DELIVERABLES CE 521 – CE PROJECTS AND ENGINEERING PLANNING (5-1)

CHECKING
NO. PARTICULARS TIME LINE REMARKS
DATE
PRODUCTION OF LOCATION MAP WITH
1 JAN 20-24, 2020 Jan 27
TECHNICAL DESCRIPTIONS
2 TOPOGRAPHIC MAP WITH CONTOUR LINES JAN 20-24, 2020 Jan 29
3 SITE DEVELOPMENT PLAN JAN 27-31, 2020 Feb 5
4 ENVIRONMENTAL COMPLIANCE JAN 20-24, 2020 Jan 29
5 GENERAL PLANS FEB 3-14, 2020 Feb 17
 STRUCTURAL FEB 3-14, 2020 Feb 17
 TRANSPORTATION FEB 3-14, 2020 Feb 17
 GEOTECHNICAL FEB 3-14, 2020 Feb 17
 WATER RESOURCES FEB 3-14, 2020 Feb 17
 MANAGEMENT FEB 3-14, 2020 Feb 17
6 ANALYSIS FEB 17-28, 2020 Mar 2
 STRUCTURAL FEB 17-28, 2020 Mar 2
 TRANSPORTATION FEB 17-28, 2020 Mar 2
 GEOTECHNICAL FEB 17-28, 2020 Mar 2
 WATER RESOURCES FEB 17-28, 2020 Mar 2
 MANAGEMENT FEB 17-28, 2020 Mar 2
7 DESIGN MAR 2-13, 2020 Mar 16
 STRUCTURAL MAR 2-13, 2020 Mar 16
 TRANSPORTATION MAR 2-13, 2020 Mar 16
 GEOTECHNICAL MAR 2-13, 2020 Mar 16
 WATER RESOURCES MAR 2-13, 2020 Mar 16
 MANAGEMENT MAR 2-13, 2020 Mar 16
8 MATERIALS TAKE-OFF MAR 23 – APR3 Apr 6
9 MANPOWER UTILIZATION APR 13-24, 2020 Apr 22
10 EQUIPMENT UTILIZATION APR 13-24, 2020 Apr 22
11 RISK MANAGEMENT APR 13-24, 2020 Apr 22
12 SAFETY PLAN APR 13-24, 2020 Apr 22
13 WORK BREAKDOWN STRUCTURE APR 13-24, 2020 Apr 22
14 MANAGEMENT TOOLS APR 13-24, 2020 Apr 22
15 PAPER WRITE-UPS - INTRODUCTION FEB 10-APR 3 Apr 6
16 - RRL FEB 10-APR 3 Apr 6
17 - METHODOLOGY FEB 10-APR 3 Apr 6
18 FINAL WRITE-UPS REVIEWS MAY 4-8, 2020 May 8
19 PANEL DEFENSE MAY 11-13, 2020
20 SUBMISSION OF FINAL OUTPUT (RING BIND) JUNE 6, 2020
21 SUBMISSION OF GRADES JUNE 1, 2020

Prepared by

ENGR. WILSON S. RAQUEL


Instructor
DELIVERABLES CE 521 – CE PROJECTS AND ENGINEERING PLANNING (5-2)

CHECKING
NO. PARTICULARS TIME LINE REMARKS
DATE
PRODUCTION OF LOCATION MAP WITH
1 JAN 20-24, 2020 Jan 28
TECHNICAL DESCRIPTIONS
2 TOPOGRAPHIC MAP WITH CONTOUR LINES JAN 20-24, 2020 Jan 30
3 SITE DEVELOPMENT PLAN JAN 27-31, 2020 Feb 6
4 ENVIRONMENTAL COMPLIANCE JAN 20-24, 2020 Jan 30
5 GENERAL PLANS FEB 3-14, 2020 Feb 18
 STRUCTURAL FEB 3-14, 2020 Feb 18
 TRANSPORTATION FEB 3-14, 2020 Feb 18
 GEOTECHNICAL FEB 3-14, 2020 Feb 18
 WATER RESOURCES FEB 3-14, 2020 Feb 18
 MANAGEMENT FEB 3-14, 2020 Feb 18
6 ANALYSIS FEB 17-28, 2020 Mar 3
 STRUCTURAL FEB 17-28, 2020 Mar 3
 TRANSPORTATION FEB 17-28, 2020 Mar 3
 GEOTECHNICAL FEB 17-28, 2020 Mar 3
 WATER RESOURCES FEB 17-28, 2020 Mar 3
 MANAGEMENT FEB 17-28, 2020 Mar 3
7 DESIGN MAR 2-13, 2020 Mar 19
 STRUCTURAL MAR 2-13, 2020 Mar 19
 TRANSPORTATION MAR 2-13, 2020 Mar 19
 GEOTECHNICAL MAR 2-13, 2020 Mar 19
 WATER RESOURCES MAR 2-13, 2020 Mar 19
 MANAGEMENT MAR 2-13, 2020 Mar 19
8 MATERIALS TAKE-OFF MAR 23 – APR3 Apr 7
9 MANPOWER UTILIZATION APR 13-24, 2020 Apr 23
10 EQUIPMENT UTILIZATION APR 13-24, 2020 Apr 23
11 RISK MANAGEMENT APR 13-24, 2020 Apr 23
12 SAFETY PLAN APR 13-24, 2020 Apr 23
13 WORK BREAKDOWN STRUCTURE APR 13-24, 2020 Apr 23
14 MANAGEMENT TOOLS APR 13-24, 2020 Apr 23
15 PAPER WRITE-UPS - INTRODUCTION FEB 10-APR 3 Apr 7
16 - RRL FEB 10-APR 3 Apr 7
17 - METHODOLOGY FEB 10-APR 3 Apr 7
18 FINAL WRITE-UPS REVIEWS MAY 4-8, 2020 May 8
19 PANEL DEFENSE MAY 11-13, 2020
20 SUBMISSION OF FINAL OUTPUT (RING BIND) JUNE 6, 2020
21 SUBMISSION OF GRADES JUNE 1, 2020

Prepared by

ENGR. WILSON S. RAQUEL


Instructor