Cebu-Negros-Panay 230

kV Backbone Project –
Stage 3
Presentation to the 2019 Visayas 30 May 2019
Energy Investment Forum
Outline
1. Project Components and Status
2. Other Transmission Projects
Project Components and Status
Cebu-Negros-Panay 230 kV Backbone Project
PANAY

BAROTAC VIEJO S/S

CADIZ S/S CNP 230 kV Backbone Project


Stage 3
CADIZ
MANAPLA CITY
E.B. MAGALONA S/S CITY ETC: Dec 2020
E.B. MAGALONA
CITY VICTORIAS
CITY Cebu-Negros transfer
CNP 230 kV Backbone capacity: 180 MW + 800 MW
Project Stage 1

ETC: Dec 2019

Negros-Panay transfer NEGROS


capacity:
2019: 90 MW + 240 MW CEBU
2020: 90 MW + 400 MW
BACOLOD S/S

CALATRAVA S/S
CALATRAVA CTS CNP 230 kV Backbone Project
Stage 2 (Cebu 230 kV Substation)
SAN CARLOS SWS
ETC: Dec 2020

CEBU S/S

TALAVERA SWS

MAGDUGO S/S
Project Components and Status
Cebu-Negros-Panay 230 kV Backbone Project – Stage 3
PANAY
BAROTAC VIEJO S/S
(3x300 MVA)

CADIZ
MANAPLA
CITY
CITY

E.B. MAGALONA
CITY VICTORIAS
CITY

NEGROS

CEBU

CALATRAVA CTS

TALAVERA–CALATRAVA S/C, 29 km
SAN CARLOS SWS (2x400 MW)

 Sites of the Barotac Viejo and


CEBU S/S
Magdugo S/S are workable.
TALAVERA SWS
 Manufacturing of the Talavera–
MAGDUGO S/S
Calatrava S/C is almost finished. (3x300 MVA)
Project Components and Status
Cebu-Negros-Panay 230 kV Backbone Project – Stage 3
PANAY
CADIZ S/S
E.B. MAGALONA-CADIZ (2x150 MVA)
230 kV T/L, 45 km

CADIZ
MANAPLA
CITY
CITY

E.B. MAGALONA
CADIZ-CALATRAVA 230
VICTORIAS
CITY
CITY
kV T/L, 80 km

NEGROS
BACOLOD S/S
(2x300 MVA)
CEBU
CALATRAVA S/S
(2x100 MVA)

CALATRAVA CTS
 Substation Sites in Negros Occidental are under
ROW negotiations. CEBU-MAGDUGO 230 kV
 Ongoing Parcellary Survey for the E.B. Magalona– SAN CARLOS SWS T/L, 35 km

Cadiz–Calatrava 230 kV OHTL.


 ROW issues on the 230 kV Transmission lines in CEBU S/S

Cebu. TALAVERA SWS

 Difficulty in acquiring LGU permit in Cebu side. TALAVERA-MAGDUGO


 Supply for the equipment is almost complete. 230 kV T/L, 6 km
Other Transmission Projects
Negros & Panay

NABAS-CATICLAN-
BORACAY PANITAN - NABAS 138 kV T/L LINE 2
138 kV T/L PROJECT Dec 2019
STAGE 1 : Jun 2020
STAGE 2 : Aug 2021

BAROTAC VIEJO - NATIVIDAD


69 kV T/L PROJECT
Oct 2022

PANAY - GUIMARAS 138 kV SAN CARLOS - GUIHULNGAN


INTERCONNECTION PROJECT 69 kV T/L PROJECT
Jul 2021 Dec 2019

AMLAN - DUMAGUETE
138 kV T/L PROJECT
FILED TO ERC
Feb 2022

ONGOING
Other Transmission Projects
Cebu & Bohol
VISAYAS SUBSTATION RELIABILITY
PROJECT 2 VISAYAS VOLTAGE IMPROVEMENT
Lapu-lapu S/S: 1x100 MVA PROJECT
Mandaue S/S: 1x100 MVA Cebu S/S: 2x20 MVAR
Sep 2019 Compostela S/S: 2x20 MVAR
Corella S/S: 1x5 MVAR
Dec 2019

LARAY 230 kV S/S


May 2022

CEBU - BOHOL 230 kV


INTERCONNECTION PROJECT
MINDANAO–VISAYAS Dec 2021
INTERCONNECTION PROJECT
Dec 2020

FILED TO ERC
TAGBILARAN 69 KV
ONGOING SUBSTATION PROJECT
Jun 2020
Other Transmission Projects TO
DAANBANTAYAN

Metro Cebu
CEBU-NEGROS-PANAY 230 kV STAGE 3
Dec 2020
COMPOSTELA

TO NEGROS

CEBU-NEGROS-PANAY 230 kV
CALONG-CALONG STAGE 2
Dec 2020

CEDC

MAGDUGO

TVI
CEBU
TOLEDO

MANDAUE
LAPULAPU

MVIP CEBU - LAPULAPU


Dec 2020 QUIOT 230 kV T/L PROJECT
(energized at 138 kV)
Dec 2020

NEW NAGA (COLON) SUBSTATION PROJECT


COLON
(REMAINING WORKS)
Dec 2019 NAGA

NAGA S/S UPGRADING PROJECT


Dec 2019 ONGOING
Other Transmission Projects
Leyte & Samar
CALBAYOG - ALLEN
138 kV T/L PROJECT
(69 kV energized)
Jul 2022

VISAYAS SUBSTATION RELIABILITY


PROJECT 2
STA. RITA - QUINAPONDAN
Sta. Rita S/S: 1x50 MVA
69 kV T/L PROJECT
Sep 2019
Sep 2019

BABATNGON - PALO
230 kV T/L PROJECT
VISAYAS SUBSTATION UPGRADING (138 kV energized)
PROJECT 1 Feb 2022
Maasin S/S: 1x50 MVA
Calbayog S/S: 1x50 MVA
Tabango S/S: 1x50 MVA
Daanbantayan S/S: 1x100 MVA
Sep 2021

VISAYAS VOLTAGE IMPROVEMENT


PROJECT
Bobolosan LES: 1x5 MVAR
Himayangan LES: 1x5 MVAR
FILED TO ERC Tolosa LES: 1x5 MVAR
Mar 2022
ONGOING