the road surface regardless of the speed
Engineer prior to use of a larger tank. The tank shall be at the truck.
covered by a minimum of 25mm Insulation. It shall be 10 The distributor shall be calibrated in the presence of
equipped with a removable access cover, an overflow pipe the Engineer before work is started and the Contractor
and a suitable strainer located at the pump intake or the shall supply equipment, tools, and materials for the
outlet to prevent the passage of any material which might calibration.
clog the nozzles. A dial gauge visible to the spray bar
operator shall indicate the contents of the tank at various 19.10 Heating Equipment
levels, and a pressure gauge shall show the pressure at
which bitumen is applied. The tank shall be fitted with an 1 The heating equipment shall have sufficient capacity
accurate measuring stick. to heat the bituminous material by circulating steam or
3 The bitumen distributor shall be equipped with a hot oil through coils in the tank or by any other method
heating system. The system shall consist of heat flues approved by the Engineer. Tanks which have defective
having sufficient radiation to give rapid circulation of hot coils or which are without coils will be rejected unless
gases of combustion from one or more efficient smokeless some satisfactory auxiliary means can be provided by the
burners of the torch type, a circulating device to give Contractor to heat the material without introduction of
uniform heating of material, and a suitable fuel supply moisture. Use of any equipment to agitate bituminous
tank. material while it is being heated will be prohibited if, in the
4 The distributor pump shall be of a rotary positive opinion of the Engineer, it changes the characteristics of
pressure type of sufficient size and discharge capacity to the material. Free steam or hot oil shall not be introduced
apply uniformly the specified amount of bitumen in widths directly into the material.
up to 7.5m. It shall be driven by a petrol motor, other than
the vehicle propelling motor. The pump motor shall have 19.11 Mixers for Concrete Pavements
sufficient power to operate the distributor pump at the
required volume and pressure. If the pump motor is 1 Paving mixers shall be the batch type and shall have
equipped with a transmission it shall have a governor. 3
a rated capacity of not less than 0.75m of mixed concrete.
Suitable housing or heating jackets shall be provided to Mixers having multiple mixing drums may be used. The
enclose the distributor pump and piping. mixer shall be equipped with boom and bucket delivery
5 Spray bars of various lengths shall be used to spray and the bucket shall be so constructed that it will
bitumen over widths varying from 1.2m to 7.5m. Spray distribute concrete in a uniform and satisfactory manner.
bars shall be arranged so that they may be traversed The mixer skip shall be equipped with a bulkhead suitably
laterally over a distance of not less than 230mm to match placed and capable of retaining a full batch of aggregates
joints and to clear obstructions. They shall be fitted with and cement without spillage.
spray nozzles to give uniform distribution of the material 2 The mixer shall be equipped with a batch meter for
in the specified quantities. Means shall be provided to counting batches and a timing device which automatically
stop the flow quickly and to prevent it from dripping when locks the discharge lever until the end of the mixing period.
the flow is shut off. Means shall be provided for obtaining The timing device shall be equipped with a bell adjusted
samples of material from the tank or from piping leading to ring each time the lock is released. If the timing device
from the tank to the spray bars. becomes out of order the Contractor will be permitted to
6 A hand spray bar and nozzle having a suitable length continue while it is being repaired, provided each batch is
of flexible hose with packed couplings shall be provided mixed and manually timed for at least 1.5 minutes. If the
for applying material at intersections, shoulders and timing device is not in good working order within 72 hours,
similar locations. further use of the mixer shall be prohibited until repairs
7 A mercury thermometer with a stem extending into are completed.
the material or into a well, shall be placed in a suitable 3 The mixer shall be equipped with a water measuring
position in the tank to give the temperature of the contents. device which shall be capable of measuring and
8 A substantial platform for the operator shall be discharging the specified amount of water to ± 1%. The
provided at the rear of the distributor. It shall be so located accuracy of measurement shall not be affected by
variations in pressure in the water supply. Water

♦ 19-6 ♦
copy 249
measuring equipment shall include an auxiliary tank from accuracy of 1%. If water is added during transit, the
which the water measuring tank shall be filled. The measuring device may be mounted on the truck mixer and
volume of the auxiliary tank shall be not less than the an outside tap or valve shall be provided for checking the
volume of measuring tank. Equipment shall be so graduations on the indicator, unless other means are
arranged that water pressure in the measuring tank cannot provided for readily and accurately determining the
exceed that due to the difference in elevation between the amount of mixing water discharged. Provision shall be
two tanks. The measuring tank shall be equipped with an made to automatically stop the flow of water when the
outside tap to provide for checking the graduation on the desired amount has been delivered. If not mounted on the
indicator unless other means are provided for readily and truck, the water measuring device shall be located at the
accurately determining the amount of water discharged. site selected for adding water and shall conform to the
Means shall be provided to automatically stop the flow of requirements of Sub-section 19.11.
water from the measuring tank when the desired quantity 4 Equipment for weighing and batching materials
has been delivered. intended for truck mixing shall comply with the relevant
4 The type of equipment shall be such that the quantity clauses of these specifications
of water delivered shall not be affected by tilting the mixer. 5 Truck agitators shall be of the type having a
There shall be no leakage and if the water measuring watertight revolving drum suitably mounted and fitted
equipment fails to deliver the proper quantity of water due with internal blades attached to the drum. Truck agitators
to the mechanical condition of the equipment, the when fully loaded shall be capable of maintaining the
operation of the mixer shall be suspended until repairs concrete in a thoroughly mixed and uniform mass and of
have been made. discharging concrete without segregation. Agitators shall
5 Pick-up and throw-over blades in the drum of the transport and discharge concrete without leakage of
mixer which are worn down 20mm or more in depth shall ingredients. A truck agitator shall have attached to it a
be replaced with new blades. metal plate on which is stated its capacity in terms of
volume of the pre-mixed concrete for the various uses of
19.12 Portable Concrete Mixers which the equipment is suitable.
6 Concrete from central or pre-mix plants shall not be
1 Portable concrete mixers for incidental construction in transit in truck mixers or agitators longer than 30
3 minutes, measured between loading discharge and
shall be of the batch type. Mixers involving placing 25m
or more in a single pour shall have a rated capacity of not commencement of pouring. If more than one batch is
3 required for charging a truck, the time of haul shall be
less than 0.25m per batch. Other portable mixers shall
3 reckoned from the start of mixing of the first batch.
have a rated capacity of not less than 0.17m per batch.
The mixer shall be equipped with a batch meter, timing
device and water measuring device as specified in Clause 19.14 Concrete Batch Plants
19.11.
2 Pick-up and threw-over blades in the drum of the 19.14.1 General
mixer which are worn down more than 20mm shall be
replaced with new blades. 1 The plant shall be approved by the Engineer before
production begins. Bins, weighing hoppers and scales
shall be arranged to the satisfaction of the Engineer so
19.13 Truck Mixers and Agitators that the weigh beam, dial or dial scale is in full view of the
operator controlling the gates, valves or belts that feed
1 Truck mixers shall be of the type having a watertight
material into the weighing hopper. The plant shall be
revolving drum, suitably mounted and fitted with blades equipped with a room as specified in Sub-section 19.7
inside the drum. They shall be capable of combining
2 Storage bins shall have sufficient capacity for
aggregates, cement and water into a uniform mixture and
adequate supply of material to weighing hoppers. They
of discharging the mixture without segregation. A truck
shall be supported by a rigid framework on a solid
mixer shall have attached to it a metal plate on which is
foundation. Bins shall have adequate separate
stated its capacity in terms of volume of mixed concrete
compartments for each size of aggregate and for bulk
for the various uses for which the equipment is suitable.
cement when used. The top of the fine aggregate
2 Except when used exclusively for agitating premixed
compartment shall be equipped with a tilted screen
concrete, trucks shall be provided with a batch meter and
having a maximum mesh size of 2.5mm through which all
locking device capable of preventing discharge of concrete
fine aggregate must pass. Each compartment shall be
before the required number of revolutions has been designed to discharge material efficiently and freely into
obtained or with a revolution counter suitably mounted to
the weighing hopper. Means of control shall be provided
provide means of verifying the amount of mixing
so that when the quantity to be obtained is being
performed. Water shall not be added to concrete in transit approached the flow of material can be gradually retarded
from a pre-mix plant.
and completely shut off, without leakage, at the moment
3 The water measuring device shall be capable of the desired amount has been discharged.
discharging the specified amount of water with an

♦ 19-7 ♦
copy 249
3 Weighing hoppers shall be completely suspended 8 Springless dial scales shall be provided with suitable
from scale and shall hang free and except as further markers inside the glass cover and in front of the dial
provided, shall have sufficient capacity to contain which may be set to show the position of the dial indicator
materials to be weighed for one batch of concrete without for the required load or various cumulative loads when
shoveling and without jiggling the hopper to keep bin more than one size or kind of aggregate is weighed in the
gates and chute openings free of material. Cement shall same hopper. Markers shall be in distinctive colors for the
be weighed in a hopper and independent of the hoppers various materials to be weighed.
used for weighing aggregate. 9 The value of the minimum graduation interval of any
4 Batching equipment insufficient in capacity to weigh scale shall be not more than 0.2% of the batch mass and
materials required for a full batch will be permitted not more than 0.1% of the capacity of the scale. The value
provided the capacity of the hoppers is sufficient to weigh of the minimum graduation interval of any scale used for
3
all materials for at least 1m of concrete for any mixer of weighing water shall be not less than 1kg. Scales shall be
3
rated capacity of 1m or larger. Disproportion between designed and built so that accuracy within the maximum
batching equipment and the mixer shall not be so great tolerance of ± 0.4% of the net load in the hopper will be
that more than 3 weighings of each material will be maintained.
required for charging the mixer. 10 When a beam scale is used for weighing cement a
5 Aggregate hoppers shall have a port or other tare shall be provided and the weigh beams shall be
opening for removal of overload unless sufficient capable of being lifted out of the weighing position so that
clearance exists between the bottom of the bin gate and the tare weight of the hopper can be checked after each
the top of the hopper. The top of the cement hopper shall weighing operation to determine if all the cement has
be closed to prevent escape of cement while it is being been discharged into the batch.
weighed. Hoppers shall be designed to eliminate 11 Scales shall be housed or otherwise protected
accumulation of unused material and leakage through against the effect of wind in a manner meeting the
discharge gates during weighing. They shall be capable of approval of the Engineer.
discharging material efficiently and completely into batch
12 Ten standard 10kg weights shall be available on Site
trucks or the mixer without the necessity of beating or
for use in calibrating and testing weighing equipment.
jiggling. If a hopper in the opinion of the Engineer does
Weights will not be required when scales are calibrated by
not discharge material satisfactorily, it shall be provided
trained scale personnel with adequate scale testing
with a vibrator of sufficient frequency and power to
equipment and the calibration is observed by the Engineer.
provide complete discharge. Weighing hoppers shall be
enclosed or otherwise protected against wind. When bins 13 Means of access for inspection purposes shall be
are not available, materials shall be weighed in containers. safe and shall meet the approval of the Engineer. In the
End loaders shall not be used for loading the weighing case of permanently located batching plants, means of
hopper. access shall be an inclined stairway with a handrail
located so that its upward flight will end on the scale
6 Scales may be of either the horizontal beam or
operator’s platform. It shall be firmly attached to the
springless dial type designed as an integral unit of the
supporting members of the bin. The weigh platform shall
batching plant and shall be of rugged construction. Beam
have a floor of metal grid or 50mm thick timber planks.
type scales used for weighing one size or kind of
aggregate shall have one full capacity weigh beam.
Multiple beam scales used in weighing more than one size 19.14.2 Automatic Concrete Batching Plants
or kind of aggregate shall have as many beams as the 1 Automatic equipment for weighing, measuring,
number of sizes or kinds of aggregate to be weighed. batching and mixing materials for concrete shall conform
Individual beams shall have such capacities as will permit to Sub-section 19.11 except as modified and extended by
the required mass of each size or kind of material to be set the following provisions.
off on a single beam. The scale shall be provided with
2 Each batch shall be mixed for the full period required
suitable lockouts so that weigh beams may be engaged to
after all the materials have entered the mixer and
weigh in the desired order.
recharging the mixer shall not occur before the previous
7 Each weigh beam shall have some means placed in a batch has been discharged; When batching plants are
position from which it can be viewed without parallax by used for successive batches of the same size, the mixing
the operator while charging the hopper, to indicate when time adjusting control shall be capable of being locked.
the beam is in the proper balance position. Poises shall be
3 Cement and mixing water shall be weighed or
constructed so that they will be held firmly in position.
otherwise measured within the tolerance of ±1% of the
Beam scales shall have a provision such as a tell-tale dial
required quantity. Each of the aggregates, whether
for indicating to the operator that the required load in the
weighed separately or cumulatively, shall be weighed
hopper is being approached. Such a device shall indicate
within the tolerance of ± 1.5% of the respective required
at least the last 100kg of load in the case of scales used for
masses. Interlocks shall be set so that the amounts of
weighing aggregate and at least the last 50kg of load in
materials will be delivered within the tolerance stated.
the case of scales used for weighing cement.

♦ 19-8 ♦
copy 249
4 The arrangement shall be such that the scales of the remainder of the batch. Water shall then enter uniformly
system can be conveniently checked for accuracy. Scales while mixing is continued and all water shall be in the
shall be designed and built so that when drag due to the drum by the end of the first 15 seconds of the mixing
weighing control device is included, accuracy within ±0.4% period.
of the net load in the hopper will be maintained. 12 Means shall be provided for easy adjustment from
5 When mixing water is measured volumetrically preset quantities of aggregates and mixing water. Suitable
provision shall be made for by-passing measured water equipment indicating the amount of free water in fine
into a container for checking the accuracy of delivery. If aggregate as it is being batched shall be provided and the
water is measured during the course of its flow into the quantities of fine aggregate and mixing water shall be
batch, means shall be provided to show at any time adjusted concurrently as concrete is being produced.
during the flow, the amount that has entered. Devices for 13 The weighman shall not interfere with the operation
volumetric measurement of mixing water shall of any part of the scale mechanism during the weighing
automatically reset at the initial position immediately after process for the purpose of circumventing the interlock or
delivery of the measured amount and be ready for the causing malfunction of the equipment. The Engineer may
next batch cycle. require that equipment be provided with a positive means
6 The dispenser for an admixture shall provide a visual for preventing such interference.
indication that the admixture is actually entering the batch. 14 Automatic and semi-automatic batching plant may
The tube through which it is conducted into the stream of be constructed so that it can be switched to manual
the mixing water shall be transparent, or shall have a control. However, when switching to manual control is
translucent section. necessary, batching operations shall continue only until
7 The plant shall be provided with gates, valves or repairs can be made, but not for a period exceeding 72
other suitable devices, which, when activated by a single hours. If provision is made for switching to manual
starting mechanism, shall set in motion the charging of operation, then the scale or a scale follower shall be
weigh hoppers or other containers and which, in weighing placed within view of the operator, but not further then 6m
or measuring any given material, shall end the charging from the location from which the manual batching is being
when the desired amount has been attained. It shall be performed.
capable of having quantities preset on a central control 15 Batching plant that does not fully comply with the
panel that will result in the correct measurement of the requirements prescribed for automatic batching shall be
material for each batch. Control adjustments shall be considered as semi-automatic. The minimum requirement
capable of being performed on the same panel. for semi-automatic batching shall be gates, valves or other
8 An over and under indicating device shall be suitable devices which open or start separately when
provided to show whether the amount of material actuated by individual starting mechanisms to permit
weighed is within the allowable tolerance. An interlock material to be weighed or measured, and close or stop
shall be provided, firstly so that the charging device can automatically when the desired amount has been attained.
open or start only when the scale indicates zero load and
when the weigh hopper or container discharging gate or 19.15 Equipment for Concrete Pavement
valve is closed, and secondly so that the discharge gate or
valve can open only when the desired mass within the
19.15.1 General
allowable tolerance is in the weigh hopper or container
and when the charging device is closed or stopped. If 1 Flexible or curved forms of proper radius, made of
different kinds or classes of aggregates are weighed either metal or wood, shall be supplied for use on curves
cumulatively into the same hopper, control and interlock of 30m radius or less. Straight side forms shall be of metal.
shall be provided with respect to each increment of mass, They shall be of adequate cross section and supplied in
as required for material weighed into an individual hopper. sections not less than 3m in length. They shall have a
Mixing water and admixture may be measured height not less than the edge thickness of the pavement to
volumetrically. be constructed, a base width equal to or greater than the
9 Automatic batching equipment for weighing or height and not less than 6mm in thickness, except that a
measuring batch quantities in increments shall be minimum thickness of 5mm will be permitted if the form is
provided with an automatic repeater having a counter that of trapezoidal cross section. They shall have flange braces
can be set for the number of increments required and extending outward on the base not less than 2/3 the
allowing the required number of increments to be height of the form and spaced not more than 1.5m apart.
accurately delivered and discharged into each batch. Sections shall have a steel pin at each end and at least one
intermediate pin; provision shall be made to lock pins to a
10 The batching system shall be activated by a single
true grade. Locked joints shall be provided between form
starting mechanism and be completely interlocked so that
the discharge gates or valves can open only when the
mixer is in the proper position for receiving material.
11 The interlocking system shall allow the batch to enter
the mixer so that some water is in advance of the

♦ 19-9 ♦
copy 249
sections which are free from play or movement and which 19.15.3 Mechanical Concrete Spreaders and
provide support and connection. Finishers
2 Forms shall withstand impact and vibration of the
compacting and finishing equipment without visible 1 When pavement forms are used, mechanical
springing or settlement. They shall be straight edged and spreaders shall operate on the forms and when formless
free from warp. Forms with an upper edge out more than paving is constructed they shall operate on wheels or
1mm in 1.5m from a straight line will be rejected. The tracks. Spreaders shall be self-propelled and capable of
longitudinal axis of an upstanding leg shall not vary more spreading the concrete mix to the desired cross sections.
than 2mm in 1m from a straight line. They shall be easily adjustable to spread different
thicknesses of concrete.
3 When used, wood forms not of marine ply shall be
made of well seasoned, surfaced plank not less than 2 Full width vibrators of the surface pan type, or
50mm nominal thickness, and shall be the full depth of the internal type with multiple spuds, may be attached to the
concrete slab. Provision shall be made for rigid, smooth spreader finishing machine or may be mounted on a
connections and suitable means for securely fastening in separate carriage but shall not come in contact with joints,
place to lines and profiles given. load transfer devices, reinforcement, subgrade, subbase
or side forms. Vibrating impulses shall be applied through
4 The supply of forms shall be sufficient to permit their
apparatus designed for this purpose, and constructed to
remaining in place not less than 48 hours after concrete
operate satisfactorily ahead of the finishing machine.
has been placed, or longer if deemed necessary by the
Vibratory impulses shall be transmitted through the
Engineer.
concrete with sufficient intensity to compact it throughout
5 Mechanical form graders, if used, shall be so its entire depth and width. The pavement vibrator shall not
designed that they may be adjusted and controlled to cut be used to level or spread pavement concrete.
to a given profile and produce a subgrade for the
3 Surface pan vibrators shall be designed so that
pavement forms or for slip-form paver track as shown on
vibrating impulses are applied directly to the surface of
the drawings.
the concrete. They shall be equipped with at least two
vibrating elements for each 3m width of pavement
19.15.2 Subgrade Preparation Equipment vibrated. The operating frequency shall be not less than
50Hz.
1 Subgrade planers shall be of steel and shall be
mounted on rollers when forms are used, or wheels or 4 Internal vibrators shall be of a suitable design with a
tracks when slip-form paving is being employed. They minimum operating frequency of 100Hz. Vibrating
shall be equipped with steel cutting edges or cutting elements shall be so spaced that the concrete will be
rollers so designed that they may be accurately adjusted compacted throughout its entire depth and width, with a
vertically. A subgrade planer shall be of sufficient mass so maximum vibrator spacing of 600mm.
as not to rise under pressure from the material being 5 Finishing machines shall be power driven and
planed. The subgrade planer shall be capable of producing equipped with at least 2 screeds fully and accurately
cross sections in accordance with the Drawings and shall adjustable to produce a crowned, sloping or flat surface as
develop a centre deflection of not more than 3mm. required. They shall be designed and operated to strike off,
2 Subgrade finishing machines shall be of steel screed and compact. The machine shall have ample
mounted on crawler tracks and shall be equipped with strength and sufficient power, and be geared to operate
steel cutting edges so designed that they may be consistently and smoothly.
accurately adjusted vertically and held in place firmly. The 6 Concrete finisher floats shall be either self-propelled
subgrade machines shall weigh not less than 3175kg and or attached to the finishing machine. They shall be fitted
have such strength and rigidity that changing the supports with independent wheels which ride on the forms and be
from wheels to centre will develop a deflection of not of sufficient mass not to flex under the pressure of
more than 3mm. concrete. The floats shall be easily adjustable from crown
3 Heavy subgrade templates shall be made of steel and to flat. They shall be at least 750mm long with at least
designed so that they can be moved backwards and 600mm in contact with the concrete. They shall be
forwards in a vertical position. They shall be mounted on designed to prevent tearing of the concrete surface or
rollers, wheels or tracks, adjustable vertically, and have a rolling of the aggregate under the float. The float pan shall
total mass not less than 225kg for widths of 5m or more. be suspended from the frame, and be capable of
Test points shall be spaced not more than 150mm centre adjustment in both height and width. Once adjusted, it
to centre and be adjustable so that they may be set to shall hydraulically or by other suitable means be raised
conform to the cross section of the subgrade. from the operator's platform. When lowered it shall
automatically return to its present position.
4 Water supply equipment shall be of such capacity
and design as to provide an ample supply and adequate
pressure simultaneously for all the requirements of
machinery, mixing, curing, wetting subgrade and other
features of the work.

♦ 19-10 ♦
copy 249
7 Longitudinal float machines shall be so constructed quality bass or bassine fiber not more than 120mm in
that travel of the floating mechanism can be adjusted to length. The handle shall be at least 300mm longer than
conform to the pavement cross section shown on the half the width of the slab and be readily adjustable.
Drawings or formed by the finishing machine. 10 Edging tools shall have a radius of 6mm.
8 Formless pavers shall be self-propelled and fitted
with suitable devices for distributing, finishing and 19.16 Method of Measurement and
spreading concrete to the full-width and thickness as
Basis of Payment
shown on the Drawings. The tracks shall be of sufficient
length and width to properly support the machine and its
1 Plant and equipment used in the works will not be
load without causing depressions. They shall be equipped
separately measured for payment, unless provided under
with a strike-off screed and internal vibrators of sufficient
a Dayworks arrangement, but will be considered
quantity to provide complete compaction regardless of the
subsidiary to the construction work items for which they
depth of concrete placed.
are being used and which are contained in the Bill of
Quantities.
19.15.4 Miscellaneous Minor Equipment for
Concrete Pavements
1 Hand vibrators shall be of the internal type,
adequately powered to operate under full load at a
frequency of at least 75Hz and shall have an intensity and
period of vibration sufficient to obtain thorough
compaction of concrete.
2 Headers shall be shaped to conform to the cross
section shown on the Drawings. They shall be of wood or
metal and of sufficient thickness and rigidity to provide a
vertical construction joint. Headers for continuous
reinforced pavement shall be of wood or metal, split
longitudinally to provide for the proper depth of
continuous reinforcing steel in accordance with the
Drawings.
3 Footbridges shall be durably constructed, readily
movable and so designed that no part of the bridge will
come in contact with the pavement at any time.
4 Hand operated longitudinal floats shall be not less
than 3.5m in length and 150mm in width. Floats shall be
properly stiffened to prevent flexing and warping, and be
provided with handles.
5 Long-handled floats shall have a blade at least 1m
long and 150mm wide. The handle shall be long enough
to permit operation of the float from the shoulder.
6 Vibrating screeds used to strike off and compact
concrete by the hand method shall be durably constructed,
and shaped to provide the cross section shown on the
Drawings. They shall be 600mm longer than the width of
the pavement, sufficiently strong and rigid to retain shape
under all working conditions and be provided with
handles. If of wood, they shall be at least 70mm thick and
steel shod.
7 Standard 3m straightedges shall be made of suitable
material and maintained in accurate alignment. They shall
be fitted with a handle long enough to permit operation of
the straightedge from the shoulder.
8 Belts shall be of canvas or canvas/rubber
composition, 2 to 4 ply, at least 150mm wide and 600mm
longer than the width of pavement.
9 Brooms shall be of the push type at least 450mm
wide. They shall contain no more than 3 rows of good

♦ 19-11 ♦
copy 249
copy 249
Ref. Title Page No.

20.1 Preamble 20-1


20.1.1 Materials 20-1
20.1.2 Quantities 20-1
20.1.3 Descriptions 20-1
20.1.4 Symbols, Abbreviations
and Definitions 20-2
20.1.5 Work of Special Types 20-3

copy 249
copy 249
20.1 Preamble apply. General directions and descriptions of
items of work given elsewhere in the Tender
Documents are not generally repeated in the
20.1.1 Materials Bill of Quantities. Reference must be made to
the Drawings, Specification and Conditions of
a) The rules contained in this Method of Contract for this information
Measurement apply equally to both proposed
b) Dimensions are stated in descriptions generally
and executed works.
in the sequence length, width, height. Where
b) The Bills of Quantities are to be read and ambiguity could arise, the dimensions are
construed in association with the Drawings, the identified.
Specification and this Method of Measurement.
Information which is given on the Drawings c) Dimensions given in descriptions are in
and/or in the Specification is identified by millimetres unless otherwise indicated.
cross-references included in the descriptions of
d) Unless otherwise specifically stated in the Bill
work in the Bills of Quantities.
of Quantities or herein, the costs of the
c) Where work cannot be fully described or where following are deemed to be included in the
the quantity of work required cannot be rates for measured work:
accurately determined, it is given as a unit and
priced as a Provisional Sum. (P.S.) i. Labor and all costs in connection
therewith, including transport,
d) Unless the term meter, used in this Method of
Measurement, is preceded by the words square ii. Materials, products, goods and all costs in
or cubic it is deemed to be linear. connection therewith including transport,

20.1.2 Quantities iii. Contractor’s equipment and temporary


works, including but not limited to
construction plant, scaffolding, tools,
a) Quantities set out in the Bills of Quantities are
vehicles and the like, and all costs in
the estimated quantities and they shall not be
connection therewith, including
taken as the actual and correct quantities for
maintaining, adapting, relocating, clearing
ordering or purchasing of materials.
away and making good,
b) Works shall be measured net as fixed in
iv. assembling, fitting and fixing materials,
position in accordance with the rules contained
products and goods in position,
in this Method of Measurement or except
where otherwise stated in a measurement rule v. any method of fixing, fixing to any nature
applicable to the work. of base or background including
preparation and providing fixing
c) Dimensions used in calculating quantities are
materials,
taken to the nearest 1 mm. (i.e. 0.5 mm and
over is regarded as 1 mm. Less than 0.5 mm is vi. breaking down for transport and
disregarded). installation and subsequent re-assembly
of composite items manufactured off site,
d) Quantities measured in tonnes are given to
three (3) places of decimals. Other quantities vii. waste of materials, and for consumable
are given to the nearest whole unit except that materials.
any quantity less than one unit is given as one
unit. viii. square, raking and curved cutting,

e) Unless otherwise stated, where minimum ix. work at any location or height,
deductions for voids are dealt with in this
x. work in small, isolated quantities,
Method of Measurement they refer only to
openings which are within the boundaries of xi. protection of all work,
measured areas. Openings which are at the
boundaries of measured areas are always xii. protection of all existing structures,
deducted irrespective of size. utilities, site improvements, trees and
vegetation, features, pavements and other
facilities on and adjacent to the site,
20.1.3 Descriptions
which are to remain upon completion of
the work,
a) Headings to groups of items in the Bill of
all other enabling tasks, associated and
Quantities are to be read as part of the
subsidiary components and items of
descriptions of the items to which the headings

♦ 20-1 ♦
copy 249
work, which are indicated or reasonably xviii. setting out and survey work as required in
inferred from the Drawings and/or the the Contract,
Specification and necessary to perform
xix. samples of materials and testing of
and complete the work described,
materials, including providing equipment
xiii. establishment and overhead charges and for testing,
profit.
xx. design drawings, working drawings, road
e) Except where items are included in the Bill of cross sections, shop drawings, co-
Quantities and are priced separately by the ordination, installation and as-built record
Contractor therein, the costs of the following drawings, operation and maintenance
are deemed to be included in the rates for manuals and the like,
measured work:
xxi. preparation and submittal of reports,
i. site administration and security, records, certificates, notices, proposals,
designs, details, calculations and other
ii. insurances,
information and data required by the
iii. bonds and guarantees, Specification,

iv. water for the works, xxii. cost of work items for which there are no
direct payments and which are
v. lighting and power for the works, considered in the Specification and other
contract documents as subsidiary to other
vi. temporary facilities and temporary
items in the Bill of Quantities,
accommodation for the use of the
Contractor and the Engineer, xxiii. allowance in unit rates for all other
requirements services, provisions,
vii. temporary telephones, faxes and
liabilities and obligations contained in the
photocopying equipment for the use of
General Requirements and Conditions of
the Contractor and the Engineer, and the
Contract.
cost of local calls,

viii. temporary roads, hardstandings, 20.1.4 Symbols, Abbreviations and


crossings and the like, Definitions
ix. temporary fencing, hoardings, screens,
a) The following symbols and abbreviations are
fans, foot- ways, guardrails, gantries and
used in this Method of Measurement and in the
the like,
Bills of Quantities:
x. giving notices and making applications to
lin.m. = linear meter
all Concerned Authorities and owners,
including the payment of fees, royalties, sq.m = square meter
taxes and charges in connection
therewith, cu.m = cubic meter

xi. safety, health and welfare of workpeople, cm = centimeter

xii. compliance with traffic regulations, mm = millimeter

xiii. maintenance of public and private roads, nr = number


services and adjoining property, kg = kilogramme
xiv. control of noise and pollution, prevention t = tonne (metric)
of fire and compliance with all other
statutory and general obligations, % = percentage

xv. removing rubbish, protective casings and L.S. = lump sum


coverings and cleaning the works on
dn = nominal diameter
completion,
Qty = quantity
xvi. drying the works,
Drg = drawing.
xvii. testing and commissioning of service
installations including providing fuel, Mpa = Mega Pascal

PS = Provisional Sum

♦ 20-2 ♦
copy 249
b) The following definitions apply to all work:

i. 'horizontal' means level or sloping work


not exceeding 15 degrees from the
horizontal,

ii. 'sloping' means sloping work exceeding


15 degrees but not exceeding 80 degrees
from the horizontal,

iii. 'vertical' means work exceeding 80


degrees from the horizontal,

iv. 'curved' means curved in any direction or


in more than one direction and to any
radius or radii, and includes curved work
to domes, vaults and the like.

20.1.5 Work of Special Types

a) Work of each of the following special types is


separately identified:

i. work on or in existing buildings (i.e.


buildings existing before the current
project),

ii. work to be carried out and subsequently


removed (other than temporary works),

iii. work outside the boundaries of the site,

iv. work carried out in, or under, water (i.e.


canal, river or sea water),

v. work carried out in compressed air.

♦ 20-3 ♦
copy 249
copy 249
PROJECT TITLE
Subsection (If necessary)
BILL OF QUANTITIES
BILL (I) PRELIMINARIES

Unit Rate Amount


Estimated
Item No Description Unit R.O. Bz R.O. R.O.
Quantity Bz Bz
(Omani (Omani (Number) (Words)
(Number) Omani Baiza (Words) Omani Baiza
Riyal) Baiza) Omani Riyal Omani Riyal

CONDITIONS OF CONTRACT
The Contractor is deemed to have carefully studied and understood and taken
into account the provisions and requirements of the General and Particular
Conditions of Contract. The rates and prices stated in the Bill of Quantities shall
include for all costs of compliance with the Conditions except for the costs of
the items given in this Section 1 and for which a separate amount is stated
herein.

1 GENERAL

1.3 Project Site


1.3.5(i) Soil investigation and report LS

1.4 Contractor's Site Facilities


1.4.3(i) Mobilization and demobilization of Contractor's
Contractor s site facilities LS
1.4.3(ii) Maintenance of Contractor's site facilities month

1.5 Engineer's Facilities


1.5.13(i) Provision of Engineer's offices (type) (No of units) month
1.5.13(ii) Maintenance of Engineer's offices (type) (No of units) month
1.5.13(ii) Provision of surveying equipment for the Engineer month
1.5.13(iv) Maintenance of surveying equipment for the Engineer month
1.5.13(v) Provision of Engineer's accommodation (type) (No of units) month
1.5.13(vi) Maintenance of Engineer's accommodation (type) (No of units) month
1.5.13(vii) Provision of site laboratory (type) month
1.5.13(viii) Maintenance of site laboratory month

page I-I CARRIED TO SUMMARY

copy 249
Oman Standard Specifications for Road and Bridge Construction 2010
PROJECT TITLE
Subsection (If necessary)
BILL OF QUANTITIES
BILL (I) PRELIMINARIES (continued)

Unit Rate Amount


Estimated
Item No Description Unit R.O. Bz R.O. R.O.
Quantity Bz Bz
(Omani (Omani (Number) (Words)
(Number) Omani Baiza (Words) Omani Baiza
Riyal) Baiza) Omani Riyal Omani Riyal

1 GENERAL (continued)

1.7 Control of Traffic and Access


1.7.6(i) Maintenance and protection of traffic month
1.7.6(ii) Supply and compaction of sub-base on diversions where ordered
by the Engineer cu. m
Supply and compaction of bituminous base course on diverions where ordered
1.7.6(iii) cu.m.
by the Engineer
1.7.6.(iv) Prime coat (rate of application) sq.m.

1.10 Management Procedures


1.10.6(i) Provision of five sets of photographs as specified month
1.10.6(ii) Provision of two sets of video recordings as specified month

1.11 Submittals
Provision of As-built drawings, record drawings, record specifications and
1.11.8(i) LS
miscellaneous records as specified

1.14 Contractor's Temporary Works and Services


1.14.7(i) Provision, erection, relocation, maintenance and removal of
project signboards (type) nr

1.15 Commemorative Plaque and Opening Ceremony


1.15.4(i) Provision and erection of commemorative plaque LS
1.15.4(ii) Opening ceremony including all facilities LS

page I-II CARRIED TO SUMMARY

copy 249
Oman Standard Specifications for Road and Bridge Construction 2010
PROJECT TITLE
Subsection (If necessary)
BILL OF QUANTITIES
BILL (I) PRELIMINARIES SUMMARY
Amount
Item No Description R.O. R.O.
Bz Bz
(Number) (Words)
(Number) Omani Baiza (Words) Omani Baiza
Omani Riyal Omani Riyal

SUMMARY
Page I-I
Page I-II

page I-III CARRIED TO GRAND SUMMARY

copy 249
Oman Standard Specifications for Road and Bridge Construction 2010
copy 249
PROJECT TITLE
Subsection (If necessary)
BILL OF QUANTITIES
BILL (II) EARTHWORKS

Unit Rate Amount


Estimated
Item No Description Unit R.O. Bz R.O. R.O.
Quantity Bz Bz
(Omani (Omani (Number) (Words)
(Number) Omani Baiza (Words) Omani Baiza
Riyal) Baiza) Omani Riyal Omani Riyal

2 EARTHWORKS

2.1 Clearing and Grubbing


2.1.5 (i) Clearing and Grubbing sq.m.
2.1.5 (ii) Removal and delivery of trees of 300mm trunk diameter or greater nr.

2.2 Removal of Structures and Obstructions


2.2.5 (i) Removal of existing building (type and description) nr.
2.2.5 (ii) Removal of reinforced concrete (type, location, dimensions) cu.m.
2.2.5 (iii) Removal of mass concrete (type, location, dimensions) cu.m.
2.2.5 (iv) Removal of prestressed concrete (type, location, dimensions) cu.m.
2.2.5 (v) Removal of curbs lin.m.
2.2.5 (vi) Removal of tiles sq.m.
2.2.5 (vii) Removal of pipe culverts (diameter) lin.m.
2.2.5 (viii) Removal of existing pavement (description, type) cu.m.
2.2.5 (ix) Removal of reusable Road Studs nr.
2.2.5 (x) Removal of steel safety barrier including posts and foundations lin.m.
2.2.5 (xi) Removal of concrete barrier lin.m.
2.2.5 (xii) Removal of sign boards (size) nr.
2.2.5 (xiii) Removal of floodway marker posts and foundations nr.
2.2.5 (xiv) Removal of reusable concrete safety barrier lin.m.
2.2.5 (xv) Removal of re-usable steel safety barrier (dims) (type) lin.m.
2.2.5 (xvi) Removal of re-usable sign board , posts and foundations (size) nr.
2.2.5 (xvii) Removal of re-usable sign crossing marker posts nr.
2.2.5 (xviii) Removal of drainage protection works (type) cu.m.
2.2.5 (xix) Removal of existing fences and gates (description, type, ) lin.m.
2.2.5 (xx) Removal of existing block and masonry walls cu.m.
2.2.5 (xxi) Removal of ditches (type/size) lin.m.
2.2.5 (xxii) Removal of bridges (type, description and dimensions) nr.
2.2.5 (xxiii) Removal of rocks/boulders larger than 0.2 cu.m. or 500 kg (description) cu.m.
2.2.5 (xxiv) Removal of wells and shafts (description and location) nr.
2.2.5 (xxv) Removal of sand dunes (location) (description) cu.m.
2.2.5 (xxvi) Removal of lighting poles, cable and foundations (size) nr.

page II-I CARRIED TO SUMMARY

copy 249
Oman Standard Specifications for Road and Bridge Construction 2010
PROJECT TITLE
Subsection (If necessary)
BILL OF QUANTITIES
BILL (II) EARTHWORKS (continued)

Unit Rate Amount


Estimated
Item No Description Unit R.O. Bz R.O. R.O.
Quantity Bz Bz
(Omani (Omani (Number) (Words)
(Number) Omani Baiza (Words) Omani Baiza
Riyal) Baiza) Omani Riyal Omani Riyal

2 EARTHWORKS (continued)

2.3 Roadway Excavation


2.3.6 (i) Unclassified excavation cu.m.
2.3.6 (ii) Excavation of unstable material outside Right-of-Way cu.m.
2.3.6 (iii) Unclassified excavation under water cu.m.
2.3.6 (iv) Excavate and stockpile suitable topsoil and recompact as directed cu.m.

2.4 Borrow Materials


2.4.6 (i) Borrow excavation cu.m.

2.6 Sub-grade Construction


2.6.6 (i) Subgrade preparation in cut sq.m.
2.6.6 (ii) Drainage blanket cu.m.
2.6.6 (iii) Subgrade construction on Sabkha sq.m.
2.6.6 (iv) Subgrade construction on top of dune sand sq.m.

2.7 Excavation and Backfilling for Structures


2.7.6 (i) Unclassified structural excavation (depth 0 to 2.0m) cu.m.
2.7.6 (ii) Unclassified structural excavation (depth > 2.0m <4.0m) cu.m.
2.7.6 (iii) Unclassified structural excavation (depth > 4.0m) cu.m.
2.7.6 (iv) Unclassified structural excavation (under water) cu.m.

2.8 Earthwork for Pipe Trenches


2.8.6.(i) Trench excavation and backfilling (depth 0 to 2.0m) cu.m.
2.8.6.(ii) Trench excavation and backfilling (depth > 2.0m < 3.0m) cu.m.
2.8.6.(iii) Trench excavation and backfilling (depth >3.0m < 4.0m) cu.m.
2.8.6.(iv) Trench excavation and backfilling (depth > 4m) cu.m.

page II-II CARRIED TO SUMMARY

copy 249
Oman Standard Specifications for Road and Bridge Construction 2010
PROJECT TITLE
Subsection (If necessary)
BILL OF QUANTITIES
BILL (II) EARTHWORKS SUMMARY

Amount
Item No Description R.O. R.O.
Bz Bz
(Number) (Words)
(Number) Omani Baiza (Words) Omani Baiza
Omani Riyal Omani Riyal

SUMMARY
Page II-I
Page II-II

page II-III CARRIED TO GRAND SUMMARY

copy 249
Oman Standard Specifications for Road and Bridge Construction 2010
copy 249
PROJECT TITLE
Subsection (If necessary)
BILL OF QUANTITIES
BILL (III) GRANULAR SUB-BASE, AGGREGATE BASE COURSE AND STABILIZED BASE COURSES

Unit Rate Amount


Item Estimated
Description Unit R.O. Bz R.O. R.O.
No Quantity Bz Bz
(Omani (Omani (Number) (Words)
(Number) Omani Baiza (Words) Omani Baiza
Riyal) Baiza) Omani Riyal Omani Riyal

3 GRANULAR SUB-BASE, AGGREGATE BASE COURSE


AND STABILIZED BASE COURSES.

3.2 Granular Sub-base Course


3.2.6 (i) Granular sub-base course (Class A) cu.m.
3.2.6 (ii) Granular sub-base course (Class B) cu.m.
3.2.6 (iii) Granular sub-base course (Class C) cu.m.

3.3 Aggregate Base Course


3.3.6 (i) Aggregate base course (Class A) cu.m.
3.3.6 (ii) Aggregate base course (Class B) cu.m.
3.3.6 (iii) Aggregate base course (Class C) cu.m.

3.4 Stabilized Base Courses


3.4.6 (i) Cement stabilized base course (thickness) cu.m.
3.4.6 (ii) Bitumen stabilized base course (thickness) cu m
cu.m.
3.4.6 (iii) Lime stabilized base course (thickness) cu.m.
3.4.6 (iv) Curing seal cu.m.

page III-I CARRIED TO SUMMARY

copy 249
Oman Standard Specifications for Road and Bridge Construction 2010
PROJECT TITLE
Subsection (If necessary)
BILL OF QUANTITIES
BILL (III) GRANULAR SUB-BASE, AGGREGATE BASE COURSE AND STABILIZED BASE COURSES

Amount
Item
Description R.O. R.O.
No Bz Bz
(Number) (Words)
(Number) Omani Baiza (Words) Omani Baiza
Omani Riyal Omani Riyal

SUMMARY
Page III-I

page III-II CARRIED TO GRAND SUMMARY

copy 249
Oman Standard Specifications for Road and Bridge Construction 2010
PROJECT TITLE
Subsection (If necessary)
BILL OF QUANTITIES
BILL (IV) BITUMINOUS PAVEMENT

Unit Rate Amount


Item Estimated
Description Unit R.O. Bz R.O. R.O.
No Quantity Bz Bz
(Omani (Omani (Number) (Words)
(Number) Omani Baiza (Words) Omani Baiza
Riyal) Baiza) Omani Riyal Omani Riyal

4 BITUMINOUS PAVEMENT

4.2 Bituminous Materials for Prime and Tack Coats


4.2.8 (i) Bituminous prime coat sq.m.
4.2.8 (ii) Bituminous tack coat sq.m.
4.2.8 (iii) Polymer modified tack coat sq.m.

4.4 Bituminous Base Course


4.4.14 (i) Bituminous base course (Class A/B) cu.m.
4.4.14 (ii) Polymer modified bituminous base course (Class A/B) cu.m.

4.5 Bituminous Binder and Wearing Courses


4.5.14 (i) Bituminous binder course cu.m.
4.5.14 (ii) Bituminous wearing course (Class A/B)) cu.m.
4.5.14 (iii) Polymer modified bituminous binder course cu.m.
4.5.14 (iv) Polymer modified bituminous wearing course (Class A/B ) cu.m.

4.6 Bituminous Seal Coats - Surface Dressing


4.6.10 (i) Single bituminous surface treatment sq.m.
4.6.10 (ii) Double bituminous surface treatment sq.m.
4.6.10 (iii) Bituminous slurry seal coat sq.m.

4.7 Bituminous Leveling Course and Patching Work


4.7.14 (i) Bituminous leveling course cu.m.
4.7.14 (ii) Bituminous patching work cu.m.

4.8 Bituminous Cold Mix Courses


4.8.14 (i) Bituminous cold mix course cu.m.

4.9 Pavement Repairs and Reinstatement


4.9.10 (i) Surface milling sq.m.
4.9.10 (ii) Crack sealing lin.m.
4.9.10 (iii) Pavement repairs (overlay and surface preparation) sq.m.
4.9.10 (iv) Pavement repairs (complete reconstruction) sq.m.
4.9.10 (v) Trench reinstatement sq.m.

page IV-I CARRIED TO SUMMARY

copy 249
Oman Standard Specifications for Road Bridge Construction 2010
PROJECT TITLE
Subsection (If necessary)
BILL OF QUANTITIES
BILL (IV) BITUMINOUS PAVEMENT (continued)

Unit Rate Amount


Item Estimated
Description Unit R.O. Bz R.O. R.O.
No Quantity Bz Bz
(Omani (Omani (Number) (Words)
(Number) Omani Baiza (Words) Omani Baiza
Riyal) Baiza) Omani Riyal Omani Riyal

4 BITUMINOUS PAVEMENT (continued)

4.10 Pavement Widening


4.10.6 (i) Pavement widening sq.m.

4.11 Recycled Bituminous Mixes


4.11.14 (i) Recycled bituminous base course cu.m.

4.12 Surface Rideability Measurement


4.12.10 (i) International roughness index (IRI) for bituminous pavement lin.m
4.12.10 (ii) International roughness index (IRI) for concrete pavement lin.m

page IV-II CARRIED TO SUMMARY

copy 249
Oman Standard Specifications for Road Bridge Construction 2010
PROJECT TITLE
Subsection (If necessary)
BILL OF QUANTITIES
BILL (IV) BITUMINOUS PAVEMENT SUMMARY

Amount
Item
Description R.O. R.O.
No Bz Bz
(Number) (Words)
(Number) Omani Baiza (Words) Omani Baiza
Omani Riyal Omani Riyal

SUMMARY
Page IV-I
Page IV-II

page IV-III CARRIED TO GRAND SUMMARY

copy 249
Oman Standard Specifications for Road Bridge Construction 2010
copy 249
PROJECT TITLE
Subsection (If necessary)
BILL OF QUANTITIES
BILL (V) CONCRETE AND CONCRETE STRUCTURES

Unit Rate Amount


Item Estimated
Description Unit
No Quantity R.O. Bz R.O. R.O. Bz Bz
(Omani Riyal) (Omani Baiza) (Number) - Omani Riyal (Words) - Omani Riyal (Number) Omani Baiza (Words) Omani Baiza

5 CONCRETE AND CONCRETE STRUCTURES

5.1 Concrete Materials and Mixes


5.1.7 (i) Concrete (Class) in (type of structure), (location) and (finish) cu.m.

5.2 Reinforcing Steel


5.2.6 (i) Mild steel bar reinforcement of any diameter t.
5.2.6 (ii) High tensile steel bar reinforcement of any diameter t.
5.2.6 (iii) Fabric wire mesh reinforcement of any size t.

5.4 Prestressed Concrete Structures


5.4.6 (i) Prestressing wires (state size and type) t.
5.4.6 (ii) Prestressing strands (state size and type) t.
5.4.6 (iii) Prestressing bars (state size and type) t.

5.7 Cement Concrete Pavement


5.7.6 (i) Unreinforced cement concrete pavement cu.m.
5.7.6 (ii) Reinforced cement concrete pavement cu.m.

5.10 Waterproofing for Structures


5.10.6 (i) Tar or bituminous paint (state type, number of coats) sq.m.
5.10.6 (ii) Membrane waterproofing (state type, thickness) sq.m.
5.10.6 (iii) Epoxy coating to internal surfaces of concrete (state type, thickness) sq.m.

5.12 Load Testing of Bridges


5.12.7 (i) Bridge Loading Test nr.

6 STRUCTURAL STEEL AND OTHER METAL WORK

6.6 (i) Structural Steel (grade) t.


6.6 (ii) Railings (type) (height) lin.m.

7 PAINT

7.6 (i) Painting of Existing Concrete Structure (type) (Structure Reference) sq.m.
7.6 (ii) Painting of Existing Steel Structure (type) (Structure Reference) sq.m.
7.6 (iii) Painting of Existing Steel Railings (type) (Structure Reference) lin.m.

page V-I CARRIED TO SUMMARY

copy 249
Oman Standard Specifications for Road and Bridge Construction 2010
PROJECT TITLE
Subsection (If necessary)
BILL OF QUANTITIES
BILL (V) CONCRETE AND CONCRETE STRUCTURES (continued)

Unit Rate Amount


Item Estimated
Description Unit
No Quantity R.O. Bz R.O. R.O. Bz Bz
(Omani Riyal) (Omani Baiza) (Number) - Omani Riyal (Words) - Omani Riyal (Number) Omani Baiza (Words) Omani Baiza

8 DRAINAGE

8.1 Pipe Culverts


8.1.6 (i) Unreinforced precast concrete pipe culvert (diameter) lin.m.
8.1.6 (ii) Reinforced precast concrete pipe culvert (diameter) lin.m.
8.1.6 (iii) Reinforced precast concrete arch culvert (size) lin.m.
8.1.6 (iv) Reinforced precast concrete elliptical culvert (size) lin.m.
8.1.6 (v) Corrugated steel pipe culvert (diameter) (coating) lin.m.
8.1.6 (vi) Corrugated steel pipe arch culvert (size) (coating) lin.m.
8.1.6 (vii) Cast in-situ concrete pipe or arch culverts (state type) lin.m.

8.2 Storm Sewers


8.2.6 (i) Storm sewer (type) (diameter) lin.m.

8.3 Manholes and Inlets


8.3.6 (i) Manhole (size and type) nr.
8.3.6 (ii) Grated Inlet (type) nr.
8.3.6 (iii) Curb inlet (type) nr.
8.3.6 (iv) Ditch inlet (type) nr.
8.3.6 (v) Ditch outlet (type) nr.
8.3.6 (vi) Grated Channel (width and depth) lin.m.

8.4 Drainage of Structures


8.4.6 (i) Gully grate and frame (type) nr.
8.4.6 (ii) Drainage pipe in structure (type) (diameter) (location) lin.m.
8.4.6 (iii) Permeable backing sq.m.
8.4.6 (iv) Granular backfill cu.m.

10 PILING

10.1 Piling General


10.1.6 (i) Setting up at each pile nr.
10.1.6 (ii) Piling (type)(length)(size) lin.m.
10.1.6 (iii) Expendable piles (type)(length)(size) lin.m.

10.2 Pile Testing


10.2.6 (i) Static load testing of expendable piles (type)(length)(size) nr.
10.2.6 (ii) Static load testing of working piles (type)(length)(size) nr.
10.2.6 (iii) Non-destructive Integrity Test (type) nr.

page V-II CARRIED TO SUMMARY

copy 249
Oman Standard Specifications for Road and Bridge Construction 2010
PROJECT TITLE
Subsection (If necessary)
BILL OF QUANTITIES
BILL (V) CONCRETE AND CONCRETE STRUCTURES (continued)

Unit Rate Amount


Item Estimated
Description Unit
No Quantity R.O. Bz R.O. R.O. Bz Bz
(Omani Riyal) (Omani Baiza) (Number) - Omani Riyal (Words) - Omani Riyal (Number) Omani Baiza (Words) Omani Baiza

11 BRIDGE ACCESSORIES

11.1 Bearings – General


11.1.6 Bridge Bearing (type), vertical and horizontal loads (kN), movement (mm) nr.

11.2 Elastomeric Bearings


11.2.6 Elastomeric Bearing (type), vertical and horizontal loads (kN) nr.

11.3 Pot Bearings


11.3.6 Pot Bearing (type), vertical and horizontal loads (kN), movement (mm) nr.

11.4 Bridge Expansion Joints


11.4.6 (i) Buried Joint Movement range ( ) lin.m.
11.4.6 (ii) Elastomeric (waterproof) Joint Movement range ( ) lin.m.
11.4.6 (iii) Modular joint with neoprene insert Movement range ( ) lin.m.
11.4.6 (iv) Metallic finger joint with neoprene insert Movement range ( ) lin.m.
11 4 6 (v) Metallic finger joint no insert Movement range ( )
11.4.6 lin m
lin.m.
11.4.6 (vi) Asphaltic Plug Joint Movement range ( ) lin.m.

11.6 Bridge Parapets and Railings


11.6.6 (i) Concrete bridge parapet (state type) lin.m.
11.6.6 (ii) Concrete bridge parapet with metal rail (state type) lin.m.
11.6.6 (iii) Steel bridge parapet lin.m.
11.6.6 (iv) Aluminum bridge parapet lin.m.
11.6.6 (v) Steel pedestrian railing lin.m.
11.6.6 (vi) Aluminum pedestrian railing lin.m.

page V-III CARRIED TO SUMMARY

copy 249
Oman Standard Specifications for Road and Bridge Construction 2010
PROJECT TITLE
Subsection (If necessary)
BILL OF QUANTITIES
BILL (V) CONCRETE AND CONCRETE STRUCTURES SUMMARY

Amount
Item
Description R.O. R.O.
No Bz Bz
(Number) Omani (Words) Omani
(Number) Omani Baiza (Words) Omani Baiza
Riyal Riyal

SUMMARY
Page V-I
Page V-II
Page V-III

page V-IV CARRIED TO GRAND SUMMARY

copy 249
Oman Standard Specifications for Road and Bridge Construction 2010
PROJECT TITLE
Subsection (If necessary)
BILL OF QUANTITIES
BILL (VI) INCIDENTAL CONSTRUCTION

Unit Rate Amount


Estimated
Item No Description Unit R.O. Bz R.O. R.O.
Quantity Bz Bz
(Omani (Omani (Number) (Words)
(Number) Omani Baiza (Words) Omani Baiza
Riyal) Baiza) Omani Riyal Omani Riyal

9 SLOPE PROTECTION AND STABILIZATION

9.1 Riprap
9.1.6 (i) Loose stone riprap (class) cu.m.
9.1.6 (ii) Mortared stone riprap (class) cu.m.
9.1.6 (iii) Filter material (thickness) sq.m.
9.1.6 (iv) Filter membrate sq.m.

9.2 Gabions
9.2.6 (i) Gabions (size) cu.m.
9.2.6 (ii) Mastic asphalt grout cu.m.
9.2.6 (iii) Sand-cement grout cu.m.

9.3 Slope Netting


9.3.6 (i) Wire netting slope protection sq.m.

9.4 Rock Bolts, Anchors and S


Sprayed C
Concrete
9.4.6 (i) Rock bolts lin.m.
9.4.6 (ii) Rock Anchors lin.m.
9.4.6 (iii) Shotcrete cu.m.
9.4.6 (iv) Gunite cu.m.
9.4.6 (v) Wire netting for shotcrete sq.m.
9.4.6 (vi) Reinforcing mesh sq.m.
9.4.6 (vii) Painting sq.m.

9.5 Rock Grouting


9.5.6 (i) Drillholes for grouting rock (diameter)(length) lin m
9.5.6 (ii) Rock grout cu.m.

9.6 Reinforced Concrete Slope Protection


9.6.6 (i) Reinforced concrete slope protection cu.m.

page VI-I CARRIED TO SUMMARY

copy 249
Oman Standard Specifications for Road and Bridge Construction 2010
PROJECT TITLE
Subsection (If necessary)
BILL OF QUANTITIES
BILL (VI) INCIDENTAL CONSTRUCTION (continued)

Unit Rate Amount


Estimated
Item No Description Unit R.O. Bz R.O. R.O.
Quantity Bz Bz
(Omani (Omani (Number) (Words)
(Number) Omani Baiza (Words) Omani Baiza
Riyal) Baiza) Omani Riyal Omani Riyal

9.7 Sacked Concrete Revetment


9.7.6 (i) Sacked concrete revetement cu.m.

9.8 Paving Tile Slope Protection


9.8.6 (i) Paving tile slope protection sq.m.

9.9 Ditch Lining


9.9.6 (i) Paving slab protection and ditch lining (type) (thickness) sq.m.
9.9.6 (ii) Grouted stone ditch lining (type) (thickness) sq.m.
9.9.6 (iii) Grouted stone wash checks (type) (thickness) sq.m.

9.10 Filter Layers


9.10.6 (i) Granular filter layer (thickness) sq.m.
9.10.6 (ii) Fabric membrane sq.m.

9 11 Barriers for Sand Dunes


9.11
9.11.6 (i) Fences for dune stabilization (type) (height) lin.m.
9.11.6 (ii) Bituminous stabilization of dunes sq.m.
9.11.6 (iii) Vegetative stabilization of dunes sq.m.
9.11.6 (iv) Dune stabilization with blankets sq.m.

9.12 Mechanically Stabilized Earth Retaining Walls


9.12.7 (i) Mechanically Stabilized Earth Retaining Walls (MSERWs) sq.m.
9.12.7 (ii) Standard Coping for MSERWs lin.m.
9.12.7 (iii) Concrete Barrier Parapet for MSERWs lin.m.

9.13 Coastal Protection


9.13.6 (i) Underlayer cu.m.
9.13.6 (ii) Quarry run cu.m.
9.13.6 (iii) Rock armour cu.m.
9.13.6 (iv) Dredging cu.m.
9.13.6 (v) Fabrics and Membranes (type) sq.m.

page VI-II CARRIED TO SUMMARY

copy 249
Oman Standard Specifications for Road and Bridge Construction 2010
PROJECT TITLE
Subsection (If necessary)
BILL OF QUANTITIES
BILL (VI) INCIDENTAL CONSTRUCTION (continued)

Unit Rate Amount


Estimated
Item No Description Unit R.O. Bz R.O. R.O.
Quantity Bz Bz
(Omani (Omani (Number) (Words)
(Number) Omani Baiza (Words) Omani Baiza
Riyal) Baiza) Omani Riyal Omani Riyal

12 SIDEWALKS, PAVED AREAS AND CURBS

12.1 Sidewalks, paved areas and curbs


12.1.7 (i) Precast concrete tile paving (type) sq.m.
12.1.7 (ii) Precast concrete block paving (type) sq.m.
12.1.7 (iii) Natural stone paving (type) sq.m.
12.1.7 (iv) In situ concrete paving (type) (thickness) sq.m.
12.1.7 (v) Precast concrete curb/edging,/channel (type and size) lin.m.
12.1.7 (vi) Cast in-situ curb (type) lin.m.

13 SAFETY BARRIERS AND FENCES

13.1 Roadside Barriers


13.1.7 (i) W-Beam Guardrail standard section (type) lin.m.
13.1.7 (ii) W-Beam Guardrail transition section (type) lin.m.
13 1 7 (iii)
13.1.7 W-Beam Guardrail terminal (end type) nr.
13.1.7 (iv) Thrie Beam Guardrail standard section lin.m.
13.1.7 (v) Thrie Beam Guardrail transition section lin.m.
13.1.7 (vi) Thrie Beam Guardrail terminal (end type) nr.
13.1.7 (vii) Concrete Barrier, single face (type) lin.m.
13.1.7 (viii) Concrete Barrier, double face (type) lin.m.
13.1.7 (ix) Concrete Barrier, transition section (type) lin.m.
13.1.7 (x) Impact Attenuator (type) nr.

13.2 Fences
13.2.7 (i) Chain link fence (type) (height) lin.m.
13.2.7 (ii) Fence (type) (height) lin.m.
13.2.7 (iii) Wire fence (type) (height) lin.m.
13.2.7 (iv) Gate (type) sq.m

page VI-III CARRIED TO SUMMARY

copy 249
Oman Standard Specifications for Road and Bridge Construction 2010
PROJECT TITLE
Subsection (If necessary)
BILL OF QUANTITIES
BILL (VI) INCIDENTAL CONSTRUCTION (continued)

Unit Rate Amount


Estimated
Item No Description Unit R.O. Bz R.O. R.O.
Quantity Bz Bz
(Omani (Omani (Number) (Words)
(Number) Omani Baiza (Words) Omani Baiza
Riyal) Baiza) Omani Riyal Omani Riyal

14 TRAFFIC SIGNS AND ROAD MARKINGS

14.1 Traffic Signs


14.1.7 (i) Highway sign, triangular, (height - mm) nr.
14.1.7 (ii) Highway sign, circular, (diameter - mm) nr.
14.1.7 (iii) Highway sign, rectangular - size (finished sign area) sq.m.
14.1.7 (iv) Highway sign, octgagonal, (height - mm) nr.
14.1.7 (v) Sign post support assembly including foundation (type) nr.
14.1.7 (vi) Breakaway sign post support assembly including foundation (type) nr.
14.1.7 (vii) Overhead sign support including foundation (type) nr.

14.2. Road Markings


14.2.6 (i) Traffic line (type) (material) (mechanical application) sq.m.
14.2.6 (ii) Raised rib road markings sq.m.
14.2.6 (iii) Special markings (type) (material) (hand applied) sq.m.
14.2.6 ((iv)) p g
Curb painting q
sq.m.
14.2.6 (v) Removal of markings sq.m.

14.3 Road Studs


14.3.6 (i) Reflecting road studs (type and colour) nr.
14.3.6 (ii) Non-reflecting road studs nr.

page VI-IV CARRIED TO SUMMARY

copy 249
Oman Standard Specifications for Road and Bridge Construction 2010
PROJECT TITLE
Subsection (If necessary)
BILL OF QUANTITIES
BILL (VI) INCIDENTAL CONSTRUCTION SUMMARY

Amount
Item No Description R.O. R.O.
Bz Bz
(Number) (Words)
(Number) Omani Baiza (Words) Omani Baiza
Omani Riyal Omani Riyal

SUMMARY
Page VI-I
Page VI-II
Page VI-III
Page VI-IV

page VI-V CARRIED TO GRAND SUMMARY

copy 249
Oman Standard Specifications for Road and Bridge Construction 2010
copy 249
PROJECT TITLE
Subsection (If necessary)
BILL OF QUANTITIES
BILL (VII) ROAD LIGHTING AND ELECTRICAL INSTALLATIONS

Unit Rate Amount


Estimated
Item No Description Unit R.O. Bz R.O. R.O.
Quantity Bz Bz
(Omani (Omani (Number) (Words)
(Number) Omani Baiza (Words) Omani Baiza
Riyal) Baiza) Omani Riyal Omani Riyal

15 ROAD LIGHTING AND ELECTRICAL INSTALLATIONS

15.1 General
15.1.20 (i) Power supply connection to the feeder pillar. nr.
15.1.20 (ii) Spare Parts (5%) as per the approved list LS.

15.2 Medium Voltage Switching Stations


15.2.6 (i) Medium voltage intake switching station (type) (voltage) (rating) (dwg) nr.

15.3 Package Sub-stations


15.3.6 (i) Package sub-station (type) (reference) (rating) (voltage) nr.

15.4 Package Medium Voltage Switching Stations


15.4.6 (i) Package medium voltage switching station (type) (reference) (voltage) nr.

15.5 33kV and 11kV Pole Mounted Transformer Sub Stations

Pole mounted transformer sub-station 33kV/415V/240V, 3-phase, 4-wire, solidly


15.5.6 (i) nr.
earthed neutral (Reference as shown on drawings)
Pole mounted transformer sub-station 11kV/415V/240V, 3-phase, 4-wire, solidly
15.5.6 (ii) nr.
earthed neutral (Reference as shown on drawings)

15.6 Feeder Pillars


15.6.6 (i) Feeder pillar (size, rating (A)) (No.of ways, type and ref.) (415V/240V) nr.

15.7 Electrical Cables


15.7.6 (i) Electrical cable (type) (voltage) (size) lin.m.

15.8 Road Lighting Masts, Columns and Luminaires


15.8.6 (i) High mast assembly (type) (height) (No & type of luminaires) ref.dwg. nr.
15.8.6 (ii) Lighting columns (type) (No of arms) (height) (type of luminaire) ref.dwg nr.
15.8.6 (iii) Column/High Mast Testing L.S

15.9 Traffic Sign Illumination


15.9.6 (i) Overhead sign lighting (gantry or cantilever) (ref. dwg.) nr.
15.9.6 (ii) Roadside sign lighting (sign ref. no.) (ref. dwg.) nr.

page VII-I CARRIED TO SUMMARY

copy 249
Oman Standard Specifications for Road and Bridge Construction 2010
PROJECT TITLE
Subsection (If necessary)
BILL OF QUANTITIES
BILL (VII) ROAD LIGHTING AND ELECTRICAL INSTALLATIONS (continued)

Unit Rate Amount


Estimated
Item No Description Unit R.O. Bz R.O. R.O.
Quantity Bz Bz
(Omani (Omani (Number) (Words)
(Number) Omani Baiza (Words) Omani Baiza
Riyal) Baiza) Omani Riyal Omani Riyal
15 ROAD LIGHTING AND ELECTRICAL INSTALLATIONS
15.10 Under Bridge Lighting
15.10.6 (i) Under bridge surface mounted luminaire (type) (ref. drwg.) nr.
15.10.6 (ii) Under bridge recessed lighting luminaire (type) (ref. drwg.) nr.

15.11 Traffic Signals


15.11.6 (i) Traffic signal installations (type and location as shown on drawings) nr.
15.11.6 (ii) Overhead traffic signal support including foundation (type) nr.

15.12 Overheight Vehicle Detection Systems


Overheight vehicle detection and warning system (system complete) (location
15.12.8 (i) nr.
shown on drawings)

15.13 Emergency Roadside Telephone System


15.13.9 (i) Emergency roadside telephone system ( Road ref. No.) nr.

15.14 Public Lighting Management and Control System (PLMCS)


PLMCS installation at each feeder pillars and all related communication and
15.14.8 (i) central control facilities. nr.

15.15 Earthing
15.15.7 (i) Twin rod earthing installation (location) nr.
15.15.7 (ii) Single rod earthing installation (location) nr.

15.17 Civil Works for Electrical Installations


15.17.6 (i) Building for medium voltage intake switching station ( ref. drawing and detail) nr.
15.17.6 (ii) Concrete foundation for packaged substation (ref. drawing and detail) nr.
15.17.6 (iii) Building for packaged med. voltage switching station (ref. drawing and detail) nr.
H type concrete foundation for 33kV/low voltage pole mounted transformer
15.17.6 (iv) nr.
station (reference drawing and detail)
H type concrete foundation for 11kV/low voltage pole mounted transformer
15.17.6 (v) nr.
station (reference drawing and detail)
15.17.6 (vi) Concrete base for feeder pillar (ref.dwg) nr.
15.17.6 (viii)a Trench for low voltage cable for one cable lin.m.
15.17.6 (vii)b Trench for low voltage cable for two cables lin.m.
15.17.6 (vii)c Trench for low voltage cable for three cables lin.m.
15.17.6 (viii)a Trench for medium voltage cable for one cable lin.m.

page VII-II CARRIED TO SUMMARY

copy 249
Oman Standard Specifications for Road and Bridge Construction 2010
PROJECT TITLE
Subsection (If necessary)
BILL OF QUANTITIES
BILL (VII) ROAD LIGHTING AND ELECTRICAL INSTALLATIONS (continued)

Unit Rate Amount


Estimated
Item No Description Unit R.O. Bz R.O. R.O.
Quantity Bz Bz
(Omani (Omani (Number) (Words)
(Number) Omani Baiza (Words) Omani Baiza
Riyal) Baiza) Omani Riyal Omani Riyal

15 ROAD LIGHTING AND ELECTRICAL INSTALLATIONS


15.17.6 (viii)b Trench for medium voltage cable for two cables lin.m.
15.17.6 (ix) Lighting column concrete foundation(Type, ref. dwg) nr.
15.17.6 (x) High Mast concrete foundation(Type, ref. dwg) nr.
15.17.6 (xi) uPVC duct (size and nr) lin.m.
15.17.6 (xii) uPVC duct, in concrete encasement (size and nr) lin.m.
15.17.6 (xiii) Cable marker (as per MEW details) nr.
15.17.6 (xiv) Manhole (type, dimension) (ref. dwg) nr.
15.17.6 (xv) Handhole / Drawpit (type, dimension) (ref. dwg) nr.
15.17.6 (xvi) Cast aluminium breakaway transformer base for column (height) (details, dwg.ref nr.

page VII-III CARRIED TO SUMMARY

copy 249
Oman Standard Specifications for Road and Bridge Construction 2010
PROJECT TITLE
Subsection (If necessary)
BILL OF QUANTITIES
BILL (VII) ROAD LIGHTING AND ELECTRICAL INSTALLATIONS SUMMARY

Amount
Item No Description R.O. R.O.
Bz Bz
(Number) (Words)
(Number) Omani Baiza (Words) Omani Baiza
Omani Riyal Omani Riyal

SUMMARY
Page VII-I
Page VII-II
Page VII-III

page VII-IV CARRIED TO GRAND SUMMARY

copy 249
Oman Standard Specifications for Road and Bridge Construction 2010
PROJECT TITLE
Subsection (If necessary)
BILL OF QUANTITIES
BILL (VIII) LANDSCAPING AND IRRIGATION

Unit Rate Amount


Estimated
Item No Description Unit R.O. Bz R.O. R.O.
Quantity Bz Bz
(Omani (Omani (Number) (Words)
(Number) Omani Baiza (Words) Omani Baiza
Riyal) Baiza) Omani Riyal Omani Riyal

16 LANDSCAPING AND IRRIGATION

16.1 Landscaping
16.1.7 (i) Excavating to reduce levels cu.m.
16.1.7 (ii) Excavating topsoil for preservation cu.m.
16.1.7 (iii) Filling to make up levels cu.m.
16.1.7 (iv) Topsoil filling to make up levels and for planting cu.m.

16.1.7 (v) Grass seeding sq.m.


16.1.7 (vi) Grass sods (turf) sq.m.
16.1.7 (vii) Grass plugs sq.m.
16.1.7 (viii) Grass sprigs sq.m.

16.1.7 (xi) Trees (type, size) nr.


16.1.7 (x) Palms (type, size) nr.
16.1.7 (xi)
( ) Shrubs (type,
( yp , size)) nr.
16.1.7 (xii) Ground cover plants (type) nr.
16.1.7 (xiii) Climbers (type) nr.

16.2 Irrigation System


16.2.6 (i) Pipe (type, class and diameter) lin.m.
16.2.6 (ii) Valves (type and diameter) nr.
16.2.6 (iii) Irrigation Program Controller (type) nr.
16.2.6 (iv) Irrigators (type and size) nr.
16.2.6 (v) Drip emitter distribution tubing (type and diameter) lin.m.
16.2.6 (vi) Spares for Irrigation System (type, class and size) nr.

page VIII-I CARRIED TO SUMMARY

copy 249
Oman Standard Specifications for Road and Bridge Construction 2010
PROJECT TITLE
Subsection (If necessary)
BILL OF QUANTITIES
BILL (VIII) LANDSCAPING AND IRRIGATION SUMMARY

Amount
Item No Description R.O. R.O.
Bz Bz
(Number) (Words)
(Number) Omani Baiza (Words) Omani Baiza
Omani Riyal Omani Riyal

SUMMARY
Page VIII-I

page VIII-II CARRIED TO GRAND SUMMARY

copy 249
Oman Standard Specifications for Road and Bridge Construction 2010
PROJECT TITLE
Subsection (If necessary)
BILL OF QUANTITIES
BILL (IX) PUMPING STATIONS AND UTILITIES

Unit Rate Amount


Estimated
Item No Description Unit R.O. Bz R.O. R.O.
Quantity Bz Bz
(Omani (Omani (Number) (Words)
(Number) Omani Baiza (Words) Omani Baiza
Riyal) Baiza) Omani Riyal Omani Riyal

17 PUMPING STATIONS

17.2 Materials
17.2.9 (i) Metalwork (Type) LS

17.2.9 (ii) Ductile iron pressure pipe (size) lin.m.


17.2.9 (iii) uPVC pressure pipe (size) lin.m.

17.2.9 (iv) Gate valves (size) nr.


17.2.9 (v) Butterfly valves (size) nr.
17.2.9 (vi) Check valves (size) nr.
17.2.9 (vii) Silent type check valves (size) nr.
17.2.9 (viii) Control valves (size) nr.
17.2.9 (ix) Surge Control Valves (size) nr.
17.2.9 (x) Cushioned Type Check Valves (size) nr.

17.3 Equipment
17.3.9 (i) Submersible Drainage Pumps nr.
17.3.9 (ii) Horizontal Pumps nr.
17.3.9 (iii) High Pressure Booster Pumping Set Employing Membrane Tank nr.
17.3.9 (iv) High Pressure Booster Pumping Set Employing Variable Speed Pumps nr.
17.3.9 (v) Duplex Sump Pumps nr.

17.3.9 (vi) Monorail System LS

page IX-I CARRIED TO SUMMARY

copy 249
Oman Standard Specifications for Road and Bridge Construction 2010
PROJECT TITLE
Subsection (If necessary)
BILL OF QUANTITIES
BILL (IX) PUMPING STATIONS AND UTILITIES (continued)

Unit Rate Amount


Estimated
Item No Description Unit R.O. Bz R.O. R.O.
Quantity Bz Bz
(Omani (Omani (Number) (Words)
(Number) Omani Baiza (Words) Omani Baiza
Riyal) Baiza) Omani Riyal Omani Riyal

17 PUMPING STATIONS (continued)

17.3.9 (vii) Fertilizer Injection Equipment LS


17.3.9 (viii) Electrical works LS
17.3.9 (ix) Instrumentation and Contols LS

18 UTILITIES

18.1 Locating and Protecting Existing Utilities


18.1.6 (i) Split Pipe (diameter) lin.m.

18.2 Removing and Disposing of or Relocationg Existing Utilities


18.2.6 (i) Remove and dispose of (utility) (size/description) lin.m.
18.2.6 (ii) Remove and relocate (utility) (size/description) lin.m.
18.2.6 (iii) Provide and install new (utility) (size/description) lin.m.

18.3 Future Utility Crossing Ducts


18.3.6 (i) Sleeves/Ducts (type), (diameter) lin.m.

page IX-II CARRIED TO SUMMARY

copy 249
Oman Standard Specifications for Road and Bridge Construction 2010
PROJECT TITLE
Subsection (If necessary)
BILL OF QUANTITIES
BILL (IX) PUMPING STATIONS AND UTILITIES SUMMARY

Amount
Item No Description R.O. R.O.
Bz Bz
(Number) (Words)
(Number) Omani Baiza (Words) Omani Baiza
Omani Riyal Omani Riyal

SUMMARY
Page IX-I
Page IX-II

page IX-III CARRIED TO GRAND SUMMARY

copy 249
Oman Standard Specifications for Road and Bridge Construction 2010
copy 249
PROJECT TITLE
Subsection (If necessary)
BILL OF QUANTITIES
Bill No (X) GRAND SUMMARY

Amount
Item No Description R.O. R.O.
Bz Bz
(Number) (Words)
(Number) Omani Baiza (Words) Omani Baiza
Omani Riyal Omani Riyal

SUMMARY
Bill No 1
Bill No 2
Bill No 3
Bill No 4
Bill No 5
Bill No 6
Bill No 7
Bill No 8
Bill No 9

page X-I GRAND SUMMARY

copy 249
Oman Standard Specifications for Road and Bridge Construction 2010
copy 249
Sultanate of Oman, Standard Specifications for Road & Bridge Construction 2010

Copyright

These Specifications have been prepared, printed and serial numbered by:
The Ministry of Transport and Communications - Directorate General of Roads and Land Transport.
This Document, or parts thereof, may not be reproduced in any form without the written permission of the
Ministry of Communications.

copy 249
copy 249

Вам также может понравиться