076551C 000D PP 813 G 1/38
TECNICAS REUNIDAS SAMSUNG ENGINEERING
The present document or drawing is property of THE BAHRAIN PETROLEUM OWNER B.S.C. (CLOSED) (BAPCO) and shall not, under any circumstances, be totally or partially, directly or indirectly, transferred, reproduced, copied, disclosed or used, without its prior written consent, for any purpose and in
TTSJV W.L.L. – Riffa AlHajiyat – Blk. 939, Rd. 3901, Bldg 98, Flt. 33 – Kingdom of Bahrain
The present document or drawing is property of THE BAHRAIN PETROLEUM OWNER B.S.C. (CLOSED) (BAPCO) and shall not, under any circumstances, be totally or partially, directly or indirectly, transferred, reproduced, copied, disclosed or used, without its prior written consent, for any purpose and in
INDEX
1 GENERAL.................................................................................................................................. 3
1.1 Scope .................................................................................................................................. 3
1.2 Definitions ........................................................................................................................... 3
1.3 Reference Documents ........................................................................................................ 4
1.4 Acronyms ............................................................................................................................ 5
2 TESTING ACTIVITIES ............................................................................................................... 5
2.1 General ............................................................................................................................... 5
2.2 Test Package (Engineering Phase) .................................................................................. 5
2.2.1 Test Package Folder (TPF) ............................................................................................. 6
2.2.2 Test Package Flow Chart ................................................................................................ 6
2.2.3 Test Package Folder management ................................................................................. 6
2.2.4 Test Package Folder issue .............................................................................................. 7
2.3 Test Preparation (Construction Phase) ............................................................................ 7
2.3.1 Punch Listing ................................................................................................................... 8
2.3.2 QC Reviewing ................................................................................................................. 9
2.3.3 Test Preparation .............................................................................................................. 9
2.4 Test Execution (Construction Phase) ........................................................................... 14
2.4.1 Test Authorization ....................................................................................................... 14
2.4.2 Service Test ................................................................................................................. 15
2.4.3 Visual Inspection Test ................................................................................................ 15
any way other than that for which it is specifically furnished or outside the extent of the agreed upon right of use.
TTSJV W.L.L. – Riffa AlHajiyat – Blk. 939, Rd. 3901, Bldg 98, Flt. 33 – Kingdom of Bahrain
Project N° Unit Document Code Serial N° Rev. Page
076551C 000D PP 813 G 3/38
TECNICAS REUNIDAS SAMSUNG ENGINEERING
1 GENERAL
1.1 Scope
1- This procedure defines OWNER, CONTRACTOR and SUBCONTRACTOR duties and
responsibilities on Piping Pressure Test preparation, execution, and reinstatement.
3- This procedure refers to the Project Specification and Codes listed below in the para.
1.3, giving additional requirements and defining the Management of the Piping Pressure
Test and related Test Flow Diagram.
4- This procedure does not apply the piping services such as HVAC & plumbing and all
piping systems under Building Quality Control Plan, and sewer (under Civil Quality Control
Plan).
5- In the case of conflict and or discrepancies with other applicable documents, the most
stringent requirement shall be applied. Meanwhile, with reference with coordination matters,
this procedure will lead the job.
1.2 Definitions
Pressure Test:
o Hydrostatic Leak Test: a pressure test, that uses water or another approved
liquid as test medium, to verify the integrity of the piping system for service at
design pressure.
o Pneumatic Leak Test: a pressure test that uses air or another compressed gas
as test medium.
TTSJV W.L.L. – Riffa AlHajiyat – Blk. 939, Rd. 3901, Bldg 98, Flt. 33 – Kingdom of Bahrain
Project N° Unit Document Code Serial N° Rev. Page
076551C 000D PP 813 G 4/38
TECNICAS REUNIDAS SAMSUNG ENGINEERING
Other Test
o Service Test: a pressure test to prove the integrity of the piping system using
the service fluid at the maximum attainable operating pressure.
o Visual Inspection Test: Piping System visually examined when the piping is
operating at atmosphere conditions such as vent, drain and piping downstream
of pressure relieving devices that discharge directly to the atmosphere.
This procedure refers to the latest edition and Addenda of the following codes, standards
and specifications.
TTSJV W.L.L. – Riffa AlHajiyat – Blk. 939, Rd. 3901, Bldg 98, Flt. 33 – Kingdom of Bahrain
Project N° Unit Document Code Serial N° Rev. Page
076551C 000D PP 813 G 5/38
TECNICAS REUNIDAS SAMSUNG ENGINEERING
1.4 Acronyms
2 TESTING ACTIVITIES
2.1 General
The whole Pressure Test execution is split in several main activities and phases, as follows:
Before the Pressure Test Campaign begin, all equipment and necessary materials, e.g.
manifolds, blind flanges, other fittings etc., shall be inventoried and offered to Contractor
inspection to confirm the suitability, including the calibration certificates according to
SUBCONTRACTOR Calibration Procedure. The material availability assessment shall
confirm the schedule.
All activities related to the hydrotest shall be coordinated by the Test Pack Coordinator
any way other than that for which it is specifically furnished or outside the extent of the agreed upon right of use.
(TPC). The TPC will be responsible to follow up all working phases such as:
Coordination of the Engineering, Quality Control, and Construction team,
Coordination of the signature of the involved personnel on TP Tracking Sheet,
Coordination of the activities of punch list and related clearance,
Updating the status of test packs,
Authorization of the Pressure Test,
Authorization of the Reinstatement,
Authorization of control/safety valve reinstallation,
Authorization of Instruments/Components reinstallation,
Clearance and Closure of the Test Pack Folder,
Both CONTRACTOR and SUBCONTRACTOR will appoint a Test Pack Coordinator in their
organization.
Testpackage coordinators shall be experienced Construction professionals, with sufficient
knowledge, expertise and organizational skills to effectively execute the duties of the role
TTSJV W.L.L. – Riffa AlHajiyat – Blk. 939, Rd. 3901, Bldg 98, Flt. 33 – Kingdom of Bahrain
Project N° Unit Document Code Serial N° Rev. Page
076551C 000D PP 813 G 6/38
TECNICAS REUNIDAS SAMSUNG ENGINEERING
The first page of the Folder shall be the Test Package Flow Chart that shall collect all
signatures of the nominated representative of the work phases according to the defined and
planned Test Pack work sequence.
The TP Folder will circulate among all personnel in charge of review or punching.
At care of the TP Coordinator the original TP folder will be transmitted to the appointed
personnel.
To facilitate the coordination of the TP Folders and the pressure testing activities the
SUBCONTRACTOR, CONTRACTOR, and OWNER personnel will attend the daily
pressure testing coordination. Purpose of the meeting is to review the schedule of pressure
testing activities, based on the follow up of the activities previously scheduled.
TTSJV W.L.L. – Riffa AlHajiyat – Blk. 939, Rd. 3901, Bldg 98, Flt. 33 – Kingdom of Bahrain
Project N° Unit Document Code Serial N° Rev. Page
076551C 000D PP 813 G 7/38
TECNICAS REUNIDAS SAMSUNG ENGINEERING
1- Before issue the TP Folder for CONTRACTOR review, the SUBCONTRACTOR will
identify the complete interconnected piping (Testing Circuit) to be tested based on the Plant
System prepared by CONTRACTOR.
2- The test limits will be shown in the P& Id’s and the position of all temporary testing blinds
for blind-off will be red marked on the ISO.
3- The P& Id’s and ISO (red marked up copy) attached in the TP Folder must be the latest
revision.
4- The lines included in the test shall be listed in the form QCF W13 suitable for test
pressure record.
6- After review of the TP Folder, the engineering of the CONTRACTOR will sign the
tracking sheet for acceptance or comments.
any way other than that for which it is specifically furnished or outside the extent of the agreed upon right of use.
7- In case of the comment, the SUBCONTRACTOR will revise and re-issue the TP Folder.
1- Once the construction of the piping system to be tested is completed and the TPF has
been issued and reviewed by the piping engineer, the SUBCONTRACTOR,
CONTRACTOR and OWNER should start the actions needed before test execution, that
are:
Punch Listing,
QC reviewing,
Test Preparation,
2- During the daily meeting for the coordination of the whole testing activities, the Test Pack
Coordinator will assign to the inspectors/supervisors the TP Folders to be punched &
reviewed, and those to be set up for test execution.
TTSJV W.L.L. – Riffa AlHajiyat – Blk. 939, Rd. 3901, Bldg 98, Flt. 33 – Kingdom of Bahrain
Project N° Unit Document Code Serial N° Rev. Page
076551C 000D PP 813 G 8/38
TECNICAS REUNIDAS SAMSUNG ENGINEERING
1- Once the construction is completed a jointly walk through of the lines pertaining to the
same Test Pack/Test Circuit should be performed by SUBCONTRACTOR, CONTRACTOR
and OWNER Supervisor or Inspectors.
Purpose of this walk through is to verify the construction against the Iso’s and P&Ids
2- All activities not completed or to be rectified, as result of the walk through, shall be listed
in the QC Form PL10 (See Appendix 4.4).
The punched items shall be managed through the QC Form PL10 up to the Test Pack
Folder close-out. through EasyPlant database).
4- The following reinstatement actions shall not be classed as punch listing because of
under Precommissioning management, such as:
Line cleaning.
Line Leak Test.
Car Seal installation
Valve Lock Open/Close.
Spring Hanger Pin removal & setting.
Orifice Plate installation. (FE, RO, FO)
Rupture/Burst Disk installation
Corrosion Probes installation.
Insulation Kit installation for Cathodic Protection.
TTSJV W.L.L. – Riffa AlHajiyat – Blk. 939, Rd. 3901, Bldg 98, Flt. 33 – Kingdom of Bahrain
Project N° Unit Document Code Serial N° Rev. Page
076551C 000D PP 813 G 9/38
TECNICAS REUNIDAS SAMSUNG ENGINEERING
2.3.2 QC Reviewing
CONTRACTOR QC shall release the piping circuit identified into the TPF as ready for
test.
Warning 1: Use of the closed block valves (gate, globe, plug, ball to isolate
equipment or piping sections) shall be avoided, unless it is confirmed by
CONTRACTOR engineering and OWNER approval that the involved valves are able
TTSJV W.L.L. – Riffa AlHajiyat – Blk. 939, Rd. 3901, Bldg 98, Flt. 33 – Kingdom of Bahrain
Project N° Unit Document Code Serial N° Rev. Page
076551C 000D PP 813 G 10/38
TECNICAS REUNIDAS SAMSUNG ENGINEERING
to withstand the testing pressure value. In that case, written authorization must be
attached to the test pack folder.
Validation: the SUBCONTRACTOR will provide the material test certificate and
calculation for thickness verification/acceptance by CONTRACTOR engineering
department.
Welding: the SUBCONTRACTOR will issue the applicable WPS with a suitable
Preheating/Post-heating of nozzle welding. The welding joint shall be verified by
PT/MT. A RFI shall be issued.
3- Gasket & Bolting - The SUBCONTRACTOR for each piping system to be tested shall
identify all bolted connections and issue a “Gasket installation and bolting torque
verification” list (QC Form BTC 01) to ensure that in each bolted connection has been
any way other than that for which it is specifically furnished or outside the extent of the agreed upon right of use.
installed the right final gasket and the permanent bolts are tightened according to 000-L-
MST-50003-001 and BMPS-L14 or torque/tension value defined by the Engineering.
TTSJV W.L.L. – Riffa AlHajiyat – Blk. 939, Rd. 3901, Bldg 98, Flt. 33 – Kingdom of Bahrain
Project N° Unit Document Code Serial N° Rev. Page
076551C 000D PP 813 G 11/38
TECNICAS REUNIDAS SAMSUNG ENGINEERING
installation and torque filling and signing off the QC Form BTC 01 already initialized
by the SUBCONTRACTOR.
4- Vent & Drain - The SUBCONTRACTOR in addition to the process vent & drain as
requested by the P &Id should install testing vent & drain, as needed:
Vents: shall be provided at all high points of the piping system under testing.
Warning 1: High points on associated facilities require vents so that the amount of residual
air in the system during hydro testing can be minimized.
Warning 2: Filling the test system shall only be started after it has been verified that the high
point vent is open.
Warning 1: Low points within the system should be avoided at critical areas such as valves,
sphere toes or branch connections. Pipework should allow free drainage away from dead
any way other than that for which it is specifically furnished or outside the extent of the agreed upon right of use.
Warning 2: Draining shall only be started after it has been verified that the high point vents
are open.
Warning 3: The rate of drainage shall be controlled in respect to the inflow of air to the
testing system to prevent formation of a vacuum or partial vacuum.
Warning 4: Tthe piping system should contain a sufficient number of low point drains to
ensure that no water remains trapped after a hydro-test
TTSJV W.L.L. – Riffa AlHajiyat – Blk. 939, Rd. 3901, Bldg 98, Flt. 33 – Kingdom of Bahrain
Project N° Unit Document Code Serial N° Rev. Page
076551C 000D PP 813 G 12/38
TECNICAS REUNIDAS SAMSUNG ENGINEERING
Subcontractor shall prepare and submit for approval a Calibration procedure for
testing gauges
one test gauge on piping circuit at ground nearby the test pump;
one or more (according to circuit complexity) along the piping circuit in the highest
portion of the line, anyway at the maximum distance from one another.
Warning 1: Pressure test gauges shall have an adequate scale to the test pressure. The
full-scale value shall be in the range of 1.25 to 2 times the required test pressure.
Warning 2: Pressure test gauges shall be calibrated once a month to ensure accurate
readings.
Warning 3: Pressure test gauges shall be identified by means of a tag with pressure test
gauge item and date of last calibration.
6- Testing Fluid - The SUBCONTRACTOR will follow the recommendation given by spec
BMPS-B12 for Testing Fluid. The following minimum actions/consideration should be
taken:
Warning 1: During pressure test, fluid thermal expansion shall be foreseen, and then
precautions shall be taken by SUBCONTRACTOR to avoid overpressure.
Warning 2 after test the water shall not re-used for other Austenitic stainless steel, Duplex
and Inconel 625 piping system, unless the chemical and bacteriological properties are
confirmed by adequate testing and certificates (carried out/issued after previous usage) and
proper storage has been established.
issued.
Warning 4: Lube and seal oil piping shall be hydrotested with its own fluid.
TTSJV W.L.L. – Riffa AlHajiyat – Blk. 939, Rd. 3901, Bldg 98, Flt. 33 – Kingdom of Bahrain
Project N° Unit Document Code Serial N° Rev. Page
076551C 000D PP 813 G 13/38
TECNICAS REUNIDAS SAMSUNG ENGINEERING
Warning 1: temporary supports shall be never welded to pressure retaining piping; bolted -
type temporary support shall be utilized. Whereas welded additional temporary supports will
be needed they will be used only after CONTRACTOR approval; these welds shall respect
the same weld conditions applied to the rest of piping line. Temporary supports should be
identified by yellow and red strips color painting.
Warning 2: temporary supports shall not be removed until after the system has been fully
drained.
proof Load Tested shall be clearly, permanently marked showing the maximum safe working
load.
Check valve - Unless there is a by-pass, the check valve shall be turned to permit
the filling and discharge. Each modified check valve shall be tagged, and such tag
easily identifiable. A record of such modified valves shall be maintained into the
Test Pack as well.
Warning 1: temporary removal of the disc (securely attached to the outside of the body) is
not allowed.
Warning 2: after test the check valve must be re-positioned according to the P & Id with the
final gasket and proper torque.
TTSJV W.L.L. – Riffa AlHajiyat – Blk. 939, Rd. 3901, Bldg 98, Flt. 33 – Kingdom of Bahrain
Project N° Unit Document Code Serial N° Rev. Page
076551C 000D PP 813 G 14/38
TECNICAS REUNIDAS SAMSUNG ENGINEERING
TTSJV W.L.L. – Riffa AlHajiyat – Blk. 939, Rd. 3901, Bldg 98, Flt. 33 – Kingdom of Bahrain
Project N° Unit Document Code Serial N° Rev. Page
076551C 000D PP 813 G 15/38
TECNICAS REUNIDAS SAMSUNG ENGINEERING
2- Plant utility piping in air and inert gases services with a designed pressure and equal to
less than 1035 KPa (ga) (150 psig) should be service tested.
3- CONTRACTOR Engineer will identify piping systems that could be tested as Service
test. The list shall be submitted to OWNER for acceptance.
2- Visual Leak Test shall be done in lieu of Pressure Leak Test for circuits for which
internal lining could be affected by the pressure test or it shall be performed when the
pressure test is carried out before internal lining is applied (e.g. galvanization, FBE, rubber,
etc…) after the installation is completed.
3- The Visual Leak Test shall be performed only after clearance of the punched item list.
4- The Visual Leak Test shall be recorded with the same QC Form W13.
TTSJV W.L.L. – Riffa AlHajiyat – Blk. 939, Rd. 3901, Bldg 98, Flt. 33 – Kingdom of Bahrain
Project N° Unit Document Code Serial N° Rev. Page
076551C 000D PP 813 G 16/38
TECNICAS REUNIDAS SAMSUNG ENGINEERING
2- Joints: The SUBCONTRACTOR will leave all joints un-insulated and exposed for
examination during the test, unless authorized by CONTRACTOR/OWNER according to
ASME B.31.3.
Joints welds that are painted may be hydro/pneumatic tested without paint removal (ASME
B 31.3 clause 345.3.1).
3- Pressure Test: The SUBCONTRACTOR will connect the filling hose from the pressure
generator to the lowest drain point of the system to minimize entrapped air.
Warning 1: The isolation valve shall be closed immediately after the pressure test is
reached and stabilized and the pressure generator shall be disconnected.
Warning 3: The amount of any static head acting in service and in testing must be
considered. (the static pressure caused by the content of the piping during service and/or
testing does not need to be taken into account if it does not increase the stress in the wall by
more than 5%).
Warning 4: In plant areas and shops the test area are marked and warning signs posted to
alert approaching personnel.
4- Test Duration: The final test pressure shall be maintained to permit complete inspection
of all joints for leakage or signs of failure, at least 60 minutes after stabilization.
any way other than that for which it is specifically furnished or outside the extent of the agreed upon right of use.
Warning 1: In case of tests performed during rain period, CONTRACTOR together with
OWNER may, in their unobjectionable opinion, accept or not the testing under execution. In
any case the piping circuit being tested shall remain under pressure, at the testing value,
without the necessity of a further pumping or compression, for a sufficient time (4 hours).
Warning 2: If for justifiable safety reasons underground line piping must be back-filled, the
joints must be 100% radio graphed, otherwise the test shall be a 24 hour recorded test
.
Warning 3 Depressurization will be done slowly and safely after completion of test or
discovery of leaks. Bleed off the system slowly to an approved safe discharge area and
monitor discharge.
5- Test Acceptance: Any connection leaking during a pressure test shall be repaired and
retested to the specified test pressure.
Warning 1: If welds are involved in leaks and/or piping modifications, the entire piping circuit
shall be depressurized, leaks eliminated, NDE performed, certification performed, and the
piping circuit shall be retested.
TTSJV W.L.L. – Riffa AlHajiyat – Blk. 939, Rd. 3901, Bldg 98, Flt. 33 – Kingdom of Bahrain
Project N° Unit Document Code Serial N° Rev. Page
076551C 000D PP 813 G 17/38
TECNICAS REUNIDAS SAMSUNG ENGINEERING
Warning 2: If flanged connections, including those that are part of components (e.g. Valves
body/bonnet and packing), leaks (if the tightening cannot eliminate them), the following shall
be done after hydro test.:
6- De-watering: Disposal of test water shall be in accordance with all local laws/regulations
(see in particular local regulatory wastewater effluent discharge requirements), and the
OWNER's facility emission standards, as stated in the appropriate "Project Specifications”.
After testing, test water shall be recovered, to the extent possible, for reuse, according to
BMPS-B12.
7- Lay-Up: Equipment must be laid-up after hydrotesting, unless it can be ensured that it
will be returned to service within 30 days from the first introduction of hydrotest water to the
system.
Lay-Up procedure shall be developed by SUBCONTRACTOR and submitted to
CONTRACTOR for approval prior the hydrotest campaign.
Remove all water from the circuit. For facilities other than pipes, drain the system
completely, sweep and mop as required to ensure that no visible traces of water remains.
For piping systems, dewatering shall be performed by scraping with a three-or four-cup
displacement scraper (or better) unless system limitation make this option impracticable.
After removal of all water, close the system to prevent the entry of sand or rainwater.
TTSJV W.L.L. – Riffa AlHajiyat – Blk. 939, Rd. 3901, Bldg 98, Flt. 33 – Kingdom of Bahrain
Project N° Unit Document Code Serial N° Rev. Page
076551C 000D PP 813 G 18/38
TECNICAS REUNIDAS SAMSUNG ENGINEERING
Once the test pressure is completed and accepted the SUBCONTRACTOR will proceed
with the following activities before transferring monitoring activities from Construction to
Precommissioning team:
Fully drainage (according to Para 2.4.4 item 4) and air blowing of the piping
system under testing immediately after test completion. Acceptance criteria shall be
any way other than that for which it is specifically furnished or outside the extent of the agreed upon right of use.
Warning 1: special care MUST BE taken on piping system where the material is Austenitic
Stainless Steel (304, 316, and 321), Duplex SS, and Inconel 625. The piping system must
be drained immediately after pressure test is completed and accepted.
Warning 2 piping system drainage shall be certified. The SUBCONTRACTOR will issue a
dedicated RFI to CONTRACTOR.
Warning 1: all seal welds MUST BE PT/MT tested. The SUBCONTRACTOR will issue a
dedicated RFI.
Warning 2: PWHT shall be applied if requested by the applicable job specification (FORM
W09). The SUBCONTRACTOR will issue a dedicated RFI.
TTSJV W.L.L. – Riffa AlHajiyat – Blk. 939, Rd. 3901, Bldg 98, Flt. 33 – Kingdom of Bahrain
Project N° Unit Document Code Serial N° Rev. Page
076551C 000D PP 813 G 19/38
TECNICAS REUNIDAS SAMSUNG ENGINEERING
3 MODIFICATIONS
3.1 Modifications
3.1.1- After the test, modifications of the piping system could be executed.
TTSJV W.L.L. – Riffa AlHajiyat – Blk. 939, Rd. 3901, Bldg 98, Flt. 33 – Kingdom of Bahrain
Project N° Unit Document Code Serial N° Rev. Page
076551C 000D PP 813 G 20/38
TECNICAS REUNIDAS SAMSUNG ENGINEERING
3.1.2- The CONTRACTOR Engineering will issue the QC Form W16 where will be explained
the reasons of the modification and shall define if the modified piping system should be re-
tested and welding, NDE, PWHT & PMI shall be performed according to the job specification,
or the welding joints (if any) shall not re-hydro tested. In this case the welding procedure and
further inspections shall be done according to the point 3.3 “Golden Joint”.
Warning 1: miss-alignment of flange after test on rotating equipment suction and discharge
shall consider as modification or rework, heating and partial welding on full
circumferential weld in order to align shall not permitted.
3.1.3- The SUBCONTRACTOR will issue an addendum to the original Test Package Folder
with the QC Form W16 and all other inspection forms requested by the rework due to the
revision.
3.2.1The CONTRACTOR will issue the list of the Plant Tie-in to be implemented and
recorded, as follows:
ii. Between OWNER and Public Authority: they will be inspected and recorded as per
applicable local rule/authority .
iii. Between OWNER and Others: they will be inspected and recorded such us
golden joint (see the next 3.3) or bolt connection joint (see 2.3.3. 3)
3.3.1 Anytime it is impractical to carry out the pressure test for safety or construction reasons
any way other than that for which it is specifically furnished or outside the extent of the agreed upon right of use.
or other the CONTRACTOR will issue the QC Form W16 to perform the welding and related
NDE (according to Appendix 4.5 and 000-L-MST-50001-001), PWHT & PMI as replacement
of the pressure test to be submitted to OWNER for approval of Golden Joint.
3.3.2 The whole construction (welding and related inspection) must be managed as a Hold
Point and the SUBCONTRACTOR is requested to issue a dedicated RFI for each activity.
3.3.3 The CONTRACTOR and SUBCONTRACTOR will perform the same Precommissioning
activity such us cleaning, blowing, etc… before to proceed with the welding and related
inspections.
The CONTRACTOR will issue the Golden Joint list. The SUBCONTRACTOR will maintain a
separate Golden Joint Folder collecting all inspection QC Form W53 duly filled and signed off
by them and CONTRACTOR QC personnel.
TTSJV W.L.L. – Riffa AlHajiyat – Blk. 939, Rd. 3901, Bldg 98, Flt. 33 – Kingdom of Bahrain
The present document or drawing is property of THE BAHRAIN PETROLEUM OWNER B.S.C. (CLOSED) (BAPCO) and shall not, under any circumstances, be totally or partially, directly or indirectly, transferred, reproduced, copied, disclosed or used, without its prior written consent, for any purpose and in
any way other than that for which it is specifically furnished or outside the extent of the agreed upon right of use.
4 APPENDIX
Unit
000D
TTSJV W.L.L. – Riffa AlHajiyat – Blk. 939, Rd. 3901, Bldg 98, Flt. 33 – Kingdom of Bahrain
Page
21/38
The present document or drawing is property of THE BAHRAIN PETROLEUM OWNER B.S.C. (CLOSED) (BAPCO) and shall not, under any circumstances, be totally or partially, directly or indirectly, transferred, reproduced, copied, disclosed or used, without its prior written consent, for any purpose and in
any way other than that for which it is specifically furnished or outside the extent of the agreed upon right of use.
4.1 APPENDIX
000D
TTSJV W.L.L. – Riffa AlHajiyat – Blk. 939, Rd. 3901, Bldg 98, Flt. 33 – Kingdom of Bahrain
Page
22/38
Project N° Unit Document Code Serial N° Rev. Page
076551C 000D PP 813 G 23/38
TECNICAS REUNIDAS SAMSUNG ENGINEERING
APPENDIX 4.1
(Test pack numbering)
The Test Package shall be identified by the progressive numbering as clarified below.
1 1 1 1 2 2 2 3 3 4 4 4 5 6 6
TTSJV W.L.L. – Riffa AlHajiyat – Blk. 939, Rd. 3901, Bldg 98, Flt. 33 – Kingdom of Bahrain
The present document or drawing is property of THE BAHRAIN PETROLEUM OWNER B.S.C. (CLOSED) (BAPCO) and shall not, under any circumstances, be totally or partially, directly or indirectly, transferred, reproduced, copied, disclosed or used, without its prior written consent, for any purpose and in
any way other than that for which it is specifically furnished or outside the extent of the agreed upon right of use.
4.2 APPENDIX
Unit
000D
TTSJV W.L.L. – Riffa AlHajiyat – Blk. 939, Rd. 3901, Bldg 98, Flt. 33 – Kingdom of Bahrain
Page
24/38
Project N° Unit Document Code Serial N° Rev. Page
076551C 000D PP 813 G 25/38
TECNICAS REUNIDAS SAMSUNG ENGINEERING
1. ENGINEERING PHASE
(preliminary 1st issue)
CONTRACTOR SUBCONTRACTOR
team activity activity
Issue the preliminary TP Folder
Precommissioning Issue the Project System List Define the Test Circuits for each Project System
Engineer Review and sign Issue the Test Package Flow Chart
Engineer Review revision & test limits Issue the P&ID with the identified isolation limits
Engineer Review revision & test limits Issue the ISO with the identified isolation limits
Engineer Review
Hand over Issue the Blind Control Sheet (form BCS 01)
Review
Manager
Review & confirm torque
Engineer Bolt Connection list and torque (form BTC 01)
values
Piping Supervisor Review Pipework after pressure test (form PL10)
(2nd issue)
CONTRACTOR SUBCONTRACTOR
team activity activity
Construction Appoint Test Pack Coordinator Appoint Test Pack Coordinator
Issue the Final TP Folder
Engineer Review and sign
Issue the Test Package Flow Chart
Supervisor Review and sign
Engineer Confirm last revision & test limits Issue the P&Id/ Iso’s with the test limits
Supervisor Review the test limits
Issue the Blind Control Sheet (form BCS
Hand over
Review 01)
Manager
Engineer Review & confirm torque values Bolt Connection list and torque (form
Supervisor Review split between Constr/Precom BTC 01)
Supervisor Review & confirm
Pipework after pressure test (form PL10)
Precommissioning Review & confirm
any way other than that for which it is specifically furnished or outside the extent of the agreed upon right of use.
(punch listing)
CONTRACTOR SUBCONTRACTOR
team activity activity
Supervisor or walk through for line check with OWNER
Pipework before test (PL10)
QC Inspector and list of points “A
Supervisor or Verification and signature of all points Clearance of all points “A”, before
QC Inspector “A” cleared testing
Supervisor or
Sign the Test Package Flow Chart Sign the Test Package Flow Chart
QC Inspector
TTSJV W.L.L. – Riffa AlHajiyat – Blk. 939, Rd. 3901, Bldg 98, Flt. 33 – Kingdom of Bahrain
Project N° Unit Document Code Serial N° Rev. Page
076551C 000D PP 813 G 26/38
TECNICAS REUNIDAS SAMSUNG ENGINEERING
(QC reviewing)
CONTRACTOR SUBCONTRACTOR
team activity activity
Review the completeness of the TP Issue the TP Folder according to QC Form
Quality Control
folder against the QC Form W510 W510
Issue the welding map updated with the
Quality Control Welding completed and accepted
last ISO revision(red marked up copy)
Confirm Welding are completed and Declare the Welding are completed and
Quality Control
accepted accepted
Confirm that NDE completed, Declare the NDE completed, accepted, and
Quality Control accepted, and verified against the level verified against the level control class (QC
control class (QC Form W09) Form W09)
Confirm that PWHT/HT completed, Declare the PWHT/HT completed,
Quality Control accepted, and verified against the level accepted, and verified against the level
control class (QC Form W09) control class (QC Form W09)
Confirm that PMI and traceability Declare the PMI and traceability
completed, accepted, and verified completed, accepted, and verified against
Quality Control
against 000-B-MST-50003-001 000-B-MST-50003-001 53 (included
(included instruments) instruments)
Review that QC Form WHS completed Issue the QC Form WHS completed and
Quality Control
and signed signed
Review that Shop fabrication & related Issue the Shop fabrication & related QC
Quality Control
QC Forms completed and signed Forms completed and signed
Review that all other QC Forms/ and Issue the all other QC Forms and
Quality Control
certificates completed and signed certificates completed and signed
Quality Control Sign the Tracking Sheet (form W510) Sign the Tracking Sheet (form W510)
(test preparation)
CONTRACTOR SUBCONTRACTOR
team activity activity
Verification of proper Pressure Testing Installation of proper Pressure Testing
Supervisor
Manifold against the Pressure Test Manifold against the Pressure Test
any way other than that for which it is specifically furnished or outside the extent of the agreed upon right of use.
TTSJV W.L.L. – Riffa AlHajiyat – Blk. 939, Rd. 3901, Bldg 98, Flt. 33 – Kingdom of Bahrain
Project N° Unit Document Code Serial N° Rev. Page
076551C 000D PP 813 G 27/38
TECNICAS REUNIDAS SAMSUNG ENGINEERING
Verification of reinstallation,
Reinstallation of all items included
included items listed on form W14B.
Supervisor those listed on form W14B. Signature
Signature of the Test Package Flow
of the Test Package Flow Chart
Chart
Closure of Test pack Folder and
Test Pack Acceptance and signature
Quality Control signature of the Test Package Flow
of the Test Package Flow Chart
Chart
TTSJV W.L.L. – Riffa AlHajiyat – Blk. 939, Rd. 3901, Bldg 98, Flt. 33 – Kingdom of Bahrain
The present document or drawing is property of THE BAHRAIN PETROLEUM OWNER B.S.C. (CLOSED) (BAPCO) and shall not, under any circumstances, be totally or partially, directly or indirectly, transferred, reproduced, copied, disclosed or used, without its prior written consent, for any purpose and in
any way other than that for which it is specifically furnished or outside the extent of the agreed upon right of use.
TTSJV W.L.L. – Riffa AlHajiyat – Blk. 939, Rd. 3901, Bldg 98, Flt. 33 – Kingdom of Bahrain
Page
28/38
Project N° Unit Document Code Serial N° Rev. Page
076551C 000D PP 813 G 29/38
TECNICAS REUNIDAS SAMSUNG ENGINEERING
APPENDIX 4.3
(pneumatic leak test)
1- Precautions
Pneumatic testing involves the hazard of released energy stored in compressed gas.
Particular care must therefore be taken to minimize the chance of brittle failure during a pneumatic
leak test.
Test temperature is important in this regard and must be considered when the designer chooses
the material of construction.
To set down properly all necessary safety precautions, Subcontractor shall evaluate the energy
contained into the pressurized system and shall report all calculation into the Pneumatic
Calculation sheet (for each pneumatic test). The Pneumatic Calculation sheet shall be attached to
the test package folder.
Reference document applicable is BMPS-B12.
The test equipment shall be examined before pressure is applied to ensure that it is tightly
connected.
All items not subjected to the test pressure shall be disconnected or other suitable means.
A pressure relief device shall be provided, having a set pressure not higher than the test pressure
plus the lesser of 345 kPa (50 psi) or 10% of the test pressure.
4- Test Fluid
The gas used as test fluid, if not air, shall be non-flammable and non-toxic.
any way other than that for which it is specifically furnished or outside the extent of the agreed upon right of use.
5- Test Pressure
6- Procedure
The pressure shall be gradually increased until a gage pressure which is the lesser of one-half the
test pressure or 170 kPa (25 psi) is attained, at which time a preliminary check shall be made,
including visual examination of joints in accordance with ASME B 31.3 para. 341.4.1(a).
Thereafter, the pressure shall be gradually increased in steps until the test pressure is reached,
holding the pressure at each step long enough to equalize piping strains.
The pressure shall then be reduced to the design pressure before examining for leakage in
accordance.
TTSJV W.L.L. – Riffa AlHajiyat – Blk. 939, Rd. 3901, Bldg 98, Flt. 33 – Kingdom of Bahrain
Project N° Unit Document Code Serial N° Rev. Page
076551C 000D PP 813 G 30/38
TECNICAS REUNIDAS SAMSUNG ENGINEERING
The leak test shall be maintained for at least 30 min after stabilization, and all joints and
connections shall be examined for leaks.
any way other than that for which it is specifically furnished or outside the extent of the agreed upon right of use.
TTSJV W.L.L. – Riffa AlHajiyat – Blk. 939, Rd. 3901, Bldg 98, Flt. 33 – Kingdom of Bahrain
The present document or drawing is property of THE BAHRAIN PETROLEUM OWNER B.S.C. (CLOSED) (BAPCO) and shall not, under any circumstances, be totally or partially, directly or indirectly, transferred, reproduced, copied, disclosed or used, without its prior written consent, for any purpose and in
any way other than that for which it is specifically furnished or outside the extent of the agreed upon right of use.
4.4 APPENDIX
Unit
000D
TTSJV W.L.L. – Riffa AlHajiyat – Blk. 939, Rd. 3901, Bldg 98, Flt. 33 – Kingdom of Bahrain
Page
31/38
Project N° Unit Document Code Serial N° Rev. Page
076551C 000D PP 813 G 32/38
TECNICAS REUNIDAS SAMSUNG ENGINEERING
APPENDIX 4.4
(Pre-test punch/check list – PL10 )
27 check if support clips, shoes and guides on lines have been correctly installed X
28 check if insulation welded supports are installed X
29 check clearances for insulation between other lines, conduit tubing, equipment X
30 check that the internal weld penetration of all orifice flanges have been ground X
31 check that all process vents & drains are installed X
32 check if temporary vents & drains for testing are required X
check water test certificate (Cl- max 50 ppm for SS material and 250 ppm for CS
33 X
material)
34 check pressure testing gauges calibration is correct X
35 check relief testing valve calibration is correct X
36 check that orifice flanges have required upstream & downstream clearances X
TTSJV W.L.L. – Riffa AlHajiyat – Blk. 939, Rd. 3901, Bldg 98, Flt. 33 – Kingdom of Bahrain
Project N° Unit Document Code Serial N° Rev. Page
076551C 000D PP 813 G 33/38
TECNICAS REUNIDAS SAMSUNG ENGINEERING
Tab. 2: Punch Items which does not hold the circuit pressure test (could not be A Items)
CHECK LIST / ACTION
TTSJV W.L.L. – Riffa AlHajiyat – Blk. 939, Rd. 3901, Bldg 98, Flt. 33 – Kingdom of Bahrain
The present document or drawing is property of THE BAHRAIN PETROLEUM OWNER B.S.C. (CLOSED) (BAPCO) and shall not, under any circumstances, be totally or partially, directly or indirectly, transferred, reproduced, copied, disclosed or used, without its prior written consent, for any purpose and in
any way other than that for which it is specifically furnished or outside the extent of the agreed upon right of use.
4.5 APPENDIX
Unit
000D
TTSJV W.L.L. – Riffa AlHajiyat – Blk. 939, Rd. 3901, Bldg 98, Flt. 33 – Kingdom of Bahrain
Page
34/38
Project N° Unit Document Code Serial N° Rev. Page
076551C 000D PP 813 G 35/38
TECNICAS REUNIDAS SAMSUNG ENGINEERING
APPENDIX 4.5
(Method Statement for Golden Joint)
1- The CONTRACTOR Field Engineer will issue and keep updated the list the Golden Joint (or
closure weld). The Golden Joint could be specified after the piping system pressure test due to
some modification.
2- The Field Engineer on the QC Form W16 (Modification after Test Pressure) will assign the
progressive number GJ XXX when the Golden Joint procedure should be implemented when the
hydrotest repetition of the piping system could be waived. The waiver should be based on:
Safety concerns
Temporary Construction.
Constructability sequence.
NOTE: golden joints are different than joint executed due to modification after pressure test (see
above). SUBCONTRACTOR Engineering should study the configuration of the Piping System and
prepare a list of proposed GJ to be reviewed by CONTRACTOR/OWNER.
Precommissioning activities:
any way other than that for which it is specifically furnished or outside the extent of the agreed upon right of use.
o Inspection related to the activities could not be performed later the welding,
such us cleaning, blowing, or etc…
Construction activities.
4- The SUBCONTRACTOR shall issue the RFI before Precommissioning and before joint fit-up.
TTSJV W.L.L. – Riffa AlHajiyat – Blk. 939, Rd. 3901, Bldg 98, Flt. 33 – Kingdom of Bahrain
Project N° Unit Document Code Serial N° Rev. Page
076551C 000D PP 813 G 36/38
TECNICAS REUNIDAS SAMSUNG ENGINEERING
5- For each Golden Joint, the following inspections shall be always performed and recorded on QC
Form W53:
PT/MT after 2nd pass. (cooling and pre-heating shall be executed according to
applicable WPS and shall be strongly monitored)
Welder ID,
Golden Joint dossier: copy of W 16 only for GJ coming from modifications, P&D red
mark, OWNER approval
TTSJV W.L.L. – Riffa AlHajiyat – Blk. 939, Rd. 3901, Bldg 98, Flt. 33 – Kingdom of Bahrain
The present document or drawing is property of THE BAHRAIN PETROLEUM OWNER B.S.C. (CLOSED) (BAPCO) and shall not, under any circumstances, be totally or partially, directly or indirectly, transferred, reproduced, copied, disclosed or used, without its prior written consent, for any purpose and in
any way other than that for which it is specifically furnished or outside the extent of the agreed upon right of use.
4.6 APPENDIX
Unit
000D
TTSJV W.L.L. – Riffa AlHajiyat – Blk. 939, Rd. 3901, Bldg 98, Flt. 33 – Kingdom of Bahrain
Page
37/38
Project N° Unit Document Code Serial N° Rev. Page
076551C 000D PP 813 G 38/38
TECNICAS REUNIDAS SAMSUNG ENGINEERING
APPENDIX 4.6
(QC Forms applicable list)
LIST
#
QCF rev DESCRIPTION
1 WHS A NDT/PMI/PWHT/HT AND MATERIAL TRACEABILITY SUMMARY
2 V01 A VALVE INSTALLATION INSPECTION
2 W13 A PIPING PRESSURE TEST REPORT
3 PL10 A PUNCH LIST ITEM
4 W14 A DIMENSIONAL CHECK
5 W16 A MODIFICATIONS AFTER PRESSURE TEST (LINE/ISO CHECK REPORT)
6 W18 A HOLIDAY DETECTOR TEST
7 W31A A INSPECTION OF VENTURI, RENSTRICTION ORIFICE AND FLOW ORIFICE
8 W50 A PIPING PREFABRICATION SUMMARY REPORT
9 W 510 A TEST PACK CONTENT
10 PL10 A PIPEWORK AFTER TEST
11 BCS 01 A BLIND CONTROL SHEET
12 BTC 01 A FLANGE PARALLELISM/ALLIGNMENT & STUD BOLT TIGHTENING
13 W53 A GOLDEN JOINT REPORT
From
14 000-L-PQP- - TEST PACKAGE FLOW CHART
50006-001
15 IC 01 A PIPING/EQUIPMENT INTERNAL CLEANING
16 W 31B A REINFORCING PAD PNEUMATIC TEST
17 SS 01 A SLOPE SURVEY REPORT
18 W 53 A GOLDEN JOINT REPORT
19 W 16 A MODIFICATIONS AFTER PRESSURE TEST
20 W 12 A INSPECTION REPORT
21 W 18 A HOLIDAY DETECTOR TEST
22 W 61 A SECTION EXCAVATION & BACKFILLING
23 VARIOUS - FINAL ALLIGNMENT (fre & flanged) AFTER PIPING P.T. (see para: 2.5.1)
any way other than that for which it is specifically furnished or outside the extent of the agreed upon right of use.
TTSJV W.L.L. – Riffa AlHajiyat – Blk. 939, Rd. 3901, Bldg 98, Flt. 33 – Kingdom of Bahrain
PROJECT: BAPCO MODERNIZATION PROGRAM
QUALITY CONTROL FORM W 510 PROJ. No.: 076551C QCF REV. SH. 1 OF 3
SIGNATURE
DATE
TEMPORARY
TPG TEMPORARY PLUG TI
ASSEMBLY WITH
PRESSURE
INDICATOR
QUALITY CONTROL FORM W 510 PROJ. No.: 076551C QCF Rev SH. 3 OF 3
OWNER: BAPCO
INSPECTION REPORT
_________________________________________________________________
TYPE OF INSPECTION
___________________________ CHECK
___________________________
WITH REMARKS
7. ATTACHMENT:
SIGNATURE
DATE
TTSJV W.L.L. – Riffa AlHajiyat – Blk. 939, Rd. 3901, Bldg 98, Flt. 33 – Kingdom of Bahrain
TECNICAS REUNIDAS SAMSUNG ENGINEERING
TYPE OF TEST:
TEST MEDIUM:
TESTING PRESSURE:
MIN TEST PRESSURE/MAX TEST PRESSURE
MINIMUM HOLD TIME WITH TEST CIRCUIT PRESSURIZED
SYSTEM:
SUB-SYSTEM:
REMARKS:
General Note: