FOR APPROVAL

B 27.12.2019 L.C.Hai Y.H.Lee J.T.Seo Revised following the Owner’s comment


A 01.12.2019 L.C.Hai Y.H.Lee J.T.Seo For Approval
Rev Date Prepared Checked Approved Details of Revision
Owner

Owner’s Engineer

Contractor

DOOSAN HEAVY INDUSTRIES VIETNAM

Sub-Supplier

BAC MIEN TRUNG CONSULTANCY INVESTMENT


CONSTRUCTION AND TRADING JOINT STOCK COMPANY

Project

NGHI SON 2 BOT THERMAL POWER PLANT PROJECT


(2 X 600 MW)
Title

[Housing Complex]
Inspection and Test Plan for Masonry Works
(Using for Concrete block)
Document No. Rev. Page No.

NS2-DH01-P0UYK-770010 B 05 Pages
ID No: NS2-DH01-P0UYK-770010
NGHI SON 2 BOT THERMAL POWER PLANT Rev: B
(2x600 MW) Date: 27.12.2019
TITLE: INSPECTION AND TEST PLAN FOR MASONRY WORKS
Participation by
Applicable Code & Specification;
No. Description of Inspection/Test Process Acceptance Criteria Reporting Format Sampling Frequency Remarks
Check method Sub- Main Owner/
Contractor Contractor Engineer

BLOCK WORK

I Check before work

As per ASTM C140-03, Item 4:


Concrete Masonry Block Test - Testing of
1 ASTM C140 Lab. Form P W W - Each lots of ~10.000 units :
blocks and frequency
Take 6 specimens

II Block work construction

1 Setting-Out - Horizontally & vertically

TCVN 4085:2011; Item 4.1.1 Table 1.


- Vertical < 10mm
1.1 Marking base line on floor Total station, measurement, vertical, NS2-DH01-P0UYK-770010-01 P W S
- Horizontally < 30mm
levelling machine

TCVN 4085:2011 Item 6.9 Table 4


Deviations due to the move of the structure axis - Vertical < 20mm
1.2 Leveling machine, measurement, NS2-DH01-P0UYK-770010-01 P W S
line - Horizontally < 20mm
vertical

2 Block Work Construction & workman ship

- Sampling as per ASTM C270;


Test method as per ASTM C190;
- The mortar mixing ratio table must
be visible at the mixing location;
ASTM C270 / C109; TCVN 4085- 1 group sampling for each floor
2.1 Workability and sampling of mortar - The deviation in measuring the Lab. Form P W W
2011, Item 4.3.7 (Min. 10 MPa)
composition of the mortar is not
greater than 1% for water and
cement; for sand not larger than
5%;

Joint thickness is not less than


Size and type of block, wetting of blocks, laying,
8mm, not bigger than 15mm,
2.2 joint thickness, raking/pointing, course level and TCVN 4085- 2011, Item 5.3.1.4 NS2-DH01-P0UYK-770010-01 P W S
plumbness is not over 5mm, course
plumbness.
level is not over 20 mm each 1,2m

- Anchor bar D10 @400 (Vertical);


Reinforcement of blockwork, fixing of NS2-UV01-P0UYK-760003 Sheet No
2.3 - Length of anchor in vertical NS2-DH01-P0UYK-770010-01 P W W
accessories, junctions and connections 1; Detail 01 & 03, 04.
support Min 120mm,

2.4 Surface roughness, cleaned TCVN 4085:2011 ; ruler TCVN 4085: 2011 Table 4 Item 6.9 NS2-DH01-P0UYK-770010-01 P W S

The new wall need to avoid impact


2.5 Curing of concrete block wall TCVN 4085- 2011, Item 5.3.6.2 and curing by water in 03 day as NS2-DH01-P0UYK-770010-01 P W S
per

PLASTERING WORK

Page 1 of 4
ID No: NS2-DH01-P0UYK-770010
NGHI SON 2 BOT THERMAL POWER PLANT Rev: B
(2x600 MW) Date: 27.12.2019
TITLE: INSPECTION AND TEST PLAN FOR MASONRY WORKS
Applicable Code & Specification;
No. Description of Inspection/Test Process Acceptance Criteria Reporting Format Participation by Sampling Frequency Remarks
Check method

I Plastering construction

- Sampling as per ASTM C270; Test


method as per ASTM C190;
- The mortar mixing ratio table must
be visible at the mixing location;
ASTM C270 / C109; TCVN 4085- 1 group sampling for each floor
1 Workability and sampling of mortar - The deviation in measuring the NS2-DH01-P0UYK-770010-02 P W W
2011, Item 4.3.7 (Min. 10 MPa)
composition of the mortar is not
greater than 1% for water and
cement; for sand not larger than
5%;

Vertical < 15mm


2 Check setting out TCVN 9377- 2012, Item 4.2.2 NS2-DH01-P0UYK-770010-02 P W S
Horizontal < 10mm

Surface preparation - Cleanliness, raking of


TCVN 9377-2:2012; NS2-DD09-
3 block works/scarifying concrete surface, fixing of Item 4.1.2 (TCVN 9377-2:2012) NS2-DH01-P0UYK-770010-02 P W S Checked prior to plaster
level markings, fixing of accessories and wetting. P0UYK-770014

NS2-DD09-P0UYK-770014, NS2- - Thickness 10-12 per each layer.


4 Application of plaster UV01-P0UYK-760003; TCVN 9377- - Thickness. > 12mm have to apply NS2-DH01-P0UYK-770010-02 P W S
2012, Item 4.2 mesh per each layer.

II Criteria for Workmanship, making thickness of mortar on background surface

Roughness < 3 mm (2m length


TCVN 9377-2:2012 ; Item 5 table 4; yard)
1 Roughness checked NS2-DH01-P0UYK-770010-02 P W W
ruler
Indentation < 5mm (2m length yard)

TCVN 9377-2:2012;Item 5 table 4;


2 Vertical tolerance of wall and ceiling < 15 mm (Entire length and width) NS2-DH01-P0UYK-770010-02 P W W
Vertical tool, level, ruler

TCVN 9377-2:2012;Item 5 table 4;


3 Slant path of column edge line < 10mm (Entire structure height) NS2-DH01-P0UYK-770010-02 P W W
Vertical tool, level, ruler

Tolerance of window sills, column sills, part of TCVN 9377-2:2012; Item 5 table < 3mm (1m length) & 10mm (All
4 NS2-DH01-P0UYK-770010-02 P W W
wall protruding from horizontal and vertical. 4;Vertical tool, level, ruler entire structure length)

Abbreviation P: Performance R: Report Review W: Witness Inspection H: Hold Inspection S: Surveillance Inspection

Page 2 of 4
Code: NS2-DH01-P0UYK-770010-01
NGHI SON 2 BOT THERMAL POWER PLANT PROJECT Rev: B
Date: 27.12.2019

Date:
Sub-Contractor:
Start:
Finish:
Work title:

Area No:
Inspected Item:

Inspection Report for Concrete Block Work


Approved shop drawing No.:
Assessed by
Inspected Item Check method
OK NOT OK
I Check before work

1 Concrete Masonry type, dimension & Block Test Sample test

II Block work construction

1 Setting-Out

1.1 Marking base line on floor Plumb, Level

1.2 Deviations due to the move of the structure axis line Instrument

2 Block Work Construction & workman ship

2.1 Workability and sampling of mortar Sample test


Size and type of block, wetting of blocks, laying, joint thickness,
2.2 Instrument
raking/pointing, course level and plumbness.

2.3 Reinforcement of blockwork, fixing of accessories, junctions and connections Instrument

2.4 Surface roughness, cleaned 2m Yard

2.5 Curing of concrete block wall Visual

CONCLUSION

Approved Not approved


…………………………………………………………………………………………………………………………………………………………………

…………………………………………………………………………………………………………………………………………………………………

…………………………………………………………………………………………………………………………………………………………………

Description Full Name Signature

Owner

Contractor

Subcontractor

Page 3 of 4
Code: NS2-DH01-P0UYK-770010-02
NGHI SON 2 BOT THERMAL POWER PLANT PROJECT Rev: B
Date: 27.12.2019

Date:
Sub-Contractor:
Start:
Finish:
Work title:

Area No:
Inspected Item:

Inspection Report for Plastering and Surface Preparation Works


Approved shop drawing No.:
Assessed by
Inspected Items Check method
OK NOT OK
I Plastering construction

1 Workability and sampling of mortar Sample test

2 Check setting out Rule

Cleanliness, raking of block works/scarifying


Visual
concrete surface

Block wall defect repaired Visual

3 Surface preparation Concrete and block surface was removed other


Visual
contaminants.

Fixing of required accessories Visual

Wetting of background (During plastering work) Visual

4 Application of plastering surface Visual

II Criteria for Workmanship, making thickness of mortar on background surface

1 Roughness checked Rule

Vertical tool, level,


2 Vertical tolerance of wall and ceiling
rule
Vertical tool, level,
3 Slant path of column edge line
rule
Tolerance of windowsills, column sills, part of wall protruding from Vertical tool, level,
4
horizontal and vertical rule

CONCLUSION

Approved Not approved


…………………………………………………………………………………………………………………………………………………………………

…………………………………………………………………………………………………………………………………………………………………

…………………………………………………………………………………………………………………………………………………………………

Description Full Name Signature

Owner

Contractor

Subcontractor

Page 4 of 4