Академический Документы
Профессиональный Документы
Культура Документы
Indice de révision : 1
Page 1 of 41
B & R- C J???-PEP-???-0-02
This Template is to be used for the creation of all Project Execution Plans.
The areas in blue text need specifically updating to include specific project details.
Le présent document est la propriété exclusive de B&R-C. Il ne peut être diffusé en externe sans l’autorisation écrite du responsable qualité
Project Execution Plan Date : 1 October 2002
Indice de révision : 1
Page 2 of 41
B & R- C J???-PEP-???-0-02
Date
Evolution du document :
Date Indice Objet de la modification
Le présent document est la propriété exclusive de B&R-C. Il ne peut être diffusé en externe sans l’autorisation écrite du responsable qualité
Project Execution Plan Date : 1 October 2002
Indice de révision : 1
Page 3 of 41
B & R- C J???-PEP-???-0-02
Contents
1.0 INTRODUCTION 5
1.1 Purpose 5
1.2 Project History 5
2.0 PROJECT PROFILE 5
2.1 Contract Title 5
2.2 Customer 5
2.3 Project Participants 5
2.4 Form of Contract 6
2.5 Scope of Work 7
2.6 Key Contract Dates 8
2.7 Critical Success Factors 8
3.0 ORGANISATION 9
3.1 Organisation Structure 9
3.2 Roles and Responsibilities 10
3.3 Authorisation Matrix 15
3.4 Communications Matrix 16
4.0 WORK BREAKDOWN STRUCTURE 16
5.0 PLANNING & SCHEDULING 18
5.1 Scope 18
5.2 Schedule 18
5.3 Schedule Baseline 18
5.4 Project Master Schedule 19
5.5 Detailed Schedules 19
5.6 Schedule Control 19
5.7 Change Management 19
5.8 Schedule Maintenance 19
6.0 INFORMATION TECHNOLOGY 20
6.1 IT Strategy 20
6.2 Information Management 20
6.3 Project Controls 21
6.4 Document Control 21
7.0 COMMERCIAL 21
8.0 RISK MANAGEMENT 23
9.0 QUALITY ASSURANCE 24
9.1 Organisation 24
9.2 Objectives 24
9.3 Audit Programme 24
9.4 Procurement QA/QC 24
9.5 Site QA/QC 25
9.6 Continuous Improvement 25
10.0 HEALTH, SAFETY & ENVIRONMENTAL 25
10.1 Organisation 25
10.2 Objectives 26
10.3 Engineering HSE 26
10.4 Site HSE 26
Le présent document est la propriété exclusive de B&R-C. Il ne peut être diffusé en externe sans l’autorisation écrite du responsable qualité
Project Execution Plan Date : 1 October 2002
Indice de révision : 1
Page 4 of 41
B & R- C J???-PEP-???-0-02
Le présent document est la propriété exclusive de B&R-C. Il ne peut être diffusé en externe sans l’autorisation écrite du responsable qualité
Project Execution Plan Date : 1 October 2002
Indice de révision : 1
Page 5 of 41
B & R- C J???-PEP-???-0-02
Le présent document est la propriété exclusive de B&R-C. Il ne peut être diffusé en externe sans l’autorisation écrite du responsable qualité
Project Execution Plan Date : 1 October 2002
Indice de révision : 1
Page 7 of 41
B & R- C J???-PEP-???-0-02
1.0 INTRODUCTION
1.1 Purpose
To document the scope and execution method for the contract between ‘Ministere de la Defense
Nationale Direction Centrale des Services de Sante Militaire Direction des Projets de Realisation’ and
‘Brown & Root-Condor Spa’ (BRC) for the Engineering design, Procurement and Construction of the
new Oran and Constantine Regional Military University Hospitals.
ORAN
May 1999 - Request for Proposal
2.2 Customer
Le présent document est la propriété exclusive de B&R-C. Il ne peut être diffusé en externe sans l’autorisation écrite du responsable qualité
Project Execution Plan Date : 1 October 2002
Indice de révision : 1
Page 8 of 41
B & R- C J???-PEP-???-0-02
ORAN
The contract is bound by all Algerian legal and regulatory requirements applicable to Public Contracts,
as defined in the contract.
Contract 1 – Lump sum & estimated quantities priced according to the agreed unit prices in the contract.
The actual quantities will be measured during construction and the price recalculated. The prices are
fixed and are subject to adjustment for escalation and currency exchange rate.
Contract 2 - Lump sum & estimated quantities priced according to the agreed unit prices in the contract.
The actual quantities will be measured during construction and the price recalculated. The prices are
fixed and are subject to adjustment for escalation and currency exchange rate.
Contract 3 - Lump sum & estimated quantities priced according to the agreed unit prices in the contract.
The actual quantities will be measured during construction and the price recalculated. The prices are
fixed and are subject to adjustment for escalation and currency exchange rate.
Bank Guarantee: All advance payments will be made against a bank guarantee of equal value until to
total amount paid reaches 80% of the contract price.
Retention Bond: A 5% retention bond will be held against each progress payment and the bond will be
released 1 month after signature of the Final Acceptance.
Liquidated Damages: Liquidated damages will be payable for delays extending beyond 4 weeks the
specified time limits, according to the contract formula but not exceeding 5% of the contract price.
Warranty: All materials and equipment are guaranteed for a period of 12 months following the
provisional acceptance of the works. The building and structures are guaranteed for 10 years in
accordance with article 554 of the Algerian civil construction code.
Le présent document est la propriété exclusive de B&R-C. Il ne peut être diffusé en externe sans l’autorisation écrite du responsable qualité
Project Execution Plan Date : 1 October 2002
Indice de révision : 1
Page 9 of 41
B & R- C J???-PEP-???-0-02
The Engineering Design, Procurement and Construction of a Regional Military University Hospital at
Oran, Algeria, having a capacity of 354 beds.
Contract 1
Engineering (Lump Sum)
Design and detailed engineering studies
Medical consultants
Contract 2
Construction (Lump Sum)
Construction shop drawings
Site Supervision - 22 months
Contract 3
Equipment Procurement (Lump Sum)
Site Supervision–20 Months (Lump Sum)
Contract 4
Equipment Procurement (Lump Sum)
Medical equipment – Fixed
Le présent document est la propriété exclusive de B&R-C. Il ne peut être diffusé en externe sans l’autorisation écrite du responsable qualité
Project Execution Plan Date : 1 October 2002
Indice de révision : 1
Page 10 of 41
B & R- C J???-PEP-???-0-02
Zero Accidents
Completion on time
Completion within Budget
Technical Compliance
Effective Communication
Management of William A. Berry & Son Inc
Engineering Management
Procurement Management
Site Supervision & QC
Building Finishes
Special Medical Finishes
Commissioning & Client Acceptance
Le présent document est la propriété exclusive de B&R-C. Il ne peut être diffusé en externe sans l’autorisation écrite du responsable qualité
Project Execution Plan Date : 1 October 2002
Indice de révision : 1
Page 11 of 41
B & R- C J???-PEP-???-0-02
3.0 ORGANISATION
P ro je c t M a n a g e r
HM RUO
M o h a m e d T A IB I
H SE M anager Q a u lity M a n a g e r
Y o u c e f A O U IS S I C o in L e G E Y T
D e p u ty P ro je c t M a n a g e r
M oham ed R eda G U EM AZ I
F in a n c e
S ee sheet 2 P ro c u re m e n t M a n a g e r S ee S heet 3 C ost M anager S ee S heet 4
A b d e l k r im K A C I N acer B E N H ALLA B r a h a m S A ID I
W A B e rry F a y c a l B E N T IR
S ouad
M a te r ia ls C o n tr o l
M anager S n r C o s t E n g in e e r
B r ia n O 'C O N N E L L S te p h e n P O T T E R
S ee S heet 3 C o s t E n g in e e r s
C h ik h A B D E L K R IM
M ah di K E R AZ
P la n n in g
S a lim B E N H A M O U D A
N a c e r a Z E B IR I
R ic h a r d R E N S H A W
S e n io r
D o c u m e n t C o n tro l
M a h ie d d i n e H A M D A N I
D o c u m e n t C o n tro l
N a ta c h a L A D O U I R e s p o n s ib l e f o r
HM RUO & HM RUC
Le présent document est la propriété exclusive de B&R-C. Il ne peut être diffusé en externe sans l’autorisation écrite du responsable qualité
Project Execution Plan Date : 1 October 2002
Indice de révision : 1
Page 12 of 41
B & R- C J???-PEP-???-0-02
Project Manager:
Responsible for the overall execution and day to day management of the project in accordance with the
contract, technical, budget, programme, quality and HSE requirements whilst maximising profit. To
manage and support to the project team to ensure that the key success factors are understood and
achieved. Approval of all sub-contracts, purchase orders, payments and client invoices. Day to day
management of the client and reporting to the client. Management of all client communications and
approval of all formal communication to the client. Staff performance management and development.
Reporting to the General Project Manager.
Quality Manager:
Responsible for the project Quality Assurance/Quality Control activities and for quality management of
all project processes and quality control of all project deliverables, including site inspection and
equipment certification. Plans and establishes the site Quality programs. Interfaces with DG/operations,
client, and corporate Quality Assurance/Quality Control to ensure Quality objectives are met. Advises
the Technical Manager on quality issues during the design process. Staff performance management and
development. Reports to the Project Manager under the operational control of the BRC Quality Director.
HSE Manager:
Responsible for implementation of BRC’s Health, Safety and Environmental (HSE) plan & procedures
and is further responsible for ensuring correction of any unsafe practices, which may exist in company
operated facilities or tasks. Advises the Technical Manager on HSE issues during the design process.
Monitors employee and subcontractor safe work practices and performance to contract, Company, and
Algerian HSE requirements. Staff performance management and development. Reports to the Project
Manager under the operational control of the BRC Health, Safety & Environmental Director.
Technical Manager:
Responsible for all engineering design and the technical integrity of the project including in-house and
sub-contract design work. Planning and managing all aspects of the design process from concept design
through to development of as-built drawings and operating and maintenance manuals. Plans and
manages design reviews. Manages the design team to ensure contract requirements are satisfied within
the established budget and time-scale. Verifies co-ordination between disciplines, and co-ordinates with
procurement and construction management in the development of work packages. Responsible for
ensuring HSE requirements are addressed at all stages of the design process. Obtaining approvals from
Le présent document est la propriété exclusive de B&R-C. Il ne peut être diffusé en externe sans l’autorisation écrite du responsable qualité
Project Execution Plan Date : 1 October 2002
Indice de révision : 1
Page 13 of 41
B & R- C J???-PEP-???-0-02
certification bodies, including CTC and DPP. Staff performance management and development. Reports
to the Project Manager.
Lead Engineer: Responsible managing engineering design performance by the respective design team
and design subcontractor(s). Ensures client requirements are understood by the design team and that they
are reflected by design deliverables. Provides interface between BRC, the client and the design
subcontractor. Develops the deliverables lists and manages delivery to satisfy agreed project schedules.
Provides continuous review of design documents to confirm contract compliance and HSE requirements.
Responsible to develop the commissioning plan and procedures for the respective disciplines. During
construction, performs subcontractor submittal review; conducts routine site visits to assess installation
per design documents; and provides technical assistance as requested from the Construction Manager.
Provides “As-Built” information to design subcontractor for production of As-Built drawings. Reports to
the Technical Manager.
P&M Manager:
Responsible for the planning and direction of all project procurement and materials management
services. Management and support of the Procurement team to ensure that they meet the project
objectives by delivering materials and related services on time and within budget, in an ethical manner at
all times, in accordance with published company procedures. Staff performance management and
development. Responsible for managing the personnel and processes in executing the procurement of
specific materials to ensure such are within budget and delivered in accordance with agreed project
schedules. To ensure that all parties maintain the high standard of ethics required by BRC. Reporting to
the Project Manager.
Procurement Manager (WA Berry): Responsible for managing and reporting progress on all
procurement related activities with the design sub-contractor (W. A. Berry) in their execution of the
procurement of specific materials and sub contracted services to ensure such materials and services are
delivered in accordance with agreed project schedules. To ensure that the correct information is provided
in the correct format by the sub-contractor, in a timely manner, for all items to be supplied by Brown &
Root Condor (Algiers). Ensuring that all parties maintain the high standard of ethics required by BRC at
all times. Reporting to the Senior Procurement Manager.
Sub-contracts Manager: Responsible for the management of all project sub-contracts including, the
contract, change control, correspondence, invoices and payment. Reporting to the Procurement Manager.
Buyer – Local: Responsible for selecting and negotiating with approved suppliers and placing purchase
orders in response to material requirements established by field operations or project management.
Reports to the Procurement Manager.
Le présent document est la propriété exclusive de B&R-C. Il ne peut être diffusé en externe sans l’autorisation écrite du responsable qualité
Project Execution Plan Date : 1 October 2002
Indice de révision : 1
Page 14 of 41
B & R- C J???-PEP-???-0-02
with Planning, Engineering, Procurement, Expediting, Traffic, and the construction site, in the
identification of requirements and progressing those requirements through / delivery cycle to meet the
needs of the construction schedule. Reporting to the project P&M Manager.
Senior Planner: Responsible for the provision and management of planning, scheduling and analysis
services to the Project Managers. Ensuring BRC standard procedures and controls are applied to the
production and maintenance of schedules. Provides direction, guidance and oversight of the Project
Planner. Reports to the Project Controls Manager.
Planning Engineers: Support the Senior Planner by production and monitoring the programme, regularly
measuring and recording progress, being pro-active with rectification measures and producing progress
reports for the Project Managers. Reporting to the Senior Planner.
Senior Cost Engineer: Responsible for the provision cost control services to the Project Managers.
Ensuring standard procedures and controls are applied to the production and maintenance of cost reports,
forecast and analysis for the Project Managers. Provides direction, guidance and oversight of the Cost
Engineers. Reports to the Project Controls Manager.
Cost Engineers: Responsible for project cost and revenue recording, monitoring the cost, cash flow,
forecasting and analysis, being pro-active with rectification measures and producing cost reports. Cost
control of sub-contract work in conjunction with the Sub-contracts Manager. Reporting to the Senior
Cost Engineer.
Document Control: Responsible for the management, registration, control, issue, copying, distribution,
transmittal and producing status reports of all project documents (BRC, sub-contract and supplier
documents) in accordance with BRC procedures for the Project Mangers.
Estimator: Responsible for producing and updating estimates as the design progresses to ensure
compliance with the approved project budget. Evaluates design options for most economical solution
satisfying contract requirements. Provides estimates required supporting procurement work packages.
Provides estimates for all proposed contract and subcontract changes. Reports to the Project Controls
Manager.
Construction Manager:
Management of the construction camp and construction elements of the works with responsibility for the
safe delivery of the works to time, and quality. Responsible for the planning and scheduling of all site
activities and supporting the site teams to deliver the project in accordance with the contract. Ensures
that the construction elements of the works are co-ordinated and managed in accordance with the BRC
Le présent document est la propriété exclusive de B&R-C. Il ne peut être diffusé en externe sans l’autorisation écrite du responsable qualité
Project Execution Plan Date : 1 October 2002
Indice de révision : 1
Page 15 of 41
B & R- C J???-PEP-???-0-02
procedures. Management of and liaison with all site sub-contractors. To advise the Technical Manager
on constructibilité during the design process. To provide weekly and monthly construction activity
reports. Staff performance management and development. Reporting to the Project Manager.
Deputy Construction Manager: Reports to the Construction Manager and is responsible for overseeing
the site procurement, engineering, and project control activities. Works with the craft superintendents to
co-ordinate the subcontractor activities to ensure orderly, efficient, and safe completion of work.
Maintains positive working relationships with clients, architects/engineers, suppliers, subcontractors, and
job site staff. To achieve the goals of the project, the Deputy Construction Manager works in
co-ordination with the craft Superintendents.
Site QA/QC Manager: reports to the Construction Manager but reports to the Project Quality Manager
on quality maters. The site QA/QC Manager and the QC Supervisors take a pro-active approach to
assisting the fabrication yards. They participate in the resolution of any non-conformance that require a
specific disposition (repair, use-as-is and re-design) and they require field installation records by
discipline craft supervision for inclusion in the final documentation package (Mechanical completion
files). The site QA/QC Manager and the QC Supervisors assist the representatives of the Client and the
Algerian authorities (CTC, DPP, ONML…) in the execution of their duties.
QC Supervisor: reports to the Site QA/QC Manager and eventually to the Construction Manager. He
monitors construction and installation work performed by subcontractors. He assures that the work is
done in accordance with the Contract and Engineering requirements. He performs inspections and
witness tests identified in the inspections and tests plans for the work.
Superintendent / Civil and Architectural (Hospital): reports to the Construction Manager and is
responsible for managing the implementation of the civil works, the interior and exterior finishing of the
buildings, the preparation of revisions to drawings and specifications at the site, and the interface with
the engineering offices in Algiers and North America. Provides daily and weekly construction reports
and ensures that the work is progressing in a safe and efficient manner and in accordance with the
schedule. Interfaces with the CTC to resolves concerns that the CTC present.
Superintendent / Electrical (Hospital): reports to the Construction Manager and is responsible for
managing the installation of the temporary power and its distribution, the installation of the electrical
work, the preparation of revisions to drawings and specifications at the site, the interface with the
engineering groups, the timely delivery of materials and tools to the site. Provides daily and weekly
construction reports and ensures that the work is being executed in a safe and efficient manner and in
accordance with the schedule. Interfaces directly with the subcontractor and client.
Superintendent Piping / Plumbing / Mechanical (Hospital): reports to the Construction Manager and
is responsible for the installation of the piping, plumbing, and mechanical materials plus equipment, the
preparation of revisions to drawings and specifications at the site, the interface with engineering groups,
the timely delivery to the site of materials, equipment and tools. Provides daily and weekly construction
reports and ensures that the work is being executed in a safe and efficient manner and in accordance with
the schedule. Interfaces directly with the subcontractor and client.
HVAC Superintendent (Hospital): reports to the Construction Manager and is responsible for
managing the installation of the HVAC materials and equipment, directing the HVAC supervisors, the
managing of the revisions to drawings and specifications at the site, the interface with engineering
groups, the timely delivery to the site of materials, equipment and tools. Provides daily and weekly
Le présent document est la propriété exclusive de B&R-C. Il ne peut être diffusé en externe sans l’autorisation écrite du responsable qualité
Project Execution Plan Date : 1 October 2002
Indice de révision : 1
Page 16 of 41
B & R- C J???-PEP-???-0-02
construction reports and ensures that the work is being executed in a safe and efficient manner and in
accordance with the schedule. Interfaces directly with the subcontractor and client.
Deputy Superintendent / Leader Electrical Discipline: reports to the Electrical Superintendent and is
responsible for managing the construction of the electrical work, directing the craft supervisors,
preparing field revisions to the construction drawings and specifications, interfacing with the
subcontractors, preparing the daily construction report, and ensuring that the materials and people are at
the work area to execute the work. Interfaces directly with the client to ensure that the work is being
carried to his satisfaction. Ensures that the work is being executed in a safe and efficient manner.
Deputy Superintendent / Leader Civil and Architectural: reports to the Civil / Architectural
Superintendent to manage the installation of the civil works, the masonry, the top coat of concrete for the
floors, the interior finishing and exterior cladding comprising ceramic tiles and metallic materials.
Interfaces directly with the subcontractors and directs the activities of the supervisors who oversee the
work. Interfaces directly with the client to ensure that the client requirements are being met.
Responsible to ensure that the installation of the work is performed in an efficient and safe manner.
Site Procurement Superintendent: reports to the Deputy Construction Manager and is responsible for
managing the activities of the Subcontract Administrator, the Site Buyer and Accountant, the
warehousemen, and the material control people. Interfaces directly with the procurement department in
Algiers to ensure that the invoices are paid on time and the required materials, equipment, and
documents arrive on site in a timely manner.
Site Engineering Superintendent: reports to the Deputy Construction Manager and is responsible for
managing the site engineering group to carry out the site modifications for drawings. Co-ordinates his
work and the activities of the group with the engineering department in Algiers to ensure that site work is
being executed within the norms and specifications of BRC.
Commissioning Manager:
Plans and manages all commissioning activities including sub-contractor commissioning. Leading the
commissioning teams responsible for verifying that the design intent of the facility is satisfactorily
achieved. Achieving Client acceptance of all system acceptance tests and equipment certification. Staff
performance management and development. Reports to Project Manager.
Le présent document est la propriété exclusive de B&R-C. Il ne peut être diffusé en externe sans l’autorisation écrite du responsable qualité
Project Execution Plan Date : 1 October 2002
Indice de révision : 1
Page 17 of 41
B & R- C J???-PEP-???-0-02
The matrix defines the lowest approval levels. All approvals may be given at a higher level than defined.
Sub-Contracts and Purchase Orders: All Sub-Contracts and Purchase Orders must be presented to the
‘Commission de Marche’ for review and signature, in accordance with BRC Corporate Procurement
Policy.
Payments: All payments and cheques must be authorised in accordance with BRC Corporate Finance
Policy.
Le présent document est la propriété exclusive de B&R-C. Il ne peut être diffusé en externe sans l’autorisation écrite du responsable qualité
Project Execution Plan Date : 1 October 2002
Indice de révision : 1
Page 18 of 41
B & R- C J???-PEP-???-0-02
Delegation: The Manager responsible may delegate approval authority, all approvals may be given at
the next organisation level up.
Le présent document est la propriété exclusive de B&R-C. Il ne peut être diffusé en externe sans l’autorisation écrite du responsable qualité
Project Execution Plan Date : 1 October 2002
Indice de révision : 1
Page 19 of 41
B & R- C J???-PEP-???-0-02
Note: The apparent redundancies within the building element portions of the WBS structure are
necessary in order for Primavera® to generate cost and schedule reports at each of the four element
levels.
Le présent document est la propriété exclusive de B&R-C. Il ne peut être diffusé en externe sans l’autorisation écrite du responsable qualité
Project Execution Plan Date : 1 October 2002
Indice de révision : 1
Page 20 of 41
B & R- C J???-PEP-???-0-02
5.1 Scope
During the course of the project’s development, changes will be identified which will affect the project
cost and schedule. Each of the Engineering, Procurement and Construction mangers are responsible for
the control of the scope based upon the awarded client contract and must ensure that the changes are
identified to project controls staff to enable evaluation for schedule and cost impact, before any
commitments are made. Project Controls will maintain a register of potential changes and reports the
stage in processing these changes. Changes can be additions, deletions and revisions to the baseline
scope (described within Client Contract) and the Work Breakdown Structure (WBS).
5.2 Schedule
The project schedule is prepared to reflect the project’s scope of work for each of the WBS elements
described within Section 4.0 of this document. The schedule defines the sequence and relationship
among the schedule activities. Through the estimating and budgeting process, resource requirements are
identified in accordance with the WBS and time durations for each activity are established. Date
calculations within the scheduling system provide the start and finish dates for each activity and
resources are time phased in accordance with the schedule dates. There are three project calendars used
on the project:
Calendar 5 – Five day work pattern for Engineering and Procurement activities.
Calendar 6 – Six day work pattern for Construction and Commissioning activities.
Calendar 7 – Client contracts using 7 days a week.
For the calendar numbers 5 and 6, public holidays are shown within the scheduling system as non-
workdays.
A Critical Path Method (CPM) scheduling program ‘Primavera P3’ facilitates the modelling of the
project plan. Workflow sequencing is based on BRC’s work processes. Throughout the life of the
project, the schedule is maintained with current status and is analysed against the approved baseline
(target) schedule to identify deviations that require corrective action by the relevant manager:
Engineering, Procurement and Construction teams.
At the time the schedule is baselined, the Planned dates are the same as forecast dates. Subsequent
changes to the schedule based upon actual performance or revised activity duration’s will result in new
forecast dates as a variance against the schedule baseline.
Le présent document est la propriété exclusive de B&R-C. Il ne peut être diffusé en externe sans l’autorisation écrite du responsable qualité
Project Execution Plan Date : 1 October 2002
Indice de révision : 1
Page 21 of 41
B & R- C J???-PEP-???-0-02
The more detailed level 3 schedule will continue to break the work into individual procurement work
packages. In the early planning, Construction logic will be developed to the extent that each WBS work
element and each work activity type is represented for each area. As construction planning progresses the
construction activities will be more fully defined as required to execute the work. As an example for
construction scheduling of the building structural work, activity sub-elements of Foundations and
Superstructure are described:
- Block A
- Block B
- Block C
And assigned area designations: A1, A2, A3, A4, A5, A6, B1, B2 C1, C2, & C3. These correspond to
structural areas as defined by seismic control joints.
1. Monitoring the schedule activities for actual start and finish dates and projecting the remaining
duration’s for work that is in process.
2. Performance evaluations of progress and earned value.
3. Schedule Analysis to determine critical path and schedule deviations from plan.
Schedule Control provides early indication of deviations from plan in order that corrective actions
(amending activity sequences and logic) can be implemented to minimise schedule and cost impact to
the project’s performance.
Le présent document est la propriété exclusive de B&R-C. Il ne peut être diffusé en externe sans l’autorisation écrite du responsable qualité
Project Execution Plan Date : 1 October 2002
Indice de révision : 1
Page 22 of 41
B & R- C J???-PEP-???-0-02
the schedule from Level 5 to Level 0 satisfies contract requirements. After re-sequencing activities,
loading additional resources, and/or accelerating the start of activities, the planner shall update the
project management team and obtain Project Manager approval. Impacts to cost, quality, and customer
satisfaction will be considered prior to implementation.
LEVELS
PROJECT MASTER
SCHEDULE
Line 1 of 5
BR-C Plan with Contract Milestones and 1
Line 2 of 5
Line
Line
Line
Line
3 of 5
4 of 5
5 of 5
1 of 4
Summary Activities
Line 2 of 4
Line 3 of 4
Line 4 of 4
Risk Analysis
PROJECT MANAGEMENT
CONTROL PROGRAMME
Key activities & Project/Contract milestones by
Variances, Trends Line 1 of 5
Line 2 of 5
Line 3 of 5
discipline against WBS 2
Line 4 of 5
Line 5 of 5
Line 1 of 4
Line 2 of 4
Forecasts
Line 3 of 4
Line 4 of 4
CONTROL NETWORK
& SUPPORTING Basic Programme
Status Reports and Forecasts SCHEDULES
for All Phases 3
WORK PACKAGES
for All Phases and Disciplines 4
Line 1 of 5 Line 1 of 5 Line 1 of 5 Line 1 of 5
Line 2 of 5 Line 2 of 5 Line 2 of 5 Line 2 of 5
Line 3 of 5 Line 3 of 5 Line 3 of 5 Line 3 of 5
& Forecasts
Line 4 of 5 Line 4 of 5 Line 4 of 5 Line 4 of 5
Line 5 of 5 Line 5 of 5 Line 5 of 5 Line 5 of 5
Line 1 of 4 Line 1 of 4 Line 1 of 4 Line 1 of 4
Line 2 of 4 Line 2 of 4 Line 2 of 4 Line 2 of 4
Line 3 of 4 Line 3 of 4 Line 3 of 4 Line 3 of 4
Line 4 of 4 Line 4 of 4 Line 4 of 4 Line 4 of 4
Te am Te am
6.1 IT Strategy
The project will use the Halliburton common operating environment (COE). Drawing are being
produced using AutoCAD and Micro-station, all other documents will be produced using Microsoft
Office.
The architect and medical specialist for the project William A. Berry & Son Inc. will use the same
standard software.
Le présent document est la propriété exclusive de B&R-C. Il ne peut être diffusé en externe sans l’autorisation écrite du responsable qualité
Project Execution Plan Date : 1 October 2002
Indice de révision : 1
Page 23 of 41
B & R- C J???-PEP-???-0-02
William A. Berry & Son Inc (WAB) have established a project specific web site. To facilitate use of
common project data and the transfer of Cad drawings, the web site is known as ‘Bricsnet’. The Logon
web page address is http://projectcenter.com
All hard copy documents are controlled through the BRC document control system including issue to
sub-contractors via procurement and to the construction site.
The project budget and costs are recorded, tracked, managed and reported using Microsoft Excel
Spreadsheets and a Microsoft Access Database at present. It is planned to implement the Halliburton
Cost Management System HCMS.
7.0 COMMERCIAL
The agreed contract values are:
1 US$ = 70 DA
Contract Item Lump Sum Unit Prices
US$ US$
Contract 1 Engineering
Design and detailed engineering studies
Medical consultants
Construction Site Establishment
Mobilisation site personnel
Site offices
Temporary site service connections
Preliminary Construction Work
Site preparation
Earth works
Road & Parking areas, base layers
Perimeter Fencing
Gate House & barriers
Site Supervision – 6 months
Sub Total
Le présent document est la propriété exclusive de B&R-C. Il ne peut être diffusé en externe sans l’autorisation écrite du responsable qualité
Project Execution Plan Date : 1 October 2002
Indice de révision : 1
Page 24 of 41
B & R- C J???-PEP-???-0-02
Landscaping
Heliport
Construction shop drawings
Site Supervision - 22 months
Construction General Civil Works
Substructure works
Superstructure works
Prefabrication works
Waterproofing
Exterior masonry
Interior walls
Wall finishes
Floor finishes
Ceiling
Ceiling for IT room
Exterior painting
Interior painting
Miscellaneous accessories
Construction Special Works:
MRI Faraday room
Radiation Shielding
Sub Total
Le présent document est la propriété exclusive de B&R-C. Il ne peut être diffusé en externe sans l’autorisation écrite du responsable qualité
Project Execution Plan Date : 1 October 2002
Indice de révision : 1
Page 25 of 41
B & R- C J???-PEP-???-0-02
Perimeter Fencing
Guard post
Miscellaneous equipment:
MILCARE equipment
Medical equipment
Furniture
Domestic Equipment
TV system
Archive System
Sterilisation
Consumables:
Installation of Medical Equipment
Work shop tools
Commissioning, Training,
Testing and Handover
Fixed Equipment:
IT system
Provisional Costs
Sub Total
Contract Sub Total
Reimbursable Costs
Contract Total
The management of project risk is key to ensuring a satisfactory outcome to the project. The purpose of
this process is to identify the risks, which have potential to prevent project completion within cost and
schedule, and to formulate a methodology such that they can be accommodated and managed within the
budget estimate.
Avoid - These are risks so onerous they cannot be accepted by any of the contracting
parties. These may result in a “no bid” decision or even in a postponement or
cancellation of the project.
Accept - In some cases it will not be possible (or cost effective) to mitigate a risk and, in
such circumstances, a likely contingency fund must be set aside and the risk left in
“free fall” mode.
Reduce - Develop a plan and series of actions that will reduce the probability of the risk
occurring and/or reduce the impact if it does happen.
Transfer - Transfer the risks to another party whom is more able to manage the risk, e.g.
Contractual or Insurance.
Le présent document est la propriété exclusive de B&R-C. Il ne peut être diffusé en externe sans l’autorisation écrite du responsable qualité
Project Execution Plan Date : 1 October 2002
Indice de révision : 1
Page 26 of 41
B & R- C J???-PEP-???-0-02
9.1 Organisation
All employees are responsible for the quality of their own work, for ensuring that all work is submitted
“right first time”, already checked. The Project Director has overall responsibility for project quality as a
whole including that of sub-contractors.
The project will follow the BR-C company quality management system in particular following the
outline described in the Quality Manual comprising:
A Project Quality Manager shall be nominated to oversee project quality as a whole. His role shall
include participation in project management meetings.
QA/QC staff assigned to the project team on a part time or full time basis report directly to the relevant
project departmental supervisor. QA/QC staff nevertheless maintains a discipline reporting line to the
Project Quality Manager and through him the BRC Quality Director to assure that company Quality
standards are maintained.
9.2 Objectives
Project QA/QC objectives shall be identified and reviewed prioritised and refined periodically
throughout the project. These objectives shall be quantifiable and measured and analysed on a monthly
basis to identify trends.
Corrective and preventive actions associated with corporate audit findings shall be agreed with the home
office auditor by project management.
These findings and associated actions will be reviewed and expedited during project meetings and the
progress on outstanding actions reported to the Director of Quality on a monthly basis.
- review for completeness of RFQ’s and PO’s as part of the approval-for-issue process.
Le présent document est la propriété exclusive de B&R-C. Il ne peut être diffusé en externe sans l’autorisation écrite du responsable qualité
Project Execution Plan Date : 1 October 2002
Indice de révision : 1
Page 27 of 41
B & R- C J???-PEP-???-0-02
- factory release
Where appropriate, specific factory visits can be assigned to parent companies or approved inspection
agencies. This may be the most effective way to manage overseas packages economically.
- Surveillance of materials, construction, installation and testing activities including site qualification
testing. In the case of hospitals, this could include: concrete mix trials; road base trials; floor screed
trials; preparation of reference paint panels etc;
- management of the BR-C non-conformance control system and supervision of sub-contractor non-
conformance;
- QA audit and spot checks on: document control including verification of specifications and
construction drawings; field changes; materials, construction, procurement package, installation and
testing records; materials laboratory activities including calibration; batch plant calibration;
The Project Manager shall ensure that Quality issues and actions, including customer feedback are
reported monthly and through the project close out process to ensure that project data is captured by the
home office and the BR-C quality management system.
10.1 Organisation
The Project Manager is responsible for Health, Safety and Environmental issues and in particular with
ensuring project compliance with legislation and voluntary company standards.
Le présent document est la propriété exclusive de B&R-C. Il ne peut être diffusé en externe sans l’autorisation écrite du responsable qualité
Project Execution Plan Date : 1 October 2002
Indice de révision : 1
Page 28 of 41
B & R- C J???-PEP-???-0-02
The Construction Manager has overall responsibility and authority to ensure site safety.
There will be a full time HSE representative on site who reports directly to the Construction
Management. The HSE manager nevertheless maintains a discipline reporting line to the BRC HSE
Director to assure that company HSE standards are maintained.
All staff and in particular those on site are responsible for ensuring their own health & safety and that of
co-workers and visitors. All personnel are requested to identify hazards and notify them to responsible
management for corrections.
10.2 Objectives
Health & Safety and Environmental measurable objectives shall be identified and periodically reviewed
prioritised and refined throughout the project.
- over-sight of safe site working practices including use of protective equipment, house keeping,
moving equipment, lifting equipment, access including temporary staircases and elevators, site
manufacturing and construction activities, barriers around openings, traffic.
- management of regular site safety meetings and following up and progress reporting on actions
11.0 PROJECT REPORTING
Le présent document est la propriété exclusive de B&R-C. Il ne peut être diffusé en externe sans l’autorisation écrite du responsable qualité
Project Execution Plan Date : 1 October 2002
Indice de révision : 1
Page 29 of 41
B & R- C J???-PEP-???-0-02
1. Summary
2. Management
2.1. Engineering
2.2. Construction
2.3. Project Controls
3. Project Progress
3.1. Schedule
3.2. Actual progress against planned
3.3. Cost of work to-date
3.4. Cash Flow
4. Construction
5. Cost Report (Internal report Only)
6. Project Photographs
Schedule
The project plan will be updated weekly by Project Controls based on the individual reports from the
discipline managers and issued internally at level 4.
Engineering
Each Lead Engineer will report weekly with; progress as a percentage of actual work complete, forecast
remaining duration, any changes to planned activities, network logic and resources.
A status report for all in house and sub-contract engineering activities will be prepared monthly
detailing; progress, technical issues effecting progress, and status of engineering changes.
Construction
A status report for all construction activities will be prepared weekly and monthly detailing; progress,
technical, HSE and Quality non-conformity reports (NCR) and procurement issues effecting progress.
Procurement
A status report for the procurement of services, equipment and materials will be prepared monthly,
showing enquiries, tenders, purchase orders and their status.
Cost
A financial report will be submitted for BRC Project Management & Operations review on the 30 th of
each month. Reporting Original Budget; Approved Changes; Revised Budget; Committed Cost;
Expended Cost; remaining to commit; Current Forecast; Budget Variance; Forecast Variance; and
Previous Forecast.
Le présent document est la propriété exclusive de B&R-C. Il ne peut être diffusé en externe sans l’autorisation écrite du responsable qualité
Project Execution Plan Date : 1 October 2002
Indice de révision : 1
Page 30 of 41
B & R- C J???-PEP-???-0-02
activities or network logic changes, issue effecting progress and the status of any contract changes. The
progress reporting form is included at Appendix – F.
Monthly Meetings
Day Time Project Subject Chairman
Sunday 2:00 HMRUO Operations Directors Review Operations
Director
Weekly Meetings
Day Time Project Subject Chairman
Saturday 10:00 HMRUO Project Management General Project
Technical Manager
Schedule
Cost
Finance
12.0 ADMINISTRATION
The project Secretary and Administrator will receive, issue, distribute and maintain records of all
timesheets and travel request.
Le présent document est la propriété exclusive de B&R-C. Il ne peut être diffusé en externe sans l’autorisation écrite du responsable qualité
Project Execution Plan Date : 1 October 2002
Indice de révision : 1
Page 31 of 41
B & R- C J???-PEP-???-0-02
The Document Controller will maintain; records of all project correspondence, minutes of meetings, the
design document register, design records, client comments and approval records, sub-contract design
documents and associated BRC comments and approval.
13 .1 Strategy
GPS engineering design will be done BR-C in Algiers
Hospital Foundation detail design will done by BR-C in Algiers
Hospital Superstructure detail design will done by BR-C in Algiers
Mechanical & Electrical, HVAC, Equipment detail design and construction drawings will be done by
W A Berry & Son Inc. with BR-C support
The engineering design work on the project will be split between the design of the Hospital and the GPS
and between BRC and William A. Berry & Son Inc. (WAB) as detailed below.
GPS Design
Description Level Company Approval
Architectural / Civil Preliminary drawings BRC Client
Layout drawings BRC Client
Detail drawings BRC Client
Le présent document est la propriété exclusive de B&R-C. Il ne peut être diffusé en externe sans l’autorisation écrite du responsable qualité
Project Execution Plan Date : 1 October 2002
Indice de révision : 1
Page 32 of 41
B & R- C J???-PEP-???-0-02
Hospital Design
Description Level Company Approval
Architectural / Civil Preliminary drawings WAB / BRC Client
Layout drawings WAB / BRC Client
Detail drawings WAB / BRC Client
13.4 Calculations
All design calculations will be recorded on BRC calculation sheets; they will be numbered, dated, signed
and independently checked by the Lead Engineer and approved by the Technical Manager.
13.5 Checking
All design documents (design rules, standards, specifications, drawings, instructions, and CAD
drawings) will be independently checked by the Lead Engineer.
Le présent document est la propriété exclusive de B&R-C. Il ne peut être diffusé en externe sans l’autorisation écrite du responsable qualité
Project Execution Plan Date : 1 October 2002
Indice de révision : 1
Page 33 of 41
B & R- C J???-PEP-???-0-02
13.6 Approval
All design documents (design rules, standards, specifications, drawings, instructions, and CAD
drawings) will be approved by the Technical Manager.
14.0 PROCUREMENT
14.1 Strategy
All procurement will be managed by BRC
Major Sub-contracts will be placed for:
Hospital Architectural - Design
Hospital Civil & Structural - Construction
Hospital Mechanical, Electrical & Piping - Design & Procurement
Sports Centre - Design, Procurement and Construction
GPS - Construction
Medical equipment will be procured by BRC in conjunction with the Contracting Authority
Le présent document est la propriété exclusive de B&R-C. Il ne peut être diffusé en externe sans l’autorisation écrite du responsable qualité
Project Execution Plan Date : 1 October 2002
Indice de révision : 1
Page 34 of 41
B & R- C J???-PEP-???-0-02
14.3 Sub-contracts
The Subcontracts Manager is responsible for the commercial activities relative to sub-contract services
required for the project. The Sub-contract Manager is responsible to the Project Manager for the award
of all Sub-contracts, for tracking and forecasting each of the respective budgets and reporting to the Cost
Engineer. Nevertheless, all subcontract staff maintain a discipline reporting line to the Procurement and
Materials Division General Manager..
The Site Subcontract Administrator administers the issued Sub-contracts from mobilisation through
closeout. They have a non-functional reporting line to the Construction Manager. Any requirements by
the Construction Manager that may necessitate a change in the Sub-contract will be referred to the Sub-
contract Manager for resolution, raising of change orders and Project Management/Client approval.
All subcontract activities will be undertaken in accordance with the BRC corporate Procurement Policy,
Procedures and project Work Instructions and to the highest professional and ethical standards.
Le présent document est la propriété exclusive de B&R-C. Il ne peut être diffusé en externe sans l’autorisation écrite du responsable qualité
Project Execution Plan Date : 1 October 2002
Indice de révision : 1
Page 35 of 41
B & R- C J???-PEP-???-0-02
15.0 CONSTRUCTION
15.1 Strategy
Hospital Civil construction contractor is Cosider spa for HMRUO and will be placed with Cosider
spa for HMRUC
Le présent document est la propriété exclusive de B&R-C. Il ne peut être diffusé en externe sans l’autorisation écrite du responsable qualité
Project Execution Plan Date : 1 October 2002
Indice de révision : 1
Page 36 of 41
B & R- C J???-PEP-???-0-02
15.2 Management
The objective of the Construction Management Team is to build a safe, cost effective Hospital in
accordance with the project specifications. The construction team will supervise and co-ordinate all sub-
contract construction activities and plant, equipment and material in an optimum sequence, to enable
timely completion of the works.
The construction team provide common site services such as storage, material control, receipt and issue,
QC, inspection, quantity surveying, scheduling, project controls, safety, security and medical services.
Le présent document est la propriété exclusive de B&R-C. Il ne peut être diffusé en externe sans l’autorisation écrite du responsable qualité
Project Execution Plan Date : 1 October 2002
Indice de révision : 1
Page 37 of 41
B & R- C J???-PEP-???-0-02
15.6 Schedule
All construction work will be undertaken in accordance with Project Master Schedule requirements. The
Site Planning Engineer will co-ordinate all site planning and scheduling activities with the Senior
Planning Engineer in Algiers and Sub-contractors producing detailed site schedules which will be
updated weekly. Monthly and weekly construction look ahead schedules will be used to report progress.
Le présent document est la propriété exclusive de B&R-C. Il ne peut être diffusé en externe sans l’autorisation écrite du responsable qualité
Project Execution Plan Date : 1 October 2002
Indice de révision : 1
Page 38 of 41
B & R- C J???-PEP-???-0-02
The Algerian ‘Contrôle Technique de la Construction’ (CTC) are the Algerian certification body
responsible for technical monitoring of the construction works.
16.0 COMMISSIONING
16.1 Strategy
BR-C will manage all Commissioning and acceptance activities
An integrated Commissioning Schedule will be established and maintained by BR-C
Each Sub-contractor will be responsible for commissioning there scope of work in accordance with
an integrated commissioning schedule
Detailed Commissioning and Acceptance plans will be produced and approved by the client
16.2 Management
A Commissioning Manager will be appointed reporting to the Construction Manager supported by a
team of Commissioning Engineers. The objective of the Commissioning team is to manage the
progressive Commissioning and Acceptance of the works. To plan and co-ordinate the activities of the
sub-contractors, CTC, and client.
The project will endeavour to develop and maintain of a good professional working relationship with the
local authorities, local residents, department of transport and the electricity, gas, telecommunication,
water supply and drainage supply companies. The provision of essential site services will be contracted
from these 3rd parties there by requiring close liaison to agree; the service supply and loading required
for the hospital, the service routings and interfaces.
Le présent document est la propriété exclusive de B&R-C. Il ne peut être diffusé en externe sans l’autorisation écrite du responsable qualité
Project Execution Plan Date : 1 October 2002
Indice de révision : 1
Page 39 of 41
B & R- C J???-PEP-???-0-02
Brown & Root Condor Spa Buttes des Deux Bassins, Contact: Mohamed Taibi
Oeud Romane, Tel: +213 21 94 74 21
El-Achour, Fax: +213 21 94 71 52
Algiers, E-mail: mohamed.taibi @Halliburton.com
Algeria
Architect Contact:
Tel:
Fax:
E-mail:
Le présent document est la propriété exclusive de B&R-C. Il ne peut être diffusé en externe sans l’autorisation écrite du responsable qualité
Project Execution Plan Date : 1 October 2002
Indice de révision : 1
Page 40 of 41
B & R- C J???-PEP-???-0-02
Le présent document est la propriété exclusive de B&R-C. Il ne peut être diffusé en externe sans l’autorisation écrite du responsable qualité
Project Execution Plan Date : 1 October 2002
Indice de révision : 1
Page 41 of 41
B & R- C J???-PEP-???-0-02
Le présent document est la propriété exclusive de B&R-C. Il ne peut être diffusé en externe sans l’autorisation écrite du responsable qualité