NO: VKS/ISC/TZ-ZK/0-20KM/2017-18/ Dated Kohima, the 17th March 2020

To,
The Chief Engineer,
Public Works Department,
Road & Bridges,
Nagaland : Kohima.

Sub: Application for extension of time for the Project “Construction of road from Tizit to
Zangkham – Pumao Via Sangsa {Phase-I: from Tizit (Km 0) to Zangkham (Km 20)
Length - 20 Km under inter-State Connectivity (ISC) in the State of Nagaland (Job
No. ISC/NG/2017-18/28)”
Ref: NO.CE/RnB/ISC-EI/2017-18/ Dated Kohima, the 25th April 2018

Dear madam,
With reference to the subject cited above I have the honour to state the following points
for your kind consideration.

1. Due to incessant rainfall for the last two monsoon season, it has greatly hampered the
smooth progress of the work.
2. There is no Bridge to cross Titho River and Nganu river so even during slight rainfall
the vehicle cannot cross this two river to transport basic Construction materials such as
diesel for machineries and its spare parts.
3. Land dispute in some stretch of road also delayed the progress of work.
In consideration of all the above mentioned points, the smooth progress of work is hampered due
to which the work could not be completed in the stipulated period of time.
Therefore, I would like to request your kind authority to extend the project duration for
another 12 Months for which act of your kindness I shall be ever grateful to you.

Thanking you.

Enclosed:
1. Rainfall Data for Mon District
2. Images of river

Yours faithfully,

(VILELIE KHAMO)
NO: VKS/ISC/TZ-ZK/0-20KM/2017-18/ Dated Kohima, the 3rd May 2019

To,
The Chief Engineer,
Public Works Department,
Road & Bridges,
Nagaland : Kohima

Sub: Submission of Renewed Performance Bank Guarantee for the work


“Construction of road from Tizit to Zangkham – Pumao Via Sangsa {Phase-I:
from Tizit (Km 0) to Zangkham (Km 20) Length - 20 Km under inter-State
Connectivity (ISC) in the State of Nagaland (Job No. ISC/NG/2017-18/28).
Ref: NO.CE(R&B)/DAC-BG-FD/TB-I/2018-19/649, Dated Kohima, the 20th March 2019

Dear sir,
With reference to the subject cited above I am submitting herewith the renewed
Performance Bank Guarantee for the above mentioned work bearing Guarantee
No. 37644025271 valid upto 11-04-2020.

Thanking You.

Enclosed: Original Renewed Performance Bank Guarantee

Yours faithfully,

(VILELIE KHAMO)
Proprietor
M/s. Vilelie Khamo & Sons
NO: VKS/ISC/TZ-ZK/0-20KM/2017-18/04 Dated Kohima, the 30th August, 2018

To,
The Executive Engineer,
Public Works Department,
Road & Bridges,
Nagaland: Mon

Sub: Construction of road from Tizit to Zangkham – Pumao Via Sangsa {Phase-I:
from Tizit (Km 0) to Zangkham (Km 20) Length - 20 Km under inter-State
Connectivity (ISC) in the State of Nagaland (Job No. ISC/NG/2017-18/28).

Reg: Revision of Works Program and Milestone of the project.

Dear Sir,

The subjected work has been awarded to me Vide LOA No. CE/RnB/ISC-
EI/2017-18/520-24 Dated Kohima, the 04th April, 2018 and Agreement No.
CE/R&B/AGT/2017-18/28/06 Dated Kohima, the 25th April, 2018.
However, with reference to the regard cited above, I bring it to your notice that
the delay in handing over the construction site due to the Alignment issue with the
villagers which is the sole responsibility of the Authority to look into the matter,
whereby the issue has been amicably solved and was handed over to me on 25 August
2018. Keeping in view of the fact, it is quite obvious that the targets of Scheduled
Milestone Completion cannot be achieved as specified in Contract Data of contract
Agreement. Therefore, Considering the prolonged alignment issue, we do hereby submit
the revised work program and milestone as on 01.09.2018 and requesting you to please
accord your approval for revised Milestone.

The Revised Milestone is tabulated below:

Sl No. Revised Milestone Revised period of Milestone

1 1st Milestone 365 Days


2 2nd Milestone 365 Days
3 3rd Milestone 300 Days

Enclosed:

1. Revised work Programme.


2. Revised Milestone Chart.
Yours faithfully,

(VILELIE KHAMO)
Proprietor
M/s. Vilelie Khamo & Sons

Copy to:
1. Executive Engineer PWD(R&B), Mon, Nagaland for necessary action.

(VILELIE KHAMO)
Proprietor
M/s. Vilelie Khamo & Sons
Sl
Milestones as described in Agreement Revised Milestones as described
No.
Description Period Description Period
Earthwork for road
1 Formation Pucca side 6 Months Preliminary set up 1 Months
drain
Road composition (Sub-
12 Earthwork for road
2 grade, Shoulder, GSB & 19 Months
Months formation
WBM)
Cross Drainage works (i/c.
3 9 Months Pucca side drain 16 Months
RCC T-BEAM)
4 Protection work 3 Months Cross Drainage works 23 Months
5 Bituminous works 5 Months Protection work 23 Months
6 Road furniture 1 Months Subgrade Preparation 18 Months
Granular Sub-base &
7 __ __ 18 Months
earthen shoulder
Water bound
8 __ __ 15 Months
Macadam
9 __ __ Bituminous work 8 Months
10 __ __ Road Furniture 4 Months
Scheduled Completion 36 Months 34 Months

Thanking you and assuring our best attention at all times

Enclosed:

3. Revised work Programme.


4. Revised Milestone Chart.

Yours Faithfully,

(VILELIE KHAMO)
Proprietor
M/s. Vilelie Khamo & Sons