Group Assignment
Case Study
SMART Construction is a reliable company in building construction projects in Sydney. It has
been active in construction for the last 20 years. The main aim of the company is to provide
high quality and luxurious construction buildings that fulfil the needs of the customers.
Recently the company signed a contract for constructing a building for Asia Pacific
International College (APIC), Sydney.
CONTRACT
PARTIES Customer/Client: APIC Company: SMART Construction
SMART Construction CEO: Mr Bob Smithes
The building should be completed in 268 days otherwise the contractor will be panelised
AU$200 for each day late. Alternatively, will be rewarded with AU$150 for each day before the
dead line day.
BUILDING SPECIFICATIONS
The building area is 700 square meters with basement, ground level and first level. This
building is mainly designed for administration, dean office, and staff offices. The basement
includes the car parks, storage rooms and building facilities room, the ground level includes
the administration office, reception room, and three meeting rooms. The first level includes the
dean room and the staff rooms.
6- Establish and calculate detailed cost estimation for each main deliverable and activity
in the WBS Hint: Use the total cost that you calculated from table 1, and then use
cost percentages in table 2.
7- For the main deliverable Walls and Roof, develop schedule resource plan
considering that only three labourers are available each day staring from the first day
the first activity (C10) under this main deliverable until the end of the last activity
(C40) under this main deliverable finishes.