CARBON PORTFOLIO - PERU 2010

Energy, Industry and Others

PORVENIR Hydropower Plant H43


Description: The Purpose of the Project is renewable electricity generation for the National Electric Grid (SEIN). The project will have an installed ca-
pacity of 9.6 MW and it will deliver 69.81 GWh to the National Grid annually. It is located in the districts of Condesuyos, Salamanca, and department
of Arequipa.

Current Status: Projects Benefits:


Earliest project start date: 2011. Number of direct and indirect jobs generated:
Operation start date: 2012. It generates 130 new direct and 230 indirect jobs.
Project lifetime: 30 years. Sustainable development contribution:
Current Status: Feasibility studies completed. Authorizations already The project will contribute to the reduction of carbon dioxide emissions
granted through displacing energy from thermoelectric plants. Purification and
cleaning of water for irrigation. Better electricity supply in the region.
Estimated Annual Emission Reductions (tCO2/year): Local milling/grinding agricultural based projects shall be benefited
An average of 37,000 tCO2-equivalent per year.
CER´s negotiation:
Project Participant and Financing Open.
Total project cost: US$ 10,500,000

Sources of finance to be sought or already identified: Contact Information:


Equity: 10 % Name: Berthy Verta Sullaime
Debt: 90 % Company: EMGEL AGROMIN SRL
Title:
Phone: (51-54) 288515
E-mail: berthyvera@hotmail.com

QUITARACSA I The Project H44


Description: The project consists of a run-of-river hydropower plant to be located in Peru, department of Ancash, province of Huaylas. The projects
installed capacity and estimated yearly average generation will be 114.6 MW and 457.79 GWh.

Current Status: Projects Benefits:


Earliest project start date: February 2011. Sustainable development contribution:
Operation start date: October 2014. It will produce cheap energy with environmental impact.
Project lifetime: 40 years. It would allow rural communities, improving their economic and pro-
Current Status: Environmental study approved. Energy and Water con- duction activities.
cession were given. Feasibility study completed. Letter of Approval was It will fulfill the environment norms through the approval of its Environ-
issued by DNA. It has been registered at the Executive Board. mental Impact Study.

Estimated Annual Emission Reductions (tCO2/year):


An average of 249,463 tCO2-equivalent per year. CER´s negotiation:
Open.
Project Participant and Financing
Total project cost: US$ 101,100,000

Contact Information:
Sources of finance to be sought or already identified:
Name: Alexis Ledeque
Equity: 20 % Company: EnerSur S.A.
Debt: 80 % Title: Representative
Phone: (51-84) 6167979
E-mail:

www.fonamperu.org