Get prepared for the PMP® Exam

Self Assessment Test


75 Free Sample Questions related to the PMP exam after 30 June 2009 (PMBOK® Guide 4th Edition)

“If money is your hope for independence you will never have it. The only
real security that a man will have in this world is a reserve of knowledge,
experience, and ability.”
Henry Ford
Explanations I want to skip the Feedback
explanations
Each question in this self section and go Mailed August 25 2008 by Aarti S. (USA): "Your tips and practice exams were really
helpful and I was able to focus on areas that I was weak at and pass the exam.."
assessment test has one down to the test
best answer. right now Mailed October 17 2007 by Tony C. (Japan): "Thanks, passed the PMP with 67%.
Almost exactly as on your 75 question practice test."
Mailed October 10 2007 by Naji C. (Canada): "I am glad that I did your tests online,
Time to finish the test: 90 Minutes.
the free 75q and the 175 one. The questions helped me pass the exam and really
find gaps in my knowledge. By the way, you are the only one who covered the PTA
There is a timer in the title bar (top of questions. I had on my exam 3 PTA related questions."
most browsers).
Mailed October 10 2007 by Stefano B. (Italy): "I would like to thank you again for
the free and precious support provided by your tests. They were really close to the
Click the dark blue button (below) to reset exam and helped much me and my other 2 colleagues to pass the PMP exam with a
the timer to 00:00:00. good score."
Mailed July 14 2007 by Belinda C. (USA): "I did take the exam and passed it back in
This sample test has been designed to May. I believe that your questions were the closest to prep for the exam."
help you practicing for the current PMP® Mailed March 15 2007 by Dorin V. (Canada): "The sample test was very useful in
exam—based on the PMBOK® Guide 4th evaluating my knowledge prior to the exam and deciding when I was really ready for
Edition. it. I passed the exam on my first attempt with roughly the same percentage as the
sample test. Thank you."

It is also helpful in preparation for other Mailed March 8 2007 by Pam H. (USA): "I only whish I could have found you earlier.
I missed this exam 3 times. I even went through #######'s Boot Camp... a good
project management exams including
course but something went amiss for me when I really saw the questions on the
PMI's CAPM® and PgMP® or CompTIA's test ... I have not been studying these type of questions given to me from the Boot
Project+. Camp."
Mailed January 8 2007 by Joseph K. (UK): "I did the test and had 54 correct
The passing score (the number of right answers. I then passed the exam. Your questions were a good preparation for the
answers to pass this preparation test) is real thing. "
75%.
Mailed September 12 2006 by Claudia D. (USA): "I just took (and passed) the PMP
exam yesterday. Your test is the closest I have found to the real thing. I was getting
fairly high scores from other practice tests and was quite shocked yesterday by how
Please visit www.pmi.org and navigate to difficult the real exam was."
Mailed May 9 2006 by Rick M. (USA): "I teach an 8 day PMP Prep Course. I have had
over 120 of my students pass the PMP exam over the past 2 years. I have always
encouraged my students to take your exam to test their knowledge."
Mailed April 20 2006 by Walid T. (Canada): "I found some of the questions quite
challenging and requiring more than the allocated 72 seconds to answer ... the
sample test provided a good learning experience."
Mailed January 25 2006 by John C. (USA): "Your test questions are very useful and
helped me assessing where I need to do more."

Mailed August 1 2005 by Stephen L. (New Zealand): "Good questions."


Mailed June 14 2005 by Saurabh V. (India): "The test is the most comprehensive
one that I have seen so far."
to find more information about the PMP
exam. Mailed January 5 2005 by Bob H. (USA): "I passed with an 80%. Your site was quite
helpful and a good benchmark. Thanks!"

Mailed August 26 2004 by David S. (UK): "I can start breathing again, score for the
Visit the author at exam 158/200, thanks for the confidence boost from your test questions!"
- www.oliverlehmann.com (English) or
Mailed June 29 2004 by Nadja V. (Finland): "I took several practice exams. Your
- www.oliverlehmann-training.de (German) exam provided the best reality check both in terms of level of difficulty of the actual
PMP exam and my score on the final exam. Thanks."
Click here for over 2,000 more prep
Mailed Jan 12 2004 by Andrea I. (Italy): "I did the test two days before the exam
questions from various providers. and found it useful and also a good approximation of the real exam question,
compared with other sample tests taken before. Moreover, the result reached was
exactly the same as in the exam (84%)."
PMI® did not participate in the
Test time: 018:43:39 - Total test time: 90 Min. Page 2 of 43
development of this self assessment test Mailed May 05 2003 by Dana P.B. (USA): "I did find the questions helpful. To the
and has not reviewed the content. extent that I passed the exam on my first attempt."

Click here to reset the timer and start the test

See references Marked for review

1. ________ is typically not referred to as a buffer type in Critical Chain project


management.

Resource buffer

Free buffer

Feeding buffer

Project buffer

See references Marked for review

2. A company has to make a choice between two projects, because the available resources in
money and kind are not sufficient to run both at the same time. Each project would take 9
months and would cost $250,000.

1. The first project is a process optimization which would result in a cost reduction of
$120,000 per year. This benefit would be achieved immediately after the end of the
project.

2. The second project would be the development of a new product which could produce
the following net profits after the end of the project:

1. year: $ 15,000
2. year: $ 125,000
3. year: $ 220,000

Assumed is a discount rate of 5% per year. Looking at the present values of the benefits
of these projects in the first 3 years, what is true?

Both projects are equally attractive.

The first project is more attractive by app. 7%.

The second project is more attractive by app. 5%.

The first project is more attractive by app. 3%.


Test time: 018:43:39 - Total test time: 90 Min. Page 3 of 43

See references Marked for review

3. A production process has been defined as part of an industrial equipment manufacturing


project. The process is intended to produce steel bolts with a length of 20 cm. The control
limits are 19.955cm and 20.045cm.

The measurements made at the end of the process yielded the following results:

20.033cm, 19.982cm, 19,995cm, 20.006cm, 19.970cm,


19.968cm, 19.963cm, 19.958cm, 19.962cm, 19.979cm,
19.959cm.

What should be done?

The process is under control. It should not be adjusted.

A special cause should be investigated, the process should be adjusted.

The control limits should be adjusted.

The measuring equipment should be recalibrated.

See references Marked for review

4. Your project management team includes two external consultants each from a different
company. You found that repeated conflicts between the two consultants already slow
down project progress and jeopardize achievement of objectives.

Which stage of team development can be difficult to overcome in such a situation?

Storming from Forming, Storming, Norming, Performing

Panic from Enthusiasm, Panic, Hope, Solution

Kickoff from Assignment, Kickoff, Training, Communicating

Frustration from Direction, Frustration, Cooperation, Collaboration


Test time: 018:43:39 - Total test time: 90 Min. Page 4 of 43

See references Marked for review

5. During a project Earned Value Analysis is performed and gives the following numbers:

EV: 523,000; PV: 623,000; AC: 643,000.

Which results are correct?

CV: +120,000; SV: +100,000

CV: +100,000; SV: +120,000

CV: -100,000; SV: -120,000

CV: -120,000; SV: -100,000

See references Marked for review

6. A project manager spent some days to create a multi-page document which he called
Project charter. The document should have been issued by the project sponsor. The
sponsor found the document outsized and asked for a condensed document.

Which of the following is not normally an element of the Project charter?


The authority level of the project manager

Detailed control account and work package descriptions

The business need that the project was undertaken to address

High-level risks
Test time: 018:43:39 - Total test time: 90 Min. Page 5 of 43

See references Marked for review

7. A document called ____________ is created by decomposing the project scope into


smaller, more manageable elements.

Scope Statement

Network Logic Diagram

Work Breakdown Structure

Requested Change

See references Marked for review

8. Which of the following tools is used to create a Risk Management Plan?

Risk planning meetings

Documentation reviews

Data precision rankings

Diagramming techniques
Test time: 018:43:39 - Total test time: 90 Min. Page 6 of 43

See references Marked for review

9. In order to speed up a project, you made a decision to fast-track a phase currently


performed with five team members and another one which was planned to begin in four
weeks time with another five team members.

Which of the following activities should you do first?

Make sure that all exit criteria of the consecutive phase have been met to ensure the
flow of communications in a team situation which is more complex by a factor of 2.
Make sure that all entry criteria of the previous phase have been met by planning and
performing a phase gate meeting to assess technical aptness.
Make sure that all exit criteria of the previous phase have been met by planning and
performing a phase gate meeting to assess technical performance.
Restructure your team and delegate tasks in order to ensure the flow of
communications in a team with the number of communication channels increased by a
factor of 4.5.

See references Marked for review

10. A project manager needs a certain number of identical valve housings for a power station
project.

He starts with 100 raw items which are made as metal castings. Out of this batch, 15 are
found leaking from micro-porosities in a subsequent pressure test. 6 of these housings
can be recovered by a special sealing process for raw castings.

The 91 housings are then being machined. After this process step 10 machined castings
are found leaking. 3 of these items can also be saved using another sealing process for
machined castings.

The remaining 84 housings are getting mounted to the power plant pipe work. During a
pressure test after this process step it is found that 12 valves are leaking. Out of these a
number of 6 valves can be saved by replacing the sealing rings used.

Finally the project manager has 78 valves which he can use. What is true?

RTY = 0.84

RTY = 0.78

RTY = 0.91

RTY = 0.65
Test time: 018:43:39 - Total test time: 90 Min. Page 7 of 43

See references Marked for review

11. You found the following Earned Value Analysis information for a recently closed out
project:

SPI = 0.7, CPI = 1.0

The project has been cancelled while it was executed. At that time the project was
behind schedule and on budget.
The project's deliverables have all been finished. The project came in behind
schedule but on budget.
The project's deliverables have all been finished. The project came in ahead of
schedule but on budget.
The project's deliverables have all been finished. The project came in on schedule
but over budget.

See references Marked for review

12. Which should be included in a Requirements management plan?

The document should trace requirements to project scope / WBS deliverables.

It should describe how requirements activities will be planned, tracked, and reported.

It should trace high-level requirements to more detailed requirements.

It should trace requirements to business needs, opportunities, goals, and objectives.


Test time: 018:43:39 - Total test time: 90 Min. Page 8 of 43

See references Marked for review

13. In a traditionally drawn decision tree, a circle represents


___________.

a chance to which no Expected Monetary Value can be assigned so that a likely pay-
off can not be shown.
a decision to which no Expected Monetary Value can be assigned so that a likely pay-
off can not be shown.
a chance to which an Expected Monetary Value may be assigned to calculate the
most likely pay-off.
a decision to which an Expected Monetary Value may be assigned to calculate the
most likely pay-off.

See references Marked for review

14. A project management team has subcontracted work to a service company. Which of the
following tools is the best choice to assure that this company will be able to meet the
quality requirements of the project?

Quality audit

Deliverable inspection

Fixed price contract

Service level agreement


Test time: 018:43:39 - Total test time: 90 Min. Page 9 of 43

See references Marked for review

15. With your team you are using judgment from subject matter experts to identify and
analyze project risks. There is a small number of experts available, but some of them
have long been in a teacher-student or manager-assistant relationship.

Which of the following techniques can ensure best that there is no dominating opinion
during an expert review?

Peer review

SWOT analysis

Delphi technique

Monetary value calculation

See references Marked for review

16. You are running a project for a customer based on a cost reimbursable contract with the
following terms:

Target costs: $ 1,000,000


Fixed fee: $ 100,000
Benefit/cost sharing: 80% / 20%
Price ceiling: $ 1,200,000

Which is the PTA (= Point of total assumption, Break point) of the project?

$1,300,000

$1,500,000

$80,000

$1,125,000
Test time: 018:43:39 - Total test time: 90 Min. Page 10 of 43

See references Marked for review

17. During execution of a project which is performed for a customer on a T&M (Time and
Material) contract base, a new project manager is taking over the assignment.

He discovers that two members assigned to the project have charged time without
performing any work for the project customer. Upon further investigation, he determines
that this occurred because there have been no other project assignments open for these
employees. The customer is unaware of these facts.

What should the project manager do?

Try to find some productive work for these staff members in the project and leave
them on the team.
The best thing is to do nothing. The customer will not realize the problem anyway.

Try to find a responsible person for the over-assignment who can be made
accountable.
Take the two people off the team immediately and arrange for the refund of the
excess charges to the customer.

See references Marked for review

18. In the following network logic diagram start dates are defined as early morning, finish
dates are evening.

If tasks are scheduled to begin at early start date, what is true?

Activity B has a free float of 10 d.

Activity B has a total float of 10 d.

Activity A has a free float of 10 d.

Activity A has a total float of 10 d.


Test time: 018:43:39 - Total test time: 90 Min. Page 11 of 43

See references Marked for review

19. Your project is executed with a globally spread virtual team. The project progress has
been found to be too slow. Which measure is most likely to immediately speed up the
project?

Technical training for all team members

Daily phone conferences and detailed reporting

A team meeting at a location convenient to all team members

Collocation of team members at a suitable place

See references Marked for review

20. A project management team wants to procure some customized products which are
available in identical grade and quality from many vendors. What should be included in
the procurement package to ensure that their offers will be comparable?

A statement of work describing the needs of the project in sufficient detail to enable
vendors to make suitable proposals
A statement of work specifying attributes and metrics of the requested deliverables in
detail to allow vendors submission of bids
The approved project scope statement, the WBS which should be broken down to
Work Package level and the WBS dictionary
The risk management plan and the reports from those risk management reviews
which have been made so far
Test time: 018:43:39 - Total test time: 90 Min. Page 12 of 43

See references Marked for review

21. Which of the following becomes increasingly important in a virtual team environment?
Requirements engineering

Communication planning

Formal procurements closure

Network diagramming

See references Marked for review

22. You are assigned as the project manager to a project which is executed for a customer
under FP contract. Your customer informed you this morning that they insist on certain
"refinements" of the project scope.

You agree that the requested actions make really sense to the project, but believe that
they constitute a major change increasing the project scope. What should you do next?

Accept the request of the customer. Diligently document the additional costs and
working hours spent by yourself and the team on the implementation of the change
and invoice these to the customer at appropriate rates.
Perform Earned Value Analysis to assess the current status of the project and get all
the numbers you need to communicate the case to the Change Control Board which
then will have to make the best decision regarding the customer request.
Check the contract, the project charter, the scope statement and other documents
related to the project and the contract. Implement ADR (Alternative Dispute
Resolution) procedures if the conflict cannot be resolved otherwise.
Talk to the project sales department and find a joint solution with them how to best
reject the request considering the commercial and strategic value of the customer to
the organization you are working for.
Test time: 018:43:39 - Total test time: 90 Min. Page 13 of 43

See references Marked for review

23. During a project the scope of a product purchased on a cost reimbursable contract has
increased. The contract defines a fixed fee to cover the contractor‘s indirect costs and
allow a profit. What is most likely to be true?

The contractor‘s indirect costs will increase and the customer‘s payment for them will
increase, too.
The contractor‘s indirect costs will increase but the customer‘s payment for them will
not increase.
The contractor‘s indirect costs will not increase but the customer‘s payment for them
will.
Neither the contractor's indirect costs nor the customer‘s payment for them
will increase.

See references Marked for review

24. A project management team is evaluating the causes that might contribute to
unsatisfactory performance and quality. Which of the following statements is not true?

Normal process variation is attributable to random causes and sometimes also called
"white noise".
Special causes are easier to predict and handle than random causes (also called
common causes).
Special causes are unusual events which are difficult to foresee and mostly produce
outliers.
A process can be optimized to limit the bandwidth of variations due to random
causes.
Test time: 018:43:39 - Total test time: 90 Min. Page 14 of 43

See references Marked for review

25. You are performing a project management audit in your company and find that most of
the project plans are neither consistent nor up-to-date.

Which of the following statements is not true?

Projects should never be executed without a valid, updated and working project
management plan.
The consistency of the project management plan is secondary because it is only the
results that matter.
A great deal of effort is required to develop and update a project plan, but the
benefits include less pressure on all stakeholders and a resulting product that will
satisfy the requirements.
Poor planning and insufficient updating of project management plans are common
reasons for cost and time overruns.

See references Marked for review

26. You want to perform active risk acceptance. What should you do?

Create contingency reserves in resources, money and time.

Develop a plan to minimize impact in case that an identified risk occurs.

Develop a plan to minimize the probability of occurrence for identified risks.

Make additional resources available to speed up the project.


Test time: 018:43:39 - Total test time: 90 Min. Page 15 of 43

See references Marked for review

27. A project manager made 3-point estimates on a critical path and found the following
results:

Assuming ±3 Sigma precision level for each estimate, what is the standard deviation of
the allover path?

App. 4.2 days

App. 5.2 days

App. 6.2 days

You can not derive the path standard deviation from the information given.

See references Marked for review

28. When do bidder conferences normally take place?

After the contract has been awarded to keep alternatives open.

After submittal of bid or proposal, but before contract award.

Prior to the submittal of a bid or proposal by the bidder.

After technical meetings with bidders to discuss contract requirements.


Test time: 018:43:39 - Total test time: 90 Min. Page 16 of 43

See references Marked for review

29. What is defined by control limits?

A measuring instrument solely used to describe process capability. The process is


found capable if the ±3 Sigma range is exceeded by not more than 0.3% of a tested
sample lot.
The limits of the six Sigma area on either side of a control chart to plot measured
values; data found outside the area are out of specification and can lead to rejection
of an entire batch.
The area consisting of typically three standard deviations on either side of a mean
value of a control chart to plot measured values found in statistical quality control
The area consisting of typically three standard deviations on either side of a mean
value of a control chart to plot measured values found in quality assurance

See references Marked for review

30. The Scope baseline consists of what?


Scope statement, WBS, and WBS dictionary

Cost baseline, Quality baseline and Schedule baseline

Configuration management plan and Configuration identification document

Procurement statement of work and Project scope statement


Test time: 018:43:39 - Total test time: 90 Min. Page 17 of 43

See references Marked for review

31. Activity 1 has a duration of 20 days, Activity 2 of 10 days, Activity 3 of 5 days and
Activity 4 of 6 days.

What is the minimum total duration between the Milestones A and B?

36 days

37 days

39 days

42 days

See references Marked for review

32. Which tool and technique is used to Create WBS and Define activities?

Nominal group technique

Human resource assignment

Brainstorming

Decomposition
Test time: 018:43:39 - Total test time: 90 Min. Page 18 of 43

See references Marked for review

33. Which of the following statement(s) regarding whistle-blowing is/are not true?

a. It is a term used to define an employee’s decision to disclose information on


unethical, immoral or illegal actions at work to an authority figure.
b. An employee should always discuss the matter with people external to the company
before following the "chain of command" and discuss it with the immediate
superior.
c. The consequences of whistle-blowing are often extreme and include possible being
branded as having bad judgment, firing, civil action and imprisonment.
d. Carefully considered whistle-blowing can lead to the end of unethical business
practices.
a

b, c

c, d

See references Marked for review

34. Which of the following statements is not true?

Attribute sampling is the process of assessing whether results conform to


specifications or not.
Prevention means keeping errors out of the process by applying actions before the
process starts changing its input.
Variables sampling means that the result is classified into one of the 3 categories:
"acceptable" - "acceptable after rework" - "rejected".
Inspection is often mainly done to keep errors out of the hands of the customer
instead of as a means of process control.
Test time: 018:43:39 - Total test time: 90 Min. Page 19 of 43

See references Marked for review

35. Which statement describes best why you should document assumptions?

Assumptions might prove to be wrong. Knowing which assumptions were


incorrect allows baseline adjustments in case of project crisis.
Assumption analysis is a valuable tool and technique to explore the validity of
assumptions during risk identification.
Assumptions limit the project management team's options for decision making
because they can not be controlled by the team.
In case of schedule or budget overruns, the documentation of assumptions supports
a clear assignment of responsibility.

See references Marked for review

36. Which is normally not regarded as an element of Cost of quality?

Prevention costs

Maintenance cost

Appraisal costs

Failure costs
Test time: 018:43:39 - Total test time: 90 Min. Page 20 of 43

See references Marked for review

37. You have recently been assigned as a project manager to a new B-O-T (Build, Operate,
Transfer) capital project. Reviewing the initial documentation you found out that it has
been calculated with a very small margin during operations of its product for the
shareholders. What should you do?

As you are not responsible for lifecycle costing, you don't have to worry about
operation profits. Focus on project costs from initiation through handover.
Ensure maximum profits by buying the best and cheapest items, components and
modules - potentially from a big number of different suppliers - and integrating them.
Create a realistic plan broken down to a sufficient level of detail. Perform all risk
management processes. Ensure real-time communications with all stakeholders.
Try to get a second project manager assigned to share decision making and
accountability to shareholders with the person.

See references Marked for review

38. A project is handled by departments of an organization and expedited by a project


coordinator. Which of the following statements is most likely to be true?

The performing organization is a weak matrix.

The performing organization is doing "management by projects".

The performing organization is a strong matrix.

The performing organization is projectized.


Test time: 018:43:39 - Total test time: 90 Min. Page 21 of 43

See references Marked for review

39. You are project manager in a global project with a team consisting of people from various
countries. What can you try to prevent misunderstandings due to cross-cultural
differences?

Use all communication methods available that are suitable for the team and follow up
in writing when communicating verbally. Remember that cultural and individual
diversity may help project teams solving unforeseen problems during the course of
the project.
When you are about to form a team for your project, keep in mind that some cultures
are developed, others are more primitive. Some have values, some not. You should
consequently avoid choosing members from countries with cultures that are not
similar to your own.
Cultural dilemmas can prevent any project from being successful. They should
therefore be smoothed or suppressed so as to make sure that they cannot disrupt
project work. Your effort should concentrate on communication that can help reach
that goal.
As norms regarding communication habits differ significantly across various cultures,
communicating between people from different countries should only be done using
language. The nonverbal dimension simply bears too many risks.

See references Marked for review

40. Which statement on conflicts is true?


Conflict resolution should focus on people, not issues.

Conflict is natural and forces a search for alternatives.

Conflict should always be handled in private and not in the team.

Too much openness is a common cause of conflict.


Test time: 018:43:39 - Total test time: 90 Min. Page 22 of 43

See references Marked for review

41. A change request in a project has been rejected some weeks ago. Yesterday, the project
manager found out that it nevertheless has been implemented by the team members,
who knew of the change request, but not of the rejection.

In order to avoid such a situation, Rejected change requests should be consistently


communicated to stakeholders through which process?
Report performance

Verify scope

Perform integrated change control

Monitor and control risks

See references Marked for review

42. What is a trigger in project risk management?

An expected situation causing an unidentified risk to occur

A warning sign that a previously identified risk might be occurring or has occurred

An unexpected situation causing an identified risk to occur

An unexpected situation causing an unidentified risk to occur


Test time: 018:43:39 - Total test time: 90 Min. Page 23 of 43

See references Marked for review

43. According to the project plan, a contractor is scheduled to deliver some software
components today afternoon. A regular payment is due to be made to this contractor
tomorrow.

You and your project team received a note this morning informing you that the software
delivery will be delayed by 2 weeks.

What should you do right now?

You should delay the payment also for 2 weeks.

You must immediately find a different contractor.

You should conduct a meeting with the contractor to resolve the delivery issues
before making the payment.
You should make the payment and reschedule the project plan.

See references Marked for review

44. In a software company a large number of simultaneously performed projects utilize the
same groups of human and other resources.

What is the term commonly used for this situation?

Concurrent engineering

Resource over-allocation

Resource pooling

Program management
Test time: 018:43:39 - Total test time: 90 Min. Page 24 of 43

See references Marked for review

45. What does the acronym RACI commonly stand for in project management?

Responsible, Accountable, to be Consulted, to be Informed

Remote, Attached, Connected, Integrated

Risk Analysis and Caution Initiative

Randomly Accessible Cashflow Information

See references Marked for review

46. You have used estimates made by your team members and applied the Critical path
method to compute a Network logic diagram for your project. Then you found out that it
cannot be sufficiently optimized for scarce resources and fast progress towards a given
deadline. What should you do next?

Apply resource leveling heuristics to uncritical activities only.

Reduce estimates on duration and work efforts by an adequate percentage.

Apply Three-point estimation and Critical chain project management.

Remove physical constraints and replace hard logic with soft logic.
Test time: 018:43:39 - Total test time: 90 Min. Page 25 of 43

See references Marked for review

47. Liquidated damages (LDs) are contractually agreed payments in order to...
...give the contractor an incentive to meet an aggressive schedule or challenging
quality objectives.
...penalize the contractor for late completion of a project or failure to meet
specifications.
...cover the customer's costs caused by late completion or failure to meet
specifications by the contractor.
...make a bid or proposal binding for the offerer while the customer has time to select
among various bidders.

See references Marked for review

48. What should not be covered by a risk management plan?


Roles and responsibilities for handling project risks

Timing of project risk management activities

The methodological approach used for risk management

Individual risks and potential responses to them


Test time: 018:43:39 - Total test time: 90 Min. Page 26 of 43

See references Marked for review

49. You are assigned as the project manager to a project which had a on-time cost variance
in the past caused by unexpected rework which has meanwhile been finished.

You perform Earned Value Analysis and find the following results:

EV: 250,000; PV: 200,000; AC 275,000

BAC is 500,000.

What is right?

EAC = 550,000

EAC = 525,000

EAC = 500,000

EAC = 425,000

See references Marked for review

50. An estimation has been made that the construction of a residential home will cost a
certain amount per square foot of living area. This is an example of what type of
estimating?

Analogous estimating

Bottom-up estimating

Top-down estimating

Parametric modeling
Test time: 018:43:39 - Total test time: 90 Min. Page 27 of 43

See references Marked for review

51. What is true for prototypes?


Prototyping causes significant costs and should be avoided wherever possible.

They are tangible and allow for early feedback on requirements by stakeholders.

Prototypes are mostly developed toward the end of a design or build phase.

Prototypes increase the risk of misunderstandings between developers and users.

See references Marked for review

52. What is a constructive change?


A change request that helps improving the project and its product, service or result
and is discussed generally in a friendly style.
A direction by the buyer or an action taken by the seller that the other party
considers an undocumented change to the contract.
A field change or ad-hoc change mandated by the project customer in a public
construction project.
A change request which will lead to the re-construction of an older version of the
project performance baseline by the contractor.
Test time: 018:43:39 - Total test time: 90 Min. Page 28 of 43

See references Marked for review

53. Which of the following is generally not regarded to be a motivator according to Frederick
Herzberg?

Working conditions and interpersonal relations

Responsibility for enlarged task

Interest in the task

Recognition for achievement

See references Marked for review

54. What is true for modern project management? Project managers need...

... to have a strict standing in negotiating

... to show experience in tricking business partners

... to be team players and facilitators instead of "bosses"

... to be strongly linked to local traditions


Test time: 018:43:39 - Total test time: 90 Min. Page 29 of 43

See references Marked for review

55. You are the project manager in an engineering project and have recently signed a
contract with a software vendor for the development of a complicated control solution.
The software will be used to control machinery equipment which your project team is
currently developing. The contract is a lump-sum contract. The contractor has target cost
estimated which seem rather low to you. Which of the following statements is not true for
this situation?

It is the contractor's risk in this type of contract that their profit may vanish if costs
have been underestimated.
This form of contract should only be chosen when all the requirements for the
building of the product are well-known by all parties involved.
In a fixed-price contract, change requests can cause issues regarding additional time
and extra costs for the changes to be applied.
It is likely that your organization may have to assume any unexpected additional
costs for the software development.

See references Marked for review

56. A review to determine whether of project activities comply with organizational and project
policies, processes, and procedures is commonly called

Quality auditing

Inspection

Quality testing

Reject screening
Test time: 018:43:39 - Total test time: 90 Min. Page 30 of 43

See references Marked for review

57. Which of the following is true in regard to the Code of Accounts?

It allows one to easily identify the breakdown level of the item in the resource
structure.
It describes the coding structure used by the performing organization to report
financial information in its general ledger.
It is the collection of unique identifiers generally assigned to WBS items.

It defines ethical behavior in the project and the responsibilities to the customer and
the profession.

See references Marked for review

58. You are the manager of your company's project management office. The company is
running many concurrent projects; most of them share a resource pool of technical staff.
Understanding how resources are utilized across projects has been found essential to
overall project performance, including cost effectiveness and profitability.

This morning you received a message that the resource pool members will be unable to
perform as planned for the next months because the overall work load has grown too
high and while delays are adding up, the morale of the staff is going down.

What should you do next?

Ensure that quantitative information for all projects is being made available in a
uniform and reliable fashion and verify that the project management methodology is
adhered to. Then consolidate the information to get an understanding of the
problems related with the use of shared resources.
Implement an enterprise project management software solution which is able to
level the human resources across the various projects and which has the capability to
model resource assignment on a percentage level thus optimizing resource utilization
for the overall organization.
Do nothing related to the described problem unless you are explicitly requested by
the organizations upper management. Supporting decision making on the level on
which project portfolio management is done, is not the project management office's
business.
Evaluate project management software which supports planning and scheduling
across enterprise-wide project portfolios. Avoid managing the availability of shared
enterprise resources for the projects run by an organization because this is not the
business of a project management office.
Test time: 018:43:39 - Total test time: 90 Min. Page 31 of 43

See references Marked for review

59. You have been criticized that certain specifications in your Scope Statement do not pass
the test for SMART objectives. What are SMART objectives?

Objectives specified in far more detail than necessary for a execution of a successful
project.
Easily achievable objectives which help you reducing the pressure on yourself and the
team.
Objectives that should be achieved in order to attain formal recognition by both the
customer and the project sponsor.
Objectives that are described using specific, measurable, assignable, realistic and
time-related specifications.

See references Marked for review

60. You have been assigned as a project manager to a software project. While you and your
team are working on a WBS (Work breakdown structure), estimations for activity
durations based on the activity list vary significantly. Which additional documents may
help you clarify this situation?

Milestone list and scope baseline.

Project schedule network diagrams and human resource plan.

Activity cost estimates and scope baseline.

Activity attributes and project scope statement.


Test time: 018:43:39 - Total test time: 90 Min. Page 32 of 43

See references Marked for review

61. You are performing Earned value technique on your project.

After budget approval, an additional and unexpected cost item has been identified, which
made the project more expensive some weeks ago. The item has meanwhile been paid by
the project team, and it is expected that for the remaining duration of the project, costs
will be as budgeted.

In this case, which is the best formula to calculate EaC (Estimate at Completion)?

EaC = BaC - CV

EaC = BaC / CPI

EaC = AC + BtC / CV

You can not compute the EaC.

See references Marked for review

62. During a company event, you had the opportunity to talk to a colleague project manager.
He told you that in his current project actual costs are 15% under cumulated costs
budgeted for today.

What do you think?


The information given to you by the colleague is not sufficient to assess project
performance.
The project will probably be completed with total costs remaining under budget until
the end.
A significant cost increase during the further course of the project will probably bring
the costs back to baseline level.
Original cost forecasting and budgeting for the project must have been poor to allow
this variance.
Test time: 018:43:39 - Total test time: 90 Min. Page 33 of 43

See references Marked for review

63. What is the meaning of a concept called the "Journey to Abilene"?

Project managers should visit their customers far more often than what is usual in
order to avoid misunderstandings and bad emotions.
International projects may have an increased need for traveling which can lead to
additional costs and troubles with time zones.
Committee decisions can have the paradox outcome, that a jointly made or approved
decision is not desired by any individual group member.
A project is a temporary endeavor undertaken to create a unique product, service or
result. Repeating it would be similar to making the same journey twice.

See references Marked for review

64. Which of the following statements describes best the relationship between project phases
and the Project life cycle?

The Project life cycle includes the time when the project is performed and the
expected product lifespan after that.
In project management, the sequence of project phases and phase gates is often
referred to as Project life cycle.
The Project life cycle is regarded as a sequence of project activities while phases are
defined to control overlapping activities.
The Project life cycle describes how iterations of project management processes are
used when a project schedule is developed.
Test time: 018:43:39 - Total test time: 90 Min. Page 34 of 43

See references Marked for review

65. Which is an appropriate order in most project situations for the development of scope-
related documents?

1. Project SOW (Statement of work),


2. Project charter,
3. Project scope management plan,
4. Project scope statement,
5. WBS (Work breakdown structure) and WBS dictionary.
1. Work breakdown structure,
2. Scope statement,
3. Project charter,
4. CSOW (Contractual statement of work),
5. Contractual Work breakdown structure
1. Feasibility study
3. Contract,
4. CWBS (Contractual work breakdown structure),
5. Scope of work descriptions,
6. PID (Project initiation document).
1. BOM (Bill of materials),
2. CAP (Control account plan),
3. Project charter
4. Change management plan,
5. Scope baseline.

See references Marked for review

66. What is the S-curve in project management?

A graph that is generated if a normal curve is integrated.

A graph that is to be integrated to generate a normal curve.

A metaphoric description of the short term uncertainties that are present in every
Test time: 018:43:39 - Total test time: 90 Min. Page 35 of 43
project.
The graph that describes the typical growth of earned value during the course of the
project.
Test time: 018:43:39 - Total test time: 90 Min. Page 36 of 43

See references Marked for review

67. An output of the Estimate activity resources process is a document called "Activity
resource requirements". It identifies the types and quantities of resources...
...while the term resources is limited to equipment and materials.

...required for each activity in a work package.

...while the term resources is limited to human resources.

...to be obtained solely from the performing organization.

See references Marked for review

68. What is not the purpose of Configuration control when Configuration management is
applied in a project?
Verification that the configuration identification for a configuration item is accurate,
complete, and will meet specified program needs.
Ensuring that proposed and approved changes to configuration items are fully
analyzed.
Ensuring that proposed and approved changes to configuration items are fully
documented.
Managing and controlling the frequently requested changes to a project by applying
agreed rules.
Test time: 018:43:39 - Total test time: 90 Min. Page 37 of 43

See references Marked for review

69. Which statement describes best the meaning of the term Cost baseline?
A cost baseline is always created by translating time-phased cost information into
cost data on activity or work-package level.
A cost baseline is an approved time-phased budget that will be used to measure and
monitor cost performance on the project.
Data to draw a cost baseline can be easily generated and updated as necessary from
information related to actual project cost.
A cost baseline is usually displayed in the form of an inverse S-curve drawn from the
beginning of the project until data date.

See references Marked for review

70. Which is not true in regard of RoI (Return on Investment) for a project?

It defines the cumulated net income from an investment at a given point in time or
during a defined period.
It includes investment, direct and indirect costs and may include allowances for
capital cost, depreciation, risk of loss, and/or inflation.
It is most commonly stated as a percentage of the investment or as a dimensionless
index figure.
It is the time when cumulated net income is equal to the investment.
Test time: 018:43:39 - Total test time: 90 Min. Page 38 of 43

See references Marked for review

71. A project sponsor requested Earned Value Data on two concurrent projects from the
project managers. Both projects are regarded as equally important and strategically
beneficial and have been finished by over 80%. He received the following information:

Project A:
PV: $1,800,000
EV: $2,300,000
AC: $2,100,000

Project B:
PV: $2,000,000
EV: $1,500,000
AC: $1,600,000

The sponsor considers to shift some resources from Project A to Project B to speed up the
second project which is currently behind schedule.

What is the most likely outcome of such a measure?

Changing team assignments during late course of a project typically increases cost
efficiency.
Changing team assignments during late course of a project typically increases time
efficiency.
According to the Law of diminishing returns, the consolidated Cost variance of the
two projects will decrease.
According to the Law of diminishing returns, the consolidated Cost variance of the
two projects will increase.

See references Marked for review

72. Which of the following statements describes best the relationship of quality and grade?

Low grade is always a problem; low quality may be overcome by a good rework and
repair process.
Grade is a category or rank given to entities having different functional requirements
but the same need for quality.
Both quality and grade can often be improved through intelligent measuring, testing
and examining.
Low quality is always a problem as it bears on the ability of an item to meet
requirements; low grade may sometimes be acceptable.
Test time: 018:43:39 - Total test time: 90 Min. Page 39 of 43

See references Marked for review

73. Network templates which contain only portions of a network are often referred to as

Subnetworks or fragment networks

Subprojects

Programs

WBS items

See references Marked for review

74. What is the Internal Rate of Return (IRR) of a project?

The time period needed to pay back the investment from a project when future
income is discounted.
The inherent discount rate or investment yield rate produced by the project over a
pre-defined period of time.
The rate of negative risk that can be accepted for a project without turning the
Expected net present value negative.
The expected benefit from a project’s deliverable calculated as a percentage of the
original investment over a specified time period.
Test time: 018:43:39 - Total test time: 90 Min. Page 40 of 43

See references Marked for review

75. You just created the following network logic diagram to describe the planned flow of
activities for your project which will start tomorrow:

Which potential inconsistency in the diagram should you solve right now?

Activity E is a logical dangle in relation to the sink before the finish milestone.

Activity F is a logical dangle in relation to the burst point after the start milestone.

You cannot calculate a critical path when lags and/or leads are calculated in percent.

Activities E to F need another task drawn as a hammock to calculate Level Of Effort.

Reset all answers Solve Sample Test Print Sample Test

Result: of 75, %

Notes:
- After clicking the Solve Sample Test button, the correct answers will be highlighted in blue color above in the questions &
answers section.
- PMI made a decision in 2006 to not publish passing scores for the exams any more. The actual score is estimated to be between 61%
and 75%. I recommend to target 75% results or better in this and all other difficult prep tests you are taking, 82% in simple tests.

I am...
...generally interested in the PMP
certification.
...on my way to pass the PMP exam.

...already certified as a PMP.


Finished? Klick here to send your feedback to me.

More providers of free PMP preparation Did you stumble over


questions on project
questions selection and decision
tree technique?

Christelle P. from Canada mailed Oct 11 2003:


Then check this link for Decision Tree
Test time: 018:43:39 - Total test time: 90 Min. Page 41 of 43
"I passed the test! Thanks for the 75 prep questions. The only
Software, which is free for those
way to succeed is to write tons of practice exams!" studying for the PMP certification
exam.
So true! Here are more free sample tests with more than 2,000
prep items (questions and answering options). Of course, I can give no guarantee regarding
their quality, but practicing is always helpful.

Free Test
Provider URL Comment
Questions

Ajith Namboothiri www.ajithn.com 180 Requires registration. Number of questions may


grow, as visitors are invited to add further
questions. Many questions of CAPM exam style.
Related to 3rd Edition
CertGear www.certgear.com 6 Free trial of CertGear's exam simulator. Version
based on PMBOK® Guide 4th Edition is
announced for July 31st
Certification.about.com certification.about.com 20 Questions based on Whizlabs' Exam Simulator
software trial. Whizlabs has discontinued any PMP
exam preparation software, so these questions
might not be up to date any more.
GetPMP getpmp.com 20 20 free questions
Related to 3rd Edition
Head First Labs www.headfirstlabs.com 200 Online practice exam from the authors of Head
First PMP in various time formats. Also, a PDF file
with 2MB for download.
Awaiting reply
MeasureUp www.measureup.com 7 Simulates a test environment online similar to the
original environment. Related to 4th Edition
Oliver F. Lehmann www.oliverlehmann.com 175 PDF file (app. 1MB) for download.
Just like the real thing: Questions are written
against the PMP Examination Specification and
reference to a current project management
source.
Related to 4th Edition.
www.oliverlehmann- 175 German language aid for the 175 questions.
training.de Related to PMBOK Guide 4th Ed.

PMConnection www.pmconnection.com 10 Related to 3rd edition


PMExam.com www.pmexam.com ? Order their free Daily Digest as an e-mail service.
A great resource with intelligent questions.
Related to 3rd and 4th Edition
PMPQuest.com www.pmpquest.com 12 Related to 3rd Edition
PMP Question Bank pmpbank.googlepages.com 200 New site (4-2009) with good, difficult questions.
Related to 4th edition
PM Study www.pmstudy.com 50 200 free questions after optional registration.
Related to 4th Edition

PMTI www.4pmti.com 15 Registration required. Related to 4th Edition


Pmzilla www.pmzilla.com 155 Registration required. Related to 3rd Edition
PreparePM www.preparepm.com 165 High quality questions, which simulate the real
test very well.
Visitors are invited to contribute with further
questions. Number of questions may therefore
grow. Related to 4th Edition.
ProXalt www.proxalt.com 20 Registration required. Related to 4th Edition
Tutorials Point www.tutorialspoint.com 200 Related to 4th Edition
Voight Project Solutions www.voightps.com 500 My friend and colleague Dr. Roger Voight has a
large body of free questions. Many of them are
also helpful for CAPM candidates. Questions
related to 4th Edition have been announced
Test Prep Review www.testprepreview.com 15 Awaiting reply

Version information: We contacted some providers and checked their offerings. The statements made above reflect
the status per 30 June 2009. We will update the list when we have new information.
Test time: 018:43:39 - Total test time: 90 Min. Page 42 of 43
Please send an e-mail to Oliver F. Lehmann, PMP if you are another provider, if a description is not correct any more,
if you have any comments on the quality and relevance of test questions, or if one of the links appears to be broken.

A Note to My Visitors

Thanks a lot ☺ to all who informed me that the owners of the websites

have copied my free sample questions and re-published them with their copyright assigned .

The second of these two even sells my work for a fee - and the work of other good colleagues too.

That people are using my work may be honorable. But: I prefer to be asked before my material is used by others—I would probably
have allowed it, as I have done so often.

I also value rightful copyright information and a reference to the author. This is how I am quoting others or use their materials in my
websites and seminar literature wherever possible.

We Germans have a term for that: Gute Kinderstube – good manners from good education by good parents.

The 250 sample questions in this website (and the many more used in my seminars)

- match the updated exam (per September 2005),

- are written against PMI's original PMP Examination Specification,

- reference to the appropriate body of knowledge,

- have been peer-reviewed for correctness and appropriateness,

- are open for discussion and feedback - of which I receive a lot,

- will be updated on time when the exam will be renewed in June 2009.

20 April 2006, updated 09 March 2007and 30 March 2009, Munich, Germany

Advertisment

Acumen Fund
Building transformative businesses to solve the problems of poverty
Public Service Ads by Google

"PMI", "PMP", PgMP", "CAPM", "PMBOK" are marks of the Project Management Institute (PMI) which are registered in the United States
of America and in other nations
PMI has not participated in the creation of this self assessment test and has not reviewed it for correctness.
This test is for self assessment only and no guaranty is given for passing the PMP®.
Some of the names of companies and their products listed and linked to on this page are marks which are registered in various
countries.
© 2004-2007, all rights reserved. The owner of this website is not responsible for contents of external pages to which he placed