Вы находитесь на странице: 1из 11

Ruta del Sol -

Community
Santiago Castillo
Edouard Klein
Paula Martin
Juan Diego Zambrano
Introduction - Ruta del Sol

The construction From: Cune (Villeta, Cundinamarca)


started in 2010 as
the biggest project To: La Y (Ciénaga, Magdalena)
of the government
plan of 3G roads. Crossing:

Length of the road: Cundinamarca


Boyacá
Sector 1: 78 km Santander
Sector 2: 528 km Cesar
Sector 3: 465 km Magdalena
Total: 1.071 km
Introduction - Ruta del Sol

54%
of the roads is
completed

CORRUPTION
2017
Liquidation of the
Sector 2 contract

2009:
$2.0 bn $COP
BRIBES
2010:
$2.4 bn $COP
2016
2019:
$3.5 bn $COP - 54%
THESIS: As a community we recognize that the Ruta del
Sol project affects us negatively and does not generate
significant benefits for our economic and social
development.
Arg 1: the project of the via del sol is risky for
the local economy

Arg 2: The investment given for La Ruta del Sol


Project should be invested to solve higher
requirements of the community

Arg. 3 The project does not offer monetary


retribution or helps to ensure the vital services
of the affected population
Arg 1: the project of the via del sol is risky for the local economy

Arg1.1: the average speed of 100km per hour


impedes the work of local vendors that are
located along the highway

Arg 1.1.1: road vendors are an important


economical income for small towns.

Arg1.2: the project does not offer jobs that


compensate those that will be eliminated

Arg1.2.1: although work is offered to the


locals, they are not considered capable due
to the lack of work experience required,
which deviate the work to external people.
Arg 1.2.1.1: According to MinEdu reports in
the areas where the project is developed,
there is an illiteracy rate close to 12.9%,
which is higher than the national result that
averages 8.0%. In addition, only 26% of the
population reached the level of secondary
education and just 15% at the technician /
technology level.

Arg. 1.3 Studies shows that this type of


project increases the cost of living for local
communities due to the floating population
that arrives new to the area
ARG 2: The inversion given for La Ruta del Sol Project
should be invested to solve higher requirements of the
community

Arg2.1 Only 77.8% of the community from the coastal side of


the country has access to the aqueduct, below the national
average of 80% according to the Superintendency of Public
Services, a situation that is worse in the rural sector: Only 4
out of 10 inhabitants are constantly receiving water suitable for
human consumption.

Arg 2.2 According to a study on DEVELOPMENT POLICY FOR


THE CARIBBEAN REGION, more than 33.4% of the population
of the region is above the poverty line. This is a problem that
must be prioritized
Arg. 3 The project does not offer monetary retribution or
helps to ensure the vital services of the affected
population
Arg. 3.1 La Ruta del Sol Project endangers the natural
resources which the population depends on and there are
not enough parameters that guarantees the preservation of
water resources and reserve ecosystems that provide
water for the region in spaces like Guaduas territory.

Arg. 3.2 There are no guarantees after selling our land for
the project, when these are in many cases our only asset.

Arg. 3.2 Those responsible for the project do not offer


commitments, at least formally speaking, since there are
no documents to which the population can appeal to
demand compensation
Civil Community

- The economy of the small sellers

- The general pollution (auditive and environmental)

- The price are going to rise in general for the inhabitants of the towns
Indigenous Community

2013 2014
First debates between Yuma destroyed 52 sacred
government (Ministerio del locations of the
Interior and CIF) - Confederación Indígena
Conclusion: Take care and Tayrona (ecosystem ● Compensation for the destructed
respect of sacred locations services of the Sierra locations
of the indigenous Nevada). Indigenous told
community that they are against the ● We don´t trust in what
project. government say, if they broke the
contract once, what we can
expect?
Black Community

● Conflict between economic value and corruption story.

● Basic services are not a priority for the government.

● How can we be ok with this project if we don't even have city lightning.

● Environmental issues are not well defined.