These are the preliminary information needed.

1. Complete specification of solar panels used


Included the complete string plan of the solar panels
2. Complete specification of inverter used.
Included the harmonic spectrum of the inverter/s used.
3. Single Line Diagrams (both of the facility and the solar PV system) *
Must contain the information from the Utility down to the tapping point of the solar PV
system and show the immediate (specific or cumulative) after the tapping point.
Must also contain complete length measurements.
4. Load Data
Load Profile every hour (kW, kVAR, kVA) of the loads. Taken at LVSG.
5. Utility Data
Fault Level at the connection point.
6. Protective Device Data or Circuit Breaker Data
Picture of the brands and models of the circuit breakers used. Preferably on all types used
in the system.
kAIC info must be included.
If the circuit breaker has trip units (LSIG), please include the settings indicated.