GAME PLAN KHRS-710

Aug 6, 2012

 M/U HOWCO 7”, 26# RBP, RIH & set RBP @ (+-) 3000'. ( Note: Top of 7” liner @
1176’) P/T annulus to 1500 PSI w/ 102 PCF Brine. Release setting tool from RBP and
POH.
 R/U Halliburton E-Line Logging Unit, run CAST-CBL Log to 3000'.
1. Nipple down flow nipple and nipple up shooting nipple.
2. Rig up Halliburton E-line.
a) Hold pre-job safety meeting.
b) Pressure test to 2000 psi.
3. Run CAST-CBL LOG on TRACTOR to 3000'.
4. Rig down E-line.
5. Nipple down shooting nipple and nipple up flow line.
 RIH HOWCO 7”, 26# RBP retrieving tool to 2500’, M/U, RIH 2 STDS w/ 9-5/8” 40#
RTTS and storm valve, set RTTS @ (+-) 180’. Release from RTTS and POH, Pressure
test to 1500 psi w/ 102 PCF brine.
 N/D BOPE.
 Perform wellhead work to install 10” PWI and UT inspection.
1. Dig down 6” below landing base and expose surface casing for UT inspection.
2. Install New 10” 3M PWI.
3. Have all required tools ready.
4. Check casing joints are correct weight and we have all sizes required.
 N/U P/Test BOPE.
 RIH 2 STDS latch and release packer, POH L/D RTTS. RIH latch and release RBP @
3000’. F/Check & record losses, POH L/D RBP.
 Close 10” Ball Valve, P/Test against Blind Rams 2300 psi.
 L/D all DP from derrick.
 N/D BOPE, N/U wellhead.
 Bullhead and displace well to inhibited water.

Please read above instruction carefully.


If unsure of any point, please ask. If in doubt= STOP
Work safely – Work as Team – Plan ahead – PJSM & JSA as required.
Thanks for doing a good safe job

Thanks……Pat