Document Title: CE & EH WHP - Pressure Test & Test Pack Procedure
GLF-WHP02-EPCI4
Remarks:
The information contained in this document is the proprietary to North Oil Company. It must not be reproduced, stored, disclosed to any third party or used for any purpose not authorized by North
Oil Company. Printed documents are uncontrolled and considered as "for information only". Reference should always be made to the on-line EDMS for the updated version
Major Projects Template MAJOR-ASY-MPQA-FOR-000004_Rev00 Dated 09/06/2018
Page 1 of 49
Block 5 - AL SHAHEEN FIELD Development
Document Title: CE & EH WHP - Pressure Test & Test Pack Procedure
REVISION HISTORY
Rev. Rev. Date Status History Issuer Reviewer Approver
The information contained in this document is the proprietary to North Oil Company. It must not be reproduced, stored, disclosed to any third party or used for any purpose not authorized by North
Oil Company. Printed documents are uncontrolled and considered as "for information only". Reference should always be made to the on-line EDMS for the updated version
Major Projects Template MAJOR-ASY-MPQA-FOR-000004_Rev00 Dated 09/06/2018
Page 2 of 49
Block 5 - AL SHAHEEN FIELD Development
Document Title: CE & EH WHP - Pressure Test & Test Pack Procedure
CONTENTS
Table of Contents
Revision history................................................................................................................................ 2
contents............................................................................................................................................. 3
1 Introduction................................................................................................................................ 6
2 Objective..................................................................................................................................... 6
3 Scope.......................................................................................................................................... 6
4 References.................................................................................................................................. 6
5 Definition and Abbreviation......................................................................................................7
5.1 Definitions............................................................................................................................................ 7
5.2 Abbreviations....................................................................................................................................... 9
6 Role And Responsibilities.......................................................................................................10
7 Safety Requirements Prior to Pressure Test.........................................................................11
8 General Pressure Test Requirements....................................................................................11
9 General Test Preparation........................................................................................................14
9.1 Gauges, Recorder and Thermometer Requirements.........................................................................14
9.2 Testing Equipment............................................................................................................................. 15
9.3 Temporary closure material................................................................................................................ 16
9.4 Documents / Record Preparation....................................................................................................... 17
9.4.1 Document of Test Package..........................................................................................17
9.4.2 Test Package Issuance................................................................................................18
9.4.3 Test Package Work Flow.............................................................................................18
10 Cleaning and Flushing.........................................................................................................19
10.1 Cleaning Methods.............................................................................................................................. 19
10.1.1 Cleaning with Air (Blowing or Air Flushing)..................................................................19
10.1.2 Cleaning with Water (Water Flushing)..........................................................................20
10.1.3 Mechanical Cleaning....................................................................................................20
10.1.4 Chemical Cleaning.......................................................................................................20
10.2 Application Specific to be cleaned...................................................................................................... 20
11 Vessel and Equipment.........................................................................................................21
12 Hydrostatic Test Procedure.................................................................................................21
12.1 Scope and purpose............................................................................................................................ 21
12.2 Preparation for Hydrostatic Test......................................................................................................... 22
The information contained in this document is the proprietary to North Oil Company. It must not be reproduced, stored, disclosed to any third party or used for any purpose not authorized by North
Oil Company. Printed documents are uncontrolled and considered as "for information only". Reference should always be made to the on-line EDMS for the updated version
Major Projects Template MAJOR-ASY-MPQA-FOR-000004_Rev00 Dated 09/06/2018
Page 3 of 49
Block 5 - AL SHAHEEN FIELD Development
Document Title: CE & EH WHP - Pressure Test & Test Pack Procedure
The information contained in this document is the proprietary to North Oil Company. It must not be reproduced, stored, disclosed to any third party or used for any purpose not authorized by North
Oil Company. Printed documents are uncontrolled and considered as "for information only". Reference should always be made to the on-line EDMS for the updated version
Major Projects Template MAJOR-ASY-MPQA-FOR-000004_Rev00 Dated 09/06/2018
Page 4 of 49
Block 5 - AL SHAHEEN FIELD Development
Document Title: CE & EH WHP - Pressure Test & Test Pack Procedure
1 INTRODUCTION
This procedure covers the detail requirements of flushing, draining, hydrostatic & pneumatic
pressure strength test and drying of piping system of Block 5 - AL SHAHEEN FIELD Development
“Gallaf Batch 2”.
The test pressure and system boundary limits shall be covered and will be shown on respective
piping pressure test packages.
2 OBJECTIVE
The objective of this procedure is to provide sufficient guideline on system cleaning &flushing,
strength testing of all pressure component and reinstatement within the test boundary of the system.
This to ensure a consistent project requirement is always achieved as per schedule with highest
quality standard from fabrication and installation of pipework across all project facilities with safe
working environment.
3 SCOPE
This procedure shall apply to Piping for Block 5 - AL SHAHEEN FIELD Development “Gallaf Batch 2”
4 REFERENCES
Document No Title
ASME PCC-1 Guidelines for Pressure Boundary Bolted Flange Joint Assembly
Standard Specification for Alloy Steel and Stainless Steel Bolting Materials for
ASTM A193
High Temperature Service
Document Title: CE & EH WHP - Pressure Test & Test Pack Procedure
API Standard 614 Lubrication, Shaft-sealing and Oil-control Systems and Auxiliaries
SD-NOC-PVV-178 Design and Erection of Glass Reinforced Plastic (GRP) Piping System
Term Definitions
The information contained in this document is the proprietary to North Oil Company. It must not be reproduced, stored, disclosed to any third party or used for any purpose not authorized by North
Oil Company. Printed documents are uncontrolled and considered as "for information only". Reference should always be made to the on-line EDMS for the updated version
Major Projects Template MAJOR-ASY-MPQA-FOR-000004_Rev00 Dated 09/06/2018
Page 6 of 49
Block 5 - AL SHAHEEN FIELD Development
Document Title: CE & EH WHP - Pressure Test & Test Pack Procedure
The information contained in this document is the proprietary to North Oil Company. It must not be reproduced, stored, disclosed to any third party or used for any purpose not authorized by North
Oil Company. Printed documents are uncontrolled and considered as "for information only". Reference should always be made to the on-line EDMS for the updated version
Major Projects Template MAJOR-ASY-MPQA-FOR-000004_Rev00 Dated 09/06/2018
Page 7 of 49
Block 5 - AL SHAHEEN FIELD Development
Document Title: CE & EH WHP - Pressure Test & Test Pack Procedure
5.2 Abbreviations
Acronym Description
QC Quality Control
QA Quality Assurance
PL Punch List
MC Mechanical Completion
Document Title: CE & EH WHP - Pressure Test & Test Pack Procedure
Document Title: CE & EH WHP - Pressure Test & Test Pack Procedure
entries of unauthorized personnel. Their also responsibility to approve hydro test work permit
prior to activities.
g) Company Representative Company representative responsibility is to witnessing and
accepting of the pressure test as required by QC.
Document Title: CE & EH WHP - Pressure Test & Test Pack Procedure
PVV-178. Prior to carrying out pressure testing, users of this procedure shall carefully consider the
following test requirements:
a) Pressure gauges, temperature and time recorders shall be used for all pressure tests. The
pressure gauges shall be shown in Bars(g)/Psi (g), recorders shall indicate temperature in
degree Celsius (°C) & pressure in Bars(g)/Psi (g).
b) Pressure test equipment/recorder shall be calibrated. Certificate to be review and attached in
the test pack, calibration sticker shall be available at each equipment/recorder.
c) Lines shall have all permanent supports installed before pressure test. Requirement for
hydrostatic test for gas service shall be verified that supports is adequate for liquid filling. The
system as designed and constructed will support the weight of liquid required for
flushing/hydro testing. Provision of additional temporary support for testing where if
necessary.
d) The line list shall indicate the type of test and pressure to use on each line. Maximum
operating pressure of each piece of equipment, including instruments, shall be checked
against the test pressure of the piping system in which the piece of equipment is included. If
the test pressure of the piping system is greater than the maximum operating pressure of the
equipment, the equipment shall be blanked-off and tested separately.
e) All joints, including welds, are to be left un-insulated and unpainted for examination during
testing. In case welded joints are painted before testing, then the following requirements shall
apply:
One-hour minimum piping pressure test duration provided that the rating of the related
piping class does not exceed 300#.
Two-hours minimum piping pressure test duration for 600# and above related piping
class.
f) Test medium, test pressure and minimum holding time shall be based on company standards
SD-NOC-PVV-171, SD-NOC-PVV-173 and SD-NOC-PVV-178.
g) Any test shall include a preliminary cleaning of the piping after fabrication, to be performed
externally and internally, in order to remove all loose scale, weld spatter, sand and other
foreign material. The cleaning shall be performed according company standards SD-NOC-
PVV-175.
h) Any test shall include a preliminary check at no more than 2 bars (g) to locate any major leak.
Hydrostatic pressure testing shall only be carried-out on perfectly dry surfaces to allow for
proper visual check for leaks.
i) Pneumatic testing over 7 bars (g) shall use Nitrogen as test medium. It is not permitted to use
compressed air and top up with nitrogen.
j) SMOE QA/QC personnel responsible to follow up, review and secure Employer
representative acceptance signature on hard copy report of weld summary which states fit
up, visual, welder identification, WPS no., NDT/material traceability are compiled in the test
pack document before commence pressure test.
The information contained in this document is the proprietary to North Oil Company. It must not be reproduced, stored, disclosed to any third party or used for any purpose not authorized by North
Oil Company. Printed documents are uncontrolled and considered as "for information only". Reference should always be made to the on-line EDMS for the updated version
Major Projects Template MAJOR-ASY-MPQA-FOR-000004_Rev00 Dated 09/06/2018
Page 11 of 49
Block 5 - AL SHAHEEN FIELD Development
Document Title: CE & EH WHP - Pressure Test & Test Pack Procedure
k) Pressure shall be maintained for a sufficient time to permit thorough inspection, visual
examination of all surfaces, welds and connections, but not less than 30 min. During increase
of pressure, hold pumping to stabilize pressure and inspect for any leaks. Release air locked
inside test object to avoid fluctuation of pressure. if require, de-air from vent points as
indicated on test isometric. Test recorder shall be started when pressure is stable and test
pump is either disconnected from test manifold or energy source disconnected.
l) Test water shall be clean and free from minerals and suspended matter. Only water having a
chloride content of 25 ppm or less shall be used in contact with stainless steel. Sea water
shall never be used, accordance with company standard SD-NOC-PVV-171.
m) Test temperature it is recommended that the metal temperature during test be maintained at
least 30°F (17°C) above the minimum design metal temperature to minimize the risk of brittle
fracture, but not exceed 50°C. Para 8.2.4 (a). the permissible minimum test temperature is
specified on the drawing, ASME Sec. VIII Div.2. The temperature of water shall not be less
than the atmospheric temperature and in no case it shall be less than 70°F (20°C). pressure
is not applied until metal temperature and water temperature are equalizer ASME B31.1.
n) Unless otherwise required by company, the following systems are excluded from pressure
testing.
o) Any package unit previously tested by manufacturer in accordance with the applicable
codes/specification.
p) Punch category A (items related to safety/integrity of the system), which affects the integrity
of the system accordance company standard SD-NOC-EC-600 shall be rectified before
flushing and Pressured testing. Original filled in and updated punch list shall be part of the
test package.
q) Pressure and temperature record test chart shall indicate the following;
Test pack number/Test Date (refer Isometric index for line numbers/spool numbers)
Responsible test person name/sign
Test pressure and medium
SMOE inspector name/sign
NOC inspector name/sign
Start time/actual duration of test
Start/Finish pressure(barg/psig)
Start/Finish temperature(°C)
Pressure gauge ID/Serial Number
Pressure & temperature recorder ID/Serial Number
r) If any inline item, such as valves, instrument and other items that will be exposed to pressure
are included in the pressure test must be capable of withstanding the pressure that includes
the internals and valve housing.Valve acceptable opening position during the test shall be
The information contained in this document is the proprietary to North Oil Company. It must not be reproduced, stored, disclosed to any third party or used for any purpose not authorized by North
Oil Company. Printed documents are uncontrolled and considered as "for information only". Reference should always be made to the on-line EDMS for the updated version
Major Projects Template MAJOR-ASY-MPQA-FOR-000004_Rev00 Dated 09/06/2018
Page 12 of 49
Block 5 - AL SHAHEEN FIELD Development
Document Title: CE & EH WHP - Pressure Test & Test Pack Procedure
complied and removed items shall be identify. Any inline items, instrument and valve included
on test shall be identified during pre-line walk before the test. SMOE Piping Engineer shall
ensure that the test isometric indicate the specific valve which shall be in half open position
during pressure test. All other valves shall be tested in the fully open position. When check
valves are included in pressure test theyshall be jacked open or have their internals removed.
Ball and gate valves shall be wide open during flushing and three quarter open during testing.
s) After system testing is successfully completed, testing team shall carry out the release of
pressure and vent shall be opened. Hose connected to drain/filling points shall empty the
system.
t) Test object shall be free from any covers and tarpaulin except for pipe protection during
pressure test. Pipe protection shall be required to open if there is significant pressure drop or
water moisture observed during visual inspection.
u) Following pressure test, SMOE QC shall prepare piping system pressure test report and shall
be offered to sign off after acceptance of pressure test by all authorised persons.
v) Systematic low pressure passing test shall be executed on critical valves upon reception and
before installation. Valves shall be tested in close position based on an approved procedure,
in both directions at low pressure with Nitrogen at 5 bars (g) and the result of the test shall
comply with Vendor datasheet and Standards. Low pressure closure test shall be carried out
strictly in accordance with company standards SD-NOC-EC-601, GM-NOC-PVV-142 and API
STD 598.
The information contained in this document is the proprietary to North Oil Company. It must not be reproduced, stored, disclosed to any third party or used for any purpose not authorized by North
Oil Company. Printed documents are uncontrolled and considered as "for information only". Reference should always be made to the on-line EDMS for the updated version
Major Projects Template MAJOR-ASY-MPQA-FOR-000004_Rev00 Dated 09/06/2018
Page 13 of 49
Block 5 - AL SHAHEEN FIELD Development
Document Title: CE & EH WHP - Pressure Test & Test Pack Procedure
Dial indicating pressure gauge used in testing shall be graduated over a range of about two times
the maximum intended pressure, but in no case shall the range be less than one and one-half no
more than four times the intended test pressure. (ASME Sect VIII Div.2 Para.8.1.4) (b).
A minimum of one pressure gauge shall be installed in the highest point with a vent valve. Second
pressure gauge at lowest point and one recorder shall be installed at lowest or highest point of the
piping system. Test chart shall be approved/signed by all concerned personnel. Test recorders shall
have pressure & temperature indicators. Water filling connection shall be at the lowest point of the
system for test.
Identification number of pressure gauges and recorder shall also be recorded on the test chart. The
chart shall be attached to the pressure test pack after testing is completed successfully.
9.2 Testing Equipment
Following testing equipment shall be used and when applicable calibration certificate shall be
provided:
a) Centrifugal pump for filling water;
b) Tanks for water storage;
c) Water filter;
d) Oil free air compressor;
e) Air driven pump for pressurizing the system;
f) Calibrated analog pressure gauge with valid certificate, reading in Bar or PSI.:
Accuracy: maximum 2% of full scale;
Validation shall be for a maximum 12 months. However, re-calibration is required if
the calibrated gauge is damaged;
g) Calibrated analog pressure recorder with valid certificate:
Applicable/valid range: 30% - 90% of full scale;
Accuracy: maximum 2% of full scale or ½ chart graduation;
Validation shall be for a maximum 12 months; however, re-calibration is required if the
calibrated gauge is damaged.
h) Digital pressure gauge may be used during pressure test in lieu of both analog pressure
recorder / pressure gauge. However it shall be met requirement as below:
Having capability to record data. Recorded data normally store in internal memory
and it can be downloaded once the test is completed and printed. The printed data
has similar function as chat record.
Digital pressure gauge can be used with wider range (unlike analog where applicable
range is limited as explained in point f and g in Para.9.2) compare to analog pressure
recorder/pressure gauge as long as same providing same degree of accuracy as
obtained with analog pressure recorder/pressure gages.
The information contained in this document is the proprietary to North Oil Company. It must not be reproduced, stored, disclosed to any third party or used for any purpose not authorized by North
Oil Company. Printed documents are uncontrolled and considered as "for information only". Reference should always be made to the on-line EDMS for the updated version
Major Projects Template MAJOR-ASY-MPQA-FOR-000004_Rev00 Dated 09/06/2018
Page 14 of 49
Block 5 - AL SHAHEEN FIELD Development
Document Title: CE & EH WHP - Pressure Test & Test Pack Procedure
The information contained in this document is the proprietary to North Oil Company. It must not be reproduced, stored, disclosed to any third party or used for any purpose not authorized by North
Oil Company. Printed documents are uncontrolled and considered as "for information only". Reference should always be made to the on-line EDMS for the updated version
Major Projects Template MAJOR-ASY-MPQA-FOR-000004_Rev00 Dated 09/06/2018
Page 15 of 49
Block 5 - AL SHAHEEN FIELD Development
Document Title: CE & EH WHP - Pressure Test & Test Pack Procedure
The information contained in this document is the proprietary to North Oil Company. It must not be reproduced, stored, disclosed to any third party or used for any purpose not authorized by North
Oil Company. Printed documents are uncontrolled and considered as "for information only". Reference should always be made to the on-line EDMS for the updated version
Major Projects Template MAJOR-ASY-MPQA-FOR-000004_Rev00 Dated 09/06/2018
Page 16 of 49
Block 5 - AL SHAHEEN FIELD Development
Document Title: CE & EH WHP - Pressure Test & Test Pack Procedure
Document Title: CE & EH WHP - Pressure Test & Test Pack Procedure
Avoid to raise PL related to hot work since hot work shall be completed & accepted prior to test. Hot
work means any direct welded to the pipe.
Once clearing off all hot work internally, PT SMOE QC inspector will issue RFI to Company for
official line walk/inspection. Punch list may rise during official line walk/inspection and it will be
recorded.
On Company and PT SMOE QC Inspector approval, the test circuit as indicated in test package will
be handed over and tested by piping pre-commissioning team. Pressure test will be witnessed by all
relevant parties.
Once test is accepted, ITR will be signed by all parties. “Original Test Pack” and its original content
including ITR will be archived in test package center.
References Attachment .3 Test Pack Work Flow
Document Title: CE & EH WHP - Pressure Test & Test Pack Procedure
The information contained in this document is the proprietary to North Oil Company. It must not be reproduced, stored, disclosed to any third party or used for any purpose not authorized by North
Oil Company. Printed documents are uncontrolled and considered as "for information only". Reference should always be made to the on-line EDMS for the updated version
Major Projects Template MAJOR-ASY-MPQA-FOR-000004_Rev00 Dated 09/06/2018
Page 19 of 49
Block 5 - AL SHAHEEN FIELD Development
Document Title: CE & EH WHP - Pressure Test & Test Pack Procedure
c) The diameter of the outlet pipe shall be at least two thirds of the diameter of the line to be
cleaned.
d) Main headers shall be cleaned first (i.e. before their connecting lines).
e) Large diameter pipes shall be cleaned before small diameter ones.
f) Dead ends shall be avoided or, if not possible, cleaned separately.
g) Protection of the devices included in the network (control valves, turbine-type flowmeters,
orifice restrictions, etc. shall be carefully studied.
h) Protection of the devices in the vicinity of the network shall be carefully studied, in particular
near the water (or air) outlet, in order not to damage electric motors or instruments with
water or dirty air.
i) Existing block-valves on the lines to be cleaned shall not be used to control an air flow as
they could be damaged by erosion (due to the high velocity of the fluid).
j) A special care shall be taken for vessels designed only for an atmospheric pressure service,
in order not to create, during washing, a high pressure due to a water head.
k) Whenever a vessel full of water has to be emptied, a special note shall be issued to state
that a vent will have to be opened previously in order not to create vacuum in the vessel.
l) Generally, the cleaning fluid shall not flow through a conventional exchanger (use the
bypass, if any, or "break" the line before the exchanger). It shall never flow through a plate
exchanger.
m) The cleaning fluid shall never flow through pumps or compressors: the line shall be
disconnected before the equipment or a "jumper" shall be installed.
n) For large diameter pipes, some temporary supports, hangers, pads, etc., may have to be
added to withstand the weight of valves when a line is disconnected.
o) During flushing, the spring supports, spring hangers, etc., shall be blocked according to the
Manufacturer’s instructions.
p) When a couple of flanges has to be opened to allow the flow to flush out, the distance
between the two flanges shall be at least 1/6 of the pipe diameter.
Document Title: CE & EH WHP - Pressure Test & Test Pack Procedure
SMOE. Tubing pressure test is not part of this procedure. The purpose of this document is to specify
pressure test procedure and acceptance criteria of piping/pipeline/riser works to guarantee the piping
mechanical completion and quality associated required.
12.2 Preparation for Hydrostatic Test
Reference attachment 1 Typical Hydrostatic Set up
12.2.1 Safety Precaution
a) JRA (Job Risk Assessment) shall be conducted prior to hydrostatic test to identify all
foreseeable critical situations, to evaluate associated risks and to define mitigation measures.
b) Prior starting pressure test activity, the following actions are to be put in place:
Approved permit by relevant authorities and keep a copy of permit and JSA on the
work site. P&ID must be attached to the Permit to work together with the JSA.
Fence off/barricade at required safe distance from the test circuit.
Showing signs around the barricaded area.
Verify access to all necessary valves, hose(s), and other parts of test circuit is
available, in case not available scaffolding to be provided.
Verify all equipment (e.g. hose(s), fittings, valves, manifold etc.) to be used as per
suitable rating to test circuit to be tested.
Whip check shall be used during connecting two or more hose(s).
System to be properly supported and anchored, in case required, temporary support
may be added.
Verify that all involved people wearing appropriate PPE.
Suspend all activities other than pressure test activities inside the barricaded area
when the activities is being executed. Barricaded area as per calculation.
Unauthorized persons should be out from the area involved in the test.
Ensure temporary blind flange/bolt type of closure material is tightening with
appropriate value, in order to ensure unexpected release of pressure during testing.
Adequate & appropriate illumination is in place in case work continues to second shift
or working at night.
All personnel involved in the activity shall be experienced/competent/trained.
Carry out a tool box meeting prior starting the activity.
c) During Testing:
Pressurization of test circuit shall be gradually increased. Following strictly the
indication reported in the pressurization operational steps.
Inspection by all parties shall be done during holding time and it shall be performed in
safe manner.
d) After Completion of Test:
Once the test has been completed, depressurization of the test circuit should be done
gradually, and do not stand close to or in front of the depressurization valve.
All connection containing pressure part e.g. hose(s), safety valves, pressure gauges,
manifold etc., should be dismantled once “ZERO” pressure inside the system.
Keep the work area clean and tidy.
The information contained in this document is the proprietary to North Oil Company. It must not be reproduced, stored, disclosed to any third party or used for any purpose not authorized by North
Oil Company. Printed documents are uncontrolled and considered as "for information only". Reference should always be made to the on-line EDMS for the updated version
Major Projects Template MAJOR-ASY-MPQA-FOR-000004_Rev00 Dated 09/06/2018
Page 21 of 49
Block 5 - AL SHAHEEN FIELD Development
Document Title: CE & EH WHP - Pressure Test & Test Pack Procedure
The information contained in this document is the proprietary to North Oil Company. It must not be reproduced, stored, disclosed to any third party or used for any purpose not authorized by North
Oil Company. Printed documents are uncontrolled and considered as "for information only". Reference should always be made to the on-line EDMS for the updated version
Major Projects Template MAJOR-ASY-MPQA-FOR-000004_Rev00 Dated 09/06/2018
Page 22 of 49
Block 5 - AL SHAHEEN FIELD Development
Document Title: CE & EH WHP - Pressure Test & Test Pack Procedure
Document Title: CE & EH WHP - Pressure Test & Test Pack Procedure
air), as defined in ASME B31.3, shall be service tested where the test pressure is at normal
operating pressure. The piping system working at atmospheric pressure (e.g. drains and
vents) as indicated in line list shall not be subject to pressure test, only visual inspection.
During holding time, PT SMOE-QC and Company shall proceed inspections as follows:
a) Check the test pressure.
b) Check welds and overall piping system. In order to verify possible leakages on piping
connection:
Visual inspection is utilized if liquid is used as a test fluid.
Inspection may be repeated in the case such as small leaks or sweating from
welds.
c) The inspection may be repeated in the case such as small leaks or sweating from welds.
The pressure test is declared as accepted when no major leak obverse on tested
piping system moreover on weldment area.
Note:
Performing hydro test during hot or cold weather will lead to disturbance of
pressure gauges reading/pressure recording, and this condition shall be taken into
account during review chart pressure.
Pumping or venting operation during inspection for hydrostatic testing shall not be
allowed and are not required to manage pressure variation from ambient
temperature
12.2.3.7 Rectification of Leak
Leak during test may occur on joints (e.g. flange joint, or threaded connection). This
leakage source shall be rectified prior re-test, below are the steps of rectifying the leak.
Flanged joints/threaded connection:
a) Step1
Isolate the pressure from the pump.
Depressurize the system being tested gradually.
Identify from which bolt position or threaded connection the leaking comes
from.
Loosen the stud bolt or thread connection. Check the flange face or threaded
of the fitting.
Retighten the stud bolts at using progressive value from recommended value
of tensioning/torqueing (e.g. added 5%, 10% etc. more from recommended
value) but not higher than yield strength of bolt. For the threaded connection,
check the thread condition, if still good, re-apply teflon tape and re-tight.
b) Step2
If leak does not stop after re-tightening, disassemble the flange joint and perform
inspection as follow:
Inspect the flange face / RTJ groove. Flange face/RTJ groove may repair as
per applicable standard (e.g.as described in ASME PCC-2). Lapping paste
may use during RTJ groove repair activity.
The information contained in this document is the proprietary to North Oil Company. It must not be reproduced, stored, disclosed to any third party or used for any purpose not authorized by North
Oil Company. Printed documents are uncontrolled and considered as "for information only". Reference should always be made to the on-line EDMS for the updated version
Major Projects Template MAJOR-ASY-MPQA-FOR-000004_Rev00 Dated 09/06/2018
Page 24 of 49
Block 5 - AL SHAHEEN FIELD Development
Document Title: CE & EH WHP - Pressure Test & Test Pack Procedure
Document Title: CE & EH WHP - Pressure Test & Test Pack Procedure
The information contained in this document is the proprietary to North Oil Company. It must not be reproduced, stored, disclosed to any third party or used for any purpose not authorized by North
Oil Company. Printed documents are uncontrolled and considered as "for information only". Reference should always be made to the on-line EDMS for the updated version
Major Projects Template MAJOR-ASY-MPQA-FOR-000004_Rev00 Dated 09/06/2018
Page 26 of 49
Block 5 - AL SHAHEEN FIELD Development
Document Title: CE & EH WHP - Pressure Test & Test Pack Procedure
The information contained in this document is the proprietary to North Oil Company. It must not be reproduced, stored, disclosed to any third party or used for any purpose not authorized by North
Oil Company. Printed documents are uncontrolled and considered as "for information only". Reference should always be made to the on-line EDMS for the updated version
Major Projects Template MAJOR-ASY-MPQA-FOR-000004_Rev00 Dated 09/06/2018
Page 27 of 49
Block 5 - AL SHAHEEN FIELD Development
Document Title: CE & EH WHP - Pressure Test & Test Pack Procedure
a) Testing shall not take place in rain or if the ambient temperature is below 5°C Reading is
made on highest point in order to assure that all elements in piping were effectively
tested. However, the effect of static head shall be taken into account during testing in
order not to exceed allowable stress of the test circuit.
b) Piping system shall be filled from low point. Multiple points may use if required.
c) Air or nitrogen shall be slowly admitted to the test assembly until the pressure reaches
the lesser of one-half of the required test pressure or 1.5 bars (g), accordance with
company standard SD-NOC-PVV-173.
d) The pressure shall be slowly increased in increments of approximately 1 bar. The
pressure shall be held for sufficient time at each stage to permit piping strains to equalize.
e) When the required test pressure is attained, the test assembly shall be isolated from the
air or nitrogen source (but not from the relief valve) and the pressure shall be held for 20
minutes to observe any fall in pressure indicative of a major leak.
f) In order to ensure that there will be no leaks on the circuit under test, all joints, flanges
and welds shall be checked by applying the soapy water.
g) If no pressure drops are indicated at the test pressure, the pressure within the test
assembly shall be slowly released, down to the atmospheric pressure.
h) Pressure shall be released by means of a suitable valve arrangement. Pressure release
shall not be achieved by loosening of flange bolts or plugs or via a line ball valve or gate
valve. Care shall be taken to avoid metal temperatures falling below 0°C, particularly near
the vent connection during depressurizing.
13.2.3.5 Holding Time
When the required test pressure is attained, the test assembly shall be isolated from the air
or nitrogen source (but not from the relief valve) and the pressure shall be held for 20
minutes to observe any fall in pressure indicative of a major leak. Consideration shall be
given to the effects of ambient/metal temperature changes during this period. Personnel shall
not stay nearby the test assembly at this stage or during pressurization. Monitoring of
pressure and temperature shall be made from a remote location.
13.2.3.6 Pneumatic Test Acceptance Criteria
Test pressure and type of test shall (e.g. hydro test, pneumatic or service test), unless
otherwise specified, shall be in accordance with the line list or applicable codes and
standards (e.g. ASME B31.3, B31.8 etc.) unless otherwise specified. As general rules, the
test pressure for pneumatic test will be 1.1 x design pressure. Piping systems D category
(utility air), as defined in ASME B31.3, shall be service tested where the test pressure is at
normal operating pressure. The piping system working at atmospheric pressure (e.g. drains
and vents) as indicated in line list shall not be subject to pressure test, only visual inspection.
During holding time, PT SMOE-QC and Company shall proceed inspections as follows:
a) Check the test pressure.
b) Check welds and overall piping system. In order to verify possible leakages on piping
connection:
The information contained in this document is the proprietary to North Oil Company. It must not be reproduced, stored, disclosed to any third party or used for any purpose not authorized by North
Oil Company. Printed documents are uncontrolled and considered as "for information only". Reference should always be made to the on-line EDMS for the updated version
Major Projects Template MAJOR-ASY-MPQA-FOR-000004_Rev00 Dated 09/06/2018
Page 28 of 49
Block 5 - AL SHAHEEN FIELD Development
Document Title: CE & EH WHP - Pressure Test & Test Pack Procedure
Visual inspection and soap solution is utilized if air/gas is used as a test fluid
Refer to attachment .4 Snoop liquid leak detector
Inspection may be repeated in the case such as small leaks or sweating from
welds.
c) The inspection may be repeated in the case such as small leaks or sweating from welds.
The pressure test is declared as accepted when no major leak obverse on tested
piping system moreover on weldment area.
Note:
Performing pneumatic test during hot or cold weather will lead to disturbance of
pressure gauges reading/pressure recording, and this condition shall be taken into
account during review chart pressure.
Compressing or venting operation during inspection for Pneumatic testing shall
not be allowed and are not required to manage pressure variation from ambient
temperature.
13.2.3.7 Rectification of Leak
If any defects are found in a welded joint, they shall be repaired (after depressurization) using
an approved weld repair procedure and proved acceptable by radiographic testing prior to
repeating the pneumatic test. Any defects at flanged joints shall be investigated prior to
remedial action. Care shall be taken not to apply excessive torque to bolting in order to
achieve a leak-tight seal. Following repair of any defects, the full pneumatic test procedure of
Section 13.2.2.4 shall be followed when repeating the test.
13.2.3.8 Reinstatement
Upon completion of pressure testing and drying, reinstatement activities to be performed:
a) Remove temporary item such as blind flange, gasket, stud bolt, plug, valve and pup piece
etc.
b) Restore any equipment/instrument which is excluded from the test.
c) Restore any supports e.g. spring support which is excluded/dismantled from the test.
d) Final flange management to be performed.
e) Perform preservation accordance company standard SD-NOC-PVV-175 (e.g. closing the
pipe or flange by plastic flange cap/tarpaulin)
14 COMPLETION OF TEST
Tested system shall be depressurized slowly in stages by opening the depressurizing valve in the
test rig. All vents and low point drain valves shall be open, system shall be thoroughly drained after
successful completion of hydro-test or pneumatic test. Where required, blowing by air or pressurized
air shock blowing to remove any trapped water shall be performed to remove any residual or trapped
water accordance with company standard SD-NOC-PVV-175.
Downstream of the check valves shall be check for possible trapped pressure generated during test
and flushing medium to drained off and dry.
End of pipes and nozzle shall be fully protected against the ingress of foreign materials by the use of
end caps, plugs or blind plates sealed with gaskets. These shall not be removed until just prior to
The information contained in this document is the proprietary to North Oil Company. It must not be reproduced, stored, disclosed to any third party or used for any purpose not authorized by North
Oil Company. Printed documents are uncontrolled and considered as "for information only". Reference should always be made to the on-line EDMS for the updated version
Major Projects Template MAJOR-ASY-MPQA-FOR-000004_Rev00 Dated 09/06/2018
Page 29 of 49
Block 5 - AL SHAHEEN FIELD Development
Document Title: CE & EH WHP - Pressure Test & Test Pack Procedure
final assembly or box up. Connection to tie-in points shall be verified from the area or package owner
before opening sealed points.
All lines and joints that fail to pass the pressure test shall be re-tested to the same procedure after
repairs.
15 VENTING /DRAINING/DRYING
After acceptance of the test, the pressure shall be released in a manner and at a rate so as not to
endanger personnel or damage equipment and in a slow and controlled manner. Accordance with
company standard SD-NOC-PVV-175.
1) All vents shall be opened before the system is drained and shall remain open during draining
to prevent pulling a vacuum on the system.
2) Valves, orifice plates, expansion joints and short pieces of piping, which have been removed,
shall be reinstalled with correct gaskets in place and orientation if required.
3) All lines and piping components shall be completely drained and dried All draining to be done
with compressed air.
17 RECORDS
PT SMOE QC shall prepare piping system flushing & pressure testing reports which is to be
witnessed and signed by authorized persons. The report shall be enclosed on the test pack which
includes the following below:
Date of Test
Identification of piping system tested as shown on marked up P&ID’s test boundary limit
including isometrics
Test pressure and holding time
Test medium
Ambient temperature
Design pressure and temperature
Result of testing
Names and Signatures of PT SMOE Q.C. inspector and company representative
Copies of valid calibration certificates
The information contained in this document is the proprietary to North Oil Company. It must not be reproduced, stored, disclosed to any third party or used for any purpose not authorized by North
Oil Company. Printed documents are uncontrolled and considered as "for information only". Reference should always be made to the on-line EDMS for the updated version
Major Projects Template MAJOR-ASY-MPQA-FOR-000004_Rev00 Dated 09/06/2018
Page 30 of 49
Block 5 - AL SHAHEEN FIELD Development
Document Title: CE & EH WHP - Pressure Test & Test Pack Procedure
Pressure/temperature recording chart shall be installed prior to start of test and must be fully
signed off after test.
Once the hydrostatic or pneumatic test is successfully completed. Piping system that require
cleaning and dry up after pressure test shall be completed the reinstatement and Reinstatement of
all items removed from the test shall be carried out.
The information contained in this document is the proprietary to North Oil Company. It must not be reproduced, stored, disclosed to any third party or used for any purpose not authorized by North
Oil Company. Printed documents are uncontrolled and considered as "for information only". Reference should always be made to the on-line EDMS for the updated version
Major Projects Template MAJOR-ASY-MPQA-FOR-000004_Rev00 Dated 09/06/2018
Page 31 of 49
Block 5 - AL SHAHEEN FIELD Development
Document Title: CE & EH WHP - Pressure Test & Test Pack Procedure
17.1 Appendix .1
The information contained in this document is the proprietary to North Oil Company. It must not be reproduced, stored, disclosed to any third party or used for any purpose not authorized by North
Oil Company. Printed documents are uncontrolled and considered as "for information only". Reference should always be made to the on-line EDMS for the updated version
Major Projects Template MAJOR-ASY-MPQA-FOR-000004_Rev00 Dated 09/06/2018
Page 32 of 49
Block 5 - AL SHAHEEN FIELD Development
Document Title: CE & EH WHP - Pressure Test & Test Pack Procedure
17.2 Appendix .2
The information contained in this document is the proprietary to North Oil Company. It must not be reproduced, stored, disclosed to any third party or used for any purpose not authorized by North
Oil Company. Printed documents are uncontrolled and considered as "for information only". Reference should always be made to the on-line EDMS for the updated version
Major Projects Template MAJOR-ASY-MPQA-FOR-000004_Rev00 Dated 09/06/2018
Page 33 of 49
Block 5 - AL SHAHEEN FIELD Development
Document Title: CE & EH WHP - Pressure Test & Test Pack Procedure
17.3 Appendix .3
The information contained in this document is the proprietary to North Oil Company. It must not be reproduced, stored, disclosed to any third party or used for any purpose not authorized by North
Oil Company. Printed documents are uncontrolled and considered as "for information only". Reference should always be made to the on-line EDMS for the updated version
Major Projects Template MAJOR-ASY-MPQA-FOR-000004_Rev00 Dated 09/06/2018
Page 34 of 49
Block 5 - AL SHAHEEN FIELD Development
Document Title: CE & EH WHP - Pressure Test & Test Pack Procedure
17.4 Appendix .4
The information contained in this document is the proprietary to North Oil Company. It must not be reproduced, stored, disclosed to any third party or used for any purpose not authorized by North
Oil Company. Printed documents are uncontrolled and considered as "for information only". Reference should always be made to the on-line EDMS for the updated version
Major Projects Template MAJOR-ASY-MPQA-FOR-000004_Rev00 Dated 09/06/2018
Page 35 of 49
Block 5 - AL SHAHEEN FIELD Development
Document Title: CE & EH WHP - Pressure Test & Test Pack Procedure
17.5 Appendix .5
The information contained in this document is the proprietary to North Oil Company. It must not be reproduced, stored, disclosed to any third party or used for any purpose not authorized by North
Oil Company. Printed documents are uncontrolled and considered as "for information only". Reference should always be made to the on-line EDMS for the updated version
Major Projects Template MAJOR-ASY-MPQA-FOR-000004_Rev00 Dated 09/06/2018
Page 36 of 49
Block 5 - AL SHAHEEN FIELD Development
Document Title: CE & EH WHP - Pressure Test & Test Pack Procedure
17.6 Appendix .6
The information contained in this document is the proprietary to North Oil Company. It must not be reproduced, stored, disclosed to any third party or used for any purpose not authorized by North
Oil Company. Printed documents are uncontrolled and considered as "for information only". Reference should always be made to the on-line EDMS for the updated version
Major Projects Template MAJOR-ASY-MPQA-FOR-000004_Rev00 Dated 09/06/2018
Page 37 of 49
Block 5 - AL SHAHEEN FIELD Development
Document Title: CE & EH WHP - Pressure Test & Test Pack Procedure
17.7 Appendix .7
The information contained in this document is the proprietary to North Oil Company. It must not be reproduced, stored, disclosed to any third party or used for any purpose not authorized by North
Oil Company. Printed documents are uncontrolled and considered as "for information only". Reference should always be made to the on-line EDMS for the updated version
Major Projects Template MAJOR-ASY-MPQA-FOR-000004_Rev00 Dated 09/06/2018
Page 38 of 49
Block 5 - AL SHAHEEN FIELD Development
Document Title: CE & EH WHP - Pressure Test & Test Pack Procedure
17.8 Appendix .8
The information contained in this document is the proprietary to North Oil Company. It must not be reproduced, stored, disclosed to any third party or used for any purpose not authorized by North
Oil Company. Printed documents are uncontrolled and considered as "for information only". Reference should always be made to the on-line EDMS for the updated version
Major Projects Template MAJOR-ASY-MPQA-FOR-000004_Rev00 Dated 09/06/2018
Page 39 of 49
Block 5 - AL SHAHEEN FIELD Development
Document Title: CE & EH WHP - Pressure Test & Test Pack Procedure
17.9 Appendix .9
The information contained in this document is the proprietary to North Oil Company. It must not be reproduced, stored, disclosed to any third party or used for any purpose not authorized by North
Oil Company. Printed documents are uncontrolled and considered as "for information only". Reference should always be made to the on-line EDMS for the updated version
Major Projects Template MAJOR-ASY-MPQA-FOR-000004_Rev00 Dated 09/06/2018
Page 40 of 49
Block 5 - AL SHAHEEN FIELD Development
Document Title: CE & EH WHP - Pressure Test & Test Pack Procedure
17.10Appendix .10
The information contained in this document is the proprietary to North Oil Company. It must not be reproduced, stored, disclosed to any third party or used for any purpose not authorized by North
Oil Company. Printed documents are uncontrolled and considered as "for information only". Reference should always be made to the on-line EDMS for the updated version
Major Projects Template MAJOR-ASY-MPQA-FOR-000004_Rev00 Dated 09/06/2018
Page 41 of 49
Block 5 - AL SHAHEEN FIELD Development
Document Title: CE & EH WHP - Pressure Test & Test Pack Procedure
17.11Appendix .11
The information contained in this document is the proprietary to North Oil Company. It must not be reproduced, stored, disclosed to any third party or used for any purpose not authorized by North
Oil Company. Printed documents are uncontrolled and considered as "for information only". Reference should always be made to the on-line EDMS for the updated version
Major Projects Template MAJOR-ASY-MPQA-FOR-000004_Rev00 Dated 09/06/2018
Page 42 of 49
Block 5 - AL SHAHEEN FIELD Development
Document Title: CE & EH WHP - Pressure Test & Test Pack Procedure
17.12Appendix .12
The information contained in this document is the proprietary to North Oil Company. It must not be reproduced, stored, disclosed to any third party or used for any purpose not authorized by North
Oil Company. Printed documents are uncontrolled and considered as "for information only". Reference should always be made to the on-line EDMS for the updated version
Major Projects Template MAJOR-ASY-MPQA-FOR-000004_Rev00 Dated 09/06/2018
Page 43 of 49
Block 5 - AL SHAHEEN FIELD Development
Document Title: CE & EH WHP - Pressure Test & Test Pack Procedure
17.13Appendix .13
The information contained in this document is the proprietary to North Oil Company. It must not be reproduced, stored, disclosed to any third party or used for any purpose not authorized by North
Oil Company. Printed documents are uncontrolled and considered as "for information only". Reference should always be made to the on-line EDMS for the updated version
Major Projects Template MAJOR-ASY-MPQA-FOR-000004_Rev00 Dated 09/06/2018
Page 44 of 49
Block 5 - AL SHAHEEN FIELD Development
Document Title: CE & EH WHP - Pressure Test & Test Pack Procedure
17.14Appendix .14
The information contained in this document is the proprietary to North Oil Company. It must not be reproduced, stored, disclosed to any third party or used for any purpose not authorized by North
Oil Company. Printed documents are uncontrolled and considered as "for information only". Reference should always be made to the on-line EDMS for the updated version
Major Projects Template MAJOR-ASY-MPQA-FOR-000004_Rev00 Dated 09/06/2018
Page 45 of 49
Block 5 - AL SHAHEEN FIELD Development
Document Title: CE & EH WHP - Pressure Test & Test Pack Procedure
The information contained in this document is the proprietary to North Oil Company. It must not be reproduced, stored, disclosed to any third party or used for any purpose not authorized by North
Oil Company. Printed documents are uncontrolled and considered as "for information only". Reference should always be made to the on-line EDMS for the updated version
Major Projects Template MAJOR-ASY-MPQA-FOR-000004_Rev00 Dated 09/06/2018
Page 46 of 49
Block 5 - AL SHAHEEN FIELD Development
Document Title: CE & EH WHP - Pressure Test & Test Pack Procedure
The information contained in this document is the proprietary to North Oil Company. It must not be reproduced, stored, disclosed to any third party or used for any purpose not authorized by North
Oil Company. Printed documents are uncontrolled and considered as "for information only". Reference should always be made to the on-line EDMS for the updated version
Major Projects Template MAJOR-ASY-MPQA-FOR-000004_Rev00 Dated 09/06/2018
Page 47 of 49
Block 5 - AL SHAHEEN FIELD Development
Document Title: CE & EH WHP - Pressure Test & Test Pack Procedure
The information contained in this document is the proprietary to North Oil Company. It must not be reproduced, stored, disclosed to any third party or used for any purpose not authorized by North
Oil Company. Printed documents are uncontrolled and considered as "for information only". Reference should always be made to the on-line EDMS for the updated version
Major Projects Template MAJOR-ASY-MPQA-FOR-000004_Rev00 Dated 09/06/2018
Page 48 of 49
Block 5 - AL SHAHEEN FIELD Development
Document Title: CE & EH WHP - Pressure Test & Test Pack Procedure
The information contained in this document is the proprietary to North Oil Company. It must not be reproduced, stored, disclosed to any third party or used for any purpose not authorized by North
Oil Company. Printed documents are uncontrolled and considered as "for information only". Reference should always be made to the on-line EDMS for the updated version
Major Projects Template MAJOR-ASY-MPQA-FOR-000004_Rev00 Dated 09/06/2018
Page 49 of 49