Activity Unit used Quantity productive rate number gage Duration

Earth work
Excavation&clening M3 60.72 50 1 2
Backfilling M3 48.22 50 1 1
Totla 3 days
Footing
Formwork M2 24.8 20 1 2
reinforcement K.G 483.1 500 1 1
Blinding M3 3.06 15/hr 1 0.21 hr
concret 9.6 15/hr 1 .64 hr

Totla 3 days
column neck
formwork M2 10.17 20 1 0.5
reinforcement K.G 242.38 500 1 0.5

concret M3 0.69 15/hr 1 0.32 hr


Totla 1
Tie beam
formwork M2 37.6 20 1 2
reinforcement K.G 334.23 500 1 1
concret M3 3.76 15/hr 1 0.25hr
Totla 3 days
foundation backfilling M3 33 20 1 2
Totla 2 days
ground slab
formwork M2 8 20 1 1
reinforcement K.G 358.2 500 1 1
concret M3 13.6 15/hr 1 1hr
Totla 2 days
column
formwork M2 79.2 20 1 4
reinforcement K.G 573.97 500 1 2
concret M3 3.465 15/hr 1 0.23hr
Totla 6 days
external wall

blocks and concrete M2 98.15 20 1 5


Totla 5 days
slab
formwork M2 80.4 20 2 2
reinforcement K.G 1675 500 2 2
concret M3 17 15/hr 1 1.1 hr
Totla 4 days
internal walls
walls M2 73.95 20 1 4
Totla 4days
primary electrical
Total 1days
primary mechanical
Total 1days
Door(farms)
Total 1day
plastering
All Area M2 424.6 20 2 10
Total 10days
Tiling
All Area M2 85 30 1 3
Total 3 days
windows and door
Total 2days
painting
All Area M2 424.6 50 1 9
Total 9days
Furniture
Total 7 days
electrical (finishing)
Total 1days
mechanical (finishing)
Total 1days
Aluminum
Total 1days
cleaning
Total 1 day
Total duration 71 days
Activity predecessor
Earth work
Footing Earth work
column neck Footing
3 Tie beam column neck
foundation backfilling Tie beam
ground slab foundation backfilling
column ground slab
external wall column
slab external wall
slab and remove
3 internal walls formwork
primary mechanical internal walls
primary electrical internal walls
Door(farms) internal walls
primary mechanical
plastering &electrical
1 Tiling plastering
windows and door Tiling
painting plastering
electrical (finishing) plastering
mechanical (finishing) plastering
3 Aluminum plastering
cleaning
2

4
1

10

1
0
1

71
Activity predecessor
Earth work
Footing Earth work
column neck Footing
Tie beam column neck
foundation backfilling Tie beam
ground slab foundation backfilling
column ground slab
external wall column
slab external wall
internal walls slab and remove formwork
primary mechanical internal walls
primary electrical internal walls
Door(farms) internal walls
primary mechanical
plastering &electrical
Tiling plastering
windows and door Tiling
painting plastering
electrical (finishing) plastering
mechanical (finishing) plastering
Aluminum plastering
cleaning