Вы находитесь на странице: 1из 12

Received: 3 October 2019 Revised: 11 February 2020 Accepted: 18 March 2020

DOI: 10.1002/suco.201900382

PREVIEW

Advanced FE modeling supported by monitoring toward


management of large civil infrastructures: The case study
of Lezíria Bridge

Helder Sousa1,2,3

1
Department of Research & Innovation,
HS Consulting, Matosinhos, Portugal
Abstract
2
Department Brisa Gest~ao de The knowledge on the effective long-term behavior of large civil infrastruc-
Infraestruturas, BRISA Group, S~ao tures, for example, bridges, is becoming highly desired by owners and conces-
Domingos de Rana, Portugal
sionaires. Based on the case of the Lezíria Bridge in Portugal, one of the most
3
Department of Civil & Environmental
Engineering, University of Surrey,
comprehensive case studies available in the literature, a set of good practices
Guildford, United Kingdom to achieve reliable assessments on the long-term behavior is outlined. Span-
ning the construction phase, the loading test (at the end of construction) and
Correspondence
Helder Sousa, PhD, Department of
the operation phase, the behavior of the bridge is well predicted for several
Research & Innovation, HS Consulting, physical parameters. Nevertheless, the extrapolation of creep and shrinkage
Matosinhos, Portugal. models, the influence of interior and exterior environments, and significant
Email: mail@hfmousousa.com
thickness variations along cross-sections are key issues that deserve special
attention. The role of advanced FE modeling supported by monitoring data is
showed to be one of the most robust approaches for supporting the manage-
ment of large civil infrastructures in this era of digitalization (Industry 4.0).

KEYWORDS
advanced FE modeling, concrete bridges, construction, creep, large civil infrastructures, load
test, management, monitoring, operation, relaxation, shrinkage

1 | INTRODUCTION (SGD 17). In such context, it becomes evident that the


role of advanced FE modeling devoted to large civil infra-
According to Reference,1 current engineering practice for structures will play an important role in a near future,
conservation management is typically based on minimiz- which is already being catalyzed by the current era of dig-
ing costs to achieve and maintain a minimum perfor- italization (Industry 4.0).
mance/quality requirements. On the other hand, the Case studies available in the literature addressing,
Sustainable Development Goals (SDGs) defined in the comprehensively, the long-term performance of large
2030 Agenda for Sustainable Development,2 signed, in civil infrastructures subjected time-dependent effects still
2015, by all countries in the United Nations toward a sus- scarce.3–8 Among these, Lezíria Bridge, crossing the
tainable planet, is promoting Industry, Innovation And Tagus River nearby of Lisbon in Portugal, is perhaps one
Infrastructure (SGD 9) and Partnerships For The Goals of the most comprehensive case studies available in the
literature. The combination of several factors, including
(a) the bridge size, (b) the 13 years of monitoring, (c) the
Discussion on this paper must be submitted within two months of the
print publication. The discussion will then be published in print, along
comprehensive scanning of important characteristics of
with the authors’ closure, if any, approximately nine months after the the bridge, and (d) the FE modeling approach, makes this
print publication. case study holding some merits that, in the author's

Structural Concrete. 2020;1–12. wileyonlinelibrary.com/journal/suco © 2020 fib. International Federation for Structural Concrete 1
2 SOUSA

opinion, are worthwhile to be summarized into a single 2.1 | Main bridge


piece of work by addressing both the scientific commu-
nity and stakeholders involved in the management of With a total length of 970 m, the main bridge is com-
large civil infrastructures. posed by eight spans of 95 m + 127 m + 133 m
In this context, a set of good practices for advanced + 4 × 130 m + 95 m length, which are supported on two
FE modeling devoted to the assessment of the long-term outer piers, TPN and TPS, and seven inner piers, P1 to
performance of large civil infrastructures is outlined, by P7, founded on pilecaps over the riverbed. Each pilecap is
taking as an example the aforementioned case study of supported on eight circular piles of 2.2 m diameter,
Lezíria Bridge. The set of good practices spans, compre- except for piers P1 and P2 (which sets the navigation
hensively, from the construction phase to the operation channel) both supported on 10 piles each. The piles were
phase, including a loading test performed at the end of constructed using permanent metallic casing, to reach
construction. the Miocene layer at approximately 40 m deep, whereas
the pilecaps were built with precast concrete caissons. A
set of four concrete walls of 1.20 m thickness forms each
2 | T H E ST R U C T U R E pier. The width and height of these walls range from 3.90
to 7.50 m and from 13.48 to 16.66 m, respectively. The
The Lezíria Bridge, built-in 2005–2007, is part of the A10 bridge girder is a box girder of variable inertia, with a
highway nearby of the Portuguese capital, Lisbon. With a height ranging from 4 to 8 m and width of 14.0 m, which
total length of 39.9 km, A10 is an outer boundary to the is monolithically connected to the piers except at piers
metropolitan area. The Lezíria Bridge appears here with TPN, P6, P7, and TPS. The construction of the inner
a total length of 11,670 m of prestressed concrete mate- spans was performed by using the segmental
rial, being one of the longest bridges in the world, and construction-balanced cantilever method, whereas the
materialized by three substructures, mainly: (a) the main end-spans were partially built using a formwork placed
bridge; (b) the north approach viaduct; (c) and the south on the soil surface. In a second stage, the edge deck slabs
approach viaduct. of the box girder were built with a specific formwork

F I G U R E 1 Lezíria Bridge and monitoring plan (based on Reference28). (a.1) Elevation of the main bridge. (a.2) Cross sections 11 m
apart from pier axis in (a.1). (a.3) Cross section at mid-spans in (a.1). (b.1) Elevation of the north approach viaduct V2N. (b.2) Cross
section CD-P2P3 in (b.1). (c.1) Elevation of the south approach viaduct V14S. (c.2) Cross section CD-TPS14P1 in (c.1)
SOUSA 3

suspended at each extremity to attain the 29.95 m width. the inner piers. The piers and foundation are similar to
Figures 1a and 2a show the main bridge elevation and its the north approach viaduct, that is, pier–pile elements of
construction stage at the beginning.9 1.5 m of diameter. Between viaducts, one of them is con-
nected to the pier through fixed pot bearings, whereas
the other one is supported by means of sliding guided
2.2 | North approach viaduct bearings. The deck girder, of 29.95 m wide, is composed
of four 1.75 m high precast and U-shaped beams and a
The north approach viaduct consists of three elementary 0.25 m thick slab. The beams are prestressed using pre-
viaducts, V1N, V2N, and V3N, with a length of approxi- tension strands and were made in a factory specifically
mately 500 m each and regular spans of 33 m. The deck built at the construction site. The slab is composed of pre-
girder has a total width of 29.95 m and it is supported by cast planks and a cast-in-place layer. The monolithic con-
four alignments of circular piers-pile with 1.5 m of diam- nection between spans is established through a cast-in-
eter and lengths up to 40 m deep. The construction pro- place diaphragm and continuity reinforcement including
cess adopted was the self-supporting movable scaffolding prestressing employing straight post-tensioning cables,
system supported on the piers. This movable structure which are also monolithically connected to the piers. On
was recurrently mounted and dismounted span by span. the top of the piers, there is an octagonal capital whose
After positioning, works related to reinforcement maximum dimension reaches 1.7 m so that the girders
arrangement, metallic sheaths, and anchorage systems can be positioned properly. The piles cross alluviums
installation were performed. Then, the span construction with a variable constitution, and the maximum deepness
proceeded with the concrete pouring. Finally, the pre- reached by each pile varies between 35 and 60 m. Fig-
stressing cables were tensioned and the movable scaffold- ures 1c and 2c show the elevation of the V14S viaduct
ing was moved to the next span. For the scope of this and a detail on the deck girder at the stage of positioning
work, viaduct V2N is focused as presented in Figure 1b, the precast beams, respectively.11
whereas Figure 2b details the construction stage.10

3 | MODELING
2.3 | South approach viaduct
The modus operandi in the construction of the FE
The south approach viaduct, built with precast beams, is models has been based on a detailed and rigorous scan-
composed by 22 elementary viaducts, V1S to V22S, with ning of all available and relevant information from the
total lengths ranging from 250 to 530 m and with a com- Lezíria Bridge, mainly properties related to (a) concrete,
mon span length of 36 m. Each of the 22 viaducts is com- (b) prestressing cables, (c) soil, (d) loading, and
posed by a continuous deck monolithically connected to (e) geometry. Further to this data collection, the respec-
tive average values have been quantified and used at the
structural level.

3.1 | Concrete

3.1.1 | Compressive strength

The quantification of the mechanical properties of concrete


was based on compressive tests on 150 mm cubes per-
formed during the construction12 and creep and shrinkage
measurements taken from 150 mm × 150 mm × 550 mm
concrete prisms.7,13–15
The European Code EC216 was used with some of the
model parameters being updated based on the aforemen-
tioned measurements. Each structural component, that
is, pile, pier, span, and segment, was exhaustively
scrutinized.
F I G U R E 2 Construction of the Lezíria Bridge. (a) Main The compressive strength at a given age, fcm(t), is
bridge. (b) North approach viaduct. (c) South approach viaduct given by Equation (1), where t represents the concrete
4 SOUSA

age in days, s is a cement hardening coefficient, and fcm


is the mean value of the concrete compressive strength,
at the age of 28 days. Because concrete cubes were used,
it took 82% of the observed values to obtain the
corresponding cylinder compressive strengths, fcm, cyl, as
recommended by EC2. Regarding the parameter, s, in
Equation (1), this was determined by a curve fitting pro-
cedure that minimized the mean square error between
the test results at different ages and values given by
Equation (1). As an example, Figure 3 shows the fitting
results obtained for three main structural components for
the north approach viaduct V2N (i.e., piles, piers, and
deck girder), whereas Table 1 summarizes the average
values obtained for the substructures analyzed, that is,
the north approach viaduct V2N, the main bridge and
the south approach viaduct V14S.
h  pffiffiffiffiffiffiffiffiffiffiffiffii
fcm ðt Þ = βcc ðt Þ  fcmð28Þ , βcc ðt Þ = exp s  1 − 28t − 1 ð1Þ

3.1.2 | Modulus of elasticity

The tangent modulus of elasticity, Ec, is calculated based


on the compressive strength, by means of Equation (2),
where fcm, cyl represents the mean value of the concrete
cylinder strength at the age of 28 days. The time-
dependent variability of the concrete elasticity modulus
correlates to the time variation of the compressive
strength (Equation (1)). Taking the value previously
obtained for s, the evolution of the modulus of elasticity
is straightforwardly obtained (Equation (3)).

 0:3
E c = 1:05  22000  f cm,cyl =10 ðMPaÞ ð2Þ

h  pffiffiffiffiffiffiffiffiffiffiffiffii0:5
E c ðt Þ = βE ðt Þ  E c , βE ðt Þ = exp 0:5s  1 − 28t − 1 ð3Þ

3.1.3 | Shrinkage

The total shrinkage strain, ɛcs, is set in two parts


(Equation (4)): (a) the drying shrinkage strain, ɛcd, and
(b) the autogenous shrinkage strain, ɛca. Both mathemati-
cal models for these two parts, Equations (5) and (6),
respectively, are expressed by a multiplicative model with
F I G U R E 3 Compressive strength evolution (based on
a nominal coefficient, ɛc, ∞ and a time factor, βs(t), where Reference13). (a) Pile V2N-P2. (b) Pier V2N-P2. (c) Deck girder
t is a generic point in time and ts the time when drying V2N-P2P3
SOUSA 5

TABLE 1 Average values of the mechanical properties of concrete13,15,18

North approach viaduct V2N Main bridge South approach viaduct V14S

Piles Piers Deck Piles Piers Deck Piles Piers Deck


fcm, 28d (MPa) 48.9 43.7 49.3 50.4 56.6 55.5 60.5 46.7 68.0
s 0.20 0.18 0.20 0.23 0.25 0.26 0.35 0.25 0.18

begins (in days). Additionally, kcs, 0 and kcs, t parameters


are added to Equation (5) to scale and shape the drying
shrinkage model to measurements collected from the
aforementioned concrete prisms. Similar to the quantifi-
cation of parameter s that explains the evolution of the
compressive strength with time (Section 3.1.1), the addi-
tional parameters, that is, kcs, 0 and kcs, t, were deter-
mined by a curve-fitting procedure that minimizes the
mean square error between both measurements and
model values at different ages. The autogenous shrinkage
is not considered in the fitting problem taking into
account that it mainly occurs during the early days after
casting16 and the focus here is on the long-term behavior
(i.e., years). Hence, its effect is initially removed to the
measurements, by subtracting a quantity expressed by
Equation (6), and after the fitting problem is solved its
contribution is restored.
In the particular case of the main bridge, the concrete
prisms are positioned inside and outside of the box girder
due to the different environmental conditions observed.
Although an accurate quantification of their influence
stills a challenging task,17 their effects were considered,
for simplicity, proportional to the cross-section perimeter
exposed to each environment.13–15,18 The total shrinkage,
considered for the curve-fitting procedure, was calculated
based on 30% and 70% of the prisms placed inside and
outside the box girder, respectively, and considering aver-
age values for temperature and relative humidity.19

εcs ðt Þ = εcd ðt Þ + εca ðt Þ ð4Þ

εcd ðt Þ = k cs,0  εcd,∞  ½βds ðt, t s Þkcs,t ð5Þ F I G U R E 4 Scale-up from specimen level to structural level
(based on Reference7,15). (a) Shrinkage deformations—prisms.
εca ðt Þ = εca,∞  βas ðt Þ ð6Þ (b) Shrinkage deformations—structural components

The notional size of the structural elements of the between the bottom slab, web and top slab of the box
bridge goes up to 1,575 mm, which is significantly girder was accordingly taken into account.3,4,20,21 For
higher than the respective one for the shrinkage prisms illustration, Figure 4 shows the results for the main
(150 mm). Hence, the shrinkage for the concrete ele- bridge. More specifically, Figure 4a shows the results
ments (structural level) was set based on their effective obtained from the aforementioned curve-fitting proce-
notional size and the fitted model for the concrete dure for the measurements collected from the concrete
prisms (specimen level, Equation (4)). For the specific prism, whereas Figure 4b shows the extrapolation (from
case of the main bridge, the thickness differences the previous) to the structural components based on the
6 SOUSA

associated value for the notional size parameter. A simi- are conducted in flexible metal ducts, the relaxation class
lar approach has been taken for the north and south 2 is adopted, with a wobble coefficient, K, fixed to 0.05 and
approach viaducts. a coefficient of friction, μ, set to 0.19, according to the
Model Code 2010 recommendations.1 Regarding the pre-
stress loss due to relaxation, Δσ pr, the EC2 model has been
3.1.4 | Creep used and implemented numerically accordingly to
Reference,22 considering low relaxation and that the elon-
The creep deformations of concrete, ɛcc(t, t0), at a generic gation of the tendon varies gradually over time as per
time t for a constant applied compressive stress at age t0 is Equations (9) and (10).
given by Equation (7), where φ (t, t0) is the creep coeffi-
cient and ɛc(t0) is the instantaneous deformation due to the σ p,− i + 1 = σ p,i
+
+ E p  Δεi −Δσ pr,i ð9Þ
applied stress. The creep coefficient is given by Equa-
tion (8), where φ0 is the notional creep coefficient, and  
t e + Δt i 0:75ð1 − μ’Þ
βc(t, t0) is a time function to describe the development of Δσ pr,i = A  ρ1000  eBμ’ 
creep after loading. Similar to shrinkage, additional param- Xi − 1  1000 Xi − 1
eters, kcc, 0 and kcc, t, were added in Equation (8) so that  j=1
Δσ pr,j + σ p,i  10 − 5 −
+
j=1
Δσ pr,j ð10Þ
the model for the evolution of creep deformations could be
adjusted to measurements collected from concrete prisms
by a curve-fitting procedure that minimizes the mean 3.3 | Soil
square error between both at different ages.6 Also, the dif-
ferent environmental conditions, for the case of the main The interaction pile-soil is modeled with elastic springs
bridge, as well as the scale effect from specimen level to based on the Winkler model, as expressed by Equa-
structural level was accordingly taken into account. tion (11). The spring stiffness is taken proportional to the
subgrade reaction module, ks, and the influence area of
εcc ðt,t 0 Þ = φðt, t0 Þ  εc ðt 0 Þ ð7Þ the spring, Ainf. The former is quantified from geological
and geotechnics tests performed by the constructor,23
φðt, t 0 Þ = k cc,0  φ0  ½βc ðt, t 0 Þkcc,t ð8Þ whereas the latter is defined by the pile diameter, ϕ, mul-
tiplied by an influence length, L. Table 2 summarizes the
range of values with interest, which was used to compute
the stiffness of the springs.

3.2 | Prestressing cables k v = k s  Ainf , Ainf = ϕ  L ð11Þ

A comprehensive scanning was carried out to characterize


the modulus of elasticity of the prestressing steel, Ep, based
on the manufacturer specifications.12 Average values are 3.4 | Loading
considered associated with the construction of a new span
(approach viaducts) and a new segment (main bridge). Concerning the loading conditions, the effective loads
Overall, an average value of 196.6 GPa and a coefficient of have been quantified according to information available
variation of 2.3% is found, which is in agreement with the from the constructor.12 Hence, the following were consid-
EC2 limits.16 Taking the fact that the prestressing cables ered (Table 3): (a) self-weight of the reinforced concrete,

TABLE 2 Average values of the properties of soil23

Soil description Clay deposits Sludge Muddy fine to medium sand Medium sand Clay silt
Deep (m) 0–2 2–6 4–6 6–8 >6
3
ks (MN/m ) 4–8 1–2 7–30 8–20 90–120

TABLE 3 Average values of loading conditions12

Parameter Self-weight γ c Movable scaffolding, Fms Prestressing, fPE Imposed-loads, pDL Fully loaded truck, Ft
3
Value 25.0 KN/m 570–1,127 kN 0.71fpym 93.7 kN/m 315.9 KN
SOUSA 7

γc; (b) self-weight of the movable scaffolding systems tools.7 As far as the external prestressing cables are con-
based on the equipment specifications, Fms12; (c) forces cerned, truss elements are used and connected to the
applied to the prestressing cables based on the elongation girder beam elements through dummy elements with
measurements, fPE12; (d) imposed loads concerning the high inertia to guarantee the same displacement field.
bituminous layer, border beams, walkways, and safety The movable scaffolding systems used during construc-
barriers, pdl; and (e) fully loaded truck used in the load tion are also modeled with beam elements, which are
test, Ft. linked to the piers of the north approach viaduct, and the
box girder of the main bridge. Figure 5 shows the FE
models implemented for the viaducts, mainly for the north
3.5 | Geometry approach viaduct V2N and the main bridge, by depicting
beam elements, truss elements, reinforcements, spring
All concrete components are represented by their axis elements and supports.
with a structural discretization of approximately 1–2 m
long (depending on the structural component type, that
is, piles, piers, or girder). These were set directly from the 3.6 | Structural analysis
final project CAD drawings of the bridge,9,10,11 supported
by CAD tools specifically developed and used for the Further to the modeling of the input parameters
scanning process.7 Beam elements of three nodes are (i.e., concrete, steel, soil, loading, and geometry), the FE
used to model the concrete elements, with a special case structural analysis, performed by using the general pur-
for the main bridge where two overlapped alignments of pose FE code DIANA,24 was done based on the phased
beam elements are considered, with the same displace- concept to simulate the structural performance over time.
ment field, to take into account the phased construction For each stage new elements were added/removed and
of the bridge girder and the edge deck slabs. Three layers the support configuration updated accordingly. During
of ordinary reinforcement are modeled along faces and each stage, the mechanical system, material properties,
axis of the concrete components, whereas the embedded boundary and loading conditions remain unchanged and
prestressing cables of the bridge girder were precisely only subjected to time-dependent effects.
modeled by importing coordinates directly from the final Taking into account the restraining effects between
project drawings,9 also supported by dedicated CAD concrete and steel, the ordinary and prestressed

F I G U R E 5 FE models of the Lezíria Bridge (DIANA 10.3). (a) Main bridge (based on Reference15). (b) North approach viaduct V2N
(based on Reference 13)
8 SOUSA

reinforcements are modeled in a way that their deforma-


tion is computed from the displacement field of the
mother element in which they are embedded (i.e., the
3-node beam elements). Consequently, the restrained
deformations are automatically taken into account to
guarantee both the compatibility of deformations and
static equilibrium.
Finally, and to guarantee that the numerical results
may be directly compared to the collected data, the real
construction chronology is accurately considered
according to information gathered from the construc-
tor.12 With this, the predictions obtained for vertical dis-
placements, bearing movements, rotations and strains
have been computed and directly assessed against moni-
toring data collected on the bridge on the time domain
(i.e., time-series graphs).

4 | R ESULTS A ND ASSESSMENT

4.1 | Loading test

The FE models were initially tuned through an elastic


analysis focusing on the loading test performed at the
end of the bridge construction. More precisely, the FE
models' stiffness was verified by adjusting the parameters
with higher scatter and with influence in the structural
behavior, mainly: (a) soil stiffness, (b) metallic casing of
piles, (c) axial deformability of piles, and (d) dimensions
of the pier–deck intersection zone. Overall, a good corre-
lation is observed between the FE results and measure-
ments either on pattern or amplitude for vertical
displacements, rotations, and strains. Figure 6 shows,
respectively, a representative sample of all database gath-
ered and, based on this, it can be stated that the FEs' dis-
cretization and simulation of boundary conditions are
adequate to simulate the effective structural behavior of
the bridge under static loads.

4.2 | Long-term performance

4.2.1 | Construction phase

Regarding the main bridge, typically, the segmental con-


struction took 7 days on average, with an identical phased
procedure as for the north approach viaduct. Figure 7a
shows the strains in the top deck-slab for section P7. Nine
segments of approximately 6 m long were built, with the F I G U R E 6 Loading test assessment—FE results versus
last eight identified by the pattern of the results. Later, the measurement (based on Reference15). (a) Mid-span displacements
prestressing applied at the mid-span P6P7, the pushing (Figure 1a). (b) Deck girder rotations (Figure 1a). (c) Mid-span
curvatures (Figure 1a)
forces applied in the last closing segment of the bridge,
SOUSA 9

and the external prestressing applied in all bridge length is


identified with a clear agreement between both FE predic-
tions and measurements on a final deformation of εcffi
−500 με in the top deck-slab.
The girder construction of the north approach viaduct
was based on the following phases: (a) positioning of the
movable scaffolding—phase 0, (b) reinforcement place-
ment and concrete pouring—phase 1, (c) prestressing—
phase 2, (d) moving forward the movable scaffolding—phase
3. Figure 7b shows the measurements obtained in
section P2P3 of V2N, where the mentioned phases can
be identified. The most relevant change is observed
when the prestressing cables of span P2P3 were ten-
sioned (phase 2), leading to a strain variation of εcffi
−300 με, in the bottom face of the girder (strain gauge
CD-1I, Figure 1.b2). Shortly after, the strain decreased
due to the release of the movable scaffolding (phase 3)
revealing that the span weight was partly supported by
the movable scaffolding even after the prestressing. It is
also visible minor offsets at August 11, 2006 and August
13, 2006, which reveals the influence of the construction
of the following span P3P4.
Finally, Figure 7c shows the strains for the mid-span
section V14S-PTS14P1 of the south approach viaduct
V14S. Similar to the main bridge and the north approach
viaduct, the results presented in this figure includes the
FE results in which the concrete properties were based
on monitored parameters. Again, the FE results closely
agrees with the measurements with the main events asso-
ciated with the construction clearly detected by both.

4.2.2 | Operational phase

Regarding the bridge behavior over time, that is, the


operational phase, Figure 8 shows both FE predictions
and monitoring data for four sections of the main bridge
and related to vertical displacements, rotations, concrete
deformations, and bearing displacements, respectively, in
some critical sections (Figure 1). The FE predictions (up to
the year 2033) are overlapped with the measurements
collected until present (i.e., 2020). Overall, both the mea-
surement magnitudes and trends seem to be well cap-
tured by using the proposed methodology presented in
Section 3. The vertical displacement for one of the spans
with highest displacements show god agreement with the
FIGURE 7 Construction assessment—FE results versus monitoring data, despite that for this further investigation
monitoring data. (a) Concrete deformations (section CD-P7, needs to be done due to some interruptions in the data
Figure 1A, based on Reference15). (b) Concrete deformations acquisition process (Figure 8a). Despite the good agree-
(section CD-P2P3, Figure 1b, based on Reference13). (c) Concrete ment generally observed, the scale-up from specimen
deformations (section CD-TPS14P1, Figure 1c, based on level to structural level plays a crucial role in the FE pre-
Reference18) dictions. In other words, the quantification of creep and
10 SOUSA

F I G U R E 8 Long-term assessment—FE results versus monitoring data. (a) Vertical displacement (section DV-P7TPS, Figure 1a).
(b) Rotation (section RO-P1, Figure 1a). (c) Concrete deformations (section CD-TPNP1, Figure 1a). (d) Bearing movement (section BD-TPN,
Figure 1a)

shrinkage effects on the structural elements, based on movement on section PTN3 (Figure 8d). This is mainly
measurements collected on concrete specimens, is sub- due to the temperature variation. Laboratory tests rev-
jected to extrapolation errors. The higher the difference ealed that the thermal dilation coefficient of the
on the notional size (i.e., in the structural components employed concrete is approximately 7.9 × 10−6 C−1,25
and concrete prisms), the higher might be the committed which is 21% lower than the specified in Eurocode 1—
error. For instance, the rotation above pier P1 (Figure 8b) EC1.26 This value is consistent with results obtained by
seems to be underestimated by the FE model, mainly in the other authors.17,27
trend over time, which indeed might be explained by the
high thickness of the structural components in this zone of
the deck girder. Even though the long-term behavior is 5 | CONCLUSIONS
mostly constrained by time-dependent phenomena, that
is, creep and shrinkage of concrete, the environmental A set of good practices is highlighted, mainly:
conditions have also an important contribution, as it can (a) rigorous scanning of the structure geometry; (b) in
be highly noticed by the seasonal variation of the mea- situ properties of the structural materials and foundation
surements for the rotation (Figure 8b) and bearing soil; (c) effective loading conditions; and (d) real
SOUSA 11

construction sequence. Based on the FE modeling for the ORCID


three substructures of Lezíria Bridge, the following con- Helder Sousa https://orcid.org/0000-0001-8310-0119
clusions could be drawn and extended to other civil infra-
structures in similar conditions, mainly: RE FER EN CES
1. Fédération Internationale du Béton (fib). Model code for con-
• Good correlation is observed between both FE predic- crete structures 2010. Switzerland: Lausanne, 2010.
tions and monitoring data during the loading test. 2. United Nations. About the sustainable development goals.
Generally, differences are less than 7% regarding the 2015. Retrieved Feb 11, 2020 from https://www.un.org/
sustainabledevelopment/sustainable-development-goals/.
maximum vertical displacements of midspan sections.
3. Bažant Z k P, Yu Q, Li G-H. Excessive long-time deflections of
Also, good agreement has been observed for rotations Prestressed box girders. II: Numerical analysis and lessons
and strains in several monitored sections. This allows learned. J Struct Eng. 2012a;138(6):687–696. https://doi.org/10.
assuring, in a first instance, that the FE models show 1061/(ASCE)ST.1943-541X.0000375.
adequate stiffness under static loading conditions. 4. Bažant ZP, Yu Q, Li G-H. Excessive long-time deflections of
• The FE models show high conformity with the moni- Prestressed box girders. I: Record-span bridge in Palau and
toring data during the construction period. The con- other paradigms. J Struct Eng. 2012b;138(6):676–686. https://
struction phases and critical events are clearly doi.org/10.1061/(ASCE)ST.1943-541X.0000487.
5. Robertson IN. Prediction of vertical deflections for a long-span
identified with very good agreement between both FE
prestressed concrete bridge structure. Eng Struct. 2005;27(12):
predictions and monitoring data. Taking into account 1820–1827. https://doi.org/10.1016/j.engstruct.2005.05.013.
the results obtained for the loading test, these results 6. Santos LO. Observaç~ao e análise do comportamento diferido de
increase the level of confidence in their further exploi- pontes de bet~ao [observation and analysis of the deferred behaviour
tation, that is, over the operational phase. Also, the of concrete bridges] (PhD). Portugal, Lisbon, Portugal: Instituto
stress limit of 0.45 × fc from EC2 has not been Superior Técnico da Universidade Técnica de Lisboa, 2002.
exceeded. 7. Sousa H. Data-based engineering techniques for the manage-
ment of concrete bridges (PhD thesis). Porto, Portugal: Univer-
• Regarding the operational lifetime period, the mea-
sity of Porto; 2012.
surements trends are satisfactorily predicted by the FE
8. Takács PF. Deformations in concrete cantilever bridges: Obser-
models, where creep and shrinkage measurements col- vations and theoretical modelling (PhD thesis). The Norwegian
lected from concrete prisms reveals to be crucial. University of Science and Technology Trondheim; 2002.
• The relaxation of the prestressing steel has a minor 9. Coba-PC&A-Civilser-Arcadis. Construç~ao da Travessia do Tejo
effect for the Lezíria Bridge, with an influence lower no Carregado Sublanço A1/Benavente, da A10 Auto-Estrada
than 2.0% (up to the end of the operational phase). The Bucelas/ Carregado/IC3, Empreitada de Concepç~ao, Projecto
low relaxation class of the steel and the moderate e Construç~ao da Travessia do Tejo no Carregado, Volume II
– Ponte sobre o rio Tejo. Portugal: Lisbon, 2005a in
stress level applied (approximately 0.7×fpuk) justify
Portuguese.
this fact. 10. COBA-PC&A-CIVILSER-ARCADIS. Construç~ao da Travessia do
• Some aspects still careful further investigation, mainly: Tejo no Carregado Sublanço A1/Benavente, da A10 Auto-
(a) better quantification of creep and shrinkage proper- Estrada Bucelas/Carregado/IC3, vol. I. “Viaduto Norte”.
ties for the structural components; (b) the effective Empreitada de Concepç~ao. Lisbon, Portugal: Projecto e Con-
influence of the relative importance of interior and struç~ao da Travessia do Tejo no Carregado, 2005c in Portuguese.
exterior environments for box-girder structures; and 11. COBA-PC&A-CIVILSER-ARCADIS. Construç~ao da Travessia do
(c) the effect on the creep and shrinkage kinetics when Tejo no Carregado Sublanço A1/Benavente, da A10 Auto-
Estrada Bucelas/Carregado/IC3, vol. III. “Viaduto Sul”.
relevant differences on the thickness along the cross-
Empreitada de Concepç~ao. Lisbon, Portugal: Projecto e Con-
section (e.g., between the bottom slab and top slab of a struç~ao da Travessia do Tejo no Carregado, 2005d in Portuguese.
box-girder section). 12. TACE. Construç~ao da Travessia do Tejo no Carregado Sublanço
• The current era of digitalization (Industry 4.0), by A1/ Benavente, da A10 Auto-Estrada Buce-las/Carregado/IC3:
means of the increased availability of monitoring data, Plano de Qualidade. Portugal: Lisbon, 2007 in Portuguese.
puts advanced FE modeling with high potential to sup- 13. Sousa H, Bento J, Figueiras J. Construction assessment and
port management protocols throughout the opera- long-term prediction of prestressed concrete bridges based on
monitoring data. Eng Struct. 2013a;52:26–37. https://doi.org/
tional phase of civil infrastructures in general. The
10.1016/j.engstruct.2013.02.003.
case study of the Lezíria Bridge shows that with a care-
14. Sousa H, Sousa C, Neves A, Bento J, Figueiras J. Long-term
ful and detailed scanning of quantities related to the monitoring and assessment of a precast continuous viaduct.
input parameters, that is, concrete, prestressing steel, Struct Infrastruct Eng. 2013b;9(8):777–793. https://doi.org/10.
soil, loading, and geometry, reliable predictions are 1080/15732479.2011.614260.
possible which can be compared to monitoring data 15. Sousa H, Bento J, Figueiras J. Assessment and Management of
without the need of any type of FE model updating. Concrete Bridges Supported by monitoring data-based finite-
12 SOUSA

element modeling. J Bridg Eng. 2014;19(6):05014002. https:// 26. Standardization European Committee. Eurocode 1 – Actions
doi.org/10.1061/(ASCE)BE.1943-5592.0000604. on structures. Part 1–5: General actions; thermal actions. Brus-
16. European Committee for Standardization. Design of concrete sels, Belgium: CEN, 2009.
structures—Part 1–1: General rules and rules for buildings, 27. Kada H, Lachemi M, Petrov N, Bonneau O, Aïtcin P-C. Deter-
Eurocode 2: EN January 1, 1992. Brussels, Belgium: CEN, 2004. mination of the coefficient of thermal expansion of high perfor-
17. Santos TO. Concrete shrinkage in bridges: Observation and mance concrete from initial setting. Mater Struct. 2002;35(1):
analysis (PhD thesis). Lisbon, Portugal: LNEC; (2007). 35–41. https://doi.org/10.1007/bf02482088.
18. Sousa C, Sousa H, Neves AS, Figueiras J. Numerical evaluation 28. Sousa H, Félix C, Bento J, Figueiras J. Design and implementa-
of the long-term behavior of precast continuous bridge decks. tion of a monitoring system applied to a long-span prestressed
J Bridg Eng. 2012;17(1):89–96. https://doi.org/10.1061/(ASCE) concrete bridge. Struct Concr. 2011;12(2):82–93. https://doi.
BE.1943-5592.0000233. org/10.1002/suco.201000014.
19. Barr BIG, Vitek JL, Beygi MA. Seasonal shrinkage variation in
bridge segments. Mater Struct. 1997;30(2):106–111. https://doi. AUTHOR BIOGRAPHY
org/10.1007/bf02486311.
20. Kristek V, Bazant ZP, Zich M, Kohoutkova A. Box girder
deflections: Why is the initial trend deceptive? ACI Concr Int. Helder Sousa, PhD
2006;28(1):55–63. Department of Research & Innova-
21. Malm R, Sundquist H. Time-dependent analyses of segmentally tion, HS Consulting
constructed balanced cantilever bridges. Eng Struct. 2010;32(4): Matosinhos, Portugal
1038–1045. https://doi.org/10.1016/j.engstruct.2009.12.030. mail@hfmousousa.com
22. Sousa C, Neves A. DIANA user-supplied subroutine for concrete
creep modelling. Porto, Portugal: University of Porto, 2009.
23. Coba-PC&A-Civilser-Arcadis. Construç~ao da Travessia do Tejo
no Carregado Sublanço A1/Benavente, da A10 Auto-Estrada
Bucelas/Carregado/IC3, Empreitada de Concepç~ao, Projecto e
Construç~ao da Travessia do Tejo no Carregado, Vol. IV, Estudo
Geológico e Geotécnico. Portugal: Lisbon, 2005b in Portuguese.
24. DIANA FEA bv. DIANA – Finite element analysis release How to cite this article: Sousa H. Advanced FE
notes release 10.3. TNO DIANA, BV. Delftechpark, Delft: The
modeling supported by monitoring toward
Netherlands, 2019.
management of large civil infrastructures: The case
25. Sousa H, Figueiras J. Experimental evaluation of thermal com-
pensation for vibrating wire strain gauges placed in concrete study of Lezíria Bridge. Structural Concrete. 2020;
prisms. Internal report. LABEST, Faculty of Engineering, Uni- 1–12. https://doi.org/10.1002/suco.201900382
versity of Porto, Portugal, 2009 in Portuguese.

Вам также может понравиться