Вы находитесь на странице: 1из 7

See discussions, stats, and author profiles for this publication at: https://www.researchgate.

net/publication/325977371

Protection coordination assessment and improvement of electrical network of


an industrial complex in connection to power grid: An experience report

Conference Paper · May 2018


DOI: 10.1109/ICEEE2.2018.8391343

CITATIONS READS

0 627

3 authors:

Rahman Dashti Salahedin Hassani


Persian Gulf University 1 PUBLICATION   0 CITATIONS   
42 PUBLICATIONS   200 CITATIONS   
SEE PROFILE
SEE PROFILE

Hamid Reza Shaker


University of Southern Denmark
109 PUBLICATIONS   631 CITATIONS   

SEE PROFILE

Some of the authors of this publication are also working on these related projects:

Analysis of Neutral Ground Resistance Behavior of Fourth Refinery Gas Power Plant in Real Short Circuit Faults View project

fault section estimation in power distribution network View project

All content following this page was uploaded by Rahman Dashti on 30 June 2018.

The user has requested enhancement of the downloaded file.


Protection Coordination Assessment and Improvement of Electrical Network of an
Industrial Complex in Connection to Power Grid: An Experience Report

Rahman Dashti Salahedin Hassani


Persian Gulf University, Electrical Engineering Department,
Electrical Engineering Department, Faculty of Third South Pars Refinery,
Engineering, Asalouyeh, I.R.Iran
Bushehr 7516913817, I.R.Iran Email : hassanisala@gmail.com
r.dashti@pgu.ac.ir
Hamid Reza Shaker
Center for Energy Informatics
The Maersk Mc Kinney Moller Institute
University of Southern Denmark
Odense, Denmark
hrsh@mmmi.sdu.dk

Abstract— Protection of electrical network of an industrial South Pars’s third refinery in connection to the power grid.
complex is a challenging task in particular in connection to the For this purpose, first the third refinery’s internal network
power grid. This paper is focused on this challenging task and will be briefly introduced, and this network in connection to
reports on the experience of protection coordination the power grid will be simulated using ETAP software.
assessment and improvement of electrical network of South Then, load flow study, to determine the main electrical
Pars Gas Complex (SPGC) and in particular the third south parameters such as current and power will be carried out.
Pars refinery. Today South Pars is the economic hub and heart Next the short circuit study by creating a symmetrical three-
of the gas and petrochemical industry in Iran. The continuous phase fault in both configurations, island and connected to
and stable production of gas from the South Pars Gas Field is
the network, will be done. Finally, protection coordination of
very important. In order to supply power to the third south
Pars refinery four gas turbine generators (GTG) each with a
major equipment and the 33kV switchgear will be assessed.
capacity of 41.1MW and two emergency diesel generators Protection implementation of electrical network includes a
(EDG) each with a capacity of 4.5 MW have been installed. In setting and coordination between the primary and backup
addition to this, one external line to connect the plant to the relays that should have acceptable performance and time
power grid is considered. Now the third refinery as an island margins. According to third refinery’s documents time
electrical network operates independently from the power grid margins between the main and back up relays operation at
and provides energy needs of the refinery process and utility least should be 250ms. The protective relay settings based on
units. By connecting the refinery’s electrical network to the the Refinery document and relay setting report have been set
power grid short-circuit current value increases. If an error and protection coordination will be evaluated on this basis. If
occurs on the internal network when the refinery is connected modifications are required, the necessary recommendations
to the power grid, the fault current will be higher compared to would be made.
when the Refinery works in island mode. This is because
current is also injected from the power grid to the faulty point. II. INTRODUCTION TO ELECTRICAL NETWORK OF THE
In this paper, the third south Pars refinery protection THIRD REFINARY
coordination in connection to the power grid will be assessed.
The ETAP software will be used for the simulation. While the A. Production and Distribution of Electric Energy
paper reports the practical experience in relation to this
11 kV voltage is generated by four gas turbine generator
particular case study, the approach and experience helps to
face the practical challenges in similar projects.
sets and increased to 33 kV using four transformer units to
supply 33kV switchgear as shown in “Fig. 1”. The 33 kV
Keywords-protection coordination; power grid; third south switchgear has two parts, A and B connecting to each other
Pars refinery; gas turbine generator; by a normally closed bus-tie, thus all generators are parallel
and working in synchronous together. In addition to all
power substations, the 33 KV Switchgear feeds ten 11KV
I. INTRODUCTION
electro motors using step-down 33 to 11 KV transformers.
In a protection system that its relay coordination has been As well as two ground transformers with zigzag connections
optimized, the minimum electrical equipment trip and clean are installed in both sides of the switchgear. Voltage
parts of the system are still able to carry out their duty, in distribution levels in the Refinery network are 33, 11, 6 and
case of a fault [1-10]. The main objective here is to assess 4.0 kV. In order to distribute electrical energy for different
and if necessary improve the protection coordination of the
Figure 1. 33KV swicthgear and gas turbine generator incomers
processing units thirteen substations have been installed three generators A, B and C are running and generator D is
at various load centers of the refinery. Required power is in standby mode, also grid’s incomer circuit breaker is
transmitted to all substations through two 33KV opened. The results of load flow study in island mode are
underground cables and turns to 6KV using two 33 / 6KV shown in TABLE II and “Fig. 2,” and “Fig. 3,”.
power transformers. Also there are some low voltage As shown, near to 48MW of active power is produced by
switchgear and MCCs, which supplies low voltage loads three gas turbine generators in island mode. Drawn current
such as three-phase 400-volt motors, lighting systems, from each generator is about 330A at 33KV or 963A at
heaters, UPS, sockets, etc. At 6 kV and 0.4 kV voltage levels 11KV voltage level. The power factor of the generators is
in addition to the normal switchgears, there are emergency 0.83 and the apparent power of each generator is
switchgears to supply critical loads. All installed switchgears approximately 18.736MVA.
are made by the ABB Company.
B. Load flow results in conetion to the power grid
B. Load Summary At this stage, for the refinery’s network when connected
Load summary of the South Pars’s third refinery is to the power grid, current and power of various equipments,
shown in TABLE I. The entire installed active power is including generators and grid incomers are measured. In this
about 75MW and operational load is about 50MW. Majority state, two generators B and C are running and the other two
of electrical loads are electro motors which are used as prime A and D are in standby mode. Also the Grid’s incomer
movers for mechanical equipment such as pumps, refrigerant circuit breaker is closed. The results of the load flow study in
compressors and cooling fans. The other popular electrical this state are shown in TABLE III and “Fig. 4,” and “Fig.
loads are heaters, lighting systems and HVAC accessories. 5,”.
TABLE I. LOAD SUMMARY IV. SHORT CIRCUIT ANALYSIS
P (KW) Q (KVAR) S (KVA) In this section short circuit study of the refinery’s
75.18 44.515 87.373 network in both island and in connection with the power grid
states,will be carried out and short-circuit current values will
III. LOAD FLOW ANALYSIS be calculated in different parts of the network. A
A load flow study should be performed during the plan symmetrical three-phase short-circuit fault will be applied at
designing stages of a power system and when evaluating the following switchgears and short circuit current value will
changes to an existing system. Load flow study determines be calculated.
the normal and emergency load currents at each load center  33 kV switchgear with tag number 1S11
and through each circuit branch. The load current data are  Normal 6 KV switchgear with tag number1S31A
used to establish continuous-current ratings for conductors,  Emergency 6 kV switchgear with tag number
equipment, and protective devices. Such data are valuable 1ES31A
when setting protective devices to protect both the equipment
and the installed conductors. TABLE II. LOAD FLOW RESAULS IN ISLAND CONFIGURATION
GTG-A GTG-C GTG-B
A. Island configuration load flow results I(A)
329.7 329.6 329.6
At this stage, for the refinery’s network with island 15974 15973 15974 P(KW)
configurations, current and power of various equipment, 9791 9789 9790 Q(KVAR)
including generators are measured. In this configuration, 18736 18734 18736 S(KVA)
Figure 4. Load flow resaults for grid incomer GTG-A & GTG-C
when the refinary is connected to the power grid

V. PROTECTION COORDINATION
Figure 2. Load flow results for GTG-A & GTG-C in island mode
An electrical power system is designed so that if a short-
 Normal 400V switchgear with tag number 1S41A circuit occurs, a protective device (such as a fuse or circuit
 Emergency 400V switchgear with tag number breaker) will operate to “open the circuit” and prevent the
1ES41 continued flow of electrical energy to the faulted area. To
The short-circuit current drawn from generator and the minimize the interruption of electrical services to other areas
power grid in both modes are summarized in TABLE IV. of the power system, the system is also designed so that the
Also short-circuit current value of faulty switchgears are protective device closest to the short-circuit operates first to
shown in TABLE V. “clear the fault.” For example, if a short-circuit occurs on a
downstream circuit branch cable as shown in “Fig. 1,”
Regarding the short circuit withstand capacity of (below), the branch circuit breaker feeding that cable (circuit
switchgears the results are acceptable. breaker a) should open first to isolate the fault, rather than
the main breaker in the panel which would interrupt service
TABLE III. LOAD FLOW RESAULS IN CONNETION TO THE POWER GRID to all circuit branches.
If a circuit breaker a fails to operate after a given time,
Power Grid GTG-C GTG-B
then the main breaker would operate to open or “trip” the
285.9 349.9 350 I(A) circuit, thus providing back-up protection. This time-
15800 15260 15263 P(KW) sequence of operation is called “coordination of protective
3289 12545 12545 Q(KVAR) devices.” A protection-coordination study is done to
16318 19755 19757 S(KVA) determine the trip settings of each protective device in the
power system so that maximum protection with minimum
interruptions is provided for all faults that may happen in the
system.

TABLE IV. SHORT CIRCUIT STUDY RESAULTS FOR GTG,S AND THE POWER
GRID

Grid GTG-A GTG-C GTG-B GTG-D I(KA)


0 3.13 3.13 3.13 0 Island
Grid
4.62 0 3.13 3.13 0
Connected

TABLE V. SHORT CIRCUIT STUDY RESAULTS FOR MAIN


SUBSTAION BUSBAR,S

A. Protection Coordination of the Incomer from the Power


Grid
1) Overcurrent IDMT (51): The peak value is selected to
100% of transformer’s rated current and the TMS (time
Figure 3. Load flow resaultsfor GTG-B in island mode multiplier setting) should be selected not to trip at the largest
motor starting current plus all other running load and to be
laid above overcurrent protection curve of the 33kv through a fault current is 4.618KA which overcurrent relay
switchgear’s outgoing feeders at the system’s maximum fault IDMT function (51IDMT) operated at 0.789 Seconds.
current providing coordination of at least 0.25sec.

TABLE VI. SHORT CIRCUIT STUDY RESAULTS FOR MAIN SUBSTAION


BUSBAR,S

1S11 1S31A 1ES31A 1S41A 1ES41A I(KA)


16.5 16.9 18.9 42.3 52.2 Island
Grid
18 17.4 17.3 42.5 57
Connected
SC
31.5 25 25 50 63
Witstand

Figure 5. Load flow resaults for GTG-B when refinary is connected Figure 6. Single Line Diagram of the 11KV electromotor and the power
to the power grid grid’s incomer
2) Illustration of protection behavior of the largest 11kv
electromotor in coordination with the power grid’s incomer:
B. Protection Coordination of the Gas Turbine
“Fig. 6,” depicts a portion of the system’s single-line
Generator’s Incomers
diagram and shows the power grid’s incomer (in figure it
shown as “INCOMER BESAT”) and the 33kV outgoing 1) Overcurrent IDMT (51): The peak value is selected
feeder which supplies the largest electromotor with tag 111 to100% of the rated current and the TMS should be selected
KM 101. Protection curve of the power grid incoming from not to trip at the largest motor starting current plus all other
the BESAT substation, the current-time characteristic of running loads and to be laid above the overcurrent protection
electric motor, transformer rated and inrush currents are curve of the 33kv switchgear’s outgoing feeders at the
illustrated in “Fig. 7,”. The power grid’s incomer overcurrent system’s maximum fault current providing coordination of at
protection curve is laid above of the electric motor protection least 0.25sec.
curve. Also the power grid’s transformer inrush current and 2) Assessment of fault occurrence in the 33KV output
outgoing feeder transformer inrush current are located below feeder (9TR1311) and overcurrent relay curves in
the power grid’s incomer overcurrent protection curve. coordination with the generator incomer. A symmetrical
The single line diagram and protection curve for the other three phase fault applied and the performance of the feeder
11KV electro motors are the same as the motor above and the generator’s incomer relays are illustrated in “Fig. 9,”.
(111-KM-101). As “Fig. 9,” Shows, the 33 kV output feeders 9TR1311
3) Analyzing the fault occurrence in the 33KV output through a fault current is equal to 17.893KA which the
feeder (2TR1311) and overcurrent relay curves in feeder’s relay instantaneous overcurrent function (50)
coordination with the power grid’s incomer. A symmetrical operated at 0.02 seconds and overcurrent TDMT function
three phase fault applied and the performance of the feeder (51IDMT) operated at 0.384 seconds. Maximum power of
and the grid’s incomer relays are shown in “Fig. 8,”. As the generator’s incomer through a fault current \ is 3.128KA
“Fig. 8,” shows, the 33 kV output feeders 2TR1311 through which overcurrent relay IDMT function (51IDMT) operated
a fault current is equal to 17.7KA which the feeder’s relay at 1.18 seconds.
instantaneous overcurrent function (50) operated at 0.02 Time margin between the overcurrent protection 51IDMT
seconds and overcurrent TDMT function (51IDMT) operated of the 9TR1311 feeder and the generator’s incomer
at 0.291 seconds. Maximum power of the grid’s incomer (120TR101C) is 0.836S.
C. Bus-Tie Overcurrent Protection Coordination problem and overcurrent relay settings can be able to carry
Overcurrent IDMT (51): The peak value is selected to out their duties.
200% of the Generator’s transformer incomer rated For some 33KV outgoing feeders, time margin between
current. Since this function is used as a backup of the the feeder and bus-tie relay is a little less than 0.25S (for
example for feeder 11TR1311 time margin is 0.21S) but it’s
turbine generator and the external line (grid) incomers
not a critical problem and can be ignored. If a relay of the
overcurrent protection, the following in relation to
33KV outgoing feeder fails, it’s better to rapidly open the
coordination and TMS setting should be met:
bus-tie’s circuit breaker, otherwise it may cause to open all
 Bus-Tie Overcurrent Protection Curve at the 33KV switchgear incomers and consequently, total
system’s maximum fault current should be laid shutdown of the refinery.
above the 33KV output feeders Overcurrent This study was repeated for other 6 kV and 0.4 kV
protection curves. switchgears and observed that protection coordination
 Bus-Tie Overcurrent Protection Curve at the between downstream and upstream relays is established.
system’s maximum fault current should be laid The study shows that by connecting the third refinery’s
above the generator and the Grid’s incomer network to the power grid, short-circuit current values of the
Overcurrent protection curves. switchgears will not exceed the short circuit resistance
“Fig. 10,” compares the generator incomer Overcurrent rating, because all bus bars have a short-circuit resistance
protection curve with the Bus-Tie Overcurrent protection rating that is greater than the maximum available fault
Curve, As shown at the maximum generator power through current.
a fault current(3.3KA) coordination margin is 0.729SEC.
REFERENCES
D. Protection Coordination of 33/6KV Transformer
Feeder [1] Abraham Olatoke and Mohamed Darwish, “Relay Coordination and
Harmonic Analysis in a Distribution Network With Over 20%
1) Overcurrent IDMT (51): The peak value is selected Renewable Sources”, IEEE Power Engineering Conference (UPEC),
to150% of transformer rated current and the TMS setting 48th Interpower Universities, 2013, 978-1-4799-3254-2/13.
curve should be laid below the overcurrent protection curve [2] Ashrafi Habibabadi Reza, “New Method on the Relays Protective
Coordination Due To Presence Of Distributed Generation “, IEEE
of the 33kv switchgear’s incomer from the Generator and the Power Engineering and Automation Conference (PEAM), 2012, 978-
Grid and laid above the overcurrent protection curve of the 1-4577-1600-3/12.
6KV switchgear’s incomer feeder providing coordination of [3] Ashwin Kumar Sahoo, “Protection of Microgrid through Coordinated
Directional Over current Relays”, IEEE Global Humanitarian
at least 0.25sec. Technology Conference - South Asia Satellite (GHTC-SAS) |
Assessment of fault occurance in the 33KV output feeder September 26-27, 2014 | Trivandrum.
(11TR1311) and overcurrent relay curves, the coordination [4] H. H. Zeineldin, Hebatallah M. Sharaf, Doaa K. Ibrahim and Essam
beetween relays is established. Sequence of the overcuurent El-Din Abou El-Zahab, “Optimal Protection Coordination for Meshed
Distribution Systems With DG Using Dual Setting Directional Over-
protection relay operations are as follows: Current Relays “, IEEE TRANSACTIONS ON SMART GRID, 2014,
 33KV output feeder 11TR1311 instantaneous overcurrent 1949-3053.
protection at t=0.02S [5] H. Wan, K. Li, and K. Wong, “An adaptive multiagent approach to
 33KV output feeder 11TR1311 IDMT overcurrent protection relay coordination with distributed generators in industrial
power distribution system,” IEEE Trans. Ind. Appl. Sep./Oct. 2010,
protection at t=0.355S vol. 46, no. 5, pp. 2118–2124.
 33KV Bus-Tie IDMT overcurrent protection at t= 0.542S [6] Hui Yang, Fushuan and Gerard Ledwich, “Optimal coordination of
 33KV incomers from generators and power grid IDMT overcurrent relays in distribution systems with distributed generators
overcurrent protection at t=1.18S based on differential evolution algorithm “, Euro. Trans. Electr.
Power (2011), Published online in Wiley Online Library
Figure 6. Time margin between feeder and bus-tie relay (wileyonlinelibrary.com). DOI: 10.1002/etep.635.
is a little less than 0.25S (margin is 0.21S) but it’s not a
[7] Mansour Ojaghi, Zeinab Sudi and Jawad Faiz, “Implementation of
critical problem and can be ignored. In case of a fail of the Full Adaptive Technique to Optimal Coordination of Overcurrent
33KV outgoing feeders relay it’s better to rapidly open bus- Relays “, IEEE TRANSACTIONS ON POWER DELIVERY,
tie’s circuit breakers, otherwise it may cause to open all JANUARY 2013, VOL. 28, NO. 1.
33KV switchgear incomers and consequently, total [8] N. Rezaei and M.R. Haghifam, “Protection scheme for a distribution
shutdown of the refinery. system with distributed generation using neural networks “,Elsevier
Electrical Power and Energy Systems 30, 2008, 235–241.
[9] Sachit A. Gopalan, Victor Sreeram and Herbert H.C. Iu, “A review of
VI. CONCLUSION coordination strategies and protection schemes for microgrids “,
Elsevier Renewable and Sustainable Energy Reviews 32, 2014, 222–
According to this study, it was observed that protection 228.
coordination between the main and backup relays at 33 kV [10] Waleed K. A. Najy, H. H. Zeineldin and Wei Lee Woon, “Optimal
bus, main bus of the South Pars’s third refinery, in Protection Coordination for Microgrids With Grid-Connected and
connection to the power grid will not deal with a critical Islanded Capability “, IEEE TRANSACTIONS ON INDUSTRIAL
ELECTRONICS, APRIL 2013, VOL. 60, NO. 4.
Figure 7. Overcurrent protection curves of the 11KV electro motors

Figure 9. Overcurrent protection curves of the 33KV feeder 9TR1311


and GTG-C incomer

Figure 8. Overcurrent protection curves of the 33KV feeder 2TR1311 and


power grid incomer

Figure 10. Overcurrent protection curves of the 33KV Bus-Tie and


generator’s incomer

View publication stats

Вам также может понравиться