Earth work
Excavation&clening M3 60.72 50 1 2
Backfilling M3 48.22 50 1 1
Totla 3 days
Footing
Formwork M2 24.8 20 1 2
reinforcement K.G 483.1 500 1 1
Blinding M3 3.06 15/hr 1 0.21 hr
concret 9.6 15/hr 1 .64 hr
Totla 3 days
column neck
formwork M2 10.17 20 1 0.5
reinforcement K.G 242.38 500 1 0.5
4
1
10
1
0
1
71
Activity predecessor
Earth work
Footing Earth work
column neck Footing
Tie beam column neck
foundation backfilling Tie beam
ground slab foundation backfilling
column ground slab
external wall column
slab external wall
internal walls slab and remove formwork
primary mechanical internal walls
primary electrical internal walls
Door(farms) internal walls
primary mechanical
plastering &electrical
Tiling plastering
windows and door Tiling
painting plastering
electrical (finishing) plastering
mechanical (finishing) plastering
Aluminum plastering
cleaning