Вы находитесь на странице: 1из 3

011 FIRST UNITED CONSTRUCTION CORP. V.

VALDEZ equity shall not be controlling, it does not mean that orders in
(IGNACIO) administrative proceedings can be justified without substantial
10 December 2008 | Carpio-Morales, J. | Suppletory/analogous application in evidence.
administrative or quasi-judicial proceedings under Sec 4, Rule 1
FACTS:
PETITIONER: First United Construction Corporation (FUCC) 1.! FEB 1998: The National Housing Authority (NHA) contracted
RESPONDENTS: Menandro G. Valdez & Ramon Adea FUCC for its Freedom Valley Resettlement Project (the Project) in
Antipolo, Rizal. Valdez & Adea (the respondents) are Principal
SUMMARY: The National Housing Authority (NHA) contrated FUCC Engineers of the NHA and was part of the team that was to oversee
for its Freedom Valley Resettlement Project in Antipolo, Rizal. One of FUCC's contract works.
the works to be constructed are the roads leading up to the Project, and 2.! Problems arose when FUCC refused to comply with the technical
instead of following technical specifications, FUCC used concrete specifications of the Project, by using substituted concrete treated
treated base course (CTBC) instead of the prescribed subbase course; it base course (CTBC) for a subbase course. FUCC also refused to
also refused to have field density tests and proceeded to pour the have necessary materials and field density tests before pouring
concrete without proper approval. The road collapsed after a typhoon, concrete on the roads; and even proceeded to pour concrete without
and investigations were conducted as to the handling of government proper approval. (very technical neto, basta long story short pasaway
funds in the project. Respondents Valdez and Adea were Principal si FUCC.)
Engineers of the NHA assigned to oversee FUCC's contract works, and 3.! 11 DEC 1998: FUCC submitted its 2nd Progress Billing with an
they brought up the problem with the Officer-in-Charge (OIC). It was attached Abstract of Accomplishment (covering the period of 1 JUL
agreed that tests would be conducted, and Valdez recommended a much 1998- 30 NOV 1998). This billed the NHA for a total of PHP
lower billing based on his own assessment of FUCC's work (at 16m 50,701,846.80; inclusive of the costs for subbase course on major
PHP, instead of the 50m PHP billing that FUCC provided). roads & minor roads.
4.! The road that was built (leading up to the Project) collapsed after
This prompted FUCC to file administrative cases in the Ombudsman a typhoon, and was reported in three articles in The Philippine Star.
against respondents Valdez & Adea, alleging that the respondents had These articles prompted a series of investigations as to the handling
tried (and failed) to extort money from them, which is why they (Valdez of funds in the project.
& Adea) refused to act on FUCC's 2nd Progress Billing. Valdez & Adea 5.! 12 JAN 1999: NHA-Contractors held a meeting, where Valdez
countered that FUCC and their superiors from the NHA were pressuring (respondent) raised the non-compliance by FUCC with the
them (Valdez & Adea) to pass off the collapse of the road as due to specifications of the Project, specifically the use of CTBC (see #1, a)
natural causes, and to justify payments that were made outside of the instead of the subbase course. Though the Officer-in-Charge of the
specifications in the project. The Ombudsman found Valdez & Adea Project said that the practice of using CBTC was acceptable (and
guilty of extortion and dismissed them from service. Upon petition in most advantageous during rainy season), it was agreed that tests
the CA, however, the Ombudsman decision was reversed because it would be conducted to find out of the constructed roads met the
lacked substantial evidence. acceptable standard. Valdez also later recommended to the OIC that
based on NHA's own Abstract of Physical Accomplishment, only
The Supreme Court dismissed FUCC & NHA's petitions, and ruled that PHP 16,342,226.23 should be paid to FUCC.
there was no substantial evidence to warrant the termination of Valdez 6.! 29 MAR 1999: FUCC filed an administrative complaint against
& Adrea from employment. Although rules of evidence are not respondents Valdez & Adea in the Office of the Ombudsman, on the
controlling in administrative cases, evidence must still be substantial for grounds of dishonesty, grave misconduct, gross neglect of duty,
orders and decisions to be justified. and conduct prejudicial to the best interest of the service.
7.! FUCC alleged that Valdez & Adea tried to extort money from them,
DOCTRINE: While rules of evidence prevailing in courts of law and but because of FUCC's refusal, Valdez & Adea refused to act on the
2nd Progress Billing & to officially document various variation orders implementing the Ombudsman decision of 13 Jan 2000 (see # 8).
despite instructions by their (Valdez) superiors. 18.! 28 FEB 2002: CA REVERSED the Ombudsmand's decision,
8.! FUCC also alleged that Valdez & Adea consistently arrived late at finding that the FUCC's administrative complaint lacked
the project side; used for personal purposes the service vehicles substantial evidence. The administrative cases were dismissed.
leased to it by the NHA; and that they used the project site as their 19.! FUCC's MR was DENIED.
private gun firing range. 20.! Because the administrative cases were dismissed, the CA also
9.! In response, Valdez & Adea filed a Joint-Counter Affidavit, alleging dismissed the NHA petition (see #9, a) for being moot and academic.
that the complaint was instituted to coerce them into recommending 21.! FUCC appealed the CA decision (see #11), while NHA appealed the
the full payment of the 2nd Progress billing (worth 50m), and to force CA decision which dismissed their petition (see #11, a; #9, a). The
them to help the NHA and FUCC in covering up the investigations Supreme Court consolidated the two cases in a Resolution dated 16
on the project (see #3). JUL 2003.
10.! Valdez & Adea likewise alleged that the Project's OIC (Raner) &
NHA's General Manager (Leynes) pressured them to pass off the ISSUE/s:
collapse of road as due to natural causes; and to justify payment on 1.! Whether or not FUCC had substantial evidence for the petitions to
the works done outside of the specifications. prosper against respondents Valdez & Adea? – NO. There was no
11.! 8 AUG 1999: A preliminary conference was held and respondents substantial evidence to warrant the dismissal of Valdez & Adea. The
manifested that they were foregoing the conduct of a formal hearing petitions cannot prosper.
& were submitting the case for resolution on the basis of the
available evidence on record. 30 AUG 1999: Ombudsman limited RULING: IN SUM, FUCC having failed to support its charges against
the issues of the case & ordered the parties to submit their respective respondents with substantial evidence, the Court of Appeals did not err in
memoranda. reversing the Ombudsman decision and accordingly dismissing the
12.! 13 JAN 2000: The Ombudsman absolved Valdez & Adea of administrative complaint against respondents to thus render NHA's petition
negligence in acting on FUCC's 2nd Billing, but found them liable in G.R. No. 157505 moot and academic. WHEREFORE, the petitions are
for extortion and using the vehicles leased to NHA for personal DENIED.
use. Valdez & Adea were dismissed from service.
13.! Valdez & Adea wrote a letter to NHA informing them of their intent RATIO:
to file an MR to the OMB, and that pending the finality of the case, 1.! In administrative proceedings, the complainant has the burden of
they had the right to remain in office. The letter reached the NHA on proving with substantial evidence the allegations in the complaint.
15 Feb 2000, and the next day Valdez & Adea received a Memo While rules of evidence prevailing in courts of law and equity shall
dated 14 Feb 2000 which effectively terminated them from not be controlling, it does not mean that orders in administrative
employment. proceedings can be justified without basis in evidence having
14.! Valdez & Adea filed in the RTC QC a complaint against NHA, Gen. rational probative force.
Manager Leynes, and NHA HR Dep't Manager Seraspe, for 2.! Ombudsman found Valdez & Adea liable for extortion based only on
inkunction with application and prayer for the issuance of the affidavits of FUCC's witnesses, holding that cases of extortion
preliminary prohibitory injunction and/or a TRO. depend on the credibility of the complainant/s' testimony, because
15.! TRO & preliminary prohibitory injunction was issued. NHA filed a only the participants can testify to their occurrences.
petition in the CA against the RTC judge & respondents, for a.! But the records show that Valdez recommended that FUCC
certiorari and prohibition with prayer for the issuance of a writ of be paid 16m only because he found that FUCC failed to lay
preliminary injunction and TRO. subbase (and used CBTC instead) in accordance with the
16.! Valdez & Adea filed an MR with the Ombudsman, which was specifics of the project.
denied. They petitioned the case to the CA. b.! FUCC itself admitted not having laid subbase, even when it
17.! The CA issued a TRO, enjoining the Ombudsman and the NHA from charged NHA for 50m. FUCC claims that NHA approved
the use of CBTC, although there is no evidence other than its
own letters to NHA, stating its intention to use CTBC.
3.! As to the charge that Valdez & Adea used NHA vehicles for
personal purposes, it was unsupported by substantial evidence.
Though Valdez' signature appears on the entries of the logbooks of
the trips made by these vehicles, it does not necessarily mean he or
Adea took the trips; this could have been a mere attestation to the
authenticity of the trips. FUCC was also unable to refute the claim.

Вам также может понравиться