CHB Estimator

DIMENSION INPUTS
Length (m) 2.5
Height (m) 1.2
CHB Thickness (mm) 100.00
Plaster Thickness (mm) 12.00
Sides to Plaster (0/1/2) 0
Spacing of Horizontal Reinforcements (m) 0.6
Spacing of Vertical Reinforcements (m) 0.6
Distance of Bottom CHB To Wall Footing Cont. Bars + Hook (m) 0.2

CHB
Final No. of Columns 7
Final No. of Rows 6
Total CHB: 42
Total CHB + 10% 46

MORTAR
Mortar Volume for CHB (cu.m.) 0.2076
Mortar Volume for Plaster (cu.m.) 0.0000
Total Mortar Volume (cu.m.) 0.2076
Total Mortar Volume + 10% (cu.m.) 0.2284
Cement (bags) 1.8688
Sand (cu.m.) 0.2336
Cement + 10% (cu.m.) 2.0557
Sand + 10% (cu.m.) 0.2570

DEFORMED BAR
Final No. of Lines of Horizontal Reinforcement 3
Final No. of Lines of Vertical Reinforcement 5
Total Combined Length of All Reinforcements 14.5
Length of Deformed Bar (6m, 7.5m, 9m, 10.5m, 12m, etc.) 6
NO. OF LENGTHS OF DEFORMED BARS
Conservative 3.02
Safe 3.32
Very Safe 3.63
CHB Estimator
**CHB Thickness Limited to 100m
NECESSARY CALCULATED VALUES **CHB Dimensions 200mm x 400
6.25 Exact No. of Columns **CHB Wall Thickness for 100mm
6.00 Exact No. of Rows **CHB Wall Thickness for 150mm
0.004224 Hollow Volume per CHB **Recommended Final No. of Co
0.00072 Side Volume per CHB **Recommended Final No. of Ro
**Cement factor taken as 9 bags
3 Exact No. of Lines of Horizontal Reinf. + 1 **Sand Density taken as 2400 kg
5.1666666666667 Exact No. of Lines of Vertical Reinf. + 1 **Sand Bulk Density taken as 16
**Recommended No. of Lengths

CHB
**Input Final No. of Columns based from exact value from D3
**Input Final No. of Rows based from exact value from D4

pcs.

MORTAR
Input C:S Ratio Below:
Cement 1
Sand 3

bags
cu.m.

DEFORMED BAR
**Input Final No. of Lines of Hor. Reinf. Based on exact value from D10
**Input Final No. of Lines of Vert. Reinf. Based on exact value from D11

pcs.
pcs.
pcs.
NOTES:
**CHB Thickness Limited to 100mm and 150mm
**CHB Dimensions 200mm x 400mm
**CHB Wall Thickness for 100mm taken as 18mm
**CHB Wall Thickness for 150mm taken as 25mm
**Recommended Final No. of Columns = Rounded up Exact No. of Columns
**Recommended Final No. of Rows = Rounded up Exact No. of Columns
**Cement factor taken as 9 bags per cubic meter
**Sand Density taken as 2400 kg/cu.m.
**Sand Bulk Density taken as 1600 kg/cu.m.
**Recommended No. of Lengths of DRB = Safe, rounded up