Академический Документы
Профессиональный Документы
Культура Документы
progressing the main project. This is sometime a technique of the management to avoid workers
to be idle if they have extra people while the project is at starting stage.
So here are the method statement for interlock work that you might want to learn how it will be
done.
1. Title
The purpose of this method statement is to describe the measures and ways of proper installation
of interlock or paving block within our project. The work will be as per the project specification
and approved drawing.
3. Work procedure
1. Preparation
Before interlock work starts, make sure that sub-grade is compacted when the
area is above natural ground.
The sub-base shall be compacted with vibratory roller, size of roller shall be
suitable for the area where it could maneuver and can move back and fort.
Once compacted and met the specification requirement for compaction and
approved by Engineer, base course shall then be placed above compacted sub-base
but make sure thickness of the bases are as per approved drawing.
MEP rough-in or underground embedments (wherever applicable) shall be in
placed before interlock work commences.
In the areas where there are kerb stone, the blinding shall be constructed first
serve as the base but make sure it shall be as per drawing.
The importance of pre-installation of kerb stone is to prevent the migration or dis-
alignment of interlock or block, and it will serve as reference line or level.
After compaction of base-course, the black sand shall be laid on it of 50 mm
thick. There are cases that the bedding is mixed with cement to adhere cohesiveness
but it will be as per specification requirements.
Installation of Interlock or Paving block
Interlocking Concrete Block Pavement (ICBP) has been extensively used in a number of countries for
quite sometime as a specialized problem-solving technique for providing pavement in areas where
conventional types of construction are less durable due to many operational and environmental
constraints. ICBP technology has been introduced in India in construction, a decade ago, for specific
requirement viz. footpaths, parking areas etc. but now being adopted extensively in different uses where
the conventional construction of pavement using hot bituminous mix or cement concrete technology is not
feasible or desirable. The paper dwells upon material, construction and laying of concrete block pavement
as a new approach in construction of pavement using Interlocking Concrete Paver Blocks.
Introduction
Concrete paver blocks were first introduced in Holland in the fifties as replacement of paver bricks which
had become scarce due to the post-war building construction boom. These blocks were rectangular in
shape and had more or less the same size as the bricks. During the past five decades, the block shape
has steadily evolved from non-interlocking to partially interlocking to fully interlocking to multiply
interlocking shapes. Consequently, the pavements in which non-interlocking blocks are used are
designated as Concrete Block Pavement (CBP) or non-interlocking CBP, and those in which partially, fully
or multiply interlocking blocks are used are designated as 'Interlocking Concrete Block Pavement (ICBP).
CBP/ICBP consists of a surface layer of small-element, solid un-reinforced pre-cast concrete paver blocks
laid on a thin, compacted bedding material which is constructed over a properly profiled base course and
is bounded by edge restraints/kerb stones. The block joints are filled using suitable fine material. A
properly designed and constructed CBP/ICBP gives excellent performance when applied at locations
where conventional systems have lower service life due to a number of geological, traffic, environmental
and operational constraints [1-8]. Many number of such applications for light, medium, heavy and very
heavy traffic conditions are currently in practice around the world.
Mass production under factory conditions ensures availability of blocks having consistent quality
and high dimensional accuracy.
Good quality of blocks ensures durability of pavements, when constructed to specifications.
ICBP tolerates higher deflections without structural failure and will not be affected by thermal
expansion or contraction.
ICBP does not require curing, and so can be opened for traffic immediately after construction.
Construction of ICBP is labor intensive and requires less sophisticated equipment.
The system provides ready access to underground utilities without damage to pavement.
Maintenance of ICBP is easy and simple and it is not affected by fuel and oil spillage.
Use of coloured blocks facilitates permanent traffic markings.
ICBP is resistant to punching loads and horizontal shear forces caused by maneuvering of heavy
vehicles
Low maintenance cost and a high salvage value ensures low life cycle cost.
However, important limitations of the technique are the following:
Quality control of blocks at the factory premises is a prerequisite for durable "ICBP"
Any deviations of base course profile will be reflected on the "ICBP" surface. Hence extra care
needs to be taken to fix the same.
High quality and gradation of coarse bedding sand and joint filling material are essential for good
performance.
"ICBP" over unbound granular base course is susceptible to the adverse effects of poor drainage
and will deteriorate faster. "ICBP" is not suited for high speed roads (speed above 60 km/h)
Physical Requirements
Since zero slump concrete is used in production of paver blocks, the quality of blocks produced will
depend upon various parameters like the capacity of compaction and vibration of machine, grade of
cement used, water content, quality of aggregates used, their gradation and mix design adopted,
additives used, handling equipment employed, curing method adopted, level of supervision, workmanship
and quality control achieved, etc. Recommended grades of paver blocks to be used for construction of
pavements having different traffic categories are given in Table 1 [9].
a. Type A: Paver blocks with plain vertical faces, which do not key into each other when paved in
any pattern,
b. Type B: Paver blocks with alternating plain and curved/corrugated vertical faces, which key into
each other along the curve/corrugated faces, when paved in any pattern,
c. Type C: Paver blocks having all faces curved or corrugated, which key into each other along all
the vertical faces when paved in any pattern and
d. Type D: 'L' and 'X' shaped paver blocks which have all faces curved or corrugated and which key
into each other along all the vertical faces when paved in any pattern.
The generic shapes and groups of paver blocks identified to four types are illustrated in Figures 1 & 2.
Materials
The quality of materials, cement concrete strength, durability and dimensional tolerance of paving blocks,
etc. is of great importance for the satisfactory performance of block pavements. These aspects and the
block manufacturing process itself, which immensely affect the quality of paving blocks, have been
outlined in the Indian Roads Congress Special Publications [9]. The Central Road Research Institute
(CRRI) has prepared the specifications for ICBP [10]
Paving Blocks
The quality of materials, strength of cement concrete and durability as well as dimensional tolerances etc.
are of great importance for satisfactory performance of block pavement. The recommended thickness of
block and grades of concrete for various applications and specification for paving in which materials used
for preparation of blocks, physical requirements, physical test methods, sampling and acceptance criteria
has already been formulated in BIS Code [10].
It is well established that if proper attention is not paid to the quality of bedding sand, and if the thickness
of bedding sand layer is not uniform enough, serious irregularities in surface profile can result; excessive
differential deformation and rutting can occur early in service life of the block pavement. The gaps in
between two adjacent paving blocks (typically about 3 mm wide) need be filled with sand, relatively finer
than the bedding sand itself. The desired gradation for the bedding and joint filling sands are given in
Table 2 [9].
It is necessary to restrict the fines (silt and/or clay passing 75 micron sieve) to 10 percent, since
excessive fines make joint filling very difficult. Similarly, it is not advised to use cement in the joint filling
sand, which may not only make it difficult to completely fill the joints, but may also adversely affect the
desired flexibility characteristics of the paving block layer. The joint filling sand should be advisably as dry
as possible; otherwise complete filling of joints may be difficult.
Sequencing of operations
The sequencing of operations (Fig. 3) for construction of block pavement should be as follows [1 & 4]:
Construction of Sub–grade
This is the foundation layer over which the block pavement is constructed. Like in conventional
pavements, the water table level should not be at a level of 600 mm or higher, below the subgrade level.
It should be compacted in layers of either150 or 100 mm thickness guidelines [10]. The prepared
subgrade should be graded and surface dressed to a tolerance of ± 20 mm of the design levels, and its
surface evenness should have a tolerance of within 15 mm under a 3 m straight edge [10].
Concrete blocks on trafficked pavements tend to move sideways and forward due to braking and
maneuvering of vehicles. The tendency to move sideways has to be counteracted at the edges by special
edge blocks and kerbs. The edge block should be designed and anchored to the base such that the
rotation or displacement of blocks is resisted [7]. These are to be made of high strength concrete for
withstanding the traffic wheel-load without getting damaged. These members should be manufactured or
constructed in-situ to have at least a 28-day characteristic compressive strength of 30 MPa or flexural
strength of 3.8 MPa. As far as possible the edge blocks should have vertical face towards the inside
blocks. A few typical edge-blocks are also shown in Fig. 4. Where the space is not easily permitting the
use of plate vibrators, jhurmut or manual compactor using small size plate rammer may be used. The
road kerbs provided on edges of roads also serve the purpose of edge blocks. In case the kerbs are not
provided, it has to be replaced by edge strips. In case of heavy traffic 150 mm x 150 mm plain cement
concrete (M-25) may also be provided over dry lean concrete to give further confinement of blocks. In-
between the edge-restraint blocks cement mortar (1: 6, cement: coarse sand) may be used in place of
sand for sealing of blocks [7].
Laying of Blocks
Blocks can be laid generally by manual labour but mechanical aids like hand-pushed trolleys can expedite
the work. Normally, laying should commence from the edge strip and proceed towards central line. When
dentated blocks are used, the laying done at two fronts will create problem for matching joints in the
middle. Hence, as far as possible, laying should proceed in one direction only, along the entire width of
the area to be paved [4, 5, 6, 7, 8 & 10].
On a sloping site, start from the lowest point and proceed to up-slop on a continuous basis, to
avoid down-slop creep in incomplete areas.
In case of irregular shaped edge restraints or strips, it is better to start from straight string line as
shown in Fig. 5.
Influence of alignment of edge restraints on achieving and maintaining laying bond.
Laying of block pavement at National Highway - 08 Jaipur-Kishangarh section for heavy commercial
vehicles for truck-lay-byes on both side of pavement are shown in Figs 6 and 7.
Changes in alignment: Changes in alignment of a road pavement can some times be achieved by the
use of special blocks. However, it is generally easier to choose a block that can be installed in
Herringbone bond through simply cutting the blocks to fit into the edge restraints. Where aesthetic
requirements of shape of the paving unit dictate the use of Stretcher bond, then only a 90o shape change
in alignment can be achieved without cutting the blocks (Fig. 10). At intersections, if a Herringbone bond
laying pattern is adopted, the block laying can proceed without the need for construction joints (Figs 11).
An alternative to this is to install a shoulder (support) course of rectangular blocks between the main road
and the side streets; this permits different laying patterns to be used in two roadways [10].
Compaction
For compaction of the bedding sand and the blocks laid over it, vibratory plate compactors are used over
the laid paving blocks; at least two passes of the vibratory plate compactor are needed. Such vibratory
compaction should be continued till the top of each paving block is in level with its adjacent blocks. It is
not a good practice to leave compaction till the end of the day, as some blocks may move under
construction traffic, resulting in the widening of joints and corner contact of blocks, which may cause
spalling or cracking of blocks. There should not be delay in compaction after laying of paving blocks to
achieve uniformity of compaction and retention of the pattern of laying. During vibratory compaction of the
laid blocks, some amount of bedding sand may get filled up into the joints between them; the extent of
sand getting filled up into the joints will depend on the degree of compaction of sand, i.e. the force applied
by the compactor. Standard compactors may have a weight of about 90 kg, plate area of about 0.3
m2and apply a centrifugal force of about 15 kN, while heavy duty compactors may weigh 300-600 kg,
have a plate area of about 0.5-0.6 m2 and apply a centrifugal force of 30-65 kN. Where the bedding sand
is required to be compacted for heavy traffic block pavements, heavy-duty compactors should be used.
After compaction by vibratory plate compactors, some 2 to 6 passes of a vibratory roller (with rubber
coated drums or those of static weight less than 4 tonnes and nominal amplitude of not more than 0.6
mm) will further help in compaction of bedding sand and joint filling [4 & 10].
While constructing the block pavement, the surface tolerances of individual layers may be observed as
shown in Table 4 [4 & 10].
Conclusion
1. ICBP technology can provide durable and sustainable road infrastructure where construction and
maintenance of conventional pavements are not cost effective.
2. ICBP is much cheaper than rigid (concrete) pavement designed for identical conditions.
Compared to bituminous pavement for low traffic volumes and high strength subgrade, the initial
construction cost of ICBP is likely to be equal to or marginally higher. For high traffic volumes and
low strength subgrade, ICBP will be cheaper than flexible pavement.
3. Guidelines for use of Interlocking Concrete Block Pavement and Specification on Paver Blocks
are published in Codes and available with Indian Roads Congress and Bureau of Indian
Standards which are very useful for Indian industries and highway professions for adoption of
block pavement technology.
Acknowledgments
Author is thankful to Dr. S. Gangopadhyay, Director, CRRI, for his kind permission to publish this paper
and continuous encouragement. Sincere thanks are also due to Shri B.M. Sharma, Head, Pavement
Evaluation Division for encouraging support to write this paper. The cooperation and valuable suggestions
extended by Shri T. Muraleedharan, Retired Senior Scientist, Pavement Evaluation Division is gratefully
also acknowledged.
References
Muraleedharan, T., Sharma, S.D., Sridhar, S.K. and Nanda, P.K., "Face Lifting of Old Concrete
Pavement Using Interlocking Concrete Block Pavement Technique," Proceeding, International
Seminar on New Trends in Highway Construction, New Delhi, pp 161-174, Nov-1997.
Muraleedharan, T. and Nanda, P.K., (1992) "Application and Performance of Interlocking
Concrete Block Pavement – An Overview," The Indian Concrete Journal, pp 395 -400, July 1992.
Muraleedharan, T. and Nanda, P.K., Laboratory and Field Study on Interlocking Concrete Block
Pavement foe Special Purpose Paving in India," Proceeding, Fifth International Conference on
Concrete Block Paving, Tel Aviv, Israel, pp413-422, June-1996.
Sharma, S.D., Prashant Kumar, Nanda, P.K., "Interlocking Concrete Block Pavements: New
Trends in Construction," Civil Engineering & Construction Review, (Roads), 2005
Sharma, S.D., Sood, V.K. and Sikdar, P.K., "Interlocking Block Pavement For Sustainable Road
Infrastructure For Cold Region," International Conference on Sustainable Habitat For Cold
Climates, Leh, India, September 16-18, 2004.
Sharma, S.D., Sikdar, P.K., Rao, Y.V., (2004) "Interlocking Concrete Block Pavements – Its
Prospects," Seminar on Design Construction and Maintenance of Cement Concrete Pavements,
IRC, October, 2004.
"New and Improved Road Technologies (Tenth Five Year Plan 200207) – Material for Special
Road Applications – Development of Paving Surface for High Altitude and Desert Areas, Central
Road Research Institute, New Delhi, March 2007.
Sharma, S.D., "Interlocking Concrete Blocks Pavement: New Approach in Construction for Rural
Roads," All India Seminar on "Highways Development: Design, Construction, Operation and
Repairs & Concrete Day Celebration – Lucknow, 2008.
IS:15658:2006 on "Precast Concrete Blocks for Paving – Specification," Bureau of Indian
Standards,
IRC SP: 63-2004 "Guidelines for Use of Interlocking Concrete Block Pavement" Indian Roads
Congress.
IRC: SP: 49 – 1998: "Guidelines for Use of Dry Lean Concrete as Sub-base for Rigid Pavement,"
Indian Roads Congress.
IRC:50-1973, "Recommended Design Criteria for Use of Cement Modified Soil in Road
Construction."
IRC:51-1992, "Guidelines for the Use of Soil Lime Mixes in Road Construction."
IRC:63-1976, "Tentative Guidelines for the Use of Low Grade Aggregates and Soil Aggregate
Mixtures in Road Construction."
IRC:19-1977, "Standard Specifications and Code of Practice for Water Bound Macadam."
IRC SP-11-1988: "Handbook of Quality Control for Construction of Roads And Runways," Indian
Roads Congress, (Second Revision).
IRC:37-2001: Guidelines for the Design of Flexible Pavements (Second Edition).